EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Duct liners in systems operating with air velocities exceeding 2,000 feet
per minute (10.2 m/s) shall be fastened with both adhesive and
mechanical fasteners
SAES-K-100
A4 Note: Air velocities may be read from the contract specification or
Section 1
Drawings. However, if the air velocities are not shown, the expected air
velocity at the concerned duct section (s) shall be provided by SAPMT
through designers
Ducts shall be insulated in accordance with Table 6-D of the Uniform SAES-K-001
A5
Mechanical Code. See attachment no. 1 Para 4.8.13.1
Page 1 of 3
SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Metal Duct Insulation Installation SAIC-K-4015 18-May-05 HVAC
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
REMARKS:
REFERENCE DOCUMENTS:
1-SAES-K-001 -- Heating, Ventilation and Air Conditioning, May 31, 2004
ATTACHMENTS:
1. Table 6-D-Insulation of Ducts
Page 2 of 3
SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Metal Duct Insulation Installation SAIC-K-4015 18-May-05 HVAC
Attachment 1 --
1997 UNIFORM MECHANICAL
Page 3 of 3