Professional Documents
Culture Documents
POWER
NET 256 MW
COMBINED-CYCLE
POWER PLANT WITH
ZERO CO2 EMISSIONS
Prepared For: Mr. Jim Sorensen
Prepared By: JTMMAN Power
CH E 465
Team 5
Theresa Cho, Aji Kefas, Jessie Wang, Maryam
Gul, Michelle Liu, Nicole Temple
Executive Summary
To address impacts of increasing greenhouse gas emissions, the Climate Leadership Plan
(CLP) was introduced by the Government of Alberta in 2015. CLP initiatives include the
implementation of carbon pricing as well as a strategy to phase out coal-generated electricity by
2030. The strategy outlined by the CLP does not address an alternative method to meet the
growing provincial power requirement. Combined-cycle power plants are considered an efficient
method of power generation. Oxyfuel combustion conditions provide an ideal flue gas stream for
carbon dioxide (CO2) sequestration processes. The objective of this project is to design an
economically feasible combined-cycle power plant that produces zero CO 2 emissions.
This report presents the design of a net 256 MW power plant, which is comprised of three
process units. The first unit is an air separation unit that produces 80.3 tonnes/hr of 98.2 mol%
purity oxygen. This stream is produced by employing cryogenic distillation to separate air.
Nitrogen is a saleable by-product of this process. The second unit utilizes a gas and steam turbine
in a combined-cycle configuration to generate power. A total of 341 MW of power is produced
by this unit, but after accounting for operating power requirements, a net 256 MW of power is
sent to the grid. CO2 in the flue gas of the power generation unit is compressed and dehydrated
for use in enhanced oil recovery (EOR) processes. On an annual basis, 9.8 million tonnes of CO 2
are captured for re-use, which would have been otherwise released to atmosphere. The water
content in the stream is reduced to 67 ppmv (3.2 lb H2O /mmscf).
A detailed economic analysis was conducted to determine the feasibility of the proposed
process. The project requires a capital investment of $1.4 B, with projected annual operating and
revenue costs of $278 MM and $585 MM, respectively. The revenue stream is comprised of
marketed electricity, nitrogen, CO2 used for EOR, and carbon tax credits. A cash flow analysis
was performed based on a 25-year plant lifetime. The net present value obtained from this
analysis is $1.2 B with a payback period of 10 years. The results obtained in the economic
analysis indicate that the proposed process is economically feasible.
The feasibility of the proposed process was also analyzed with regards to risk,
environment impacts, and social benefits. A high-level risk assessment highlighted the necessity
for the implementation of mitigation methods outlined for major risks identified. Environmental
i
benefits of the proposed process outweighed the impacts according to the environmental analysis.
Predominantly positive social impacts further justify the proposed project.
The project is to be carried out following the Engineering, Procurement, and Construction
Management (EPCM) model, over a five-year period starting with conceptual design.
Engineering is scheduled for completion by early 2020 to allow for construction start-up by the
spring of 2020. The plant is targeted to be fully operational by the spring of 2023. Approximately
20 months of the total five-year project life will be devoted to the completion of engineering
design, while 30 months will be allocated for the construction phase. Commissioning and start-up
is forecasted to take up to nine months in total.
ii
Table of Contents
Executive Summary i
Table of Contents iii
List of Tables v
List of Figures v
1. Introduction and Statement of Objectives 1
2. Background 2
4. Project Justification 3
4.1 Air Separation Unit 3
4.2 Power Generation Unit 3
4.3 Carbon Dioxide Unit 5
5. Alternatives Considered 6
5.1 Option 1: Do Nothing 6
5.2 Option 2: Design a Net 256 MW Power Plant with Zero CO2 Emissions 6
A comprehensive evaluation of technologies considered is presented in Appendix A. 6
5.2.1 Air Separation Unit 6
5.2.2 Power Generation Unit Configuration 7
5.2.3 Carbon Dioxide Unit 8
6. Project Description 10
6.1 Process Description 10
6.1.1 Air Separation Unit 11
6.1.2 Power Generation Unit 11
6.1.3 CO2 Unit 12
6.2 Process Flow Diagrams (PFD) 13
6.3. Summary of Material and Energy Balances 18
6.4 Equipment List 19
6.4.1 Air Separation Unit 20
6.4.2. Power Generation Unit 21
6.4.3. CO2 Unit 22
6.5 Utility Requirements and Sources 24
6.6 Materials of Construction and Control Strategy 24
6.6.1 Materials of Construction 24
6.6.2 Control Strategy 25
iii
6.7 Assumptions, Constraints, and Limitations of the Design 25
6.7.1 Assumptions 25
6.7.2 Limitations 25
6.8 Project Execution Strategy 26
6.8.1 Engineering Plan 26
6.8.2 Procurement Plan 26
6.8.3 Construction Plan 27
7. Project and Net Social Benefit Analyses (Economic, Environmental, Safety, Risk, Society) 29
7.1 Economic Analysis 29
7.1.1 Fixed Capital Cost 29
7.1.2 Working Capital Cost 31
7.1.3 Operating Costs and Revenue 31
7.1.4 Capital Expenditure 33
7.1.5 Engineering Work Force Requirements 34
7.1.6 Trades Labour Work Force Requirements 35
7.1.7 Discounted Cash Flow Analysis 36
7.1.8 Sensitivity Analysis 37
7.1.9 Financing Plan 38
7.1.10 Summary of Economic Analysis 38
