You are on page 1of 13

A rticle

A “Construction Industry Payment


And Adjudication Act”:
Reducing Payment-Default and
Increasing Dispute Resolution Efficiency
in Construction
By Sr Noushad Ali Naseem Ameer Ali, President, The Institution of Surveyors Malaysia & Chair – Construction Industry
Working Group On Payment (WG 10). He can be contacted at e-mail: naseem@pd.jaring.my

This paper is in two parts. Part I covers various issues relating to payment in the Malaysian construction
industry, the proposed ‘Construction Industry Payment and Adjudication Act’ and some details on construction
adjudication as a speedy, economical, contemporaneous, and binding dispute resolution mechanism. Part II is
in a question and answer format covering nearly 50 questions that attempts to provide responses to many
questions that may remain in various related areas.

PART I

Introduction & Background projected estimated figures run into Since then there are now similar Acts in
billions of Ringgit. Australia, New Zealand and Singapore.
Payment Default In The Malaysian These include:
Construction Industry Master Builders Association Malaysia
(MBAM) has also long been lamenting on ● Building and Construction Industry
Payment has been said to be the life- the problems of delayed and non- Security of Payment Act 1999
blood of the construction industry. Yet payment in the construction industry. amended in 2002 (New South Wales,
the industry knows payment default, And MBAM too has been carrying out Australia)
specifically delayed and non-payment, surveys on payment issues. The surveys ● Building and Construction Industry
remain a major problem. A recent only confirm the harsh reality – payment Security of Payment Act 2002
survey done by the Construction default is a major problem in the (Victoria, Australia)
Industry Development Board (CIDB) in construction industry. Only the extent ● Construction Contracts Act 2002
collaboration with University Malaya varies with each survey. (New Zealand)
(UM) ‘merely’ formally documents what ● Building and Construction Industry
many in the construction industry Experience Of Other Countries Payments Act 2004 (Queensland,
already know - there is a chronic Australia)
problem of delayed and non-payment One of the moves in the UK construction ● Construction Contracts Act 2004
in the Malaysian construction industry industry following Sir Michael Latham’s (Western Australia)
affecting the entire delivery chain. What 1994 report ‘Constructing the Team’ ● Construction Contracts (Security of
the survey does do is to provide generally known as the Latham Report, Payment) Act 2004 (Northern
empirical evidence. It also extends the was the drafting of the Housing Grants, Territory, Australia)
findings to project estimates of delayed Construction and Regeneration Act 1996 ● Building and Construction Industry
and non-payment amounts based on (UK Act). Part of the Act deals with a Security of Payment Act 2004
feedback from a sample of industry scheme for payment and the resolution (Singapore)
players providing information on of construction disputes through a
payment problems between 2000 and contemporaneous, speedy and Some of these countries learnt the
early 2006. The projected amounts are economical dispute resolution method consequences of payment default
staggering. Putting it mildly the called adjudication. the hard ways – slow and sudden

01

3 r d Q u a r t e r 2 0 0 6
A rticle

insolvencies, and minor and major Payment And The Cash Flow
insolvencies. Some of these countries Construction Industry
scrambled to get statutory provisions Cash flow in the construction industry
after a few major disasters. The importance of payment in the is critical because of the relatively long
construction industry duration of projects. A planned
Construction Industry Working Group expected revenue flow is usually
on Payment (WG 10) The total contribution to Gross represented by an S curve. Any
Domestic Product (GDP) by the deviation due to either project delays or
Based on our own problems, payment construction industry is significant. cash flow delays can have a major
was identified as one of ten priority Whilst in Malaysia it is in single digit, impact on the project.
areas in the Malaysian construction some developed countries have the
industry during a construction construction industry contributing Diagram 1 below shows two planned S
industry roundtable in June 2003. An more than 10% to GDP. curves with different contract sums. If a
industry working group (WG 10) led by deviation occurs halfway through the
the Institution of Surveyors Malaysia Payment in any industry has generally project, it becomes increasingly more
(ISM) was then formed. Given the been an issue of concern. In the difficult to recover if the original
industry experience on payment construction industry payment is an duration is to be maintained. This is
problems and taking heed of issue of major concern. This is because: because the graph starts with a gentle
experience of other countries, WG 10 slope then moves into a steep slope
then made various recommendations (a) Unlike many other industries, the before tapering off gently. Accelerating
during the construction industry durations of construction projects to catch up on lost time on an already
roundtable in June 2004 chaired by the are relatively long; steep slope is an enormous task.
Honorable Minister of Works. One of
the recommendations was for the (b) The size of each construction The Self-Test Question On Payment
creation of a Malaysian ‘Construction project is relatively large and each
Industry Payment and Adjudication Act’. progress payment sum involved The United Kingdom, nearly all states in
are often relatively large; and Australia, New Zealand, and more
Following agreement in principle recently Singapore have all statutorily
during the meeting, WG 10 moved (c) Payment terms are usually on credit enacted provisions to address issues on
towards its evolving vision which could rather than payment on delivery. payment in the construction industry
be summarized as: ‘payment in the and have introduced adjudication as a
construction industry is timely’ - where Contrast these with say the medical fast, economical dispute resolution
everyone in the construction industry industry or the tourism industry where method for the construction industry.
pays the appropriate amounts due in a the size of each transaction is typically Malaysia too must not under-estimate
timely manner. That ties in with the much smaller. The durations of the potential disastrous consequences
construction industry masterplan vision transactions in other industries are also of persistent payment default across the
of making the Malaysian construction generally much shorter. industry and the economy. At some
industry world class by 2015. These in
turn fit in with Malaysia’s 2020 vision of
Construction S Curve
becoming a fully developed country.
50,000,000.00

