Sub:- Submission of estimates for the Construction of damaged boundary wall at the Front Side of
BSNL store compound Lamphel, Imphal Manipur.
The Preliminary Estimate cum Detailed estimate basis amounting to Rs 5,41,100/- for the
above cited work is submitted in duplicate for accord of A/A & E/S from competent authority.
The necessity of framing the estimates has been explained in the body of history sheet of the
estimate.
One copy of estimates duly sanctioned by the competent authority may please be returned to
this office for further necessary action accordingly.
Encl :- As above.
To,
The Divisional Engineer,
BSNL, Satellite Maintenance,
Imphal.
The Preliminary Cum Detailed Estimate for the above noted work is sent
herewith in duplicate for accord of A/A & E/S from your end please.
The necessities of framing the estimate has been explained in the body of
history sheet of each estimate.
One copy of the above estimate duly sanctioned by the competent authority
may please be returned to this office for record.
Enclo: - As above .
To,
The Superintending Engineer (C),
BSNL Civil Circle,
Dimapur.
The Preliminary Cum Detailed Estimate for the above noted work is sent
herewith for taking necessary action at your end please.
The necessity of framing the estimate has been explained in the body of history
sheet of the estimate.
The estimate has been registered under the office No. 06/EE/BSNL/CD-IMP/16-
17.
Enclo: - As above
To,
The A.G.M(Plg),
O/o GMTD, Manipur SSA,
Imphal, Manipur.
Sub:- Submission of Estimate for the work Construction of damaged boundary wall at the front
side of BSNL store compound due to earth quake on 04.01.2016, Lamphel, Imphal
The Preliminary Estimate on Detailed basis for the above cited work is submitted in duplicate
for accord of A/A & E/S from competent authority.
The necessity of framing the estimates has been explained in the body of history sheet of the
estimate.
The Estimates had been registered under the office No. 04 /EE/BSNL/CD/IMP/16-17.
One copy of estimates duly sanctioned by the competent authority may please be returned to
this office for further necessary action accordingly.
Encl :- As above.
To,
The A.G.M(Plg),
O/o GMTD, Manipur SSA,
Imphal, Manipur.
The Preliminary Estimate on Detailed basis for the above cited works is submitted in
duplicate for accord of A/A & E/S from competent authority.
The necessity of framing the estimates has been explained in the body of history sheet of the
estimate.
The Estimates had been registered under the office No. 02 & 03 /EE/BSNL/CD/IMP/16-17.
One copy of estimates duly sanctioned by the competent authority may please be returned to
this office for further necessary action accordingly.
Encl :- As above.
To,
The Dy.G.M(Mtce),
O/o GMM, ETR,
Dimapur, Nagaland.
Sub:- Submission of Estimate for the works “Demolishing damaged portion of R.R. wall
and reconstruction of R.R. wall at the back side of Satellite building at BSNL Satellite
compound, KOhima, Nagaland.
The Preliminary Estimate on Detailed basis for the above cited work is submitted in duplicate
for accord of A/A & E/S from competent authority.
The necessity of framing the estimates has been explained in the body of history sheet of the
estimate.
One copy of estimates duly sanctioned by the competent authority may please be returned to
this office for further necessary action accordingly.
Encl :- As above.
Copy to :-
1. The SDE(C), BSNL Sub-Division, Kohima for information please.
To,
The AGM (Plg)
O/o GMTD,BSNL NLD-SSA,
Dimapur Nagaland .
Subject:-Revision of Estimate.
The Estimates for construction of chain link fencing at (1) Aitepyong BTS (2) Longsa BTS (3)
Pangti BTS (4) Diphupar BTS and (5) Tseminyu-2 BTS were prepared based on standard DSR-2007 and
submitted to your office for accord of A/A & E/S.
It is a standard estimate for providing chain link fencing in BTS sites and there is no scope for
reducing the cost as the area of the plot occupied by the department is to be covered.
No.54(508)BSNL/CD-DMP/10-11/
Dated:22/04/2010
To,
The General Manager Telecom District,
BSNL, Nagaland SSA,
Dimapur.
The Detailed Estimate for the above noted works are sent herewith in duplicate
for accord of A/A & E/S from your end please.
The necessities of framing the estimates have been explained in the body of
history sheet of each estimate.
The estimates have been registered under the office No. /EE/BSNL/CD-
DMP/10-11.
One copy of each of the above estimate duly sanctioned by the competent
authority may please be returned to this office for record.
