MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
JR. 23 DE MAYO- AV. 2 DE MAYO (DERECHA) TIP1( 3UND) 1.00 AREA 5.67 5.67
VERMA CENTRAL TIP1( 4UND) 1.00 AREA 7.56 7.56
PARQUE TIP1( 2UND) 1.00 AREA 3.78 3.78
JR. 23 DE MAYO- PILICIA (IZQUIERDA) TIP1( 3UND) 1.00 AREA 5.67 5.67
AV. L.G. CHIPOCO-AV. FAUSTINO SANCHEZ TIP1( 2UND) 1.00 AREA 3.78 3.78
AV. FAUSTINO SANCHEZ-AV. 2 DE MAYO TIP1( 4UND) 1.00 AREA 7.56 7.56
RAMPAS VEHICULOS PESADOS
ENTRE AV. BENAVIDES-AV L.G. CHIPOCO
AV. PROGRESO-AV. UNION (IZQUIERDA) TIP 1 (2 und) 1.00 AREA 22.18 22.18
AV. BENAVIDES-AV. L G. CHIPOCO (IZQUIERDA) TIP 1 (1 und) 1.00 AREA 8.07 8.07
RAMPAS VEHICULOS LIVIANOS
ENTRE AV. BENAVIDES-AV L.G. CHIPOCO
AV. PROGRESO-AV. UNION (IZQUIERDA) 1.00 AREA 4.58 4.58
AV. SAN MARTIN- BELAUNDE IZQUIERDA 1.00 AREA 14.54 14.54
AV. BENAVIDES-AV. L G. CHIPOCO (IZQUIERDA) 1.00 AREA 41.55 41.55
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
RAMPAS DISCAPASITADOS
ENTRE AV. ALFONZO UGARTE-AV. MIGUEL GRAU
AV. ALFONZO UGARTE-AV. MIGUEL GRAU (DERECHA) TIP1( 4 UND) 1.00 AREA 7.56 7.56
VERMA CENTRAL
TIPO 1 (4 UND) 1.00 AREA 7.56 7.56
TIPO 2 (2 UND) 1.00 AREA 7.53 7.53
CALLE-ALFONZO UGARTE-CALLE MIGUEL GRAU(IZQUIERDA) TIP1 (4UND) 1.00 AREA 7.56 7.56
SARDINEL
ENTRE AV. ALFONZO UGARTE - AV SUCRE
AV.MIGUEL GRAU - AV. BOLOGNESI (DERECHA)
1.00 12.34 0.15 1.85
CALLE. ALFORNSO UGARTE - AV. MIGUEL GRAU (IZQUIERDA)
1.00 14.80 0.15 2.22
1.00 15.76 0.15 2.36
PASJE ROSALES - AV. SUCRE (IZQUIERDA)
1.00 17.15 0.15 2.57
1.00 25.41 0.15 3.81
AREAS VERDES
AV. MIGUEL GRAU - PASAJE ROSALES (CENTRAL)
ENTRE AV. ALFONZO UGARTE - AV.SUCRE
AV.MIGUEL GRAU - AV. BOLOGNESI
1.00 AREA 6.78 6.78
CALLE. ALFORNSO UGARTE - AV. MIGUEL GRAU
1.00 AREA 14.80 14.80
1.00 AREA 15.76 15.76
PASJE ROSALES -AV.SUCRE
1.00 AREA 10.66 10.66
1.00 AREA 11.85 11.85
01.01.04 INTERFERENCIAS
01.01.04.01 PROTECCIÓN TUBERÍA TRONCAL ACERO AB DE LINEA GAS Ø 6" M
PRIMERA ETAPA
AV. ANDRES BELAUNDE - AV 2 DE MAYO 1.00 427.31 427.31
AV. ANDRE BLEAUNDE D.C. IZQUIERDA 1.00 41.63 41.63
SEGUNDA ETAPA
ENTRE AV. 2 DE MAYO - AV SIMON BOLIVAR 1.00 400.14 400.14
AV. SIMON BOLIVAR B.C. DERECHA 1.00 22.39 22.39
METRADO
PROYECTO: "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DE LA AVENIDA UNION DISTRITO
DE PUEBLO NUEVO- PROVINCIA CHINCHA- DEPARTAMENTO ICA"
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
ENTRE AV. SIMON BOLIVAR - AV. ALFONZO UGARTE 1.00 250.70 250.70
AV. ALFONZO UGARTE B.C. DERECHA 1.00 24.82 24.82
AV. ALFONZO UGARTE B.C. IZQUIERDA 1.00 27.45 27.45
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
SEGUNDA ETAPA
PROLG. RAZURI - PSJ SAN ANTONIO 49.00 49.00
PSJ SAN ANTONIO- JIRON SAN ANTONIO(IZQUIERDA) 7.00 7.00
AV. 2 DE MAYO - JIRON TUPAC AMARU(DERECHA) 6.00 6.00
AV. SIMON BOLIVAR - AV. ALFONSO UGARTE(DERECHA) 8.00 8.00
JIRON SAN ANTONIO- AV. ALFONSO UGARTE(IZQUIERDA) 20.00 20.00
TERCERA ETAPA
AV. ALFONSO UGARTE- AV. GRAU(IZQUIERDA) 6.00 6.00
AV. GRAU - PSJ LOS ROSALES(IZQUIERDA) 7.00 7.00
PSJ LOS ROSALES-AV.SUCRE(IZQUIERDA) 6.00 6.00
AV. ALFONSO UGARTE- AV. SUCRE(DERECHA) 9.00 9.00
01.01.06 REMOCIONES
01.01.06.01 DESMONTAJE DE POSTES METALICOS DE SEMAFORO VEHICULAR UND
PRIMERA ETAPA
ENTRE AV. BENAVIDES- AV. UNION 3.00 3.00
ENTRE AV L.G CHIPOCO-AV UNION 2.00 2.00
SEGUNDA ETAPA
ENTRE AV. 2 DE MAYO - AV. UNION 2.00 2.00
01.01.06.02 DESMONTAJE DE POSTES METALICOS DE SEMAFORO PATONAL UND
PRIMERA ETAPA
ENTRE AV. BENAVIDES- AV. UNION 3.00 3.00
SEGUNDA ETAPA
ENTRE AV. 2 DE MAYO - AV. UNION 1.00 1.00
01.01.06.03 DESMONTAJE DE PARANTES DE BAMBU UND
PRIMERA ETAPA
AV. BENAVIDES- AV BELAUNDE (DERECHA) 2.00 2.00
AV. BELAUNDE-AV. SANCHEZ CARRION (IZQUIERDA) 7.00 7.00
AV. 12 DE OCTUBRE - AV. 2 DE MAYO(DERECHA) 2.00 2.00
AV. SANCHEZ CARRION - AV. RAZURI 3.00 3.00
SEGUNDA ETAPA
AV. RAZURI -JIRON SAN ANTONIO (IZQUIERDA) 34.00 34.00
AV. SIMON BOLIVAR - AV. LOS INCAS (DERECHA) 6.00 6.00
JIRON SAN ANTONIO-AV. ALFONSO UGARTE (IZQUIERDA) 8.00 8.00
TERCERA ETAPA
AV. ALFONSO UGARTE - PSJ LOS ROSALES (IZQUIERDA) 11.00 11.00
AV GRAU- AV. SUCRE (DERECHA) 4.00 4.00
PSJ LOS ROSALES- AV.SUCRE(IZQUIERDA) 1.00 1.00
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
SEGUNDA ETAPA
AV. 2 DE MAYO - JIRON SAN ISIDRO (DERECHA) 5.00 5.00
PROL. RAZURI-JR. SAN ANTONIO (IZQUIERDA) 7.00 7.00
PSJ SAN ANTONIO-AV. ALFONSO UGARTE(IZQUIERDA) 4.00 4.00
TERCERA ETAPA
AV. ALFONSO UGARTE- AV. SUCRE (DERECHO) 4.00 4.00
AV. GRAU- PSJ LOS ROSALES (IZQUIERDO) 3.00 3.00
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
01.01.07 DEMOLICIONES
01.01.07.01 CORTE DE VEREDA EXISTENTE h=4´ M
PRIMERA ETAPA
AV. SAN MARTIN(DERECHA) 1.00 1.80 1.80
1.00 1.90 1.90
AV. BELAUNDE (DERECHA) 1.00 3.01 3.01
AV. 12 DE OCTUBRE(DERECHA) 1.00 3.00 3.00
1.00 3.00 3.00
AV. SANCHEZ CARRION (IZQUIERDA) 1.00 2.25 2.25
1.00 2.17 2.17
SEGUNDA ETAPA
PROL. A. RAZURI(IZQUIERDA) 1.00 1.70 1.70
AV. SIMON BOLIVAR (DERECHA) 1.00 2.35 2.35
1.00 2.28 2.28
AV. LOS INCAS (IZQUIERDA) 1.00 2.12 2.12
1.00 2.17 2.17
PSJ. SAN ANTONIO (IZQUIERDA) 1.00 0.82 0.82
1.00 1.21 1.21
AV. I. GARCILAZO DE LA VEGA (DERECHA) 1.00 3.43 3.43
TERCERA ETAPA
AV. ALFONSO UGARTE (DERECHA) 1.00 2.30 2.30
1.00 3.03 3.03
AV. GRAU 1.00 2.27 2.27
1.00 2.27 2.27
AV. SUCRE 1.00 1.58 1.58
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
PRIMERA ETAPA
AV. BENAVIDES-AV. CHIPOCO(IZQUIERDA) 2.00 2.00
AV. GALVEZ CHIPOCO-AV. SANCHEZ CARRION(IZQUIERDA) 1.00 1.00
SEGUNDA ETAPA
JIRON SAN ISIDRO-JIRON TUPAC AMARU 1.00 1.00
PSJ SAN ANTONIO-AV. ALFONSO UGARTE 3.00 3.00
TERCERA ETAPA
AV. GRAU-AV. BOLOGNESI 2.00 2.00
METRADO
PROYECTO: "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DE LA AVENIDA UNION DISTRITO
DE PUEBLO NUEVO- PROVINCIA CHINCHA- DEPARTAMENTO ICA"
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
RAMPAS DISCAPASITADOS
ENTRE AV. ALFONZO UGARTE-AV. MIGUEL GRAU
AV. ALFONZO UGARTE-AV. MIGUEL GRAU (DERECHA) TIP1( 4 UND) 1.00 AREA 7.56 7.56
VERMA CENTRAL
TIPO 1 (4 UND) 1.00 AREA 7.56 7.56
TIPO 2 (2 UND) 1.00 AREA 7.53 7.53
CALLE-ALFONZO UGARTE-CALLE MIGUEL GRAU(IZQUIERDA) TIP1 (4UND) 1.00 AREA 7.56 7.56
SARDINEL
ENTRE AV. ALFONZO UGARTE - AV. SUCRE
AV.MIGUEL GRAU - AV. BOLOGNESI (DERECHA)
1.00 12.34 0.15 1.85
CALLE. ALFORNSO UGARTE - AV. MIGUEL GRAU (IZQUIERDA)
1.00 14.80 0.15 2.22
1.00 15.76 0.15 2.36
PASJE ROSALES - AV.SUCRE (IZQUIERDA)
1.00 17.15 0.15 2.57
1.00 25.41 0.15 3.81
AREA VERDE
ENTRE AV. ALFONZO UGARTE - AV.SUCRE
AV.MIGUEL GRAU - AV. BOLOGNESI (DERECHA)
METRADO
PROYECTO: "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DE LA AVENIDA UNION DISTRITO