45,000,000.00
One cannot have a ‘world class
40,000,000.00
construction industry’ if even ‘mundane’
35,000,000.00
Amount (RM)

things like payment is not being


30,000,000.00
honoured – whether in a timely manner
25,000,000.00
or at all! 20,000,000.00

15,000,000.00
I outline, in this paper, some key 10,000,000.00
recommendations and developments on 5,000,000.00
the plans to make the WG 10 vision a reality -
0 1 2 3 4 5 6 7 8 9 10 11 12 13
including the main recommendation for a
Malaysian ‘Construction Industry Payment Construction Period (m onth)

and Adjudication Act’. Diagram 1

02

3 r d Q u a r t e r 2 0 0 6
A rticle

levels the problems are serious. We recommended an international reducing payment default and
cannot also deny that existing conference to be held in Kuala Lumpur. increasing efficiency in resolving
contractual arrangements and general This was primarily sponsored by the disputes in the construction industry.
legislation has not prevented the CIDB and held on 13 & 14 September
problems. The test is in present results – 2005. The international conference ‘Everyone’
not what results we could have gathered about 18 top authorities from
achieved. around the world including all the Everyone means everyone involved in
countries that have introduced the delivery chain of construction
There is one self-test question that can legislation on payment and projects. They include:
be used to assess the seriousness of the construction adjudication. This
problem. Ask yourself the following international conference on payment ● Clients (both public and private
question and answer honestly: and adjudication legislation was sectors),
acclaimed to be the first of its kind in the ● Construction consultants involved
If all the past amounts due were paid world. Valuable feedback and in construction projects such as
to your company today, and from comments based on international architects, engineers and quantity
today onwards all amounts due are experience were noted. Since then surveyors. (Peculiarly, the New
paid promptly and in a timely further wide consultation and briefings Zealand Act does not cover
manner, where would that put you have been held in Malaysia including professional services relating to
and your company financially – briefings to captains of industry, construction work)
today, and in the future? professional bodies, trade ● Main contractors,
organizations, academic institutions, ● Sub-contractors,
The more significant the impact of your federal and state government ministries ● Sub-sub-contractors,
answer on your company’s financial and departments and the Attorney- ● Suppliers
situation, the more serious the problem General’s chambers. Following the
on payment is. development of early concept ‘The Construction Industry’
proposals of our model, exchanges of
Even without the benefits of the survey feedback was also held with experts The construction industry includes
results commissioned by the CIDB and from Singapore, New Zealand and the the building and civil engineering
UM, that question remains a self-test United Kingdom. sectors. Whether other sectors such as
question for individuals in the industry the oil and gas and shipping sectors
to realize the seriousness of the The Malaysian Visions should be included is a question of
problem and to realize the potential policy to be decided. Other countries
benefit of reducing the problem. The Malaysia has set its vision to be a fully do not include the shipping industry
seriousness of the problem has already developed nation by 2020. The and I think rightfully so. However
been recognized by leaders in the construction industry has set it own typically the oil and gas sector too has
construction industry. Thus the vision to be ‘among the best in the world’ been excluded. If ‘because there is no
identification of payment as an issue of by 2015. As part of the plan, working problem on payment in the oil and gas
major concern and the formation of groups on ten priority areas were set up sector’ is the only reason, I do not see
WG 10. Further recognition of the in June 2003. WG 10 was but only one why the oil and gas sector should be
problem was evident when the of ten. excluded. Some of the court cases on
recommendations for the proposed Act adjudication in the UK are on
were rapidly accepted by the industry If the Malaysian construction industry is ‘peripheral’ issues such as whether a
during the Construction Industry to be ‘among the best in the world’, the contract falls under the definition of a
Roundtable in June 2004 chaired by the working group had to have an equally ‘construction contract.’ By having an
Honorable Minister of Works. challenging vision. The vision of the all encompassing definition, disputes
working group on payment is: on such ‘peripheral’ issues can be
Following the June 2004 industry avoided.
roundtable, a further open national Everyone in the construction industry
conference was held in August 2004 to pays all appropriate amounts due in The UK Act has been so successful since
gather wider feedback from industry. a timely manner. it came into force in May 1998 that the
And in order to get the maximum process of adjudication is now even
benefit from the experience of other I now elaborate on the vision of WG 10 being discussed for use in other
countries around the world, WG 10 and how it can contribute towards industries.

