Professional Documents
Culture Documents
STRUCTURE MODIFICATION
(JDE CEREAL PROJECT)
METHOD STATEMENT
STEEL STRUCTURE ERECTION AND SLAB OPENING REINFORCEMENT WORKS
AMENDMENT HISTORY
REVISION
DETAILS OF AMENDMENT
NO.
00 First Issue
JDE-PT-MST-0009_0
METHOD STATEMENT
STEEL STRUCTURE ERECTION AND SLAB OPENING
REINFORCEMENT WORKS
TABLE OF CONTENTS
1. SCOPE OF WORK.............................................................................................................. 4
1.1 General Description ..................................................................................................................4
1.2 Reference ....................................................................................................................................7
1.3 Materials ......................................................................................................................................8
1.3 Plant and Equipment ................................................................................................................8
1.4 Manpower ....................................................................................................................................9
1.6 Construction Procedure and Sequence ............................................................................10
2 SAFETY AND HEALTH .................................................................................................... 23
2.1 Job Safety & Health Analysis ...............................................................................................23
2.2 Information to Personnel.......................................................................................................23
2.3 Emergency Arrangement ......................................................................................................23
2.1 Permit Requirement ................................................................................................................27
2.2 Housekeeping ..........................................................................................................................28
3 ENVIRONMENTAL ISSUES ............................................................................................. 28
4 QUALITY ASSURANCE AND QUALITY CONTROL ...................................................... 28
5 APPENDICES ................................................................................................................... 28
JDE-PT-MST-0009_0
Page 3 of 32
METHOD STATEMENT
STEEL STRUCTURE ERECTION AND SLAB OPENING
REINFORCEMENT WORKS
1. SCOPE OF WORK
1.1 General Description
• The general scope of works include supply & install of steel structure at Level 4
HVAC Room, Mixing Room 2 and 3, platform for Packing Room 1,2 and 3 and
also slab opening reinforcement works at Level 4 all in accordance to the
Approved Construction Drawings (2100a/P/PB/01_Rev 3 & 2100a/P/PB/02_Rev
3).
JDE-PT-MST-0009_0
Page 4 of 32
METHOD STATEMENT
STEEL STRUCTURE ERECTION AND SLAB OPENING
REINFORCEMENT WORKS
Figure 2.0 Drawing AHU platform Floor plan level 27.3m at Level 4.
Figure 3.0 From side view of AHU platform Floor Plan level 27.3m Level 4.
JDE-PT-MST-0009_0
Page 5 of 32
METHOD STATEMENT
STEEL STRUCTURE ERECTION AND SLAB OPENING
REINFORCEMENT WORKS
Figure 4.0 Layout Plan Indicating Location of steel structure at Mixing Room 2 & 3 Level 4.
Figure 5.0 3D design indicating location of steel structure and truss at Mixing Room 2 & 3
Level 4.
JDE-PT-MST-0009_0
Page 6 of 32
METHOD STATEMENT
STEEL STRUCTURE ERECTION AND SLAB OPENING
REINFORCEMENT WORKS
Figure 6.0 Layout Plan Indicating Location of chequered plate platform at Packing
Room 1, 2 & 3 at Level 3.
1.2 Reference
• 2100a/P/PB/01_Rev 3
• 2100a/P/PB/02_Rev 3
• 2100a/P/PB/03_Rev 3
• 2100a/P/PB/04_Rev 3
• 2100a/P/PB/05_Rev 3
• Contractor Safety Management JDE ASIA (Rev 3)
JDE-PT-MST-0009_0
Page 7 of 32
METHOD STATEMENT
STEEL STRUCTURE ERECTION AND SLAB OPENING
REINFORCEMENT WORKS
1.3 Materials
No Material Description
Shape of structural steel used in buildings and as a support member
1 533x210x82 KG/M UB in structures.
Shape of structural steel used in buildings and as a support member
2 457x191x67 KG/M UB in structures.
Shape of structural steel used in buildings and as a support member
3 203x133x25 KG/M UB in structures.
Shape of structural steel used in buildings and as a support member
4 254x254x73 KG/M UC in structures.
5 Beam clamp To provide steel-to-steel connections between structural beams
7
UC 1Base Plate As a base before anchoring work
(350x350x20mm)
8
Anchor Bolt M20 To make a bolted joint
HILTI/HAS/RE-500
Screwed permanently into a fixed part at one end and to receive a nut
9 Stud Bolt on the other
11 Spider Crane 2.8 tons Capacity For lifting, tilting & positioning
JDE-PT-MST-0009_0
Page 8 of 32
METHOD STATEMENT
SLAB OPENING REINFORCEMENT STEEL STRUCTURE
1.5 Manpower
No Type of Manpower Qty. Description
2 Project Engineer (Ms. Tasha) 1 To manage overall technical and operation issues
Site Safety Supervisor (Ms.
