You are on page 1of 9

R E S E A R C H

COBRA ‘98

Response to the new engineering contract - a review of

experts’ observations on this radical new contract

M A Lavin and K F Potts, University of Wolverhampton

ISBN 1-873 640-23-4


Response to the New Engineering Contract
- a review of experts’observations
- on this radical new contract
M.A. Lavin and K.F.Potts
School of Engineering and the Built Environment
University of Wolverhampton
Wulfruna Street
Wolverhampton WV1 1SB

Abstract required based on sound management


principles. He went further stating that the
The New Engineering Contract (NEC) is a “the approach of the New Engineering
radical new form of construction contract Contract is very attractive” and he
containing many new procedures and recommended that it should be used by
methods. Despite its recommendation by government departments.
Sir Michael Latham in 1994, many parties,
particularly in the building sector, are The NEC was first issued as a
reluctant to use it mainly because of their consultative document in 1991, followed
unfamiliarity with its terms. by the 1st edition proper in 1993. The
document was reissued in 1995 under the
The NEC has been developed based on title The Engineering and Construction
principles of sound project management. Contract 2nd edition (ECC).
It requires the parties to act in a spirit of
mutual trust and cooperation - the very The ECC is essentially a family of
same philosophy that is required under a interlocking documents, including
partnership arrangement. subcontract and professional services,
suitable for a variety of uses and
This paper seeks to identify the key contracting methods and contains a
characteristics of the NEC and review the number of secondary options for
industry’s initial reaction to it based on an contractual flexibility.
extensive literature search. It is the first
stage in a Ph.D. research project The principal objectives of the NEC
examining the effectiveness of the NEC drafting team were to design a contract
undertaken by the first author with the which was flexible, clear and simple and
second author as Director of Studies. was a stimulus to good project
management (Perry, 1995).
Further research will involve the
identification of the main causes of 2.0 Initial reaction
disputes on construction projects and the
identification of the effectiveness of the Many early reviewers responded
NEC in managing these areas. favourably to the publication of the NEC
and applauded its radical approach.
Keywords Mugurian (1991) for example commented
that the form brought “a great draught of
New Engineering Contract, attitude survey fresh air and new thought into this most
difficult of subjects” and Cottam (1991)
thought “there is clearly much which is
1.0 Introduction good about the NEC”. Both authors
agreed that it would help reduce disputes
Sir Michael Latham in his report but did not believe it would eliminate
“Constructing the Team” (1994) them. Webster (1991) remarked that “it is
considered that endless refining of a sensible revision to standard forms and
existing conditions of contract would not a brave step forward”.
solve adversarial problems. He
considered that a new approach was

Cobra 1998 Conference


One commentator Chappell (1991) felt the forms of contract in order to maximise the
idea of a simple and flexible contract was financial recovery from a project.
a good one. Unfortunately in his view the
authors had followed this concept too This early skepticism was, according to
closely and consequently the NEC was Barnes (1994), being replaced by positive
needlessly complex in execution, as were reactions from contractors who had
some of its provisions. He felt that the actually carried out work under the new
NEC would only work if the philosophy of contract. Clients who had provided case
team effort was embraced by all parties study material to support these claims
and he found this difficult to visualise. included BAA, National Power, Anglian
Water, Yorkshire Water and others.
A few authors expressed serious doubts
about the form. Clarke (1993) discounted 3.0 Flexibility
the favourable comment of early users.
Whatever enlightened motives these Users of the NEC were given the
clients had in choosing the NEC he felt opportunity to decide upon a contract
that they were clearly out to make it strategy that was commercially
succeed, if only to prove that they had appropriate for the project in hand, instead
made a sensible choice. of being forced to adopt a single contract
strategy for all projects (Bill, 1987),
Webster (1991) summed up the views of (Jones, 1992)
many in the industry. He acknowledged
that by using effective management The form was suitable for use on
techniques, the parties concerned would engineering, building, electrical and
co-operate and work efficiently, which mechanical work or any combination of
would give rise to fewer disputes. He did these. The level of design responsibility
not however feel that this alone would allocated to the contractor could be varied
change ingrained adversarial attitudes. between 0% and 100% within a priced
Indeed he felt it inevitable that disputes contract with activity schedule or with bill
would occur “If relationships do of quantities, a target contract with activity
deteriorate, the loose drafting and schedule or bill of quantities, a cost
unfamiliar technology should give the reimbursable contract, or a management
claims advisors of the parties contract.
considerable scope for gainful
employment”.
Further flexibility was achieved through
the mechanism of a core text together
2.1 Industry’s reaction to the with appropriate optional secondary
form clauses. Thus the emphasis was placed
on the client allocating the risks and
The initial reaction to the NEC from the thinking through his contracting strategy in
Federation of Civil Engineering advance of the works (Cox & Thompson,
Contractors (FCEC) was to express 1996)
serious doubts that it would be much of an
aid to efficiency. Indeed it was thought The question of design responsibility was
that it would increase the workload of discussed by both Meara (1995) and
estimators and those preparing contract Cornes (1991). Meara (1995) admired how
documentation (Bill, 1987). the contractor’s design responsibility and
its extent was clearly defined within the
Wildgoose (1993) identified the industry’s works information document
mixed reaction to the NEC. He felt that (specification); “all too often within
some clients would be enthusiastic contracts where both employer and
because of their disillusionment with the contractor are responsible for a part of the
more traditional forms and the adversarial design the exact demarcation between the
relationships which they tended to respective responsibilities is blurred”.
generate. On the other hand contractors
had reacted cautiously because their Cornes (1991), on the other hand
systems and management procedures questioned why the contractor’s design
have been built around the traditional responsibility was clearly defined, but
significantly, not the obligation this
imposed. In effect statutory warranties are