03

3 r d Q u a r t e r 2 0 0 6
A rticle

‘Pay All Appropriate Amounts Due’ ‘Timely Manner’ Actual Time or Absolute Time

‘Appropriate amounts due’ means This is a key point in the WG 10 vision The actual time or period needed would
someone would have to decide what statement. It is important to vary among players in the construction
such amount is. Where standard distinguish: industry. The time period needed can
terms of contracts are used the be stated in the contracts - upfront.
mechanism would be through the (i) the actual time or duration within Circumstances of the paying party can
normal existing certification process which payment must be made; be incorporated eg. internal accounting
by an independent contract and procedures, audit procedures and even
administrator eg superintending management bureaucracy. The party
officer or architector contract (ii) the timeliness of payment. bidding for the contract can then price
administrator. Even if the contract accordingly. Example, if the contract
administrator is not employed The actual time within which payment states payment is due within 90 days
independently but is instead an must be made is the duration eg. 30 from the date of certification on a
employee of one of the parties, the days or 60 days given, within which particular project compared to a typical
law would imply that duty to be payment must be made. 30 day due period, the bidder can plan
discharged fairly. And if payment is and price for the long period through
still not made following the normal Timeliness on the other hand refers to extra facilities such as overdraft
certification process or the amount the punctuality of payment. knowing well upfront the longer period
certified is alleged to be ‘unfair’, an for payment due. In some cases the
adjudicator may be called upon to Example. if a contract specifies bidder may even opt not to tender if the
‘adjudicate’ on the certificate or other payment within 30 days, payment period is unacceptable.
claims. must be made within 30 days. If the
contract specifies payment within 14 Timeliness
Where there is no provision for a days or 6 months then payment is due
contract administrator or progress within the 14 days or 6 months Failure on timeliness on the other hand
payment at all, such as the thousands respectively. has wide ranging implications.
of present ‘domestic’ sub-contracts or
‘one-off ’ small contracts that are If a contract stipulates payment within ● Integrity
entered into on a regular basis, 90 days and payment is made in 80
legislation can step in to regularize days payment can be said to be timely. A failure to pay within the time
payment through a default payment But in a contract which stipulates stipulated is a breach of promise – a
mechanism. Again the process of payment within 60 days, if payment is compromise on business ethics.
adjudication can step in to ensure it is made in 80 days, payment is not timely. Studies on leadership consistently
done independently and fairly. identify integrity as among the top
Both, actual time for payment and traits of leaders. A person of integrity
Following the independent process of timeliness are important. But does not breach promises. The
adjudication through legislation, between the two, consistent timely Malaysian construction industry has
there is a much higher possibility of payment is more important. There are set its target to be ‘among the best in
support from the court system in two reasons for this. First, because the world’. To be among the best means
enforcing adjudicators’ decisions. This planned cash flow is critical to a to be a leader in the world.
has been the experience in other business, par ticularly in the
countries with such legislation. construction industry. And secondly, Studies also suggest the trait of
because a longer period for payment, integrity must be present consistently
Parties who have had a fair ‘hearing’ known upfront, can be planned and if we are to achieve this vision of world
of their case through an independent priced for in advance. Indeed if the leadership. Without consistent
adjudicator too are likely to accept the time for payment is unacceptably integrity, eventually one will fall.
adjudicator’s decision and are less long a contractor might even choose ‘Situational integrity’ would not do – if
likely to seek to open up the same not to tender. On the other hand, we are to be world class leaders.
dispute in a protracted, relatively deviations from an original plan ‘Situational integrity’ is where the level
expensive arbitration or litigation. require re-planning, are often of integrity of a person fluctuates
Again that has been the experience in unpredictable and can have a knock- depending on the situation faced.
other countries with such legislation. on effect on many other activities. Thus a breach on using pirated

04

3 r d Q u a r t e r 2 0 0 6
A rticle

software on one computer in the office Thus, a failure on timely payment can ‘financial collapse’ at various forums
is sometimes waved away as trivial result in project delays, reduced including briefings mostly organized by
which doesn’t affect the company’s profitability and can even lead to the Construction Industry Development
‘overall integrity’! Or a company which companies going into liquidation. None Board (which comes under the purview
has tax planned and has avoided (which of these effects should be present at any of the Ministry of Works) to captains of
is lawful) some taxes and at the same significant levels if an industry is to be industry, professional bodies, trade
time evaded (which is unlawful) some ‘among the best in the world’. Currently it organizations, academic institutions,
tax cannot be said to be a company of is common for construction projects in federal and state government ministries
integrity. One is either pregnant or not Malaysia to be late. Some of the reasons and departments and the Attorney-
pregnant. One cannot be ‘partly for the delay can be attributed to General’s chambers. In my capacity as
pregnant’ nor have ‘situational delayed payment. We have only nine President of the Institution of Surveyors
pregnancy’. In the same way one either years to go before 2015. Much work Malaysia, I similarly highlighted these
has integrity or doesn’t. Situational needs to be done over the next nine reminders at the 2005 annual dialogue
integrity usually means no integrity. years – if we are to move towards with the Honorable Minister of Trade
substantially eliminating payment and Industry and the annual budget
● Project Delays, Reduced Profitability default. Tall order. But not impossible. dialogue chaired by the Right
and Possible Liquidation Honorable Prime Minister in the
‘Some men see things as they are and say presence of the Honorable Finance
A failure on timely payment also affects why. I dream things that never were and Minister II and all other Ministry
programmes which are pre-planned. say why not.’ Robert F Kennedy, representatives. My request was for
This affects cash flow which in turn can paraphrasing George Bernard Shaw. timely support of the proposed Act.
affect progress of the works and After all the wise learn from other
profitability. In bad cases as has Many in the construction industry see people’s mistakes.
happened in other countries such as the and often themselves suffer the effects
United Kingdom, Australia, New of payment default and keep moaning Addressing The Vision – A Two
Zealand and Singapore, many about the problem – sometimes giving Pronged Approach
companies facing unplanned cashflow reasons for the problem. What we must
problems ended up in liquidation. In do is to envision a dream like ‘payment Nine years may seem a long time to
the UK, between 1989 and 1994, over in the construction industry is timely’ - achieve the stated vision. But it is not. To
35,000 businesses and companies where everyone in the construction achieve this vision, a two pronged
became insolvent with almost half a industry pays the appropriate amounts approach is recommended:
million jobs lost. That and the Latham due in a timely manner. Thus dreaming
Report eventually resulted in the of things even if it may appear idealistic 1. A fundamental change in the
drafting of the UK Act. and maintain the stand ‘why not.’ After mindset towards timely payment.
all the construction industry masterplan This can partly be achieved through
In New Zealand, insolvencies specifically does speak of being ‘world class’. self realization of concepts such as
in the construction industry since 1998 present buzz words like ‘good
included names spread throughout the When I speak to people in the industry corporate governance’, or through
country such as David Brown about the WG 10 long term vision of concepts I have stated earlier in this
Construction, Auckland, Voss 2015, I keep hearing a common lament paper such as realization of
Construction, Wellington, Replica – ‘I hope that is not too late.’ Fresh in their ‘situational integrity’ or ‘partial
Homes, Christchurch and several others minds are the ‘safety collapse’ case of Dr integrity’ and its analogy of being
such as Campbell Construction, Equinox Liew in Sri Hartamas, Kuala Lumpur, and ‘part pregnant’; and
Construction and Hartner Construction. the gory reminder of the Highlands
Earlier, major insolvencies included Towers case – a ‘quality collapse’. The 2. Statutory enactment to give
McMillan & Lockwood Ltd and Angus Malaysian construction industry could enough bite, particularly in the short
Construction. These were followed by do without a ‘financial collapse’ as was to medium term and in cases where
consequential failures of large numbers the case in many other countries. there are chronic problems.
of subcontractors. These events
prompted serious action which I have highlighted these reminders, the This paper covers the second prong
eventually resulted in the drafting and re-action in other countries and how we, rather than the first – although I would
enactment of the New Zealand in Malaysia, should be ‘pro-active’ in our recommend the first be also taken up,
Construction Contracts Act 2002. actions and avoid any potential possibly at other forums.

