Professional Documents
Culture Documents
Executive Summary
Canadian Natural Resources Ltd. (CNRL) wishes to increase the capacity of the Steam
Methane Reformer (SMR) unit to produce more hydrogen for increased synthetic crude oil
production. However, increasing the SMR capacity requires an increase in the CO2 Recovery Plant
capacity to maintain the CO2 concentrations in the process streams at an acceptable level.
Okane Engineering was requested by CNRL to develop a redesign of the CO2 Recovery
Plant at Horizon Oil Sands near Fort McKay, Alberta that would increase the operating capacity
by 15% and 25%. This project would reduce the greenhouse gas (GHG) emissions costs incurred
under the provincial and federal climate leadership plans. Without reductions in GHG emissions,
the increasing carbon tax prices would compromise the profitability of the Horizon Oil Sands
facility. This project would also provide an opportunity for additional revenue from the sale of
ProMax simulation software was used to develop the process redesigns. The design and
operating data provided by CNRL were used as benchmarks for design. An AACE Class 4 cost
estimate was completed using a discount rate of 15% and hurdle rate of 20% over a 20-year project
life to evaluate economic feasibility. Project revenues were calculated using a carbon tax price of
C$30 per tonne of CO2 equivalent (/tCO2e) and estimated CO2 selling price of C$23 /tCO2.
The proposed redesign for the 125% operating capacity involves the optimization of
operating pressures and temperatures and modification of packing configurations in the CO2
Absorber and LP Flash Stripper. Three additional exchangers and the upsizing of two drums are
also required. The resulting CO2 product flow rate is 63.2 tonnes per hour (t/h), which is a 20.9%
increase from the base case. Project execution is expected to take 23 months, which includes 7
months for engineering, 8 months for procurement, 7 months for construction, and 4 months for
i
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
commissioning and start-up. The estimated capital cost was C$14.76 MM with a C$4.51 MM
increase in annual operating costs compared to the base case. This redesign was not feasible at
current economic conditions, with a net present value (NPV) of -C$10.69 MM. For this redesign
to be economically feasible, the combined total of the sale price of CO2 and carbon tax price would
Due to the design constraints of the existing equipment, a 12% capacity increase was
proposed instead of a 15% increase. The 112% capacity redesign optimizes the operating pressures
and temperatures for the existing equipment. The resulting CO2 product flow rate is 56.2 t/h, which
is a 7.7% increase from the base case. Implementation of this redesign is done onstream, so project
execution time is minimal. The estimated increase in the annual operating cost was C$670 K,
which gave an NPV of C$6.64 MM. This redesign was determined to be economically feasible
and would provide an additional revenue of C$1.86 MM per year compared to the base case.
Both capacity redesigns were determined to be properly risk managed and socially and
environmentally sustainable. Safety and risk analyses identified potential high-velocity lines in
both cases which should be evaluated for corrosion concerns prior to project execution.
Based on economic feasibility and project execution time, Okane Engineering recommends
the 112% capacity redesign. Field tests should be completed to verify the CO2 recovery efficiencies
stated in the redesign due to limitations in the simulation model. The vendor compressor unit
equipment specifications were also out of scope and must be validated prior to project execution.
ii
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Table of Contents
Executive Summary ......................................................................................................................... i
1. Introduction and Statement of Objectives ............................................................................... 1
2. Background ............................................................................................................................. 2
3. Proposed Solution.................................................................................................................... 3
4. Justification ............................................................................................................................. 4
5. Alternatives Considered .......................................................................................................... 5
5.1. Do Nothing .................................................................................................................. 5
5.2. Replacement of Plant with Gasification System ......................................................... 6
6. Project Description .................................................................................................................. 6
6.1. Existing Process Design Description – Kaitlin ........................................................... 9
Model Verification ....................................................................................... 11
Separation Model Verification ..................................................................... 11
Areas of Heat Exchange Verification .......................................................... 12
Staged Compression Verification ................................................................ 12
6.2. Project Assumptions, Constraints, and Limitations .................................................. 12
Assumptions and Constraints ....................................................................... 12
Limitations ................................................................................................... 14
Project Dependencies ................................................................................... 14
Technical Feasibility .................................................................................... 15
7. Option A: 125% Capacity Redesign ..................................................................................... 15
7.1. Process Description ................................................................................................... 15
CO2 Absorption............................................................................................ 18
CO2 Desorption ............................................................................................ 19
Design Considerations ................................................................................. 19
Start-Up and Shutdown Considerations ....................................................... 19
7.2. Heat Integration ......................................................................................................... 20
7.3. Material and Energy Balances ................................................................................... 21
7.4. Equipment List and Sizing ........................................................................................ 22
iii
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Columns ....................................................................................................... 23
Heat Exchangers .......................................................................................... 23
Vessels ......................................................................................................... 24
Pumps........................................................................................................... 25
Compressors ................................................................................................. 25
Process Piping .............................................................................................. 26
Materials of Construction ............................................................................ 27
7.5. Utility Requirements ................................................................................................. 27
7.6. Project Execution Strategy ........................................................................................ 28
Engineering Plan .......................................................................................... 30
Procurement Plan ......................................................................................... 30
Construction Plan ......................................................................................... 31
Commissioning Plan .................................................................................... 31
Project Management Schedule ..................................................................... 32
7.7. Economic Analysis .................................................................................................... 33
Economic Introduction................................................................................. 33
Fixed Capital Expenditure ........................................................................... 33
Working Capital Expenditure ...................................................................... 35
Operating Cost ............................................................................................. 35
Financing Plan ............................................................................................. 37
Discounted Cash Flow Analysis .................................................................. 37
Sensitivity Analysis ..................................................................................... 38
Economic Conclusions................................................................................. 39
7.8. Environmental Analysis ............................................................................................ 39
Environmental Conclusions ......................................................................... 41
7.9. Safety and Risk Analysis ........................................................................................... 41
Identification of Hazards and Safety Risks .................................................. 42
What If? Process Hazard Analysis ............................................................... 42
Hazard and Operability Study...................................................................... 43
Chemical Exposure Index ............................................................................ 44
iv
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
v
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
vi
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
List of Figures
Figure 1: Block Flow Diagram of CO2 Recovery Plant with CO2 Removal Unit Scope
Indicated .......................................................................................................................... 7
Figure 2. Process Flow Diagram for the Base Case and 112% Capacity Redesign ....................... 8
Figure 7: Operating Cost Breakdown for the 125% Capacity Increase ........................................ 36
Figure 8: Discounted Cash Flow Profile for the 125% Case ........................................................ 37
Figure 10: IRR Tornado Diagram for the 125% Case .................................................................. 39
Figure 11: Chemical Exposure Radii by ERPG Level Overlaid on Satellite Imagery for the
Figure 12: Operating Cost Breakdown for the 112% Capacity Increase ...................................... 54
Figure 13: Discounted Cash Flow Profile for the 112% Case ...................................................... 55
Figure 14: NPV Tornado Diagram for the 112% Case ................................................................. 56
Figure 16: Chemical Exposure Radii by ERPG Level Overlaid on Satellite Imagery for the
vii
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
List of Tables
Table 1: Outline of Given Stream Specifications ......................................................................... 13
Table 2: Temperature, Pressure, and Flow Rate Changes for the 125% Capacity Redesign ....... 16
Table 3: Equipment Modifications and Additions Required for the 125% Redesign Case .......... 16
Table 4: Summary of Streams Requiring Cooling or Heating for Heat Integration ..................... 20
Table 12: Additional Utility Requirements for 125% Capacity Redesign ................................... 28
Table 15. Fire and Explosion Index Summary Table for the 125% Redesign Case ..................... 46
Table 16: Temperature, Pressure, and Flow Rate Changes for the 112% Capacity Redesign ..... 49
Table 22: Fire and Explosion Index Summary Table for the 112% Redesign Case..................... 60
viii
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
bitumen into synthetic crude oil (SCO) using delayed coking and hydrotreating processes (1). This
requires a large excess of hydrogen which is supplied by the Steam Methane Reformer (SMR) unit.
The SMR produces 144 million standard cubic feet per day of hydrogen (2). CNRL wishes to
increase the capacity of the SMR unit to improve hydrogen supply to support future increases in
SCO production. However, increasing the capacity of the SMR would result in higher flow rates
of syngas feed to the CO2 Recovery Plant. At current conditions, this increase would result in
higher concentrations of CO2 in the feed to the Pressure Swing Adsorption (PSA) unit and potential
corrosion issues. Therefore, if the capacity of the SMR unit is increased, the CO2 Recovery Plant
The CO2 Recovery Plant reduces the greenhouse gas (GHG) emissions of the Horizon Oil
Sands site by recovering 438,000 tonnes of CO2 each year (2). Under the Alberta climate change
plan, the current price of GHG emissions exceeding the nominal limit is C$30 per tonne of CO2
equivalent (/tCO2e), which is proposed to rise to C$50 /tCO2e by 2022 under Canada’s federal
climate change plan (3; 4). Recovering more CO2 would reduce the GHG emissions compliance
costs and provide economic benefit. Increased recovery of CO2 would also minimize long-term
economic risks from potential increases in carbon prices. Recovering more CO2 is also an
opportunity for additional revenue. CO2 product is utilized in tailings management processes and
can be sold to other facilities in Alberta at a current market price of C$23 per tonne.
CNRL has requested Okane Engineering to complete a capacity augmentation study of the
Horizon Oil Sands CO2 Recovery Plant. The objective of this project is to develop cost-effective
process redesigns of the CO2 Recovery Plant that will increase its existing operating capacity by
1
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
15% and 25%. The redesigns must increase operating capacity while optimizing CO2 recovery and
energy input.
2. Background
The CNRL Horizon Oil Sands site is a regulated facility under the Carbon Competitiveness
Incentive Regulation (CCIR) and subject to the carbon tax (5; 6). Regulated facilities are not
penalized under the CCIR if their GHG emissions are below a designated limit, which depends on
the industry specific emissions benchmarks. If regulated facilities emit GHGs above the designated
limits, they are subject to compliancy costs calculated based on excess GHG emissions. To
maintain compliancy with the CCIR, these facilities must either reduce their emissions intensity,
Climate Change and Emissions Management Fund (CCEMF) (7). The cost to purchase carbon
offset credits or contribute to the CCEMF is currently C$30 /tCO2e excess, which could rise to
C$50 /tCO2e by 2022 (8). By increasing the CO2 Removal Unit’s capacity, CNRL would improve
its compliancy with CCIR limits by avoiding significant increases in CO2 emissions that would
have resulted from increased hydrogen production. CNRL may also be eligible to earn emission
offset credits for its GHG reduction, lessening the amount of credits they would have to purchase
Canada produces roughly 2% of global CO2 emissions despite representing only 0.5% of the
world’s population, 10% of which is accounted for by the oil sands alone (9). To encourage
emissions reductions, the Alberta Government implemented the Oil Sands Emissions Limit Act
(Bill 25) in December 2016 which specifies an annual 100 MT GHG emissions limit for all oil
sands sites combined (10). Therefore, oil sands facilities must collectively limit emissions
2
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
fundamental value of CNRL (12). CNRL has thus developed an integrated GHG emissions
reduction strategy which aims to reduce CNRL’s emissions intensities to below the global crude
average of 63.78 kgCO2e per barrel of crude oil (13; 14; 15). Increased CO2 recovery would
contribute towards this goal and strengthen the company’s position as an industry leader in GHG
emissions reduction. Additional recovered CO2 can also be used to support environmental
initiatives in nearby oil sands facilities who currently truck in purchased CO2 from Edmonton (16).
Examples of initiatives include the Non-Segregating Tailings process and Carbon Capture and
The current global demand for CO2 is estimated to be 80 megatonnes per annum (MTPA)
and is forecasted to reach 140 MTPA by 2020 (18). At least 50 MTPA is utilized for enhanced oil
recovery (EOR) exclusively within North America. The market price for bulk CO2 sold via
pipeline has historically been in the range of C$12 to C$35 per tonne (18). Recovering more CO2
would supply Horizon Oil Sands with additional CO2 that could be sold to other large-scale
3. Proposed Solution
Okane Engineering initially proposed that a 115% capacity redesign of the CO2 Recovery
Plant would be achieved within the design limits of the existing equipment. However, further
investigation revealed that the maximum achievable operating capacity using only existing
equipment was 112%. After consultation with the client, a 112% capacity redesign was accepted
Okane Engineering proposes two options to increase the CO2 Recovery Plant’s operating
capacity. The first option achieves the desired capacity increase to 125% and requires equipment
additions and modifications. This method requires a large capital expenditure and significantly
3
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
higher utility usages, raising operating costs as well. However, it achieves the desired 125%
capacity with the potential for further increases through optimization of operating conditions.
The second option achieves an increased capacity to 112% by modifying process operating
conditions and utility usage. It does not require the addition or modification of equipment and thus
no capital expenditure. However, the disadvantage is that the increase in capacity is limited to 12%
Both redesigns would increase the amount of CO2 recovered. This would result in cost
savings by reducing the number of GHG emissions credits purchased and would provide an
opportunity for increased revenue from the sale of additional CO2 recovered. Increasing the CO2
Recovery Plant capacity would also enable more hydrogen production in the SMR, enabling
4. Justification
Appendix A contains the decision analysis criteria used to evaluate the alternatives
considered. First, the options were evaluated against the “must” criteria which included having the
ability to reduce GHG emissions and ability to achieve a minimum capacity increase of 12%.
Options that passed these criteria were then rated and compared quantitatively based on the desired
“wants” of minimizing capital costs, GHG emissions, operating costs, and project execution time.
The addition or modification of process equipment option was chosen for the 125%
capacity redesign. This was due to limitations in the design capacities of the existing equipment
and a lower capital cost relative to the other options. The optimization of process operating
conditions was chosen for the 112% capacity redesign because it was able to achieve a 12%
4
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
The 25% increase in operating capacity was achieved by changing the packing
configurations in the columns, adding three additional exchangers, and upsizing two drums. The
amount of CO2 recovered is 1435 kmol/h of CO2 which corresponds to an increase of C$5.09 MM
in the annual revenue compared to the base case. The total capital cost is C$14.76 MM with an
increase of C$4.51 MM in the annual operating cost. Based on a 20-year project lifetime and
corporate discount rate of 15%, the NPV is -C$10.69 MM indicating that the 125% capacity
redesign is not economically feasible. For the project to be economically feasible at the current
carbon tax, the selling price of CO2 would need to be C$49 /tCO2 which is unreasonably expensive
for commercial grade CO2. This option was therefore not recommended from an economic
The 12% capacity increase was achieved through optimization of operating pressures and
temperatures within the design limits of the existing equipment. The amount of CO2 recovered was
1278 kmol/h of CO2, corresponding to an increase of C$1.86 MM in the annual revenue compared
to the base case. No capital cost is involved in this redesign. The increase in annual operating cost
is C$0.67 MM. The calculated NPV is C$6.64 MM indicating that the 112% capacity redesign is
economically feasible. Therefore, pursuing the 112% capacity redesign is justified based on the
Feedstock availability is not a foreseeable issue as the syngas feed used is a byproduct of the
SMR. The amine make-up required is also very minimal, so amine availability is not a concern.
5. Alternatives Considered
5.1. Do Nothing
In the “Do Nothing” option, no equipment or operational changes are made to the CO2
Removal Unit. This would result in increased CO2 concentrations in the syngas feed to the PSA at
5
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
higher feed flow rates, resulting in corrosion issues. The CO2 recovery efficiency of the unit would
also decrease as feed rates increase due to process design limitations. This would result in higher
GHG emissions and would progressively cost more in the long-term due to increasing GHG
emissions compliance costs. Thus, this option is economically and environmentally undesirable.
gasification system. This type of system can produce a high purity CO2 product at increased feed
flow rates without the need for excess dehydration units and is currently used a the North West
Sturgeon Refinery (19). The capital cost of this option is very high due to the major reconstruction
of the plant and reconfigurations of upstream and downstream tie-ins. As a result, this option is
6. Project Description
The CO2 Removal Unit begins with the syngas inlet stream to the CO2 Absorber and ends
with the CO2 product stream at battery limits. The project scope includes existing equipment within
the battery limits of the CO2 Removal Unit and excludes the dehydration unit, make-up vessels,
pumps, and anti-foam injection system. It does not include upstream or downstream processes,
such as the separation of syngas or processing of syngas through pressure swing adsorption. The
treatment of steam, cooling water, boiler feed water, fuel gas, and natural gas are also not included
in this project scope. A block flow diagram outlining the major processes of the CO2 Recovery
Plant and the identified CO2 Removal Unit project scope is shown in Figure 1. A process flow
diagram (PFD) of the CO2 Removal Unit is shown in Figure 2 and in Appendix E with associated
stream tables.
6
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Pressure Swing
Tail Gas
Absorption
Lean Amine
Syngas
Project Scope
Separation
System
Boiler Feed
Water
High
Process Gas Temperature
Reaction
Figure 1: Block Flow Diagram of CO2 Recovery Plant with CO2 Removal Unit Scope Indicated
7
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
94
FC
96
87 G-83A/B
Synthesis Gas 25
C-80 LC
82
FC
PC C-82
Process Water to
Flash Gas to Steam
Methane Reformer
75
C-81 E-81A/B Battery Limits
83 78 FC
73 74
LC E-82 LP Steam
81
86 76
LP Condensate
85
E-84 84
C-84
LP Steam
LP Condensate G-82A/B/C G-81A/B
G-84
Revamp of Carbon Dioxide Recovery Plant
Amine Solution
Figure 2. Process Flow Diagram for the Base Case and 112% Capacity Redesign
8
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
effective CO2 absorption accelerator used in aqueous MDEA solutions. The two key processes of
the CO2 Removal Unit are the absorption of CO2 by lean amine solution and the desorption of CO2
from the rich amine solution which occur in the CO2 Absorber and LP Flash Stripper, respectively.
The absorption and desorption of CO2 by MDEA occur based on the following reactions (20):
where R3N represents MDEA (C5H13NO2). The resulting net total reaction is:
These reactions determine the overall amount of CO2 that can be recovered by the unit.
The PFD of the existing CO2 Recovery Plant is shown in Figure 2. The syngas is fed to the
CO2 Absorber (C-80) at a flow rate of 8217 kmol/h and flows countercurrent against the liquid
lean amine solution. The lean amine solution removes the CO2 from the syngas and exits the
bottom of the column as rich amine solution. The syngas released from the top of the CO2 Absorber
contains less than 3 mol% CO2 and is cooled to 40 °C in the CO2 Absorber Overhead Cooler (E-
80). The condensed water is separated and removed in the Absorber Overhead Knockout Drum
(C-87) under level control. The remaining syngas exits the drum and is further treated in the PSA
9
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
unit. A small amount of LP Condensate is fed to the top of the CO2 Absorber under flow control
The rich amine solution exiting the bottom of the CO2 Absorber is directed under level
control to the HP Amine Flash Drum (C-81). Some gas is flashed off and sent to the SMR while
the remaining liquid rich amine is routed to the LP Flash Stripper (C-82). The LP Flash Stripper
In the flash section, CO2 is separated at an operating pressure of 40 kPa(g). The gas exiting
the top of the LP Flash Stripper contains water and 82 mol% CO2 and is cooled in the Stripper
Overhead Condenser (E-83) to 45 °C. The resulting water condensate is removed in the Reflux
Vessel (C-83) and returned to the LP Flash Stripper by the Stripper Reflux Pump (G-83A/B) under
flow control. This prevents the entrainment of amine in the stripper overhead gases. The CO2 rich
gas exiting the top of the Reflux Vessel is routed to the compressor and dehydration units before
going to battery limits. The final CO2 product stream has a 99.9 mol% purity of CO2 and flow rate
of 1188 kmol/h. This translates to 438,000 tonnes of CO2 recovered annually (2; 17).
The semilean amine solution produced in the flash section is withdrawn under level control
into a pumparound loop, where it is heated against the hot lean amine solution from the stripper
bottoms in the Lean/Rich Amine Exchanger (E-81A/B). The heated semilean amine solution is
returned under level control to the top of the stripping section of the LP Flash Stripper by the
In the stripping section, the Stripper Reboiler (E-82) heats the column bottoms using low
pressure steam to 114°C at 50 kPa(g) based on a temperature control loop. The vaporized water
and CO2 gas rises countercurrent to the semilean amine solution and removes enough CO2 from
10
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
the semilean solution to regenerate lean amine solution suitable for use in the CO2 Absorber. The
lean amine exits the bottom of the LP Flash Stripper at 114 °C.
The hot lean amine solution is cooled against the semilean amine solution in the Lean/Rich
Amine Exchanger to 83°C, and then cooled to 45 °C in the Lean Amine Air Cooler (E-84). The
lean amine is routed by the HP Lean Amine Pump (G-82A/B/C) under flow control to the top of
Model Verification
The ProMax simulation software by Bryan Research & Engineering (BRE) was used to
model the CO2 Removal Unit. The client provided the material balance for the design basis and
operating data summaries for select equipment which were used as the benchmark for design.
Appendix B contains detailed explanations for simulation assumptions. Appendix C shows the
calculations used to validate the simulation model. More detailed calculations on separation can
be found in Appendix D. The model was validated based on the accuracies of the property package,
The separation model selected for the CO2 Absorber was the TSWEET Kinetics Model. This
model was recommended by BRE for electrolytic property package environments and for columns
where CO2 is present in one of the feed streams. The separation model used for the LP Flash
Stripper was the TSWEET Absorber/Stripper Model because it was the most accurate in modelling
the desorption of CO2 when compared to the design basis. Model verification was done using the
average absorption factor method outlined by Kremser and Brown, Robbins correlation for
pressure drop, and Eckert generalized pressure drop correlation for vapor flows (21; 22).
11
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Heat exchangers in the simulation model were verified by comparing the simulated area of
heat exchange to the area of heat exchange provided in the operating data summary. The simulated
areas were within 5% of the provided heat exchanger areas indicating strong agreement.
Modelling of the vendor compressor unit in the simulation was validated using calculations
based on isentropic gas compression. The number of calculated required compression stages was
three, which was consistent with the obtained simulation results. The number of compression
The CO2 Removal Unit uses aMDEA, which was assumed to be 3 wt% piperazine activator
and 97 wt% MDEA. The amine solution makeup was assumed to be 96 wt% aMDEA and 4 wt%
water. The specifications for the inlet streams to the CO2 Absorber were provided by CNRL. These
specifications are summarized in Table 1 and shown in Appendix B. It was assumed that the molar
12
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
The inlet stream compositions, pressures, and temperatures were used as constraints in the
redesign. The CO2 product stream had to have a CO2 purity of 92.0 mol% or higher for redesign.
The syngas feed to the PSA was limited to having a CO2 concentration of 3 mol% or less to prevent
corrosion issues in the downstream equipment. The 3 wt% piperazine concentration was also not
be increased in order to prevent corrosion issues. The CO2 loading for the rich amine was
At the request of the client, the number of bypasses and recycles were kept to a minimum to
avoid major changes to the existing process design. Thus, bypasses and recycles were avoided as
For modelling of the CO2 Removal Unit in ProMax, additional assumptions were needed to
Assumptions included the use of an adiabatic system, negligible changes in inlet and outlet
13
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
pressures for equipment where pressure drops were not specified, pump efficiencies being 90% of
the hydraulic efficiencies, compressor efficiencies of 80%, and tray weir heights of 5.08 cm (2 in).
Limitations
The simulation model used for design had limited accuracy in modelling the CO2 absorption
process, which was likely due to the property package used. A more accurate custom property
package for the CO2 Removal Unit system could not be developed or purchased due to a lack of
resources. As a result, the stated CO2 recovery efficiencies in the redesigns may have some error.
It is recommended to verify the CO2 recovery efficiencies stated in the redesigns by performing
The constraints of the 112% capacity redesign were the design limits of the existing
equipment, as specified in the given equipment data or based on design calculations using the
simulated base case model. No sizing information was given for the process piping sizes, so sizing
approximations were determined using the provided material balance for the design basis. Velocity
flow limitations must be verified against the existing pipe sizes, as high velocity lines were
identified as potential risks for the 112% and 125% capacity redesigns. Limited information was
provided for the vendor compressor unit, which was approximated using a three-stage compression
process. The capacity of the vendor compressor unit would also need to be verified prior to
Project Dependencies
The CO2 Removal Unit is a subunit of the CO2 Recovery Plant, which is part of the Hydrogen
Plant. The outlet syngas from the CO2 Absorber passes through the Absorber Overhead K.O. Drum
and is treated in the PSA. Implementing the 112% or 125% capacity redesign will result in an
increased feed flow rate of syngas to the PSA. The ability of the PSA unit to handle the increased
14
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
feed would need to be evaluated prior to project execution. The redesigns also have higher utility
usages, requiring more cooling water and electricity. This would put extra stress on the cooling
water supply and return headers and electricity power transmission lines. The capability of these
facilities to support the increased demand in utilities would thus need to be verified. The existing
amine make-up vessel is also currently sized to contain the total amount of amine circulated in the
base case for maintenance purposes. In the 112% and 125% capacity redesigns, the amine flow
rates increase, so the ability of the make-up vessel to hold the additional amine would also need to
be verified.
Technical Feasibility
The feasibility of the project is contingent upon the accuracies of the stated assumptions.
The process was simulated using the design basis provided and benchmarked using operating data
of the existing plant. Calculations used to validate equipment modifications can be found in
Appendix D. Where required, additional equipment was added with considerations given to the
space available in the existing plant as indicated by the provided plot plan. Provided that field
testing is done to verify the accuracy of the simulated CO2 Absorber efficiency, the redesigns of
the CO2 Removal Unit outlined in this study are technically feasible.
pressures and temperatures and by adding and modifying equipment. The changes in operating
setpoints needed to achieve 125% operating capacity are shown by stream in Table 2. The
equipment additions and modifications are summarized in Table 3. A PFD of the 125% capacity
15
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Table 2: Temperature, Pressure, and Flow Rate Changes for the 125% Capacity Redesign
Stream Description Base Case 125% Case
25 SG to CO2 Absorber Flow Rate 8214 kmol/h 10271 kmol/h
27 SG from CO2 Absorber OH Cooler Temperature 40.0 °C 39.0 °C
36 CO2 to Reflux Vessel Temperature 45.0 °C 41.5 °C
72 Steam Condensate to CO2 Absorber Flow Rate 122 kmol/h 130 kmol/h
86 Lean Amine from Air Cooler aMDEA Flow Rate 2018 kmol/h 2211 kmol/h
86(C) Lean Amine from Air Cooler Temperature 45.0 °C 40 °C
95 Process Condensate to LP Flash Stripper Flow Rate 142 kmol/h 116 kmol/h
- CO2 Absorber Bottom Operating Pressure 3285 kPa(g) 3300 kPa(g)
- LP Flash Stripper Bottom Operating Pressure 50 kPa(g) 55 kPa(g)
Table 3: Equipment Modifications and Additions Required for the 125% Redesign Case
Equipment Tag Description Base Case 125% Case
C-80 CO2 Absorber Packing Type IMTP #40 IMTP #25
C-80 CO2 Absorber Total Packing Height 8.6 m 10.2 m
C-82 LP Flash Stripper Packing Type IMTP #50 IMTP #40
C-83 Stripper Reflux Vessel Volume 14.8 m3 36.8 m3
C-87 Absorber Overhead K.O. Drum Volume 5.7 m3 9.7 m3
E-81A/B(/C) Lean/Rich Amine Exchanger Area 1190 m2 1785 m2
E-85A/B Lean Amine Cooler Area - 815 m2
16
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
In the 125% capacity redesign, the process flow remains largely the same as the base case.
The only change is the addition of a Lean Amine Cooler (E-85A/B) downstream of the Lean Amine
Air Cooler (E-84). Like the base case design, the hot lean amine solution is cooled against the
semilean amine solution in the Lean/Rich Amine Exchanger (E-81A/B/C). The lean amine is then
air cooled to 40 °C in the Lean Amine Air Cooler and flows to the Lean Amine Cooler which cools
the lean amine to 34.7 °C. The HP Lean Amine Pump (G-82A/B/C) is still used under flow control
to pump lean amine to the top of the CO2 Absorber (C-80). In the 125% capacity redesign, the
amount of CO2 product produced is 1435 kmol/h. This is a 20.9% increase from the base case CO2
CO2 Absorption
The operating pressure at the bottom of the CO2 Absorber (C-80) is increased to raise the
partial pressure of CO2 in the column. The flow rate of aMDEA fed to the column is increased to
allow for better wetting of the packing to increase the effective area for mass transfer in the CO2
Absorber, further increasing absorption rates. The temperature of the lean amine stream is also
lowered to compensate for the heat generated by the exothermic absorption process. These factors
all improve the mass transfer of CO2 to amine solution, increasing the absorption rate of the CO2
Absorber (23). To further increase absorption rates, the existing IMTP #40 packing in the column
is replaced with IMTP #25 to increase the effective area for mass transfer by a factor of 1.4 (22).
The packing height is also increased by 0.8 m in both beds to accommodate an additional 12.1 m3
of packing to further increase the effective area for mass transfer. These changes improve the
efficiency of the CO2 Absorber and maintain a CO2 concentration just below 3.00 mol% in the
outlet syngas. Note that the Absorber Overhead Knockout Drum (C-87) must be upsized in order
18
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
CO2 Desorption
To effectively regenerate lean amine, the packing type in the LP Flash Stripper (C-82) is
changed to IMTP #40 to allow for better stripping of the CO2 from the semilean amine solution.
The bottom operating pressure of the stripper is increased to 55 kPa(g) to accommodate for the
increased pressure drop caused by the smaller packing type. The required flow rate of water recycle
to the LP Flash Stripper for tray backwashing is reduced due to the improved separation efficiency
of the column. An additional exchanger is added to the Lean/Rich Amine Exchanger (E-81A/B/C)
to recycle more cooling duty in the hot lean amine stream. This minimizes the size of the new Lean
Amine Cooler (E-85A/B). Note that the Reflux Vessel (C-83) must be upsized in order to
Design Considerations
No further increases in operating capacity were investigated beyond the 25% increase due
to project time constraints and concerns regarding the economic feasibility of design. The 125%
redesign also uses a CO2 loading factor of 0.71 mol CO2/mol amine. This is 0.06 higher than the
recommended limit but is still within the maximum equilibrium CO2 loading capacity of 1.0 mol
CO2/mol amine (24). However, this may cause corrosion issues and should be further evaluated
if implementation of the 125% capacity redesign is pursued. The 125% capacity redesign outlined
in this study is not economically feasible due to the large capital costs for equipment. Further
increases in capacity would likely require more equipment modifications and be less economically
feasible.
shell after cleaning and prior to commissioning to protect the carbon steel shell from corrosion.
19
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Modifications to the existing start-up and shutdown procedures will also be needed to include the
plot plan was provided, and it had been requested to keep the addition of recycle and bypass
streams to a minimum. Due to limitations in space and restrictions on stream flexibility, the
existing integrated heat exchanger system was optimized instead of proposing a new network.
There are four main process streams that require the addition or removal of heat which are
summarized in Table 4.
The existing heat integration system transfers heat from the hot lean amine (Stream 83) to
the semilean amine (Stream 78) through the Lean/Rich Amine Exchanger (E-81A/B) in the
pumparound loop. As the semilean amine is heated and returned to the LP Flash Stripper, some of
To optimize energy input into the 125% case, heat exchange in E-81A/B is maximized by
adding a third unit (E-81C). This is more cost-effective than using two separate heat exchangers
for cooling and heating using cooling water and steam. Although this configuration is not able to
provide the full cooling duty required by the lean amine stream, it reduces the duty of the new
20
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Lean Amine Exchanger (E-85A/B) by 8.9 MW which significantly reduces its size and the amount
Table 6. Detailed balances which include the breakdown of the compressor unit energy
consumption are presented in Appendix G. The envelope used for all material and energy balances
is the box shown in Figure 1 which outlines the project scope. The material and energy balances
close with negligible percent differences, indicating that both mass and energy were conserved.
96 -
Water Header 36.7
Amine Blowdown Amine Blowdown - 0.0
Water Blowdown Water Blowdown - 0.0
37C Stage 1 Compressor K.O. Vessel - 64.9
37G Stage 2 Compressor K.O. Vessel - 23.0
Total (kmol/h) 10403.1 10403.0
Percent Difference 0.0%
21
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
96 - -2,898
Water Header
Amine Blowdown Amine Blowdown - 0
Water Blowdown Water Blowdown - 0
37C Stage 1 Compressor K.O. Vessel - -5,124
37G Stage 2 Compressor K.O. Vessel - -1,822
E-80 CO2 Absorber Overhead Cooler - 1,107
E-82 Stripper Reboiler 31,600 -
E-83 Stripper Overhead Condenser - 2,190
EQUIPMENT
Appendix H. Operating data provided by the client for select pieces of equipment are also included
in this appendix. Methodologies from Gas Processors Suppliers Association (GPSA) Engineering
Data Book, Perry’s Chemical Engineers’ Handbook, and Process Heat Transfer by Kern (1950)
were employed in the sizing of equipment. Equipment sizing is preliminary and performed to the
22
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
level required for economic evaluation except for the Lean Amine Cooler (E-85A/B). Detailed
Columns
The two main columns in the process are the CO2 Absorber and the LP Flash Stripper.
Column separation efficiencies, tray spacings, and packing, disengagement, and liquid pool
heights were validated for the existing column heights and diameters. These calculations can be
found in Appendix D. The additional separation capacities required for redesign were satisfied by
changing the type and volume of packing in the existing columns. Increased pressure drops were
Heat Exchangers
The use of existing heat exchangers was maximized in the 125% capacity redesign. The heat
transfer coefficients of the existing exchangers were derived using operating data and were used
to calculate the heat exchanger areas required for redesign. Part of the increased cooling duty
required in the 125% redesign is met by adding a third plate and frame heat exchanger E-81C (595
m2) to the Lean/Rich Amine Exchanger (E-81A/B). This is a very compact unit, so the footprint
required is minimal compared to a shell and tube heat exchanger. The remaining cooling duty
required is supplied by the additional Lean Amine Cooler (E-85A/B). The temperature difference
23
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
required two shell passes and four tube passes which are met by two 1-2 heat exchangers with U-
tube bundles placed in series. This eliminates gaskets that are prone to leaking and minimizes the
footprint required, as the exchangers are stacked on top of each other. A temperature transmitter
with a high temperature alarm set at 45°C is located on the lean amine outlet. At 45°C, the CO2
concentration is significantly higher than 3 mol%, resulting in potential corrosion issues in the
PSA unit. The temperature transmitter is also used in conjunction with a control valve to set the
flow rate of cooling water to the heat exchanger. The existing flow transmitter located downstream
of the Lean Amine Cooler is used to control the flow rate of lean amine to the CO2 Absorber.
