Professional Documents
Culture Documents
Abstract: Building information modeling (BIM) is rapidly restructuring the construction industry, offering major enhancements in project
outcomes. Although the emerging demands for BIM adoption are developing to become an industry norm, there are still uncertainties con-
Downloaded from ascelibrary.org by Heriot-Watt University on 11/07/22. Copyright ASCE. For personal use only; all rights reserved.
cerning the ability of the existing legal paradigm to fully incubate and promote BIM. Existing conventional construction contracts do not cope
with the collaborative approach of BIM, causing potential contractual disputes to arise. These contractual disputes may become obstacles in
the sufficient implementation of BIM and achieving anticipated productivity gains. This research aims to identify the provisions in the
contract that should be addressed when BIM is utilized in the project. The research highlights the main contractual issues associated with
BIM and explains the current treatment of BIM in contractual documents from standard forms of contracts and BIM protocols. The directed
content analysis method is used to analyze three main standard forms of contracts that adopt BIM and have a different approach to drafting,
covering multiparty agreement, partnering agreement, and standard biparty agreement. A comparative study is held between the contracts
under investigation. The research presents and assesses the extent to which these standard forms of contracts deal with the contractual issues
identified and accordingly the research proposes a drafting structure and framework for provisions that should be included in a BIM-based
contract. DOI: 10.1061/(ASCE)CO.1943-7862.0002123. © 2021 American Society of Civil Engineers.
Author keywords: Building information modeling (BIM); Contractual issues; Standard forms of contracts; Content analysis.
does not mean that parties’ liabilities are diluted when compared to
proach regarding the status of the granted model license in case traditional models (Winfield 2015).
of nonpayment. According to ConsensusDOCS 301, a party not
entitled to initiate the right of suspension or revocation until a de-
cision of a court or arbitration. It also creates a waiver in favor of
other project team members not directly involved in the payment Information Loss Issues
dispute by excluding them and licenses issued by them from any According to the National BIM Report (NBS 2015), 26% of the
liability on account of the suspension or revocation of the IP/ respondents developed a BIM model over the last year using more
copyright rights.
than one type of software. Winfield and Rock (2018) clarified that
interoperability issues take place during information transmission
Risk Allocation between different systems due to the insufficient integrity of data. It
is difficult to withhold the same consistency of integration for
BIM caused significant change in the allocation of risk and liabil- shared information in a multidisciplinary platform (Olatunji 2014).
ities due to its collaborative nature, which differs from the traditional This is because multiple disciplinary users tend to select the infor-
procurement and contractual models that depend more on definite mation of their point of interest, which they will use in their
and single obligations. Moreover, new types of risk emerged related own discipline, leading to distortion of information (Amor et al.
to dissipation of shared data, clash detecting, and integrity of data. 2007).
Single roles and responsibilities of a traditional legal framework The ability to rely on the shared information between different
may not fit with BIM (Dastbaz et al. 2017). Mosey et al. (2016) disciplines and parties is a vital issue to implement BIM efficiently
indicated that BIM provides designers working together with major (Arensman and Ozbek 2012). Although, in a BIM project, parties
enhancements when it comes to risk management. One of the key should anticipate receiving a model free of omissions and defects
features of BIM is that it facilitates detecting any design deficiencies and be able to rely on the model and the information included
that occur due to conflicts that arise from different design disciplines within during their model development, parties are also keen to
(e.g., structural and mechanical, electrical, and plumbing (MEP). limit their liability once the model has left their control. This leads
These deficiencies can be detected and resolved through clash de- to the loss in efficiency of the BIM process as many parties
tection facilitated by BIM, but the process of detecting and resolving redevelop the model from two-dimensional drawings because they
such clashes can cause an extra burden of effort, usually with no do not rely on the transmitted model and responsibility of the model
predefined fee. Furthermore, the liability of resolving clashes is left data validity against omissions when transmission is ambiguous
in practice to bargaining power between parties with no clear role of (Larson and Golden 2007).