Cobra 1998 Conference


imposed on the contractor because the provisions with the Contract Data section
contract was silent on the matter. they were unlikely at tender stage to
Consequently the design warranty was provide the correct information - which
one of fitness for purpose, insurance could lead to conflict at the post-contract
cover for which Cornes advised was stage.
commercially impossible to obtain. Following reviews of projects based on the
NEC Broome (1995) advised that the
4.0 Clarity compensation events clause had caused
most of the problems. He considered that
Throughout the NEC simple language has the guidance notes were deficient and by
been used and precise definitions given inference the core text was unclear.
for the activities each party must follow. Nevertheless he maintained that generally
There is easy reference to a particular at site level the NEC was found easier to
subject area because the core text is use than the traditional contract forms.
arranged into separate subject areas, such
as time, payment and insurance. 5.0 Guidance Notes
The amount of text has been kept to a One notable feature of the NEC is the
minimum and there is no confusing cross- provision of Guidance Notes. The ECC
referencing system. Likewise there is no Guidance Notes comprise 113 pages of
use of the words “fair”, reasonable” and diagrams and closely typed text. The
“opinion”. The authors of the NEC believe Introduction states that their purpose is to
that these measures permit easier provide a background to the NEC, explain
understanding of the text and will reduce why certain provisions are included and
the incidence of disputes. The absence of provide guidance for the user. There is
legal jargon and the identification of nine also a declaration that no part of the
subject areas was applauded by Mugurian Guidance Notes or the Flow Charts form
(1991) and Chappell (1991). They both part of the contract and should not be
reasoned that the clear division of function used for legal analysis.
and responsibility eliminated the need for
cross referencing and the use of simple The notes themselves provide guidance
language brought clarity. on contract strategy, tender documents
and their preparation as well as a clause
Beside the use of simple language, the by clause explanation of the contract.
NEC was reduced to the minimum by There are seven appendices which
omitting anything not considered include sample forms of tender, form of
essential. However Baird (1994) warned agreement and a worked example of the
that this meant that the contract did not Contract Data. Barnes (1991a) viewed
cover every eventuality. Subjects not the guidance notes as essential because
catered for, but required, should be of the form’s novelty and confirmed that
included in the “works information”. anything not considered essential to the
However several commentators were NEC had gone into the notes. He
unhappy about the use throughout of acknowledged that because of the
simple English and the present tense contract’s brevity the notes themselves
(Meara, 1995), (Cottam, 1991), (Cornes, might become the subject of a dispute.
1991), which they felt was at the expense Mugurian (1991) thought that the
of good grammar and clarity. They Guidance Notes were an excellent idea.
considered that the avoidance of words He commented that the courts had
and descriptions in common use meant complained about the lack of explanatory
that the form lacked any legal certainty on notes from the authors of traditional
interpretation. According to Cornes, contract forms. Without this guidance
(1991) and Cottam (1991) the lack of judges were left with no indication of the
cross referencing made the form difficult drafters’true intentions and were left with
to understand as a whole. In particular unenviable task of second guessing their
they stressed the importance of properly motives. The size of the Guidance Notes
completing the Contract Data section was commented on by Meara (1995) and
(appendix), which defined the contract Chappell (1991), which is larger than the
information and specified the performance NEC itself. They thought the document
parameters required. Unless the parties unnecessarily copious and considered that
understood and connected the contract

