IP10
Update Scheduling
to IP03 and IP24
Sometimes this
scheduling
information is not
updated correctly
from IP10 or IP30
(reasons ??)
1
IP03
Step 1
Before Scheduling Updating
(issue of IP03 schedule dates
not sync with IP10)
Sometimes this
2
scheduling IP24
information is not
updated correctly
from IP10 or IP30
(reasons ??)
Step 1
Before Scheduling Updating
(issue of IP24 schedule dates
not sync with IP10)
Goto IP10
click
“update scheduling”
ICON
Step 2
Perform Scheduling
Updating in IP10
2
IP10
Step 3
After Scheduling Updating
(dates in IP10 should sync
with IP03)
2
IP24
Step 3
After Scheduling Updating
(dates in IP10 should sync
with IP24)
Why SAP created
the