S-000-1654-400-F.01
Pembangunan Aviation Fuel System & DPP Rev :
Kulon Progo Project Date :
LIFTING EQUIPMENT
CHEKLIST INSPECTION
INCLUDED
REQUIREMENTS
YES NO N/A
1. Detailed written procedure prepared, including step-by-step operation /procedure.
2. Pre-lift meeting to discuss step-by-step operation including roles & responsibilities of
all parties involved.
3. Plans/drawings consisting of the following
A. Plot Plan
B. Plan view with crane locations relative to the lift item. All movements and
obstructions and information shall be clearly shown as listed below.
1). Location and size of underground facilities.
2). Results of calculations of ground bearing pressures.
3). Results of calculations for soil bearing analysis.
4). Dimensions for centerline of lift equipment to CG of the lift item at the
beginning of lift and at final set.
5). All swinging and traveling of lift equipment including clearances.
6). At final set locations, note any required rotation of load.
7). Matting plan / layout
C. Elevation view with data charts and crane locations relative to the lift Item. All
movements and obstructions shall be clearly shown as listed below.
1). Dimensions from centerline of equipment to CG of the lift item at the beginning
of lift and at final set.
2). All swinging and traveling of lift equipment and clearances.
3). Rigging assembly and all lifting attachments clearly labeled.
4). Lifting and tail lug orientation.
5). Detailed of sling connection at crane hook and equipment (lift and tail cranes)
6). Lift crane data chart consisting of:
a) Crane make / model
b) Radius – boom type and length
c) Chart ID Number and crane counter weights
d) Chart capacity
e) Lift item weight
f) Rigging weight
g) % Safety
h) % Chart
7). Tail crane data chart consisting of:
a) Crane make / model
b) Radius boom type and length
c) Chart ID Number and crane counter weights
d) Chart capacity
Page 1 of 3
Doc No :
S-000-1654-400-F.01
Pembangunan Aviation Fuel System & DPP Rev :
Kulon Progo Project Date :
4. The following notations shall appear in the body of the procedure.
a) All rigging will be attached and then visually inspected by a Contractor rigging
supervisor.
b) Contractor rigging supervisor is responsible for verifying that all prescribed
conditions are met prior to the lift.
c) All cranes shall be inspected and deemed in good operational condition by
Contractor rigging supervisor prior to the lift.
d) All cranes will have a current certification of receipt on project.
e) The use of tag lines.
f) All test certification data will be provided to Contractor rigging supervisor.
g) Load test (when required) will be witnessed by Contractor rigging supervisor.
h) The process supervisor and fire department will be notified prior to the lift.
5. Load weight verified against calculated engineering weight and one of the following:
(weight to be calculated on + side of mill tolerance)
a) Certified D.O.T. scale ticket (truck of rail).
b) Calibrated hook scale.
6. Load test at 110% of lift weight
7. Third party engineering review.
8. Drug testing of crane operators and rigging personnel prior to lift.
Page 2 of 3
Doc No :
S-000-1654-400-F.01
Pembangunan Aviation Fuel System & DPP Rev :
Kulon Progo Project Date :
Reviewed by : Reviewer :
Inspected by : Inspector :
Date : Date :
Page 3 of 3