10 Reinforment bar
Column 16mm 9 4 4.5 1.579 255.80 Kg
Stirrup8mm 9 24 0.95 0.395 81.05
Jali 10mm 9 18 1.2 0.617 119.94
Beams16mm 1 6 24 1.579 227.38
Stirrup8mm 1 160 1.05 0.395 66.36
750.53 Kg
Wastage 750.53 2% 15.01
765.54
Say 766.00 Kg
Say 32.00 Kg
19 Barbed wire fencing…..
Hori 1 6 24.00 144.00 M
Say 144.00 M
20 Credit value for old brick... L/S 2800.00 Nos
21 Credit value for reinforcement bar L/S 400.00 Kg
Name of Work:- Construction of damaged boundary wall at the Front Side of BSNL store compound Lamphel, Imphal Manipur.
Item REMARK
No Description of item Quantity Unit Rate Amount S
1 DSR 2014
Earth work in excavation by mechanical means (Hydraulic
excavator) / manual means in foundation trenches or drains (not
exceeding 1.5 m in width or 10 sqm on plan) including dressing of
sides and ramming of bottoms, lift up to 1.5 m, including getting out
the excavated soil and disposal of surplus excavated soil as directed,
within a lead of 50 m.
a) All kinds of soil. 16.00 Cum 157.50 2520.00 2.8.1
2 Filling available excavated earth (excluding rock) in trenches, plinth,
sides of foundations etc. in layers not exceeding 20cm in depth,
consolidating each deposited layer by ramming and watering, lead
up to 50 m and lift up to 1.5 m. 16.00 Cum 112.40 1798.00 2.25
3 Demolishing brick work manually/ by mechanical means including
stacking of serviceable material and disposal of unserviceable
material within 50 metres lead as per direction of Engineer-in-
charge.
a) In cement mortar 15.00 Cum 754.10 11312.00 15.7.4
4 Demolishing R.C.C. work manually/ by mechanical means
including stacking of steel bars and disposal of unserviceable
material within 50metres lead as per direction of Engineer - in-
charge. 8.00 Cum 1302.30 10418.00 15.3
5 Providing and laying in position cement concrete of specified grade
excluding the cost of centering and shuttering - All work up to plinth
level :
a)
1:5:10 (1 Cement : 5coarse sand : 10graded stone aggregate 40 mm
nominal size). 1.00 Cum 4004.00 4004.00 4.1.10
35 Providing and laying cement concrete in retaining walls,
return walls, walls (any thickness) including attached
pilasters, columns, piers, abutments, pillars, posts, struts,
buttresses, string or lacing courses, parapets, coping, bed
blocks, anchor blocks, plain window sills, fillets, sunken
floor, etc., up to floor five level, excluding the cost of
centering, shuttering and finishing :
a) 1:2:4 (1 Cement : 2 coarse sand : 4 graded stone aggregate 20 1.00 Cum 6450.00 6450.00 4.2.3
mm nominal size)
6
Providing and laying in position specified grade of reinforced
cement concrete excluding the cost of centering, shuttering,
finishing and reinforcement - All work up to plinth level : Providing
and fixing tie bolt, spring coil and plastic cone in wall shuttering
complete as per the direction of Engineer-in-charge
a) 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20
mm nominal size) 6.00 Cum 6230.20 37381.00 5.1.2
7
Reinforced cement concrete work in walls (any thickness), including
attached pilasters, buttresses, plinth and string courses, fillets,
columns, pillars, piers, abutments, posts and struts etc. up to floor
five level excluding cost of centering, shuttering, finishing and
reinforcement :
a) 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 10
mm nominal size) 1.00 Cum 7074.30 7074.00 5.2.2
8 Centering and shuttering including strutting, propping etc. and
removal of form for : Foundations, footings, bases of columns, etc.
for mass concrete.
a) Foundations, footings, bases of columns, etc. for mass concrete. 13.00 Sqm 196.45 2554.00 5.9.1
b)
Lintels, beams, plinth beams, girders, bressumers and cantilevers. 20.00 Sqm 332.15 6643.00 5.9.5
c) Columns, Pillars, Piers, Abutments, Posts and Struts. 23.00 Sqm 453.35 10427.00 5.9.6
9 Steel reinforcement for R.C.C. work including straightening,
cutting, bending, placing in position and binding all complete up to
plinth level.
a) Thermo-Mechanically Treated bars. 766.00 Kg 68.10 52165.00 5.22.6
10
Half brick masonry with common burnt clay F.P.S. (non modular)
bricks of class designation 7.5 in foundations and plinth in.
a) cement mortar 1:4 (1 cement : 4 coarse sand) 26.00 Sqm 584.75 15204.00 6.12.2
11
Half brick masonry with common burnt clay F.P.S. (non modular)
bricks of class designation 7.5 in superstructure above plinth level
up to floor V level.
