Professional Documents
Culture Documents
Stock Piping Reco Endations: General Information Piping Recommendations
Stock Piping Reco Endations: General Information Piping Recommendations
.
I NIFG O' N S-kc~C+r-L (?' n P ~ ,~C, ~
a V
,, r;l
TOP VIEW
LOWER
QUADRANT
45 DEGREES ~
OR LESS
FLOW
V a 7 TO 14 FPS
(128 TO 256 mpm)
HORIZONTAL
Figure 1 . Main Lines and Secondary Entrance Lines Pitched Upward from the Horizontal
. 12
iW
V= 7 TO 14 FPS
HORIZONTAL
3. "Metalap Flanges", or fiaages where the 7 degrees) minimum (Figure i), wherever
male and female sides are machined to possible.
be exactly concentric with pipe LD . (no 2 Secondary entrance lines (Figure 1)
gasket), should be used between screen should enter main pipe in a lower quad-
and headbox in machines where opti- rant, pitched up at a slope greater than
mum cleanliness must be maintained. the slope of the main pipe, and not more
than 45 degrees from the direction of
NOTE: See Beloit manual "Metalap main pipe.
Flange - Welding Instructions" (L 008-
3. If it is impossible to reach an objective
10002) .
at this pitch, the pipe lines should drop
4. All interior welds and interior surfaces vertically where necessary . High points
must be polished so that a cotton ball should be vented to the wire pit (or seal
passed over them will not hang up fibers. pit) and pipe continued, sloping upward
Aversge surface roughness of welds in the flow direction (Figure 2) .
should be less than 150 mioroinches
(3.8 micrometers). NOTE: A high point is any pipe location
that will collect air due to a change
5 . All joints should be flush . in flow direction. .
8. All pipe lines should be adequately
supported . 4. Horizontal lines which are impossible to
slope due to equipment location should
7. Avoid any sharp corners or combination be designed for a velocity of 10 fps (183
of circumstances that may be conducive
mpm) minimum . See (Figure 3).
to stock deposits.
8. Pipes should be sized for 7 fps (128 mpm)
minimum velocity and 14 _ fps (256 mpm)
ma:imum velocity . V= 10 FPS MINIM M
(183mpm
F
INSTALLATI O N
i. All pipe lines should be pitched upward
in the directfon of tlow at 1-1/2 to 12 (or Figure 3. Sizing Hori=ontai Piping
2
2030029502
02
http://legacy.library.ucsf.edu/tid/nzr63e00/pdf
STUFF BOX
r
HEADBOX
1'h====.
12 FROM
RECIRCULATION
(2 TO 3) x D
SYSTEM
C
5. Install drain in all low points. Drain plug 10. Pit or silo outlets such as fan pump suc-
should be flush with pipe LD . if located tion line should be designed with a
between screen and headboz . transition piece (Figure 5) . The sub-
NOTE: A low point is any location that merged height in feet (m) should be
cannot be drained unless an addi- equal to or greater than the numerical
tion outlet is provided. value of the velocity in feet per second
(mps) of the outlet
6. Locate stuff box as clolme as possible to
pump suction. Drop stock line vertically
and then slope upward 1 .5 to 12 mini-
mum to enter fan pump suction. (Figure H (FT.)= V (FPS)
4). H (M)&V (MPS)
7. Heavy stock line between stuff box and
basis weight valve should be sized at 2
to 4 fps (36 to 72 mpm). Use line siae
identical to valve siae between basis
weight valve and suction side of fan
PUMP-
8. Locate basis weight valve well below
silo level - preferably two to three '"pipe
V
diameters" above bottom elbow (Figure
4). t
9. The level in the stuff box should be a 12
minimum of 15 feet (4500 mm) above the
level in the silo (Figure 4) . Figure 5 . Pit or Silo Outlet
2030029503
3
http://legacy.library.ucsf.edu/tid/nzr63e00/pdf
11 . Vortexing (swirling action) of stock is 13. Pipe reducers or increasers used in
caused by not maintaining adequate sloped piping should be made of a non-
submergence above a discharge opening ; symmetrical conical section . Top sur-
for example : an elevated stuff box. The face (Figure 8) should be designed to
submerged height in feet (m) should be allow free movement of air and avoid air
equal to or greater than the numerical pockets . Bottom surface (Figure 9)
value of discharge velocity in feet per should allow good drainage when wash-
second (mps). See Figure 6. ing the pipe lines . Side slopes of pipe
increaser (Figure 8) should be limited
12. All lines entering chests, pits, or silos (1:16) where possible, to prevent flow
should be submerged and equipped with separation from side walls and the
a transition piece. Mazimum velocity formation of eddy currents . Otherwise
from the outlet of the transition piece slope should be determined by available
should be .5 fps to 2.5 fps (9 to 46 mpm) commercial sizes, but no more than 1 :3.
higher than the main flow channel velo-
city, to ensure good mizing, and prevent 14. Whenever possible, a minimum of 6 feet
"back flow" . If a valve is used, it should to 8 feet (1800 to 2400 mm) straight pipe
be located below the liquid level to pre- should preceed the inlet of the headbox
vent flow from cascading (water fall) . header.