Vessels
The vessels for this process are primarily used for vapour-liquid phase separation. The
existing HP Amine Flash Drum (C-81) was sufficient for operation at 125% capacity. However,
the Absorber Overhead K.O. Drum (C-87) and Reflux Vessel (C-83) required larger diameters to
achieve effective separation at the increased flow rates. The gravity settling approach and Souders-
24
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Brown approach were used to determine the minimum dimensions required to obtain effective
separation. Vessel thickness was calculated according to ASME Section VIII Division 1.
Pumps
Pump capacities as well as maximum and minimum pressures were maintained within the
allowable ranges stated in the operating data given by the client for the 125% capacity redesign.
No additional pumps were required for this case. However, the power consumption of the pumps
increased slightly due to more shaft power being required at higher flow rates. Overall pump
Compressors
In the PFD provided by the client, the compression of CO2 was shown as a single vendor
unit with a note stating that compressors, interstage coolers, and knockout drums were included.
Due to the lack of information, the vendor compressor unit was approximated using the three-stage
25
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
required compression could be achieved within three stages, it was assumed that the existing
vendor unit was sufficient. In the 125% capacity redesign, only three stages of compression were
needed, so the vendor unit was deemed to be sufficient. The maximum allowable discharge
temperature used for the compressors was 150°C based on GPSA recommendations (21).
Process Piping
Information on the existing process pipe sizes was not provided by the client. Due to the lack
of information, the existing pipe sizes were approximated using the material balance for the design
basis provided by the client, taking into consideration pressure drops for single-phase and two-
phase flow, pump suction lines, and guidelines for minimizing erosion-corrosion in amine units.
Based on the flow rates in the 125% capacity redesign, the piping fluid velocities are mostly within
acceptable ranges indicating that existing piping sizes are sufficient. However, streams 35, 36, and
37 were found to have expected velocities above recommended values. A table listing the nominal
pipe size, schedule, material specification, expected velocity, and type of flow through all main
process lines can be found in Appendix H. Calculations for the process lines sizing are also
26
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Materials of Construction
Detailed analyses of the material selection and corrosion mechanisms identified for this
project can be found in Appendix H. In the CO2 Removal Unit, the primary degradation
mechanism is amine corrosion. Amine corrosion refers to the general or localized corrosion that
occurs primarily on carbon steel in amine treating processes. It results from dissolved acid gases
(e.g. CO2), amine degradation products, heat stable amine salts and other contaminants (25; 26).
Low-carbon and stabilized grades of austenitic steels have successfully been used in areas of high
corrosion rates due to their high strength and corrosion resistance over a wide range of operating
conditions.
To protect against amine corrosion, corrosion prone areas were constructed out of ASTM
A358 Type 304L and Type 316L stainless steel. Corrosion prone areas were identified as regions
having high acid gas loading, high flow velocities, turbulent flow, flow impingement, vapour
flashing, two-phase flow, and operating temperatures over 110 °C. Regions with low acid gas
concentrations or lower operating temperatures were less prone to amine corrosion. These regions
were constructed of ASTM A106 Grade B carbon steel, which costs less but still has high strength.
ASTM A333 Grade 6 killed carbon steel was used at the bottom of the LP Flash Stripper due to
higher operating temperatures. Type 316L stainless steel has higher corrosion resistance in
chloride containing environments, so it was preferentially selected for equipment and lines
capacity. The calculations used to determine these values are presented in Appendix J. The
additional utility requirements for the 125% capacity redesign include increased cooling water
27
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
demands for heat exchangers and higher electricity usages for the pumps, air cooler, and
compressors. CNRL is currently purchasing about 70 MW from the Alberta power grid (16).
Therefore, the additional electricity requirements for the 125% capacity redesign were assumed to
Cooling water will be recycled and reused throughout the operation to minimize water intake.
Any additional water utility required is sourced from the Athabasca River (28). Since the duty of
the Stripper Reboiler (E-82) is the same as the base case, no additional steam was required.
Additional makeup amine was required due to the increase in the amount of amine circulating. The
makeup amine in the base case was 0.00006% of the total flow rate, which was the same percentage
execution strategy. The Direct Field Labour (DFL) hours calculated using the equipment purchase
costs and the average hourly rates for labour were used to plan an appropriate design to
commissioning timeline. The project execution strategy is composed of four distinct stages, which
are engineering, procurement planning, construction, and commissioning. The detailed timeline
for this project is outlined in Figure 4, with critical path items indicated in red. The project is
estimated to take 23 months from the start of engineering to the full operation of the facility.
28
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Engineering Plan
The engineering timeline of this project is composed of three phases. The first phase is the
Basis of Design (BOD), which is the development of the project scope, design basis memorandum,
block flow diagram, and completion of research for technological evaluation. The second phase is
Front End Engineering Design (FEED), which requires the completion of the process simulation,
PFD, P&ID, plot plan, preliminary sizing and economics, and preliminary safety and risk analyses.
The BOD and FEED phases taken together make up the basic engineering design, which is 3
months of the total engineering timeline. Upon completion of the BOD and FEED phases, the
design proposal is submitted to the client for review. Once approved, the third phase begins, which
is detailed engineering. Based on the current project timeline, detailed engineering design would
commence in April 2020. This phase involves the work of various engineering disciplines,
including process drawings, structural and mechanical designs for all major pieces of equipment,
detailed piping designs, electrical instrumentation and control designs, and Hazard and Operability
Studies (HAZOPs). The estimated duration for the detailed engineering phase is 4 months.
Procurement Plan
The procurement plan will commence upon the completion of the engineering plan which
occurs in August 2020. The procurement plan outlines procedures for vendor selection, equipment
ordering and fabrication, equipment transportation and logistics, and labour acquisition. Vendor
selection and quote acquisition is selected carefully based on the project being primarily cost
driven as opposed to schedule driven. To maximize the economics of this project, a competitive
bidding process will be conducted for each piece of equipment that is ordered. To minimize the
project execution time, the procurement phase overlaps with the engineering phase and bidding
begins while the detailed engineering phase is still in process. The total duration of the procurement
30
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
plan is estimated to be 8 months from the onset of the bidding process to the onsite delivery of the
Construction Plan
This phase involves the installation of equipment, piping, instrumentation, and electrical
components along with initial equipment testing and inspection. The equipment installations and
modifications required must be done while the CO2 Recovery Plant is in shutdown. Construction
work is thus scheduled during the annual sitewide Horizon Oil Sands outage that occurs in
September. A significant amount of field work is completed during this time. Proper planning and
coordination of the CO2 Removal Unit work scope with other site work is thus expected to take 3
months. Construction planning is scheduled to begin on March 25, 2021 with construction work
beginning on September 7, 2021. The replacement of packing in the columns is estimated to take
the longest amount of time due to the welding and post weld heat treatment required for the support
rings. Installation of the heat exchangers and drums is expected to take less time as they are
Commissioning Plan
Upon the completion of the construction phase of the project, the commissioning of the
facility will commence on October 2021. This final stage of the project timeline involves the final
equipment testing and monitoring such that it meets all applicable safety and environmental
regulations. Production testing and troubleshooting is done onstream after start-up of the unit. This
phase is expected to be 4 months in duration, and the project is scheduled to close by December
2021.
31
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
construction phases. Detailed calculations made to obtain the capital expenditure and manpower
profiles for the project management schedule are presented in Appendix K. As shown in Section
7.7.2, the engineering expense of the project is 18% of the total module cost plus contingency,
prorated based on the estimated fixed capital expenditure. The calculated DFL hours for this
project is approximately 86,000 hours based on the DFL cost of C$5.43 MM at a base labour rate
of $36 per hour. Using the relationship presented in K.M. Guthrie (1974), this number of DFL
hours gives an onsite construction duration of approximately 12 months when taking into account
the winter location factor and the limited construction work being done during that time (29).
Figure 5 displays the manpower distribution for labour and engineering throughout the project
timeline.
32
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
The economic feasibility of the 125% capacity redesign was largely determined based on
the net present value (NPV) and internal rate of return (IRR). A discounted cash flow analysis was
also used to determine the economic feasibility of the project. The economic analysis outlined in
this report is a Class 4 preliminary cost estimation as defined by the Association for the
Advancement of Cost Estimating (AACE) with an accuracy of -30% to +50% (30). Detailed
calculations, tables, and assumptions for the project economics can be found in Appendix J. The
economic analysis for this project is based on the difference in the amount of CO2 recovered
compared to the base case. It is assumed that all additional CO2 recovered can be sold. The goal is
to have the increased revenue from the additional CO2 recovered pay off the initial investment and
additional operating costs for the 20-year project lifetime. CNRL uses 50% of the current CO2
produced for their Non-Segregating Tailings process (31). This value was assumed to be static
across the capacity redesigns based on client input and was thus not factored into the revenue
calculations. Additionally, the infrastructure used to export the CO2 by truck is assumed to already
be in place. Unless otherwise specified, all prices are expressed in Canadian dollars.
All equipment was costed using the equipment based costing method outlined in Ulrich &
Vasudevan except for the IMTP random packing for the CO2 Absorber (C-80) and LP Flash
Stripper (C-82) (32). The packing was costed based on quotes provided by Koch-Glitsch. Figure
6 displays the breakdown of the total fixed capital expenditure of $13.42 MM. The breakdown of
the equipment purchase cost and the detailed calculations used to estimate the capital costs for this
project are included in Appendix J. Guidelines from the Electric Power Research Institute (EPRI)
33
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
were referred to when determining the contingencies for the project (33). The process contingency
was 0% because the process is already in commercial use and well studied, as it is an existing plant.
The proposed 125% capacity redesign is considered to be at the preliminary stage. Thus, the project
contingency used was 40%. A 7% contractor fee, 18% engineering and procurement cost, 3%
owner’s cost, and 4% commissioning and start-up cost were also applied to obtain the total fixed
capital cost of the project (33). An exchange rate of 1.33 was used to convert from USD to CAD
(34). The target Chemical Engineering Plant Cost Index (CEPCI) from November 2018 was 616.4,
each DFL factor used. A factor of 1.25 was applied to the US Gulf Coast estimates to account for
the Alberta location. Since the project site is located in Fort McMurray, an additional Fort
McMurray adjustment factor of 1.25 was applied. A winter work factor of 1.30 was applied to
34
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
account for reduced productivity from November 31 to March 1 (36). Limited work will be done
during the winter based on the project schedule, so the percent applicability was limited to 5%.
Modular installation of equipment, such as heat exchangers and drums, is faster than onsite
fabrication. Shop fabrication can also produce higher quality fabrication through the use of
specialized machining equipment that cannot be brought to site. The heat exchangers and drums
required for the 125% capacity redesign will be delivered to site in pre-assembled modules to allow
for efficient installation during the outage period. This method is also economically beneficial as
the labour force required onsite is reduced. Installation of the packing support rings in the CO2
Absorber (C-80) cannot be done in the shop. The support trays will have to be shipped in and then
welded into the column onsite during the outage, requiring some degree of field fabrication.
materials and spare parts inventory required to keep the facility in operation. The recommended
range for working capital expenditure was 10 to 20% of the fixed capital expenditure (32). Since
the CO2 Removal Unit is relatively small and the 125% capacity redesign does not add a significant
number of equipment, the working capital is chosen to be 10% of the total fixed capital, which in
this case is $1.34 MM. The loss in amine solution due to operation is also minimal, which also
Operating Cost
Appendix J includes the detailed calculations, assumptions, and tables made to estimate the
operating expenditure for the 125% capacity increase. The prices of utilities used to calculate the
35
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
operating cost were provided by the client and are shown in Table 13. Figure 7 presents the
operating cost breakdown in the form of a pie chart. Percentages from Ulrich & Vasudevan were
adjusted based on the project circumstances to calculate the direct, indirect, and general expenses
(32). The increase in annual operating cost for the 125% capacity redesign compared to the base
The sources of revenue for this project are the sale of CO2 production to other facilities and
the cost savings generated from having to purchase fewer GHG emissions credits. The market
demand for CO2 in the Fort McMurray region is from other oil and gas facilities who use CO2 for
EOR or CCS initiatives. The sale price of CO2 has historically been between $12 and $35 /tCO2
36
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
(18). Based on this range, the price of CO2 used to calculate revenue was chosen to be $23 /tCO2.
GHG emissions credits are currently priced at $30/tCO2e, which was the value used to determine
Financing Plan
Since this project is sponsored by CNRL, financing costs are not included as part of the
capital budget. CNRL is a large company with a steady cash flow profile and is assumed to have
sufficient capital to fund the project using their own resources. There would be no need for loans
from banks or private companies. Therefore, an investment schedule was not developed for this
project.
calculations and cash flow tables are presented in Appendix J. A corporate discount rate of 15%,
hurdle rate of 20%, inflation rate of 3%, and provincial income tax rate of 27% were used. The
Capital Cost Allowance (CCA) was 15% for the first operating year and 30% for every subsequent
year based on process plants which fall under Asset Class 43 (37).
37
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Sensitivity Analysis
The sensitivity analysis was conducted to determine which factors have the greatest impact
on the project’s economic feasibility. Figure 9 and Figure 10 illustrate the sensitivity analysis
results with respect to NPV and IRR, respectively. Fixed capital, operating cost, and utility unit
prices were varied by 10% to investigate their effects on the NPV and IRR. Since the onstream
factor cannot be greater than 1.0, a variation of 5% from the assumed 0.92 value was used. The
sale price of CO2 and cost of GHG emissions credits were also varied. The historical range for the
sale price of CO2 was $12 to $35 CAD /tCO2, so these boundaries were taken as the lower and
upper limits of the variable (18). To account for the possibility of GHG emissions credits rising
from $30 /tCO2e to $50 /tCO2e due to the federal climate plan, $50 /tCO2e was taken as the upper
limit. At a price of $12 /tCO2, an IRR could not be obtained due to divergence. The figures show
that the variation in onstream factor and utility prices are shown to have little effect on both the
project NPV and IRR. The most influential parameters are the price of GHG emissions credits and
38
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Economic Conclusions
The 125% capacity redesign is not economically feasible. The increase in revenue is not
enough to offset the initial fixed and working investments of $13.42 MM and $1.34 MM,
respectively. This ultimately results in a negative NPV of -$10.69 MM and negative IRR of -0.36%.
Assuming the GHG emission credit price remains at $30 /tCO2e, a CO2 sale price of C$49 /tCO2
would be needed to achieve economic feasibility at a hurdle rate of 20%. Considering that the unit
is producing commercial grade CO2 and that this price is outside of the historical range, this price
is highly unlikely to occur in the near future (18). However, it may be worthwhile to re-evaluate
this option if the carbon tax or CO2 market selling price changes substantially under different
regulatory scenario.
vapours from equipment due to irregular venting or unintended release such as leaks. These
39
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
fugitive emissions are small in comparison to leakage emissions from mine faces, tailings ponds,
and other facilities onsite. No additional reporting requirements are necessary under the Specified
Gas Reporting Regulation under the Climate Change and Emissions Management Act (38; 39).
CNRL participates in local and regional monitoring programs to ensure a high standard of
air quality for its stakeholders (40). CNRL is an active participant in the Wood Buffalo
NOX, SOX, volatile organic compounds, and particulate matter (41). There is no expected increase
in these parameters as a direct result of this project. Consequently, no changes to existing and
approved air quality under the Alberta Ambient Air Quality Objectives and Guidelines is expected
(42).
Increasing the capacity of the CO2 Removal Unit would reduce the overall GHG emissions
in the upgrader facility, which is a key environmental metric for this project. The 125% redesign
case captures 95,453 tCO2e/yr more than the “do nothing” alternative, which is equivalent to
removing approximately 20,750 passenger vehicles from the road (43). The increased CO2
recovery would help slow the rate at which global warming is occurring, slowing the increase in
global mean temperatures. It would also contribute to CNRL’s goal of reducing their emissions
intensity to below the global crude average (13). Further studies would be required to determine
the overall net GHG emissions reduction that is achieved when taking into account other units
affected by the feed flow rate increase, such as the PSA unit and downstream dehydration unit.
Supporting the increased utilities requirements may also affect the net GHG emissions reduction.
The increased CO2 recovery would also have large implications in terms of the cost of the
carbon levy imposed on GHG emissions by the Climate Leadership Regulation under the Climate
40
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Leadership Act, and enforced by the Carbon Competitiveness Incentive Regulation under the
The Water Act Licence No. 00186921-01-00 for CNRL enforces a maximum diversion rate
of 66.1 MMm3/yr of water from surface water sources, which is equivalent to drawing 3.1 m3/s of
water from the Athabasca River (46). The 125% redesign case would increase the cooling water
requirements of the CO2 Removal Unit by 0.101 m3/s. This marginal increase is not likely to be an
issue. However, limited information was provided regarding the current water draw from surface
water sources. Further study would be required to assess the impact of the additional cooling water
Environmental Conclusions
The proposed project will meet or exceed all applicable environmental regulations and will
recover 95,452 tCO2e/yr more than the “do nothing” case. The project will demonstrate a strong
sustainability of the oil sands industry. Furthermore, the project would contribute to CNRL’s long-
term goal of reducing emissions intensity, which is a significant environmental driver for this
project. Additional studies would be needed to determine the net impact on Horizon Oil Sands’
overall GHG emissions, taking into account the other units at the facility which are outside of this
project scope.
safety, environmental, legal, financial, and social consequences. Risk management methodologies
were conducted according to the “Guideline for Management of Risk in Professional Practice”
41
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
(47). For this project, several different hazard identification methods and risk assessment tools
were utilized, including: a What If? Process Hazard Analysis (PHA), a HAZOP, and analysis of
the DOW Fire and Explosion Index (F&EI) and Chemical Exposure Index (CEI). The complete
identify the potential hazards and safety risks for all process equipment and streams. Primary
process hazards identified from the checklist PFD based analysis included overpressurization of
equipment resulting in leakage or rupture, increased erosion in piping due to higher flow velocities
in the capacity redesign cases, and loss of containment of syngas with the potential for fire or
explosion.
CO2 Removal Unit. The PFD was divided into four nodes based on commodity streams. The
hazards identified using the checklist PFD based analysis were used to guide the formulation of
several What If? questions, which described different hazardous scenarios that could occur within
each node. The causes and consequences of these hazards were quantitatively evaluated using the
CNRL corporate risk matrix. An initial risk rating was assigned to each hazardous scenario
assuming no safeguards or controls were in place. This was then re-evaluated based on the
engineering safeguards and administrative controls assumed to be in place at Horizon Oil Sands.
After the safeguards and controls were accounted for, recommendations for further risk reduction
were developed for hazards that had unacceptable or conditionally tolerable levels of residual risk.
The full What If? analysis and PHA worksheets can be found in Appendix L.
42
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
analyze the risks introduced by the new piece of equipment. The complete HAZOP analysis as
well as the full list of recommendations and implications can be found in Appendix L. Process
deviations that could occur due to unexpected operating conditions were evaluated for four
operating states, including commissioning, steady state, start-up, and shutdown. The causes,
consequences, and risk rating evaluation were then completed using the method described in
Section 7.9.2.
Engineering safeguards were incorporated into the design of the Lean Amine Cooler to keep
residual risks at an as low as reasonably practicable (ALARP) level. The safety and control
mechanisms designed for the Lean Amine Cooler are shown in the P&ID in Appendix E. Two
pressure relief devices were designed according to the American Petroleum Institute Standards
520 and 521, and methods outlined in GPSA. The set pressure of the pressure safety valve (PSV)
located on the cooling water return line is 1354 kPa(g) and was designed to protect against
overpressurization caused by the vaporization of cooling water during blockage. The set pressure
on the pressure relief valve (PRV) located on the lean amine inlet is 6044 kPa(g) and was designed
for thermal relief in the event that the lean amine temperature rises and results in thermal expansion
of the fluid. Detailed PSV and PRV sizing calculations can be found in Appendix M. Two double
block and bleed valves located on the outlet streams and four block valves located on all four
corners ensure that the exchanger can be properly isolated and depressurized for maintenance or
cleaning. A vent and drain were placed on the high and low points of the exchanger to allow the
43
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Other safeguards identified for the Lean Amine Cooler included the verification of the
correct valve failure response positions, proper material selection, and use of a comprehensive and
frequent inspection, cleaning, and equipment maintenance program. Other recommendations from
the HAZOP analysis included evaluation of the identified high velocity lines, and updating of the
existing operating, start-up, and shutdown procedures to include the modifications listed in the
125% capacity redesign. Additionally, the CO2 loading factor for the 125% capacity redesign is
0.71 mol CO2/mol amine, which is 0.06 higher than the recommended maximum loading factor of
0.65 mol CO2/mol amine. This should be evaluated for any potential impacts on equipment
reliability or performance.
monoxide and is known to be flammable and toxic at ambient conditions. In a process breach
scenario, this could potentially be released into the atmosphere, posing a severe risk to the health
and safety of nearby personnel. A Dow CEI was calculated around stream 26, which had the
highest temperature, pressure, and concentration of carbon monoxide. All relevant calculations
can be found in Appendix L. It was found that a rupture in this stream would result in the largest
airborne release of gas. ERPG-1 is not included in the analysis since it is an odorless gas. Table
14 shows the CEI and the hazard distances for ERPG-2 and ERPG-3 for the base case compared
to the 125% design case. Figure 11 shows the exposure radii to scale.
44
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Figure 11: Chemical Exposure Radii by ERPG Level Overlaid on Satellite Imagery for the 125%
Case
hazard radius. As shown in Figure 11, the radius is limited to the eastern quadrant of the Horizon
Oil Sands plant. However, the outer radius of both ERPG-2 and ERPG-3 breach the administrative
building where most of the personnel would be located. The radius of ERPG-2 does not extend
beyond the site so there are no immediate risks to communities nearby the site, but communities
and counties nearby should be notified so that encroachment does not occur.
The exposure radii are based on the assumption of a five-minute continuous release.
Considering that the area of operation is located outdoors, the carbon monoxide would most likely
45
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
dissipate into the atmosphere as soon as a breach in the equipment occurs. Therefore, the identified
(C-87), and HP Lean Amine Flash Drum (C-81) for the base case and 125% capacity redesign.
Table 15 below shows the summary of the F&EI, exposure radius, capital loss, and business
interruptions for the three pieces of equipment for each case. Detailed calculations for the F&EI
can be found in Appendix L. The CO2 Absorber and Absorber Overhead K.O. Drum had the
highest pressure and concentration of synthesis gas, resulting in the largest exposure radius for
equipment containing synthesis gas. The HP Lean Amine Flash Drum had the highest pressure and
concentration of lean amine out of the process, resulting in the largest exposure radius for
None of the equipment in the 125% capacity redesign is classified as dangerous according
to the Dow F&EI, as none of the index values exceeded 128. The placement of the Lean Amine
Cooler (E-85A/B) was thus more dependent on access considerations rather than the exposure
radius, as the safety risk due to poor access was higher than that identified by the DOW F&EI.
Table 15. Fire and Explosion Index Summary Table for the 125% Redesign Case
Base Case 125% Design Case
Equipment Number C-80 C-81 C-87 C-80 C-81 C-87
Fire & Explosion Index 72.03 42.88 71.86 76.17 42.95 75.79
Radius of Exposure (m) 18.49 11.01 18.04 19.55 11.02 19.45
Maximum Probable Property Damage
0.99 0.69 1.40 1.09 0.69 1.52
(MM CAD)
Maximum Probable Days Outage 20 15 25 21 15 30
Business Interruption (MM CAD) 0.41 0.31 0.52 5.28 0.38 0.75
46
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
and plumbing systems are bound by the Alberta Safety Codes Act and must adhere to applicable
codes and regulations under the act including the CSA C22.1-18 Canadian Electrical Code,
National Plumbing Code of Canada 2015, Fire Code and Pressure Equipment Safety Regulation
(48; 49; 50; 51; 52). Additionally, all employers, workers, suppliers, contractors, and other project
personnel must conduct their business according to the Alberta Occupational Health and Safety
(OHS) Act, OHS Regulation, and OHS Code, as well as the Oil and Gas Occupational Safety and
Health Regulations under the Canada Labour Code (53; 54; 55; 56; 57). These regulations affect
the construction, testing, installation, operation, repair, and maintenance of equipment, and must
be followed to ensure that the facility operates in a safe and legal manner. A full list of applicable
Okane Engineering to identify proper safeguards for minimizing project risks to an ALARP level.
Compliance with the identified safety regulations and code requirements ensures that the project
will operate in a safe manner with proper risk management throughout the facility’s lifetime.
course of action (58). The net social benefit for the 125% redesign case was evaluated based on
several factors, including the potential contributions to the local and regional economy, noise,
traditional land and resource use, and effect on human health. A full list of considered factors and
47
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Increasing the capacity of the CO2 removal unit to 125% capacity would reduce overall GHG
emissions of the Horizon Oil Sands facility by 95,452 tCO2e/yr more than the base case. There is
also the potential to reduce the carbon footprint of other oil sands facilities, by selling the additional
CO2 recovered to other facilities around the Fort McMurray area to be used for EOR, tailings
management, or other CCS methods. The 125% capacity redesign would also generate a corporate
income tax revenue for the provincial government of C$3.12 MM over the project lifetime. During
the design and construction phases, the 125% redesign case would also see business and
There are minimal negative impacts to society identified for the 125% redesign case. There
would be marginally increased noise around the CO2 Removal Unit due to pump motors operating
at higher speeds and temporary increases in noise due to construction activities during project
execution. Increased traffic during construction may also have a slight impact on the air quality in
the region due to dust and increased diesel and gasoline consumption. CNRL’s established
transportation policy would help to minimize the effects of traffic on nearby residents.
Horizon Oil Sands is relatively isolated from other residents, which minimizes the project risks
to society. Numerous safeguards are in place to ensure that the 125% redesign case is properly risk
managed. Overall, implementation of the 125% redesign case would have a positive net social
benefit.
operating pressures and temperatures. The aMDEA flow rates are also adjusted to improve the
48
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
At increased syngas feed rates, the CO2 recovery efficiency decreases primarily due to limits
in the CO2 absorption rates in the CO2 Absorber (C-80). Desorption rates in the LP Flash Stripper
(C-82) also limit CO2 recovery efficiency but are secondary to the CO2 Absorber. Thus, minor
increases in capacity are achieved by optimizing CO2 absorption rates in the CO2 Absorber (C-80)
through temperature, pressure, and flow rate modifications. The changes in operating setpoints
needed to achieve 112% operating capacity are shown by stream in Table 16. In the 112% capacity
redesign, the amount of CO2 product produced is 1278 kmol/h, which is a 7.7% increase from the
base case CO2 output of 1187 kmol/h. A PFD of the 112% capacity redesign is shown in Figure 2
Table 16: Temperature, Pressure, and Flow Rate Changes for the 112% Capacity Redesign
Stream Description Base Case 112% Case
25 SG to CO2 Absorber Flow Rate 8214 kmol/h 9148 kmol/h
27 SG from CO2 Absorber OH Cooler Temperature 40.0 °C 39.8 °C
36 CO2 to Reflux Vessel Temperature 45.0 °C 44.4 °C
86 Lean Amine from Air Cooler aMDEA Flow Rate 2018 kmol/h 2106 kmol/h
86 Lean Amine from Air Cooler Temperature 45.0 °C 41.5 °C
95 Process Condensate to LP Flash Stripper Flow Rate 142 kmol/h 148 kmol/h
- CO2 Absorber Bottom Operating Pressure 3285 kPa(g) 3300 kPa(g)
CO2 Absorption
The bottom operating pressure, aMDEA flow rate, and lean amine stream temperature for
the CO2 Absorber (C-80) are modified to improve CO2 absorption rates, as explained in Section
7.1.1. This maintains a CO2 concentration in the outlet syngas fed to the PSA at an acceptable level
CO2 Desorption
Effective desorption of CO2 from the rich amine solution is achieved at 112% capacity
without modifications to the operating pressures of the LP Flash Stripper (C-82). The additional
49
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
process condensate recycled to the LP Flash Stripper is needed to effectively wash the exiting gas
Design Considerations
The increase in capacity of the CO2 Recovery Unit is limited to 112% due to the design
limits of the CO2 Absorber (C-80) and Lean Amine Air Cooler (E-84). The CO2 loading factor
used was 0.66 mol CO2/mol amine which was 1.3% higher than the recommended value of 0.65
mol CO2/mol amine. While this is unlikely to cause corrosion issues due to the lower operating
temperatures used, it should still be taken note of in the unit’s Corrosion Control Document.
be done. The existing integrated heat exchanger system was thus optimized as mentioned in
Section 7.2 by maximizing the area of the Lean/Rich Amine Exchanger (E-81A/B).
and Table 18. Detailed balances are presented in Appendix G. The envelope used for all material
and energy balances is the box shown in Figure 1. The material and energy balances close with
negligible percent differences, indicating that both mass and energy were conserved.
50
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
96 - 21.0
Water Header
Amine Blowdown Amine Blowdown - 0.0
Water Blowdown Water Blowdown - 0.0
37C Stage 1 Compressor K.O. Vessel - 72.7
37G Stage 2 Compressor K.O. Vessel - 20.8
Total (kmol/h) 9270.0 9270.0
Percent Difference 0.0%
51
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
96 - -1,659
Water Header
Amine Blowdown Amine Blowdown - 0
Water Blowdown Water Blowdown - 0
37C Stage 1 Compressor K.O. Vessel - -5,748
37G Stage 2 Compressor K.O. Vessel - -1,649
E-80 CO2 Absorber Overhead Cooler - 1,267
E-82 Stripper Reboiler 31,600 -
EQUIPMENT
additions were made. The equipment required for this case is the existing equipment already on
site. Design and operating data for the equipment was provided by the client and can be found in
Appendix H.
52
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
112% capacity. Detailed calculations done to determine these values are presented in Appendix J.
As described in the 125% redesign case, additional utility requirements included cooling water,
electricity, and makeup amine. The duty of the stripper reboiler also did not change from the base
case, resulting in no change in the LP steam requirement. The additional amine was estimated
required due to the absence of equipment additions or modifications. A project execution strategy
The methods and assumptions used for the economic analysis of the 112% redesign case are
the same as the ones used in the 125% redesign case and are outlined in Section 7.7.1. Unless
otherwise specified, all prices and costs are expressed in Canadian dollars.
53
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Since this option involves the optimization of existing operating conditions and does not
Operating Cost
Appendix J contains the calculations used to estimate the operating expenditure for the 112%
capacity redesign. Figure 12 presents the operating cost breakdown in the form of a pie chart. The
methods used to estimate operating cost are outlined in Section 7.7.4. Figure 12 shows that most
of the additional operating expenditure comes from the cooling water and electricity utility costs.
The total increase in annual operating expense was determined to be $0.67 MM.
Figure 12: Operating Cost Breakdown for the 112% Capacity Increase
The unit price data for the utilities provided by CNRL was used to determine the additional
utilities expenditure, as explained in Section 7.7.4. The results are shown in Table 20.
54
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
The sources of revenue for the 112% capacity redesign are the same as the ones listed in
Section 7.7.4 for the 125% capacity redesign. The increase in annual revenue determined for the
Figure 13 displays the cash flow diagram of the project for the 112% redesign case. Detailed
calculations and cash flow tables are presented in Appendix J. The method used for the cash flow
$10
Cumulative Discounted Cash
$9
$8
$7
Flow ($MM)
$6
$5
$4
$3
$2
$1
$0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Project Year
Figure 13: Discounted Cash Flow Profile for the 112% Case
55
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Sensitivity Analysis
The sensitivity analysis was conducted using the same method outlined in 7.7.6. Figure 14
illustrates the sensitivity analysis results with respect to NPV. Since a proper IRR could not be
obtained for the 112% case, a sensitivity analysis with respect to IRR was not performed. Figure
14 shows that the most influential parameters are the price of GHG emissions credits and sale price
of CO2. The market variation in the utility prices is shown to have little effect on the project NPV.
Economic Conclusions
The lack of capital expenditure and relatively low operating cost for the 112% capacity
increase results in a positive NPV of $6.64 MM. Based on the NPV analysis, the 112% capacity
environmental management conclusions for the 112% capacity redesign are the same as the 125%
case. The environmental metrics used to evaluate the proposed solution were also the same but
56
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
with slightly different values. The 112% capacity redesign for the CO2 Removal Unit would
capture 34,925 tCO2e/yr more than the “do nothing” alternative, which is equivalent to removing
approximately 7,600 passenger vehicles from the road (43). Although the emissions reduction in
the 112% capacity redesign would be smaller than the 125% case, implementation of the project
would still contribute to CNRL’s environmental management goals. The cooling water use for the
CO2 Removal Unit would also increase by 0.013 m3/s. This increase in cooling water usage is
negligible in relation to the total cooling water supply used at Horizon Oil Sands facility. Thus, it
was assumed that the existing water treatment systems would be able to handle the marginal
redesign case using similar methodology to the 125% case. No HAZOP was completed for the
112% capacity redesign due to a lack of time and resources for this project. However, the safety
and risk analysis for the 112% capacity redesign identified several recommendations, including
review of the existing PSVs and PRVs for potential re-ratings to accommodate the increased flow
rates, and confirmation of process lines sizing for the identified high velocity lines. Additionally,
the CO2 loading factor for the 112% capacity redesign is 0.66 mol CO2/mol amine, which is
slightly higher than the recommended maximum loading factor of 0.65 mol CO2/mol amine. This
should be evaluated for any potential impacts on equipment reliability or performance. The full
list recommendations identified for the 112% capacity redesign can be found in Appendix L.
57
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
calculations can be found in Appendix L. ERPG-1 is also not included in the analysis since it is
the same gas as the base and 125% design case. Table 21 shows the CEI and the hazard distances
for ERPG-2 and ERPG-3 for the 112% case compared to the base case. Figure 15 shows the
exposure radii to scale. As shown in the Figure 15, the radius of the 112% design case is similar
to the 125% design case. Thus, the risks identified as the same as those listed in 7.9.4 but on a
58
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
ERPG-2 (1741 m)
ERPG-3 (1458 m)
Figure 15: Chemical Exposure Radii by ERPG Level Overlaid on Satellite Imagery for the 112%
Case
Overhead K.O. Drum (C-87), and the HP Lean Amine Flash Drum (C-81) for the 112% redesign
case. Table 22 shows the summary of the F&EI, exposure radius, capital loss, and business
interruptions for the three pieces of equipment in the 112% redesign case compared to the base
59
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Table 22: Fire and Explosion Index Summary Table for the 112% Redesign Case
Base Case 112% Design Case
Equipment number C-80 C-81 C-87 C-80 C-81 C-87
Fire & Explosion Index 72.03 42.88 71.86 74.05 42.91 73.72
Radius of Exposure (m) 18.49 11.01 18.04 19.01 11.01 18.92
Maximum Probable Property Damage
0.99 0.69 1.40 1.01 0.69 1.42
($MM CAD)
Maximum Probable Days Outage 20 15 25 21 15 25
Business Interruption ($MM CAD) 0.41 0.31 0.52 0.47 0.34 0.56
not already identified for the 125% redesign case. After applying the assumed engineering
safeguards and administrative controls, all risks for the 112% case were determined to be at an
ALARP level.
including contribution towards the local and regional economy, noise, traditional land and resource
use, and affect on human health. Increasing the capacity of the CO2 Removal Unit by 12% would
reduce the overall GHG emissions of the Horizon Oil Sands facility by 34,925 tCO2e/yr over the
“do nothing” case. This would also contribute to CNRL’s GHG emissions reduction strategy and
benefit other oil sands facilities in the Fort McMurray area, albeit to a lower magnitude than the
125% redesign. The Provincial tax revenue for the 125% capacity redesign was C$8.90 MM,
which was much higher than the 125% case due to there being no CCA applicable to this solution.