DE PUEBLO NUEVO- PROVINCIA CHINCHA- DEPARTAMENTO ICA"
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
JR. 23 DE MAYO- AV. 2 DE MAYO (DERECHA) TIP1( 3UND) 1.00 AREA 5.67 5.67
VERMA CENTRAL TIP1( 4UND) 1.00 AREA 7.56 7.56
PARQUE TIP1( 2UND) 1.00 AREA 3.78 3.78
JR. 23 DE MAYO- PILICIA (IZQUIERDA) TIP1( 3UND) 1.00 AREA 5.67 5.67
AV. L.G. CHIPOCO-AV. FAUSTINO SANCHEZ TIP1( 2UND) 1.00 AREA 3.78 3.78
AV. FAUSTINO SANCHEZ-AV. 2 DE MAYO TIP1( 4UND) 1.00 AREA 7.56 7.56
RAMPAS VEHICULOS PESADOS
ENTRE AV. BENAVIDES-AV L.G. CHIPOCO
AV. PROGRESO-AV. UNION (IZQUIERDA) TIP 1 (2 und) 1.00 AREA 22.18 22.18
AV. BENAVIDES-AV. L G. CHIPOCO (IZQUIERDA) TIP 1 (1 und) 1.00 AREA 8.07 8.07
RAMPAS VEHICULOS LIVIANOS
ENTRE AV. BENAVIDES-AV L.G. CHIPOCO
AV. PROGRESO-AV. UNION (IZQUIERDA) 1.00 AREA 4.58 4.58
AV. SAN MARTIN- BELAUNDE IZQUIERDA 1.00 AREA 14.54 14.54
AV. BENAVIDES-AV. L G. CHIPOCO (IZQUIERDA) 1.00 AREA 41.55 41.55
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
RAMPAS DISCAPASITADOS
ENTRE AV. ALFONZO UGARTE-AV. MIGUEL GRAU
AV. ALFONZO UGARTE-AV. MIGUEL GRAU (DERECHA) TIP1( 4 UND) 1.00 AREA 7.56 7.56
VERMA CENTRAL
TIPO 1 (4 UND) 1.00 AREA 7.56 7.56
TIPO 2 (2 UND) 1.00 AREA 7.53 7.53
CALLE-ALFONZO UGARTE-CALLE MIGUEL GRAU(IZQUIERDA) TIP1 (4UND) 1.00 AREA 7.56 7.56
SARDINEL
ENTRE AV. ALFONZO UGARTE - COMPLEJO MIGUEL GRAU
AV.MIGUEL GRAU - AV. BOLOGNESI (DERECHA)
1.00 12.34 0.15 1.85
CALLE. ALFORNSO UGARTE - AV. MIGUEL GRAU (IZQUIERDA)
1.00 14.80 0.15 2.22
1.00 15.76 0.15 2.36
PASJE ROSALES - COMPLEJO DEORTIVO MIGUEL GRAU (IZQUIERDA)
1.00 17.15 0.15 2.57
1.00 25.41 0.15 3.81
AREA VERDE
AV. MIGUEL GRAU - PASAJE ROSALES (CENTRAL)
ENTRE AV. ALFONZO UGARTE - AV.SUCRE
AV.MIGUEL GRAU - AV. BOLOGNESI (DERECHA)
1.00 AREA 6.78 6.78
CALLE. ALFORNSO UGARTE - AV. MIGUEL GRAU (IZQUIERDA)
1.00 AREA 14.80 14.80
1.00 AREA 15.76 15.76
PASJE ROSALES - AV. SUCRE (IZQUIERDA)
1.00 AREA 10.66 10.66
1.00 AREA 11.85 11.85
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
1.00 1.00
02 PISTAS Y VEREDAS
02.01 MOVIMIENTO DE TIERRA
EXCAVACION A NIVEL DE SUBRASANTE PISTA, VEREDAS, MARTILLOS Y
02.01.01 m3
RAMPAS
DETALLE EN PLANTILLA MOVIMIENTO DE TIERRAS 1.00 VOLIMEN 19,854.82 19,854.82
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
PRIMERA ETAPA
AV. PROGRESO 1.00 AREA 1655.15 1655.15
AV BENAVIDES B.C. DERECHA 1.00 AREA 98.12 98.12
ENTRE AV. BENAVIDES-AV L.G. CHIPOCO 1.00 AREA 2527.80 2527.80
AV. SAN MARTIN B.C. DERECHA 1.00 AREA 86.24 86.24
AV. LG.CHIPOCO B.C. DERECHA 1.00 AREA 336.93 336.93
AV. LG.CHIPOCO B.C. IZQUIERDA 1.00 AREA 421.65 421.65
ENTRE AV. L.G. CHIPOCO- AV 12 DE OCTUBRE 1.00 AREA 1840.57 1840.57
AV. 12 DE OCTUBRE B.C. DERECHA 1.00 AREA 66.75 66.75
ENTRE AV.12 DE OCTUBRE- OVALO FELIX TARDIO 1.00 AREA 1887.19 1887.19
ENTRE JR 23 DE MAYO-OVALO FELIX TARDIO 1.00 AREA 1972.37 1972.37
OVALO FELIX TARDIO 1.00 AREA 850.00 850.00
ENTRE OVALO FELIX TARDIO-AV.2 DE MAYO 1.00 AREA 842.38 842.38
SEGUNDA ETAPA AREA
OVALO 2 DE MAYO 1.00 AREA 751.17 751.17
AV. 2 DE MAYO B.C. DERECHA 1.00 AREA 320.21 320.21
AV. 2 DE MAYO B.C. IZQUIERDA 1.00 AREA 45.06 45.06
ENTRE OVALO 2 DE MAYO-JR. SAN ISIDRO 1.00 AREA 157.39 157.39
JR. SAN ISIDRO B.C. DERECHA 1.00 AREA 107.77 107.77
ENTRE JR. SAN ISIDRO-JR. SIMON BOLIVAR 1.00 AREA 4398.56 4398.56
JR. TUPAC AMARU B.C. DERECHA 1.00 AREA 52.89 52.89
JR. SIMON BOLIVAR B.C. DERECHA 1.00 AREA 58.14 58.14
PSJ. SAN ANTONIO B.C. IZQUIERDA 1.00 AREA 98.36 98.36
ENTRE JR. SIMON BOLIVAR-AV. LOS INCAS 1.00 AREA 1547.87 1547.87
AV. LOS INCAS B.C. DERECHA 1.00 AREA 66.41 66.41
JR. SAN ANTONIO B.C. IZQUIERDA 1.00 AREA 81.55 81.55
ENTRE AV. LOS INCAS-AV. ALFONZO UGARTE 1.00 AREA 1894.26 1894.26
AV. GARCILAZO DE LA VEGA B.C. DERECHA 1.00 AREA 163.32 163.32
TERCERA ETAPA AREA
ENTRE AV. ALFONZO UGARTE-AV. MIGUEL GRAU 1.00 AREA 1608.62 1608.62
AV. ALFONZO UGARTE B.C. DERECHA 1.00 AREA 82.92 82.92
CALLE ALFONZO UGARTE B.C. IZQUIERDA 1.00 AREA 113.04 113.04
AV MIGUEL GRAU B.C. DERECHA 1.00 AREA 55.99 55.99
CALLE MIGUEL GRAU B.C. IZQUIERDA 1.00 AREA 80.35 80.35
ENTRE AV. MIGUEL GRAU- AV. BOLOGNESI 1.00 AREA 1845.33 1845.33
AV. BOLOGNESI B.C. DERECHA 1.00 AREA 176.73 176.73
PSJ. LAS FLORES B.C. IZQUIERDA 1.00 AREA 162.64 162.64
ENTRE AV. BOLOGNESI-AV.SUCRE 1.00 AREA 1172.77 1172.77
AV. SUCRE B.C. DERECHA 1.00 AREA 176.73 176.73
PRIMERA ETAPA
METRADO
PROYECTO: "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DE LA AVENIDA UNION DISTRITO
DE PUEBLO NUEVO- PROVINCIA CHINCHA- DEPARTAMENTO ICA"
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
PRIMERA ETAPA
ENTRE AV. BENAVIDES-AV L.G. CHIPOCO
AV. RPOGRESO- AV. UNION (DERECHA) 1.00 AREA 40.32 40.32
AV. BENAVIDES-AV SAN MARTIN (DERECHA) 1.00 AREA 87.50 87.50
AV. SAN MARTIN- BELAUNDE 1.00 AREA 281.59 281.59
VERMA CENTRAL 1.00 AREA 693.94 693.94
AV. PROGRESO-AV. UNION (IZQUIERDA) 1.00 AREA 153.38 153.38
AV. BENAVIDES-AV. L G. CHIPOCO (IZQUIERDA) 1.00 AREA 613.26 613.26
SEGUNDA ETAPA
ENTRE OVALO 2 DE MAYO-JR SIMON BOLIVAR
AV. 2 DE MAYO-JR. SAN ISIDRO (DERECHA) 1.00 AREA 298.89 298.89
JR. SAN ISIDRO-JR. TUPAC AMARU (DERECHA) 1.00 AREA 103.50 103.50
JR. TUPAC AMARU-JR. SIMON BOLIVAR 1.00 AREA 764.42 764.42
OVALO 2 DE MAYO 1.00 AREA 71.23 71.23
VERMA CENTRAL 1.00 AREA 2789.24 2789.24
PROLONG. RASURI-PSJ SAN ANTONIO 1.00 AREA 1377.55 1377.55
TERCERA ETAPA
ENTRE AV. ALFONZO UGARTE-AV. MIGUEL GRAU
AV. ALFONZO UGARTE-AV. MIGUEL GRAU (DERECHA) 1.00 AREA 199.10 199.10
VERMA CENTRAL 1.00 AREA 695.14 695.14
CALLE-ALFONZO UGARTE-CALLE MIGUEL GRAU(IZQUIERDA) 1.00 AREA 225.92 225.92
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
SEGUNDA ETAPA
ENTRE OVALO 2 DE MAYO-JR SIMON BOLIVAR
AV. UNION Y AV. 2 DE MAYO 1.00 AREA 46.96
AV. UNION Y JR. SAN ISIDRO 1.00 AREA 49.43
AV. UNION Y JR. TUPAC AMARU 1.00 AREA 23.09 23.09
AV. UNION Y JR. SIMON BOLIVAR 1.00 AREA 99.83 99.83
ENTRE JR. SIMON BOLIVAR-AV. LOS INCAS
AV. UNION Y JR. SIMON BOLIVAR 1.00 AREA 85.17 85.17
AV. UNION Y JR. SAN ANTONIO 1.00 AREA 53.57 53.57
AV. UNION Y LOS INCAS 1.00 AREA 96.25 96.25
ENTRE AV. LOS INCAS-AV. ALFONZO UGARTE
AV. UNION Y AV. GARCILAZO DE LA VEGA 1.00 AREA 33.38 33.38
AV. UNION Y AV. ALFONZO UGARTE 1.00 AREA 55.57 55.57
TERCERA ETAPA
ENTRE AV. ALFONZO UGARTE-AV. MIGUEL GRAU
AV. UNION Y AV. ALFONZO UGARTE 1.00 AREA 81.69 81.69
AV. UNION Y AV. MIGUEL GRAU 1.00 AREA 114.30 114.30
ENTRE AV. MIGUEL GRAU- AV. BOLOGNESI
AV UNION Y AV. BOLOGNESI 1.00 AREA 87.11 87.11
ENTRE AV. BOLOGNESI-AV.SUCRE
AV. UNION Y AV. SUCRE 1.00 AREA 29.59 29.59
SEGUNDA ETAPA