05

3 r d Q u a r t e r 2 0 0 6
A rticle

Although the first is the preferred because there were few cases on PAM adjudication for disputes relating to
method in a mature society, to achieve 69 in Malaysia does not mean the a construction contract
the vision within nine years, the stick contract was ‘ok’. It required the efforts ● The provision of remedies for the
method (such as through statutory of only a few – commissioned by recovery and security of payment
provisions) is also needed. Here is an Pertubuhan Akitek Malaysia - to make under a construction contract
analogy. The tax laws in Malaysia have the transformation to what is now the
now been amended assuming a more PAM 98 contract and possibly and These are some of the major issues that
mature society where everyone is hopefully soon the 2006 or 2007 have been debated by the industry at
responsible enough to self-assess their edition. length for inclusion in the proposed
own taxes and declare and pay all taxes Malaysian Act. In addition, statutorily
due. But the tax department too knows Few people are all that is needed to providing the right to interest on late
the ‘stick’ method must complement initiate the move for the construction payment has also been suggested.
the ‘mature’ method. Hence the industry to achieve its 2015 vision of
warning that their officers will conduct being ‘world class’. Likewise for WG 10 I now briefly consider some of the
random checks! to achieve its vision of: areas that may be covered in the
proposed Malaysian Act and how they
A Malaysian ‘Construction Everyone in the construction may help towards eliminating
Industry Payment and industry pays all appropriate payment default:
Adjudication Act’ amounts due in a timely manner.
A scheme for payment where there is
Support for a Malaysian ‘Construction Although only a few people are no provision for progress payment in
Industry Payment and Adjudication Act’ needed to initiate the change, the a construction contract
by the construction industry players has masses must support it to make it a
been overwhelming. And MBAM has success. And ideally there must be This can be an issue in one-off
been a consistent major supporter and consensus. The construction industry contracts typical on smaller projects
contributor to the refinement of the has supported it overwhelmingly so far and in the large number of sub-
conceptual proposals. – although certain aspects of security contracts and sub-sub-contracts
for payment suited to Malaysia is yet to where the main contractor selects his
The next question to be considered is be agreed consensually. own sub-contractor – generally
how our version of a model referred to as ‘domestic’ sub-
‘Construction Industry Payment and Contents of a Construction contractors. A typical statutory
Adjudication Act’ should be. Should we Industry Payment and provision would provide for a default
just adopt any one of the models Adjudication Act mechanism if a construction contract
already developed around the world? does not provide for a payment
Or is our situation different such that we Typically the relevant acts around the mechanism.
cannot accept these models ‘lock, stock world cover various common aspects
and barrel’. Should we have something including the following. These are The intentions in the proposals for the
that is better than the current best? considered in some detail below: Malaysian Act are clear. The parties to
a construction contract are free to
We have in the past adopted the UK ● A scheme for regular payment agree terms of payment – whether
JCT 63 building contract lock, stock and where there is no provision for a payment in 30 days or even 100 days
nearly all barrels. We renamed it the payment mechanism in a of certification, milestone payments, a
PAM 69 contract. And despite serious construction contract. I repeat – single bullet payment on completion
judicial criticism we ‘lived with it’ for ‘where there is no provision for a or even payment in kind. Much of the
nearly thirty years! The vast majority of payment mechanism in a concept of freedom of contract is
Malaysian society, not being a litigious construction contract.’ preserved. The default mechanism for
one, did not directly face the ● Outlawing ‘pay-when-paid’ and ‘pay- regular payment is only for cases
consequences of the shortfalls of the if-paid’ clauses in construction where there is no payment mechanism
contract. But ask the few who did end contracts provided in the contract.
up in court. They will clearly say ● The rights for a party who has not
reforms to the contract must be made been paid to suspend works This clearly is a sensible provision and
and ought to have been made much ● The provision of a speedy dispute one that will avoid uncertainty on
earlier. Ignorance is not bliss. Just resolution process called payment provisions.

