You are on page 1of 408

Revamp of CO2 Recovery Plant Final Report

Client: Canadian Natural Resources Ltd.


Team 5 Date of Submission: 2019-04-09

Executive Summary
Canadian Natural Resources Ltd. (CNRL) wishes to increase the capacity of the Steam

Methane Reformer (SMR) unit to produce more hydrogen for increased synthetic crude oil

production. However, increasing the SMR capacity requires an increase in the CO2 Recovery Plant

capacity to maintain the CO2 concentrations in the process streams at an acceptable level.

Okane Engineering was requested by CNRL to develop a redesign of the CO2 Recovery

Plant at Horizon Oil Sands near Fort McKay, Alberta that would increase the operating capacity

by 15% and 25%. This project would reduce the greenhouse gas (GHG) emissions costs incurred

under the provincial and federal climate leadership plans. Without reductions in GHG emissions,

the increasing carbon tax prices would compromise the profitability of the Horizon Oil Sands

facility. This project would also provide an opportunity for additional revenue from the sale of

excess CO2 produced by the CO2 Recovery Plant.

ProMax simulation software was used to develop the process redesigns. The design and

operating data provided by CNRL were used as benchmarks for design. An AACE Class 4 cost

estimate was completed using a discount rate of 15% and hurdle rate of 20% over a 20-year project

life to evaluate economic feasibility. Project revenues were calculated using a carbon tax price of

C$30 per tonne of CO2 equivalent (/tCO2e) and estimated CO2 selling price of C$23 /tCO2.

The proposed redesign for the 125% operating capacity involves the optimization of

operating pressures and temperatures and modification of packing configurations in the CO2

Absorber and LP Flash Stripper. Three additional exchangers and the upsizing of two drums are

also required. The resulting CO2 product flow rate is 63.2 tonnes per hour (t/h), which is a 20.9%

increase from the base case. Project execution is expected to take 23 months, which includes 7

months for engineering, 8 months for procurement, 7 months for construction, and 4 months for

i
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

commissioning and start-up. The estimated capital cost was C$14.76 MM with a C$4.51 MM

increase in annual operating costs compared to the base case. This redesign was not feasible at

current economic conditions, with a net present value (NPV) of -C$10.69 MM. For this redesign

to be economically feasible, the combined total of the sale price of CO2 and carbon tax price would

need to be C$79 /tCO2.

Due to the design constraints of the existing equipment, a 12% capacity increase was

proposed instead of a 15% increase. The 112% capacity redesign optimizes the operating pressures

and temperatures for the existing equipment. The resulting CO2 product flow rate is 56.2 t/h, which

is a 7.7% increase from the base case. Implementation of this redesign is done onstream, so project

execution time is minimal. The estimated increase in the annual operating cost was C$670 K,

which gave an NPV of C$6.64 MM. This redesign was determined to be economically feasible

and would provide an additional revenue of C$1.86 MM per year compared to the base case.

Both capacity redesigns were determined to be properly risk managed and socially and

environmentally sustainable. Safety and risk analyses identified potential high-velocity lines in

both cases which should be evaluated for corrosion concerns prior to project execution.

Based on economic feasibility and project execution time, Okane Engineering recommends

the 112% capacity redesign. Field tests should be completed to verify the CO2 recovery efficiencies

stated in the redesign due to limitations in the simulation model. The vendor compressor unit

equipment specifications were also out of scope and must be validated prior to project execution.

ii
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Table of Contents
Executive Summary ......................................................................................................................... i
1. Introduction and Statement of Objectives ............................................................................... 1
2. Background ............................................................................................................................. 2
3. Proposed Solution.................................................................................................................... 3
4. Justification ............................................................................................................................. 4
5. Alternatives Considered .......................................................................................................... 5
5.1. Do Nothing .................................................................................................................. 5
5.2. Replacement of Plant with Gasification System ......................................................... 6
6. Project Description .................................................................................................................. 6
6.1. Existing Process Design Description – Kaitlin ........................................................... 9
Model Verification ....................................................................................... 11
Separation Model Verification ..................................................................... 11
Areas of Heat Exchange Verification .......................................................... 12
Staged Compression Verification ................................................................ 12
6.2. Project Assumptions, Constraints, and Limitations .................................................. 12
Assumptions and Constraints ....................................................................... 12
Limitations ................................................................................................... 14
Project Dependencies ................................................................................... 14
Technical Feasibility .................................................................................... 15
7. Option A: 125% Capacity Redesign ..................................................................................... 15
7.1. Process Description ................................................................................................... 15
CO2 Absorption............................................................................................ 18
CO2 Desorption ............................................................................................ 19
Design Considerations ................................................................................. 19
Start-Up and Shutdown Considerations ....................................................... 19
7.2. Heat Integration ......................................................................................................... 20
7.3. Material and Energy Balances ................................................................................... 21
7.4. Equipment List and Sizing ........................................................................................ 22

iii
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Columns ....................................................................................................... 23
Heat Exchangers .......................................................................................... 23
Vessels ......................................................................................................... 24
Pumps........................................................................................................... 25
Compressors ................................................................................................. 25
Process Piping .............................................................................................. 26
Materials of Construction ............................................................................ 27
7.5. Utility Requirements ................................................................................................. 27
7.6. Project Execution Strategy ........................................................................................ 28
Engineering Plan .......................................................................................... 30
Procurement Plan ......................................................................................... 30
Construction Plan ......................................................................................... 31
Commissioning Plan .................................................................................... 31
Project Management Schedule ..................................................................... 32
7.7. Economic Analysis .................................................................................................... 33
Economic Introduction................................................................................. 33
Fixed Capital Expenditure ........................................................................... 33
Working Capital Expenditure ...................................................................... 35
Operating Cost ............................................................................................. 35
Financing Plan ............................................................................................. 37
Discounted Cash Flow Analysis .................................................................. 37
Sensitivity Analysis ..................................................................................... 38
Economic Conclusions................................................................................. 39
7.8. Environmental Analysis ............................................................................................ 39
Environmental Conclusions ......................................................................... 41
7.9. Safety and Risk Analysis ........................................................................................... 41
Identification of Hazards and Safety Risks .................................................. 42
What If? Process Hazard Analysis ............................................................... 42
Hazard and Operability Study...................................................................... 43
Chemical Exposure Index ............................................................................ 44

iv
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Fire and Explosion Index ............................................................................. 46


Applicable Safety Regulations and Codes Requirements ............................ 47
Health and Safety Risk Management Conclusions ...................................... 47
7.10. Net Social Benefit Analysis ...................................................................................... 47
8. Option B: 112% Capacity Redesign ...................................................................................... 48
8.1. Process Description ................................................................................................... 48
CO2 Absorption............................................................................................ 49
CO2 Desorption ............................................................................................ 49
Design Considerations ................................................................................. 50
8.2. Heat Integration ......................................................................................................... 50
8.3. Material and Energy Balances ................................................................................... 50
8.4. Equipment List and Sizing ........................................................................................ 52
8.5. Utility Requirements ................................................................................................. 53
8.6. Project Execution Strategy ........................................................................................ 53
8.7. Economic Analysis .................................................................................................... 53
Economic Introduction................................................................................. 53
Fixed Capital Expenditure ........................................................................... 54
Operating Cost ............................................................................................. 54
Discounted Cash Flow Analysis .................................................................. 55
Sensitivity Analysis ..................................................................................... 56
Economic Conclusions................................................................................. 56
8.8. Environmental Analysis ............................................................................................ 56
8.9. Safety and Risk Analysis ........................................................................................... 57
Hazard Identification and Risk Evaluation .................................................. 57
Chemical Exposure Index ............................................................................ 58
Fire and Explosion Index ............................................................................. 59
Applicable Safety Regulations and Risk Management Conclusions ........... 60
8.10. Net Social Benefit Analysis ...................................................................................... 60
9. Conclusions and Recommendations ...................................................................................... 61
10. References ............................................................................................................................ 64

v
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Appendix A: Decision Analysis................................................................................................... A1


Appendix B: Simulation Assumptions.......................................................................................... B1
Appendix C: Simulation Validation.............................................................................................. C1
Appendix D: Separation Calculations .......................................................................................... D1
Appendix E: Drawing Package ..................................................................................................... E1
Appendix F: Start-up and Shutdown Procedures .......................................................................... F1
Appendix G: Detailed Material and Energy Balances ................................................................. G1
Appendix H: Detailed Equipment List and Sizing ...................................................................... H1
Appendix I: Heat Exchanger Design ............................................................................................. I1
Appendix J: Economics ................................................................................................................. J1
Appendix K: Project Management Schedule ............................................................................... K1
Appendix L: Safety and Risk ........................................................................................................ L1
Appendix M: Pressure Relief Device Sizing ............................................................................... M1
Appendix N: Environmental and Net Social Benefit Assessments ............................................. N1
Appendix O: Pertinent Articles .................................................................................................... O1
Appendix P: Email Correspondence ............................................................................................. P1

vi
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

List of Figures
Figure 1: Block Flow Diagram of CO2 Recovery Plant with CO2 Removal Unit Scope

Indicated .......................................................................................................................... 7

Figure 2. Process Flow Diagram for the Base Case and 112% Capacity Redesign ....................... 8

Figure 3: Process Flow Diagram for the 125% Capacity Redesign.............................................. 17

Figure 4: Project Execution Schedule ........................................................................................... 29

Figure 5: Manpower Distribution for Engineering and Labour .................................................... 32

Figure 6: Fixed Capital Expenditure Breakdown ......................................................................... 34

Figure 7: Operating Cost Breakdown for the 125% Capacity Increase ........................................ 36

Figure 8: Discounted Cash Flow Profile for the 125% Case ........................................................ 37

Figure 9: NPV Tornado Diagram for the 125% Case ................................................................... 38

Figure 10: IRR Tornado Diagram for the 125% Case .................................................................. 39

Figure 11: Chemical Exposure Radii by ERPG Level Overlaid on Satellite Imagery for the

125% Case ................................................................................................................... 45

Figure 12: Operating Cost Breakdown for the 112% Capacity Increase ...................................... 54

Figure 13: Discounted Cash Flow Profile for the 112% Case ...................................................... 55

Figure 14: NPV Tornado Diagram for the 112% Case ................................................................. 56

Figure 16: Chemical Exposure Radii by ERPG Level Overlaid on Satellite Imagery for the

112% Case ................................................................................................................... 59

vii
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

List of Tables
Table 1: Outline of Given Stream Specifications ......................................................................... 13

Table 2: Temperature, Pressure, and Flow Rate Changes for the 125% Capacity Redesign ....... 16

Table 3: Equipment Modifications and Additions Required for the 125% Redesign Case .......... 16

Table 4: Summary of Streams Requiring Cooling or Heating for Heat Integration ..................... 20

Table 5: 125% Case Overall Material Balance ............................................................................. 21

Table 6: 125% Case Overall Energy Balance ............................................................................... 22

Table 7: Summary of Column Specifications ............................................................................... 23

Table 8: Summary of Heat Exchanger Specifications .................................................................. 24

Table 9: Summary of Vessel Specifications ................................................................................. 25

Table 10: Summary of Pump Specifications ................................................................................ 25

Table 11: Summary of Compressor Specifications ...................................................................... 26

Table 12: Additional Utility Requirements for 125% Capacity Redesign ................................... 28

Table 13: Utility Cost Summary ................................................................................................... 36

Table 14: Chemical Exposure Index Summary Table .................................................................. 44

Table 15. Fire and Explosion Index Summary Table for the 125% Redesign Case ..................... 46

Table 16: Temperature, Pressure, and Flow Rate Changes for the 112% Capacity Redesign ..... 49

Table 17: 112 % Case Overall Material Balance .......................................................................... 51

Table 18: 112 % Case Overall Energy Balance ............................................................................ 52

Table 19: Additional Utility Requirements................................................................................... 53

Table 20: Utility Cost Summary ................................................................................................... 55

Table 21: Chemical Exposure Index Summary Table .................................................................. 58

Table 22: Fire and Explosion Index Summary Table for the 112% Redesign Case..................... 60

Table 23: Summary of Requirements for Redesign ...................................................................... 61

viii
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

1. Introduction and Statement of Objectives


The Horizon Oil Sands upgrading facility located north of Fort McKay, Alberta transforms

bitumen into synthetic crude oil (SCO) using delayed coking and hydrotreating processes (1). This

requires a large excess of hydrogen which is supplied by the Steam Methane Reformer (SMR) unit.

The SMR produces 144 million standard cubic feet per day of hydrogen (2). CNRL wishes to

increase the capacity of the SMR unit to improve hydrogen supply to support future increases in

SCO production. However, increasing the capacity of the SMR would result in higher flow rates

of syngas feed to the CO2 Recovery Plant. At current conditions, this increase would result in

higher concentrations of CO2 in the feed to the Pressure Swing Adsorption (PSA) unit and potential

corrosion issues. Therefore, if the capacity of the SMR unit is increased, the CO2 Recovery Plant

capacity should also be increased.

The CO2 Recovery Plant reduces the greenhouse gas (GHG) emissions of the Horizon Oil

Sands site by recovering 438,000 tonnes of CO2 each year (2). Under the Alberta climate change

plan, the current price of GHG emissions exceeding the nominal limit is C$30 per tonne of CO2

equivalent (/tCO2e), which is proposed to rise to C$50 /tCO2e by 2022 under Canada’s federal

climate change plan (3; 4). Recovering more CO2 would reduce the GHG emissions compliance

costs and provide economic benefit. Increased recovery of CO2 would also minimize long-term

economic risks from potential increases in carbon prices. Recovering more CO2 is also an

opportunity for additional revenue. CO2 product is utilized in tailings management processes and

can be sold to other facilities in Alberta at a current market price of C$23 per tonne.

CNRL has requested Okane Engineering to complete a capacity augmentation study of the

Horizon Oil Sands CO2 Recovery Plant. The objective of this project is to develop cost-effective

process redesigns of the CO2 Recovery Plant that will increase its existing operating capacity by

1
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

15% and 25%. The redesigns must increase operating capacity while optimizing CO2 recovery and

energy input.

2. Background
The CNRL Horizon Oil Sands site is a regulated facility under the Carbon Competitiveness

Incentive Regulation (CCIR) and subject to the carbon tax (5; 6). Regulated facilities are not

penalized under the CCIR if their GHG emissions are below a designated limit, which depends on

the industry specific emissions benchmarks. If regulated facilities emit GHGs above the designated

limits, they are subject to compliancy costs calculated based on excess GHG emissions. To

maintain compliancy with the CCIR, these facilities must either reduce their emissions intensity,

purchase Alberta-based carbon offset credits, or make a monetary contribution to Alberta’s

Climate Change and Emissions Management Fund (CCEMF) (7). The cost to purchase carbon

offset credits or contribute to the CCEMF is currently C$30 /tCO2e excess, which could rise to

C$50 /tCO2e by 2022 (8). By increasing the CO2 Removal Unit’s capacity, CNRL would improve

its compliancy with CCIR limits by avoiding significant increases in CO2 emissions that would

have resulted from increased hydrogen production. CNRL may also be eligible to earn emission

offset credits for its GHG reduction, lessening the amount of credits they would have to purchase

for CO2 generation above allocated limits.

Canada produces roughly 2% of global CO2 emissions despite representing only 0.5% of the

world’s population, 10% of which is accounted for by the oil sands alone (9). To encourage

emissions reductions, the Alberta Government implemented the Oil Sands Emissions Limit Act

(Bill 25) in December 2016 which specifies an annual 100 MT GHG emissions limit for all oil

sands sites combined (10). Therefore, oil sands facilities must collectively limit emissions

production to ensure long-term sustainability of the industry (11). Environmental stewardship is a

2
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

fundamental value of CNRL (12). CNRL has thus developed an integrated GHG emissions

reduction strategy which aims to reduce CNRL’s emissions intensities to below the global crude

average of 63.78 kgCO2e per barrel of crude oil (13; 14; 15). Increased CO2 recovery would

contribute towards this goal and strengthen the company’s position as an industry leader in GHG

emissions reduction. Additional recovered CO2 can also be used to support environmental

initiatives in nearby oil sands facilities who currently truck in purchased CO2 from Edmonton (16).

Examples of initiatives include the Non-Segregating Tailings process and Carbon Capture and

Storage (CCS) (2; 17).

The current global demand for CO2 is estimated to be 80 megatonnes per annum (MTPA)

and is forecasted to reach 140 MTPA by 2020 (18). At least 50 MTPA is utilized for enhanced oil

recovery (EOR) exclusively within North America. The market price for bulk CO2 sold via

pipeline has historically been in the range of C$12 to C$35 per tonne (18). Recovering more CO2

would supply Horizon Oil Sands with additional CO2 that could be sold to other large-scale

facilities in the Fort McKay area to increase profitability.

3. Proposed Solution
Okane Engineering initially proposed that a 115% capacity redesign of the CO2 Recovery

Plant would be achieved within the design limits of the existing equipment. However, further

investigation revealed that the maximum achievable operating capacity using only existing

equipment was 112%. After consultation with the client, a 112% capacity redesign was accepted

in lieu of the 115% capacity redesign.

Okane Engineering proposes two options to increase the CO2 Recovery Plant’s operating

capacity. The first option achieves the desired capacity increase to 125% and requires equipment

additions and modifications. This method requires a large capital expenditure and significantly

3
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

higher utility usages, raising operating costs as well. However, it achieves the desired 125%

capacity with the potential for further increases through optimization of operating conditions.

The second option achieves an increased capacity to 112% by modifying process operating

conditions and utility usage. It does not require the addition or modification of equipment and thus

no capital expenditure. However, the disadvantage is that the increase in capacity is limited to 12%

with no potential for further increases without capital investment.

Both redesigns would increase the amount of CO2 recovered. This would result in cost

savings by reducing the number of GHG emissions credits purchased and would provide an

opportunity for increased revenue from the sale of additional CO2 recovered. Increasing the CO2

Recovery Plant capacity would also enable more hydrogen production in the SMR, enabling

further increases in SCO production at Horizon Oil Sands.

4. Justification
Appendix A contains the decision analysis criteria used to evaluate the alternatives

considered. First, the options were evaluated against the “must” criteria which included having the

ability to reduce GHG emissions and ability to achieve a minimum capacity increase of 12%.

Options that passed these criteria were then rated and compared quantitatively based on the desired

“wants” of minimizing capital costs, GHG emissions, operating costs, and project execution time.

The addition or modification of process equipment option was chosen for the 125%

capacity redesign. This was due to limitations in the design capacities of the existing equipment

and a lower capital cost relative to the other options. The optimization of process operating

conditions was chosen for the 112% capacity redesign because it was able to achieve a 12%

increase in capacity using only existing equipment, requiring no capital cost.

4
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

The 25% increase in operating capacity was achieved by changing the packing

configurations in the columns, adding three additional exchangers, and upsizing two drums. The

amount of CO2 recovered is 1435 kmol/h of CO2 which corresponds to an increase of C$5.09 MM

in the annual revenue compared to the base case. The total capital cost is C$14.76 MM with an

increase of C$4.51 MM in the annual operating cost. Based on a 20-year project lifetime and

corporate discount rate of 15%, the NPV is -C$10.69 MM indicating that the 125% capacity

redesign is not economically feasible. For the project to be economically feasible at the current

carbon tax, the selling price of CO2 would need to be C$49 /tCO2 which is unreasonably expensive

for commercial grade CO2. This option was therefore not recommended from an economic

standpoint but was investigated further at the request of the client.

The 12% capacity increase was achieved through optimization of operating pressures and

temperatures within the design limits of the existing equipment. The amount of CO2 recovered was

1278 kmol/h of CO2, corresponding to an increase of C$1.86 MM in the annual revenue compared

to the base case. No capital cost is involved in this redesign. The increase in annual operating cost

is C$0.67 MM. The calculated NPV is C$6.64 MM indicating that the 112% capacity redesign is

economically feasible. Therefore, pursuing the 112% capacity redesign is justified based on the

economic analysis results.

Feedstock availability is not a foreseeable issue as the syngas feed used is a byproduct of the

SMR. The amine make-up required is also very minimal, so amine availability is not a concern.

5. Alternatives Considered
5.1. Do Nothing
In the “Do Nothing” option, no equipment or operational changes are made to the CO2

Removal Unit. This would result in increased CO2 concentrations in the syngas feed to the PSA at

5
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

higher feed flow rates, resulting in corrosion issues. The CO2 recovery efficiency of the unit would

also decrease as feed rates increase due to process design limitations. This would result in higher

GHG emissions and would progressively cost more in the long-term due to increasing GHG

emissions compliance costs. Thus, this option is economically and environmentally undesirable.

5.2. Replacement of Plant with Gasification System


This option replaces the existing CO2 Recovery Plant with a hydrogen-producing

gasification system. This type of system can produce a high purity CO2 product at increased feed

flow rates without the need for excess dehydration units and is currently used a the North West

Sturgeon Refinery (19). The capital cost of this option is very high due to the major reconstruction

of the plant and reconfigurations of upstream and downstream tie-ins. As a result, this option is

not cost-effective and was therefore rejected.

6. Project Description
The CO2 Removal Unit begins with the syngas inlet stream to the CO2 Absorber and ends

with the CO2 product stream at battery limits. The project scope includes existing equipment within

the battery limits of the CO2 Removal Unit and excludes the dehydration unit, make-up vessels,

pumps, and anti-foam injection system. It does not include upstream or downstream processes,

such as the separation of syngas or processing of syngas through pressure swing adsorption. The

treatment of steam, cooling water, boiler feed water, fuel gas, and natural gas are also not included

in this project scope. A block flow diagram outlining the major processes of the CO2 Recovery

Plant and the identified CO2 Removal Unit project scope is shown in Figure 1. A process flow

diagram (PFD) of the CO2 Removal Unit is shown in Figure 2 and in Appendix E with associated

stream tables.

6
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Pressure Swing
Tail Gas
Absorption

Lean Amine

Rich Amine Vendor


CO2 Amine Lean Amine Dehydration
Compression CO2 Product
Absorption Regeneration Unit
Unit

Syngas

Project Scope
Separation
System
Boiler Feed
Water
High
Process Gas Temperature
Reaction

Figure 1: Block Flow Diagram of CO2 Recovery Plant with CO2 Removal Unit Scope Indicated

7
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

E-80 E-81A/B/C E-82 E-83 E-84 G-81A/B G-82A/B/C G-83A/B G-84


CO2 Absorber Lean/Rich Amine Stripper Reboiler Stripper Overhead Lean Amine Air Semilean Amine HP Lean Amine Stripper Reflux Amine Make-Up
2
Overhead Cooler Exchanger Area: 1150.0 m Condenser Cooler Pump Pump Pump Pump
Area: 85.8 m2 Area: 1190.0 m2 Area: 381.7 m2 Duty: 27838 kW Duty: 120.4 kW Duty: 1158.1 kW Duty: 1.1 kW

C-80 C-81 C-82 C-83 C-87


C-84
CO2 Absorber HP Amine Flash Drum LP Flash Stripper Reflux Vessel Absorber Overhead
Make Up Storage
Volume: 177.0 m3 Volume: 75.4 m3 Volume: 443.0 m3 Volume: 14.8 m 3 K.O. Drum
Vessel
Volume: 5.7 m3 37 CMP49PFD

Synthesis Gas to PSA


E-83
(49-V-400)
28
35 36
E-80
LC
C-83
26 27 CWS CWR
FC LC C-87 95
CWS CWR
LP Condensate 72 77
93
LC

94

FC
96
87 G-83A/B
Synthesis Gas 25
C-80 LC

82
FC
PC C-82
Process Water to
Flash Gas to Steam
Methane Reformer
75
C-81 E-81A/B Battery Limits

83 78 FC
73 74

LC E-82 LP Steam

81
86 76
LP Condensate
85
E-84 84
C-84
LP Steam
LP Condensate G-82A/B/C G-81A/B

G-84
Revamp of Carbon Dioxide Recovery Plant
Amine Solution

4 SEPARATION OF COMPRESSION STAGES FROM MAIN BODY EK 2019/03/08


3 DEHYDRATION UNIT ADJUSTMENT EK 2019/03/01
2 ADJUSTMENT AFTER ACADEMIC ADVISOR MEETING EK 2019/02/23
PROCESS FLOW DIAGRAM – UNIT 49 – BASE AND 112% CASE
1 ADJUSTMENT AFTER INDUSTRIAL MEETING EK 2019/01/31
0 PFD DRAFT EK 2019/01/23 BY: E. KWAK DRAWING NUMBER REV
REV DESCRIPTION BY DATE DATE: 2019/03/01 CN49PFD 4

Figure 2. Process Flow Diagram for the Base Case and 112% Capacity Redesign

8
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

6.1. Existing Process Design Description – Kaitlin


The CO2 Removal Unit recovers CO2 using an amine solution of aMDEA and water.

aMDEA consists of n-methyldiethanolamine (MDEA) and a piperazine activator. Piperazine is an

effective CO2 absorption accelerator used in aqueous MDEA solutions. The two key processes of

the CO2 Removal Unit are the absorption of CO2 by lean amine solution and the desorption of CO2

from the rich amine solution which occur in the CO2 Absorber and LP Flash Stripper, respectively.

The absorption and desorption of CO2 by MDEA occur based on the following reactions (20):

2 H2O ⇌ H3O+ + OH-

R3N + H3O+ ⇌ R3NH+ + H2O

CO2 + 2 H2O ⇌ HCO3- + H3O+

HCO3- + H2O ⇌ H3O+ + CO32-

where R3N represents MDEA (C5H13NO2). The resulting net total reaction is:

CO2 + 2 H2O + R3N ⇌ R3NH+ + H3O+ + CO32-

These reactions determine the overall amount of CO2 that can be recovered by the unit.

The PFD of the existing CO2 Recovery Plant is shown in Figure 2. The syngas is fed to the

CO2 Absorber (C-80) at a flow rate of 8217 kmol/h and flows countercurrent against the liquid

lean amine solution. The lean amine solution removes the CO2 from the syngas and exits the

bottom of the column as rich amine solution. The syngas released from the top of the CO2 Absorber

contains less than 3 mol% CO2 and is cooled to 40 °C in the CO2 Absorber Overhead Cooler (E-

80). The condensed water is separated and removed in the Absorber Overhead Knockout Drum

(C-87) under level control. The remaining syngas exits the drum and is further treated in the PSA

9
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

unit. A small amount of LP Condensate is fed to the top of the CO2 Absorber under flow control

to avoid entrainment of amine in the overhead gas.

The rich amine solution exiting the bottom of the CO2 Absorber is directed under level

control to the HP Amine Flash Drum (C-81). Some gas is flashed off and sent to the SMR while

the remaining liquid rich amine is routed to the LP Flash Stripper (C-82). The LP Flash Stripper

consists of an upper flash section and lower stripping section.

In the flash section, CO2 is separated at an operating pressure of 40 kPa(g). The gas exiting

the top of the LP Flash Stripper contains water and 82 mol% CO2 and is cooled in the Stripper

Overhead Condenser (E-83) to 45 °C. The resulting water condensate is removed in the Reflux

Vessel (C-83) and returned to the LP Flash Stripper by the Stripper Reflux Pump (G-83A/B) under

flow control. This prevents the entrainment of amine in the stripper overhead gases. The CO2 rich

gas exiting the top of the Reflux Vessel is routed to the compressor and dehydration units before

going to battery limits. The final CO2 product stream has a 99.9 mol% purity of CO2 and flow rate

of 1188 kmol/h. This translates to 438,000 tonnes of CO2 recovered annually (2; 17).

The semilean amine solution produced in the flash section is withdrawn under level control

into a pumparound loop, where it is heated against the hot lean amine solution from the stripper

bottoms in the Lean/Rich Amine Exchanger (E-81A/B). The heated semilean amine solution is

returned under level control to the top of the stripping section of the LP Flash Stripper by the

Semilean Amine Pump (G-81A/B).

In the stripping section, the Stripper Reboiler (E-82) heats the column bottoms using low

pressure steam to 114°C at 50 kPa(g) based on a temperature control loop. The vaporized water

and CO2 gas rises countercurrent to the semilean amine solution and removes enough CO2 from

10
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

the semilean solution to regenerate lean amine solution suitable for use in the CO2 Absorber. The

lean amine exits the bottom of the LP Flash Stripper at 114 °C.

The hot lean amine solution is cooled against the semilean amine solution in the Lean/Rich

Amine Exchanger to 83°C, and then cooled to 45 °C in the Lean Amine Air Cooler (E-84). The

lean amine is routed by the HP Lean Amine Pump (G-82A/B/C) under flow control to the top of

the CO2 Absorber.

Model Verification

The ProMax simulation software by Bryan Research & Engineering (BRE) was used to

model the CO2 Removal Unit. The client provided the material balance for the design basis and

operating data summaries for select equipment which were used as the benchmark for design.

Appendix B contains detailed explanations for simulation assumptions. Appendix C shows the

calculations used to validate the simulation model. More detailed calculations on separation can

be found in Appendix D. The model was validated based on the accuracies of the property package,

separation models, heat exchanger areas, and number of compression stages.

Separation Model Verification

The separation model selected for the CO2 Absorber was the TSWEET Kinetics Model. This

model was recommended by BRE for electrolytic property package environments and for columns

where CO2 is present in one of the feed streams. The separation model used for the LP Flash

Stripper was the TSWEET Absorber/Stripper Model because it was the most accurate in modelling

the desorption of CO2 when compared to the design basis. Model verification was done using the

average absorption factor method outlined by Kremser and Brown, Robbins correlation for

pressure drop, and Eckert generalized pressure drop correlation for vapor flows (21; 22).

11
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Areas of Heat Exchange Verification

Heat exchangers in the simulation model were verified by comparing the simulated area of

heat exchange to the area of heat exchange provided in the operating data summary. The simulated

areas were within 5% of the provided heat exchanger areas indicating strong agreement.

Staged Compression Verification

Modelling of the vendor compressor unit in the simulation was validated using calculations

based on isentropic gas compression. The number of calculated required compression stages was

three, which was consistent with the obtained simulation results. The number of compression

stages used was also verified by the client.

6.2. Project Assumptions, Constraints, and Limitations


Assumptions and Constraints

The CO2 Removal Unit uses aMDEA, which was assumed to be 3 wt% piperazine activator

and 97 wt% MDEA. The amine solution makeup was assumed to be 96 wt% aMDEA and 4 wt%

water. The specifications for the inlet streams to the CO2 Absorber were provided by CNRL. These

specifications are summarized in Table 1 and shown in Appendix B. It was assumed that the molar

composition of syngas would remain constant regardless of flow rate.

12
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Table 1: Outline of Given Stream Specifications


Stream Units Syngas to CO2 Absorber Lean aMDEA
Phase Vapor -
Mass Flow kg/hr - ~ 584000
3
Volumetric Flow Nm /h 185000 -
Molar Flow kmol/h 8220 21400
Temperature °C 40 45
Pressure kPa(g) 3325 4100
CO mol % 3.3 0.0
CO2 mol % 16.6 0.2
H2 mol % 75.6 0.0
H2O mol % 2.0 90.4
CH4 mol % 4.2 0.0
N2 mol % 0.1 0.0
MDEA with activator mol % 0.0 9.4

The inlet stream compositions, pressures, and temperatures were used as constraints in the

redesign. The CO2 product stream had to have a CO2 purity of 92.0 mol% or higher for redesign.

The syngas feed to the PSA was limited to having a CO2 concentration of 3 mol% or less to prevent

corrosion issues in the downstream equipment. The 3 wt% piperazine concentration was also not

be increased in order to prevent corrosion issues. The CO2 loading for the rich amine was

recommended to be kept between 0.45 and 0.65 mol CO2/mol amine.

At the request of the client, the number of bypasses and recycles were kept to a minimum to

avoid major changes to the existing process design. Thus, bypasses and recycles were avoided as

part of the project constraints.

For modelling of the CO2 Removal Unit in ProMax, additional assumptions were needed to

achieve model convergence. These assumptions are described in detail in Appendix B.

Assumptions included the use of an adiabatic system, negligible changes in inlet and outlet

13
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

pressures for equipment where pressure drops were not specified, pump efficiencies being 90% of

the hydraulic efficiencies, compressor efficiencies of 80%, and tray weir heights of 5.08 cm (2 in).

Limitations

The simulation model used for design had limited accuracy in modelling the CO2 absorption

process, which was likely due to the property package used. A more accurate custom property

package for the CO2 Removal Unit system could not be developed or purchased due to a lack of

resources. As a result, the stated CO2 recovery efficiencies in the redesigns may have some error.

It is recommended to verify the CO2 recovery efficiencies stated in the redesigns by performing

field tests on the CO2 Absorber.

The constraints of the 112% capacity redesign were the design limits of the existing

equipment, as specified in the given equipment data or based on design calculations using the

simulated base case model. No sizing information was given for the process piping sizes, so sizing

approximations were determined using the provided material balance for the design basis. Velocity

flow limitations must be verified against the existing pipe sizes, as high velocity lines were

identified as potential risks for the 112% and 125% capacity redesigns. Limited information was

provided for the vendor compressor unit, which was approximated using a three-stage compression

process. The capacity of the vendor compressor unit would also need to be verified prior to

execution of the capacity redesigns.

Project Dependencies

The CO2 Removal Unit is a subunit of the CO2 Recovery Plant, which is part of the Hydrogen

Plant. The outlet syngas from the CO2 Absorber passes through the Absorber Overhead K.O. Drum

and is treated in the PSA. Implementing the 112% or 125% capacity redesign will result in an

increased feed flow rate of syngas to the PSA. The ability of the PSA unit to handle the increased

14
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

feed would need to be evaluated prior to project execution. The redesigns also have higher utility

usages, requiring more cooling water and electricity. This would put extra stress on the cooling

water supply and return headers and electricity power transmission lines. The capability of these

facilities to support the increased demand in utilities would thus need to be verified. The existing

amine make-up vessel is also currently sized to contain the total amount of amine circulated in the

base case for maintenance purposes. In the 112% and 125% capacity redesigns, the amine flow

rates increase, so the ability of the make-up vessel to hold the additional amine would also need to

be verified.

Technical Feasibility

The feasibility of the project is contingent upon the accuracies of the stated assumptions.

The process was simulated using the design basis provided and benchmarked using operating data

of the existing plant. Calculations used to validate equipment modifications can be found in

Appendix D. Where required, additional equipment was added with considerations given to the

space available in the existing plant as indicated by the provided plot plan. Provided that field

testing is done to verify the accuracy of the simulated CO2 Absorber efficiency, the redesigns of

the CO2 Removal Unit outlined in this study are technically feasible.

7. Option A: 125% Capacity Redesign


7.1. Process Description
The 125% capacity design increases the amount of CO2 recovered by modifying operating

pressures and temperatures and by adding and modifying equipment. The changes in operating

setpoints needed to achieve 125% operating capacity are shown by stream in Table 2. The

equipment additions and modifications are summarized in Table 3. A PFD of the 125% capacity

redesign is shown in Figure 3 and in Appendix E with associated stream tables.

15
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Table 2: Temperature, Pressure, and Flow Rate Changes for the 125% Capacity Redesign
Stream Description Base Case 125% Case
25 SG to CO2 Absorber Flow Rate 8214 kmol/h 10271 kmol/h
27 SG from CO2 Absorber OH Cooler Temperature 40.0 °C 39.0 °C
36 CO2 to Reflux Vessel Temperature 45.0 °C 41.5 °C
72 Steam Condensate to CO2 Absorber Flow Rate 122 kmol/h 130 kmol/h
86 Lean Amine from Air Cooler aMDEA Flow Rate 2018 kmol/h 2211 kmol/h
86(C) Lean Amine from Air Cooler Temperature 45.0 °C 40 °C
95 Process Condensate to LP Flash Stripper Flow Rate 142 kmol/h 116 kmol/h
- CO2 Absorber Bottom Operating Pressure 3285 kPa(g) 3300 kPa(g)
- LP Flash Stripper Bottom Operating Pressure 50 kPa(g) 55 kPa(g)

Table 3: Equipment Modifications and Additions Required for the 125% Redesign Case
Equipment Tag Description Base Case 125% Case
C-80 CO2 Absorber Packing Type IMTP #40 IMTP #25
C-80 CO2 Absorber Total Packing Height 8.6 m 10.2 m
C-82 LP Flash Stripper Packing Type IMTP #50 IMTP #40
C-83 Stripper Reflux Vessel Volume 14.8 m3 36.8 m3
C-87 Absorber Overhead K.O. Drum Volume 5.7 m3 9.7 m3
E-81A/B(/C) Lean/Rich Amine Exchanger Area 1190 m2 1785 m2
E-85A/B Lean Amine Cooler Area - 815 m2

16
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Figure 3: Process Flow Diagram for the 125% Capacity Redesign


17
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

In the 125% capacity redesign, the process flow remains largely the same as the base case.

The only change is the addition of a Lean Amine Cooler (E-85A/B) downstream of the Lean Amine

Air Cooler (E-84). Like the base case design, the hot lean amine solution is cooled against the

semilean amine solution in the Lean/Rich Amine Exchanger (E-81A/B/C). The lean amine is then

air cooled to 40 °C in the Lean Amine Air Cooler and flows to the Lean Amine Cooler which cools

the lean amine to 34.7 °C. The HP Lean Amine Pump (G-82A/B/C) is still used under flow control

to pump lean amine to the top of the CO2 Absorber (C-80). In the 125% capacity redesign, the

amount of CO2 product produced is 1435 kmol/h. This is a 20.9% increase from the base case CO2

output of 1187 kmol/h.

CO2 Absorption

The operating pressure at the bottom of the CO2 Absorber (C-80) is increased to raise the

partial pressure of CO2 in the column. The flow rate of aMDEA fed to the column is increased to

allow for better wetting of the packing to increase the effective area for mass transfer in the CO2

Absorber, further increasing absorption rates. The temperature of the lean amine stream is also

lowered to compensate for the heat generated by the exothermic absorption process. These factors

all improve the mass transfer of CO2 to amine solution, increasing the absorption rate of the CO2

Absorber (23). To further increase absorption rates, the existing IMTP #40 packing in the column

is replaced with IMTP #25 to increase the effective area for mass transfer by a factor of 1.4 (22).

The packing height is also increased by 0.8 m in both beds to accommodate an additional 12.1 m3

of packing to further increase the effective area for mass transfer. These changes improve the

efficiency of the CO2 Absorber and maintain a CO2 concentration just below 3.00 mol% in the

outlet syngas. Note that the Absorber Overhead Knockout Drum (C-87) must be upsized in order

to accommodate the increased overhead flow rates and condensate produced.

18
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

CO2 Desorption

To effectively regenerate lean amine, the packing type in the LP Flash Stripper (C-82) is

changed to IMTP #40 to allow for better stripping of the CO2 from the semilean amine solution.

The bottom operating pressure of the stripper is increased to 55 kPa(g) to accommodate for the

increased pressure drop caused by the smaller packing type. The required flow rate of water recycle

to the LP Flash Stripper for tray backwashing is reduced due to the improved separation efficiency

of the column. An additional exchanger is added to the Lean/Rich Amine Exchanger (E-81A/B/C)

to recycle more cooling duty in the hot lean amine stream. This minimizes the size of the new Lean

Amine Cooler (E-85A/B). Note that the Reflux Vessel (C-83) must be upsized in order to

accommodate the increased overhead flow rates.

Design Considerations

No further increases in operating capacity were investigated beyond the 25% increase due

to project time constraints and concerns regarding the economic feasibility of design. The 125%

redesign also uses a CO2 loading factor of 0.71 mol CO2/mol amine. This is 0.06 higher than the

recommended limit but is still within the maximum equilibrium CO2 loading capacity of 1.0 mol

CO2/mol amine (24). However, this may cause corrosion issues and should be further evaluated

if implementation of the 125% capacity redesign is pursued. The 125% capacity redesign outlined

in this study is not economically feasible due to the large capital costs for equipment. Further

increases in capacity would likely require more equipment modifications and be less economically

feasible.

Start-Up and Shutdown Considerations

It is recommended to perform a passivation procedure on the Lean Amine Cooler (E-85A/B)

shell after cleaning and prior to commissioning to protect the carbon steel shell from corrosion.

19
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Modifications to the existing start-up and shutdown procedures will also be needed to include the

Lean Amine Cooler (E-85A/B). These changes are outlined in Appendix F.

7.2. Heat Integration


The redesign of the CO2 Removal Unit is classified as a brownfield project. The existing

plot plan was provided, and it had been requested to keep the addition of recycle and bypass

streams to a minimum. Due to limitations in space and restrictions on stream flexibility, the

existing integrated heat exchanger system was optimized instead of proposing a new network.

There are four main process streams that require the addition or removal of heat which are

summarized in Table 4.

Table 4: Summary of Streams Requiring Cooling or Heating for Heat Integration


Stream Stream Description Cooling or Heating Duty Required
(MW)
26 SG from CO2 Absorber Cooling 0.35
35 CO2 from LP Flash Stripper Cooling 2.19
78 Semilean Amine from LP Flash Stripper Heating 27.06
83 Lean Amine from LP Flash Stripper Cooling 31.71

The existing heat integration system transfers heat from the hot lean amine (Stream 83) to

the semilean amine (Stream 78) through the Lean/Rich Amine Exchanger (E-81A/B) in the

pumparound loop. As the semilean amine is heated and returned to the LP Flash Stripper, some of

the cooling duty required by the hot lean amine is reduced.

To optimize energy input into the 125% case, heat exchange in E-81A/B is maximized by

adding a third unit (E-81C). This is more cost-effective than using two separate heat exchangers

for cooling and heating using cooling water and steam. Although this configuration is not able to

provide the full cooling duty required by the lean amine stream, it reduces the duty of the new

20
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Lean Amine Exchanger (E-85A/B) by 8.9 MW which significantly reduces its size and the amount

of cooling water required.

7.3. Material and Energy Balances


The material and energy balances for the 125% case are summarized below in Table 5 and

Table 6. Detailed balances which include the breakdown of the compressor unit energy

consumption are presented in Appendix G. The envelope used for all material and energy balances

is the box shown in Figure 1 which outlines the project scope. The material and energy balances

close with negligible percent differences, indicating that both mass and energy were conserved.

Table 5: 125% Case Overall Material Balance


Material In Material Out
Stream Name Description
(kmol/h) (kmol/h)
25 SG to CO2 Absorber 10271.0 -
Amine Makeup Amine Makeup 1.9 -
IN

Water Makeup Water Makeup 0.1 -


72 Steam Condensate to CO2 Absorber 130.0 -
28 SG from CO2 Recovery Unit - 8813.6
38 CO2 to Dehydration Unit - 1447.9
75 Flash Gas from HP Amine Flash Drum - 17.0
Process Condensate to BL Process
OUT

96 -
Water Header 36.7
Amine Blowdown Amine Blowdown - 0.0
Water Blowdown Water Blowdown - 0.0
37C Stage 1 Compressor K.O. Vessel - 64.9
37G Stage 2 Compressor K.O. Vessel - 23.0
Total (kmol/h) 10403.1 10403.0
Percent Difference 0.0%

21
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Table 6: 125% Case Overall Energy Balance


Energy In Energy Out
Stream Name Description
(kW) (kW)
25 SG to CO2 Absorber -206,676 -
Amine Makeup Amine Makeup -211 -
IN

Water Makeup Water Makeup -12 -


72 Steam Condensate to CO2 Absorber -10,258 -
28 SG from CO2 Recovery Unit - -48,497
38 CO2 to Dehydration Unit - -158,205
75 Flash Gas from HP Amine Flash Drum - -1,090
Process Condensate to BL Process
OUT

96 - -2,898
Water Header
Amine Blowdown Amine Blowdown - 0
Water Blowdown Water Blowdown - 0
37C Stage 1 Compressor K.O. Vessel - -5,124
37G Stage 2 Compressor K.O. Vessel - -1,822
E-80 CO2 Absorber Overhead Cooler - 1,107
E-82 Stripper Reboiler 31,600 -
E-83 Stripper Overhead Condenser - 2,190
EQUIPMENT

E-84 Lean Amine Air Cooler - 24,870


E-85A/B Lean Amine Cooler - 3,467
G-81A/B Semilean Amine Pump 123 -
G-82A/B/C HP Lean Amine Pump 1,185 -
G-83A/B Stripper Reflux Pump 1 -
Compressor Unit - 1825
Total (kW) -152,103 -152,047
Percent Difference 0.0%

7.4. Equipment List and Sizing


The detailed list of equipment for the 125% case and sizing calculations are presented in

Appendix H. Operating data provided by the client for select pieces of equipment are also included

in this appendix. Methodologies from Gas Processors Suppliers Association (GPSA) Engineering

Data Book, Perry’s Chemical Engineers’ Handbook, and Process Heat Transfer by Kern (1950)

were employed in the sizing of equipment. Equipment sizing is preliminary and performed to the

22
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

level required for economic evaluation except for the Lean Amine Cooler (E-85A/B). Detailed

design of this exchanger is shown in Appendix I.

Columns

The two main columns in the process are the CO2 Absorber and the LP Flash Stripper.

Column separation efficiencies, tray spacings, and packing, disengagement, and liquid pool

heights were validated for the existing column heights and diameters. These calculations can be

found in Appendix D. The additional separation capacities required for redesign were satisfied by

changing the type and volume of packing in the existing columns. Increased pressure drops were

resolved by increasing the operating pressures.

Table 7: Summary of Column Specifications


Diameter Length Volume Material of
Tag Item Description Quantity
(mm) (mm) (m3) Construction
CO2 Absorber Shell 3100 23500 177 CS
C-80
IMTP #25 Packing 77 SS 316
Montz-Thormann Tray 3 SS 316
LP Flash Stripper Shell 3800 39100 443 CS/SS 316L
C-82
IMTP #40 Packing 181 SS 316
Montz-Thormann Tray 3 SS 316

Heat Exchangers

The use of existing heat exchangers was maximized in the 125% capacity redesign. The heat

transfer coefficients of the existing exchangers were derived using operating data and were used

to calculate the heat exchanger areas required for redesign. Part of the increased cooling duty

required in the 125% redesign is met by adding a third plate and frame heat exchanger E-81C (595

m2) to the Lean/Rich Amine Exchanger (E-81A/B). This is a very compact unit, so the footprint

required is minimal compared to a shell and tube heat exchanger. The remaining cooling duty

required is supplied by the additional Lean Amine Cooler (E-85A/B). The temperature difference

23
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

required two shell passes and four tube passes which are met by two 1-2 heat exchangers with U-

tube bundles placed in series. This eliminates gaskets that are prone to leaking and minimizes the

footprint required, as the exchangers are stacked on top of each other. A temperature transmitter

with a high temperature alarm set at 45°C is located on the lean amine outlet. At 45°C, the CO2

concentration is significantly higher than 3 mol%, resulting in potential corrosion issues in the

PSA unit. The temperature transmitter is also used in conjunction with a control valve to set the

flow rate of cooling water to the heat exchanger. The existing flow transmitter located downstream

of the Lean Amine Cooler is used to control the flow rate of lean amine to the CO2 Absorber.

Table 8: Summary of Heat Exchanger Specifications


Duty Area Material of
Tag Description Type
(MW) (m2) Construction
CO2 Absorber Shell: SS 316L
E-80 Shell and Tube 0.2 86
Overhead Cooler Tube: SS 316L
Lean/Rich Amine
E-81A/B/C Plate and Frame 27.0 1785 SS 316L
Exchanger
Shell: CS
E-82 Stripper Reboiler Kettle Reboiler 31.6 1150
Tube: SS 316L
Stripper Overhead Shell: SS 316L
E-83 Shell and Tube 2.2 382
Condenser Tube: SS 316L
E-84 Lean Amine Air Cooler Air Cooler 24.8 - CS
Shell: CS
E-85A/B Lean Amine Cooler Shell and Tube 3.5 813
Tube: SS 316L

Vessels

The vessels for this process are primarily used for vapour-liquid phase separation. The

existing HP Amine Flash Drum (C-81) was sufficient for operation at 125% capacity. However,

the Absorber Overhead K.O. Drum (C-87) and Reflux Vessel (C-83) required larger diameters to

achieve effective separation at the increased flow rates. The gravity settling approach and Souders-

24
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Brown approach were used to determine the minimum dimensions required to obtain effective

separation. Vessel thickness was calculated according to ASME Section VIII Division 1.

Table 9: Summary of Vessel Specifications


Diameter Length Volume Thickness Material of
Tag Description
(mm) (mm) (m3) (mm) Construction
C-81 HP Amine Flash Drum 2200 19840 75 11.4 CS/ SS 316L
C-83 Reflux Vessel 2500 7500 37 4.3 SS 304L
Absorber Overhead
C-87 1600 4800 10 30.1 CS
K.O. Drum

Pumps

Pump capacities as well as maximum and minimum pressures were maintained within the

allowable ranges stated in the operating data given by the client for the 125% capacity redesign.

No additional pumps were required for this case. However, the power consumption of the pumps

increased slightly due to more shaft power being required at higher flow rates. Overall pump

efficiencies were assumed to be 90% of hydraulic efficiencies given by the client.

Table 10: Summary of Pump Specifications


Total
Shaft
Dynamic Overall Material of
Tag Description Type Power
Head Efficiency Construction
(kW)
(m)
G-81 Semilean Amine Pump Centrifugal 123.1 47 67.5% SS 316L
G-82 HP Lean Amine Pump Centrifugal 1156.0 410 59.4% SS 316L
G-83 Stripper Reflux Pump Centrifugal 1.0 49 36.0% SS 304L

Compressors

In the PFD provided by the client, the compression of CO2 was shown as a single vendor

unit with a note stating that compressors, interstage coolers, and knockout drums were included.

Due to the lack of information, the vendor compressor unit was approximated using the three-stage

25
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

compression process shown in Appendix E based on calculations shown in Appendix C. If the

required compression could be achieved within three stages, it was assumed that the existing

vendor unit was sufficient. In the 125% capacity redesign, only three stages of compression were

needed, so the vendor unit was deemed to be sufficient. The maximum allowable discharge

temperature used for the compressors was 150°C based on GPSA recommendations (21).

Table 11: Summary of Compressor Specifications


Fluid Discharge
Compression Polytropic Material of
Tag Description Power Temperature
Ratio Efficiency Construction
(kW) (°C)
CO2 Product
K-100 1831.0 3.1 80.0% 150 SS 316L
Compressor 1
CO2 Product
K-101 1699.6 3.0 80.0% 150 SS 316L
Compressor 2
CO2 Product
K-102 1540.6 2.9 80.0% 147 SS 316L
Compressor 3

Process Piping

Information on the existing process pipe sizes was not provided by the client. Due to the lack

of information, the existing pipe sizes were approximated using the material balance for the design

basis provided by the client, taking into consideration pressure drops for single-phase and two-

phase flow, pump suction lines, and guidelines for minimizing erosion-corrosion in amine units.

Based on the flow rates in the 125% capacity redesign, the piping fluid velocities are mostly within

acceptable ranges indicating that existing piping sizes are sufficient. However, streams 35, 36, and

37 were found to have expected velocities above recommended values. A table listing the nominal

pipe size, schedule, material specification, expected velocity, and type of flow through all main

process lines can be found in Appendix H. Calculations for the process lines sizing are also

included in this appendix.

26
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Materials of Construction

Detailed analyses of the material selection and corrosion mechanisms identified for this

project can be found in Appendix H. In the CO2 Removal Unit, the primary degradation

mechanism is amine corrosion. Amine corrosion refers to the general or localized corrosion that

occurs primarily on carbon steel in amine treating processes. It results from dissolved acid gases

(e.g. CO2), amine degradation products, heat stable amine salts and other contaminants (25; 26).

Low-carbon and stabilized grades of austenitic steels have successfully been used in areas of high

corrosion rates due to their high strength and corrosion resistance over a wide range of operating

conditions.

To protect against amine corrosion, corrosion prone areas were constructed out of ASTM

A358 Type 304L and Type 316L stainless steel. Corrosion prone areas were identified as regions

having high acid gas loading, high flow velocities, turbulent flow, flow impingement, vapour

flashing, two-phase flow, and operating temperatures over 110 °C. Regions with low acid gas

concentrations or lower operating temperatures were less prone to amine corrosion. These regions

were constructed of ASTM A106 Grade B carbon steel, which costs less but still has high strength.

ASTM A333 Grade 6 killed carbon steel was used at the bottom of the LP Flash Stripper due to

higher operating temperatures. Type 316L stainless steel has higher corrosion resistance in

chloride containing environments, so it was preferentially selected for equipment and lines

circulating process or cooling water (27).

7.5. Utility Requirements


Table 12 summarizes the additional utility requirements need to support 125% operating

capacity. The calculations used to determine these values are presented in Appendix J. The

additional utility requirements for the 125% capacity redesign include increased cooling water

27
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

demands for heat exchangers and higher electricity usages for the pumps, air cooler, and

compressors. CNRL is currently purchasing about 70 MW from the Alberta power grid (16).

Therefore, the additional electricity requirements for the 125% capacity redesign were assumed to

be purchased from the Alberta power grid.

Cooling water will be recycled and reused throughout the operation to minimize water intake.

Any additional water utility required is sourced from the Athabasca River (28). Since the duty of

the Stripper Reboiler (E-82) is the same as the base case, no additional steam was required.

Additional makeup amine was required due to the increase in the amount of amine circulating. The

makeup amine in the base case was 0.00006% of the total flow rate, which was the same percentage

used in the 125% capacity redesign to estimate makeup amine requirements.

Table 12: Additional Utility Requirements for 125% Capacity Redesign


Utility Makeup Amine Electricity Cooling Water
Comparison (kg/h) (kWh) (m3/h)
Base Case Usage 0.135 5483 566
125% Case Usage 0.148 6634 931
Increase from Base Case 0.013 1151 365

7.6. Project Execution Strategy


Successful completion of an engineering project relies heavily on a well-developed project

execution strategy. The Direct Field Labour (DFL) hours calculated using the equipment purchase

costs and the average hourly rates for labour were used to plan an appropriate design to

commissioning timeline. The project execution strategy is composed of four distinct stages, which

are engineering, procurement planning, construction, and commissioning. The detailed timeline

for this project is outlined in Figure 4, with critical path items indicated in red. The project is

estimated to take 23 months from the start of engineering to the full operation of the facility.

28
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Figure 4: Project Execution Schedule


29
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Engineering Plan

The engineering timeline of this project is composed of three phases. The first phase is the

Basis of Design (BOD), which is the development of the project scope, design basis memorandum,

block flow diagram, and completion of research for technological evaluation. The second phase is

Front End Engineering Design (FEED), which requires the completion of the process simulation,

PFD, P&ID, plot plan, preliminary sizing and economics, and preliminary safety and risk analyses.

The BOD and FEED phases taken together make up the basic engineering design, which is 3

months of the total engineering timeline. Upon completion of the BOD and FEED phases, the

design proposal is submitted to the client for review. Once approved, the third phase begins, which

is detailed engineering. Based on the current project timeline, detailed engineering design would

commence in April 2020. This phase involves the work of various engineering disciplines,

including process drawings, structural and mechanical designs for all major pieces of equipment,

detailed piping designs, electrical instrumentation and control designs, and Hazard and Operability

Studies (HAZOPs). The estimated duration for the detailed engineering phase is 4 months.

Procurement Plan

The procurement plan will commence upon the completion of the engineering plan which

occurs in August 2020. The procurement plan outlines procedures for vendor selection, equipment

ordering and fabrication, equipment transportation and logistics, and labour acquisition. Vendor

selection and quote acquisition is selected carefully based on the project being primarily cost

driven as opposed to schedule driven. To maximize the economics of this project, a competitive

bidding process will be conducted for each piece of equipment that is ordered. To minimize the

project execution time, the procurement phase overlaps with the engineering phase and bidding

begins while the detailed engineering phase is still in process. The total duration of the procurement

30
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

plan is estimated to be 8 months from the onset of the bidding process to the onsite delivery of the

final piece of equipment.

Construction Plan

This phase involves the installation of equipment, piping, instrumentation, and electrical

components along with initial equipment testing and inspection. The equipment installations and

modifications required must be done while the CO2 Recovery Plant is in shutdown. Construction

work is thus scheduled during the annual sitewide Horizon Oil Sands outage that occurs in

September. A significant amount of field work is completed during this time. Proper planning and

coordination of the CO2 Removal Unit work scope with other site work is thus expected to take 3

months. Construction planning is scheduled to begin on March 25, 2021 with construction work

beginning on September 7, 2021. The replacement of packing in the columns is estimated to take

the longest amount of time due to the welding and post weld heat treatment required for the support

rings. Installation of the heat exchangers and drums is expected to take less time as they are

installed as pre-assembled modules. The total duration is expected to be 7 months.

Commissioning Plan

Upon the completion of the construction phase of the project, the commissioning of the

facility will commence on October 2021. This final stage of the project timeline involves the final

equipment testing and monitoring such that it meets all applicable safety and environmental

regulations. Production testing and troubleshooting is done onstream after start-up of the unit. This

phase is expected to be 4 months in duration, and the project is scheduled to close by December

2021.

31
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Project Management Schedule


The total fixed capital expenditure is divided into engineering, procurement, and

construction phases. Detailed calculations made to obtain the capital expenditure and manpower

profiles for the project management schedule are presented in Appendix K. As shown in Section

7.7.2, the engineering expense of the project is 18% of the total module cost plus contingency,

prorated based on the estimated fixed capital expenditure. The calculated DFL hours for this

project is approximately 86,000 hours based on the DFL cost of C$5.43 MM at a base labour rate

of $36 per hour. Using the relationship presented in K.M. Guthrie (1974), this number of DFL

hours gives an onsite construction duration of approximately 12 months when taking into account

the winter location factor and the limited construction work being done during that time (29).

Figure 5 displays the manpower distribution for labour and engineering throughout the project

timeline.

Figure 5: Manpower Distribution for Engineering and Labour

32
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

7.7. Economic Analysis


Economic Introduction

The economic feasibility of the 125% capacity redesign was largely determined based on

the net present value (NPV) and internal rate of return (IRR). A discounted cash flow analysis was

also used to determine the economic feasibility of the project. The economic analysis outlined in

this report is a Class 4 preliminary cost estimation as defined by the Association for the

Advancement of Cost Estimating (AACE) with an accuracy of -30% to +50% (30). Detailed

calculations, tables, and assumptions for the project economics can be found in Appendix J. The

economic analysis for this project is based on the difference in the amount of CO2 recovered

compared to the base case. It is assumed that all additional CO2 recovered can be sold. The goal is

to have the increased revenue from the additional CO2 recovered pay off the initial investment and

additional operating costs for the 20-year project lifetime. CNRL uses 50% of the current CO2

produced for their Non-Segregating Tailings process (31). This value was assumed to be static

across the capacity redesigns based on client input and was thus not factored into the revenue

calculations. Additionally, the infrastructure used to export the CO2 by truck is assumed to already

be in place. Unless otherwise specified, all prices are expressed in Canadian dollars.

Fixed Capital Expenditure

All equipment was costed using the equipment based costing method outlined in Ulrich &

Vasudevan except for the IMTP random packing for the CO2 Absorber (C-80) and LP Flash

Stripper (C-82) (32). The packing was costed based on quotes provided by Koch-Glitsch. Figure

6 displays the breakdown of the total fixed capital expenditure of $13.42 MM. The breakdown of

the equipment purchase cost and the detailed calculations used to estimate the capital costs for this

project are included in Appendix J. Guidelines from the Electric Power Research Institute (EPRI)

33
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

were referred to when determining the contingencies for the project (33). The process contingency

was 0% because the process is already in commercial use and well studied, as it is an existing plant.

The proposed 125% capacity redesign is considered to be at the preliminary stage. Thus, the project

contingency used was 40%. A 7% contractor fee, 18% engineering and procurement cost, 3%

owner’s cost, and 4% commissioning and start-up cost were also applied to obtain the total fixed

capital cost of the project (33). An exchange rate of 1.33 was used to convert from USD to CAD

(34). The target Chemical Engineering Plant Cost Index (CEPCI) from November 2018 was 616.4,

with a base reference of 2004 with a CEPCI of 400 (35).

Figure 6: Fixed Capital Expenditure Breakdown

7.7.2.1. Location Effects


The DFL analysis is outlined in Appendix J and lists the justifications and weightings for

each DFL factor used. A factor of 1.25 was applied to the US Gulf Coast estimates to account for

the Alberta location. Since the project site is located in Fort McMurray, an additional Fort

McMurray adjustment factor of 1.25 was applied. A winter work factor of 1.30 was applied to

34
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

account for reduced productivity from November 31 to March 1 (36). Limited work will be done

during the winter based on the project schedule, so the percent applicability was limited to 5%.

7.7.2.2. Field vs. Shop Fabrication


Shop fabrication is preferred for this project as it would reduce the project execution time.

Modular installation of equipment, such as heat exchangers and drums, is faster than onsite

fabrication. Shop fabrication can also produce higher quality fabrication through the use of

specialized machining equipment that cannot be brought to site. The heat exchangers and drums

required for the 125% capacity redesign will be delivered to site in pre-assembled modules to allow

for efficient installation during the outage period. This method is also economically beneficial as

the labour force required onsite is reduced. Installation of the packing support rings in the CO2

Absorber (C-80) cannot be done in the shop. The support trays will have to be shipped in and then

welded into the column onsite during the outage, requiring some degree of field fabrication.