3 1 Responsible for safety issues at site
Fiza)
Responsible for construction activity for his shift under direction
4 Supervisor 1 (Mr. Nicholas) 1
of engineer
Responsible for construction activity for his shift under direction
5 Supervisor 2 (Mr. Wong) 1
of engineer
6 General Workers 15 To work at site
JDE-PT-MST-0009_0
Page 9 of 32
METHOD STATEMENT
STEEL STRUCTURE ERECTION AND SLAB OPENING
REINFORCEMENT WORKS
1
2
JDE-PT-MST-0009_0
Page 10 of 32
METHOD STATEMENT
STEEL STRUCTURE ERECTION AND SLAB OPENING
REINFORCEMENT WORKS
Plan view of Mixing Room 2 and 3 at Level 4 with height 3750 mm, width 13,530 mm
and length 18, 275 mm as per attachment Appendix 5.2.
JDE-PT-MST-0009_0
Page 11 of 32
METHOD STATEMENT
STEEL STRUCTURE ERECTION AND SLAB OPENING
REINFORCEMENT WORKS
JDE-PT-MST-0009_0
Page 12 of 32
METHOD STATEMENT
STEEL STRUCTURE ERECTION AND SLAB OPENING
REINFORCEMENT WORKS
• Prior to the erection of the steel structural, ensure all the column area has been
erected first as per the approved construction drawings and the surface has
been cleaned free of dust.
• Column materials were arranged closed to design position.
• Column materials need to be cleaned, paint touching up and assembled before
erection.
• Columns should be arranged closed to their anchor bolt position.
• Attach driven rope to column.
• Check level and position of level nuts and anchor bolts with design.
• Check lifting weight and crane hook position with capacity of applied crane with
2.8MT.
• During erection work of column, lift the column and move slightly to design
position.
JDE-PT-MST-0009_0
Page 13 of 32
METHOD STATEMENT
STEEL STRUCTURE ERECTION AND SLAB OPENING
REINFORCEMENT WORKS
JDE-PT-MST-0009_0
Page 14 of 32
METHOD STATEMENT
STEEL STRUCTURE ERECTION AND SLAB OPENING
REINFORCEMENT WORKS
• Drilling the hole. Clean the hole immediately before setting the anchor. Remove
drilling dust and standing water from the base of the hole by blowing out well.
Ensure that the specified setting depth is marked on the anchor rod.
• After setting, adhesive mortar must fill the annular gap completely, right up to the
concrete surface. A load may be applied to the anchor only after the curing time
“tcure” has elapsed.
JDE-PT-MST-0009_0
Page 15 of 32
METHOD STATEMENT
STEEL STRUCTURE ERECTION AND SLAB OPENING
REINFORCEMENT WORKS
• The column that under the RC beam will install by using base plate hook as
shown in red marking that already install before while others will use lifting
frame.
• 2.8MT crane hook will be use as lifting device for lift up the column whereas will
attach to base plate hook and lifting frame to lift up.
• Standard equipment of beam clamp will be used with load and dimensions is
shown below.
• All the column and tie beam will lay horizontal at the point of installation for
easier during lift up.
• The lifting shackle will wrap at ¾ of the length from top of the beam as shown
in figure below.
JDE-PT-MST-0009_0
Page 16 of 32
METHOD STATEMENT
STEEL STRUCTURE ERECTION AND SLAB OPENING
REINFORCEMENT WORKS
• During erection work of beam, lift the tie beam and lifting slightly by using beam
clamp SWL 1T with shackle SWL 1T and hook by crane 2.8MT with sling belt
SWL 2T.
• Scissor lift will be use as work platform during positioning the I beam at the
column.
• The I beam will be installed to get the column safe for standing and lift by 2.8MT
crane hook that attach with base plate hook.
• 2 manpower on the scissor lift will hold the I beam and positioning at the column.
• The I beam will secure with bolt and nut once reach the positioning.
• Crane hook is only released when all connection bolts were tightened,
temporary bracings, bracing purlins, flange braces were installed adequately.
• All connection joints must be completed bolt tightening before releasing lifting
equipment.
• Steel erection installation is then completed. Similar installation procedures are
utilized for the next section of installation.