ENTRE OVALO 2 DE MAYO-JR SIMON BOLIVAR
AV. 2 DE MAYO-JR. SAN ISIDRO (DERECHA) TIP1 (4 UND) 1.00 AREA 7.56 7.56
JR. SAN ISIDRO-JR. TUPAC AMARU (DERECHA) TIP (2UND) 1.00 AREA 3.78 3.78
JR. TUPAC AMARU-JR. SIMON BOLIVAR TIP (4UND) 1.00 AREA 7.56 7.56
VERMA CENTRAL
TIPO 1 (14 UND) 1.00 AREA 26.47 26.47
TIPO2 ( 5 UND) 1.00 AREA 18.84 18.84
PROLONG. RASURI-PSJ SAN ANTONIO TIP1 (7 UND) 1.00 AREA 13.24 13.24
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
TERCERA ETAPA
ENTRE AV. ALFONZO UGARTE-AV. MIGUEL GRAU
AV. ALFONZO UGARTE-AV. MIGUEL GRAU (DERECHA) TIP1( 4 UND) 1.00 AREA 7.56 7.56
VERMA CENTRAL
TIPO 1 (4 UND) 1.00 AREA 7.56 7.56
TIPO 2 (2 UND) 1.00 AREA 7.53 7.53
CALLE-ALFONZO UGARTE-CALLE MIGUEL GRAU(IZQUIERDA) TIP1 (4UND) 1.00 AREA 7.56 7.56
SEGUNDA ETAPA
ENTRE JR. SIMON BOLIVAR-AV. LOS INCAS TIP1 (1 UND)
CRUCE LOS INCAS- CALLE ALFONZO UGARTE (IZQUIERDA) 1.00 AREA 4.05 4.05
TERCERA ETAPA
ENTRE AV. MIGUEL GRAU- AV. BOLOGNESI TIP2(1 UND)
AV. MIGUEL GRAU-AV. BOLOGNESI (DERECHA) 1.00 AREA 20.63 20.63
AV. BOLOGNESI-AV. SUCRE (DERECHA) TIP1 (1und) 1.00 AREA 1.97 1.97
CRUCE BOLOGNESI-AV.SUCRE (IZQUIERDA) TIP2 (1und) 1.00 AREA 19.18 19.18
SUB BASE GRANULAR EN RAMPAS VEHICULOS LIVIANOS E=20CM
PRIMERA ETAPA
ENTRE AV. BENAVIDES-AV L.G. CHIPOCO
AV. PROGRESO-AV. UNION (IZQUIERDA) 1.00 AREA 4.58 4.58
AV. SAN MARTIN- BELAUNDE IZQUIERDA 1.00 AREA 14.54 14.54
AV. BENAVIDES-AV. L G. CHIPOCO (IZQUIERDA) 1.00 AREA 41.55 41.55
SEGUNDA ETAPA
ENTRE OVALO 2 DE MAYO-JR SIMON BOLIVAR
AV. 2 DE MAYO-JR. SAN ISIDRO (DERECHA) 1.00 AREA 15.22 15.22
JR. SAN ISIDRO-JR. TUPAC AMARU (DERECHA) 1.00 AREA 2.46 2.46
JR. TUPAC AMARU-JR. SIMON BOLIVAR 1.00 AREA 15.94 15.94
PROLONG. RASURI-PSJ SAN ANTONIO 1.00 AREA 36.49 36.49
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
TERCERA ETAPA
ENTRE AV. ALFONZO UGARTE-AV. MIGUEL GRAU
AV. ALFONZO UGARTE-AV. MIGUEL GRAU (DERECHA) 1.00 AREA 3.94 3.94
CALLE-ALFONZO UGARTE-CALLE MIGUEL GRAU(IZQUIERDA) 1.00 AREA 8.66 8.66
SEGUNDA ETAPA
ENTRE OVALO 2 DE MAYO-JR SIMON BOLIVAR
AV. 2 DE MAYO-JR. SAN ISIDRO (DERECHA) 1.00 AREA 298.89 298.89
JR. SAN ISIDRO-JR. TUPAC AMARU (DERECHA) 1.00 AREA 103.50 103.50
JR. TUPAC AMARU-JR. SIMON BOLIVAR 1.00 AREA 764.42 764.42
OVALO 2 DE MAYO 1.00 AREA 71.23 71.23
VERMA CENTRAL 1.00 AREA 2789.24 2789.24
PROLONG. RASURI-PSJ SAN ANTONIO 1.00 AREA 1377.55 1377.55
TERCERA ETAPA
ENTRE AV. ALFONZO UGARTE-AV. MIGUEL GRAU
AV. ALFONZO UGARTE-AV. MIGUEL GRAU (DERECHA) 1.00 AREA 199.10 199.10
VERMA CENTRAL 1.00 AREA 695.14 695.14
CALLE-ALFONZO UGARTE-CALLE MIGUEL GRAU(IZQUIERDA) 1.00 AREA 225.92 225.92
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
SEGUNDA ETAPA
ENTRE OVALO 2 DE MAYO-JR SIMON BOLIVAR
AV. 2 DE MAYO-JR. SAN ISIDRO (DERECHA) 1.00 98.13 0.15 14.72
JR. SAN ISIDRO-JR. TUPAC AMARU (DERECHA) 1.00 48.23 0.15 7.23
JR. TUPAC AMARU-JR. SIMON BOLIVAR 1.00 225.42 0.15 33.81
OVALO 2 DE MAYO 1.00 33.10 0.15 4.97
VERMA CENTRAL 1.00 1578.45 0.15 236.77
PROLONG. RASURI-PSJ SAN ANTONIO 1.00 301.51 0.15 45.23
TERCERA ETAPA
ENTRE AV. ALFONZO UGARTE-AV. MIGUEL GRAU
AV. ALFONZO UGARTE-AV. MIGUEL GRAU (DERECHA) 1.00 49.23 0.15 7.38
VERMA CENTRAL 1.00 159.57 0.15 23.94
CALLE-ALFONZO UGARTE-CALLE MIGUEL GRAU(IZQUIERDA) 1.00 57.50 0.15 8.62
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
SEGUNDA ETAPA
ENTRE OVALO 2 DE MAYO-JR SIMON BOLIVAR
AV. UNION Y AV. 2 DE MAYO 1.00 AREA 46.96
AV. UNION Y JR. SAN ISIDRO 1.00 AREA 49.43
AV. UNION Y JR. TUPAC AMARU 1.00 AREA 23.09 23.09
AV. UNION Y JR. SIMON BOLIVAR 1.00 AREA 99.83 99.83
ENTRE JR. SIMON BOLIVAR-AV. LOS INCAS
AV. UNION Y JR. SIMON BOLIVAR 1.00 AREA 85.17 85.17
AV. UNION Y JR. SAN ANTONIO 1.00 AREA 53.57 53.57
AV. UNION Y LOS INCAS 1.00 AREA 96.25 96.25
ENTRE AV. LOS INCAS-AV. ALFONZO UGARTE
AV. UNION Y AV. GARCILAZO DE LA VEGA 1.00 AREA 33.38 33.38
AV. UNION Y AV. ALFONZO UGARTE 1.00 AREA 55.57 55.57
TERCERA ETAPA
ENTRE AV. ALFONZO UGARTE-AV. MIGUEL GRAU
AV. UNION Y AV. ALFONZO UGARTE 1.00 AREA 81.69 81.69
AV. UNION Y AV. MIGUEL GRAU 1.00 AREA 114.30 114.30
ENTRE AV. MIGUEL GRAU- AV. BOLOGNESI
AV UNION Y AV. BOLOGNESI 1.00 AREA 87.11 87.11
ENTRE AV. BOLOGNESI-AV.SUCRE
AV. UNION Y AV. SUCRE 1.00 AREA 29.59 29.59
SEGUNDA ETAPA
ENTRE OVALO 2 DE MAYO-JR SIMON BOLIVAR
AV. UNION Y AV. 2 DE MAYO 1.00 13.89 0.15 2.08
AV. UNION Y JR. SAN ISIDRO 1.00 13.76 0.15 2.06
AV. UNION Y JR. TUPAC AMARU 1.00 13.64 0.15 2.05
AV. UNION Y JR. SIMON BOLIVAR 1.00 18.93 0.15 2.84
ENTRE JR. SIMON BOLIVAR-AV. LOS INCAS
AV. UNION Y JR. SIMON BOLIVAR 1.00 23.96 0.15 3.59
AV. UNION Y JR. SAN ANTONIO 1.00 28.89 0.15 4.33
AV. UNION Y LOS INCAS 1.00 21.16 0.15 3.17
ENTRE AV. LOS INCAS-AV. ALFONZO UGARTE
AV. UNION Y AV. GARCILAZO DE LA VEGA 1.00 12.51 0.15 1.88
AV. UNION Y AV. ALFONZO UGARTE 1.00 12.83 0.15 1.92
TERCERA ETAPA
ENTRE AV. ALFONZO UGARTE-AV. MIGUEL GRAU
AV. UNION Y AV. ALFONZO UGARTE 1.00 23.31 0.15 3.50
AV. UNION Y AV. MIGUEL GRAU 1.00 29.31 0.15 4.40
ENTRE AV. MIGUEL GRAU- AV. BOLOGNESI
AV UNION Y AV. BOLOGNESI 1.00 31.83 0.15 4.77
ENTRE AV. BOLOGNESI-AV.SUCRE
AV. UNION Y AV. SUCRE 1.00 10.20 0.15 1.53
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
SEGUNDA ETAPA M
ENTRE AV. 2 DE MAYO - AV. ALFONSO UGARTE
EXCAVACION PARA UÑAS DE VEREDAS LATERALES
AV. 2 DEMAYO - JR. SAN ISIDRO (DERECHA) 1.00 176.30 176.30
JR. SAN ISIDRO - JR. TUPAC AMARU (DERECHA) 1.00 86.26 86.26
JR. TUPAC AMARU - JR. SIMON BOLIVAR (DERECHA) 1.00 276.65 276.65
JR. SIMON BOLIVAR - AV- LOS INCAS (DERECHA) 1.00 125.04 125.04
AV. LOS INCAS - AV. INCA GARCILAZO D.VEGA (DERECHA) 1.00 103.61 103.61
AV. INCA GARCILAZO D.VEGA - AV ALFONSO UGARTE (DERECHA) 1.00 111.15 111.15
PROL. RAZURI - PASAJ. SAN COSME (IZQUIERDA) 1.00 457.20 457.20
PASAJ. SAN COME - PASAJ. SAN ANTONIO (IZQUIERDA) 1.00 103.56 103.56
PASAJ. SAN ANTONIO - CALLE. ALFONSO UGARTE (IZQUIERDA) 1.00 235.95 235.95
EXCAVACION PARA UÑAS DE VEREDAS CENTRAL
AV. 2 DEMAYO - JR. SAN ISIDRO 1.00 247.64 247.64
JR. SAN ISIDRO - JR.SIMON BOLIVAR 1.00 584.56 584.56
JR. SIMON BOLIVAR - AV- LOS INCAS 1.00 191.83 191.83
AV. LOS INCAS - AV. INCA GARCILAZO D.VEGA 1.00 140.01 140.01
AV. INCA GARCILAZO D.VEGA - AV ALFONSO UGARTE 1.00 166.13 166.13
UÑA EN RAMPAS PEATONALES Y VEICULARES
EXCAVACION PARA UÑAS DE RAMPAS LATERALES
AV. 2 DEMAYO - JR. SAN ISIDRO (DERECHA) 1.00 40.09 40.09
JR. SAN ISIDRO - JR. TUPAC AMARU (DERECHA) 1.00 13.01 13.01
JR. TUPAC AMARU - JR. SIMON BOLIVAR (DERECHA) 1.00 22.29 22.29
JR. SIMON BOLIVAR - AV- LOS INCAS (DERECHA) 1.00 16.99 16.99