7.2 Environmental Analysis 39
7.3 Safety and Risk Analysis 40
7.3.1 Risk and Process Hazards Assessment 40
7.3.2 . Potential Impacts and Applicable Regulations 41
7.3.3. PFD Based PHA and P&ID HAZOP 42
7.3.4 Applicable Code and Regulations and Long-Term Management of Hazards and
Risks and Hazards 42
7.3.5 PSV Sizing 43
7.4 Net Social Benefit Analysis 43
8. Conclusions and Recommendations 44
8.1 Conclusions 44
8.2 Recommendations 44
9. References 46
10. Appendices 53
iv
List of Tables
List of Figures
v
1. Introduction and Statement of Objectives
2. Background
In 2015, the CLP was introduced by the Government of Alberta, which outlined a long-
term strategy to combat greenhouse gas emissions [3]. This plan introduced a provincial carbon
levy and the phase out of coal-powered generation plants in an effort to lower CO 2 emissions [3,
4]. In 2015, Alberta contributed to 38% of Canada’s total greenhouse gas emissions, where the
electricity sector is one of the top two contributors [2]. As of 2016, coal-powered plants
accounted for 38% of Alberta’s electricity generation [1]. The elimination of coal-generated
power will create a deficiency in the province’s electricity supply if not addressed.
Combined cycle power plants optimize power generation by using heat from the gas
turbine exhaust to increase overall efficiency [5]. The waste heat recovered is used to generate
steam, which powers a steam turbine, producing more electricity without extra fuel input. Use of
pure oxygen produced by the ASU for combustion in the gas turbine can further increase
efficiency and reductions in greenhouse gas emissions [6]. The ASU produces pure nitrogen
streams, which generate additional revenue for the facility. CO 2 is recovered from the flue gas
generated by oxyfuel combustion in the gas turbine, which can be utilized in enhanced oil
recovery processes (EOR).
3. Proposed Solution
The following solution is proposed to meet the objectives of this project. First, an ASU
was designed to produce pure oxygen from air, which is utilized for oxyfuel combustion in the
gas turbine. The PGU has been designed to generate enough power to sustain the facility, while
providing a net 256 MW of power to the grid. To meet the objective of producing zero CO 2
emissions, the flue gas stream from the power generation is compressed and dehydrated for
enhanced oil recovery (EOR). The proposed power plant will be built north of Edmonton,
Canada, in close proximity to an oil field. Natural gas feed will be supplied from one of the five
2
major natural gas pipelines in Alberta and received at the battery limits of the proposed power
plant.
4. Project Justification
3
Figure 1. Forecasted long-term electricity load growth in Alberta by AESO [9]
4
To produce 256 MW of power for the facility, natural gas is required as a feedstock. As
shown in Figure 3, the increase in natural gas price under the base case is expected to remain
relatively stable over the next 10 years at $4.5/GJ [10]. The stability of natural gas prices
provides further justification for the implementation of this project.
5
5. Alternatives Considered
5.2 Option 2: Design a Net 256 MW Power Plant with Zero CO 2 Emissions
A comprehensive evaluation of technologies considered is presented in Appendix A.
6
5.2.2 Power Generation Unit Configuration
7
5.2.2.4 Oxygen Control
O2 concentration in the flue gas must be below 10 ppm in order to adhere to strict EOR
specifications [15]. Three methods were considered to control the O 2 content in the flue gas. A
catalytic oxidizer can be used to remove excess oxygen in the flue gas. Catalyst deactivation can
occur due to high water concentration in the process stream, which is around 10% by volume at
an operating temperature of 135oC [16]. Employing this oxygen control method at the operating
conditions of the process stream is not advisable. Another option investigated for oxygen control
is to feed excess O2 through the gas turbine. The O2 remaining in the flue gas after combustion in
the gas turbine will be utilized for combustion in the duct burners. The flow rate of the natural
gas to the duct burners should be controlled to ensure that virtually all of the remaining O 2 is
combusted as this point. Additionally, an O2 sensor will be installed downstream of duct burners
to ensure that the O2 concentration is monitored. If the O2 concentration exceeds the limit for
EOR, the natural gas feed rate will be adjusted accordingly. This option reduces capital cost
while meeting EOR specifications.
8
Table 1. Specifications of final CO2 used for EOR [17, 18]
Parameter Specification
Nitrogen, N2 4% (maximum)
Hydrocarbons 5% (maximum)
Temperature, T 40℃
9
TEG is thermally regenerated for re-use. The second dehydration method investigated was the
use of molecular sieves. Molecular sieves utilize a solid desiccant to remove the H 2O from the
CO2 stream. Molecular sieves can achieve very low dry gas H2O content, but tend to have higher
capital and operating costs when compared to TEG dehydration [24]. Auto-refrigeration was also
considered as a potential dehydration technology as it has lower capital and operating costs than
TEG dehydration; however, it was not able to achieve the required H 2O removal [25]. TEG
dehydration was the method selected to remove the H 2O from the CO2 stream.