The 112% capacity design does not provide business opportunities for qualified local or
regional contractors due to the lack of construction activities. However, concerns regarding traffic,
60
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
dust, and noise around the facility during project implementation are consequently minimized.
Overall, the 112% redesign was determined to have a positive net social benefit.
risks resulting from rising carbon taxes costs. Okane Engineering was requested by CNRL to
redesign the existing CO2 Recovery Plant to increase the operating capacity by 15% and 25%. A
12% capacity increase was pursued instead of 15% after consultation with the client. The 12%
increase in capacity was achieved within the design limits of the existing equipment through
optimization of operating conditions. The 25% increase in capacity was achieved through the
addition of new equipment and modification and replacement of some existing equipment. The
design changes needed to achieve operating capacities of 112% and 125% in the CO2 Removal
61
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Preliminary economic analyses of the 112% and 125% redesign cases were completed to
assess economic feasibility. The 125% redesign case was found to be economically unfeasible,
with an NPV of -C$10.69 MM. It was calculated that a selling price of C$49 /tCO2 would be
required for the 125% redesign case to be financially viable at the current carbon tax of C$30
/tCO2e. The 112% redesign case was found to be economically feasible with an NPV of C$6.64
MM. The additional operating costs were found to be C$0.67 MM per year with an annual revenue
of C$1.86 MM.
An environmental assessment was performed for the proposed project. It was found that both
the 112% and 125% redesign cases would meet or exceed all applicable environmental regulations.
The 112% and 125% capacity redesigns would recover approximately 35,000 and 95,000 tCO2e/yr
more than the current process, respectively. Both redesigns would also contribute to CNRL’s goal
of reducing emissions intensity to below the global crude average and strengthen the company’s
The completion of multiple hazard identifications and risk assessment methodologies, such
as a process hazard checklist, What If? analysis, HAZOP, and DOW indices were used to identify
safeguards to minimize project risks to an ALARP level. Overall, both redesigns would have an
overall positive net social benefit and be environmentally and socially sustainable.
Based on the design evaluations conducted, Okane Engineering advises CNRL to not pursue
the 125% redesign case which was determined to be economically unfeasible. The 112% design
case is economically feasible and should be pursued further. Further evaluation of potential
corrosion issues, piping velocity limitations, and effects of high CO2 loading is still required. It is
also strongly recommended to complete field testing to verify the CO2 recovery efficiencies stated
in the 112% capacity redesign. Upon completion of these recommendations, project execution of
62
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
the 112% redesign case would be the best course of action, as it would increase the profitability of
63
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
10. References
1. Canadian Natural Resources Ltd. The Horizon Oil Sands. Canadian Natural. [Online]
[Cited: January 1, 2019.]
https://cnrl.hgcareers.com/en/media/cnrl/The%20Oil%20Sands%20Process.pdf.
2. —. Managing Tailings. [Online] [Cited: January 20, 2019.] https://www.cnrl.com/corporate-
responsibility/advancements-in-technology/managing-tailings.html.
3. Environment and Climate Change Canada. Pan-Canadian Framework on Clean Growth
and Climate Change. [Online] 2016.
https://www.canada.ca/content/dam/themes/environment/documents/weather1/20170125-
en.pdf.
4. Government of Alberta. Carbon Competitiveness Incentive Regulation Fact Sheet. [Online]
April 2018. [Cited: January 20, 2019.] https://www.alberta.ca/assets/documents/cci-fact-
sheet.pdf.
5. —. Carbon Competitiveness Incentive Regulation. [Online] November 20, 2018. [Cited:
January 20, 2019.]
http://www.qp.alberta.ca/1266.cfm?page=2017_255.cfm&leg_type=Regs&isbncln=9780779
800193.
6. —. Output Based Allocation Engagement. [Online] [Cited: January 25, 2019.]
https://www.alberta.ca/output-based-allocation-engagement.aspx.
7. Alberta Environment and Parks. Climate Change and Emissions Management Fund Credit
Amount Order. [Online] December 21, 2017. [Cited: January 25, 2019.]
https://www.alberta.ca/assets/documents/CCEMA-fund-credit-ministerial-order.PDF.
8. Canada's Oil Sands. GHG Emissions. [Online] https://www.canadasoilsands.ca/en/explore-
topics/ghg-emissions.
9. Government of Alberta. Climate Leadership Plan - Implementation Plan 2018-19. Open
Government Portal. [Online] June 2018. [Cited: January 17, 2019.]
https://open.alberta.ca/dataset/da6433da-69b7-4d15-9123-01f76004f574/resource/b42b1f43-
7b9d-483d-aa2a-6f9b4290d81e/download/clp_implementation_plan-jun07.pdf.
10. —. Oil Sands Emissions Limit Act. Alberta Queen's Printer. [Online] December 14, 2016.
[Cited: April 4, 2019.] http://www.qp.alberta.ca/documents/Acts/O07p5.pdf.
11. Barry Sacifrage. Oilsands pollution on collision course with Canada's climate plan.
Canada's National Observer. [Online] February 20, 2018. [Cited: April 4, 2019.]
https://www.nationalobserver.com/2018/02/20/opinion/oilsands-pollution-collision-course-
canadas-climate-plan.
12. Canadian Natural Resources Ltd. Corporate Statement on Environmental Management.
[Online] June 2018. [Cited: April 4, 2019.]
http://webadmin.cnrl.com/upload/media_element/445/07/2018-corporate-statement-on-
environmental-management_final.pdf.
64
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
65
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
29. Guthrie, Kenneth M. Process Plant Estimating Evaluation and Control. Solana Beach :
Craftsman Book Company of America, 1974.
30. International, AACE. Cost Estimate Classification System - As Applied in Engineering,
Procurements, and Construction for the Process Industries. AACE International
Recommended Practice No. 18R-97. s.l. : AACE® International, March 1, 2016.
31. Narayanasarma, Prabhu. P. Eng. Industry Advisor Meeting #1. Edmonton, January 31,
2019.
32. Ulrich, Gael D. and Vasudevan, Palligarnai T. Chemical Engineering Process Design and
Economics: A Practical Guide (Second Edition). Durham : Process (Ulrich) Publishing,
2004. 0-97087683-2-3.
33. Jamieson & Church. Contingency Estimating. Edmonton, AB, Canada : s.n., 2015.
34. Live Exchange Rates. OANDA Corporation. [Online] https://www.oanda.com/currency/live-
exchange-rates/USDCAD/.
35. Chemical Plant Cost Index. Chemical Engineering Essentials for the CPI Professional.
[Online] https://www.chemengonline.com/2019-cepci-updates-january-prelim-and-
december-2018-final/.
36. Jamieson & Church. Adjusting FBM. Edmonton, AB, Canada : s.n., 2015.
37. Common CCA Classes and Rates. Donnelly & Co. LLP. [Online]
http://donnellyco.ab.ca/cca-rates-and-classes.
38. Government of Alberta. Specified Gas Reporting Regulation. Alberta Queen's Printer.
[Online] November 20, 2018. [Cited: April 4, 2019.]
http://www.qp.alberta.ca/1266.cfm?page=2017_255.cfm&leg_type=Regs&isbncln=9780779
800193.
39. —. Climate Change and Emissions Management Act. Alberta Queen's Printer. [Online]
January 1, 2017. [Cited: April 4, 2019.]
http://www.qp.alberta.ca/documents/Acts/C16P7.pdf.
40. Canadian Natural Resources Ltd. Protecting Air Qualtiy. [Online] [Cited: April 5, 2019.]
https://www.cnrl.com/corporate-responsibility/environment/climate-change/air-quality.
41. Woof Buffalo Environmental Association. Horizon. Wood Buffalo Environmental
Association. [Online] March 6, 2019. [Cited: April 4, 2019.]
https://wbea.org/stations/horizon/.
42. Government of Alberta. Alberta Ambient Air Quality Objectives and Guidelines Summary.
Open Government Portal. [Online] January 2019. [Cited: April 4, 2019.]
https://open.alberta.ca/dataset/0d2ad470-117e-410f-ba4f-aa352cb02d4d/resource/4ddd8097-
6787-43f3-bb4a-908e20f5e8f1/download/aaqo-summary-jan2019.pdf.
43. United States Environmental Protection Agency. Greenhouse Gas Emissions from a Typical
Passenger Vehicle. [Online] March 2018. [Cited: April 6, 2019.]
https://www.epa.gov/greenvehicles/greenhouse-gas-emissions-typical-passenger-vehicle.
66
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
44. Province of Alberta. Climate Leadership Regulation. Alberta Queen's Printer. [Online]
November 20, 2018. [Cited: April 4, 2019.]
http://www.qp.alberta.ca/documents/Regs/2016_175.pdf.
45. Government of Alberta. Climate Leadership Act. Alberta Queen's Printer. [Online] June 7,
2017. [Cited: April 4, 2019.] http://www.qp.alberta.ca/documents/Acts/C16P9.pdf.
46. Alberta Energy Regulator, Alberta Environment and Parks. Authorization Viewer. [Online]
August 5, 2015. [Cited: April 4, 2019.]
https://avw.alberta.ca/ApprovalViewerResults.aspx?Click=Search&exapv_id=186921.
47. APEGA. Guideline for Management of Risk in Professional Practice. [Online] September
2006. [Cited: January 20, 2019.] https://www.apega.ca/assets/PDFs/risk.pdf.
48. Government of Alberta. Safety Codes Act. Alberta Queen's Printer. [Online] December 1,
2017. [Cited: April 4, 2019.] http://www.qp.alberta.ca/documents/Acts/S01.pdf.
49. —. Electrical codes and standards. [Online] 2019. [Cited: April 4, 2019.]
https://www.alberta.ca/electrical-codes-and-standards.aspx.
50. —. Fire codes and standards - Overview. [Online] May 1, 2015. [Cited: April 5, 2019.]
https://www.alberta.ca/fire-codes-and-standards-overview.aspx.
51. —. Plumbing codes and standards - Overview. [Online] 2019. [Cited: April 4, 2019.]
https://www.alberta.ca/plumbing-codes-and-standards-overview.aspx.
52. —. Pressure Equipment Safety Regulation. Alberta Queen's Printer. [Online] 2015. [Cited:
April 4, 2019.] http://www.qp.alberta.ca/documents/Regs/2006_049.pdf.
53. —. Occupational Health and Safety Act. Alberta Queen's Printer. [Online] June 11, 2018.
[Cited: April 4, 2019.] http://www.qp.alberta.ca/documents/Acts/O02P1.pdf.
54. —. Occupational Health and Safety Regulation. Alberta Queen's Printer. [Online] 2018.
[Cited: April 4, 2019.] http://www.qp.alberta.ca/documents/Regs/2003_062.pdf.
55. —. Occupational Health and Safety Code 2018 Explanation Guide. Alberta Queen's Printer.
[Online] January 2019. [Cited: April 4, 2019.]
http://www.qp.alberta.ca/documents/OHS/OHSCodeExplanationGuide.pdf.
56. Government of Canada. Oil and Gas Occupational Safety and Health Regulations. Justice
Laws Website. [Online] March 26, 2019. [Cited: April 4, 2019.] https://laws-
lois.justice.gc.ca/eng/regulations/sor-87-612/index.html.
57. —. Canada Labour Code. Justice Laws Website. [Online] March 12, 2019. [Cited: April 5,
2019.] https://laws-lois.justice.gc.ca/eng/acts/L-2/.
58. IGI Global. What is Net Social Benefit. IGI Global - Disseminator of Knowledge. [Online]
[Cited: April 7, 2019.] https://www.igi-global.com/dictionary/net-social-benefit/62132.
67
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
decision analysis procedure undertaken to evaluate them. The project musts and wants are defined.
Options are then assessed on their ability to meet the musts and rated on their ability to meet the
wants.
Table of Contents
1. Options Considered ............................................................................................................... A-1
1.1. Option A: Do Nothing ................................................................................................... A-1
1.2. Option B: Optimization of Operating Conditions with Existing Equipment ................ A-1
1.2.1. The Effects of Temperature, Pressure, and Flow Rate on CO2 Recovery............... A-2
1.3. Option C: Modification of Absorber and Stripper Column .......................................... A-3
1.4. Option D: Replacement of Plant with Gasification System .......................................... A-3
2. Decision Analysis Criteria .................................................................................................... A-5
3. Evaluation of Options ........................................................................................................... A-6
List of References ....................................................................................................................... A-7
i
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
1. Options Considered
1.1. Option A: Do Nothing
In the “Do Nothing” option, no equipment or operational changes would be made to the
CO2 Removal Unit, maintaining the plant’s current capacity and recovery. The operating
expenditure would increase due to higher energy inputs as a result of increased syngas feed
rates, but no capital expenditure would be required. Since the CO2 recovery would remain the
same, more CO2 would be released to atmosphere resulting in increased carbon tax costs. The
advantages of this option are that CNRL would save time, effort, and capital costs, as no
additional work is required due to the absence of redesign. The disadvantage is that doing
nothing would progressively cost CNRL more in the long-term due to higher carbon taxes,
particularly if carbon pricing increases in accordance with the federal climate plan.
conditions within the confines of the existing infrastructure, forcing the existing equipment to
operate at maximum capacity. This option modifies the operating temperatures, pressures, and
flowrates to support the increased feed flow rate and increase recovery of CO2 while balancing
energy input and utilities usage. The advantages of this option are that it reduces carbon tax
costs through reductions in GHG emissions and has a low capital expenditure, as the process
equipment is utilized as is. The disadvantage is that the existing design limits of equipment
would hinder the achievable increase in capacity and CO2 recovery. Unless the CO2 Removal
Unit was originally overdesigned, it is likely that the plant’s capacity will be limited by the
equipment’s original design before reaching 125%. A significant increase in the CO2 recovery
percentage is also unlikely, thus a higher feed rate would result in higher carbon tax costs.
A-1
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Changing operating conditions would require increased energy input and utilities usage adding
to operating costs as well. Determining the capacity and recovery limits of this option requires
further investigation.
1.2.1. The Effects of Temperature, Pressure, and Flow Rate on CO2 Recovery
Increasing operating temperature in an absorption column typically increases the rate of
mass transfer based on reaction kinetics; however, CO2 absorption is an exothermic process
(1). Too high of a temperature could hinder the absorption process due to shifts in the reaction
temperatures (1). Column temperatures can be manipulated by changing the duty of reboilers
or associated heat exchangers; however, more energy input is required and would result in a
When the partial pressure of CO2 is increased, an increase in CO2 absorption efficiency
of the column is observed. The high interfacial tension resulting from the increased partial
pressure causes an interfacial disturbance that improves mass transfer rate (1). Reducing the
overall system pressure or increasing the CO2 concentration of the inlet streams can increase
the partial pressure of CO2 in both the CO2 Absorber and Low Pressure (LP) Flash Stripper.
Assuming the composition of the syngas fed to the CO2 Absorber is fixed, reducing the
pressure of the column is more reasonable. However, decreasing the pressure will also
decrease the temperature which can negatively impact mass transfer (1).
The flow rate of absorbent used also influences the extent of mass transfer achieved.
Increasing flow rate increases the amount of packing surface covered with absorbent, which
consequently increases the effective area for mass transfer (1). For the CO2 Removal Unit, an
A-2
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
increase in flow rate of lean MDEA would thus increase the amount of CO2 absorbed. This
would also require a higher rate of regeneration of lean MDEA from rich MDEA, leading to
a higher operating cost due to increased utilities usage and potential capital expenditure costs
equipment modifications will be made to the CO2 Absorber, LP Flash Stripper, or both. The
key processes of the CO2 Removal Unit are CO2 absorption by lean MDEA and desorption of
CO2 from rich MDEA, which occurs in the CO2 Absorber and LP Flash Stripper respectively.
Increasing the capacity of either one would increase the plant’s capacity. These two processes
also largely control the CO2 recovery efficiency; therefore, improving efficiency in one or both
columns would increase CO2 recovery. This would be advantageous in avoiding increases in
carbon tax costs due to the additional CO2 introduced by higher feed flow rates. This option
offers the advantage of design flexibility, ensuring that the equipment is designed to achieve
the desired 115% and 125% capacity and product specifications as requested. The disadvantage
is that this option is capital expenditure intensive. The cost for modification or replacement of
columns is significantly higher than that of smaller equipment like exchangers. The higher
capacity columns will have increased energy input requirements, raising operating costs as
well.
North West Sturgeon Refinery (NWSR) currently utilizes, in place of the existing CO 2
A-3
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Recovery Plant. This system can produce a high purity CO2 product stream with higher feed
flow rates without the need for excess dehydration units (2). Lurgi’s Multi-Purpose Gasifier
(MPG®) with Rectisol® synthesis gas processing and conditioning technology is used at
NWSR. Rectisol® is a mature acid gas separation technology that has commercially
demonstrated the ability to safely and reliably process a variety of raw materials, from natural
gas to coal (3). This technology would produce hydrogen and CO2 using the following:
1. MPG® gasifier reactors that react feedstock with O2 in the presence of steam under high
pressure and temperature conditions
2. A quenching unit that cools superheated raw syngas via direct injection of water
3. A gas scrubber and ash recovery unit that removes ash and soot
4. A raw gas CO-shift conversion unit
5. A Rectisol® syngas processing unit that conditions and purifies H2, CO2, and H2S
The advantage of this option is that it can easily produce the specified 92 mol% purity of the
CO2 product stream for operations at 115% and 125% capacity with potential reductions in
energy input and utility usage due to less intensive product purification processes. The capital
involves replacement of the CO2 Recovery Plant in its entirety along with major
A-4
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
A-5
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
3. Evaluation of Options
Musts Option A Option B Option C Option D
Reduce emissions to better comply with ✗ ✓ ✓ ✓
regulations
Increase plant capacity by at least 15% ✗ ✓ ✓ ✓
Go / No Go No Go Go Go Go
Weight Option B Option C Option D
Wants
(%) (/10) (/10) (/10)
Minimize capital costs 30 10 2 0
Maximize reduction of GHG emissions 30 6 8 10
Minimize operating costs 25 6 6 4
Minimize construction time 15 10 6 2
Total (/10) 100 7.8 5.4 4.3
Note that the investigation of Option B resulted in optimization of operating conditions that could
support a 12% capacity increase rather than the 15% initially proposed. Upon consultation with
the client, a 112% capacity redesign was deemed to be acceptable in place of the 15% capacity
redesign, provided that the 112% capacity redesign was completed using only existing equipment.
This change modifies the required must for the design to be able to “increase plant capacity by at
least 12%”.
A-6
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
List of References
1. Tan, L.S., et al. Factors affecting CO2 absorption efficiency in packed column: A review.
2. Heal, Kevin and Kemp, Terry. North West Sturgeon Refinery Project Overview - Carbon
Capture Through Innovative Commercial Structuring in the Canadian Oil Sands. Calgary : s.n.,
2013.
3. Rectisol Wash Units: Acid Gas Removal for Polygeneration Concepts downstream Gasification.
A-7
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
made when simulating the project in BRE ProMax. Three separate modelling files were
constructed for the base case, 115 % capacity increase, and 125 % capacity increase.
Table of Contents
1. Thermodynamic Model Selection ........................................................................................... B-1
2. Amine Solution Modelling ..................................................................................................... B-2
3. Adiabatic ................................................................................................................................. B-2
4. Isobaric .................................................................................................................................... B-3
5. Equipment Efficiencies ........................................................................................................... B-3
6. Tray Weir Height .................................................................................................................... B-4
7. Use of Make-Up and Recycle Blocks ..................................................................................... B-4
8. Fictitious Heat Exchanger ....................................................................................................... B-5
9. Feed Stream Compositions ..................................................................................................... B-6
10. Utility Stream Compositions................................................................................................. B-7
List of References ....................................................................................................................... B-8
i
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
CO2 Recovery Plant. The CO2 Absorber will be modelled using the TSWEET Kinetics model
while the LP Flash Stripper will be modelled using the TSWEET Alternate Stripper.
Justification: Based on the ProMax help section written by Bryan Research & Engineering (BRE),
the property package recommended for amine sweetening processes is Amine Sweetening
Electrolytic ELR. This property package was also found to be relatively accurate in modelling CO2
capturing processes by Ahmadi (1). Using the Amine Sweetening Electrolytic ELR property
package, the modelled syngas feed stream entering the CO2 Absorber has a Cp value of 2992
J/kg/K, while the given material balance for the design basis lists a value of 3003 J/kg/K. Since
the modelled value only differs by 0.4% from the benchmark for design, the property package is
deemed suitable for simulating the process. The TSWEET Kinetics Model using Ideal Stages
modified by thermal efficiencies is used to model the CO2 Absorber, while the TSWEET
Absorber/Stripper Model is used to model the LP Flash Stripper. The TSWEET Kinetics Model is
used for the CO2 Absorber because it is able to model the absorption of CO2 more accurately than
the TSWEET Absorber/Stripper Model when compared to the design basis compositions. BRE
also recommends the TSWEET Kinetics model with Ideal Stages for amine absorbers and
TSWEET Alternate Stripper with Mass and Heat Transfer for amine regenerators. The simulation
results using the separation models were compared to the design basis for validation and compared
B-1
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Justification: Greater activator composition in the solution results in improved absorption but
increases the risk of corrosion. It is common for industries to use approximately 3 wt% piperazine
to assist in the extraction of CO2. At a 3 wt% piperazine concentration at the given amine solution
flow rates, 87.5% of the CO2 in the inlet Syngas stream can be recovered from the rich amine
stream in the CO2 Absorber. This is consistent with the material balance provided for the process,
verifying this assumption. This assumption was also reviewed and accepted by the Industry
Advisor. Thus, the aMDEA flow rates are modelled as 3 wt% piperazine and 97% MDEA in the
3. Adiabatic
Decision: The process will be simulated as being adiabatic; ignoring heat losses to the
environment.
Justification: Accurate consideration of heat losses in a system is difficult to achieve and requires
rigorous calculations with considerations of many factors, such as insultation thicknesses and heat
tracing. Due to the limitations of the information provided regarding the existing equipment and
piping designs, the process will be assumed to be adiabatic. The project is also a preliminary
assessment, qualifying as a Class 4 economic estimate by the Association for the Advancement of
Cost Estimating (AACE) standards. Thus, in order to complete the study of the proposed solutions
to the accuracy required for this project, the process is assumed to be adiabatic.
B-2
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
4. Isobaric
Decision: The differences in the inlet and outlet stream pressures compared to the given operating
pressures for equipment will be considered negligible where pressure drops are not specified.
Justification: The material balance for the design basis of the CO2 Recovery Plant was provided
as well as operating data for select pieces of equipment. In cases where a pressure drop is indicated
by inlet and outlet streams conditions, as listed in the design basis or operating data provided, the
stated pressure drop is accounted for and used in the simulation. Otherwise, if the operating
pressure, inlet pressure, and outlet pressures are shown to be equal across a piece of equipment,
the pressure drop is assumed to be negligible and specified as 0 kPa(g) in the simulation.
Realistically, pressure drop cannot be eliminated across any type of equipment. However, for the
purpose of reflecting what was given in the design basis, this was applied to the process.
5. Equipment Efficiencies
Decision: Pump efficiencies in the simulation will be calculated as 90% of the stated hydraulic
Justification: For centrifugal pumps, a typical efficiency range is 50 to 85% (Ulrich &
Vasudevan). Operating data was provided for existing pumps in the process, but only hydraulic
efficiency was provided. ProMax requires an overall efficiency, which is a function of the pump’s
volumetric and hydraulic efficiency. As a conservative estimate, the overall efficiency is assumed
to be 90% of the hydraulic efficiencies stated in the operating data summary provided by the
Industry Advisor. Regarding compressors, Ulrich & Vasudevan list the typical efficiencies of
B-3
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Justification: Weir height of the existing trays in the absorber and stripper were not provided. A
typical weir height of 2 inches is then assumed to allow for convergence in each of the columns.
CO2 Removal Unit’s existing make-up streams and equipment, which are not simulated in detail.
The make-up block will be used in the rich amine stream going to the LP Flash Stripper to close
the amine cycle. The recycle block will be used in the lean amine stream going to the CO 2
Absorber. A make-up block will also be used to account for discrepancies in the water balance.
Justification: Make-up blocks are required to supplement lost components in closed loops and
ensure that the material balances close. The make-up units in ProMax solve based on inlet and
make-up stream compositions and a desired outlet flow rate. In the existing plant, the make-up
stream enters the lean amine feed stream to the CO2 Absorber. Due to the interdependence of the
CO2 Absorber and LP Flash Stripper when modelling CO2 recovery, a recycle block is used in this
location instead. The recycle block allows for composition guesses to be made to begin iteration
of the simulation and are needed when simulating a closed loop. To model the CO2 absorption and
desorption as a single process block, the make-up block is used in the rich amine stream instead.
Likewise, a recycle block is used in order to solve the LP Flash Stripper water recycle loop. A
make-up block for water is then used in the lean amine stream to account for water loss in the LP
Flash Stripper which results due to error in the property package when simulating the separation
B-4
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
the LP Flash Stripper to account for static head pressure in the pumparound stream. Another
fictitious exchanger will be added in the overhead stream upstream of the CO2 Absorber Overhead
Cooler (E-80) to compensate for error in the simulation of the CO2 absorption process in the CO2
Absorber (C-80).
Justification: The pumparound piping off the LP Flash Stripper is vertical. This piping
configuration ensures that only the liquid portion of the pumparound draw is drawn into the
Semilean Amine Pump (G-81A/B). The phase separation and added static head of the liquid level
prevents vapor locking of the pump. Since, ProMax does not account for piping configuration, a
fictitious exchanger is added in the pumparound stream to model the pumparound stream as being
pure liquid. This allows the Semilean Amine Pump to solve, allowing the simulation model to
converge. In modelling the absorption of CO2 in the CO2 Absorber (C-80), the property package
used resulted in much higher heat generation from the absorption process than was identified in
the design basis. In order to compensate for this error, a fictitious exchanger was added in the
overhead stream to remove some duty. This allowed for the inlet stream temperature to the CO2
Absorber Overhead Cooler to be consistent with the design basis. This fixed amount of duty was
then carried over to the 112% and 125% design basis as a conservative estimate for the minimum
B-5
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Justification: Based on discussions with the Industry Advisor, the composition of the syngas did
not vary significantly at increased flow rates. The molar compositions were thus taken to be
B-6
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
operating data is not available, the conditions will be based on the typical utility conditions.
Justification: Due to confidentiality restrictions, not all operating data could be made available.
As a result, the following table of typical conditions for utilities was provided by the Industry
Advisor to use for assumed operating conditions where other data was available:
B-7
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
List of References
1. Ahmadi, F. Assessing the Performance of Aspen Plus and Promax for the Simulation of CO2
2. Ulrich, Gael D. and Vasudevan, Palligarnai T. Chemical Engineering Process Design and
Economics: A Practical Guide (Second Edition). Durham : Process (Ulrich) Publishing, 2004. 0-
97087683-2-3.
B-8
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
values to the outputs from the simulation. This will determine whether the output of the simulation
is within range of what is expected from the design basis and provided operating conditions,
Table of Contents
1. Stream Properties .................................................................................................................. C-1
1.1. Specific Heat Capacity .................................................................................................. C-1
1.2. Density........................................................................................................................... C-2
1.3. Viscosity ........................................................................................................................ C-2
2. Heat Exchanger Selection ..................................................................................................... C-2
3. CO2 Absorber Separation ...................................................................................................... C-5
4. Compression Stage................................................................................................................ C-8
List of References ..................................................................................................................... C-10
i
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
1. Stream Properties
1.1. Specific Heat Capacity
The selection of property package is detrimental to the accuracy of the simulation. The
specific heat capacity from the simulation is compared to the values given in the design basis,
as laid out below in kJ/kg/K, to confirm the validity of the simulation. All simulation streams
agree within 5% of the specific heat capacity values given in the design basis.
C-1
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
1.2. Density
Streams that were simulated by specifying molar flow rates were also assessed for
agreement with the design basis. The density of these streams in kg/m3 are tabulated below.
1.3. Viscosity
Viscosity of the specified streams in the simulation were also examined. Values from the
design basis and the simulation agreed within 12%. Although the percent difference appears to be
high, the discrepancy is attributed to differences in stream molecular weights due to property
package selection.
the Tubular Exchanger Manufacturers Association (TEMA) designations. In other words, this heat
exchanger is a shell and tube heat exchanger with a bonnet stationary head, one-pass shell, and
C-2
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
fixed tube sheet. It was assumed that there are two tube passes. From U&V (1) (Table 4.12, Pg
194) this type of heat exchanger has a maximum surface area per unit of 800 m2, a maximum
operating pressure of 200 bara on the shell side and 140 bara on the tube side, a maximum
operating temperature of 150 °C, and a minimum practical approach temperature of 5 °C. From
operating data provided, the actual heat exchanger surface area is 85.8 m2, the operating pressure
is 33.8 bara on the shell side and 6.0 bara on the tube side, the operating temperature is 45 °C, and
the approach temperature is 16 °C. Therefore, heat exchanger type selection is valid for this
service. The remaining heat exchangers were also deemed valid for their respective services.
To validate the simulation used to model the CO2 Removal Unit, the following assumptions
were made:
The overall heat transfer coefficients (U) were calculated from the design basis by
simulating each heat exchanger on ProMax and applied to the base case simulation to calculate
heat exchange areas. Comparison of heat exchange areas from the simulation and the actual areas
from the operating data provided by the client showed good agreement. Since phase change in the
condensers were minimal, a constant U value was assumed. A mean temperature difference was
used for the reboiler instead of a log mean temperature difference. Note that the average reference
U values were used when it could not be calculated as in E-82 and E-84. The duty of E-84 given
was simulated and the resulting fan power required was used as benchmark for further redesign.
C-3
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
The reference heat transfer coefficients were obtained with the following considerations:
1. Stripper OH Condenser
Shell: CO2 and Water
Tube: Water
Source: Kern, 1950 (2) (Aqueous Solutions 250-500 Btu/F/h/ft2)
2. CO2 Absorber OH Cooler
Shell: Syngas
Tube: Water
Source: Perry, 2008 (3) (H2 Containing Natural-Gas Mixtures 80-125 Btu/F/h/ft2)
3. Lean Amine Air Cooler
Tube: Lean Amine
Source: Brown, 1978 (4) (Ammonia 100-120 Btu/F/h/ft2, Water 120-140 Btu/F/h/ft2)
Note: Lean amine solution is ~90% Water, ~10% aMDEA, and <1% CO2. May be
able to use above values for approximation
4. Lean/Rich Amine Exchanger
Shell: Most likely lean amine since it has less CO2 and less corrosive
Tube: Most likely semilean amine since it has more CO2
Source: Perry, 2008 (3) (Ethanol amine 10-25% solution shell side 140-200 Btu/F/h/ft2)
Note: No exact match, can use above source as approximate value
5. Stripper Reboiler
Shell: Most likely lean amine
Tube: Most likely water
C-4
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Source: Perry, 2008 (3) (Ethanol amine 10-25% solution shell side 140-200 Btu/F/h/ft2)
Note: same comments as Item 4
based on, the number of stages required to obtain the stated absorption of CO2 from the syngas
stream was calculated. Reasonable agreement between the calculated number of stages and the
actual number of stages provided in the CO2 Absorber data sheet. Since the simulation of the CO2
Absorber was created from the design basis and the data sheet, this agreement validates the
C-5
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
C-6
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
C-7
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
4. Compression Stage
The CO2 stream leaving the LP Flash Stripper is compressed before being sent to battery
limits. In the process flow diagram provided, this step was shown as a single compressor with
a note that states “compressor includes required intercoolers, separators, and antisurge
protection”. According to GPSA (5) (Pg 13.11), the maximum recommended outlet
temperature of a compressor is 150 °C. This design limitation is taken into account to avoid
damage to lubricants and seals. Following this constraint, the number of stages required was
calculated to be three as shown below. The number of stages was simulated in BRE Promax
C-8
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
C-9
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
List of References
1. Ulrich, Gael D. and Vasudevan, Palligarnai T. Chemical Engineering Process Design and
Economics: A Practical Guide (Second Edition). Durham : Process (Ulrich) Publishing, 2004. 0-
97087683-2-3.
2. Process Heat Transfer. Kern, D. Q. New York : McGraw-Hill Book Company, Inc., 1950.
3. Perry, Robert H and Green, Don W. Perry's Chemical Engineers' Handbook. 8th. New York :
4. A Procedure for Preliminary Estimate. Brown, R. s.l. : Chem. Eng., 1978, Vol. 85.
5. Engineering Data Book. Gas Processors Suppliers Association. Tulsa : s.n., 2004, Vol. 1 and
2.
C-10
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
the revamp project. The analysis will focus on the CO2 Absorber, C-80, and the LP Flash Stripper,
C-82. This appendix will include separation calculations and additional information pertaining to
Table of Contents
1. Number of Stages .................................................................................................................. D-1
2. Pressure Drop ........................................................................................................................ D-3
2.1. Sample Pressure Drop Calculations .............................................................................. D-3
2.2. CO2 Absorber ................................................................................................................ D-4
2.2.1. Base Case (IMTP #40) ............................................................................................ D-4
2.2.2. 112% Case (IMTP #40) ........................................................................................... D-5
2.2.3. 125% Case (IMTP #40) ........................................................................................... D-6
2.2.4. 125% Case (IMTP #25) ........................................................................................... D-6
2.3. LP Flash Stripper ........................................................................................................... D-7
2.3.1. Base Case (IMTP #50) ............................................................................................ D-7
2.3.2. 125% Case (IMTP #40) ........................................................................................... D-8
3. Column Diameter Considerations ......................................................................................... D-9
4. Column Height Considerations ............................................................................................. D-9
4.1. Trays .............................................................................................................................. D-9
4.2. Packing Height .............................................................................................................. D-9
4.3. Disengagement Height ................................................................................................ D-10
4.4. Height of Liquid Pool .................................................................................................. D-10
5. Additional Cost ................................................................................................................... D-10
List of References ..................................................................................................................... D-11
i
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
1. Number of Stages
Using the composition of the streams entering and leaving the CO2 Absorber in the 125%
capacity simulation, the number of stages and consequently the amount of packing required were
D-1
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
D-2
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
2. Pressure Drop
2.1. Sample Pressure Drop Calculations
D-3
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
D-4
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
D-5
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
D-6
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
D-7
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
D-8
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
the LP Flash Stripper. Using the pressure drops and the resulting flow rates, the diameter of the
columns were confirmed to stay the same across the redesign cases using the Eckert generalized
the tray spacing) and packing, the disengagement height at the top of the column, and the height
of liquid pool at the bottom. Taking these into account, the columns were verified to handle the
increase in capacity.
