SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)

SAIC NUMBER DATE APPROVED QR NUMBER


SAUDI ARAMCO INSPECTION CHECKLIST
Metal Duct, Hangers and Supports and Insulation Receiving SAIC-K-4008 18-May-05 HVAC
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
A General
Schedule “Q”
A1 Delivered equipment and material shall be free of damage. Attachment IV
Para 7.1
B Metal Duct Hangers and Supports
Duct Hangers and Support material shall be in accordance with table SAES-K-100
B1
6-E of UMC (UMC Section 603). See attachment 5 Section 1

Duct Hangers and Support size and thickness shall be in accordance SAES-K-100
B2
with table 6-E of UMC (UMC Section 603). See attachment 5 Section 1
C Metal Ducts
Duct wall thickness of the supplied sheet metals for positive pressure
SAES-K-001
C1 ducting systems shall be as per the attached table. See attachment 3 &
clause 4.8.12.5
4 (UMC tables 6-A and 6-B)
Duct wall thickness of the supplied sheet metal thickness for negative
SAES-K-001
C2 pressure ducting system shall be as per the attached table. See
clause 4.8.13.1
attached tables See attachment 1 & 2 (UMC tables 5-B & 5C)
Galvanized steel sheet metal shall have a coating class of not less than SAES-K-100
C3
G-90 (UMC Section 602) Section 1
Grease ducts and plenums serving a Type I kitchen hood shall be
constructed of at least 0.055-inch-thick (1.40 mm) (No. 16 manufacturers
SAES-K-100
C4 standard gauge) steel or stainless at least 0.044 inch (1.10 mm) in
Section 1
thickness.
(UMC Para 507.3)
D Metal Duct Insulation
Faced insulation of metal ducts shall be legibly printed with the name of SAES-K-100
D1
the manufacturer. (UMC Para 604.4) Section 1
Faced insulation of metal ducts shall be legibly printed with the thermal SAES-K-100
D2
resistance ® value at the installed thickness (UMC Para 604.4) Section 1
Insulation applied to the exterior surface of ducts located in buildings
SAES-K-100
D3 shall have a flame spread index of not more than 25 and a smoke-
Section 1
density index not exceeding 50 (UMC 604.3)

Faced insulation of metal ducts shall be legibly printed with the flame
SAES-K-100
D4 spread index and smoke-developed index of the composite material.
Section 1
(UMC Para 604.4)

Page 1 of 7
SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Metal Duct, Hangers and Supports and Insulation Receiving SAIC-K-4008 18-May-05 HVAC
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

REMARKS:

REFERENCE DOCUMENTS:
1-SAES-K-001 -- Heating, Ventilating, and Air Conditioning, 31 May, 2004

2-Schedule "Q" -- Quality Requirements

3-SAES K-100 -- Saudi Aramco Mechanical Code (HVAC), 31 May, 2004

4-Uniform Mechanical Code (UMC), 1997

ATTACHMENTS:
1.Table 5B-Minimum Sheet Metal Thickness for Round Ducts
2.Table 5C-Minimum Sheet Metal Thickness for Rectangulare Ducts
3-Table 6B-Construction Details for Round and Flat-Oval Ducts
4-Table 6A-Construction of Details for Rectangular Sheet Metal Ducts
5-Table 6E- Duct Supports

Contractor / Third-Party Saudi Aramco


Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Inspector PID Representative


Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED

Page 2 of 7
SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Metal Duct, Hangers and Supports and Insulation Receiving SAIC-K-4008 18-May-05 HVAC

Attachment 1 --

Page 3 of 7
SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Metal Duct, Hangers and Supports and Insulation Receiving SAIC-K-4008 18-May-05 HVAC

Attachment 2 --

Page 4 of 7
SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Metal Duct, Hangers and Supports and Insulation Receiving SAIC-K-4008 18-May-05 HVAC

Attachment 3 --
1997 UNIFORM MECHANICAL CODE

Page 5 of 7
SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Metal Duct, Hangers and Supports and Insulation Receiving SAIC-K-4008 18-May-05 HVAC

Attachment 4 --

Page 6 of 7
SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Metal Duct, Hangers and Supports and Insulation Receiving SAIC-K-4008 18-May-05 HVAC

Attachment 5 --
1997 UNIFORM MECHANICAL CODE

Page 7 of 7