Enclo: - As above
Executive Engineer
(Civil)
BSNL, Civil Division,
Dimapur
Copy to :-
To,
The Superintending Engineer (C),
BSNL Civil Circle,
Dimapur.
The Detailed Estimate in triplicate for the above noted work is sent herewith for
taking necessary action at your end please.
The necessity of framing the estimate has been explained in the body of history
sheet of the estimate.
The estimate has been registered under the office No. /EE/BSNL/CD-
DMP/10-11.
Executive Engineer
(Civil)
BSNL, Civil Division-I,
Dimapur.
BHARAT SANCHAR NIGAM LIMITED
( A Government of India Enterprise)
OFFICE OF THE EXECUTIVE ENGINEER (Civil)
BSNL, Civil Division, Dimapur-797112.
No.54(506)BSNL/CD-DMP/10-11/ Dated:22/04/2010
To,
The General Manager Telecom District,
BSNL, Nagaland SSA,
Dimapur.
The Detailed Estimate for the above noted work is sent herewith in duplicate for
accord of A/A & E/S from your end please.
The necessities of framing the estimate has been explained in the body of
history sheet of each estimate.
The estimate has been registered under the office No. /EE/BSNL/CD-
I/DMP/10-11.
One copy of the above estimate duly sanctioned by the competent authority
may please be returned to this office for record.
Enclo: - As above
Executive Engineer
(Civil)
BSNL, Civil Division,
Dimapur
Copy to :-
1. The Sub-Divisional Engineer (Civil), BSNL, Civil Sub-Division-I, Dimapur for
information.
To,
The Executive Engineer(civil)
BSNL Civil Division-I
Dimapur.
Subject:-Submission Estimates for the works ” Laying O.F. Cable from NH-
61 to USO site at Phensenyu, Kohima, Nagaland.”
The Detailed Estimate for the above noted work is sent herewith in
Quadruplicate onward transmission and further necessary action at your end please.
The necessities of framing the estimate has been explained in the body of
history sheet of each estimate.
Enclo: - As above
Sub-Divisional Engineer
(Civil)
BSNL, Civil Sub- Division-III,
Dimapur
BHARAT SANCHAR NIGAM LIMITED
( A Government of India Enterprise)
OFFICE OF THE EXECUTIVE ENGINEER (Civil)
BSNL, Civil Division, Dimapur-797112.
No.54(492)BSNL/CD-DMP/09-10/ Dated:18/03/2010
To,
The General Manager Telecom District,
BSNL, Nagaland SSA,
Dimapur.
The Preliminary Cum Detailed Estimate for the above noted works are sent
herewith in duplicate for accord of A/A & E/S from your end please.
The necessities of framing the estimates have been explained in the body of
history sheet of each estimate.
The estimates have been registered under the office No. 58 /EE/BSNL/CD-
DMP/09-10.
One copy of each of the above estimate duly sanctioned by the competent
authority may please be returned to this office for record.
Executive Engineer
(Civil)
BSNL, Civil Division,
Dimapur
Copy to :-
1. The Sub-Divisional Engineer (Civil), BSNL, Civil Sub-Division-I,Dimapur for
information.
Executive Engineer (Civil)
To,
The General Manager ETR,
M/W Compound,
Dimapur.
The Preliminary Cum Detailed Estimate for the above noted works are sent
herewith in duplicate for accord of A/A & E/S from your end please.
The necessities of framing the estimates have been explained in the body of
history sheet of each estimate.
The estimates have been registered under the office No. /EE/BSNL/CD-
DMP/09-10.
One copy of each of the above estimate duly sanctioned by the competent
authority may please be returned to this office for record.
Enclo: - As above .
Executive Engineer
(Civil)
BSNL, Civil Division,
Dimapur
Copy to :-
1. The Sub-Divisional Engineer (Civil), BSNL, Civil Sub-Division, Kohima for
information.
To,
The General Manager ETR,
M/W Compound,
Dimapur.
The Preliminary Cum Detailed Estimate for the above noted works are sent
herewith in duplicate for accord of A/A & E/S from your end please.
The necessities of framing the estimates have been explained in the body of
history sheet of each estimate.
The estimates have been registered under the office No. /EE/BSNL/CD-
DMP/09-10.
One copy of each of the above estimate duly sanctioned by the competent
authority may please be returned to this office for record.
Enclo: - As above .
Executive Engineer
(Civil)
BSNL, Civil Division,
Dimapur
Copy to :-
1. The Sub-Divisional Engineer (Civil), BSNL, Civil Sub-Division, Kohima for
information.