Cobra 1998 Conference


a first-time user might find them difficult to abitrational powers. He is expected to be
follow and understand. a “hands on person”, site based and
available to make prompt decisions.
6.0 Stimulus to good project
The conflict of interests under the
management traditional contracts have been avoided by
dividing the engineer’s/architect’s duties
The Guidance notes to the ECC 2nd into four separate and clearly defined
edition state that the contract is based roles of: designer, project manager,
upon two principles: supervisor and adjudicator.

1. foresight applied collaboratively Mugurian (1991) and Clarke (1993)


mitigates problems and shrinks risk approved of these split roles, but Allen
2. clear division of function and (1991) warned that there would be
responsibility helps accountability and substantial rear-guard action to preserve
motivates people to play their part the role of the engineer (or architect) as
an even-handed arbitrator between
Barnes (1991b) and his team believed this employer and contractor. Mugurian
would promote a spirit of co-operation and (1991) commented that it was impossible
foresight and “still provide a commercial to reconcile the role of designer and quasi
incentive for the contractor”. In addition, - arbitrator under the traditional forms
every function was examined and because of “the requirement of his
designed so that it contributed towards a professional indemnity insurance whereby
successful outcome for the employer, the he is obliged to deny all negligence or
main contractor and the sub-contractors - liability”.
a common interest. The procedures set
down are fashioned so that people and Birkby (1993) emphasised the
organisations are commercially motivated considerable responsibility that the project
to follow them. Then “we will have shrunk manager was now given and the need
the adversarial dimension” (Allen, 1991), therefore for a technically qualified
in other words removed most of the person, or failing this substantial technical
grounds for dispute. support. He would, for example, be
responsible for issuing instructions to
Nicholson (1992), confirmed the change the design and assessing the
explanations given by Barnes. In addition contractor’s own design and the liability in
he emphasised the importance given to this respect was considerable.
the early resolution of disputes. However
Cottam (1991) questioned whether people
would work in the manner intended.
7.0 Contract Data

The good management procedures are The Contract Data section provides the
identified by Cox and Thompson (1996) definition of the details of the contract
as: active planning and programming, agreement and corresponds to the
early warning procedures, advanced appendix found in traditional forms. There
quotation and assessment, tight response are two sections in the Contract Data.
periods for administrative matters and
quick resolution of disputes. However Cox Part One is completed by the employer
and Thompson identify that the and is issued to tenderers; it contains the
administrative procedures may prove to names of the project manager, supervisor
be a “burdensome (and expensive) and adjudicator together with the works
challenge for site management”. and site information. It also includes
details of the contract type and any
secondary options chosen.
6.1 Use of the Project Manager
Part Two is completed and returned by
The project manager is appointed by the tenderers as part of their offer and
employer to manage the contract and act contains the names and details of key
on his behalf. Unlike the engineer under personnel, any data required for contract
the ICE 6th or an architect under JCT80 options chosen by the employer, data for
the role of the project manager is not the schedule of cost components including
independent and he has no quasi- the fee and overhead percentages.

