Professional Documents
Culture Documents
2017
Transmission
Capability Statement
(2017-2021)
Preface
This Transmission Capability Statement is provided by the Oman Electricity Transmission
Company according to Transmission and Dispatch Licence Condition number 27 and the Grid
Code (Planning Code). The Statement describes in detail the MIS and Dhofar transmission systems
capability over the coming five years 2017-2021. The Statement provides up-to-date transmission
system data in order to identify those parts of the system, which offer the opportunity for future
development of existing and potential users of the system.
In this Capability Statement, the results of load flow and short circuit analysis are presented based
on the planned system expansion reinforcement to meet the generation plan provided by Oman
Power and Water Procurement Company and the demand forecast provided by the Distribution
Companies (MEDC, MJEC, MZEC and DPC). The OETC grid model has been updated to include
new projects schedule, demand foecast, generation data and transmission system data. Total of 68
transmission projects at MIS and Dhofar are planned over the five years period. Most of projects
are designed to increase the transmission system capacity so that it can meet future growth in
demand and satisfy the security criteria.
The existing and planned development in the generation and transmission system is described,
including the compeletion of 400kV transmission network to connect the 2000MW Sur power
plant in 2017. This is in addition to the introduction of three new power plants at Ibri in 2018 with
capacity of 1508MW, at Sohar in 2019 with capacity of 1708MW and at Misfah in 2021 with
capacity of 1000MW. In addition, Salalah 2 IPP Power Plant is expected to be in service in 2018
and it will be connected to Dhofar transmission system. Also, the first 50 MW Wind Farm project
in the Sultanate of Oman will be connected to Dhofar transmission system in 2019.
It is one of OETC’s strategic planning concepts to introduce the 400kV system as a backbone to
allow the power evacuation from the centralized power plants. Major developments in the MIS
transmission system include the installation and operation of new 400kV transmission lines with
associated new 400/220kV and 400/132kV grid stations. In addition, the developments include the
installation of 220kV and 132kV transmission lines with associated new 220/132kV and 132/33kV
grid stations at MIS and Dhofar systems. The OETC strategy to operate the 400kV as backbone,
220kV as transmission and 132kV as subtransmission systems.
OETC has made an effort in reveiwing and updating the Transmission Secuirty Standard to cover
the recent development in generation, 400kV Transmission System and Renewable Energy. The
Authority for Electricity Regulation has granted the approval of the second edition of the
Transmission Secuirty Standard in July 2016.
Page | 1
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Contents
Preface 1
List of Figures 5
List of Tables 7
Document History and Status 8
Distribution of Copies 8
Glossary 9
1. Executive Summary 0
2. Introduction 22
2.1 Licence conditions, Codes and Standards 22
3. Technical requirements for compliance with the Grid Code and Licence 24
3.1 System Frequency 24
3.2 System Voltage 25
5.2.4 Projects expected to be completed in time to meet the 2020 peak demand 33
5.2.5 Projects expected to be completed in time to meet the 2021 peak demand 33
5.3 Summary 34
Page | 2
Five-Year Annual Transmission Capability Statement (2017 - 2021)
6.5.1 Interconnection with the GCCIA Grid through UAE (Transco Abu Dhabi) 55
9. Development Opportunities 91
9.1 Review of the Generation Versus Load Balance on an Area Basis 91
A.3 Projects expected to be completed to meet the 2018 peak demand 120
A.4 Projects expected to be completed to meet the 2019 peak demand 123
A.5 Projects expected to be completed to meet the 2020 peak demand 127
A.6 Projects expected to be completed to meet the 2021 peak demand 127
Page | 3
Five-Year Annual Transmission Capability Statement (2017 - 2021)
C.3 Diagrames of the model for the Load Flow Study Results 157
Page | 4
Five-Year Annual Transmission Capability Statement (2017 - 2021)
List of Figures
Figure 1: Existing MITS in Peak 2017 35
Figure 2: Existing MITS in Peak 2018 36
Figure 3: MITS expected development by Peak 2019 37
Figure 4: MITS expected development by Peak 2020 38
Figure 5: MITS expected development by Peak 2021 39
Figure 6: Dhofar existing transmission system in Peak 2017 40
Figure 7: Dhofar System expected development by Peak 2018 41
Figure 8: Dhofar System expected development by Peak 2019 42
Figure 9: Dhofar System expected development by Peak 2020 43
Figure 10: Dhofar System expected development by Peak 2021 44
Figure 11: MIS Load on 2016 Peak Day 56