assigned responsibilities. In order to overcome such an issue, unam- Furthermore, the issue of assigning the risks associated with
biguous procedures should be stated defining the steps to be taken in model integrity was addressed by BIM protocols in different
respect to clashes that were detected and could not be resolved con- approaches (Fan et al. 2018). According to ConsensusDOCS Sub-
sensually in design team meeting. Another feature that distinguishes clause 3.1, the architect/engineer, contractor/construction manager,
BIM is the management of the common data environment (CDE) or any other party may be designated as the information manager
and the federated model and by default who will be assigned the (IM). ConsensusDOCS adopts a check-the-box approach and im-
risks associated with such responsibility (Mosey et al. 2016). poses on the IM numerous duties, including maintaining the model
and all appropriate records. ConsensusDOCS 301, Subclause 5.1 at-
tempts to address the issue of liability by specifically enumerating
BIM and Collaboration
the risk allocation between the parties, “Each party shall be respon-
The National Building Specification (NBS) National BIM Report sible for any Contribution that it makes to a Model or that arises from
(NBS 2015) stated that 57% of the respondents to the NBS National that Party’s access to that Model. Such responsibility includes any
BIM Survey agreed that BIM is “all about real time collaboration” Contribution or access to a Model by a Project Participant
and 31% considered loss of collaboration as one of the main ob- in privity with that Party and of a lower tier than that Party.” Fur-
stacles to implement BIM. The approach to promote collaboration thermore, concerning the right to rely on other documents, Consen-
under contractual terms as optional or nonbinding will not succeed susDOCS Subclause 5.1 states, “To the extent any or all Design
and collaboration will be marginalized once a dispute arises, which Models are included as Contract Documents, Project Participants
is very common in the construction industry (Winfield 2015). Fur- may rely upon the accuracy of information in those Design Models.”
thermore, an effective contract must encourage and obligate parties The CIC BIM protocol adopts a different approach, as under
to act collaboratively during the project. Traditional contracting re- Clause 5 project team members are not liable for the integrity
sults in neglecting the significance of the contract and lead to the of electronic data transmission or alteration after transmission,
tion industry about development of neutral, open platforms for sis goes beyond merely counting words to examining language
graphical model exchange, such as Industry Foundation Classes intensely for the purpose of classifying amounts of text into an ef-
(Benghi and Greenwood 2018). ficient number of categories that represent similar meanings (Weber
Mosey et al. (2016) discussed the exclusion of liability for BIM 1990). Content analysis is a set of systematic procedures, which is
software providers and empathized the significance of this issue segregated from the personal preferences of the researcher allowing
because software vendors typically limit their liability for any de- more objective results when compared to other techniques such as
ficiencies that occur. As an example, the Autodesk software user expert elicitation or interviews. As a research technique, content
will be governed by the standard Autodesk license and services analysis provides new insights and increases a researcher’s under-
agreement (Autodesk 2015), which limits any warranty to no more standing of particular phenomena. In addition, content analysis can
than 90 days and any remedy shall not exceed a refund for the easily be learned and replicated by other researchers, yielding re-
license fees. As a result, accepting such exclusions and limitations sults with high reliability (Krippendorff 2010). According to Elo
of liability might cause clients to doubt the adoption of BIM, which et al. (2014), content analysis allows direct examination and more
mostly relies on the sufficiency on the software used. The case of closeness to the data. Furthermore, it allows for both qualitative and
M. A. Mortenson Co. v. Timberline Software Corp. (1999) clearly quantitative analysis. Previous publications used content analysis to
emphasizes the limited liability of software vendors (Alwash et al. analyze contracts, such as Patterson and Trebes (2013) and Gibbs
2017). Contracts need to stipulate clearly the assigned responsibil- et al. (2015).
