Finishing 

Works

Description of work Unit Qty Unit Price Amount

Head room  Block work 200mm Sqm 850                 189.75         161,287.50

Pump House Block work  200mm Sqm 126                 189.75            23,908.50

Car Park Block work  200mm Sqm 750                 189.75         142,312.50

NOB balance  Stair Plaster (15mm to 20mm) Sqm 420                    94.25            39,585.00

Pump House internal Plaster (15mm to 20mm) Sqm 516                    94.25            48,633.00

NOB basement Plster (15mm to 20mm) Sqm 175                    94.25            16,493.75

O&M basement internal plaster (15mm to 20mm) Sqm 325                    94.25            30,631.25

Control Building External Plaster (20mm) Sqm 390                    94.25            36,757.50

Building Externlal painting as per specification (2coats) Sqm 2640                    51.00         134,640.00

Buildings internal approval Sqm 1265                    51.00            64,515.00

Gallery wall Surface finishing  on concrete wall  Sqm 16000                    40.00         640,000.00

Total Amount       1,338,764.00