6. Project Description
10
6.1.1 Air Separation Unit
The ASU produces pure oxygen required for oxyfuel combustion in the downstream
PGU. Filtered ambient air is compressed to 951 kPag using eight stages. Fin fan air coolers
provide interstage cooling to 40°C and a portion of H 2O is removed from the air stream in
the knock-out drums. The compressed air is passed through molecular sieves for final
removal of all remaining H2O and CO2 present in the air stream. The dehydrated air is
precooled to 28.5°C using cryogenic N2 product gas and is further cooled through turbo gas
expansion. Following expansion, the air is subcooled to liquefaction conditions of -171.7°C
in a cold box heat exchanger using cold products from cryogenic distillation. A double
Linde column consisting of a high pressure (HP) and low pressure (LP) tower is used to
separate the air into N2 and O2. Air is initially separated in the HP column. A 30.5 mol% O 2
enriched stream from the bottom of the HP column and a mostly pure N 2 stream from the
condenser of the HP column are sent through a subcooler and throttled before entering the
LP column. Ultra-high purity N2 at 99.9 mol% is drawn from the overhead, while lower
purity N2 at 97.9 mol% is drawn from the second stage of the LP column. High purity O 2, at
98.3 mol% is drawn from the bottom of the LP column. Both N 2 product streams from the
LP column are used as cooling agents in the subcooler and the cold box heat exchanger. The
O2 product stream from the LP column is also used for cooling in the cold box heat
exchanger. The lower purity N2 stream is then sent to a plate and fin heat exchanger to
precool the feed air, while the O2 product stream is compressed to 50 kPag and sent to the
PGU.
The ASU contains a set up for the regeneration of the molecular sieves. Each
molecular sieve is designed for 16 hours of online operation before regeneration is required.
The regeneration process is carried out using heated, dry air at 260°C at a flow rate of 64
kg/s.
11
O2 stream from ASU is fed into the gas turbine at a flow rate of 44.6 kg/s, where it is
subsequently compressed and reacted with natural gas. Natural gas is supplied to the combustion
chamber at a flow rate of 8.95 kg/s. The natural, composed primarily of methane and ethane,
reacts completely with O2 to produce H2O and CO2, as outlined in Equations 1 and 2.
𝐶𝐻 ( )
+ 2𝑂 ( ) → 𝐶𝑂 ( ) + 2𝐻 𝑂 ( ) (1)
2𝐶 𝐻 ( )
+ 7𝑂 ( ) → 4𝐶𝑂 ( ) + 6𝐻 𝑂 ( ) (2)
The process flow diagrams for each unit are presented in the following section.
13
14
15
16
17
6.3. Summary of Material and Energy Balances
Appendix C outlines the material and energy balances for each unit. Minor discrepancies
observed in the mass and energy balances can be attributed to rounding error. The overall
material balance is shown in Table 2 and the overall energy balance is shown in Table 3.
18
Table 3. Overall energy balance
Overall Energy Balance
Description Energy In (MW) Energy Out (MW)
Feed Air 58.42
Feed Natural Gas 6.56
Cooling Water -17900.00
Low Pressure Steam 11.00
Spent Cooling Water -17330.00
Water Removed by
Knock Out Streams -46.97
liquid Carbon Dioxide
Product -0.23
Low Purity Nitrogen 41.60
High Purity Nitrogen 4.43
Column Reboilers 28.05
Column Condensers 27.59
Compressors 73.97
Air Coolers 166.43
Turbine 4.40
Combustion Chamber 152.80
Duct Burners -606.67
Gas Turbine 91.00
Steam Turbine 250.00
Pump 9.56
Heat of Reaction -522.75
Total -17723.44 -17757.37
Table 4 summarizes the equipment required for the process. Detailed equipment
specifications and operating parameters can be found in Appendices D-F. Major process line
sizing is shown in Appendix G.
19
6.4.1 Air Separation Unit
6.4.1.1 Air Feed Compressor (K-100)
The air feed compressor brings atmospheric air to 951 kPag after eight stages of
compression and reaches a maximum operating temperature of 182 oC. An axial air compressor
was chosen due to its operability with higher efficiencies and ability to handle high flow rates
compared to centrifugal compressors. The air compressor operates with 85% adiabatic efficiency.
Water is removed through interstage cooling and knockout drums. The compressor was designed
for a flow capacity of 265 Sm3/s and shaft power of 99 MW based on start-up conditions to
account for the additional air required to establish the regeneration gas loop for the molecular
sieves.