Working Capital Expenditure


The working capital cost of this project was estimated based on the amount of additional raw

materials and spare parts inventory required to keep the facility in operation. The recommended

range for working capital expenditure was 10 to 20% of the fixed capital expenditure (32). Since

the CO2 Removal Unit is relatively small and the 125% capacity redesign does not add a significant

number of equipment, the working capital is chosen to be 10% of the total fixed capital, which in

this case is $1.34 MM. The loss in amine solution due to operation is also minimal, which also

justifies a smaller working capital estimation.

Operating Cost
Appendix J includes the detailed calculations, assumptions, and tables made to estimate the

operating expenditure for the 125% capacity increase. The prices of utilities used to calculate the

35
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

operating cost were provided by the client and are shown in Table 13. Figure 7 presents the

operating cost breakdown in the form of a pie chart. Percentages from Ulrich & Vasudevan were

adjusted based on the project circumstances to calculate the direct, indirect, and general expenses

(32). The increase in annual operating cost for the 125% capacity redesign compared to the base

case was determined to be $4.51 MM.

Table 13: Utility Cost Summary


Utility Unit Cost Additional Annual Expense
(x103 $)
Makeup Amine $12.25/kg 1.3
Electricity $0.12/kWh 840
Cooling Water $0.07/m3 206

Figure 7: Operating Cost Breakdown for the 125% Capacity Increase

The sources of revenue for this project are the sale of CO2 production to other facilities and

the cost savings generated from having to purchase fewer GHG emissions credits. The market

demand for CO2 in the Fort McMurray region is from other oil and gas facilities who use CO2 for

EOR or CCS initiatives. The sale price of CO2 has historically been between $12 and $35 /tCO2

36
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

(18). Based on this range, the price of CO2 used to calculate revenue was chosen to be $23 /tCO2.

GHG emissions credits are currently priced at $30/tCO2e, which was the value used to determine

revenue. The resulting estimated annual revenue was $5.09 MM.

Financing Plan
Since this project is sponsored by CNRL, financing costs are not included as part of the

capital budget. CNRL is a large company with a steady cash flow profile and is assumed to have

sufficient capital to fund the project using their own resources. There would be no need for loans

from banks or private companies. Therefore, an investment schedule was not developed for this

project.

Discounted Cash Flow Analysis


Figure 8 displays the project cash flow diagram over the 20-year project lifetime. Detailed

calculations and cash flow tables are presented in Appendix J. A corporate discount rate of 15%,

hurdle rate of 20%, inflation rate of 3%, and provincial income tax rate of 27% were used. The

Capital Cost Allowance (CCA) was 15% for the first operating year and 30% for every subsequent

year based on process plants which fall under Asset Class 43 (37).

Figure 8: Discounted Cash Flow Profile for the 125% Case

37
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Sensitivity Analysis
The sensitivity analysis was conducted to determine which factors have the greatest impact

on the project’s economic feasibility. Figure 9 and Figure 10 illustrate the sensitivity analysis

results with respect to NPV and IRR, respectively. Fixed capital, operating cost, and utility unit

prices were varied by 10% to investigate their effects on the NPV and IRR. Since the onstream

factor cannot be greater than 1.0, a variation of 5% from the assumed 0.92 value was used. The

sale price of CO2 and cost of GHG emissions credits were also varied. The historical range for the

sale price of CO2 was $12 to $35 CAD /tCO2, so these boundaries were taken as the lower and

upper limits of the variable (18). To account for the possibility of GHG emissions credits rising

from $30 /tCO2e to $50 /tCO2e due to the federal climate plan, $50 /tCO2e was taken as the upper

limit. At a price of $12 /tCO2, an IRR could not be obtained due to divergence. The figures show

that the variation in onstream factor and utility prices are shown to have little effect on both the

project NPV and IRR. The most influential parameters are the price of GHG emissions credits and

sale price of CO2.

Figure 9: NPV Tornado Diagram for the 125% Case

38
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Figure 10: IRR Tornado Diagram for the 125% Case

Economic Conclusions
The 125% capacity redesign is not economically feasible. The increase in revenue is not

enough to offset the initial fixed and working investments of $13.42 MM and $1.34 MM,

respectively. This ultimately results in a negative NPV of -$10.69 MM and negative IRR of -0.36%.

Assuming the GHG emission credit price remains at $30 /tCO2e, a CO2 sale price of C$49 /tCO2

would be needed to achieve economic feasibility at a hurdle rate of 20%. Considering that the unit

is producing commercial grade CO2 and that this price is outside of the historical range, this price

is highly unlikely to occur in the near future (18). However, it may be worthwhile to re-evaluate

this option if the carbon tax or CO2 market selling price changes substantially under different

regulatory scenario.

7.8. Environmental Analysis


The only waste streams identified for the CO2 Removal Unit are fugitive emissions of

vapours from equipment due to irregular venting or unintended release such as leaks. These

39
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

fugitive emissions are small in comparison to leakage emissions from mine faces, tailings ponds,

and other facilities onsite. No additional reporting requirements are necessary under the Specified

Gas Reporting Regulation under the Climate Change and Emissions Management Act (38; 39).

CNRL participates in local and regional monitoring programs to ensure a high standard of

air quality for its stakeholders (40). CNRL is an active participant in the Wood Buffalo

Environmental Association which continuously monitors a number of air pollutants, including

NOX, SOX, volatile organic compounds, and particulate matter (41). There is no expected increase

in these parameters as a direct result of this project. Consequently, no changes to existing and

approved air quality under the Alberta Ambient Air Quality Objectives and Guidelines is expected

(42).

Increasing the capacity of the CO2 Removal Unit would reduce the overall GHG emissions

in the upgrader facility, which is a key environmental metric for this project. The 125% redesign

case captures 95,453 tCO2e/yr more than the “do nothing” alternative, which is equivalent to

removing approximately 20,750 passenger vehicles from the road (43). The increased CO2

recovery would help slow the rate at which global warming is occurring, slowing the increase in

global mean temperatures. It would also contribute to CNRL’s goal of reducing their emissions

intensity to below the global crude average (13). Further studies would be required to determine

the overall net GHG emissions reduction that is achieved when taking into account other units

affected by the feed flow rate increase, such as the PSA unit and downstream dehydration unit.

Supporting the increased utilities requirements may also affect the net GHG emissions reduction.

The increased CO2 recovery would also have large implications in terms of the cost of the

carbon levy imposed on GHG emissions by the Climate Leadership Regulation under the Climate

40
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Leadership Act, and enforced by the Carbon Competitiveness Incentive Regulation under the

Climate Change and Emissions Management Act (44; 45; 5; 39).

The Water Act Licence No. 00186921-01-00 for CNRL enforces a maximum diversion rate

of 66.1 MMm3/yr of water from surface water sources, which is equivalent to drawing 3.1 m3/s of

water from the Athabasca River (46). The 125% redesign case would increase the cooling water

requirements of the CO2 Removal Unit by 0.101 m3/s. This marginal increase is not likely to be an

issue. However, limited information was provided regarding the current water draw from surface

water sources. Further study would be required to assess the impact of the additional cooling water

requirements, with consideration given to periods of low-flow in the Athabasca River.

Environmental Conclusions
The proposed project will meet or exceed all applicable environmental regulations and will

recover 95,452 tCO2e/yr more than the “do nothing” case. The project will demonstrate a strong

commitment to environmental stewardship by CNRL and contribute to the environmental

sustainability of the oil sands industry. Furthermore, the project would contribute to CNRL’s long-

term goal of reducing emissions intensity, which is a significant environmental driver for this

project. Additional studies would be needed to determine the net impact on Horizon Oil Sands’

overall GHG emissions, taking into account the other units at the facility which are outside of this

project scope.

7.9. Safety and Risk Analysis


Proper identification, evaluation, and management of risk is necessary to mitigate health,

safety, environmental, legal, financial, and social consequences. Risk management methodologies

were conducted according to the “Guideline for Management of Risk in Professional Practice”

published by the Association of Professional Engineers and Geoscientists of Alberta (APEGA)

41
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

(47). For this project, several different hazard identification methods and risk assessment tools

were utilized, including: a What If? Process Hazard Analysis (PHA), a HAZOP, and analysis of

the DOW Fire and Explosion Index (F&EI) and Chemical Exposure Index (CEI). The complete

safety and risk assessment can be found in Appendix L.

Identification of Hazards and Safety Risks


A checklist PFD based analysis was conducted during the early stages of the project to

identify the potential hazards and safety risks for all process equipment and streams. Primary

process hazards identified from the checklist PFD based analysis included overpressurization of

equipment resulting in leakage or rupture, increased erosion in piping due to higher flow velocities

in the capacity redesign cases, and loss of containment of syngas with the potential for fire or

explosion.

What If? Process Hazard Analysis


A “What If? Analysis” PHA was conducted on the PFD to identify high-level hazards in the

CO2 Removal Unit. The PFD was divided into four nodes based on commodity streams. The

hazards identified using the checklist PFD based analysis were used to guide the formulation of

several What If? questions, which described different hazardous scenarios that could occur within

each node. The causes and consequences of these hazards were quantitatively evaluated using the

CNRL corporate risk matrix. An initial risk rating was assigned to each hazardous scenario

assuming no safeguards or controls were in place. This was then re-evaluated based on the

engineering safeguards and administrative controls assumed to be in place at Horizon Oil Sands.

After the safeguards and controls were accounted for, recommendations for further risk reduction

were developed for hazards that had unacceptable or conditionally tolerable levels of residual risk.

The full What If? analysis and PHA worksheets can be found in Appendix L.

42
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Hazard and Operability Study


A HAZOP was completed on the P&ID created for the Lean Amine Cooler (E-85A/B) to

analyze the risks introduced by the new piece of equipment. The complete HAZOP analysis as

well as the full list of recommendations and implications can be found in Appendix L. Process

deviations that could occur due to unexpected operating conditions were evaluated for four

operating states, including commissioning, steady state, start-up, and shutdown. The causes,

consequences, and risk rating evaluation were then completed using the method described in

Section 7.9.2.

Engineering safeguards were incorporated into the design of the Lean Amine Cooler to keep

residual risks at an as low as reasonably practicable (ALARP) level. The safety and control

mechanisms designed for the Lean Amine Cooler are shown in the P&ID in Appendix E. Two

pressure relief devices were designed according to the American Petroleum Institute Standards

520 and 521, and methods outlined in GPSA. The set pressure of the pressure safety valve (PSV)

located on the cooling water return line is 1354 kPa(g) and was designed to protect against

overpressurization caused by the vaporization of cooling water during blockage. The set pressure

on the pressure relief valve (PRV) located on the lean amine inlet is 6044 kPa(g) and was designed

for thermal relief in the event that the lean amine temperature rises and results in thermal expansion

of the fluid. Detailed PSV and PRV sizing calculations can be found in Appendix M. Two double

block and bleed valves located on the outlet streams and four block valves located on all four

corners ensure that the exchanger can be properly isolated and depressurized for maintenance or

cleaning. A vent and drain were placed on the high and low points of the exchanger to allow the

process fluids to be evacuated.

43
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Other safeguards identified for the Lean Amine Cooler included the verification of the

correct valve failure response positions, proper material selection, and use of a comprehensive and

frequent inspection, cleaning, and equipment maintenance program. Other recommendations from

the HAZOP analysis included evaluation of the identified high velocity lines, and updating of the

existing operating, start-up, and shutdown procedures to include the modifications listed in the

125% capacity redesign. Additionally, the CO2 loading factor for the 125% capacity redesign is

0.71 mol CO2/mol amine, which is 0.06 higher than the recommended maximum loading factor of

0.65 mol CO2/mol amine. This should be evaluated for any potential impacts on equipment

reliability or performance.

Chemical Exposure Index


The feed stream for the CO2 absorption process contains syngas, which contains carbon

monoxide and is known to be flammable and toxic at ambient conditions. In a process breach

scenario, this could potentially be released into the atmosphere, posing a severe risk to the health

and safety of nearby personnel. A Dow CEI was calculated around stream 26, which had the

highest temperature, pressure, and concentration of carbon monoxide. All relevant calculations

can be found in Appendix L. It was found that a rupture in this stream would result in the largest

airborne release of gas. ERPG-1 is not included in the analysis since it is an odorless gas. Table

14 shows the CEI and the hazard distances for ERPG-2 and ERPG-3 for the base case compared

to the 125% design case. Figure 11 shows the exposure radii to scale.

Table 14: Chemical Exposure Index Summary Table


Cases Base Case 125% Design Case
Chemical Exposure Index 164.9 184.4
ERPG-2 (m) 1649 1844
ERPG-3 (m) 1382 1545

44
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Figure 11: Chemical Exposure Radii by ERPG Level Overlaid on Satellite Imagery for the 125%

Case

Emergency contingencies should be in place to evacuate individuals within the ERPG-2

hazard radius. As shown in Figure 11, the radius is limited to the eastern quadrant of the Horizon

Oil Sands plant. However, the outer radius of both ERPG-2 and ERPG-3 breach the administrative

building where most of the personnel would be located. The radius of ERPG-2 does not extend

beyond the site so there are no immediate risks to communities nearby the site, but communities

and counties nearby should be notified so that encroachment does not occur.

The exposure radii are based on the assumption of a five-minute continuous release.

Considering that the area of operation is located outdoors, the carbon monoxide would most likely

45
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

dissipate into the atmosphere as soon as a breach in the equipment occurs. Therefore, the identified

exposure radii are considered to be a very conservative estimate.

Fire and Explosion Index


A Dow F&EI was completed for the CO2 Absorber (C-80), Absorber Overhead K.O. Drum

(C-87), and HP Lean Amine Flash Drum (C-81) for the base case and 125% capacity redesign.

Table 15 below shows the summary of the F&EI, exposure radius, capital loss, and business

interruptions for the three pieces of equipment for each case. Detailed calculations for the F&EI

can be found in Appendix L. The CO2 Absorber and Absorber Overhead K.O. Drum had the

highest pressure and concentration of synthesis gas, resulting in the largest exposure radius for

equipment containing synthesis gas. The HP Lean Amine Flash Drum had the highest pressure and

concentration of lean amine out of the process, resulting in the largest exposure radius for

equipment containing lean amine.

None of the equipment in the 125% capacity redesign is classified as dangerous according

to the Dow F&EI, as none of the index values exceeded 128. The placement of the Lean Amine

Cooler (E-85A/B) was thus more dependent on access considerations rather than the exposure

radius, as the safety risk due to poor access was higher than that identified by the DOW F&EI.

Table 15. Fire and Explosion Index Summary Table for the 125% Redesign Case
Base Case 125% Design Case
Equipment Number C-80 C-81 C-87 C-80 C-81 C-87
Fire & Explosion Index 72.03 42.88 71.86 76.17 42.95 75.79
Radius of Exposure (m) 18.49 11.01 18.04 19.55 11.02 19.45
Maximum Probable Property Damage
0.99 0.69 1.40 1.09 0.69 1.52
(MM CAD)
Maximum Probable Days Outage 20 15 25 21 15 30
Business Interruption (MM CAD) 0.41 0.31 0.52 5.28 0.38 0.75

46
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Applicable Safety Regulations and Codes Requirements


The pressure equipment and piping located within the facility, as well as the electrical, gas,

and plumbing systems are bound by the Alberta Safety Codes Act and must adhere to applicable

codes and regulations under the act including the CSA C22.1-18 Canadian Electrical Code,

National Plumbing Code of Canada 2015, Fire Code and Pressure Equipment Safety Regulation

(48; 49; 50; 51; 52). Additionally, all employers, workers, suppliers, contractors, and other project

personnel must conduct their business according to the Alberta Occupational Health and Safety

(OHS) Act, OHS Regulation, and OHS Code, as well as the Oil and Gas Occupational Safety and

Health Regulations under the Canada Labour Code (53; 54; 55; 56; 57). These regulations affect

the construction, testing, installation, operation, repair, and maintenance of equipment, and must

be followed to ensure that the facility operates in a safe and legal manner. A full list of applicable

regulations and standards for this project is included in Appendix L.

Health and Safety Risk Management Conclusions


Completion of multiple hazard identification and risk assessment methodologies has allowed

Okane Engineering to identify proper safeguards for minimizing project risks to an ALARP level.

Compliance with the identified safety regulations and code requirements ensures that the project

will operate in a safe manner with proper risk management throughout the facility’s lifetime.

7.10. Net Social Benefit Analysis


Net social benefit is the increase in the welfare of a society that is derived from a particular

course of action (58). The net social benefit for the 125% redesign case was evaluated based on

several factors, including the potential contributions to the local and regional economy, noise,

traditional land and resource use, and effect on human health. A full list of considered factors and

detailed analysis of net social benefit can be found in Appendix N.

47
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Increasing the capacity of the CO2 removal unit to 125% capacity would reduce overall GHG

emissions of the Horizon Oil Sands facility by 95,452 tCO2e/yr more than the base case. There is

also the potential to reduce the carbon footprint of other oil sands facilities, by selling the additional

CO2 recovered to other facilities around the Fort McMurray area to be used for EOR, tailings

management, or other CCS methods. The 125% capacity redesign would also generate a corporate

income tax revenue for the provincial government of C$3.12 MM over the project lifetime. During

the design and construction phases, the 125% redesign case would also see business and

employment opportunities for qualified local or regional contractors and businesses.

There are minimal negative impacts to society identified for the 125% redesign case. There

would be marginally increased noise around the CO2 Removal Unit due to pump motors operating

at higher speeds and temporary increases in noise due to construction activities during project

execution. Increased traffic during construction may also have a slight impact on the air quality in

the region due to dust and increased diesel and gasoline consumption. CNRL’s established

transportation policy would help to minimize the effects of traffic on nearby residents.

Horizon Oil Sands is relatively isolated from other residents, which minimizes the project risks

to society. Numerous safeguards are in place to ensure that the 125% redesign case is properly risk

managed. Overall, implementation of the 125% redesign case would have a positive net social

benefit.

8. Option B: 112% Capacity Redesign


8.1. Process Description
The 112% capacity design increases the amount of CO2 recovered by modifying the existing

operating pressures and temperatures. The aMDEA flow rates are also adjusted to improve the

CO2 recovery rates. No new equipment is required for this redesign.

48
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

At increased syngas feed rates, the CO2 recovery efficiency decreases primarily due to limits

in the CO2 absorption rates in the CO2 Absorber (C-80). Desorption rates in the LP Flash Stripper

(C-82) also limit CO2 recovery efficiency but are secondary to the CO2 Absorber. Thus, minor

increases in capacity are achieved by optimizing CO2 absorption rates in the CO2 Absorber (C-80)

through temperature, pressure, and flow rate modifications. The changes in operating setpoints

needed to achieve 112% operating capacity are shown by stream in Table 16. In the 112% capacity

redesign, the amount of CO2 product produced is 1278 kmol/h, which is a 7.7% increase from the

base case CO2 output of 1187 kmol/h. A PFD of the 112% capacity redesign is shown in Figure 2

and in Appendix E with associated stream tables.

Table 16: Temperature, Pressure, and Flow Rate Changes for the 112% Capacity Redesign
Stream Description Base Case 112% Case
25 SG to CO2 Absorber Flow Rate 8214 kmol/h 9148 kmol/h
27 SG from CO2 Absorber OH Cooler Temperature 40.0 °C 39.8 °C
36 CO2 to Reflux Vessel Temperature 45.0 °C 44.4 °C
86 Lean Amine from Air Cooler aMDEA Flow Rate 2018 kmol/h 2106 kmol/h
86 Lean Amine from Air Cooler Temperature 45.0 °C 41.5 °C
95 Process Condensate to LP Flash Stripper Flow Rate 142 kmol/h 148 kmol/h
- CO2 Absorber Bottom Operating Pressure 3285 kPa(g) 3300 kPa(g)

CO2 Absorption
The bottom operating pressure, aMDEA flow rate, and lean amine stream temperature for

the CO2 Absorber (C-80) are modified to improve CO2 absorption rates, as explained in Section

7.1.1. This maintains a CO2 concentration in the outlet syngas fed to the PSA at an acceptable level

below 3.00 mol%.

CO2 Desorption
Effective desorption of CO2 from the rich amine solution is achieved at 112% capacity

without modifications to the operating pressures of the LP Flash Stripper (C-82). The additional

49
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

process condensate recycled to the LP Flash Stripper is needed to effectively wash the exiting gas

to prevent entrainment of amine in the overheads.

Design Considerations
The increase in capacity of the CO2 Recovery Unit is limited to 112% due to the design

limits of the CO2 Absorber (C-80) and Lean Amine Air Cooler (E-84). The CO2 loading factor

used was 0.66 mol CO2/mol amine which was 1.3% higher than the recommended value of 0.65

mol CO2/mol amine. While this is unlikely to cause corrosion issues due to the lower operating

temperatures used, it should still be taken note of in the unit’s Corrosion Control Document.

8.2. Heat Integration


No equipment was added in the 112% redesign case so only limited heat integration could

be done. The existing integrated heat exchanger system was thus optimized as mentioned in

Section 7.2 by maximizing the area of the Lean/Rich Amine Exchanger (E-81A/B).

8.3. Material and Energy Balances


The material and energy balances for the 112% case are summarized below in Table 17

and Table 18. Detailed balances are presented in Appendix G. The envelope used for all material

and energy balances is the box shown in Figure 1. The material and energy balances close with

negligible percent differences, indicating that both mass and energy were conserved.

50
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Table 17: 112 % Case Overall Material Balance


Material In Material Out
Stream Name Description
(kmol/h) (kmol/h)
25 SG to CO2 Absorber 9148.0 -
Amine Makeup Amine Makeup 0.0 -
IN

Water Makeup Water Makeup 0.0 -


72 Steam Condensate to CO2 Absorber 122.0 -
28 SG from CO2 Recovery Unit - 7849.7
38 CO2 to Dehydration Unit - 1289.7
75 Flash Gas from HP Amine Flash Drum - 16.1
Process Condensate to BL Process
OUT

96 - 21.0
Water Header
Amine Blowdown Amine Blowdown - 0.0
Water Blowdown Water Blowdown - 0.0
37C Stage 1 Compressor K.O. Vessel - 72.7
37G Stage 2 Compressor K.O. Vessel - 20.8
Total (kmol/h) 9270.0 9270.0
Percent Difference 0.0%

51
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Table 18: 112 % Case Overall Energy Balance


Energy In Energy Out
Stream Name Description
(kW) (kW)
25 SG to CO2 Absorber -184,079 -
Amine Makeup Amine Makeup 0 -
IN

Water Makeup Water Makeup -1 -


72 Steam Condensate to CO2 Absorber -9,627 -
28 SG from CO2 Recovery Unit - -43,164
38 CO2 to Dehydration Unit - -140,898
75 Flash Gas from HP Amine Flash Drum - -1,002
Process Condensate to BL Process
OUT

96 - -1,659
Water Header
Amine Blowdown Amine Blowdown - 0
Water Blowdown Water Blowdown - 0
37C Stage 1 Compressor K.O. Vessel - -5,748
37G Stage 2 Compressor K.O. Vessel - -1,649
E-80 CO2 Absorber Overhead Cooler - 1,267
E-82 Stripper Reboiler 31,600 -
EQUIPMENT

E-83 Stripper Overhead Condenser - 2,361


E-84 Lean Amine Air Cooler - 27,838
G-81A/B Semilean Amine Pump 120 -
G-82A/B/C HP Lean Amine Pump 1,158 -
G-83A/B Stripper Reflux Pump 1 -
Compressor Unit - 1850
Total (kW) -135,046 -135,035
Percent Difference 0.0%

8.4. Equipment List and Sizing


In the 112 % case, operating conditions were optimized, and no equipment modifications or

additions were made. The equipment required for this case is the existing equipment already on

site. Design and operating data for the equipment was provided by the client and can be found in

Appendix H.

52
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

8.5. Utility Requirements


Table 19 summarizes the additional utility requirements in order to facilitate the increase to

112% capacity. Detailed calculations done to determine these values are presented in Appendix J.

As described in the 125% redesign case, additional utility requirements included cooling water,

electricity, and makeup amine. The duty of the stripper reboiler also did not change from the base

case, resulting in no change in the LP steam requirement. The additional amine was estimated

using the same method described in Section 7.5.

Table 19: Additional Utility Requirements


Utility Makeup Amine Electricity Cooling Water
Comparison (kg/h) (kWh) (m3/h)
Base Case Usage 0.135 5483 566
125% Case Usage 0.141 6106 612
Increase from Base Case 0.006 623 46

8.6. Project Execution Strategy


The only project work required for this option is review of the modification of existing

operating procedures to accommodate the new setpoints. No construction or procurement work is

required due to the absence of equipment additions or modifications. A project execution strategy

was therefore not developed.

8.7. Economic Analysis


Economic Introduction

The methods and assumptions used for the economic analysis of the 112% redesign case are

the same as the ones used in the 125% redesign case and are outlined in Section 7.7.1. Unless

otherwise specified, all prices and costs are expressed in Canadian dollars.

53
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Fixed Capital Expenditure

Since this option involves the optimization of existing operating conditions and does not

require the addition or modification of equipment, there is no fixed capital expenditure.

Operating Cost

Appendix J contains the calculations used to estimate the operating expenditure for the 112%

capacity redesign. Figure 12 presents the operating cost breakdown in the form of a pie chart. The

methods used to estimate operating cost are outlined in Section 7.7.4. Figure 12 shows that most

of the additional operating expenditure comes from the cooling water and electricity utility costs.

The total increase in annual operating expense was determined to be $0.67 MM.

Figure 12: Operating Cost Breakdown for the 112% Capacity Increase

The unit price data for the utilities provided by CNRL was used to determine the additional

utilities expenditure, as explained in Section 7.7.4. The results are shown in Table 20.

54
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Table 20: Utility Cost Summary


Utility Unit Cost Additional Annual Expense
(x103 CAD)
Makeup Amine $12.25/kg $0.6
Electricity $0.11/kWh $556
Cooling Water $0.07/m3 $26

The sources of revenue for the 112% capacity redesign are the same as the ones listed in

Section 7.7.4 for the 125% capacity redesign. The increase in annual revenue determined for the

112% capacity redesign case was $1.86 MM.

Discounted Cash Flow Analysis

Figure 13 displays the cash flow diagram of the project for the 112% redesign case. Detailed

calculations and cash flow tables are presented in Appendix J. The method used for the cash flow

analysis is the same method described in 7.7.6.

$10
Cumulative Discounted Cash

$9
$8
$7
Flow ($MM)

$6
$5
$4
$3
$2
$1
$0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Project Year
Figure 13: Discounted Cash Flow Profile for the 112% Case

55
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Sensitivity Analysis

The sensitivity analysis was conducted using the same method outlined in 7.7.6. Figure 14

illustrates the sensitivity analysis results with respect to NPV. Since a proper IRR could not be

obtained for the 112% case, a sensitivity analysis with respect to IRR was not performed. Figure

14 shows that the most influential parameters are the price of GHG emissions credits and sale price

of CO2. The market variation in the utility prices is shown to have little effect on the project NPV.

Figure 14: NPV Tornado Diagram for the 112% Case

Economic Conclusions
The lack of capital expenditure and relatively low operating cost for the 112% capacity

increase results in a positive NPV of $6.64 MM. Based on the NPV analysis, the 112% capacity

redesign is deemed to be economically feasible.

8.8. Environmental Analysis


The process waste streams, potential impacts, applicable environmental regulations, and

environmental management conclusions for the 112% capacity redesign are the same as the 125%

case. The environmental metrics used to evaluate the proposed solution were also the same but

56
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

with slightly different values. The 112% capacity redesign for the CO2 Removal Unit would

capture 34,925 tCO2e/yr more than the “do nothing” alternative, which is equivalent to removing

approximately 7,600 passenger vehicles from the road (43). Although the emissions reduction in

the 112% capacity redesign would be smaller than the 125% case, implementation of the project

would still contribute to CNRL’s environmental management goals. The cooling water use for the

CO2 Removal Unit would also increase by 0.013 m3/s. This increase in cooling water usage is

negligible in relation to the total cooling water supply used at Horizon Oil Sands facility. Thus, it

was assumed that the existing water treatment systems would be able to handle the marginal

increase without issue.

8.9. Safety and Risk Analysis


Hazard Identification and Risk Evaluation
A checklist PFD based analysis and What If? PHA was also completed for the 112% capacity

redesign case using similar methodology to the 125% case. No HAZOP was completed for the

112% capacity redesign due to a lack of time and resources for this project. However, the safety

and risk analysis for the 112% capacity redesign identified several recommendations, including

review of the existing PSVs and PRVs for potential re-ratings to accommodate the increased flow

rates, and confirmation of process lines sizing for the identified high velocity lines. Additionally,

the CO2 loading factor for the 112% capacity redesign is 0.66 mol CO2/mol amine, which is

slightly higher than the recommended maximum loading factor of 0.65 mol CO2/mol amine. This

should be evaluated for any potential impacts on equipment reliability or performance. The full

list recommendations identified for the 112% capacity redesign can be found in Appendix L.

57
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Chemical Exposure Index


A Dow CEI was also calculated around stream 26 for the 112% design case. All relevant

calculations can be found in Appendix L. ERPG-1 is also not included in the analysis since it is

the same gas as the base and 125% design case. Table 21 shows the CEI and the hazard distances

for ERPG-2 and ERPG-3 for the 112% case compared to the base case. Figure 15 shows the

exposure radii to scale. As shown in the Figure 15, the radius of the 112% design case is similar

to the 125% design case. Thus, the risks identified as the same as those listed in 7.9.4 but on a

slightly smaller scale.

Table 21: Chemical Exposure Index Summary Table


Cases Base Case 112% Design Case
Chemical Exposure Index 164.9 174.1
ERPG-2 (m) 1649 1741
ERPG-3 (m) 1382 1458

58
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

ERPG-2 (1741 m)
ERPG-3 (1458 m)

0 0.5 km 1.0 km 1.5 km 2.0 km

Figure 15: Chemical Exposure Radii by ERPG Level Overlaid on Satellite Imagery for the 112%

Case

Fire and Explosion Index


A Dow Fire and Explosion Index was also completed for the CO2 Absorber (C-80), Absorber

Overhead K.O. Drum (C-87), and the HP Lean Amine Flash Drum (C-81) for the 112% redesign

case. Table 22 shows the summary of the F&EI, exposure radius, capital loss, and business

interruptions for the three pieces of equipment in the 112% redesign case compared to the base

case. Detailed calculations for the F&EI can be found in Appendix L.

59
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Table 22: Fire and Explosion Index Summary Table for the 112% Redesign Case
Base Case 112% Design Case
Equipment number C-80 C-81 C-87 C-80 C-81 C-87
Fire & Explosion Index 72.03 42.88 71.86 74.05 42.91 73.72
Radius of Exposure (m) 18.49 11.01 18.04 19.01 11.01 18.92
Maximum Probable Property Damage
0.99 0.69 1.40 1.01 0.69 1.42
($MM CAD)
Maximum Probable Days Outage 20 15 25 21 15 25
Business Interruption ($MM CAD) 0.41 0.31 0.52 0.47 0.34 0.56

Applicable Safety Regulations and Risk Management Conclusions


There are no additional safety regulations applicable to the 112% redesign case that were

not already identified for the 125% redesign case. After applying the assumed engineering

safeguards and administrative controls, all risks for the 112% case were determined to be at an

ALARP level.

8.10. Net Social Benefit Analysis


The net social benefit for the 112% redesign case was also evaluated based on factors

including contribution towards the local and regional economy, noise, traditional land and resource

use, and affect on human health. Increasing the capacity of the CO2 Removal Unit by 12% would

reduce the overall GHG emissions of the Horizon Oil Sands facility by 34,925 tCO2e/yr over the

“do nothing” case. This would also contribute to CNRL’s GHG emissions reduction strategy and

benefit other oil sands facilities in the Fort McMurray area, albeit to a lower magnitude than the

125% redesign. The Provincial tax revenue for the 125% capacity redesign was C$8.90 MM,

which was much higher than the 125% case due to there being no CCA applicable to this solution.

The 112% capacity design does not provide business opportunities for qualified local or

regional contractors due to the lack of construction activities. However, concerns regarding traffic,

60
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

dust, and noise around the facility during project implementation are consequently minimized.

Overall, the 112% redesign was determined to have a positive net social benefit.

9. Conclusions and Recommendations


Pre-emptive reductions in GHG emissions are crucial to minimizing long-term economic

risks resulting from rising carbon taxes costs. Okane Engineering was requested by CNRL to

redesign the existing CO2 Recovery Plant to increase the operating capacity by 15% and 25%. A

12% capacity increase was pursued instead of 15% after consultation with the client. The 12%

increase in capacity was achieved within the design limits of the existing equipment through

optimization of operating conditions. The 25% increase in capacity was achieved through the

addition of new equipment and modification and replacement of some existing equipment. The

design changes needed to achieve operating capacities of 112% and 125% in the CO2 Removal

Unit are summarized in Table 23.

Table 23: Summary of Requirements for Redesign


112% 125%
Change in Specified Parameters Base Case
Case Case
Flow Rate of Steam Codensate to CO2 Absorber
122 122 130
(kmol/h)
Flow Rate of aMDEA (kmol/h) 2018 2106 2211
Temperature of Lean Amine Fed to CO2 Absorber (K) 318.15 314.65 307.85
CO2 Absorber Operating Pressure (bottom/top) (kPag) 3285/3275 3300/3275 3315/3275
CO2 Absorber Packing Type IMTP #40 IMTP #40 IMTP #25
CO2 Absorber Packing Height (m) 8.6 8.6 10.2
LP Flash Stripper Operating Pressure (bottom/top)
50/40 50/40 55/40
(kPag)
LP Flash Stripper Packing Type IMTP #50 IMTP #50 IMTP #40
Process Condensate Recycle to LP Flash Stripper
142 148 116
(kmol/h)
Number of Exchangers to be Added or Replaced 0 0 3
Number of Drums to be Replaced 0 0 2

61
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Preliminary economic analyses of the 112% and 125% redesign cases were completed to

assess economic feasibility. The 125% redesign case was found to be economically unfeasible,

with an NPV of -C$10.69 MM. It was calculated that a selling price of C$49 /tCO2 would be

required for the 125% redesign case to be financially viable at the current carbon tax of C$30

/tCO2e. The 112% redesign case was found to be economically feasible with an NPV of C$6.64

MM. The additional operating costs were found to be C$0.67 MM per year with an annual revenue

of C$1.86 MM.

An environmental assessment was performed for the proposed project. It was found that both

the 112% and 125% redesign cases would meet or exceed all applicable environmental regulations.

The 112% and 125% capacity redesigns would recover approximately 35,000 and 95,000 tCO2e/yr

more than the current process, respectively. Both redesigns would also contribute to CNRL’s goal

of reducing emissions intensity to below the global crude average and strengthen the company’s

position as an industry leader in responsible GHG management.

The completion of multiple hazard identifications and risk assessment methodologies, such

as a process hazard checklist, What If? analysis, HAZOP, and DOW indices were used to identify

safeguards to minimize project risks to an ALARP level. Overall, both redesigns would have an

overall positive net social benefit and be environmentally and socially sustainable.

Based on the design evaluations conducted, Okane Engineering advises CNRL to not pursue

the 125% redesign case which was determined to be economically unfeasible. The 112% design

case is economically feasible and should be pursued further. Further evaluation of potential

corrosion issues, piping velocity limitations, and effects of high CO2 loading is still required. It is

also strongly recommended to complete field testing to verify the CO2 recovery efficiencies stated

in the 112% capacity redesign. Upon completion of these recommendations, project execution of

62
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

the 112% redesign case would be the best course of action, as it would increase the profitability of

CNRL and provide significant environmental and economic benefits.

63
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

10. References
1. Canadian Natural Resources Ltd. The Horizon Oil Sands. Canadian Natural. [Online]
[Cited: January 1, 2019.]
https://cnrl.hgcareers.com/en/media/cnrl/The%20Oil%20Sands%20Process.pdf.
2. —. Managing Tailings. [Online] [Cited: January 20, 2019.] https://www.cnrl.com/corporate-
responsibility/advancements-in-technology/managing-tailings.html.
3. Environment and Climate Change Canada. Pan-Canadian Framework on Clean Growth
and Climate Change. [Online] 2016.
https://www.canada.ca/content/dam/themes/environment/documents/weather1/20170125-
en.pdf.
4. Government of Alberta. Carbon Competitiveness Incentive Regulation Fact Sheet. [Online]
April 2018. [Cited: January 20, 2019.] https://www.alberta.ca/assets/documents/cci-fact-
sheet.pdf.
5. —. Carbon Competitiveness Incentive Regulation. [Online] November 20, 2018. [Cited:
January 20, 2019.]
http://www.qp.alberta.ca/1266.cfm?page=2017_255.cfm&leg_type=Regs&isbncln=9780779
800193.
6. —. Output Based Allocation Engagement. [Online] [Cited: January 25, 2019.]
https://www.alberta.ca/output-based-allocation-engagement.aspx.
7. Alberta Environment and Parks. Climate Change and Emissions Management Fund Credit
Amount Order. [Online] December 21, 2017. [Cited: January 25, 2019.]
https://www.alberta.ca/assets/documents/CCEMA-fund-credit-ministerial-order.PDF.
8. Canada's Oil Sands. GHG Emissions. [Online] https://www.canadasoilsands.ca/en/explore-
topics/ghg-emissions.
9. Government of Alberta. Climate Leadership Plan - Implementation Plan 2018-19. Open
Government Portal. [Online] June 2018. [Cited: January 17, 2019.]
https://open.alberta.ca/dataset/da6433da-69b7-4d15-9123-01f76004f574/resource/b42b1f43-
7b9d-483d-aa2a-6f9b4290d81e/download/clp_implementation_plan-jun07.pdf.
10. —. Oil Sands Emissions Limit Act. Alberta Queen's Printer. [Online] December 14, 2016.
[Cited: April 4, 2019.] http://www.qp.alberta.ca/documents/Acts/O07p5.pdf.
11. Barry Sacifrage. Oilsands pollution on collision course with Canada's climate plan.
Canada's National Observer. [Online] February 20, 2018. [Cited: April 4, 2019.]
https://www.nationalobserver.com/2018/02/20/opinion/oilsands-pollution-collision-course-
canadas-climate-plan.
12. Canadian Natural Resources Ltd. Corporate Statement on Environmental Management.
[Online] June 2018. [Cited: April 4, 2019.]
http://webadmin.cnrl.com/upload/media_element/445/07/2018-corporate-statement-on-
environmental-management_final.pdf.

64
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

13. —. 2017 Stewardship Report to Stakeholders. [Online] 2017.


http://webadmin.cnrl.com/upload/multi_media_element/185/04/2017-stewardship-report-to-
stakeholders.pdf.
14. Global carbon intensity of crude oil production. Masnadi, Mohammad S., et al. 6405, s.l. :
Science Magazine, 2018, Vol. 361.
15. Statistics Canada. Energy Statistics Handbook - Appendix A: Conversion Factors. Statistics
Canada. [Online] July 29, 2005. [Cited: April 8, 2019.]
https://www150.statcan.gc.ca/n1/pub/57-601-x/00105/4173282-eng.htm.
16. Melnyk, Kevin. Vice President Upgrading and Utilities. Industrial Advisor Meeting #3.
Edmonton, April 2, 2019.
17. Canadian Natural Resources Ltd. GHG emissions reduction program. [Online] [Cited:
April 4, 2019.] https://www.cnrl.com/corporate-responsibility/environment/climate-
change/ghg-emissions.
18. Global CCS Institute. Accelerating the Uptake of CCS: Industrial Use of Captured Carbon
Dioxide. 2011.
19. Heal, Kevin and Kemp, Terry. North West Sturgeon Refinery Project Overview - Carbon
Capture Through Innovative Commercial Structuring in the Canadian Oil Sands. Calgary :
s.n., 2013.
20. Gas-Liquid Equilibrium in a CO2-MDEA-H2O System and the Effect of Piperazine on It.
Xu, Guo-Wen, et al. 4, Shanghai : Industrial & Engineering Chemistry Research, 1998, Vol.
37, pp. 1473-1477.
21. Engineering Data Book. Gas Processors Suppliers Association. Tulsa : s.n., 2004, Vol. 1
and 2.
22. Perry, Robert H and Green, Don W. Perry's Chemical Engineers' Handbook. 8th. New
York : McGraw-Hill, 2007. 978-0071422949.
23. Tan, L.S., et al. Factors affecting CO2 absorption efficiency in packed column: A review.
Tronoh : Journal of Industrial and Engineering Chemistry, 2012.
24. Scale-Up Effects of CO2 Capture by Methyldiethanolamine (MDEA) Solutions in Terms of
Loading Capacity. Santos, Samuel P, Gomes, João F and Bordado, João C. 19, s.l. :
MDPI, 2016, Vol. 4.
25. American Petroleum Institute. Avoiding Environmental Cracking in Amine Units.
[Document] 2008. API RP945.
26. —. Damage Mechanisms Affecting Fixed Equipment in the Refining Industry. [Document]
2011. API RP 571.
27. Corrosion and Materials Selection for Amine Service. Rennie, S. s.l. : Materials Forum,
2006, Vol. 30.
28. Canadian Natural Resources Ltd. Integrated Application and Environmental Impact
Assessment. s.l. : Environment and Parks, 2018.

65
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

29. Guthrie, Kenneth M. Process Plant Estimating Evaluation and Control. Solana Beach :
Craftsman Book Company of America, 1974.
30. International, AACE. Cost Estimate Classification System - As Applied in Engineering,
Procurements, and Construction for the Process Industries. AACE International
Recommended Practice No. 18R-97. s.l. : AACE® International, March 1, 2016.
31. Narayanasarma, Prabhu. P. Eng. Industry Advisor Meeting #1. Edmonton, January 31,
2019.
32. Ulrich, Gael D. and Vasudevan, Palligarnai T. Chemical Engineering Process Design and
Economics: A Practical Guide (Second Edition). Durham : Process (Ulrich) Publishing,
2004. 0-97087683-2-3.
33. Jamieson & Church. Contingency Estimating. Edmonton, AB, Canada : s.n., 2015.
34. Live Exchange Rates. OANDA Corporation. [Online] https://www.oanda.com/currency/live-
exchange-rates/USDCAD/.
35. Chemical Plant Cost Index. Chemical Engineering Essentials for the CPI Professional.
[Online] https://www.chemengonline.com/2019-cepci-updates-january-prelim-and-
december-2018-final/.
36. Jamieson & Church. Adjusting FBM. Edmonton, AB, Canada : s.n., 2015.
37. Common CCA Classes and Rates. Donnelly & Co. LLP. [Online]
http://donnellyco.ab.ca/cca-rates-and-classes.
38. Government of Alberta. Specified Gas Reporting Regulation. Alberta Queen's Printer.
[Online] November 20, 2018. [Cited: April 4, 2019.]
http://www.qp.alberta.ca/1266.cfm?page=2017_255.cfm&leg_type=Regs&isbncln=9780779
800193.
39. —. Climate Change and Emissions Management Act. Alberta Queen's Printer. [Online]
January 1, 2017. [Cited: April 4, 2019.]
http://www.qp.alberta.ca/documents/Acts/C16P7.pdf.
40. Canadian Natural Resources Ltd. Protecting Air Qualtiy. [Online] [Cited: April 5, 2019.]
https://www.cnrl.com/corporate-responsibility/environment/climate-change/air-quality.
41. Woof Buffalo Environmental Association. Horizon. Wood Buffalo Environmental
Association. [Online] March 6, 2019. [Cited: April 4, 2019.]
https://wbea.org/stations/horizon/.
42. Government of Alberta. Alberta Ambient Air Quality Objectives and Guidelines Summary.
Open Government Portal. [Online] January 2019. [Cited: April 4, 2019.]
https://open.alberta.ca/dataset/0d2ad470-117e-410f-ba4f-aa352cb02d4d/resource/4ddd8097-
6787-43f3-bb4a-908e20f5e8f1/download/aaqo-summary-jan2019.pdf.
43. United States Environmental Protection Agency. Greenhouse Gas Emissions from a Typical
Passenger Vehicle. [Online] March 2018. [Cited: April 6, 2019.]
https://www.epa.gov/greenvehicles/greenhouse-gas-emissions-typical-passenger-vehicle.

66
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

44. Province of Alberta. Climate Leadership Regulation. Alberta Queen's Printer. [Online]
November 20, 2018. [Cited: April 4, 2019.]
http://www.qp.alberta.ca/documents/Regs/2016_175.pdf.
45. Government of Alberta. Climate Leadership Act. Alberta Queen's Printer. [Online] June 7,
2017. [Cited: April 4, 2019.] http://www.qp.alberta.ca/documents/Acts/C16P9.pdf.
46. Alberta Energy Regulator, Alberta Environment and Parks. Authorization Viewer. [Online]
August 5, 2015. [Cited: April 4, 2019.]
https://avw.alberta.ca/ApprovalViewerResults.aspx?Click=Search&exapv_id=186921.
47. APEGA. Guideline for Management of Risk in Professional Practice. [Online] September
2006. [Cited: January 20, 2019.] https://www.apega.ca/assets/PDFs/risk.pdf.
48. Government of Alberta. Safety Codes Act. Alberta Queen's Printer. [Online] December 1,
2017. [Cited: April 4, 2019.] http://www.qp.alberta.ca/documents/Acts/S01.pdf.
49. —. Electrical codes and standards. [Online] 2019. [Cited: April 4, 2019.]
https://www.alberta.ca/electrical-codes-and-standards.aspx.
50. —. Fire codes and standards - Overview. [Online] May 1, 2015. [Cited: April 5, 2019.]
https://www.alberta.ca/fire-codes-and-standards-overview.aspx.
51. —. Plumbing codes and standards - Overview. [Online] 2019. [Cited: April 4, 2019.]
https://www.alberta.ca/plumbing-codes-and-standards-overview.aspx.
52. —. Pressure Equipment Safety Regulation. Alberta Queen's Printer. [Online] 2015. [Cited:
April 4, 2019.] http://www.qp.alberta.ca/documents/Regs/2006_049.pdf.
53. —. Occupational Health and Safety Act. Alberta Queen's Printer. [Online] June 11, 2018.
[Cited: April 4, 2019.] http://www.qp.alberta.ca/documents/Acts/O02P1.pdf.
54. —. Occupational Health and Safety Regulation. Alberta Queen's Printer. [Online] 2018.
[Cited: April 4, 2019.] http://www.qp.alberta.ca/documents/Regs/2003_062.pdf.
55. —. Occupational Health and Safety Code 2018 Explanation Guide. Alberta Queen's Printer.
[Online] January 2019. [Cited: April 4, 2019.]
http://www.qp.alberta.ca/documents/OHS/OHSCodeExplanationGuide.pdf.
56. Government of Canada. Oil and Gas Occupational Safety and Health Regulations. Justice
Laws Website. [Online] March 26, 2019. [Cited: April 4, 2019.] https://laws-
lois.justice.gc.ca/eng/regulations/sor-87-612/index.html.
57. —. Canada Labour Code. Justice Laws Website. [Online] March 12, 2019. [Cited: April 5,
2019.] https://laws-lois.justice.gc.ca/eng/acts/L-2/.
58. IGI Global. What is Net Social Benefit. IGI Global - Disseminator of Knowledge. [Online]
[Cited: April 7, 2019.] https://www.igi-global.com/dictionary/net-social-benefit/62132.

67
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Appendix A: Decision Analysis


Description
The purpose of this appendix is to show solution options considered and outline the

decision analysis procedure undertaken to evaluate them. The project musts and wants are defined.

Options are then assessed on their ability to meet the musts and rated on their ability to meet the

wants.

Table of Contents
1. Options Considered ............................................................................................................... A-1
1.1. Option A: Do Nothing ................................................................................................... A-1
1.2. Option B: Optimization of Operating Conditions with Existing Equipment ................ A-1
1.2.1. The Effects of Temperature, Pressure, and Flow Rate on CO2 Recovery............... A-2
1.3. Option C: Modification of Absorber and Stripper Column .......................................... A-3
1.4. Option D: Replacement of Plant with Gasification System .......................................... A-3
2. Decision Analysis Criteria .................................................................................................... A-5
3. Evaluation of Options ........................................................................................................... A-6
List of References ....................................................................................................................... A-7

i
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

1. Options Considered
1.1. Option A: Do Nothing
In the “Do Nothing” option, no equipment or operational changes would be made to the

CO2 Removal Unit, maintaining the plant’s current capacity and recovery. The operating

expenditure would increase due to higher energy inputs as a result of increased syngas feed

rates, but no capital expenditure would be required. Since the CO2 recovery would remain the

same, more CO2 would be released to atmosphere resulting in increased carbon tax costs. The

advantages of this option are that CNRL would save time, effort, and capital costs, as no

additional work is required due to the absence of redesign. The disadvantage is that doing

nothing would progressively cost CNRL more in the long-term due to higher carbon taxes,

particularly if carbon pricing increases in accordance with the federal climate plan.

1.2. Option B: Optimization of Operating Conditions with Existing Equipment


This option increases the capacity of the CO2 Removal Unit by optimizing the operating

conditions within the confines of the existing infrastructure, forcing the existing equipment to

operate at maximum capacity. This option modifies the operating temperatures, pressures, and

flowrates to support the increased feed flow rate and increase recovery of CO2 while balancing

energy input and utilities usage. The advantages of this option are that it reduces carbon tax

costs through reductions in GHG emissions and has a low capital expenditure, as the process

equipment is utilized as is. The disadvantage is that the existing design limits of equipment

would hinder the achievable increase in capacity and CO2 recovery. Unless the CO2 Removal

Unit was originally overdesigned, it is likely that the plant’s capacity will be limited by the

equipment’s original design before reaching 125%. A significant increase in the CO2 recovery

percentage is also unlikely, thus a higher feed rate would result in higher carbon tax costs.

A-1
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Changing operating conditions would require increased energy input and utilities usage adding

to operating costs as well. Determining the capacity and recovery limits of this option requires

further investigation.

1.2.1. The Effects of Temperature, Pressure, and Flow Rate on CO2 Recovery
Increasing operating temperature in an absorption column typically increases the rate of

mass transfer based on reaction kinetics; however, CO2 absorption is an exothermic process

(1). Too high of a temperature could hinder the absorption process due to shifts in the reaction

equilibrium, so the maximization of CO2 absorption requires optimization of reaction

temperatures (1). Column temperatures can be manipulated by changing the duty of reboilers

or associated heat exchangers; however, more energy input is required and would result in a

higher operating expenditure.

When the partial pressure of CO2 is increased, an increase in CO2 absorption efficiency

of the column is observed. The high interfacial tension resulting from the increased partial

pressure causes an interfacial disturbance that improves mass transfer rate (1). Reducing the

overall system pressure or increasing the CO2 concentration of the inlet streams can increase

the partial pressure of CO2 in both the CO2 Absorber and Low Pressure (LP) Flash Stripper.

Assuming the composition of the syngas fed to the CO2 Absorber is fixed, reducing the

pressure of the column is more reasonable. However, decreasing the pressure will also

decrease the temperature which can negatively impact mass transfer (1).

The flow rate of absorbent used also influences the extent of mass transfer achieved.

Increasing flow rate increases the amount of packing surface covered with absorbent, which

consequently increases the effective area for mass transfer (1). For the CO2 Removal Unit, an

A-2
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

increase in flow rate of lean MDEA would thus increase the amount of CO2 absorbed. This

would also require a higher rate of regeneration of lean MDEA from rich MDEA, leading to

a higher operating cost due to increased utilities usage and potential capital expenditure costs

for additional equipment to increase amine regeneration capacity.

1.3. Option C: Modification of Absorber and Stripper Column


If the existing infrastructure cannot achieve the desired increase in plant capacity,

equipment modifications will be made to the CO2 Absorber, LP Flash Stripper, or both. The

key processes of the CO2 Removal Unit are CO2 absorption by lean MDEA and desorption of

CO2 from rich MDEA, which occurs in the CO2 Absorber and LP Flash Stripper respectively.

Increasing the capacity of either one would increase the plant’s capacity. These two processes

also largely control the CO2 recovery efficiency; therefore, improving efficiency in one or both

columns would increase CO2 recovery. This would be advantageous in avoiding increases in

carbon tax costs due to the additional CO2 introduced by higher feed flow rates. This option

offers the advantage of design flexibility, ensuring that the equipment is designed to achieve

the desired 115% and 125% capacity and product specifications as requested. The disadvantage

is that this option is capital expenditure intensive. The cost for modification or replacement of

columns is significantly higher than that of smaller equipment like exchangers. The higher

capacity columns will have increased energy input requirements, raising operating costs as

well.

1.4. Option D: Replacement of Plant with Gasification System


This option involves implementing a hydrogen-producing gasification system, which the

North West Sturgeon Refinery (NWSR) currently utilizes, in place of the existing CO 2

A-3
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Recovery Plant. This system can produce a high purity CO2 product stream with higher feed

flow rates without the need for excess dehydration units (2). Lurgi’s Multi-Purpose Gasifier

(MPG®) with Rectisol® synthesis gas processing and conditioning technology is used at

NWSR. Rectisol® is a mature acid gas separation technology that has commercially

demonstrated the ability to safely and reliably process a variety of raw materials, from natural

gas to coal (3). This technology would produce hydrogen and CO2 using the following:

1. MPG® gasifier reactors that react feedstock with O2 in the presence of steam under high
pressure and temperature conditions
2. A quenching unit that cools superheated raw syngas via direct injection of water
3. A gas scrubber and ash recovery unit that removes ash and soot
4. A raw gas CO-shift conversion unit
5. A Rectisol® syngas processing unit that conditions and purifies H2, CO2, and H2S
The advantage of this option is that it can easily produce the specified 92 mol% purity of the

CO2 product stream for operations at 115% and 125% capacity with potential reductions in

energy input and utility usage due to less intensive product purification processes. The capital

expenditure required is a major disadvantage, as implementation of this new technology

involves replacement of the CO2 Recovery Plant in its entirety along with major

reconfiguration of upstream and downstream tie-ins.

A-4
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

2. Decision Analysis Criteria


Musts Description
As an Alberta-based facility regulated under the CCIR, the Horizon Oil Sands
Demonstrate
are subject to compliance costs for every tonne of GHGs emitted above the
the ability to
allocated limit. The cost to offset these emissions by purchasing carbon offset or
reduce
CCEMF credits is currently $30/tCO2e and may rise to as high as $50/tCO2e in
emissions to
2022. Since SMR capacity augmentation would contribute to increased emission
better
from the Horizon Oils Sands facility, the options explored in this analysis must
comply with
demonstrate the ability to reduce emissions and maintain profitability for the
regulations
Horizon Oil Sands.
Increase The primary objective of the project is to identify suitable equipment or
plant operational changes necessary to facilitate the increased capacity of the syngas
capacity by feed stream. An incremental increase in capacity smaller than 15% is not a large
at least 15% enough change to have an impact and would not meet the project objectives.
Wants Description Weight
Minimize Equipment additions or modifications are likely to be expensive. 30%
capital cost The solution should limit the amount of complex alterations made
to the process design, since the economic significance for this
project lies with innovative solutions to achieve the project musts
through minimum capital investment.
Maximize This project aims to maximize the amount of CO2 emissions being 30%
reduction of recovered to minimize the operating costs associated with carbon
GHG tax and CCIR compliance costs.
emissions
Minimize The proposed redesign should minimize required utilities input, 25%
operating such as steam and power input, as these resources increase
costs operating costs which can affect economic profitability.
Minimize The proposed redesign should also aim to minimize the time 15%
construction required for installation of additional equipment or tear down of
time existing equipment for the capacity augmentation.
Rating Description
0 Alternative will not meet criteria
2 Poor chance of meeting criteria
4 Fair chance of meeting criteria
6 Acceptable/average chance of meeting criteria
8 Very good chance of meeting criteria
10 Excellent chance of meeting or exceeding criteria

A-5
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

3. Evaluation of Options
Musts Option A Option B Option C Option D
Reduce emissions to better comply with ✗ ✓ ✓ ✓
regulations
Increase plant capacity by at least 15% ✗ ✓ ✓ ✓
Go / No Go No Go Go Go Go
Weight Option B Option C Option D
Wants
(%) (/10) (/10) (/10)
Minimize capital costs 30 10 2 0
Maximize reduction of GHG emissions 30 6 8 10
Minimize operating costs 25 6 6 4
Minimize construction time 15 10 6 2
Total (/10) 100 7.8 5.4 4.3

Note that the investigation of Option B resulted in optimization of operating conditions that could

support a 12% capacity increase rather than the 15% initially proposed. Upon consultation with

the client, a 112% capacity redesign was deemed to be acceptable in place of the 15% capacity

redesign, provided that the 112% capacity redesign was completed using only existing equipment.

This change modifies the required must for the design to be able to “increase plant capacity by at

least 12%”.

A-6
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

List of References
1. Tan, L.S., et al. Factors affecting CO2 absorption efficiency in packed column: A review.

Tronoh : Journal of Industrial and Engineering Chemistry, 2012.

2. Heal, Kevin and Kemp, Terry. North West Sturgeon Refinery Project Overview - Carbon

Capture Through Innovative Commercial Structuring in the Canadian Oil Sands. Calgary : s.n.,

2013.

3. Rectisol Wash Units: Acid Gas Removal for Polygeneration Concepts downstream Gasification.

Haberle, Thomas and Kerestecioglu, Ulvi. Washington DC : s.n., 2010.

A-7
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Appendix B: Simulation Assumptions


Description
This appendix contains supporting information and justification regarding assumptions

made when simulating the project in BRE ProMax. Three separate modelling files were

constructed for the base case, 115 % capacity increase, and 125 % capacity increase.

Table of Contents
1. Thermodynamic Model Selection ........................................................................................... B-1
2. Amine Solution Modelling ..................................................................................................... B-2
3. Adiabatic ................................................................................................................................. B-2
4. Isobaric .................................................................................................................................... B-3
5. Equipment Efficiencies ........................................................................................................... B-3
6. Tray Weir Height .................................................................................................................... B-4
7. Use of Make-Up and Recycle Blocks ..................................................................................... B-4
8. Fictitious Heat Exchanger ....................................................................................................... B-5
9. Feed Stream Compositions ..................................................................................................... B-6
10. Utility Stream Compositions................................................................................................. B-7
List of References ....................................................................................................................... B-8

i
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

1. Thermodynamic Model Selection


Decision: The Amine Sweetening Electrolytic ELR property package will be used to simulate the

CO2 Recovery Plant. The CO2 Absorber will be modelled using the TSWEET Kinetics model

while the LP Flash Stripper will be modelled using the TSWEET Alternate Stripper.

Justification: Based on the ProMax help section written by Bryan Research & Engineering (BRE),

the property package recommended for amine sweetening processes is Amine Sweetening

Electrolytic ELR. This property package was also found to be relatively accurate in modelling CO2

capturing processes by Ahmadi (1). Using the Amine Sweetening Electrolytic ELR property

package, the modelled syngas feed stream entering the CO2 Absorber has a Cp value of 2992

J/kg/K, while the given material balance for the design basis lists a value of 3003 J/kg/K. Since

the modelled value only differs by 0.4% from the benchmark for design, the property package is

deemed suitable for simulating the process. The TSWEET Kinetics Model using Ideal Stages

modified by thermal efficiencies is used to model the CO2 Absorber, while the TSWEET

Absorber/Stripper Model is used to model the LP Flash Stripper. The TSWEET Kinetics Model is

used for the CO2 Absorber because it is able to model the absorption of CO2 more accurately than

the TSWEET Absorber/Stripper Model when compared to the design basis compositions. BRE

also recommends the TSWEET Kinetics model with Ideal Stages for amine absorbers and

TSWEET Alternate Stripper with Mass and Heat Transfer for amine regenerators. The simulation

results using the separation models were compared to the design basis for validation and compared

to calculations performed using fundamental separation theories, as shown in Appendix B.

B-1
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

2. Amine Solution Modelling


Decision: The aMDEA compound will be modelled as 3 wt% piperazine and 97 wt% MDEA.

Justification: Greater activator composition in the solution results in improved absorption but

increases the risk of corrosion. It is common for industries to use approximately 3 wt% piperazine

to assist in the extraction of CO2. At a 3 wt% piperazine concentration at the given amine solution

flow rates, 87.5% of the CO2 in the inlet Syngas stream can be recovered from the rich amine

stream in the CO2 Absorber. This is consistent with the material balance provided for the process,

verifying this assumption. This assumption was also reviewed and accepted by the Industry

Advisor. Thus, the aMDEA flow rates are modelled as 3 wt% piperazine and 97% MDEA in the

ProMax simulation model.

3. Adiabatic
Decision: The process will be simulated as being adiabatic; ignoring heat losses to the

environment.

Justification: Accurate consideration of heat losses in a system is difficult to achieve and requires

rigorous calculations with considerations of many factors, such as insultation thicknesses and heat

tracing. Due to the limitations of the information provided regarding the existing equipment and

piping designs, the process will be assumed to be adiabatic. The project is also a preliminary

assessment, qualifying as a Class 4 economic estimate by the Association for the Advancement of

Cost Estimating (AACE) standards. Thus, in order to complete the study of the proposed solutions

to the accuracy required for this project, the process is assumed to be adiabatic.