a) Cement mortar 1:4 (1 cement :4 coarse sand) 28.00 Sqm 665.80 18642.00 6.13.2
12 12 mm cement plaster of mix :
a) 1:6 (1 cement: 6 coarse sand) 54.00 Sqm 158.40 8554.00 13.4.2
13
15 mm cement plaster on the rough side of single or half brick wall
of mix :
a) 1:6 (1 cement: 6 coarse sand) 54.00 Sqm 183.45 9906.00 13.5.2
14 6 mm cement plaster of mix :
a) 1:3 (1 cement: 3 fine sand) 19.00 Sqm 134.70 2559.00 13.16.1
15
Finishing walls with water proofing cement paint of required shade :
a) New work (Two or more coats applied @ 3.84 kg/10 sqm). 120.00 Sqm 57.85 6942.00 13.44.1
16 Painting with synthetic enamel paint of approved brand and
manufacture to give an even shade :
a) Two or more coats on new work. 3.00 Sqm 74.40 223.00 13.61.1
17
Supplying at site Angle iron post & strut of required size including
bottom to be split and bent at right angle in opposite direction for 10
cm length and drilling holes upto 10 mm dia. etc. complete. 32.00 Kg 70.90 2269.00 16.19
16
Total 208510.00
Less MR Total -10400.00
DSR Total 218910.00
Correction for CP instead of 15% CP over schedule rate items as per
Corp. Office order No. 4-10/ 97-A & C (Vol-III)/ Part/ 180. Dt. 6-8-
2008 DSR total after modified CP 209392
Cost index of Imphal :
CI of Imphal vide CPWD letter no 43(1)/NEZ-II/2014/1091
dated 02/09/2014 wef 01/07/2014 171.00
Enhanced CI @ 7.5% per annum for 3 years 212
Add difference between Cost Indicies of DSR-14 (CI-105) and
Imphal(CI=212) on DSR-14 items only:
209392X(212-105)/105 213381
422773
Add for MR item 10400
Total 433173 (A)
Add 18% GST On A 433173 18.00% 77971
Add 1.0% Labour welfare cess on "A" 422773 1.00% 4228
515372
Add 5% contingencies 515372 5% 25769
Grand total 541141
Say Rs. 541100.00
Executive Engineer ( C )
BSNL Civil Division-II
Dimapur
Analysis of Rate
Item Code: 15.7.4
Demolishing brick work : In cement mortar.
Details of Cost for : 1.00 Cum
Code Description Unit Quantity Rate Amount
LABOUR
0114 Beldar Day 1.06 350.00 371.00
0115 Coolie Day 0.90 350.00 315.00
9999 Sundries L.S. 2.47 3.02 7.46
Total: 693.46
Add 12.5% on labour component due to 693.46 12.50% 86.68
less labour efficiency.
Total: 780.14
Add water charges @ 1% on 780.14 7.80
787.94
Add C.P & OH @10% on 787.94 78.79
Cost for 1.00 Cum 866.73
Add 5.60 % for WCT 866.73 5.60% 48.54
915.27
Add labour cess 1% 866.73 1.0% 8.67
923.94
Add service tax 2.8% 866.73 2.80% 24.27
Cost for 1.00 Cum 948.21
349811.91
Add Service Tax on total 339785.91 5.60% 19028.00
368839.91
Add 5% contingencies 368839.91 5% 18442.00
Grand total 387281.91
Say Rs. 387300.00
1. DSR Total= 175492.00
2. Analysed DSR 154627.00
3. Analysed done 88.11
Say 90.00
4. Analysed amount 328108.35
5. Justified %age 9.09
6. Justified amount 360236.31
JTO Civil Sub-Divisional Engineer ( C ) Executive Engineer ( C )
8499.00
7832.00
3593.00
30569.00
5736.00
5245.00
47684.00
10841.00
13352.00
7133.00
8294.00
455.00
5394.00
154627.0
147904.087
151483.366
299387.453
-12400.00
286987.453
16765.6974
303753.15
-2993.87453
300759.276
%
%
%
eer ( C )
BHARAT SANCHAR NIGAM LIMITED
(A GOVERNMENT OF INDIA ENTERPRISE)
OFFICE OF THE EXECUTIVE ENGINEER (CIVIL)
BSNL CIVIL DIVISION
IMPHAL
Estimate No. /BSNL/CD/NE-II//IMP/2017-2018 Dated . . 2017
Branch: BSNL Civil Wing Division: BSNL Civil Division, Imphal.
State: Manipur Sub-Division: BSNL Civil Sub-Division-II, Imphal.
Name of Work : Construction of damaged boundary wall at the Front Side of BSNL store compound
Lamphel, Imphal Manipur.
1. Major Head:-
2. Minor Head:-
3. Detail Head:-
This preliminary cum detailed estimate has been framed by the O/o the Executive Engineer (C),
BSNL Civil Division-II, Dimapur amounting to Rs. 5,41,100.00 including 5% contingencies to cover the
probable cost of the above mentioned work.
REPORT
1. History : This preliminary cum detailed estimate amounting to Rs. 541100.00 including 5%
contingencies has been framed by the O/o the Executive Engineer (C), BSNL Civil Division-imphal to
cover the probable cost of the above mentioned work and for accord of A/A & E/S by the competent
authority. The requisition has bee given by SDE (store) vide letter No SDE
(Store)/lamphel/report/2017-18/02 dated 28.8.2017 . It is also related to security of the BSNL store
compound at Lamphel. Hence this estimate has been prepared.
2. Design & Scope:- All the required items of work has been considered in the estimate to construct the
damaged compound wall like demolishing of RCC/brick work, RCC work, brick work, barbed wire
fencing, plaster, painting etc.
3. RATE :The estimate is based on DSR 2014 and Market rate
1200MM
150MM
300MM
1200MM