Professional Documents
Culture Documents
ABSTRACT
This paper describes the design of an SABC grinding circuit using CEET technology applied to grindability data
produced from testing 100 samples and distributed across the blocks of a mine plan using a geostatistical
approach. The data distribution required the identification of the location of the sample points and a geological
plan of the 130 million ton Ruby Creek orebody together with a mine plan of about 11000 blocks to be mined
during the proposed 18 year life of the mine. The mill design was then made with consideration for the estimated
hardness of each block in terms of both SAG and Ball milling with allowance for annual periods when the ore is
harder to grind. Operating specifications were selected to achieve an optimum of capital and operating costs
through use of the CEET program. The geostatistics assigned the statistical error that arises from having a limited
amount of sample testing data to the hardness estimate of each block of ore in the mine plan. The final design
could then include a quantification of risk and determination of safety factors based on the accuracy of block
hardness estimates and CEET model fitting.
INTRODUCTION This paper outlines a design procedure index, BWi (for ball mill grinding). A
suited to an orebody that is described by further measure, the Minnovex crusher
a geostatistical analysis of a reasonably index, Ci was also measured for use in
The traditional approach to plant design
large number of small samples of the CEET program to determine SAG
involves the extensive testing of a single
drill core. The analysis required the mill feed size (Kosick and Bennett, 2001).
large composite sample or a small
identification of the location of the The SPI values varied from 13.5 to 107
number of composite samples that
sample points and a geological plan of minutes with an average of 53 minutes.
are reputed to represent the ore body.
the orebody, together with a mine plan This variability, although apparently very
It is accepted that the tests used can
of the blocks to be mined during the high, is less than normal compared with
accurately measure in the laboratory the
proposed life of the mine. The mill design sample sets from other orebodies; COV
grindability of the sample by a process
was then made using the estimated (i.e. standard deviation divided by mean
representing that to be used in the
hardness of each individual block with an value) is about 30% compared with a
plant. The size of equipment required
allowance for annual fluctuations in the typical 40%. The BWi varied from 10.0
to achieve a specified throughput and
grindability of the ore. The geostatistical to 15.3 kWh/t with an average of 12.5
product size is then calculated from one
analysis assigned a statistical error to kWh/t. The variability is a little less than
of a variety of models that have been
the hardness estimates of blocks and of usual with COV at 10%. The lack of
developed by metallurgists over years
each production year such that the final correlation of BWi with SPI in this set
of trial and error. Since these tests and
design included risk estimates and safety of samples is very unusual, as shown in
models are tried and tested, they are
factors based on the possible errors that Figure 1. Normally BWi and SPI increase
accepted as reasonably precise; however
arise from having a limited amount of together with a correlation coefficient of
during the operation of the resulting
sample data (Kosick et al. 2002). about 0.5. However, in this case there is
plant the design is sometimes found
a small trend to higher BWi with lower
to be inadequate. It is then suspected
that the flaw in the design process lies
ORE BODY SPECIFICATION SPI; the ore can be relatively soft at
4036
5100
1003
5765
9801
0.04
6.36
10.3
Grates from 50 to 75mm and screens
906
210
974
115
3.9
75
25
69
8
from 13 to 25mm were investigated
during this study.
4469
4092
5676
9768
3.99
0.05
6.26
10.3
977
906
998
127
210
75
22
79
A pebble crusher is included in the SAG
9
circuit with the crushed product size of
80% passing 16mm.
10.31
3844
5562
9734
4172
0.07
6.14
979
906
994
139
210
4.1
75
92
19
10
Since CEET is an economic evaluation
tool and not just a mill sizing calculator,
10.32
4300
5407
9707
3213
4.25
5.97
209
981
906
990
153
106
the various site specific operating
0.1
75
16
12
costs were included as part of the
input. Electrical energy cost was of
10.31
4578
9698
5186
4512
particular concern in this project. Capital
4.47
5.72
0.12
209
981
906
989
123
169
75
13
14
equipment costs are estimated using
CEET default values and updated in the
software as necessary.
10.31
4967
5728
9888
4160
1011
3.96
0.03
6.32
972
906
211
60
25
60
97
7
DESIGN FOR COMPLETE ORE BODY
The results of CEET runs comparing
10.32
4335
4230
5632
9862
1007
4.06
0.04
6.22
973
906
107
211
22
69
8
and screen apertures are shown in Table
2. The CEET program maintains the
10.32
4321
9832
3714
1003
5511
0.06
6.08
4.18
average tph at the specified level of 906 975
906
210
118
60
81
19
9
and the average P80 at 210 microns at all
apertures. The major effect of increasing
10.32
the screen aperture is a change in the
3094
4459
5350
9809
4.34
0.08
999
977
906
132
210
5.9
60
94
16
10
SAG to Ball mill transfer size, T80, from
about 2.5 to 5 mm, resulting in a move
in maximum demand for power for SAG
10.32
4682
9805
5123
2474
4.57
5.65
998
978
906
147
210
110
0.1
milling to that for Ball milling as
60
13
12
10.32
4859
4261
9962
5701
1012
0.02
6.29
4.01
906
211
50
25
52
85
Table 2: Effect on energy requirements and equipment sizes of changes to SAG grate and screen apertures
4341
9942
1012
0.04
6.18
4.12
972
906
211
50
22
61
94
4445
9919
1009
5474
4.25
0.05
6.04
906
104
211
974
72
19
4594
5306
1006
4.42
0.07
5.86
906
211
116
50
85
16
4828
9902
1005
4.65
0.09
906
131
100
976
211
5.6
50
13
11
microns
mm
mm
Screen aperture
CL/PCCL (%)
kWh/t Total
kWh/tCrusher
kWh/tSAG
kWh/tBM
t/hCircuit
kWBM
lWSAG
t/hSAG
t/hBM
P80
T80
SGS MINERALS SERVICES TECHNICAL BULLETIN 2007-01 5
After adjusting SAG screen sizes each year, as above, the minimum average annual
tph can be maintained within 2% of the 906 specified, with P80 between 204 and 210
microns every year, as shown in Figure 9.
The geostatistical analysis assigned a precision (or statistical error) to the hardness
estimate for each block of ore and each production year in the mine plan. The expected
average hardness for each production year (in terms of SPI, Ci and BWi) is listed in
Table 3 together with the statistical standard error for each average. There is 95%
confidence that the true average lies within twice the standard error of the expected
(best estimate) average, e.g. in Year 1 the average SPI should be between 36.9 and
55.5. This range of uncertainty could be reduced by testing more drill core samples that
lie within or close to the blocks that will be mined in that year.
SGS MINERALS SERVICES TECHNICAL BULLETIN 2007-01 8
Preece, R., “Use of point samples to estimate spatial distribution of hardness in the
Escondida Porphyry copper deposit, Chile”; SAG 2006, Vancouver, British Columbia