AV. LOS INCAS - AV. INCA GARCILAZO D.VEGA (DERECHA) 1.00 14.99 14.99
AV. INCA GARCILAZO D.VEGA - AV ALFONSO UGARTE (DERECHA) 1.00 14.40 14.40
PROL. RAZURI - PASAJ. SAN COSME (IZQUIERDA) 1.00 91.88 91.88
PASAJ. SAN COME - PASAJ. SAN ANTONIO (IZQUIERDA) 1.00 24.15 24.15
PASAJ. SAN ANTONIO - CALLE. ALFONSO UGARTE (IZQUIERDA) 1.00 60.37 60.37
EXCAVACION PARA UÑAS DE RAMPAS CENTRAL
AV. 2 DEMAYO - JR. SAN ISIDRO 1.00 22.94 22.94
METRADO
PROYECTO: "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DE LA AVENIDA UNION DISTRITO
DE PUEBLO NUEVO- PROVINCIA CHINCHA- DEPARTAMENTO ICA"
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
SEGUNDA ETAPA
ENTRE JR. SIMON BOLIVAR-AV. LOS INCAS TIP1 (1 UND)
CRUCE LOS INCAS- CALLE ALFONZO UGARTE (IZQUIERDA) 1.00 AREA 4.05 4.05
TERCERA ETAPA
ENTRE AV. MIGUEL GRAU- AV. BOLOGNESI TIP2(1 UND)
AV. MIGUEL GRAU-AV. BOLOGNESI (DERECHA) 1.00 AREA 20.63 20.63
ENTRE AV. BOLOGNESI-AV.SUCRE TIP1( 1UND)-TIP2(1 UND)
AV. BOLOGNESI-AV. SUCRE (DERECHA) TIP1 (1und) 1.00 AREA 1.97 1.97
CRUCE BOLOGNESI-AV.SUCRE (IZQUIERDA) TIP2 (1und) 1.00 AREA 19.18 19.18
SEGUNDA ETAPA
ENTRE JR. SIMON BOLIVAR-AV. LOS INCAS TIP1 (1 UND)
CRUCE LOS INCAS- CALLE ALFONZO UGARTE (IZQUIERDA) 1.00 9.00 0.10 0.90
TERCERA ETAPA
ENTRE AV. MIGUEL GRAU- AV. BOLOGNESI TIP2(1 UND)
AV. MIGUEL GRAU-AV. BOLOGNESI (DERECHA) 1.00 17.56 0.10 1.76
ENTRE AV. BOLOGNESI-AV.SUCRE TIP1( 1UND)-TIP2(1 UND)
AV. BOLOGNESI-AV. SUCRE (DERECHA) TIP1 (1und) 1.00 4.83 0.10 0.48
CRUCE BOLOGNESI-AV.SUCRE (IZQUIERDA) TIP2 (1und) 1.00 15.31 0.10 1.53
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
SEGUNDA ETAPA
ENTRE OVALO 2 DE MAYO-JR SIMON BOLIVAR
AV. 2 DE MAYO-JR. SAN ISIDRO (DERECHA) 1.00 AREA 15.22 15.22
JR. SAN ISIDRO-JR. TUPAC AMARU (DERECHA) 1.00 AREA 2.46 2.46
JR. TUPAC AMARU-JR. SIMON BOLIVAR 1.00 AREA 15.94 15.94
PROLONG. RASURI-PSJ SAN ANTONIO 1.00 AREA 36.49 36.49
TERCERA ETAPA
ENTRE AV. ALFONZO UGARTE-AV. MIGUEL GRAU
AV. ALFONZO UGARTE-AV. MIGUEL GRAU (DERECHA) 1.00 AREA 3.94 3.94
CALLE-ALFONZO UGARTE-CALLE MIGUEL GRAU(IZQUIERDA) 1.00 AREA 8.66 8.66
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
SEGUNDA ETAPA
ENTRE OVALO 2 DE MAYO-JR SIMON BOLIVAR
AV. 2 DE MAYO-JR. SAN ISIDRO (DERECHA) 1.00 40.04 0.10 4.00
JR. SAN ISIDRO-JR. TUPAC AMARU (DERECHA) 1.00 6.71 0.10 0.67
JR. TUPAC AMARU-JR. SIMON BOLIVAR 1.00 12.40 0.10 1.24
PROLONG. RASURI-PSJ SAN ANTONIO 1.00 98.01 0.10 9.80
TERCERA ETAPA
ENTRE AV. ALFONZO UGARTE-AV. MIGUEL GRAU
AV. ALFONZO UGARTE-AV. MIGUEL GRAU (DERECHA) 1.00 19.45 0.10 1.94
CALLE-ALFONZO UGARTE-CALLE MIGUEL GRAU(IZQUIERDA) 1.00 22.47 0.10 2.25
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
AV. FAUSTINO SANCHEZ-AV. 2 DE MAYO TIP1( 4UND) 1.00 AREA 7.56 7.56
SEGUNDA ETAPA
ENTRE OVALO 2 DE MAYO-JR SIMON BOLIVAR
AV. 2 DE MAYO-JR. SAN ISIDRO (DERECHA) TIP1 (4 UND) 1.00 AREA 7.56 7.56
JR. SAN ISIDRO-JR. TUPAC AMARU (DERECHA) TIP (2UND) 1.00 AREA 3.78 3.78
JR. TUPAC AMARU-JR. SIMON BOLIVAR TIP (4UND) 1.00 AREA 7.56 7.56
VERMA CENTRAL
TIPO 1 (14 UND) 1.00 AREA 26.47 26.47
TIPO2 ( 5 UND) 1.00 AREA 18.84 18.84
PROLONG. RASURI-PSJ SAN ANTONIO TIP1 (7 UND) 1.00 AREA 13.24 13.24
TERCERA ETAPA
ENTRE AV. ALFONZO UGARTE-AV. MIGUEL GRAU
AV. ALFONZO UGARTE-AV. MIGUEL GRAU (DERECHA) TIP1( 4 UND) 1.00 AREA 7.56 7.56
VERMA CENTRAL
TIPO 1 (4 UND) 1.00 AREA 7.56 7.56
TIPO 2 (2 UND) 1.00 AREA 7.53 7.53
CALLE-ALFONZO UGARTE-CALLE MIGUEL GRAU(IZQUIERDA) TIP1 (4UND) 1.00 AREA 7.56 7.56
SEGUNDA ETAPA
ENTRE OVALO 2 DE MAYO-JR SIMON BOLIVAR
AV. 2 DE MAYO-JR. SAN ISIDRO (DERECHA) TIP1 (4 UND) 1.00 14.74 0.10 1.47
JR. SAN ISIDRO-JR. TUPAC AMARU (DERECHA) TIP (2UND) 1.00 7.37 0.10 0.74
JR. TUPAC AMARU-JR. SIMON BOLIVAR TIP (4UND) 1.00 14.74 0.10 1.47
VERMA CENTRAL
TIPO 1 (14 UND) 1.00 51.58 0.10 5.16
TIPO2 ( 5 UND) 1.00 32.92 0.10 3.29
PROLONG. RASURI-PSJ SAN ANTONIO TIP1 (7 UND) 1.00 25.79 0.10 2.58
METRADO
PROYECTO: "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DE LA AVENIDA UNION DISTRITO
DE PUEBLO NUEVO- PROVINCIA CHINCHA- DEPARTAMENTO ICA"
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
TERCERA ETAPA
ENTRE AV. ALFONZO UGARTE-AV. MIGUEL GRAU
AV. ALFONZO UGARTE-AV. MIGUEL GRAU (DERECHA) TIP1( 4 UND) 1.00 14.74 0.10 1.47
VERMA CENTRAL
TIPO 1 (4 UND) 1.00 14.74 0.10 1.47
TIPO 2 (2 UND) 1.00 13.17 0.10 1.32
CALLE-ALFONZO UGARTE-CALLE MIGUEL GRAU(IZQUIERDA) TIP1 (4UND) 1.00 14.74 0.10 1.47
SEGUNDA ETAPA
ENTRE OVALO 2 DE MAYO-JR SIMON BOLIVAR
AV. 2 DE MAYO-JR. SAN ISIDRO (DERECHA) 1.00 125.53 125.53
JR. SAN ISIDRO-JR. TUPAC AMARU (DERECHA) 1.00 46.16 46.16
JR. TUPAC AMARU-JR. SIMON BOLIVAR 1.00 369.41 369.41
OVALO 2 DE MAYO 1.00 38.80 38.80
VERMA CENTRAL 1.00 1639.22 1639.22
PROLONG. RASURI-PSJ SAN ANTONIO 1.00 483.49 483.49
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
TERCERA ETAPA
ENTRE AV. ALFONZO UGARTE-AV. MIGUEL GRAU
AV. ALFONZO UGARTE-AV. MIGUEL GRAU (DERECHA) 1.00 91.90 91.90
VERMA CENTRAL 1.00 378.89 378.89
CALLE-ALFONZO UGARTE-CALLE MIGUEL GRAU(IZQUIERDA) 1.00 107.34 107.34
MARTILLOS
ENTRE AV. BENAVIDES-AV L.G. CHIPOCO
AV.UNION Y AV. PROGRESO 1.00 AREA 71.24 71.24
AV. UNION Y AV. SAN MARTIN 1.00 AREA 28.14 28.14
AV. UNION Y AV. L.G. CHIPOCO 1.00 AREA 61.32 61.32
RAMPAS PEATONALES
ENTRE AV. L.G. CHIPOCO- OVALO 2 DE MAYO
AV. L.G. CHIPOCO-AV. FAUSTINO SANCHEZ ( IZQUIERDA) 1.00 AREA 16.72 16.72
METRADO
PROYECTO: "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DE LA AVENIDA UNION DISTRITO
DE PUEBLO NUEVO- PROVINCIA CHINCHA- DEPARTAMENTO ICA"
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
RAMPAS DISCAPASITADOS
ENTRE AV. BENAVIDES-AV L.G. CHIPOCO
AV. RPOGRESO- AV. UNION (DERECHA) TIP1( 2UND) 1.00 AREA 3.78 3.78
AV. BENAVIDES-AV SAN MARTIN (DERECHA) TIP1( 4UND) 1.00 AREA 7.56 7.56
AV. SAN MARTIN- BELAUNDE DERECHA TIP1( 3UND) 1.00 AREA 5.67 5.67
VERMA CENTRAL TIP1( 14UND) 1.00 AREA 26.47 26.47
AV. PROGRESO-AV. UNION (IZQUIERDA) TIP1( 1UND) 1.00 AREA 1.89 1.89
AV. BENAVIDES-AV. L G. CHIPOCO (IZQUIERDA) TIP1( 6UND) 1.00 AREA 11.35 11.35
SEGUNDA ETAPA
VEREDA
ENTRE OVALO 2 DE MAYO-JR SIMON BOLIVAR
AV. 2 DE MAYO-JR. SAN ISIDRO (DERECHA) 1.00 AREA 298.89 298.89
JR. SAN ISIDRO-JR. TUPAC AMARU (DERECHA) 1.00 AREA 103.50 103.50
JR. TUPAC AMARU-JR. SIMON BOLIVAR 1.00 AREA 764.42 764.42
OVALO 2 DE MAYO 1.00 AREA 71.23 71.23
VERMA CENTRAL 1.00 AREA 2789.24 2789.24
PROLONG. RASURI-PSJ SAN ANTONIO 1.00 AREA 1377.55 1377.55
MARTILLOS
ENTRE OVALO 2 DE MAYO-JR SIMON BOLIVAR
AV. UNION Y AV. 2 DE MAYO 1.00 AREA 46.96 46.96
AV. UNION Y JR. SAN ISIDRO 1.00 AREA 49.43 49.43