To,
The AGM(Plg)
O/O the GMTD, NLD SSA,
Dimapur.
Subject:-Submission Detailed Estimate for the work” Providing chain
link fencing to earthern side boundary ( collaped portion) at BSNL
compound,Peren, Nagaland”.
The Preliminary Cum Detailed Estimate for the above noted work is sent
herewith in duplicate for accord of A/A & E/S from your end please.
The necessities of framing the estimate has been explained in the body of
history sheet of each estimate.
The estimate has been registered under the office No. /EE/BSNL/CD-
DMP/09-10.
One copy of the above estimate duly sanctioned by the competent authority
may please be returned to this office for record.
Enclo: - As above .
Executive Engineer
(Civil)
BSNL, Civil Division,
Dimapur
Copy to :-
1. The Sub-Divisional Engineer (Civil), BSNL, Civil Sub-Division-III,Dimapur for
information.
Executive Engineer
(Civil)
BSNL, Civil Division,
Dimapur
To,
The General Manager (Sales & Marketing)
O/O the CGMT, OCB Building,
Dimapur.
Subject:-Submission Detailed Estimate for the work” Miscellaneous
civil works for 3G Experience Counter at OCB building, Kohima,
Nagaland”.
The Preliminary Cum Detailed Estimate for the above noted work is sent
herewith in duplicate for accord of A/A & E/S from your end please.
The necessities of framing the estimate has been explained in the body of
history sheet of each estimate.
The estimate has been registered under the office No. /EE/BSNL/CD-
DMP/09-10.
One copy of the above estimate duly sanctioned by the competent authority
may please be returned to this office for record.
Enclo: - As above .
Executive Engineer
(Civil)
BSNL, Civil Division,
Dimapur
No.54(502)BSNL/CD-DMP/10-11/ Dated:-08-04-2010
To,
The Superintending Engineer ©,
BSNL Civil Circle,
Dimapur.
The Detailed Estimate in duplicate for the above noted work is sent herewith for
taking necessary action and kind instruction from your end please.
The necessity of framing the estimate has been explained in the body of history
sheet of the estimate.
The estimate has been registered under the office No. /EE/BSNL/CD-
DMP/10-11.
Enclo: - As above .
Executive Engineer
(Civil)
BSNL, Civil Division-I,
Dimapur
No.54(348)BSNL/CD-DMP/08-09/ Dated:03-02-2010
To,
The Superintending Engineer ©,
BSNL Civil Circle,
Dimapur.
The Preliminary Cum Detailed Estimate for the above noted work is sent
herewith in duplicate for accord of A/A & E/S from the competent authority.
The necessity of framing the estimate has been explained in the body of history
sheet of the estimate.
The estimate has been registered under the office No. 85/EE/BSNL/CD-
DMP/08-09.
Enclo: - As above .
Executive Engineer
(Civil)
BSNL, Civil Division-II,
Dimapur
BHARAT SANCHAR NIGAM LIMITED
( A Government of India Enterprise)
OFFICE OF THE EXECUTIVE ENGINEER (Civil)
BSNL, Civil Division, Dimapur-797112.
To,
The General Manager ETR,
M/W Compound,
Dimapur.
The Preliminary Cum Detailed Estimate for the above noted works are sent
herewith in duplicate for accord of A/A & E/S from your end please.
The necessities of framing the estimates have been explained in the body of
history sheet of each estimate.
The estimates have been registered under the office No. /EE/BSNL/CD-
DMP/10-11.
One copy of each of the above estimate duly sanctioned by the competent
authority may please be returned to this office for record.
Enclo: - As above .
Executive Engineer
(Civil)
BSNL, Civil Division,
Dimapur
Copy to :-
1. The Sub-Divisional Engineer (Civil), BSNL, Civil Sub-Division, Kohima for
information.
To,
The General Manager Telecom District,
BSNL, Nagaland SSA,
Dimapur.
The Preliminary Cum Detailed Estimate for the above noted works are sent
herewith in duplicate for accord of A/A & E/S from your end please.
The necessities of framing the estimates have been explained in the body of
history sheet of each estimate.
The estimates have been registered under the office No. /EE/BSNL/CD-
DMP/09-10.
One copy of each of the above estimate duly sanctioned by the competent
authority may please be returned to this office for record.
Enclo: - As above .
Executive Engineer
(Civil)
BSNL, Civil Division,
Dimapur
Copy to :-
1. The Sub-Divisional Engineer (Civil), BSNL, Civil Sub-Division, Kohima for
information.