B-2
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

4. Isobaric
Decision: The differences in the inlet and outlet stream pressures compared to the given operating

pressures for equipment will be considered negligible where pressure drops are not specified.

Justification: The material balance for the design basis of the CO2 Recovery Plant was provided

as well as operating data for select pieces of equipment. In cases where a pressure drop is indicated

by inlet and outlet streams conditions, as listed in the design basis or operating data provided, the

stated pressure drop is accounted for and used in the simulation. Otherwise, if the operating

pressure, inlet pressure, and outlet pressures are shown to be equal across a piece of equipment,

the pressure drop is assumed to be negligible and specified as 0 kPa(g) in the simulation.

Realistically, pressure drop cannot be eliminated across any type of equipment. However, for the

purpose of reflecting what was given in the design basis, this was applied to the process.

5. Equipment Efficiencies
Decision: Pump efficiencies in the simulation will be calculated as 90% of the stated hydraulic

efficiencies. Compressors will be simulated using an efficiency of 80%.

Justification: For centrifugal pumps, a typical efficiency range is 50 to 85% (Ulrich &

Vasudevan). Operating data was provided for existing pumps in the process, but only hydraulic

efficiency was provided. ProMax requires an overall efficiency, which is a function of the pump’s

volumetric and hydraulic efficiency. As a conservative estimate, the overall efficiency is assumed

to be 90% of the hydraulic efficiencies stated in the operating data summary provided by the

Industry Advisor. Regarding compressors, Ulrich & Vasudevan list the typical efficiencies of

centrifugal compressors operating in a staged configuration to be between 75 to 85% (2). The

midpoint of this range is taken as the assumed compressor efficiency of 80%.

B-3
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

6. Tray Weir Height


Decision: The tray weir heights will be assumed to be 2 in.

Justification: Weir height of the existing trays in the absorber and stripper were not provided. A

typical weir height of 2 inches is then assumed to allow for convergence in each of the columns.

7. Use of Make-Up and Recycle Blocks


Decision: Make-up blocks and recycle blocks will be added to the simulation to account for the

CO2 Removal Unit’s existing make-up streams and equipment, which are not simulated in detail.

The make-up block will be used in the rich amine stream going to the LP Flash Stripper to close

the amine cycle. The recycle block will be used in the lean amine stream going to the CO 2

Absorber. A make-up block will also be used to account for discrepancies in the water balance.

Justification: Make-up blocks are required to supplement lost components in closed loops and

ensure that the material balances close. The make-up units in ProMax solve based on inlet and

make-up stream compositions and a desired outlet flow rate. In the existing plant, the make-up

stream enters the lean amine feed stream to the CO2 Absorber. Due to the interdependence of the

CO2 Absorber and LP Flash Stripper when modelling CO2 recovery, a recycle block is used in this

location instead. The recycle block allows for composition guesses to be made to begin iteration

of the simulation and are needed when simulating a closed loop. To model the CO2 absorption and

desorption as a single process block, the make-up block is used in the rich amine stream instead.

Likewise, a recycle block is used in order to solve the LP Flash Stripper water recycle loop. A

make-up block for water is then used in the lean amine stream to account for water loss in the LP

Flash Stripper which results due to error in the property package when simulating the separation

of CO2 and water.

B-4
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

8. Fictitious Heat Exchanger


Decision: A pseudo-heat exchanger will be added in the semilean amine pumparound stream from

the LP Flash Stripper to account for static head pressure in the pumparound stream. Another

fictitious exchanger will be added in the overhead stream upstream of the CO2 Absorber Overhead

Cooler (E-80) to compensate for error in the simulation of the CO2 absorption process in the CO2

Absorber (C-80).

Justification: The pumparound piping off the LP Flash Stripper is vertical. This piping

configuration ensures that only the liquid portion of the pumparound draw is drawn into the

Semilean Amine Pump (G-81A/B). The phase separation and added static head of the liquid level

prevents vapor locking of the pump. Since, ProMax does not account for piping configuration, a

fictitious exchanger is added in the pumparound stream to model the pumparound stream as being

pure liquid. This allows the Semilean Amine Pump to solve, allowing the simulation model to

converge. In modelling the absorption of CO2 in the CO2 Absorber (C-80), the property package

used resulted in much higher heat generation from the absorption process than was identified in

the design basis. In order to compensate for this error, a fictitious exchanger was added in the

overhead stream to remove some duty. This allowed for the inlet stream temperature to the CO2

Absorber Overhead Cooler to be consistent with the design basis. This fixed amount of duty was

then carried over to the 112% and 125% design basis as a conservative estimate for the minimum

amount of error heat generated when modelling CO2 absorption.

B-5
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

9. Feed Stream Compositions


Decision: The molar composition of the feed stream will remain constant with flow rate.

Justification: Based on discussions with the Industry Advisor, the composition of the syngas did

not vary significantly at increased flow rates. The molar compositions were thus taken to be

consistent and are listed below:

Stream Units Syngas to CO2 Absorber Lean MDEA


Phase Vapor
Mass Flow kg/hr ~ 584000
Volumetric Flow Nm3/h 185000
Molar Flow kmol/h ~ 8220 21400
Temperature °C 40 45
Pressure kPa[g] 3325 4100
CO mol % 3.3
CO2 mol % 16.6 0.2
H2 mol % 75.6
H2O mol % 2 90.4
CH4 mol % 4.2
C2H6 mol % 0
C3H8 mol % 0
N-C4H10 mol % 0
N-C5H12 mol % 0
N2 mol % 0.1
O2 mol % 0
AR mol % 0
MDEA with activator mol % 0 9.4

B-6
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

10. Utility Stream Compositions


Decision: The utility stream conditions will be taken from the operating data. However, when

operating data is not available, the conditions will be based on the typical utility conditions.

Justification: Due to confidentiality restrictions, not all operating data could be made available.

As a result, the following table of typical conditions for utilities was provided by the Industry

Advisor to use for assumed operating conditions where other data was available:

Utility Stream Typical Conditions


HP Steam 4300 kPa(g) 370°C
MP Steam 1300 kPa(g) 220°C
LP Steam 400 kPa(g) 150°C
Boiler Feed Water 6150 kPa(g) 128°C
Cooling Water Supply 100 kPa(g) 24°C
Cooling Water Return 930 kPa(g) 38°C
Fuel Gas 600 kPa(g) 40°C
Natural Gas 600 kPa(g) 40°C

B-7
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

List of References
1. Ahmadi, F. Assessing the Performance of Aspen Plus and Promax for the Simulation of CO2

Capture Plants. Regina : University of Regina, 2012.

2. Ulrich, Gael D. and Vasudevan, Palligarnai T. Chemical Engineering Process Design and

Economics: A Practical Guide (Second Edition). Durham : Process (Ulrich) Publishing, 2004. 0-

97087683-2-3.

B-8
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Appendix C: Simulation Validation


Description
The purpose of this appendix is to show calculations for the process and compare these

values to the outputs from the simulation. This will determine whether the output of the simulation

is within range of what is expected from the design basis and provided operating conditions,

verifying whether the simulation output can be trusted.

Table of Contents
1. Stream Properties .................................................................................................................. C-1
1.1. Specific Heat Capacity .................................................................................................. C-1
1.2. Density........................................................................................................................... C-2
1.3. Viscosity ........................................................................................................................ C-2
2. Heat Exchanger Selection ..................................................................................................... C-2
3. CO2 Absorber Separation ...................................................................................................... C-5
4. Compression Stage................................................................................................................ C-8
List of References ..................................................................................................................... C-10

i
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

1. Stream Properties
1.1. Specific Heat Capacity
The selection of property package is detrimental to the accuracy of the simulation. The

specific heat capacity from the simulation is compared to the values given in the design basis,

as laid out below in kJ/kg/K, to confirm the validity of the simulation. All simulation streams

agree within 5% of the specific heat capacity values given in the design basis.

Stream Design Basis Simulation (Base Case) Difference


Number (J/kg/K) (J/kg/K) (%)
25 3003 2992 0%
26 6175 6187 0%
27 6218 6191 0%
28 6209 6214 0%
35 1000 978 2%
36 1359 1288 5%
37 906 904 0%
38 1164 1112 4%
72 4301 4170 3%
73 3672 3578 3%
74 3671 3581 2%
75 1413 1377 3%
77 3637 3554 2%
78 3745 3714 1%
81 3745 3714 1%
82 3831 3834 0%
83 4138 4224 2%
84 3960 4087 3%
85 3960 4081 3%
86 3737 3879 4%
87 4186 4174 0%
93 4209 4175 1%
94 4209 4174 1%
95 4209 4176 1%
96 4209 4175 1%

C-1
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

1.2. Density
Streams that were simulated by specifying molar flow rates were also assessed for

agreement with the design basis. The density of these streams in kg/m3 are tabulated below.

Agreement within 8% was obtained for density.

Stream Design Basis Simulation (Base Case) Difference


Number (kg/m3) (kg/m3) (%)
25 14 14 1%
72 920 990 8%
86 1026 1029 0%
95 990 990 0%

1.3. Viscosity
Viscosity of the specified streams in the simulation were also examined. Values from the

design basis and the simulation agreed within 12%. Although the percent difference appears to be

high, the discrepancy is attributed to differences in stream molecular weights due to property

package selection.

Stream Design Basis Simulation (Base Case) Difference


Number (mPa*s) (mPa*s) (%)
25 0.000014 0.000014 3%
86 0.002808 0.002463 12%
95 0.000619 0.000615 1%

2. Heat Exchanger Selection


The CO2 Absorber Overhead Cooler, E-80, is designated as a BEM type exchanger under

the Tubular Exchanger Manufacturers Association (TEMA) designations. In other words, this heat

exchanger is a shell and tube heat exchanger with a bonnet stationary head, one-pass shell, and

C-2
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

fixed tube sheet. It was assumed that there are two tube passes. From U&V (1) (Table 4.12, Pg

194) this type of heat exchanger has a maximum surface area per unit of 800 m2, a maximum

operating pressure of 200 bara on the shell side and 140 bara on the tube side, a maximum

operating temperature of 150 °C, and a minimum practical approach temperature of 5 °C. From

operating data provided, the actual heat exchanger surface area is 85.8 m2, the operating pressure

is 33.8 bara on the shell side and 6.0 bara on the tube side, the operating temperature is 45 °C, and

the approach temperature is 16 °C. Therefore, heat exchanger type selection is valid for this

service. The remaining heat exchangers were also deemed valid for their respective services.

To validate the simulation used to model the CO2 Removal Unit, the following assumptions

were made:

• Heat losses are negligible

• Overall heat transfer coefficient is constant

• Specific heat of each fluid is constant

The overall heat transfer coefficients (U) were calculated from the design basis by

simulating each heat exchanger on ProMax and applied to the base case simulation to calculate

heat exchange areas. Comparison of heat exchange areas from the simulation and the actual areas

from the operating data provided by the client showed good agreement. Since phase change in the

condensers were minimal, a constant U value was assumed. A mean temperature difference was

used for the reboiler instead of a log mean temperature difference. Note that the average reference

U values were used when it could not be calculated as in E-82 and E-84. The duty of E-84 given

was simulated and the resulting fan power required was used as benchmark for further redesign.

C-3
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Tag Description Reference Calculated Actual Calculated


U U Area Area (m2)
(W/m2/K) (W/m2/K) (m2)
E-80 CO2 Absorber Overhead Cooler 454-709 489 85.8 88.8
E-81A/B Lean/Rich Amine Exchanger 794-1134 1532 595.0 596.0
E-82 Stripper Reboiler 794-1134 1150.0 301.0
E-83 Stripper Overhead Condenser 1418-2837 267 381.7 376.0
E-84 Lean Amine Air Cooler 680-794

The reference heat transfer coefficients were obtained with the following considerations:
1. Stripper OH Condenser
Shell: CO2 and Water
Tube: Water
Source: Kern, 1950 (2) (Aqueous Solutions 250-500 Btu/F/h/ft2)
2. CO2 Absorber OH Cooler
Shell: Syngas
Tube: Water
Source: Perry, 2008 (3) (H2 Containing Natural-Gas Mixtures 80-125 Btu/F/h/ft2)
3. Lean Amine Air Cooler
Tube: Lean Amine
Source: Brown, 1978 (4) (Ammonia 100-120 Btu/F/h/ft2, Water 120-140 Btu/F/h/ft2)
Note: Lean amine solution is ~90% Water, ~10% aMDEA, and <1% CO2. May be
able to use above values for approximation
4. Lean/Rich Amine Exchanger
Shell: Most likely lean amine since it has less CO2 and less corrosive
Tube: Most likely semilean amine since it has more CO2
Source: Perry, 2008 (3) (Ethanol amine 10-25% solution shell side 140-200 Btu/F/h/ft2)
Note: No exact match, can use above source as approximate value
5. Stripper Reboiler
Shell: Most likely lean amine
Tube: Most likely water

C-4
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Source: Perry, 2008 (3) (Ethanol amine 10-25% solution shell side 140-200 Btu/F/h/ft2)
Note: same comments as Item 4

3. CO2 Absorber Separation


To confirm the accuracy of the CO2 Absorber simulation as well as the design basis it was

based on, the number of stages required to obtain the stated absorption of CO2 from the syngas

stream was calculated. Reasonable agreement between the calculated number of stages and the

actual number of stages provided in the CO2 Absorber data sheet. Since the simulation of the CO2

Absorber was created from the design basis and the data sheet, this agreement validates the

simulation. Detailed calculations are shown in the following pages.

C-5
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

C-6
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

C-7
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

4. Compression Stage
The CO2 stream leaving the LP Flash Stripper is compressed before being sent to battery

limits. In the process flow diagram provided, this step was shown as a single compressor with

a note that states “compressor includes required intercoolers, separators, and antisurge

protection”. According to GPSA (5) (Pg 13.11), the maximum recommended outlet

temperature of a compressor is 150 °C. This design limitation is taken into account to avoid

damage to lubricants and seals. Following this constraint, the number of stages required was

calculated to be three as shown below. The number of stages was simulated in BRE Promax

for the base case as well as the redesigns.

C-8
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

C-9
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

List of References
1. Ulrich, Gael D. and Vasudevan, Palligarnai T. Chemical Engineering Process Design and

Economics: A Practical Guide (Second Edition). Durham : Process (Ulrich) Publishing, 2004. 0-

97087683-2-3.

2. Process Heat Transfer. Kern, D. Q. New York : McGraw-Hill Book Company, Inc., 1950.

3. Perry, Robert H and Green, Don W. Perry's Chemical Engineers' Handbook. 8th. New York :

McGraw-Hill, 2007. 978-0071422949.

4. A Procedure for Preliminary Estimate. Brown, R. s.l. : Chem. Eng., 1978, Vol. 85.

5. Engineering Data Book. Gas Processors Suppliers Association. Tulsa : s.n., 2004, Vol. 1 and

2.

C-10
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Appendix D: Separation Calculations


Description
The purpose of this appendix is to demonstrate understanding of separation as it relates to

the revamp project. The analysis will focus on the CO2 Absorber, C-80, and the LP Flash Stripper,

C-82. This appendix will include separation calculations and additional information pertaining to

the 112% and 125% capacity redesign.

Table of Contents
1. Number of Stages .................................................................................................................. D-1
2. Pressure Drop ........................................................................................................................ D-3
2.1. Sample Pressure Drop Calculations .............................................................................. D-3
2.2. CO2 Absorber ................................................................................................................ D-4
2.2.1. Base Case (IMTP #40) ............................................................................................ D-4
2.2.2. 112% Case (IMTP #40) ........................................................................................... D-5
2.2.3. 125% Case (IMTP #40) ........................................................................................... D-6
2.2.4. 125% Case (IMTP #25) ........................................................................................... D-6
2.3. LP Flash Stripper ........................................................................................................... D-7
2.3.1. Base Case (IMTP #50) ............................................................................................ D-7
2.3.2. 125% Case (IMTP #40) ........................................................................................... D-8
3. Column Diameter Considerations ......................................................................................... D-9
4. Column Height Considerations ............................................................................................. D-9
4.1. Trays .............................................................................................................................. D-9
4.2. Packing Height .............................................................................................................. D-9
4.3. Disengagement Height ................................................................................................ D-10
4.4. Height of Liquid Pool .................................................................................................. D-10
5. Additional Cost ................................................................................................................... D-10
List of References ..................................................................................................................... D-11

i
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

1. Number of Stages
Using the composition of the streams entering and leaving the CO2 Absorber in the 125%

capacity simulation, the number of stages and consequently the amount of packing required were

validated in the following calculations.

D-1
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

D-2
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

2. Pressure Drop
2.1. Sample Pressure Drop Calculations

D-3
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

2.2. CO2 Absorber


2.2.1. Base Case (IMTP #40)
Base Case Absorber (IMTP #40)
Total Pressure Drop, ΔPt (in H2O/ft) 0.326 kPa/m 0.266
Dry Pressure Drop, ΔPd (in H2O/ft) 0.321
Pressure Drop due to Liquid, ΔPL (in H2O/ft) 0.004

Gas Loading Factor, Gf (lb/hr*ft2) 1426.94


Liquid Loading Factor, Lf (lb/hr*ft2) 12188.56

Superficial F-factor for Gas, Fs (ft/s(lb/ft3)0.5) 0.703


Dry Packing Factor, Fpd (ft-1) 25.91 m-1 85.00
Gas Density, ρG (lb/ft3) 0.858 kg/m3 13.75
Liquid Mass Velocity, L (lb/hr*ft2) 15960.32
Liquid Density, ρL (lb/ft3) 64.21 kg/m3 1028.57
Liquid Viscosity, µL (cP) 0.025 Pa*s 0.002

Cross Sectional Area, A (ft2) 81.24 m2 7.55

D-4
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Volumetric Gas Flow (ft3/s) 61.62 m3/s 1.74


Superficial Gas Flow, Ut (ft/s) 0.76
Liquid Mass Flow (lb/hr) 1296656.52 kg/s 163.38

Column Pressure Drop


Packing Height (m) 8.60
Pressure Drop (kPa) 2.29
Actual Pressure Drop (kPa) 10.00
Contingency Factor 4.38

2.2.2. 112% Case (IMTP #40)


112% Case Absorber (IMTP #40)
Total Pressure Drop, ΔPt (in H2O/ft) 0.418 kPa/m 0.341
Dry Pressure Drop, ΔPd (in H2O/ft) 0.407
Pressure Drop due to Liquid, ΔPL (in H2O/ft) 0.010

Gas Loading Factor, Gf (lb/hr*ft2) 1588.61


Liquid Loading Factor, Lf (lb/hr*ft2) 12539.03

Superficial F-factor for Gas, Fs (ft/s(lb/ft3)0.5) 0.782


Dry Packing Factor, Fpd (ft-1) 25.91 m-1 85.00
Gas Density, ρG (lb/ft3) 0.858 kg/m3 13.75
Liquid Mass Velocity, L (lb/hr*ft2) 16222.79
Liquid Density, ρL (lb/ft3) 64.38 kg/m3 1031.31
Liquid Viscosity, µL (cP) 0.029 Pa*s 0.003

Cross Sectional Area, A (ft2) 81.24 m2 7.55


Volumetric Gas Flow (ft3/s) 68.60 m3/s 1.94
Superficial Gas Flow, Ut (ft/s) 0.84
Liquid Mass Flow (lb/hr) 1317980.45 kg/s 166.06

Column Pressure Drop


Packing Height (m) 8.60
Pressure Drop (kPa) 2.93
Calculated Pressure Drop (kPa) 8.80
Contingency Factor 3.00
Note: 25 kPa was used in the 112% simulation case.

D-5
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

2.2.3. 125% Case (IMTP #40)


125% Case Absorber (IMTP #40)
Total Pressure Drop, ΔPt (in H2O/ft) 0.565 kPa/m 0.461
Dry Pressure Drop, ΔPd (in H2O/ft) 0.534
Pressure Drop due to Liquid, ΔPL (in H2O/ft) 0.031

Gas Loading Factor, Gf (lb/hr*ft2) 1783.63


Liquid Loading Factor, Lf (lb/hr*ft2) 13161.99

Superficial F-factor for Gas, Fs (ft/s(lb/ft3)0.5) 0.878


Dry Packing Factor, Fpd (ft-1) 25.91 m-1 85.00
Gas Density, ρG (lb/ft3) 0.858 kg/m3 13.75
Liquid Mass Velocity, L (lb/hr*ft2) 16693.38
Liquid Density, ρL (lb/ft3) 64.67 kg/m3 1035.87
Liquid Viscosity, µL (cP) 0.036 Pa*s 0.004

Cross Sectional Area, A (ft2) 81.24 m2 7.55


Volumetric Gas Flow (ft3/s) 77.02 m3/s 2.18
Superficial Gas Flow, Ut (ft/s) 0.95
Liquid Mass Flow (lb/hr) 1356212.49 kg/s 170.88

Column Pressure Drop


Packing Height (m) 5.40
Pressure Drop (kPa) 2.49
Calculated Pressure Drop (kPa) 7.47
Contingency Factor 3.00

2.2.4. 125% Case (IMTP #25)


125% Case Absorber (IMTP #25)
Total Pressure Drop, ΔPt (in H2O/ft) 1.740 kPa/m 1.421
Dry Pressure Drop, ΔPd (in H2O/ft) 1.120
Pressure Drop due to Liquid, ΔPL (in H2O/ft) 0.620

Gas Loading Factor, Gf (lb/hr*ft2) 2297.23


Liquid Loading Factor, Lf (lb/hr*ft2) 16952.03

D-6
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Superficial F-factor for Gas, Fs (ft/s(lb/ft3)0.5) 0.878


Dry Packing Factor, Fpd (ft-1) 42.98 m-1 141.00
Gas Density, ρG (lb/ft3) 0.858 kg/m3 13.75
Liquid Mass Velocity, L (lb/hr*ft2) 16693.38
Liquid Density, ρL (lb/ft3) 64.67 kg/m3 1035.87
Liquid Viscosity, µL (cP) 0.036 Pa*s 0.004

Cross Sectional Area, A (ft2) 81.24 m2 7.55


Volumetric Gas Flow (ft3/s) 77.02 m3/s 2.18
Superficial Gas Flow, Ut (ft/s) 0.95
Liquid Mass Flow (lb/hr) 1356212.49 kg/s 170.88

Column Pressure Drop


Packing Height (m) 10.20
Pressure Drop (kPa) 14.49
Calculated Pressure Drop (kPa) 43.47
Contingency Factor 3.00
Note: 40 kPa was used in 125% simulation case.

2.3. LP Flash Stripper


2.3.1. Base Case (IMTP #50)
Base Case LP Flash (IMTP #50)

Total Pressure Drop, ΔPt (in H2O/ft) 0.107 kPa/m 0.087


Dry Pressure Drop, ΔPd (in H2O/ft) 0.107
Pressure Drop due to Liquid, ΔPL (in H2O/ft) 0.000

Gas Loading Factor, Gf (lb/hr*ft2) 980.29


Liquid Loading Factor, Lf (lb/hr*ft2) 6513.58

Superficial F-factor for Gas, Fs (ft/s(lb/ft3)0.5) 1.035


Dry Packing Factor, Fpd (ft-1) 17.07 m-1 56.00
Gas Density, ρG (lb/ft3) 0.057 kg/m3 0.91
Liquid Mass Velocity, L (lb/hr*ft2) 11539.85
Liquid Density, ρL (lb/ft3) 62.31 kg/m3 998.18
Liquid Viscosity, µL (cP) 0.007 Pa*s 0.001

Cross Sectional Area, A (ft2) 122.08 m2 11.34

D-7
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Volumetric Gas Flow (ft3/s) 531.15 m3/s 15.04


Superficial Gas Flow, Ut (ft/s) 4.35
Liquid Mass Flow (lb/hr) 1408728.50 kg/s 177.50

Column Pressure Drop


Packing Height (m) 10.00
Pressure Drop (kPa) 0.87
Calculated Pressure Drop (kPa) 2.61
Contingency Factor 3.00

2.3.2. 125% Case (IMTP #40)


125% Case LP Flash (IMTP #40)
Total Pressure Drop, ΔPt (in H2O/ft) 0.173 kPa/m 0.141
Dry Pressure Drop, ΔPd (in H2O/ft) 0.172
Pressure Drop due to Liquid, ΔPL (in H2O/ft) 0.000

Gas Loading Factor, Gf (lb/hr*ft2) 1167.01


Liquid Loading Factor, Lf (lb/hr*ft2) 8625.62

Superficial F-factor for Gas, Fs (ft/s(lb/ft3)0.5) 0.952


Dry Packing Factor, Fpd (ft-1) 25.91 m-1 85.00
Gas Density, ρG (lb/ft3) 0.128 kg/m3 2.04
Liquid Mass Velocity, L (lb/hr*ft2) 11974.11
Liquid Density, ρL (lb/ft3) 67.73 kg/m3 1084.98
Liquid Viscosity, µL (cP) 0.023 Pa*s 0.002

Cross Sectional Area, A (ft2) 122.08 m2 11.34


Volumetric Gas Flow (ft3/s) 325.43 m3/s 9.22
Superficial Gas Flow, Ut (ft/s) 2.67
Liquid Mass Flow (lb/hr) 1461740.63 kg/s 184.18

Column Pressure Drop


Packing Height (m) 10.00
Pressure Drop (kPa) 1.41
Calculated Pressure Drop (kPa) 4.23
Contingency Factor 3.00
Note: 5 kPa was used in the 125% simulation case.

D-8
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

3. Column Diameter Considerations


The pressure drops were calculated and adjusted to keep the diameter of the CO2 Absorber and

the LP Flash Stripper. Using the pressure drops and the resulting flow rates, the diameter of the

columns were confirmed to stay the same across the redesign cases using the Eckert generalized

pressure drop correlation (1).

4. Column Height Considerations


An estimate of the column height considers the space occupied by trays (number of stages with

the tray spacing) and packing, the disengagement height at the top of the column, and the height

of liquid pool at the bottom. Taking these into account, the columns were verified to handle the

increase in capacity.

4.1. Trays
The CO2 Absorber has three backwash trays at the top of the column. Tray spacing is

usually 2 ft. According to the data sheet provided, the tray spacing is 1.64 ft. Since these trays only

serve the purpose of preventing entrainment of amine into the overhead stream, the lower tray

spacing is acceptable. In the 125% redesign, the backwash tray spacing was kept at 1.64 ft (500

mm).

4.2. Packing Height


Still looking at the CO2 Absorber, the packing type was changed, and the amount was

increased to increase the amount of CO2 removed from the inlet stream. Increasing the amount of

packing changes the total height in the column occupied by packing. Considerations were made to

ensure that the placement of additional packing did not interfere with existing nozzles. Liquid

distributors were also integrated to ensure proper flow through the packing.

D-9
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

4.3. Disengagement Height


Disengagement height is required to allow the liquid to disengage from the vapour.

Typically, this height is around 5 to 10 ft (1.5 – 3 m). In the provided CO2 Absorber data sheet,

the top backwash tray is located approximately 6 ft from the top of the column. The recommended

disengagement height is met and kept for the 125% capacity redesign.

4.4. Height of Liquid Pool


At the bottom of the tower, some surge protection is needed which typically corresponds

to 5 to 10 minutes worth of flow. In the 125% capacity redesign, the total liquid flow to the CO2

Absorber is 0.166 m3/s. In 5 minutes, the corresponding volume accumulated is 49.7 m3. Using

the column diameter of 3.1 m, this corresponds to a required surge height of 6.6 m (21.7 ft). The

provided data sheet shows 7.9 m (25.9 ft) from the bottom of the column to the inlet syngas nozzle.

With the increase in capacity, the tower still has adequate surge height.

5. Additional Cost
To obtain better separation of CO2 from the syngas stream, packing with higher efficiency is

required. Changing the existing packing to a higher efficiency type as well as increasing the

amount of it in the CO2 Absorber incurs additional cost. Installation of the new packing will also

require labour from trained personnel. Similar costs will be incurred in changing the packing type

in the LP Flash Stripper.

D-10
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

List of References
1. Engineering Data Book. Gas Processors Suppliers Association. Tulsa : s.n., 2004, Vol. 1 and

2.

2. Perry, Robert H and Green, Don W. Perry's Chemical Engineers' Handbook. 8th. New York :

McGraw-Hill, 2007. 978-0071422949.

D-11
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Appendix E: Drawing Package


Description
This appendix contains the index, plot plan, block diagram, process flow diagram, and the

piping and instrumentation diagram. A stream table and equipment list for the entire process is

also included.

A plot plan was created for the base, 112% design, and 125% design case. The base and

112% design case have identical plot plans since the 112% design case does not require any

addition equipment or resizing. The 125% design case includes the lean amine cooler (E-85) that

was added for further cooling of the lean amine to the CO2 absorber (C-80).

A process flow diagram was created for the base, 112% design, and 125% design case. The

base and 112% design case have identical plot plans since the 112% design case does not require

any addition equipment. The 125% design case includes the E-85 that was added for further

cooling of the lean amine to C-80.

A piping and instrumentation diagram was created for E-85 in the 125% design case. The

base and 112% design case does not have a piping and instrumentation diagram since the proper

information was not provided to Okane Engineering to draw one.

i
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Table of Contents
1. List of Drawings ....................................................................................................................E-1
2. Plot Plan for the Base and 112% Design Case ......................................................................E-1
3. Plot Plan for the 125% Design Case ......................................................................................E-3
4. Block Flow Diagram ..............................................................................................................E-4
5. Stream Table for the Base Case .............................................................................................E-5
6. Stream Table for the 112% Case ...........................................................................................E-6
7. Process Flow Diagram for the Base and 112% Cases ...........................................................E-7
8. Stream Table for the 125% Case ...........................................................................................E-8
9. Process Flow Diagram for the 125% Case ............................................................................E-9
10. Process Flow Diagram for the Vendor Compression Unit ..................................................E-10
11. Line Designation Table for CN49PID .................................................................................E-11
12. CN49PID for E-85 ...............................................................................................................E-12

ii
DRAWING NO. DRAWING TITLE REV REMARKS

INDEX OKANE ENGINEERING INDEX 0

CN49PLT PLOT PLAN - UNIT 49 - BASE AND 112% DESIGN CASE 1

CN49PLT PLOT PLAN - UNIT 49 - 125% DESIGN CASE 1

CN49BFD BLOCK FLOW DIAGRAM - UNIT 49 1

STREAM TABLE STREAM TABLE FOR BASE CASE 0 CANADIAN NATURAL RESOURCES LTD.

STREAM TABLE STREAM TABLE FOR 112% DESIGN CASE 0 REVAMP OF CO2 RECOVERY PLANT

CN49PFD PROCESS FLOW DIAGRAM - UNIT 49 - BASE AND 112% DESIGN CASE 4

STREAM TABLE STREAM TABLE FOR 125% DESIGN CASE 0

CN49PFD PROCESS FLOW DIAGRAM - UNIT 49 - 125% DESIGN CASE 4

CM49PFD PROCESS FLOW DIAGRAM - UNIT 49 - COMPRESSOR STAGE 1

LDT LINE DESIGNATION TABLE - E-85 0 INDEX

CN49PID PIPING AND INSTRUMENTATION DIAGRAM - E-85 2

1. List of Drawings
1. List of Drawings

2. E-1
SCALE (m) : EQUIPMENT LIST
Prevailing Wind
2.5 5 10 20 Direction E-80 – CO2 Absorber Overhead Cooler

E-81A/B – Lean/Rich Amine Exchanger


Plot Plan for the Base and 112% Design Case
E-82 – Stripper Reboiler
Pipe Rack
Elevevation: 7m E-83 – Stripper Overhead Condensor

E-84 – Lean Amine Air Cooler

C-80 – CO 2 Absorber

C-81 – HP Amine Flash Drum


ROAD
C-82 – LP Flash Stripper

C-83 – Reflux Vessel


C-85 C-84
E-84 C-84 – Make-Up Storage Vessel
PUMP G-86A
C-87 – Absorber Overhead K.O Drum
PUMP G-86A
G-84 G-82A PUMP G-81A/B – Semilean Amine Pump
PUMP G-86B PUMP
G-82B PUMP G-82A/B/C – HP Lean Amine Pump
PUMP G-87A
G-82C PUMP ROAD G-83A/B – Stripper Reflux Pump
PUMP G-87B E-81A/B
G-84 – Amine Make-Up Pump
G-81A PUMP

E-82 G-81B PUMP KEY PLAN


C-83
PUMP G-83A/B
E-80
C-86 E-83
FTR-80
C-87

C-81
C-80
C-82

ROAD Revamp of Carbon Dioxide Recovery Plant

PLOT PLAN – BASE & 112% DESIGN CASE

BY: E. KWAK DRAWING NUMBER REV


DAT E : 2019/03/ 14 CN49PLT 1

E-2
SCALE (m) : EQUIPMENT LIST
Prevailing Wind
2.5 5 10 20 Direction E-80 – CO2 Absorber Overhead Cooler

E-81A/B/C – Lean/Rich Amine Exchanger


3. Plot Plan for the 125% Design Case
E-82 – Stripper Reboiler
Pipe Rack
E-83 – Stripper Overhead Condensor
Elevevation: 7m
E-84 – Lean Amine Air Cooler

E-85A/B – Lean Amine Cooler

C-80 – CO 2 Absorber

ROAD C-81 – HP Amine Flash Drum

C-82 – LP Flash Stripper

C-84 C-83 – Reflux Vessel


C-85
PUMP G-86A C-84 – Make-Up Storage Vessel
E-84
PUMP G-86A C-87 – Absorber Overhead K.O Drum
G-84 G-82A PUMP
PUMP G-86B PUMP G-81A/B – Semilean Amine Pump
G-82B PUMP
G-82A/B/C – HP Lean Amine Pump
PUMP G-87A
G-82C PUMP G-83A/B – Stripper Reflux Pump
PUMP G-87B E-81A/B/C
ROAD G-84 – Amine Make-Up Pump
G-81A PUMP

E-82 G-81B PUMP KEY PLAN


C-83
PUMP G-83A/B
E-85A/B
E-80
C-86 E-83
FTR-80
C-87

C-81
C-80
C-82

ROAD Revamp of Carbon Dioxide Recovery Plant

PLOT PLAN – DESIGN CASE

BY: E. KWAK DRAWING NUMBER REV


DAT E : 2019/03/ 14 CN49PLT 1
E-3
4. Block Flow Diagram

Pressure Swing
Tail Gas
Absorption

Lean Amine

Rich Amine Vendor


CO2 Amine Lean Amine Dehydration
Compression CO2 Product
Absorption Regeneration Unit
Unit

Syngas

Project Scope
Separation
System
Boiler Feed
Water
High
Process Gas Temperature
Reaction

Revamp of Carbon Dioxide Recovery Plant

1 ADDITION OF DEHYDRATION BLOCK EK 2019/01/ 31


BLOCK FLOW DIAGRAM
0 BLOCK FLOW DIAGRAM DRAFT EK 2019/01/ 23 BY: E. KWAK DRAWING NUMBER REV
REV DESCRIPTION BY DATE DATE: 2019/03/01 CMP49BFD 1

E-4
2. Block Flow Diagram L-4
5. Stream Table for the Base Case

E-5
L-5
6. Stream Table for the 112% Case

E-6
L-6
E-80 C-87 C-82 E-83 G-83A/B C-83 E-82 C-81
CO2 Absorber Absorber Overhead LP Flash Stripper Stripper Overhead Stripper Reflux Reflux Vessel Stripper Reboiler HP Amine Flash Drum
3 3 2 3
Overhead Cooler K.O. Drum Volume: 443.0 m Condenser Pump Volume: 36.8 m Area: 298.1 m Volume: 75.0 m
2 3 2
Area: 90.0 m Volume: 9.7 m Area: 381.0 m Duty: 1 kW
E-84 G-82A/B/C E-81A/B G-81A/B G-84 C-80 C-84
Lean Amine Air HP Lean Amine 7. Process Flow DiagramSemilean
for the
Lean/Rich Amine Base and
Amine Amine112%
Make-Up Cases CO Absorber 2
3
Make Up Storage
Cooler Pump Exchanger Pump Pump Volume: 177.0 m Vessel
2
Duty: 27838 kW Duty: 1158 kW Area: 1217.6 m Duty: 120 kW 37 CMP49PFD

Synthesis Gas to PSA


E-83
(49-V-400) 28
35 36
E-80
LC C-83
26 27 CWS CWR
FC LC C-87 95
CWS CWR
LP Condensate 72 77
93
LC

94

FC
96
87 G-83A/B
Synthesis Gas 25
C-80 LC

82
FC
PC C-82
Process Water to
Flash Gas to Steam Battery Limits
Methane Reformer 75
C-81 E-81A/B
83 78 FC
73 74

LC E-82 LP Steam

81
86 76
LP Condensate
85
E-84 84
C-84
LP Steam
LP Condensate G-82A/B/C G-81A/B

G-84
Revamp of Carbon Dioxide Recovery Plant
Amine Solution

4 SEPARATION OF COMPRESSION STAGES FROM MAIN BODY EK 2019/03/08


3 DEHYDRATION UNIT ADJUSTMENT EK 2019/03/01
2 ADJUSTMENT AFTER ACADEMIC ADVISOR MEETING EK 2019/02/23
PROCESS FLOW DIAGRAM–_UNIT 49 –_BASE AND 112% CASE
1 ADJUSTMENT AFTER INDUSTRIAL MEETING EK 2019/01/31
0 PFD DRAFT EK 2019/01/23 BY: E. KWAK DRAWING NUMBER REV
REV DESCRIPTION BY DATE DATE: 2019/03/01 E-7
CN49PFD 4
L-7
8. Stream Table for the 125% Case

E-8
L-8
E-80 C-87 C-82 E-83 G-83A/B C-83 E-82 C-81
CO 2 Absorber Absorber Overhead LP Flash Stripper Stripper Overhead Stripper Reflux Reflux Vessel Stripper Reboiler HP Amine Flash Drum
Overhead Cooler K.O. Drum Volume: 443 m3 Condenser Pump Volume: 36.8 m3 Area: 301.1 m2 Volume: 75 m3
Area: 74.39 m2 Volume: 9.7 m3 Area: 382.1 m2 Duty: 1 kW
E-84 G-82A/B/C E-81A/B/C G-81A/B G-84 E-85A/B C-80 C-84
Lean Amine Air HP Lean Amine Lean/Rich Amine Semilean Amine Amine Make-Up Lean Amine Cooler CO 2 Absorber Make Up Storage
Cooler Pump Exchanger Pump Pump Area: 815.4 m2 Volume: 177 m3 Vessel
2
Duty: 24870 kW Duty: 1185 kW Area: 1772.2 m Duty: 123 kW
9. Process Flow Diagram for the 125% Case E-83
37 CMP4 9PFD

Synthesis Gas to PSA


(4 9-V-400)
28

E-80 35 36

LC C-83
26 27 CWS CWR
FC LC C-87 95
CWS CWR
LP Condensate 72 77
93
LC

94

FC
96
87 G-83A/B
Synthesis Gas 25
C-80 LC

82
FC
86 PC C-82
Process Water to
Flash Gas to Steam Battery Limits
75
Methane Reformer
C-81 E-81A/B/C
83 78 FC
E-85A/B 73 74

CWS CWR LC E-82 LP Steam

81
86C 76
LP Condensate
85
E-84 84
C-84
LP Steam
LP Condensate G-82A/B/C G-81A/B

G-84
Amine Solution Revamp of Carbon Dioxide Recovery Plant

4 SEPARATION OF COMPRESSION STAGES FROM MAIN BODY EK 2019/03/ 08


3 DEHYDRATION UNIT ADJUSTMEN T EK 2019/03/ 01
2 ADJUSTMENT AFTER ACADEMIC ADVISOR MEETING EK 2019/02/ 23
PROCESS FLOW DIAGRAM – UNIT 49 – CASE
1 ADJUSTMENT AFTER INDUSTRIAL MEETING EK 2019/01/ 31
0 PFD DRAFT EK 2019/01/ 23 BY: E. KWAK DRAWING NUMBER REV
REV DESCRIPTION BY DATE DATE: 2019/03/01 CN49 PFD 4
E-9
L-9
K-100 K-101 K-102 D-100/101 E-101/102/103
CO2 Product CO 2 Product CO 2 Product Knockout Drums Interstage Coolers
Compressor Compressor Compressor
10.1606Process
Duty (112%): kW Flow
Duty Diagram
(112%): 1521 kWfor Duty
the Vendor Compression
(112%): 1416 kW Unit
Duty (125%): 1831 kW Duty (125%): 1670 kW Duty (125%): 1541 kW

CN49PFD

37

PC PC PC

K-100 K-101 K-102

37D 37H

CWS CWS CWS


37A 37E 37I

CO2 Product to
37B 37F 38 Dehydration Unit

CWR CWR CWR


E-101 E-102 E-103

LC LC

D-100 D-101

37C 37G

Revamp of Carbon Dioxide Recovery Plant

PROCESS FLOW DIAGRAM – COMP RESSION STAGE


1 REMOVAL OF FOU RTH STAGE EK 2019/03/10
0 COMP RESSION STAGE DRAFT EK 2019/03/08 BY: E. KWAK DRAWING NUMBER REV
REV DESCRIPTION BY DATE DATE: 2019/03/01 CMP49PFD 1

E-10
L-10
LINE DESIGNATION DESCRIPTION MECHANICAL OPREATING CONDITIONS DESIGN CONDITIONS REFERENCE DRAWINGS

COM LINE NO PIPE SIZE FROM TO SERVICE MATERIAL TEMP ( C) PRESSURE (kPag) TEMP ( C) PRESSURE (kPag) P&ID

AOAA 86C 16 LEAN AMINE AIR COOLER (E-84) LEAN AMINE COOLER (E-85) LEAN SS-316 41 4099 165 6448 CN49PID

AOAA 86 16 LEAN AMINE COOLER (E-85) CARBON DIOXIDE ABSORBER (C-80) LEAN SS-316 35 4099 165 6448 CN49PID

CWS 86 10 UTILITY COOLING WATER TANK LEAN AMINE COOLER (E-85) WATER SS-316 24 500 65 550 CN49PID

CWR 86 10 LEAN AMINE COOLER (E-85) WATER DRAIN/RECYCLE SYSTEM WATER SS-316 32 480 65 550 CN49PID

Notes:

11. Line Designation Table for CN49PID

E-11
L-11
12. CN49PID for E-85

E-12
L-12
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Appendix F: Start-Up and Shutdown Procedures


Description
This appendix outlines the modifications that will be needed for start-up and shutdown of

the CO2 Recovery Plant in the 112% and 125% capacity redesigns.

Table of Contents
1. 112% Capacity Redesign ....................................................................................................... F-1
2. 125% Capacity Redesign ....................................................................................................... F-1
2.1. Start-Up Procedures ....................................................................................................... F-1
2.2. Shutdown Procedures ..................................................................................................... F-2

i
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

1. 112% Capacity Redesign


No equipment is added or modified in the 112% capacity redesign. Start-up and shutdown

procedures shall be consistent with the existing procedures. Only the flow rate of amine solution

will need to be adjusted when filling the amine system with lean amine solution during start-up.

The pressure, temperature, and flow rate setpoints that need to be adjusted are identified below:

Table K1: Temperature, Pressure, and Flow Rate Changes for the 112% Capacity Redesign

Stream Description Base Case 112% Case


No
25 SG to CO2 Absorber Flow Rate 8214 kmol/h 9148 kmol/h
27 SG from CO2 Absorber OH Cooler Temperature 40.0 °C 39.8 °C
36 CO2 to Reflux Vessel Temperature 45.0 °C 44.4 °C
86 Lean Amine from Air Cooler aMDEA Flow Rate 2018 kmol/h 2106 kmol/h
86 Lean Amine from Air Cooler Temperature 45.0 °C 41.5 °C
95 Process Condensate to LP Flash Stripper Flow Rate 142 kmol/h 148 kmol/h
- CO2 Absorber Bottom Operating Pressure 3285 kPa(g) 3300 kPa(g)

2. 125% Capacity Redesign


2.1. Start-Up Procedures
Passivation of the Lean Amine Cooler (E-85A/B) should be completed according to the

existing passivation procedures developed by Canadian Natural Resources Ltd. prior to

commissioning the exchanger. This is recommended in order to provide better corrosion protection

for the carbon steel shell of the exchanger. The following must also be added to the requirements

for preparation prior to start-up of the CO2 Recovery Plant:

• The amine system, including the Lean Amine Cooler (E-85A/B) and Lean/Rich Amine

Exchanger (E-81A/B/C), must be filled with lean amine solution

F-1
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

• The column packings must be flushed and degreased before being installed into the

CO2 Absorber (C-80) and LP Flash Stripper (C-82)

• The cooling water supply to the Lean Amine Cooler (E-85A/B) must be in operation

after the system is filled with lean amine solution

• The upsized Absorber Overhead Knockout Drum (C-87) and Reflux Vessel (C-83)

must be filled with condensate or demineralized water to prevent dew point corrosion

During the start-up sequence, the cooling water supply to the Lean Amine Cooler (E-85A/B) must

be increased prior to operating the Stripper Reboiler (E-82) at full steam flow rates. This is to the

prevent the hot lean amine solution from vaporizing the cooling water in the tube side of the Lean

Amine Cooler (E-85A/B). This would result in over pressurization of the exchanger tubes and

would trigger the release of steam from the pressure relief valve on the cooling water outlet piping.

The pressure, temperature, and flow rate setpoints that need to be adjusted are identified below:

Table K2: Temperature, Pressure, and Flow Rate Changes for the 125% Capacity Redesign

Stream Description Base Case 125% Case


No
25 SG to CO2 Absorber Flow Rate 8214 kmol/h 10271 kmol/h
27 SG from CO2 Absorber OH Cooler Temperature 40.0 °C 39.0 °C
36 CO2 to Reflux Vessel Temperature 45.0 °C 41.5 °C
72 Steam Condensate to CO2 Absorber Flow Rate 122 kmol/h 130 kmol/h
86 Lean Amine from Air Cooler aMDEA Flow Rate 2018 kmol/h 2211 kmol/h
86(C) Lean Amine from Air Cooler Temperature 45.0 °C 40 °C
95 Process Condensate to LP Flash Stripper Flow Rate 142 kmol/h 116 kmol/h
- CO2 Absorber Bottom Operating Pressure 3285 kPa(g) 3300 kPa(g)
- LP Flash Stripper Bottom Operating Pressure 50 kPa(g) 55 kPa(g)

2.2. Shutdown Procedures


Cooling water to the Lean Amine Cooler (E-85A/B) should be turned off after the steam

flow rate to the Stripper Reboiler (E-82) is reduced to avoid vaporization of water in the tubes.

F-2
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Appendix G: Detailed Material and Energy Balances


Description
This appendix contains the detailed material and energy balance tables for the base, 112%,
and 125% cases. The tables all include the stream numbers and corresponding descriptions.

Table of Contents
1. Overall Material Balances..................................................................................................... G-1
1.1. Base Case ...................................................................................................................... G-1
1.2. 112% Case ..................................................................................................................... G-2
1.3. 125% Case ..................................................................................................................... G-3
2. Overall Energy Balances....................................................................................................... G-4
2.1. Base Case ...................................................................................................................... G-5
2.2. 112% Case ..................................................................................................................... G-6
2.3. 125% Case ..................................................................................................................... G-7

i
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

1. Overall Material Balances


Mass balances were constructed using stream flow rates outputted by the simulation. Individual

mass balances around each equipment were checked and verified minimal losses as indicated by

overall mass balance agreements shown in the following sections. Mass was conserved for all three

cases.

𝑀𝑎𝑠𝑠 𝐼𝑛 = 𝑀𝑎𝑠𝑠 𝑂𝑢𝑡

1.1. Base Case


Material In Material Out
Stream Name Description
(kmol/h) (kmol/h)
25 SG to CO2 Absorber 8217.0 -
Amine MakeUp Amine Makeup 0.0 -
IN

Water Makeup Water Makeup 5.1 -


72 Steam Condensate to CO2 Absorber 122.0 -
28 SG from CO2 Recovery Unit - 7009.8
38 CO2 to Dehydration Unit - 1198.3
75 Flash Gas from HP Amine Flash Drum - 15.9
Process Condensate to BL Process
96 - 28.2
OUT

Water Header
Amine Blowdown Amine Blowdown - 1.3
Water Blowdown Water Blowdown - 0.0
37C Stage 1 Compressor K.O. Vessel - 71.1
37G Stage 2 Compressor K.O. Vessel - 19.4
Total (kmol/h) 8344.1 8344.1
Percent Difference 0.00%

G-1
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

1.2. 112% Case


Material In Material Out
Stream Name Description
(kmol/h) (kmol/h)
25 SG to CO2 Absorber 9148.0 -
Amine MakeUp Amine Makeup 0.0 -
IN

Water Makeup Water Makeup 0.0 -


72 Steam Condensate to CO2 Absorber 122.0 -
28 SG from CO2 Recovery Unit - 7849.7
38 CO2 to Dehydration Unit - 1289.7
75 Flash Gas from HP Amine Flash Drum - 16.1
Process Condensate to BL Process
96 - 21.0
OUT

Water Header
Amine Blowdown Amine Blowdown - 0.0
Water Blowdown Water Blowdown - 0.0
37C Stage 1 Compressor K.O. Vessel - 72.7
37G Stage 2 Compressor K.O. Vessel - 20.8
Total (kmol/h) 9270.0 9270.0
Percent Difference 0.00%

G-2
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

1.3. 125% Case


Material In Material Out
Stream Name Description
(kmol/h) (kmol/h)
25 SG to CO2 Absorber 10271.0 -
Amine MakeUp Amine Makeup 1.9 -
IN

Water Makeup Water Makeup 0.1 -


72 Steam Condensate to CO2 Absorber 130.0 -
28 SG from CO2 Recovery Unit - 8813.6
38 CO2 to Dehydration Unit - 1447.9
75 Flash Gas from HP Amine Flash Drum - 17.0
Process Condensate to BL Process
96 -
OUT

Water Header 36.7


Amine Blowdown Amine Blowdown - 0.0
Water Blowdown Water Blowdown - 0.0
37C Stage 1 Compressor K.O. Vessel - 64.9
37G Stage 2 Compressor K.O. Vessel - 23.0
Total (kmol/h) 10403.1 10403.0
Percent Difference 0.0%

G-3
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

2. Overall Energy Balances


The energy balances were constructed using simulation output. In the model validation

appendix, it had been shown that specific heat capacities of streams were adequately modelled in

the simulation and the duty as well as heat exchange areas had been verified for the heat

exchangers. Note that a Fictional Exchanger has been added to the semilean pump-around to reflect

stream properties in the design basis. Also, due to inadequacy of the simulation to reflect the

exothermic absorption process, another fictitious heat exchanger with a duty of 918 kW was

introduced to reflect this in the absorber as shown in the addendum simulation file “CO2 Recovery

Unit Simulation (Addendum) Rev0”. This duty was then deducted from the E-80 duties in the

original simulation files. Without having accounted for this duty, the size of the E-80 would have

been twice as large as what it really is.

Further validation of stream enthalpies involved in the overall energy balance was performed.

These enthalpies were multiplied by the mass flow rates for ease of comparison with the base case

energy balance provided below. Since the design basis flow rates were used in the base case

simulation, this multiplication is acceptable. Good agreement between the actual design basis

values and the simulated values support the accuracy of the energy balances included in this study.

Stream Actual Mass Simulated Mass Percent


Description
Name Enthalpy (kJ/s) Enthalpy (kJ/s) Difference (%)
25 SG to CO2 Absorber -165,308 -165,345 0.02
SG from CO2 Recovery -34,363 -34,363 0.00
28
Unit
38 CO2 to Dehydration Unit -131,743 -130,910 0.63

G-4
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

2.1. Base Case


Energy In Energy Out
Stream Name Description
(kW) (kW)
25 SG to CO2 Absorber -165,345 -
Amine MakeUp Amine Makeup 0 -
IN

Water Makeup Water Makeup -400 -


72 Steam Condensate to CO2 Absorber -9,627 -
28 SG from CO2 Recovery Unit - -34,363
38 CO2 to Dehydration Unit - -130,910
75 Flash Gas from HP Amine Flash Drum - -977
Process Condensate to BL Process Water
96 - -2,230
OUT

Header
Amine Blowdown Amine Blowdown - -111
Water Blowdown Water Blowdown - 0
37C Stage 1 Compressor K.O. Vessel - -5,615
37G Stage 2 Compressor K.O. Vessel - -1,537
E-80 CO2 Absorber Overhead Cooler - 1,267
E-81A/B Lean/Rich Amine Exchanger (Semilean Side) 18,149 -
E-81A/B Lean Amine Exchanger (Lean Side) 18,149
E-82 Stripper Reboiler 31,600
E-83 Stripper Overhead Condenser 2,362
Fictional Exchanger Semilean Amine Preheat 9
EQUIPMENT

E-84 Lean Amine Air Cooler 27,838


E-101 Interstage Compression Cooler 1 2,392
E-102 Interstage Compression Cooler 2 1,741
E-103 Interstage Compression Cooler 3 1,865
G-81A/B Semilean Amine Pump 111
G-82A/B/C HP Lean Amine Pump 1,143
G-83A/B Stripper Reflux Pump 1
K-100 CO2 Product Compressor 1 1,488
K-101 CO2 Product Compressor 2 1,415
K-102 CO2 Product Compressor 3 1,325
Total (kW) -120,130 -120,129
Percent Difference 0.0%

G-5
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

2.2. 112% Case


Energy In Energy Out
Stream Name Description
(kW) (kW)
25 SG to CO2 Absorber -184,079 -
Amine MakeUp Amine Makeup 0 -
IN

Water Makeup Water Makeup -1 -


72 Steam Condensate to CO2 Absorber -9,627 -
28 SG from CO2 Recovery Unit - -43,164
38 CO2 to Dehydration Unit - -140,898
75 Flash Gas from HP Amine Flash Drum - -1,002
Process Condensate to BL Process Water
96 - -1,659
OUT

Header
Amine Blowdown Amine Blowdown - 0
Water Blowdown Water Blowdown - 0
37C Stage 1 Compressor K.O. Vessel - -5,748
37G Stage 2 Compressor K.O. Vessel - -1,649
E-80 CO2 Absorber Overhead Cooler - 1,267
E-81A/B Lean/Rich Amine Exchanger (Semilean Side) 21,225 -
E-81A/B Lean Amine Exchanger (Lean Side) - 21,225
E-82 Stripper Reboiler 31,600 -
E-83 Stripper Overhead Condenser - 2,361
Fictional Exchanger Semilean Amine Preheat 13 -
EQUIPMENT

E-84 Lean Amine Air Cooler - 27,838


E-101 Interstage Compression Cooler 1 - 2,524
E-102 Interstage Compression Cooler 2 - 1,872
E-103 Interstage Compression Cooler 3 - 1,998
G-81A/B Semilean Amine Pump 120 -
G-82A/B/C HP Lean Amine Pump 1,158 -
G-83A/B Stripper Reflux Pump 1 -
K-100 CO2 Product Compressor 1 1,606 -
K-101 CO2 Product Compressor 2 1,521 -
K-102 CO2 Product Compressor 3 1,416 -
Total (kW) -135,046 -135,035
Percent Difference 0.0%

G-6
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

2.3. 125% Case


Energy In Energy Out
Stream Name Description
(kW) (kW)
25 SG to CO2 Absorber -206,676 -
Amine MakeUp Amine Makeup -211 -
IN

Water Makeup Water Makeup -12 -


72 Steam Condensate to CO2 Absorber -10,258 -
28 SG from CO2 Recovery Unit - -48,497
38 CO2 to Dehydration Unit - -158,205
75 Flash Gas from HP Amine Flash Drum - -1,090
Process Condensate to BL Process Water
96 - -2,898
OUT

Header
Amine Blowdown Amine Blowdown - 0
Water Blowdown Water Blowdown - 0
37C Stage 1 Compressor K.O. Vessel - -5,124
37G Stage 2 Compressor K.O. Vessel - -1,822
E-80 CO2 Absorber Overhead Cooler - 1,107
E-81A/B/C Lean/Rich Amine Exchanger (Semilean Side) 27,059
E-81A/B/C Lean Amine Exchanger (Lean Side) 27,059
E-82 Stripper Reboiler 31,600 -
E-83 Stripper Overhead Condenser - 2,190
Fictional Exchanger Semilean Amine Preheat 14
EQUIPMENT

E-84 Lean Amine Air Cooler - 24,870


E-85A/B Lean Amine Cooler - 3,467
E-101 Interstage Compression Cooler 1 2,610
E-102 Interstage Compression Cooler 2 2,092
E-103 Interstage Compression Cooler 3 2,194
G-81 Semilean Amine Pump 123 -
G-82 HP Lean Amine Pump 1,185 -
G-83 Stripper Reflux Pump 1 -
K-100 CO2 Product Compressor 1 1,831
K-101 CO2 Product Compressor 2 1,700
K-102 CO2 Product Compressor 3 1,541
Total (kW) -152,103 -152,047
Percent Difference 0.0%

G-7
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Appendix H: Detailed Equipment List and Sizing


Description
This appendix includes calculations completed to obtain sizes of equipment included in the

existing plant as well as those required for a capacity increase to 125 %. The existing operating

data for each equipment, the output of the base case simulation, as well as the output of the capacity

increase redesign are compared to identify additional units to be procured. Heat exchangers,

separators, and pumps were sized using Gas Processors Suppliers Association Engineering Data

Book.