• The installation of the steel structure for I beam at Mixing Room 2 and 3 is
illustrated as follow:
JDE-PT-MST-0009_0
Page 17 of 32
METHOD STATEMENT
STEEL STRUCTURE ERECTION AND SLAB OPENING
REINFORCEMENT WORKS
• Concern to install all main column and tie beam to ensure the structure is
strong enough for positioning the equipment.
• The tie beam that obstructs during installing the equipment will install later
once the equipment already on positioning.
• The smaller tie beam as orange colour will be erect later just by using scissor
lift.
• The truss will be joint together with 3 section of the length on site by using bolt
and nuts.
JDE-PT-MST-0009_0
Page 18 of 32
METHOD STATEMENT
STEEL STRUCTURE ERECTION AND SLAB OPENING
REINFORCEMENT WORKS
LEVEL 3
JDE-PT-MST-0009_0
Page 19 of 32
METHOD STATEMENT
STEEL STRUCTURE ERECTION AND SLAB OPENING
REINFORCEMENT WORKS
JDE-PT-MST-0009_0
Page 20 of 32
METHOD STATEMENT
STEEL STRUCTURE ERECTION AND SLAB OPENING
REINFORCEMENT WORKS
• The lifting stand will install at 4th floor SBFI for lift up the reinforcement
457x191x67 KG/M UB through the holes.
• 3T chain block will be used as lifting device and controlling by experience
person.
• The communication will use walkie talkie during pull up.
• Before lift up the reinforcement 457x191x67 KG/M UB , the column 254x254x73
KG/M UC will lift up as per JDE-PT-MST009 steel structure erection.
• The bolt on RC beam will install by using M20 Hilti adhesive whereas required
for drill hole for put in the bolt.
• Vacuum need to put at the drill point for controlling the dust.
• During installing the steel structure manually, the reinforcement still hold by 3T
chain block that attach to lifting frame until the installation complete.
JDE-PT-MST-0009_0
Page 21 of 32
METHOD STATEMENT
STEEL STRUCTURE ERECTION AND SLAB OPENING
REINFORCEMENT WORKS
Bolt install at
existing tie Bolt install at
beam RC beam
• Once the steel structure completed, the chain block will release slowly until the
reinforcement stand on the steel structure and secure by bolt and nut.
• The sling belt only can release after all the bolt and nut completely tighten.
• There are 2 tie beams need to install for complete the stand support.
• The 2 tie beam will install by using scissor lift from below and secure by bolt
and nut.
JDE-PT-MST-0009_0
Page 22 of 32
METHOD STATEMENT
STEEL STRUCTURE ERECTION AND SLAB OPENING
REINFORCEMENT WORKS
• A task briefing, LMRA based on the control measures detailed in the Job Safety &
Health Analysis is required for all work activity
• Site supervisor will responsible for task briefing assist by HSE Supervisor and
must record in Toolbox Talk form.
• Task briefing will be held daily every morning on 0830hrs.
• All team members is compulsory to attend
AUTHORITY ACTION
JDE-PT-MST-0009_0
Page 23 of 32
METHOD STATEMENT
STEEL STRUCTURE ERECTION AND SLAB OPENING
REINFORCEMENT WORKS
•Identify Person-in-Charge i.e. Emergency Rescue Team, First-Aider, Fire Marshall and their
contact number etc.
"
•Identify relevant required emergency response equipment and facilities e.g. siren, fire
fighting equipment, first-aid equipment etc.
"
•Obtain emergency contact number i.e. police station, fire department, ambulance etc.
"
•Plan and conduct evacuation drill and / or fire fighting training at least once a year.
"
• Notification Of Emergency
The mobile phone is the primary means of emergency notification at the project site. This
system is intended for immediate transmission of specific information regarding an
JDE-PT-MST-0009_0
Page 24 of 32
METHOD STATEMENT
STEEL STRUCTURE ERECTION AND SLAB OPENING
REINFORCEMENT WORKS
emergency.
In typical construction setting and site office, the diesel tanks and flammable
substance are the main risks factor in causing fire and explosion. Similar provision will
be made at flammable substance storage areas. Flammable substances will be stored
in suitably ventilated compound at designated locations except when in immediate
use. A fire exit plan should be prepared.
