Professional Documents
Culture Documents
ABSTRACT: Design of cavern during the basic engineering design (BED) was carried out by collating the
inputs from geotechnical investigation and surface mapping performed during the initial site investigation stage.
However, during excavation, geological hotspots or locations of particular geotechnical interest are identified
along the cavern alignment based on the geological information obtained from the excavation of cavern at
various stages, including core drilling and deformation of excavation surface measured from monitoring targets.
One of the geological hotspot, which consists of mafic dyke intruded in the parent rock, is discussed here.
Stability of cavern is further re-checked at this location owing to an assessment of geotechnical features
encountered. The paper outlines the design aspects of underground rock caverns based on updated structural
geological maps, staged excavation, & verification by monitoring.
1 INTRODUCTION
1.1 Project Description
Rock cavern taken for the analysis are generically of U-shaped in Plan & D shape in cross section and are
kept parallel to each other. Orientation (trend) of the underground cavern is kept at N60°E. The underground
facilities; See Figure 1, essentially consist of access tunnel, main cavern (30 m height, 20m width and about
700m length) and water curtain tunnels running parallel to and 20m above each U shaped cavern with a series of
water curtain boreholes drilled perpendicular to it. The cavern gallery roof is seated at about 60m below the
ground surface with each leg having a separation distance of 30m between them. The project consists of two U
shaped caverns placed at an inter distance of about 100m.
Water curtain tunnel, which is excavated before the cavern excavation, also acts as a pilot tunnel exposing
the actual geology to be encountered during cavern excavation. The excavation of cavern is carried out in four
stages i.e. top gallery and three benches each of about 7-8m in height.
All the major discontinuities along with different types of dykes etc encountered in the project area are
shown in Figure 2.
Details of the structural discontinuities within the rock mass as determined from site investigation mapping
reveals three major discontinuities (sub-vertical) and one sub-horizontal as shown in table 1. The sub-vertical
discontinuities are persistent and oriented in almost north-south and east-west direction with a dip of about 80-85
degrees both sides. Sub-horizontal joints are oriented East to N60°E and dipping about 5 - 15 degrees both ways.
Results from the wedge analyses shows that rock bolt in combination with shotcrete is essential in increasing
the factor of safety to an acceptable level. The maximum apex height of wedge formed at crown is about 4.0 m.
Therefore, minimum length of recommended rock bolt is 5.0 m i.e. at least 1 m more than the maximum wedge
apex height.
INDOROCK 2013: Fourth Indian Rock Conference 29 – 31 May 2013
Results of the FEM analysis shows that no global failure occurs even in the case of poor and very poor rock
mass condition. The proposed rock support was found to be adequate and sufficient. Summary of recommended
rock support for the cavern are given in Table 2.
Out of those identified critical locations, analysis of one geological hotspot stretched in a span of about 50m,
and is marked in circle, is discussed here. The dyke TD1 that is intruded in the parent rock is thin i.e. about 1m
and highly permeable. Their contact is slightly weathered with occurrence of 5 -10 mm soft gouge material.
These dykes are fresh & hard and moderately fractured. The dyke was found to be highly persistent and this was
accounted for in the analysis.
INDOROCK 2013: Fourth Indian Rock Conference 29 – 31 May 2013
Table 5 Results of Unwedge analysis & size of critical wedge formed on north wall
Wedge Information Joint Combination
J1,J2 & J3 J1,J3 & J5 J3,J4 & J5
FOS without support stable 0.8 0.8
Wedge volume (m3) 0.33 12.537 67.44
Wedge weight (MN) 0.009 0.35 1.88
Apex Height (m) 0.5 2.85 4.5
Excavation face area (m2) 2.82 13.87 44.95
Min. Rock support type As per Q system Class-II Class-III
INDOROCK 2013: Fourth Indian Rock Conference 29 – 31 May 2013
Table 6 Results of Unwedge analysis & size of critical wedge formed on south wall
Wedge Information Joint Combination
J1,J3 & J4 J1,J2& J3 J1,J2 & J4
FOS without support 0.8 No wedge is formed stable
3
Wedge volume (m ) 24.94 - 13.36
Wedge weight (MN) 0.70 - 0.37
Apex Height (m) 4.67 - 2.09
2
Excavation face area (m ) 16.0 - 19.16
Min. Rock support type Class-II As per Q-System As per Q-System
Results of the analysis in north wall indicate that a large wedge ; see Figure 4 (a), of about 4.5 m height,
weight of about 1.88 MN and wedge volume of about 67.44 m3 is formed with joint set combinations ( J3,J4 &
J5).Here persistence of mafic dyke TD1 has a considerable role in the formation of wedge size. Apex height of
wedge varies from 3.5 m to 4.5 m when the persistence of TD1 varies from 10m to 12.5m. In the present case,
when the persistence of other joint set is limited to 10m, maximum apex height of wedge formed is restricted to
4.5m even after the persistence of TD1 extent larger than 12.5m. Based on above, a minimum rock support of
rock support type Class III i.e. rock bolt 5m @ 2.0m c/c and 75 mm shotcrete is recommended. For joint set
combinations (J1, J3 & J5), a minimum rock support of rock support type Class II is required. For all other joint
set combination, minimum rock support as per Q system is adequate.