6.4.1.4 High Pressure and Low Pressure Distillation Columns (T-100A/B and T-101A/B)
Each combined distillation tower consists of a HP column (T-100A/B) at the bottom and
a LP column at the top (T-101A/B). A combined condenser-reboiler (E-103A/B) integrates heat
between the two towers and improves overall efficiency. The HP columns perform the initial
separation of air into N2 and O2. The column operates at a pressure of 389 kPag and at a
20
temperature of -176oC. The HP tower has a height of 18.1 m, a diameter of 3.7 m, and 62 valve
trays with 0.25 m tray spacing. The LP column uses N2 and O2 from the HP column to further
purify the streams. The column operates at 60 kPag and a operating temperature range of -192 oC
to -179oC. The LP tower has a height of 35.0 m, a diameter of 4.5 m, and 129 valve trays with
0.25 m tray spacing.
21
6.4.2.3 Steam Turbine (ST-200)
A GE 800 series REHEAT STF-D600 steam turbine was selected for the process. This
turbine model was selected based on the net power requirement, while accounting for the
generation capacity of the gas turbine. The condenser is attached directly below the steam turbine
with a heat exchange area of 18,000 m2 and heat duty of 598 MW.
22
Table 4. Summary of equipment for all units
23
6.5 Utility Requirements and Sources
Utility requirements for this project include electricity, boiler feed water (BFW), cooling
water, wastewater treatment, and steam. Electricity requirements for each unit are met using a
portion of the electricity generated onsite. BFW fed to the LP HRSG is purchased continuously.
The BFW fed to the HP HRSG is made up of 97% recycled water, while 3% is purchased to
make up for losses to the environment during the steam cycle. Cooling water is required to
condense exhaust steam from steam turbine and requires 9,472 kg/s water continuously pumped
to the condenser (C-200). Wastewater from knockout drums in the ASU and CDU contains
dissolved concentrations of CO2, and may require pH adjustment before discharge to the rivers.
Low grade utility steam at 10.8 kg/s is required for heating the regeneration gas in the ASU and
the reboiler in the CDU. Table 5 summarizes the annual utility requirements for this facility.
24
special consideration of material selection due to low operating temperatures in cryogenic units.
Heat exchangers in the cryogenic section of the ASU are constructed of brazed aluminum, as it
allows for efficient heat transfer at low temperatures [26].
6.7.1 Assumptions
The main assumptions for the design are:
● Natural gas undergoes complete combustion
● NOx formation is negligible under oxyfuel combustion
● Natural gas composition is constant
● Design methods outlined in Ulrich and Vasudevan are applicable to our process
6.7.2 Limitations
Using VMGSim to simulate the process presents several limitations:
● The ASU was simulated in VMGSim at steady state condition, while molecular sieve
regeneration is a transient process.
● Turbines and HRSGs cannot be directly simulated in VMGSim. Components of the units
were used to mimic the equipment, which may result in simulation error.
● VMGSim does not have detailed equipment to select for simulation. Using generic
equipment in place of specialized equipment could incur inaccuracies (compressors and
heat exchangers).
● VMGSim is not necessarily the best software to model supercritical CO 2.
● The excessively high temperature observed at the HP duct burner in the HRSG (>1000
o
C) could be caused by unknown limitations in VMGSim.
25
6.8 Project Execution Strategy
The project execution strategy details a plan to carry out the engineering, procurement,
and construction phases of this project. Due to the extensive scope required to complete this
project, an Engineering, Procurement, and Construction Management (EPCM) approach is
utilized. With the large scope of the project, the alternative approach of Engineering,
Procurement, and Construction (EPC) is not recommended due to the limited number of firms
with the technical expertise and resources to carry out design and construction. In contrast, an
EPCM approach will allow for a competitive bid comprised of an increase number of firms that
have the construction expertise required to build the ASU, PGU, and CDU. Guthrie’s Method
was used to estimate the man hours required for engineering and construction for this project
[34]. A detailed outline of the project execution strategy, including estimated time and manpower
required for the design phases through to construction and commissioning of the project can be
found in Appendix J.
27
28
Economic feasibility of the proposed process was evaluated using various economic
measures. These include examination of the effect of fixed capital cost from purchased
equipment, working capital cost, annual operating costs, and cash flow analysis. This includes
the determination of net present value (NPV) and internal rate of return (IRR). The economic
analysis was conducted using methods outlined in Ulrich and Vasudevan. A sensitivity analysis
was also conducted to determine the impact of key variables on the NPV. A brief discussion of
the mentioned economic measures can be found in this section while a more detailed breakdown
of the calculation and justification can be referenced Appendix K.
29
Figure 6. Fixed capital cost breakdown
31
Figure 7. Annual operating cost distribution in 2023
32
7.1.3.3 Utilities
Annual utility costs was determined to be $30.8 MM. Cooling water contributes to the
majority of the utility cost as high flow rates are required to condense steam from the steam
turbine. The unit cost for cooling water was determined to be $0.042/m 3 [44]. BFW was
estimated to be $9.68/m3.