Table of Contents
1. Detailed Equipment List – Base Case ................................................................................... H-1
2. Detailed Equipment List – 112 % Case ................................................................................ H-5
3. Detailed Equipment List – 125 % Case ................................................................................ H-9
4. Heat Exchanger Sizing ........................................................................................................ H-13
4.1. Operating Data Provided ............................................................................................. H-13
4.2. Design Data Sheet Provided ........................................................................................ H-14
4.3. Heat Exchanger Sizing Sample Calculations .............................................................. H-15
4.4. Base Case Sizes ........................................................................................................... H-16
4.5. 112 % Case Sizes ........................................................................................................ H-18
4.6. 125 % Case Sizes ........................................................................................................ H-19
5. Vessel Sizing....................................................................................................................... H-21
5.1. Operating Data Provided ............................................................................................. H-22
5.2. Separator Sizing Sample Calculations ........................................................................ H-22
5.3. Base Case Sizes ........................................................................................................... H-28
5.4. 112 % Case Sizes ........................................................................................................ H-29
5.5. 125 % Case Sizes ........................................................................................................ H-30
6. Column Sizing .................................................................................................................... H-31

i
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

6.1. Operating Data Provided ............................................................................................. H-32


6.1.1. CO2 Absorber (C-80) ............................................................................................. H-32
6.1.2. LP Flash Stripper (C-82) ....................................................................................... H-35
7. Pump Sizing ........................................................................................................................ H-39
7.1. Operating Data Provided ............................................................................................. H-39
7.2. Base Case .................................................................................................................... H-40
7.1. Pump Sizing Methodology .......................................................................................... H-42
7.2. 112 % Case .................................................................................................................. H-42
7.3. 125 % Case .................................................................................................................. H-44
8. Process Lines Sizing ........................................................................................................... H-45
8.1. Methodology ............................................................................................................... H-45
8.1.1. Single Phase Vapour Flow .................................................................................... H-46
8.1.2. Single Phase Liquid Flow...................................................................................... H-46
8.1.3. Two Phase Flow .................................................................................................... H-47
8.2. Sample Calculations .................................................................................................... H-47
8.2.1. Single Phase Flow ................................................................................................. H-47
8.2.2. Two-Phase Flow .................................................................................................... H-51
8.2.3. Pipe Thickness ....................................................................................................... H-53
8.1. Size of Main Process Lines Summary ......................................................................... H-56
9. Material Selection ............................................................................................................... H-57
9.1. Potential Cracking Mechanisms .................................................................................. H-57
9.1.1. Sulfide Stress Cracking (SSC) .............................................................................. H-57
9.1.2. Hydrogen-induced Cracking (HIC) ....................................................................... H-57
9.1.3. Stress-Oriented Hydrogen-Induced Cracking (SOHIC)........................................ H-58
9.1.4. Alkaline Stress Corrosion Cracking (ASCC) ........................................................ H-58
9.1.5. Chloride Stress Corrosion Cracking ...................................................................... H-59
9.1.6. Amine Stress Corrosion Cracking ......................................................................... H-59
9.2. Potential Corrosion Mechanisms................................................................................. H-60
9.2.1. Erosion / Erosion-Corrosion .................................................................................. H-60
9.2.2. Vibration-Induced Fatigue .................................................................................... H-60
9.2.3. Cavitation .............................................................................................................. H-61

ii
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

9.2.4. Cooling Water Corrosion ...................................................................................... H-61


9.2.5. CO2 Corrosion ....................................................................................................... H-61
9.2.6. Flue-Gas Dew-Point Corrosion ............................................................................. H-62
9.2.7. Hydrogen Embrittlement ....................................................................................... H-62
9.2.8. Amine Corrosion ................................................................................................... H-63
9.2.9. High Temp H2/H2S Corrosion ............................................................................... H-63
9.3. Carbon Steel ................................................................................................................ H-63
9.3.1. Killed Carbon Steel ............................................................................................... H-64
9.4. Stainless Steel .............................................................................................................. H-64
List of References ..................................................................................................................... H-66

iii
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

1. Detailed Equipment List – Base Case


Equipment Identification Heat Exchangers
Number E-80 E-81A/B/C E-82 E-83 E-84
CO2 Absorber Lean/Rich Amine Stripper Reboiler Stripper Overhead Lean Amine Air
Name
Overhead Cooler Exchanger Condenser Cooler
Stream Number 26 81 83 35 85
Semilean Amine to Lean Amine from
SG from CO2 Lean Amine from LP CO2 from LP
Name L/R Amine HP Lean Amine
Absorber Flash Stripper Flash Stripper
Exchanger Pump
Process Orientation Shell-Side Cold Side Shell-Side Shell-Side Hot Side
Phase Vapour Liquid Liquid In, Vapour Out Vapour Liquid
Residence Time (s)
Temperature (℃) In 57 76 114 66 88
Out 40 90 114 45 45
Pressure (kPa) In 3376 740 151 141 4300
Out 3350 145 151 125 4200
Flow Rate Mass (kg/h) 34028 551918 588052 57137 588052
Volumetric (m3/h) 5817 523 601 28959 588
Ave. Density (kg/m3) 6 1056 978 2 1001
Ave. Heat Capacity
(kJ/kg/K) 6.19 3.71 4.22 0.98 4.08
Ave. Viscosity (mPa.s) 1.24E-08 1.31E-06 6.21E-07 1.67E-08 9.50E-07
Enthalpy (kJ/kg) In -3677 -10837 -10578 -9285 -10682
Out -3811 -10718 -12841 -9434 -10853
Stream Number CWS1 83 CWS2

Lean Amine from


Name Cooling Water LP Steam Cooling Water Air
LP Flash Stripper

Process Orientation Tube-Side Hot Side Tube-Side Tube-Side Cold Side


Phase Liquid Liquid Vapour In, Liquid Out Liquid Vapour
Residence Time (s)
Temperature (℃) In 24 114 156 24 17
Out 40 87 143 40 22
Pressure (kPa) In 601 151 400 601 101
Out 549 140 581 101
Flow Rate Mass (kg/h) 68285 588052 52455 127213 6125
Volumetric (m3/h) 68.50 601 127.61 5000.00
3
Ave. Density (kg/m ) 997 978 997
Ave. Heat Capacity
(kJ/kg/K) 4.18 4.22 3.26 4.18 1.00
Ave. Viscosity (mPa.s) 9.34E-01 6.21E-07 9.34E-01
Enthalpy (kJ/kg) In -15858 -10578 -15858
Out -15791 -10689 -15791
Heat-Transfer Coefficient
(J/m2s*K) 489 1532 965 267 795
Efficiency (%)
Heating Duty (kJ/s) 349 18149 31600 2362 27838
LMTD (℃) 9.46 9.94 23.54 42.31
MTD (℃) 109
FT 0.85 1.00 1.00 1.00 0.96
Δtm 8.04 9.94 108.71 23.54 40.62
Utilities
Electricity (kW) 235.8
Cooling Water (m3/h) 68.50 127.61
Equipment Size
Length or height, L (m) 8.049
Width or diameter, D (m)
Surface Area, A (m2) 85.8 1190.0 1150.0 381.7
Volume, V (m3)
Design Pressure (kPa) 3801 801
Shaft Power, ws (kW)
Physical Orientation
Material of Construction SS 304L/SS 316L SS 316L CS/SS 316L SS 316L CS

Other Specifications

H-1
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Equipment Identification Vessels


Number C-81 C-83 C-87
HP Flash Drum Reflux Vessel Absorber Overhead K.O. Drum
Name

Stream Number 74 75 36 37 27 28
CO2 to CO2
Rich Amine to HP Flash Gas from HP CO2 to Reflux SG from CO2 SG from CO2
Name Product
Amine Flash Drum Amine Flash Drum Vessel Absorber OH Cooler Recovery Unit
Compressor
Process Orientation
Phase Mixed Vapour Mixed Vapour Mixed Vapour
Residence Time (s)
Temperature (℃) In 75 45 40
Out 75 44 40
Pressure (kPa) In 875 125 3350
Out 875 120 3350
Flow Rate Mass (kg/h) 643079 410 57137 54067 34028 33651
3
Volumetric (m /h) 646 52 27026 28115 5538 5537
3
Ave. Density (kg/m ) 995 8 2 2 6 6
Ave. Heat Capacity
(kJ/kg/K)
Ave. Viscosity (mPa.s) 1.73E-08 1.59E-08 1.19E-08
Enthalpy (kJ/kg) In
Out
Stream Number 76 93 87
Process
Rich Amine from Process Cond. From
Condensate to
Name HP Amine Flash Absorber OH K.O.
Stripper Reflux
Drum Drum
Pump
Process Orientation
Phase Liquid Liquid Liquid
Residence Time (s)
Temperature (℃) In
Out 75 44 40
Pressure (kPa) In
Out 875 120 3350
Flow Rate Mass (kg/h) 642668 3070 378
3
Volumetric (m /h) 594 3 0
3
Ave. Density (kg/m ) 1081 990 991
Ave. Heat Capacity
(kJ/kg/K)
Ave. Viscosity (mPa.s) 1.53E-06 6.18E-07 6.72E-07
Enthalpy (kJ/kg) In
Out
Heat-Transfer Coefficient
(J/m2s*K)
Efficiency (%)
Heating Duty (kJ/s)
LMTD (℃)
MTD (℃)
FT
Δtm
Utilities
Electricity (kW)
Cooling Water (m3/h)
Equipment Size
Length or height, L (m) 19.8 3.9 3.7
Width or diameter, D (m) 2.2 2.2 1.4
Surface Area, A (m2)
Volume, V (m3) 75.4 14.8 5.7
Design Pressure (kPa)
Shaft Power, ws (kW)
Physical Orientation Vertical Vertical Vertical
Material of Construction CS/ SS 316L SS 304L CS

Other Specifications

H-2
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Equipment Identification Columns


Number C-80 C-82
CO2 Absorber LP Flash Stripper
Name

Stream Number 25 72 86 77 82 95
Lean Amine from Process
SG to CO2 Steam Condensate Rich Amine to LP Semilean Amine to
Name Lean Amine Air Condensate to LP
Absorber to CO2 Absorber Flash Stripper LP Flash Stripper
Cooler Flash Stripper
Process Orientation
Phase Vapour Liquid Liquid Mixed Mixed Liquid
Residence Time (s)
Temperature (℃) In 40 45 45 65 90 45
Out
Pressure (kPa) In 3426 3376 4200 143 145 141
Out
Flow Rate Mass (kg/h) 86377 2198 588154 642631 551918 2558
Volumetric (m3/h) 6281 2 572 8695 14766 3
Ave. Density (kg/m3) 14 990 1029 74 37 990
Ave. Heat Capacity
(kJ/kg/K)
Ave. Viscosity (mPa.s) 1.44E-08 6.16E-07 2.46E-06 6.15E-07
Enthalpy (kJ/kg) In
Out
Stream Number 26 73 78 83 35
Semilean Amine
SG from CO2 Rich Amine from Lean Amine from CO2 from LP
Name from LP Flash
Absorber CO2 Absorber LP Flash Stripper Flash Stripper
Stripper
Process Orientation
Phase Vapour Liquid Liquid Liquid Vapour
Residence Time (s)
Temperature (℃) In
Out 57 74 76 114 66
Pressure (kPa) In
Out 3376 3435 222 151 141
Flow Rate Mass (kg/h) 34028 642701 551918 588052 57137
Volumetric (m3/h) 5817 594 523 601 28959
3
Ave. Density (kg/m ) 6 1082 1056 978 2
Ave. Heat Capacity
(kJ/kg/K)
Ave. Viscosity (mPa.s) 1.24E-08 1.55E-06 1.31E-06 6.21E-07 1.67E-08
Enthalpy (kJ/kg) In
Out
Heat-Transfer Coefficient
(J/m2s*K)
Efficiency (%)
Heating Duty (kJ/s)
LMTD (℃)
MTD (℃)
FT
Δtm
Utilities
Electricity (kW)
Cooling Water (m3/h)
Equipment Size
Length or height, L (m) 23.5 39.1
Width or diameter, D (m) 3.1 3.8
Surface Area, A (m2)
Volume, V (m3) 177 443
Design Pressure (kPa)
Shaft Power, ws (kW)
Physical Orientation Vertical Vertical
Material of Construction CS CS/SS 316L
Vertical tower with Montz-Thormann trays and IMTP #40 Vertical tower with Montz-Thormann trays and IMTP #50
Other Specifications
packing packing

H-3
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Equipment Identification Pumps Compressors


Number G-81 G-82 G-83 K-100 K-101 K-102
Semilean Amine Lean Amine Pump Stripper Reflux CO2 Product CO2 Product CO2 Product
Name
Pump Pump Compressor 1 Compressor 2 Compressor 3
Stream Number 78 84 93 37 37D 37H
Process CO2 to CO2 CO2 to CO2
Semilean Amine CO2 to CO2
Lean Amine to HP Condensate to Product Product
Name from LP Flash Product Compressor
Lean Amine Pump Stripper Reflux Compressor Stage Compressor Stage
Stripper Stage 1
Pump 2 3
Process Orientation
Phase Liquid Liquid Liquid Vapour Vapour Vapour
Residence Time (s)
Temperature (℃) In 76 87 44 44 43 43
Out 76 88 45 150 150 150
Pressure (kPa) In 222 140 120 120 359 1094
Out 740 4300 600 359 1094 3291
Flow Rate Mass (kg/h) 551918 588052 3070 54067 52785 52433
3
Volumetric (m /h) 523 588 3 28115 8761 2726
Ave. Density (kg/m3) 1056 1000 990 2 6 19
Ave. Heat Capacity
(kJ/kg/K)
Ave. Viscosity (mPa.s) 1.31E-06 9.56E-07 6.18E-07 1.59E-08 1.60E-08 1.62E-08
Enthalpy (kJ/kg) In
Out
Stream Number

Name

Process Orientation
Phase
Residence Time (s)
Temperature (℃) In
Out
Pressure (kPa) In
Out
Flow Rate Mass (kg/h)
Volumetric (m3/h)
3
Ave. Density (kg/m )
Ave. Heat Capacity
(kJ/kg/K)
Ave. Viscosity (mPa.s)
Enthalpy (kJ/kg) In
Out
Heat-Transfer Coefficient
(J/m2s*K)
Efficiency (%) 67.5 59.4 36.0 80 80 80
Heating Duty (kJ/s)
LMTD (℃)
MTD (℃)
FT
Δtm
Utilities
Electricity (kW)
Cooling Water (m3/h)
Equipment Size
Length or height, L (m)
Width or diameter, D (m)
Surface Area, A (m2)
Volume, V (m3)
Design Pressure (kPa)
Shaft Power, ws (kW) 111.5 1143.4 1.1 1487.8 1414.6 1324.6
Physical Orientation
Material of Construction SS 316L SS 316L SS 304L SS 316L SS 316L SS 316L

Other Specifications

H-4
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

2. Detailed Equipment List – 112 % Case


Equipment Identification Heat Exchangers
Number E-80 E-81A/B/C E-82 E-83 E-84
CO2 Absorber Lean/Rich Amine Stripper Reboiler Stripper Overhead Lean Amine Air
Name
Overhead Cooler Exchanger Condenser Cooler
Stream Number 26 81 83 35 85
Semilean Amine to Lean Amine from
SG from CO2 Lean Amine from LP CO2 from LP
Name L/R Amine HP Lean Amine
Absorber Flash Stripper Flash Stripper
Exchanger Pump
Process Orientation Shell-Side Cold Side Shell-Side Shell-Side Hot Side
Phase Vapour Liquid Liquid In, Vapour Out Vapour Liquid
Residence Time (s)
Temperature (℃) In 55 77 114 65 84
Out 40 90 114 44 41
Pressure (kPa) In 3376 740 151 141 4300
Out 3350 145 151 125 4200
Flow Rate Mass (kg/h) 39801 620865 597825 61171 597825
3
Volumetric (m /h) 6470 586 611 30704 595
3
Ave. Density (kg/m ) 6 1060 979 2 1004
Ave. Heat Capacity
(kJ/kg/K) 5.93 3.70 4.23 0.97 4.06
Ave. Viscosity (mPa.s) 1.25E-08 1.37E-06 6.39E-07 1.67E-08 1.06E-06
Enthalpy (kJ/kg) In -3934 -10731 -10447 -9265 -10568
Out -4049 -10608 -12838 -9404 -10736
Stream Number CWS1 83 CWS2

Lean Amine from


Name Cooling Water LP Steam Cooling Water Air
LP Flash Stripper

Process Orientation Tube-Side Hot Side Tube-Side Tube-Side Cold Side


Phase Liquid Liquid Vapour In, Liquid Out Liquid Vapour
Residence Time (s)
Temperature (℃) In 24 114 156 24 17
Out 38 83 143 39 22
Pressure (kPa) In 601 151 400 601 101
Out 549 140 581 101
Flow Rate Mass (kg/h) 79285 597825 52455 138048 6125
3
Volumetric (m /h) 79.53 611 138.48 5000.00
3
Ave. Density (kg/m ) 997 979 997
Ave. Heat Capacity
(kJ/kg/K) 4.18 4.23 3.26 4.18 1.00
Ave. Viscosity (mPa.s) 9.34E-01 6.39E-07 9.34E-01
Enthalpy (kJ/kg) In -15858 -10447 -15858
Out -15801 -10575 -15797
Heat-Transfer Coefficient
2
(J/m s*K) 489 1532 965 267 795
Efficiency (%)
Heating Duty (kJ/s) 332 21225 31600 2361 27838
LMTD (℃) 8.87 11.38 23.23 40.48
MTD (℃) 110
FT 0.85 1.00 287751.69 1.00 0.96
Δtm 7.54 11.38 31600000.00 23.23 38.86
Utilities
Electricity (kW) 518.8
3
Cooling Water (m /h) 79.53 138.48
Equipment Size
Length or height, L (m) 8.049

Width or diameter, D (m)


2
Surface Area, A (m ) 85.8 1190.0 1150.0 381.7
3
Volume, V (m )
Design Pressure (kPa) 3801 801
Shaft Power, ws (kW)
Physical Orientation
Material of Construction SS 304L/SS 316L SS 316L CS/SS 316L SS 316L CS

Other Specifications

H-5
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Equipment Identification Vessels


Number C-81 C-83 C-87
HP Flash Drum Reflux Vessel Absorber Overhead K.O. Drum
Name

Stream Number 74 75 36 37 27 28
CO2 to CO2
Rich Amine to HP Flash Gas from HP CO2 to Reflux SG from CO2 SG from CO2
Name Product
Amine Flash Drum Amine Flash Drum Vessel Absorber OH Cooler Recovery Unit
Compressor
Process Orientation
Phase Mixed Vapour Mixed Vapour Mixed Vapour
Residence Time (s)
Temperature (℃) In 73 44 40
Out 73 44 40
Pressure (kPa) In 875 125 3350
Out 875 120 3350
Flow Rate Mass (kg/h) 656751 421 61171 58124 39801 39437
Volumetric (m3/h) 655 52 28947 30113 6195 6194
Ave. Density (kg/m3) 1002 8 2 2 6 6
Ave. Heat Capacity
(kJ/kg/K)
Ave. Viscosity (mPa.s) 1.72E-08 1.59E-08 1.20E-08
Enthalpy (kJ/kg) In
Out
Stream Number 76 93 87
Process
Rich Amine from Process Cond. From
Condensate to
Name HP Amine Flash Absorber OH K.O.
Stripper Reflux
Drum Drum
Pump
Process Orientation
Phase Liquid Liquid Liquid
Residence Time (s)
Temperature (℃) In
Out 73 44 40
Pressure (kPa) In
Out 875 120 3350
Flow Rate Mass (kg/h) 656331 3047 364
Volumetric (m3/h) 603 3 0
Ave. Density (kg/m3) 1089 990 992
Ave. Heat Capacity
(kJ/kg/K)
Ave. Viscosity (mPa.s) 1.71E-06 6.25E-07 6.74E-07
Enthalpy (kJ/kg) In
Out
Heat-Transfer Coefficient
(J/m2s*K)
Efficiency (%)
Heating Duty (kJ/s)
LMTD (℃)
MTD (℃)
FT
Δtm
Utilities
Electricity (kW)
Cooling Water (m3/h)
Equipment Size
Length or height, L (m) 19.8 3.9 3.7

Width or diameter, D (m) 2.2 2.2 1.4


Surface Area, A (m2)
3
Volume, V (m ) 75.4 14.8 5.7
Design Pressure (kPa)
Shaft Power, ws (kW)
Physical Orientation Vertical Vertical Vertical
Material of Construction CS/ SS 316L SS 304L CS

Other Specifications

H-6
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Equipment Identification Columns


Number C-80 C-82
CO2 Absorber LP Flash Stripper
Name

Stream Number 25 72 86 77 82 95
Lean Amine from Process
SG to CO2 Steam Condensate Rich Amine to LP Semilean Amine to
Name Lean Amine Air Condensate to LP
Absorber to CO2 Absorber Flash Stripper LP Flash Stripper
Cooler Flash Stripper
Process Orientation
Phase Vapour Liquid Liquid Mixed Mixed Liquid
Residence Time (s)
Temperature (℃) In 40 45 41 63 90 44
Out
Pressure (kPa) In 3426 3376 4200 143 145 141
Out
Flow Rate Mass (kg/h) 96164 2198 597827 656330 620865 2666
Volumetric (m3/h) 6993 2 580 8868 17948 3
Ave. Density (kg/m3) 14 990 1031 74 35 990
Ave. Heat Capacity
(kJ/kg/K)
Ave. Viscosity (mPa.s) 1.44E-08 6.16E-07 2.85E-06 6.22E-07
Enthalpy (kJ/kg) In
Out
Stream Number 26 73 78 83 35
Semilean Amine
SG from CO2 Rich Amine from Lean Amine from CO2 from LP
Name from LP Flash
Absorber CO2 Absorber LP Flash Stripper Flash Stripper
Stripper
Process Orientation
Phase Vapour Liquid Liquid Liquid Vapour
Residence Time (s)
Temperature (℃) In
Out 55 73 76 114 65
Pressure (kPa) In
Out 3376 3450 241 151 141
Flow Rate Mass (kg/h) 39801 656387 620865 597825 61171
Volumetric (m3/h) 6470 603 586 611 30704
Ave. Density (kg/m3) 6 1089 1060 979 2
Ave. Heat Capacity
(kJ/kg/K)
Ave. Viscosity (mPa.s) 1.25E-08 1.73E-06 1.37E-06 6.39E-07 1.67E-08
Enthalpy (kJ/kg) In
Out
Heat-Transfer Coefficient
(J/m2s*K)
Efficiency (%)
Heating Duty (kJ/s)
LMTD (℃)
MTD (℃)
FT
Δtm
Utilities
Electricity (kW)
Cooling Water (m3/h)
Equipment Size
Length or height, L (m) 23.5 39.1

Width or diameter, D (m) 3.1 3.8


Surface Area, A (m2)
Volume, V (m3) 177 443
Design Pressure (kPa)
Shaft Power, ws (kW)
Physical Orientation Vertical Vertical
Material of Construction CS CS/SS 316L
Vertical tower with Montz-Thormann trays and IMTP #40 Vertical tower with Montz-Thormann trays and IMTP #50
Other Specifications
packing packing

H-7
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Equipment Identification Pumps Compressors


Number G-81 G-82 G-83 K-100 K-101 K-102
Semilean Amine Lean Amine Pump Stripper Reflux CO2 Product CO2 Product CO2 Product
Name
Pump Pump Compressor 1 Compressor 2 Compressor 3
Stream Number 78 84 93 37 37D 37H
Process CO2 to CO2 CO2 to CO2
Semilean Amine CO2 to CO2
Lean Amine to HP Condensate to Product Product
Name from LP Flash Product Compressor
Lean Amine Pump Stripper Reflux Compressor Stage Compressor Stage
Stripper Stage 1
Pump 2 3
Process Orientation
Phase Liquid Liquid Liquid Vapour Vapour Vapour
Residence Time (s)
Temperature (℃) In 76 83 44 44 43 43
Out 77 84 44 150 150 150
Pressure (kPa) In 241 140 120 120 361 1101
Out 740 4300 600 361 1101 3291
Flow Rate Mass (kg/h) 620865 597825 3047 58124 56811 56433
3
Volumetric (m /h) 586 595 3 30113 9357 2915
Ave. Density (kg/m3) 1060 1004 990 2 6 19
Ave. Heat Capacity
(kJ/kg/K)
Ave. Viscosity (mPa.s) 1.37E-06 1.07E-06 6.25E-07 1.59E-08 1.60E-08 1.62E-08
Enthalpy (kJ/kg) In
Out
Stream Number

Name

Process Orientation
Phase
Residence Time (s)
Temperature (℃) In
Out
Pressure (kPa) In
Out
Flow Rate Mass (kg/h)
3
Volumetric (m /h)
Ave. Density (kg/m3)
Ave. Heat Capacity
(kJ/kg/K)
Ave. Viscosity (mPa.s)
Enthalpy (kJ/kg) In
Out
Heat-Transfer Coefficient
(J/m2s*K)
Efficiency (%) 67.5 59.4 36.0 80 80 80
Heating Duty (kJ/s)
LMTD (℃)
MTD (℃)
FT
Δtm
Utilities
Electricity (kW)
Cooling Water (m3/h)
Equipment Size
Length or height, L (m)

Width or diameter, D (m)


Surface Area, A (m2)
Volume, V (m3)
Design Pressure (kPa)
Shaft Power, ws (kW) 120.4 1158.1 1.1 1606.5 1520.8 1415.8
Physical Orientation
Material of Construction SS 316L SS 316L SS 304L SS 316L SS 316L SS 316L

Other Specifications

H-8
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

3. Detailed Equipment List – 125 % Case


Equipment Identification Heat Exchangers
Number E-80 E-81A/B/C E-82 E-83 E-84 E-85
CO2 Absorber Lean/Rich Amine Stripper Reboiler Stripper Overhead Lean Amine Air Lean Amine
Name
Overhead Cooler Exchanger Condenser Cooler Cooler
Stream Number 26 81 83 35 85 86C
Semilean Amine to Lean Amine from Lean Amine to
SG from CO2 Lean Amine from LP CO2 from LP
Name L/R Amine HP Lean Amine Lean Amine
Absorber Flash Stripper Flash Stripper
Exchanger Pump Cooler
Process Orientation Shell-Side Cold Side Shell-Side Shell-Side Hot Side Shell-Side
Phase Vapour Liquid Liquid In, Vapour Out Vapour Liquid Liquid
Residence Time (s)
Temperature (℃) In 51 73 114 62 77 40
Out 39 90 114.4557111 41.5 40 34.7
Pressure (kPa) In 3376 740 156 141 4300 4200
Out 3350 146 156 125 4200 4200
Flow Rate Mass (kg/h) 44572 648133 615311 67708 615311 615168
3
Volumetric (m /h) 7171 606 629 33043 609 595
3
Ave. Density (kg/m ) 6 1070 979 2 1010 1033
Ave. Heat Capacity
(kJ/kg/K) 5.94 3.64 4.23 0.96 4.02 3.84
Ave. Viscosity (mPa.s) 1.24E-08 1.58E-06 6.50E-07 1.66E-08 1.26E-06 3.11E-06
Enthalpy (kJ/kg) In -3931 -10639 -10339 -9209 -10490 -10638
Out -4021 -10489 -12733 -9326 -10636 -10658
Stream Number CWS1 83 CWS2 CWS3

Lean Amine from


Name Cooling Water LP Steam Cooling Water Air Cooling Water
LP Flash Stripper

Process Orientation Tube-Side Hot Side Tube-Side Tube-Side Cold Side Tube-Side
Phase Liquid Liquid Vapour In, Liquid Out Liquid Vapour Liquid
Residence Time (s)
Temperature (℃) In 24 114 156 24 17 24
Out 40 76 143 35.5 21.01806247 38
Pressure (kPa) In 601 156 400 601 101 601
Out 549 140 581 101 581
Flow Rate Mass (kg/h) 59639 615311 52455 164042 6189 160634
3
Volumetric (m /h) 59.82 629 164.55 5052.63 161.13
3
Ave. Density (kg/m ) 997 979 997 997
Ave. Heat Capacity
(kJ/kg/K) 4.18 4.23 3.26 4.18 1.00 4.18
Ave. Viscosity (mPa.s) 9.34E-01 6.50E-07 9.34E-01 9.34E-01
Enthalpy (kJ/kg) In -15858 -10339 -15858 -15858
Out -15791 -10497 -15810 -15800
Heat-Transfer Coefficient
2
(J/m s*K) 489 1532 965 267 879 594
Efficiency (%)
Heating Duty (kJ/s) 189 27059 31600 2190 24870 3467
LMTD (℃) 5.46 9.97 21.48 37.09 7.49
MTD (℃) 108.71
FT 0.95 1 1 1 0.96 0.955
Δtm 5.19 9.97 108.71 21.48 35.60 7.15
Utilities
Electricity (kW) 518.8
3
Cooling Water (m /h) 59.82 164.55 161.13
Equipment Size
Length or height, L (m)

Width or diameter, D (m)


2
Surface Area, A (m ) 85.8 1785.0 1150.0 382.1 813.0
3
Volume, V (m )
Design Pressure (kPa) 3801 801
Shaft Power, ws (kW)
Physical Orientation
Material of Construction SS 304L/SS 316L SS 316L CS/SS 316L SS 316L CS CS/SS 316L
Other Specifications

H-9
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Equipment Identification Vessels


Number C-81 C-83 C-87
HP Flash Drum Reflux Vessel Absorber Overhead K.O. Drum
Name

Stream Number 74 75 36 37 27 28
CO2 to CO2
Rich Amine to HP Flash Gas from HP CO2 to Reflux SG from CO2 SG from CO2
Name Product
Amine Flash Drum Amine Flash Drum Vessel Absorber OH Cooler Recovery Unit
Compressor
Process Orientation
Phase Mixed Vapour Mixed Vapour Mixed Vapour
Residence Time (s)
Temperature (℃) In 69 42 39
Out 69 41 39
Pressure (kPa) In 875 125 3350
Out 875 120 3350
Flow Rate Mass (kg/h) 681200 457 67708 64953 44572 44279
3
Volumetric (m /h) 674 55 31848 33131 6938 6938
Ave. Density (kg/m3) 1010 8 2 2 6 6
Ave. Heat Capacity
(kJ/kg/K)
Ave. Viscosity (mPa.s) 1.71E-08 1.58E-08 1.20E-08
Enthalpy (kJ/kg) In
Out
Stream Number 76 93 87
Process
Rich Amine from Process Cond. From
Condensate to
Name HP Amine Flash Absorber OH K.O.
Stripper Reflux
Drum Drum
Pump
Process Orientation
Phase Liquid Liquid Liquid
Residence Time (s)
Temperature (℃) In
Out 69 41 39
Pressure (kPa) In
Out 875 120 3350
Flow Rate Mass (kg/h) 680743 2755 293
Volumetric (m3/h) 620 3 0
Ave. Density (kg/m3) 1099 991 992
Ave. Heat Capacity
(kJ/kg/K)
Ave. Viscosity (mPa.s) 1.99E-06 6.59E-07 6.84E-07
Enthalpy (kJ/kg) In
Out
Heat-Transfer Coefficient
(J/m2s*K)
Efficiency (%)
Heating Duty (kJ/s)
LMTD (℃)
MTD (℃)
FT
Δtm
Utilities
Electricity (kW)
Cooling Water (m3/h)
Equipment Size
Length or height, L (m) 19.8 7.5 4.8

Width or diameter, D (m) 2.2 2.5 1.6


Surface Area, A (m2)
3
Volume, V (m ) 75.4 36.8 9.7
Design Pressure (kPa)
Shaft Power, ws (kW)
Physical Orientation Vertical Vertical Vertical
Material of Construction CS/ SS 316L SS 304L CS
Other Specifications

H-10
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Equipment Identification Columns


Number C-80 C-82
CO2 Absorber LP Flash Stripper
Name

Stream Number 25 72 86 77 82 95
Lean Amine from Process
SG to CO2 Steam Condensate Rich Amine to LP Semilean Amine to
Name Lean Amine Air Condensate to LP
Absorber to CO2 Absorber Flash Stripper LP Flash Stripper
Cooler Flash Stripper
Process Orientation
Phase Vapour Liquid Liquid Mixed Mixed Liquid
Residence Time (s)
Temperature (℃) In 40 45 35 60 90 41
Out
Pressure (kPa) In 3426 3376 4200 143 146 141
Out
Flow Rate Mass (kg/h) 107969 2342 615168 680927 648133 2092
Volumetric (m3/h) 7851 2 594 9029 22348 2
3
Ave. Density (kg/m ) 14 990 1036 75 29 991
Ave. Heat Capacity
(kJ/kg/K)
Ave. Viscosity (mPa.s) 1.44E-08 6.16E-07 3.64E-06 6.56E-07
Enthalpy (kJ/kg) In
Out
Stream Number 26 73 78 83 35
Semilean Amine
SG from CO2 Rich Amine from Lean Amine from CO2 from LP
Name from LP Flash
Absorber CO2 Absorber LP Flash Stripper Flash Stripper
Stripper
Process Orientation
Phase Vapour Liquid Liquid Liquid Vapour
Residence Time (s)
Temperature (℃) In
Out 51 69 73 114 62
Pressure (kPa) In
Out 3376 3465 246 156 141
Flow Rate Mass (kg/h) 44572 680907 648133 615311 67708
3
Volumetric (m /h) 7171 619 606 629 33043
3
Ave. Density (kg/m ) 6 1099 1070 979 2
Ave. Heat Capacity
(kJ/kg/K)
Ave. Viscosity (mPa.s) 1.24E-08 2.02E-06 1.58E-06 6.50E-07 1.66E-08
Enthalpy (kJ/kg) In
Out
Heat-Transfer Coefficient
(J/m2s*K)
Efficiency (%)
Heating Duty (kJ/s)
LMTD (℃)
MTD (℃)
FT
Δtm
Utilities
Electricity (kW)
Cooling Water (m3/h)
Equipment Size
Length or height, L (m) 23.5 39.1

Width or diameter, D (m) 3.1 3.8


Surface Area, A (m2)
3
Volume, V (m ) 177 443
Design Pressure (kPa)
Shaft Power, ws (kW)
Physical Orientation Vertical Vertical
Material of Construction CS CS/SS 316L
Vertical tower with Montz-Thormann trays and IMTP #25 Vertical tower with Montz-Thormann trays and IMTP #40
Other Specifications
packing packing

H-11
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Equipment Identification Pumps Compressors


Number G-81 G-82 G-83 K-100 K-101 K-102
Semilean Amine Lean Amine Pump Stripper Reflux CO2 Product CO2 Product CO2 Product
Name
Pump Pump Compressor 1 Compressor 2 Compressor 3
Stream Number 78 84 93 37 37D 37H
Process CO2 to CO2 CO2 to CO2
Semilean Amine CO2 to CO2
Lean Amine to HP Condensate to Product Product
Name from LP Flash Product Compressor
Lean Amine Pump Stripper Reflux Compressor Stage Compressor Stage
Stripper Stage 1
Pump 2 3
Process Orientation
Phase Liquid Liquid Liquid Vapour Vapour Vapour
Residence Time (s)
Temperature (℃) In 73 76 41 41 43 43
Out 73 77 41 150 150 147
Pressure (kPa) In 246 140 120 120 374 1134
Out 740 4300 600 374 1134 3291
Flow Rate Mass (kg/h) 648133 615311 2755 64953 63783 63365
Volumetric (m3/h) 606 609 3 33131 10158 3177
Ave. Density (kg/m3) 1070 1010 991 2 6 20
Ave. Heat Capacity
(kJ/kg/K)
Ave. Viscosity (mPa.s) 1.58E-06 1.27E-06 6.59E-07 1.58E-08 1.60E-08 1.62E-08
Enthalpy (kJ/kg) In
Out
Stream Number

Name

Process Orientation
Phase
Residence Time (s)
Temperature (℃) In
Out
Pressure (kPa) In
Out
Flow Rate Mass (kg/h)
3
Volumetric (m /h)
Ave. Density (kg/m3)
Ave. Heat Capacity
(kJ/kg/K)
Ave. Viscosity (mPa.s)
Enthalpy (kJ/kg) In
Out
Heat-Transfer Coefficient
(J/m2s*K)
Efficiency (%) 67.5 59.4 36.0 80 80 80
Heating Duty (kJ/s)
LMTD (℃)
MTD (℃)
FT
Δtm
Utilities
Electricity (kW)
Cooling Water (m3/h)
Equipment Size
Length or height, L (m)

Width or diameter, D (m)


Surface Area, A (m2)
3
Volume, V (m )
Design Pressure (kPa)
Shaft Power, ws (kW) 123.2 1184.8 1.0 1831.0 1699.6 1540.6
Physical Orientation
Material of Construction SS 316L SS 316L SS 304L SS 316L SS 316L SS 316L
Other Specifications

H-12
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

4. Heat Exchanger Sizing


4.1. Operating Data Provided
49-E-80: CO2 Absorber Overhead Cooler
Type BEM
Orientation Horizontal
Nominal diameter per shell (mm) 800
Nominal length (straight tube length, mm) 3000
Gross exchange surface per unit (m2) 85.8
Exchanged heat 425 kW
Shell side Tube side
Medium Syngas Cooling water
Operating temperature (in/out, °C) 45/40 24/40
Operating pressure (in, kPag) 3275 500
Total mass flow (kg/h) 43246 22871
Liquid total (in/out, kg/h) 0/106 22871/22871
Vapor/gas total (in/out, kg/h) 43246/43140 0/0
Pressure drop (allowable/calculation, bar) 0.20/0.15 1.00/0.52

E-81A/B: Lean/Rich Amine Exchanger


Type CP
Orientation Horizontal
Nominal width (mm) 1963
Nominal length (mm) 1963
Nominal height (mm) 2516
2
Actual exchange surface per unit (m ) 595
Total heat flow (MW) 22 (with 10% overdesign margin)
Hot Side Cold Side
Medium Lean amine Semilean amine
Operating temperature (in/out, °C) 114.0/83.4 73.4/103.4
Operating pressure (in, kPag) 50 640
Total mass flow (kg/h) 641770 692236
Liquid total (in/out, kg/h) 641770/641170 692236/692236
Vapor/gas total (in/out, kg/h) 0/0 0/0
Pressure drop (allowable/calculation, kPa) 30.0/29.90 35.0/33.20

E-83: Stripper Overhead Condenser


Type BJ21M
Orientation Horizontal
Nominal diameter per shell (mm) 1600
Nominal length (straight tube length) 5486

H-13
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Gross exchange surface per unit (m2) 381.72


Exchanged heat 2.70 MW (with 20% overdesign margin)
Shell Side Tube Side
Medium Carbon Dioxide Cooling water supply
Operating temperature (in/out, °C) 65.6/45 24/40
Operating pressure (in, kPag) 40 500
Total mass flow (kg/h) 66160 145303
Liquid total (in/out, kg/h) 0/3524 145303/145303
Vapor/gas total (in/out, kg/h) 66160.4/62637 0/0
Pressure drop (allowable/calculation, kPa) 10/3.1 40/20
Velocity (m/s) 8.17 0.75

E-84: Lean Amine Cooler


Orientation Horizontal
Type draft Forced
Tube length (mm) 8049
Heat exchanged per unit (MW) 27.6 (with 15% overdesign margin)
Medium Lean amine
Operating temperature (in/out, °C) 83.44/45
Operating pressure (in, kPag) 4280
Total mass flow (kg/h) 670941
Liquid total (in/out) 670941/670941
Gas total (in/out) 0/0
Pressure drop allowable (kPa) 120

4.2. Design Data Sheet Provided


E-82: Stripper Reboiler
Type BKU
Orientation Horizontal
Nominal diameter per shell (mm) 1600
Nominal length (straight tube length) 6096
Gross exchange surface per unit (m2) 1150
Exchanged heat 31.6 MW (with 10% overdesign margin)
Shell Side Tube Side
Medium Lean Solution LP Steam
Operating temperature (in/out, °C) 114/114 156/143
Operating pressure (in, kPag) 60 299
Total mass flow (kg/h) 693118 52455
Liquid total (in/out, kg/h) 693118/640038 0/52455
Vapor/gas total (in/out, kg/h) 0/53081 52455/0
Pressure drop (allowable/calculation, kPa) 0/0.95 0/11.27
Velocity (m/s) 15.23 14.88

H-14
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

4.3. Heat Exchanger Sizing Sample Calculations


The heat transfer equation is solved for the additional lean amine cooler, E-85. The cold

fluid is cooling water and the hot fluid is lean amine. Based on the inlet and outlet stream

temperatures tabulated below, R and S were calculated, and a correction factor FT was obtained to

be applied to LMTD. An overall heat transfer coefficient was obtained for the specific fluids

present in the heat exchanger. Using the heat exchanger duty from the simulation output, Q, the

total heat exchange surface, A, was obtained.

E-85 Lean Amine Exchanger


Cooling Water In, t1 K 297.15
Lean Amine In, T1 K 313.15
Cooling Water Out, t2 K 308.15
Lean Amine Out, T2 K 307.85
LMTD K 7.49
S - 0.69
R - 0.48
Correction Factor, FT - 0.96
Duty, Q W 3467278
2
Overall Heat Transfer Coefficient, U W/m /K 594.30
2
Area, A m 815.40

𝑄 = 𝑈𝐴 × 𝐿𝑀𝑇𝐷 × 𝐹𝑇

(𝑇1 − 𝑡2 ) − (𝑇2 − 𝑡1 ) (313.15 𝐾 − 308.15 𝐾) − (307.85 𝐾 − 297.15 𝐾)


𝐿𝑀𝑇𝐷 = = = 7.5 𝐾
(𝑇1 − 𝑡2 ) (313.15 𝐾 − 308.15 𝐾)
𝑙𝑛 𝑙𝑛
(𝑇2 − 𝑡1 ) (307.85 𝐾 − 297.15 𝐾)

𝑇1 − 𝑇2 313.15 𝐾 − 307.15 𝐾
𝑅= = = 0.48
𝑡2 − 𝑡1 308.15 𝐾 − 297.15 𝐾

𝑡2 − 𝑡1 308.15 𝐾 − 297.15 𝐾
𝑆= = = 0.69
𝑇1 − 𝑡1 313.15 𝐾 − 297.15 𝐾

H-15
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Using Kern (1950), the correction factor for a 2-4 shell and tube heat exchanger is 0.96.

Therefore, the total area of the heat exchanger is

𝑄 3467278 W
𝐴= = = 815.4 𝑚2
𝑈 × 𝐿𝑀𝑇𝐷 × 𝐹𝑇 594.3 𝑊 × 7.5 𝐾 × 0.96
𝑚2 𝐾

The procedure shown above was used for calculating the size of all heat exchangers present in

the design. Note that for the Lean Amine Air Cooler, the fan power required to facilitate the

required flow rate for the base case was taken as the benchmark. Additional power required for

the 112 % case and 125 % case were costed accounted for in the operating costs.

4.4. Base Case Sizes


E-80 CO2 Absorber Overhead Cooler
Tube Side Fluid In, t1 K 297.15
Shell Side Fluid In, T1 K 318.15
Tube Side Fluid Out, t2 K 313.15
Shell Side Fluid Out, T2 K 313.15
LMTD K 9.46
S - 0.76
R - 0.31
Correction Factor, FT - 0.85
Duty, Q W 349220
Overall Heat Transfer Coefficient, U W/m2/K 489.11
2
Area, A m 88.82

E-81 Lean/Rich Amine Exchanger


Tube Side Fluid In, t1 K 349.56
Shell Side Fluid In, T1 K 386.72
Tube Side Fluid Out, t2 K 377.25
Shell Side Fluid Out, T2 K 359.98
LMTD K 9.94
S - 0.75
R - 0.97
Correction Factor, FT - 0.95

H-16
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Duty, Q W 18148961
2
Overall Heat Transfer Coefficient, U W/m /K 1531.76
2
Area, A m 1191.57

E-82 Stripper Reboiler


Tube Side Fluid In, t1 K 313.15
Shell Side Fluid In, T1 K 313.15
Tube Side Fluid Out, t2 K 514.56
Shell Side Fluid Out, T2 K 297.15
Average Temperature Difference K 108.71
31600000
Duty, Q W
Overall Heat Transfer Coefficient, U W/m2/K 965.31
Area, A m2 301.14

E-83 Stripper Overhead Condenser


Tube Side Fluid In, t1 K 297.15
Shell Side Fluid In, T1 K 339.42
Tube Side Fluid Out, t2 K 313.15
Shell Side Fluid Out, T2 K 318.15
LMTD K 23.54
S - 0.38
R - 1.33
Correction Factor, FT - 1.00
Duty, Q W 2362061
Overall Heat Transfer Coefficient, U W/m2/K 266.77
Area, A m2 376.18

E-84 Lean Amine Air Cooler


Tube Side Fluid In, t1 K 290.15
Air Side Fluid In, T1 K 360.97
Tube Side Fluid Out, t2 K 300.15
Air Side Fluid Out, T2 K 318.15
LMTD K 42.31
S - 0.60
R - 0.23
Correction Factor, FT - 0.96
Duty, Q W 27838271
2
Overall Heat Transfer Coefficient, U W/m /K 794.96

H-17
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Area, A m2 862.15

4.5. 112 % Case Sizes


Since the 112 % capacity case is an optimization of the existing base case equipment through

modification of operating conditions, the size of the equipment remain the same with little

variation from the base case.

E-80 CO2 Absorber Overhead Cooler


Tube Side Fluid In, t1 K 297.15
Shell Side Fluid In, T1 K 317.41
Tube Side Fluid Out, t2 K 313.15
Shell Side Fluid Out, T2 K 313.15
LMTD K 8.87
S - 0.79
R - 0.27
Correction Factor, FT - 0.85
Duty, Q W 331900
2
Overall Heat Transfer Coefficient, U W/m /K 489.11
2
Area, A m 90.03

E-81 Lean/Rich Amine Exchanger


Tube Side Fluid In, t1 K 349.73
Shell Side Fluid In, T1 K 386.85
Tube Side Fluid Out, t2 K 368.15
Shell Side Fluid Out, T2 K 356.01
LMTD K 11.38
S - 0.50
R - 1.67
Correction Factor, FT - 1
Duty, Q W 21224849
Overall Heat Transfer Coefficient, U W/m2/K 1531.73
Area, A m2 1217.59

E-82 Stripper Reboiler


Tube Side Fluid In, t1 K 313.15
Shell Side Fluid In, T1 K 310.93

H-18
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Tube Side Fluid Out, t2 K 514.56


Shell Side Fluid Out, T2 K 297.15
Average Temperature Difference K 109.82
31600000
Duty, Q W
Overall Heat Transfer Coefficient, U W/m2/K 965.31
Area, A m2 298.09

E-83 Stripper Overhead Condenser


Tube Side Fluid In, t1 K 297.15
Shell Side Fluid In, T1 K 338.26
Tube Side Fluid Out, t2 K 311.89
Shell Side Fluid Out, T2 K 317.51
LMTD K 23.23
S - 0.36
R - 1.41
Correction Factor, FT - 1.00
Duty, Q W 2361493
Overall Heat Transfer Coefficient, U W/m2/K 266.77
Area, A m2 380.99

E-84 Lean Amine Air Cooler


Tube Side Fluid In, t1 K 290.15
Shell Side Fluid In, T1 K 356.99
Tube Side Fluid Out, t2 K 294.69
Shell Side Fluid Out, T2 K 314.62
LMTD K 40.48
S - 0.63
R - 0.11
Correction Factor, FT - 0.96
Duty, Q W 27838271
2
Overall Heat Transfer Coefficient, U W/m /K 794.96
2
Area, A m 901.18

4.6. 125 % Case Sizes


E-80 CO2 Absorber Overhead Cooler
Tube Side Fluid In, t1 K 297.15
Shell Side Fluid In, T1 K 314.35

H-19
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Tube Side Fluid Out, t2 K 313.15


Shell Side Fluid Out, T2 K 312.15
LMTD K 5.46
S - 0.93
R - 0.14
Correction Factor, FT - 0.95
Duty, Q W 188750
Overall Heat Transfer Coefficient, U W/m2/K 489.11
Area, A m2 74.39

E-81 Lean/Rich Amine Exchanger


Tube Side Fluid In, t1 K 346.19
Shell Side Fluid In, T1 K 387.61
Tube Side Fluid Out, t2 K 364.15
Shell Side Fluid Out, T2 K 349.21
LMTD K 9.97
S - 0.93
R - 0.47
Correction Factor, FT - 1
Duty, Q W 27044854
2
Overall Heat Transfer Coefficient, U W/m /K 1531.76
2
Area, A m 1772.16

E-82 Stripper Reboiler


Tube Side Fluid In, t1 K 313.15
Shell Side Fluid In, T1 K 313.15
Tube Side Fluid Out, t2 K 514.56
Shell Side Fluid Out, T2 K 297.15
Average Temperature Difference K 108.71
31600000
Duty, Q W
Overall Heat Transfer Coefficient, U W/m2/K 965.31
Area, A m2 301.14

E-83 Stripper Overhead Condenser


Tube Side Fluid In, t1 K 297.15
Shell Side Fluid In, T1 K 334.67
Tube Side Fluid Out, t2 K 308.65
Shell Side Fluid Out, T2 K 314.65

H-20
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

LMTD K 21.48
S - 0.53
R - 0.57
Correction Factor, FT - 1.00
Duty, Q W 2189579
Overall Heat Transfer Coefficient, U W/m2/K 266.77
Area, A m2 382.14

E-84 Lean Amine Air Cooler


Tube Side Fluid In, t1 K 290.15
Shell Side Fluid In, T1 K 350.18
Tube Side Fluid Out, t2 K 294.17
Shell Side Fluid Out, T2 K 313.15
LMTD K 37.09
S - 0.62
R - 0.11
Correction Factor, FT - 0.96
Duty, Q W 24869695
2
Overall Heat Transfer Coefficient, U W/m /K 794.96
2
Area, A m 878.65

E-85 Lean Amine Exchanger


Cooling Water In, t1 K 297.15
Lean Amine In, T1 K 313.15
Cooling Water Out, t2 K 308.15
Lean Amine Out, T2 K 307.85
LMTD K 7.49
S - 0.69
R - 0.48
Correction Factor, FT - 0.955
Duty, Q W 3467278
2
Overall Heat Transfer Coefficient, U W/m /K 594.30
2
Area, A m 815.41

5. Vessel Sizing

H-21
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

5.1. Operating Data Provided


C-81: HP Amine Flash Drum
Orientation Vertical
3
Volume (m ) 75
Inner Diameter (mm) 2200
Length (mm) 19840
Medium Rich Amine/Flash Gas
Operating Temperature (max °C) 75
Operating Pressure (max kPag) 600
Material CS/SS 316L

C-83: Reflux Vessel


Orientation Vertical
Volume (m3) 14.8
Inner Diameter (mm) 2200
Length (mm) 3890
Medium CO2 Gas/Process Condensate
Operating Temperature (max °C) 45
Operating Pressure (max kPag) 20
Material SS 304L

C-87: Absorber Overhead K.O Drum


Orientation Vertical
3
Volume (m ) 55.4
Inner Diameter (mm) 1400
Length (mm) 3690
Medium Synthesis Gas/Process Condensate
Operating Temperature (max °C) 40
Operating Pressure (max kPag) 3250
Material CS
3
Note: The volume was corrected to 5.68 m based on the diameter and length given.

5.2. Separator Sizing Sample Calculations


For the separators mentioned above, the terminal velocity and the resulting minimum diameter

and length of the vessel are calculated using two sizing guidelines:

i) Gravity Settling Theory approach outlined in GPSA (2014)

ii) Souders-Brown approach presented by PetroSkills (2015)

H-22
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

The most conservative dimensions resulting from these methods were taken as the separator size.

The following parameters have been defined for the Absorber Overhead Knockout Drum C-87:

C-87 Absorber Overhead Knockout Drum


Temperature, T °C 40
Pressure, P kPa(g) 3249
Droplet Diameter, Dp µm 500
Liquid Density, ρL kg/m3 991.4260102
Vapour Density, ρV kg/m3 6.076971649
Liquid Viscosity, µL Pa*s 0.000671697
Vapour Viscosity, µV Pa*s 1.18861E-05
Inlet Liquid Flow, QL m3/s 0.000105874
Inlet Vapour Flow, QV m3/s 1.5381639
Material - CS
L/D Ratio - 3
Demister Height, hD m 0.15
Residence Time, t s 300

In GPSA Section 7: Separation Equipment, particle diameter size for gravity settling chambers

range from 5 to 10,000 µm. A value of 500 µm was assumed for the separators. It was also stated

that the length to diameter ratio (L:D) for vertical separators is typically 2 to 4; a value of 3 was

used for calculations. Demisters will add 0.15 m to the total height and diameter of the

separators. A residence time of 5 minutes will be used to determine liquid holdup capacity. An

overdesign factor of 25% will be considered for the flow rate.

Gravity Settling Theory

In the following equations, the subscript c denotes the continuous phase. With vapour as the

continuous phase and liquid as the dispersed or discontinuous phase, the terminal velocity was

calculated based on the Reynolds number, Re, range:

For Re < 2

H-23
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

𝑚 −6 2 𝑘𝑔
1000𝑔𝐷𝑝 2 (𝜌𝐿 − 𝜌𝑉 ) 1000(9.81 𝑠 2 )(500 ∙ 10 𝑚) (991.4 − 6.07 𝑚3 ) 𝑚
𝑉𝑡 = = −2
= 11.3
18𝜇𝐶 18(1.19 ∙ 10 𝑚𝑃𝑎 ∙ 𝑠) 𝑠

𝑘𝑔 −6 𝑚
1000𝜌𝑉 𝐷𝑝 𝑉𝑡 1000 (6.07 𝑚3 ) (500 ∙ 10 𝑚) (11.3 𝑠 )
𝑅𝑒 = = = 2882
𝜇𝐶 1.19 ∙ 10−2 𝑚𝑃𝑎 ∙ 𝑠

Since the Re value calculated is not within the stated range, this terminal velocity cannot be used.

For 2 < Re < 500

2.94𝑔0.71 𝐷𝑝 1.14 (𝜌𝐿 − 𝜌𝑉 )0.71


𝑉𝑡 =
𝜌𝑉 0.29 𝜇𝑉 0.43

𝑚 0.71 𝑘𝑔
2.94(9.81 2 ) (500 ∙ 10−6 𝑚)1.14 (991.4 − 6.07 3 )0.71 𝑚
= 𝑠 𝑚 = 1.37
𝑘𝑔 𝑠
(6.07 3 )0.29 (1.19 ∙ 10−2 𝑚𝑃𝑎 ∙ 𝑠)0.43
𝑚

𝑘𝑔 −6 𝑚
1000𝜌𝑉 𝐷𝑝 𝑉𝑡 1000 (6.07 𝑚3 ) (500 ∙ 10 𝑚) (1.37 𝑠 )
𝑅𝑒 = = = 349
𝜇𝐶 1.19 ∙ 10−2 𝑚𝑃𝑎 ∙ 𝑠

Since the calculated Re is within the specified range, use this velocity for the next calculation. If

this was not the case, the final terminal velocity formula below could have been used for higher

Re values.

For 500 < Re < 200,000

𝑔𝐷𝑝 (𝜌𝐿 − 𝜌𝑉 )
𝑉𝑡 = 1.74√
𝜌𝑉

H-24
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Assuming the droplets are spherical, the Re is used to obtain a drag coefficient CD and a terminal

velocity is recalculated. Iterations, i, are done until the velocities are within 5% of the last

iteration.

𝑚 𝑘𝑔
4𝑔𝐷𝑝 (𝜌𝐿 − 𝜌𝑉 ) 4(9.81 2 )(500 ∙ 10−6 𝑚)(991.4 − 6.07 3 )
𝑉𝑡,𝑖 = √ =√ 𝑠 𝑚 = 1.45 𝑚
3𝜌𝑉 𝐶𝐷 𝑘𝑔 𝑠
3(6.07 3 )(0.5)
𝑚

The corresponding diameter is:

𝑄𝑉 4𝑄𝑉
𝑉𝑡 = =
𝐴 𝜋𝐷2

𝑚3
4(125 % × 1.538
𝐷=√
4𝑄𝑉
=√ 𝑠 ) = 1.3 𝑚
𝜋𝑉𝑡 𝑚
𝜋(1.45 𝑠 )

𝐿 = 3𝐷 = 3(1.3 𝑚) = 3.9 𝑚

With the demister, the separator dimensions are

Separator Dimensions with Demister


Diameter, D m 1.4
Length, L m 4.0
Volume, V m3 6.2

The same procedure is repeated but with liquid as the continuous phase and vapour as the

dispersed phase. The more conservative dimensions will be taken as the size of the separator. In

this case, the dimensions above are more conservative since the liquid flow into the vessel is not

as large as the vapour phase. Note that the diameter above agrees with the actual diameter of the

H-25
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

existing C-87 provided by the client. The length is slightly higher but this is acceptable since we

are using a conservative L/D ratio.

Souders-Brown

The maximum gas velocity is

𝜌𝐿 − 𝜌𝑉
𝑉𝑚𝑎𝑥 = 𝐾𝑆 √
𝜌𝑉

PetroSkills | John M. Campbell (2015) provided a correlation for the design parameter KS of 500

micron droplets as a function of pressure. Correlation for the lower curve is used to get a

conservative value. At a pressure of 3350 kPa (a), the correlation is

𝐾𝑆 = 0.1225 + 0 × 𝑃 = 0.1225

The deration factor due to the mesh pad was determined to be 80% of the design parameter.

𝑘𝑔
991.4 − 6.07
𝑉𝑚𝑎𝑥 = (0.1225 × 80%)√ 𝑚3 = 1.25 𝑚
𝑘𝑔 𝑠
6.07 3
𝑚

The minimum diameter is

𝑚3
4𝑄𝑉 4(1.538 𝑠 )
𝐷=√ =√ 𝑚 = 1.25 𝑚
𝜋𝐹𝐺 𝑉𝑚𝑎𝑥 𝜋(1)(1.25 𝑠 )

Where FG is the fraction of cross section area available for gas flow which has a value of 1 for

vertical separators.

H-26
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Typically, a disengagement height of 1 m is added to the liquid holdup height hL required and the

demister pad height. The liquid holdup volume VL for the 5 minute residence time is:

𝑚3
𝑉𝐿 = 125 %𝑄𝐿 𝑡 = 125 % × 0.0001 × 300𝑠 = 0.0397 𝑚3
𝑠

4𝑉𝐿 4(0.0397 𝑚3 )
ℎ𝐿 = = = 0.0323 𝑚
𝜋𝐷2 𝜋(1.25 𝑚)2

𝐿 = ℎ𝐿 + 1.0 𝑚 + 0.15 𝑚 = 1.2 𝑚

From this approach, the separator dimensions are:

Separator Dimensions with Demister


Diameter, D m 1.3
Length, L m 1.2
Volume, V m3 1.5

Final Dimensions

The most conservative dimensions from the two methods used to size equipment C-87 are used.

Separator Dimensions with Demister


Diameter, D m 1.4
Length, L m 4.0
Volume, V m3 6.2

This agrees with the provided dimensions and validates the sizing procedure used going forward.

Again, the volume is slightly higher than the existing value, but this is due to the conservative

value of L/D being used.

H-27
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

5.3. Base Case Sizes


C-81: HP Amine Flash Drum
Orientation Vertical
3
Volume (m ) 66.3
Inner Diameter (mm) 2200
Length (mm) 17400
Medium Rich Amine/Flash Gas
Operating Temperature (max °C) 75
Operating Pressure (max kPag) 600
Material CS/SS 316L
Note: Minimum diameter obtained was 140 mm. The existing diameter was taken, and length

was sized to be able to handle liquid holdup capacity with the disengagement height.

C-83: Reflux Vessel


Orientation Vertical
3
Volume (m ) 4.6
Inner Diameter (mm) 2200
Length (mm) 1200
Medium CO2 Gas/Process Condensate
Operating Temperature (max °C) 45
Operating Pressure (max kPag) 24
Material SS 304L
Note: Length calculated was 1200 mm considering liquid capacity and disengagement height.

However, this gives L/D=0.55 which is not ideal. In reality, a ratio between 2 to 4 is preferred.

The existing vessel length is acceptable at 3890 mm.

C-87: Absorber Overhead K.O Drum


Orientation Vertical
3
Volume (m ) 1.6
Inner Diameter (mm) 1300
Length (mm) 1200
Medium Synthesis Gas/Process Condensate
Operating Temperature (max °C) 40
Operating Pressure (max kPag) 3250
Material CS
Note: Similar comment on the length as above. The L/D is 0.92 which is not ideal. In reality, a

ratio between 2 to 4 is preferred. The existing vessel length is acceptable at 3690 mm.

H-28
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

5.4. 112 % Case Sizes


Since the 112 % capacity case is an optimization of the existing base case equipment through

modification of operating conditions, the size of the equipment remain the same with little

variation from the base case.

C-81: HP Amine Flash Drum


Orientation Vertical
Volume (m3) 67.2
Inner Diameter (mm) 2200
Length (mm) 17700
Medium Rich Amine/Flash Gas
Operating Temperature (max °C) 75
Operating Pressure (max kPag) 600
Material CS/SS 316L
Note: Minimum diameter obtained was 140 mm. The existing diameter was taken, and length

was sized to be able to handle liquid holdup capacity with the disengagement height.

C-83: Reflux Vessel


Orientation Vertical
Volume (m3) 5.0
Inner Diameter (mm) 2300
Length (mm) 1200
Medium CO2 Gas/Process Condensate
Operating Temperature (max °C) 45
Operating Pressure (max kPag) 24
Material SS 304L
Note: Similar to the base case, length calculated was 1200 mm which gives L/D=0.55. In reality,

a ratio between 2 to 4 is preferred. The existing vessel length is acceptable at 3890 mm.

C-87: Absorber Overhead K.O Drum


Orientation Vertical
3
Volume (m ) 1.4
Inner Diameter (mm) 1200
Length (mm) 1200
Medium Synthesis Gas/Process Condensate
Operating Temperature (max °C) 40
Operating Pressure (max kPag) 3250

H-29
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Material CS
Note: Similar comment on the length as above. The L/D is 1. Ideally, a ratio between 2 to 4 is

preferred. The existing vessel length is acceptable at 3690 mm.

5.5. 125 % Case Sizes


C-81: HP Amine Flash Drum
Orientation Vertical
Volume (m3) 68.9
Inner Diameter (mm) 2200
Length (mm) 18100
Medium Rich Amine/Flash Gas
Operating Temperature (max °C) 75
Operating Pressure (max kPag) 600
Material CS/SS 316L
Note: Minimum diameter obtained was 140 mm. The existing diameter was taken, and length

was sized to be able to handle liquid holdup capacity with the disengagement height.

C-83: Reflux Vessel


Orientation Vertical
Volume (m3) 5.9
Inner Diameter (mm) 2500
Length (mm) 1200
Medium CO2 Gas/Process Condensate
Operating Temperature (max °C) 45
Operating Pressure (max kPag) 24
Material SS 304L
Note: There is an increase in diameter therefore a new vessel will be required. The diameter has

been sized using 25% overdesign factor on flow rate. Although the minimum calculated length is

1200 mm, the actual length will be a conservative estimate using an L/D of 3. The actual length

of the vessel will be 7500 mm.

C-87: Absorber Overhead K.O Drum


Orientation Vertical
Volume (m3) 1.5
Inner Diameter (mm) 1300
Length (mm) 1200

H-30
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Medium Synthesis Gas/Process Condensate


Operating Temperature (max °C) 40
Operating Pressure (max kPag) 3250
Material CS
Note: Similar comment on the length as above. The L/D is 1. Ideally, a ratio between 2 to 4 is

preferred. The existing vessel length is acceptable at 3690 mm.

6. Column Sizing
Detailed calculations on the CO2 Absorber and LP Flash Stripper can be found in

Appendix D Separation Calculations. To keep the diameter of the columns the same, resultant

pressure drop from the operational and equipment changes was calculated and applied to the

simulation. The diameters are then reverified using the simulation output pressure drop and flow

rates using the Eckert generalized pressure drop correlation (GPDC). The diameters were

verified to be the same across the base, 112 %, and 125 % case.