Site storage and offices areas should display appropriate fire advisory and warning
notices like “NO SMOKING”, “FIRE EXIT Route”, etc. The actions to be taken in the
contingency plan in event of fire include:
In event of structural collapse or technical failure i.e. crane overturn, boring machine
collapse, scaffolding collapse, landslide, construction equipment collapse etc.; work
on site should be IMMEDIATELY STOPPED in an orderly manner. It may cause fatal
accident and injury incident. The contingency plan in should be taken include:
i. Stop work
ii. Sound the alarm
iii. Call Fire Bridged / Rescue Team / Ambulance
iv. If a fire threat, call fire service
v. If chemical spillage, cordon the area (Refer Chemical Spillage)
vi. Clear the area
vii. Assemble the workers
viii. Conduct head count
ix. Wait for emergency service arrival
In event of fall or rescue at height to be performed, actions to be taken are listed below:
JDE-PT-MST-0009_0
Page 25 of 32
METHOD STATEMENT
STEEL STRUCTURE ERECTION AND SLAB OPENING
REINFORCEMENT WORKS
JDE-PT-MST-0009_0
Page 26 of 32
METHOD STATEMENT
STEEL STRUCTURE ERECTION AND SLAB OPENING
REINFORCEMENT WORKS
Noryafiza Azwar
Amira Natasha (Project Engineer)
(Safety Supervisor) Sub-Contractor
017-7002530
018-764 7797
Major
Minor
Emergency Handled by relevant
Emergency Handled Internally by:
authorities & site staff:
Safety personnel
Fire Incident:
Site Staff
BOMBA (994)
First Aid Team
Serious Accident:
JPA, PDRM (999)
JDE-PT-MST-0009_0
Page 27 of 32
METHOD STATEMENT
STEEL STRUCTURE ERECTION AND SLAB OPENING
REINFORCEMENT WORKS
2.2 Housekeeping
• Housekeeping shall include maintaining the access road to all working area, no littering
around the site, and keep site tidy.
• Segregation between rest area, work area, machinery movement area, and storage area
must be clearly demarcated, identified, and labelled with signages.
3 ENVIRONMENTAL ISSUES
3.1 Appendix
• NIL
3.2 Temporary Erosion Protection
• NIL
3.3 Air Quality and Noise Level
• NIL
3.4 Water Quality QUALITY ASSURANCE AND QUALITY CONTROL
• NIL
3.5 Waste Management
• NIL
JDE-PT-MST-0009_0
Page 28 of 32
METHOD STATEMENT
STEEL STRUCTURE ERECTION AND SLAB OPENING
REINFORCEMENT WORKS
APPENDIX 5.1
SITE ORGANIZATION CHART
NORSYAFIZA AZWAR
018-7647797
SAFETY SUPERVISOR
JDE-PT-MST-0009_0
Page 29 of 32
METHOD STATEMENT
STEEL STRUCTURE ERECTION AND SLAB OPENING
REINFORCEMENT WORKS
APPENDIX 5.2
LAYOUT DRAWING LEVEL 3 AND LEVEL 4
JDE-PT-MST-0009_0
Page 30 of 32
DOOR & WINDOW SCHEDULE
TYPE DESCRIPTION SIZE
FRD Motorised Heavy Duty Two Hour Fire Rated 3000 x 3000
Roller Shutter With Bomba Approved Type
FRD1 Motorised Heavy Duty Two Hour Fire Rated 2500 x 4500
Roller Shutter With Bomba Approved Type
FW1 Fixed Glass Panel WIth Aluminium Frame 1500 x 1200
Laminated Clear Glass (Inside)
Motorised Fire Roller Shutter Door (120MIN
Fire Rated c/w Bomba Approved
Type)(Outside)
2000 216000
9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000
1950 2550 1950 2550 4200 6000 7800 2550 1950 2550 1950
1
LIMIT WORKZONE
2000
1000
3000
14000
LIMIT WORKZONE
K
K
2000 2000 2000
3600
3600
3600
3600
4600
PACKING ROOM 3
22600 4816
PACKING ROOM 2
1200
1200
9579
PACKING ROOM 1
10600
K
CHA NG ING ROOM 1
42000
CHA NGING
14000
RO O M 2
CHA NGING
RO O M 3
1200 1200
1200
K K
K
2000
2500
2000
4521
3500
LIMIT WORKZONE
14000
4034
RE S TROOM 3
7875
.......................................................................................................