ities in case of information loss due to defects in the integrity of The approach model adopted in the research was a directed con-
data or software errors because ambiguity in such clauses could tent analysis approach. According to Hsieh and Shannon (2005),
lead to disputes (Winfield 2015). directed content analysis is used to provide a more detailed under-
standing of an available theory or an existing relevant study. The
initial coding schemes are developed based on previous relevant
Professional Legal Duty studies. The findings of the analysis either extend a further detailed
understanding of the initial hypothesis of the research or offer a
The standard of care suggests that architects are liable to perform contradicting perspective of such hypothesis. The availability of
their services with adequate care, relative to other practicing such research background enables the research to be precise and
professionals in the same field (Macdonald 2012). Furthermore, narrow the study scope. Furthermore, it can facilitate in identifying
professionals should keep pace with all the emerging technology the coding scheme and aspects of interest to determine the catego-
and developments considered as a norm in their field while accom- rizing system. This approach is recognized as a deductive category
plishing their scope of work. Mosey et al. (2016) referred to the application (Flick et al. 2004). The legal issues in Table 1 were used
case law of Wimpey Construction UK LTD v. D V Poole (1984), to initiate the coding scheme used in the directed content analysis
which stated that consultants are responsible to perform their pro- process to investigate the approach of each contract form in
fession according to the state of the art at the time of providing addressing such issues.
consultancy services. Because BIM is being adopted in the
construction sector with all its potential capabilities to optimize
productivity and reduce errors and conflicts in construction proj- Research Framework
ects, this will lead project owners to increase the level of perfor- To sufficiently meet the set objectives, this study is conducted in
mance they expect from architects (Pressman 2007). After the five main steps, as shown in Fig. 1. These steps are (1) identification
adoption of BIM in the construction sector, there will be an issue of the initial coding scheme, (2) selection of the unit of analysis,
of identifying what is reasonable for the previously mentioned (3) developing sense of the whole, (4) analyzing the contract
duties of designers (Mosey et al. 2016). Furthermore, according forms, and (5) cluster analysis. The identification of the initial
to Fan et al. (2018), the standard of care in BIM projects may coding scheme step involves a review of the literature to identify
be altered because BIM leads to additional contractual liabilities the contractual aspects associated with BIM such as Cerimagic
on project participants and further research is needed to approach et al. (2015), Winfield (2015), Mosey et al. (2016), Chong et al.
such issue. (2017), Alwash et al. (2017), Winfield and Rock (2018), Fan et al.
Mosey et al. (2016) highlighted that the CIC BIM protocol (2018), and Arshad et al. (2019). Moreover, these contractual
Clause 4, “Obligations of the Project Team Member,” is inconsis- aspects are further divided into subcategories and the keywords as-
tent with most standard forms of contracts. The protocol adopts an sociated with each subcategory are identified, as shown in Table 1.
approach were project parties are liable for “reasonable endeavors” Subsequently, selection of the unit of analysis is performed, and
when undergoing their duties, which is a lower, reduced duty of three main standard form of contracts were selected based on three
care than the custom “reasonable skill and care.” criteria:
Professional legal duty Standard of care Duty of care, reasonable skill and care, reasonable endeavor
• The drafting body recognized and considered BIM when pub- • Most updated versions with newest amendments were
lishing its standard contract forms, studied.
• Previous relevant studies that would be a benchmark and strong The previous selected contracts are PPC2000, NEC4 ECC, and
basis to initiate further detailed analysis were available, and JCT CE. The previous contacts were described by Saxon (2013) as
the forefront of contracts developing a new era of construction
contracts.
The third step of the study is developing a sense of the whole
and is initiated by conducting an overview of each of the contracts
in order to develop a complementary understanding of the contract
clauses and to identify keywords used in the contract forms related
to the previously identified contractual subcategories. Finally, ana-
lyzing the contract forms takes place utilizing ATLAS.ti data analy-
sis software to analyze the contract forms. The analysis defines
contractual categories as code groups and subcategories as codes,
the identified keywords are used to filter the contract clauses, and
keywords are allocated to relevant contact clauses forming quota-
tions. Codes are assigned to relevant quotes; this is followed by
formulating a network diagram illustrating each code group. The
number of quotations associated with each code is shown in the
network diagram, for example, irrevocable license is associated
with two quotations (G ¼ 2), while the number of links (density)
a quote has with other codes is shown as D, for example, Subclause
4.10 of the JCT CE is linked with three codes (D ¼ 3). Finally,
cluster analysis is performed using results from ATLAS.ti to study
each code group and determine the different adopted approaches
associated with each contractual issue. Fig. 1 depicts the flowchart
of the proposed framework in this research.
