Planning for Project Success

Conflicts of Interest

Dealing with Conflicts of Interest in Turnkey Solutions

Cost control is a key to project manager makes recommendations for


success. Yet, a threat to cost control resources needed to complete project
that often goes unrecognised has execution, which happen to include his
become prevalent in the oil and gas or her friends from past projects.
industry – a key supplier’s conflict of Although the incentives are different,
interest. This type of conflict exists both situations can result in the project
whenever a supplier advises on project owner’s loss of opportunity to secure
strategy and could benefit by that very the best available resources and
advice by supplying other types of ultimately in bearing unnecessary
goods or services at other stages of costs for the project.
the project.
The Contractor as Manager
When a key supplier has a conflict of
interest, the project owner’s costs are Many traditional engineering and
likely to increase on the project with no construction firms in recent years have
corresponding benefit. Accordingly, announced moves into “project
even aside from moral or ethical management”. This means that the
issues, an effective cost control same company providing project
requires management services will likely
provide some combination of design
1. Elimination of conflicts of
engineering, fabrication, and construc-
interest and
tion services on the same project.
2. Mitigation of conflicts that are Rather than protecting the client’s
unavoidable. interest, the project management arm
in such a venture will likely protect first
Supplier conflicts of interest can and its own corporate interests.
have developed in a number of ways.
This article focuses on the types of A project owner should expect its
conflicts that arise from “turnkey project management company to
solutions”. These can range from protect the project owner’s interests,
advice given by a project consulting much as its attorneys, accountants,
firm that is part of a larger integrated and bankers. The ideal relationship is
construction company to the situation shown in the figure below:
where an outside project execution

www.epeusservices.com
-1-
Planning for Project Success
Conflicts of Interest

Project Owner
Client Group Protect Client’s Interest

Project Management Attorneys


Company Accountants
Financiers

Contracted To Perform
Contractor Group
Good Job

Engineering Construction Others

This structure, however, is not the advice of these formerly independent


expectation for the contractor group. consultancies, and their integration
The contractual standard for a into EPC contractors raises real
contractor is generally to perform “in a conflict of interest issues.
good and workmanlike manner,” or
some similar rubric, not as a fiduciary For example, in the case of an
of the project owner’s interest. When a independent consulting firm whose
company in the contractor group takes business is to assist project owners in
on the role of a project management the planning stages of a project, the
company, the real world distinctions incentive is to find the best resources
are confused, often with results that for project execution based on the
are not beneficial to the project owner. client’s cost, schedule, and quality
parameters. This kind of
recommendation enhances the likeli-
The Vertically-Integrated EPC
hood of overall project success and
Contractor
repeat business for the independent
In recent years, some contracting consultancy.
firms have also sought to provide
If that same consultancy is acquired
turnkey solutions for their clients’ oil
by an EPC contractor, however, the
and gas industry projects by, among
incentives change. The acquiring party
other things, acquiring independent
typically expects “synergies” from such
boutique consultancies. Project
an acquisition, which among other
owners, however, may have previously
things include enhanced profits
come to rely on the expertise and
throughout the organisation. Advance-

www.epeusservices.com
-2-
Planning for Project Success
Conflicts of Interest

ment opportunities or even continued also provides personnel for other


employment for personnel of the project execution positions. This
formerly independent firm depends practice has been around longer than
upon delivering what is expected by the integrated EPC contractor and has
the acquiring company. been used often. The owners,
however, may or may not have
A project owner would likely not recognised the potential for conflicts.
approve a similar relationship among
its attorneys, investment bankers, and A statistic that is often cited is that 6
auditors or, if in insolvency, its out of 10 projects fail. Whether actually
administrators. Yet presumably, the true or not and regardless of the
EPC firms have acquired formerly parameters on which the project may
independent consulting firms at least have “failed,” many of the failed
partially because of client expressions projects have been managed by an
of interest in a “total solution”. The only outside project manager who hires his
possible conclusions are (1) the or her friends to fill various jobs on the
owners have considered the conflict project execution. When the project
issues and are dealing with them in owner accepts these recommenda-
ways discussed below in this paper, or tions on a wholesale basis, it has
(2) the owners have not considered apparently given little or no thought as
the issues and are open to a to whether it will obtain the best
substantial risk of abuse of trust by the available resources for project
contractor. success.

