Professional Documents
Culture Documents
RAusAcT1ous
B.5.1
0 scope changes,
0 constructive change orders, When owners or their authorized representatives
give or fail to give directions that interfere with
0 errors and omissions, the normal contract development without acknowledging
cost and schedule implications, what is usually called
c contract acceleration and expediting, a "constructive change" may be disputed by contrac-
tors. Additionally, constructive changes are some-
o work suspension and stoppages, times found after the fact, when reviewing schedules,
records, letters and minutes of meetings. This does
0 site access or availability, not negate the contractor's right to recover addition-
al expenses.
o other contractors interferences and delays, and
Contractors are advised to train their construc-
0 strikes and acts of God. tion teams to recognize constructive changes since
this can make the difference between a profit or a
Poor Project flying loss situation.
Lack of adequate attention to front-end planning Errors 5nd Cmissi.onia
of the project usually ends up in:
A potential for claims arises when the contractor
0 inadequately defined scope of work, and questions plans and specifications given by contractu-
al terms, and the owners or their representatives fail
0 incomplete and/or incorrect design. to recognize it as a valid change order. Constructive
change orders may be generated by absence of agreement
Most of the time, poor planning is attributed to on this issue. Even if the contractor is forced to
fast track projects that bring about: proceed as directed by the owner and contractual
obligations, recovery of additional costs may be
0 shortened bid periods, pursued at a later occasion. Contractors are advised
to document these cases as closely as Possible for
0 limited site investigation, future identification of additional costs.
0 unreasonable construction periods, CoxltractzJcce1eration andlXXpE&t~
c badly specified construction materials, and Contractors are frequently directed to accelerate
performance of the contract or a portion of it within
0 inappropriate staffing. the original or adjusted completion date. This
direction constitutes a change in the contractual
Whatever the reason is, claims are abundant when obligations, and the contractors have the right to
planning is not taken seriously enough to produce an pursue compensation for it.
adequate environment to develop a project. Moreover,
this situation is seldom acknowledged by owner repre- Furthermore, contractors may expend extra effort
sentatives for obvious reasons. Only well-trained in response to a directed increase in work without an
project'team personnel will be able to ascertain it increase in time. This constitutes a constructive
before it develops into a costly problem. acceleration which should be carefully analyzed, docu-
mented and decided upon. Validation of this kind of
8cope cllangea claims is, of course, difficult and requires the con-
tractors to prove their case.
Scope changes are usually initiated by a change
order, letter of intent, or a field directive. They rork Su~sion and Stoppaqee
may direct changes, work deletions or additions to the
original scope of the contract. When contractors are notified to suspend work due
to reasons out of their control, they have the right
Change orders are just part of everyday business to be compensated for the time and cost involved in
in construction environments. To think that a project the susp&nsion or part of the suspension even if the
or a construction contract can be executed without contract document calls for "work-around" directives.
them is a fallacy unsupported by experience. An Contractors are compelled to keep detailed data
effectively organized effort to eliminate cost and related to cases like these to be able to recover
time impact as a result of processing work outside the related expenses.
original scope of the contract should be high on the
list of priorities of every management team since Site Access or i2maiiardbility
change orders are the usual reason for cost and time
overruns. This is especially true for contractors When the contractors' scheduled activities have
wanting to realize their planned profits. the need for a right of way and/or a location to
proceed and the owner fails to provide them on time,
Scope changes are often narrowly and poorly the contractors should pursue a compensation for the
defined, and estimates of the associated cost and time and cost of the resources scheduled and not being
schedule impact are usually lacking accuracy in order- able to perform productively.
of-magnitude estimates.
Contractor, designer and owner may agree on the fact
that something should be done, but they may not be so When the contractual obligation forces the
agreeable on its full description and associated cost contractor to joint-occupancy, interference by other
implications. owners' contractors' actions or lack of progress in
the area may hamper performance and a justifiable
E.5.2
1991 AlLcB Tlzm~Iws
/’ E.5.3 ',
0 organized sequence of activities needed to 0 Job staffing and layoff schedules are contractual
perform the job, obligations, and lack of compliance constitutes
a breach of the contract.