AV. UNION Y JR. TUPAC AMARU 1.00 AREA 23.09 23.09
AV. UNION Y JR. SIMON BOLIVAR 1.00 AREA 99.83 99.83
ENTRE JR. SIMON BOLIVAR-AV. LOS INCAS
AV. UNION Y JR. SIMON BOLIVAR 1.00 AREA 85.17 85.17
AV. UNION Y JR. SAN ANTONIO 1.00 AREA 53.57 53.57
AV. UNION Y LOS INCAS 1.00 AREA 96.25 96.25
ENTRE AV. LOS INCAS-AV. ALFONZO UGARTE
AV. UNION Y AV. GARCILAZO DE LA VEGA 1.00 AREA 33.38 33.38
AV. UNION Y AV. ALFONZO UGARTE 1.00 AREA 55.57 55.57
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
RAMPAS PEATONALES
ENTRE JR. SIMON BOLIVAR-AV. LOS INCAS
PSJ. SAN ANTONIO-JR. SAN ANTONIO (IZQUIERDA) 1.00 AREA 4.78 4.78
JR. SAN ANTONIO- CRUCE LOS INCAS (IZQUIERDA) 1.00 AREA 4.78 4.78
RAMPAS DISCAPASITADOS
ENTRE OVALO 2 DE MAYO-JR SIMON BOLIVAR
AV. 2 DE MAYO-JR. SAN ISIDRO (DERECHA) TIP1 (4 UND) 1.00 AREA 7.56 7.56
JR. SAN ISIDRO-JR. TUPAC AMARU (DERECHA) TIP (2UND) 1.00 AREA 3.78 3.78
JR. TUPAC AMARU-JR. SIMON BOLIVAR TIP (4UND) 1.00 AREA 7.56 7.56
VERMA CENTRAL
TIPO 1 (14 UND) 1.00 AREA 26.47 26.47
TIPO2 ( 5 UND) 1.00 AREA 18.84 18.84
PROLONG. RASURI-PSJ SAN ANTONIO TIP1 (7 UND) 1.00 AREA 13.24 13.24
TERCERA ETAPA
VEREDA
ENTRE AV. ALFONZO UGARTE-AV. MIGUEL GRAU
AV. ALFONZO UGARTE-AV. MIGUEL GRAU (DERECHA) 1.00 AREA 199.10 199.10
VERMA CENTRAL 1.00 AREA 695.14 695.14
CALLE-ALFONZO UGARTE-CALLE MIGUEL GRAU(IZQUIERDA) 1.00 AREA 225.92 225.92
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
PSJ LOS ROSALES- CRUCE AV. BOLOGNESI (IZQUIERDA) 1.00 AREA 98.89 98.89
MARTILLOS
ENTRE AV. ALFONZO UGARTE-AV. MIGUEL GRAU
AV. UNION Y AV. ALFONZO UGARTE 1.00 AREA 81.69 81.69
AV. UNION Y AV. MIGUEL GRAU 1.00 AREA 114.30 114.30
ENTRE AV. MIGUEL GRAU- AV. BOLOGNESI
AV UNION Y AV. BOLOGNESI 1.00 AREA 87.11 87.11
ENTRE AV. BOLOGNESI-AV.SUCRE
AV. UNION Y AV. SUCRE 1.00 AREA 29.59 29.59
RAMPAS DISCAPACITADOS
ENTRE AV. ALFONZO UGARTE-AV. MIGUEL GRAU
AV. ALFONZO UGARTE-AV. MIGUEL GRAU (DERECHA) TIP1( 4 UND) 1.00 AREA 7.56 7.56
VERMA CENTRAL
TIPO 1 (4 UND) 1.00 AREA 7.56 7.56
TIPO 2 (2 UND) 1.00 AREA 7.53 7.53
CALLE-ALFONZO UGARTE-CALLE MIGUEL GRAU(IZQUIERDA) TIP1 (4UND) 1.00 AREA 7.56 7.56
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
PRIMERA ETAPA
AV. BELAUNDE -AV. UNION (IZQUIERDO)) 1.00 10.52 10.52
AV. BELAUNDE -AV. UNION (IZQUIERDO)) 1.00 10.71 10.71
AV. BELAUNDE -AV. UNION (IZQUIERDO) 7.00 0.39 2.73
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
02.05 SARDINELES
02.05.01 SARDINEL PERALTADO DE CONCRETO fc´=175kg/cm2 0.15 x 0.35m M
METRADO
PROYECTO: "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DE LA AVENIDA UNION DISTRITO
DE PUEBLO NUEVO- PROVINCIA CHINCHA- DEPARTAMENTO ICA"
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
PRIMERA ETAPA
ENTRE AV. BENAVIDES - PROLONGACION RASURI
AV. RPOGRESO - AV.OSCAR R. BENAVIDES (IZQUIERDA)
1.00 29.69 29.69
1.00 20.20 20.20
1.00 11.06 11.06
1.00 10.64 10.64
1.00 12.04 12.04
AV.OSCAR R. BENAVIDES - AV.UNION (CENTRAL)
1.00 4.97 4.97
1.00 5.68 5.68
AV. SAN MARTIN - AV.UNION (AMBOS)
1.00 4.33 4.33
1.00 5.68 5.68
AV. BENAVIDES - AV. LUIS G. CHIPOCO (IZQUIERDA)
1.00 25.78 25.78
1.00 7.29 7.29
AV. BENAVIDES - AV UNION (DERECHA)
1.00 10.56 10.56
1.00 10.56 10.56
AV. 12 DE OCTUBRE- AV. UNION (DERECHA)
1.00 9.86 9.86
1.00 16.78 16.78
1.00 15.67 15.67
1.00 9.27 9.27
JR.23 DE MAYO - AV. 2 DE MAYO (DERECHA)
1.00 7.16 7.16
1.00 6.99 6.99
PASAJE S/N - PROLONGACION RASURI (IZQUIERDA)
1.00 10.23 10.23
PARQUE FRENTE A COMISARIA (CENTRAL)
1.00 18.65 18.65
1.00 16.01 16.01
1.00 12.62 12.62
1.00 13.57 13.57
SEGUNDA ETAPA
ENTRE AV. 2 DE MAYO - AV. ALFONSO UGARTE
AV. 2 DEMAYO - JR. SAN ISIDRO (DERECHA)
1.00 11.88 11.88
1.00 9.06 9.06
JR. SAN ISIDRO - JR. TUPAC AMARU (DERECHA)
1.00 6.90 6.90
JR. TUPAC AMARU - JR. SIMON BOLIVAR (DERECHA)
1.00 8.10 8.10
1.00 10.54 10.54
1.00 13.41 13.41
1.00 13.41 13.41
1.00 13.50 13.50
1.00 16.31 16.31
1.00 11.80 11.80
1.00 10.34 10.34
JR. SIMON BOLIVAR - AV- LOS INCAS (DERECHA)
1.00 13.35 13.35
1.00 13.45 13.45
PROL. RAZURI - PASAJ. SAN COSME (IZQUIERDA)
1.00 7.68 7.68
1.00 9.45 9.45
1.00 25.46 25.46
1.00 13.23 13.23
1.00 12.75 12.75
1.00 10.82 10.82
PASAJ. SAN COME - PASAJ. SAN ANTONIO (IZQUIERDA)
1.00 12.07 12.07
PASAJ. SAN ANTONIO - CALLE. ALFONSO UGARTE (IZQUIERDA)
1.00 17.93 17.93
METRADO
PROYECTO: "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DE LA AVENIDA UNION DISTRITO
DE PUEBLO NUEVO- PROVINCIA CHINCHA- DEPARTAMENTO ICA"
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
TERCERA ETAPA
ENTRE AV. ALFONZO UGARTE - AV.SUCRE
AV.MIGUEL GRAU - AV. BOLOGNESI (DERECHA)
1.00 12.34 12.34
CALLE. ALFORNSO UGARTE - AV. MIGUEL GRAU (IZQUIERDA)
1.00 14.80 14.80
1.00 15.76 15.76
PASJE ROSALES - AV.SUCRE (IZQUIERDA)
1.00 17.15 17.15
1.00 25.41 25.41
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
TERCERA ETAPA
ENTRE AV. ALFONZO UGARTE - AV.SUCRE
AV.MIGUEL GRAU - AV. BOLOGNESI (DERECHA)
1.00 12.34 0.40 4.93
CALLE. ALFORNSO UGARTE - AV. MIGUEL GRAU (IZQUIERDA)
1.00 14.80 0.40 5.92
1.00 15.76 0.40 6.30
PASJE ROSALES - AV.SUCRE (IZQUIERDA)
1.00 17.15 0.40 6.86
1.00 25.41 0.40 10.16
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
TERCERA ETAPA
ENTRE AV. ALFONZO UGARTE - AV.SUCRE
AV.MIGUEL GRAU - AV. BOLOGNESI (DERECHA)
1.00 12.34 0.40 4.93
CALLE. ALFORNSO UGARTE - AV. MIGUEL GRAU (IZQUIERDA)
1.00 14.80 0.40 5.92
1.00 15.76 0.40 6.30
PASJE ROSALES - AV.SUCRE (IZQUIERDA)
1.00 17.15 0.40 6.86
1.00 25.41 0.40 10.16
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
PRIMERA ETAPA
ENTRE AV. BENAVIDES - PROLONGACION RASURI
AV. RPOGRESO - AV.OSCAR R. BENAVIDES (IZQUIERDA)
1.00 14.98 14.98
1.00 9.96 9.96
1.00 5.57 5.57
1.00 5.23 5.23
1.00 6.67 6.67
AV. BENAVIDES - AV. LUIS G. CHIPOCO (IZQUIERDA)
1.00 0.00 0.00
1.00 0.00 0.00
AV. 12 DE OCTUBRE- JR. 23 ME MAYO (DERECHA)
1.00 3.45 3.45
1.00 5.35 5.35
1.00 5.67 5.67
1.00 2.81 2.81
JR.23 DE MAYO - AV. 2 DE MAYO (DERECHA)
1.00 2.99 2.99
1.00 2.99 2.99
ALCORQUE 10.00 2.25 22.50
PASAJE S/N - PROLONGACION RASURI (IZQUIERDA)
1.00 0.00 0.00
PARQUE FRENTE A COMISARIA (CENTRAL)
1.00 10.83 10.83
1.00 8.86 8.86
1.00 6.62 6.62
1.00 8.44 8.44
ALCORQUE 5.00 2.25 11.25
BERMA CENTRAL(PLANTAS DE BAMBU) 0.00 0.87 0.00
PLANTAS DE CEREZO 4.00 2.25 9.00
BERMA CENTRAL 6.00 2.25 13.50
BERMA CENTRAL(PLANTAS DE BAMBU) 0.00 0.87 0.00
SEGUNDA ETAPA
ENTRE AV. 2 DE MAYO - AV. ALFONSO UGARTE
BERMA CENTRAL 2 DE MAYO 2.00 2.25 4.50
BERMA CENTRAL 1 9.00 2.25 20.25
21.00 2.25 47.25
CERMA CENTRAL 2 6.00 2.25 13.50
BERMA CENTRAL 3 4.00 2.25 9.00
BERMA CENTRAL 4 4.00 2.25 9.00
2.00 0.87 1.74