To,
The General Manager Telecom District,
BSNL, Nagaland SSA,
Dimapur.
The Detailed Estimate for the above noted work is sent herewith in duplicate for
accord of A/A & E/S from your end please.
The necessity of framing the estimate has been explained in the body of history
sheet of the estimate.
The estimate has been registered under the office No. /EE/BSNL/CD-
DMP/09-10.
One copy of the above estimate duly sanctioned by the competent authority
may please be returned to this office for record.
Enclo: - As above .
Executive Engineer
(Civil)
BSNL, Civil Division,
Dimapur
Copy to :-
1. The Sub-Divisional Engineer (Civil), BSNL, Civil Sub-Division, Kohima for
information.
To,
The General Manager Telecom District,
BSNL, Nagaland SSA,
Dimapur.
The Detailed Estimate for the above noted work is sent herewith in duplicate for
accord of A/A & E/S from your end please.
The necessity of framing the estimate has been explained in the body of history
sheet of the estimate.
The estimate has been registered under the office No. /EE/BSNL/CD-
DMP/09-10.
One copy of the above estimate duly sanctioned by the competent authority
may please be returned to this office for record.
Enclo: - As above .
Executive Engineer
(Civil)
BSNL, Civil Division,
Dimapur
Copy to :-
1. The Sub-Divisional Engineer (Civil), BSNL, Civil Sub-Division, Kohima for
information.
To,
The General Manager Telecom District,
BSNL, Nagaland SSA,
Dimapur.
The Detailed Estimate for the above noted work is sent herewith in duplicate for
accord of A/A & E/S from your end please.
The necessity of framing the estimate has been explained in the body of history
sheet of the estimate.
The estimate has been registered under the office No. /EE/BSNL/CD-
DMP/09-10.
One copy of the above estimate duly sanctioned by the competent authority
may please be returned to this office for record.
Enclo: - As above .
Executive Engineer
(Civil)
BSNL, Civil Division,
Dimapur
Copy to :-
1. The Sub-Divisional Engineer (Civil), BSNL, Civil Sub-Division, Kohima for
information.
To,
The General Manager Telecom District,
BSNL, Nagaland SSA,
Dimapur.
The Detailed Estimate for the above noted work is sent herewith in duplicate for
accord of A/A & E/S from your end please.
The necessity of framing the estimate has been explained in the body of history
sheet of the estimate.
The estimate has been registered under the office No. /EE/BSNL/CD-
DMP/09-10.
One copy of the above estimate duly sanctioned by the competent authority
may please be returned to this office for record.
Enclo: - As above .
Executive Engineer
(Civil)
BSNL, Civil Division,
Dimapur
Copy to :-
1. The Sub-Divisional Engineer (Civil), BSNL, Civil Sub-Division, Kohima for
information.
To,
The General Manager Telecom District,
BSNL, Nagaland SSA,
Dimapur.
The Preliminary Cum Detailed Estimate for the above noted work is sent
herewith in duplicate for accord of A/A & E/S from your end please.
The necessity of framing the estimate has been explained in the body of history
sheet of the estimate.
The estimate has been registered under the office No. /EE/BSNL/CD-
DMP/09-10.
One copy of the above estimate duly sanctioned by the competent authority
may please be returned to this office for record.
Enclo: - As above .
Executive Engineer
(Civil)
BSNL, Civil Division,
Dimapur
Copy to :-
1. The Sub-Divisional Engineer (Civil), BSNL, Civil Sub-Division-III, Dimapur for
information.
To,
The General Manager Telecom District,
BSNL, Nagaland SSA,
Dimapur.
The Preliminary Cum Detailed Estimate for the above noted work is sent
herewith in duplicate for accord of A/A & E/S from your end please.
The necessity of framing the estimate has been explained in the body of history
sheet of the estimate.
The estimate has been registered under the office No. /EE/BSNL/CD-
DMP/09-10.
One copy of the above estimate duly sanctioned by the competent authority
may please be returned to this office for record.
Enclo: - As above .
Executive Engineer
(Civil)
BSNL, Civil Division,
Dimapur
Copy to :-
1. The Sub-Divisional Engineer (Civil), BSNL, Civil Sub-Division-III, Dimapur for
information.
To,
The General Manager Telecom District,
BSNL, Nagaland SSA,
Dimapur.
Enclosed please find herewith the above noted estimate in duplicate for accord
of Administrative approval and Expenditure sanctioned of the competent authority.