7.1.3.4 Revenue
Annual revenue consists of the selling price of electricity, CO 2 for EOR, Carbon Tax
credits, and N2 price. Electricity and Carbon Tax credit values were provided by the client at
$80/MWh and $150/t by 2023, respectively. These prices were assumed to stay constant
throughout the lifetime of the plant. N2 price was taken to be 200 times less than the packaged
cost. Table 6 summarizes all revenue streams for the facility.
Electricity 166
33
procurement cost is calculated as 10% of the subtotal grassroots cost. The total for engineering
and procurement was calculated to be $113 MM. Engineering costs make up 80.5% of this value,
while the remaining 19.5% covers the procurement cost. Construction comprises the total cost of
installation at $346M. The commissioning and start up cost was estimated at 8% of subtotal
grassroots facility and contingency cost. The value calculated for commissioning and start up
cost is $90.8 MM. Additional information on the breakdown of capital expenditure can be found
in Appendix K.
34
engineering effort will be devoted to the detailed design phase. Additional information on the
planning of engineering effort requirements can be found in Appendix J.
35
Figure 10. Distribution of construction hours
36
Figure 11. Cumulative discounted cash flow for a 25 year operating time.
37
Figure 12. Sensitivity analysis
38
which was well above the require MARR hurdle rate of 10%. The sensitivity analysis shows
that high capital cost was a major factor affecting the feasibility of the project; therefore,
government funding was explored to examine its effect on the economic analysis. The project
feasibility was further improved with a NPV of $1.86 B, a payout time of only 5 years, a ROI
of 45.6%, and an IRR of 31%.
39
Due to the presence of large quantity of fin fans, pumps, expanders and compressors,
as well as the piping required for the operation of this project, noise pollution was also
identified as a one of the main environmental concerns applicable to each of the three units.
Installation of noise reducing equipment, such as vibration dampeners on pump discharges
and insulation on piping can also mitigate the level of noise pollution produced [50].
After environmental analysis, it is concluded that the benefits of this project outweigh
the potential negative impacts. The implementation of this project would establish Alberta and
Canada as international environmental leaders.
A detailed risk assessment and process hazard assessment for the proposed process can be
referenced in Appendix (M). Additionally, the HAZOP conducted for this facility is outlined in
Appendix N.
40
7.3.2 . Potential Impacts and Applicable Regulations
The impacts associated with the major risks outlined were determined based on the
consequences to people, the environment, assets, and production according to standards for risk
management outlined by APEGA [52]. Loss of containment is the root cause for many of the
major risks identified for the facility. One of the most important consequences to consider is the
potential impacts to humans. Many components processed at this facility are harmful to humans.
A large release of N2 or CO2 would result in operator injury or fatality due to asphyxiation [53].
Explosions and fires are a major risk identified for this process due to large amounts of natural
gas, O2, and TEG onsite. In the event of an explosion or fire, humans may be injured or killed by
burns, chemical inhalation, or flying pieces of equipment. Environmental impacts will also occur
in the event of a major unplanned release, especially through air pollution in the event of a fire or
explosion. The fines incurred would be dependent on the parameter released. N 2, O2, and CO2
have been identified to have widespread impact in the event of a major release. These parameters
are not included on Dow’s Chemical Exposure Index (CEI) material list. Dispersion modelling of
these components is required to determine the evacuation radii in the event of a major release. It
is especially important to observe the bounds of the oxidative environment relative to natural gas
combustion in the PGU. This data will help inform the next stage of engineering to determine if
further modifications need to be made to the current plot plan. Dispersion modelling can also be
used to ensure that the PSVs installed vent to a safe location. Another important consideration in
the event of a major loss incident is the impact to the facility assets. A breach of equipment
would require replacement or repair before the unit can be brought online. In the event of a fire
or explosion, there is a chance that surrounding equipment would be at risk due to flying
material. DOW Fire and Explosion Index (FEI) was utilized to determine an appropriate radius
for high risk equipment handling natural gas and TEG. The detailed calculation was included in
Appendix O. This data was used to allow for a safer design with regards to equipment placement.
As this facility requires the operation of all three units to meet production and environmental
initiatives, the maintenance of vital equipment in any unit would require a facility wide shut
down. Major loss incidents that impact operators would be subject to investigation under the
Alberta Occupational Health and Safety Act [54].
41
7.3.3. PFD Based PHA and P&ID HAZOP
A detailed what-if PHA analysis was performed through the use of a checklist, for each of
the three units that compose the facility: the ASU, the PGU, and the CDU. The purpose of this
analysis is to identify process hazards that result from upset operating conditions. Effects of
parameters such as temperature, flow rate, and pressure were analyzed. One of the main
takeaways determined through the analysis of all three units was that a sophisticated control
system is necessary to ensure operating conditions do not deviate from design. The system must
be designed to handle minor upsets; however, the use of major safeguards must be employed to
ensure the equipment does not operate outside of its limits. This includes the implementation of
important safety mitigation methods such as PSVs and pipe leak detectors located at regular
intervals along the piping.
A HAZOP analysis was performed on the condenser downstream of the steam turbine.