AV. 2 DEMAYO - JR. SAN ISIDRO (DERECHA)
1.00 10.53 10.53
1.00 5.27 5.27
JR. SAN ISIDRO - JR. TUPAC AMARU (DERECHA) 0.00
2.00 2.79 5.58
JR. TUPAC AMARU - JR. SIMON BOLIVAR (DERECHA)
1.00 3.05 3.05
1.00 4.87 4.87
2.00 6.63 13.25
ALCORQUE 3.00 2.25 6.75
1.00 9.74 9.74
1.00 6.07 6.07
1.00 0.00 0.00
1.00 0.00 0.00
1.00 3.89 3.89
JR. SIMON BOLIVAR - AV- LOS INCAS (DERECHA)
METRADO
PROYECTO: "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DE LA AVENIDA UNION DISTRITO
DE PUEBLO NUEVO- PROVINCIA CHINCHA- DEPARTAMENTO ICA"
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
SEGUNDA ETAPA
ENTRE AV. 2 DE MAYO - AV. ALFONSO UGARTE
BERMA CENTRAL 2 DE MAYO 2.00 2.25 4.50
BERMA CENTRAL 1 8.00 2.25 18.00
25.00 2.25 56.25
CERMA CENTRAL 2 14.00 2.25 31.50
BERMA CENTRAL 3 5.00 2.25 11.25
BERMA CENTRAL 4 5.00 2.25 11.25
AV. 2 DEMAYO - JR. SAN ISIDRO (DERECHA)
1.00 5.64 5.64
1.00 3.52 3.52
JR. SAN ISIDRO - JR. TUPAC AMARU (DERECHA) 0.00
1.00 2.23 2.23
JR. TUPAC AMARU - JR. SIMON BOLIVAR (DERECHA)
1.00 2.80 2.80
1.00 4.40 4.40
1.00 6.08 6.08
ALCORQUE 3.00 2.25 6.75
1.00 6.08 6.08
1.00 6.31 6.31
1.00 11.43 11.43
1.00 6.84 6.84
1.00 4.90 4.90
JR. SIMON BOLIVAR - AV- LOS INCAS (DERECHA)
1.00 8.43 8.43
1.00 8.54 8.54
PROL. RAZURI - PASAJ. SAN COSME (IZQUIERDA)
1.00 2.67 2.67
1.00 4.20 4.20
1.00 21.02 21.02
1.00 8.44 8.44
1.00 7.50 7.50
1.00 5.59 5.59
PASAJ. SAN COME - PASAJ. SAN ANTONIO (IZQUIERDA)
1.00 6.46 6.46
PASAJ. SAN ANTONIO - CALLE. ALFONSO UGARTE (IZQUIERDA)
1.00 3.25 3.25
1.00 10.08 10.08
TERCERA ETAPA
ENTRE AV. ALFONZO UGARTE - AV.SUCRE
BERMA CENTRAL1 11.00 2.25 24.75
BERMA CENTRAL 2 3.00 2.25 6.75
BERMA CENTRAL 3 1.00 2.25 2.25
AV.MIGUEL GRAU - AV. BOLOGNESI (DERECHA)
1.00 6.78 6.78
METRADO
PROYECTO: "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DE LA AVENIDA UNION DISTRITO
DE PUEBLO NUEVO- PROVINCIA CHINCHA- DEPARTAMENTO ICA"
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
CRUCE AV. LOS INCAS - CRUCE AV. GARCILAZO DE LA VEGA(CENTRO BULEVAR) 5.00 5.00
CRUCE AV. MIGUEL GRAU-CRUCE PASAJE LOS ROSALES (CENTRO BULEVAR) 5.00 5.00
PRIMERA ETAPA
AV. BELAUNDE-AV. LUIS GALVEZ CHIPOCO (CENTRO) 5.00 AREA 2.25 11.25
PARQUE FRENTE A COMISARIA 5.00 AREA 2.25 11.25
JIRON 23 DE MAYO -AV UNION(DERECHA) 10.00 AREA 2.25 22.50
BERMA CENTRAL 10.00 AREA 2.25 22.50
SEGUNDA ETAPA
AV. DOS DE MAYO(IZQUIERDO) 2.00 AREA 2.25 4.50
PROLG. RAZURI-CRUCE JIRON SAN ISIDRO (CENTRO) 8.00 AREA 2.25 18.00
CRUCE JIRON SAN ISIDRO-CRUCE JIRON SIMON BOLIVAR(DERECHO) 3.00 AREA 2.25 6.75
CRUCE JIRON SAN ISIDRO-CRUCE JIRON SIMON BOLIVAR(CENTRO BULEVAR) 25.00 AREA 2.25 56.25
CRUCE JIRON SIMON BOLIVAR-CRUCE AV. LOS INCAS(CENTRO BULEVAR) 14.00 AREA 2.25 31.50
CRUCE AV. LOS INCAS - CRUCE AV. GARCILAZO DE LA VEGA(CENTRO BULEVAR) 5.00 2.25 11.25
AREA
CRUCE AV. GARCILAZO DE LA VEGA- CRUCE AV. ALFONSO UGARTE(CENTRO
5.00 2.25 11.25
BULEVAR) AREA
TERCERA ETAPA
CRUCE AV. ALFONSO UGARTE-CRUCE MIGUEL GRAU (CENTRO BULEVAR) 11.00 AREA 2.25 24.75
CRUCE AV. MIGUEL GRAU-CRUCE PASAJE LOS ROSALES (CENTRO BULEVAR) 4.00 2.25 9.00
AREA
METRADO
PROYECTO: "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DE LA AVENIDA UNION DISTRITO
DE PUEBLO NUEVO- PROVINCIA CHINCHA- DEPARTAMENTO ICA"
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
PRIMERA ETAPA
AV. BENAVIDES-AV. UNION (IZQUIERDA) 2.00 2.00
AV. FAUSTINO SANCHEZ CARRION - PROLG RAZURI(CENTRO BULEVAR) 4.00 4.00
CALLE. ALFORNSO UGARTE - AV. MIGUEL GRAU (IZQUIERDA) 1.00 AREA 10.58 10.58
1.00 AREA 11.76 11.76
METRADO
PROYECTO: "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DE LA AVENIDA UNION DISTRITO
DE PUEBLO NUEVO- PROVINCIA CHINCHA- DEPARTAMENTO ICA"
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
02.07 SEÑALIZACION
02.07.01 SEÑALES PREVENTIVAS UND
PRIMERA ETAPA
AV. PROGRESO- AV. BENAVIDES(DERECHA) 1.00 1.00
AV. BENAVIDES-AV. SAN MARTIN(DERECHA) 1.00 1.00
AV. SAN MARTIN- AV. BELAUNDE(DERECHA) 1.00 1.00
AV. BELAUNDE -AV. 12 DE OCTUBRE(DERECHA) 1.00 1.00
AV. 12 DE OCTUBRE- COMISARIA(DERECHA) 1.00 1.00
AV.M PROGRESO-AV. BENAVIDES(IZQUIERDA) 1.00 1.00
AV. BENAVIDES- AV. LUIS GALVEZ CHIPOCO(IZQUIERDA) 2.00 2.00
AV. LUIS GALVEZ CHIPOCO-PROLG RAZURI(IZQUIERDA) 5.00 5.00
JIRON 23 DE MAYO - AV. 2 DE MAYO(DERECHA) 4.00 4.00
JIRON 23 DE MAYO-AV. UNION(IZQUIERDA) 3.00 3.00
SEGUNDA ETAPA
AV. 2 DE MAYO SAN ISIDRO(DERECHA) 2.00 2.00
JIRON TUPAC AMARU - JIRON SIMON BOLIVAR(DERECHA) 3.00 3.00
AV. SIMON BOLVAR-AV. LOS INCAS(DERECHA) 1.00 1.00
AV. LOS INCAS-AV. GARCILAZO DE LA VEGA(DERECHA) 1.00 1.00
AV. GARCILAZO DE LA VEGA - AV. ALFONSO UGARTE(DERECHA) 1.00 1.00
PROLG RAZURI- JPSJ SAN COSME (IZQUIERDA) 4.00 4.00
PSJ SAN ANTONIO - CALLE ALFONSO UGARTE(IZQUIERDA) 2.00 2.00
TERCERA ETAPA
AV. ALFONOS UGARTE- AV. GRAU(DERECHA) 1.00 1.00
AV. GRAU- AV. BOLOGNESI(DERECHA) 1.00 1.00
AV. BOLOGNESI - AV. SUCRE(DERECHA) 1.00 1.00
CALLE ALFONOS UGARTE- CALLE GRAU(IZQUIERDA) 1.00 1.00
CALLE GRAU- PSJ LOS ROSALES (IZQUIERDA) 2.00 2.00
PSJ LOS ROSALES - AV.SUCRE(IZQUIERDA) 2.00 2.00
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
PRIMERA ETAPA
JIRON 23 DE MAYO -AV. UNION(DERECHA) 1.00 AREA 18.00 18.00
AV. FAUSTINO SANCHEZ CARRION- PROLG RAZURI(CENTRO PARQUE) 1.00 2.37 2.37
AREA
1.00 AREA 0.78 0.78
SEGUNDA ETAPA
JIRON TUPAC AMARU- JIRON SIMON BOLIVAR(DERECHA) 1.00 AREA 18.00 18.00
CRUCE DE JIRON TUPAC AMARU-PSJ SAN ANTONIO(IZQUIERDA) 1.00 AREA 18.00 18.00
TERCERA ETAPA
CALLE MIGUEL GRAU-AV. BOLOGNESI(IZQUIERDA) 1.00 AREA 18.00 18.00
1.00 AREA 2.13 2.13
1.00 AREA 4.92 4.92
02.07.06 PINTURA DE SARDINELES Y UÑAS DE VEREDAS, PINTURA DE TRAFICO AMARILL M2
PRIMERA ETAPA
ENTRE AV. BENAVIDES - AV. 2 DE MAYO Y RAZURI
AV. PROGRESO - AV.OSCAR R. BENAVIDES (DERECHA) 1.00 51.57 0.30 15.47
AV. BENAVIDES - AV SAN MARTIN (DERECHA) 1.00 46.44 0.30 13.93
AV. SAN MARTIN - AV.ANDRES BELAUNDE(DERECHA) 1.00 112.85 0.30 33.86
AV. BELAUNDE-AV 12 DE OCTUBRE (DERECHA) 1.00 154.23 0.30 46.27
AV. 12 DE OCTUBRE-JR. 23 DE MAYO (DERECHA) 1.00 122.47 0.30 36.74
AV. 12 DE OCTUBRE- AV. 2 DE MAYO (DERECHA) 1.00 263.95 0.30 79.19
AV. RPOGRESO - AV.OSCAR R. BENAVIDES (IZQUIERDA) 1.00 49.54 0.30 14.86
AV. BENAVIDES - AV. LUIS G. CHIPOCO (IZQUIERDA) 1.00 131.66 0.30 39.50
AV. L.G. CHIPOCO-AV. FAUSTINO SANCHEZ(IZQUIERDA) 1.00 144.97 0.30 43.49
AV. 12 DE OCTUBRE- AV. UNION (IZQUIERDA) 1.00 95.78 0.30 28.73
AV. FAUSTINO SANCHEZ-PROL.RAZURI (IZQUIERDA) 1.00 191.20 0.30 57.36
METRADO
PROYECTO: "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DE LA AVENIDA UNION DISTRITO
DE PUEBLO NUEVO- PROVINCIA CHINCHA- DEPARTAMENTO ICA"
