PT.

Frasers Indonesia Mandiri


PEKERJAAN TIMBUNAN SUB GRADE
HIGH SPEED RAILWAY PROJECT JAKARTA - BANDUNG

Job Fill Embankment Date


Location 12# Subgrade Drawing
Stasioning

CALCULATION SHEET
CRUSH STONE MATERIAL A/B
NO STATION L/R AREA AVERAGE AREA LENGTH VOLUME AREA AVERAGE AREA LENGTH VOLUME
(M2) (M2) (M) (M3) (M2) (M2) (M) (M3)
1 54+068,00 L/R 36.220
31.455 20 629.100 20
2 54+088,00 L/R 26.690
20 20
3 54+100,00 L/R
0 0
4 54+100,00 L/R 18.600
8 18.6 8 148.800
5 54+108,00 L/R 18.600
20 18.015 20 360.300
6 54+128,00 L/R 17.43
20 17.455 20 349.100
7 54+148,00 L/R 17.48
20 17.410 20 348.200
8 54+168,00 L/R 17.34
20 17.495 20 349.900
9 54+188,00 L/R 17.65
20 17.595 20 351.900
10 54+208,00 L/R 17.54
20 17.315 20 346.300
11 54+228,00 L/R 17.090
20 17.190 20 343.800
12 54+248,00 L/R 17.290
20 17.260 20 345.200
13 54+268,00 L/R 17.230
19 17.185 19 326.515
14 54+287,00 L/R 17.14
18 17.215 18 309.870
15 54+305,00 L/R 17.29
18 17.380 18 312.840
16 54+323,00 L/R 17.47
20 17.505 20 350.100
17 54+343,00 L/R 17.540
20 17.465 20 349.300
18 54+363,00 L/R 17.390
24 17.470 24 419.280
19 54+387,00 L/R 17.550
22 17.480 22 384.560
20 54+409,00 L/R 17.410
21 17.245 21 362.145
21 54+430,00 L/R 17.080
20 17.370 20 347.400
22 54+450,00 L/R 17.660
20 17.585 20 351.700
23 54+470,00 L/R 17.510
20 17.550 20 351.000
24 54+490,00 L/R 17.590
10 17.435 10 174.350
25 54+500,00 L/R 17.280
0 0.000 0 0.000
26 54+500,00 L/R 19.77
10 18.710 10 187.100
27 54+510,00 L/R 17.650
10
28 54+520,00 L/R 13.9
14.930 10 149.300
29 54+530,00 L/R 15.96

SUB TOTAL 1 778.400 SUB TOTAL 1 7,169.660