Subclause 9.1 of the PPC2000 provided for intellectual property of assigned quotes (G ¼ 6), and JCT CE Subclause 4.10 and PPC
rights between all parties signing the partnering agreement. In ad- 2000 Subclause 9.2 have the highest density assigned to three
dition, any partnering member shall be liable to compensate for any codes (D ¼ 3).
breach related to IP rights. Under Subclause 9.2 of PPC2000, the
originator of any contribution throughout the project is entitled for Risk Allocation Aspects
intellectual property rights. Furthermore, each partnering team According to Fig. 5, which illustrates the word cloud for risk
member shall grant the client and other partnering team members allocation aspects, the most frequent words used are as follows:
an irrevocable license to use the designs and relevant documents for early (26), warning (26), project (14), manager (10), and meeting
purposes of completion of the project, and only the client shall be (10). Under Subclause 3.7 of PPC2000, all partnering members
granted a similar license for operation of the project. In addition, shall adopt an early warning system, which provides that each
the client has the right to transfer such license to other parties for partnering team member shall be obligated to notify other team
the same purposes. members once they become aware of a potential risk that might
According to Subclause 9.2, partnering members shall ensure the affect the project. Such notification shall include proposals
that similar terms shall govern sublicense from any relevant supply on how to overcome such risk. Furthermore, the proposal shall
chain member (e.g., subcontractors) that contribute to the model be referred to the core group for agreement on the course of action
development. Subclause 9.3 stipulates the use of any design con- to be taken. As discussed previously, the ability of a party to rely on
tribution to the intended purposes for which they were prepared others’ contribution to the model is vital for a sufficient integrated
unless agreed otherwise. According to Subclause 9.5, which is in- process. According to Subclause 2.4, each partnering team shall
serted in case BIM is used, any data, software, or other item related bear consequences of their contribution to the partnering docu-
to BIM is recognized as part of the design and is subject to all reg- ments, which includes the BIM model. The PPC2000 contract
ulations concerning ownership and IP discussed in Clause 9 of under Subclause 3.10 mentions that partnering team members shall
PPC2000. consider arrangements of the common data environment such as
Subclause 22.1 of NEC4 ECC provides for the entitlement of shared database and networks, subject to Clause 25.5 concerning
the Client to use the contractor’s design for any purpose related confidentiality.
to “construction, use, alteration or demolition of the works.” Fur- NEC4 ECC includes Clause 15, which provides for early warn-
thermore, Option X10.6 of NEC4 grants the client the ownership of ing. According to Subclause 15.1, both the contractor and project
the model and the contractor’s information contribution to the manager shall initiate a warning once aware of any matter that
model. The clause also provides that such ownership rights are could lead to increase in price, delay schedule, or affect work per-
formance. The project manager shall record such matter in the early
warning register. Furthermore, according to Subclause 15.2, the
project manager or contractor is entitled to invite other relevant
parties to attend an early warning meeting if the other approves.
Following the call for an early warning meeting, Subclause 15.3
instructs that the attendees of such meeting cooperate in reviewing
proposals and “deciding on the actions which will be taken and
who, in accordance with the contract will take them.”
Furthermore, NEC4 ECC includes Option X10: Information
Modeling, which clearly states, “The Contractor and the Project
Manager give an early warning by notifying the other as soon
as either becomes aware of any matter which could adversely
affect the creation or use of the Information Model.” Also, in
Option X12: Multiparty Collaboration, early warning is mentioned
as “Each Partner gives an early warning to the other partners
when it becomes aware of any matter that could affect the achieve-
ment of another Partner’s objectives stated in the Schedule of
Partners.”
