3 Week Look Ahead Schedule

3865 - UTM 2019-20-06 RO Project May 2020


Ashwin Rodrigues Mon Tues Wed Thur Fri Sat Sun Mon Tues Wed Thur Fri Sat Sun Mon Tues Wed Thur Fri Sat Sun
May May May May May May May May May May May May May May May May May May May May May

Activity Description Areas Affected 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 Noise Rating After Hours Work


Penthouse
Electrical Installation Block A Penthouse x x x x S
Equipment Layout Block A Penthouse x x x x T
RO Piping Installation Block A Shaft A x x x x x x x
T

H
O
L
I
D
A
Y

LEGEND NOISE DESCRIPTION RATING


Construction Activity None N/A
Construction Milestone Low Noise Activity (no audible sound for adjacent labs)
Low to Medium Noise Activity (audible sound to adjacent labs)
UTM Activity Medium Noise Activity (audible sound to labs above and below)
UTM Milestone Medium to High Noise Activity (audible sound within the building section)
High Noise Activity (will have significant impact on building)