4.1. Trays
The CO2 Absorber has three backwash trays at the top of the column. Tray spacing is
usually 2 ft. According to the data sheet provided, the tray spacing is 1.64 ft. Since these trays only
serve the purpose of preventing entrainment of amine into the overhead stream, the lower tray
spacing is acceptable. In the 125% redesign, the backwash tray spacing was kept at 1.64 ft (500
mm).
increased to increase the amount of CO2 removed from the inlet stream. Increasing the amount of
packing changes the total height in the column occupied by packing. Considerations were made to
ensure that the placement of additional packing did not interfere with existing nozzles. Liquid
distributors were also integrated to ensure proper flow through the packing.
D-9
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Typically, this height is around 5 to 10 ft (1.5 – 3 m). In the provided CO2 Absorber data sheet,
the top backwash tray is located approximately 6 ft from the top of the column. The recommended
disengagement height is met and kept for the 125% capacity redesign.
to 5 to 10 minutes worth of flow. In the 125% capacity redesign, the total liquid flow to the CO2
Absorber is 0.166 m3/s. In 5 minutes, the corresponding volume accumulated is 49.7 m3. Using
the column diameter of 3.1 m, this corresponds to a required surge height of 6.6 m (21.7 ft). The
provided data sheet shows 7.9 m (25.9 ft) from the bottom of the column to the inlet syngas nozzle.
With the increase in capacity, the tower still has adequate surge height.
5. Additional Cost
To obtain better separation of CO2 from the syngas stream, packing with higher efficiency is
required. Changing the existing packing to a higher efficiency type as well as increasing the
amount of it in the CO2 Absorber incurs additional cost. Installation of the new packing will also
require labour from trained personnel. Similar costs will be incurred in changing the packing type
D-10
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
List of References
1. Engineering Data Book. Gas Processors Suppliers Association. Tulsa : s.n., 2004, Vol. 1 and
2.
2. Perry, Robert H and Green, Don W. Perry's Chemical Engineers' Handbook. 8th. New York :
D-11
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
piping and instrumentation diagram. A stream table and equipment list for the entire process is
also included.
A plot plan was created for the base, 112% design, and 125% design case. The base and
112% design case have identical plot plans since the 112% design case does not require any
addition equipment or resizing. The 125% design case includes the lean amine cooler (E-85) that
was added for further cooling of the lean amine to the CO2 absorber (C-80).
A process flow diagram was created for the base, 112% design, and 125% design case. The
base and 112% design case have identical plot plans since the 112% design case does not require
any addition equipment. The 125% design case includes the E-85 that was added for further
A piping and instrumentation diagram was created for E-85 in the 125% design case. The
base and 112% design case does not have a piping and instrumentation diagram since the proper
i
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Table of Contents
1. List of Drawings ....................................................................................................................E-1
2. Plot Plan for the Base and 112% Design Case ......................................................................E-1
3. Plot Plan for the 125% Design Case ......................................................................................E-3
4. Block Flow Diagram ..............................................................................................................E-4
5. Stream Table for the Base Case .............................................................................................E-5
6. Stream Table for the 112% Case ...........................................................................................E-6
7. Process Flow Diagram for the Base and 112% Cases ...........................................................E-7
8. Stream Table for the 125% Case ...........................................................................................E-8
9. Process Flow Diagram for the 125% Case ............................................................................E-9
10. Process Flow Diagram for the Vendor Compression Unit ..................................................E-10
11. Line Designation Table for CN49PID .................................................................................E-11
12. CN49PID for E-85 ...............................................................................................................E-12
ii
DRAWING NO. DRAWING TITLE REV REMARKS
STREAM TABLE STREAM TABLE FOR BASE CASE 0 CANADIAN NATURAL RESOURCES LTD.
STREAM TABLE STREAM TABLE FOR 112% DESIGN CASE 0 REVAMP OF CO2 RECOVERY PLANT
CN49PFD PROCESS FLOW DIAGRAM - UNIT 49 - BASE AND 112% DESIGN CASE 4
1. List of Drawings
1. List of Drawings
2. E-1
SCALE (m) : EQUIPMENT LIST
Prevailing Wind
2.5 5 10 20 Direction E-80 – CO2 Absorber Overhead Cooler
C-80 – CO 2 Absorber
C-81
C-80
C-82
E-2
SCALE (m) : EQUIPMENT LIST
Prevailing Wind
2.5 5 10 20 Direction E-80 – CO2 Absorber Overhead Cooler
C-80 – CO 2 Absorber
C-81
C-80
C-82
Pressure Swing
Tail Gas
Absorption
Lean Amine
Syngas
Project Scope
Separation
System
Boiler Feed
Water
High
Process Gas Temperature
Reaction
E-4
2. Block Flow Diagram L-4
5. Stream Table for the Base Case
E-5
L-5
6. Stream Table for the 112% Case
E-6
L-6
E-80 C-87 C-82 E-83 G-83A/B C-83 E-82 C-81
CO2 Absorber Absorber Overhead LP Flash Stripper Stripper Overhead Stripper Reflux Reflux Vessel Stripper Reboiler HP Amine Flash Drum
3 3 2 3
Overhead Cooler K.O. Drum Volume: 443.0 m Condenser Pump Volume: 36.8 m Area: 298.1 m Volume: 75.0 m
2 3 2
Area: 90.0 m Volume: 9.7 m Area: 381.0 m Duty: 1 kW
E-84 G-82A/B/C E-81A/B G-81A/B G-84 C-80 C-84
Lean Amine Air HP Lean Amine 7. Process Flow DiagramSemilean
for the
Lean/Rich Amine Base and
Amine Amine112%
Make-Up Cases CO Absorber 2
3
Make Up Storage
Cooler Pump Exchanger Pump Pump Volume: 177.0 m Vessel
2
Duty: 27838 kW Duty: 1158 kW Area: 1217.6 m Duty: 120 kW 37 CMP49PFD
94
FC
96
87 G-83A/B
Synthesis Gas 25
C-80 LC
82
FC
PC C-82
Process Water to
Flash Gas to Steam Battery Limits
Methane Reformer 75
C-81 E-81A/B
83 78 FC
73 74
LC E-82 LP Steam
81
86 76
LP Condensate
85
E-84 84
C-84
LP Steam
LP Condensate G-82A/B/C G-81A/B
G-84
Revamp of Carbon Dioxide Recovery Plant
Amine Solution
E-8
L-8
E-80 C-87 C-82 E-83 G-83A/B C-83 E-82 C-81
CO 2 Absorber Absorber Overhead LP Flash Stripper Stripper Overhead Stripper Reflux Reflux Vessel Stripper Reboiler HP Amine Flash Drum
Overhead Cooler K.O. Drum Volume: 443 m3 Condenser Pump Volume: 36.8 m3 Area: 301.1 m2 Volume: 75 m3
Area: 74.39 m2 Volume: 9.7 m3 Area: 382.1 m2 Duty: 1 kW
E-84 G-82A/B/C E-81A/B/C G-81A/B G-84 E-85A/B C-80 C-84
Lean Amine Air HP Lean Amine Lean/Rich Amine Semilean Amine Amine Make-Up Lean Amine Cooler CO 2 Absorber Make Up Storage
Cooler Pump Exchanger Pump Pump Area: 815.4 m2 Volume: 177 m3 Vessel
2
Duty: 24870 kW Duty: 1185 kW Area: 1772.2 m Duty: 123 kW
9. Process Flow Diagram for the 125% Case E-83
37 CMP4 9PFD
E-80 35 36
LC C-83
26 27 CWS CWR
FC LC C-87 95
CWS CWR
LP Condensate 72 77
93
LC
94
FC
96
87 G-83A/B
Synthesis Gas 25
C-80 LC
82
FC
86 PC C-82
Process Water to
Flash Gas to Steam Battery Limits
75
Methane Reformer
C-81 E-81A/B/C
83 78 FC
E-85A/B 73 74
81
86C 76
LP Condensate
85
E-84 84
C-84
LP Steam
LP Condensate G-82A/B/C G-81A/B
G-84
Amine Solution Revamp of Carbon Dioxide Recovery Plant
CN49PFD
37
PC PC PC
37D 37H
CO2 Product to
37B 37F 38 Dehydration Unit
LC LC
D-100 D-101
37C 37G
E-10
L-10
LINE DESIGNATION DESCRIPTION MECHANICAL OPREATING CONDITIONS DESIGN CONDITIONS REFERENCE DRAWINGS
COM LINE NO PIPE SIZE FROM TO SERVICE MATERIAL TEMP ( C) PRESSURE (kPag) TEMP ( C) PRESSURE (kPag) P&ID
AOAA 86C 16 LEAN AMINE AIR COOLER (E-84) LEAN AMINE COOLER (E-85) LEAN SS-316 41 4099 165 6448 CN49PID
AOAA 86 16 LEAN AMINE COOLER (E-85) CARBON DIOXIDE ABSORBER (C-80) LEAN SS-316 35 4099 165 6448 CN49PID
CWS 86 10 UTILITY COOLING WATER TANK LEAN AMINE COOLER (E-85) WATER SS-316 24 500 65 550 CN49PID
CWR 86 10 LEAN AMINE COOLER (E-85) WATER DRAIN/RECYCLE SYSTEM WATER SS-316 32 480 65 550 CN49PID
Notes:
E-11
L-11
12. CN49PID for E-85
E-12
L-12
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
the CO2 Recovery Plant in the 112% and 125% capacity redesigns.
Table of Contents
1. 112% Capacity Redesign ....................................................................................................... F-1
2. 125% Capacity Redesign ....................................................................................................... F-1
2.1. Start-Up Procedures ....................................................................................................... F-1
2.2. Shutdown Procedures ..................................................................................................... F-2
i
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
procedures shall be consistent with the existing procedures. Only the flow rate of amine solution
will need to be adjusted when filling the amine system with lean amine solution during start-up.
The pressure, temperature, and flow rate setpoints that need to be adjusted are identified below:
Table K1: Temperature, Pressure, and Flow Rate Changes for the 112% Capacity Redesign
commissioning the exchanger. This is recommended in order to provide better corrosion protection
for the carbon steel shell of the exchanger. The following must also be added to the requirements
• The amine system, including the Lean Amine Cooler (E-85A/B) and Lean/Rich Amine
F-1
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
• The column packings must be flushed and degreased before being installed into the
• The cooling water supply to the Lean Amine Cooler (E-85A/B) must be in operation
• The upsized Absorber Overhead Knockout Drum (C-87) and Reflux Vessel (C-83)
must be filled with condensate or demineralized water to prevent dew point corrosion
During the start-up sequence, the cooling water supply to the Lean Amine Cooler (E-85A/B) must
be increased prior to operating the Stripper Reboiler (E-82) at full steam flow rates. This is to the
prevent the hot lean amine solution from vaporizing the cooling water in the tube side of the Lean
Amine Cooler (E-85A/B). This would result in over pressurization of the exchanger tubes and
would trigger the release of steam from the pressure relief valve on the cooling water outlet piping.
The pressure, temperature, and flow rate setpoints that need to be adjusted are identified below:
Table K2: Temperature, Pressure, and Flow Rate Changes for the 125% Capacity Redesign
flow rate to the Stripper Reboiler (E-82) is reduced to avoid vaporization of water in the tubes.
F-2
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Table of Contents
1. Overall Material Balances..................................................................................................... G-1
1.1. Base Case ...................................................................................................................... G-1
1.2. 112% Case ..................................................................................................................... G-2
1.3. 125% Case ..................................................................................................................... G-3
2. Overall Energy Balances....................................................................................................... G-4
2.1. Base Case ...................................................................................................................... G-5
2.2. 112% Case ..................................................................................................................... G-6
2.3. 125% Case ..................................................................................................................... G-7
i
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
mass balances around each equipment were checked and verified minimal losses as indicated by
overall mass balance agreements shown in the following sections. Mass was conserved for all three
cases.
Water Header
Amine Blowdown Amine Blowdown - 1.3
Water Blowdown Water Blowdown - 0.0
37C Stage 1 Compressor K.O. Vessel - 71.1
37G Stage 2 Compressor K.O. Vessel - 19.4
Total (kmol/h) 8344.1 8344.1
Percent Difference 0.00%
G-1
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Water Header
Amine Blowdown Amine Blowdown - 0.0
Water Blowdown Water Blowdown - 0.0
37C Stage 1 Compressor K.O. Vessel - 72.7
37G Stage 2 Compressor K.O. Vessel - 20.8
Total (kmol/h) 9270.0 9270.0
Percent Difference 0.00%
G-2
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
G-3
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
appendix, it had been shown that specific heat capacities of streams were adequately modelled in
the simulation and the duty as well as heat exchange areas had been verified for the heat
exchangers. Note that a Fictional Exchanger has been added to the semilean pump-around to reflect
stream properties in the design basis. Also, due to inadequacy of the simulation to reflect the
exothermic absorption process, another fictitious heat exchanger with a duty of 918 kW was
introduced to reflect this in the absorber as shown in the addendum simulation file “CO2 Recovery
Unit Simulation (Addendum) Rev0”. This duty was then deducted from the E-80 duties in the
original simulation files. Without having accounted for this duty, the size of the E-80 would have
Further validation of stream enthalpies involved in the overall energy balance was performed.
These enthalpies were multiplied by the mass flow rates for ease of comparison with the base case
energy balance provided below. Since the design basis flow rates were used in the base case
simulation, this multiplication is acceptable. Good agreement between the actual design basis
values and the simulated values support the accuracy of the energy balances included in this study.
G-4
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Header
Amine Blowdown Amine Blowdown - -111
Water Blowdown Water Blowdown - 0
37C Stage 1 Compressor K.O. Vessel - -5,615
37G Stage 2 Compressor K.O. Vessel - -1,537
E-80 CO2 Absorber Overhead Cooler - 1,267
E-81A/B Lean/Rich Amine Exchanger (Semilean Side) 18,149 -
E-81A/B Lean Amine Exchanger (Lean Side) 18,149
E-82 Stripper Reboiler 31,600
E-83 Stripper Overhead Condenser 2,362
Fictional Exchanger Semilean Amine Preheat 9
EQUIPMENT
G-5
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Header
Amine Blowdown Amine Blowdown - 0
Water Blowdown Water Blowdown - 0
37C Stage 1 Compressor K.O. Vessel - -5,748
37G Stage 2 Compressor K.O. Vessel - -1,649
E-80 CO2 Absorber Overhead Cooler - 1,267
E-81A/B Lean/Rich Amine Exchanger (Semilean Side) 21,225 -
E-81A/B Lean Amine Exchanger (Lean Side) - 21,225
E-82 Stripper Reboiler 31,600 -
E-83 Stripper Overhead Condenser - 2,361
Fictional Exchanger Semilean Amine Preheat 13 -
EQUIPMENT
G-6
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Header
Amine Blowdown Amine Blowdown - 0
Water Blowdown Water Blowdown - 0
37C Stage 1 Compressor K.O. Vessel - -5,124
37G Stage 2 Compressor K.O. Vessel - -1,822
E-80 CO2 Absorber Overhead Cooler - 1,107
E-81A/B/C Lean/Rich Amine Exchanger (Semilean Side) 27,059
E-81A/B/C Lean Amine Exchanger (Lean Side) 27,059
E-82 Stripper Reboiler 31,600 -
E-83 Stripper Overhead Condenser - 2,190
Fictional Exchanger Semilean Amine Preheat 14
EQUIPMENT
G-7
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
existing plant as well as those required for a capacity increase to 125 %. The existing operating
data for each equipment, the output of the base case simulation, as well as the output of the capacity
increase redesign are compared to identify additional units to be procured. Heat exchangers,
separators, and pumps were sized using Gas Processors Suppliers Association Engineering Data
Book.
Table of Contents
1. Detailed Equipment List – Base Case ................................................................................... H-1
2. Detailed Equipment List – 112 % Case ................................................................................ H-5
3. Detailed Equipment List – 125 % Case ................................................................................ H-9
4. Heat Exchanger Sizing ........................................................................................................ H-13
4.1. Operating Data Provided ............................................................................................. H-13
4.2. Design Data Sheet Provided ........................................................................................ H-14
4.3. Heat Exchanger Sizing Sample Calculations .............................................................. H-15
4.4. Base Case Sizes ........................................................................................................... H-16
4.5. 112 % Case Sizes ........................................................................................................ H-18
4.6. 125 % Case Sizes ........................................................................................................ H-19
5. Vessel Sizing....................................................................................................................... H-21
5.1. Operating Data Provided ............................................................................................. H-22
5.2. Separator Sizing Sample Calculations ........................................................................ H-22
5.3. Base Case Sizes ........................................................................................................... H-28
5.4. 112 % Case Sizes ........................................................................................................ H-29
5.5. 125 % Case Sizes ........................................................................................................ H-30
6. Column Sizing .................................................................................................................... H-31
i
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
ii
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
iii
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Other Specifications
H-1
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Stream Number 74 75 36 37 27 28
CO2 to CO2
Rich Amine to HP Flash Gas from HP CO2 to Reflux SG from CO2 SG from CO2
Name Product
Amine Flash Drum Amine Flash Drum Vessel Absorber OH Cooler Recovery Unit
Compressor
Process Orientation
Phase Mixed Vapour Mixed Vapour Mixed Vapour
Residence Time (s)
Temperature (℃) In 75 45 40
Out 75 44 40
Pressure (kPa) In 875 125 3350
Out 875 120 3350
Flow Rate Mass (kg/h) 643079 410 57137 54067 34028 33651
3
Volumetric (m /h) 646 52 27026 28115 5538 5537
3
Ave. Density (kg/m ) 995 8 2 2 6 6
Ave. Heat Capacity
(kJ/kg/K)
Ave. Viscosity (mPa.s) 1.73E-08 1.59E-08 1.19E-08
Enthalpy (kJ/kg) In
Out
Stream Number 76 93 87
Process
Rich Amine from Process Cond. From
Condensate to
Name HP Amine Flash Absorber OH K.O.
Stripper Reflux
Drum Drum
Pump
Process Orientation
Phase Liquid Liquid Liquid
Residence Time (s)
Temperature (℃) In
Out 75 44 40
Pressure (kPa) In
Out 875 120 3350
Flow Rate Mass (kg/h) 642668 3070 378
3
Volumetric (m /h) 594 3 0
3
Ave. Density (kg/m ) 1081 990 991
Ave. Heat Capacity
(kJ/kg/K)
Ave. Viscosity (mPa.s) 1.53E-06 6.18E-07 6.72E-07
Enthalpy (kJ/kg) In
Out
Heat-Transfer Coefficient
(J/m2s*K)
Efficiency (%)
Heating Duty (kJ/s)
LMTD (℃)
MTD (℃)
FT
Δtm
Utilities
Electricity (kW)
Cooling Water (m3/h)
Equipment Size
Length or height, L (m) 19.8 3.9 3.7
Width or diameter, D (m) 2.2 2.2 1.4
Surface Area, A (m2)
Volume, V (m3) 75.4 14.8 5.7
Design Pressure (kPa)
Shaft Power, ws (kW)
Physical Orientation Vertical Vertical Vertical
Material of Construction CS/ SS 316L SS 304L CS
Other Specifications
H-2
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Stream Number 25 72 86 77 82 95
Lean Amine from Process
SG to CO2 Steam Condensate Rich Amine to LP Semilean Amine to
Name Lean Amine Air Condensate to LP
Absorber to CO2 Absorber Flash Stripper LP Flash Stripper
Cooler Flash Stripper
Process Orientation
Phase Vapour Liquid Liquid Mixed Mixed Liquid
Residence Time (s)
Temperature (℃) In 40 45 45 65 90 45
Out
Pressure (kPa) In 3426 3376 4200 143 145 141
Out
Flow Rate Mass (kg/h) 86377 2198 588154 642631 551918 2558
Volumetric (m3/h) 6281 2 572 8695 14766 3
Ave. Density (kg/m3) 14 990 1029 74 37 990
Ave. Heat Capacity
(kJ/kg/K)
Ave. Viscosity (mPa.s) 1.44E-08 6.16E-07 2.46E-06 6.15E-07
Enthalpy (kJ/kg) In
Out
Stream Number 26 73 78 83 35
Semilean Amine
SG from CO2 Rich Amine from Lean Amine from CO2 from LP
Name from LP Flash
Absorber CO2 Absorber LP Flash Stripper Flash Stripper
Stripper
Process Orientation
Phase Vapour Liquid Liquid Liquid Vapour
Residence Time (s)
Temperature (℃) In
Out 57 74 76 114 66
Pressure (kPa) In
Out 3376 3435 222 151 141
Flow Rate Mass (kg/h) 34028 642701 551918 588052 57137
Volumetric (m3/h) 5817 594 523 601 28959
3
Ave. Density (kg/m ) 6 1082 1056 978 2
Ave. Heat Capacity
(kJ/kg/K)
Ave. Viscosity (mPa.s) 1.24E-08 1.55E-06 1.31E-06 6.21E-07 1.67E-08
Enthalpy (kJ/kg) In
Out
Heat-Transfer Coefficient
(J/m2s*K)
Efficiency (%)
Heating Duty (kJ/s)
LMTD (℃)
MTD (℃)
FT
Δtm
Utilities
Electricity (kW)
Cooling Water (m3/h)
Equipment Size
Length or height, L (m) 23.5 39.1
Width or diameter, D (m) 3.1 3.8
Surface Area, A (m2)
Volume, V (m3) 177 443
Design Pressure (kPa)
Shaft Power, ws (kW)
Physical Orientation Vertical Vertical
Material of Construction CS CS/SS 316L
Vertical tower with Montz-Thormann trays and IMTP #40 Vertical tower with Montz-Thormann trays and IMTP #50
Other Specifications
packing packing
H-3
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Name
Process Orientation
Phase
Residence Time (s)
Temperature (℃) In
Out
Pressure (kPa) In
Out
Flow Rate Mass (kg/h)
Volumetric (m3/h)
3
Ave. Density (kg/m )
Ave. Heat Capacity
(kJ/kg/K)
Ave. Viscosity (mPa.s)
Enthalpy (kJ/kg) In
Out
Heat-Transfer Coefficient
(J/m2s*K)
Efficiency (%) 67.5 59.4 36.0 80 80 80
Heating Duty (kJ/s)
LMTD (℃)
MTD (℃)
FT
Δtm
Utilities
Electricity (kW)
Cooling Water (m3/h)
Equipment Size
Length or height, L (m)
Width or diameter, D (m)
Surface Area, A (m2)
Volume, V (m3)
Design Pressure (kPa)
Shaft Power, ws (kW) 111.5 1143.4 1.1 1487.8 1414.6 1324.6
Physical Orientation
Material of Construction SS 316L SS 316L SS 304L SS 316L SS 316L SS 316L
Other Specifications
H-4
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Other Specifications
H-5
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Stream Number 74 75 36 37 27 28
CO2 to CO2
Rich Amine to HP Flash Gas from HP CO2 to Reflux SG from CO2 SG from CO2
Name Product
Amine Flash Drum Amine Flash Drum Vessel Absorber OH Cooler Recovery Unit
Compressor
Process Orientation
Phase Mixed Vapour Mixed Vapour Mixed Vapour
Residence Time (s)
Temperature (℃) In 73 44 40
Out 73 44 40
Pressure (kPa) In 875 125 3350
Out 875 120 3350
Flow Rate Mass (kg/h) 656751 421 61171 58124 39801 39437
Volumetric (m3/h) 655 52 28947 30113 6195 6194
Ave. Density (kg/m3) 1002 8 2 2 6 6
Ave. Heat Capacity
(kJ/kg/K)
Ave. Viscosity (mPa.s) 1.72E-08 1.59E-08 1.20E-08
Enthalpy (kJ/kg) In
Out
Stream Number 76 93 87
Process
Rich Amine from Process Cond. From
Condensate to
Name HP Amine Flash Absorber OH K.O.
Stripper Reflux
Drum Drum
Pump
Process Orientation
Phase Liquid Liquid Liquid
Residence Time (s)
Temperature (℃) In
Out 73 44 40
Pressure (kPa) In
Out 875 120 3350
Flow Rate Mass (kg/h) 656331 3047 364
Volumetric (m3/h) 603 3 0
Ave. Density (kg/m3) 1089 990 992
Ave. Heat Capacity
(kJ/kg/K)
Ave. Viscosity (mPa.s) 1.71E-06 6.25E-07 6.74E-07
Enthalpy (kJ/kg) In
Out
Heat-Transfer Coefficient
(J/m2s*K)
Efficiency (%)
Heating Duty (kJ/s)
LMTD (℃)
MTD (℃)
FT
Δtm
Utilities
Electricity (kW)
Cooling Water (m3/h)
Equipment Size
Length or height, L (m) 19.8 3.9 3.7
Other Specifications
H-6
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Stream Number 25 72 86 77 82 95
Lean Amine from Process
SG to CO2 Steam Condensate Rich Amine to LP Semilean Amine to
Name Lean Amine Air Condensate to LP
Absorber to CO2 Absorber Flash Stripper LP Flash Stripper
Cooler Flash Stripper
Process Orientation
Phase Vapour Liquid Liquid Mixed Mixed Liquid
Residence Time (s)
Temperature (℃) In 40 45 41 63 90 44
Out
Pressure (kPa) In 3426 3376 4200 143 145 141
Out
Flow Rate Mass (kg/h) 96164 2198 597827 656330 620865 2666
Volumetric (m3/h) 6993 2 580 8868 17948 3
Ave. Density (kg/m3) 14 990 1031 74 35 990
Ave. Heat Capacity
(kJ/kg/K)
Ave. Viscosity (mPa.s) 1.44E-08 6.16E-07 2.85E-06 6.22E-07
Enthalpy (kJ/kg) In
Out
Stream Number 26 73 78 83 35
Semilean Amine
SG from CO2 Rich Amine from Lean Amine from CO2 from LP
Name from LP Flash
Absorber CO2 Absorber LP Flash Stripper Flash Stripper
Stripper
Process Orientation
Phase Vapour Liquid Liquid Liquid Vapour
Residence Time (s)
Temperature (℃) In
Out 55 73 76 114 65
Pressure (kPa) In
Out 3376 3450 241 151 141
Flow Rate Mass (kg/h) 39801 656387 620865 597825 61171
Volumetric (m3/h) 6470 603 586 611 30704
Ave. Density (kg/m3) 6 1089 1060 979 2
Ave. Heat Capacity
(kJ/kg/K)
Ave. Viscosity (mPa.s) 1.25E-08 1.73E-06 1.37E-06 6.39E-07 1.67E-08
Enthalpy (kJ/kg) In
Out
Heat-Transfer Coefficient
(J/m2s*K)
Efficiency (%)
Heating Duty (kJ/s)
LMTD (℃)
MTD (℃)
FT
Δtm
Utilities
Electricity (kW)
Cooling Water (m3/h)
Equipment Size
Length or height, L (m) 23.5 39.1
H-7
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Name
Process Orientation
Phase
Residence Time (s)
Temperature (℃) In
Out
Pressure (kPa) In
Out
Flow Rate Mass (kg/h)
3
Volumetric (m /h)
Ave. Density (kg/m3)
Ave. Heat Capacity
(kJ/kg/K)
Ave. Viscosity (mPa.s)
Enthalpy (kJ/kg) In
Out
Heat-Transfer Coefficient
(J/m2s*K)
Efficiency (%) 67.5 59.4 36.0 80 80 80
Heating Duty (kJ/s)
LMTD (℃)
MTD (℃)
FT
Δtm
Utilities
Electricity (kW)
Cooling Water (m3/h)
Equipment Size
Length or height, L (m)
Other Specifications
H-8
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Process Orientation Tube-Side Hot Side Tube-Side Tube-Side Cold Side Tube-Side
Phase Liquid Liquid Vapour In, Liquid Out Liquid Vapour Liquid
Residence Time (s)
Temperature (℃) In 24 114 156 24 17 24
Out 40 76 143 35.5 21.01806247 38
Pressure (kPa) In 601 156 400 601 101 601
Out 549 140 581 101 581
Flow Rate Mass (kg/h) 59639 615311 52455 164042 6189 160634
3
Volumetric (m /h) 59.82 629 164.55 5052.63 161.13
3
Ave. Density (kg/m ) 997 979 997 997
Ave. Heat Capacity
(kJ/kg/K) 4.18 4.23 3.26 4.18 1.00 4.18
Ave. Viscosity (mPa.s) 9.34E-01 6.50E-07 9.34E-01 9.34E-01
Enthalpy (kJ/kg) In -15858 -10339 -15858 -15858
Out -15791 -10497 -15810 -15800
Heat-Transfer Coefficient
2
(J/m s*K) 489 1532 965 267 879 594
Efficiency (%)
Heating Duty (kJ/s) 189 27059 31600 2190 24870 3467
LMTD (℃) 5.46 9.97 21.48 37.09 7.49
MTD (℃) 108.71
FT 0.95 1 1 1 0.96 0.955
Δtm 5.19 9.97 108.71 21.48 35.60 7.15
Utilities
Electricity (kW) 518.8
3
Cooling Water (m /h) 59.82 164.55 161.13
Equipment Size
Length or height, L (m)
H-9
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Stream Number 74 75 36 37 27 28
CO2 to CO2
Rich Amine to HP Flash Gas from HP CO2 to Reflux SG from CO2 SG from CO2
Name Product
Amine Flash Drum Amine Flash Drum Vessel Absorber OH Cooler Recovery Unit
Compressor
Process Orientation
Phase Mixed Vapour Mixed Vapour Mixed Vapour
Residence Time (s)
Temperature (℃) In 69 42 39
Out 69 41 39
Pressure (kPa) In 875 125 3350
Out 875 120 3350
Flow Rate Mass (kg/h) 681200 457 67708 64953 44572 44279
3
Volumetric (m /h) 674 55 31848 33131 6938 6938
Ave. Density (kg/m3) 1010 8 2 2 6 6
Ave. Heat Capacity
(kJ/kg/K)
Ave. Viscosity (mPa.s) 1.71E-08 1.58E-08 1.20E-08
Enthalpy (kJ/kg) In
Out
Stream Number 76 93 87
Process
Rich Amine from Process Cond. From
Condensate to
Name HP Amine Flash Absorber OH K.O.
Stripper Reflux
Drum Drum
Pump
Process Orientation
Phase Liquid Liquid Liquid
Residence Time (s)
Temperature (℃) In
Out 69 41 39
Pressure (kPa) In
Out 875 120 3350
Flow Rate Mass (kg/h) 680743 2755 293
Volumetric (m3/h) 620 3 0
Ave. Density (kg/m3) 1099 991 992
Ave. Heat Capacity
(kJ/kg/K)
Ave. Viscosity (mPa.s) 1.99E-06 6.59E-07 6.84E-07
Enthalpy (kJ/kg) In
Out
Heat-Transfer Coefficient
(J/m2s*K)
Efficiency (%)
Heating Duty (kJ/s)
LMTD (℃)
MTD (℃)
FT
Δtm
Utilities
Electricity (kW)
Cooling Water (m3/h)
Equipment Size
Length or height, L (m) 19.8 7.5 4.8
H-10
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Stream Number 25 72 86 77 82 95
Lean Amine from Process
SG to CO2 Steam Condensate Rich Amine to LP Semilean Amine to
Name Lean Amine Air Condensate to LP
Absorber to CO2 Absorber Flash Stripper LP Flash Stripper
Cooler Flash Stripper
Process Orientation
Phase Vapour Liquid Liquid Mixed Mixed Liquid
Residence Time (s)
Temperature (℃) In 40 45 35 60 90 41
Out
Pressure (kPa) In 3426 3376 4200 143 146 141
Out
Flow Rate Mass (kg/h) 107969 2342 615168 680927 648133 2092
Volumetric (m3/h) 7851 2 594 9029 22348 2
3
Ave. Density (kg/m ) 14 990 1036 75 29 991
Ave. Heat Capacity
(kJ/kg/K)
Ave. Viscosity (mPa.s) 1.44E-08 6.16E-07 3.64E-06 6.56E-07
Enthalpy (kJ/kg) In
Out
Stream Number 26 73 78 83 35
Semilean Amine
SG from CO2 Rich Amine from Lean Amine from CO2 from LP
Name from LP Flash
Absorber CO2 Absorber LP Flash Stripper Flash Stripper
Stripper
Process Orientation
Phase Vapour Liquid Liquid Liquid Vapour
Residence Time (s)
Temperature (℃) In
Out 51 69 73 114 62
Pressure (kPa) In
Out 3376 3465 246 156 141
Flow Rate Mass (kg/h) 44572 680907 648133 615311 67708
3
Volumetric (m /h) 7171 619 606 629 33043
3
Ave. Density (kg/m ) 6 1099 1070 979 2
Ave. Heat Capacity
(kJ/kg/K)
Ave. Viscosity (mPa.s) 1.24E-08 2.02E-06 1.58E-06 6.50E-07 1.66E-08
Enthalpy (kJ/kg) In
Out
Heat-Transfer Coefficient
(J/m2s*K)
Efficiency (%)
Heating Duty (kJ/s)
LMTD (℃)
MTD (℃)
FT
Δtm
Utilities
Electricity (kW)
Cooling Water (m3/h)
Equipment Size
Length or height, L (m) 23.5 39.1
H-11
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Name
Process Orientation
Phase
Residence Time (s)
Temperature (℃) In
Out
Pressure (kPa) In
Out
Flow Rate Mass (kg/h)
3
Volumetric (m /h)
Ave. Density (kg/m3)
Ave. Heat Capacity
(kJ/kg/K)
Ave. Viscosity (mPa.s)
Enthalpy (kJ/kg) In
Out
Heat-Transfer Coefficient
(J/m2s*K)
Efficiency (%) 67.5 59.4 36.0 80 80 80
Heating Duty (kJ/s)
LMTD (℃)
MTD (℃)
FT
Δtm
Utilities
Electricity (kW)
Cooling Water (m3/h)
Equipment Size
Length or height, L (m)
H-12
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
H-13
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
H-14
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
fluid is cooling water and the hot fluid is lean amine. Based on the inlet and outlet stream
temperatures tabulated below, R and S were calculated, and a correction factor FT was obtained to
be applied to LMTD. An overall heat transfer coefficient was obtained for the specific fluids
present in the heat exchanger. Using the heat exchanger duty from the simulation output, Q, the
𝑄 = 𝑈𝐴 × 𝐿𝑀𝑇𝐷 × 𝐹𝑇
𝑇1 − 𝑇2 313.15 𝐾 − 307.15 𝐾
𝑅= = = 0.48
𝑡2 − 𝑡1 308.15 𝐾 − 297.15 𝐾
𝑡2 − 𝑡1 308.15 𝐾 − 297.15 𝐾
𝑆= = = 0.69
𝑇1 − 𝑡1 313.15 𝐾 − 297.15 𝐾
H-15
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Using Kern (1950), the correction factor for a 2-4 shell and tube heat exchanger is 0.96.
