FURNHURST MINE PRELIMINARY

PROJECT TITLE GEOLOGICAL AND ECONOMICAL


ASSESSMENT
ROY AGYEMANG NEVILLE
PROJECT MANAGER
HENDRICKS

TASK
WBS TASK TITLE
DESCRIPTION

1.0 Miner Contracting


1.1 Appointment of Miner

1.2 Reconnaissance Site Visit


Quotation from Miner for supervision of fabrication,installation of ladders and BOQ
1.3

1.4 Installation of ladders

1.5 Make safe underground environment for all existing shafts

1.6 Identifying all hazards, removing or mitigating identified hazards

2.0 Survey Work


2.1 Reconnaissance Site Visit
2.2 Topographic Survey
2.3 Underground Survey all existing shafts
Deliverables submission;
i) Surface map, ii) Underground map for all shafts, iii) Installation of
2.4
underground pegs, iv)Longitudinal Sections, v) hard copies and soft copies of
maps
3.0 Underground Mapping for all shafts
3.1 Geological mapping
3.2 Geotechnical Mapping - rock mechanics

3.3 Underground sampling (Systematic)- i) along drive, ii) crosscuts,

3.4 Sample submission to laboratory for analysis

3.3 Plotting all assay values on plan

3.4 Underground Mapping report


4.0 Trenching
4.1 Siting of trench positions
4.2 Sampling Intercepted reefs
4.3 Sample submission to laboratory for analysis
4.4 Plotting and mapping
4.5 Report
5.0 Process Design
5.1 Bench Scale Metallurgical testwork
5.2 Flowsheet Development
5.3 Equipment Sizing and selection
5.4 Process Plant design
6.0 Production Planning
6.1 Activities TBA
URST MINE PRELIMINARY
GICAL AND ECONOMICAL COMPANY NAME NAR LIMITED
SMENT
GYEMANG NEVILLE
ICKS
PROJECT START DATE 23/09/2019 0

PCT OF TASK SCHEDULED SCHEDULED


DEPENDENCIES TASK OWNER ACTUAL START
COMPLETE START FINISH

23/Sep/19 7/Oct/19
50% 23/Sep/19 25/Sep/19
26/Sep/19 26/Sep/19

26/Sep/19 27/Sep/19

30/Sep/19 7/Oct/19
30/Sep/19 4/Oct/19
30/Sep/19 4/Oct/19
4/Oct/19 18/Oct/19
4/Oct/19 4/Oct/19
7/Oct/19 9/Oct/19
10/Oct/19 15/Oct/19

15/Oct/19 18/Oct/19

7/Oct/19 18/Oct/19
7/Oct/19 9/Oct/19
7/Oct/19 9/Oct/19

7/Oct/19 9/Oct/19

10/Oct/19 14/Oct/19

14/Oct/19 16/Oct/19

16/Oct/19 18/Oct/19
21/Oct/19 31/Oct/19
21/Oct/19 21/Oct/19
22/Oct/19 25/Oct/19
25/Oct/19 28/Oct/19
28/Oct/19 30/Oct/19
30/Oct/19 31/Oct/19
18/Oct/19 30/Oct/19
18/Oct/19 25/Oct/19
25/Oct/19 28/Oct/19
25/Oct/19 28/Oct/19
28/Oct/19 30/Oct/19
TBA TBA
Sep-19 [W39] Sep-19 [W40]

FINISH DURATION 23 24 25 26 27 28 29 30 1 2 3
ACTUAL FINISH
VARIANCE IN DAYS M T W T F S S M T W T

0
0
0

0
0
0
0
0
0
0

0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
Oct-19 [W41] Oct-19 [W42] Oct-19 [W43]

4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

F S S M T W T F S S M T W T F S S M T W
Oct-19 [W44]

24 25 26 27 28 29 30 30

T F S S M T W T

You might also like