The P&ID drafted for this heat exchanger was utilized to conduct the analysis. The major nodes
identified in the HAZOP are the condenser, the centrifugal pumps, and the piping. A few of the
major process hazards identified for these nodes include equipment integrity, explosion, and
deviation from design conditions. A mitigation strategy has been formulated to safeguard against
the consequences of the risks identified. These strategies include the implementation of
monitoring equipment and alarm systems. Another layer of risk mitigation was included in this
strategy by addressing isolation methods that can be employed by operators. This includes the
use of PPE on site, as well as following outlined safe work procedures. It is important to note
that the HAZOP was only conducted on a small portion of the process. To ensure safe operation
of the facility, a complete HAZOP for all equipment on site should be carried out.
7.3.4 Applicable Code and Regulations and Long-Term Management of Hazards and Risks
and Hazards
The planned facility lifetime is 25 years. The probability of an occurrence of a major
loss incident for this period without safeguards is high. As discussed previously, there is
considerable risk to the people, environment, assets, and production in the event of a major loss
incident. In order to ensure the sustainability of this facility, many long-term safety initiatives
need to be implemented. Safeguards such as PSVs and sophisticated control systems will be
employed to prevent loss incidents resulting from deviations from design conditions. Physical
42
safety mitigation methods will be incorporated into the facility design, such as well-ventilated
buildings, alarm systems, and accessible and remote shutdown buttons. In addition, an intensive
training program will be used to ensure operators are knowledgeable in both everyday and
emergency response procedures. Standard safe work procedures will also be drafted and
utilized for work completed onsite. Safety is a value at JTMMAN Power, and the safety
programs used at this facility will continuously improve as standards change and technology
advances. Even with the implementation of safeguards, risks are not completely eliminated;
therefore, safety standards implemented shall be periodically reviewed and improved to ensure
that the residual risk is sufficiently managed.
Appendix Q outlines a detailed analysis of the net social benefits identified for this
project. Key social benefits determined for this project include job growth, technology
development, lower carbon footprint, satisfying increasing electricity demand, and positive
community influence. This project provides employment opportunities for construction workers
and engineers, especially considering the impending shutdown of coal-fired power plants. The
implementation of this project would help establish Alberta’s role as an environmental leader,
while enhancing Canada’s reputation worldwide, which could provide economic benefits.
Electricity is the key product stream created through the implementation of this project, which
will assist in satisfying increasing electricity demand in the future.
43
Negative social impact is caused by high capital cost investment necessary for project
implementation as well as high water consumption. Carbon credits and government subsidies are
considered plausible funding options, which could end up increasing personal income tax rates.
8.1 Conclusions
8.2 Recommendations
Based on the final overview of the proposed design, the following improvements are suggested
for future stages of design:
A catalytic oxidizer can be considered for installation downstream of the CDU to remove
excess amount of O2.
To prevent corrosion, deaerators should be designed to remove dissolved O 2 and
CO2 from condensate/feedwater to LP and HP HRSGs.
During the early stages of the proposed design, the LP stream from the LP HRSG was to
be utilized by the ASU. It was determined later that the ASU would require HP Steam
44
instead of LP Steam. As future recommendations, the LP HRSG will not be necessary as
HP HRSG will supply required steam.
Use two gas turbines instead of a single gas turbine. Using two gas turbines will
reduce the amount of supplementary heating required by the duct burners. This will
lower the required process temperature in the HRSG, which is beneficial as
temperature control is a major concern in the PGU.
Explore potential opportunities to receive government funding.
It is recommended to simulate overall process in more advanced modelling software
due to limitations in VMGSim.
A complete HAZOP analysis should be conducted for the entire facility before final
approval of design
Proceed with dispersion modeling for application in risk analysis
45
9. References
[1]. Alberta Energy. (2017). Alberta Electricity Overview.[pdf document]. Retrieved from
http://www.energy.alberta.ca/Electricity/pdfs/Elec101.pdf
[2]. Government of Alberta. (2016-17) Climate Leadership Plan Progress Report. Retrieved
from https://www.alberta.ca/assets/documents/CLP-progress-report-2016-17.pdf
[3]. Government of Alberta. (2017). Phasing out coal pollution. Retrieved from
https://www.alberta.ca/climate-coal-electricity.aspx
[4]. Government of Alberta. (2017). Fiscal Plan-Climate Leadership Plan. Retrieved from
http://finance.alberta.ca/publications/budget/budget2017/fiscal-plan-climate-leadership-plan.pdf
[5]. Polyzakis, A. L., Koroneos, C., & Xydis, G. (2008). Optimum gas turbine cycle for
combined cycle power plant. Energy Conversion and Management, 49(4), 551-563.
[6] Coombe, H.S., & Nieh, S. (2007). Polymer membrane air separation performance for portable
oxygen enriched combustion applications. Energy Conversion and Management, Vol 48, 1499-
1505.
[7] Universal Industrial Gases Inc. (n.d). Production/ Supply System optimization. Retrieved from
http://www.uigi.com/optimalplant.html
[8]. Praxair Technology Inc. (2018). Industrial Gases. Nitrogen. Retrieved from
http://www.praxair.co.in/gases/buy-liquid-nitrogen-or-compressed-nitrogen-gas?tab=industries.