See Figure 7. See Beloit manual "Cheek-
ing Piece Bleeds (with Skimmer Piping)" NOTE : See Beloit manual "Headbox Re-
J 006-10011 for variations in silo en- circulation System" (J 006-10001) for
trance lines for bleeds and skimmer header balance and recirculation in-
discharge piping. structions.
H2
HI (FT.)> VI (FPS)
HI (M)LbV, (MPS)
2030029504 ~
Figure 6 . DFscharge Opening
http://legacy.library.ucsf.edu/tid/nzr63e00/pdf
1 12
TOP VIEW OF
TRANSITION PIECE
rq
.. ..~ ~--s
VALVE- ~ •
,~l 12
t
TRANSITION 1/4
PIECE 12
e S = VALVE SUBMERGENCE
1/4
12
2030029505
Pa Ro " `7' .
http://legacy.library.ucsf.edu/tid/nzr63e00/pdf
5
16
TOP
ViEW
SIDE
VIEW
12
16
FLOW
TRANSITION
PIECE ~r--- 6 TO 8 FT. ~~
(1800 TO 2400 MM)
SECTION X-X
SHOWING PIPING ONLY
SECTION Y-Y
30
Figure 11 . Concentric Piping Arrangement (TYP. )
2030029507
7
http://legacy.library.ucsf.edu/tid/nzr63e00/pdf
0 One inch (25 mm) round bars welded in STUFF BOX
position shown to support piping .
The function of a stuff box (Figure 12) is
0 For general stock piping recommenda- two-fold : deareation of the heavy stock and
tions, refer to previous instructions in
this manual. to provide a constant head over the basis
weight valve .
® All concrete or support structures to be
determined by others . All piping mater- Stock flow velocities are as follows :
ial should be corrosion resistant.
A. 2 to 4 fps (36 to 72 mpm) heavy stock .
0 Increase pipe siae to compensate for
area lost because of concentric pipe . B . 1 fps (18 mpm) .
© Piping for heavy stock after basis weight C . 1 fps (18 mpm) maximum .
valve to be same size as valve . D . 1 .5 fps (27 mpm) maximum .
/X~*~ ------------------- r
~ .75" RAD .
15° Q _f (19 MM)
, SLOPE
~_ = ;;: ~__ == ~-__ r
~
SECT . "A-A"
12.
AX . BYPASS GATE
(304 MM) OPERATOR AIR
CYLINDER ..c, .
FROM 0.-ft.
.5" REFINER
(13 MM)
p
A
u a n ~ i
Pq~
t7
~
OVERFLOW OVERFLOW
& BYPASS & BYPASS
Figure 12. Stuff Box Flow Velocities and Design Principles
0 J© 02 9 50 8
8
http://legacy.library.ucsf.edu/tid/nzr63e00/pdf
Design notes: As indicated in Figure 14, these design
principles should be observed :
0 All interior surfaces in contact with
stock must be corrosion resistant . All
interior welds must pass cotton test . 0 The desired minimum retention time for
deaeration in the flow channel is 30
seconds from downspout to silo proper
0 Dimensions "a" and "b" sized for a maxi-
at velocity shown . This area to be kept
mum velocity of 1 foot per second (18
mpm) . horizontal.
follows:
® A continuous silo overflow of 100 gpm / ft.
(1240 lpm/m) of wire width is recom-
A. 1.25 to 1 .75 fps (23 to 32 mpm). mended to maintain a stable and foam
free liquid level at the fan pump suction .
B. 1.0to 1 .25 fps (18to23mpm) .
2030029509 9
http://legacy.library.ucsf.edu/tid/nzr63e00/pdf
MAXIMUM
LIQUID
/ 01
LEVEL
SECTION
Y-Y SAVEALL DOWNSPOUTS
, '
r=1 F9
~ 1DIRT TRAP
Y B
.
LIQUID
LEVEL
1
f-- B
--= 1 ~ COUCH PIT
(QESIGN
BY MILL)
SECTION
Z-Z
10 2030029510
http://legacy.library.ucsf.edu/tid/nzr63e00/pdf
® VANE ELBOW
~` ON SAVEALL PAN
(SEE FIGURE 15 FOR DETAILS)
SECTI ON
Y-Y
. o
~
4\Lrff Y 12 9~ ~y
4 , 0 ,, ,
®0
SECTION
Z-Z
11
http://legacy.library.ucsf.edu/tid/nzr63e00/pdf
(635 mm), use 4 vanes .
