You are on page 1of 1

Rev‐01

31‐Dec‐2014

Project: Brown field modification project
LOI No: HHI‐Q5CO‐FAP‐Modification
Client: HHI 
Unit rates applicable for Equipments & Tools(Offshore).

Mob/De‐
Daily Rate in  Stand by 
SI No: Item/Description mob rate per 
US$(24 Hrs) rate(50%)
unit(US$)

1 Diesel Welding Machine                        75.00                     37.50            300.00 


2 Electric Welding Machine                        50.00                     25.00            200.00 
3 Air Compressor 365 cfm                      105.00                     52.50            420.00 
4 Generator 100 KVA                      110.00                     55.00            440.00 
5 Pressurized habitat                        50.00                     25.00            200.00 
6 Scaffolding (Approx 2400 Cu M)                      400.00                   200.00         1,600.00 
7 Torquing set                      250.00                   125.00         1,000.00 
8 Lifting tools                      350.00                   175.00         1,400.00 
9 Safety Gears                      600.00                   300.00         2,400.00 
10 Other Misc tools,tackles(Drilling 
m/c,pneumatic saw,hydrotest                       150.00                     75.00            600.00 
pump,spanners,threading m/c etc.)

Prepared by(Trags): Approved by(HHI):

Name & Signature Name & Signature

Page 1 of 1