The necessity for framing of the estimates have been explained in the body of the
history sheet of each estimate
After accord of the sanctioned, one copy of the sanctioned estimate may please
be send to this office for office record and for further action on the matter please
Superintending Engineer
(Civil)
BSNL, Civil Circle,
Dimapur
Copy to :-
1. The Executive Engineer (Civil), BSNL, Civil Division-I, Dimapur.
Superintending Engineer
(Civil)
To,
The Superintending Engineer (Civil),
BSNL Civil Circle,
Dimapur.
The Detailed Estimate for the above noted work is sent herewith in
quadruplicate for further necessary action at your end please.
The estimate may be sent to GMTD, BSNL, Nagaland SSA, Dimapur for accord
of A/A & E/S please.
The estimate has been registered under this office No- /EE/BSNL/CD/DMP/09-
10.
Enclo: - As above .
Executive Engineer
(Civil)
BSNL, Civil Division-I,
Dimapur
No.54(416)BSNL/CD-DMP/08-09/ Dated:16-02-2009
To,
The Dy.General Manager,
O/o the GMTD, BSNL,
Nagaland SSA, Dimapur.
The Preliminary Cum Detailed Estimate for the above noted work is sent
herewith in duplicate for accord of A/A & E/S from your end please.
The necessity of framing the estimate has been explained in the body of history
sheet of the estimate.
The estimate has been registered under the office No. /EE/BSNL/CD-
DMP/08-09.
One copy of the above estimate duly sanctioned by the competent authority
may please be returned to this office for record.
Enclo: - As above .
Executive Engineer
(Civil)
BSNL, Civil Division-I,
Dimapur
Copy to :-1. The Sub-Divisional Engineer (Civil), BSNL, Civil Sub-Division- III,
Dimapur
for information.
FILE NO :- 54(416)BSNL/CD-I/DMP/
No.54(416)BSNL/CD-DMP/08-09/ Dated:16-02-2009
To,
The Chief Engineer ©,
NE Civil Zone-II, BSNL
Dimapur.
The Preliminary Cum Detailed Estimate for the above noted work is sent
herewith in duplicate for accord of A/A & E/S from your end please.
The necessity of framing the estimate has been explained in the body of history
sheet of the estimate.
The estimate has been registered under the office No. /EE/BSNL/CD-
DMP/08-09.
One copy of the above estimate duly sanctioned by the competent authority
may please be returned to this office for record.
Enclo: - As above .
Executive Engineer
(Civil)
BSNL, Civil Division,
Dimapur
BHARAT SANCHAR NIGAM LIMITED
( A Government of India Enterprise)
OFFICE OF THE EXECUTIVE ENGINEER (Civil)
BSNL, Civil Division, Dimapur-797112.
No.54(409)BSNL/CD-DMP/08-09/ Dated:26-12-2008
To,
The Dy.General Manager,
O/o the GMTD, BSNL,
Nagaland SSA, Dimapur.
The Preliminary Cum Detailed Estimate for the above noted work is sent
herewith in duplicate for accord of A/A & E/S from your end please.
The necessity of framing the estimate has been explained in the body of history
sheet of the estimate.
The estimate has been registered under the office No. /EE/BSNL/CD-
DMP/08-09.
One copy of the above estimate duly sanctioned by the competent authority
may please be returned to this office for record.
Enclo: - As above .
Executive Engineer
(Civil)
BSNL, Civil Division,
Dimapur
Copy to :-1. The Sub-Divisional Engineer (Civil), BSNL, Civil Sub-Division- I, Dimapur
for information.
No.54(400)BSNL/CD-DMP/08-09/ Dated:27-10-2008
To,
The Superintending Engineer (Civil),
BSNL, Civil Circle,
Silchar.
Subject:-Submission of A/A & E/S for the works 1) C/o 40M NBLW tower i/c
painting, earthing, antenna mounting fixture and anti-sabotage work at Green
Ply Industries TIZIT, Mon District &
2) C/o 40M NBLW tower i/c painting, earthing, antenna mounting fixture and
anti-sabotage work at Longa village, Wokha district, Nagaland.
Enclosed please find herewith the 2(two) Nos of A/A & E/S for the above
mentioned works for taking further necessary action.
Enclo: - As above .
Executive Engineer
(Civil)
BSNL, Civil Division,
Dimapur
No.54(401)BSNL/CD-DMP/08-09/ Dated:26-09-2008
To,
The Superintending Engineer (Civil),
BSNL, Civil Circle,
Silchar.