𝑄 3467278 W
𝐴= = = 815.4 𝑚2
𝑈 × 𝐿𝑀𝑇𝐷 × 𝐹𝑇 594.3 𝑊 × 7.5 𝐾 × 0.96
𝑚2 𝐾
The procedure shown above was used for calculating the size of all heat exchangers present in
the design. Note that for the Lean Amine Air Cooler, the fan power required to facilitate the
required flow rate for the base case was taken as the benchmark. Additional power required for
the 112 % case and 125 % case were costed accounted for in the operating costs.
H-16
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Duty, Q W 18148961
2
Overall Heat Transfer Coefficient, U W/m /K 1531.76
2
Area, A m 1191.57
H-17
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Area, A m2 862.15
modification of operating conditions, the size of the equipment remain the same with little
H-18
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
H-19
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
H-20
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
LMTD K 21.48
S - 0.53
R - 0.57
Correction Factor, FT - 1.00
Duty, Q W 2189579
Overall Heat Transfer Coefficient, U W/m2/K 266.77
Area, A m2 382.14
5. Vessel Sizing
H-21
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
and length of the vessel are calculated using two sizing guidelines:
H-22
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
The most conservative dimensions resulting from these methods were taken as the separator size.
The following parameters have been defined for the Absorber Overhead Knockout Drum C-87:
In GPSA Section 7: Separation Equipment, particle diameter size for gravity settling chambers
range from 5 to 10,000 µm. A value of 500 µm was assumed for the separators. It was also stated
that the length to diameter ratio (L:D) for vertical separators is typically 2 to 4; a value of 3 was
used for calculations. Demisters will add 0.15 m to the total height and diameter of the
separators. A residence time of 5 minutes will be used to determine liquid holdup capacity. An
In the following equations, the subscript c denotes the continuous phase. With vapour as the
continuous phase and liquid as the dispersed or discontinuous phase, the terminal velocity was
For Re < 2
H-23
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
𝑚 −6 2 𝑘𝑔
1000𝑔𝐷𝑝 2 (𝜌𝐿 − 𝜌𝑉 ) 1000(9.81 𝑠 2 )(500 ∙ 10 𝑚) (991.4 − 6.07 𝑚3 ) 𝑚
𝑉𝑡 = = −2
= 11.3
18𝜇𝐶 18(1.19 ∙ 10 𝑚𝑃𝑎 ∙ 𝑠) 𝑠
𝑘𝑔 −6 𝑚
1000𝜌𝑉 𝐷𝑝 𝑉𝑡 1000 (6.07 𝑚3 ) (500 ∙ 10 𝑚) (11.3 𝑠 )
𝑅𝑒 = = = 2882
𝜇𝐶 1.19 ∙ 10−2 𝑚𝑃𝑎 ∙ 𝑠
Since the Re value calculated is not within the stated range, this terminal velocity cannot be used.
𝑚 0.71 𝑘𝑔
2.94(9.81 2 ) (500 ∙ 10−6 𝑚)1.14 (991.4 − 6.07 3 )0.71 𝑚
= 𝑠 𝑚 = 1.37
𝑘𝑔 𝑠
(6.07 3 )0.29 (1.19 ∙ 10−2 𝑚𝑃𝑎 ∙ 𝑠)0.43
𝑚
𝑘𝑔 −6 𝑚
1000𝜌𝑉 𝐷𝑝 𝑉𝑡 1000 (6.07 𝑚3 ) (500 ∙ 10 𝑚) (1.37 𝑠 )
𝑅𝑒 = = = 349
𝜇𝐶 1.19 ∙ 10−2 𝑚𝑃𝑎 ∙ 𝑠
Since the calculated Re is within the specified range, use this velocity for the next calculation. If
this was not the case, the final terminal velocity formula below could have been used for higher
Re values.
𝑔𝐷𝑝 (𝜌𝐿 − 𝜌𝑉 )
𝑉𝑡 = 1.74√
𝜌𝑉
H-24
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Assuming the droplets are spherical, the Re is used to obtain a drag coefficient CD and a terminal
velocity is recalculated. Iterations, i, are done until the velocities are within 5% of the last
iteration.
𝑚 𝑘𝑔
4𝑔𝐷𝑝 (𝜌𝐿 − 𝜌𝑉 ) 4(9.81 2 )(500 ∙ 10−6 𝑚)(991.4 − 6.07 3 )
𝑉𝑡,𝑖 = √ =√ 𝑠 𝑚 = 1.45 𝑚
3𝜌𝑉 𝐶𝐷 𝑘𝑔 𝑠
3(6.07 3 )(0.5)
𝑚
𝑄𝑉 4𝑄𝑉
𝑉𝑡 = =
𝐴 𝜋𝐷2
𝑚3
4(125 % × 1.538
𝐷=√
4𝑄𝑉
=√ 𝑠 ) = 1.3 𝑚
𝜋𝑉𝑡 𝑚
𝜋(1.45 𝑠 )
𝐿 = 3𝐷 = 3(1.3 𝑚) = 3.9 𝑚
The same procedure is repeated but with liquid as the continuous phase and vapour as the
dispersed phase. The more conservative dimensions will be taken as the size of the separator. In
this case, the dimensions above are more conservative since the liquid flow into the vessel is not
as large as the vapour phase. Note that the diameter above agrees with the actual diameter of the
H-25
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
existing C-87 provided by the client. The length is slightly higher but this is acceptable since we
Souders-Brown
𝜌𝐿 − 𝜌𝑉
𝑉𝑚𝑎𝑥 = 𝐾𝑆 √
𝜌𝑉
PetroSkills | John M. Campbell (2015) provided a correlation for the design parameter KS of 500
micron droplets as a function of pressure. Correlation for the lower curve is used to get a
𝐾𝑆 = 0.1225 + 0 × 𝑃 = 0.1225
The deration factor due to the mesh pad was determined to be 80% of the design parameter.
𝑘𝑔
991.4 − 6.07
𝑉𝑚𝑎𝑥 = (0.1225 × 80%)√ 𝑚3 = 1.25 𝑚
𝑘𝑔 𝑠
6.07 3
𝑚
𝑚3
4𝑄𝑉 4(1.538 𝑠 )
𝐷=√ =√ 𝑚 = 1.25 𝑚
𝜋𝐹𝐺 𝑉𝑚𝑎𝑥 𝜋(1)(1.25 𝑠 )
Where FG is the fraction of cross section area available for gas flow which has a value of 1 for
vertical separators.
H-26
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Typically, a disengagement height of 1 m is added to the liquid holdup height hL required and the
demister pad height. The liquid holdup volume VL for the 5 minute residence time is:
𝑚3
𝑉𝐿 = 125 %𝑄𝐿 𝑡 = 125 % × 0.0001 × 300𝑠 = 0.0397 𝑚3
𝑠
4𝑉𝐿 4(0.0397 𝑚3 )
ℎ𝐿 = = = 0.0323 𝑚
𝜋𝐷2 𝜋(1.25 𝑚)2
Final Dimensions
The most conservative dimensions from the two methods used to size equipment C-87 are used.
This agrees with the provided dimensions and validates the sizing procedure used going forward.
Again, the volume is slightly higher than the existing value, but this is due to the conservative
H-27
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
was sized to be able to handle liquid holdup capacity with the disengagement height.
However, this gives L/D=0.55 which is not ideal. In reality, a ratio between 2 to 4 is preferred.
ratio between 2 to 4 is preferred. The existing vessel length is acceptable at 3690 mm.
H-28
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
modification of operating conditions, the size of the equipment remain the same with little
was sized to be able to handle liquid holdup capacity with the disengagement height.
a ratio between 2 to 4 is preferred. The existing vessel length is acceptable at 3890 mm.
H-29
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Material CS
Note: Similar comment on the length as above. The L/D is 1. Ideally, a ratio between 2 to 4 is
was sized to be able to handle liquid holdup capacity with the disengagement height.
been sized using 25% overdesign factor on flow rate. Although the minimum calculated length is
1200 mm, the actual length will be a conservative estimate using an L/D of 3. The actual length
H-30
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
6. Column Sizing
Detailed calculations on the CO2 Absorber and LP Flash Stripper can be found in
Appendix D Separation Calculations. To keep the diameter of the columns the same, resultant
pressure drop from the operational and equipment changes was calculated and applied to the
simulation. The diameters are then reverified using the simulation output pressure drop and flow
rates using the Eckert generalized pressure drop correlation (GPDC). The diameters were
verified to be the same across the base, 112 %, and 125 % case.
H-31
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
H-32
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
H-33
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
H-34
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
H-35
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
H-36
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
H-37
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
H-38
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
7. Pump Sizing
7.1. Operating Data Provided
G-81A/B: Semilean Amine Pump
Type Centrifugal
Medium Lean amine
Operating temperature (°C) 73
3
Volumetric flow rate Q (m /h):
Maximum (rated Qmax) 720
Normal 655
Minimum (Qmin) 197
Suction pressure (kPag)
Minimum (rated Qmax) 329
Maximum 703
Discharge pressure (kPag)
Rated @ Qmax 662
Maximum shut off 1100
Differential pressure @ Qmax (kPa) 333
Differential head @ Qmax (m) 32.1
Plant NPSH available (m) 28
Material SS 316L
Speed estimated (rpm) 1775
Power estimated (kW) 89
Estimated hydraulic efficiency (%) 75
H-39
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
each pump.
H-40
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
639 kPag.
H-41
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
499 kPag.
case and operating data provided, it was found that all pump operating conditions remained well
within allowable limits. No additional pumps were required for the 112 % or 125 % capacity
redesign cases. The simulated pump operating conditions for the redesigns are shown in the
subsequent sections.
639 kPag.
H-42
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
499 kPag.
H-43
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
639 kPag.
H-44
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
499 kPag.
To identify process lines sizes that are representative of what is already in place in the existing
CO2 Recovery Facility, the lines were sized using properties and flow rates given by the client
material balance specifications. Various sizing techniques were utilized, including simulation
using VMGSim, rules of thumb provided in previous Chemical Engineering Courses at the
University of Alberta (U of A), and utilizing standard sizing charts. To select a nominal pipe size
calculated based on the three different techniques, economical fluid velocities, pressure drops,
pump suction line maximum recommended velocities, and guidelines for minimizing corrosion
in amine units were considered. Pipe Schedules were then calculated using the American Society
H-45
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
The internal diameter of the pipe was then determined based on the pipe thickness
required by ASME B31.3. If this internal diameter provided flow that was outside of
recommended ranges for velocity or pressure drop, the process was iterated again with a
different pipe size. The details of the sizing process for the different types of flow are provided
below. Sample calculations for the sizing process are given in Section 5.2. Conversion factors
between different units were obtained from Ulrich and Vasudevan (2).
Engineering Handbook, Seventh Edition (3). An economic optimum velocity for gases with
densities ranging from 0.2 to 20 kg/m3 was reported to be 40 m/s to 9 m/s. All vapour streams
using design basis and simulated information fell within this specified density.
The recommended maximum allowable velocity for the vapour streams were also
considered based on the calculated sonic velocity of the gas (4). The velocity of the vapour
should remain less than 0.1 times the sonic velocity of the vapour, which is given by:
𝑉𝑠 = √𝑘𝑃/𝜌
The ratio of specific heats, k, for each component was obtained from Engineering Toolbox (5).
The maximum friction loss in the pipe in kPa/100m was determined by linear interpolation of the
m/s) based on the Kolmetz Handbook of Process Equipment Design (7). The allowable pressure
drop for low viscosity liquids was also taken from the Kolmetz Handbook, with a value of 2.2
H-46
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
psi/100ft (49.77 kPa/100m). To increase the NPSHa to avoid cavitation in pump suction lines, a
maximum velocity of 5ft/s (1.52m/s) was chosen (7) (8). The recommended velocity through
carbon steel pipes is also recommended to be below 1.8 m/s for MDEA units (9). This was taken
by guidelines given by Church, and distributed or segregated flow was targeted wherever
possible to avoid intermittent flow (6). The flow regime was determined from Empirical flow
parameters from the design basis for stream 25 are provided in the table below.
Stream Number 25
Description SG to CO2 Absorber
Phase Vapor
Vapour fraction 100
Temperature (K) 313.15
Pressure (kPa(g)) 3325.00
Volumetric Flow Rate (m3/s) 1.76
Eff Density (kg/m3) 13.65
Viscosity (Pa s) 1.40E-05
Component mol/mol
CO 0.03
CO2 0.17
H2 0.76
H2O 0.00
CH4 0.04
N2 0.00
H-47
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
O2 0.00
aMDEA 0.00
MDEA 0.00
PZ 0.00
The ratio of specific heats was calculated by multiplying each component’s k value with their
molar fraction.
𝑘 = (0.033 ∗ 1.4 + 0.166 ∗ 1.28 + 0.756 ∗ 1.41 + 0.002 ∗ 1.33 + 0.042 ∗ 1.32 + 0.001 ∗ 1.4) = 1.38414
1000𝑃𝑎 1 𝑚3
𝑉𝑚𝑎𝑥 = 0.1 ∗ 𝑉𝑠 = 0.1 ∗ √1.38414 ∗ (3325 𝑘𝑃𝑎 + 101.325 𝑘𝑃𝑎) ∗ ∗
1 𝑘𝑃𝑎 13.65 𝑘𝑔
𝑉𝑠 = 58.94 𝑚/𝑠
32 − 18
𝛥𝑃 = 18 + (3325 − 1500) = 30.78 𝑘𝑃𝑎/100𝑚
3500 − 1500
Using this velocity and the volumetric flow rate provided in the design basis:
4Q 4 ∗ 1.76 m3 /𝑠
𝐷=√ =√ = 0.38 𝑚
πV π ∗ 15.55 m/s
1 𝑖𝑛𝑐ℎ
𝐷 = 0.38𝑚 ∗ = 14.94 𝑖𝑛𝑐ℎ𝑒𝑠
0.0254 𝑚
H-48
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
The velocity obtained from inputting the design basis information and assuming commercial
steel pipe with a roughness of 0.0045 cm gave an estimated pipe diameter of 27.34 cm, which is
Approximating the inside pipe diameter as the nominal pipe diameter for convenience,
the calculated nominal pipe sizes were 12.00 inches and 16.00 inches, which had some
discrepancy. The velocity of the fluids using these diameters was then calculated.
𝑚3
4𝑄 4 ∗ 1.76 𝑠 𝑚
𝑉𝐷=12.00𝑖𝑛 = 2= = 24.09
πD 0.0254 𝑚 2 𝑠
π ∗ (12.00 inches ∗ )
1 𝑖𝑛𝑐ℎ
Similarly, VD=14.00in = 17.70 m/s and VD=16.00in = 13.55 m/s. All of these calculated velocities
Next, the pressure drop for each calculated pipe size was determined.
𝑘𝑔 𝑚 0.0254 𝑚
𝜌𝑉𝐷 13.65 𝑚3 ∗ 24.09 𝑠 ∗ 12.00 𝑖𝑛𝑐ℎ𝑒𝑠 ∗ 1 𝑖𝑛𝑐ℎ
𝑅𝑒𝐷=12.00𝑖𝑛 = = = 7.16 ∗ 106
µ 1.4 ∗ 10−5 𝑃𝑎 ∗ 𝑠
Similarly, ReD=14.00in = 6.14*106 and ReD=16.00in = 5.37*106. The equivalent roughness was taken
𝜀 0.0045 𝑐𝑚
= = 0.00015
𝐷𝐷=12.00𝑖𝑛 12.00 𝑖𝑛𝑐ℎ𝑒𝑠 ∗ 2.54𝑐𝑚
1 𝑖𝑛𝑐ℎ
The Moody friction factor was then taken from a Moody chart to be 0.013 (10). Similarly, the
14.00 inch pipe diameter had an ε/D of 0.00013 and a friction factor of 0.0125, and the 16.00
H-49
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
The pressure drop along the pipe length was then calculated:
𝑘𝑔 𝑚 2
13.65 ∗ 0.013 ∗ 100𝑚 ∗ (24.09 𝑠 ) 1 𝑘𝑃𝑎
2
𝛥𝑃 𝜌𝑓𝑚 𝐿𝑉 𝑚3
= = = 16.89 𝑘𝑃𝑎
100𝑚 2𝐷 0.0254 𝑚 1000 𝑃𝑎
2 ∗ 12.00 𝑖𝑛𝑐ℎ𝑒𝑠 ∗
1 𝑖𝑛𝑐ℎ
The pressure drop for the 14.00 inch and 16.00 inch diameter pipes were calculated to be 7.51
Since the maximum allowable pressure drop is 30.78 kPa/100m, a nominal pipe size of
12.00 inches was selected. If the inside diameter changed significantly after the pipe thickness
was calculated, the process was repeated again with a new nominal diameter and calculated
inside diameter to verify that the pressure drop and velocities were within allowable ranges.
For process line sizing for vapours, the chart technique for process lines sizing taken
from McDonald et. al was not used, as the chart is applicable only for air with a relatively low
flow rate (11). However, the chart method was used for liquid streams, using the calculated
allowable pressure drop in ft.H2O/100ft and volumetric flow rate in U.S gallons per minute. The
After the line sizing process was completed for the design case, the entire process was
repeated for the base simulation case to verify the accuracy of the simulated results. This was
H-50
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
done because the simulation provided stream properties that were slightly different than the
design basis. If the line sizing for the base case and design case agreed, that would be reasonable
indication that the predicted fluid velocities and flow regimes for the 112 % and 125 % redesign
Stream Number 38
Description CO2 to Dehydration Unit
Phase Mixed
Vapour fraction 98.5
Temperature (K) 307.15
Pressure (kPa(g)) 3190.00
Volumetric Flow Rate (m3/s) 0.21
Eff Density (kg/m3) 68.16
Viscosity (Pa s) 0.00
Component mol/mol
CO 0.00
CO2 0.98
H2 0.00
H2O 0.02
CH4 0.00
N2 0.00
O2 0.00
aMDEA 0.00
MDEA 0.00
PZ 0.00
The vapour fraction was 0.9850 which corresponds to a liquid fraction of 0.0150. The
Froude number was calculated using the maximum and minimum allowable velocities, which
H-51
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
122 122
𝑉𝑚𝑎𝑥 = = = 14.78 𝑚/𝑠
√𝜌𝑚 √68.16 𝑘𝑔3
𝑚
73 122
𝑉𝑚𝑖𝑛 = = = 8.84 𝑚/𝑠
√𝜌𝑚 √68.16 𝑘𝑔3
𝑚
The diameters that correspond to those maximum and minimum velocities were calculated as:
0.21 m3
4Q 4∗ 1 𝑖𝑛𝑐ℎ
𝐷𝑚𝑖𝑛 =√ =√ 𝑠 = 0.136𝑚 ∗ = 5.35 𝑖𝑛𝑐ℎ𝑒𝑠
πV𝑚𝑎𝑥 m 0.0254 𝑚
π ∗ 14.78 s
Rounding up, the minimum pipe diameter for stream 38 is 6.00 inches. Similarly, the maximum pipe
diameter was calculated to be 6.92 inches. Rounding down from this maximum, the pipe diameter was
𝑚
𝑉𝑚𝑎𝑥 14.78 𝑠
𝐹𝑟𝑚𝑎𝑥 = = = 9.6156
√𝑔 ∗ 𝐷 √9.81 𝑚2 ∗ 6.00 𝑖𝑛𝑐ℎ𝑒𝑠 ∗ 0.0254 𝑚
𝑠 1 𝑖𝑛𝑐ℎ
Using the charts provided by Church’s presentation, the flow regime for stream 38 was
If the two-phase flow analysis provided different minimum and maximum pipe
diameters, the flow regime for each of those intermediate pipe diameters was calculated to
ensure distributed or segregated flow could be achieved. If multiple pipe diameters could achieve
non-intermittent flow, then the pipe diameter that allowed the highest velocity within the
H-52
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
For Stream 36 it was determined that intermittent flow was unavoidable. For this stream,
lines should be constructed with a slight decline to ensure liquid moves through the pipe without
plug or slug flow. Other streams 27 and 74 were identified as two-phase flow in the design basis,
however the simulated results suggested the streams were single phases flow. The vapour
fraction for the design basis was thus used for these streams to approximate the vapour fraction
of the simulated cases to determine the type of two-phase flow regime that could be expected.
according to (1):
𝑃𝐷
𝑡=
2(𝑆𝐸𝑊 + 𝑃𝑌)
The design pressure of the stream was based on design pressures specified in existing
equipment data sheets provided by CNRL for the CO2 absorber and LP Flash Stripper. The
design pressure of other streams were calculated as the highest pressure that the stream could
experience based on adjacent streams, or taken as the minimum between the operating pressure +
200 kPa or the operating pressure *1.1. The minimum design temperature was taken to be 65 °C
for streams below operating temperatures of 65 °C. The maximum design temperature was taken
S, E, W, and Y were taken from tables within ASME B31.3. The outside diameters of
each nominal pipe size was determined from standard carbon steel and stainless steel pipe sizes
and thicknesses based on ASME B36.10M-2018 for Welded and Seamless Wrought Steel Pipe
and B36.19M-2018 for Stainless Steel Pipe (12) (13). The total pipe thickness could then be
H-53
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
calculated as the thickness determined using the above formula added by the sum of mechanical
allowances.
𝑡𝑚 = 𝑡 + 𝑐
A corrosion allowance of 0 mm was specified for stainless steel and 3.0 mm for carbon
steel based on corrosion allowances applied for existing CO2 Recovery Plant equipment. An
additional 0.5 mm was applied to the sum of mechanical allowances to account for machined
Sample calculations will be shown for Stream 73, which is used to transport rich amine
from the CO2 absorber. The line was sized to be 14.00 inches nominal diameter (14.00 O.D).
Stainless steel was selected as the material specification due to the high acid gas content. The
reasons for this material selection will be explored further in Section 6 of this Appendix.
0.0254 𝑚
3700 𝑘𝑃𝑎 ∗ 14.00 𝑖𝑛𝑐ℎ𝑒𝑠 ∗
𝑡= 1 𝑖𝑛𝑐ℎ = 0.00565 𝑚 = 5.65 𝑚𝑚
2 ∗ (115,000 𝑘𝑃𝑎 ∗ 1.00 ∗ 1.00 + 3700 𝑘𝑃𝑎 ∗ 0.4)
1 𝑖𝑛𝑐ℎ
𝑡𝑚 = 5.65𝑚𝑚 + 0.5 𝑚𝑚 = 6.15 𝑚𝑚 ∗ = 0.24 𝑖𝑛𝑐ℎ𝑒𝑠
25.4 𝑚𝑚
Looking at ASME B36.19M, the required schedule for 14.00 inch pipe would be
Schedule 40S with a wall thickness of 0.375 inches. The lower schedule would have a wall
After the thickness was calculated, the inside diameter of the pipe was determined by the
simple formula:
H-54
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
The fluid velocity was re-calculated using this inner diameter using the method described in
5.2.2. If the velocity or pressure drop for this inside diameter was out of the allowable range, the
whole process was repeated for the next pipe size higher. The lines for two-phase flow were also
re-evaluated to see if the variance between the inside diameter and nominal pipe size constituted
Several high velocity lines were identified through the line sizing process for the 112 %
and 125 % redesign cases. These high velocity lines exceeded the 1.8 m/s recommended
maximum velocity from API RP 945 (9). The existing process line sizes may be different than
what was determined through this sizing process and the simulation produces different properties
than the design basis, meaning the pipes may not be high velocity in the existing facility.
However, it is recommended that the client investigates this potential risk to ensure that
A summary of the main process lines, including the nominal pipe size, schedule, material
specification, expected velocity, and type of flow regime is shown on the next page.
H-55
8.1. Size of Main Process Lines Summary
H-56
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
9. Material Selection
Proper material selection is imperative to ensure that process equipment operates in a safe
manner throughout its projected lifetime. Some of the materials of construction selected were
based on existing specifications from equipment data sheets provided by the client. For other
streams that were unknown, the material selection was conducted based on potential corrosion and
cracking mechanisms found in the American Petroleum Institute (API) Recommended Practices
945 and 571, and guidelines found in literature (14; 15; 16; 17; 18).
of tensile stress and corrosion in the presence of water and hydrogen sulphide. The hydrogen
sulfide liberates atomic hydrogen at the metal surface, and poisons the recombination of atomic
hydrogen into molecular hydrogen, which promotes the absorption of atomic hydrogen by the
steel. The SSC mechanism involves hydrogen embrittlement, particularly in areas of high metal
hardness such as weld deposits and weld heat-affected zones in the adjacent base metal. The
potential for SSC was not evaluated in-depth due to the presence of hydro-desulphurization
reactors located upstream of the CO2 Removal Unit that removes H2S to a high purity. However,
SSC can be minimized by applying proper Post Weld Heat Treatment (PWHT).
is defined as stepwise internal cracks that connect adjacent hydrogen blisters on different planes
in the metal, or to the metal surface. No externally applied stress is needed for the formation of
H-57
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
HIC. HIC can be minimized by selecting a higher quality steel with low inclusion content.
Increased resistance to blistering and HIC is usually achieved by lowering the sulfur content of the
steel and controlling the sulfide inclusion morphology by calcium or rare earth metal additions to
produce spheroidal sulfide shapes. Base metal heat treatments, such as normalizing or quenching,
base metal, adjacent to the heat-affected zone of a weld, where there are high residual stresses from
welding. The use of higher quality HIC-resistant steels can reduce the likelihood of SOHIC. Tests
have shown that these steels generally have a higher hydrogen flux threshold for SOHIC than
conventional steels, but SOHIC would still occur in these steels if that threshold was exceeded.
corrosion in an aqueous alkaline environment containing H2S, CO2, and tensile stress. It typically
occurs in non-stress relieved carbon steels. In as-welded steels, cracks typically propagate parallel
to the weld in adjacent base metals but can also occur in the weld deposits or heat-affected zones.
ASCC can occur over a wide range of temperatures, but susceptibility appears to increase as
temperature rises.
ASCC can occur in a variety of steels. Tests have indicated there is no significant
correlation between susceptibility to ASCC and steel properties, since the metal hardness has no
relation to ASCC. Susceptibility to ASCC does have correlation to temperature and tensile stress
H-58
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
levels. Therefore, a way to effectively control ASCC is post welding heat treatment and proper
temperatures, and an aqueous chloride environment. The presence of dissolved oxygen can
increase the propensity for cracking. Tests have shown that increasing temperatures can increase
the susceptibility to cracking. Increasing levels of chloride increase the likelihood of cracking as
well.
Cl SCC usually occurs in 300 series stainless steels. The use of resistant materials such as
duplex stainless steels and nickel-based alloys can help reduce the likelihood of Cl SCC. Duplex
stainless steels are more resistant than 300 series stainless steels but are still susceptible. Nickel-
based alloys are highly resistant, but not immune. Designs should be adjusted so that there are no
equipment should undergo PWHT in accordance with API RP 945. The use of solid or clad
stainless steel, Alloy 400 or other corrosion resistant alloys should be considered in place of carbon
steel.
Amine Stress Corrosion Cracking is caused by a combination of tensile stress and corrosion
in aqueous alkanolamine systems used to remove/absorb H2S and/or CO2 and their mixtures from
various gas and liquid hydrocarbon streams. Tests have shown that increasing temperatures can
increase the susceptibility to Amine Stress Corrosion Cracking. Cracking is more likely to occur
H-59
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
in lean MEA and DEA services but is also found in most amines, including MDEA and DIPA.
Cracking can also occur in non-PWHT’d piping and equipment as a result exposure to steamout
and to short-term amine carryover. To prevent Amine Stress Corrosion Cracking, all carbon steel
welds in piping and equipment should undergo PWHT in accordance with API RP 945. The use
of solid or clad stainless steel, Alloy 400 or other corrosion resistant alloys should be considered
results in the accelerated mechanical removal of surface material. Erosion-corrosion is the term
used when corrosion processes contribute to the erosion, such as when metal surfaces are exposed
to oxidating environments. All types of equipment exposed to moving fluids are subject to this
mechanism. Methods of mitigation include increasing pipe diameter to reduce fluid velocity,
increasing the wall thickness, using more corrosion resistant alloys, installation of cathodic
unstable fluid flow results in cracking of the material. The affected units or equipment include heat
exchanger tubes which may be susceptible to vortex shedding or safety relief valves which are
subject to chatter and premature pop-off. Mitigation strategies for vibration-induced fatigue
include the addition of anchors or dampening equipment to lessen the vibration or the removal of
the source of vibration entirely. Material upgrades are not usually a solution for this mechanism.
H-60
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
9.2.3. Cavitation
This mechanism is a form of erosion that occurs when fluid movement from low to high
pressure regions result in the formation and instantaneous collapse of tiny vapor bubbles. This
causes severe localized impact damage which debilitates the mechanical integrity of the
equipment. This phenomenon is most often found in pump casings and impellers where the
available net pressure suction head (NPSH) is inadequate. Strategies to prevent or mitigate
cavitation include the avoidance of conditions that allow the absolute pressure of the fluid to fall
below its vapor pressure or the usage of stronger, more corrosion resistant alloys. Streamlining the
flow path to reduce turbulence or decreasing the fluid velocities are examples of ways to avoid
conditions where cavitation may occur. Materials with high toughness will be better able to
withstand the high local pressures and impacts of the collapsing bubbles.
by dissolved salts, gases, organic compounds, or microbiological activity present in the cooling
water. This mechanism is a concern for heat exchangers using cooling water as their utility stream,
along with cooling towers. Mitigation strategies include the proper treatment of the cooling water
systems and improving the metallurgy so that it is resistant to waters with high chloride content,
low velocities, high process temperatures, or poorly maintained water chemistry. Cooling water
should be on the tube side of heat exchangers to minimize stagnant areas where there is a high risk
(H2CO3) and lowers the pH of the water, promoting an environment with high risk of corrosion.
H-61
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
This form of corrosion is generally weaker, so the only affected materials are carbon steel and low
alloy steels. Effluent gas streams of the shift converters in hydrogen plants and overhead systems
of regenerators within CO2 removal plants are examples of areas subjected to CO2 corrosion.
Mitigation strategies include Increasing the condensate pH to above 6 in steam condensate systems
or the usage of 300 Series, 400 Series, or duplex SS for the material selection as they are highly
dioxide, sulfur trioxide, and hydrogen chloride within the combustion products. At low enough
temperatures, these gases and the water vapor in the flue gas will condense to form sulfurous acid,
sulfuric acid, and hydrochloric acid which can lead to severe corrosion. Carbon steel, low alloy
steels, and 300 series SS are the most commonly affect materials. Mitigation strategies include
maintaining the metallic surfaces at the back end of the boiler fired heaters above the temperatures
of sulfuric acid dewpoint corrosion. The use of 300 series SS in feedwater heaters should be
the loss in ductility of high strength steels. Ultimately this leads to brittle cracking of the material.
The affected materials include carbon steel, 400 Series SS, Precipitation Hardenable (PH) SS, and
certain high strength nickel-based alloys. Bolts and springs made of high strength steel are very
susceptible to hydrogen embrittlement. Alloys which have a tensile strength of higher than 150 ksi
can absorb hydrogen during electroplating and crack. Other areas of concern would be carbon steel
piping and vessels in wet H2S services in amine, hydroprocessing, and sour water units. The
H-62
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
prevention and mitigation strategies include the usage of lower strength steels and PWHT to
temper the microstructure, improve ductility, and reduce residual stresses and hardness. Another
strategy would be to apply protective linings, SS claddings, or weld overclays to prevent surface
on carbon steel in amine treating processes. The corrosion is not caused by the amine itself, but
results from dissolved acid gases, amine degradation products, Heat Stable Amine Salts, and
other containments. Mitigation strategies included upgrading from carbon steel to 300 Series SS
or other corrosion resistant materials when possible. The most effective way to control corrosion
is the proper operation of the amine system with particular attention to acid gas loading.
of high temperature sulfide corrosion at temperatures above about 260°C. The operating
temperature of the syngas feed is very low (<65°C), therefore this corrosion mechanism will not
CO2, as opposed to other units that remove hydrogen sulfide or mixtures of hydrogen sulfide (14).
This is because hydrogen sulfide forms a protective iron sulfide scales on carbon steel.
Nevertheless, carbon steel has been widely used in locations with mild processing conditions and
low acid gas concentration, such as lean amine streams. This is due to its affordability and
H-63
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
relatively high strength in comparison to other materials of choice. Thus, ASTM A106 Grade B
carbon steel was selected for these streams. To reduce chances of cracking or corrosion in carbon
steel piping, the velocity of amine streams is recommended to be kept below 1.8 m/s (14). For
MDEA units, PWHT is also recommended for all carbon steel equipment exposed to amine service
temperature of the stream being 113.6°C in the base case. Killed carbon steel is steel manufactured
by a specific process to reduce voids in the material where hydrogen can collect and react to form
hydrogen gas and cause hydrogen blisters or hydrogen induced cracking. Kill carbon steel is more
of high corrosion rates due to their high strength and corrosion resistance over a wide range of
operating conditions (14). Types of stainless steel used in literature and historically for MDEA
units were ASTM A358 Type 304L and Type 316L stainless steel. Stainless steel was thus used
for regions of the process that are more prone to corrosion, such as areas with a high acid gas
loading, high velocity, vapour flashing, two-phase flow, and operating temperatures well above
110°C. Type 316L stainless steel has higher corrosion resistance in chloride containing
environments, and was selected over Type 304L stainless steel for areas of the process that
circulated process water or cooling water, which had a high chance of containing trace amounts of
chlorides.
H-64
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
H-65
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
List of References
1. The American Society of Mechanical Engineers. ASME Code for Pressure Piping.
2. Ulrich, Gael D. and Vasudevan, Palligarnai T. Chemical Engineering Process Design and
Economics: A Practical Guide (Second Edition). Durham : Process (Ulrich) Publishing, 2004. 0-
97087683-2-3.
4. Pick, W. Pipelines, Flow and Line Sizing. [Document] Edmonton : Ch E 464 Winter 2018 -
5. Engineering Toolbox. Ratios of Specific Heat of Gases. Engineering Toolbox. [Online] 2003.
6. Church, Len. Line Sizing. [Document] Edmonton : CH E 465 Winter 2019 - Tutorial 12 -
7. KLM Technology Group. Piping Hydraulics Fluid Flow - Line Sizing and Material
8. Ludwig, Ernest E. Applied Process Design for Chemical and Petrochemical Plants. s.l. :
H-66
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Fundamentals of Fluid Mechanics, Sixth Edition. s.l. : John WIley & Sons, Inc., 2009.