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
VEREDAS CENTRAL
BULEVAR 1 1.00 63.41 0.30 19.02
BULEVAR 2 1.00 237.06 0.30 71.12
VEREDA CENTRAL 1.00 301.67 0.30 90.50
VEREDA CENTRAL 1.00 12.78 0.30 3.83
VEREDA CENTRAL 1.00 153.00 0.30 45.90
VEREDA CENTRAL 1.00 153.00 0.30 45.90
1.00 9.08 0.30 2.72
1.00 120.00 0.30 36.00
COMISARIA PARQUE 1.00 119.44 0.30 35.83
VEREDA JIRON 23 DE MAYO CENTRO 1.00 14.70 0.30 4.41
1.00 171.65 0.30 51.50
1.00 110.84 0.30 33.25
OVALO 1.00 44.96 0.30 13.49
PARQUE 1.00 151.09 0.30 45.33
SEGUNDA ETAPA
OVALO DOS DE MAYO 1.00 33.13 0.30 9.94
PARUE DOS AV. DOS DE MAYO 1.00 56.92 0.30 17.08
AV. DOS DE MAYO - JIRON SAN ISISRO(DERECHO) 1.00 116.09 0.30 34.83
JIRON SAN ISIDRO-JIRON TUPACA AMARU(DERECHO) 1.00 65.51 0.30 19.65
JIRON TUPAC AMARU- JRN SIMON BOLIBAR(DERECHO) 1.00 240.96 0.30 72.29
JIRON SIMON BOLIVAR- AV. LOS INCAS(DERECHA) 1.00 87.55 0.30 26.27
AV. LOS INCAS- A.V. INCA GARCILAZO DE LA VEGA(DERTECHA]) 1.00 72.28 0.30 21.68
AV. GARCILAZO- AV. ALFONSO UGARTE(DERECHA) 1.00 81.58 0.30 24.47
PROLG RAZURI-PSJ SAN ANTONIO(IZQUIERDA) 1.00 318.03 0.30 95.41
PSJ SAN ANTONIO JIRON SAN ANTONIO(IZQUIERDA) 1.00 69.90 0.30 20.97
JIRON SAN ANTONIO-CALLE ALFONSO UGARTE(IZQUYIERDA) 1.00 152.23 0.30 45.67
PARQUE CENTRALES
PARQUE 1 1.00 35.58 0.30 10.67
PARQUE2 1.00 177.38 0.30 53.21
PARQUE 3 1.00 546.91 0.30 164.07
PARQUE4 1.00 163.69 0.30 49.11
PARQUE 5 1.00 113.84 0.30 34.15
PARQUE 6 1.00 137.61 0.30 41.28
TERCERA ETAPA
CALLE ALFONSO UGARTE - CALLE GRAU(IZQUIERDA) 1.00 75.91 0.30 22.77
CALLE GRAU -PSJ LOS ROSALES(IZQUIERDA) 1.00 85.85 0.30 25.76
PSJ LOS ROSALES-AV.SUCRE(IZQUIERA) 1.00 250.53 0.30 75.16
AV. ALFONSO UGARTE- AV. GRAU(DERECHA) 1.00 47.44 0.30 14.23
AV. MIGUEL GRAU- AV. BOLOGNESI(DERECHA) 1.00 76.13 0.30 22.84
AV. BOLOGNESI- AV. SUCRE(DERECHA) 1.00 78.16 0.30 23.45
BOCACALLE AV. SUCRE(DERECHA) 1.00 11.34 0.30 3.40
PARQUE CENTRAL 1 1.00 159.59 0.30 47.88
PARQUE CENTRAL2 1.00 100.89 0.30 30.27
PARQUE TRES 1.00 54.03 0.30 16.21
VEREDA CENTRAL 1 1.00 45.38 0.30 13.61
VEREDA 2 1.00 122.50 0.30 36.75
VEREDA 3 1.00 11.47 0.30 3.44
02.07.07 SUMINISTRO Y COLOCACION DE TACHAS REFLECTIVAS (10.16X10.16X1.67CM) UND
PRIMERA ETAPA
JR. 23 DE MAYO-AV. 2 DE MAYO (DERECHA) 24.00 24.00
SEGUNDA ETAPA
JR. TUPAC AMARU-JR ALFONZO UGARTE (DERECHA) 24.00 24.00
PROLG. RASURI- PSJ SAN ANTONIO (IZQUIERDA) 24.00 24.00
TERCERA ETAPA
AV. MIGUEL GRAU- AV. BOLOGNESI (DERECHA) 48.00 48.00
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
02.08.03.04 ASTAS DE BANDERAS SECCION VARIABLE F°G° D=5"-2" SEGÚN DISEÑO Und
ASTA EN PARQUE JR. 23 DE MAYO 3.00 3.00
ASTA EN OVALO 2 DE MAYO 3.00 3.00
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
MURO DE CONCRETO ARMADO F'C=175 kg/cm2 1.00 5.81 Area= 0.33 1.92
LOSA DE CONCRETO ARMADO F´c=175 kg/cm2 1.00 AREA= 10.41 0.15 1.56
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
PRIMERA ETAPA
3.00 3.00
SEGUNDA ETAPA
3.00 3.00
TERCERA ETAPA
3.00 3.00
PRIMERA ETAPA
AV. BENAVIDES 24.44 24.44
ENTRE AV. BENAVIDES - AV. L.G. CHIPOCO 203.06 203.06
ENTRE AV. L.G. CHIPOCO - FAUSTINO SANCHEZ 181.56 181.56
ENTRE FAUSTINO SANCHES - PROLONG. RAZURI 231.34 231.34
ETAPA 2
AV. 2 DE MAYO 19.84 19.84
ENTRE AV. 2 DE MAYO - JR. SIMON BOLIVAR 392.25 392.25
ENTRE JR. SIMON BOLIVAR - AV. ALFONSO UGARTE 250.90 250.90
TERCERA ETAPA
ENTRE AV. ALFONSO UGARTE - CALLE BOLOGNESI 131.80 131.80
CALLE BOLOGNESI B.C. IZQUIERDA 54.94 54.94
PRIMERA ETAPA
ENTRE BENAVIDES Y AV. PROGRESO 50.94 50.94
AV, BENAVIDES B,C, IZQUIERDA 12.09 12.09
03.01.02.05 RETIRO DE RED TRONCAL AGUA EN MAL ESTADO (TUB. PVC U.R. Ø 10" ).
ETAPA 2
AV. 2 DE MAYO 10.54 10.54
ENTRE AV. 2 DE MAYO - JR. SIMON BOLIVAR 391.58 391.58
ENTRE JR. SIMON BOLIVAR - AV. ALFONSO UGARTE 250.66 250.66
TERCERA ETAPA 0.00
ENTRE AV. ALFONSO UGARTE - CALLE BOLOGNESI 114.38 114.38
CALLE BOLOGNESI B.C. IZQUIERDA 63.19 63.19
03.01.02.06 RETIRO DE RED TRONCAL AGUA EN MAL ESTADO (TUB. ASB. CEMENTO, Ø 12" ). M
PRIMERA ETAPA
AV. BENAVIDES 16.44 16.44
ENTRE AV. BENAVIDES - AV. L.G. CHIPOCO 197.66 197.66
ENTRE AV. L.G. CHIPOCO - FAUSTINO SANCHEZ 181.44 181.44
ENTRE FAUSTINO SANCHES - PROLONG. RAZURI 227.79 227.79
SEGUNDA ETAPA 0.00
AV. 2 DE MAYO 10.82 10.82
03.01.02.07 RETIRO DE RED TRONCAL AGUA EN MAL ESTADO (TUB. ASB. CEMENTO, Ø 20" ). M
PRIMERA ETAPA
ENTRE AV. BENAVIDES - AV. PROGRESO 50.94 50.94
AV, BENAVIDES B,C, IZQUIERDA 12.09 12.09
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
PRIMERA ETAPA
AV. BENAVIDES 24.44 24.44
ENTRE AV. BENAVIDES - AV. L.G. CHIPOCO 203.06 203.06
ENTRE AV. L.G. CHIPOCO - FAUSTINO SANCHEZ 181.56 181.56
ENTRE FAUSTINO SANCHES - PROLONG. RAZURI 231.34 231.34
ETAPA 2
AV. 2 DE MAYO 19.84 19.84
ENTRE AV. 2 DE MAYO - JR. SIMON BOLIVAR 392.25 392.25
ENTRE JR. SIMON BOLIVAR - AV. ALFONSO UGARTE 250.90 250.90
TERCERA ETAPA
ENTRE AV. ALFONSO UGARTE - CALLE BOLOGNESI 131.80 131.80
CALLE BOLOGNESI B.C. IZQUIERDA 54.94 54.94
PRIMERA ETAPA
ENTRE AV. BENAVIDES - AV. PROGRESO 50.94 50.94
AV, BENAVIDES B,C, IZQUIERDA 12.09 12.09
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
03.01.03.04 SUMINISTRO E INSTALACION DE CODO PVC UF ISO 1452 315MM x 45° UND
SEGUNDA ETAPA
ENTRE AV. 2 DE MAYO 2.00 2.00
TERCERA ETAPA
ENTRE AV. MIGUEL GRAU - AV. BOLOGNESI 1.00 1.00
METRADO
PROYECTO: "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DE LA AVENIDA UNION DISTRITO
DE PUEBLO NUEVO- PROVINCIA CHINCHA- DEPARTAMENTO ICA"
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
03.01.03.05 SUMINISTRO E INSTALACION DE CODO PVC UF ISO 1452 315MM x 22.5° UND
PRIMERA ETAPA
ENTRE AV. L.G. CHIPOCO - AV. ANDRES BELAUNDE 2.00 2.00
TERCERA ETAPA
ENTRE CALLE BOLOGNESI 1.00 1.00
PRIMERA ETAPA
ENTRE AV. BENAVIDES 1.00 1.00
ENTRE AV L.G. CHIPOCO - AV. ANDRES BELAUNDE 1.00 1.00
PROLONG. RAZURI 1.00 1.00
ETAPA 2 0.00
ENTRE AV. 2 DE MAYO 1.00 1.00
ENTRE AV. SAN ISIDRO 1.00 1.00
ENTRE JR. TUPAC AMARU 1.00 1.00
ENTRE AV. SIMON BOLIVAR (PRL) 2.00 2.00
ENTRE AV. ALFONSO UGARTE 1.00 1.00
TERCERA ETAPA 0.00
ENTRE AV. BOLOGNESI 2.00 2.00
ENTRE CALLE BOLOGNESI 1.00 1.00
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
ENTRE JR. SIMON BOLIVAR - AV. LOS INCAS B.C. DERECHA 4.00 4.00
ENTRE AV. LOS INCAS - AV. GARCILAZO DE LA VEGA 2.00 2.00
ENTRE AV. GARCILAZO DE LA VEGA - AV. ALFONSO UGARTE B.C. DERECHA 1.00 1.00
ENTRE AV. SIMON BOLIVAR - AV. ALFONSO UGARTE B.C. IZQUIERDA 3.00 3.00
TERCERA ETAPA
ENTRE AV. ALFONSO UGARTE - CALLE MIGUEL GRAU 1.00 1.00
ENTRE CALLE MIGUEL GRAU - CALLE BOLOGNESI 3.00 3.00
ENTRE AV. MIGUEL GRAU - AV. BOLOGNESI 1.00 1.00
ENTRE AV. BOLOGNESI - AV. SUCRE 2.00 2.00
04 INFRAESTRUCTURA ELECTRICA
04.01 REUBICACION DE POSTES MEDIA Y BAJA TENSION ( ELECTRODUNAS)
04.01.01 REUBICACION DE POSTES MEDIA Y BAJA TENSION ( ELECTRODUNAS) GLB
1.00 1.00
04.02 BAJA TENSION
04.02.01 REUBICACION DE MEDIDORES DOMICILIARIOS DE LUZ UND
PRIMERA ETAPA
ENTRE AV. BENAVIDES-AV L.G. CHIPOCO
AV. BENAVIDES-AV. L G. CHIPOCO (IZQUIERDA) 1.00 1.00
TERCERA ETAPA
ENTRE AV. ALFONZO UGARTE-AV. MIGUEL GRAU
CALLE-ALFONZO UGARTE-CALLE MIGUEL GRAU(IZQUIERDA) 1.00 1.00
SEGUNDA ETAPA
ENTRE OVALO 2 DE MAYO-JR SIMON BOLIVAR
OVALO 2 DE MAYO 1.00 AREA 1.00 1.00
VERMA CENTRAL 25.00 AREA 1.00 25.00
TERCERA ETAPA
ENTRE AV. ALFONZO UGARTE-AV. MIGUEL GRAU
VERMA CENTRAL 3.00 AREA 1.00 3.00
SEGUNDA ETAPA
ENTRE OVALO 2 DE MAYO-JR SIMON BOLIVAR
OVALO 2 DE MAYO 1.00 VOLUMEN 1.20 1.20
LATERAL 25.00 VOLUMEN 1.20 30.00
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
TERCERA ETAPA
ENTRE AV. ALFONZO UGARTE-AV. MIGUEL GRAU
VERMA CENTRAL 3.00 VOLUMEN 1.20 3.60
SEGUNDA ETAPA
ENTRE OVALO 2 DE MAYO-JR SIMON BOLIVAR
OVALO 2 DE MAYO 1.00 1.00
LATERAL 25.00 25.00
TERCERA ETAPA
ENTRE AV. ALFONZO UGARTE-AV. MIGUEL GRAU
VERMA CENTRAL 3.00 3.00
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
PRIMERA ETAPA
INTERSECCION DE AV. UNION CON AV. O.R. BENAVIDES 3.00 1.00 3.00
INTERSECCION DE AV. UNION CON AV. V.A. BELAUNDE 2.00 1.00 2.00
SEGUNDA ETAPA
INTERSECCION AV. UNION CON AV. 2 DE MAYO 4.00 1.00 4.00
TERCERA ETAPA
INTERSECCION AV UNION CON CALLE ALFONZO UGARTE 3.00 1.00 3.00
PRIMERA ETAPA
INTERSECCION DE AV. UNION CON AV. O.R. BENAVIDES 3.00 1.00 3.00
INTERSECCION DE AV. UNION CON AV. V.A. BELAUNDE 2.00 1.00 2.00
INTERSECCION DE AV. UNION CON JR 23 DE MAYO 3.00 1.00 3.00
SEGUNDA ETAPA
INTERSECCION AV. UNION CON AV. 2 DE MAYO 3.00 1.00 3.00
TERCERA ETAPA
INTERSECCION AV UNION CON CALLE ALFONZO UGARTE 2.00 1.00 2.00
04.04.01.07 MURETE DE CONCRETO ARDAMO UND
PRIMERA ETAPA
INTERSECCION DE AV. UNION CON AV. O.R. BENAVIDES 1.00 1.00
INTERSECCION DE AV. UNION CON AV. V.A. BELAUNDE 1.00 1.00
INTERSECCION DE AV. UNION CON JR 23 DE MAYO 1.00 1.00
SEGUNDA ETAPA
INTERSECCION AV. UNION CON AV. 2 DE MAYO 1.00 1.00
TERCERA ETAPA
INTERSECCION AV UNION CON CALLE ALFONZO UGARTE 1.00 1.00
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
PRIMERA ETAPA
INTERSECCION DE AV. UNION CON AV. O.R. BENAVIDES 4.00 4.00
INTERSECCION DE AV. UNION CON AV. V.A. BELAUNDE 4.00 4.00
INTERSECCION DE AV. UNION CON JR 23 DE MAYO 3.00 3.00
SEGUNDA ETAPA
INTERSECCION AV. UNION CON AV. 2 DE MAYO 4.00 4.00
TERCERA ETAPA
INTERSECCION AV UNION CON CALLE ALFONZO UGARTE 4.00 4.00
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
INTERSECCION DE AV. UNION CON AV. O.R. BENAVIDES 1.00 63.91 0.60 0.40 15.34
INTERSECCION DE AV. UNION CON AV. V.A. BELAUNDE 1.00 65.49 0.60 0.40 15.72
INTERSECCION DE AV. UNION CON JR 23 DE MAYO 1.00 47.29 0.60 0.40 11.35
SEGUNDA ETAPA
INTERSECCION AV. UNION CON AV. 2 DE MAYO 1.00 76.56 0.60 0.40 18.37
TERCERA ETAPA
INTERSECCION AV UNION CON CALLE ALFONZO UGARTE 1.00 52.91 0.60 0.40 12.70
04.04.06.05 CAJAS DE PASO DE CONCRETO F´=175KG/CM2 UND
PRIMERA ETAPA
INTERSECCION DE AV. UNION CON AV. O.R. BENAVIDES 6.00 6.00
INTERSECCION DE AV. UNION CON AV. V.A. BELAUNDE 4.00 4.00
INTERSECCION DE AV. UNION CON JR 23 DE MAYO 3.00 3.00
SEGUNDA ETAPA
INTERSECCION AV. UNION CON AV. 2 DE MAYO 7.00 7.00
TERCERA ETAPA
INTERSECCION AV UNION CON CALLE ALFONZO UGARTE 5.00 5.00
PRIMERA ETAPA
INTERSECCION DE AV. UNION CON AV. O.R. BENAVIDES 1.00 1.00
INTERSECCION DE AV. UNION CON AV. V.A. BELAUNDE 1.00 1.00
INTERSECCION DE AV. UNION CON JR 23 DE MAYO 1.00 1.00
SEGUNDA ETAPA
INTERSECCION AV. UNION CON AV. 2 DE MAYO 1.00 1.00
TERCERA ETAPA
INTERSECCION AV UNION CON CALLE ALFONZO UGARTE 1.00 1.00
05 IMPACTO AMBIENTAL
05.01 PLAN DE PARTICIPACION CIUDADANA
05.01.01 TALLER PARTICIPATIVO TALLER 5.00 5.00
MEDIDAS RESULTADO
ITEM DENOMINACION Y/O DESCRIPCION UND CANT.
