SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - Mar 2013) Rev 7 Mar-13

SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER

Air Handling Unit (AHU) Installation SAIC-K-4005 30-Apr-13 HVAC


PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

Air handlers, refrigeration condenser units, pumps, or any equipment


mounted outside shall be mounted on a concrete housekeeping pad, at a SAES-K-001
A1
minimum of 100 mm (4") above the floor or a minimum of 150 mm (6") Para 5.1.1
above unpaved ground.
AHU's shall be installed at the location indicated on the drawings and in SAES-K-001 Para
A2
accordance with details of mounting. 5.1.7
Evaporators of air handling units shall be mounted a minimum of 150 mm SAES-K-001 Para
A3
(6 inch) off the floor, to allow room for condensate trap. 5.3.4.1

Equipment clearance shall be provided with a minimum of 1 m clearance


on each side of equipment with openable panel or controls, unless SAES-K-001 Para
A4
equipment manufacturer requires greater clearances. Adequate space 5.1.4
shall be provided for coil removal.

SAES-K-001 Para
A5 Fans shall be V-belt driven with drive rated at 150% of fan rated power.
4.8.9.3

A raw water hose bib with a pressure-type anti-siphon valve shall be used SAES-S-060
on each hose connections and shall be provided within close proximity Para 603.4.23(b)
A6 (not to exceed 10 feet) of HVAC equipment that require periodic washing.
Note: Whether the equipment requires periodic washing or not is SAES-K-001
determined by either the designer, manufacturer or proponent. Para 5.1.9

Reciprocating compressors shall be vibration isolated from the unit, and


SAES-K-001 Para
A7 frame shall have vibration isolation (such as a vibration pad) between
4.8.14.2
equipment and equipment base.

Reciprocating compressors shall be vibration isolated from refrigerant line


SAES-K-001 Para
A8 connections by the use of flexible pipe connectors (as per manufacturer's
4.8.14.2
recommendation).

Casings shall include doors to provide maintenance and removal access SAES-K-001 Para
A9
for all fans, motors, coils, filters, and humidifiers. 4.8.8.7

Access doors or frames shall have resilient gasketing material to prevent


SAES-K-001 Para
A10 air leakage. Access doors shall have corrosion-resistant hinges and
4.8.8.7
positive latches.*

Spring vibration isolators shall be provided on moving or rotating


SAES-K-001 Para
A11 equipment within the housing of the units in accordance with ASHRAE
4.8.14.4
recommendations.

SAES-K-001 Para
A11 Vibration isolators shall be provided between AHU and foundations.
4.8.14.1

The tag or name plate shall be located such that the information is visible SAES-K-001 Para
A12
and can be read after equipment installation 4.8.1.2.2

* Verification is required by checking the equipment submittal if verification is not possible by visual inspection
REMARKS:

REFERENCE DOCUMENTS:
1-SAES-K-001 -- Heating, Ventilating and Air Conditioning (HVAC), 5 Dec 2012

Contractor / Third-Party Saudi Aramco


Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Inspector PID Representative


Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others

Page 1 of 2
Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED

Page 2 of 2