Cobra 1998 Conference


needs careful consideration before use.
The majority of commentators welcomed The principle behind the clause is that the
the amount of detail which the contract employer’s risks are stated and all other
data schedules required from both parties. risks are the contractor’s. Mugurian (1991)
Baird (1994) stated that the thought and believed that the clause now clearly
care necessary to properly complete the defined the risks allocated to each party
Contract Data would provide both parties “The risks ..... are now for the first time in
with a “much greater awareness of what any conditions of contract
the contract actually means and requires comprehensively and accurately defined”.
of them”.
Mugurian (1991) and Wildgoose (1993) 9.0 Compensation Events
agreed with this view and commented that
it should ensure that misunderstandings Compensation Events are events which if
are less likely to occur. At the very least, they occur through no fault of the
they believed, it would provide a useful contractor, compensate for the time and
checklist for both parties to follow. cost effect of the event. The contractor is
required to prepare a quotation for a time
Baird (1994) warned that the schedules and cost assessment of the event. If the
must be prepared by skilled and capable quotation is accepted by the project
people. Cottam (1991) felt the contract manager it remains a firm price,
required “a bewildering amount of regardless of the actual time and cost
information to be supplied” and in his outcome. This arrangement for dealing
experience practitioners had not always with compensation events benefits both
correctly completed the simple appendix parties. The employer gains price and
to the ICE contract. Obviously if Cottam’s time certainty. The contractor gains as it is
(1991) views prevail then the likelihood of his own forecast of the time and cost
disputes would not be diminished. impact which forms the basis of
reimbursement. This radical approach to
8.0 Core clauses the valuation of changes was praised by
the great majority of commentators.
The “pick and mix” concept of core text Mugurian (1991) believed “this is an
with the addition of appropriate optional excellent way of dealing with the financial
clauses was not a new concept, although consequences of changes or unforeseen
it had never before been included in a consequences of changes, including
standard contract form (Chappell, 1991). delays”. Cottam (1991) also considered
Parry (1995) cautioned that disputes are that this approach benefited the contractor
less likely when and contract type is and employer alike.
selected which ensured the minimum of
compensation events, which as Broome Opinions amongst reviewers differed on
(1995) confirmed, are the major cause of what was meant by the term
dispute when using the NEC. If the “Compensation Event”. Knowles (1991)
project design was unfinished at tender explained that it was a new name for
stage, the employer should consider a “claim”, whilst Chappell (1994) described
management (Option F) or a cost it as a variation, extension of time and
reimbursable (Option E) contract rather loss and expense claim rolled into one.
than a lump sum contract (Option A and
B). Completing the design, then issuing The assessment procedure, according to
changes as Compensation Events was, in Wildgoose (1993), sought to diffuse the
principle, wrong. Parry (1995) advised that “traditionally adversarial nature of such
when using the NEC for building projects, matters”, but he wondered if problems
where significant numbers of variations would occur when assessing large
are commonplace, the design should be numbers of Compensation Events.
“substantially complete” if a lump sum Broome (1995) had found that some
contract was envisaged. clients avoided this by grouping
compensation events together for
The ECC substantially revised core clause assessment purposes. Bolton (1993),
8 “Risks and Insurances”. It is now far advised that Contractors and employers
more straightforward and easy to had commented positively about the NEC,
understand; however it is brief and given especially the joint assessment of time
the importance attached to this area and cost. However he found that

Cobra 1998 Conference


contractors were less keen on the level of works information (specification)
detail required document. Baird (1994) also warned of
this problem and provided a list
10.0 Programmes (incomplete) of possible subjects for
consideration.
Broome’s (1995) investigations into the
The NEC requires the submission of the
use of the NEC found the need for
contractor’s first programme within the
participants to receive training was a
time specified in the Contract Data
“massive undertaking”. His conclusion, the
(appendix). Failure to do so results in the
same as Meara (1995) was that
retention of one quarter of any payments
contractors would be unwilling to invest in
due. Revised programmes are submitted
staff training until such time as use of the
at regular intervals, the effect of a
NEC became widespread. The likelihood
compensation event is assessed based on
of this happening, has to some extent,
the latest accepted programme.
increased with Sir Michael Latham’s
Wildgoose (1993) and Chappell (1994)
recommendations that the NEC should be
both viewed these arrangements as a
widely used.
refinement of familiar procedures. The
emphasis was on ensuring that both
parties possessed a current programme. Another author (Baird, 1994) with
The requirement to give early warning of experience of using the NEC confirmed
problems provided a valuable Broome’s (1995) observations on training.
management tool that should assist in But he argued that any training costs
developing a team approach “rather than incurred would be offset by better
merely historical data to be used only in management practices and a better
the analysis of claims” (Chappell, 1994). understanding of the risks involved. This
should reduce the incidence and “the
effect of claims which have arisen in the
11.0 Training past as a result of poor initial definition or
attention to detail in the contract
Several commentators highlighted the documentation”.
need for adequate staff training before the
NEC was used (Birkby, 1993; Meara,
1995). Obviously the form was new and its
12.0 Conclusions
procedures needing explaining, but staff
should also become familiar with the The initial response from experts within
form’s novel characteristics and the roles the construction industry on the NEC was
and responsibilities of the parties generally favourable. Many thought the
involved, which were often different from use of simple language and the adoption
traditional practice. It was particularly felt of management techniques which
that the Contract Data section which encouraged cooperation and teamwork
required completion at pre-tender stage, would reduce the likelihood of disputes,
and the provision of quotations for although some writers felt that this alone
Compensation Events, were two would not change ingrained adversarial
procedures which required an in-depth attitudes.
knowledge of the form and considerable
care in preparation. At site level, users generally found the
NEC easier to use than the traditional
Chappell (1994) maintained that the form contract forms, with most of the problems
would not be simple to use and advised arising over compensation events.
everyone intending to use the form to However adequate staff training was
spend time getting to grips with it; “it is not considered essential before using the
just a legal document enshrining rights form, because of its novel characteristics
and duties”. Besides the philosophy of and different roles and responsibilities of
teamwork and the detailed tendering the parties.
process, he highlighted the exclusion from
the core text of anything not considered The exclusion of anything not considered
essential, which is one reason for the essential from the core text was
form’s relatively short length. Users will highlighted and the need for including
need to identify the excluded subjects and every other relevant issue in the Works
where necessary include them in the Information; this being a potential area of
ambiguity and hence dispute.

