Professional Documents
Culture Documents
net/publication/341900673
CITATIONS READS
0 5,118
2 authors, including:
Ashwin M Joshi
RASTA - Center for Road Technology, Bangalore, India
36 PUBLICATIONS 64 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
Utilization of Demolished Brick Masonry Waste in Production of Masonry Unit View project
All content following this page was uploaded by Ashwin M Joshi on 04 June 2020.
CITATIONS READS
0 18,280
2 authors:
Some of the authors of this publication are also working on these related projects:
Utilization of Demolished Brick Masonry Waste in Production of Masonry Unit View project
Development of Masonry Units using Construction and Demolition (C&D) Waste View project
All content following this page was uploaded by Ashwin Joshi on 18 December 2019.
Abstract. Construction plays a very important role in economic growth through the multiple effects
on the other sectors of the country’s economy. Precast construction concept include those structures
where the majority of structural components are standardized and produced in plants or yards in a
location nearer or away from the construction site, and transported to the site location for its
assembly. The standardized precast elements facilitate mass production, in order to build large
number of buildings in short duration. In the present case study, where the project consists of 62
towers with twelve floors each. Precast construction method has been adopted as the moulds of
standardized components facilitates mass production with stringent quality control. Precast
construction method involves setting up of casting yard, production & stacking, transportation and
erection of precast elements.
Precast Construction is effective in terms of time, labours requirement, superior quality, better
performance & finish, optimal material requirement, less wastage, reduced use of shuttering,
desired shape, better finish etc., It is convenient to establish precast yard and to erect the precast
elements at (near) site which speeds up the process & contributes towards mitigating delays in large
scale construction projects. As this method requires huge initial investments, it is feasible for Large
Scale Construction Projects only.
Introduction
Construction is the second largest economic activity in our country next to agriculture. Precast
or Prefabricated construction concept includes those buildings where the majority of structural
components are standardized and produced in plants or yards at a location nearer to the construction
site; transported to building area for assembly or erection. These precast building components are
manufactured in order to cater large number of buildings in a short duration at lower cost [3]. The
main features of precast construction process are as follows:
The use of standard tools, machinery, and equipment in the production of standard,
interchangeable parts and products.
In urban areas, residential buildings of this type are usually five to ten stories high or more.
Many countries used various precast building systems to provide low-income housing for the
growing urban population. In general, precast building systems are proved to speed up the project
with better quality control; which leads to economy when compared to conventional method of
construction (apartment buildings) in many countries.
Objectives
Following objectives have been considered in this work:
To study Precast Construction & Erection methodology
Equipment used for precast construction
Comparison between conventional and precast construction
Research Methodology
The production of precast elements and related resources are synchronized with the project
schedule so that rate of production of precast elements should match with rate of demand from
construction site including buffer stock. Planning involves detailed work plan of following
parameters:
1. Precast Elements Layout 2. Precast Yard Planning 3. Production Planning
4. Stacking area for precast elements 5. Transportation of precast elements
6. Erection of precast elements
Broad classification of different works involved in construction and their sequence are
pictorially represented in the Fig-1. The precast construction method involves following activities:
1. Setting up of casting yard 2. Production of precast elements 3. Stacking of precast elements
4. Transportation of precast elements 5. Erection of precast elements
Precast Elements Layout. Layout of precast elements forms basic input for planning of precast
construction project. Maximum weight of the element is decided based on capacity of the tower
crane available at the site for erection. In the present study total 236 precast elements were planned
for every typical floor which included walls, beams, Precast Beam – Slab (PBS) and slabs. List of
elements in 2 BHK and 3 BHK units are given below:
The structural plan of typical floor was in the form of plus shape; where each side contains two
flats and opposite side flats are considered as mirror flats. Hence plan becomes much simpler and
understandable. Fig- 2 and Fig- 3 represent the dimensional views of typical floor and tower
respectively. The detailed scope of the precast elements to be produced are given in Table 2.
Fig 2: Precast Elements in a typical floor plan Fig 3: Dimensional view of typical tower
Phase-I of project has been considered in present study. Production and erection of precast elements
were planned in Phase-I of project over duration of 12 months.
Production of Precast Elements. Precast elements production planning has been made based
on the quantity of work for 22 months (Phase -I) to be done. Monthly casting schedule was prepared
based on scope of elements to be produced for Phase-I construction. Production of Elements has
been carried out from 6th to 17th month of the Phase – I.
Stacking of Precast Elements. Lifting and handling of precast elements has been done using
gantry cranes and other approved lifting devices. Number and location of lifting points have been
decided such that the ‘handling stresses’ were always within allowable limits. For members having
unsymmetrical geometry or projecting sections required supplementary lifting points. Typical
method of lifting or handling of a wall panel is shown Fig 5.
Precast elements after demoulding or curing activity, were stacked at planned stacking area to
accommodate minimum 10 days’ production of precast elements as a buffer stock to maintain
uninterrupted supply of precast elements. Stacking area was calculated based on element detailing
and method of stacking. On an average, total 136 precast elements have been cast per day.
