Professional Documents
Culture Documents
The Tehri Dam is the tallest dam in India. It is a multi-purpose rock and earth-
fill embankment dam on the Bhagirathi River near Tehri in Uttarakhand, India. It is the
primary dam of the THDC India Ltd. and the Tehri hydroelectric complex. Phase 1 was
completed in 2006. The Tehri Dam withholds a reservoir for irrigation, municipal water
supply and the generation of 1,000 megawatts (1,300,000 hp) of hydroelectricity. The dam's
expected commissioning in 2022. The Tehri Dam provides a reservoir for agriculture,
municipal water supply, and hydroelectric power generating of 1,000 megawatts (1,300,000
hp). The dam's 1,000 MW variable-speed pumped-storage scheme is now being built, with
In 1947, Bhakra Dam construction was already underway while Tehri was locked in logjam.
Timely completion of Bhakra transformed the face of Punjab bringing prosperity to it and its
adjoining areas but Tehri could taste this prosperity late. When Bhakra finally saw the light of
the day in 1962, only a preliminary survey was completed for Tehri Dam.
Preliminary investigation for Tehri Dam Project got completed in 1961 and it took 11 long
years for the design to get completed. After the design of the dam was completed in 1972
came the feasibility studies which took another six years (completed in 1978). Though the
construction of the dam began soon after there were massive delays caused by various
The newly-formed Tehri Bandh Virodhi Sangarsh Samiti (Anti-Tehri Dam Struggle
Committee) started holding protest dharnas. Many non-violent demonstrations were staged
during which a number of people were arrested and jailed. Opposing Tehri Dam had became
If the locals were resisting acquisition of their land environmentalists were raising heckles
over environmental issues. Politicians went about haggling over their petty interests and gains
while a vast segment of people did not want their sacred Bhagirathi River to be tamed at any
cost. Add to this, a villager, dispatching a letter every day in protest against the construction
of dam at Tehri All this happened despite the fact that the construction of the would mean 24-
hour electricity supply in Tehri and its surrounding areas. It also meant better civic
infrastructure and an improved lifestyle. However, project abandoned in mid-80s after it was
Bandh Virodhi Sangara sh Samiti (TBVSS) challenged the project in the Supreme Court.
Financial crunch, technical glitches and protests.
he Indian Government which was already facing funds crunch regarding the dam construction
looked for outside support. In 1986, the erstwhile USSR started providing financial
assistance.
During Soviet leader Mikhail Gorbachev's visit to India in November 1986, a Soviet
economic aid package for India's nuclear programme suddenly fell through due to Indian
opposition. In an attempt to salvage the prestige of the visit, a project was promptly sought
that would win both Soviet and Indian approvals. As a result, the then Indian Prime Minister
Rajiv Gandhi and Gorbachev signed an agreement on the Tehri Dam project.
But the happiness was short-lived as political instability in erstwhile USSR spelt doom for the
project here. Additionally, the valley was still smouldering in protests. There were misgivings
not just in the mind of those at the helm of affairs but also among general public. The mere
mention of building a dam on a holy river saw a number of people and organisations along
with environmentalists proclaiming that the dam would spell doom for ecology and natural
habitat of the area. There were human right concerns too. A large dam in a fragile ecosystem
of the Himalayan foothills can never be a good idea, argued environmentalists Concerns were
raised on the dam's geological stability as the dam is located in the Central Himalayan
In October 1991, the region faced an earthquake of magnitude 6.8 on Richter scale with its
epicentre being 53 km from the dam's location. Some seismologists feared that earthquakes
with a magnitude of 8.5 or more could occur in this region which would not only cause dam-
break but submerge numerous towns downstream whose population totalled half-a-million.
Sunder Lal Bahuguna was quite vocal in his protest against the dam. Common slogans doing
rounds those days included "We don't want the dam" or "The dam is the mountain's
destruction." Locals claimed the sanctity of River Ganges was being compromised upon for
the generation of electricity. As a result, for years after the Government had approved
implementation of the first stage of the mega Tehri Power Complex in 1994, the project
seemed to be in a limbo. The main task before THDCIL was countering questions relating to
the dam’s safety, environmental concerns and Resettlement Rehabilitation (R&R0 exercise.