Cobra 1998 Conference


Clarke J R (1993), NEC - thoughts and
A general reluctance to change to a questions, Civil Engineering Surveyor,
radically different contract was main July/August, p 14
obstacle to be overcome. Some
commentators welcomed the new roles of Cornes D & Barnes M (1991),
the engineer or architect with the Controversial Contract, New Builder, 31
introduction of the project manager. Jan., pp. 20-21
However they warned that engineers and Cottam G (1991), ICE set for user-friendly
architects are unlikely to recommend a contract, Construction News, Jan. 24, p 13
form of contract which considerably
reduced their own authority and workload. Cox A and Thompson P (1996), Is the
NEC going to succeed? - an examination
Bibliography of the Engineering and Construction
Contract (alias the NEC 2nd edition), The
Allen J D (1991), Civils heads latest effort International Construction Law Review, pt
to curtail disputes, Construction News, 24 3, pp 327-337
January, p 6
Jones E (1992), New Engineering
Baird A (1994), New Engineering Contract Contract, Constructional Law, 20,
- A management summary for plant Dec./Jan. pp. 182-184
industry users, International Construction
Law Review, 11 Apr., pp 114-127 Knowles R (1991), The NEC: a user’s
guide, Chartered Quantity Surveyor, June,
Barnes M (1991a), Civil Engineering p 8.
Surveyor, November 5, p 5
Latham M (1994) Constructing the Team -
Barnes M (1991b), 1991 Cambridge Final Report of the Government/Industry
Lecture: The New Engineering Contract, Review of procurement and contractual
Construction News, Nov. pp 4-6 arrangements in the UK construction
industry, HMSO, London
Barnes M (1994), The New Engineering
Contract: a promising start, ICE Meara C (1995), Using the New
Proceedings, 102, Aug., pp. 94-95 Engineering Contract, CSM, March, pp.
24-25
Birkby G (1993), New Engineering
Contract - not just for engineers, Project, Mugurian G (1991), The New Civil
Nov., pp 16-17 Engineering Contract, Civil Engineering
Surveyor, May, pp 18-20
Bill B (1987), Barnes Storms Another
Nicholson T (1992), The New Engineering
Contract, Building, 18 September 1987,
Contract, Proceedings of the ICE, Civil
pp 32-33
Engineering, vol. 92, issue 4, Nov., pp
146-148
Bolton A (1993), Clear for take off, New
Builder, April 2, p 15
Parry A (1995) The NEC in Hong Kong,
Engineering, Construction and
Broome J (1995), Experiences of the use
Architectural Management, vol. 2, issue 4,
of the New Engineering Contract,
p 310
Engineering, Construction and
Architectural Management, vol. 2, issue 4,
Perry J (1995), The New Engineering
pp 271-285
Contract: principles of design and risk
allocation, Engineering, Construction and
Chappell D (1991), New Contract NEC Architectural Management, vol. 2, no. 3,
Reviewed, Architects Journal, 5 June, pp pp 197-208
53-55
Webster M (1991), New Engineering
Chappell D (1994), The New Engineering Contracts - the 19912 Mancunian Lecture,
Contract, Architect’s Journal, 3 Nov. p 47 Civil Engineering Surveyor, Oct. 1991, pp
12-13

Cobra 1998 Conference


Wildgoose I (1993), Building Law Digest,
pp 328-331

File: cobranec (50)

Cobra 1998 Conference

You might also like