Results of the analysis in south wall indicate that in general a minimum rock support as per Q-system is
adequate except for a joint set combinations (J1, J3 & J4), wherein a minimum rock support type class-II i.e.
rock bolt of 5m @ 2.5m c/c and 50 mm shotcrete is required. Apex height of formed wedge is about 4.6m ; see
Figure 4 (b), however, the wedge volume and weight are less as compared to the wedge formed in north wall.
Persistence of TD1 has no considerable role in wedge height and it is restricted with the overall persistence of
other joint set of 10m.
Based on the results, it was therefore recommended that before taking up next bench excavation, an
additional rock support to be install in the present bench (if required) in the given segment subject to the given
joint set combination as shown in table 5 & 6.
Fig. 4(a) Wedges formed on north wall Fig. 4(b) Wedges formed on south wall
Fig. 4 Critical wedges formed
3.4 Geotechnical Monitoring
Monitoring array stations within the caverns are typically arranged at every 25m interval with five optical
targets being placed within the top heading and two targets on either side in each bench of excavation. In
addition, some extensometers at geologically critical areas are installed in the drilled boreholes of water curtain
tunnel located above the cavern. These extensometers are anchored at 3 points to measure vertical displacement
of each point.
INDOROCK 2013: Fourth Indian Rock Conference 29 – 31 May 2013
At one of the monitoring array station falling in the present geological hotspot segment, displacement
recorded at pilot and side slashing was about 6-8mm, which was greater than or equal to trigger value in top
heading. The trigger value is set at 80% of the estimated design displacement. However, the displacement plot
shows stabilizing trend and seems stable. It was further advised to monitor the present array station once every
day before taking up any further excavation. It was also recommended to inspect physically at this location for
any distress in rock mass in terms of cracks in the shotcrete and increase in seepage etc. Displacements recorded
on both the north & sidewall were limited to 3-4mm and showed stable condition.
Result from the extensometer shows a deformation of about 3-4mm at crown, which stipulate a stable
condition as there is no significant deformation/movement of the rock mass observed at the crown region.
Stability of cavern was further ascertained from the monitoring results after bench-2 excavation, which
shows stable condition with the above installed support.
4 CONCLUSIONS
Following conclusions can be drawn from the present study to develop best practice to tackle the enormous
uncertainties involved in construction of underground large cavern.
Stability of large rock cavern excavation should be ensured by an observation approach i.e. the original design
assumptions are to be updated by means of the results from monitoring during construction, to allow for an
optimized design and not to be limited to a one off design exercise, which is performed at the basic design stage.
In the cavern, which is discussed in this paper, some geological hotspot or locations of particular geotechnical
interest are identified along the cavern alignment based on the updated geological information collated from the
excavation at various stages. Quality of rock mass and major geological features at specific location has been
derived from core drill log performed from water curtain galleries just above the main cavern as well as joint
information collated from heading and first bench excavation in the sidewall of cavern. With respect to the
updated geotechnical information, cavern design is re-checked by performing a block analysis using the program
Unwedge. A minimum rock support based on the class type is recommended for both walls. Stability of cavern is
also being ascertained from the displacement behaviour obtained from geotechnical monitoring scheme. Here,
the displacement plot both from optical targets and from extensometer shows stabilizing trend, however, regular
monitoring of displacement behaviour has been suggested in the specific geological hotspot area.
REFERENCES
Barton N., Lien R. and Lunde J. (1974), “Engineering classification of rock masses for the design of tunnel
support, Rock Mechanics”, Vol.6, no. 4, pp. 189-236.
Mandal A., C. P. Chakravarthy, R. Rath, A. Nanda and A. Usmani (2011), “Analysis and Design Approach of
Large Storage Caverns”, (In Press), Int. Journal of Geomechanics, ASCE. doi:10.1061/(ASCE)GM.1943-
5622.0000180
Nanda A., Design and construction of storage caverns, Proceedings of Indian Geotechnical conference, Dec.13-
15, 2012, Delhi.