Tehri Dam is a rock and earth-fill embankment dam with a height of 260.5 metres (855 feet).
It has a length of 575 metres (1,886 feet), a crest width of 20 metres (66 feet), and a base
width of 1,128 metres (3,701 ft). The dam creates a 4.0 cubic kilometre (3,200,000 acreft)
reservoir with a 52 km2 surface area (20 sq mi). The installed hydroelectric capacity is 1,000
MW, plus further 1,000 MW of pumped storage hydropower. The Koteshwar Dam
The Tehri Hydropower Complex, which also contains the 400 MW Koteshwar Dam, includes
the Tehri Dam and the Tehri Pumped Storage Hydroelectric Power Plant. The variable speed
features of the Tehri pumped storage facility (4 x 250 MW) can enhance round trip efficiency
under varied water levels in its reservoirs. Uttar Pradesh, Uttarakhand, Punjab, Delhi,
Haryana, Jammu and Kashmir, Chandigarh, Rajasthan, and Himachal Pradesh receive
electricity.
Hydro turbine: - Four numbers of vertical Francis Turbine supplied by Power Machine
installed at Tehri HEP. Each machine has a rated capacity of 255MW and can be operated in
the head range of 122.6-230.0 m. The unique features of the design of francis turbine is single
runner which is capable of operation under large head variation of over 100.0m The direction
of rotation is anti-clockwise when viewed from the top. The rated speed of Machine is 214.28
rpm and maximum runway speed is 410rpm. The maximum efficiency of turbine is 95.5%.
Hydro Generator: - Tehri Hydro generator ( CB 870/300-28) is a vertical shaft, alternating
current, 3 phase synchronous machine of semi umbrella type with combined Thrust and Lower
Guide Bearing located below the Rotor and Upper Guide Bearing above the Rotor. It can
generate 275 MW maximm output power continuously. The rated Voltage and Current are
15.75KV and 10190.7Amp respectively with Power Factor 0.9. The hydro Generator is directly
coupled with Hydraulic Turbine. The total weight of generator comprising of rotor and Stator
is approximately 1300T.
Turbine Governing System: - Governor employed in Tehri machine senses change in speed
and then controls wicket gate opening automatically through servomotors so as to oppose
changes in turbine speed due to change in system demand and ensure the generation of power
at fixed frequency. The Tehri governor is EHT based consists of a digital programmable
electronic part for control and regulating function and a hydraulic part for power amplifying to
servo unit.
Auxiliary Equipment: - The auxiliary equipment like compressed Air System , MIV and BFV
along with Oil Pressure systems , Cooling Water System , Oil Handling and Generator Fire
Fighting System etc also formed the part of supply of main equipment.
Spillways: - According to the initial design elaborated by the Indian engineers, the flood in the
diameter: two on the right bank of the Bhagirathi river and two on the left bank of the
Bhilangana river. Discharge capacity of each tunnel is 1840 m3/s. The chute spillway which
requires deep incision into the slope over the height more than 200 m was proposed as the
service spillway structure. HPI proposed to use the diversion tunnels after refitting them into
the shaft spillways and conjugation with the vertical shafts. Discharge capacity of the shaft
spillway is 1800 m3/s. At each section of vertical shaft conjugation with the horizontal section
of the tunnel, provision shall be made for arrangement of a spiral case for creation of "vortexed
flow" to avoid the cavitation due to water flow impact on the tunnel concrete lining.
Department in Roorkee, UP (India). From the result of studies, the vortexed flow persists at the
usable sections of the diversion tunnels for about 1000 m in length. At that, due to the
centripetal forces, the air, entrained into the flow, is shaped in the form of "vortex core" in the
centre of tunnel cross-section, and the positive water pressure is developed around the
periphery of the tunnel lining which precludes cavitation impact on the tunnel lining. Such
design solution made it possible to eliminate four bays of the chute spillway and leave only
three bays. The total discharge capacity of the chute spillway at MWL is 5485 m3/s. At that, it
became possible to reduce, significantly, the volume of the right bank undercutting. In order to
MDDL=740.0 m, the water intake at the intermediate level is provided on one of the shaft
spillways on the right bank. Each out of the two shaft spillways on the right bank has the
overflow funnel for automatic operation of the spillways at flood flow handling on rising the
In the course of construction of the intake structures and maintenance gates shafts (MGS), a
series of cross tectonic discontinuities with a thick zone of de-stressing was discovered.