I hereby certify that these structural details / calculations are in accordance with
the uniform building by-laws (Chapter 5, Structural requirements)
DOOR & WINDOW SCHEDULE
TYPE DESCRIPTION SIZE
FRD Motorised Heavy Duty Two Hour Fire Rated 3000 x 3000
Roller Shutter With Bomba Approved Type
FRD1 Motorised Heavy Duty Two Hour Fire Rated 2500 x 4500
Roller Shutter With Bomba Approved Type
FW1 Fixed Glass Panel WIth Aluminium Frame 1500 x 1200
Laminated Clear Glass (Inside)
Motorised Fire Roller Shutter Door (120MIN
Fire Rated c/w Bomba Approved
Type)(Outside)
2000 216000
9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000
1950 2550 1950 2550 4200 6000 7800 2550 1950 2550 1950
LIMIT WORKZONE
1
331 279 8650
4175 8665
5340
7080
3490
3000
4230
223
229
14000
5980
3000
4660
2000 E X IS TING FIRE WALL
EL
650
EL
EXISTING FIRE
EL
WALL
6465
3000
EL
EL EL
18145
11202
42000
14000
EL
EL EL
3000
P RO DUCTIO N OFFICE
LEV 25.80M
1200 1200
1200
CHA NGING CHA NGING
RO O M
EL1 ROEL
OM 2
3298
EL EL EL
CHA NGING
RO O M 3
1200
1200 1200
14000
E L E CTRICAL
RO OM
B LO WER
RO OM
1
LEVEL 4 FLOOR PLAN (JM0783988-X)
Scale: 1:350
No. 4 Jalan Perjiranan 10/21 Bandar Dato' Onn,
81100 Johor Bahru, Johor Darul Takzim.
Tel : 07-350 0587
email : afkdesign81@gmail.com
I hereby certify that these structural details / calculations are in accordance with
the uniform building by-laws (Chapter 5, Structural requirements)
DOOR & WINDOW SCHEDULE
TYPE DESCRIPTION SIZE
FRD Motorised Heavy Duty Two Hour Fire Rated 3000 x 3000
Roller Shutter With Bomba Approved Type
FRD1 Motorised Heavy Duty Two Hour Fire Rated 2500 x 4500
Roller Shutter With Bomba Approved Type
FW1 Fixed Glass Panel WIth Aluminium Frame 1500 x 1200
Laminated Clear Glass (Inside)
Motorised Fire Roller Shutter Door (120MIN
Fire Rated c/w Bomba Approved
Type)(Outside)
2000 216000
9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000
1950 2550 1950 2550 4200 6000 7800 2550 1950 2550 1950
LIMIT WORKZONE 1
AHU PLATFORM
AHU PLATFORM
LEV 27.300M
4230
LEV 27.300M
4.5MM THK. M.S CHEQUERED PLATE
50MM THK PIR PANEL CEILING BELOW
14000
14000
LIMIT WORKZONE
14000
1
LEVEL 4 UPPER FLOOR PLAN
Scale: 1:350
(JM0783988-X)
.......................................................................................................
I hereby certify that these structural details / calculations are in accordance with
the uniform building by-laws (Chapter 5, Structural requirements)
DOOR & WINDOW SCHEDULE
TYPE DESCRIPTION SIZE
FRD Motorised Heavy Duty Two Hour Fire Rated 3000 x 3000
Roller Shutter With Bomba Approved Type
FRD1 Motorised Heavy Duty Two Hour Fire Rated 2500 x 4500
Roller Shutter With Bomba Approved Type
FW1 Fixed Glass Panel WIth Aluminium Frame 1500 x 1200
Laminated Clear Glass (Inside)
Motorised Fire Roller Shutter Door (120MIN
Fire Rated c/w Bomba Approved
Type)(Outside)
2000 216000
9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000 9000
1950 2550 1950 2550 4200 6000 7800 2550 1950 2550 1950
LIMIT WORKZONE
14000
14000
14000
1
LEVEL 4 UPPER CEILING PLAN (JM0783988-X)
Scale: 1:350
I hereby certify that these structural details / calculations are in accordance with
the uniform building by-laws (Chapter 5, Structural requirements)
LIMIT WORKZONE
AHU PLATFORM
FFL LEV 27.300M
(JM0783988-X)