The formulated network diagram for risk allocation aspects is
shown in Fig. 6. Clash detection has the most assigned quotes
(G ¼ 7), and all of the quotes are assigned to only one code
Fig. 3. Word cloud for model ownership code group.
(D ¼ 1).
© ASCE
04021094-10
Fig. 6. Risk allocation network diagram.
protocols and the precedence of documents in a BIM project. Fur- Amor, R., Y. Jiang, and X. Chen. 2007. “BIM in 2007—Are we there yet?”
ther research should consider the impact of BIM on the accepted In Proc., CIB W78 Conf. on Bringing ITC Knowledge to Work, 26–29.
professional legal duty (standard of care) and drafting standards to Auckland, New Zealand: International Council for Building Research
adopt such an impact. Studies and Documentation.
Arayici, Y., P. Coates, L. Koskela, M. Kagioglou, C. Usher, and K.
O’Reilly. 2011. “Technology adoption in the BIM implementation
for lean architectural practice.” Autom. Constr. 20 (2): 189–195.
Data Availability Statement https://doi.org/10.1016/j.autcon.2010.09.016.
Arensman, D. B., and M. E. Ozbek. 2012. “Building information modeling
Some or all data, models, or code that support the findings of this and potential legal issues.” Int. J. Constr. Educ. Res. 8 (2): 146–156.
study are available from the corresponding author upon reasonable https://doi.org/10.1080/15578771.2011.617808.
request. Arshad, M. F., M. J. Thaheem, A. R. Nasir, and M. S. A. Malik. 2019.
“Contractual risks of building information modeling: Toward a stand-
ardized legal framework for design-bid-build projects.” J. Constr. Eng.
References Manage. 145 (4): 04019010. https://doi.org/10.1061/(ASCE)CO.1943
-7862.0001617.
ACA (Association of Consultant Architects). 2013. ACA standard form of Ashcraft, H. W. 2008. “Building information modeling: A framework for
contract for project partnering. Bromley, England: ACA. collaboration.” Constr. Law 28 (1): 5.
AIA (American Institute of Architects). 2013. Building information Autodesk. 2015 “License and services agreement.” Accessed April 7, 2020.
modeling and digital data exhibit. AIA E203-2013. New York: AIA. https://www.autodesk.com/company/legal-notices-trademarks/software
AIA (American Institute of Architects). 2017. Standard form of agreement -license-agreements-legacy#1.
between owner and architect. AIA B101. New York: AIA. Benghi, C., and D. Greenwood. 2018. “Constraints in authoring BIM
Akintan, O. A., and R. Morledge. 2013. “Improving the collaboration components: Results of longitudinal interoperability tests.” In Proc.,
between main contractors and subcontractors within traditional con- Contemporary Strategies and Approaches in 3D Information Modeling,
struction procurement.” J. Constr. Eng. 2013: 1–11. https://doi.org/10 27–51. Hershey, PA: IGI Global.
.1155/2013/281236. Buchanan, D., L. Fitzgerald, D. Ketley, R. Gollop, J. L. Jones,
Alashwal, A. M., H. A. Rahman, and A. M. Beksin. 2011. “Knowledge S. S. Lamont, A. Neath, and E. Whitby. 2005. “No going back: A
sharing in a fragmented construction industry: On the hindsight.” review of the literature on sustaining organizational change.” Int. J.
Sci. Res. Essays 6 (7): 1530–1536. Manage. Rev. 7 (3): 189–205. https://doi.org/10.1111/j.1468-2370
Alwash, A., P. E. D. Love, and O. Olatunji. 2017. “Impact and remedy .2005.00111.x.
of legal uncertainties in building information modeling.” J. Leg. Aff. Cerimagic, S., J. Smith, and J. J. Ochoa. 2015. “Communication
Dispute Resolut. Eng. Constr. 9 (3): 04517005. https://doi.org/10.1061 and relationship building in cross-cultural project management: An
/(ASCE)LA.1943-4170.0000219. Australia-UAE study.” In Proc., Construction, Building and Real Estate