06

3 r d Q u a r t e r 2 0 0 6
A rticle

Outlawing ‘pay-when-paid’ and ‘pay-if- Section 13 of the NZ Act states that a that such provisions do exist in
paid’ clauses in construction contracts ‘conditional payment provision of a industry now.
construction contract has no legal effect’
None of the nominated sub-contracts and ‘is not enforceable in any civil Payments conditional upon an
published in Malaysia including under proceedings’. Similar provisions are found architect, engineer, superintending
the PAM 69, PAM 98, PWD 203 series, IEM in the UK Act and the New South Wales, officer, or contract administrator’s
or CIDB 2000 contracts contain a ‘pay- Victorian, Queensland, Western certificate must not however be
when-paid’ or ‘pay-if-paid’ clause. They all Australian, Northern Territory and outlawed. This is because these
have ‘pay-when-certified’ clauses. In Singaporean Acts. A limited exception is certifiers are expected to certify fairly
other words payment must be made by made in the UK Act allowing pay-when- irrespective of their employer. In any
the main contractor upon certification paid provisions in situations when a case the adjudication provisions
by the certifier whether or not the main client becomes insolvent. The logic recommended for the proposed Act
contractor is paid in a timely manner as behind the UK Act excluding such will be a check on any unreasonable
provided under the main contract. protection in the event of insolvency is conduct by the certifier
that the main contractor is in a better contemporaneously.
But many contractor-drafted ‘domestic’ position to be able to ascertain the
sub-contracts or sub-sub-contracts financial credentials of the client with The rights of a party who has not
contain ‘pay-when-paid’ or ‘pay-if-paid’ whom the contractor contracted. been paid to suspend works
provisions. ‘Domestic’ sub-contracts are
contracts which a contractor enters into Although my earlier views were open on This is a typical right provided in other
with a sub-contractor chosen by the whether to outlaw such provisions, on statutory provisions around the world
contractor. The only standard terms of balance, it now appears clear that like in dealing with payment and
‘domestic’ sub-contact published in other countries, these provisions must be adjudication. The right to suspend
Malaysia – the ‘Model Terms of outlawed for the Act to be effective as a work is not provided in common law.
Construction Contract for Subcontract whole. See eg. Canterbury Pipe Lines Ltd v
Work’ published in September 2006 does Christchurch Drainage Board [1979] 2
not have a ‘pay-when-paid’or‘pay-if-paid’ Consider also a client organization that NZLR 347 (CA) and Lubenham Fidelities
provision. awards a construction contract to a & Investments Co Ltd v South
company within its own group and Pembrokeshire District Council (1986)
Pay-when-paid clauses are those clauses which is then sub-contracted out. A pay- 33 BLR 39. Newer standard terms of
which defer the time when payment is due if-paid clause if not outlawed can then be construction contracts tend to
from say a main contractor to a sub- used as an excuse for not paying the sub- provide an express right to suspend
contractor until the main contractor has contractor (an outside party) who works following non payment. Eg the
received payment from the client. Pay-if- actually does the work. CIDB Standard Form of Building
paid clauses are clauses which attempt Contract 2000 and possibly the 2006
to exclude even the liability for payment to It may be timely to remind ourselves or 2007 amendments to the PAM
a sub-contractor until the main ‘cash flow is the life blood of the Standard Form of Building Contract
contractor is paid. construction industry.’ 1998. The PAM nominated sub-
contract standard terms have
The effect of such clauses is that sub- Whilst pay-when-paid and pay-if-paid however always had a provision for
contractors may well end up not being provisions in construction contracts the sub-contractor to suspend works.
paid for reasons beyond their control. are known and are becoming Strangely, a similar provision was
Worse still is a situation where a client increasingly common, and these have never correspondingly provided in
may set off amounts due to a main been recommended to be outlawed, the main contract.
contractor due to the main contractor’s there is one other ‘conditional
own fault. The sub-contractor then does payment’ provision worthy of The necessity for such rights to be
not get paid although they may have attention. Recommendations have conferred statutorily arises because
done their work properly and were not also been made in Malaysia for not all construction work is undertaken
in breach of their contract. outlawing payments which are using published standard terms of
conditional upon ‘other arrangements’ contract.
All the similar Acts around the world eg conditional upon availability of
typically effectively outlaw pay-when- funds or drawdown of financing Typically the Acts confer an automatic
paid and pay-if-paid provisions. They facilities. Eg a client organisation right to extension of time to the
may not be worded such that such providing for payment to a contractor contractor who rightfully suspends
provisions are ‘banned’, but the effects of being conditional upon there being work following non-payment. This
the wordings are such that such say a minimum balance of RM 2 million right will of course cease when
provisions are ‘effectively prohibited’. Eg in the bank or other accounts. I know payment is finally made.

07

3 r d Q u a r t e r 2 0 0 6
A rticle

The recommendation to date for the arbitration – whenever negotiations disputes in the construction industry
Malaysian Act is for the right to suspend could not conclude a disagreement (from referring a dispute to an appointing
work to be conferred only following an which has become a dispute. body through to getting an award from
adjudicator’s decision. Theoretically, and the intent of an arbitrator) could take anything from
arbitration was for a fast and economical, over a year to a few years and sometimes
The provision of a speedy dispute binding private dispute resolution even more than 5 years. Construction
resolution process (adjudication) for mechanism. The reality based on disputes in court usually take longer. The
disputes relating to a construction experience is rather different. Rarely will table below is an estimated indicative
contract you find an arbitration on a construction comparison of some salient features
dispute being completed from the start comparing litigation, arbitration,
Traditionally disputes in the construction of a dispute to a final arbitrator’s award adjudication and mediation on a typical
industry have been resolved through in under a year. A typical arbitration on construction dispute.

STATUTORILY
DESCRIPTION LITIGATION ARBITRATION PROVIDED MEDIATION
ADJUDICATON

Basis of resolution Rights based; based on Rights based; based on Rights based; based on Interest based; need
of dispute facts, evidence and law facts, evidence and law facts, evidence and law not be based on
facts, evidence or
law. Parties may
agree anything (that
is lawful)

Tribunal cost* (RM) 5K 50 K – 300 K 10 K – 50 K 2 K – 15 K

Parties’ costs – both 100 K – 600 K 100 K – 500 K 50 K - 100 K 10 K – 20 K


sides** (RM)

Duration*** 2 - 7 years 1 - 5 years 4 - 8 weeks 1 - 14 days

Rights to the Usually right to May only resort to With an enabling Act, Mediation can
process and pre- litigation precluded if arbitration if there is a adjudication would always be used by
conditions there is an arbitration written arbitration usually be permitted at the parties at any
clause in the contract, agreement in the any time time
but may be used to contract or if agreed by
challenge an the parties at any time
arbitrator’s award
although only on very
limited grounds