SECTION 1-1
1 Scale: 1:100 .......................................................................................................
I hereby certify that these structural details / calculations are in accordance with
the uniform building by-laws (Chapter 5, Structural requirements)
WASTE OUT
CHECK WEIGHER
CHECK WEIGHER
CHECK WEIGHER
CHECK WEIGHER
16A 16A
2000
16A
16A
C
PACKING
C
16A 16A
C
16A 16A
PACKING ROOM
C
1971.0000
20A
ROOM #2 HBL
CHECK WEIGHER
#1 FFL+0
760.0000
FFL+3096
FFL+0
HBL
CDA
HBL
2"
FFL+3196
FFL+0
16A 16A
1.5"
16A 16A
C
EL EL EL FFL+4696 FFL+4696
C
C
16A 16A
16A 16A 16A
16A 16A 16A
C
C
C
C
C
1"
C
LEVEL 3
EL
1928,51
960,28
C
CDA
1215
1"
1199,93
HBL
C
CDA HBL HBL
EL
1" FFL+5220
CDA CDA
830,6
1" 1"
20A
FFL+5220
20A
2090
EL EL EL EL
EL 20A
20A
20A
16A 16A
EL EL FFL+5220
FFL+3777
PACKING
FFL+5220
1199,93 FFL+0
MATERIAL IN
20A
EL
ROOM
16A
C
FFL+3096
2000
FFL+0
#3
20A
C
20A
HBL EL
16A 16A
CHANGING
16A 16A
C C
HBL
C
ROOM 2
C
16A 16A 20A
C
FFL+3196
EL EL
C
20A
CHANGING
FFL+0
20A
ROOM 3
20A 20A
1199,93
1199,93 1199,93
HBL EL
DB-Packaging 3 (150A)
EL EL HBL EL HBL
EL
20A
20A
1199,93
20A 20A
20A 20A
C C K
K
20A 16A 16A 20A
2000
K 20A MATERIAL IN
2000
2529,87
DB-Packaging 1 (150A) MATERIAL IN DB-Packaging 2 (150A)
1900
3000
20A 20A
13923,17
16A 16A
C
3610
EL 6973,31
1247,11
20A IN & OUT
346,89
EL EL 16A 16A
CDA K 20A
20A K
1"
C C
3000
C
16A 16A
1818,99
C
2668,66 1"
32A
615
1015,73
Ø
LBL 250 LBL
790
HBL HBL
HBL 248,3
11541,16
CDA
1" 5403,99 CDA
1"
2274,29
3455
EL LBL LBL
3871,99
3529,55
3774,11
Ø2
50
4063,4
779,22
CDA
3610 3650 1.5"
EL CDA
EL
16A 16A
1.5"
3670
32A 32A 32A 32A 16A 16A
3685
Ø1553,33
250
553,5 553,5
Ø2
C
50
931,88
931,49
779,5
EL
16A 16A
16A 16A
EL
Ø400 Ø4
00
C
CDA
931,49
14646,98
931,49
1"
EL Ø40
HBL
C
C
CDA 0 Ø4
553,5 553,5
1"
00
C
EL CDA
EL
16A 16A
1.5"
250
C
32A 32A LBL
3750,08 LBL
EL
20A
20A
5282,08
C
16A 16A
C
IN & OUT
EL EL LBL LBL
MATERIAL
HBL
3000
HBL HBL
EL EL
DB-Mixer 2 (150A)
16A 16A
20A 20A 20A 20A
C C
DB-Mixer 1 (150A) 3670 3685
2153,65
1200
1200
1200
1200
1200
1200
HBL LBL ROOM 2
1783,93 2557,96 LBL
1200 1200 1200
300 300 300
APPENDIX 5.3
SAFETY & HEALTH ANALYSIS
JDE-PT-MST-0009_0
Page 31 of 32
METHOD STATEMENT
STEEL STRUCTURE ERECTION AND SLAB OPENING
REINFORCEMENT WORKS
JSA / RA Title
STEEL STRUCTURE ERECTION AND SLAB OPENING REINFORCEMENT WORKS
Organisation Contract:
sessment Date Revision Status 00
JDE-PT-MST-0009_0
Page 32 of 32
METHOD STATEMENT
STEEL STRUCTURE ERECTION AND SLAB OPENING
REINFORCEMENT WORKS
JDE-PT-MST-0009_0
METHOD STATEMENT
STEEL STRUCTURE ERECTION AND SLAB OPENING
REINFORCEMENT WORKS
JDE-PT-MST-0009_0
METHOD STATEMENT
STEEL STRUCTURE ERECTION AND SLAB OPENING
REINFORCEMENT WORKS
JDE-PT-MST-0009_0
METHOD STATEMENT
STEEL STRUCTURE ERECTION AND SLAB OPENING
REINFORCEMENT WORKS
Sharp edges 1 Staff 2 3 6 1. Ensure any sharp edges need to cover/ put safety cap 4 Supervisor
7 Housekeeping Body injury. 2 2
2 Labour M 2. Wear cut resistance glove L
JDE-PT-MST-0009_0