12. The American Society of Mechanical Engineers. Stainless Steel Pipe. [Standard] New
13. The American Society of Mechanical Engineers. Welded and Seamless Wroght Steel Pipe.
15. American Petroleum Institute. Damage Mechanisms Affecting Fixed Equipment in the
16. Glocal CCS Institute. Material Selection for Amine Environments. Global CCS Institute.
materials-selection-ccs-systems/73-material-selection-amine-environments.
17. Corrosion and Materials Selection for Amine Service. Rennie, S. s.l. : Materials Forum,
18. Predicting and Mitigating Corrosion in Amine Units. Jones, Clayton E., et al. Oklahoma :
H-67
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
19. Perry, Robert H and Green, Don W. Perry's Chemical Engineers' Handbook. 8th. New
20. Engineering Data Book. Gas Processors Suppliers Association. Tulsa : s.n., 2004, Vol. 1
and 2.
21. A Procedure for Preliminary Estimate. Brown, R. s.l. : Chem. Eng., 1978, Vol. 85.
22. Process Heat Transfer. Kern, D. Q. New York : McGraw-Hill Book Company, Inc., 1950.
23. Production & Processing Facilities Tip of the Month. PetroSkills|John M. Campbell. 2015.
H-68
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
guideline provided by Donald Quentin Kern in Process Heat Transfer (1950) for the design of a
heat exchanger was followed. ASME Boiler & Pressure Vessel Code Section VIII Division 1,
ASME B31.3 Process Piping, and Standards of Tubular Exchanger Manufacturers Association
As part of the 125% capacity increase, an additional heat exchanger, E-85A/B, was
proposed to increase the cooling of the lean amine stream as it enters the CO2 Absorber. A
completed design specification sheet for the heat exchanger is included with calculations and
Table of Contents
1. Preliminary Heat Exchanger Design Considerations .............................................................. I-1
2. Heat Exchanger Type .............................................................................................................. I-2
3. Fouling and Corrosion Concerns ............................................................................................ I-2
3.1. Placement of Fluid........................................................................................................... I-2
3.2. Material Specification ..................................................................................................... I-3
3.3. Fluid Flow ....................................................................................................................... I-3
4. Calculations............................................................................................................................. I-3
4.1. Process Conditions .......................................................................................................... I-3
4.1. Heat Balance.................................................................................................................... I-4
4.2. True Temperature Difference .......................................................................................... I-5
4.3. Iteration Method .............................................................................................................. I-6
4.3.1. Tube Side: Film Coefficient Calculation................................................................... I-7
4.3.2. Tube Side: Pressure Drop Calculation ...................................................................... I-9
4.3.3. Shell Side: Film Coefficient Calculation................................................................... I-9
i
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
ii
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
I-1
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
ability of the tower to absorb CO2 from the inlet Syngas stream.
Carbonic avid corrosion must also be considered.
Cooling water will not be completely rid of
contaminants/particles when circulated throughout the process.
Fouling This can lead to scaling in the tube walls and cause fouling.
Cooling water will be passed on the tube side as this side is
easier to clean.
Research PSV
Safety
requirements.
Potential health effects on personnel exposed to MDEA. Vessel
Risk
could be over-pressurized by upstream lean amine pump.
Type of
Heat CEU
Exchanger
and kettle reboilers depending on the service needed. A shell and tube heat exchanger was chosen
since its wide variety can cater to the specific needs of the lean amine and cooling water heat
exchange. To mitigate thermal stress and to allow for maintenance, removable U-tube bundles
were chosen. Based on the temperatures desired, the number of tube and shell passes is determined,
and the type of heat exchanger specified. Using the analysis outlined below, the 2-4 shell and tube
heat exchanger was chosen which was achieved by using two 1-2 CEU shell and tube heat
exchanger.
Flash Stripper and cooling water. The lean amine must be cooled before entering the CO2 Absorber
to improve absorption. Cooling water will be placed on the tube side of the heat exchanger due to
I-2
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
fouling concerns. This is because of the mineral content of the cooling water and the tendency of
scaling from cooling water use. Since the lean amine is less of a fouling concern, it will be placed
in the shell.
Mechanisms Affecting Fixed Equipment in the Refining Industry. The mechanisms considered
include amine corrosion, amine stress corrosion cracking, and carbon dioxide corrosion. However,
since the lean amine has low carbon dioxide content, carbon steel will suffice for the shell side.
Stainless steel was chosen for the tubes to account for increased mineral content of the water that
could cause corrosion and to combat the effects of the contacting lean amine. Even if stainless
steel is more expensive, this will make the tubes more resistant to corrosion.
turbulence will cause localized thickness losses. On the other hand, lower velocities result in
stagnant fluids which encourage fouling. Due to the effects of flow on the fouling and corrosion
mechanisms involved, the velocities were calculated and verified to be in the acceptable range.
4. Calculations
4.1. Process Conditions
In this heat exchanger, the lean mine is the hot fluid while cooling water is the cold fluid.
English Engineering Units will be used in this analysis to be consistent with the procedure and
correlations provided by Kern (1950). The final parameters will be converted to SI Units. The
I-3
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Note that these properties are taken at the average temperature of each fluid since temperatures at
𝑄 = 𝑊𝐶(𝑇1 − 𝑇2 ) = 𝑤𝑐(𝑡2 − 𝑡1 )
I-4
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
There is minimal discrepancy between the two fluid duties. The simulated value will be used for
design.
(𝑇1 − 𝑡2 ) − (𝑇2 − 𝑡1 )
𝐿𝑀𝑇𝐷 =
(𝑇 − 𝑡2 )
𝑙𝑛 1
(𝑇2 − 𝑡1 )
𝑇1 − 𝑇2
𝑅=
𝑡2 − 𝑡1
𝑡2 − 𝑡1
𝑆=
𝑇1 − 𝑡1
𝛥𝑡 = 𝐿𝑀𝑇𝐷 × 𝐹𝑇
LMTD °F 13.49
R - 0.48
S - 0.69
Correction Factor, FT - 0.74
True Temperature Difference, Δt °F 9.98
However, since the correction factor is below 0.75, the desired heat duty will be difficult to
achieve in a 1-2 shell and tube heat exchanger. Considering a 2-4 exchanger, the new values are:
LMTD °F 13.49
R - 0.48
S - 0.69
Correction Factor, FT - 0.96
True Temperature Difference, Δt °F 12.88
I-5
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Given the heat duty required for this service, an exchanger with 2 shell passes and 4 tube passes
may be too large. It is good practice to design two smaller units than one large exchanger. For
this reason, two 1-2 heat exchangers will be designed and connected in series. The total heat
a) Assume a tentative overall heat transfer coefficient, UD and compute the total surface
Initial tube characteristics are assumed, and the number of tubes calculated as:
𝐴
𝑁𝑇 =
𝜋𝐷𝑜 𝐿
BWG - 11
Outside Diameter, Do in 0.75
Inside Diameter, Di in 0.51
Tube Wall Thickness, Δx in 0.12
Length, L ft 16
Number of Passes, n - 2
Pitch (Square), PT in 1.00
Clearance between tubes, C' in 0.25
Flow area per tube, a't in2 0.204
Number of Tubes, NT - 1392
I-6
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
b) Assume a number of tube passes for the pressure drop allowed. Select an exchanger for
As stated, the heat exchanger will have 2 tube passes. For a 0.75 in tube outside diameter
The performance calculation for the film coefficients starts with the tube side first. If the film
coefficient is greater than UD and the pressure drop is not exceeded, analysis moves on to the
shell side.
shell side. Therefore, cooling water properties will be used for tube side calculations and lean
𝑁𝑡 𝑎′𝑡
𝑎𝑡 =
144𝑛
I-7
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
𝑤
𝐺𝑡 =
𝑎𝑡
𝐷𝑖 𝐺𝑡
𝑅𝑒𝑡 =
µ
The factor for heat transfer, jH, is obtained from Kern (1950). Since the properties are taken at an
average temperature, no correction factors will be necessary. The heat transfer coefficient is
determined as:
𝑘 𝑐µ 1
ℎ𝑖 = 𝑗𝐻 ( )3
𝐷𝑖 𝑘
𝐷𝑖
ℎ𝑖𝑜 = ℎ𝑖
𝐷𝑜
Since the calculated coefficient is higher than UD, analysis can move on to the pressure drop.
I-8
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
𝑓𝐺𝑡 2 𝐿𝑛
∆𝑃𝑡 =
5.22 × 1010 𝐷𝑖 𝑠
Using the tube mass velocity, the term V2/2g’ is obtained and
4𝑛𝑉 2
∆𝑃𝑟 =
𝑠2𝑔′
The total pressure drop for 2 tube passes is 1.65 psi. For 4 tube passes, the pressure drop is 3.3
psi.
𝐼𝐷 × 𝐶′𝐵
𝑎𝑠 =
144𝑃𝑇
I-9
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
𝑊
𝐺𝑠 =
𝑎𝑠
𝐷𝑒 𝐺𝑠
𝑅𝑒𝑠 =
µ
Where De is the equivalent diameter. The factor for heat transfer, jH, is obtained from Kern
(1950). Since the properties are taken at an average temperature, no correction factors will be
𝑘 𝑐µ 1
ℎ𝑜 = 𝑗𝐻 ( )3
𝐷𝑒 𝑘
12𝐿
𝑁+1=
𝐵
I-10
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
𝑓𝐺𝑠 2 𝐷𝑒 (𝑁 + 1)
∆𝑃𝑠 =
5.22 × 1010 𝐷𝑒 𝑠
The pressure drop for 1 shell pass is 2.93 psi. For 2 shell passes, the shell side pressure drop is
5.86 psi.
Since the film coefficient and pressure drop for each side are satisfactory, iteration is concluded.
ℎ𝑖𝑜 ℎ𝑜
𝑈𝑐 =
ℎ𝑖𝑜 + ℎ𝑜
water respectively, the resistance from the tube wall, Rd,w, is also considered.
∆𝑥
𝑅𝑑,𝑤 =
𝑘
I-11
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
𝑈𝑐 − 𝑈𝐷
𝑅𝑑 =
𝑈𝑐 𝑈𝐷
Since the actual dirt factor is greater than required, the designed heat exchanger is sufficient for
service.
1 1 1
= + + 𝑅𝑑
𝑈𝐷 ℎ𝑜 ℎ𝑖𝑜
pressure and temperature are laid out in the specification sheet below. Design conditions were
determined using ASME Code Section VIII Division 1 and ASME B31.3 Process Piping.
I-12
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
REV DATE BY
0 03/23/2019 Nympha Escobar
OKANE ENGINEERING
I-13
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
List of References
1. Process Heat Transfer. Kern, D. Q. New York : McGraw-Hill Book Company, Inc., 1950.
3. ASME Boiler & Pressure Vessel Code. The Americal Society of Mechanical Engineers.
4. ASME B31.3 Process Piping. The Americal Society of Mechanical Engineers. New York :
Petroleum Institute. Washington : API Publishing Services, 2010, Vol. Second Edition. API RP
571.
I-14
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Appendix J: Economics
Description
This appendix contains all the information relating to the project economics, and outlines
the detailed calculations and assumptions made to obtain the fixed capital expenditure, operating
costs, discounted cash flows, and sensitivity analyses. Unless otherwise specified, all prices and
Table of Contents
1. Economic Assumptions ......................................................................................................... J-1
2. Fixed Capital Expenditure ..................................................................................................... J-1
2.1. Equipment Purchase and Bare Module Costs ................................................................ J-1
2.1.1. Lean/Rich Amine Exchanger E-81C ........................................................................ J-2
2.1.2. Lean Amine Cooler E-85A/B ................................................................................... J-4
2.1.3. Reflux Vessel C-83 .................................................................................................. J-6
2.1.4. Absorber Overhead K.O. Drum C-87 ...................................................................... J-7
2.2. DFL Factors .................................................................................................................... J-8
2.3. Total Fixed Capital Expenditure .................................................................................... J-1
3. Working Capital Expenditure ................................................................................................ J-2
4. Operating Costs ...................................................................................................................... J-3
4.1. Onstream Time ............................................................................................................... J-3
4.2. Operating Labour ........................................................................................................... J-3
4.3. Utilities ........................................................................................................................... J-4
4.1. Remaining Expenses ...................................................................................................... J-6
5. Discounted Cash Flows.......................................................................................................... J-8
6. Sensitivity Analyses ............................................................................................................. J-17
6.1. 112% Case .................................................................................................................... J-17
6.2. 125% Case .................................................................................................................... J-18
7. References ............................................................................................................................ J-19
i
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
1. Economic Assumptions
The economic analysis is based on the additional CO2 being produced from the base case
and assumes all of this extra CO2 is being sold to potential consumers around the Fort McMurray
region. It is also assumed that the infrastructure required to transport the CO2 is already in place.
From the discussions with the client, 50% of the CO2 produced on a molar basis is sent for tailings
treatment, which is a static value of approximately 594,000 mol/h or 26,000 kg/h. This amount of
CO2 being sent to tailings treatment is not accounted for in this analysis since it is only applied to
material and pressure factors. Figure J1 displays the purchase cost breakdown in the form of a pie
chart. The purchase costs, material factors, and pressure factors for the heat exchangers and drums
were obtained using Ulrich & Vasudevan costing charts, which are based on the US Gulf Coast
2004 pricing (1). These costs were adjusted to account for inflation and currency, resulting in an
appropriate value in $CAD for 2019. An exchange rate of 1.33 was used to convert from $USD to
$CAD (2). The target Chemical Engineering Plant Cost Index (CEPCI) used was 616.4 from
J-1
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Heat Exchangers,
Total Purchase
$.11 MM
Cost:
Vessels,
$.06 MM
Packing,
$.88 MM
125% capacity increase. The calculated heat exchange area is 595 m2. This is a flat plate heat
exchanger, so the equipment purchase cost is obtained from Figure 5.39 in Ulrich & Vasudevan:
This cost assumes the equipment uses carbon steel as the material and operates at relatively low
pressures. To adjust for material and pressure factors, a bare module factor must be applied. E-
J-2
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
81C uses stainless steel SS316 on both the shell and tube sides due to the corrosivity of the amine
solutions. From Table 5.39, the material factor for this exchanger is:
𝐹𝑀 = 3
Figure 5.37 is then used to obtain the pressure factor needed alongside the material factor to obtain
the bare module factor. The pressure factor of flat and spiral plate heat exchangers is 1 regardless
𝐹𝑃 = 1
Using the above material and pressure factors, and the bare module factor is obtained from Figure
5.38:
𝑎
𝐹𝐵𝑀 = 5.8
Applying this factor to the equipment purchase cost, the bare module cost of E-81C is calculated
as:
𝑎
𝐶𝐵𝑀 = 𝐶𝑃 ∙ 𝐹𝐵𝑀 = ($50,000)(5.8) = $290,000 𝑈𝑆𝐷, 𝑈𝑆𝐺𝐶, 2004
This value is then adjusted for time and currency factors to obtain the bare module cost today in
CAD. The target CEPCI is November 2018 with a value of 616.4, and the base is the January 2004
CEPCI of 400. The current conversion rate from USD to CAD is 1.33. Applying the time and
616.4
𝐶𝐵𝑀 = ($290,000 𝑈𝑆𝐷, 𝑈𝑆𝐺𝐶, 2004) ( ) (1.33) = $594,364 𝐶𝐴𝐷, 𝐴𝐵, 2018
400
J-3
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
The bare module factor must then be adjusted for DFL considerations. The detailed calculations
for this are contained in Section 1.2 DFL Factors. The bare module factor adjusted for DFL is
calculated to be:
𝑎
𝐹𝐵𝑀,𝐷𝐹𝐿 𝑎𝑑𝑗𝑢𝑠𝑡𝑒𝑑 = 11.07
Applying this DFL factor along with time and currency factors to the equipment purchase cost
𝑎 616.4
𝐶𝐵𝑀,𝑎𝑑𝑗𝑢𝑠𝑡𝑒𝑑 = 𝐶𝑃 ∙ 𝐹𝐵𝑀,𝐷𝐹𝐿 𝑎𝑑𝑗𝑢𝑠𝑡𝑒𝑑 = ($50,000)(11.07) ( ) (1.33)
400
cooling of the regenerated lean amine solution before it enters the C-80 CO2 Absorber. This
exchanger is designed as two TEMA designated CEU type shell and tube heat exchangers arranged
in series. CEU exchangers utilize a U-tube as the rear end head type. The total calculated heat
exchanger area is 815.41 m2. The exchanger is split into two equal areas of 408 m2 each and the
cost of each area is added together to obtain the cost of E-85A/B. From Figure 5.36 in Ulrich &
E-85A/B uses carbon steel (CS) on the shell side and stainless steel (SS316) on the tube side. From
𝐹𝑀 = 1.7
J-4
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
E-80 operates using a shell side inlet pressure of 4099 kPa or 40.99 barg and a tube side inlet
pressure of 448 kPa or 4.48 barg, so the heat exchanger operates at high pressure on the shell side
𝐹𝑃 = 1.13
Using the above material and pressure factors, and the bare module factor is obtained from Figure
5.38:
𝑎
𝐹𝐵𝑀 = 4.5
Applying this factor to the equipment purchase cost, the bare module cost of E-85A/B is calculated
as:
𝑎
𝐶𝐵𝑀 = 𝐶𝑃 ∙ 𝐹𝐵𝑀 = (60,000)(4.5) = $270,000 𝑈𝑆𝐷, 𝑈𝑆𝐺𝐶, 2004
Applying the time and currency factors gives a bare module cost of:
616.4
𝐶𝐵𝑀 = ($270,000 𝑈𝑆𝐷, 𝑈𝑆𝐺𝐶, 2004) ( ) (1.33) = $553,373 𝐶𝐴𝐷, 𝐴𝐵, 2018
400
𝑎
𝐹𝐵𝑀,𝐷𝐹𝐿 𝑎𝑑𝑗𝑢𝑠𝑡𝑒𝑑 = 8.64
Applying this DFL factor along with time and currency factors to the equipment purchase cost
𝑎 616.4
𝐶𝐵𝑀,𝑎𝑑𝑗𝑢𝑠𝑡𝑒𝑑 = 𝐶𝑃 ∙ 𝐹𝐵𝑀,𝐷𝐹𝐿 𝑎𝑑𝑗𝑢𝑠𝑡𝑒𝑑 = ($60,000)(8.64) ( ) (1.33)
400
J-5
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
replace the existing vessel to accommodate the 125% capacity increase. This is a vertically
oriented vessel with a height and inside diameter of 7.5 m and 2.5 m, respectively, calculated using
the Sauders Brown method. From Figure 5.44 in Ulrich & Vasudevan, the equipment purchase
cost is:
The material of this vessel is stainless steel SS 304L. Table 5.45 gives a material factor of:
𝐹𝑀 = 4
The reflux vessel operates with an inlet pressure of 24 kPa or 0.24 barg. Figure 5.45 gives a
𝐹𝑃 = 1.25
Using the above material and pressure factors, and the bare module factor is obtained from Figure
5.46:
𝑎
𝐹𝐵𝑀 = 11.2
Applying this factor to the equipment purchase cost, the bare module cost of C-83 is calculated as:
𝑎
𝐶𝐵𝑀 = 𝐶𝑃 ∙ 𝐹𝐵𝑀 = (38,000)(11.2) = $425,600 𝑈𝑆𝐷, 𝑈𝑆𝐺𝐶, 2004
Applying the time and currency factors gives a bare module cost of:
616.4
𝐶𝐵𝑀 = ($425,600 𝑈𝑆𝐷, 𝑈𝑆𝐺𝐶, 2004) ( ) (1.33) = $872,280 𝐶𝐴𝐷, 𝐴𝐵, 2018
400
J-6
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
𝑎
𝐹𝐵𝑀,𝐷𝐹𝐿 𝑎𝑑𝑗𝑢𝑠𝑡𝑒𝑑 = 23.25
Applying this DFL factor along with time and currency factors to the equipment purchase cost
𝑎 616.4
𝐶𝐵𝑀,𝑎𝑑𝑗𝑢𝑠𝑡𝑒𝑑 = 𝐶𝑃 ∙ 𝐹𝐵𝑀,𝐷𝐹𝐿 𝑎𝑑𝑗𝑢𝑠𝑡𝑒𝑑 = ($38,000)(23.25) ( ) (1.33)
400
and will replace the existing vessel to accommodate the 125% capacity increase. This is a vertically
oriented vessel with a GPSA calculated height and inside diameter of 4.8 m and 1.6 m,
respectively. From Figure 5.44 in Ulrich & Vasudevan, the equipment purchase cost is:
The material of this vessel is carbon steel. Table 5.45 gives a material factor of:
𝐹𝑀 = 1
The reflux vessel operates with inlet and outlet pressures of 3249 kPa or 32.49 barg. Figure 5.45
𝐹𝑃 = 2.8
Using the above material and pressure factors, and the bare module factor is obtained from Figure
5.46:
J-7
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
𝑎
𝐹𝐵𝑀 = 7.5
Applying this factor to the equipment purchase cost, the bare module cost of C-87 is calculated as:
𝑎
𝐶𝐵𝑀 = 𝐶𝑃 ∙ 𝐹𝐵𝑀 = (18,000)(7.5) = $135,000 𝑈𝑆𝐷, 𝑈𝑆𝐺𝐶, 2004
Applying the time and currency factors gives a bare module cost of:
616.4
𝐶𝐵𝑀 = ($135,000 𝑈𝑆𝐷, 𝑈𝑆𝐺𝐶, 2004) ( ) (1.33) = $276,687 𝐶𝐴𝐷, 𝐴𝐵, 2018
400
𝑎
𝐹𝐵𝑀,𝐷𝐹𝐿 𝑎𝑑𝑗𝑢𝑠𝑡𝑒𝑑 = 15.64
Applying this DFL factor along with time and currency factors to the equipment purchase cost
𝑎 616.4
𝐶𝐵𝑀,𝑎𝑑𝑗𝑢𝑠𝑡𝑒𝑑 = 𝐶𝑃 ∙ 𝐹𝐵𝑀,𝐷𝐹𝐿 𝑎𝑑𝑗𝑢𝑠𝑡𝑒𝑑 = ($18,000)(15.64) ( ) (1.33)
400
Exchanger. Table J3 summarizes all equipment costs accounted for DFL. The initial DFL and bare
module factors for each type of equipment are taken from Table 9-13 in Guthrie (1969) (4). Table
G2 provides the purchase cost and DFL summary for all pieces of equipment. Since Guthrie (1969)
does not provide DFL data for the IMTP random packing, an assumed factor of 0.05 was used. For
E-80, the basis factors for a shell and tube heat exchanger are chosen:
𝑐𝑠
𝐹𝐵𝑀 = 3.37
J-8
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
𝐷𝐹𝐿𝐺𝑢𝑡ℎ𝑟𝑖𝑒 = 0.63
These values use a basis of carbon steel material unadjusted for high pressure operations. Thus,
material and pressure adjustments must be made by first obtaining the bare module factor from
𝑎
𝐹𝐵𝑀 = 5.8
Using the above bare module factors, the material and pressure adjusted DFL factor is:
𝑎
𝐹𝐵𝑀 5.8
𝐷𝐹𝐿𝑈&𝑉 = 𝐷𝐹𝐿𝐺𝑢𝑡ℎ𝑟𝑖𝑒 × 𝑐𝑠 = 0.63 × = 1.08
𝐹𝐵𝑀 3.37
This is the DFL factor for the US Gulf Coast. Cumulative adjustments are then made to this
value. The DFL adjustment factors and percent applicabilities are shown in Table J2 below:
J-9
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
The first adjustment is the Alberta Greenfield factor to account for the effect of location:
= 1.36
The Fort McMurray factor is then added to account for the construction taking place in the Fort
McMurray region. This is due to the region being a busy industrial area with extensive amounts
of production traffic.
J-10
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
The operating facility factor is then added to adjust for the project being Brownfield. There will
The facility turnaround factor is then added to account for loss of labour productivity during a
turnaround. Since this is a unit revamp project, the chosen percent applicability was 75%:
The winter work factor is then added to account for the loss of labour productivity during the
Once the winter work adjustment has been added, the resultant factor is known as the total DFL
factor. The cumulative adjustments for the indirect project expenses will be performed next. The
DFL additions must be calculated, which is simply the difference between the DFL factor after
the winter work addition and the DFL taken from Ulrich & Vasudevan:
J-11
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
The next indirect expense is the scaffolding cost, which is required due to the increasingly strict
The next indirect expense is the cost of any miscellaneous items to be accounted for in the
project, which can include bottled water, coffee and lunch, or the construction of temporary
roads. Based on the estimated capital expenditure of our project being below $25 million CAD,
The final indirect expense item is the construction camp cost, which is included due to the facility
being in a relatively remote area. Since the project involves adding the equipment in modules, the
percent applicability is slightly less than 100%. The value chosen for the project is 80%.
This value represents the total DFL factor that accounts for both labour productivity and indirect
expenses, and is used to adjust the bare module factor for DFL:
𝑎 𝑎
𝐹𝐵𝑀,𝐷𝐹𝐿 𝑎𝑑𝑗𝑢𝑠𝑡𝑒𝑑 = 𝐹𝐵𝑀 + (𝐶𝑜𝑛𝑠𝑡𝑟𝑢𝑐𝑡𝑖𝑜𝑛 𝐶𝑎𝑚𝑝 − 𝐷𝐹𝐿𝑈&𝑉 ) = 6.2 + (6.36 − 1.08) = 11.07
It was assumed that demolition costs were not applicable for the DFL estimation in this project.
J-12
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
J-1
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
of $7.95 million. Applying the contingencies along, contractor fees, engineering fees, owner fees,
and startup costs gives a total fixed capital expenditure of $14.89 million. Guidelines from the
Electric Power Research Institute (EPRI) were referred to when determining the contingencies for
the project. Since the project involves the revamp of an existing, well known amine process already
in commercial use, the chosen process contingency was 0% (5). After discussions with Len
Church, the contractual fee was allocated at 7% of the total bare module cost. At this stage of the
project, only one P&ID has been developed and equipment specifications are considered to be at
the preliminary stage, so the project falls within the simplified category. Thus, the chosen project
contingency was 40% of the total module cost. The engineering or procurement expense was
prorated based on the estimated fixed capital expenditure of the project and was determined to be
18% of the total module cost plus project contingency. This percentage would be closer to 20% if
the estimated fixed capital was low at around $5 million and would be closer to 10% if the fixed
capital was high at around $50 million or over. The owner’s cost and the commissioning and
startup cost were allocated at 3% and 4% of the total module cost plus project contingency,
J-1
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Process Contingency $0
Engineering/Procurement $1.93
materials and spare parts inventory required to keep the facility in operation. The recommended
range for working capital expenditure was 10 to 20% of the fixed capital expenditure (1). Since
the CO2 Removal Unit is relatively small, and the 125% capacity redesign does not add a
significant number of equipment, the working capital is chosen to be 10% of the total fixed capital,
which in this case is $1.34 MM. This percentage would be closer to 20% or even 30% if the raw
materials inventory was included as part of the scope and is expensive, the process produces a
diverse range of products, or if the plant itself is constructed using cheap materials such as cast
iron or carbon steel (1) (6). The loss in amine solution due to operation is also minimal, which also
J-2
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
4. Operating Costs
This section includes the detailed calculations and assumptions done for the operating cost
estimation. Table J5 displays the breakdown of all operating cost components divided into direct,
indirect, and general expenses. Percentages from Ulrich & Vasudevan (2004) and
recommendations from Jamieson and Church (2015) were used to calculate the operating expenses
maintenance and cleaning purposes. This is the fraction of time that the plant is running at full
ℎ ℎ
𝑂𝑛𝑠𝑡𝑟𝑒𝑎𝑚 𝑇𝑖𝑚𝑒 = 0.92 × 8760 = 8059.2
𝑦𝑟 𝑦𝑟
Ulrich & Vasudevan (2004) was referenced to determined how many additional operators are
required per shift. Since a total of three additional heat exchangers are being added to the current
facility to facilitate the 125% capacity increase (one additional E-81 lean/rich amine exchanger
and E-85 which is two exchangers arranged in series), the number of additional operators per shift
J-3
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
is 0.15. Operators at CNRL work on a 7 day on 7 day off schedule, which translates into 24 shifts
per year when accounting for the annual four-week planned shutdown. Using an assumed operator
yearly salary of $100,000 CAD, the annual operating labour cost is:
𝑠ℎ𝑖𝑓𝑡𝑠 𝑜𝑝𝑒𝑟𝑎𝑡𝑜𝑟𝑠
𝑂𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔 𝐿𝑎𝑏𝑜𝑢𝑟 = 24 × 0.15 × $100,000 𝐶𝐴𝐷 = $360,000 𝐶𝐴𝐷
𝑦𝑒𝑎𝑟 𝑠ℎ𝑖𝑓𝑡
4.3. Utilities
Table J5 displays the utility cost data provided by CNRL. Steam, amine, natural gas, and
cooling water utility costs were provided by CNRL, but steam was not included to the unchanging
Since the additional power required for the pumps and compressor units are provided by the
electricity generated onsite, the following equation from Table 6.3 in Ulrich & Vasudevan (2004)
Where CS,u is the unit price of electricity and CS,f is the unit price of the fuel used to generate the
electricity, which is natural gas. CEPCI is the current cost index of November 2018 which is 616.4.
J-4
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Since CNRL is currently buying about 70MW off the Alberta power grid, the cost coefficients a
and b are taken as 0.00013 and 0.010, respectively from Table 6.3:
Table J6 summarizes the additional utility costs for each case. The makeup amine was calculated
by taking the MDEA mass flowrate of streams 37, 75, and 96 since they are exiting the unit. This
amount was found to be 0.00006% of the total MDEA mass flow rate of stream 86, which was the
same percentage used in the 112% and 125% capacity redesigns to estimate makeup amine
requirements.
Table J7 summarizes the additional makeup amine requirements for the utility cost estimation:
J-5
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Sample calculations for the additional utility costs for the 112% capacity increase are shown
below:
𝐴𝑑𝑑𝑖𝑡𝑖𝑜𝑛𝑎𝑙 𝑈𝑡𝑖𝑙𝑖𝑡𝑦 𝐶𝑜𝑠𝑡 = 𝑈𝑡𝑖𝑙𝑖𝑡𝑦 𝑃𝑟𝑖𝑐𝑒 × 𝐴𝑑𝑑𝑡𝑖𝑜𝑛𝑎𝑙 𝑈𝑡𝑖𝑙𝑖𝑡𝑦 𝑈𝑠𝑎𝑔𝑒 × 𝑂𝑛𝑠𝑡𝑟𝑒𝑎𝑚 𝑇𝑖𝑚𝑒
For electricity, the additional power required for the E-84 air cooler, G-81A/B, G-82A/B/C, G-
83A/B pumps and the K-100, K-101, K-102 compressors is 623 kW. The additional electricity
ℎ
𝐴𝑛𝑛𝑢𝑎𝑙 𝐸𝑙𝑒𝑐𝑡𝑟𝑖𝑐𝑖𝑡𝑦 𝐶𝑜𝑠𝑡 = $0.11/𝑘𝑊ℎ × 623 𝑘𝑊 × 8059.2 = $555,739 𝐶𝐴𝐷/𝑦𝑟
𝑦𝑟
The additional cooling water required to cool the E-80, E-83, and the three compressor stage
𝑚3 ℎ
𝐴𝑛𝑛𝑢𝑎𝑙 𝐶𝑜𝑜𝑙𝑖𝑛𝑔 𝑊𝑎𝑡𝑒𝑟 𝐶𝑜𝑠𝑡 = $0.07/𝑚3 × 46 × 8059.2 = $26,159 𝐶𝐴𝐷/𝑦𝑟
ℎ 𝑦𝑟
J-6
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
• Maintenance costs amount to 2% of the fixed capital, due to the low number of additional
• Indirect overhead costs amount to 60% of the sum of operating labour, supervisory labour, and
maintenance costs.
• Distribution and selling costs are 10% of the total manufacturing expense.
J-7
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Table J8: Operating Cost Summary for the 112% and 125% Capacity Increases
Expense 112% Case Annual Cost 125% Case Annual Cost
($MM) ($MM)
Fixed Capital $0 $13.42
Working Capital $0 $1.34
Total Capital $0 $14.76
Operating Labour $0 $0.36
Supervisory Labour $0 $0.05
Utilities $0.58 $1.24
Maintenance $0 $0.80
Operating Supplies $0 $0.12
Lab Charges $0 $0.05
Total Direct Expense $0.58 $2.63
Overhead $0 $0.73
Local Taxes $0 $0.27
Insurance $0 $0.13
Total Indirect Expense $0 $1.13
Administrative Costs $0 $0.18
Distribution and Selling $0.06 $0.38
Research and Development $0.03 $0.19
Total General Expense $0.09 $0.75
Total Operating Expense $0.67 $4.51
and IRR for each case. The discounted cash flow analysis for this project utilizes a corporate
discount rate of 15%, a hurdle rate of 20%, and a project life of 20 years. An inflation rate of 3%
and a provincial income tax rate of 27% was used. For the 125% cash flow analysis, the 2019 fiscal
values were used as the baseline despite the operations starting at 2022 as opposed to 2020, so the
estimation for this case may be less accurate than the 112% case. To account for this, a future
CEPCI value had to be assumed, which is very risky since the CEPCI depends on various economic
J-8
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
and societal factors and is therefore very unpredictable. The sample calculations for the 125%
capacity case during the initial investment and the first operating year are shown below:
This is the initial investment to the project made at year 0 and is presented as a negative or outwards
cash flow. The working capital is 10% of the fixed capital and is added as another negative cash
flow. The depreciated value during year 0 is equal to this initial investment.