Subject:-Submission Detailed Estimates for the works (1) Project Arrow ->
Kohima Head Post Office, Kohima. " A window to Aam Aadmi"
( SH : Post office interior ) [ Civil work ]
(2) Project Arrow -> Wokha Sub- Post Office, " A window to Aam
Aadmi"
( SH : Post office interior ) [ Civil work ]
Enclosed please find herewith the 2(two) Nos of estimates for the above
mentioned works for taking further necessary action.
Enclo: - As above .
Executive Engineer
(Civil)
BSNL, Civil Division,
Dimapur
Copy to :- 1. The Chief Engineer (Civil), BSNLN.E-Zone, Shillong for kind information
please.
No.54(400)BSNL/CD-DMP/08-09/ Dated:26-09-2008
To,
The Dy.General Manager,
O/o the GMTD, BSNL,
Nagaland SSA, Dimapur.
The Preliminary Cum Detailed Estimate for the above noted work is sent
herewith in duplicate for accord of A/A & E/S from your end please.
The necessity of framing the estimate has been explained in the body of history
sheet of the estimate.
The estimate has been registered under the office No. /EE/BSNL/CD-
DMP/08-09.
One copy of the above estimate duly sanctioned by the competent authority
may please be returned to this office for record.
Enclo: - As above .
Executive Engineer
(Civil)
BSNL, Civil Division,
Dimapur
Copy to :- 1. The Superintending Engineer (Civil), BSNL, Civil Circle, Silchar along
with a
copy of the estimate for taking further necessary action please.
To,
The Dy.General Manager,
O/o the GMTD, BSNL,
Nagaland SSA, Dimapur.
The Preliminary Cum Detailed Estimate for the above noted works is sent
herewith in duplicate for accord of A/A & E/S from your end please.
The necessity of framing the estimate has been explained in the body of history
sheet of the estimate.
The estimate has been registered under the office No. /EE/BSNL/CD-
DMP/08-09.
One copy of the above estimate duly sanctioned by the competent authority
may please be returned to this office for record.
Enclo :- As above .
Executive Engineer
(Civil)
BSNL, Civil Division,
Dimapur
Copy to :- 1. The Superintending Engineer (Civil), BSNL, Civil Circle, Silchar along
with a
copy of the estimate for taking further necessary action please.
To,
The Dy.General Manager,
O/o the GMTD, BSNL,
Nagaland SSA, Dimapur.
The Preliminary Cum Detailed Estimate for the above noted works is sent
herewith in duplicate for accord of A/A & E/S from your end please.
The necessity of framing the estimate has been explained in the body of history
sheet of the estimate.
The estimate has been registered under the office No. /EE/BSNL/CD-
DMP/08-09.
One copy of the above estimate duly sanctioned by the competent authority
may please be returned to this office for record.
Enclo :- As above .
Executive Engineer
(Civil)
BSNL, Civil Division,
Dimapur
Copy to :- 1. The Superintending Engineer (Civil), BSNL, Civil Circle, Silchar along
with a
copy of the estimate for taking further necessary action please.
To,
The Dy.General Manager,
O/o the GMTD, BSNL,
Nagaland SSA, Dimapur.
The Preliminary Cum Detailed Estimate for the above noted works is sent
herewith in duplicate for accord of A/A & E/S from your end please.
The necessity of framing the estimate has been explained in the body of history
sheet of the estimate.
The estimate has been registered under the office No. /EE/BSNL/CD-
DMP/08-09.
One copy of the above estimate duly sanctioned by the competent authority
may please be returned to this office for record.
Enclo :- As above .
Executive Engineer
(Civil)
BSNL, Civil Division,
Dimapur
Copy to :- 1. The Superintending Engineer (Civil), BSNL, Civil Circle, Silchar along
with a
copy of the estimate for taking further necessary action please.
To,
The Dy.General Manager,
O/o the GMTD, BSNL,
Nagaland SSA, Dimapur.
The Preliminary Cum Detailed Estimate for the above noted works is sent
herewith in duplicate for accord of A/A & E/S from your end please.
The necessity of framing the estimate has been explained in the body of history
sheet of the estimate.
The estimate has been registered under the office No. /EE/BSNL/CD-
DMP/08-09.
One copy of the above estimate duly sanctioned by the competent authority
may please be returned to this office for record.
Enclo :- As above .
Executive Engineer
(Civil)
BSNL, Civil Division,
Dimapur
Copy to :- 1. The Superintending Engineer (Civil), BSNL, Civil Circle, Silchar along
with a
copy of the estimate for taking further necessary action please.