VANED ELBOW
In high speed applications, a vaned elbow 0 Size opening for velocity of 1 .25 to 1.75
fps (23 to 32 mpm) . Use flow from stock
with or without air evacuation may be re- piping data .
quired on the saveall pans of the forming
6 Multiply 0 x .7
unit. Suggested design arrangement is shown
in Figure 15 with the following design notes : 0 This dimension is © divided equally .
Refer to ®
0 Channel width, determined by flow re-
quirements, should match saveall ® Angle to be determined by space avail-
downspout outlet. able . Thirty degree is recommended .
0 Channel height, determined by flow re- 0 Air evacuation outlet (if required) .
quirements, should be approximately
twice calculated liquid depth . 110 It is recommended that a covered open-
ing is provided on side of elbow for
0 To findMmultiply[2]z .7 clean-out purposes.
ii Material thickness and size to be deter-
® This dimension is 3 divided equally. If
E3 is less %q n 25 inches (63S mm), use mined by structural requirements . All
3 vanes. 3 Is greater than 25 inches material to be corrosion resistant
L° 0
http://legacy.library.ucsf.edu/tid/nzr63e00/pdf
FAN PUMP SELECTION The nature of centrifugal pumps makes
some vibration and pulsation inevitable but
Type of Fan Pump pump attributes which increase the frequency
Beloit's best recommendation for the type and decrease the amplitude of predominant
of secondary fan pump (the pump feeding the disturbances are highly desirable . In fact .
headbox) is a variable speed . centrifugal once per impeller revolution pressure vibra-
pump. Variable speed pumps are more adapt- tion cycles have been found to be most detri-
able to changing flow rates than constant mental to the paper making process . Since
speed pump-Stream Flow Valve combinations ; the secondary fan pump is closest to the
and, therefore, we feel variable speed drives headboa. it is essential that this pump per-
provide a more stable flow to the headbox over form as smoothly as possible . Items which
a range of flow rates . Variable speed pumps enhance pump performance are as follows :
adapt readily to automatic spouting velocity
controls and provide for gradual start-up to 1. Pumps should be selected for a mazi-
eliminate shock loading of equipment. These mum impeller rpm .
pumps should always be equipped with the
most precise speed controls available.
2 . The impeller should have a mazimum
Primary fan pumps being located farther number of vanes .
down the piping from the paper machine wet
end aren't quite as crucial to the proper per- 3. The impeller vanes should be split,
formance of the headboz, but they should be staggered, and skewed if a double suc-
selected to perform as efficiently as possible tion pump is selected .
in order that they cause minimum pulsations
and piping vibrations . The choice of constant 4 The impeller must be properly balanced
speed or variable speed drive should be made and obviously must not operate near
on the basis of the anticipated pump flow critical speeds . The impeller must be
2030029513 13
http://legacy.library.ucsf.edu/tid/nzr63e00/pdf
Taps should be located at least one pipe
PULSATION STUDY diameter away from any elbows, pumps,
A complete pulsation study is usually screens, valves or other pipe line obstruc- ,
necessary to identify system stability for a tions if possible .
specific piping arrangement. From t,his study Pump speeds and screen speeds will need
a better determination of potential problems to be lmown during the study .
can be made.
The number of vanes on the pump impel-
The more accurate and precise the infor- lers and the number of foils on screen rotors
mation furnished, the more accurate the will also be needed .
pulsation study will be. Typical measure-
The following taps (Figures 16 and 17)
ment locations are:
do not allow air to collect at tap locations
1. Before pump 6. After screens and provide an unobstructed "view" into the
2 After pump T. Before stream flow valve pipe. Do not locate taps on elbows . Allow
3 . Before cleaners 8. After stream flow vavle 12-18 inches (300 to 450 mm) of clearance
4 After cleaners 9 Before headboz beyond the end of ball valve for transducer
5. Before screens 10 . Aiter headbox installation.
Two locations may be measured from one tap :
After cleaners and before screens . '
BELOIT PRESSURE TAP
Pipe taps should be made according to
(P/N 2AY29461)
Beloit recommendation. Any other points of
interest can also be measured if desired .
A schematic of your stock approach sys-
tem should be sent to Beloit to be marked
where suggested taps should be located .
BELOIT PRESSURE
TAP (P/N 2AY29461)
14 2430029514
http://legacy.library.ucsf.edu/tid/nzr63e00/pdf
i
2030029515
15
http://legacy.library.ucsf.edu/tid/nzr63e00/pdf