H-31
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

6.1. Operating Data Provided


6.1.1. CO2 Absorber (C-80)

H-32
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

H-33
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

H-34
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

6.1.2. LP Flash Stripper (C-82)

H-35
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

H-36
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

H-37
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

H-38
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

7. Pump Sizing
7.1. Operating Data Provided
G-81A/B: Semilean Amine Pump
Type Centrifugal
Medium Lean amine
Operating temperature (°C) 73
3
Volumetric flow rate Q (m /h):
Maximum (rated Qmax) 720
Normal 655
Minimum (Qmin) 197
Suction pressure (kPag)
Minimum (rated Qmax) 329
Maximum 703
Discharge pressure (kPag)
Rated @ Qmax 662
Maximum shut off 1100
Differential pressure @ Qmax (kPa) 333
Differential head @ Qmax (m) 32.1
Plant NPSH available (m) 28
Material SS 316L
Speed estimated (rpm) 1775
Power estimated (kW) 89
Estimated hydraulic efficiency (%) 75

G-82 A/B/C: HP Lean Amine Pump


Type Centrifugal
Medium Lean amine
Operating temperature (°C) 83
3
Volumetric flow rate Q (m /h):
Maximum (rated Qmax) 322
Normal 392
Minimum (Qmin) 117
Suction pressure (kPag)
Minimum (rated Qmax) 39
Maximum 508
Discharge pressure (kPag)
Rated @ Qmax 4199
Maximum shut off 5508
Differential pressure @ Qmax (kPa) 4160
Differential head @ Qmax (m) 426

H-39
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

G-82 A/B/C: HP Lean Amine Pump


Plant NPSH available (m) 9.1
Material SS 316L
Speed estimated (rpm) 3570
Power estimated (kW) 546
Estimated hydraulic efficiency (%) 66

G-83 A/B: Stripper Reflux Pump


Type Centrifugal
Medium Process condensate
Operating temperature (°C) 45
3
Volumetric flow rate Q (m /h):
Maximum (rated Qmax) 8.0 plus min. flow required
Normal 3.9
Minimum (Qmin) 1.2
Suction pressure (kPag)
Minimum (rated Qmax) 49.0
Maximum 397
Discharge pressure (kPag)
Rated @ Qmax 776
Maximum shut off 1219
Differential pressure @ Qmax (kPa) 726
Differential head @ Qmax (m) 74.8
Plant NPSH available (m) 3
Material SS 304L
Speed estimated (rpm) 3490
Power estimated (kW) 6.2
Estimated hydraulic efficiency (%) 40
7.2. Base Case
The overall pump efficiency was estimated to be 90 % of the hydraulic efficiency provided for

each pump.

G-81A/B: Semilean Amine Pump


Type Centrifugal
Volumetric flow rate Q (m3/h): 522.9
Maximum (rated Qmax) 720
Minimum (Qmin) 197
Suction pressure (kPag) 121
Minimum 329
Maximum 703

H-40
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Discharge pressure (kPag) 639


Rated @ Qmax 662
Maximum shut off 1100
Differential pressure (kPa) 518
Total Dynamic Head (m) 50.1
Material SS 316L
Power (kW) 111.5
Overall pump efficiency (%) 67.5
Note: Suction pressure given in design basis is 44 kPag. The discharge pressure is also given at

639 kPag.

G-82 A/B/C: HP Lean Amine Pump


Type Centrifugal
Volumetric flow rate Q (m3/h): 587.8
Maximum (rated Qmax) 322
Minimum (Qmin) 117
Suction pressure (kPag) 39
Minimum 39
Maximum 508
Discharge pressure (kPag) 4199
Rated @ Qmax 4199
Maximum shut off 5508
Differential pressure (kPa) 4160
Total Dynamic Head (m) 424
Material SS 316L
Power (kW) 1143
Overall pump efficiency (%) 59.4
Note: The volumetric flow in the design basis is 585 m3/h.

G-83 A/B: Stripper Reflux Pump


Type Centrifugal
3
Volumetric flow rate Q (m /h): 3.1
Maximum (rated Qmax) 8.0 plus min. flow required
Minimum (Qmin) 1.2
Suction pressure (kPag) 19
Minimum (rated Qmax) 49.0
Maximum 397
Discharge pressure (kPag) 499
Rated @ Qmax 776
Maximum shut off 1219
Differential pressure (kPa) 480
Total Dynamic Head (m) 49.4

H-41
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

G-83 A/B: Stripper Reflux Pump


Material SS 304L
Power (kW) 1.15
Overall pump efficiency (%) 36
Note: Suction pressure given at 19 kPag in the design basis. Discharge pressure is also given at

499 kPag.

7.1. Pump Sizing Methodology


When comparing the simulated results for the 112 % and 125 % redesign cases with the base

case and operating data provided, it was found that all pump operating conditions remained well

within allowable limits. No additional pumps were required for the 112 % or 125 % capacity

redesign cases. The simulated pump operating conditions for the redesigns are shown in the

subsequent sections.

7.2. 112 % Case


G-81A/B: Semilean Amine Pump
Type Centrifugal
Volumetric flow rate Q (m3/h): 585.9
Maximum (rated Qmax) 720
Minimum (Qmin) 197
Suction pressure (kPag) 139.6
Minimum 329
Maximum 703
Discharge pressure (kPag) 639
Rated @ Qmax 662
Maximum shut off 1100
Differential pressure (kPa) 499.4
Total Dynamic Head (m) 48.1
Material SS 316L
Power (kW) 120.4
Overall pump efficiency (%) 67.5
Note: Suction pressure given in design basis is 44 kPag. The discharge pressure is also given at

639 kPag.

H-42
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

G-82 A/B/C: HP Lean Amine Pump


Type Centrifugal
3
Volumetric flow rate Q (m /h): 595.4
Maximum (rated Qmax) 322
Minimum (Qmin) 117
Suction pressure (kPag) 39
Minimum 39
Maximum 508
Discharge pressure (kPag) 4199
Rated @ Qmax 4199
Maximum shut off 5508
Differential pressure (kPa) 4160
Total Dynamic Head (m) 422.4
Material SS 316L
Power (kW) 1158
Overall pump efficiency (%) 59.4
Note: The volumetric flow in the design basis is 585 m3/h.

G-83 A/B: Stripper Reflux Pump


Type Centrifugal
Volumetric flow rate Q (m3/h): 3.1
Maximum (rated Qmax) 8.0 plus min. flow required
Minimum (Qmin) 1.2
Suction pressure (kPag) 19
Minimum (rated Qmax) 49.0
Maximum 397
Discharge pressure (kPag) 499
Rated @ Qmax 776
Maximum shut off 1219
Differential pressure (kPa) 480
Total Dynamic Head (m) 49.4
Material SS 304L
Power (kW) 1.14
Overall pump efficiency (%) 36
Note: Suction pressure given at 19 kPag in the design basis. Discharge pressure is also given at

499 kPag.

H-43
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

7.3. 125 % Case


G-81A/B: Semilean Amine Pump
Type Centrifugal
3
Volumetric flow rate Q (m /h): 605.1
Maximum (rated Qmax) 720
Minimum (Qmin) 197
Suction pressure (kPag) 145
Minimum 329
Maximum 703
Discharge pressure (kPag) 639
Rated @ Qmax 662
Maximum shut off 1100
Differential pressure (kPa) 494
Total Dynamic Head (m) 47.1
Material SS 316L
Power (kW) 123.1
Overall pump efficiency (%) 67.5
Note: Suction pressure given in design basis is 44 kPag. The discharge pressure is also given at

639 kPag.

G-82 A/B/C: HP Lean Amine Pump


Type Centrifugal
3
Volumetric flow rate Q (m /h): 609
Maximum (rated Qmax) 322
Minimum (Qmin) 117
Suction pressure (kPag) 39
Minimum 39
Maximum 508
Discharge pressure (kPag) 4099
Rated @ Qmax 4199
Maximum shut off 5508
Differential pressure (kPa) 4060
Total Dynamic Head (m) 410
Material SS 316L
Power (kW) 1156
Overall pump efficiency (%) 59.4
Note: The volumetric flow in the design basis is 585 m3/h.

H-44
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

G-83 A/B: Stripper Reflux Pump


Type Centrifugal
3
Volumetric flow rate Q (m /h): 2.78
Maximum (rated Qmax) 8.0 plus min. flow required
Minimum (Qmin) 1.2
Suction pressure (kPag) 19
Minimum (rated Qmax) 49.0
Maximum 397
Discharge pressure (kPag) 499
Rated @ Qmax 776
Maximum shut off 1219
Differential pressure (kPa) 480
Total Dynamic Head (m) 49.4
Material SS 304L
Power (kW) 1.03
Overall pump efficiency (%) 36
Note: Suction pressure given at 19 kPag in the design basis. Discharge pressure is also given at

499 kPag.

8. Process Lines Sizing


8.1. Methodology
The size of the main process lines in the existing plant were not provided by the client.

To identify process lines sizes that are representative of what is already in place in the existing

CO2 Recovery Facility, the lines were sized using properties and flow rates given by the client

material balance specifications. Various sizing techniques were utilized, including simulation

using VMGSim, rules of thumb provided in previous Chemical Engineering Courses at the

University of Alberta (U of A), and utilizing standard sizing charts. To select a nominal pipe size

calculated based on the three different techniques, economical fluid velocities, pressure drops,

pump suction line maximum recommended velocities, and guidelines for minimizing corrosion

in amine units were considered. Pipe Schedules were then calculated using the American Society

of Mechanical Engineers (ASME) Code B31.3 for Pressure Piping (1).

H-45
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

The internal diameter of the pipe was then determined based on the pipe thickness

required by ASME B31.3. If this internal diameter provided flow that was outside of

recommended ranges for velocity or pressure drop, the process was iterated again with a

different pipe size. The details of the sizing process for the different types of flow are provided

below. Sample calculations for the sizing process are given in Section 5.2. Conversion factors

between different units were obtained from Ulrich and Vasudevan (2).

8.1.1. Single Phase Vapour Flow


The economical pipe diameter for the vapour streams was taken from Perry’s Chemical

Engineering Handbook, Seventh Edition (3). An economic optimum velocity for gases with

densities ranging from 0.2 to 20 kg/m3 was reported to be 40 m/s to 9 m/s. All vapour streams

using design basis and simulated information fell within this specified density.

The recommended maximum allowable velocity for the vapour streams were also

considered based on the calculated sonic velocity of the gas (4). The velocity of the vapour

should remain less than 0.1 times the sonic velocity of the vapour, which is given by:

𝑉𝑠 = √𝑘𝑃/𝜌

The ratio of specific heats, k, for each component was obtained from Engineering Toolbox (5).

The maximum friction loss in the pipe in kPa/100m was determined by linear interpolation of the

information provided by Church (6).

8.1.2. Single Phase Liquid Flow


The economical pipe diameter for liquid streams was taken to be 3.3 – 10 ft/s (1.01 – 3.05

m/s) based on the Kolmetz Handbook of Process Equipment Design (7). The allowable pressure

drop for low viscosity liquids was also taken from the Kolmetz Handbook, with a value of 2.2

H-46
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

psi/100ft (49.77 kPa/100m). To increase the NPSHa to avoid cavitation in pump suction lines, a

maximum velocity of 5ft/s (1.52m/s) was chosen (7) (8). The recommended velocity through

carbon steel pipes is also recommended to be below 1.8 m/s for MDEA units (9). This was taken

into consideration as well during the line sizing process.

8.1.3. Two Phase Flow


For two-phase flow, the minimum and maximum velocity of the fluids were determined

by guidelines given by Church, and distributed or segregated flow was targeted wherever

possible to avoid intermittent flow (6). The flow regime was determined from Empirical flow

regime maps and figures provided by the presentation by Church.

8.2. Sample Calculations


8.2.1. Single Phase Flow
A sample calculation for a vapour line (Stream 25) is provided in this section. Relevant

parameters from the design basis for stream 25 are provided in the table below.

Stream Number 25
Description SG to CO2 Absorber
Phase Vapor
Vapour fraction 100
Temperature (K) 313.15
Pressure (kPa(g)) 3325.00
Volumetric Flow Rate (m3/s) 1.76
Eff Density (kg/m3) 13.65
Viscosity (Pa s) 1.40E-05
Component mol/mol
CO 0.03
CO2 0.17
H2 0.76
H2O 0.00
CH4 0.04
N2 0.00

H-47
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

O2 0.00
aMDEA 0.00
MDEA 0.00
PZ 0.00

The ratio of specific heats was calculated by multiplying each component’s k value with their

molar fraction.

𝑘 = (0.033 ∗ 1.4 + 0.166 ∗ 1.28 + 0.756 ∗ 1.41 + 0.002 ∗ 1.33 + 0.042 ∗ 1.32 + 0.001 ∗ 1.4) = 1.38414

The sonic velocity of the gas was then calculated as:

1000𝑃𝑎 1 𝑚3
𝑉𝑚𝑎𝑥 = 0.1 ∗ 𝑉𝑠 = 0.1 ∗ √1.38414 ∗ (3325 𝑘𝑃𝑎 + 101.325 𝑘𝑃𝑎) ∗ ∗
1 𝑘𝑃𝑎 13.65 𝑘𝑔

𝑉𝑠 = 58.94 𝑚/𝑠

Allowable pressure drop was interpolated from Church (6):

32 − 18
𝛥𝑃 = 18 + (3325 − 1500) = 30.78 𝑘𝑃𝑎/100𝑚
3500 − 1500

The rule of thumb velocity was calculated from Pick (4):

𝑉 = √3300/𝜌𝑚 = √3300/13.65 = 15.55𝑚/𝑠

Using this velocity and the volumetric flow rate provided in the design basis:

4Q 4 ∗ 1.76 m3 /𝑠
𝐷=√ =√ = 0.38 𝑚
πV π ∗ 15.55 m/s

1 𝑖𝑛𝑐ℎ
𝐷 = 0.38𝑚 ∗ = 14.94 𝑖𝑛𝑐ℎ𝑒𝑠
0.0254 𝑚

H-48
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

The velocity obtained from inputting the design basis information and assuming commercial

steel pipe with a roughness of 0.0045 cm gave an estimated pipe diameter of 27.34 cm, which is

equal to 10.68 inches (10).

Approximating the inside pipe diameter as the nominal pipe diameter for convenience,

the calculated nominal pipe sizes were 12.00 inches and 16.00 inches, which had some

discrepancy. The velocity of the fluids using these diameters was then calculated.

𝑚3
4𝑄 4 ∗ 1.76 𝑠 𝑚
𝑉𝐷=12.00𝑖𝑛 = 2= = 24.09
πD 0.0254 𝑚 2 𝑠
π ∗ (12.00 inches ∗ )
1 𝑖𝑛𝑐ℎ

Similarly, VD=14.00in = 17.70 m/s and VD=16.00in = 13.55 m/s. All of these calculated velocities

were within the range of allowable vapour velocities.

Next, the pressure drop for each calculated pipe size was determined.

𝑘𝑔 𝑚 0.0254 𝑚
𝜌𝑉𝐷 13.65 𝑚3 ∗ 24.09 𝑠 ∗ 12.00 𝑖𝑛𝑐ℎ𝑒𝑠 ∗ 1 𝑖𝑛𝑐ℎ
𝑅𝑒𝐷=12.00𝑖𝑛 = = = 7.16 ∗ 106
µ 1.4 ∗ 10−5 𝑃𝑎 ∗ 𝑠

Similarly, ReD=14.00in = 6.14*106 and ReD=16.00in = 5.37*106. The equivalent roughness was taken

as 0.0045 cm from Munson et. al (10). Thus,

𝜀 0.0045 𝑐𝑚
= = 0.00015
𝐷𝐷=12.00𝑖𝑛 12.00 𝑖𝑛𝑐ℎ𝑒𝑠 ∗ 2.54𝑐𝑚
1 𝑖𝑛𝑐ℎ

The Moody friction factor was then taken from a Moody chart to be 0.013 (10). Similarly, the

14.00 inch pipe diameter had an ε/D of 0.00013 and a friction factor of 0.0125, and the 16.00

inch pipe had an ε/D of 0.00011 and a friction factor of 0.0125.

H-49
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

The pressure drop along the pipe length was then calculated:

𝑘𝑔 𝑚 2
13.65 ∗ 0.013 ∗ 100𝑚 ∗ (24.09 𝑠 ) 1 𝑘𝑃𝑎
2
𝛥𝑃 𝜌𝑓𝑚 𝐿𝑉 𝑚3
= = = 16.89 𝑘𝑃𝑎
100𝑚 2𝐷 0.0254 𝑚 1000 𝑃𝑎
2 ∗ 12.00 𝑖𝑛𝑐ℎ𝑒𝑠 ∗
1 𝑖𝑛𝑐ℎ

The pressure drop for the 14.00 inch and 16.00 inch diameter pipes were calculated to be 7.51

kPa/100m and 3.85 kPa/100m, respectively.

The summary of these calculations are shown in the table below:

Pipe Diameter Velocity Reynold’s ε/D fm Pressure Drop


(inches) (m/s) Number (kPa/100m)
12.00 24.09 7.16*106 0.00015 0.013 16.89
14.00 17.70 6.14*106 0.00013 0.0125 7.51
16.00 13.55 5.37*106 0.00011 0.0125 3.85

Since the maximum allowable pressure drop is 30.78 kPa/100m, a nominal pipe size of

12.00 inches was selected. If the inside diameter changed significantly after the pipe thickness

was calculated, the process was repeated again with a new nominal diameter and calculated

inside diameter to verify that the pressure drop and velocities were within allowable ranges.

For process line sizing for vapours, the chart technique for process lines sizing taken

from McDonald et. al was not used, as the chart is applicable only for air with a relatively low

flow rate (11). However, the chart method was used for liquid streams, using the calculated

allowable pressure drop in ft.H2O/100ft and volumetric flow rate in U.S gallons per minute. The

pipe sizes were rounded up to be conservative.

After the line sizing process was completed for the design case, the entire process was

repeated for the base simulation case to verify the accuracy of the simulated results. This was

H-50
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

done because the simulation provided stream properties that were slightly different than the

design basis. If the line sizing for the base case and design case agreed, that would be reasonable

indication that the predicted fluid velocities and flow regimes for the 112 % and 125 % redesign

cases would be realistic.

8.2.2. Two-Phase Flow


Two-phase flow pipes were sized based on the method outlined by Church (6). For

stream 38, the design basis information is as follows:

Stream Number 38
Description CO2 to Dehydration Unit
Phase Mixed
Vapour fraction 98.5
Temperature (K) 307.15
Pressure (kPa(g)) 3190.00
Volumetric Flow Rate (m3/s) 0.21
Eff Density (kg/m3) 68.16
Viscosity (Pa s) 0.00
Component mol/mol
CO 0.00
CO2 0.98
H2 0.00
H2O 0.02
CH4 0.00
N2 0.00
O2 0.00
aMDEA 0.00
MDEA 0.00
PZ 0.00

The vapour fraction was 0.9850 which corresponds to a liquid fraction of 0.0150. The

Froude number was calculated using the maximum and minimum allowable velocities, which

were calculated as follows:

H-51
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

122 122
𝑉𝑚𝑎𝑥 = = = 14.78 𝑚/𝑠
√𝜌𝑚 √68.16 𝑘𝑔3
𝑚

73 122
𝑉𝑚𝑖𝑛 = = = 8.84 𝑚/𝑠
√𝜌𝑚 √68.16 𝑘𝑔3
𝑚

The diameters that correspond to those maximum and minimum velocities were calculated as:

0.21 m3
4Q 4∗ 1 𝑖𝑛𝑐ℎ
𝐷𝑚𝑖𝑛 =√ =√ 𝑠 = 0.136𝑚 ∗ = 5.35 𝑖𝑛𝑐ℎ𝑒𝑠
πV𝑚𝑎𝑥 m 0.0254 𝑚
π ∗ 14.78 s

Rounding up, the minimum pipe diameter for stream 38 is 6.00 inches. Similarly, the maximum pipe

diameter was calculated to be 6.92 inches. Rounding down from this maximum, the pipe diameter was

chosen to be 6.00 inches.

𝑚
𝑉𝑚𝑎𝑥 14.78 𝑠
𝐹𝑟𝑚𝑎𝑥 = = = 9.6156
√𝑔 ∗ 𝐷 √9.81 𝑚2 ∗ 6.00 𝑖𝑛𝑐ℎ𝑒𝑠 ∗ 0.0254 𝑚
𝑠 1 𝑖𝑛𝑐ℎ

Using the charts provided by Church’s presentation, the flow regime for stream 38 was

determined to be segregated flow.

If the two-phase flow analysis provided different minimum and maximum pipe

diameters, the flow regime for each of those intermediate pipe diameters was calculated to

ensure distributed or segregated flow could be achieved. If multiple pipe diameters could achieve

non-intermittent flow, then the pipe diameter that allowed the highest velocity within the

allowable ranges was specified.

H-52
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

For Stream 36 it was determined that intermittent flow was unavoidable. For this stream,

lines should be constructed with a slight decline to ensure liquid moves through the pipe without

plug or slug flow. Other streams 27 and 74 were identified as two-phase flow in the design basis,

however the simulated results suggested the streams were single phases flow. The vapour

fraction for the design basis was thus used for these streams to approximate the vapour fraction

of the simulated cases to determine the type of two-phase flow regime that could be expected.

8.2.3. Pipe Thickness


The thickness of pipe was then determined from the method outlined in ASME B31.3

according to (1):

𝑃𝐷
𝑡=
2(𝑆𝐸𝑊 + 𝑃𝑌)

The design pressure of the stream was based on design pressures specified in existing

equipment data sheets provided by CNRL for the CO2 absorber and LP Flash Stripper. The

design pressure of other streams were calculated as the highest pressure that the stream could

experience based on adjacent streams, or taken as the minimum between the operating pressure +

200 kPa or the operating pressure *1.1. The minimum design temperature was taken to be 65 °C

for streams below operating temperatures of 65 °C. The maximum design temperature was taken

to be the operating temperature rounded to the nearest 50°C.

S, E, W, and Y were taken from tables within ASME B31.3. The outside diameters of

each nominal pipe size was determined from standard carbon steel and stainless steel pipe sizes

and thicknesses based on ASME B36.10M-2018 for Welded and Seamless Wrought Steel Pipe

and B36.19M-2018 for Stainless Steel Pipe (12) (13). The total pipe thickness could then be

H-53
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

calculated as the thickness determined using the above formula added by the sum of mechanical

allowances.

𝑡𝑚 = 𝑡 + 𝑐

A corrosion allowance of 0 mm was specified for stainless steel and 3.0 mm for carbon

steel based on corrosion allowances applied for existing CO2 Recovery Plant equipment. An

additional 0.5 mm was applied to the sum of mechanical allowances to account for machined

surfaces or grooves where the tolerance was not specified.

Sample calculations will be shown for Stream 73, which is used to transport rich amine

from the CO2 absorber. The line was sized to be 14.00 inches nominal diameter (14.00 O.D).

Stainless steel was selected as the material specification due to the high acid gas content. The

reasons for this material selection will be explored further in Section 6 of this Appendix.

0.0254 𝑚
3700 𝑘𝑃𝑎 ∗ 14.00 𝑖𝑛𝑐ℎ𝑒𝑠 ∗
𝑡= 1 𝑖𝑛𝑐ℎ = 0.00565 𝑚 = 5.65 𝑚𝑚
2 ∗ (115,000 𝑘𝑃𝑎 ∗ 1.00 ∗ 1.00 + 3700 𝑘𝑃𝑎 ∗ 0.4)

1 𝑖𝑛𝑐ℎ
𝑡𝑚 = 5.65𝑚𝑚 + 0.5 𝑚𝑚 = 6.15 𝑚𝑚 ∗ = 0.24 𝑖𝑛𝑐ℎ𝑒𝑠
25.4 𝑚𝑚

Looking at ASME B36.19M, the required schedule for 14.00 inch pipe would be

Schedule 40S with a wall thickness of 0.375 inches. The lower schedule would have a wall

thickness of 0.188 which is less than what is required.

After the thickness was calculated, the inside diameter of the pipe was determined by the

simple formula:

𝐼. 𝐷. = 𝑂. 𝐷 − 2 ∗ 𝑡𝑚 = 14.00 𝑖𝑛𝑐ℎ𝑒𝑠 − 2 ∗ 0.375 𝑖𝑛𝑐ℎ𝑒𝑠 = 13.25 𝑖𝑛𝑐ℎ𝑒𝑠

H-54
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

The fluid velocity was re-calculated using this inner diameter using the method described in

5.2.2. If the velocity or pressure drop for this inside diameter was out of the allowable range, the

whole process was repeated for the next pipe size higher. The lines for two-phase flow were also

re-evaluated to see if the variance between the inside diameter and nominal pipe size constituted

enough of a different to change the type of flow regime.

Several high velocity lines were identified through the line sizing process for the 112 %

and 125 % redesign cases. These high velocity lines exceeded the 1.8 m/s recommended

maximum velocity from API RP 945 (9). The existing process line sizes may be different than

what was determined through this sizing process and the simulation produces different properties

than the design basis, meaning the pipes may not be high velocity in the existing facility.

However, it is recommended that the client investigates this potential risk to ensure that

corrosion of the CO2 Recovery Plant equipment is minimized.

A summary of the main process lines, including the nominal pipe size, schedule, material

specification, expected velocity, and type of flow regime is shown on the next page.

H-55
8.1. Size of Main Process Lines Summary

H-56
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

9. Material Selection
Proper material selection is imperative to ensure that process equipment operates in a safe

manner throughout its projected lifetime. Some of the materials of construction selected were

based on existing specifications from equipment data sheets provided by the client. For other

streams that were unknown, the material selection was conducted based on potential corrosion and

cracking mechanisms found in the American Petroleum Institute (API) Recommended Practices

945 and 571, and guidelines found in literature (14; 15; 16; 17; 18).

9.1. Potential Cracking Mechanisms

9.1.1. Sulfide Stress Cracking (SSC)


Sulphide Stress Cracking is defined at the cracking of a metal under the combined action

of tensile stress and corrosion in the presence of water and hydrogen sulphide. The hydrogen

sulfide liberates atomic hydrogen at the metal surface, and poisons the recombination of atomic

hydrogen into molecular hydrogen, which promotes the absorption of atomic hydrogen by the

steel. The SSC mechanism involves hydrogen embrittlement, particularly in areas of high metal

hardness such as weld deposits and weld heat-affected zones in the adjacent base metal. The

potential for SSC was not evaluated in-depth due to the presence of hydro-desulphurization

reactors located upstream of the CO2 Removal Unit that removes H2S to a high purity. However,

SSC can be minimized by applying proper Post Weld Heat Treatment (PWHT).

9.1.2. Hydrogen-induced Cracking (HIC)


Hydrogen-Induced Cracking (HIC) is a result of excessive internal hydrogen pressure. HIC

is defined as stepwise internal cracks that connect adjacent hydrogen blisters on different planes

in the metal, or to the metal surface. No externally applied stress is needed for the formation of

H-57
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

HIC. HIC can be minimized by selecting a higher quality steel with low inclusion content.

Increased resistance to blistering and HIC is usually achieved by lowering the sulfur content of the

steel and controlling the sulfide inclusion morphology by calcium or rare earth metal additions to

produce spheroidal sulfide shapes. Base metal heat treatments, such as normalizing or quenching,

and tempering above 593 ℃, increase resistance to HIC.

9.1.3. Stress-Oriented Hydrogen-Induced Cracking (SOHIC)


Stress-Oriented Hydrogen-Induced Cracking is a special form of HIC that occurs in the

base metal, adjacent to the heat-affected zone of a weld, where there are high residual stresses from

welding. The use of higher quality HIC-resistant steels can reduce the likelihood of SOHIC. Tests

have shown that these steels generally have a higher hydrogen flux threshold for SOHIC than

conventional steels, but SOHIC would still occur in these steels if that threshold was exceeded.

9.1.4. Alkaline Stress Corrosion Cracking (ASCC)


Alkaline Stress Corrosion is the cracking of a metal produced by the combined action of

corrosion in an aqueous alkaline environment containing H2S, CO2, and tensile stress. It typically

occurs in non-stress relieved carbon steels. In as-welded steels, cracks typically propagate parallel

to the weld in adjacent base metals but can also occur in the weld deposits or heat-affected zones.

ASCC can occur over a wide range of temperatures, but susceptibility appears to increase as

temperature rises.

ASCC can occur in a variety of steels. Tests have indicated there is no significant

correlation between susceptibility to ASCC and steel properties, since the metal hardness has no

relation to ASCC. Susceptibility to ASCC does have correlation to temperature and tensile stress

H-58
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

levels. Therefore, a way to effectively control ASCC is post welding heat treatment and proper

heat treatment after cold forming.

9.1.5. Chloride Stress Corrosion Cracking


Chloride Stress Corrosion Cracking caused by a combination of tensile stresses,

temperatures, and an aqueous chloride environment. The presence of dissolved oxygen can

increase the propensity for cracking. Tests have shown that increasing temperatures can increase

the susceptibility to cracking. Increasing levels of chloride increase the likelihood of cracking as

well.

Cl SCC usually occurs in 300 series stainless steels. The use of resistant materials such as

duplex stainless steels and nickel-based alloys can help reduce the likelihood of Cl SCC. Duplex

stainless steels are more resistant than 300 series stainless steels but are still susceptible. Nickel-

based alloys are highly resistant, but not immune. Designs should be adjusted so that there are no

stagnant regions where chlorides can concentrate or deposit.

9.1.6. Amine Stress Corrosion Cracking


To prevent Amine Stress Corrosion Cracking, all carbon steel welds in piping and

equipment should undergo PWHT in accordance with API RP 945. The use of solid or clad

stainless steel, Alloy 400 or other corrosion resistant alloys should be considered in place of carbon

steel.

Amine Stress Corrosion Cracking is caused by a combination of tensile stress and corrosion

in aqueous alkanolamine systems used to remove/absorb H2S and/or CO2 and their mixtures from

various gas and liquid hydrocarbon streams. Tests have shown that increasing temperatures can

increase the susceptibility to Amine Stress Corrosion Cracking. Cracking is more likely to occur

H-59
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

in lean MEA and DEA services but is also found in most amines, including MDEA and DIPA.

Cracking can also occur in non-PWHT’d piping and equipment as a result exposure to steamout

and to short-term amine carryover. To prevent Amine Stress Corrosion Cracking, all carbon steel

welds in piping and equipment should undergo PWHT in accordance with API RP 945. The use

of solid or clad stainless steel, Alloy 400 or other corrosion resistant alloys should be considered

in place of carbon steel.

9.2. Potential Corrosion Mechanisms


9.2.1. Erosion / Erosion-Corrosion
Erosion occurs when relative movement or impact between any combination of phases

results in the accelerated mechanical removal of surface material. Erosion-corrosion is the term

used when corrosion processes contribute to the erosion, such as when metal surfaces are exposed

to oxidating environments. All types of equipment exposed to moving fluids are subject to this

mechanism. Methods of mitigation include increasing pipe diameter to reduce fluid velocity,

increasing the wall thickness, using more corrosion resistant alloys, installation of cathodic

protection systems, or altering the process environment so that it is less corrosive.

9.2.2. Vibration-Induced Fatigue


This mechanism occurs when the dynamic loading due to vibration, water hammer, or

unstable fluid flow results in cracking of the material. The affected units or equipment include heat

exchanger tubes which may be susceptible to vortex shedding or safety relief valves which are

subject to chatter and premature pop-off. Mitigation strategies for vibration-induced fatigue

include the addition of anchors or dampening equipment to lessen the vibration or the removal of

the source of vibration entirely. Material upgrades are not usually a solution for this mechanism.

H-60
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

9.2.3. Cavitation
This mechanism is a form of erosion that occurs when fluid movement from low to high

pressure regions result in the formation and instantaneous collapse of tiny vapor bubbles. This

causes severe localized impact damage which debilitates the mechanical integrity of the

equipment. This phenomenon is most often found in pump casings and impellers where the

available net pressure suction head (NPSH) is inadequate. Strategies to prevent or mitigate

cavitation include the avoidance of conditions that allow the absolute pressure of the fluid to fall

below its vapor pressure or the usage of stronger, more corrosion resistant alloys. Streamlining the

flow path to reduce turbulence or decreasing the fluid velocities are examples of ways to avoid

conditions where cavitation may occur. Materials with high toughness will be better able to

withstand the high local pressures and impacts of the collapsing bubbles.

9.2.4. Cooling Water Corrosion


Cooling water corrosion is described as the general or localized corrosion of material caused

by dissolved salts, gases, organic compounds, or microbiological activity present in the cooling

water. This mechanism is a concern for heat exchangers using cooling water as their utility stream,

along with cooling towers. Mitigation strategies include the proper treatment of the cooling water

systems and improving the metallurgy so that it is resistant to waters with high chloride content,

low velocities, high process temperatures, or poorly maintained water chemistry. Cooling water

should be on the tube side of heat exchangers to minimize stagnant areas where there is a high risk

of cooling water corrosion.

9.2.5. CO2 Corrosion


This mechanism of corrosion occurs when the dissolved CO2 in water forms carbonic acid

(H2CO3) and lowers the pH of the water, promoting an environment with high risk of corrosion.

H-61
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

This form of corrosion is generally weaker, so the only affected materials are carbon steel and low

alloy steels. Effluent gas streams of the shift converters in hydrogen plants and overhead systems

of regenerators within CO2 removal plants are examples of areas subjected to CO2 corrosion.

Mitigation strategies include Increasing the condensate pH to above 6 in steam condensate systems

or the usage of 300 Series, 400 Series, or duplex SS for the material selection as they are highly

resistant to this form of corrosion.

9.2.6. Flue-Gas Dew-Point Corrosion


This mechanism of corrosion occurs when the sulfur and chlorin species in fuel form sulfur

dioxide, sulfur trioxide, and hydrogen chloride within the combustion products. At low enough

temperatures, these gases and the water vapor in the flue gas will condense to form sulfurous acid,

sulfuric acid, and hydrochloric acid which can lead to severe corrosion. Carbon steel, low alloy

steels, and 300 series SS are the most commonly affect materials. Mitigation strategies include

maintaining the metallic surfaces at the back end of the boiler fired heaters above the temperatures

of sulfuric acid dewpoint corrosion. The use of 300 series SS in feedwater heaters should be

avoided if the environment is likely to contain chlorides.

9.2.7. Hydrogen Embrittlement


The phenomenon occurs when atomic hydrogen penetrates through the material resulting in

the loss in ductility of high strength steels. Ultimately this leads to brittle cracking of the material.

The affected materials include carbon steel, 400 Series SS, Precipitation Hardenable (PH) SS, and

certain high strength nickel-based alloys. Bolts and springs made of high strength steel are very

susceptible to hydrogen embrittlement. Alloys which have a tensile strength of higher than 150 ksi

can absorb hydrogen during electroplating and crack. Other areas of concern would be carbon steel

piping and vessels in wet H2S services in amine, hydroprocessing, and sour water units. The

H-62
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

prevention and mitigation strategies include the usage of lower strength steels and PWHT to

temper the microstructure, improve ductility, and reduce residual stresses and hardness. Another

strategy would be to apply protective linings, SS claddings, or weld overclays to prevent surface

hydrogen reactions in corrosive aqueous environments.

9.2.8. Amine Corrosion


This mechanism of corrosion refers to the general and/or localized corrosion principally

on carbon steel in amine treating processes. The corrosion is not caused by the amine itself, but

results from dissolved acid gases, amine degradation products, Heat Stable Amine Salts, and

other containments. Mitigation strategies included upgrading from carbon steel to 300 Series SS

or other corrosion resistant materials when possible. The most effective way to control corrosion

is the proper operation of the amine system with particular attention to acid gas loading.

9.2.9. High Temp H2/H2S Corrosion


The presence of hydrogen in H2S-containing hydrocarbon streams increases the severity

of high temperature sulfide corrosion at temperatures above about 260°C. The operating

temperature of the syngas feed is very low (<65°C), therefore this corrosion mechanism will not

be applicable for the CO2 Removal Unit.

9.3. Carbon Steel


Corrosion in amine units has typically been higher for amine units that remove primarily

CO2, as opposed to other units that remove hydrogen sulfide or mixtures of hydrogen sulfide (14).

This is because hydrogen sulfide forms a protective iron sulfide scales on carbon steel.

Nevertheless, carbon steel has been widely used in locations with mild processing conditions and

low acid gas concentration, such as lean amine streams. This is due to its affordability and

H-63
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

relatively high strength in comparison to other materials of choice. Thus, ASTM A106 Grade B

carbon steel was selected for these streams. To reduce chances of cracking or corrosion in carbon

steel piping, the velocity of amine streams is recommended to be kept below 1.8 m/s (14). For

MDEA units, PWHT is also recommended for all carbon steel equipment exposed to amine service

temperatures above 82°C.

9.3.1. Killed Carbon Steel


ASTM A333 Grade 6 killed carbon steel was selected for stream 83 due to the operating

temperature of the stream being 113.6°C in the base case. Killed carbon steel is steel manufactured

by a specific process to reduce voids in the material where hydrogen can collect and react to form

hydrogen gas and cause hydrogen blisters or hydrogen induced cracking. Kill carbon steel is more

resistant to these types of corrosion damage than conventional carbon steel.

9.4. Stainless Steel


Low-carbon and stabilized grades of austenitic steels have successfully been used in areas

of high corrosion rates due to their high strength and corrosion resistance over a wide range of

operating conditions (14). Types of stainless steel used in literature and historically for MDEA

units were ASTM A358 Type 304L and Type 316L stainless steel. Stainless steel was thus used

for regions of the process that are more prone to corrosion, such as areas with a high acid gas

loading, high velocity, vapour flashing, two-phase flow, and operating temperatures well above

110°C. Type 316L stainless steel has higher corrosion resistance in chloride containing

environments, and was selected over Type 304L stainless steel for areas of the process that

circulated process water or cooling water, which had a high chance of containing trace amounts of

chlorides.

H-64
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

H-65
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

List of References
1. The American Society of Mechanical Engineers. ASME Code for Pressure Piping.

[Standard] New York : s.n., 2016. B31.3.

2. Ulrich, Gael D. and Vasudevan, Palligarnai T. Chemical Engineering Process Design and

Economics: A Practical Guide (Second Edition). Durham : Process (Ulrich) Publishing, 2004. 0-

97087683-2-3.

3. Robert H. Perry, Don W. Green, James O. Maloney. Perry's Chemical Engineering

Handbook, Seventh Edition. [Document] s.l. : McGraw-Hill, 1997.

4. Pick, W. Pipelines, Flow and Line Sizing. [Document] Edmonton : Ch E 464 Winter 2018 -

Chemical Engineering Design I: Module 02 (Lecture 5), 2018.

5. Engineering Toolbox. Ratios of Specific Heat of Gases. Engineering Toolbox. [Online] 2003.

[Cited: April 7, 2019.] https://www.engineeringtoolbox.com/specific-heat-ratio-d_608.html.

6. Church, Len. Line Sizing. [Document] Edmonton : CH E 465 Winter 2019 - Tutorial 12 -

Process Line Sizing and Fluid Flow, 2014.

7. KLM Technology Group. Piping Hydraulics Fluid Flow - Line Sizing and Material

Selection. [Document] 2013.

8. Ludwig, Ernest E. Applied Process Design for Chemical and Petrochemical Plants. s.l. :

Gulf Professional Publishing, 1999.

9. The American Petroleum Institute. Avoiding Environmental Cracking in Amine Units.

[Document] Washington : s.n., 2008. API RP 945.

H-66
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

10. Bruce R. Munson, Donald F. Young, Theodore H. Okiishi, Wade W. Huebsch.

Fundamentals of Fluid Mechanics, Sixth Edition. s.l. : John WIley & Sons, Inc., 2009.

11. Andre G. McDonald, Hugh L. Magande. Introduction to Thermo-Fluids System Design.

s.l. : John Wiley & Sons, 2012.

12. The American Society of Mechanical Engineers. Stainless Steel Pipe. [Standard] New

York : s.n., 2018. B36.19M.

13. The American Society of Mechanical Engineers. Welded and Seamless Wroght Steel Pipe.

[Standard] New York : s.n., 2018. B36.10M.

14. American Petroleum Insititute. Avoiding Environmental Cracking in Amine Units.

[Document] Washington : s.n., 2008. API RP 945.

15. American Petroleum Institute. Damage Mechanisms Affecting Fixed Equipment in the

Refining Industry. [Document] Washington : s.n., 2011. API RP 571.

16. Glocal CCS Institute. Material Selection for Amine Environments. Global CCS Institute.

[Online] [Cited: April 9, 2019.] https://hub.globalccsinstitute.com/publications/corrosion-and-

materials-selection-ccs-systems/73-material-selection-amine-environments.

17. Corrosion and Materials Selection for Amine Service. Rennie, S. s.l. : Materials Forum,

2006, Vol. 30.

18. Predicting and Mitigating Corrosion in Amine Units. Jones, Clayton E., et al. Oklahoma :

Laurance Reid Gas Conditioning Conference, 2015.

H-67
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

19. Perry, Robert H and Green, Don W. Perry's Chemical Engineers' Handbook. 8th. New

York : McGraw-Hill, 2007. 978-0071422949.

20. Engineering Data Book. Gas Processors Suppliers Association. Tulsa : s.n., 2004, Vol. 1

and 2.

21. A Procedure for Preliminary Estimate. Brown, R. s.l. : Chem. Eng., 1978, Vol. 85.

22. Process Heat Transfer. Kern, D. Q. New York : McGraw-Hill Book Company, Inc., 1950.

23. Production & Processing Facilities Tip of the Month. PetroSkills|John M. Campbell. 2015.

H-68
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Appendix I: Heat Exchanger Design


Description
This appendix includes the procedure for the detailed design of a heat exchanger. The

guideline provided by Donald Quentin Kern in Process Heat Transfer (1950) for the design of a

heat exchanger was followed. ASME Boiler & Pressure Vessel Code Section VIII Division 1,

ASME B31.3 Process Piping, and Standards of Tubular Exchanger Manufacturers Association

were also referenced.

As part of the 125% capacity increase, an additional heat exchanger, E-85A/B, was

proposed to increase the cooling of the lean amine stream as it enters the CO2 Absorber. A

completed design specification sheet for the heat exchanger is included with calculations and

justification supporting how values were chosen.

Table of Contents
1. Preliminary Heat Exchanger Design Considerations .............................................................. I-1
2. Heat Exchanger Type .............................................................................................................. I-2
3. Fouling and Corrosion Concerns ............................................................................................ I-2
3.1. Placement of Fluid........................................................................................................... I-2
3.2. Material Specification ..................................................................................................... I-3
3.3. Fluid Flow ....................................................................................................................... I-3
4. Calculations............................................................................................................................. I-3
4.1. Process Conditions .......................................................................................................... I-3
4.1. Heat Balance.................................................................................................................... I-4
4.2. True Temperature Difference .......................................................................................... I-5
4.3. Iteration Method .............................................................................................................. I-6
4.3.1. Tube Side: Film Coefficient Calculation................................................................... I-7
4.3.2. Tube Side: Pressure Drop Calculation ...................................................................... I-9
4.3.3. Shell Side: Film Coefficient Calculation................................................................... I-9

i
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

4.3.4. Shell Side: Pressure Drop Calculation .................................................................... I-10


4.4. Clean Overall Coefficient .............................................................................................. I-11
4.5. Dirt Factor ..................................................................................................................... I-11
4.6. Overall Heat Transfer Coefficient ................................................................................. I-12
5. Heat Exchanger Specification Sheet ..................................................................................... I-12
List of References ....................................................................................................................... I-14

ii
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

1. Preliminary Heat Exchanger Design Considerations


Heat Concerns and
Knowns
Exchanger Unknowns
The purpose of the heat exchanger E-85 is to cool down lean
amine before it enters the CO2 Absorber to increase CO2
absorption. Lean amine leaving the LP Flash Stripper is cooled
Purpose
by the semilean amine stream and further cooled by an air
cooler. Before entering the absorber, this exchanger will fulfill
additional cooling required to increase absorption.
The lean amine is regenerated in the LP Flash Stripper, no
reaction occurs as it travels to the heat exchanger. Cooling of
Process
this stream does not cause a reaction. Lean amine will be cooled
Chemistry
by utility water with only sensible heat. No phase change will
occur.
The process side will operate at 4099 kPa[g] and 304.8 - 307.9
Process
K. The utility side will operate at 500 kPa[g] and 297.2 - 304.2
Conditions
K.
Cooling water will be used as the utility stream. In the scope of
Utilities this project, additional utility requirement is assumed to be
Required supplied by existing infrastructure. Building a new facility will
not be required.
U will be determined by
Duty and Only sensible heat will be transferred. The heat duty Q will be hand calculations. A
Area 350 kW and the UA will be 50.18 kW/K. will be calculated once
this is done.
The most common heat exchangers used are shell and tube, air
coolers, and plate and frame. Since plate and frame exchangers
foul quickly, shell and tube heat exchangers are the most
suitable when using cooling water to cool process stream. Using
the heat exchanger selection chart (Ludwig), U-Tube/U-Bundle Need effective area A
is the most suitable type. Although our streams are all below required to justify heat
Possible
315 K, this type can handle high temperature differentials which exchanger type. Other
Exchanger
could be possible if insufficient cooling occurs in upstream information such as P,
Types
exchangers. It can easily be cleaned on the tube side as well as T, Q can also be used to
the shell side and can be installed vertically or horizontally help in selection.
depending on the space available. Fixed tube sheet is also an
option but is more limited in terms of fouling service and
cleanability on the shell side. It also does not allow for thermal
expansion.
Turbulent Turbulence is not required. In terms of corrosion, higher
Calculate velocity.
Flow velocities and turbulence will cause localized thickness losses.
Amine corrosion due to dissolved CO2 and H2S can affect
carbon steel (300 Series SS are highly resistant). Additionally,
low alloy steels subjected to tensile stress can undergo amine
Corrosion
stress corrosion cracking. If an exchanger tube leaks, water will
mix with the lean amine solution entering the CO2 absorber and
the stream will not be sufficiently cooled. This will affect the

I-1
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

ability of the tower to absorb CO2 from the inlet Syngas stream.
Carbonic avid corrosion must also be considered.
Cooling water will not be completely rid of
contaminants/particles when circulated throughout the process.
Fouling This can lead to scaling in the tube walls and cause fouling.
Cooling water will be passed on the tube side as this side is
easier to clean.
Research PSV
Safety
requirements.
Potential health effects on personnel exposed to MDEA. Vessel
Risk
could be over-pressurized by upstream lean amine pump.
Type of
Heat CEU
Exchanger

2. Heat Exchanger Type


The most common types of heat exchangers in industry include shell and tube, plate and frame,

and kettle reboilers depending on the service needed. A shell and tube heat exchanger was chosen

since its wide variety can cater to the specific needs of the lean amine and cooling water heat

exchange. To mitigate thermal stress and to allow for maintenance, removable U-tube bundles

were chosen. Based on the temperatures desired, the number of tube and shell passes is determined,

and the type of heat exchanger specified. Using the analysis outlined below, the 2-4 shell and tube

heat exchanger was chosen which was achieved by using two 1-2 CEU shell and tube heat

exchanger.

3. Fouling and Corrosion Concerns


3.1. Placement of Fluid
The heat exchanger will be exchanging heat between lean amine regenerated from the LP

Flash Stripper and cooling water. The lean amine must be cooled before entering the CO2 Absorber

to improve absorption. Cooling water will be placed on the tube side of the heat exchanger due to

I-2
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

fouling concerns. This is because of the mineral content of the cooling water and the tendency of

scaling from cooling water use. Since the lean amine is less of a fouling concern, it will be placed

in the shell.

3.2. Material Specification


The heat exchanger material was selected with considerations from API 571: Damage

Mechanisms Affecting Fixed Equipment in the Refining Industry. The mechanisms considered

include amine corrosion, amine stress corrosion cracking, and carbon dioxide corrosion. However,

since the lean amine has low carbon dioxide content, carbon steel will suffice for the shell side.

Stainless steel was chosen for the tubes to account for increased mineral content of the water that

could cause corrosion and to combat the effects of the contacting lean amine. Even if stainless

steel is more expensive, this will make the tubes more resistant to corrosion.

3.3. Fluid Flow


Turbulent flow is not required in this service. In terms of corrosion, higher velocities and

turbulence will cause localized thickness losses. On the other hand, lower velocities result in

stagnant fluids which encourage fouling. Due to the effects of flow on the fouling and corrosion

mechanisms involved, the velocities were calculated and verified to be in the acceptable range.

4. Calculations
4.1. Process Conditions
In this heat exchanger, the lean mine is the hot fluid while cooling water is the cold fluid.

English Engineering Units will be used in this analysis to be consistent with the procedure and

correlations provided by Kern (1950). The final parameters will be converted to SI Units. The

following process conditions were obtained for both fluids:

I-3
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Hot Fluid: Lean Amine


Inlet Temperature, T1 °F 104
Outlet Temperature, T2 °F 94
Mass flow rate, W lb/hr 1356214
Specific Heat Capacity, C BTU/lb/°F 0.92
Specific Gravity, s - 1.04
Dynamic Viscosity, µ lb/ft/hr 8.16
Thermal Conductivity, k BTU/hr/ft2/(°F/ft) 0.22
2
Dirt Factor, Rd (hr*ft *°F)/BTU 0.002
Allowable Pressure Drop, ΔP psi 10

Cold Fluid: Cooling Water


Inlet Temperature, t1 °F 75
Outlet Temperature, t2 °F 95
Mass flow rate, w lb/hr 598708
Specific Heat Capacity, c BTU/lb/°F 1.00
Specific Gravity, s - 1.00
Dynamic Viscosity, µ lb/ft/hr 2.03
Thermal Conductivity, k BTU/hr/ft2/(°F/ft) 0.35
Dirt Factor, Rd (hr*ft2*°F)/BTU 0.001
Allowable Pressure Drop, ΔP psi 10

Note that these properties are taken at the average temperature of each fluid since temperatures at

the tube wall are not known.

4.1. Heat Balance


The total heat duty exchanged is calculated as:

𝑄 = 𝑊𝐶(𝑇1 − 𝑇2 ) = 𝑤𝑐(𝑡2 − 𝑡1 )

Lean Amine Duty BTU/hr 11831133


Cooling Water Duty BTU/hr 11837019
Simulation Duty BTU/hr 11830844

I-4
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

There is minimal discrepancy between the two fluid duties. The simulated value will be used for

design.

4.2. True Temperature Difference


Assuming a 1-2 shell and tube heat exchanger configuration:

(𝑇1 − 𝑡2 ) − (𝑇2 − 𝑡1 )
𝐿𝑀𝑇𝐷 =
(𝑇 − 𝑡2 )
𝑙𝑛 1
(𝑇2 − 𝑡1 )

𝑇1 − 𝑇2
𝑅=
𝑡2 − 𝑡1

𝑡2 − 𝑡1
𝑆=
𝑇1 − 𝑡1

𝛥𝑡 = 𝐿𝑀𝑇𝐷 × 𝐹𝑇

LMTD °F 13.49
R - 0.48
S - 0.69
Correction Factor, FT - 0.74
True Temperature Difference, Δt °F 9.98

However, since the correction factor is below 0.75, the desired heat duty will be difficult to

achieve in a 1-2 shell and tube heat exchanger. Considering a 2-4 exchanger, the new values are:

LMTD °F 13.49
R - 0.48
S - 0.69
Correction Factor, FT - 0.96
True Temperature Difference, Δt °F 12.88

I-5
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Given the heat duty required for this service, an exchanger with 2 shell passes and 4 tube passes

may be too large. It is good practice to design two smaller units than one large exchanger. For

this reason, two 1-2 heat exchangers will be designed and connected in series. The total heat

exchanger duty will be divided equally between the exchangers.

4.3. Iteration Method


A trial and error approach is used with the following steps:

a) Assume a tentative overall heat transfer coefficient, UD and compute the total surface

area, A=Q/(UD Δt). Determine the corresponding number of tubes.

Duty, Q BTU/hr 5915422


Overall Coefficient, UD BTU/hr/ft2/°F 105
True Temperature Difference, Δt °F 12.88
Heat Transfer Surface, A ft2 4374.41

Initial tube characteristics are assumed, and the number of tubes calculated as:

𝐴
𝑁𝑇 =
𝜋𝐷𝑜 𝐿

BWG - 11
Outside Diameter, Do in 0.75
Inside Diameter, Di in 0.51
Tube Wall Thickness, Δx in 0.12
Length, L ft 16
Number of Passes, n - 2
Pitch (Square), PT in 1.00
Clearance between tubes, C' in 0.25
Flow area per tube, a't in2 0.204
Number of Tubes, NT - 1392

I-6
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

b) Assume a number of tube passes for the pressure drop allowed. Select an exchanger for

the nearest number of tubes.

As stated, the heat exchanger will have 2 tube passes. For a 0.75 in tube outside diameter

and 1 in square pitch, the following was obtained:

Shell Internal Diameter, ID in 45


Number of Tubes, NT - 1436

c) Correct the tentative UD to the actual surface of tubes.

The corrected values based on the new number of tubes are:

Heat Transfer Surface, A ft2 4511


Overall Coefficient, UD BTU/hr/ft2/°F 102

The performance calculation for the film coefficients starts with the tube side first. If the film

coefficient is greater than UD and the pressure drop is not exceeded, analysis moves on to the

shell side.

4.3.1. Tube Side: Film Coefficient Calculation


Due to fouling concerns, cooling water will run in the tube side and lean amine on the

shell side. Therefore, cooling water properties will be used for tube side calculations and lean

amine properties will be used to calculate shell side values.

The flow area as is calculated as:

𝑁𝑡 𝑎′𝑡
𝑎𝑡 =
144𝑛

The mass velocity is

I-7
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

𝑤
𝐺𝑡 =
𝑎𝑡

The Reynolds number is

𝐷𝑖 𝐺𝑡
𝑅𝑒𝑡 =
µ

The factor for heat transfer, jH, is obtained from Kern (1950). Since the properties are taken at an

average temperature, no correction factors will be necessary. The heat transfer coefficient is

determined as:

𝑘 𝑐µ 1
ℎ𝑖 = 𝑗𝐻 ( )3
𝐷𝑖 𝑘

Based on the outside diameter:

𝐷𝑖
ℎ𝑖𝑜 = ℎ𝑖
𝐷𝑜

The following values are obtained:

Tube side area, at ft2 1.02


Tube mass velocity, Gt lb/hr/ft2 588604
Factor for heat transfer, jH - 44
2
Heat transfer coefficient, hi BTU/hr/ft /°F 655
Heat transfer coefficient, hio BTU/hr/ft2/°F 446

Since the calculated coefficient is higher than UD, analysis can move on to the pressure drop.

I-8
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

4.3.2. Tube Side: Pressure Drop Calculation


For the Reynolds number obtained in the previous section, the friction factor f is obtained

from correlations in Kern (1950). The tube pressure drop is:

𝑓𝐺𝑡 2 𝐿𝑛
∆𝑃𝑡 =
5.22 × 1010 𝐷𝑖 𝑠

Using the tube mass velocity, the term V2/2g’ is obtained and

4𝑛𝑉 2
∆𝑃𝑟 =
𝑠2𝑔′

The total pressure drop is

∆𝑃𝑇 = ∆𝑃𝑡 + ∆𝑃𝑟

The total pressure drop for 2 tube passes is 1.65 psi. For 4 tube passes, the pressure drop is 3.3

psi.

Friction factor, f ft2/in2 0.000255


Tube pressure drop, ΔPt psi 1.28
2
V /2g' psi 0.05
Pressure drop return, ΔPr psi 0.37
Total pressure drop, ΔPT psi 1.65
4.3.3. Shell Side: Film Coefficient Calculation
After tube side requirements are fulfilled, the shell side is examined. Using an assumed

baffle spacing, the flow area is determined:

𝐼𝐷 × 𝐶′𝐵
𝑎𝑠 =
144𝑃𝑇

The mass velocity on the shell side is

I-9
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

𝑊
𝐺𝑠 =
𝑎𝑠

The Reynolds number on the shell side is

𝐷𝑒 𝐺𝑠
𝑅𝑒𝑠 =
µ

Where De is the equivalent diameter. The factor for heat transfer, jH, is obtained from Kern

(1950). Since the properties are taken at an average temperature, no correction factors will be

necessary. The heat transfer coefficient is determined as:

𝑘 𝑐µ 1
ℎ𝑜 = 𝑗𝐻 ( )3
𝐷𝑒 𝑘

Assumed segmental baffle cut % 25


Assumed baffle spacing in 36
Shell side area, as ft2 2.81
Shell mass velocity, Gs lb/hr/ft2 482209
Reynolds number, Res - 4681
Equivalent Diameter, De ft 0.0792
Factor for heat transfer, jH - 37
2
Heat transfer coefficient, ho BTU/hr/ft /°F 335

4.3.4. Shell Side: Pressure Drop Calculation


Using the shell side Reynolds number, the corresponding friction factor f is obtained from Kern

(1950). The number of crosses in the shell is determined by

12𝐿
𝑁+1=
𝐵

And the pressure drop on the shell side is

I-10
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

𝑓𝐺𝑠 2 𝐷𝑒 (𝑁 + 1)
∆𝑃𝑠 =
5.22 × 1010 𝐷𝑒 𝑠

The pressure drop for 1 shell pass is 2.93 psi. For 2 shell passes, the shell side pressure drop is

5.86 psi.

Number of crosses, N+1 - 6


Pressure drop, ΔPs psi 2.93

Since the film coefficient and pressure drop for each side are satisfactory, iteration is concluded.

4.4. Clean Overall Coefficient


The clean overall coefficient is calculated as:

ℎ𝑖𝑜 ℎ𝑜
𝑈𝑐 =
ℎ𝑖𝑜 + ℎ𝑜

Clean overall coefficient, Uc BTU/hr/ft2/°F 191

4.5. Dirt Factor


Aside from the resistances on the shell and tube side from the lean amine and cooling

water respectively, the resistance from the tube wall, Rd,w, is also considered.

∆𝑥
𝑅𝑑,𝑤 =
𝑘

Thermal Conductivity of Tube Material, k Btu/hr/ft/°F 9.40


Wall resistance, Rd,w (hr*ft2*°F)/BTU 0.001
Total Dirt Factor Required, Rd (hr*ft2*°F)/BTU 0.004

I-11
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

The actual dirt factor is calculated as

𝑈𝑐 − 𝑈𝐷
𝑅𝑑 =
𝑈𝑐 𝑈𝐷

Calculated dirt factor, Rd (hr*ft2*°F)/BTU 0.0046

Since the actual dirt factor is greater than required, the designed heat exchanger is sufficient for

service.

4.6. Overall Heat Transfer Coefficient


In the instance where an actual dirt factor equal to the minimum dirt factor is desired

(Rd=0.004), the overall heat transfer coefficient required is calculated by

1 1 1
= + + 𝑅𝑑
𝑈𝐷 ℎ𝑜 ℎ𝑖𝑜

Overall coefficient, UD BTU/hr/ft2/°F 108

5. Heat Exchanger Specification Sheet


The design conditions including physical size of the heat exchanger as well as the design

pressure and temperature are laid out in the specification sheet below. Design conditions were

determined using ASME Code Section VIII Division 1 and ASME B31.3 Process Piping.

I-12
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

SHELL & TUBE HEAT EXCHANGER DATA SHEET

CLIENT CANADIAN NATURAL RESOURCES LTD. ITEM NO. E-85


PROJECT CO2 RECOVERY PLANT REVAMP SERVICE LEAN AMINE COOLER
SIZE 1143--4877 mm TYPE CEU HORIZONTAL CONNECTED IN 2 SERIES
SHELLS / UNIT 2 SURFACE / SHELL 406.5 m2
PERFORMANCE
IN SHELL SIDE OUT IN TUBE SIDE OUT
FLUID CIRCULATED LEAN AMINE COOLING WATER
TOTAL FLUID kg / hr 615168 271570
VAPOUR kg / hr
LIQUID kg / hr 615168 615168 271570 271570
NONCONDENSABLE kg / hr
TEMPERATURE ℃ 40 35 24 35
DENSITY - LIQUID / VAPOUR kg/m3 1033 1036 997 993
VISCOSITY - LIQUID / VAPOUR cP 3 4 1 1
MOLE WT kg/kmol 28.18 28.18 18.02 18.02
SPECIFIC HEAT - LIQUID/VAPOUR kJ / (kg℃) 3840 3817 4184 4177
THERMAL CONDUCTIVITY - LIQUID VAPOUR W / (m℃) 0.39 0.38 0.60 0.62
LATENT HEAT kJ / kG
INLET PRESSURE kPa(g) 4099 1000
VELOCITY m/ s 0.6 0.8
PRESSURE DROP kPa ALLOW 69 CALC 20 ALLOW 69 CALC 23
FOULING RESISTANCE (m2℃) / W 0.00035 0.00018
HEAT EXCHANGED kW 3467 MTD CORRECTED (℃) 12.9
TRANSFER RATE W / (m2℃) SERVICE 611 CLEAN 1086
DESIGN - MATERIAL - CONSTRUCTION
DESIGN / TEST PRESSURE kPa(g) 5708 1100
DESIGN TEMPERATURE ℃ 149 93
NO. PASSES PER SHELL 1 2
CORROSION ALLOWANCE mm 3
CONNECTIONS INLET 355.6 254
SIZE & OUTLET 355.6 254
RATING INTERMEDIATE
TUBES NO. 1436 OD (mm) 19 THICKNESS (mm) 3 LENGTH (m) 4.9
TUBE TYPE PLAIN MATERIAL SS 316L PITCH (mm) 25 PITCH TYPE SQUARE PITCH ANGLE
SHELL CS ID (mm) 1143 OD (mm) 1200 SHELL COVER CS
CHANNEL OR BONNET CS CHANNEL COVER CS
TUBESHEET STATIONARY SS 316L TUBESHEET FLOATING
FLOATING HEAD COVER IMPINGEMENT PROTECTION NONE
BAFFLES-CROSS CS TYPE SINGLE-SEGMENTAL CUT (% DIAM) 25 SPACING (C / C) (mm) 914.4
BAFFLES-LONG CS SEAL TYPE
SUPPORTS-TUBE CS U BEND SS 316L TYPE
BYPASS SEAL ARRANGEMENT TUBESHEET JOINT
EXPANSION JOINT TYPE
pV2 - INLET NOZZLE BUNDLE ENTRANCE BUNDLE EXIT
GASKETS SHELL SIDE TUBE SIDE
FLOATING HEAD
CODE REQUIREMENTS ASME Code Section VIII Division 1 TEMA CLASS R - refinery service
WEIGHT/SHELL (kg) FILLED WITH WATER (kg) BUNDLE (kg)
REMARKS: Resistance due to tube wall included in analysis (0.000187 (m2℃) / W).