[9]. Alberta electric system operator (AESO). (2017). AESO 2017 Long-Term Outlook.
Retrieved from https://www.aeso.ca/download/listedfiles/AESO-2017-Long-term-Outlook.pdf.
[10]. AECO-C Natural Gas Price. Retrieved from Alberta Energy Regulator. Retrieved from
https://www.aer.ca/data-and-publications/statistical-reports/aeco-c
46
[11]. Godec, M. L . (2011). Summary of Costs for CO2-EOR. In Global technology roadmap for
CCS in industry. Sectoral assessment: CO2 enhanced oil recovery.
[12]. HIS Markit. (2016). Air Separation Gases. In Chemical Economics Handbook. Retrieved
from https://ihsmarkit.com/products/air-separation-gases-chemical-economics-handbook.html
[13]. Rao, A. D. (2012). Combined cycle power plant configuration. In Combined Cycle
Systems for Near-Zero Emission Power Generation (1.6). Woodhead Publishing. Retrieved
from https://app.knovel.com/hotlink/pdf/id:kt00C51KE9/combined-cycle
systems/combined-c-cycle-power
[14]. International Energy Agency. (2000). Key Components For CO2 Abatement: Gas Turbines.
Retrieved from
http://www.ieaghg.org/docs/General_Docs/Reports/PH3_12%20Gas%20Turbines.pdf
[15]. Stuart Thomson. (2005). Liberty global's technology roadmap. London: Informa
Telecoms & Media Group.Retrieved from
http://hub.globalccsinstitute.com/sites/default/files/publications/15676/global-technology-
roadmap-ccs-industry-sectoral-assessment -co2-enhanced-oil-recovery.pdf
[16] Gholami, R., Alyani, M., & Smith, K. (2015). Deactivation of pd catalysts by water
during low temperature methane oxidation relevant to natural gas vehicle converters.
Catalysts, 5(2), 561-594. 10.3390/catal5020561 Retrieved from
https://search.proquest.com/docview/1706282848
[17] Stuart Thomson. (2005). Liberty global's technology roadmap. London: Informa Telecoms
& Media Group. Retrieved from https://search.proquest.com/docview/221802384
[18] WorleyParsons Limited. (2013). CCS learning from the LNG sector: A Report for the
Global CCS Institute. Retrieved from https://hub.globalccsinstitute.com/publications/global-
technology-roadmap-ccs-industry-sectoral-assessment-co2-enhanced-oil-recovery-19
47
[19]. Australian National Low Emissions Coal Research & Development. (2012). Control of
impacts of nitrogen. In Gas quality control in oxy-pf technology for carbon capture and storage.
[21].Leung, D. Y.C., Caramanna, G., & Mercedes, M. (2014). An overview of current status of
carbon dioxide capture and storage technologies. Renewable and Sustainable Energy Reviews,
Vol 39, 426-443.
[22].Yu,C. H., Huang, C. H., & Tan, C. S. (2012). A Review of CO2 Capture by Absorption and
Adsorption. Aerosol and Air Quality Research, Vol 12, 745–769
[23]. (2004). Section 20: Dehydration In Gas Processors Suppliers Association (12 Edition).
Engineering Data Book (pp. 20-1 to pp.20-48). Tulsa, Oklahoma: Gas Processors Suppliers
Association.
[24].Kemper, J., Sutherland, L., Watt, J., & Santos, S. (2014). Evaluation and analysis of the
performance of dehydration units for CO2 capture. Energy Procedia, 7568-7584.
[25]. Maddocks, J., McKay., W., and Hansen., V. “Acid Gas Dehydration - A DexPro
Technology Update. Retrieved from
https://gasliquids.com/content/2011_AcidGasDehydrationDexpro.pdf
[26]. “Brazed Aluminum Heat Exchangers.” Chart Energy and Chemicals. Retrieved from
http://files.chartindustries.com/Brazed-Aluminum-Heat-Exchangers.pdf
48
[28]. “Cogeneration and Combined-Cycle Principles Workshop Introduction to HRSGs.”
Innovative Steam Technologies. Retrieved from: http://www.iagtcommittee.com/downloads/
2009papers/Training%20Session4%20%20More%20Heat%20Recovery%20Steam%20Generato
rs.pdf
[29]. Ganapathy, V. (1996). “Heat Recovery Steam Generators: Understand the Basics.”
Chemical Engineering Progress. Retrieved from
http://www.angelfire.com/md3/vganapathy/hrsgcep.pdf
[30]. Heat Recovery Steam Generators. (2007). API Recommended Practice 534 (Second
Edition). Retrieved from: https://eclass.srv.ualberta.ca/pluginfile.php/
4064772/mod_resource/content/2/API%20534%20Heat%20Recovery%20Steam%20generators.
pdf
[31]. IEA Greenhouse Gas R&D Programme. (2011). Types and sizes of compression
machinery. In Rotating equipment for carbon dioxide capture and storage.