Timing If there is no arbitration Usually in construction Anytime Anytime


clause, anytime. If there contracts arbitration
is an arbitration clause, clauses provide that
only if an arbitrator’s arbitrations on most
award is being disputes may only start
challenged which may after completion or
be done only on very termination
limited grounds

Extent to which it Binding, but may be Binding, but the Binding but the same Not binding at any
may be binding and appealed to a higher arbitrator’s award may dispute may be time during the
appealed court be challenged in court reopened in process, except when
although in very arbitration/litigation settlement
limited circumstances agreement is reached

Relationship Usually confrontational Often quite May be a little Usually amicable


between disputing confrontational confrontational
parties

08

3 r d Q u a r t e r 2 0 0 6
A rticle

*Tribunal cost means the costs complemented with the opportunity be resolved - but it can, and often is
associated with the sitting tribunal eg for eventual ‘fine justice’ in an resolved contemporaneously (meaning
court fees, arbitrator’s, adjudicator’s or arbitration, if the parties still need it. when the dispute occurs). Unlike a
mediator’s fees and the cost of typical arbitration which can
venue, if any. The amounts shown usually only start after completion
are only an estimated indicative of works or after termination. And
range. which often results in delayed
justice – which some say is justice
**Parties’ cost means costs (again denied.
an estimated indicative range) that
the parties may incur eg. costs of In the UK more than 15,000
employing lawyers, claims adjudications have been held since
consultants or other experts. But 1998. Over the corresponding
it excludes other internal costs eg. period, the number of arbitrations
costs associated with the parties’ has dropped significantly. So has
time spent in preparing for the the number of cases in the
case, time spent at hearings or Technology and Construction
costs involved in preparing Court ( TCC) which handles
documentation or travel costs. construction cases. I would not
state that the sole reason for the
***Duration: This is an indication decline in arbitrations or the cases
of the estimated indicative time in the TCC are solely because
usually required for a typical disputes are increasingly being
construction dispute from the resolved through adjudication or
start of the process eg one party Like in arbitration, in adjudication an possibly mediation. But what I would
writing to the other stating there is a independent adjudicator who is say is there is at least anecdotal
dispute and suggesting it be resolved appointed steps in and makes a binding evidence that, as a minimum, the
in an arbitration or adjudication or decision based on the evidence, facts introduction of adjudication could be
through mediation through to a and the law. The decision binds the partly the reason. If so, isn’t that bad
judgment, award, decision or parties to the contract immediately news for the ‘traditional dispute
settlement agreement. upon getting the decision from the resolution industry’? All true
adjudicator but unlike the ‘finality’ of an professionals know that an essential
I have always held the view that various arbitrator’s award the same dispute trait of a professional (and the basis
dispute resolution methods must co- referred to in adjudication may be upon which professionals get the
exist to complement each other to suit opened up again in an arbitration authority to act – sometimes statutorily
the nature of dispute and the following the provisions in the contract. and often to the exclusion of the public
circumstances of each case. But it In construction contracts, for most at large) is altruism – putting client’s and
becomes increasingly important for disputes that typically means following society’s interest before self interest.
construction disputes to be settled: completion or termination. The UK You decide whether the potential effect
experience shows though that the vast of introducing adjudication in the
● Speedily; majority of disputes referred to construction industry would be in the
● Economically; adjudications are not subsequently best interest of society and the
● In a binding manner; opened up in arbitration. economy as a whole.
● Contemporaneously ie when it
happens as opposed to years later; Unlike arbitration, the adjudication So far the number of cases in court
and processes provided statutorily around relating to adjudication that I am aware
● Wherever possible for good the world are time limited. The duration of are 256 in the UK, 110 in Australia
relationship to be maintained. is typically statutorily set at 14 days, 20 most of which (93) are in New South
working or business days, 30 working or Wales and 3 in New Zealand. I am
Based on the above considerations, business days, 28 days or 42 days. Only aware of one in Malaysia. One party
mediation and adjudication merit if the parties agree, these durations may alleged I was properly appointed as an
serious attention as methods of be extended. Rough justice – maybe, ‘adjudicator’ as defined in their
resolving construction disputes – given the short period for the dispute to contract. The other party challenged