REV DATE BY
0 03/23/2019 Nympha Escobar
OKANE ENGINEERING

I-13
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

List of References
1. Process Heat Transfer. Kern, D. Q. New York : McGraw-Hill Book Company, Inc., 1950.

2. Standards of the Tubular Exchanger Manufacturers Association. Tubular Exchanger

Manufactureres Association, Inc. New York : Tubular Exchanger Manufacturers Association,

2007, Vol. Ninth Edition.

3. ASME Boiler & Pressure Vessel Code. The Americal Society of Mechanical Engineers.

New York : The Americal Society of Mechanical Engineers, 2009.

4. ASME B31.3 Process Piping. The Americal Society of Mechanical Engineers. New York :

The Americal Society of Mechanical Engineers, 2017.

5. Damage Mechanisms Affecting Fixed Equipment in the Refining Industry. American

Petroleum Institute. Washington : API Publishing Services, 2010, Vol. Second Edition. API RP

571.

I-14
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Appendix J: Economics
Description
This appendix contains all the information relating to the project economics, and outlines

the detailed calculations and assumptions made to obtain the fixed capital expenditure, operating

costs, discounted cash flows, and sensitivity analyses. Unless otherwise specified, all prices and

costs are expressed in Canadian dollars (C$).

Table of Contents
1. Economic Assumptions ......................................................................................................... J-1
2. Fixed Capital Expenditure ..................................................................................................... J-1
2.1. Equipment Purchase and Bare Module Costs ................................................................ J-1
2.1.1. Lean/Rich Amine Exchanger E-81C ........................................................................ J-2
2.1.2. Lean Amine Cooler E-85A/B ................................................................................... J-4
2.1.3. Reflux Vessel C-83 .................................................................................................. J-6
2.1.4. Absorber Overhead K.O. Drum C-87 ...................................................................... J-7
2.2. DFL Factors .................................................................................................................... J-8
2.3. Total Fixed Capital Expenditure .................................................................................... J-1
3. Working Capital Expenditure ................................................................................................ J-2
4. Operating Costs ...................................................................................................................... J-3
4.1. Onstream Time ............................................................................................................... J-3
4.2. Operating Labour ........................................................................................................... J-3
4.3. Utilities ........................................................................................................................... J-4
4.1. Remaining Expenses ...................................................................................................... J-6
5. Discounted Cash Flows.......................................................................................................... J-8
6. Sensitivity Analyses ............................................................................................................. J-17
6.1. 112% Case .................................................................................................................... J-17
6.2. 125% Case .................................................................................................................... J-18
7. References ............................................................................................................................ J-19

i
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

1. Economic Assumptions
The economic analysis is based on the additional CO2 being produced from the base case

and assumes all of this extra CO2 is being sold to potential consumers around the Fort McMurray

region. It is also assumed that the infrastructure required to transport the CO2 is already in place.

From the discussions with the client, 50% of the CO2 produced on a molar basis is sent for tailings

treatment, which is a static value of approximately 594,000 mol/h or 26,000 kg/h. This amount of

CO2 being sent to tailings treatment is not accounted for in this analysis since it is only applied to

the existing base CO2 production.

2. Fixed Capital Expenditure


2.1. Equipment Purchase and Bare Module Costs
Table J1 summarizes the equipment purchase costs without adjustments included for

material and pressure factors. Figure J1 displays the purchase cost breakdown in the form of a pie

chart. The purchase costs, material factors, and pressure factors for the heat exchangers and drums

were obtained using Ulrich & Vasudevan costing charts, which are based on the US Gulf Coast

2004 pricing (1). These costs were adjusted to account for inflation and currency, resulting in an

appropriate value in $CAD for 2019. An exchange rate of 1.33 was used to convert from $USD to

$CAD (2). The target Chemical Engineering Plant Cost Index (CEPCI) used was 616.4 from

November 2018, with a base reference of 400 from 2004 (3).

Table J1: Purchase Cost of each Equipment

J-1
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Equipment Purchase Cost ($MM)


E-81C $0.05
E-85A/B $0.06
C-83 $0.04
C-87 $0.02
C-80 IMTP #25 Random Packing $0.36
C-82 IMTP #40 Random Packing $0.52
Total Equipment Purchase Cost $1.04

Heat Exchangers,
Total Purchase
$.11 MM
Cost:

Vessels,
$.06 MM

Packing,
$.88 MM

Figure J1: Equipment Purchase Cost Breakdown

2.1.1. Lean/Rich Amine Exchanger E-81C


An additional E-81 exchanger will be added to facilitate further cooling needed for the

125% capacity increase. The calculated heat exchange area is 595 m2. This is a flat plate heat

exchanger, so the equipment purchase cost is obtained from Figure 5.39 in Ulrich & Vasudevan:

𝐶𝑃 = $50,000 𝑈𝑆𝐷, 𝑈𝑆𝐺𝐶, 2004

This cost assumes the equipment uses carbon steel as the material and operates at relatively low

pressures. To adjust for material and pressure factors, a bare module factor must be applied. E-

J-2
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

81C uses stainless steel SS316 on both the shell and tube sides due to the corrosivity of the amine

solutions. From Table 5.39, the material factor for this exchanger is:

𝐹𝑀 = 3

Figure 5.37 is then used to obtain the pressure factor needed alongside the material factor to obtain

the bare module factor. The pressure factor of flat and spiral plate heat exchangers is 1 regardless

of the operating pressure:

𝐹𝑃 = 1

Using the above material and pressure factors, and the bare module factor is obtained from Figure

5.38:

𝑎
𝐹𝐵𝑀 = 5.8

Applying this factor to the equipment purchase cost, the bare module cost of E-81C is calculated

as:

𝑎
𝐶𝐵𝑀 = 𝐶𝑃 ∙ 𝐹𝐵𝑀 = ($50,000)(5.8) = $290,000 𝑈𝑆𝐷, 𝑈𝑆𝐺𝐶, 2004

This value is then adjusted for time and currency factors to obtain the bare module cost today in

CAD. The target CEPCI is November 2018 with a value of 616.4, and the base is the January 2004

CEPCI of 400. The current conversion rate from USD to CAD is 1.33. Applying the time and

currency factors gives a bare module cost of:

616.4
𝐶𝐵𝑀 = ($290,000 𝑈𝑆𝐷, 𝑈𝑆𝐺𝐶, 2004) ( ) (1.33) = $594,364 𝐶𝐴𝐷, 𝐴𝐵, 2018
400

J-3
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

The bare module factor must then be adjusted for DFL considerations. The detailed calculations

for this are contained in Section 1.2 DFL Factors. The bare module factor adjusted for DFL is

calculated to be:

𝑎
𝐹𝐵𝑀,𝐷𝐹𝐿 𝑎𝑑𝑗𝑢𝑠𝑡𝑒𝑑 = 11.07

Applying this DFL factor along with time and currency factors to the equipment purchase cost

results in the adjusted bare module cost of E-81C:

𝑎 616.4
𝐶𝐵𝑀,𝑎𝑑𝑗𝑢𝑠𝑡𝑒𝑑 = 𝐶𝑃 ∙ 𝐹𝐵𝑀,𝐷𝐹𝐿 𝑎𝑑𝑗𝑢𝑠𝑡𝑒𝑑 = ($50,000)(11.07) ( ) (1.33)
400

= $1,134,692 𝐶𝐴𝐷, 𝐴𝐵, 2018

2.1.2. Lean Amine Cooler E-85A/B


A new trim cooler will be added downstream of the E-84 air cooler to facilitate further

cooling of the regenerated lean amine solution before it enters the C-80 CO2 Absorber. This

exchanger is designed as two TEMA designated CEU type shell and tube heat exchangers arranged

in series. CEU exchangers utilize a U-tube as the rear end head type. The total calculated heat

exchanger area is 815.41 m2. The exchanger is split into two equal areas of 408 m2 each and the

cost of each area is added together to obtain the cost of E-85A/B. From Figure 5.36 in Ulrich &

Vasudevan, the equipment purchase cost is:

𝐶𝑃 = 2($30,000) = $60,000 𝑈𝑆𝐷, 𝑈𝑆𝐺𝐶, 2004

E-85A/B uses carbon steel (CS) on the shell side and stainless steel (SS316) on the tube side. From

Table 5.39, the material factor for this exchanger is:

𝐹𝑀 = 1.7

J-4
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

E-80 operates using a shell side inlet pressure of 4099 kPa or 40.99 barg and a tube side inlet

pressure of 448 kPa or 4.48 barg, so the heat exchanger operates at high pressure on the shell side

alone. This corresponds to a pressure factor of:

𝐹𝑃 = 1.13

Using the above material and pressure factors, and the bare module factor is obtained from Figure

5.38:

𝑎
𝐹𝐵𝑀 = 4.5

Applying this factor to the equipment purchase cost, the bare module cost of E-85A/B is calculated

as:

𝑎
𝐶𝐵𝑀 = 𝐶𝑃 ∙ 𝐹𝐵𝑀 = (60,000)(4.5) = $270,000 𝑈𝑆𝐷, 𝑈𝑆𝐺𝐶, 2004

Applying the time and currency factors gives a bare module cost of:

616.4
𝐶𝐵𝑀 = ($270,000 𝑈𝑆𝐷, 𝑈𝑆𝐺𝐶, 2004) ( ) (1.33) = $553,373 𝐶𝐴𝐷, 𝐴𝐵, 2018
400

The bare module factor adjusted for DFL is calculated to be:

𝑎
𝐹𝐵𝑀,𝐷𝐹𝐿 𝑎𝑑𝑗𝑢𝑠𝑡𝑒𝑑 = 8.64

Applying this DFL factor along with time and currency factors to the equipment purchase cost

results in the adjusted bare module cost of E-85A/B:

𝑎 616.4
𝐶𝐵𝑀,𝑎𝑑𝑗𝑢𝑠𝑡𝑒𝑑 = 𝐶𝑃 ∙ 𝐹𝐵𝑀,𝐷𝐹𝐿 𝑎𝑑𝑗𝑢𝑠𝑡𝑒𝑑 = ($60,000)(8.64) ( ) (1.33)
400

= $1,061,950 𝐶𝐴𝐷, 𝐴𝐵, 2018

J-5
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

2.1.3. Reflux Vessel C-83


The C-83 Reflux Vessel downstream of the C-82 LP Flash Stripper is resized and will

replace the existing vessel to accommodate the 125% capacity increase. This is a vertically

oriented vessel with a height and inside diameter of 7.5 m and 2.5 m, respectively, calculated using

the Sauders Brown method. From Figure 5.44 in Ulrich & Vasudevan, the equipment purchase

cost is:

𝐶𝑃 = $38,000 𝑈𝑆𝐷, 𝑈𝑆𝐺𝐶, 2004

The material of this vessel is stainless steel SS 304L. Table 5.45 gives a material factor of:

𝐹𝑀 = 4

The reflux vessel operates with an inlet pressure of 24 kPa or 0.24 barg. Figure 5.45 gives a

pressure factor of:

𝐹𝑃 = 1.25

Using the above material and pressure factors, and the bare module factor is obtained from Figure

5.46:

𝑎
𝐹𝐵𝑀 = 11.2

Applying this factor to the equipment purchase cost, the bare module cost of C-83 is calculated as:

𝑎
𝐶𝐵𝑀 = 𝐶𝑃 ∙ 𝐹𝐵𝑀 = (38,000)(11.2) = $425,600 𝑈𝑆𝐷, 𝑈𝑆𝐺𝐶, 2004

Applying the time and currency factors gives a bare module cost of:

616.4
𝐶𝐵𝑀 = ($425,600 𝑈𝑆𝐷, 𝑈𝑆𝐺𝐶, 2004) ( ) (1.33) = $872,280 𝐶𝐴𝐷, 𝐴𝐵, 2018
400

J-6
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

The bare module factor adjusted for DFL is calculated to be:

𝑎
𝐹𝐵𝑀,𝐷𝐹𝐿 𝑎𝑑𝑗𝑢𝑠𝑡𝑒𝑑 = 23.25

Applying this DFL factor along with time and currency factors to the equipment purchase cost

results in the adjusted bare module cost of C-83:

𝑎 616.4
𝐶𝐵𝑀,𝑎𝑑𝑗𝑢𝑠𝑡𝑒𝑑 = 𝐶𝑃 ∙ 𝐹𝐵𝑀,𝐷𝐹𝐿 𝑎𝑑𝑗𝑢𝑠𝑡𝑒𝑑 = ($38,000)(23.25) ( ) (1.33)
400

= $1,810,920 𝐶𝐴𝐷, 𝐴𝐵, 2018

2.1.4. Absorber Overhead K.O. Drum C-87


The C-87 Absorber Overhead K.O. Drum downstream of the C-80 CO2 Absorber is resized

and will replace the existing vessel to accommodate the 125% capacity increase. This is a vertically

oriented vessel with a GPSA calculated height and inside diameter of 4.8 m and 1.6 m,

respectively. From Figure 5.44 in Ulrich & Vasudevan, the equipment purchase cost is:

𝐶𝑃 = $18,000 𝑈𝑆𝐷, 𝑈𝑆𝐺𝐶, 2004

The material of this vessel is carbon steel. Table 5.45 gives a material factor of:

𝐹𝑀 = 1

The reflux vessel operates with inlet and outlet pressures of 3249 kPa or 32.49 barg. Figure 5.45

gives a pressure factor of:

𝐹𝑃 = 2.8

Using the above material and pressure factors, and the bare module factor is obtained from Figure

5.46:

J-7
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

𝑎
𝐹𝐵𝑀 = 7.5

Applying this factor to the equipment purchase cost, the bare module cost of C-87 is calculated as:

𝑎
𝐶𝐵𝑀 = 𝐶𝑃 ∙ 𝐹𝐵𝑀 = (18,000)(7.5) = $135,000 𝑈𝑆𝐷, 𝑈𝑆𝐺𝐶, 2004

Applying the time and currency factors gives a bare module cost of:

616.4
𝐶𝐵𝑀 = ($135,000 𝑈𝑆𝐷, 𝑈𝑆𝐺𝐶, 2004) ( ) (1.33) = $276,687 𝐶𝐴𝐷, 𝐴𝐵, 2018
400

The bare module factor adjusted for DFL is calculated to be:

𝑎
𝐹𝐵𝑀,𝐷𝐹𝐿 𝑎𝑑𝑗𝑢𝑠𝑡𝑒𝑑 = 15.64

Applying this DFL factor along with time and currency factors to the equipment purchase cost

results in the adjusted bare module cost of C-87:

𝑎 616.4
𝐶𝐵𝑀,𝑎𝑑𝑗𝑢𝑠𝑡𝑒𝑑 = 𝐶𝑃 ∙ 𝐹𝐵𝑀,𝐷𝐹𝐿 𝑎𝑑𝑗𝑢𝑠𝑡𝑒𝑑 = ($18,000)(15.64) ( ) (1.33)
400

= $576,860 𝐶𝐴𝐷, 𝐴𝐵, 2018

2.2. DFL Factors


This section will show the sample DFL calculations for the E-81C Lean/Rich Amine

Exchanger. Table J3 summarizes all equipment costs accounted for DFL. The initial DFL and bare

module factors for each type of equipment are taken from Table 9-13 in Guthrie (1969) (4). Table

G2 provides the purchase cost and DFL summary for all pieces of equipment. Since Guthrie (1969)

does not provide DFL data for the IMTP random packing, an assumed factor of 0.05 was used. For

E-80, the basis factors for a shell and tube heat exchanger are chosen:

𝑐𝑠
𝐹𝐵𝑀 = 3.37

J-8
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

𝐷𝐹𝐿𝐺𝑢𝑡ℎ𝑟𝑖𝑒 = 0.63

These values use a basis of carbon steel material unadjusted for high pressure operations. Thus,

material and pressure adjustments must be made by first obtaining the bare module factor from

Ulrich & Vasudevan (2004):

𝑎
𝐹𝐵𝑀 = 5.8

Using the above bare module factors, the material and pressure adjusted DFL factor is:

𝑎
𝐹𝐵𝑀 5.8
𝐷𝐹𝐿𝑈&𝑉 = 𝐷𝐹𝐿𝐺𝑢𝑡ℎ𝑟𝑖𝑒 × 𝑐𝑠 = 0.63 × = 1.08
𝐹𝐵𝑀 3.37

This is the DFL factor for the US Gulf Coast. Cumulative adjustments are then made to this

value. The DFL adjustment factors and percent applicabilities are shown in Table J2 below:

Table J2: DFL Factor Summary

J-9
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Factor Applicable? % Adjustment % Applicability


Labour Productivity
Alberta Greenfield ✓ Gulf Coast*25% 100%
Fort McMurray ✓ Above*25% 100%
Operating Facility ✓ Above*30% 100%
Facility Turnaround ✓ Above*50% 75%
Winter Work ✓ Above*30% 5%
Indirect Project Expenses
Overhead for DFL ✓ Adjustments*70% N/A
Additions
Scaffolding ✓ Total DFL*25% 100%
Miscellaneous Items
• For Project Cost ✓ Total DFL*30% 100%
<$50M
• For Project Cost ✗ N/A N/A
>$50M
Construction Camp ✓ +0.25 80%
Demolition ✗ N/A N/A

The first adjustment is the Alberta Greenfield factor to account for the effect of location:

𝐷𝐹𝐿𝐴𝐵 𝐺𝑟𝑒𝑒𝑛𝑓𝑖𝑒𝑙𝑑 = 𝐷𝐹𝐿𝑈𝑆𝐺𝐶 × % 𝐴𝑑𝑗𝑢𝑠𝑡𝑚𝑒𝑛𝑡 × % 𝐴𝑝𝑝𝑙𝑖𝑐𝑎𝑏𝑖𝑙𝑖𝑡𝑦 = 1.08 × 1.25 × 1.00

= 1.36

The Fort McMurray factor is then added to account for the construction taking place in the Fort

McMurray region. This is due to the region being a busy industrial area with extensive amounts

of production traffic.

𝐷𝐹𝐿𝐹𝑡 𝑀𝑐𝑀𝑢𝑟𝑟𝑎𝑦 = 𝐷𝐹𝐿𝐴𝐵 𝐺𝑟𝑒𝑒𝑛𝑓𝑖𝑒𝑙𝑑 × % 𝐴𝑑𝑗𝑢𝑠𝑡𝑚𝑒𝑛𝑡 × % 𝐴𝑝𝑝𝑙𝑖𝑐𝑎𝑏𝑖𝑙𝑖𝑡𝑦

= 1.36 × 1.25 × 1.00 = 1.69

J-10
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

The operating facility factor is then added to adjust for the project being Brownfield. There will

be reduced labour productivity due to increased congestion at the site:

𝐷𝐹𝐿𝑂𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔 𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 = 𝐷𝐹𝐿𝐹𝑡 𝑀𝑐𝑀𝑢𝑟𝑟𝑎𝑦 × % 𝐴𝑑𝑗𝑢𝑠𝑡𝑚𝑒𝑛𝑡 × % 𝐴𝑝𝑝𝑙𝑖𝑐𝑎𝑏𝑖𝑙𝑖𝑡𝑦

= 1.69 × 1.30 × 1.00 = 2.20

The facility turnaround factor is then added to account for loss of labour productivity during a

turnaround. Since this is a unit revamp project, the chosen percent applicability was 75%:

𝐷𝐹𝐿𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝑇𝑢𝑟𝑛𝑎𝑟𝑜𝑢𝑛𝑑 = 𝐷𝐹𝐿𝑂𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔 𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 × % 𝐴𝑑𝑗𝑢𝑠𝑡𝑚𝑒𝑛𝑡 × % 𝐴𝑝𝑝𝑙𝑖𝑐𝑎𝑏𝑖𝑙𝑖𝑡𝑦

= 2.20 × 1.50 × 0.75 = 3.03

The winter work factor is then added to account for the loss of labour productivity during the

winter period of November 31 to March 1:

𝐷𝐹𝐿𝑊𝑖𝑛𝑡𝑒𝑟 = 𝐷𝐹𝐿𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝑇𝑢𝑟𝑛𝑎𝑟𝑜𝑢𝑛𝑑 × % 𝐴𝑑𝑗𝑢𝑠𝑡𝑚𝑒𝑛𝑡 × % 𝐴𝑝𝑝𝑙𝑖𝑐𝑎𝑏𝑖𝑙𝑖𝑡𝑦

= 3.03 × 1.30 × 0.05 = 3.07

Once the winter work adjustment has been added, the resultant factor is known as the total DFL

factor. The cumulative adjustments for the indirect project expenses will be performed next. The

DFL additions must be calculated, which is simply the difference between the DFL factor after

the winter work addition and the DFL taken from Ulrich & Vasudevan:

𝐷𝐹𝐿 𝐴𝑑𝑑𝑖𝑡𝑖𝑜𝑛𝑠 = 𝐷𝐹𝐿𝑊𝑖𝑛𝑡𝑒𝑟 − 𝐷𝐹𝐿𝑈&𝑉 = 3.07 − 1.08 = 1.99

The first indirect expense is the overhead for DFL additions:

𝑂𝑣𝑒𝑟ℎ𝑒𝑎𝑑 𝑓𝑜𝑟 𝐷𝐹𝐿 𝑎𝑑𝑑𝑖𝑡𝑖𝑜𝑛𝑠 = 𝐷𝐹𝐿𝑊𝑖𝑛𝑡𝑒𝑟 + 𝐷𝐹𝐿 𝐴𝑑𝑑𝑖𝑡𝑖𝑜𝑛𝑠 × % 𝐴𝑑𝑗𝑢𝑠𝑡𝑚𝑒𝑛𝑡

= 3.07 + 1.99 × 0.70 = 4.47

J-11
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

The next indirect expense is the scaffolding cost, which is required due to the increasingly strict

safety regulations over the past couple decades:

𝑆𝑐𝑎𝑓𝑓𝑜𝑙𝑑𝑖𝑛𝑔 = 𝑂𝑣𝑒𝑟ℎ𝑒𝑎𝑑 𝑓𝑜𝑟 𝐷𝐹𝐿 𝐴𝑑𝑑𝑖𝑡𝑖𝑜𝑛𝑠

+ 𝑇𝑜𝑡𝑎𝑙 𝐷𝐹𝐿 × % 𝐴𝑑𝑗𝑢𝑠𝑡𝑚𝑒𝑛𝑡 × % 𝐴𝑝𝑝𝑙𝑖𝑐𝑎𝑏𝑖𝑙𝑖𝑡𝑦

= 4.47 + 3.07 × 0.25 × 1.00 = 5.23

The next indirect expense is the cost of any miscellaneous items to be accounted for in the

project, which can include bottled water, coffee and lunch, or the construction of temporary

roads. Based on the estimated capital expenditure of our project being below $25 million CAD,

the chosen adjustment factor is 30%.

𝑀𝑖𝑠𝑐𝑒𝑙𝑙𝑎𝑛𝑒𝑜𝑢𝑠 𝐼𝑡𝑒𝑚𝑠 = 𝑆𝑐𝑎𝑓𝑓𝑜𝑙𝑑𝑖𝑛𝑔 + 𝑇𝑜𝑡𝑎𝑙 𝐷𝐹𝐿 × % 𝐴𝑑𝑗𝑢𝑠𝑡𝑚𝑒𝑛𝑡 × % 𝐴𝑝𝑝𝑙𝑖𝑐𝑎𝑏𝑖𝑙𝑖𝑡𝑦

= 5.23 + 3.07 × 0.30 × 1.00 = 6.16

The final indirect expense item is the construction camp cost, which is included due to the facility

being in a relatively remote area. Since the project involves adding the equipment in modules, the

percent applicability is slightly less than 100%. The value chosen for the project is 80%.

𝐶𝑜𝑛𝑠𝑡𝑟𝑢𝑐𝑡𝑖𝑜𝑛 𝐶𝑎𝑚𝑝 = 𝑀𝑖𝑠𝑐𝑒𝑙𝑙𝑎𝑛𝑒𝑜𝑢𝑠 𝐼𝑡𝑒𝑚𝑠 + 0.25 × % 𝐴𝑝𝑝𝑙𝑖𝑐𝑎𝑏𝑖𝑙𝑖𝑡𝑦

= 6.16 + 0.25 × 0.80 = 6.36

This value represents the total DFL factor that accounts for both labour productivity and indirect

expenses, and is used to adjust the bare module factor for DFL:

𝑎 𝑎
𝐹𝐵𝑀,𝐷𝐹𝐿 𝑎𝑑𝑗𝑢𝑠𝑡𝑒𝑑 = 𝐹𝐵𝑀 + (𝐶𝑜𝑛𝑠𝑡𝑟𝑢𝑐𝑡𝑖𝑜𝑛 𝐶𝑎𝑚𝑝 − 𝐷𝐹𝐿𝑈&𝑉 ) = 6.2 + (6.36 − 1.08) = 11.07

It was assumed that demolition costs were not applicable for the DFL estimation in this project.

J-12
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Table J3: Equipment Cost and DFL Summary


Direct Project Expenses
Heat Exchangers Packing Drums
E-80 E-81 E-85 C-80 C-82 C-83 C-87
Equipment Cost, C_p ($USD Gulf Coast 2004) $0 $50,000 $74,000 $362,000 $516,000 $38,000 $18,000
Fcs_BM (from Guthrie Table 9-13) 3.37 3.37 3.37 - - 4.20 4.20
Prorated DFL 0.63 0.63 0.63 0.05 0.05 0.95 0.95
Material Factor, F_M 3 3 3 - - 4 1
Pressure Factor, F_P 1.11 1 1.13 - - 1.25 2.8
F_P*F_M 3.33 3 3.39 - - 5 2.8
Bare Module Factor, Fa_BM from U&V 6.2 5.8 6.4 1 1 11.2 7.5
Bare Module Cost, C_BM ($CAD Alberta 2018) $0 $594,364 $970,657 $741,930 $1,057,557 $872,280 $276,687
DFL adjusted for F_M and F_P 1.16 1.08 1.20 0.05 0.05 2.53 1.70
DFL Cumulative Adjustments - Labour Productivity
Alberta Greenfield 1.45 1.36 1.50 0.06 0.06 3.17 2.12
Fort McMurray 1.81 1.69 1.87 0.08 0.08 3.96 2.65
Operating Facility 2.35 2.20 2.43 0.10 0.10 5.15 3.45
Facility Turnaround 3.24 3.03 3.34 0.14 0.14 7.08 4.74
Winter Work 3.29 3.07 3.39 0.14 0.14 7.18 4.81
Total DFL Additions 2.13 1.99 2.20 0.09 0.09 4.65 3.11
Total DFL Factor 3.29 3.07 3.39 0.14 0.14 7.18 4.81
Construction OH Cumulative Adjustments - Indirect Project Expenses
Overhead for DFL Additions 4.77 4.47 4.93 0.21 0.21 10.44 6.99
Scaffolding 5.60 5.23 5.78 0.24 0.24 12.23 8.19
Miscellaneous Items 6.58 6.16 6.79 0.28 0.28 14.39 9.63
Construction Camp 6.78 6.36 6.99 0.48 0.48 14.59 9.83
Adjusted Bare Module Factor, Fa_BM 11.82 11.07 12.20 1.43 1.43 23.25 15.64
CEPCI Adjustment 1.54 1.54 1.54 1.54 1.54 1.54 1.54
Currency Adjustment 1.33 1.33 1.33 1.33 1.33 1.33 1.33
Adjusted Bare Module Cost, C_BMa ($CAD Alberta 2018) $0.00 $1,134,692.44 $1,849,932.23 $1,063,869.64 $1,516,455.06 $1,810,919.73 $576,859.85

J-1
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

2.3. Total Fixed Capital Expenditure


Taking the sum of the adjusted bare module costs in Table J4 yields a total bare module cost

of $7.95 million. Applying the contingencies along, contractor fees, engineering fees, owner fees,

and startup costs gives a total fixed capital expenditure of $14.89 million. Guidelines from the

Electric Power Research Institute (EPRI) were referred to when determining the contingencies for

the project. Since the project involves the revamp of an existing, well known amine process already

in commercial use, the chosen process contingency was 0% (5). After discussions with Len

Church, the contractual fee was allocated at 7% of the total bare module cost. At this stage of the

project, only one P&ID has been developed and equipment specifications are considered to be at

the preliminary stage, so the project falls within the simplified category. Thus, the chosen project

contingency was 40% of the total module cost. The engineering or procurement expense was

prorated based on the estimated fixed capital expenditure of the project and was determined to be

18% of the total module cost plus project contingency. This percentage would be closer to 20% if

the estimated fixed capital was low at around $5 million and would be closer to 10% if the fixed

capital was high at around $50 million or over. The owner’s cost and the commissioning and

startup cost were allocated at 3% and 4% of the total module cost plus project contingency,

respectively. Table G3 summarizes this breakdown below:

J-1
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Table J4: Total Fixed Capital Breakdown


Cost ($MM)

Total Bare Module Cost $7.16

Process Contingency $0

Contractual Fee $0.50

Total Module Cost $7.67

Project Contingency $3.07

Engineering/Procurement $1.93

Owner’s Cost $0.32

Commissioning and Startup $0.43

Total Fixed Capital $13.42

3. Working Capital Expenditure


The working capital cost of this project was estimated based on the amount of additional raw

materials and spare parts inventory required to keep the facility in operation. The recommended

range for working capital expenditure was 10 to 20% of the fixed capital expenditure (1). Since

the CO2 Removal Unit is relatively small, and the 125% capacity redesign does not add a

significant number of equipment, the working capital is chosen to be 10% of the total fixed capital,

which in this case is $1.34 MM. This percentage would be closer to 20% or even 30% if the raw

materials inventory was included as part of the scope and is expensive, the process produces a

diverse range of products, or if the plant itself is constructed using cheap materials such as cast

iron or carbon steel (1) (6). The loss in amine solution due to operation is also minimal, which also

justifies a smaller working capital estimation.

J-2
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

4. Operating Costs
This section includes the detailed calculations and assumptions done for the operating cost

estimation. Table J5 displays the breakdown of all operating cost components divided into direct,

indirect, and general expenses. Percentages from Ulrich & Vasudevan (2004) and

recommendations from Jamieson and Church (2015) were used to calculate the operating expenses

and adjust them based on the project.

4.1. Onstream Time


The onstream factor is calculated based on the annual planned shutdown of four weeks for

maintenance and cleaning purposes. This is the fraction of time that the plant is running at full

capacity. The calculated value for the onstream factor is:

𝑤𝑘𝑠 𝑤𝑘𝑠 𝑠ℎ𝑢𝑡𝑑𝑜𝑤𝑛


52 𝑦𝑟 − 4 48
𝑦𝑟
𝑂𝑛𝑠𝑡𝑟𝑒𝑎𝑚 𝐹𝑎𝑐𝑡𝑜𝑟 = = = 0.92
𝑤𝑘𝑠 52
52 𝑦𝑟

The corresponding onstream time in hours is:

ℎ ℎ
𝑂𝑛𝑠𝑡𝑟𝑒𝑎𝑚 𝑇𝑖𝑚𝑒 = 0.92 × 8760 = 8059.2
𝑦𝑟 𝑦𝑟

4.2. Operating Labour


To calculate the direct manufacturing cost associated with operating labour, Table 6.2 from

Ulrich & Vasudevan (2004) was referenced to determined how many additional operators are

required per shift. Since a total of three additional heat exchangers are being added to the current

facility to facilitate the 125% capacity increase (one additional E-81 lean/rich amine exchanger

and E-85 which is two exchangers arranged in series), the number of additional operators per shift

J-3
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

is 0.15. Operators at CNRL work on a 7 day on 7 day off schedule, which translates into 24 shifts

per year when accounting for the annual four-week planned shutdown. Using an assumed operator

yearly salary of $100,000 CAD, the annual operating labour cost is:

𝑂𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔 𝐿𝑎𝑏𝑜𝑢𝑟 = # 𝑠ℎ𝑖𝑓𝑡𝑠 × # 𝑜𝑝𝑒𝑟𝑎𝑡𝑜𝑟𝑠 𝑝𝑒𝑟 𝑠ℎ𝑖𝑓𝑡 × 𝑜𝑝𝑒𝑟𝑎𝑡𝑜𝑟 𝑦𝑒𝑎𝑟𝑙𝑦 𝑠𝑎𝑙𝑎𝑟𝑦

𝑠ℎ𝑖𝑓𝑡𝑠 𝑜𝑝𝑒𝑟𝑎𝑡𝑜𝑟𝑠
𝑂𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔 𝐿𝑎𝑏𝑜𝑢𝑟 = 24 × 0.15 × $100,000 𝐶𝐴𝐷 = $360,000 𝐶𝐴𝐷
𝑦𝑒𝑎𝑟 𝑠ℎ𝑖𝑓𝑡

4.3. Utilities
Table J5 displays the utility cost data provided by CNRL. Steam, amine, natural gas, and

cooling water utility costs were provided by CNRL, but steam was not included to the unchanging

steam flow to the E-82 stripper reboiler between each case.

Table J5: Utility Cost Data


Utility Unit Cost (C$)
Steam (tonne) 6.10
Amine (kg) 12.25
Natural Gas (GJ) 3.06
Cooling Water (m3/s) 0.07

Since the additional power required for the pumps and compressor units are provided by the

electricity generated onsite, the following equation from Table 6.3 in Ulrich & Vasudevan (2004)

is used to convert the natural gas price to the electricity price:

𝐶𝑆,𝑢 = 𝑎 × 𝐶𝐸𝑃𝐶𝐼 + 𝑏 × 𝐶𝑆,𝑓

Where CS,u is the unit price of electricity and CS,f is the unit price of the fuel used to generate the

electricity, which is natural gas. CEPCI is the current cost index of November 2018 which is 616.4.

J-4
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Since CNRL is currently buying about 70MW off the Alberta power grid, the cost coefficients a

and b are taken as 0.00013 and 0.010, respectively from Table 6.3:

𝐶𝑆,𝑢 = 0.00013 × 616.4 + 0.010 × $3.06/𝐺𝐽 = $0.11/𝑘𝑊ℎ

Table J6 summarizes the additional utility costs for each case. The makeup amine was calculated

by taking the MDEA mass flowrate of streams 37, 75, and 96 since they are exiting the unit. This

amount was found to be 0.00006% of the total MDEA mass flow rate of stream 86, which was the

same percentage used in the 112% and 125% capacity redesigns to estimate makeup amine

requirements.

Table J6: Additional Utility Cost Summary


Additional Utilities
Base
111.60% 125%
Steam (tonne/s) N/A N/A N/A
Makeup Amine (kg/s) 0.000038 0.000002 0.000004
Electricity (kW) 5482.926934 622.738293 1151.422179
E-84 282.981084 282.981151
G-81 111.471406 8.936156 11.578975
G-82 1143.372144 14.681427 12.652463
G-83 1.148342 -0.008602 -0.120247
K-100 1487.751077 118.733474 343.284592
K-101 1414.627765 106.161664 284.993244
K-102 1324.556199 91.253090 216.052002
Cooling Water (m^3/s) 0.157351 0.012880 0.101344
Steam ($CAD/yr) N/A N/A N/A
Amine ($CAD/yr) $13,374.83 $582.55 $1,278.73
Electricity ($CAD/yr) $4,893,026.14 $555,738.71 $1,027,542.20
Cooling Water ($CAD/yr) $319,566.29 $26,158.79 $205,821.99

Table J7 summarizes the additional makeup amine requirements for the utility cost estimation:

J-5
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Table J7: Additional Makeup Amine Summary


Base 112% 125%
Total amine flow (kg/s) 6.40E+01 6.68E+01 7.02E+01
Stream 37 1.23E-10 1.35E-10 8.00E-11
Stream 96 3.61E-05 2.85E-05 4.50E-05
Stream 75 1.55E-06 1.37E-06 9.93E-07
Percent Makeup 5.88E-07
Makeup amine (kg/s) 3.76E-05 3.93E-05 4.12E-05

Sample calculations for the additional utility costs for the 112% capacity increase are shown

below:

𝐴𝑑𝑑𝑖𝑡𝑖𝑜𝑛𝑎𝑙 𝑈𝑡𝑖𝑙𝑖𝑡𝑦 𝐶𝑜𝑠𝑡 = 𝑈𝑡𝑖𝑙𝑖𝑡𝑦 𝑃𝑟𝑖𝑐𝑒 × 𝐴𝑑𝑑𝑡𝑖𝑜𝑛𝑎𝑙 𝑈𝑡𝑖𝑙𝑖𝑡𝑦 𝑈𝑠𝑎𝑔𝑒 × 𝑂𝑛𝑠𝑡𝑟𝑒𝑎𝑚 𝑇𝑖𝑚𝑒

For electricity, the additional power required for the E-84 air cooler, G-81A/B, G-82A/B/C, G-

83A/B pumps and the K-100, K-101, K-102 compressors is 623 kW. The additional electricity

cost is calculated as:


𝐴𝑛𝑛𝑢𝑎𝑙 𝐸𝑙𝑒𝑐𝑡𝑟𝑖𝑐𝑖𝑡𝑦 𝐶𝑜𝑠𝑡 = $0.11/𝑘𝑊ℎ × 623 𝑘𝑊 × 8059.2 = $555,739 𝐶𝐴𝐷/𝑦𝑟
𝑦𝑟

The additional cooling water required to cool the E-80, E-83, and the three compressor stage

intercoolers is 46 m3/h. The additional cooling water cost is calculated as:

𝑚3 ℎ
𝐴𝑛𝑛𝑢𝑎𝑙 𝐶𝑜𝑜𝑙𝑖𝑛𝑔 𝑊𝑎𝑡𝑒𝑟 𝐶𝑜𝑠𝑡 = $0.07/𝑚3 × 46 × 8059.2 = $26,159 𝐶𝐴𝐷/𝑦𝑟
ℎ 𝑦𝑟

The total additional utilities expense is then calculated as:

𝑇𝑜𝑡𝑎𝑙 𝑈𝑡𝑖𝑙𝑖𝑡𝑖𝑒𝑠 𝐶𝑜𝑠𝑡 = $555,739 𝐶𝐴𝐷/𝑦𝑟 + $26,159 𝐶𝐴𝐷/𝑦𝑟 = $581,898 𝐶𝐴𝐷/𝑦𝑟

4.1. Remaining Expenses


The remaining direct, indirect, and general operating expenses are listed below:

J-6
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

• Supervisory labour is 15% of the operating labour.

• Maintenance costs amount to 2% of the fixed capital, due to the low number of additional

equipment that would need regular maintenance.

• Operating supplies are 15% of the maintenance cost.

• Laboratory charges are 15% of the operating labour cost.

• Assume no patents or royalties are involved in this project.

• Indirect overhead costs amount to 60% of the sum of operating labour, supervisory labour, and

maintenance costs.

• Local taxes are 2% of the fixed capital.

• Insurance is 1% of the fixed capital.

• Administrative costs are 25% of the overhead costs.

• Distribution and selling costs are 10% of the total manufacturing expense.

• Research and development costs are 5% of the total manufacturing expense.

J-7
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Table J8: Operating Cost Summary for the 112% and 125% Capacity Increases
Expense 112% Case Annual Cost 125% Case Annual Cost
($MM) ($MM)
Fixed Capital $0 $13.42
Working Capital $0 $1.34
Total Capital $0 $14.76
Operating Labour $0 $0.36
Supervisory Labour $0 $0.05
Utilities $0.58 $1.24
Maintenance $0 $0.80
Operating Supplies $0 $0.12
Lab Charges $0 $0.05
Total Direct Expense $0.58 $2.63
Overhead $0 $0.73
Local Taxes $0 $0.27
Insurance $0 $0.13
Total Indirect Expense $0 $1.13
Administrative Costs $0 $0.18
Distribution and Selling $0.06 $0.38
Research and Development $0.03 $0.19
Total General Expense $0.09 $0.75
Total Operating Expense $0.67 $4.51

5. Discounted Cash Flows


Tables J9 to J12 display the full tabulated cash flow tables used to determine the project NPV

and IRR for each case. The discounted cash flow analysis for this project utilizes a corporate

discount rate of 15%, a hurdle rate of 20%, and a project life of 20 years. An inflation rate of 3%

and a provincial income tax rate of 27% was used. For the 125% cash flow analysis, the 2019 fiscal

values were used as the baseline despite the operations starting at 2022 as opposed to 2020, so the

estimation for this case may be less accurate than the 112% case. To account for this, a future

CEPCI value had to be assumed, which is very risky since the CEPCI depends on various economic

J-8
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

and societal factors and is therefore very unpredictable. The sample calculations for the 125%

capacity case during the initial investment and the first operating year are shown below:

𝐹𝑖𝑥𝑒𝑑 𝑐𝑎𝑝𝑖𝑡𝑎𝑙 = −$13,415,989

This is the initial investment to the project made at year 0 and is presented as a negative or outwards

cash flow. The working capital is 10% of the fixed capital and is added as another negative cash

flow. The depreciated value during year 0 is equal to this initial investment.

𝑊𝑜𝑟𝑘𝑖𝑛𝑔 𝐶𝑎𝑝𝑖𝑡𝑎𝑙 = −$1,341,599

𝐷𝑒𝑝𝑟𝑒𝑐𝑖𝑎𝑡𝑒𝑑 𝑉𝑎𝑙𝑢𝑒𝑌𝑒𝑎𝑟 0 = +$13,415,989

The cash flow for year 0 is:

𝐶𝑎𝑠ℎ 𝐹𝑙𝑜𝑤𝑌𝑒𝑎𝑟 0 = 𝐹𝑖𝑥𝑒𝑑 𝐶𝑎𝑝𝑖𝑡𝑎𝑙 + 𝑊𝑜𝑟𝑘𝑖𝑛𝑔 𝐶𝑎𝑝𝑖𝑡𝑎𝑙 = −$13,415,989 − $1,341,599

= −$14,757,588

The annual manufacturing expense is calculated using the formula:

𝑀𝑎𝑛𝑢𝑓𝑎𝑐𝑡𝑢𝑟𝑖𝑛𝑔 𝐸𝑥𝑝𝑒𝑛𝑠𝑒 = −𝐼𝑛𝑖𝑡𝑖𝑎𝑙 𝑀𝑎𝑛𝑢𝑓𝑎𝑐𝑡𝑢𝑟𝑖𝑛𝑔 𝐸𝑥𝑝𝑒𝑛𝑠𝑒 × (1 + 𝐼𝑛𝑓𝑙𝑎𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑒)𝑛

Where n is the project year. The manufacturing expense for the first operating year is:

𝑀𝑎𝑛𝑢𝑓𝑎𝑐𝑡𝑢𝑟𝑖𝑛𝑔 𝐸𝑥𝑝𝑒𝑛𝑠𝑒𝑌𝑒𝑎𝑟 1 = −$4,511,307 × (1 + 0.03)1 = −$4,646,647

The annual revenue from sales is calculated using the formula:

𝑅𝑒𝑣𝑒𝑛𝑢𝑒 = 𝐼𝑛𝑖𝑡𝑖𝑎𝑙 𝑅𝑒𝑣𝑒𝑛𝑢𝑒 × (1 + 𝐼𝑛𝑓𝑙𝑎𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑒)𝑛

The revenue for the first operating year is:

J-9
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

𝑅𝑒𝑣𝑒𝑛𝑢𝑒𝑌𝑒𝑎𝑟 1 = $5,085,222 × (1 + 0.03)1 = $5,237,779

The cash flow for year 1 is:

𝐶𝑎𝑠ℎ 𝐹𝑙𝑜𝑤𝑌𝑒𝑎𝑟 1 = 𝑀𝑎𝑛𝑢𝑓𝑎𝑐𝑡𝑢𝑟𝑖𝑛𝑔 𝐸𝑥𝑝𝑒𝑛𝑠𝑒 + 𝑅𝑒𝑣𝑒𝑛𝑢𝑒 = −$4,646,647 + $5,237,779

= +$591,132

The capital cost allowance (CCA) is required to calculate the depreciated value for this year. The

CCA depreciation rate for Asset Class 43 is 15% for the first year and 30% for every subsequent

year. The CCA is calculated using the following formula:

𝐶𝐶𝐴 = 𝐷𝑒𝑝𝑟𝑒𝑐𝑖𝑎𝑡𝑒𝑑 𝑉𝑎𝑙𝑢𝑒 𝑓𝑟𝑜𝑚 𝑃𝑟𝑒𝑣𝑖𝑜𝑢𝑠 𝑌𝑒𝑎𝑟 × 𝐶𝐶𝐴 𝑅𝑎𝑡𝑒

The CCA for year 1 is:

𝐶𝐶𝐴𝑌𝑒𝑎𝑟 1 = $13,415,989 × 0.15 = $2,012,398

The depreciated value for every year following the initial investment is calculated using the

following formula:

𝐷𝑒𝑝𝑟𝑒𝑐𝑖𝑎𝑡𝑒𝑑 𝑉𝑎𝑙𝑢𝑒 = 𝐷𝑒𝑝𝑟𝑒𝑐𝑖𝑎𝑡𝑒𝑑 𝑉𝑎𝑙𝑢𝑒 𝑓𝑟𝑜𝑚 𝑃𝑟𝑒𝑣𝑖𝑜𝑢𝑠 𝑌𝑒𝑎𝑟 − 𝐶𝑎𝑝𝑖𝑡𝑎𝑙 𝐶𝑜𝑠𝑡 𝐴𝑙𝑙𝑜𝑤𝑎𝑛𝑐𝑒

The depreciated value for year 1 is:

𝐷𝑒𝑝𝑟𝑒𝑐𝑖𝑎𝑡𝑒𝑑 𝑉𝑎𝑙𝑢𝑒𝑌𝑒𝑎𝑟 1 = $13,415,989 − $2,012,398 = +$11,403,590

Taxes can then be applied next. The annual taxable income is calculated using the formula:

𝑇𝑎𝑥𝑎𝑏𝑙𝑒 𝐼𝑛𝑐𝑜𝑚𝑒 = 𝐶𝑎𝑠ℎ 𝐹𝑙𝑜𝑤 − 𝐶𝐶𝐴

The taxable income for year 1 is:

J-10
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

𝑇𝑎𝑥𝑎𝑏𝑙𝑒 𝐼𝑛𝑐𝑜𝑚𝑒𝑌𝑒𝑎𝑟 1 = $591,132 − $2,012,398 = −$1,421,266

Since the taxable income for the first operating year is negative, no taxes will be applied:

𝑇𝑎𝑥𝑒𝑠𝑌𝑒𝑎𝑟 1 = $0

If the taxable income is positive, then the following formula is used to calculate the taxes using an

income tax rate of 27%:

𝑇𝑎𝑥𝑒𝑠 = 𝑇𝑎𝑥𝑎𝑏𝑙𝑒 𝐼𝑛𝑐𝑜𝑚𝑒 × 𝐼𝑛𝑐𝑜𝑚𝑒 𝑇𝑎𝑥 𝑅𝑎𝑡𝑒

The cash flow after taxes is simply the original cash flow plus the taxes:

𝐶𝑎𝑠ℎ 𝐹𝑙𝑜𝑤 𝐴𝑓𝑡𝑒𝑟 𝑇𝑎𝑥𝑒𝑠 = 𝐶𝑎𝑠ℎ 𝐹𝑙𝑜𝑤 + 𝑇𝑎𝑥𝑒𝑠

The cash flow after taxes for year 1 is:

𝐶𝑎𝑠ℎ 𝐹𝑙𝑜𝑤 𝐴𝑓𝑡𝑒𝑟 𝑇𝑎𝑥𝑒𝑠𝑌𝑒𝑎𝑟 1 = $591,132 + $0 = +$591,132

The discount factor used to calculate the discounted cash flows is obtained using the following

formula, using a discount rate of 15%:

𝐷𝑖𝑠𝑐𝑜𝑢𝑛𝑡 𝐹𝑎𝑐𝑡𝑜𝑟 = (1 + 𝐷𝑖𝑠𝑐𝑜𝑢𝑛𝑡 𝑅𝑎𝑡𝑒)−𝑛

The discount factor for year 1 is:

𝐷𝑖𝑠𝑐𝑜𝑢𝑛𝑡 𝐹𝑎𝑐𝑡𝑜𝑟𝑌𝑒𝑎𝑟 1 = (1 + 0.15)−1 = 0.870

The discounted cash flow (DCF) is then calculated by multiplying the cash flow after taxes by the

discount rate:

𝐷𝐶𝐹 = 𝐶𝑎𝑠ℎ 𝐹𝑙𝑜𝑤 𝐴𝑓𝑡𝑒𝑟 𝑇𝑎𝑥𝑒𝑠 × 𝐷𝑖𝑠𝑐𝑜𝑢𝑛𝑡 𝑅𝑎𝑡𝑒

J-11
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

The DCF for year 1 is:

𝐷𝐶𝐹𝑌𝑒𝑎𝑟 1 = $591,132 × 0.870 = +$514,028

The cumulative DCF can then be calculated using the following formula:

𝐶𝑢𝑚𝑢𝑙𝑎𝑡𝑖𝑣𝑒 𝐷𝐶𝐹 = 𝐶𝑢𝑚𝑢𝑙𝑎𝑡𝑖𝑣𝑒 𝐷𝐶𝐹 𝑓𝑟𝑜𝑚 𝑃𝑟𝑒𝑣𝑖𝑜𝑢𝑠 𝑌𝑒𝑎𝑟 + 𝐶𝑢𝑟𝑟𝑒𝑛𝑡 𝐷𝐶𝐹

The cumulative DCF for year 0 is equal to the cash flow of that year. The cumulative DCF for year

1 is therefore:

𝐶𝑢𝑚𝑢𝑙𝑎𝑡𝑖𝑣𝑒 𝐷𝐶𝐹 = −$14,757,588 + $514,028 = −$14,243,560

J-12
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Table J9: Discounted NPV Cash Flow Table for 112% Case
Fixed Capital $0
Working Capital $0
Total Operating Expense $669,182
Revenue From CO2 Production Sales $1,860,608
Inflation Rate 3.00% NPV $6,641,451 NPV Positive
Discount Rate 15.00%
Tax Rate 27.00%
Cash Flow Analysis
Other Cash
Total Flows CCA Capital Cost Discounted
Calendar Revenue Depreciated Taxable Cash Flow Discount Cumulative
Year Fixed Capital Manufacturing (including Cash Flow Depreciation Allowance Taxes Cash Flow
Year From Sales Value Income After Taxes Factor DCF
Expense working Rate (CCA) (DCF)
Capital)
2019 0 $0 $0 $0 $0 $0 $0 0 1.000 $0 $0
2020 1 -$689,258 $0 $1,916,426 $1,227,168 $0 15% 0 1,227,168 -331,335 895,833 0.870 $778,985 $778,985
2021 2 -$709,935 $0 $1,973,919 $1,263,983 $0 30% 0 1,263,983 -341,275 922,708 0.756 $697,700 $1,476,685
2022 3 -$731,233 $0 $2,033,136 $1,301,903 $0 30% 0 1,301,903 -351,514 950,389 0.658 $624,896 $2,101,581
2023 4 -$753,170 $0 $2,094,130 $1,340,960 $0 30% 0 1,340,960 -362,059 978,901 0.572 $559,690 $2,661,271
2024 5 -$775,765 $0 $2,156,954 $1,381,189 $0 30% 0 1,381,189 -372,921 1,008,268 0.497 $501,287 $3,162,558
2025 6 -$799,038 $0 $2,221,663 $1,422,624 $0 30% 0 1,422,624 -384,109 1,038,516 0.432 $448,979 $3,611,537
2026 7 -$823,010 $0 $2,288,313 $1,465,303 $0 30% 0 1,465,303 -395,632 1,069,671 0.376 $402,129 $4,013,666
2027 8 -$847,700 $0 $2,356,962 $1,509,262 $0 30% 0 1,509,262 -407,501 1,101,761 0.327 $360,168 $4,373,834
2028 9 -$873,131 $0 $2,427,671 $1,554,540 $0 30% 0 1,554,540 -419,726 1,134,814 0.284 $322,585 $4,696,419
2029 10 -$899,325 $0 $2,500,501 $1,601,176 $0 30% 0 1,601,176 -432,318 1,168,859 0.247 $288,924 $4,985,343
2030 11 -$926,305 $0 $2,575,516 $1,649,212 $0 30% 0 1,649,212 -445,287 1,203,924 0.215 $258,775 $5,244,118
2031 12 -$954,094 $0 $2,652,782 $1,698,688 $0 30% 0 1,698,688 -458,646 1,240,042 0.187 $231,773 $5,475,891
2032 13 -$982,717 $0 $2,732,365 $1,749,648 $0 30% 0 1,749,648 -472,405 1,277,243 0.163 $207,588 $5,683,479
2033 14 -$1,012,198 $0 $2,814,336 $1,802,138 $0 30% 0 1,802,138 -486,577 1,315,561 0.141 $185,926 $5,869,405
2034 15 -$1,042,564 $0 $2,898,766 $1,856,202 $0 30% 0 1,856,202 -501,175 1,355,028 0.123 $166,525 $6,035,930
2035 16 -$1,073,841 $0 $2,985,729 $1,911,888 $0 30% 0 1,911,888 -516,210 1,395,678 0.107 $149,149 $6,185,079
2036 17 -$1,106,056 $0 $3,075,301 $1,969,245 $0 30% 0 1,969,245 -531,696 1,437,549 0.093 $133,585 $6,318,665
2037 18 -$1,139,238 $0 $3,167,560 $2,028,322 $0 30% 0 2,028,322 -547,647 1,480,675 0.081 $119,646 $6,438,311
2038 19 -$1,173,415 $0 $3,262,587 $2,089,172 $0 30% 0 2,089,172 -564,076 1,525,095 0.070 $107,161 $6,545,472
2039 20 -$1,208,617 $0 $3,360,464 $2,151,847 $0 30% 0 2,151,847 -580,999 1,570,848 0.061 $95,979 $6,641,451

J-13
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Table J10: Discounted IRR Cash Flow Table for 112% Case
Fixed Capital $0
Working Capital $0
Total Manufacturing Expense $669,182
Revenue From CO2 Production Sales $1,860,608
Inflation Rate 3.00% NPV $0 NPV Zero
Discount Rate 90745139682.42%
Tax Rate 27.00%
Cash Flow Analysis
Other Cash
Total Flows Capital Cost Discounted
Calendar Revenue Depreciated CCA Depreciation Taxable Cash Flow Discount Cumulative
Year Fixed Capital Manufacturing (including Cash Flow Allowance Taxes Cash Flow
Year From Sales Value Rate Income After Taxes Factor DCF
Expense working (CCA) (DCF)
Capital)
2019 0 $0 $0 $0 $0 $0 $0 0 1.000 $0 $0
2020 1 -$689,258 $0 $1,916,426 $1,227,168 $0 15% 0 1,227,168 -331,335 895,833 0.000 $0 $0
2021 2 -$709,935 $0 $1,973,919 $1,263,983 $0 30% 0 1,263,983 -341,275 922,708 0.000 $0 $0
2022 3 -$731,233 $0 $2,033,136 $1,301,903 $0 30% 0 1,301,903 -351,514 950,389 0.000 $0 $0
2023 4 -$753,170 $0 $2,094,130 $1,340,960 $0 30% 0 1,340,960 -362,059 978,901 0.000 $0 $0
2024 5 -$775,765 $0 $2,156,954 $1,381,189 $0 30% 0 1,381,189 -372,921 1,008,268 0.000 $0 $0
2025 6 -$799,038 $0 $2,221,663 $1,422,624 $0 30% 0 1,422,624 -384,109 1,038,516 0.000 $0 $0
2026 7 -$823,010 $0 $2,288,313 $1,465,303 $0 30% 0 1,465,303 -395,632 1,069,671 0.000 $0 $0
2027 8 -$847,700 $0 $2,356,962 $1,509,262 $0 30% 0 1,509,262 -407,501 1,101,761 0.000 $0 $0
2028 9 -$873,131 $0 $2,427,671 $1,554,540 $0 30% 0 1,554,540 -419,726 1,134,814 0.000 $0 $0
2029 10 -$899,325 $0 $2,500,501 $1,601,176 $0 30% 0 1,601,176 -432,318 1,168,859 0.000 $0 $0
2030 11 -$926,305 $0 $2,575,516 $1,649,212 $0 30% 0 1,649,212 -445,287 1,203,924 0.000 $0 $0
2031 12 -$954,094 $0 $2,652,782 $1,698,688 $0 30% 0 1,698,688 -458,646 1,240,042 0.000 $0 $0
2032 13 -$982,717 $0 $2,732,365 $1,749,648 $0 30% 0 1,749,648 -472,405 1,277,243 0.000 $0 $0
2033 14 -$1,012,198 $0 $2,814,336 $1,802,138 $0 30% 0 1,802,138 -486,577 1,315,561 0.000 $0 $0
2034 15 -$1,042,564 $0 $2,898,766 $1,856,202 $0 30% 0 1,856,202 -501,175 1,355,028 0.000 $0 $0
2035 16 -$1,073,841 $0 $2,985,729 $1,911,888 $0 30% 0 1,911,888 -516,210 1,395,678 0.000 $0 $0
2036 17 -$1,106,056 $0 $3,075,301 $1,969,245 $0 30% 0 1,969,245 -531,696 1,437,549 0.000 $0 $0
2037 18 -$1,139,238 $0 $3,167,560 $2,028,322 $0 30% 0 2,028,322 -547,647 1,480,675 0.000 $0 $0
2038 19 -$1,173,415 $0 $3,262,587 $2,089,172 $0 30% 0 2,089,172 -564,076 1,525,095 0.000 $0 $0
2039 20 -$1,208,617 $0 $3,360,464 $2,151,847 $0 30% 0 2,151,847 -580,999 1,570,848 0.000 $0 $0

J-14
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Table J11: Discounted NPV Cash Flow Table for 125% Case
Fixed Capital $14,891,485
Working Capital $1,489,148
Total Operating Expense $4,753,658
Revenue From CO2 Production Sales $5,085,222
Inflation Rate 3.00% NPV -$13,954,568 NPV Negative
Discount Rate 15.00%
Tax Rate 27.00%
Cash Flow Analysis
Other Cash
Total Flows CCA Capital Cost
Calendar Revenue Depreciated Taxable Cash Flow After Discount Discounted
Year Fixed Capital Manufacturing (including Cash Flow Depreciation Allowance Taxes Cumulative DCF
Year From Sales Value Income Taxes Factor Cash Flow (DCF)
Expense working Rate (CCA)
Capital)
2020 0 -14,891,485 0 -1,489,148 0 -16,380,633 14,891,485 -16,380,633 1.000 -$16,380,633 -$16,380,633
2021 1 -4,896,267 0 5,237,779 341,512 12,657,762 15% 2,233,723 -1,892,211 0 341,512 0.870 $296,967 -$16,083,667
2022 2 -5,043,155 0 5,394,912 351,757 8,860,434 30% 3,797,329 -3,445,572 0 351,757 0.756 $265,979 -$15,817,688
2023 3 -5,194,450 0 5,556,760 362,310 6,202,303 30% 2,658,130 -2,295,820 0 362,310 0.658 $238,224 -$15,579,464
2024 4 -5,350,284 0 5,723,462 373,179 4,341,612 30% 1,860,691 -1,487,512 0 373,179 0.572 $213,366 -$15,366,097
2025 5 -5,510,792 0 5,895,166 384,374 3,039,129 30% 1,302,484 -918,109 0 384,374 0.497 $191,102 -$15,174,995
2026 6 -5,676,116 0 6,072,021 395,906 2,127,390 30% 911,739 -515,833 0 395,906 0.432 $171,161 -$15,003,834
2027 7 -5,846,399 0 6,254,182 407,783 1,489,173 30% 638,217 -230,434 0 407,783 0.376 $153,301 -$14,850,534
2028 8 -6,021,791 0 6,441,807 420,016 1,042,421 30% 446,752 -26,736 0 420,016 0.327 $137,304 -$14,713,230
2029 9 -6,202,445 0 6,635,062 432,617 729,695 30% 312,726 119,890 -32,370 400,246 0.284 $113,775 -$14,599,455
2030 10 -6,388,518 0 6,834,114 445,595 510,786 30% 218,908 226,687 -61,205 384,390 0.247 $95,015 -$14,504,440
2031 11 -6,580,174 0 7,039,137 458,963 357,550 30% 153,236 305,727 -82,546 376,417 0.215 $80,908 -$14,423,531
2032 12 -6,777,579 0 7,250,311 472,732 250,285 30% 107,265 365,467 -98,676 374,056 0.187 $69,914 -$14,353,618
2033 13 -6,980,906 0 7,467,820 486,914 175,200 30% 75,086 411,828 -111,194 375,720 0.163 $61,065 -$14,292,553
2034 14 -7,190,334 0 7,691,855 501,521 122,640 30% 52,560 448,961 -121,220 380,302 0.141 $53,748 -$14,238,805
2035 15 -7,406,044 0 7,922,611 516,567 85,848 30% 36,792 479,775 -129,539 387,028 0.123 $47,564 -$14,191,241
2036 16 -7,628,225 0 8,160,289 532,064 60,094 30% 25,754 506,310 -136,704 395,360 0.107 $42,250 -$14,148,991
2037 17 -7,857,072 0 8,405,098 548,026 42,065 30% 18,028 529,998 -143,099 404,926 0.093 $37,628 -$14,111,363
2038 18 -8,092,784 0 8,657,251 564,467 29,446 30% 12,620 551,847 -148,999 415,468 0.081 $33,572 -$14,077,791
2039 19 -8,335,567 0 8,916,968 581,401 20,612 30% 8,834 572,567 -154,593 426,808 0.070 $29,990 -$14,047,801
2040 20 -8,585,634 1,489,148 9,184,477 2,087,991 14,428 30% 6,184 2,081,808 -562,088 1,525,903 0.061 $93,233 -$13,954,568

J-15
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Table J12: Discounted IRR Cash Flow Table for 125% Case
Fixed Capital $14,891,485
Working Capital $2,233,723
Total Manufacturing Expense $4,753,658
Revenue From CO2 Production Sales $5,085,222
Inflation Rate 3.00% NPV $0 NPV Zero
Discount Rate -4.42%
Tax Rate 27.00%
Cash Flow Analysis
Other Cash
Total Flows CCA Capital Cost
Calendar Revenue Depreciated Taxable Cash Flow Discount Discounted
Year Fixed Capital Manufacturing (including Cash Flow Depreciation Allowance Taxes Cumulative DCF
Year From Sales Value Income After Taxes Factor Cash Flow (DCF)
Expense working Rate (CCA)
Capital)
2020 0 -14,891,485 0 -2,233,723 0 -17,125,208 14,891,485 -17,125,208 1.000 -$17,125,208 -$17,125,208
2021 1 -4,896,267 0 5,237,779 341,512 12,657,762 15% 2,233,723 -1,892,211 0 341,512 1.046 $357,290 -$16,767,918
2022 2 -5,043,155 0 5,394,912 351,757 8,860,434 30% 3,797,329 -3,445,572 0 351,757 1.095 $385,012 -$16,382,906
2023 3 -5,194,450 0 5,556,760 362,310 6,202,303 30% 2,658,130 -2,295,820 0 362,310 1.145 $414,884 -$15,968,022
2024 4 -5,350,284 0 5,723,462 373,179 4,341,612 30% 1,860,691 -1,487,512 0 373,179 1.198 $447,074 -$15,520,949
2025 5 -5,510,792 0 5,895,166 384,374 3,039,129 30% 1,302,484 -918,109 0 384,374 1.253 $481,761 -$15,039,187
2026 6 -5,676,116 0 6,072,021 395,906 2,127,390 30% 911,739 -515,833 0 395,906 1.311 $519,140 -$14,520,047
2027 7 -5,846,399 0 6,254,182 407,783 1,489,173 30% 638,217 -230,434 0 407,783 1.372 $559,419 -$13,960,628
2028 8 -6,021,791 0 6,441,807 420,016 1,042,421 30% 446,752 -26,736 0 420,016 1.435 $602,823 -$13,357,804
2029 9 -6,202,445 0 6,635,062 432,617 729,695 30% 312,726 119,890 -32,370 400,246 1.502 $600,990 -$12,756,815
2030 10 -6,388,518 0 6,834,114 445,595 510,786 30% 218,908 226,687 -61,205 384,390 1.571 $603,847 -$12,152,968
2031 11 -6,580,174 0 7,039,137 458,963 357,550 30% 153,236 305,727 -82,546 376,417 1.644 $618,642 -$11,534,325
2032 12 -6,777,579 0 7,250,311 472,732 250,285 30% 107,265 365,467 -98,676 374,056 1.719 $643,165 -$10,891,160
2033 13 -6,980,906 0 7,467,820 486,914 175,200 30% 75,086 411,828 -111,194 375,720 1.799 $675,875 -$10,215,285
2034 14 -7,190,334 0 7,691,855 501,521 122,640 30% 52,560 448,961 -121,220 380,302 1.882 $715,724 -$9,499,561
2035 15 -7,406,044 0 7,922,611 516,567 85,848 30% 36,792 479,775 -129,539 387,028 1.969 $762,035 -$8,737,527
2036 16 -7,628,225 0 8,160,289 532,064 60,094 30% 25,754 506,310 -136,704 395,360 2.060 $814,407 -$7,923,120
2037 17 -7,857,072 0 8,405,098 548,026 42,065 30% 18,028 529,998 -143,099 404,926 2.155 $872,650 -$7,050,470
2038 18 -8,092,784 0 8,657,251 564,467 29,446 30% 12,620 551,847 -148,999 415,468 2.255 $936,735 -$6,113,735
2039 19 -8,335,567 0 8,916,968 581,401 20,612 30% 8,834 572,567 -154,593 426,808 2.359 $1,006,762 -$5,106,973
2040 20 -8,585,634 2,233,723 9,184,477 2,832,565 14,428 30% 6,184 2,826,382 -763,123 2,069,442 2.468 $5,106,973 $0

J-16
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

6. Sensitivity Analyses
The fixed capital, operating cost, cooling water and electricity price, onstream time, CO 2

product price, and GHG emissions credit price were all varied to determine their sensitivities

towards the project NPV and IRR for 125% capacity increase. The same factors were varied for

the 112% case, minus the fixed capital.