O duration for all activities involved, and
0 Inspections and approval6 from the owner should
O resources needed to accomplish each activity. be performed according to the schedule.
In other WOrd6, critical path method schedule6 o Any deviation from the schedule should be settled
depict what has to be done, when it haS to be done, as per contractual procedure6 involving schedule
how it ha6 to be done, who has to do it, and where. revisions.
Contractual obligation6 usually include:
O approval of an original CPR,
O procedures to update the CPM periodically, Good, accurate records are the best assistance
anybody can get when negotiating change6 and diSpUtesa
O procedure6 to revise the CPM, and This is particularly important for the contractor6
since they usually have the burden to prove the impact
O procedure to utilize the CPN as a tool for claim any issue under dispute had on their performance. The
settlements. record6 usually needed to Substantiate a Claim are8
The following checklist provide6 a valuable tool for 0 progress schedules,
planning and scheduling administration:
0 daily and weekly reports,
O Establish and maintain a progress measurement
SyStX?m. 0 change order log,
O Gain construction schedule approval a6 soon a6 0 purchase orders and delivery receipts,
possible.
0 correspondence from and to the contractor,
O Establish and maintain planning and scheduling
routines. O photographs,
O Agree upon planning/scheduling indexes and their O job diary,
meaning.
0 plan and schedules revisions, and
0 RStabliSh schedule revision6 approval with
minimum turnover time. 0 minutes of daily and weekly meetings.
O Establish change order/approved schedule inter- Performance is usually documented through periodic
face System. reviews and revisions of the project approved sched-
ule. Report6 Showing scheduled v6 actual performance
O Create a scheduling revisions filing system. determine the project Status St any tima SO anybody
can visualize the work completed to date, the rate at
O Insist on detailed backup for proposed changes. which the work was performed, and the costs incurred.
Daily and weekly reports should include8
0 Promptly notify/process/document schedule vari-
ances. 0 issue date, weather conditions,
If properly included in the contract, some 0 staffing levels,
general legal implications of an approved critical
path method schedule may be summarized a6 follows: 0 equipment used and idled,
0 Roth parties are bound to follow the schedule 0 material6 utilized and future requirements,
specifications.
0 subcontractors performance,
0 There is an implied warranty by both parties that
they will not hinder, delay or disrupt the other 0 detail6 on controversial matters,
party.
o change orders work, and
0 Labor level6 and crew sizes established in the
schedule have to be followed unless Change6 are 0 safety.
duly authorized.
Since change order6 are one of the major causes
0 Equipment utilization incorporated in the sched- of claims, it iS important to maintain good record6 of
ule is binding, and failure to follow it consti- them including:
tutes a breach of the contract.
0 initiations,
0 Materials, tool6 and consumable a6 specified in
the schedule are equally binding. O cost and time estimates,
o Contractors are liable for productivity lower 0 approvals,
than that allocated by the schedule.
0 current status,
E-5.4
1991 A&cB ~sAc!rIoars
E.5.5
Project management communications, creativity, in the area of project management. Construction law
flexibility and accuracy are substantially improved by is an ever-changing issue which must be constantly
rather simplistic planning rules. Planning will work reviewed and revised to maintain the project team's
for you if you believe on it, make others in your team potential to overcome difficult situations.
realize it6 benefits and, above all, make it an exten-
sion of your project cost and schedule control philos- There is a great deal of money to be saved day in
ophy. and day out when involved in a construction endeavor
by fostering the project team.6 knowledge about issues
abat matimat~g impacting performance and the best approach to solving
them.