To,
The Dy.General Manager,
O/o the GMTD, BSNL,
Nagaland SSA, Dimapur.
The Preliminary Cum Detailed Estimate for the above noted works is sent
herewith in duplicate for accord of A/A & E/S from your end please.
The necessity of framing the estimate has been explained in the body of history
sheet of the estimate.
The estimate has been registered under the office No. /EE/BSNL/CD-
DMP/08-09.
One copy of the above estimate duly sanctioned by the competent authority
may please be returned to this office for record.
Enclo :- As above .
Executive Engineer
(Civil)
BSNL, Civil Division,
Dimapur
Copy to :- 1. The Superintending Engineer (Civil), BSNL, Civil Circle, Silchar along
with a
copy of the estimate for taking further necessary action please.
To,
The Dy.General Manager,
O/o the GMTD, BSNL,
Nagaland SSA, Dimapur.
The Preliminary Cum Detailed Estimate for the above noted works is sent
herewith in duplicate for accord of A/A & E/S from your end please.
The necessity of framing the estimate has been explained in the body of history
sheet of the estimate.
The estimate has been registered under the office No. /EE/BSNL/CD-
DMP/08-09.
One copy of the above estimate duly sanctioned by the competent authority
may please be returned to this office for record.
Enclo :- As above .
Executive Engineer
(Civil)
BSNL, Civil Division,
Dimapur
Copy to :- 1. The Superintending Engineer (Civil), BSNL, Civil Circle, Silchar along
with a
copy of the estimate for taking further necessary action please.
To,
The Dy.General Manager,
O/o the GMTD, BSNL,
Nagaland SSA, Dimapur.
The Preliminary Cum Detailed Estimate for the above noted works is sent
herewith in duplicate for accord of A/A & E/S from your end please.
The necessity of framing the estimate has been explained in the body of history
sheet of the estimate.
The estimate has been registered under the office No. /EE/BSNL/CD-DMP/08-
09.
One copy of the above estimate duly sanctioned by the competent authority
may please be returned to this office for record.
Enclo :- As above .
Executive Engineer
(Civil)
BSNL, Civil Division,
Dimapur
Copy to :- 1. The Superintending Engineer (Civil), BSNL, Civil Circle, Silchar along
with a
copy of the estimate for taking further necessary action please.
To,
The Dy.General Manager,
O/o the GMTD, BSNL,
Nagaland SSA, Dimapur.
The Preliminary Cum Detailed Estimate for the above noted works is sent
herewith in duplicate for accord of A/A & E/S from your end please.
The necessity of framing the estimate has been explained in the body of history
sheet of the estimate.
The estimate has been registered under the office No. /EE/BSNL/CD-DMP/08-
09.
One copy of the above estimate duly sanctioned by the competent authority
may please be returned to this office for record.
Enclo :- As above .
Executive Engineer
(Civil)
BSNL, Civil Division,
Dimapur
Copy to :- 1. The Superintending Engineer (Civil), BSNL, Civil Circle, Silchar along
with a
copy of the estimate for taking further necessary action please.
To,
The Dy.General Manager,
O/o the GMTD, BSNL,
Nagaland SSA, Dimapur.
The Preliminary Cum Detailed Estimate for the above noted work is sent
herewith in duplicate for accord of A/A & E/S from your end please.
The necessity of framing the estimate has been explained in the body of history
sheet of the estimate.
The estimate has been registered under the office No. /EE/BSNL/CD-
DMP/08-09.
One copy of the above estimate duly sanctioned by the competent authority
may please be returned to this office for record.
Enclo :- As above .
Copy to :- 1. The Superintending Engineer (Civil), BSNL, Civil Circle, Silchar along
with a
copy of the estimate for taking further necessary action please.
No.03/BSNL/CSD-KOH/ Dated :
To,
The Executive Engineer (Civil),
BSNL Civil Division-I,
Dimapur.
Please find enclosed herewith the above mentioned estimates in triplicate for
further necessary action at your end.
Enclo :- As above .
To,
The Divisional Engineer (OP & Mktg.),
O/o the GMTD, BSNL,
Nagaland SSA, Dimapur.
(ii) Providing and fixing bill board at National High way – 39 (Piphema to
Kohima).
The Detailed Estimates for the above noted works is sent herewith in duplicate
for accord of A/A & E/S from your end please.
The necessity of framing the estimate has been explained in the body of history
sheet of the estimate.