= −$14,757,588
Where n is the project year. The manufacturing expense for the first operating year is:
J-9
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
= +$591,132
The capital cost allowance (CCA) is required to calculate the depreciated value for this year. The
CCA depreciation rate for Asset Class 43 is 15% for the first year and 30% for every subsequent
The depreciated value for every year following the initial investment is calculated using the
following formula:
𝐷𝑒𝑝𝑟𝑒𝑐𝑖𝑎𝑡𝑒𝑑 𝑉𝑎𝑙𝑢𝑒 = 𝐷𝑒𝑝𝑟𝑒𝑐𝑖𝑎𝑡𝑒𝑑 𝑉𝑎𝑙𝑢𝑒 𝑓𝑟𝑜𝑚 𝑃𝑟𝑒𝑣𝑖𝑜𝑢𝑠 𝑌𝑒𝑎𝑟 − 𝐶𝑎𝑝𝑖𝑡𝑎𝑙 𝐶𝑜𝑠𝑡 𝐴𝑙𝑙𝑜𝑤𝑎𝑛𝑐𝑒
Taxes can then be applied next. The annual taxable income is calculated using the formula:
J-10
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Since the taxable income for the first operating year is negative, no taxes will be applied:
𝑇𝑎𝑥𝑒𝑠𝑌𝑒𝑎𝑟 1 = $0
If the taxable income is positive, then the following formula is used to calculate the taxes using an
The cash flow after taxes is simply the original cash flow plus the taxes:
The discount factor used to calculate the discounted cash flows is obtained using the following
The discounted cash flow (DCF) is then calculated by multiplying the cash flow after taxes by the
discount rate:
J-11
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
The cumulative DCF can then be calculated using the following formula:
The cumulative DCF for year 0 is equal to the cash flow of that year. The cumulative DCF for year
1 is therefore:
J-12
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Table J9: Discounted NPV Cash Flow Table for 112% Case
Fixed Capital $0
Working Capital $0
Total Operating Expense $669,182
Revenue From CO2 Production Sales $1,860,608
Inflation Rate 3.00% NPV $6,641,451 NPV Positive
Discount Rate 15.00%
Tax Rate 27.00%
Cash Flow Analysis
Other Cash
Total Flows CCA Capital Cost Discounted
Calendar Revenue Depreciated Taxable Cash Flow Discount Cumulative
Year Fixed Capital Manufacturing (including Cash Flow Depreciation Allowance Taxes Cash Flow
Year From Sales Value Income After Taxes Factor DCF
Expense working Rate (CCA) (DCF)
Capital)
2019 0 $0 $0 $0 $0 $0 $0 0 1.000 $0 $0
2020 1 -$689,258 $0 $1,916,426 $1,227,168 $0 15% 0 1,227,168 -331,335 895,833 0.870 $778,985 $778,985
2021 2 -$709,935 $0 $1,973,919 $1,263,983 $0 30% 0 1,263,983 -341,275 922,708 0.756 $697,700 $1,476,685
2022 3 -$731,233 $0 $2,033,136 $1,301,903 $0 30% 0 1,301,903 -351,514 950,389 0.658 $624,896 $2,101,581
2023 4 -$753,170 $0 $2,094,130 $1,340,960 $0 30% 0 1,340,960 -362,059 978,901 0.572 $559,690 $2,661,271
2024 5 -$775,765 $0 $2,156,954 $1,381,189 $0 30% 0 1,381,189 -372,921 1,008,268 0.497 $501,287 $3,162,558
2025 6 -$799,038 $0 $2,221,663 $1,422,624 $0 30% 0 1,422,624 -384,109 1,038,516 0.432 $448,979 $3,611,537
2026 7 -$823,010 $0 $2,288,313 $1,465,303 $0 30% 0 1,465,303 -395,632 1,069,671 0.376 $402,129 $4,013,666
2027 8 -$847,700 $0 $2,356,962 $1,509,262 $0 30% 0 1,509,262 -407,501 1,101,761 0.327 $360,168 $4,373,834
2028 9 -$873,131 $0 $2,427,671 $1,554,540 $0 30% 0 1,554,540 -419,726 1,134,814 0.284 $322,585 $4,696,419
2029 10 -$899,325 $0 $2,500,501 $1,601,176 $0 30% 0 1,601,176 -432,318 1,168,859 0.247 $288,924 $4,985,343
2030 11 -$926,305 $0 $2,575,516 $1,649,212 $0 30% 0 1,649,212 -445,287 1,203,924 0.215 $258,775 $5,244,118
2031 12 -$954,094 $0 $2,652,782 $1,698,688 $0 30% 0 1,698,688 -458,646 1,240,042 0.187 $231,773 $5,475,891
2032 13 -$982,717 $0 $2,732,365 $1,749,648 $0 30% 0 1,749,648 -472,405 1,277,243 0.163 $207,588 $5,683,479
2033 14 -$1,012,198 $0 $2,814,336 $1,802,138 $0 30% 0 1,802,138 -486,577 1,315,561 0.141 $185,926 $5,869,405
2034 15 -$1,042,564 $0 $2,898,766 $1,856,202 $0 30% 0 1,856,202 -501,175 1,355,028 0.123 $166,525 $6,035,930
2035 16 -$1,073,841 $0 $2,985,729 $1,911,888 $0 30% 0 1,911,888 -516,210 1,395,678 0.107 $149,149 $6,185,079
2036 17 -$1,106,056 $0 $3,075,301 $1,969,245 $0 30% 0 1,969,245 -531,696 1,437,549 0.093 $133,585 $6,318,665
2037 18 -$1,139,238 $0 $3,167,560 $2,028,322 $0 30% 0 2,028,322 -547,647 1,480,675 0.081 $119,646 $6,438,311
2038 19 -$1,173,415 $0 $3,262,587 $2,089,172 $0 30% 0 2,089,172 -564,076 1,525,095 0.070 $107,161 $6,545,472
2039 20 -$1,208,617 $0 $3,360,464 $2,151,847 $0 30% 0 2,151,847 -580,999 1,570,848 0.061 $95,979 $6,641,451
J-13
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Table J10: Discounted IRR Cash Flow Table for 112% Case
Fixed Capital $0
Working Capital $0
Total Manufacturing Expense $669,182
Revenue From CO2 Production Sales $1,860,608
Inflation Rate 3.00% NPV $0 NPV Zero
Discount Rate 90745139682.42%
Tax Rate 27.00%
Cash Flow Analysis
Other Cash
Total Flows Capital Cost Discounted
Calendar Revenue Depreciated CCA Depreciation Taxable Cash Flow Discount Cumulative
Year Fixed Capital Manufacturing (including Cash Flow Allowance Taxes Cash Flow
Year From Sales Value Rate Income After Taxes Factor DCF
Expense working (CCA) (DCF)
Capital)
2019 0 $0 $0 $0 $0 $0 $0 0 1.000 $0 $0
2020 1 -$689,258 $0 $1,916,426 $1,227,168 $0 15% 0 1,227,168 -331,335 895,833 0.000 $0 $0
2021 2 -$709,935 $0 $1,973,919 $1,263,983 $0 30% 0 1,263,983 -341,275 922,708 0.000 $0 $0
2022 3 -$731,233 $0 $2,033,136 $1,301,903 $0 30% 0 1,301,903 -351,514 950,389 0.000 $0 $0
2023 4 -$753,170 $0 $2,094,130 $1,340,960 $0 30% 0 1,340,960 -362,059 978,901 0.000 $0 $0
2024 5 -$775,765 $0 $2,156,954 $1,381,189 $0 30% 0 1,381,189 -372,921 1,008,268 0.000 $0 $0
2025 6 -$799,038 $0 $2,221,663 $1,422,624 $0 30% 0 1,422,624 -384,109 1,038,516 0.000 $0 $0
2026 7 -$823,010 $0 $2,288,313 $1,465,303 $0 30% 0 1,465,303 -395,632 1,069,671 0.000 $0 $0
2027 8 -$847,700 $0 $2,356,962 $1,509,262 $0 30% 0 1,509,262 -407,501 1,101,761 0.000 $0 $0
2028 9 -$873,131 $0 $2,427,671 $1,554,540 $0 30% 0 1,554,540 -419,726 1,134,814 0.000 $0 $0
2029 10 -$899,325 $0 $2,500,501 $1,601,176 $0 30% 0 1,601,176 -432,318 1,168,859 0.000 $0 $0
2030 11 -$926,305 $0 $2,575,516 $1,649,212 $0 30% 0 1,649,212 -445,287 1,203,924 0.000 $0 $0
2031 12 -$954,094 $0 $2,652,782 $1,698,688 $0 30% 0 1,698,688 -458,646 1,240,042 0.000 $0 $0
2032 13 -$982,717 $0 $2,732,365 $1,749,648 $0 30% 0 1,749,648 -472,405 1,277,243 0.000 $0 $0
2033 14 -$1,012,198 $0 $2,814,336 $1,802,138 $0 30% 0 1,802,138 -486,577 1,315,561 0.000 $0 $0
2034 15 -$1,042,564 $0 $2,898,766 $1,856,202 $0 30% 0 1,856,202 -501,175 1,355,028 0.000 $0 $0
2035 16 -$1,073,841 $0 $2,985,729 $1,911,888 $0 30% 0 1,911,888 -516,210 1,395,678 0.000 $0 $0
2036 17 -$1,106,056 $0 $3,075,301 $1,969,245 $0 30% 0 1,969,245 -531,696 1,437,549 0.000 $0 $0
2037 18 -$1,139,238 $0 $3,167,560 $2,028,322 $0 30% 0 2,028,322 -547,647 1,480,675 0.000 $0 $0
2038 19 -$1,173,415 $0 $3,262,587 $2,089,172 $0 30% 0 2,089,172 -564,076 1,525,095 0.000 $0 $0
2039 20 -$1,208,617 $0 $3,360,464 $2,151,847 $0 30% 0 2,151,847 -580,999 1,570,848 0.000 $0 $0
J-14
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Table J11: Discounted NPV Cash Flow Table for 125% Case
Fixed Capital $14,891,485
Working Capital $1,489,148
Total Operating Expense $4,753,658
Revenue From CO2 Production Sales $5,085,222
Inflation Rate 3.00% NPV -$13,954,568 NPV Negative
Discount Rate 15.00%
Tax Rate 27.00%
Cash Flow Analysis
Other Cash
Total Flows CCA Capital Cost
Calendar Revenue Depreciated Taxable Cash Flow After Discount Discounted
Year Fixed Capital Manufacturing (including Cash Flow Depreciation Allowance Taxes Cumulative DCF
Year From Sales Value Income Taxes Factor Cash Flow (DCF)
Expense working Rate (CCA)
Capital)
2020 0 -14,891,485 0 -1,489,148 0 -16,380,633 14,891,485 -16,380,633 1.000 -$16,380,633 -$16,380,633
2021 1 -4,896,267 0 5,237,779 341,512 12,657,762 15% 2,233,723 -1,892,211 0 341,512 0.870 $296,967 -$16,083,667
2022 2 -5,043,155 0 5,394,912 351,757 8,860,434 30% 3,797,329 -3,445,572 0 351,757 0.756 $265,979 -$15,817,688
2023 3 -5,194,450 0 5,556,760 362,310 6,202,303 30% 2,658,130 -2,295,820 0 362,310 0.658 $238,224 -$15,579,464
2024 4 -5,350,284 0 5,723,462 373,179 4,341,612 30% 1,860,691 -1,487,512 0 373,179 0.572 $213,366 -$15,366,097
2025 5 -5,510,792 0 5,895,166 384,374 3,039,129 30% 1,302,484 -918,109 0 384,374 0.497 $191,102 -$15,174,995
2026 6 -5,676,116 0 6,072,021 395,906 2,127,390 30% 911,739 -515,833 0 395,906 0.432 $171,161 -$15,003,834
2027 7 -5,846,399 0 6,254,182 407,783 1,489,173 30% 638,217 -230,434 0 407,783 0.376 $153,301 -$14,850,534
2028 8 -6,021,791 0 6,441,807 420,016 1,042,421 30% 446,752 -26,736 0 420,016 0.327 $137,304 -$14,713,230
2029 9 -6,202,445 0 6,635,062 432,617 729,695 30% 312,726 119,890 -32,370 400,246 0.284 $113,775 -$14,599,455
2030 10 -6,388,518 0 6,834,114 445,595 510,786 30% 218,908 226,687 -61,205 384,390 0.247 $95,015 -$14,504,440
2031 11 -6,580,174 0 7,039,137 458,963 357,550 30% 153,236 305,727 -82,546 376,417 0.215 $80,908 -$14,423,531
2032 12 -6,777,579 0 7,250,311 472,732 250,285 30% 107,265 365,467 -98,676 374,056 0.187 $69,914 -$14,353,618
2033 13 -6,980,906 0 7,467,820 486,914 175,200 30% 75,086 411,828 -111,194 375,720 0.163 $61,065 -$14,292,553
2034 14 -7,190,334 0 7,691,855 501,521 122,640 30% 52,560 448,961 -121,220 380,302 0.141 $53,748 -$14,238,805
2035 15 -7,406,044 0 7,922,611 516,567 85,848 30% 36,792 479,775 -129,539 387,028 0.123 $47,564 -$14,191,241
2036 16 -7,628,225 0 8,160,289 532,064 60,094 30% 25,754 506,310 -136,704 395,360 0.107 $42,250 -$14,148,991
2037 17 -7,857,072 0 8,405,098 548,026 42,065 30% 18,028 529,998 -143,099 404,926 0.093 $37,628 -$14,111,363
2038 18 -8,092,784 0 8,657,251 564,467 29,446 30% 12,620 551,847 -148,999 415,468 0.081 $33,572 -$14,077,791
2039 19 -8,335,567 0 8,916,968 581,401 20,612 30% 8,834 572,567 -154,593 426,808 0.070 $29,990 -$14,047,801
2040 20 -8,585,634 1,489,148 9,184,477 2,087,991 14,428 30% 6,184 2,081,808 -562,088 1,525,903 0.061 $93,233 -$13,954,568
J-15
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Table J12: Discounted IRR Cash Flow Table for 125% Case
Fixed Capital $14,891,485
Working Capital $2,233,723
Total Manufacturing Expense $4,753,658
Revenue From CO2 Production Sales $5,085,222
Inflation Rate 3.00% NPV $0 NPV Zero
Discount Rate -4.42%
Tax Rate 27.00%
Cash Flow Analysis
Other Cash
Total Flows CCA Capital Cost
Calendar Revenue Depreciated Taxable Cash Flow Discount Discounted
Year Fixed Capital Manufacturing (including Cash Flow Depreciation Allowance Taxes Cumulative DCF
Year From Sales Value Income After Taxes Factor Cash Flow (DCF)
Expense working Rate (CCA)
Capital)
2020 0 -14,891,485 0 -2,233,723 0 -17,125,208 14,891,485 -17,125,208 1.000 -$17,125,208 -$17,125,208
2021 1 -4,896,267 0 5,237,779 341,512 12,657,762 15% 2,233,723 -1,892,211 0 341,512 1.046 $357,290 -$16,767,918
2022 2 -5,043,155 0 5,394,912 351,757 8,860,434 30% 3,797,329 -3,445,572 0 351,757 1.095 $385,012 -$16,382,906
2023 3 -5,194,450 0 5,556,760 362,310 6,202,303 30% 2,658,130 -2,295,820 0 362,310 1.145 $414,884 -$15,968,022
2024 4 -5,350,284 0 5,723,462 373,179 4,341,612 30% 1,860,691 -1,487,512 0 373,179 1.198 $447,074 -$15,520,949
2025 5 -5,510,792 0 5,895,166 384,374 3,039,129 30% 1,302,484 -918,109 0 384,374 1.253 $481,761 -$15,039,187
2026 6 -5,676,116 0 6,072,021 395,906 2,127,390 30% 911,739 -515,833 0 395,906 1.311 $519,140 -$14,520,047
2027 7 -5,846,399 0 6,254,182 407,783 1,489,173 30% 638,217 -230,434 0 407,783 1.372 $559,419 -$13,960,628
2028 8 -6,021,791 0 6,441,807 420,016 1,042,421 30% 446,752 -26,736 0 420,016 1.435 $602,823 -$13,357,804
2029 9 -6,202,445 0 6,635,062 432,617 729,695 30% 312,726 119,890 -32,370 400,246 1.502 $600,990 -$12,756,815
2030 10 -6,388,518 0 6,834,114 445,595 510,786 30% 218,908 226,687 -61,205 384,390 1.571 $603,847 -$12,152,968
2031 11 -6,580,174 0 7,039,137 458,963 357,550 30% 153,236 305,727 -82,546 376,417 1.644 $618,642 -$11,534,325
2032 12 -6,777,579 0 7,250,311 472,732 250,285 30% 107,265 365,467 -98,676 374,056 1.719 $643,165 -$10,891,160
2033 13 -6,980,906 0 7,467,820 486,914 175,200 30% 75,086 411,828 -111,194 375,720 1.799 $675,875 -$10,215,285
2034 14 -7,190,334 0 7,691,855 501,521 122,640 30% 52,560 448,961 -121,220 380,302 1.882 $715,724 -$9,499,561
2035 15 -7,406,044 0 7,922,611 516,567 85,848 30% 36,792 479,775 -129,539 387,028 1.969 $762,035 -$8,737,527
2036 16 -7,628,225 0 8,160,289 532,064 60,094 30% 25,754 506,310 -136,704 395,360 2.060 $814,407 -$7,923,120
2037 17 -7,857,072 0 8,405,098 548,026 42,065 30% 18,028 529,998 -143,099 404,926 2.155 $872,650 -$7,050,470
2038 18 -8,092,784 0 8,657,251 564,467 29,446 30% 12,620 551,847 -148,999 415,468 2.255 $936,735 -$6,113,735
2039 19 -8,335,567 0 8,916,968 581,401 20,612 30% 8,834 572,567 -154,593 426,808 2.359 $1,006,762 -$5,106,973
2040 20 -8,585,634 2,233,723 9,184,477 2,832,565 14,428 30% 6,184 2,826,382 -763,123 2,069,442 2.468 $5,106,973 $0
J-16
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
6. Sensitivity Analyses
The fixed capital, operating cost, cooling water and electricity price, onstream time, CO 2
product price, and GHG emissions credit price were all varied to determine their sensitivities
towards the project NPV and IRR for 125% capacity increase. The same factors were varied for
utility prices, onstream factor, CO2 selling price per tonne, and the GHG emission credit price.
The CO2 selling price was varied using the range of $12 - $35 /tCO2 obtained from the Global
CCS Institute (7). The analysis investigates the possibility of the GHG emission credit price rising
to $50 /tCO2e due to Alberta opting into the federal climate plan, and this value was therefore set
as the upper limit. All other parameters were given a variation of 10% aside from the onstream
factor, which was varied by 5%. Since a proper IRR was not able to be obtained for this case, the
sensitivity analysis was not performed. The sensitivity analysis summary is presented in Table
J13 below:
J-17
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Table J13: Sensitivity Analysis Parameter Variation Summary for 112% Case
111.6% Case
Variable (+/- 10%) Lower Limit Base Upper Limit
Operating Cost $602,264 $669,182 $736,100
Natural Gas Price $2.75 $3.06 $3.37
Cooling Water Price $0.06 $0.07 $0.08
Onstream Factor (+/- 5%) 0.87 0.92 0.97
CO2 selling price ($CAD/tonne) $11.97 $23.28 $34.58
GHG emissions credits ($CAD/tonne CO2e) $30.00 $30.00 $50.00
NPV (10% Discount Rate) IRR
Variable Lower Limit Base Upper Limit Lower Limit Base Upper Limit
Operating Cost $7,014,478 $6,641,451 $6,268,426 N/A N/A N/A
Natural Gas Price $6,741,188 $6,641,451 $6,541,715 N/A N/A N/A
Cooling Water Price $6,665,407 $6,641,451 $6,617,496 N/A N/A N/A
Onstream Factor (+/- 5%) $6,844,184 $6,641,451 $6,438,719 N/A N/A N/A
CO2 selling price ($CAD/tonne) $4,440,563 $6,641,451 $8,842,340 N/A N/A N/A
GHG emissions credits ($CAD/tonne CO2e) $6,641,451 $6,641,451 $10,535,106 N/A N/A N/A
parameter. The parameters were varied the in the same manner for this case. The sensitivity
Table J14: Sensitivity Analysis Parameter Variation Summary for 125% Case
125% Case
Variable (+/- 10%) Lower Limit Base Upper Limit
Fixed Capital $12,074,390 $13,415,989 $14,757,588
Operating Cost $4,060,177 $4,511,307 $4,962,438
Natural Gas Price $2.75 $3.06 $3.37
Cooling Water Price $0.06 $0.07 $0.08
Onstream Factor (+/- 5%) 0.87 0.92 0.97
CO2 selling price ($CAD/tonne) $11.97 $23.28 $34.58
GHG emissions credits ($CAD/tonne CO2e) $30.00 $30.00 $50.00
NPV (10% discount rate) IRR
Variable Lower Limit Base Upper Limit Lower Limit Base Upper Limit
Fixed Capital -$9,251,204 -$10,706,078 -$12,160,953 0.45% -0.38% -1.10%
Operating Cost -$7,734,509 -$10,706,078 -$13,802,945 4.78% -0.38% -8.55%
Natural Gas Price -$10,484,580 -$10,706,078 -$10,927,577 0.05% -0.38% -0.83%
Cooling Water Price -$10,479,678 -$10,706,078 -$10,932,479 0.06% -0.38% -0.84%
Onstream Factor (+/- 5%) -$10,189,952 -$10,706,078 -$11,222,205 0.62% -0.38% -1.45%
CO2 selling price ($CAD/tonne) -$18,540,175 -$10,706,078 -$3,743,669 -0.38% 10.38%
GHG emissions credits ($CAD/tonne CO2e) -$10,706,078 -$10,706,078 $1,239,797 -0.38% -0.38% 16.44%
J-18
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
7. References
1. Ulrich, Gael D. and Vasudevan, Palligarnai T. Chemical Engineering Process Design and
Economics: A Practical Guide (Second Edition). Durham : Process (Ulrich) Publishing, 2004. 0-
97087683-2-3.
https://www.oanda.com/currency/live-exchange-rates/USDCAD/.
3. Chemical Plant Cost Index. Chemical Engineering Essentials for the CPI Professional.
[Online] https://www.chemengonline.com/2019-cepci-updates-january-prelim-and-
december-2018-final/.
4. Guthrie, Kenneth M. Process Plant Estimating Evaluation and Control. Solana Beach :
5. Jamieson & Church. Contingency Estimating. Edmonton, AB, Canada : s.n., 2015.
6. Towler & Sinnott. Chemical Engineering Design - Principles, Practice and Economics of
7. Global CCS Institute. Accelerating the Uptake of CCS: Industrial Use of Captured Carbon
Dioxide. 2011.
J-19
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
costs and hours required for the development of capital expenditure and manpower profiles. These
profiles are based off the durations outlined in the project execution plan developed for the 125%
case. This appendix is not applicable to the 112% case, as no project execution plan was developed.
Unless specified otherwise, all costs and prices are expressed in Canadian dollars ($C).
Table of Contents
1. DFL Cost and Hours ............................................................................................................. K-1
2. Engineering Cost and Hours ................................................................................................. K-3
3. Manpower Profile ................................................................................................................. K-4
4. Reference .............................................................................................................................. K-7
i
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
(1). The total DFL cost was obtained by summing the products of the total DFL factor and purchase
cost of each equipment. The process and project contingencies of 0% and 40%, respectively, were
then applied onto this value. The DFL cost for this project is summarized in Table K1 below:
The current labourer salaries for the Fort McMurray region were obtained from Living In
Canada.com and Indeed.com (2) (3). Using the presentation on Project Labour Estimates and
Project Planning as a guideline, a payroll burden factor of 1.75 was chosen to account for the
employer’s contribution to the Canada Pension Plan (CPP), employment insurance (EI), company
pension plan, health benefits, and life insurance on behalf of the employee (1). This factor is
applied to the calculated average hourly rate received by the labourer in order to obtain the total
DFL hourly rate. Table K2 summarizes the assumed worker distribution and rates for the
K-1
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
= $36.20/ℎ
𝐷𝐹𝐿 𝐻𝑜𝑢𝑟𝑙𝑦 𝑅𝑎𝑡𝑒 = 𝐴𝑣𝑒𝑟𝑎𝑔𝑒 𝐻𝑜𝑢𝑟𝑙𝑦 𝑊𝑎𝑔𝑒 ∗ 𝑃𝑎𝑦𝑟𝑜𝑙𝑙 𝐵𝑢𝑟𝑑𝑒𝑛 𝐹𝑎𝑐𝑡𝑜𝑟 = $36.20 ∗ 1.75
= $63.36/ℎ
The total DFL hours was calculated by dividing the total DFL cost by the DFL hourly rate:
Based on the correlation presented in Guthrie (1974), this number of manhours indicates an
K-2
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Figure K1: Field Duration vs. Direct Labour Manhour Correlation from Guthrie (1974)
the project contingencies and the 3% owner’s cost. The calculation of the engineering hours uses
a similar method as the DFL hour calculation. The current wages for engineers were obtained from
Alis.com (5). Table K3 summarizes the assumed distribution and rates of the engineering
K-3
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
𝐷𝐹𝐿 𝐻𝑜𝑢𝑟𝑙𝑦 𝑅𝑎𝑡𝑒 = 𝐴𝑣𝑒𝑟𝑎𝑔𝑒 𝐻𝑜𝑢𝑟𝑙𝑦 𝑊𝑎𝑔𝑒 ∗ 𝑃𝑎𝑦𝑟𝑜𝑙𝑙 𝐵𝑢𝑟𝑑𝑒𝑛 𝐹𝑎𝑐𝑡𝑜𝑟 = $50.96 ∗ 1.75
= $89.18/ℎ
The total engineering hours was calculated by dividing the total engineering cost by the
3. Manpower Profile
Tables K4 and K5 summarize the prescribed labour and engineering manpower
distributions, respectively, throughout the project timeline. Each distribution is based upon the
dates and durations outlined in the project execution plan. The tradesmen are assumed to be
working on 14 day on 2 day off shifts with 12 hour days. This totals up to approximately 336
K-4
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
working hours per month. The engineers are assumed to be working on 40 hour weeks, totaling up
portions. The engineering cost is assumed to encompass the cost of procurement. Figure K2
K-5
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
$900,000 10,000,000
Cumulative 7,000,000
$600,000
6,000,000
$500,000
5,000,000
$400,000
4,000,000
$300,000
3,000,000
$200,000
2,000,000
$100,000 1,000,000
$0 0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Number of Months
K-6
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
5. Reference
1. Jamieson & Church. Project Labour Estimates and Project Planning. Edmonton, AB,
canada.com/work-salaries-wages-canada.html.
https://ca.indeed.com/salaries?from=headercmplink&attributionid=.
4. Guthrie, Kenneth M. Process Plant Estimating Evaluation and Control. Solana Beach :
alberta/.
K-7
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
recovery plant project and identifies process hazards and their mitigation strategies. The
application of Inherently Safer Design principles, completed checklist-based risk analysis, What
If? Analysis on the process flow diagram, Hazard and Operability Study for the new heat
exchanger (E-85) P&ID, and the DOW Fire and Explosion Index (F&EI) and Chemical Exposure
Table of Contents
1. Inherently Safer Design (ISD) Principles ..............................................................................L-1
1.1. Simplify ..........................................................................................................................L-1
1.2. Moderate .........................................................................................................................L-1
1.3. Minimize ........................................................................................................................L-2
1.4. Substitution .....................................................................................................................L-2
2. Hazard Identification Checklist .............................................................................................L-2
2.1. Base Case Checklist .......................................................................................................L-3
2.2. 112% Case Checklist ......................................................................................................L-5
2.3. 125% Case Checklist ......................................................................................................L-7
3. PHA and HAZOP Methodology ............................................................................................L-9
3.1. Assumptions .................................................................................................................L-12
4. What If? Analysis ................................................................................................................L-13
4.1. Overview ......................................................................................................................L-13
4.2. Node Definition ............................................................................................................L-13
4.3. Node and Equipment Summary ...................................................................................L-15
4.4. Base Case What If? Analysis Results...........................................................................L-18
4.5. 112% and 125% Redesign Cases What If? Analysis Results ......................................L-36
4.5.1. 112% Redesign Case Recommendations ...............................................................L-36
i
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
ii
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
minimize, substitute, moderate, and simplify ISD principles were considered for this project and
the findings are outlined below. However, it was determined that there were minimal ISD
principles that could be applied to this project, since the project is brownfield and the technology
1.1. Simplify
The client had requested the capacity redesigns to be made with minimal pump-arounds and
equipment modifications. Thus, the solution for the 112% was achieved through the optimization
of operating conditions and utility requirements alone. For the 125% redesign case, several
equipment additions and modifications were made. However, the changes were relatively simple.
For columns, the random packing was changed to a different type. The increased duty of the
lean/rich amine exchangers (E-81 A/B) was achieved by adding another plate and frame exchanger
with the same specifications as existing ones. The new lean amine cooler (E-85) is a shell and tube
heat exchanger which is very widely used and understood in industry. Finally, the Reflux Vessel
(C-83) and Absorber Overhead K.O Drum (C-87) were simply redesigned with a larger diameter
to achieve the required separation. There are no major equipment overhauls or complex changes
1.2. Moderate
To achieve the required CO2 recovery for the 112% redesign, and 125% redesign cases, it was
found that most of the streams could operate at more moderate conditions than the design case.
L-1
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
This can be seen when comparing the temperatures and pressures on the stream tables between the
different cases. The main exception to this observation is the flow rate of the process streams,
1.3. Minimize
There are no vessels within the facility designed to store large volumes of chemicals aside from
the amine make-up vessel. This vessel is designed with enough capacity to store the whole solution
inventory of the unit in case of maintenance. Since the increase in flow rate of the process streams
was unavoidable to meet the project design criteria, no minimize ISD principles were found to be
1.4. Substitution
Different amine solutions were researched to see if there were safer alternatives to MDEA.
However, it was discovered that MDEA had several processing advantages over other amine
diisopropanolamine (DIPA) and diglycolamine (DGA), which are known to be more corrosive
(1). No substitution ISD principles were found to be applicable for this project.
redesign cases. To avoid redundancy, only additional hazards resulting from the design have
L-2
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Q1: Could the design result in… Q1 Event? Q2 Hazard? Explain Q1 what? and Q2 why?
Q2: If yes, could this result in a hazard? Yes No Yes No
Situations where equipment (vessel, heat exchanger, pump, Distillation Columns: Over
etc.) fails to carry out it’s intended duty? What happens? pressurization which results in
rupture
Separators: Over pressurization
which results in rupture
Heat Exchanger: Blockage causing
leaking or liquid spray. Tube leaks
Pump: Cavitation, overheating,
motor runout, deadhead or
hydraulic surge can result in
equipment damage, explosion
and/or leakage.
Compressors: Compressor surge
or excessive vibration can result,
equipment damage, fire, explosion,
and/or leakage
Valves: Seals fail or valves
become fouled or corroded,
resulting in leaks
Over pressure? Vacuum conditions? Equipment could explode and
result in injury or death
High flow? Low flow? High flow: Poor separation in
distillation columns and separation
vessels. Potential for spills, flanges
bursting, or equipment rupturing
Low flow: Surge in compressors or
pumps, resulting equipment
damage, explosion, and/or leakage
High temperature? Low Temperature? Temperatures of process fluids
range from approximately 34°C to
113.5°C. Risks for burns from
equipment ruptures or fluid leaks
Phase change? Multiple condensers and a reboiler
present in the process
Reaction? Other reactions? The absorption of CO2 with lean
amine solution is an exothermic
reaction. The temperature of the
amine should be kept below 180°C
to ensure the amine does not
degrade
Process upset condition? Process upsets could result in any
number of changes to operating
conditions for the various
equipment in the facility. The
equipment should be designed to
withstand a wide range of
conditions it may experience during
standard and upset conditions.
Heat transfer? Heat exchangers have the
potential to foul which results in
less efficient heat transfer. If
fouling goes on for long enough,
complete tube plugging may occur
L-3
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
L-4
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Q1: Could the design result in... Q1 Event? Q2 Hazard? Explain Q1 what? and Q2 why?
Q2: If yes, could this result in a hazard? Yes No Yes No
Situations where equipment (vessel, heat exchanger, pump, No new hazards
etc.) fails to carry out it’s intended duty? What happens?
L-5
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
L-6
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Q1: Could the design result in... Q1 Event? Q2 Hazard? Explain Q1 what? and Q2 why?
Q2: If yes, could this result in a hazard? Yes No Yes No
Situations where equipment (vessel, heat exchanger, pump, No new hazards
etc.) fails to carry out it’s intended duty? What happens?
Over pressure? Vacuum conditions? No new hazards
High flow? Low flow? The 125% design case involves an
increase in feed flow rate. This
increased flow rate affect operator
reaction time for alarms as well as
flow rates through the process
piping.
High temperature? Low Temperature? Stream temperatures generally
decrease as a result of the
operating condition changes. The
highest simulated stream
temperature for the 125% case is
114.5C, and the lowest
L-7
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
L-8
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
manageable nodes. For the PHA, four nodes were defined using the CO2 Removal Unit PFDs and
being missed. For the HAZOP, the node was defined around the P&ID generated for the new lean
amine cooler (E-85). The hazards identified using the checklist PFD based analysis above were
used to guide the formulation of guide questions for the PHA and HAZOP. Sections 4.2 and 4.3
of this Appendix detail the process operating conditions for the base case, which were also used to
help guide the formulation of guide questions for the PHA and HAZOP analyses. These guide
questions were then used to determine potential hazardous scenarios and their causes that could
L-9
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
The consequences of these identified hazardous scenarios were then quantitatively evaluated
using the risk matrix shown in Figure H1 below. The matrix was based on CNRL’s corporate risk
matrix. The risk ranking selected for a given scenario was assigned based on group consensus and
best judgement of the team members. The initial risk rating was assigned assuming that no
administrative controls, the risk rating for each hazardous scenario was re-evaluated. If the residual
recommendations were considered to ensure that the process could be properly risk managed.
conducted the What If? PHA and HAZOP. The team consisted of five engineering students from
Okane Engineering: Brendan Wong, Evans Kwak, Nympha Escobar, Kaitlin Wong, and Bryan
Lee. Brendan Wong was assigned the PHA Leader role, Evans Kwak was assigned the PHA
Facilitator role, and Bryan Lee was assigned the PHA Secretary role. PHA and HAZOP team
meeting results were recorded directly into an Excel spreadsheet. The complete Excel worksheets
created from the PHA and HAZOP analyses are provided in Sections 4.4 and 5.2 of this report.
L-10
L-11
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
3.1. Assumptions
Several assumptions were made when conducting the PHA and HAZOP analyses:
insufficient training were ruled out as plausible main causes of hazardous events. The
operators were assumed to have enough training and operate the equipment according to
existing startup and shutdown procedures were sufficient in the design cases where
equipment was not altered (Base Case and 112% Design Case)
• Relief valves and other equipment were assumed to have been designed, installed, and
inspected properly according to applicable codes and regulations. They were also
• Materials of construction for piping, gaskets, and other process equipment were assumed
to have been correctly selected according to applicable design codes and regulation and
• The maximum consequence of an event that may have multiple outcomes was used to
determine the risk rating, ie. if an explosion occurred, the risk of personnel working
• Existing safeguards were assumed to already be in place to mitigate certain hazards. The
client should review these assumptions and re-evaluated whether additional controls are
L-12
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
safety hazards associated with the whole CO2 recovery unit at the CNRL Horizon Oil Sands
four separate nodes based on processing step in the CO2 recovery process. The nodes were made
Marked up PFDs containing the node boundaries are shown in Figures L1 and L2 below.