Cost estimating is one of the essential area6 of
project management and usually the basis t0 SUbStanti- A simple workshop on claim related Subjects,
ate contractual disputes. given to the project team at the inception of the
projector contract can help improve dramatically your
Cost estimates for a contract in general and for chances of accomplishing profitable goals.
project changes in particular are often Used as the
basis to substantiate claim entitlements.
Cost estimates should be detailed enough to allow
later comparison with actual costs, thereby providing 1. Buffa, E. 1965. ricbhrn iFlmduction cleaagi~t.
evidence of errors, misinterpretations or construction Wew York:John Wiley hi Sons.
changes.
2. Cleland, D. 1975. sgew &mlyd.!sl and IPrcjene
A project chart of accounts for breaking costs clanegaw!6nt. Wew York:RcGraw-Hill.
down to identifiable work package6 is the best tool to
organize a cost estimate and at the same time gather 3. Daniels, J., E. Ogram, and L. Radebaugh. 1983.
actual cost6 in a consistent manner. Changed job Isternational lBusiness. Addison Wesley Publish-
conditions can be easily segregated and coded for fur- ing Co.
ther analysis against the schedule and made relevant
daily, weekly and monthly reports for possible cost 4. Levin, R. 1975. @JRmntitateJiwe Lipp-omche% ec
recovering. Banag-t . C.A. Kirkpatrick. Wew YorkrWcGraw-
Hill.
Labor cost estimate6 should be closely related to
working schedule6 and crew arrangement6 to be able to 5. Lock, D. 1966. Project .mnagwt. Gower Press.
identify planned against actual productivity and their
relative weight should a claim situation arise. 6. Lucey, T. 1984. Qmmtitatiwe ‘EaWmm. DP
Publications.
material and equipment procurement cost estimates
and schedules should allow tracking of escalation 7. lanzanera, I., ed. 1990. Prcjcact IzaimgBt
factors and productive utilization respectively. Even iRlEfamCS5. Dhahran: Saudi Aramco.
in the event of having a contract development free of
disputes, cost estimates, if approached as mentioned 8. Roder, J. and C. Phillips. 1982. lmojmt
above, can provide an exceptional amount of informa- Tsnagex6nt with 6XZ.l and Part. New Yorkrwan
tion for project management future endeavors. Wostrand Reinhold.
9. O'Brien, J. and R. Zilly. 1971. con~ac~r'e
rz.amig-t m%ndbcoIs. Wew York:McGraw-Hill.
Project management is responsible for preparing 10. POpper, H. 1979. cbdern Cobrst IXngineerhg~ New
bid cost estimates, construction schedules, contract York:RcGraw-Hill.
documents, change orders, material6 procurement, labor
and other resources schedules on daily, weekly and 11. Rigg6, .J. 1977. Engimserimg lZommica. New
monthly basis. If all this effort is performed by York:RcGraw-Hill.
personnel having a clear awareness of how essential
these information may become as evidence when contrac- 12. Specthrie, S. 1959. Indnstrial Aooounting.
tual specification6 are changed, dispute6 and claim6 Englewood Cliffs, WJ:Prentice-Hall.
may be avoided and, more importantly, additional cost
recovered. Furthermore, project management partici- 13. Weston, J. and E. Brigham. l%nageriel Pinaace .
pants should have a good working knowledge of the maze Dryden Press.
of statutory and common law developed in recent
decade6 to be able to handle profitably project6 14. 1963. Classification System for Economic Ap-
continuously increasing in size and complexity. praisals, Coet Eegineer's E!otebooIs. Section D-3.
AACErMorgantown WV.
Project teams around the world Seldom address the
legal relationship between different entities involved
E.5.6
Ignacio Hanzanera, CCE Dr. Khaled Bubshait
Saudi Aramco King Faud University of
PO Box 10089 Petroleum and Minerals
Dhahran 31311 PO Box 950
Saudi Arabia ,Dhahran 31261
Saudi Arabia
E.5.7