The estimate has been registered under the office No. /EE/BSNL/CD-
DMP/07-08.
One copy of the above estimate duly sanctioned by the competent authority
may please be returned to this office for record.
Enclo :- As above .
Copy to:-
1) The Sub Divisional Engineer(C), BSNL, Civil Sub Division-I, Dimapur.
No.03/BCSD/Koh/07-08/ Dated :
To,
The Executive Engineer(Civil),
BSNL, Civil Division,
Dimapur.
Enclosed please find herewith the estimate for the above noted work in
triplicate for further necessary action at your end.
Enclo :- As above .
Sub-Divisional Engineer
(Civil)
BSNL, Civil Sub-Division,
Kohima, Nagaland.
BHARAT SANCHAR NIGAM LIMITED
(A GOVT. OF INDIA ENTERPRISE)
OFFICE OF THE EXECUTIVE ENGINEER (CIVIL)
WALFORD ROAD, DIMAPUR.
To,
The Sub Divisional Engineer ( C ).
BSNL Civil Sub Division-I
Dimapur.
Subject:- Supplying and fixing Modular work station with furniture for the third floor of
TE building, Dimapur.
Upon checking of the 3 rd and Final bill for the above noted work it has
been found that the quantities and rates for the item no 3,5 and 11 does not match
with the approved deviation statement. It is also noted the reference to recorded
measurements were either wrong or required MBs were not submitted. Hence the bill
is returned herewith along with the two nos MBs (385 & 468) for further check and
resubmission please.
Enclo :- As above .
To,
The Dy.General Manager,
O/o the GMTD, BSNL,
Nagaland SSA, Dimapur.
The Detailed Estimate for the above noted work is sent herewith in duplicate for
accord of A/A & E/S from your end please.
The necessity of framing the estimate has been explained in the body of history
sheet of the estimate.
The estimate has been registered under the office No. /EE/BSNL/CD-
DMP/07-08.
One copy of the above estimate duly sanctioned by the competent authority
may please be returned to this office for record.
Enclo :- As above .
.
To,
The Dy.General Manager,
O/o the GMTD, BSNL,
Manipur SSA, Imphal.
Subject: - Submission of P/E for the work:- Construction of Chowkidar shed at newly
acquired T.E Compound at Porompat, Manipur.
The Detailed Estimates for the above noted work is sent herewith in duplicate for accord of
A/A & E/S from your end please.
The necessity of framing the estimate has been explained in the body of history sheet of the
estimate.
The estimate has been registered under the office No. 1/EE/BSNL/CD-II/ SIL/07-08.
One copy each of the above estimates duly sanctioned by the competent authority may
please be returned to this office for record.
Enclo :- As above .
54(519)BSNL/CD-DMP/10-
11
Name of work:- A/R & S/R works
to 1.5K T.E.Building, E/A room,
security barrack and compound
wall at T.E.Compound,Kuhoboto,
54(520)BSNL/CD-DMP/10-
11
Name of work:- A/R & S/R works
to T.E.Building, security barrack
and compound wall at
T.E.Compound Dhansiripar
54(518)BSNL/CD-DMP/10-
11
Name of work:- A/R & S/R works
to compound wall,Engine room
and Equipment room at
T.E.Compound,Chakabama,Kohi
ma
54(522)BSNL/CD-DMP/10-
11
Name of work:- Construction of
collapsed compound wall at old
T.E.Compound,Tuensang,Nagalan
d.
54(506)BSNL/CD-DMP/10-
11
Name of work:- Renovation of
existing room Nos-6 of VIP IQ in
the O/o the GMTD,Nagaland
SSA,Dimapur,Nagaland.
54(507)BSNL/CD-DMP/10-
11
Name of work:- Construction of
compound wall for Microwave
staff quarter
complex,Kohima,Nagaland.
To,
The Chief General Manager, Telecom,
BSNL, N.E-II Circle,
OCB Building, Dimapur.
The Detailed Estimate for the above work was submitted to your office for
accord of A/A & E/S vide this office letter under reference. The said estimate was
prepared as per discussion with the then CGMT,BSNL,NE-II Circle,Dimapur, which was
conveyed to the undersigned vide Chief Engineer(Civil), letter No-23(12)NE-
II/CE/DMP/71 dated :- 30-03-2009
CONFIDENTIA
L
TO,
SHRI. A.N.THAKUR
SUPERINTENDING ENGINEER (C),
BSNL,CIVIL CIRCLE,DIMAPUR