Professional Documents
Culture Documents
ABSTRACT: Information on rock mass deformation in large cavern excavations can be obtained by means of
combined repeated geodetic observations and modelling of expected deformations with numerical techniques.
Knowledge of the expected and the observed deformations of rock mass are important for reliable monitoring of
the influence of sequence of bench excavation on the surrounding rock mass. Back analysis of geotechnical
monitoring (displacements of controlled points) and numerical models of expected rock mass deformations
performed through FEM was carried out and the displacement plots of a monitoring array stations that consist of
extensometer installed downwards from a water curtain tunnel above the cavern is compared with the results of
numerical modelling. The paper discusses the geological & geotechnical conditions, results of FEM analysis and
displacement from geotechnical monitoring and the effect of successive bench excavation on the geo-mechanical
situation during excavation. The numerical modelling results were in reasonable agreement with measured
displacements which confirm the numerical modelling correctness and back analysis results. The paper also
discusses that the back analysis combined with numerical modelling and geodetic measurements can be used to
improve deformation models developed for large cavern excavation.
Key words: Back Analysis; Rock Cavern; Geotechnical Monitoring; FEM Analysis; Geological Condition.
1 INTRODUCTION
Back numerical analyses combined with geotechnical measurements provide for a safer and a more rational
approach to designing and execution of underground structures. Such analyses contribute to the development of
knowledge on rock mass behaviour and could help to verify or to modify requirements of the primary support
system. Displacements of rock masses induced by excavation can be measured to a larger extent using different
set of equipments. Therefore extensive studies have been conducted to develop different models of
displacement-based back analysis (Sakurai and Takeuchi, 1983; Swoboda et al., 1999; Sakurai, 2003).
The main purpose of this study is to use numerical analysis approach in order to evaluate the influence of
sequence of bench excavation on the surrounding rock mass and compare them with the displacement observed
through geotechnical monitoring. The instruments used for the displacement monitoring are multipoint grouted
borehole extensometers. Rock mass parameters selected for the design of cavern have been based on laboratory
tests and conventional rock mass classification methods.
2 PROJECT DESCRIPTION
2.1 Project outline
The rock cavern taken for the present case study is being used as a strategic crude oil storage project under
construction in west coast of India near Mangalore. The projects consist of caverns generally of U-shaped in
plan, D shape in cross section and are kept parallel to each other. Orientation (trend) of the underground cavern
is kept at N60°E. The underground facilities; figure 1, essentially consist of access tunnel, main cavern (30 m
height, 20m width and about 700m length) and water curtain tunnels running parallel to and 20m above each U
shaped cavern with a series of water curtain boreholes drilled perpendicular to it. The cavern gallery roof is
seated at about 60m below the ground surface with each leg having a separation distance of 30m between them.
The project consists of two U shaped caverns placed at an inter distance of about 100m.
Water curtain tunnel, which is excavated before the cavern excavation, also acts as a pilot tunnel exposing
the actual geology to be encountered during cavern excavation.
Excavation of the cavern is carried out in five stages i.e. top gallery with pilot and side slash excavation and
three benches each of about 7-8m in height.
The basic design needs to be checked, validated, updated and modified based on the actual geological,
geotechnical and hydro-geological conditions encountered during excavation, especially in areas where stability
could be critical, Nanda (2012).
2.5 Monitoring system
Stability of cavern is also being ascertained from the displacement behaviour obtained from extensive
geotechnical monitoring scheme. Monitoring array stations within the caverns are typically arranged at every
25m interval with five optical targets being placed within the top heading and two targets on either side in each
bench of excavation. In addition, some extensometers at geologically critical areas are installed in the drilled
boreholes downwards from the water curtain tunnel located above the cavern. These extensometer are a
multipoint instrument anchored at 3 points i.e. at 10m 15m and 20m measured from the top as shown in the
figure 3. These extensometers are placed into the rock mass area above the cavern crown and haunches in order
to monitor rock mass behaviour during the initial stages of cavern excavation.
3 BACK ANALYSIS
3.1 Section Description
Location of the monitoring section taken for the analysis is placed at about 25m from the end of cavern
PUA11 & PUA12 in the eastern side. The rock type is dominantly light to dark gray, fine to coarse grained
granitic gneiss with minor basic intrusion, intersected by shears; fresh to slightly weathered; strong to weak. The
rock mass is characterized by prominent two plus random to three plus random joint sets, which are rough (or
irregular) and planar to undulating with unaltered joint walls to softening clay mineral fillings. In general, the
rock mass is characterized by dry/damp to dripping ground water conditions. Based on the rating of importance
of rock mass quality parameters, the rock mass quality ranges from fair to poor. A minimum rock support of rock
support type III is recommended to achieve the required factor of safety with respect to wedge formations with
the realistic shape.
3.2 Numerical Modelling
The numerical modelling of the cavern was performed through finite element code Phase2.0 to analyze the
rock mass behaviour due to progressive excavation and rock support installation. The rock mass are assigned
properties obeying the linear-elastic perfectly plastic law where Generalized Hoek-Brown strength criterion is
considered. The rock mass is simulated by a fully deformable isotropic constitutive model. In order to use two-
dimensional numerical tools to realistically design, the methodology used for the analysis is based on the
softening behaviour of material with excavation. The three dimensional stress distributions at the face of a tunnel
can be interpreted in terms of material softening by reducing the deformation modulus of the excavated material,
John H. Curran, et all (2003). In the present study, deformation modulus was reduced up to 30%.