Precast elements such as precast slabs, beams, spandrels and staircase landing elements were
stacked horizontally and supported with strips of wood or batten across the full width of the bearing
points. Precast walls, column-beam-wall panels shall be stacked in vertical position supporting their
self-weight using racks.
Transportation of Precast Elements. Precast elements were transported to the site on flat bed
or low bed trailers. The delivery of precast elements was planned according to the erection
sequence to avoid or minimize unnecessary handling or storage at site. The precast elements were
loaded using gantry crane of 10 to 15 ton of varying capacity and delivered to the site with proper
supports, frames and cushioning to prevent transit damages. The elements were delivered in a
manner which they can be lifted directly and erected without much change in the orientation or
sequence.
Average 136 numbers of elements were to be transported per day to the site with the help of
around 10 numbers of trailers.
Discussions
Precast construction method is recently developed method, still a lot of researches going on to
improve its applications. Here few comparisons made with conventional construction system by
studying the site work and analyzing the activities.
1. Precast construction method is purely based on shear wall concept and hence the typical floor
doesn’t contain any type of columns but in conventional, columns are must to construct twelve
floors of a tower.
2. Precast construction process carried out at site as production of elements along with
simultaneous erection of the ready elements which considerably saves the time of construction
where as in conventional, block work and curing consume much time to complete.
3. Block work is limited to only 1 to 1.2m height per day to maintain proper alignment whereas;
precast elements do not have any such restrictions.
4. In conventional method, block work must proceed further with proper curing and also plastering
require curing period for sufficient hydration and to attain strength; but in precast method, no
such intense curing required because, the main and final curing done at casting yard only to
achieve maximum strength.
5. Plastering work is mandatory in conventional whereas precast method doesn’t require any kind
of plastering work.
6. For slabs, shuttering work, reinforcement works consume more time in conventional method;
but in precast, slabs also get manufactured in yard itself.
7. All parts of a structure cannot be fixed with precast elements; at few necessary locations block
work is essential in precast construction also.
8. In precast method, slab should proceed further with screed of certain thickness to provide
necessary electrical conduits; whereas conventional system contains the electrical conduit works
in normal slab shuttering work itself.
9. No alterations in design are possible in precast construction; but in conventional, any kind of
alterations are made without any problem.
10. Better quality control can be possible with precast construction but as the floor level increases,
in conventional system it is very difficult to maintain good quality.
11. Precast construction system requires almost half the number of total man power that required
for conventional system.
12. Construction activities take place at a faster rate in precast compared to conventional system.
13. Precast construction provides better alignment of structural elements than the conventional one.
14. Precast construction is best suitable for large construction projects; whereas conventional
system lead to various problems and consumes huge time for completion.
Conclusions
Precast Construction Methodology was found very effective and efficient as compared with
Conventional Construction of Large Construction Projects. It is effective in terms of time, labour
requirement, superior quality, better performance & finish, material requirement, less wastage,
eliminate shuttering, desired shape & accurate finish etc., It is convenient to establish precast yard
Acknowledgement
Authors would like to thank Mr. Aravind S, M/s Provident Housing, Bangalore for providing
platform to carry out study in their project site location. Also Ms. Hemalatha B M, PG student
RASTA for helping out during the research work.
References
[1] Tatum, C.B., Vanegas, J.A., Williams, J.M., 1986. “Constructability Improvement Using
Prefabrication”, Pre-assembly and Modularisation. Technical Report 297. Construction Industry
Institute, Stanford, USA.
[2] L. Jaillon a, C.S. Poon a,*, Y.H. Chiang b “Quantifying the waste reduction potential of using
prefabrication in building construction in Hong Kong”, Elsevier, 29 (2009) 309–320.
[3] Tomas U. Ganiron and Mohammed Almarwae (2014). “Prefabricated Technology in a Modular
House”, International Journal of Advanced Science and Technology, Vol. 73, pp 51-74.
[4] Rafael Sacks, Charles M. Eastman, Ghang Lee and David Orndorff (2005). “A Target
Benchmark of the Impact of Three-Dimensional Parametric Modeling in Precast Construction”,
Journal of the Precast/Prestressed Concrete Institute, pp 1-36.
[5] Yee, Alfred A., “Prestressed Concrete for Buildings,” PCI JOURNAL, V. 21, No. 5, September-
October 1976, Pp. 112-157.
[6] Yee, Alfred A., and Kim, Chang Nai, “One Hundred Washington Square: Structural Design and
Construction,” PCI JOURNAL, V. 29, No. 1, Jan uary-February 1984, pp. 24-48.
[7] Yee, Alfred A., “Precast Design and Construction Solutions,” CONSPEC TUS Technical
Journal 2000, Singapore Housing and Development Board, Singapore.
[8] “Precast Hybrid Moment Resistant Frames: Innovation History from Concept to Technology,”
Charles Pankow Builders, Ltd. & The Pankow Consortium, February 1996.
Suggested Citiation:
Murari, Shreyanka S. and Joshi, Ashwin M, Precast Construction Methodology in Construction Industry
(July 3, 2017). Available at SSRN: https://ssrn.com/abstract=3496019