09

3 r d Q u a r t e r 2 0 0 6
A rticle

my jurisdiction and the appointing is somewhat different. Malaysia committee on the proposed
body’s right to appoint me. Thankfully, operates substantially on a sell-on-plan ‘Construction Industry Payment and
it was settled before it proceeded to scheme. That means purchasers and Adjudication’ are for a payment bond to
hearing! end financiers would be involved early be mandated, but only at head contract
on in the development. Any attempt to level. This was seen as a compromise to
The number of cases might sound like provide security for payment to a avoid excessive cost increase.
many, but compared to over 15,000 contractor, subcontractor or supplier
adjudications done to date 369 cases through a lien or charging order There have also been other ‘creative’
around the world is considered very few. scheme might not be in the best public suggestions eg. by REHDA on the
Further, and very importantly, many of interest and of many of the parties – possibility of creating a ‘contractor’s
the cases were dealing with tangential particularly the purchasers. project account’. But this has yet to be
issues such as jurisdiction of the explored in detail.
adjudicator (including the one in According to Sr Lim Chong Fong, a
Malaysia) and not just on issues relating practicing construction lawyer with a Other Payments
to the dispute itself. Indeed even after 8 background in quantity surveying and
years and over 15,000 adjudications, who has done much research into this I have one last point on payment to be
two of the most recent cases in the UK aspect of the proposal for the Act, made. I have simply called it ‘other
Redworth Construction Limited v provisions through a mandatory trust payments’. I wish to re-visit my points
Brookdale Healthcare Limited [2006] fund too have their shortfalls in on integrity and ‘situational integrity’. As
EWHC 1994, 31 July 2006 and Harlow & Malaysia because tracking of funds I wrote earlier, one is either a person of
Milner Ltd v Mrs Linda Teasdale [2006] movement would remain a problem integrity or not.
EWHC 1708, 7 July 2006 both had given the various existing laws in
jurisdiction as a key issue. Malaysia. That leaves a third way to If we expect everyone to pay the full
obtain security for payment in the sums due in a timely manner, we
The provision of remedies for the construction industry - a system of should also pay those who we owe all
recovery of payments under a payment bonds, Sr Lim Chong Fong amounts due in a timely manner.
construction contract suggests is the best way to have some Ideally, upon the due date - whether
security for payment. demanded or not. They include the
In order to give ‘teeth’ to the statutory newspaper man, milkman (if they still
provisions, there must be provisions for So far, providing a mandated system of exist) IWK, TNB, TM, government service
remedies for the recovery of payment payment bonds has not had consensus tax and other taxes. And for
following a decision or determination of within the construction industry. It is professionals it includes paying all
an adjudicator. These are provided in also evident that having a professional subscriptions within the
various ways depending on the comprehensive scheme of bonds all the deadlines – even if one has shifted
jurisdiction. In the UK it is provided way from the client to main contractor houses and addresses have not been
through enforcing the adjudicator’s to subcontractors to sub subcontractors updated!
decision under s 42 of the Arbitration and suppliers is likely to result in
Act 1996. Under the NSW and Victorian reciprocal insistence of having Physical infrastructure is but only a part
Acts, apart from a right to suspend performance bonds or performance of a fully developed nation. In the long
works, it is recovered as a debt. The NSW security deposits or retentions sums or run personal integrity must be all-
Act has a procedure to obtain an a combination of some of these security encompassing if we are to achieve the
‘adjudication certificate’ which can then for performance all the way down the vision of:
be filed ‘as a judgment for debt in any chain of contracts. It was generally felt
court of competent jurisdiction.’ Similarly that then, the increase in costs due to (i) Everyone in the construction
the NZ Act provides for the right to banking charges involved in providing industry paying all appropriate
suspend works, to recover the a plethora of payment and performance amounts due in a timely manner;
adjudicator’s determination as a debt in bonds would not be commensurate and
court and to enter the adjudicator’s with the benefit of security of payment
determination as a judgment in the through a statutorily mandated bond (ii) Making the Malaysian construction
District Court. system within Malaysia. industry world class by 2015; and

On security for payment, unlike most At the time of my writing this, the (iii) Malaysia becoming a fully
other countries, the Malaysian scenario recommendations by the steering developed nation by 2020.

10

3 r d Q u a r t e r 2 0 0 6
A rticle

PART II - Questions and Answers


This second part is a continuation of the first and is structured in a question and answer format. It attempts to provide
responses to many questions that may remain in various related area. They include questions that may remain an area of
concern to some.

They are not necessarily frequently asked questions or ‘FAQ’s. Many of these questions were asked in some of the forums held
so far between June 2003 and October 2006 – initially during presentations on the WG 10 recommendations and subsequently
on the briefings on the proposed ‘Construction Industry Payment and Adjudication Act’ to the captains of industry, professional
bodies, trade organizations, academic institutions, government ministries and departments (federal and state) and at open
construction industry public forums. And some of these questions came from various meetings and discussions I have had
either in groups or on a one-to-one basis.

It might appear as many questions. But most of them have been deliberated widely at industry or steering committee level and
appropriate recommendations made.

The questions are in no particular order and are not meant to be exhaustive.

Q: So far the Malaysian construction industry has been Q: Would the Act ‘look after’ the ‘poor’ sub-sub-works-
‘quite okay’ and surviving. Why should there now be contractor who actually does the work but is not paid
statutory intervention through the proposed and who might not be the best in understanding
Construction Industry Payment and Adjudication complex pieces of legislation?
Act?
Q: How would the introduction of adjudication affect
Q: Aren’t other existing Acts in Malaysia adequate to the rights to other existing dispute resolution
address any problems that might exist in the mechanisms like arbitration, going to court or
construction industry? mediation?

Q: Will the proposed Act curb the concept of ‘freedom Q: The New South Wales model appears to enable only
of contract’? the party who has a right to be paid to refer a dispute
to adjudication, but not the other way round. It
Q: The New Zealand Act is known as the Construction appears to be a one-way protection. But in industry,
Contracts Act 2002. The Western Australian Act is there are also cases of poor workmanship or
similarly called Construction Contracts Act 2004. If breaches by those who do the work. Is it not unfair if
Malaysia were to follow these, does this mean there disputes can only be referred one way and not the
will be one standard form of construction contract other?
to be mandated for use in the construction industry?
Q: Can a party refuse to participate in an adjudication?
Q: Why is our Act proposed to be called ‘Construction
Industry Payment and Adjudication Act’ whereas all Q: What would happen if one of the parties to an
the other countries have different names like adjudication refuses to participate in an
‘Housing Grants Construction and Regeneration Act, adjudication?
Construction Contracts Act and quite commonly
Building and Construction Industry Security of Q: Can both parties or the adjudicator refuse to
Payment Act? Is it because our proposed Act is continue with an adjudication after having started it?
significantly different from the others?
Q: Who pays for the adjudicator’s fees and the cost of
Q: With the proposals at present, can parties to a hiring venues for meetings etc?
construction contract agree for payment to be in
kind? Example: land swap, payment in the form of Q: Can and should an adjudicator be named in advance
completed apartments or even barter trade between in a construction contract?
say palm oil and construction work?