6.1. 112% Case


For this option the varied parameters are the operating cost, natural gas and cooling water

utility prices, onstream factor, CO2 selling price per tonne, and the GHG emission credit price.

The CO2 selling price was varied using the range of $12 - $35 /tCO2 obtained from the Global

CCS Institute (7). The analysis investigates the possibility of the GHG emission credit price rising

to $50 /tCO2e due to Alberta opting into the federal climate plan, and this value was therefore set

as the upper limit. All other parameters were given a variation of 10% aside from the onstream

factor, which was varied by 5%. Since a proper IRR was not able to be obtained for this case, the

sensitivity analysis was not performed. The sensitivity analysis summary is presented in Table

J13 below:

J-17
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Table J13: Sensitivity Analysis Parameter Variation Summary for 112% Case
111.6% Case
Variable (+/- 10%) Lower Limit Base Upper Limit
Operating Cost $602,264 $669,182 $736,100
Natural Gas Price $2.75 $3.06 $3.37
Cooling Water Price $0.06 $0.07 $0.08
Onstream Factor (+/- 5%) 0.87 0.92 0.97
CO2 selling price ($CAD/tonne) $11.97 $23.28 $34.58
GHG emissions credits ($CAD/tonne CO2e) $30.00 $30.00 $50.00
NPV (10% Discount Rate) IRR
Variable Lower Limit Base Upper Limit Lower Limit Base Upper Limit
Operating Cost $7,014,478 $6,641,451 $6,268,426 N/A N/A N/A
Natural Gas Price $6,741,188 $6,641,451 $6,541,715 N/A N/A N/A
Cooling Water Price $6,665,407 $6,641,451 $6,617,496 N/A N/A N/A
Onstream Factor (+/- 5%) $6,844,184 $6,641,451 $6,438,719 N/A N/A N/A
CO2 selling price ($CAD/tonne) $4,440,563 $6,641,451 $8,842,340 N/A N/A N/A
GHG emissions credits ($CAD/tonne CO2e) $6,641,451 $6,641,451 $10,535,106 N/A N/A N/A

6.2. 125% Case


This option varies the same parameters as the 112% with fixed capital as an additional

parameter. The parameters were varied the in the same manner for this case. The sensitivity

analysis summary is presented in Table J14 below:

Table J14: Sensitivity Analysis Parameter Variation Summary for 125% Case
125% Case
Variable (+/- 10%) Lower Limit Base Upper Limit
Fixed Capital $12,074,390 $13,415,989 $14,757,588
Operating Cost $4,060,177 $4,511,307 $4,962,438
Natural Gas Price $2.75 $3.06 $3.37
Cooling Water Price $0.06 $0.07 $0.08
Onstream Factor (+/- 5%) 0.87 0.92 0.97
CO2 selling price ($CAD/tonne) $11.97 $23.28 $34.58
GHG emissions credits ($CAD/tonne CO2e) $30.00 $30.00 $50.00
NPV (10% discount rate) IRR
Variable Lower Limit Base Upper Limit Lower Limit Base Upper Limit
Fixed Capital -$9,251,204 -$10,706,078 -$12,160,953 0.45% -0.38% -1.10%
Operating Cost -$7,734,509 -$10,706,078 -$13,802,945 4.78% -0.38% -8.55%
Natural Gas Price -$10,484,580 -$10,706,078 -$10,927,577 0.05% -0.38% -0.83%
Cooling Water Price -$10,479,678 -$10,706,078 -$10,932,479 0.06% -0.38% -0.84%
Onstream Factor (+/- 5%) -$10,189,952 -$10,706,078 -$11,222,205 0.62% -0.38% -1.45%
CO2 selling price ($CAD/tonne) -$18,540,175 -$10,706,078 -$3,743,669 -0.38% 10.38%
GHG emissions credits ($CAD/tonne CO2e) -$10,706,078 -$10,706,078 $1,239,797 -0.38% -0.38% 16.44%

J-18
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

7. References
1. Ulrich, Gael D. and Vasudevan, Palligarnai T. Chemical Engineering Process Design and

Economics: A Practical Guide (Second Edition). Durham : Process (Ulrich) Publishing, 2004. 0-

97087683-2-3.

2. Live Exchange Rates. OANDA Corporation. [Online]

https://www.oanda.com/currency/live-exchange-rates/USDCAD/.

3. Chemical Plant Cost Index. Chemical Engineering Essentials for the CPI Professional.

[Online] https://www.chemengonline.com/2019-cepci-updates-january-prelim-and-

december-2018-final/.

4. Guthrie, Kenneth M. Process Plant Estimating Evaluation and Control. Solana Beach :

Craftsman Book Company of America, 1974.

5. Jamieson & Church. Contingency Estimating. Edmonton, AB, Canada : s.n., 2015.

6. Towler & Sinnott. Chemical Engineering Design - Principles, Practice and Economics of

Plant and Process Design. s.l. : Elsevier, 2013.

7. Global CCS Institute. Accelerating the Uptake of CCS: Industrial Use of Captured Carbon

Dioxide. 2011.

J-19
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Appendix K: Project Management Schedule


Description
This appendix contains the detailed calculations done to obtain the DFL and engineering

costs and hours required for the development of capital expenditure and manpower profiles. These

profiles are based off the durations outlined in the project execution plan developed for the 125%

case. This appendix is not applicable to the 112% case, as no project execution plan was developed.

Unless specified otherwise, all costs and prices are expressed in Canadian dollars ($C).

Table of Contents
1. DFL Cost and Hours ............................................................................................................. K-1
2. Engineering Cost and Hours ................................................................................................. K-3
3. Manpower Profile ................................................................................................................. K-4
4. Reference .............................................................................................................................. K-7

i
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

1. DFL Cost and Hours


The DFL hours were calculated using the method outlined by Jamieson and Church (2015)

(1). The total DFL cost was obtained by summing the products of the total DFL factor and purchase

cost of each equipment. The process and project contingencies of 0% and 40%, respectively, were

then applied onto this value. The DFL cost for this project is summarized in Table K1 below:

Table K1: DFL Cost Summary


Unit Equipment Cost DFL Factor DFL Cost
($MM)
E-81C $0.59 1.08 $0.64
E-85A/B $0.55 0.84 $0.47
C-83 $0.87 2.53 $2.21
C-87 $0.28 1.70 $0.47
C-80 Packing $0.74 0.05 $0.04
C-82 Packing $1.06 0.05 $0.05
Total ($MM) $3.88
Process Contingency (0%) $0
Project Contingency (40%) $1.55
Total DFL Cost ($MM) $5.43

The current labourer salaries for the Fort McMurray region were obtained from Living In

Canada.com and Indeed.com (2) (3). Using the presentation on Project Labour Estimates and

Project Planning as a guideline, a payroll burden factor of 1.75 was chosen to account for the

employer’s contribution to the Canada Pension Plan (CPP), employment insurance (EI), company

pension plan, health benefits, and life insurance on behalf of the employee (1). This factor is

applied to the calculated average hourly rate received by the labourer in order to obtain the total

DFL hourly rate. Table K2 summarizes the assumed worker distribution and rates for the

calculation of DFL hours:

K-1
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Table K2: Labourer Rates and Hours


Trade Number of Workers Hourly Rate (C$)
Crane Operator 1 $44.00
Crane supporter 4 $30.00
Pipe Fitter 9 $42.12
Column Technician 10 $26.00
Instrument Technician 10 $41.57
Welder 4 $39.24
Average Hourly Wage $36.20
Total Number of Workers 38
Payroll Burden Factor 1.75
DFL Hourly Rate $63.36
Total DFL Hours 85717

The hourly wages were calculated as follows:

𝐴𝑣𝑒𝑟𝑎𝑔𝑒 𝐻𝑜𝑢𝑟𝑙𝑦 𝑊𝑎𝑔𝑒

$44.00 + 4($30.00) + 9($42.12) + 10($26.00) + 10($41.57) + 4($39.24)


=
38

= $36.20/ℎ

𝐷𝐹𝐿 𝐻𝑜𝑢𝑟𝑙𝑦 𝑅𝑎𝑡𝑒 = 𝐴𝑣𝑒𝑟𝑎𝑔𝑒 𝐻𝑜𝑢𝑟𝑙𝑦 𝑊𝑎𝑔𝑒 ∗ 𝑃𝑎𝑦𝑟𝑜𝑙𝑙 𝐵𝑢𝑟𝑑𝑒𝑛 𝐹𝑎𝑐𝑡𝑜𝑟 = $36.20 ∗ 1.75

= $63.36/ℎ

The total DFL hours was calculated by dividing the total DFL cost by the DFL hourly rate:

𝐷𝐹𝐿 𝐶𝑜𝑠𝑡 $5,430,747


𝐷𝐹𝐿 𝐻𝑜𝑢𝑟𝑠 = = = 85717 𝑚𝑎𝑛ℎ𝑜𝑢𝑟𝑠
𝐷𝐹𝐿 𝐻𝑜𝑢𝑟𝑙𝑦 𝑅𝑎𝑡𝑒 $63.36

Based on the correlation presented in Guthrie (1974), this number of manhours indicates an

approximate construction duration of 7 months (4).

K-2
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Figure K1: Field Duration vs. Direct Labour Manhour Correlation from Guthrie (1974)

2. Engineering Cost and Hours


The engineering cost was taken as combination of the 18% of the total module capital plus

the project contingencies and the 3% owner’s cost. The calculation of the engineering hours uses

a similar method as the DFL hour calculation. The current wages for engineers were obtained from

Alis.com (5). Table K3 summarizes the assumed distribution and rates of the engineering

workforce in this project:

K-3
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Table K3: Engineering Rates and Hours


Discipline Number of Workers Hourly Rate (C$)
Civil/Structural 5 $50.43
Chemical 5 $52.20
Mechanical 5 $52.87
Electrical 5 $48.35
Average Hourly Wage $50.96
Total Number of Workers 20
Payroll Burden Factor 1.75
DFL Hourly Rate $89.18
Total Engineering Hours 35381

The hourly wages were calculated as follows:

5($50.43) + 5($52.20) + 5($52.87) + 5($48.35)


𝐴𝑣𝑒𝑟𝑎𝑔𝑒 𝐻𝑜𝑢𝑟𝑙𝑦 𝑊𝑎𝑔𝑒 = = $50.96/ℎ
20

𝐷𝐹𝐿 𝐻𝑜𝑢𝑟𝑙𝑦 𝑅𝑎𝑡𝑒 = 𝐴𝑣𝑒𝑟𝑎𝑔𝑒 𝐻𝑜𝑢𝑟𝑙𝑦 𝑊𝑎𝑔𝑒 ∗ 𝑃𝑎𝑦𝑟𝑜𝑙𝑙 𝐵𝑢𝑟𝑑𝑒𝑛 𝐹𝑎𝑐𝑡𝑜𝑟 = $50.96 ∗ 1.75

= $89.18/ℎ

The total engineering hours was calculated by dividing the total engineering cost by the

engineering hourly rate:

𝐸𝑛𝑔𝑖𝑛𝑒𝑒𝑟𝑖𝑛𝑔 𝐶𝑜𝑠𝑡 $5,430,747


𝐸𝑛𝑔𝑖𝑛𝑒𝑒𝑟𝑖𝑛𝑔 𝐻𝑜𝑢𝑟𝑠 = = = 35381 𝑚𝑎𝑛ℎ𝑜𝑢𝑟𝑠
𝐸𝑛𝑔𝑖𝑛𝑒𝑒𝑟𝑖𝑛𝑔 𝐻𝑜𝑢𝑟𝑙𝑦 𝑅𝑎𝑡𝑒 $89.18

3. Manpower Profile
Tables K4 and K5 summarize the prescribed labour and engineering manpower

distributions, respectively, throughout the project timeline. Each distribution is based upon the

dates and durations outlined in the project execution plan. The tradesmen are assumed to be

working on 14 day on 2 day off shifts with 12 hour days. This totals up to approximately 336

K-4
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

working hours per month. The engineers are assumed to be working on 40 hour weeks, totaling up

to approximately 160 working hours per month.

Table K4: Labour Hour Distribution


Period Fraction of Total Hours Hours per Month
Mar 2021 0.05 4286
Apr 2021 0.1 8572
May – Aug 2021 0.4 8572
Sept – Oct 2021 0.3 12858
Nov 2021 0.1 8572
Dec 2021 0.05 4286

Table K5: Engineering Hour Distribution


Period Fraction of Total Hours Hours per Month
Jan – Apr 2020 0.05 442
May – Aug 2020 0.3 2654
Sept 2020 – Mar 2021 0.4 2022
Apr -Sept 2021 0.15 885
Oct 2021 0.05 1769
Nov 2021 0.03 1061
Dec 2021 0.02 708

4. Capital Expenditure Profile


The capital expenditure profile is divided into engineering, procurement, and construction

portions. The engineering cost is assumed to encompass the cost of procurement. Figure K2

presents the capital expenditure profile throughout the project timeline.

K-5
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

$900,000 10,000,000

$800,000 Engineering & Procurement 9,000,000

Cumulative Capital Expenditure (C$)


Construction 8,000,000
$700,000
Capital Expenditure (C$)

Cumulative 7,000,000
$600,000
6,000,000
$500,000
5,000,000
$400,000
4,000,000
$300,000
3,000,000
$200,000
2,000,000

$100,000 1,000,000

$0 0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Number of Months

Figure K2: Capital Expenditure Profile

K-6
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

5. Reference
1. Jamieson & Church. Project Labour Estimates and Project Planning. Edmonton, AB,

Canada : s.n., 2015.

2. Average Salary in Canada. Living in Canada. [Online] https://www.livingin-

canada.com/work-salaries-wages-canada.html.

3. Find Salaries. Indeed. [Online]

https://ca.indeed.com/salaries?from=headercmplink&attributionid=.

4. Guthrie, Kenneth M. Process Plant Estimating Evaluation and Control. Solana Beach :

Craftsman Book Company of America, 1974.

5. Wages and Salaries. Alis. [Online] https://alis.alberta.ca/occinfo/wages-and-salaries-in-

alberta/.

K-7
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Appendix L: Safety and Risk Assessments


Description
This Appendix contains the safety and risk assessments completed for the Revamp of CO 2

recovery plant project and identifies process hazards and their mitigation strategies. The

application of Inherently Safer Design principles, completed checklist-based risk analysis, What

If? Analysis on the process flow diagram, Hazard and Operability Study for the new heat

exchanger (E-85) P&ID, and the DOW Fire and Explosion Index (F&EI) and Chemical Exposure

Index (CEI) can all be found in this Appendix.

Table of Contents
1. Inherently Safer Design (ISD) Principles ..............................................................................L-1
1.1. Simplify ..........................................................................................................................L-1
1.2. Moderate .........................................................................................................................L-1
1.3. Minimize ........................................................................................................................L-2
1.4. Substitution .....................................................................................................................L-2
2. Hazard Identification Checklist .............................................................................................L-2
2.1. Base Case Checklist .......................................................................................................L-3
2.2. 112% Case Checklist ......................................................................................................L-5
2.3. 125% Case Checklist ......................................................................................................L-7
3. PHA and HAZOP Methodology ............................................................................................L-9
3.1. Assumptions .................................................................................................................L-12
4. What If? Analysis ................................................................................................................L-13
4.1. Overview ......................................................................................................................L-13
4.2. Node Definition ............................................................................................................L-13
4.3. Node and Equipment Summary ...................................................................................L-15
4.4. Base Case What If? Analysis Results...........................................................................L-18
4.5. 112% and 125% Redesign Cases What If? Analysis Results ......................................L-36
4.5.1. 112% Redesign Case Recommendations ...............................................................L-36

i
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

4.5.2. 125% Redesign Case Recommendations ...............................................................L-37


5. HAZOP Analysis .................................................................................................................L-38
5.1. Overview ......................................................................................................................L-38
5.2. HAZOP Results ............................................................................................................L-38
5.3. List of Recommendations and Implications .................................................................L-42
6. Dow Fire and Explosion Index ............................................................................................L-43
7. Dow Chemical Exposure Index ...........................................................................................L-65
7.1. Sample calculations for the Chemical Exposure Index ................................................L-65
8. Applicable Safety Regulations and Code Requirements .....................................................L-68
8.1. Pressure Equipment Safety Regulation ........................................................................L-68
8.2. Electrical Code .............................................................................................................L-69
8.3. Plumbing Code .............................................................................................................L-69
8.4. Alberta Occupational Health and Safety (OHS) Act....................................................L-69
8.5. Fire Code ......................................................................................................................L-70
8.6. Canada Labour Code ....................................................................................................L-70
List of References ......................................................................................................................L-71

ii
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

1. Inherently Safer Design (ISD) Principles


Inherently safe designs are those that aim to avoid hazards instead of controlling them. The

minimize, substitute, moderate, and simplify ISD principles were considered for this project and

the findings are outlined below. However, it was determined that there were minimal ISD

principles that could be applied to this project, since the project is brownfield and the technology

is already very well understood.

1.1. Simplify

The client had requested the capacity redesigns to be made with minimal pump-arounds and

equipment modifications. Thus, the solution for the 112% was achieved through the optimization

of operating conditions and utility requirements alone. For the 125% redesign case, several

equipment additions and modifications were made. However, the changes were relatively simple.

For columns, the random packing was changed to a different type. The increased duty of the

lean/rich amine exchangers (E-81 A/B) was achieved by adding another plate and frame exchanger

with the same specifications as existing ones. The new lean amine cooler (E-85) is a shell and tube

heat exchanger which is very widely used and understood in industry. Finally, the Reflux Vessel

(C-83) and Absorber Overhead K.O Drum (C-87) were simply redesigned with a larger diameter

to achieve the required separation. There are no major equipment overhauls or complex changes

required to implement the selected solution.

1.2. Moderate

To achieve the required CO2 recovery for the 112% redesign, and 125% redesign cases, it was

found that most of the streams could operate at more moderate conditions than the design case.

L-1
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

This can be seen when comparing the temperatures and pressures on the stream tables between the

different cases. The main exception to this observation is the flow rate of the process streams,

which was consistently raised across the redesign cases.

1.3. Minimize

There are no vessels within the facility designed to store large volumes of chemicals aside from

the amine make-up vessel. This vessel is designed with enough capacity to store the whole solution

inventory of the unit in case of maintenance. Since the increase in flow rate of the process streams

was unavoidable to meet the project design criteria, no minimize ISD principles were found to be

applicable for this project.

1.4. Substitution

Different amine solutions were researched to see if there were safer alternatives to MDEA.

However, it was discovered that MDEA had several processing advantages over other amine

solution alternatives such as diethanolamine (DEA), monoethanolamine (MEA),

diisopropanolamine (DIPA) and diglycolamine (DGA), which are known to be more corrosive

(1). No substitution ISD principles were found to be applicable for this project.

2. Hazard Identification Checklist


A hazard identification checklist was created for the base case, 112% redesign, and 125%

redesign cases. To avoid redundancy, only additional hazards resulting from the design have

been considered in the 112% and 125% design cases.

L-2
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

2.1. Base Case Checklist

Q1: Could the design result in… Q1 Event? Q2 Hazard? Explain Q1 what? and Q2 why?
Q2: If yes, could this result in a hazard? Yes No Yes No
Situations where equipment (vessel, heat exchanger, pump, Distillation Columns: Over
etc.) fails to carry out it’s intended duty? What happens? pressurization which results in
rupture
Separators: Over pressurization
which results in rupture
Heat Exchanger: Blockage causing
leaking or liquid spray. Tube leaks
Pump: Cavitation, overheating,
motor runout, deadhead or
hydraulic surge can result in
equipment damage, explosion
and/or leakage.
Compressors: Compressor surge
or excessive vibration can result,
equipment damage, fire, explosion,
and/or leakage
Valves: Seals fail or valves
become fouled or corroded,
resulting in leaks
Over pressure? Vacuum conditions? Equipment could explode and
result in injury or death
High flow? Low flow? High flow: Poor separation in
distillation columns and separation
vessels. Potential for spills, flanges
bursting, or equipment rupturing
Low flow: Surge in compressors or
pumps, resulting equipment
damage, explosion, and/or leakage
High temperature? Low Temperature? Temperatures of process fluids
range from approximately 34°C to
113.5°C. Risks for burns from
equipment ruptures or fluid leaks
Phase change? Multiple condensers and a reboiler
present in the process
Reaction? Other reactions? The absorption of CO2 with lean
amine solution is an exothermic
reaction. The temperature of the
amine should be kept below 180°C
to ensure the amine does not
degrade
Process upset condition? Process upsets could result in any
number of changes to operating
conditions for the various
equipment in the facility. The
equipment should be designed to
withstand a wide range of
conditions it may experience during
standard and upset conditions.
Heat transfer? Heat exchangers have the
potential to foul which results in
less efficient heat transfer. If
fouling goes on for long enough,
complete tube plugging may occur

L-3
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

which could result in leaking or


liquid spray
Other energy transfer? (specify) Electricity: Potential for shorting out
of equipment or electrocution
Solid formation? Aggregation? How did it form? Fouling of heat exchangers that
plug the tube sheets and reduce
heat transfer effectiveness. If tubes
plug entirely, there is risk of over
pressurization
Liquid formation? Condensation? How did it form?
Gas formation? Boiling? How did it form? Lean amine from LP Flash Stripper
is ~113.5°C and is heated from the
reboiler. High temperatures could
cause burns if this fluid leaks. Build
up of toxic gases such as MDEA
and CO may cause asphyxiation or
other negative health
consequences for workers
Control problems? Temperature? Process temperatures must be
monitored and controlled to ensure
effective operation of process
equipment and to ensure over
heating or equipment failure does
not occur
Pressure? Pressure must be monitored and
controlled to ensure equipment is
operating under their maximum
allowable working pressure and so
that equipment does not rupture or
otherwise fail
Flow? Flow must be controlled to
eliminate possible flange, seal and
equipment rupturing.
Level? Level of storage vessels must be
monitored and controlled to ensure
that over-filling and spills do not
occur
Composition?
Interface?
Loss of Containment? Syngas loss of containment could
result in fire or explosion. Release
of toxic gases may harm nearby
workers.
Flow problems? Backflow? Backflow into pumps,
compressors, columns, or storage
vessels could result in ineffective
operation and worst case severe
equipment damage or failure
Surge? Surge in the pumps or
compressors could result in
equipment damage, explosions
and/or leakage
Two phase? Compressors deal poorly with
liquids and solids in gas streams.
Multiple knockout drums and reflux
vessels are used in the process
design to separate these phases

L-4
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Erosion? Amine filter to remove particulates.


Assume pipe has been designed
for optimal velocity in the base
Corrosion? Material of construction issues? Piperazine is corrosive. A high
concentration would result in better
absorption of CO2 but would also
corrode the piping and equipment
faster. Materials of construction
should be carefully selected. Piping
and other equipment should be
frequently inspected
Contaminants? Fines in the semilean solution are
routed through a filter
Temperature limitations? Differential expansion? Equipment maximum operating
temperature should not be
exceeded to ensure equipment
works as designed
Fire? Syngas is highly flammable and
may catch fire if there is loss of
containment and an ignition source
Explosion? Explosion could occur due to
different equipment failures. This
hazard
Toxic Release? Asphyxiation? MDEA and CO are toxic
substances. Leakages would affect
the health of nearby workers.
Radiation?
Noise? Level expected? Equipment will generate noise.
More noise than expected when
not operating under ideal
conditions. Workers should have
proper hearing protection when
working in the area.
Pollution Contaminants? Air? Unless the process is enclosed
and has adequate ventilation, gas
leaks will be released to the
atmosphere and contaminate the
surrounding air
Water? Loss of containment of process
fluids may contaminate nearby
water sources if secondary
containment measures are not
employed
Soil? Loss of containment of process
fluids may contaminate nearby soil
if secondary containment
measures are not employed

2.2. 112% Case Checklist

Q1: Could the design result in... Q1 Event? Q2 Hazard? Explain Q1 what? and Q2 why?
Q2: If yes, could this result in a hazard? Yes No Yes No
Situations where equipment (vessel, heat exchanger, pump, No new hazards
etc.) fails to carry out it’s intended duty? What happens?

L-5
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Over pressure? Vacuum conditions? No new hazards


High flow? Low flow? The 112% design case involves an
increase in feed flow rate. This
increased flow rate affect operator
reaction time for alarms as well as
flow rates through the process
piping.
High temperature? Low Temperature? Stream temperatures generally
decrease as a result of the
operating condition changes. The
highest simulated stream
temperature for the 112% case is
113.7C, and the lowest
temperature is 34.0C. No new
hazards.
Phase change? No new hazards
Reaction? Other reactions? No new hazards
Process upset condition? Since the 112% design case has
increased flow rates, it will change
the range of conditions that the
equipment may experience.
Therefore, it is necessary to test
and re calibrate the equipment to
ensure that the wide range of
conditions can be managed.
Heat transfer? No new hazards
Other energy transfer? (specify) The 112% design case involved an
increase in energy input. It is
important to make sure that the
equipment is capable of handling
the increased energy input.
Solid formation? Aggregation? How did it form? No new hazards
Liquid formation? Condensation? How did it form? N/A
Gas formation? Boiling? How did it form? No new hazards
Control problems? Temperature? The 112% design case often has
lower temperatures than the base
case so the likelihood of
overheating the equipment is
decreased.
Pressure? Due to the increased flowrate, the
risk of over pressure is increased.
It its important to monitor and
control the equipment to ensure
that it does not rupture or fail
during operation.
Flow? The increase in flowrate would
affect the reaction time for the
alarms and level controls within the
system. If the flowrate is at a high
enough rate that a vessel could fill
up before the level control alarms
could indicate, it could pose a
problem.
Level? The CO2 absorber, LP Flash
Stripper, and several other process
vessels have level controllers
attached. Due to the increased flow

L-6
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

rate, the reaction time to respond


to alarms would be reduced.
Composition? N/A
Interface? N/A
Loss of Containment? No new hazards
Flow problems? Backflow? No new hazards
Surge? No new hazards
Two phase? No new hazards
Erosion? Higher flow rates may increase the
velocity of fluid in the piping,
causing more erosion
Corrosion? Material of construction issues? Potentially increased erosion in
pipes due to increased velocity
Contaminants? No new hazards
Temperature limitations? Differential expansion? No new hazards
Fire? No new hazards
Explosion? No new hazards
Toxic Release? Asphyxiation? No new hazards
Radiation? N/A
Noise? Level expected? Equipment running at higher
throughput may generate
additional noise. Re-evaluate
hearing protection requirements if
necessary
Pollution Contaminants? Air? No new hazards
Water? No new hazards
Soil? No new hazards

2.3. 125% Case Checklist

Q1: Could the design result in... Q1 Event? Q2 Hazard? Explain Q1 what? and Q2 why?
Q2: If yes, could this result in a hazard? Yes No Yes No
Situations where equipment (vessel, heat exchanger, pump, No new hazards
etc.) fails to carry out it’s intended duty? What happens?
Over pressure? Vacuum conditions? No new hazards
High flow? Low flow? The 125% design case involves an
increase in feed flow rate. This
increased flow rate affect operator
reaction time for alarms as well as
flow rates through the process
piping.
High temperature? Low Temperature? Stream temperatures generally
decrease as a result of the
operating condition changes. The
highest simulated stream
temperature for the 125% case is
114.5C, and the lowest

L-7
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

temperature is 34.0C. No new


hazards.
Phase change? No new hazards
Reaction? Other reactions? No new hazards
Process upset condition? Since the 125% design case has
increased flow rates as well as the
addition of new equipment, it will
change the range of conditions that
the equipment may experience.
Therefore, it is necessary to test
and recalibrate the equipment to
ensure that the wide range of
conditions can be managed.
Heat transfer? Additional heat exchangers have
the potential to foul which results in
less efficient heat transfer.
Other energy transfer? (specify) The 125% design case involves a
drastic increase in energy input
due to the change in process
inputs as well as the addition of
new equipment. It is important to
make sure that the equipment can
handle the increased energy input.
Solid formation? Aggregation? How did it form? No new hazards
Liquid formation? Condensation? How did it form? N/A
Gas formation? Boiling? How did it form? No new hazards
Control problems? Temperature? The 125% design case often has
lower temperatures than the base
case so the likelihood of
overheating the equipment is
decreased.
Pressure? Due to the increased flowrate, the
risk of over pressure is increased.
It its important to monitor and
control the equipment to ensure
that it does not rupture or fail
during operation.
Flow? The increase in flowrate would
affect the reaction time for the
alarms and level controls within the
system. If the flowrate is at a high
enough rate that a vessel could fill
up before the level control alarms
could indicate, it could pose a
problem.
Level? The CO2 absorber, LP Flash
Stripper, and several other process
vessels have level controllers
attached. Due to the increased flow
rate, the reaction time to respond
to alarms would be reduced.
Composition? N/A
Interface? N/A
Loss of Containment? No new hazards
Flow problems? Backflow? No new hazards

L-8
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Surge? No new hazards


Two phase? No new hazards
Erosion? Higher flow rates may increase the
velocity of fluid in the piping,
causing more erosion
Corrosion? Material of construction issues? Potentially increased erosion in
pipes due to increased velocity
Contaminants? No new hazards
Temperature limitations? Differential expansion? No new hazards
Fire? No new hazards
Explosion? No new hazards
Toxic Release? Asphyxiation? No new hazards
Radiation? N/A
Noise? Level expected? Equipment running at higher
throughput may generate
additional noise. Re-evaluate
hearing protection requirements if
necessary
Pollution Contaminants? Air? No new hazards
Water? No new hazards
Soil? No new hazards

3. PHA and HAZOP Methodology


To complete the PHA What-If? analysis and the HAZOP, the process was first divided into

manageable nodes. For the PHA, four nodes were defined using the CO2 Removal Unit PFDs and

were selected to be as extensive as possible to minimize the chances of hazardous consequences

being missed. For the HAZOP, the node was defined around the P&ID generated for the new lean

amine cooler (E-85). The hazards identified using the checklist PFD based analysis above were

used to guide the formulation of guide questions for the PHA and HAZOP. Sections 4.2 and 4.3

of this Appendix detail the process operating conditions for the base case, which were also used to

help guide the formulation of guide questions for the PHA and HAZOP analyses. These guide

questions were then used to determine potential hazardous scenarios and their causes that could

occur within the node.

L-9
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

The consequences of these identified hazardous scenarios were then quantitatively evaluated

using the risk matrix shown in Figure H1 below. The matrix was based on CNRL’s corporate risk

matrix. The risk ranking selected for a given scenario was assigned based on group consensus and

best judgement of the team members. The initial risk rating was assigned assuming that no

safeguards or controls were in place. After implementation of engineering safeguards and

administrative controls, the risk rating for each hazardous scenario was re-evaluated. If the residual

risk of the hazardous scenario was unacceptable or conditionally tolerable, additional

recommendations were considered to ensure that the process could be properly risk managed.

A team knowledgeable in the project equipment and hazard assessment methodology

conducted the What If? PHA and HAZOP. The team consisted of five engineering students from

Okane Engineering: Brendan Wong, Evans Kwak, Nympha Escobar, Kaitlin Wong, and Bryan

Lee. Brendan Wong was assigned the PHA Leader role, Evans Kwak was assigned the PHA

Facilitator role, and Bryan Lee was assigned the PHA Secretary role. PHA and HAZOP team

meeting results were recorded directly into an Excel spreadsheet. The complete Excel worksheets

created from the PHA and HAZOP analyses are provided in Sections 4.4 and 5.2 of this report.

L-10
L-11
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

3.1. Assumptions
Several assumptions were made when conducting the PHA and HAZOP analyses:

• Organizational and institutional factors such as substandard practices or conditions or

insufficient training were ruled out as plausible main causes of hazardous events. The

operators were assumed to have enough training and operate the equipment according to

written instructions and procedures

• As this design involves a capacity increase of a brownfield site, it was determined

existing startup and shutdown procedures were sufficient in the design cases where

equipment was not altered (Base Case and 112% Design Case)

• Relief valves and other equipment were assumed to have been designed, installed, and

inspected properly according to applicable codes and regulations. They were also

assumed to be in good working order

• Materials of construction for piping, gaskets, and other process equipment were assumed

to have been correctly selected according to applicable design codes and regulation and

with due consideration towards possible corrosion mechanisms

• The maximum consequence of an event that may have multiple outcomes was used to

determine the risk rating, ie. if an explosion occurred, the risk of personnel working

nearby was evaluated instead of a case where nobody is around

• Existing safeguards were assumed to already be in place to mitigate certain hazards. The

client should review these assumptions and re-evaluated whether additional controls are

necessary to manage risks to an ALARP level.

L-12
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

4. What If? Analysis


4.1. Overview
The PHA What If? Analysis was conducted to identify causes and consequences of major

safety hazards associated with the whole CO2 recovery unit at the CNRL Horizon Oil Sands

Upgrader Site during normal operating, maintenance, and upset conditions.

4.2. Node Definition


For the purposes of this PHA What if? analysis, the CO2 recovery unit was divided into

four separate nodes based on processing step in the CO2 recovery process. The nodes were made

to be as extensive as possible to minimize the chances of hazardous consequences being missed.

Marked up PFDs containing the node boundaries are shown in Figures L1 and L2 below.

#3

Figure L1. Marked up PFD (Drawing #CN49PFD) used in the What If? Analysis

L-13
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

#4

Figure L2. Marked up PFD (Drawing #CM49PFD) used in the What If? Analysis

The descriptions for each node are as follows:

Node 1. The CO2 Absorber is where syngas rises in countercurrent flow against a descending flow

of lean amine solution to remove CO2 from the syngas feed. Syngas leaving the top of the Absorber

is cooled with the condensed water removed in a knockout drum and is then sent to the PSA unit

outside battery limits.

Node 2. The rich amine solution from the bottom of the Absorber is flashed, with a portion of the

inert gases routed to SMR firing. The liquid Rich amine solution is regenerated into lean amine

solution in the LP Flash Stripper. The Stripper Reboiler provides the required heat to the bottom

L-14
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

of the Flash Stripper. Hot lean amine solution is withdrawn from the bottom of the LP Flash

Stripper, pumped to the lean/rich amine exchanger where it is cooled against semi-lean solution,

and then sent back to the LP Flash Stripper. H2O and CO2 vapours from the top of the LP Flash

Stripper are cooled in the Stripper Overhead Condenser and separated from the CO2 in a Reflux

Vessel. Water is pumped back to the top of the LP Flash Stripper.

Node 3. The lean amine solution is pumped to the air cooler. In the 125% case only, the lean amine

is further cooled by the lean amine cooler (E-85) before being sent back to the CO2 absorber.

Node 4. The CO2 gas stream is routed through a series of compressors, condensers, and knockout

drums prior to being sent the Product Dehydration Unit outside battery limits.

4.3. Node and Equipment Summary


To facilitate discussion, a high-level overview of the equipment contained within each node

was compiled and referenced throughout the PHA meeting process. This summary is provided in

Table L1 below for the base case design.

Table L1. Summary of equipment and operating conditions for each node

Node Equipment Tag & Base Case Commodity


Description Operating Conditions
1 C-80: CO2 Absorber Bottom/top: 40/57.5°C Amine Solution /
Bottom/top: 3325/3275 Syngas
kPag
1 E-80: CO2 Absorber Shell in/out: 45/40°C Shell Side: Syngas
Overhead Cooler Shell pressure: 3275 kPag Tube Side: Cooling
Tube in/out: 24/40°C Water
Tube pressure: 500 kPag

L-15
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

1 C-87: Absorber Overhead 40°C Synthesis Gas / Process


K.O Drum 3250 kPag Condensate
2 C-81: HP Amine Flash Drum 75°C Rich Amine / Flash Gas
600 kPag
2 E-81 A/B: Lean/Rich Amine Shell in/out: 114/83.4°C Lean Amine
Exchanger Shell pressure: 50 kPag Semilean Amine
Tube in/out: 73.4/103.4°C
Tube pressure: 640 kPag
2 G-81 A/B: Semilean Amine 73°C Lean Amine
Pump Suction: 329 kPag
Discharge: 662 kPag
2 C-82: LP Flash Stripper Bottom/top: 113.6/66.3°C Rich Amine / Wet CO2
Bottom/top: 50/40 kPag Gas
2 E-82: Stripper Reboiler 113.6°C Amine solution
50 kPag
2 E-83: Stripper Overhead Shell in/out: 65.6/45°C Shell: Carbon Dioxide
Condenser Shell pressure: 40 kPag Tube: Cooling Water
Tube in/out: 24/40°C
Tube pressure: 500 kPag
2 C-83: Reflux Vessel 45°C CO2 Gas / Process
20 kPag Condensate
2 G-83 A/B: Stripper Reflux 45°C Process Condensate
Pump Suction: 49kPag
Discharge: 776kPag
3 G-82A/B/C: HP Lean Amine 83°C Lean Amine
Pump Suction: 39 kPag
Discharge: 4199 kPag
3 E-84: Lean Amine Air In/out: 83.44/45°C Lean Amine
Cooler 4280 kPag

L-16
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

3 G-84: Amine Make Up Pump 10°C Lean Amine


(NNF) Suction: 15 kPag
Discharge: 668 kPag
3 C-84: Make Up Storage No information No information
Vessel (NNF)
4 E-101: Interstage Cooler Shell in/out: 150/42.5°C Shell: CO2 Product
Shell pressure: 257.3 kPag Tube: Cooling Water
Tube in/out: 24/38°C
Tube pressure: 257.3 kPag
4 E-102: Interstage Cooler Shell in/out: 150/42.5°C Shell: CO2 Product
Shell pressure: 992.9 kPag Tube: Cooling Water
Tube in/out: 24/38°C
Tube pressure: 257.3 kPag
4 E-103: Interstage Cooler Shell in/out: 150.2°C/34°C Shell: CO2 Product
Shell pressure: 3190 kPag Tube: Cooling Water
Tube in/out: 24/38°C
Tube pressure: 930 kPag
4 K-100: CO2 Product In/out: 44.4/150°C CO2 Product
Compressor In/out: 19/257.3kPag
4 K-101: CO2 Product In/out: 42.5/150°C CO2 Product
Compressor In/out: 257.3/992.9 kPag
4 K-102: CO2 Product In/out: 42.5/150.2°C CO2 Product
Compressor In/out: 992.9/3190kPag
4 D-100: Knockout Drum 42.5°C CO2 Product and Water
257.3 kPag
4 D-101: Knockout Drum 42.5°C CO2 Product and Water
992.85kPag

L-17
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

The Material Safety Data Sheets for all process components were also obtained to ensure all

PHA members were familiar with the common hazards associated with each process stream. The

Workplace Hazardous Materials Information System (WHMIS) symbols for each component are

summarized in Table L2 below.

Table L2: Summary of WHMIS hazard classifications for process components


Health Acute Pressurized
Compound Oxidizer Flammability Hazard Irritant Toxicity Gas Corrosive
CO Extremely Yes Yes Yes
CO2 Yes
H2 Extremely Yes
H2O
CH4 Extremely Yes
C2H6 Extremely Yes
C3H8 Extremely Yes
N-C4H10 Extremely Yes Yes
N-C5H12 Extremely Yes Yes
N2 Yes
O2 Yes Yes
MDEA Yes
Piperazine Yes Yes Yes

It should be noted that H2S is removed in hydro-desulphurization reactors prior to entering

the project boundaries and is therefore not included in the analysis. Additionally, chemicals such

as antifoam agent and potash/soda used for cleaning/degreasing were not considered due to their

limited use.

4.4. Base Case What If? Analysis Results


The completed What If? analysis worksheets for the base case are as follows:

L-18
L-19
L-20
L-21
L-22
L-23
L-24
L-25
L-26
L-27
L-28
L-29
L-30
L-31
L-32
L-33
L-34
L-35
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

4.5. 112% and 125% Redesign Cases What If? Analysis Results
After speaking with Mr. Wen regarding the scope of the PHA acceptable for the project, it was

decided that completing a separate analysis for all three cases would be very time consuming and

would have a significant amount of duplicate information. Most hazards were determined to have

little change to likelihood or consequence as a result of the capacity increase. Thus, after the What

If? analysis was completed for the base case, the What If? questions were re-considered for the

112% and 125% redesign cases and evaluated qualitatively instead.

4.5.1. 112% Redesign Case Recommendations


• Existing pressure relief devices should be reviewed and re-rated if necessary, to address

the increased flow rate through the different equipment. One key area of concern was the

CO2 absorber, which saw a 15 kPa increase to the bottoms operating pressure

• The increased flow rate may reduce the time available for operators to respond to level

alarms. Proper management of change procedures should be followed

• Verify equipment operating data and material balance specifications to ensure maximum

flow rates, pressure drops, and other process parameters are permissible under the

existing equipment design. There were several discrepancies identified when reviewing

the information provided by CNRL

• Confirm the process lines sizing completed for this project with existing pipe sizing and

material specifications to confirm the identification of high velocity lines so that

preventative measures can be taken to reduce erosion-corrosion

• The CO2 loading factor for the 112% case was 0.66 mol CO2/mol amine which was 0.01

higher than the maximum recommended value of 0.65 mol CO2/mol amine. This is

L-36
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

unlikely to cause corrosion issues due to the lower operating temperatures used, but

should be taken note of by the unit’s Corrosion Control Document

4.5.2. 125% Redesign Case Recommendations


• Existing pressure relief devices should be reviewed and re-rated if necessary, to address

the increased flow rate through the different equipment. Areas of concern included the

CO2 absorber, which saw a 30 kPa increase to the bottoms operating pressure, and the LP

Flash Stripper which saw a 5 kPa increase to the bottoms operating pressure

• The increased flow rate may reduce the time available for operators to respond to level

alarms. Proper management of change procedures should be followed

• Verify equipment operating data and material balance specifications to ensure maximum

flow rates, pressure drops, and other process parameters are permissible under the

existing equipment design. There were several discrepancies identified when reviewing

the information provided by CNRL

• Confirm the process lines sizing completed for this project with existing pipe sizing and

material specifications to confirm the identification of high velocity lines so that

preventative measures can be taken to reduce erosion-corrosion

• The new heat exchanger (E-85) is approximately 45 m away from the lean amine air

cooler (E-84), and approximately 30 m away from the CO2 absorber (C-80). The HP

Amine Pump (G-82A/B/C) supplies all the head for E-84 and E-85 prior to being sent

back into the CO2 absorber. Although the discharge head of the pump (4199 kPa) is

significantly higher than the operating pressure of C-80 (3325 kPa), the pressure losses

L-37
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

between G-82 and C-80 should be evaluated using existing plant information that is

unavailable to Okane Engineering at this time

• Ensure new or modified equipment is properly winterized (electrical tracing)

• Verify placement of new equipment with existing plot plan and operator input so that

there are no slips, trips, and fall issues, or issues to access for maintenance

• Ensure new random packing material is properly degreased and de-oiled to prevent

foaming in the CO2 Removal Unit

• Ensure start-up and shutdown sequences for the facility are reviewed and revised to

account for the new or modified process equipment

• The 125% redesign also uses a CO2 loading factor of 0.71 mol CO2/mol amine. This is

0.06 higher than the recommended limit but is still within the maximum equilibrium CO2

loading capacity of 1.0 mol CO2/mol amine (2). This may pose issues for corrosion if the

125% capacity redesign is explored further

5. HAZOP Analysis
5.1. Overview
A HAZOP was completed on the P&ID created for the new lean amine cooler (E-85). Guide

words were formulated to consider process deviations for parameters during commissioning,

steady state operation, startup-up, and shutdown. Engineering safeguards were implemented

early into the heat exchanger design process to ensure risks could be properly managed.

5.2. HAZOP Results


The P&ID used for the HAZOP is shown in Appendix E. The completed HAZOP worksheet

and list of engineering safeguards considered for E-85 is shown on the subsequent page

L-38
L-39
L-40
L-41
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

5.3. List of Recommendations and Implications


The safeguards for E-85 are shown under the “safeguards” column in the worksheets above for

each deviation considered. The full list of recommendations made as a result of the HAZOP

analysis and their implications are detailed below:

• Ensure that E-85 is properly winterized so that there is minimal risk of equipment and/or

lines freezing during exceptionally cold winters

• Confirm the process line sizes selected for the heat exchanger. The line sizing methods

employed for this project may not correspond to corporate standards and guidelines.

Differences in line sizes would affect PSV and PRV sizing

• The placement of E-85 should be confirmed with the existing plot plan and piping

isometrics. Operations and maintenance should also be consulted. The reference plot plan

provided by CNRL for this project was a very rough sketch, and the HAZOP members are

unfamiliar with the piping layout and high traffic areas of the CO2 Removal Unit.

Equipment placement for E-85 was selected based on optimizing maintenance access and

piping length, and may not actually be suitable if the location is obstructed by obstacles

not shown on the provided plot plan

• The startup/shutdown procedures for the CO2 Removal Unit must be updated to account

for this new piece of equipment

• The scope of the study was limited to the course requirements and available information.

It is recommended that a complete HAZOP analysis be undertaken that utilizes existing

P&IDs and which considers parameters for the CO2 removal unit as a whole. The study

L-42
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

should include representatives from engineering, operations, maintenance, business

management, and other functions that have adequate experience and process knowledge

6. Dow Fire and Explosion Index


The proposed project deals with syngas as one of the main properties utilized in the main

process streams. Syngas is a highly flammable material and poses a major threat to employees in

the event of a leak in the system or equipment and pipeline failures. This threat can be calculated

using the Dow Fire and Explosion Index (F&EI). To obtain an accurate understanding of the risk

posed by the process, the F&EI was calculated for the major vessels that contained syngas, for the

base case, the 112% design case, and the 125% design case.

Below are the plot plans with the exposure radius for each case as well as the F&EI

calculations. The electrical area classification is for every case is, division 1 class 1 explosion

proof.