#3
Figure L1. Marked up PFD (Drawing #CN49PFD) used in the What If? Analysis
L-13
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
#4
Figure L2. Marked up PFD (Drawing #CM49PFD) used in the What If? Analysis
Node 1. The CO2 Absorber is where syngas rises in countercurrent flow against a descending flow
of lean amine solution to remove CO2 from the syngas feed. Syngas leaving the top of the Absorber
is cooled with the condensed water removed in a knockout drum and is then sent to the PSA unit
Node 2. The rich amine solution from the bottom of the Absorber is flashed, with a portion of the
inert gases routed to SMR firing. The liquid Rich amine solution is regenerated into lean amine
solution in the LP Flash Stripper. The Stripper Reboiler provides the required heat to the bottom
L-14
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
of the Flash Stripper. Hot lean amine solution is withdrawn from the bottom of the LP Flash
Stripper, pumped to the lean/rich amine exchanger where it is cooled against semi-lean solution,
and then sent back to the LP Flash Stripper. H2O and CO2 vapours from the top of the LP Flash
Stripper are cooled in the Stripper Overhead Condenser and separated from the CO2 in a Reflux
Node 3. The lean amine solution is pumped to the air cooler. In the 125% case only, the lean amine
is further cooled by the lean amine cooler (E-85) before being sent back to the CO2 absorber.
Node 4. The CO2 gas stream is routed through a series of compressors, condensers, and knockout
drums prior to being sent the Product Dehydration Unit outside battery limits.
was compiled and referenced throughout the PHA meeting process. This summary is provided in
Table L1. Summary of equipment and operating conditions for each node
L-15
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
L-16
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
L-17
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
The Material Safety Data Sheets for all process components were also obtained to ensure all
PHA members were familiar with the common hazards associated with each process stream. The
Workplace Hazardous Materials Information System (WHMIS) symbols for each component are
the project boundaries and is therefore not included in the analysis. Additionally, chemicals such
as antifoam agent and potash/soda used for cleaning/degreasing were not considered due to their
limited use.
L-18
L-19
L-20
L-21
L-22
L-23
L-24
L-25
L-26
L-27
L-28
L-29
L-30
L-31
L-32
L-33
L-34
L-35
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
4.5. 112% and 125% Redesign Cases What If? Analysis Results
After speaking with Mr. Wen regarding the scope of the PHA acceptable for the project, it was
decided that completing a separate analysis for all three cases would be very time consuming and
would have a significant amount of duplicate information. Most hazards were determined to have
little change to likelihood or consequence as a result of the capacity increase. Thus, after the What
If? analysis was completed for the base case, the What If? questions were re-considered for the
the increased flow rate through the different equipment. One key area of concern was the
CO2 absorber, which saw a 15 kPa increase to the bottoms operating pressure
• The increased flow rate may reduce the time available for operators to respond to level
• Verify equipment operating data and material balance specifications to ensure maximum
flow rates, pressure drops, and other process parameters are permissible under the
existing equipment design. There were several discrepancies identified when reviewing
• Confirm the process lines sizing completed for this project with existing pipe sizing and
• The CO2 loading factor for the 112% case was 0.66 mol CO2/mol amine which was 0.01
higher than the maximum recommended value of 0.65 mol CO2/mol amine. This is
L-36
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
unlikely to cause corrosion issues due to the lower operating temperatures used, but
the increased flow rate through the different equipment. Areas of concern included the
CO2 absorber, which saw a 30 kPa increase to the bottoms operating pressure, and the LP
Flash Stripper which saw a 5 kPa increase to the bottoms operating pressure
• The increased flow rate may reduce the time available for operators to respond to level
• Verify equipment operating data and material balance specifications to ensure maximum
flow rates, pressure drops, and other process parameters are permissible under the
existing equipment design. There were several discrepancies identified when reviewing
• Confirm the process lines sizing completed for this project with existing pipe sizing and
• The new heat exchanger (E-85) is approximately 45 m away from the lean amine air
cooler (E-84), and approximately 30 m away from the CO2 absorber (C-80). The HP
Amine Pump (G-82A/B/C) supplies all the head for E-84 and E-85 prior to being sent
back into the CO2 absorber. Although the discharge head of the pump (4199 kPa) is
significantly higher than the operating pressure of C-80 (3325 kPa), the pressure losses
L-37
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
between G-82 and C-80 should be evaluated using existing plant information that is
• Verify placement of new equipment with existing plot plan and operator input so that
there are no slips, trips, and fall issues, or issues to access for maintenance
• Ensure new random packing material is properly degreased and de-oiled to prevent
• Ensure start-up and shutdown sequences for the facility are reviewed and revised to
• The 125% redesign also uses a CO2 loading factor of 0.71 mol CO2/mol amine. This is
0.06 higher than the recommended limit but is still within the maximum equilibrium CO2
loading capacity of 1.0 mol CO2/mol amine (2). This may pose issues for corrosion if the
5. HAZOP Analysis
5.1. Overview
A HAZOP was completed on the P&ID created for the new lean amine cooler (E-85). Guide
words were formulated to consider process deviations for parameters during commissioning,
steady state operation, startup-up, and shutdown. Engineering safeguards were implemented
early into the heat exchanger design process to ensure risks could be properly managed.
and list of engineering safeguards considered for E-85 is shown on the subsequent page
L-38
L-39
L-40
L-41
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
each deviation considered. The full list of recommendations made as a result of the HAZOP
• Ensure that E-85 is properly winterized so that there is minimal risk of equipment and/or
• Confirm the process line sizes selected for the heat exchanger. The line sizing methods
employed for this project may not correspond to corporate standards and guidelines.
• The placement of E-85 should be confirmed with the existing plot plan and piping
isometrics. Operations and maintenance should also be consulted. The reference plot plan
provided by CNRL for this project was a very rough sketch, and the HAZOP members are
unfamiliar with the piping layout and high traffic areas of the CO2 Removal Unit.
Equipment placement for E-85 was selected based on optimizing maintenance access and
piping length, and may not actually be suitable if the location is obstructed by obstacles
• The startup/shutdown procedures for the CO2 Removal Unit must be updated to account
• The scope of the study was limited to the course requirements and available information.
P&IDs and which considers parameters for the CO2 removal unit as a whole. The study
L-42
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
management, and other functions that have adequate experience and process knowledge
process streams. Syngas is a highly flammable material and poses a major threat to employees in
the event of a leak in the system or equipment and pipeline failures. This threat can be calculated
using the Dow Fire and Explosion Index (F&EI). To obtain an accurate understanding of the risk
posed by the process, the F&EI was calculated for the major vessels that contained syngas, for the
base case, the 112% design case, and the 125% design case.
Below are the plot plans with the exposure radius for each case as well as the F&EI
calculations. The electrical area classification is for every case is, division 1 class 1 explosion
proof.
L-43
SCALE (m) :
2.5 5 10 20
BATTERY LIMIT
OTHER
OTHER EQUIPMENT
EQUIPMENT
PIPE RACK
Pipe Rack Elevation:
Approximately 7 m
ROAD
PUMP G-86A
G-84 PUMP G-82A PUMP
PUMP G-86B
G-82B PUMP
PUMP G-87A
G-82C PUMP
EQUIPMENT
E-82 G-81B PUMP
ROAD
C-83
PUMP G-83A/B
E-80
C-86 E-83
FTR-80
C-87
C-81
C-80
C-82
ROAD
PIPE RACK
Pipe Rack Elevation:
Approximately 7 m
OTHER OTHER
EQUIPMENT EQUIPMENT
OTHER
EQUIPMENT
L-44
SCALE (m) :
BATTERY LIMIT
2.5 5 10 20
OTHER
OTHER EQUIPMENT
EQUIPMENT
PIPE RACK
Pipe Rack Elevation:
Approximately 7 m
ROAD
PUMP G-86A
G-84 PUMP G-82A PUMP
PUMP G-86B
G-82B PUMP
PUMP G-87A
G-82C PUMP
EQUIPMENT
E-82 G-81B PUMP
ROAD
C-83
PUMP G-83A/B
E-80
C-86 E-83
FTR-80
C-87
C-81
C-80
C-82
ROAD
PIPE RACK
Pipe Rack Elevation:
Approximately 7 m
OTHER OTHER
EQUIPMENT EQUIPMENT
OTHER
EQUIPMENT
L-45
SCALE (m)
SCALE (m) ::
2.5 55
2.5 10
10 20
20
BATTERY LIMIT
BATTERY LIMIT
OTHER
OTHER
OTHER
OTHER EQUIPMENT
EQUIPMENT
EQUIPMENT
EQUIPMENT
PIPE
PIPE RACK
RACK
Pipe
Pipe Rack
Rack Elevation:
Elevation:
Approximately
Approximately 77 m
m
ROAD
ROAD
E-84
E-84 C-85
C-85 C-84
C-84
PUMP
PUMP G-86A
G-86A
PUMP
PUMP G-86A
G-86A
G-84
G-84 PUMP
PUMP G-82A
G-82A PUMP
PUMP
PUMP
PUMP G-86B
G-86B
G-82B
G-82B PUMP
PUMP
PUMP
PUMP G-87A
G-87A
G-82C
G-82C PUMP
PUMP
PUMP
PUMP G-87B
G-87B E-81A/B
E-81A/B
OTHER
OTHER G-81A
G-81A PUMP
PUMP
EQUIPMENT
EQUIPMENT
E-82 G-81B
G-81B PUMP
PUMP
E-82
ROAD
ROAD
C-83
C-83 PUMP
PUMP G-83A/B
G-83A/B
E-85
E-80
E-80
C-86
C-86 E-83
E-83
FTR-80
FTR-80
E-85 C-87
C-87
C-81
C-81
C-80
C-80
C-82
C-82
ROAD
ROAD
PIPE
PIPE RACK
RACK
Pipe
Pipe Rack
Rack Elevation:
Elevation:
Approximately
Approximately 77 m
m
OTHER
OTHER OTHER
OTHER
EQUIPMENT
EQUIPMENT EQUIPMENT
EQUIPMENT
OTHER
OTHER
EQUIPMENT
EQUIPMENT
Revamp of Carbon Dioxide Recovery Plant
L-46
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
L-47
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
L-48
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
L-49
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
L-50
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
L-51
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
L-52
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
L-53
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
L-54
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
L-55
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
L-56
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Unit 6. Absorber Overhead Knockout Drum (C-87) – 112% Design Case State:
Prepared By: Evans Kwak
Design
Material Used in Process: Synthesis Gas
Material Factor 21
Penalty Factor Penalty Factor
1. General Process Hazards
Range Used
Base Factor 1.00 1.00
A. Exothermic Reactions 0 - 1.25 0
B. Endothermic Reactions 0 - 0.40 0
C. Material Handling and Transfer 0 - 0.80 0
D. Enclosed or Indoor Process Units 0 - 0.90 0
E. Ease of Access 0 - 0.35 0.20
F. Drainage and Spill Control 0 - 0.5 0
General Process Hazards Factor (F1) 1.20
Penalty Factor Penalty Factor
2. Special Process Hazards
Range Used
Base Factor 1.00 1.00
A. Toxic Materials 0
B. Vacuum Operation 0.50 0
C. Operation Near Flammable Range 0 - 0.80 0
D. Dust Explosion 0 - 0.20 0
E. Pressure Penalty 0.83
F. Low Temperature Operation 0 - 0.30 0
G. Flammable Materials 0.90
H. Corrosion and Erosion 0 - 0.75 0.10
I. Leakage - Joints and Packing 0 -1.50 0.10
J. Fired Equipment 0
K. Hot Oil Heat Exchnage 0 - 1.15 0
L. Rotating Equipment 0.50 0
Special Process Hazards Factor (F2) 2.93
Process Unit Hazards Factor (F1 x F2 = F3) 3.51
Fire and Explosion Index (F3 x MF = F&EI) 73.72
L-57
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
L-58
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
L-59
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
L-60
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
L-61
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
L-62
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Unit 9. Absorber Overhead Knockout Drum (C-87) – 125% Design Case State:
Prepared By: Evans Kwak
Design
Material Used in Process: Synthesis Gas
Material Factor 21
Penalty Factor Penalty Factor
1. General Process Hazards
Range Used
Base Factor 1.00 1.00
A. Exothermic Reactions 0 - 1.25 0
B. Endothermic Reactions 0 - 0.40 0
C. Material Handling and Transfer 0 - 0.80 0
D. Enclosed or Indoor Process Units 0 - 0.90 0
E. Ease of Access 0 - 0.35 0.20
F. Drainage and Spill Control 0 - 0.5 0
General Process Hazards Factor (F1) 1.20
Penalty Factor Penalty Factor
2. Special Process Hazards
Range Used
Base Factor 1.00 1.00
A. Toxic Materials 0
B. Vacuum Operation 0.50 0
C. Operation Near Flammable Range 0 - 0.80 0
D. Dust Explosion 0 - 0.20 0
E. Pressure Penalty 0.83
F. Low Temperature Operation 0 - 0.30 0
G. Flammable Materials 0.98
H. Corrosion and Erosion 0 - 0.75 0.10
I. Leakage - Joints and Packing 0 -1.50 0.10
J. Fired Equipment 0
K. Hot Oil Heat Exchnage 0 - 1.15 0
L. Rotating Equipment 0.50 0
Special Process Hazards Factor (F2) 3.01
Process Unit Hazards Factor (F1 x F2 = F3) 3.61
Fire and Explosion Index (F3 x MF = F&EI) 75.79
L-63
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
L-64
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
most dangerous substance in our process. It was done for stream 26 for the base case, the 112%
design case, and the 125% design case since it contained the highest pressure, temperature, and
concentration of carbon monoxide out of all the streams and equipment in our process.
Index.
To calculate the rupture area, the pipe diameter of interest is required. The pipe diameter of
stream 26 was determined to be 10 inches (254 mm). Since the pipe diameter is greater than 4
inches, the rupture area can be approximated to be 20% of the pipe cross sectional area.
𝐷 2
𝐴𝑟𝑢𝑝𝑡𝑢𝑟𝑒 = (0.20) ∗ (𝜋) ∗ ( )
2
254 𝑚𝑚 2
𝐴𝑟𝑢𝑝𝑡𝑢𝑟𝑒 = (0.20) ∗ (𝜋) ∗ ( ) = 10134 𝑚𝑚2
2
L-65
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
𝐷𝑟𝑢𝑝𝑡𝑢𝑟𝑒 = √4 ∗ 𝐴𝑟𝑢𝑝𝑡𝑢𝑟𝑒 ∗ 𝜋
4 ∗ (10134 𝑚𝑚2 )
𝐷𝑟𝑢𝑝𝑡𝑢𝑟𝑒 = √ = 113.6 𝑚𝑚
𝜋
After the radius has been found it is necessary to find the key process conditions that would
affect the exposure radius. Table H4 shows the process conditions for the 125% design case since
Table L4. Process conditions for stream 26 for the 125% design case
Property Value
Temperature (°C) 51.5
Pressure (kPa) 3375
Quantity of gas (kg) 9558
Latent Heat of Vaporization (J/kg) 216000
Ratio of Cp/Hv 0.0048
One major assumption that Okane Engineering has made regarding the calculation of the CEI,
is that if a breach in equipment were to occur, the process would be shut down within 1 hour of
the breach. Therefore, the quantity of gas that is shown in the Table L4 is an estimated value that
is used purely for the calculation of the Chemical Exposure Index for course requirement purposes.
In the process, the synthesis gas stream does not have a set quantity since it is a by-product from
the SMR unit downstream of the CO2 Recovery Plant. Okane Engineering also does not have the
required information, regarding the SMR operation, to calculate the total quantity of synthesis gas
that would be produced. The synthesis gas stream can also be bypassed by the SMR unit if an
L-66
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
equipment breach were to occur. Therefore, the quantity of gas available for release would be the
quantity of carbon monoxide that would have been sent to the recovery unit within one hour.
Calculating the airborne quantity resulting from a process breach follows as:
𝑀𝑊
𝐴𝑄 = 4.751 ∗ 10−6 ∗ 𝐷𝑟𝑢𝑝𝑡𝑢𝑟𝑒 2 ∗ 𝑃 ∗ √
𝑇 + 273
28.01 𝑔/𝑚𝑜𝑙
𝐴𝑄 = 4.751 ∗ 10−6 ∗ (113.6 𝑚𝑚)2 ∗ (3375 𝑘𝑃𝑎) ∗ √
(41.2 ℃) + 273
𝐴𝑄 = 61.77 𝑘𝑔/𝑠
This value of the airborne quantity is saying that with the stream properties stated in Table L4,
a process breach would result in a release of 60.79 kg/s of carbon monoxide. This would mean that
the full quantity of gas would be released within approximately 2 and a half minutes. However,
the DOW Chemical Exposure Index assumes that all release scenarios are continuous for at least
5 minutes. Therefore, the release rate is calculated by dividing the quantity of gas by five minutes,
9558 𝑘𝑔
𝐴𝑄 = = 31.86 𝑘𝑔/𝑠
300 𝑠
Using the airborne quantity, the Chemical Exposure Index and the ERPG specified hazard radius
can be calculated.
𝐴𝑄
𝐶𝐸𝐼 = 655.1 ∗ √
𝐸𝑅𝑃𝐺2
L-67
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
31.86
𝐶𝐸𝐼 = 655.1 ∗ √ = 184.4
402
𝐴𝑄
𝐸𝑅𝑃𝐺𝑅𝑎𝑑𝑖𝑢𝑠 = 6551 ∗ √
𝐸𝑅𝑃𝐺2
31.86
𝐸𝑅𝑃𝐺2𝑅𝑎𝑑𝑖𝑢𝑠 = 6551 ∗ √ = 1844
402
Table L5. Summary of CEI and ERPG radii for base, 122% and 125% design cases
Calculated Parameter Base Case 112% Design Case 125% Design Case
• Canadian Standards Association (CSA) Standard B51 -14, Boiler, pressure vessel and
• American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code –
L-68
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Vessels for construction not addressed in the above codes and standards
L-69
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
L-70
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
List of References
1. Continuous absorption of CO2 in a packed column using MDEA solution for biomethane
Loading Capacity. Santos, Samuel P, Gomes, João F and Bordado, João C. 19, s.l. : MDPI,
2016, Vol. 4.
L-71
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
calculations completed to obtain sizing parameters for the device. Pressure relief was integrated
into the selected lean amine heat exchanger, E-85. The pressure-relieving device was selected and
sized with reference to API Standard 520 Part I, API Standard 521, and Gas Processors Suppliers
Table of Contents
1. Shell-side Pressure Relief .................................................................................................... M-1
1.1. Scenarios for Overpressure .......................................................................................... M-1
1.1.1. Closed Outlet .......................................................................................................... M-1
1.1.2. Cooling Water Failure ............................................................................................ M-1
1.1.3. Failure of Automatic Controls ................................................................................ M-1
1.1.4. Split Exchanger Tube ............................................................................................. M-1
1.1.5. Hydraulic Expansion .............................................................................................. M-1
1.2. Selection and Size ........................................................................................................ M-2
2. Tube-side Pressure Relief .................................................................................................... M-3
2.1. Scenarios for Overpressure .......................................................................................... M-3
2.1.1. Closed Outlet .......................................................................................................... M-3
2.1.2. Failure of Automatic Controls ................................................................................ M-3
2.1.3. Split Exchanger Tube ............................................................................................. M-3
2.2. Selection and Size ........................................................................................................ M-3
List of References ...................................................................................................................... M-5
i
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
exchanger comes from an upstream air cooler. After passing through E-85, the lean amine enters
the CO2 Absorber. A pressure relief device is proposed on the inlet lean amine stream into the heat
exchanger.
flow to address temperature fluctuation. A flow controller is also present on the inlet stream to the
exchanger.
M-1
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
valves are recommended for liquid service. Pilot operated relied valves should be used in liquid
service only when the manufacturer has approved the specific application. Since the shell-side
Where
𝑡 × 𝑇𝑆 × 𝐸
𝑀𝐴𝑊𝑃 =
𝑅 × 𝑆𝐹
M-2
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
7.07𝑉𝑙 √𝐺
𝐴=
𝐾𝑑 𝐾𝑐 𝐾𝑤 𝐾𝑣 √𝑃1 − 𝑃𝑏
and returned to the cooling water header. A pressure-relief device on the cooling water return line
is proposed.
fails and the outlet valve is not fully open, the line could be pressurized.
was chosen.
M-3
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
M-4
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
List of References
1. Engineering Data Book. Gas Processors Suppliers Association. Tulsa : s.n., 2004, Vol. 1 and
2.
2. The American Society of Mechanical Engineers. ASME Code for Pressure Piping.
Petroleum Institute. s.l. : American Petroleum Institute, 2008. API Standard 520.
5. Flanged Steel Pressure Relief Valves. American Petroleum Institute. s.l. : American
M-5
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
regulations and net social benefit considerations for the Revamp of CO2 Recovery Plant project.
Identification of process waste streams, environmental issues and mitigation strategies, and a
detailed net social benefit assessment are provided in detail within this Appendix to support
Table of Contents
1. Environmental Assessment ................................................................................................... N-1
1.1. Identification of Waste Streams .................................................................................... N-1
1.2. Applicable Regulations, Legislations, and Guidelines .................................................. N-1
1.2.1. Climate Leadership Act ........................................................................................... N-1
1.2.2. Calculation of Environmental Metric ...................................................................... N-2
1.2.3. Other Factors ........................................................................................................... N-3
1.3. Pan-Canadian Framework on Clean Growth and Climate Change ......................... N-3
1.4. Oil Sands Emissions Limit Act ............................................................................... N-4
1.5. Climate Change and Emissions Management Act (CCEMA) ................................ N-4
1.6. Water Act ................................................................................................................ N-5
1.7. Alberta Ambient Air Quality Guidelines ................................................................ N-5
2. Net Social Benefit Analysis .................................................................................................. N-6
2.1. Affected Individuals and Areas ..................................................................................... N-6
2.2. Resource Use ................................................................................................................. N-6
2.3. Socio-Economic Impacts ............................................................................................... N-7
2.4. Traffic ............................................................................................................................ N-7
2.5. Noise .............................................................................................................................. N-8
2.6. Air Quality ..................................................................................................................... N-8
References ................................................................................................................................... N-9
i
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
1. Environmental Assessment
1.1. Identification of Waste Streams
There were no waste streams identified for the CO2 Removal Unit other than fugitive
emissions of vapours from equipment. Fugitive emissions are accidental emissions of vapours or
gases from pressurized equipment, and can occur due to irregular venting, faulty equipment, or
other unintended causes such as leaking. Unfortunately, these emissions are difficult to quantify
with a high degree of accuracy due to the “accidental” nature of their release (1). However, the
fugitive emissions from the CO2 Removal Unit are infinitesimally smaller than leakage emissions
from other areas of the CNRL Horizon Facility, such as mine faces and tailings ponds.
Additionally, CNRL has a Fugitive Emission Management and Control (FEMC) program in place
to identify larger gas leaks and prioritize them for repair (2).
The process streams crossing the boundary of the project scope is further treated or
processed in other areas of the Horizon Oil Sands site. Process water and condensate is recycled
in other portions of the plant, flash gas is used as fuel for various on-site heaters, burners, and
generators, plant heaters, duct burners for heat recovery steam generator units and gas-fired steam
boilers. The syngas is also further treated in the Pressure Swing Absorption (PSA) unit, and
January 1st, 2017. Under this regulation, a price on carbon is imposed which applies to heating and
transportation fuels based on tonnes of CO2e, a standard unit for measuring carbon footprint in
terms of the 100-year time horizon global warming potential of a specified gas expressed in terms
N-1
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
of equivalency to CO2. The current price on carbon is $30/tCO2e in Alberta and may rise to
$50/tCO2e as early as 2022 under the federally-imposed carbon price (Discussed further in Section
1.3). Alberta has since opted out of the federal climate The GHG emissions reduction in tCO2e is
calculated by taking by taking the difference between the CO2 product stream molar flow rates
between the redesign case and the base case. For example, in the 112% redesign case:
𝑘𝑚𝑜𝑙 𝑘𝑔
𝑚̇𝐶𝑂2_𝑅𝑒𝑐𝑜𝑣𝑒𝑟𝑒𝑑 = 𝑛̇ 𝐶𝑂2_𝑅𝑒𝑐𝑜𝑣𝑒𝑟𝑒𝑑 ∗ 𝑀𝑊𝐶𝑂2 = 90.59 ∗ 44.01 = 3986.87 𝑘𝑔/ℎ𝑟
ℎ 𝑘𝑚𝑜𝑙
Similarly, the additional CO2 recovered for the 125% case was calculated to be 95,453 tCO2e/yr.
The CO2 emissions from increased electricity usage as a result of the capacity increase
would also have an effect on the overall GHG emissions of the facility. However, this cost was
ignored as the values were very small in comparison to the actual CO2 additional recovery. A
sample calculation for the 112% case for electricity grid usage is as follows, using the methodology
and factors given in the Carbon Offset Emission Factors Handbook. Let EC stand for Electricity
Consumption:
𝑡𝐶𝑂2 𝑒 1 𝑀𝑊ℎ
𝐸𝐶𝐶𝑂2𝑒 = 𝐸𝐶 ∗ 𝐸𝐶𝑡𝐶𝑂2𝑒 𝑝𝑒𝑟 𝑘𝑊ℎ = 622.74𝑘𝑊ℎ ∗ 0.64 ∗ = 0.398 𝑡𝐶𝑂2 𝑒
𝑀𝑊ℎ 1000 𝑘𝑊ℎ
N-2
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Further study would be required to determine the overall net GHG emissions reduction that
may be achieved when considering other portions of the upgrader site affected by the feed flow
rate increase, such as the PSA unit and downstream dehydration unit.
From the Environmental protection agency website, a typical passenger vehicle emits about
4.6 tonnes of CO2 per year (3). Thus, the increased CO2 recovery from the 125% and 112%
redesign cases would be equivalent to removing 7,592 to 20,751 passenger vehicles from the roads:
34925 𝑡𝐶𝑂2 𝑒
𝑉𝑒ℎ𝑖𝑐𝑙𝑒𝑠 𝑅𝑒𝑚𝑜𝑣𝑒𝑑 (112%) = = 7,592 𝑉𝑒ℎ𝑖𝑐𝑙𝑒𝑠
𝑡𝐶𝑂2 𝑒
4.6
𝑉𝑒ℎ𝑖𝑐𝑙𝑒
95,453 𝑡𝐶𝑂2 𝑒
𝑉𝑒ℎ𝑖𝑐𝑙𝑒𝑠 𝑅𝑒𝑚𝑜𝑣𝑒𝑑 (125%) = = 20,751 𝑉𝑒ℎ𝑖𝑐𝑙𝑒𝑠
𝑡𝐶𝑂2 𝑒
4.6
𝑉𝑒ℎ𝑖𝑐𝑙𝑒
large implications for the carbon levy. The United Conservative Party (UCP) is a loud and vocal
opponent of both the 100 MT emissions cap for the oil sands industry and the carbon levy (4). If
the UCP wins the election, UCP leader Jason Kenney has vowed to scrap the Alberta carbon levy
and fight the federal government’s Pan-Canadian Climate Framework including the federally
grow the Country’s economy while reducing emissions and building resilience to adapt to a
changing climate (5). This plan requires jurisdictions to enforce a price-based system on GHG
N-3
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
emissions. Under this plan, the federally imposed carbon price of $10/tCO2e in 2018 is expected
specified for all oil sands sites combined. Prudent consideration towards GHG emissions and
environmental management is required to ensure the sustainability of the oil sands industry.
Additional recovered CO2 as a result of this project could be used to support environmental
initiatives in nearby oil sands facilities who currently transport CO2 from Edmonton by truck.
Some examples of initiatives include the Non-Segregating Tailings process and Carbon Capture
Incentive Regulation (CCIR) under the CCEMA and is subject to the carbon tax. Regulated
facilities are not penalized under the CCIR if their GHG emissions are below the designated limit,
which depends on the industry specific emissions benchmarks. If regulated facilities emit GHGs
above the designated limits, they are subject to compliancy costs calculated based on excess GHG
emissions. To maintain compliancy with the CCIR, these facilities must reduce their emissions
Alberta’s Climate Change and Emissions Management Fund (CCEMF) (9). The cost to purchase
carbon offset credits or contribute to the CCEMF is currently $30/tCO2e excess, which could rise
to $50/tCO2e in 2022. Increasing the capacity of the CO2 Removal Unit would have the overall
benefit of reducing GHG emissions in the upgrader and reduce carbon tax costs for CNRL under
this regulation
N-4
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
Carbon Dioxide is also a Specified Gas under the CCEMA and CCIR. The reporting
threshold identified in the Specified Gas Reporting Regulation is 10,000 tonnes of emissions from
a facility. The decrease in CO2 emissions from the CNRL Horizon Facility would not be enough
enforces a 66.1 MM m3/yr of water draw from surface water sources. This includes a maximum
diversion rate of 3.1 m3/s from the Athabasca River with a total maximum diversion of 55.82
MMm3/yr, and a 34.7 MMm3/yr maximum diversion from the Tar River and surface runoff
sources tributary to the Tar and Calumet Rivers. The 112% and 125% cases would increase the
cooling water requirements of the CO2 Removal Unit by 0.013 and 0.101 m3/s, respectively. This
small change is not likely to pose an issue for the client, however limited information is available
regarding current facility water use and draw from the river. Additional study would be required
to fully understand the implications of this increased water usage for the project cases. Periods of
low flow for the surface water sources such as during dry summers or frigid winters, as well as
periods of process upsets should also be considered for further investigation. There is also no
organic compounds, and particulate matter as a direct result from the increased CO2 Removal Unit.
Implications of the increased feed flow rate for the hydro-desulphurization reactors, PSA unit, and
other sources of emissions from the Horizon Oil Sands Facility were not considered for this
analysis.
N-5
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
CNRL is committed to ensuring a high standard of air quality for its stakeholders. CNRL
continues to maintain this high standard for air quality and participation with these various
associations and monitoring programs, ambient air quality around the Horizon Oil Sands Facility
Horizon Oil Sands facility was first conducted. The facility is part of the Regional Municipality of
Wood Buffalo (RMWB) which comprises the City of Fort McMurray and the surrounding rural
areas (6). There are five First Nation members controlling approximately 26 reserves in the
surrounding rural area, which includes the Mikisew Cree First Nation in Fort Chipewyan, the
Athabasca Chipewyan First Nation in Fort Chipewyan, the Fort McKay First Nation in Fort
McKay, The Fort McMurray First Nation near Anzac, and the Chipewyan Prairie First Nation in
Janvier (6).
Sands facility and do not involve work outside of the facility’s boundaries, the traditional lands in
the RMWB will not disturbed. Non-aboriginal environmentally important areas will also not be
N-6
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
affected, including aggregate resources; agriculture; forestry; berry harvesting; hunting; trapping;
Over the project’s 20-year lifetime, the 125% and 112% redesigns would generate $1.95 million
CAD and $8.95 million CAD in corporate income tax revenue for the provincial government,
respectively. This tax can be utilized for a variety of social programs and public infrastructure. The
125% redesign case would also see business and employment opportunities for qualified local or
regional contractors and businesses during the design and construction phases. There would be job
opportunities for boilermakers, pipe fitters, iron workers, welders, electricians. Additionally, there
is the potential to reduce the carbon footprint of other oil sands facilities, by selling the additional
CO2 recovered to other facilities around the Fort McMurray area to be used for Enhanced Oil
Recovery, tailings management, or other Carbon Capture and Storage methods. Currently many
oil sands facilities around the Fort McMurray are purchasing CO2 from Edmonton which is
approximately 450 km away which is expensive and not environmentally friends due to the large
volume of trucks and fuel required for transport. Having a larger and more reliable supply of CO2
from the CNRL Horizon Facility would thus benefit other oil producers in the region.
2.4. Traffic
For the 125% redesign case, there may be increased traffic congestion and traffic safety
incidents as a result of bringing in capable workers to the site for construction. To mitigate this,
CNRL has a well-established transporation policy which requirese company and contractor
workers to travel to and from the site on buses. Additionally, the bulk of construction workers can
N-7
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
be housed in the on-site camp located at the CNRL Horizon Oil Sands facility which would
2.5. Noise
For both the 125% and 112% redesign cases, there would be a marginal increase to noise
generated by the CO2 removal unit based on the pumps and compressors running at an increased
capacity. This increase would be very minimal, as no new mechanical equipment has been added
for either of the capacity increase cases. Furthermore, noise levels are measured on a logarithmic
scale, with a diminished effect when noise is generated from multiple sources. There should be no
emissions intensity of the CNRL Horizon Oil Sands facility and consequently improve upon the
baseline air quality around the facility. Additionally, the CNRL facility was designed with a high
standard for air quality, including low-NOx burner technology and hydro-desulphurization
reactors to achieve over 99% recovery of sulphur. The generation of airborne particulates and
emissions from mobile equipment fuel consumption as a result of project construction activities
could also be mitigated with dust mitigation programs and optimization of haul route distances.
N-8
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
References
1. Picard, David. Fugitive Emissions From Oil and Natural Gas Activities. Good Practice
2. Canadian Natural Resources Ltd. GHG emissions reduction program. [Online] [Cited: April
5, 2019.] https://www.cnrl.com/corporate-responsibility/environment/climate-change/ghg-
emissions.
https://www.epa.gov/greenvehicles/greenhouse-gas-emissions-typical-passenger-vehicle.
4. Wilt, James. Canada Won't Perform an Environmental Review of Most New Oilsands
Projects. Here's Why. The Narwhal. [Online] December 18, 2018. [Cited: April 5, 2019.]
https://thenarwhal.ca/canada-wont-perform-an-environmental-review-of-most-new-oilsands-
projects-heres-why/.
https://www.canada.ca/content/dam/themes/environment/documents/weather1/20170125-en.pdf.
6. Golder Associates. CNRL Horizon Project Environmental Impact Assessment. Oil Sands
N-9
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
articles from the open literature were consulted during the analysis of the project.
Table of Contents
1. Factors affecting CO2 absorption efficiency in packed column ........................................... O-1
2. Corrosion and materials selection for amine service .......................................................... O-11
3. Scale-up effects of CO2 capture by Methyldieathanolamine (MDEA) solutions in terms of
loading capacity ........................................................................................................................ O-16
List of References ..................................................................................................................... O-26
i
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
O-1
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
O-2
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
O-3
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
O-4
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
O-5
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
O-6
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
O-7
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
O-8
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
O-9
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
O-10
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
O-11
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
O-12
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
O-13
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
O-14
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
O-15
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
O-16
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
O-17
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
O-18
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
O-19
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
O-20
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
O-21
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
O-22
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
O-23
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
O-24
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
O-25
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
List of References
1. Tan, L.S., et al. Factors affecting CO2 absorption efficiency in packed column: A review.
2. Corrosion and Materials Selection for Amine Service. Rennie, S. s.l. : Materials Forum, 2006,
Vol. 30.
Loading Capacity. Santos, Samuel P, Gomes, João F and Bordado, João C. 19, s.l. : MDPI,
2016, Vol. 4.
O-26
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
the purposes of requesting documents and information, along with clarifying questions.
i
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
P-1
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
P-2
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
P-3
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
P-4
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
P-5
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
P-6
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
P-7
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
P-8
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
P-9
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
P-10
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
P-11
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
P-12
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
P-13
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
P-14
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
P-15
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
P-16
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
P-17
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
P-18
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
P-19
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
P-20
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
P-21
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09
P-22