11

3 r d Q u a r t e r 2 0 0 6
A rticle

Q: What can a party do if the party feels the adjudicator Q: Would the proposed Act mean that there will only
has made a wrong decision? be one ‘payment scheme’ in the construction
industry?
Q: Adjudication has been said to be ‘quick and cheap’.
The same thing was said of arbitration years ago. Q: Would introducing a quick, cheap, and
What is the likelihood of adjudication becoming not contemporaneous dispute resolution mechanism
so quick and not so cheap like arbitration? like adjudication lead to a proliferation of ‘claims
consultants’?
Q: What is the likely cost of a typical adjudication? Are
there statistics from other countries which have Q: Would introducing a quick, cheap, and
similar Acts? contemporaneous dispute resolution mechanism
like adjudication lead to a higher number of
Q: If payment bond is to be the ‘security for payment’, disputes?
how would that affect other related performance
‘counter security’ measures like performance bond Q: Would it also lead to more frivolous and unwarranted
and retention sums? claims being put forward through adjudication?

Q: ‘On-demand’ bonds (often without even any need Q: What happens when frivolous or unwarranted claims
for proof of default) are common in Malaysia. If are put forward in an adjudication?
payment bonds are going to be mandated, how
would it be structured to avoid unwarranted calls on Q: What is the difference between a contractually
bonds to avoid chaos in cross calling of bonds in the agreed adjudication and statutorily enabled
industry? adjudication?

Q: What would a party do after getting an adjudicator’s Q: Who can be adjudicators?


decision? How would enforcement be made?
Q: What would the qualifications of the adjudicators
Q: Some tribunals like arbitration and even some courts be?
have a tribunal of three. Has consideration been
given for an adjudication tribunal of three? Q: What training schemes are adjudicators likely to be
put through?
Q: How would an adjudicator’s decision have a bearing
on the contract administration of an ongoing Q: Would adjudicators be accredited by various bodies
project? or a single body?

Q: Isn’t arbitration adequate as a binding dispute Q: Some in industry have lamented on the quality of
resolution mechanism in the construction industry? arbitrators in the country. Are adjudicators too likely
to fall into a similar situation?
Q: Can direct payment be legally made from a principal
(say a client) to a subcontractor without the consent Q: Can an adjudicator be sued if the decision made is
of the main contractor? believed to be wrong or is obviously wrong?

Q: How would ‘fairness’ be maintained if the claimant Q: Can the nominating body be sued for nominating an
has spent months preparing the case and the incompetent adjudicator?
process of adjudication is to be resolved in a matter
of days or weeks at the most. How would the Q: Can parties agree on an adjudicator or will
respondent have enough time to respond adjudicators only be nominated by a nominating
adequately? body?

Q: Given the new Malaysian Arbitration Act 2005, would Q: Can parties agree on an adjudicator who may not be
the proposed Construction Industry Payment and an accredited adjudicator?
Adjudication Act be redundant?

12

3 r d Q u a r t e r 2 0 0 6
A rticle

Q: There are many different sets of rules for arbitration Q: What happens on the day immediately after the
used in Malaysia now. Would there also be multiple deadline expires and the adjudicator has not given
sets of rules for adjudication or only one common his decision?
set?
Q: What happens if the dispute is on defective work or
Q: Can an adjudicator’s decision be appealed either by variation work to several hundred apartment units
another adjudicator or by an arbitrator or in the in several blocks of buildings? How would an
courts? adjudicator even have time to inspect or make
decisions on all of them?
Q: Can a dispute that has been adjudicated be referred
to another adjudicator or arbitrator or the courts? Q: If a dispute involves a complex web of issues
involving construction law, payment, variations,
Q: The Singapore model has an immediate ‘appeal’ engineering quality issues and calling of a
system. What would the purpose of an appeal be if performance bond, would one ‘expert’ adjudicator
the whole idea of adjudication was for a ‘quick, be able to handle all the issues and should only one
speedy, contemporaneous’,‘even if a bit rough justice’, ‘expert’ do so?
binding decision?
Q: There has been talk and recommendations for a
Q: What happens if an adjudicator is bribed? ‘construction court’ in Malaysia like the Technology
and Construction Court in the United Kingdom.
Q: Why has New Zealand excluded professional services What is it and in what way would it benefit the
from the scope of the Act? construction industry?

Q: Some of the Acts cover only written contracts, others Q: What does the CIDB-UM survey find? Is payment on
also include oral contracts. What would be the Government funded projects also a problem area? If
advantages and disadvantage of each scheme? so, is it at head contract level or all levels or primarily
sub and sub-sub levels?
Q: Some of the Acts cover only issues on payment, whilst
other Acts cover all other construction disputes. Q: Given the current instructions and moves by
What would be most beneficial to the Malaysian government to pay contractors promptly, would it be
construction industry? necessary to include Government funded projects in
the proposed Act? Would payment still be an issue
Q: The New South Wales Act in Australia outlaws ‘legal on Government funded projects if the Government
representation’. Why should this be so? What are the pays promptly?
views of industry in Malaysia?

Q: Would projects funded by the government be bound And finally the ‘bottom-line’ and ‘million-Ringgit’
by the Act? Should they be bound by the Act? questions:

Q: Would giving an unpaid party the right to suspend Q: With the proposed Act, will payment-default no
work lead to disruption to the work on a project? longer be an issue in the construction industry?

Q: Why can’t the concept of lien be introduced in Q: With the proposed Act, will construction disputes be
Malaysia as security for the benefit of an unpaid party? resolved much quickly and more economically than
at present? If so, how much cheaper or quicker is it
Q: What is so difficult about introducing a scheme of likely to be?
statutory trust funds in Malaysia as security for
payment? Q: Will the proposed Act help the construction industry
become more effective and efficient, helping to
Q: Aren’t 10 working or business days, 14 days, 28 days realize the Malaysia construction masterplan vision
or even 42 or 60 days too short to resolve complex of becoming ‘world-class’?
construction disputes?
MBJ

13

3 r d Q u a r t e r 2 0 0 6

You might also like