L-43
SCALE (m) :

2.5 5 10 20
BATTERY LIMIT

OTHER
OTHER EQUIPMENT
EQUIPMENT

PIPE RACK
Pipe Rack Elevation:
Approximately 7 m
ROAD

E-84 C-85 C-84


PUMP G-86A

PUMP G-86A
G-84 PUMP G-82A PUMP
PUMP G-86B
G-82B PUMP

PUMP G-87A
G-82C PUMP

PUMP G-87B E-81A/B

OTHER G-81A PUMP

EQUIPMENT
E-82 G-81B PUMP

ROAD
C-83
PUMP G-83A/B

E-80
C-86 E-83
FTR-80
C-87

C-81
C-80
C-82

ROAD

PIPE RACK
Pipe Rack Elevation:
Approximately 7 m

OTHER OTHER
EQUIPMENT EQUIPMENT

OTHER
EQUIPMENT

Revamp of Carbon Dioxide Recovery Plant

PLOT PLAN – DESIGN CASE


BY: E. KWAK DRAWING NUMBER REV
CN49PLT 1
DATE: 2019/03/14

L-44
SCALE (m) :
BATTERY LIMIT
2.5 5 10 20

OTHER
OTHER EQUIPMENT
EQUIPMENT

PIPE RACK
Pipe Rack Elevation:
Approximately 7 m
ROAD

E-84 C-85 C-84


PUMP G-86A

PUMP G-86A
G-84 PUMP G-82A PUMP
PUMP G-86B
G-82B PUMP

PUMP G-87A
G-82C PUMP

PUMP G-87B E-81A/B

OTHER G-81A PUMP

EQUIPMENT
E-82 G-81B PUMP

ROAD
C-83
PUMP G-83A/B

E-80
C-86 E-83
FTR-80
C-87

C-81
C-80
C-82

ROAD

PIPE RACK
Pipe Rack Elevation:
Approximately 7 m

OTHER OTHER
EQUIPMENT EQUIPMENT

OTHER
EQUIPMENT

Revamp of Carbon Dioxide Recovery Plant

PLOT PLAN – DESIGN CASE


BY: E. KWAK DRAWING NUMBER REV
CN49PLT 1
DATE: 2019/03/14

L-45
SCALE (m)
SCALE (m) ::

2.5 55
2.5 10
10 20
20
BATTERY LIMIT
BATTERY LIMIT

OTHER
OTHER
OTHER
OTHER EQUIPMENT
EQUIPMENT
EQUIPMENT
EQUIPMENT

PIPE
PIPE RACK
RACK
Pipe
Pipe Rack
Rack Elevation:
Elevation:
Approximately
Approximately 77 m
m
ROAD
ROAD

E-84
E-84 C-85
C-85 C-84
C-84
PUMP
PUMP G-86A
G-86A

PUMP
PUMP G-86A
G-86A
G-84
G-84 PUMP
PUMP G-82A
G-82A PUMP
PUMP
PUMP
PUMP G-86B
G-86B
G-82B
G-82B PUMP
PUMP

PUMP
PUMP G-87A
G-87A
G-82C
G-82C PUMP
PUMP
PUMP
PUMP G-87B
G-87B E-81A/B
E-81A/B

OTHER
OTHER G-81A
G-81A PUMP
PUMP

EQUIPMENT
EQUIPMENT
E-82 G-81B
G-81B PUMP
PUMP
E-82
ROAD
ROAD
C-83
C-83 PUMP
PUMP G-83A/B
G-83A/B
E-85
E-80
E-80
C-86
C-86 E-83
E-83
FTR-80
FTR-80
E-85 C-87
C-87

C-81
C-81
C-80
C-80
C-82
C-82

ROAD
ROAD

PIPE
PIPE RACK
RACK
Pipe
Pipe Rack
Rack Elevation:
Elevation:
Approximately
Approximately 77 m
m

OTHER
OTHER OTHER
OTHER
EQUIPMENT
EQUIPMENT EQUIPMENT
EQUIPMENT

OTHER
OTHER
EQUIPMENT
EQUIPMENT
Revamp of Carbon Dioxide Recovery Plant

PLOT PLAN – DESIGN CASE


BY:
BY: E.
E. KWAK
KWAK DRAWING
DRAWING NUMBER
NUMBER REV
REV
CN49PLT
CN49PLT 11
DATE:
DATE: 2019/03/14
2019/03/14

L-46
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Unit 1. Carbon Dioxide Absorber (C-80) - Base Case State:


Prepared By: Evans Kwak Normal
Material Used in Process: Synthesis Gas Operation
Material Factor 21
Penalty Factor Penalty Factor
1. General Process Hazards
Range Used
Base Factor 1.00 1.00
A. Exothermic Reactions 0 - 1.25 0
B. Endothermic Reactions 0 - 0.40 0
C. Material Handling and Transfer 0 - 0.80 0
D. Enclosed or Indoor Process Units 0 - 0.90 0
E. Ease of Access 0 - 0.35 0.20
F. Drainage and Spill Control 0 - 0.5 0
General Process Hazards Factor (F1) 1.20
Penalty Factor Penalty Factor
2. Special Process Hazards
Range Used
Base Factor 1.00 1.00
A. Toxic Materials 0
B. Vacuum Operation 0.50 0
C. Operation Near Flammable Range 0 - 0.80 0
D. Dust Explosion 0 - 0.20 0
E. Pressure Penalty 0.84
F. Low Temperature Operation 0 - 0.30 0
G. Flammable Materials 0.82
H. Corrosion and Erosion 0 - 0.75 0.10
I. Leakage - Joints and Packing 0 -1.50 0.10
J. Fired Equipment 0
K. Hot Oil Heat Exchnage 0 - 1.15 0
L. Rotating Equipment 0.50 0
Special Process Hazards Factor (F2) 2.86
Process Unit Hazards Factor (F1 x F2 = F3) 3.43
Fire and Explosion Index (F3 x MF = F&EI) 72.03

L-47
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Loss of Control Credit Factors – Unit 1

Credit Credit Credit Credit


Feature Factor Factor Feature Factor Factor
Range Used Range Used

1. Process Control Credit Factor (C1)


a. Emergency Power 0.98 0.98 f. Inert Gas 0.94 to 0.99 1
b. Cooling 0.97 to 0.99 0.97 g. Operating Procedures 0.91 to 0.99 0.91
c. Explosion Control 0.84 to 0.98 1 h. Chemical Review 0.91 to 0.98 1
d. Emergency Shutdown 0.96 to 0.99 0.96 i. Other Analysis 0.91 to 0.98 0.94
e. Computer Control 0.93 to 0.99 0.97
C1 Value 0.76

2. Material Isolation Credit Factor (C2)


a. Remote Control 0.96 to 0.98 0.98 c. Drainage 0.91 to 0.97 0.97
b. Dump/Blowdown 0.96 to 0.98 0.98 d. Interlock 0.98 0.98
C2 Value 0.91

3. Fire Protection Credit (C3)


a. Leak Detection 0.94 to 0.98 0.98 f. Water Curtains 0.97 to 0.98 1
b. Structural Steel 0.95 to 0.98 0.98 g. Foam 0.92 to 0.97 1
c. Firewater Supply 0.94 to 0.97 1 h. Hand Extinguishers 0.93 to 0.98 0.98
d. Special Systems 0.91 1 i. Cable Protection 0.94 to 0.98 1
e. Sprinkler Systems 0.74 to 0.97 1
C3 Value 0.94

Loss Control Credit Factor (C1*C2*C3) 0.65

1. Fire & Explosion Index (F&EI) 72.03


2. Radius of Exposure 18.49 m
3. Area of Exposure 1074 m2
4. Value of Area of Exposure $ 2506132
5. Damage Factor 0.61
6. Base Maximum Probable Property Damage $ 1528741
7. Loss Control Credit Factor 0.65
8. Actual Maximum Probable Property Damage $ 994654
9. Maximum Probable Days Outage 20
10. Buisness Interruption $ 415738

L-48
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Unit 2. HP Amine Flash Drum (C-81) - Base Case State:


Prepared By: Evans Kwak Normal
Material Used in Process: Rich Amine Operation
Material Factor 16
Penalty Factor Penalty Factor
1. General Process Hazards
Range Used
Base Factor 1.00 1.00
A. Exothermic Reactions 0 - 1.25 0
B. Endothermic Reactions 0 - 0.40 0
C. Material Handling and Transfer 0 - 0.80 0
D. Enclosed or Indoor Process Units 0 - 0.90 0
E. Ease of Access 0 - 0.35 0.20
F. Drainage and Spill Control 0 - 0.5 0
General Process Hazards Factor (F1) 1.20
Penalty Factor Penalty Factor
2. Special Process Hazards
Range Used
Base Factor 1.00 1.00
A. Toxic Materials 0.60
B. Vacuum Operation 0.50 0
C. Operation Near Flammable Range 0 - 0.80 0
D. Dust Explosion 0 - 0.20 0
E. Pressure Penalty 0.42
F. Low Temperature Operation 0 - 0.30 0
G. Flammable Materials 0.02
H. Corrosion and Erosion 0 - 0.75 0.10
I. Leakage - Joints and Packing 0 -1.50 0.10
J. Fired Equipment 0
K. Hot Oil Heat Exchnage 0 - 1.15 0
L. Rotating Equipment 0.50 0
Special Process Hazards Factor (F2) 2.23
Process Unit Hazards Factor (F1 x F2 = F3) 2.68
Fire and Explosion Index (F3 x MF = F&EI) 42.88

L-49
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Loss of Control Credit Factors – Unit 2

Credit Credit Credit Credit


Feature Factor Factor Feature Factor Factor
Range Used Range Used

1. Process Control Credit Factor (C1)


a. Emergency Power 0.98 0.98 f. Inert Gas 0.94 to 0.99 1
b. Cooling 0.97 to 0.99 0.97 g. Operating Procedures 0.91 to 0.99 1
c. Explosion Control 0.84 to 0.98 1 h. Chemical Review 0.91 to 0.98 1
d. Emergency Shutdown 0.96 to 0.99 1 i. Other Analysis 0.91 to 0.98 0.94
e. Computer Control 0.93 to 0.99 1
C1 Value 0.89

2. Material Isolation Credit Factor (C2)


a. Remote Control 0.96 to 0.98 1 c. Drainage 0.91 to 0.97 0.97
b. Dump/Blowdown 0.96 to 0.98 0.98 d. Interlock 0.98 0.98
C2 Value 0.93

3. Fire Protection Credit (C3)


a. Leak Detection 0.94 to 0.98 1 f. Water Curtains 0.97 to 0.98 1
b. Structural Steel 0.95 to 0.98 1 g. Foam 0.92 to 0.97 1
c. Firewater Supply 0.94 to 0.97 1 h. Hand Extinguishers 0.93 to 0.98 0.98
d. Special Systems 0.91 1 i. Cable Protection 0.94 to 0.98 1
e. Sprinkler Systems 0.74 to 0.97 1
C3 Value 0.98

Loss Control Credit Factor (C1*C2*C3) 0.82

1. Fire & Explosion Index (F&EI) 42.88


2. Radius of Exposure 11.01 m
3. Area of Exposure 381 m2
4. Value of Area of Exposure $ 2262443
5. Damage Factor 0.375
6. Base Maximum Probable Property Damage $ 848416
7. Loss Control Credit Factor 0.82
8. Actual Maximum Probable Property Damage $ 692125
9. Maximum Probable Days Outage 15
10. Buisness Interruption $ 311804

L-50
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Unit 3. Absorber Overhead Knockout Drum (C-87) - Base Case State:


Prepared By: Evans Kwak Normal
Material Used in Process: Synthesis Gas Operation
Material Factor 21
Penalty Factor Penalty Factor
1. General Process Hazards
Range Used
Base Factor 1.00 1.00
A. Exothermic Reactions 0 - 1.25 0
B. Endothermic Reactions 0 - 0.40 0
C. Material Handling and Transfer 0 - 0.80 0
D. Enclosed or Indoor Process Units 0 - 0.90 0
E. Ease of Access 0 - 0.35 0.20
F. Drainage and Spill Control 0 - 0.5 0
General Process Hazards Factor (F1) 1.20
Penalty Factor Penalty Factor
2. Special Process Hazards
Range Used
Base Factor 1.00 1.00
A. Toxic Materials 0
B. Vacuum Operation 0.50 0
C. Operation Near Flammable Range 0 - 0.80 0
D. Dust Explosion 0 - 0.20 0
E. Pressure Penalty 0.83
F. Low Temperature Operation 0 - 0.30 0
G. Flammable Materials 0.82
H. Corrosion and Erosion 0 - 0.75 0.10
I. Leakage - Joints and Packing 0 -1.50 0.10
J. Fired Equipment 0
K. Hot Oil Heat Exchnage 0 - 1.15 0
L. Rotating Equipment 0.50 0
Special Process Hazards Factor (F2) 2.85
Process Unit Hazards Factor (F1 x F2 = F3) 3.42
Fire and Explosion Index (F3 x MF = F&EI) 72.03

L-51
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Loss of Control Credit Factors – Unit 3

Credit Credit Credit Credit


Feature Factor Factor Feature Factor Factor
Range Used Range Used

1. Process Control Credit Factor (C1)


a. Emergency Power 0.98 0.98 f. Inert Gas 0.94 to 0.99 1
b. Cooling 0.97 to 0.99 0.97 g. Operating Procedures 0.91 to 0.99 1
c. Explosion Control 0.84 to 0.98 1 h. Chemical Review 0.91 to 0.98 1
d. Emergency Shutdown 0.96 to 0.99 1 i. Other Analysis 0.91 to 0.98 0.94
e. Computer Control 0.93 to 0.99 1
C1 Value 0.89

2. Material Isolation Credit Factor (C2)


a. Remote Control 0.96 to 0.98 1 c. Drainage 0.91 to 0.97 0.97
b. Dump/Blowdown 0.96 to 0.98 0.98 d. Interlock 0.98 0.98
C2 Value 0.93

3. Fire Protection Credit (C3)


a. Leak Detection 0.94 to 0.98 1 f. Water Curtains 0.97 to 0.98 1
b. Structural Steel 0.95 to 0.98 1 g. Foam 0.92 to 0.97 1
c. Firewater Supply 0.94 to 0.97 1 h. Hand Extinguishers 0.93 to 0.98 0.98
d. Special Systems 0.91 1 i. Cable Protection 0.94 to 0.98 1
e. Sprinkler Systems 0.74 to 0.97 1
C3 Value 0.98

Loss Control Credit Factor (C1*C2*C3) 0.82

1. Fire & Explosion Index (F&EI) 71.86


2. Radius of Exposure 18.04 m
3. Area of Exposure 1069 m2
4. Value of Area of Exposure $ 2807131
5. Damage Factor 0.61
6. Base Maximum Probable Property Damage $ 1712350
7. Loss Control Credit Factor 0.82
8. Actual Maximum Probable Property Damage $ 1396909
9. Maximum Probable Days Outage 25
10. Buisness Interruption $ 519673

L-52
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Unit 4. Carbon Dioxide Absorber (C-80) – 112% Design Case State:


Prepared By: Evans Kwak
Design
Material Used in Process: Synthesis Gas
Material Factor 21
Penalty Factor Penalty Factor
1. General Process Hazards
Range Used
Base Factor 1.00 1.00
A. Exothermic Reactions 0 - 1.25 0
B. Endothermic Reactions 0 - 0.40 0
C. Material Handling and Transfer 0 - 0.80 0
D. Enclosed or Indoor Process Units 0 - 0.90 0
E. Ease of Access 0 - 0.35 0.20
F. Drainage and Spill Control 0 - 0.5 0
General Process Hazards Factor (F1) 1.20
Penalty Factor Penalty Factor
2. Special Process Hazards
Range Used
Base Factor 1.00 1.00
A. Toxic Materials 0
B. Vacuum Operation 0.50 0
C. Operation Near Flammable Range 0 - 0.80 0
D. Dust Explosion 0 - 0.20 0
E. Pressure Penalty 0.84
F. Low Temperature Operation 0 - 0.30 0
G. Flammable Materials 0.90
H. Corrosion and Erosion 0 - 0.75 0.10
I. Leakage - Joints and Packing 0 -1.50 0.10
J. Fired Equipment 0
K. Hot Oil Heat Exchnage 0 - 1.15 0
L. Rotating Equipment 0.50 0
Special Process Hazards Factor (F2) 2.94
Process Unit Hazards Factor (F1 x F2 = F3) 3.53
Fire and Explosion Index (F3 x MF = F&EI) 74.05

L-53
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Loss of Control Credit Factors – Unit 4

Credit Credit Credit Credit


Feature Factor Factor Feature Factor Factor
Range Used Range Used

1. Process Control Credit Factor (C1)


a. Emergency Power 0.98 0.98 f. Inert Gas 0.94 to 0.99 1
b. Cooling 0.97 to 0.99 0.97 g. Operating Procedures 0.91 to 0.99 0.91
c. Explosion Control 0.84 to 0.98 1 h. Chemical Review 0.91 to 0.98 1
d. Emergency Shutdown 0.96 to 0.99 0.96 i. Other Analysis 0.91 to 0.98 0.94
e. Computer Control 0.93 to 0.99 0.97
C1 Value 0.76

2. Material Isolation Credit Factor (C2)


a. Remote Control 0.96 to 0.98 0.98 c. Drainage 0.91 to 0.97 0.97
b. Dump/Blowdown 0.96 to 0.98 0.98 d. Interlock 0.98 0.98
C2 Value 0.91

3. Fire Protection Credit (C3)


a. Leak Detection 0.94 to 0.98 0.98 f. Water Curtains 0.97 to 0.98 1
b. Structural Steel 0.95 to 0.98 0.98 g. Foam 0.92 to 0.97 1
c. Firewater Supply 0.94 to 0.97 1 h. Hand Extinguishers 0.93 to 0.98 0.98
d. Special Systems 0.91 1 i. Cable Protection 0.94 to 0.98 1
e. Sprinkler Systems 0.74 to 0.97 1
C3 Value 0.94

Loss Control Credit Factor (C1*C2*C3) 0.65

1. Fire & Explosion Index (F&EI) 74.05


2. Radius of Exposure 19.01 m
3. Area of Exposure 1135 m2
4. Value of Area of Exposure $ 2506132
5. Damage Factor 0.62
6. Base Maximum Probable Property Damage $ 1553902
7. Loss Control Credit Factor 0.65
8. Actual Maximum Probable Property Damage $ 1010960
9. Maximum Probable Days Outage 21
10. Buisness Interruption $ 469831

L-54
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Unit 5. HP Amine Flash Drum (C-81) – 112% Design Case State:


Prepared By: Evans Kwak
Design
Material Used in Process: Rich Amine
Material Factor 16
Penalty Factor Penalty Factor
1. General Process Hazards
Range Used
Base Factor 1.00 1.00
A. Exothermic Reactions 0 - 1.25 0
B. Endothermic Reactions 0 - 0.40 0
C. Material Handling and Transfer 0 - 0.80 0
D. Enclosed or Indoor Process Units 0 - 0.90 0
E. Ease of Access 0 - 0.35 0.20
F. Drainage and Spill Control 0 - 0.5 0
General Process Hazards Factor (F1) 1.20
Penalty Factor Penalty Factor
2. Special Process Hazards
Range Used
Base Factor 1.00 1.00
A. Toxic Materials 0.60
B. Vacuum Operation 0.50 0
C. Operation Near Flammable Range 0 - 0.80 0
D. Dust Explosion 0 - 0.20 0
E. Pressure Penalty 0.42
F. Low Temperature Operation 0 - 0.30 0
G. Flammable Materials 0.02
H. Corrosion and Erosion 0 - 0.75 0.10
I. Leakage - Joints and Packing 0 -1.50 0.10
J. Fired Equipment 0
K. Hot Oil Heat Exchnage 0 - 1.15 0
L. Rotating Equipment 0.50 0
Special Process Hazards Factor (F2) 2.23
Process Unit Hazards Factor (F1 x F2 = F3) 2.68
Fire and Explosion Index (F3 x MF = F&EI) 42.91

L-55
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Loss of Control Credit Factors – Unit 5

Credit Credit Credit Credit


Feature Factor Factor Feature Factor Factor
Range Used Range Used

1. Process Control Credit Factor (C1)


a. Emergency Power 0.98 0.98 f. Inert Gas 0.94 to 0.99 1
b. Cooling 0.97 to 0.99 0.97 g. Operating Procedures 0.91 to 0.99 1
c. Explosion Control 0.84 to 0.98 1 h. Chemical Review 0.91 to 0.98 1
d. Emergency Shutdown 0.96 to 0.99 1 i. Other Analysis 0.91 to 0.98 0.94
e. Computer Control 0.93 to 0.99 1
C1 Value 0.89

2. Material Isolation Credit Factor (C2)


a. Remote Control 0.96 to 0.98 1 c. Drainage 0.91 to 0.97 0.97
b. Dump/Blowdown 0.96 to 0.98 0.98 d. Interlock 0.98 0.98
C2 Value 0.93

3. Fire Protection Credit (C3)


a. Leak Detection 0.94 to 0.98 1 f. Water Curtains 0.97 to 0.98 1
b. Structural Steel 0.95 to 0.98 1 g. Foam 0.92 to 0.97 1
c. Firewater Supply 0.94 to 0.97 1 h. Hand Extinguishers 0.93 to 0.98 0.98
d. Special Systems 0.91 1 i. Cable Protection 0.94 to 0.98 1
e. Sprinkler Systems 0.74 to 0.97 1
C3 Value 0.98

Loss Control Credit Factor (C1*C2*C3) 0.82

1. Fire & Explosion Index (F&EI) 42.91


2. Radius of Exposure 11.01 m
3. Area of Exposure 381 m2
4. Value of Area of Exposure $ 2262443
5. Damage Factor 0.375
6. Base Maximum Probable Property Damage $ 848416
7. Loss Control Credit Factor 0.82
8. Actual Maximum Probable Property Damage $ 692125
9. Maximum Probable Days Outage 15
10. Buisness Interruption $ 335594

L-56
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Unit 6. Absorber Overhead Knockout Drum (C-87) – 112% Design Case State:
Prepared By: Evans Kwak
Design
Material Used in Process: Synthesis Gas
Material Factor 21
Penalty Factor Penalty Factor
1. General Process Hazards
Range Used
Base Factor 1.00 1.00
A. Exothermic Reactions 0 - 1.25 0
B. Endothermic Reactions 0 - 0.40 0
C. Material Handling and Transfer 0 - 0.80 0
D. Enclosed or Indoor Process Units 0 - 0.90 0
E. Ease of Access 0 - 0.35 0.20
F. Drainage and Spill Control 0 - 0.5 0
General Process Hazards Factor (F1) 1.20
Penalty Factor Penalty Factor
2. Special Process Hazards
Range Used
Base Factor 1.00 1.00
A. Toxic Materials 0
B. Vacuum Operation 0.50 0
C. Operation Near Flammable Range 0 - 0.80 0
D. Dust Explosion 0 - 0.20 0
E. Pressure Penalty 0.83
F. Low Temperature Operation 0 - 0.30 0
G. Flammable Materials 0.90
H. Corrosion and Erosion 0 - 0.75 0.10
I. Leakage - Joints and Packing 0 -1.50 0.10
J. Fired Equipment 0
K. Hot Oil Heat Exchnage 0 - 1.15 0
L. Rotating Equipment 0.50 0
Special Process Hazards Factor (F2) 2.93
Process Unit Hazards Factor (F1 x F2 = F3) 3.51
Fire and Explosion Index (F3 x MF = F&EI) 73.72

L-57
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Loss of Control Credit Factors – Unit 6

Credit Credit Credit Credit


Feature Factor Factor Feature Factor Factor
Range Used Range Used

1. Process Control Credit Factor (C1)


a. Emergency Power 0.98 0.98 f. Inert Gas 0.94 to 0.99 1
b. Cooling 0.97 to 0.99 0.97 g. Operating Procedures 0.91 to 0.99 1
c. Explosion Control 0.84 to 0.98 1 h. Chemical Review 0.91 to 0.98 1
d. Emergency Shutdown 0.96 to 0.99 1 i. Other Analysis 0.91 to 0.98 0.94
e. Computer Control 0.93 to 0.99 1
C1 Value 0.89

2. Material Isolation Credit Factor (C2)


a. Remote Control 0.96 to 0.98 1 c. Drainage 0.91 to 0.97 0.97
b. Dump/Blowdown 0.96 to 0.98 0.98 d. Interlock 0.98 0.98
C2 Value 0.93

3. Fire Protection Credit (C3)


a. Leak Detection 0.94 to 0.98 1 f. Water Curtains 0.97 to 0.98 1
b. Structural Steel 0.95 to 0.98 1 g. Foam 0.92 to 0.97 1
c. Firewater Supply 0.94 to 0.97 1 h. Hand Extinguishers 0.93 to 0.98 0.98
d. Special Systems 0.91 1 i. Cable Protection 0.94 to 0.98 1
e. Sprinkler Systems 0.74 to 0.97 1
C3 Value 0.98

Loss Control Credit Factor (C1*C2*C3) 0.82

1. Fire & Explosion Index (F&EI) 73.72


2. Radius of Exposure 18.92 m
3. Area of Exposure 1125 m2
4. Value of Area of Exposure $ 2807121
5. Damage Factor 0.62
6. Base Maximum Probable Property Damage $ 1740421
7. Loss Control Credit Factor 0.82
8. Actual Maximum Probable Property Damage $ 1419809
9. Maximum Probable Days Outage 25
10. Buisness Interruption $ 559323

L-58
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Unit 7. Carbon Dioxide Absorber (C-80) – 125% Design Case State:


Prepared By: Evans Kwak
Design
Material Used in Process: Synthesis Gas
Material Factor 21
Penalty Factor Penalty Factor
1. General Process Hazards
Range Used
Base Factor 1.00 1.00
A. Exothermic Reactions 0 - 1.25 0
B. Endothermic Reactions 0 - 0.40 0
C. Material Handling and Transfer 0 - 0.80 0
D. Enclosed or Indoor Process Units 0 - 0.90 0
E. Ease of Access 0 - 0.35 0.20
F. Drainage and Spill Control 0 - 0.5 0
General Process Hazards Factor (F1) 1.20
Penalty Factor Penalty Factor
2. Special Process Hazards
Range Used
Base Factor 1.00 1.00
A. Toxic Materials 0
B. Vacuum Operation 0.50 0
C. Operation Near Flammable Range 0 - 0.80 0
D. Dust Explosion 0 - 0.20 0
E. Pressure Penalty 0.84
F. Low Temperature Operation 0 - 0.30 0
G. Flammable Materials 0.98
H. Corrosion and Erosion 0 - 0.75 0.10
I. Leakage - Joints and Packing 0 -1.50 0.10
J. Fired Equipment 0
K. Hot Oil Heat Exchnage 0 - 1.15 0
L. Rotating Equipment 0.50 0
Special Process Hazards Factor (F2) 3.02
Process Unit Hazards Factor (F1 x F2 = F3) 3.63
Fire and Explosion Index (F3 x MF = F&EI) 76.17

L-59
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Loss of Control Credit Factors – Unit 7

Credit Credit Credit Credit


Feature Factor Factor Feature Factor Factor
Range Used Range Used

1. Process Control Credit Factor (C1)


a. Emergency Power 0.98 0.98 f. Inert Gas 0.94 to 0.99 1
b. Cooling 0.97 to 0.99 0.97 g. Operating Procedures 0.91 to 0.99 0.91
c. Explosion Control 0.84 to 0.98 1 h. Chemical Review 0.91 to 0.98 1
d. Emergency Shutdown 0.96 to 0.99 0.96 i. Other Analysis 0.91 to 0.98 0.94
e. Computer Control 0.93 to 0.99 0.97
C1 Value 0.76

2. Material Isolation Credit Factor (C2)


a. Remote Control 0.96 to 0.98 0.98 c. Drainage 0.91 to 0.97 0.97
b. Dump/Blowdown 0.96 to 0.98 0.98 d. Interlock 0.98 0.98
C2 Value 0.91

3. Fire Protection Credit (C3)


a. Leak Detection 0.94 to 0.98 0.98 f. Water Curtains 0.97 to 0.98 1
b. Structural Steel 0.95 to 0.98 0.98 g. Foam 0.92 to 0.97 1
c. Firewater Supply 0.94 to 0.97 1 h. Hand Extinguishers 0.93 to 0.98 0.98
d. Special Systems 0.91 1 i. Cable Protection 0.94 to 0.98 1
e. Sprinkler Systems 0.74 to 0.97 1
C3 Value 0.94

Loss Control Credit Factor (C1*C2*C3) 0.65

1. Fire & Explosion Index (F&EI) 76.17


2. Radius of Exposure 19.55 m
3. Area of Exposure 1201 m2
4. Value of Area of Exposure $ 2606969
5. Damage Factor 0.64
6. Base Maximum Probable Property Damage $ 1668460
7. Loss Control Credit Factor 0.65
8. Actual Maximum Probable Property Damage $ 1085561
9. Maximum Probable Days Outage 21
10. Buisness Interruption $ 527544

L-60
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Unit 8. HP Amine Flash Drum (C-81) – 125% Design Case State:


Prepared By: Evans Kwak
Design
Material Used in Process: Rich Amine
Material Factor 16
Penalty Factor Penalty Factor
1. General Process Hazards
Range Used
Base Factor 1.00 1.00
A. Exothermic Reactions 0 - 1.25 0
B. Endothermic Reactions 0 - 0.40 0
C. Material Handling and Transfer 0 - 0.80 0
D. Enclosed or Indoor Process Units 0 - 0.90 0
E. Ease of Access 0 - 0.35 0.20
F. Drainage and Spill Control 0 - 0.5 0
General Process Hazards Factor (F1) 1.20
Penalty Factor Penalty Factor
2. Special Process Hazards
Range Used
Base Factor 1.00 1.00
A. Toxic Materials 0.60
B. Vacuum Operation 0.50 0
C. Operation Near Flammable Range 0 - 0.80 0
D. Dust Explosion 0 - 0.20 0
E. Pressure Penalty 0.42
F. Low Temperature Operation 0 - 0.30 0
G. Flammable Materials 0.02
H. Corrosion and Erosion 0 - 0.75 0.10
I. Leakage - Joints and Packing 0 -1.50 0.10
J. Fired Equipment 0
K. Hot Oil Heat Exchnage 0 - 1.15 0
L. Rotating Equipment 0.50 0
Special Process Hazards Factor (F2) 2.24
Process Unit Hazards Factor (F1 x F2 = F3) 2.68
Fire and Explosion Index (F3 x MF = F&EI) 42.95

L-61
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Loss of Control Credit Factors – Unit 8

Credit Credit Credit Credit


Feature Factor Factor Feature Factor Factor
Range Used Range Used

1. Process Control Credit Factor (C1)


a. Emergency Power 0.98 0.98 f. Inert Gas 0.94 to 0.99 1
b. Cooling 0.97 to 0.99 0.97 g. Operating Procedures 0.91 to 0.99 1
c. Explosion Control 0.84 to 0.98 1 h. Chemical Review 0.91 to 0.98 1
d. Emergency Shutdown 0.96 to 0.99 1 i. Other Analysis 0.91 to 0.98 0.94
e. Computer Control 0.93 to 0.99 1
C1 Value 0.89

2. Material Isolation Credit Factor (C2)


a. Remote Control 0.96 to 0.98 1 c. Drainage 0.91 to 0.97 0.97
b. Dump/Blowdown 0.96 to 0.98 0.98 d. Interlock 0.98 0.98
C2 Value 0.93

3. Fire Protection Credit (C3)


a. Leak Detection 0.94 to 0.98 1 f. Water Curtains 0.97 to 0.98 1
b. Structural Steel 0.95 to 0.98 1 g. Foam 0.92 to 0.97 1
c. Firewater Supply 0.94 to 0.97 1 h. Hand Extinguishers 0.93 to 0.98 0.98
d. Special Systems 0.91 1 i. Cable Protection 0.94 to 0.98 1
e. Sprinkler Systems 0.74 to 0.97 1
C3 Value 0.98

Loss Control Credit Factor (C1*C2*C3) 0.82

1. Fire & Explosion Index (F&EI) 42.95


2. Radius of Exposure 11.02 m
3. Area of Exposure 382 m2
4. Value of Area of Exposure $ 2262443
5. Damage Factor 0.375
6. Base Maximum Probable Property Damage $ 848416
7. Loss Control Credit Factor 0.82
8. Actual Maximum Probable Property Damage $ 692125
9. Maximum Probable Days Outage 15
10. Buisness Interruption $ 376817

L-62
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Unit 9. Absorber Overhead Knockout Drum (C-87) – 125% Design Case State:
Prepared By: Evans Kwak
Design
Material Used in Process: Synthesis Gas
Material Factor 21
Penalty Factor Penalty Factor
1. General Process Hazards
Range Used
Base Factor 1.00 1.00
A. Exothermic Reactions 0 - 1.25 0
B. Endothermic Reactions 0 - 0.40 0
C. Material Handling and Transfer 0 - 0.80 0
D. Enclosed or Indoor Process Units 0 - 0.90 0
E. Ease of Access 0 - 0.35 0.20
F. Drainage and Spill Control 0 - 0.5 0
General Process Hazards Factor (F1) 1.20
Penalty Factor Penalty Factor
2. Special Process Hazards
Range Used
Base Factor 1.00 1.00
A. Toxic Materials 0
B. Vacuum Operation 0.50 0
C. Operation Near Flammable Range 0 - 0.80 0
D. Dust Explosion 0 - 0.20 0
E. Pressure Penalty 0.83
F. Low Temperature Operation 0 - 0.30 0
G. Flammable Materials 0.98
H. Corrosion and Erosion 0 - 0.75 0.10
I. Leakage - Joints and Packing 0 -1.50 0.10
J. Fired Equipment 0
K. Hot Oil Heat Exchnage 0 - 1.15 0
L. Rotating Equipment 0.50 0
Special Process Hazards Factor (F2) 3.01
Process Unit Hazards Factor (F1 x F2 = F3) 3.61
Fire and Explosion Index (F3 x MF = F&EI) 75.79

L-63
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Loss of Control Credit Factors – Unit 9

Credit Credit Credit Credit


Feature Factor Factor Feature Factor Factor
Range Used Range Used

1. Process Control Credit Factor (C1)


a. Emergency Power 0.98 0.98 f. Inert Gas 0.94 to 0.99 1
b. Cooling 0.97 to 0.99 0.97 g. Operating Procedures 0.91 to 0.99 1
c. Explosion Control 0.84 to 0.98 1 h. Chemical Review 0.91 to 0.98 1
d. Emergency Shutdown 0.96 to 0.99 1 i. Other Analysis 0.91 to 0.98 0.94
e. Computer Control 0.93 to 0.99 1
C1 Value 0.89

2. Material Isolation Credit Factor (C2)


a. Remote Control 0.96 to 0.98 1 c. Drainage 0.91 to 0.97 0.97
b. Dump/Blowdown 0.96 to 0.98 0.98 d. Interlock 0.98 0.98
C2 Value 0.93

3. Fire Protection Credit (C3)


a. Leak Detection 0.94 to 0.98 1 f. Water Curtains 0.97 to 0.98 1
b. Structural Steel 0.95 to 0.98 1 g. Foam 0.92 to 0.97 1
c. Firewater Supply 0.94 to 0.97 1 h. Hand Extinguishers 0.93 to 0.98 0.98
d. Special Systems 0.91 1 i. Cable Protection 0.94 to 0.98 1
e. Sprinkler Systems 0.74 to 0.97 1
C3 Value 0.98

Loss Control Credit Factor (C1*C2*C3) 0.82

1. Fire & Explosion Index (F&EI) 75.79


2. Radius of Exposure 19.45 m
3. Area of Exposure 1189 m2
4. Value of Area of Exposure $ 2907967
5. Damage Factor 0.64
6. Base Maximum Probable Property Damage $ 1861099
7. Loss Control Credit Factor 0.82
8. Actual Maximum Probable Property Damage $ 1518256
9. Maximum Probable Days Outage 30
10. Buisness Interruption $ 753635

L-64
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

7. Dow Chemical Exposure Index


The Dow Chemical Exposure Index was found for carbon monoxide which was deemed the

most dangerous substance in our process. It was done for stream 26 for the base case, the 112%

design case, and the 125% design case since it contained the highest pressure, temperature, and

concentration of carbon monoxide out of all the streams and equipment in our process.

7.1. Sample calculations for the Chemical Exposure Index


Table L3 shows the properties for carbon monoxide taken from DOW Chemical Exposure

Index.

Table L3. Properties of carbon monoxide


Property Value
Chemical Carbon Monoxide (CO)
Molecular Weight (g/mol) 28.01
Boiling Point (°C) -191.5
ERPG-2 (mg/m3) 402
ERPG-3 (mg/m3) 573

To calculate the rupture area, the pipe diameter of interest is required. The pipe diameter of

stream 26 was determined to be 10 inches (254 mm). Since the pipe diameter is greater than 4

inches, the rupture area can be approximated to be 20% of the pipe cross sectional area.

𝐷 2
𝐴𝑟𝑢𝑝𝑡𝑢𝑟𝑒 = (0.20) ∗ (𝜋) ∗ ( )
2

254 𝑚𝑚 2
𝐴𝑟𝑢𝑝𝑡𝑢𝑟𝑒 = (0.20) ∗ (𝜋) ∗ ( ) = 10134 𝑚𝑚2
2

L-65
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

𝐷𝑟𝑢𝑝𝑡𝑢𝑟𝑒 = √4 ∗ 𝐴𝑟𝑢𝑝𝑡𝑢𝑟𝑒 ∗ 𝜋

4 ∗ (10134 𝑚𝑚2 )
𝐷𝑟𝑢𝑝𝑡𝑢𝑟𝑒 = √ = 113.6 𝑚𝑚
𝜋

After the radius has been found it is necessary to find the key process conditions that would

affect the exposure radius. Table H4 shows the process conditions for the 125% design case since

it resulted in the largest exposure radius.

Table L4. Process conditions for stream 26 for the 125% design case

Property Value
Temperature (°C) 51.5
Pressure (kPa) 3375
Quantity of gas (kg) 9558
Latent Heat of Vaporization (J/kg) 216000
Ratio of Cp/Hv 0.0048

One major assumption that Okane Engineering has made regarding the calculation of the CEI,

is that if a breach in equipment were to occur, the process would be shut down within 1 hour of

the breach. Therefore, the quantity of gas that is shown in the Table L4 is an estimated value that

is used purely for the calculation of the Chemical Exposure Index for course requirement purposes.

In the process, the synthesis gas stream does not have a set quantity since it is a by-product from

the SMR unit downstream of the CO2 Recovery Plant. Okane Engineering also does not have the

required information, regarding the SMR operation, to calculate the total quantity of synthesis gas

that would be produced. The synthesis gas stream can also be bypassed by the SMR unit if an

L-66
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

equipment breach were to occur. Therefore, the quantity of gas available for release would be the

quantity of carbon monoxide that would have been sent to the recovery unit within one hour.

Calculating the airborne quantity resulting from a process breach follows as:

𝑀𝑊
𝐴𝑄 = 4.751 ∗ 10−6 ∗ 𝐷𝑟𝑢𝑝𝑡𝑢𝑟𝑒 2 ∗ 𝑃 ∗ √
𝑇 + 273

28.01 𝑔/𝑚𝑜𝑙
𝐴𝑄 = 4.751 ∗ 10−6 ∗ (113.6 𝑚𝑚)2 ∗ (3375 𝑘𝑃𝑎) ∗ √
(41.2 ℃) + 273

𝐴𝑄 = 61.77 𝑘𝑔/𝑠

This value of the airborne quantity is saying that with the stream properties stated in Table L4,

a process breach would result in a release of 60.79 kg/s of carbon monoxide. This would mean that

the full quantity of gas would be released within approximately 2 and a half minutes. However,

the DOW Chemical Exposure Index assumes that all release scenarios are continuous for at least

5 minutes. Therefore, the release rate is calculated by dividing the quantity of gas by five minutes,

which follows as:

9558 𝑘𝑔
𝐴𝑄 = = 31.86 𝑘𝑔/𝑠
300 𝑠

Using the airborne quantity, the Chemical Exposure Index and the ERPG specified hazard radius

can be calculated.

𝐴𝑄
𝐶𝐸𝐼 = 655.1 ∗ √
𝐸𝑅𝑃𝐺2

L-67
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

31.86
𝐶𝐸𝐼 = 655.1 ∗ √ = 184.4
402

𝐴𝑄
𝐸𝑅𝑃𝐺𝑅𝑎𝑑𝑖𝑢𝑠 = 6551 ∗ √
𝐸𝑅𝑃𝐺2

31.86
𝐸𝑅𝑃𝐺2𝑅𝑎𝑑𝑖𝑢𝑠 = 6551 ∗ √ = 1844
402

Table L5. Summary of CEI and ERPG radii for base, 122% and 125% design cases

Calculated Parameter Base Case 112% Design Case 125% Design Case

CEI 164.9 174.1 184.4

ERPG-2 (m) 1649 1741 1844

ERPG-3 (m) 1382 1458 1545

8. Applicable Safety Regulations and Code Requirements


The full list of applicable regulations and standards for this project are detailed in this section.

8.1. Pressure Equipment Safety Regulation


Applicable Standards, Codes, and Recommended Practices under the Pressure Equipment

Safety Regulation include:

• Canadian Standards Association (CSA) Standard B51 -14, Boiler, pressure vessel and

pressure piping code

• American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code –

2015, Section VIII

L-68
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

• ASME B31.3 Process Piping, including Appendices A to E, K, L, and X

• Manufacturers Standardization Society (MSS) Standard Practice SP-25-2013, Standard

Marking System for Valves, Fittings, Flanges and Unions

• Tubular Exchanger Manufacturers Association (TEMA) Standards of Tubular Exchanger

Manufacturers Association (9th Edition)

• International Organization for Standardization (ISO) ISO-16528 Boilers and Pressure

Vessels for construction not addressed in the above codes and standards

8.2. Electrical Code


Applicable electrical standards and Codes currently in force include:

• CSA C22.1-18 Canadian Electrical Code (24th Edition)

• Alberta Electrical Utility Code

8.3. Plumbing Code


Applicable plumbing codes and standards currently in force include:

• National plumbing Code of Canada 2015

• Plumbing Code Regulation

8.4. Alberta Occupational Health and Safety (OHS) Act


The applicable codes and regulations under the Alberta OHS Act includes:

• Occupational Health and Safety Regulation

• Occupational Health and Safety Code 2009 Order

• Occupational Health and Safety Code

L-69
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

8.5. Fire Code


The codes in the Fire discipline currently in force includes:

• Alberta Fire Code 2014

8.6. Canada Labour Code


Applicable regulations under the Canada Labour Code includes:

• Oil and Gas Occupational Safety and Health Regulations

L-70
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

List of References
1. Continuous absorption of CO2 in a packed column using MDEA solution for biomethane

production. A. Mindaryani, W. Budhijanto, S. S. Ningrum. s.l. : Materials Science and

Engineering, 2017, Vol. 162.

2. Scale-Up Effects of CO2 Capture by Methyldiethanolamine (MDEA) Solutions in Terms of

Loading Capacity. Santos, Samuel P, Gomes, João F and Bordado, João C. 19, s.l. : MDPI,

2016, Vol. 4.

L-71
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Appendix M: Pressure-Relieving Device Sizing


Description
This appendix outlines the selection process of a suitable pressure-relieving device and the

calculations completed to obtain sizing parameters for the device. Pressure relief was integrated

into the selected lean amine heat exchanger, E-85. The pressure-relieving device was selected and

sized with reference to API Standard 520 Part I, API Standard 521, and Gas Processors Suppliers

Association Engineering Data Book.

Table of Contents
1. Shell-side Pressure Relief .................................................................................................... M-1
1.1. Scenarios for Overpressure .......................................................................................... M-1
1.1.1. Closed Outlet .......................................................................................................... M-1
1.1.2. Cooling Water Failure ............................................................................................ M-1
1.1.3. Failure of Automatic Controls ................................................................................ M-1
1.1.4. Split Exchanger Tube ............................................................................................. M-1
1.1.5. Hydraulic Expansion .............................................................................................. M-1
1.2. Selection and Size ........................................................................................................ M-2
2. Tube-side Pressure Relief .................................................................................................... M-3
2.1. Scenarios for Overpressure .......................................................................................... M-3
2.1.1. Closed Outlet .......................................................................................................... M-3
2.1.2. Failure of Automatic Controls ................................................................................ M-3
2.1.3. Split Exchanger Tube ............................................................................................. M-3
2.2. Selection and Size ........................................................................................................ M-3
List of References ...................................................................................................................... M-5

i
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

1. Shell-side Pressure Relief


1.1. Scenarios for Overpressure
Lean amine flows on the shell side of the heat exchanger. The lean amine entering the heat

exchanger comes from an upstream air cooler. After passing through E-85, the lean amine enters

the CO2 Absorber. A pressure relief device is proposed on the inlet lean amine stream into the heat

exchanger.

1.1.1. Closed Outlet


If the valve on the lean amine outlet is inadvertently closed, the pressure and temperature of

the line would increase.

1.1.2. Cooling Water Failure


If cooling water supply is eliminated, the lean amine could increase in temperature and

pressure as it passes through the heat exchanger.

1.1.3. Failure of Automatic Controls


There is a temperature controller attached to the lean amine outlet that adjusts cooling water

flow to address temperature fluctuation. A flow controller is also present on the inlet stream to the

exchanger.

1.1.4. Split Exchanger Tube


In the event that the heat exchanger tubes split open due to unforeseen reasons, the pressure

inside the heat exchanger could increase.

1.1.5. Hydraulic Expansion


The volume of the liquid lean amine could increase if temperature increases due to blocked

in cooling water or heated by outside factors such as solar radiation or fire.

M-1
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

1.2. Selection and Size


According to GPSA Section 5 Relief Systems, conventional and balanced bellows relief

valves are recommended for liquid service. Pilot operated relied valves should be used in liquid

service only when the manufacturer has approved the specific application. Since the shell-side

fluid is in liquid phase, a conventional spring-loaded relief valve was chosen.

Shell Side PRV


GPSA Engineering
Standard: Data Book MAWP (kPa): 6145
Conventional Allowable stress, TS
PSV Type: Spring-Loaded (psi): 20030
Relieving Fluid Type: Liquid Thickness, t (in): 0.438
Set Pressure (kPag): 6044 Thickness, t (mm): 11.125
Fractional Overpressure: 10% Seam efficiency, E: 1
Over Pressure (kPa): 200 Radius, R (in): 6.562
Back Pressure (kPa): 0 Safety Factor, SF: 1.5
Diameter, D (in): 13.124
Standard Orifice Designation: N
Valve Body Size (Inlet D x Outlet D) (mm) 100x150
Area, A (cm2): 24.7
Flow Rate, Vl (L/s) 165.4
Coefficient of Discharge, Kd 0.65
Combination correction for rupture disc, Kc 0.9
Back pressure capacity correction factor, Kw 1
Capacity correction factor due to viscosity, Kv 1
Upstream relieving pressure, P1 (kPa (a)) 6345
Back pressure, Pb (kPa (g)) 0
Specific Gravity, G 1.034
Reynolds number, Re 5339

Where

𝑡 × 𝑇𝑆 × 𝐸
𝑀𝐴𝑊𝑃 =
𝑅 × 𝑆𝐹

M-2
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

7.07𝑉𝑙 √𝐺
𝐴=
𝐾𝑑 𝐾𝑐 𝐾𝑤 𝐾𝑣 √𝑃1 − 𝑃𝑏

2. Tube-side Pressure Relief


Cooling water flows on the tube side of the heat exchanger. Cooling water is supplied from

and returned to the cooling water header. A pressure-relief device on the cooling water return line

is proposed.

2.1. Scenarios for Overpressure


2.1.1. Closed Outlet
If the valve on the cooling water return line is inadvertently closed, the pressure and

temperature of the line would increase.

2.1.2. Failure of Automatic Controls


Cooling water flow is controlled by the temperature of the lean amine outlet stream. If this

fails and the outlet valve is not fully open, the line could be pressurized.

2.1.3. Split Exchanger Tube


If the heat exchanger tubes rupture, the high pressure of the surrounding lean amine would

increase the pressure of the cooling water line.

2.2. Selection and Size


The cooling water line is in liquid service and a conventional spring-loaded relief valve

was chosen.

M-3
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Tube Side PSV


GPSA Engineering
Standard: Data Book MAWP (kPa): 1455
Conventional Allowable stress,
PSV Type: Spring-Loaded TS (psi): 16700
Relieving Fluid Type: Liquid Thickness, t (in): 0.109
Set Pressure (kPag): 1354 Thickness, t (mm): 2.7686
Seam efficiency,
Fractional Overpressure: 10% E: 1
Over Pressure (kPa): 135 Radius, R (in): 4.3125
Back Pressure (kPa): 0 Safety Factor, SF: 2
Diameter, D (in): 8.625
Standard Orifice Designation: M
Valve Body Size (Inlet D x Outlet D) (mm) 100x150
Area, A (cm2): 22.6
Flow Rate, Vl (L/s) 75.9
Coefficient of Discharge, Kd 0.65
Combination correction for rupture disc, Kc 0.9
Back pressure capacity correction factor, Kw 1
Capacity correction factor due to viscosity, Kv 1
Upstream relieving pressure, P1 (kPa (a)) 1591
Back pressure, Pb (kPa (g)) 0
Specific Gravity, G 0.994
Reynolds number, Re 15033

M-4
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

List of References
1. Engineering Data Book. Gas Processors Suppliers Association. Tulsa : s.n., 2004, Vol. 1 and

2.

2. The American Society of Mechanical Engineers. ASME Code for Pressure Piping.

[Standard] New York : s.n., 2016. B31.3.

3. Sizing, Selection, and Installation of Pressure-relieving Devices in Refineries. American

Petroleum Institute. s.l. : American Petroleum Institute, 2008. API Standard 520.

4. Pressure-relieving and Depressuring Systems. American Petroleum Institute. s.l. : American

Petroleum Institute, 2008. API Standard 521.

5. Flanged Steel Pressure Relief Valves. American Petroleum Institute. s.l. : American

Petroleum Institute, 2002. API Standard 526.

M-5
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Appendix N: Environmental and Net Social Benefit Assessments


Description
This Appendix contains a brief review and identification of applicable environmental

regulations and net social benefit considerations for the Revamp of CO2 Recovery Plant project.

Identification of process waste streams, environmental issues and mitigation strategies, and a

detailed net social benefit assessment are provided in detail within this Appendix to support

conclusions presented in the main report.

Table of Contents
1. Environmental Assessment ................................................................................................... N-1
1.1. Identification of Waste Streams .................................................................................... N-1
1.2. Applicable Regulations, Legislations, and Guidelines .................................................. N-1
1.2.1. Climate Leadership Act ........................................................................................... N-1
1.2.2. Calculation of Environmental Metric ...................................................................... N-2
1.2.3. Other Factors ........................................................................................................... N-3
1.3. Pan-Canadian Framework on Clean Growth and Climate Change ......................... N-3
1.4. Oil Sands Emissions Limit Act ............................................................................... N-4
1.5. Climate Change and Emissions Management Act (CCEMA) ................................ N-4
1.6. Water Act ................................................................................................................ N-5
1.7. Alberta Ambient Air Quality Guidelines ................................................................ N-5
2. Net Social Benefit Analysis .................................................................................................. N-6
2.1. Affected Individuals and Areas ..................................................................................... N-6
2.2. Resource Use ................................................................................................................. N-6
2.3. Socio-Economic Impacts ............................................................................................... N-7
2.4. Traffic ............................................................................................................................ N-7
2.5. Noise .............................................................................................................................. N-8
2.6. Air Quality ..................................................................................................................... N-8
References ................................................................................................................................... N-9

i
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

1. Environmental Assessment
1.1. Identification of Waste Streams
There were no waste streams identified for the CO2 Removal Unit other than fugitive

emissions of vapours from equipment. Fugitive emissions are accidental emissions of vapours or

gases from pressurized equipment, and can occur due to irregular venting, faulty equipment, or

other unintended causes such as leaking. Unfortunately, these emissions are difficult to quantify

with a high degree of accuracy due to the “accidental” nature of their release (1). However, the

fugitive emissions from the CO2 Removal Unit are infinitesimally smaller than leakage emissions

from other areas of the CNRL Horizon Facility, such as mine faces and tailings ponds.

Additionally, CNRL has a Fugitive Emission Management and Control (FEMC) program in place

to identify larger gas leaks and prioritize them for repair (2).

The process streams crossing the boundary of the project scope is further treated or

processed in other areas of the Horizon Oil Sands site. Process water and condensate is recycled

in other portions of the plant, flash gas is used as fuel for various on-site heaters, burners, and

generators, plant heaters, duct burners for heat recovery steam generator units and gas-fired steam

boilers. The syngas is also further treated in the Pressure Swing Absorption (PSA) unit, and

recovered CO2 is sent to the Dehydration unit.

1.2. Applicable Regulations, Legislations, and Guidelines


1.2.1. Climate Leadership Act
The Climate Leadership Regulation and Climate Leadership Act came into force on

January 1st, 2017. Under this regulation, a price on carbon is imposed which applies to heating and

transportation fuels based on tonnes of CO2e, a standard unit for measuring carbon footprint in

terms of the 100-year time horizon global warming potential of a specified gas expressed in terms

N-1
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

of equivalency to CO2. The current price on carbon is $30/tCO2e in Alberta and may rise to

$50/tCO2e as early as 2022 under the federally-imposed carbon price (Discussed further in Section

1.3). Alberta has since opted out of the federal climate The GHG emissions reduction in tCO2e is

thus the most important environmental metric for this project.

1.2.2. Calculation of Environmental Metric


For the 112% and 125% redesign cases, the GHG emissions reduction amount was

calculated by taking by taking the difference between the CO2 product stream molar flow rates

between the redesign case and the base case. For example, in the 112% redesign case:

𝑘𝑚𝑜𝑙 𝑘𝑚𝑜𝑙 𝑘𝑚𝑜𝑙


𝑛̇ 𝐶𝑂2_𝑅𝑒𝑐𝑜𝑣𝑒𝑟𝑒𝑑 = 𝑛̇ 𝐶𝑂2_𝑆𝑡𝑟𝑒𝑎𝑚38_112% − 𝑛̇ 𝐶𝑂2𝑆𝑡𝑟𝑒𝑎𝑚38 = 1277.74 − 1187.15 = 90.59
𝐵𝑎𝑠𝑒 ℎ ℎ ℎ

𝑘𝑚𝑜𝑙 𝑘𝑔
𝑚̇𝐶𝑂2_𝑅𝑒𝑐𝑜𝑣𝑒𝑟𝑒𝑑 = 𝑛̇ 𝐶𝑂2_𝑅𝑒𝑐𝑜𝑣𝑒𝑟𝑒𝑑 ∗ 𝑀𝑊𝐶𝑂2 = 90.59 ∗ 44.01 = 3986.87 𝑘𝑔/ℎ𝑟
ℎ 𝑘𝑚𝑜𝑙

𝑘𝑔 1𝑡𝑜𝑛𝑛𝑒 24ℎ𝑟 𝑑𝑎𝑦 𝑡𝐶𝑂2 𝑒


𝑚̇𝐶𝑂2𝑅𝑒𝑐𝑜𝑣𝑒𝑟𝑒𝑑_𝑎𝑛𝑛𝑢𝑎𝑙 = 3986.87 ∗ ∗ ∗ 365 = 34,925
ℎ𝑟 1000𝑘𝑔 1 𝑑𝑎𝑦 𝑦𝑟 𝑦𝑟

Similarly, the additional CO2 recovered for the 125% case was calculated to be 95,453 tCO2e/yr.

The CO2 emissions from increased electricity usage as a result of the capacity increase

would also have an effect on the overall GHG emissions of the facility. However, this cost was

ignored as the values were very small in comparison to the actual CO2 additional recovery. A

sample calculation for the 112% case for electricity grid usage is as follows, using the methodology

and factors given in the Carbon Offset Emission Factors Handbook. Let EC stand for Electricity

Consumption:

𝑡𝐶𝑂2 𝑒 1 𝑀𝑊ℎ
𝐸𝐶𝐶𝑂2𝑒 = 𝐸𝐶 ∗ 𝐸𝐶𝑡𝐶𝑂2𝑒 𝑝𝑒𝑟 𝑘𝑊ℎ = 622.74𝑘𝑊ℎ ∗ 0.64 ∗ = 0.398 𝑡𝐶𝑂2 𝑒
𝑀𝑊ℎ 1000 𝑘𝑊ℎ

N-2
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Further study would be required to determine the overall net GHG emissions reduction that

may be achieved when considering other portions of the upgrader site affected by the feed flow

rate increase, such as the PSA unit and downstream dehydration unit.

From the Environmental protection agency website, a typical passenger vehicle emits about

4.6 tonnes of CO2 per year (3). Thus, the increased CO2 recovery from the 125% and 112%

redesign cases would be equivalent to removing 7,592 to 20,751 passenger vehicles from the roads:

𝑉𝑒ℎ𝑖𝑐𝑙𝑒𝑠 𝑅𝑒𝑚𝑜𝑣𝑒𝑑 = 𝑇𝑜𝑡𝑎𝑙 𝐸𝑚𝑖𝑠𝑠𝑖𝑜𝑛𝑠 𝑝𝑒𝑟 𝑌𝑒𝑎𝑟 / 𝐸𝑚𝑖𝑠𝑠𝑖𝑜𝑛𝑠 𝑝𝑒𝑟 𝐶𝑎𝑟

34925 𝑡𝐶𝑂2 𝑒
𝑉𝑒ℎ𝑖𝑐𝑙𝑒𝑠 𝑅𝑒𝑚𝑜𝑣𝑒𝑑 (112%) = = 7,592 𝑉𝑒ℎ𝑖𝑐𝑙𝑒𝑠
𝑡𝐶𝑂2 𝑒
4.6
𝑉𝑒ℎ𝑖𝑐𝑙𝑒

95,453 𝑡𝐶𝑂2 𝑒
𝑉𝑒ℎ𝑖𝑐𝑙𝑒𝑠 𝑅𝑒𝑚𝑜𝑣𝑒𝑑 (125%) = = 20,751 𝑉𝑒ℎ𝑖𝑐𝑙𝑒𝑠
𝑡𝐶𝑂2 𝑒
4.6
𝑉𝑒ℎ𝑖𝑐𝑙𝑒

1.2.3. Other Factors


Additionally, the Alberta Provincial elections will occur on April 16th, which may have

large implications for the carbon levy. The United Conservative Party (UCP) is a loud and vocal

opponent of both the 100 MT emissions cap for the oil sands industry and the carbon levy (4). If

the UCP wins the election, UCP leader Jason Kenney has vowed to scrap the Alberta carbon levy

and fight the federal government’s Pan-Canadian Climate Framework including the federally

imposed carbon tax.

1.3. Pan-Canadian Framework on Clean Growth and Climate Change


Canada released a federal climate change plan in December 2016 as a collective plan to

grow the Country’s economy while reducing emissions and building resilience to adapt to a

changing climate (5). This plan requires jurisdictions to enforce a price-based system on GHG

N-3
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

emissions. Under this plan, the federally imposed carbon price of $10/tCO2e in 2018 is expected

to increase to $50/tCO2e by 2022.

1.4. Oil Sands Emissions Limit Act


Under the Oil Sands Emissions Limit Act, an annual 100 MT limit on GHG emissions is

specified for all oil sands sites combined. Prudent consideration towards GHG emissions and

environmental management is required to ensure the sustainability of the oil sands industry.

Additional recovered CO2 as a result of this project could be used to support environmental

initiatives in nearby oil sands facilities who currently transport CO2 from Edmonton by truck.

Some examples of initiatives include the Non-Segregating Tailings process and Carbon Capture

and Storage (CCS) initiatives.

1.5. Climate Change and Emissions Management Act (CCEMA)


The CNRL Horizon Oil Sands Site is a regulated facility under the Carbon Competitiveness

Incentive Regulation (CCIR) under the CCEMA and is subject to the carbon tax. Regulated

facilities are not penalized under the CCIR if their GHG emissions are below the designated limit,

which depends on the industry specific emissions benchmarks. If regulated facilities emit GHGs

above the designated limits, they are subject to compliancy costs calculated based on excess GHG

emissions. To maintain compliancy with the CCIR, these facilities must reduce their emissions

intensity, purchase Alberta-based carbon offset credits, or make a monetary contribution to

Alberta’s Climate Change and Emissions Management Fund (CCEMF) (9). The cost to purchase

carbon offset credits or contribute to the CCEMF is currently $30/tCO2e excess, which could rise

to $50/tCO2e in 2022. Increasing the capacity of the CO2 Removal Unit would have the overall

benefit of reducing GHG emissions in the upgrader and reduce carbon tax costs for CNRL under

this regulation

N-4
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Carbon Dioxide is also a Specified Gas under the CCEMA and CCIR. The reporting

threshold identified in the Specified Gas Reporting Regulation is 10,000 tonnes of emissions from

a facility. The decrease in CO2 emissions from the CNRL Horizon Facility would not be enough

to waive this reporting requirement.

1.6. Water Act


CNRL currently has a licence under the Water Act (Licence No. 00186921-01-00) which

enforces a 66.1 MM m3/yr of water draw from surface water sources. This includes a maximum

diversion rate of 3.1 m3/s from the Athabasca River with a total maximum diversion of 55.82

MMm3/yr, and a 34.7 MMm3/yr maximum diversion from the Tar River and surface runoff

sources tributary to the Tar and Calumet Rivers. The 112% and 125% cases would increase the

cooling water requirements of the CO2 Removal Unit by 0.013 and 0.101 m3/s, respectively. This

small change is not likely to pose an issue for the client, however limited information is available

regarding current facility water use and draw from the river. Additional study would be required

to fully understand the implications of this increased water usage for the project cases. Periods of

low flow for the surface water sources such as during dry summers or frigid winters, as well as

periods of process upsets should also be considered for further investigation. There is also no

suspected increase in sediment loading or water quality as a result of this project.

1.7. Alberta Ambient Air Quality Guidelines


There are no suspected increases to air quality parameters such as NOX, SOX, volatile

organic compounds, and particulate matter as a direct result from the increased CO2 Removal Unit.

Implications of the increased feed flow rate for the hydro-desulphurization reactors, PSA unit, and

other sources of emissions from the Horizon Oil Sands Facility were not considered for this

analysis.

N-5
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

CNRL is committed to ensuring a high standard of air quality for its stakeholders. CNRL

is a founding member of the Wood buffalo Environmental Association (WBEA), Terrestrial

Environmental Effects Monitoring (TEEM) program, Regional Aquatics Monitoring Program

(RAMP) and Cumulative Environmental Management Association (CEMA). If the company

continues to maintain this high standard for air quality and participation with these various

associations and monitoring programs, ambient air quality around the Horizon Oil Sands Facility

will not be an issue.

2. Net Social Benefit Analysis


2.1. Affected Individuals and Areas
To begin the net social benefit analysis, a brief study of the area surrounding the CNRL

Horizon Oil Sands facility was first conducted. The facility is part of the Regional Municipality of

Wood Buffalo (RMWB) which comprises the City of Fort McMurray and the surrounding rural

areas (6). There are five First Nation members controlling approximately 26 reserves in the

surrounding rural area, which includes the Mikisew Cree First Nation in Fort Chipewyan, the

Athabasca Chipewyan First Nation in Fort Chipewyan, the Fort McKay First Nation in Fort

McKay, The Fort McMurray First Nation near Anzac, and the Chipewyan Prairie First Nation in

Janvier (6).

2.2. Resource Use


Because the 112% and 125% redesign cases are contained within the CNRL Horizon Oil

Sands facility and do not involve work outside of the facility’s boundaries, the traditional lands in

the RMWB will not disturbed. Non-aboriginal environmentally important areas will also not be

N-6
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

affected, including aggregate resources; agriculture; forestry; berry harvesting; hunting; trapping;

fishing; cultural or spiritual locations; and recreation.

2.3. Socio-Economic Impacts


There are several socio-economic benefits to proceeding with the 112% or 125% redesigns.

Over the project’s 20-year lifetime, the 125% and 112% redesigns would generate $1.95 million

CAD and $8.95 million CAD in corporate income tax revenue for the provincial government,

respectively. This tax can be utilized for a variety of social programs and public infrastructure. The

125% redesign case would also see business and employment opportunities for qualified local or

regional contractors and businesses during the design and construction phases. There would be job

opportunities for boilermakers, pipe fitters, iron workers, welders, electricians. Additionally, there

is the potential to reduce the carbon footprint of other oil sands facilities, by selling the additional

CO2 recovered to other facilities around the Fort McMurray area to be used for Enhanced Oil

Recovery, tailings management, or other Carbon Capture and Storage methods. Currently many

oil sands facilities around the Fort McMurray are purchasing CO2 from Edmonton which is

approximately 450 km away which is expensive and not environmentally friends due to the large

volume of trucks and fuel required for transport. Having a larger and more reliable supply of CO2

from the CNRL Horizon Facility would thus benefit other oil producers in the region.

2.4. Traffic
For the 125% redesign case, there may be increased traffic congestion and traffic safety

incidents as a result of bringing in capable workers to the site for construction. To mitigate this,

CNRL has a well-established transporation policy which requirese company and contractor

workers to travel to and from the site on buses. Additionally, the bulk of construction workers can

N-7
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

be housed in the on-site camp located at the CNRL Horizon Oil Sands facility which would

eliminate the traffic concerns from daily commuting.

2.5. Noise
For both the 125% and 112% redesign cases, there would be a marginal increase to noise

generated by the CO2 removal unit based on the pumps and compressors running at an increased

capacity. This increase would be very minimal, as no new mechanical equipment has been added

for either of the capacity increase cases. Furthermore, noise levels are measured on a logarithmic

scale, with a diminished effect when noise is generated from multiple sources. There should be no

additional concerns regarding noise for nearby residents or communities.

2.6. Air Quality


The additional CO2 recovery as a result of this project would decrease the overall GHG

emissions intensity of the CNRL Horizon Oil Sands facility and consequently improve upon the

baseline air quality around the facility. Additionally, the CNRL facility was designed with a high

standard for air quality, including low-NOx burner technology and hydro-desulphurization

reactors to achieve over 99% recovery of sulphur. The generation of airborne particulates and

emissions from mobile equipment fuel consumption as a result of project construction activities

could also be mitigated with dust mitigation programs and optimization of haul route distances.

N-8
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

References
1. Picard, David. Fugitive Emissions From Oil and Natural Gas Activities. Good Practice

Guidance and Uncertainty Management in National Greenhouse Gas Inventories.

2. Canadian Natural Resources Ltd. GHG emissions reduction program. [Online] [Cited: April

5, 2019.] https://www.cnrl.com/corporate-responsibility/environment/climate-change/ghg-

emissions.

3. United States Environmental Protection Agency. Greenhouse Gas Emissions from a

Typical Passenger Vehicle. [Online] March 2018. [Cited: April 6, 2019.]

https://www.epa.gov/greenvehicles/greenhouse-gas-emissions-typical-passenger-vehicle.

4. Wilt, James. Canada Won't Perform an Environmental Review of Most New Oilsands

Projects. Here's Why. The Narwhal. [Online] December 18, 2018. [Cited: April 5, 2019.]

https://thenarwhal.ca/canada-wont-perform-an-environmental-review-of-most-new-oilsands-

projects-heres-why/.

5. Government of Canada. Pan-Canadian Framework on Clean Growth and Climate Change.

[Online] December 2016. [Cited: April 5, 2019.]

https://www.canada.ca/content/dam/themes/environment/documents/weather1/20170125-en.pdf.

6. Golder Associates. CNRL Horizon Project Environmental Impact Assessment. Oil Sands

Information Portal. [Online] June 2002. [Cited: April 5, 2019.] http://osip.alberta.ca/map/.

N-9
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Appendix O: Pertinent Articles


Description
The purpose of this appendix is to present three articles pertinent to the project. These

articles from the open literature were consulted during the analysis of the project.

Table of Contents
1. Factors affecting CO2 absorption efficiency in packed column ........................................... O-1
2. Corrosion and materials selection for amine service .......................................................... O-11
3. Scale-up effects of CO2 capture by Methyldieathanolamine (MDEA) solutions in terms of
loading capacity ........................................................................................................................ O-16
List of References ..................................................................................................................... O-26

i
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

1. Factors affecting CO2 absorption efficiency in packed column

O-1
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

O-2
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

O-3
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

O-4
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

O-5
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

O-6
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

O-7
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

O-8
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

O-9
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

O-10
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

2. Corrosion and materials selection for amine service

O-11
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

O-12
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

O-13
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

O-14
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

O-15
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

3. Scale-up effects of CO2 capture by Methyldieathanolamine (MDEA)


solutions in terms of loading capacity

O-16
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

O-17
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

O-18
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

O-19
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

O-20
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

O-21
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

O-22
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

O-23
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

O-24
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

O-25
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

List of References
1. Tan, L.S., et al. Factors affecting CO2 absorption efficiency in packed column: A review.

Tronoh : Journal of Industrial and Engineering Chemistry, 2012.

2. Corrosion and Materials Selection for Amine Service. Rennie, S. s.l. : Materials Forum, 2006,

Vol. 30.

3. Scale-Up Effects of CO2 Capture by Methyldiethanolamine (MDEA) Solutions in Terms of

Loading Capacity. Santos, Samuel P, Gomes, João F and Bordado, João C. 19, s.l. : MDPI,

2016, Vol. 4.

O-26
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

Appendix P: Email Correspondence


Description
This appendix includes the communication with CNRL through email correspondence for

the purposes of requesting documents and information, along with clarifying questions.

i
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

P-1
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

P-2
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

P-3
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

P-4
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

P-5
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

P-6
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

P-7
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

P-8
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

P-9
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

P-10
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

P-11
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

P-12
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

P-13
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

P-14
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

P-15
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

P-16
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

P-17
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

P-18
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

P-19
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

P-20
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

P-21
Revamp of CO2 Recovery Plant Final Report
Client: Canadian Natural Resources Ltd.
Team 5 Date of Submission: 2019-04-09

P-22

You might also like