[32]. (2004). Section 20: Dehydration In Gas Processors Suppliers Association (12 Edition).
Engineering Data Book (pp. 20-1 to pp.20-48). Tulsa, Oklahoma: Gas Processors Suppliers
Association.
[33]. Ulrich, G.D. and Vasudevan, P.T. (2004). Chemical Engineering Process Design and
Economics: A Practical Guide. (Second Edition) Durham: Sheridan Books. Pg. 96-99.
[34] Guthrie, K.M., (1974). Process Plant Estimating, Evaluation, and Control. Solana Beach,
CA: Craftsman Book Company of America.
[35] Church., L., and Jamieson., M., “Project Execution Strategies: Site Influences.” University
of Alberta CH E 465 Notes. Retrieved from
Eclass:https://eclass.srv.ualberta.ca/pluginfile.php/4064997/mod_resource/content/2/Execution%
20Strategies%20-%20EPC%20II.pdf
49
[36] Chemical Engineering Essential for the CPI professional. (2018).CEPCI UPDATES:
JANUARY 2018. Retrieved from: http://www.chemengonline.com/cepci-updates-january-
2018-prelim-and-december-2017-final/
[37] Colt Engineering Corp. “6.4 Compressor (Centrifugal Air Compressors C/W electrical
driver)”. Retrieved University of Alberta CH E 465 from class course notes:
https://eclass.srv.ualberta.ca/pluginfile.php/4064928/mod_resource/content/2/6_Compressors.
pdf
[38] Green D. W. & Perry R.H. (2007). Perry's Chemical Engineers' Handbook (8th Edition).
McGraw-Hill Publishing. Table 9-13
[39] STI Group (2006).The Main Advantages of Shop Fabrication for Industrial Piping.
Retreived from: http://setxind.com/fabrication/main-advantages-shop-fabrication-industrial-
piping/
[42] AECO-C Natural Gas Price. Retrieved from Alberta Energy Regulator
https://www.aer.ca/data-and-publications/statistical-reports/aeco-c
[43] Payscale Inc. (2018). Power Plant Operator Salary (Canada): National Average. Retrieved
from: https://www.payscale.com/research/CA/Job=Power_Plant_Operator/Salary
50
https://eclass.srv.ualberta.ca/pluginfile.php/4064932/mod_resource/content/1/utilities%20cost
s%202008.pdf
[45] KPMJ. (2028). Corporate Tax Rate.Retrieved from Income Tax Rates for General
Corporations: https://home.kpmg.com/content/dam/kpmg/ca/pdf/2018/04/federal-and-
provincial-territorial-income-tax-rates-for-general-corporations-2018.pdf
[47]. US Department of Energy. (2010). Carbon Dioxide Enhanced Oil Recovery. Retrieved
from the National Energy Technology Laboratory Website:
https://www.netl.doe.gov/file%20library/research/oil-gas/CO2_EOR_Primer.pdf
[49]. Ulrich, G.D. and Vasudevan, P.T. (2004). Chemical Engineering Process Design and
Economics: A Practical Guide. (Second Edition) Durham: Sheridan Books. Pg. 526-529
[50]. (n.d.). Decoupled Barrier Materials for Pipes & Ducts Noise Reduction. Retrieved from:
http://www.acoustiguard.com/products/pipes-ducts/decoupled-barrier-materials.html
[51] Cocchio, J. R. and Winkel, G. (2014). Module 5-20: Hazard and Operability Process
(HAZOP). In Engineering Safety and Risk Management Program University of Alberta.
[52] https://www.apega.ca/assets/PDFs/risk.pdf
51
[53] Yanisko, P. and Croll, D. (2012). Use Nitrogen Safely. Air Products and Chemicals Inc..
Retrieved from http://www.airproducts.com/~/media/downloads/article/U/en-use-nitrogen-
safely-312-12-023.pdf
[54]
http://www.qp.alberta.ca/1266.cfm?page=O02.cfm&leg_type=Acts&isbncln=9780779775699&d
isplay=html
52
10. Appendices
Appendix A - Technologies Considered
Appendix B - Engineering Drawings and Stream Tables Package
Appendix C - Overall Material and Energy Balance Table
Appendix D - Air Separation Unit Equipment Sizing and Selection
Appendix E - Power Generation Unit Equipment Sizing and Selection
Appendix F - Carbon Dioxide Unit Equipment Sizing and Selection
Appendix G - Process Line Sizing
Appendix H - Detailed Heat Exchanger Sizing and Datasheet
Appendix I - Detailed Pump Sizing and Datasheet
Appendix J - Project Execution Strategy
Appendix K - Economics Analysis
Appendix L - Environmental Impacts Analysis
Appendix M - Risk Assessment and Process Hazards Analysis (PHA)
Appendix N - HAZOP Analysis
Appendix O - FEI Calculations
Appendix P - PSV Datasheet, Sizing and Selection
Appendix Q - Social Impacts Analysis
Appendix R - Process Simulation Package
Appendix S - Three Pertinent Literature Articles
Appendix T - Email Correspondences
53