The abuse of trust can include a


How To Deal with Potential
recommendation of sister companies
Conflicts
for the execution work, as well as
project “oversight” that entails A conflict of interest can therefore
reviewing the work of those arise from any situation in which close
companies. Uncovering any such advisors to the project owner
abuse is difficult at best after the fact, organisation are in a position to
since an unscrupulous company can recommend using related corporate
take advantage and even alter records entities or resources on other aspects
of work done and project audits. of a project.

The Manpower Agency Obviously, the best solution from the


project owner’s viewpoint would be to
A similar issue comes up when the eliminate completely potential conflict
project owner retains an outside situations. In rare instances, however,
project manager from an agency that a conflict is unavoidable because of

www.epeusservices.com
-3-
Planning for Project Success
Conflicts of Interest

the nature of the goods or services provision may be seen as extreme, it


offered. Even when the conflict is demonstrates the degree of
avoidable, resistance to a complete determination of some project owners
ban can come from both inside and to control costs.
outside the organisation: “This is the
way we have always done business” Some less intense measures would
or “Joe’s my mate, he’d never do seem to suffice in most situations. The
THAT”. first step in dealing with potential
conflicts is to instil a culture of zero-
Conflicts of interest are not unique to tolerance of avoidable conflicts of
projects in the oil and gas industry. For interest. Some organisations have
example, the potential for conflicts of conveyed this to their personnel and
interest exist in large accounting firms contractor, but many have not. This is
that both advise and audit companies, a long-term process and includes
the hotel management industry, and development of written policies, as well
doctor ownership of medical clinics, to as an intake and ongoing training
name a few. Project owners in the oil program.
and gas industry can learn lessons for
dealing with the potential conflicts of The second step is to identify
interest from these other industry potential conflicts. The project owner
situations. should ask any advisor on project
strategy to identify in writing its
Dealing with potential conflicts of corporate affiliates and the products
interest by contract is only part of the and services offered by those affiliates.
solution. A simple paragraph in a Then the project owner can make an
contract that prohibits conflicts will do informed evaluation of the recommen-
almost nothing to prevent dations made by the advisor or
recommendations, which when viewed consultant as to whether a conflict
later, could be seen as a conflict exists.
situation.
Conclusion
On the other hand, one company has
gone so far as to publish its standard As it turns out, therefore, solving one
contract in which a company that problem – the desire for turnkey
provides services on one part of solutions – leads to other serious
project is prohibited along with its issues. In the end, the only effective
corporate affiliates from providing substitute for strong in-house
services not only on any other part of management of outside contractors is
the same project but also or for any retention of a truly independent firm
other project for the owner for a whose personnel recognise the
specified period. While such a

www.epeusservices.com
-4-
Planning for Project Success
Conflicts of Interest

necessity for independent judgment and do not offer actual construction


and that pledges to such oversight to a personnel on project execution. We
project owner. are therefore in a unique position to
offer our clients unbiased and
Èpeus is dedicated solely to protect- independent advice on contracting and
ing its client’s interests. Èpeus project strategy in the definition and
professionals have consulted on a planning stages of a project, as well as
number of projects and maintain a during execution and commissioning.
knowledge base of lessons learned of
the things that have gone well and that For instance, during execution,
have not gone as well on a project. Èpeus can at the client’s direction
These lessons include not only ones either manage the project or audit the
learned during execution, but during all execution of a project carried out by
phases of a project, from definition another company against the project
through planning, approval, execution, parameters set during the definition
and commissioning. and planning stages.

On the other hand, Èpeus does not Visit our website for more information
offer anything but project advisory and about Èpeus and how we can help you
assurance services. We do not offer achieve project success.
FEED or other engineering services

www.epeusservices.com
-5-