Professional Documents
Culture Documents
Pack
Published by Team of SAP
Consultants at SAPTOPJOBS
Visit us at www.sap-topjobs.com
Copyright 2007-09@SAPTOPJOBS
3. PM ORGANIZATION STRUCTURE..........................................................9
4. TECHNICAL OBJECTS........................................................................12
6. EQUIPMENT ..........................................................................................40
8. MEASURING POINT.............................................................................67
8.3 Define Field selection for Measuring points and Measuring Documents...... 72
9. PERMITS................................................................................................76
Vish
2. Getting into the Configuration area of SAP
BACKGROUND
SCENARIO
It is required to configure various settings in SAP.
INSTRUCTIONS
To do configuration, first one has to logon to the system, and
go to the IMG mode. How to logon to IMG mode is explained
below. From next document onwards, it is mentioned as IMG.
2. Click
3. Click on
Note: - Plant Maintenance related configurations are
available under Node.
4. Click
Planning Plant: -
If this is not the case and the entire planning is carried out in
respective plants, then each plant will also be planning plant.
Maintenance Plant:-
BACKGROUND
SCENARIO
INSTRUCTION
Click
Click
Click
Click
3.2 Assign Planning Plant
BACKGROUND
SCENARIO
INSTRUCTION
Click
Click
Click
4. Technical Objects
¾ Functional location
¾ Equipment
BACKGROUND
SCENARIO
INSTRUCTION
Click
Click to create new technical object type
Click
Click
4.2 Define Plant Sections
BACKGROUND
SCENARIO
INSTRUCTION
Click
Click
Click
Click
4.3 Define Planner Group
BACKGROUND
SCENARIO
INSTRUCTION
Click
Click
Click
Click
4.4 Define Technical object view profile
BACKGROUND
SCENARIO
INSTRUCTION
Click
Click
Click
Click
Maintain icon
Click
Click
BACKGROUND
SCENARIO
INSTRUCTIONS
Click
Click
Click
BACKGROUND
SCENARIO
INSTRUCTIONS
Click
Click to create new entries.
Allowed letters and signs are given below for ready reference.
- Hyphen
/ slash
' ' blank
. Period
_ Underscore
= equals sign
+ Plus sign
; Semicolon
: Colon
*** - Hierarchy level indicates the number of hierarchy. Each
number must be entered at the end of first level as shown
above. Numbers from 0 to 9 can be used for this. Level 10 is
represented by the figure 0, level 11 by the figure 1, and so on.
Click
Click
BACKGROUND
SCENARIO
INSTRUCTIONS
Click
Click
Click
BACKGROUND
SCENARIO
INSTRUCTIONS
Click
Double click
Click on
Click
Click
Impact of this configuration in Master Data /
Transaction
9 Year of construction
9 Warranty period
9 Usage
9 Maintenance task to be performed
9 Record of maintenance task performed. (gauge
calibration)
9 Technical data to be analyzed
Any items, which can not be repaired due to its low cost and
that can be replaced should be defined as material assembly.
Note:-
Equipment number cannot be changed once it is created.
Functional Location:-
BACKGROUND
9 Screen sequence
9 Number range assignment
9 Usage history
9 Option to install at functional location
SCENARIO
INSTRUCTIONS
Click
Method 1:
9 Define BOM and Task list for the material.
9 Assign this material to technical objects.
9 This will avoid defining BOM & Task list these separately
for each technical object
Method 2:
9 When replacing equipment in the functional location,
right equipment can be determined with a particular
material number in its master record.
Click
Click
BACKGROUND
SCENARIO
INSTRUCTIONS
Click
Click
Click
BACKGROUND
SCENARIO
INSTRUCTIONS
Click
Click
Click
Click
Click
Click
BACKGROUND
SCENARIO
INSTRUCTIONS
Click
Tick the check box in column.
Click
Click
6.5 Define Installation at functional Location
BACKGROUND
SCENARIO
INSTRUCTIONS
Click
Tick the check box if the equipment is to be
installed at functional location.
Click
Click
6.6 Assign user status to equipment category
BACKGROUND
SCENARIO
INSTRUCTIONS
Click
Click
6.7 Define field selection for equipment master record
BACKGROUND
SCENARIO
INSTRUCTIONS
Click
Double click
BACKGROUND
SCENARIO
INSTRUCTIONS
Click
Double click
Click
Click
Click
9 Legal requirements
9 Critical values for environmental protection
9 Critical values for health and safety
9 Preventive maintenance
9 To reduce breakdown maintenance
BACKGROUND
SCENARIO
INSTRUCTIONS
Click
Click
Maintain fields as explained below
Field Name Value and Description of field
Key identifying the measuring
point category. E.g. G
Description of measuring point
category. E.g. IND6 measuring
point category
Uniqueness of the measurement
position of this measuring point
category. This measurement
category may be used in many
places, if the measurement
position is required to be unique,
it can be achieved thro this
setting.
Select.1 from available entries
Click
Click
Impact of this configuration in Master Data /
Transaction
BACKGROUND
SCENARIO
INSTRUCTIONS
BACKGROUND
SCENARIO
INSTRUCTIONS
Click
Click Page down
Double click on
Click on
Click
Click
Click
BACKGROUND
SCENARIO
INSTRUCTIONS
Click
Click
Click
Click
BACKGROUND
SCENARIO
INSTRUCTIONS
Follow the Menu Path: IMGÆPlant maintenance and
customer serviceÆ Master Data in Plant maintenance and
customer service Æ Basic settings Æ Permits Æ Define permit
groups
Click
Click
Click
Warranties