The excavation of the caverns is simulated by subdivision into an appropriate number of excavation steps:
a. Generation of initial stresses by gravity loading
b. Material softening stage of the material to be excavated within the tunnel
c. Excavation stage in which the excavation is simulated by deletion of excavated block from the model
d. Rock support installation as per the actual Rock Support Recommendation Sheet (RSRS) in the form of the
shotcrete and rock bolts
4 RESULTS & DISCUSSION
4.1 Monitoring Results
Figure 4 shows monitoring section of extensometer towards northern side showing displacement against the
actual chronological sequence of excavation i.e. pilot tunnel, side slash, bench excavation of each cavern. The
maximum deformation observed in extensometer is about 5mm. The monitoring data are evaluated and
compared with the given trigger values as per design. The monitoring data in vertical direction along the cavern
section are all in limits and are showing stable conditions. It could also be observed that the fluctuation in the
deformation diminishes after the first bench of excavation which substantiate that the vertical movement reduces
in the upper portion of cavern with the further advancement to subsequent benches. Therefore, the displacement
results up to bench 1 have only been taken for analysis and discussion.
4.2 Discussion
Figure 5* illustrates the comparison between displacement observed form field measurement by
extensometer and displacement obtained from numerical analysis.
The plot in figure 5(a) shows the displacement towards northern side i.e. cavern PUA11, the maximum
displacement observed from the field measurement is about 4.3mm & observed from numerical analysis is about
5.3mm. While the displacement towards southern side i.e. PUA1, figure 5(b), the maximum displacement from
the field measurement is 2.5mm & observed from numerical analysis is about 1.5mm.
It is to be noted that the rock mass towards the cavern PUA11 observed during excavation was of poor type
and the rock mass towards the PUA12 was of fair type. The results show that the prevailing rock mass condition
on both sides and their rock mass properties have the maximum impact on the difference in measured
displacement both from the field measurement as well as numerical analysis.
The figure also shows that the computed values from numerical analysis are in a reasonable agreement with
measured values on both plots.
Fig. 5(a) Comparison of Displacement Observed From Field Measurement Towards North & From Numerical Analysis
Fig. 5(b) Comparison of Displacement Observed From Field Measurement Towards South & From Numerical Analysis
INDOROCK 2014: Fifth Indian Rock Conference 12-14 November 2014
5.0 CONCLUSION
Following conclusions can be drawn from the present study to develop best practice to tackle the enormous
uncertainties involved in construction of underground large cavern.
Back analysis is a practical engineering tool to evaluate geotechnical condition of underground structures
based on field measurements of displacements. These measured displacements behaviour obtained from the
geotechnical monitoring scheme are necessary parameter for the stability analysis of geostructures.
Back analysis of large rock cavern used for the strategic crude oil storage project using finite element
method was carried out in the computer codes Phase 2. Initial values of input parameters required in the
models were based on results of geological and geotechnical investigations and estimated by empirical
methods.
The qualitative trend of the displacements observed in cavern should be the same in the calculation as in
reality, as a confirmation of the validity of the calculation model and of the simplified assumed hypotheses.
The results of numerical modelling are in good agreement with measured displacements which confirm the
numerical modelling correctness and back analysis results.
The studies also indicated that cavern displacement is strongly dependent on the rock mass condition and
associated rock mass properties.
ACKNOWLEDGEMENTS
The authors would like to express the appreciation and thanks to the management of Engineers Indian Limited
for granting their permission to publish the paper and JP University for their contribution to this research.
REFERENCES
Barton N., Lien R. and Lunde J. (1974), “Engineering classification of rock masses for the design of tunnel
support, Rock Mechanics”, Vol.6, no. 4, pp. 189-236.
John H. Curran, Reginald E. Hammah, Thamer E. Yacoub (2003), A two dimensional approach for designing
tunnel support in weak roc, Canadian Geotechnical Conference.
Mandal A., C. P. Chakravarthy, R. Rath, A. Nanda and A. Usmani (2011), “Analysis and Design Approach of
Large Storage Caverns”, (In Press), Int. Journal of Geomechanics, ASCE. doi:10.1061/(ASCE)GM.1943-
5622.0000180.
Nanda A., Design and construction of storage caverns, Proceedings of Indian Geotechnical conference, Dec.13-
15, 2012, Delhi.
Sakurai, S., Takeuchi, K., 1983. Back analysis of measured displacements of tunnels.Rock Mechanics and Rock
Engineering 16 (3), 173–180.
Swoboda, G., Ichikawa, Y., Dong, Q.X., Zaki, M., 1999. Back analysis of large geotechnical models.
International Journal for Numerical and Analytical Methods in Geomechanics 23, 1455–1472. Tablieh
Constraction Co.
Sakurai, S., 2003. Back analysis for tunnel engineering as a modern observational method. Tunnelling and
Underground Space Technology 185, 196.