When clearing the slope and excavation of pits for the intake structures a large sliding-prone
mass was formed which could loss its stability on flooding the slope by reservoir. In order to
ensure the slope stability, HPI has elaborated the engineering measures for the slope
protection. Those were four rows of piles, Diameter=3 m, resting on the bedrock. The piles
were of up to 48 m in depth. The pile heads exposed on the berms surface were combined by
cast-in-situ reinforced concrete pilework. A part of the slope above the water intakes
(between the pileworks) was covered by the cast-in-situ anchored reinforced concrete stepped
slabs.
Underground Machine and Transformer Halls
For elaboration of design solutions for the machine and transformer halls, based on the data
construction of massive reinforced concrete vaults and replace thems by the s called
"adjustable vaults in the form of multi hor shotcrete with anchoring the vault and walls. On
the basis of developed geological model of the rock mass enclosing the machine hall and
transformer hall the design of anchorage of the excavations was worked out providing for use
of pre-stressed multi-legged wire ropes with a design force of up to 140 t. Four measuring
sections equipped with multi-point extensometers were established in the machine and
transformer halls for monitoring the walls convergence. The obtained results of convergence
Design solutions for protection of slope above TRT outlet portals, portals of left-bank shaft
spillways and access tunnels to machine and transformer halls and administrative-and-
service building
In the course of construction of the HPP tailrace tunnels, the lengthwise slope of the
Bhagirathi River channel was undercut by blasting which resulted in formation of the large
landslide up to 80 m in height. In order to ensure the slope stability, a system of cellular type
reinforced concrete structures with rock filling was developed. The structure is three-tier
retaining walls over the slope height: the first tier is a flood-protection wall and two tiers of
walls made of reinforced concrete cellular structures 10x10x10m in size length wise the
entire slide prone slope. The undertaken engineering measures made it possible to suspend
the slide- prone mass displacement. However, the slope stability should be continuously
monitored.
Successful Journey of a Green Power Plant
Power builds a nation's economy, and clean and green power is indispensable for sustainable
development of any country more so a developing nation like ours contributing towards
country's economy is in no way marginal The started with the taking over of Tehri Dam from
the Uttar Pradesh Government as an infant, struggling with ups and downs, facing various
challenges (both external and internal) and discharging efficiently in a professional and
optimal manner has resulted in the present adolescent stage of the company.
Significantly, the Corporation started making profit right from very first year of its
commercial operation (2006-07) Continuous profit earning and consistent increase in its net
worth over the years has given it a firm financial health. It evidently reflects effective
As a socially responsible corporate, the THDCIL has been discharging its Corporate Social
Power Complex (2,400MW) Leading the way to Empower India Tehri Hydro
already installed)
• 300 cusecs (162MGD) of Drinking Water for Delhi, to meet the requirement of about
40 lakh Population. 200 cusecs (108 MGD) of Drinking Water for towns and villages
• Flood Moderation
Town with provision of all civic facilities, improved communication, education, ealth,
• The additional agricultural output in U.P. & Uttarakhand due to irrigation water is
Being the largest water body in Uttarakhand, Tehri Dam Reservoir has a vast potential to be
developed as a tourist destination and a venue for water sports. Recently, the state
government has taken initiative by developing water sports complex at Koti, about 5 km
downstream of the dam. Water sports are organised by the state government during winters.
THDCIL also have plans for the landscape designing of the entire project area to attract
national and international tourists to Tehri Dam which could be started once ongoing work of
1,000 MW Pump Storage Plant is completed. With the influx of tourists, it can be a boost to
people.
References: -