Long (m) Ancho (m) Altura (m) PARCIAL
TOTAL
10.00
10.00
2.00
10.00
47456.95
RESULTADO
TOTAL
RESULTADO
TOTAL
RESULTADO
TOTAL
RESULTADO
TOTAL
RESULTADO
TOTAL
1194.44
RESULTADO
TOTAL
436.94
2690.82
592.86
RESULTADO
TOTAL
57.83
126.88
154.29
830.57
1436.92
16.94
39.52
2657.51
RESULTADO
TOTAL
170.00
7.00
4.00
78.00
39.00
RESULTADO
TOTAL
60.00
2.00
12.00
3.00
29.17
606.02
446.54
RESULTADO
TOTAL
635.57
218.44
27.35
2.00
1.00
1.00
1.00
1.00
200.34
RESULTADO
TOTAL
200.34
44.66
165.62
RESULTADO
TOTAL
15309.96
5890.16
44.69
31.63
RESULTADO
TOTAL
39.72
0.85
5.19
50.87
9.00
RESULTADO
TOTAL
297.00
282.00
RESULTADO
TOTAL
1853.50
1853.50
1.00
47456.95
RESULTADO
TOTAL
RESULTADO
TOTAL
RESULTADO
TOTAL
RESULTADO
TOTAL
RESULTADO
TOTAL
RESULTADO
TOTAL
47456.95
RESULTADO
TOTAL
RESULTADO
TOTAL
RESULTADO
TOTAL
RESULTADO
TOTAL
RESULTADO
TOTAL
1.00
1.00
RESULTADO
TOTAL
1.00
1.00
1.00
19,854.82
7,596.98
-
668.86
27.50
9.60
13.36
25.00
14.06
1,116.00
19,190.68
27,803.18
RESULTADO
TOTAL
24,435.89
27803.18
27803.18
RESULTADO
TOTAL
27803.18
RESULTADO
TOTAL
18835.94
RESULTADO
TOTAL
RESULTADO
TOTAL
354.74
RESULTADO
TOTAL
17144.86
RESULTADO
TOTAL
1000.62
1334.07
RESULTADO
TOTAL
64.51
8505.02
RESULTADO
TOTAL
RESULTADO
TOTAL
76.08
7.19
1509.40
RESULTADO
TOTAL
278.66
56.40
RESULTADO
TOTAL
26.29
2.63
330.73
RESULTADO
TOTAL
62.25
RESULTADO
TOTAL
8034.31
RESULTADO
TOTAL
20217.81
RESULTADO
TOTAL
RESULTADO
TOTAL
RESULTADO
TOTAL
2199.06
RESULTADO
TOTAL
42.00
25.05
25.05
RESULTADO
TOTAL
25.05
25.05
25.05
25.05
23.96
17.22
27803.18
27803.18
RESULTADO
TOTAL
27803.18
668.80
RESULTADO
TOTAL
RESULTADO
TOTAL
259.09
RESULTADO
TOTAL
1268.61
259.09
RESULTADO
TOTAL
41.40
RESULTADO
TOTAL
275.39
RESULTADO
TOTAL
RESULTADO
TOTAL
462.97
RESULTADO
TOTAL
82.46
RESULTADO
TOTAL
580.84
RESULTADO
TOTAL
RESULTADO
TOTAL
102.00
52.00
6.00
240.75
RESULTADO
TOTAL
6.00
332.62
RESULTADO
TOTAL
42.00
61.00
44.00
RESULTADO
TOTAL
1502.37
RESULTADO
TOTAL
RESULTADO
TOTAL
82.20
1984.73
RESULTADO
TOTAL
120.00
30.00
140.00
RESULTADO
TOTAL
0.74
6.48
6.65
36.49
RESULTADO
TOTAL
108.00
34.00
RESULTADO
TOTAL
11.99
14.84
521.93
6.00
3.99
RESULTADO
TOTAL
29.51
94.04
20.01
1.00
2.00
2.00
297.00
RESULTADO
TOTAL
74
1553.16
9.00
RESULTADO
TOTAL
1490.13
63.03
830.35
634.15
63.03
1490.13
63.03
1490.13
RESULTADO
TOTAL
63.03
1490.13
63.03
1490.13
63.03
1159.49
RESULTADO
TOTAL
1159.49
1490.13
63.03
1553.16
1.00
1.00
2.00
3.00
RESULTADO
TOTAL
3.00
1.00
4.00
1.00
1.00
12.00
282.00
RESULTADO
TOTAL
71
46.00
RESULTADO
TOTAL
1.00
2.00
78.00
93.60
RESULTADO
TOTAL
78.00
78.00
1.00
78.00
RESULTADO
TOTAL
1.00
27.56
33.49
21.62
627.30
RESULTADO
TOTAL
12.00
13.00
5.00
13.00
12.00
18.00
10.00
2.00
8.00
RESULTADO
TOTAL
22.00
19.00
4.00
1.00
18.00
306.16
306.16
306.16
73.48
RESULTADO
TOTAL
25.00
306.16
5.00
5.00
5.00
5.00
5.00
20.00
RESULTADO
TOTAL
2.00
2.00
2.00
1.00
1.00
10.00
1.00
10.00
200.00
10.00
10.00
10.00
1.00
10.00
10.00
12.00
1.00
CUADRO DE METRADOS DE ACERO
PROYECTO: "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DE LA AVENIDA UNION DISTRITO DE PUEBLO NUEVO-
PROVINCIA CHINCHA- DEPARTAMENTO ICA"
METRADO: ESTRUCTURAS
Ø DE N° DE LONGITUD DE
ITEM DESCRIPCION UNIDAD N° DE VARILLA COD X KG PARCIAL TOTAL
VARILLA VECES VARILLA
1268.61
02.05.03 ACERO CORRUGADO fy=4200kg/cm2 GRADO 60 29.7 0.3 99
SARDINEL 50.28
AV. PROGRESO Y BENAVIDES(IZQUIERDA) 3/8" 1 100 0.50 0.56 28.00
1/4" 1 3 29.70 0.25 22.28
PROYECTO: "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DE LA AVENIDA UNION DISTRITO DE PUEBLO NUEVO-
PROVINCIA CHINCHA- DEPARTAMENTO ICA"
METRADO: ESTRUCTURAS
Ø DE N° DE LONGITUD DE
ITEM DESCRIPCION UNIDAD N° DE VARILLA COD X KG PARCIAL TOTAL
VARILLA VECES VARILLA
PROYECTO: "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DE LA AVENIDA UNION DISTRITO DE PUEBLO NUEVO-
PROVINCIA CHINCHA- DEPARTAMENTO ICA"
METRADO: ESTRUCTURAS
Ø DE N° DE LONGITUD DE
ITEM DESCRIPCION UNIDAD N° DE VARILLA COD X KG PARCIAL TOTAL
VARILLA VECES VARILLA
PROYECTO: "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DE LA AVENIDA UNION DISTRITO DE PUEBLO NUEVO-
PROVINCIA CHINCHA- DEPARTAMENTO ICA"
METRADO: ESTRUCTURAS
Ø DE N° DE LONGITUD DE
ITEM DESCRIPCION UNIDAD N° DE VARILLA COD X KG PARCIAL TOTAL
VARILLA VECES VARILLA
PROYECTO: "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DE LA AVENIDA UNION DISTRITO DE PUEBLO NUEVO-
PROVINCIA CHINCHA- DEPARTAMENTO ICA"
METRADO: ESTRUCTURAS
Ø DE N° DE LONGITUD DE
ITEM DESCRIPCION UNIDAD N° DE VARILLA COD X KG PARCIAL TOTAL
VARILLA VECES VARILLA
PROYECTO: "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DE LA AVENIDA UNION DISTRITO DE PUEBLO NUEVO-
PROVINCIA CHINCHA- DEPARTAMENTO ICA"
METRADO: ESTRUCTURAS
Ø DE N° DE LONGITUD DE
ITEM DESCRIPCION UNIDAD N° DE VARILLA COD X KG PARCIAL TOTAL
VARILLA VECES VARILLA
PROYECTO: "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DE LA AVENIDA UNION DISTRITO DE PUEBLO NUEVO-
PROVINCIA CHINCHA- DEPARTAMENTO ICA"
METRADO: ESTRUCTURAS
Ø DE N° DE LONGITUD DE
ITEM DESCRIPCION UNIDAD N° DE VARILLA COD X KG PARCIAL TOTAL
VARILLA VECES VARILLA
PROYECTO: "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DE LA AVENIDA UNION DISTRITO DE PUEBLO NUEVO-
PROVINCIA CHINCHA- DEPARTAMENTO ICA"
METRADO: ESTRUCTURAS
Ø DE N° DE LONGITUD DE
ITEM DESCRIPCION UNIDAD N° DE VARILLA COD X KG PARCIAL TOTAL
VARILLA VECES VARILLA
PROYECTO: "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DE LA AVENIDA UNION DISTRITO DE PUEBLO NUEVO-
PROVINCIA CHINCHA- DEPARTAMENTO ICA"
METRADO: ESTRUCTURAS
Ø DE N° DE LONGITUD DE
ITEM DESCRIPCION UNIDAD N° DE VARILLA COD X KG PARCIAL TOTAL
VARILLA VECES VARILLA
PROYECTO: "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DE LA AVENIDA UNION DISTRITO DE PUEBLO NUEVO-
PROVINCIA CHINCHA- DEPARTAMENTO ICA"
METRADO: ESTRUCTURAS
Ø DE N° DE LONGITUD DE
ITEM DESCRIPCION UNIDAD N° DE VARILLA COD X KG PARCIAL TOTAL
VARILLA VECES VARILLA
PROYECTO: "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DE LA AVENIDA UNION DISTRITO DE PUEBLO NUEVO-
PROVINCIA CHINCHA- DEPARTAMENTO ICA"
METRADO: ESTRUCTURAS
Ø DE N° DE LONGITUD DE
ITEM DESCRIPCION UNIDAD N° DE VARILLA COD X KG PARCIAL TOTAL
VARILLA VECES VARILLA