completion
• Contractual liabilities
• Limitations of liability
• Q&A
Contractual Liabilities
Contractual Liabilities
• Statutory Requirements
• Tort
Timeline of contractual liability
• Contractor’s insurance of the works ends / the risk of loss or damage to the works
transfers to the Employer
• Mears Ltd v Costplan Services (South East) Ltd [2019] EWCA Civ 502
• the works are completed and free from patent defects, other than ones to be ignored as “trifling”
• ‘trifling’ – is a matter of fact and degree, measured against the purpose of allowing the
Employer to take possession of the works and to use them as intended
• for patent defects there is no difference between work not completed and defective work which
needs to be remedied
• the fact a defect is irremediable does not necessarily mean that the works are not practically
complete (Mears Ltd v Costplan Services (South East) Ltd [2019] EWCA Civ 502)
• Preconditions to ‘Practical Completion’ express requirements: collateral warranties, as-
builts, O&M manuals, health & safety file
• Taking-Over Certificate
issued by the Engineer
• Latent defects
• Defect liability period - 6/12 months from completion or take over. Contractual
requirement for the Contractor to remedy notified defects.
• Defects liability periods are not, unless clearly stated to be, an exclusive remedy for
defects. The Contractor will remain liable for breaches of contract both during and
after the defects liability period
FIDIC 2017 JCT 2016 NEC4 IChemE
(Red/Yellow/Silver) Design & Build (ECC) Red Book
• Defect not defined • Defect not defined? • Defect is “(i) part of the • Defect is “any work done or
• Defects Notification Period • Contractor is to make good works not in accordance any Materials or the Plant or
(DNP), in which Employer is any defect, shrinkage or with the Scope or (ii) any part of it which does not
entitled to notify the other faults in the Works works designed by the comply with the Contract”.
Contractor of defects or which appear within the Contractor which are not • Final Certificate is issued by
damage to the works. Rectification Period due to in accordance with the the PM once the Contractor
• Contractor is obliged to any failure of the applicable law or the has made good all defects or
rectify all defects or damage Contractor to comply with Contractor's design the defects liability period for
notified—even if not caused its obligations under the accepted by PM. the plant has expired
by the Contractor. Treated Contract. • The Supervisor may whichever is the later.
as a variation and additional • Contractor only obliged to notify the Contractor of a • Following the Final
payment (Clause 11.2), do so if instructed. Once defect as soon as it finds Certificate the Contractor has
including for any additional instructed must do so in a it. no right or obligation to do
testing of the (Clause 11.6). reasonable time. • The Contractor must also any further work to any part
• If defect is not Contractor’s • Once all defects have correct a defect even if it of the plant and the Final
responsibility, under the been rectified, the is not notified by the Certificate shall “constitute
2017 Red Book it must give Employer issues a Notice supervisor (Clause 44.1). conclusive evidence in any
prompt notice to the of Completion of Making • Contractor must correct a proceedings whatsoever”
engineer. Good. defect before the end of that the Contractor has
• Contractor should make • Final Statement becomes the ‘defects correction completed all plant and
good a notified defect within payable. period’ – Contract Data made good all Defects in
a reasonable time • Clause 1.8 - The Final Part 1. accordance with his
• Performance Certificate Statement does not • If no defects notified, the obligations under the
absolve the Contractor Supervisor issues a contract. (Clause 38.4).
from its ongoing (general) Defects Certificate.
liability for defects. Otherwise at the earlier
of the last defects
correction period or the
date or when all notified
defects have been
corrected (Clause 44.3).
Limitations
Limitations
• Limitation Act 1980 (as amended by the Latent Damage Act 1986) governs the time
limits for bringing different types of legal claims
• Contractual Claims
• Simple contract / signed underhand – 6 years from the cause of action (date of breach)
• Deed – 12 years from cause of action (date of breach)
• The cause of action for defects claims typically accrues at practical completion
• Tort Claims
Jatinder Garcha
jgarcha@fenwickelliott.com
Edward Colclough
ecolclough@fenwickelliott.com
62