Figure 12: Dhofar System Load on 2016 Peak Day 57
Figure 13: MIS Load on 2016 Minimum Load Day 59
Figure 14: Dhofar System Load on 2016 Minimum Load Day 59
Figure 15: Number of out-of-firm grid stations during 2017-2021 of MIS 79
Figure 16: Number of out-of-firm grid stations during 2017-2021 of Dhofar 79
Figure 17: Voltage profile at 400kV busbars in p.u. 81
Figure 18: Voltage profile (p.u.) at Airport Heights Grid Station 82
Figure 19: Voltage profile (p.u.) at MIS Grid Station 83
Figure 20: Voltage profile (p.u.) at Salalah Free Zone Grid Station 84
Figure 21: Voltage profile (p.u.) at Ittin Grid Station 85
Figure 22: Voltage profile (p.u.) at Al Qarm Grid Station 86
Figure 23: Transmission power losses at peak demand of the years 2017-2021 of MIS 87
Figure 24: Transmission power losses at peak demand of the years 2017-2021 of Dhofar 87
Figure 25: Peak load growth over the period 2017-2021 of MIS 88
Figure 26: Peak load growth over the period 2017-2021 of Dhofar 89
Figure 27: Future OETC MIS Transmission System (2021) 92
Figure 28: Future OETC Dhofar Transmission System (2021) 93
Figure 29: Generation and load balance in Muscat area 99
Figure 30: Generation and load balance in Al Batinah South area 100
Figure 31: Generation and load balance in Al Batinah North area 100
Figure 32: Generation and load balance in Al Bureimi area 101
Figure 33: Generation and load balance in Al Dhahirah area 102
Figure 34: Generation and load balance in Al Dakhiliah area 102
Figure 35: Generation and load balance in Al Sharqiyah area 103
Figure 36: Generation and load balance in Dhofar area 104
Figure 37: Used and available MVA in Muscat area at 2021 peak demand 106
Page | 5
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Figure 38: Used and available MVA in Muscat area at 2021 peak demand 107
Figure 39: Used and available MVA in Muscat area at 2021 peak demand 107
Figure 40: Used and available MVA in Al Batinah South area at 2021 peak demand 108
Figure 41: Used and available MVA in Al Batinah North area at 2021 peak demand 108
Figure 42: Used and available MVA in Al Bureimi and Al Dhahiriah area at 2021 peak demand 109
Figure 43: Used and available MVA in Al Dakhiliah area at 2021 peak demand 109
Figure 44: Used and available MVA in Al Sharqiyah area at 2021 peak demand 110
Figure 45: Used and available MVA in Dhofar area at 2021 peak demand 110
Figure C 1: MIS 2017 Max. Load Flow Condition 205
Figure C 2: MIS 2018 Max. Load Flow Condition 206
Figure C 3: MIS 2019 Max. Load Flow Condition 207
Figure C 4: MIS 2020 Max. Load Flow Condition 208
Figure C 5: MIS 2021 Max. Load Flow Condition 209
Figure C 6: Dhofar System 2017 Max. Load Flow Condition 210
Figure C 7: Dhofar System 2018 Max. Load Flow Condition 211
Figure C 8: Dhofar System 2019 Max. Load Flow Condition 212
Figure C 9: Dhofar System 2020 Max. Load Flow Condition 213
Figure C 10: Dhofar System 2021 Max. Load Flow Condition 214
Page | 6
Five-Year Annual Transmission Capability Statement (2017 - 2021)
List of Tables
Table 1: Summary of Planned Developments on OETC Transmission System (2017 - 2021) 3
Table 2: Demand Connections – Demand Class Sepecification 26
Table 3: Existing and committed future generating capacity 48
Table 4: New Contracted and Planned Generating Capacity 53
Table 5: Non-Contracted Generating Capacity 54
Table 6: Centrally Dispatched Generating Capacity on OETC Transmission System 54
Table 7: Historic Growth in Peak Demand and Transmission Losses (2003 – 2016) 57
Table 8: Expected Load Transfers between Grid Supply Points (2017-2021) 62
Table 9: OETC Transmission System Demand Forecast by Grid Station 66
Table 10: Comparison of Demand Forecast with Available Generating Capacity including Planned Retirements 71
Table 11: Comparison of Demand Forecast with Available Generating Capacity and Non-Contracted Generation
in service 72
Table 12: Summary of Connected Generation Used in Load Flow Studies of Maximum Demand 75
Table 13: Summary of Connected Generation Used in Load Flow Studies of Minimum Demand 76
Table 14: Estimated Power Surplus and Power Deficit on an Area Basis (2017-2021) 94
Table 15: Available Grid Station Capacity of More than 10 MVA in 2021 105
Table 16: Expected Over headlines/ Cables Which will not omply with Transmission Security Standard (First
Outage) at Peak Demand in 2017 113
Table 17: Expected Grid stations 132/33kV, which will not comply with Transmission Security Standard (First
Outage) at Peak Demand in 2017 114
Table 18: Expected Grid stations 132/33kV, which will not comply with Transmission Security Standard at
Maintenance Period in 2017. 115
Table B 1: Load and Capacitor Data for Grid Station (2017-2021) 130
Table C 2: Available Capacity at Grid Stations (2017-2021) for Connection of New Demand 163
Table C 3: Overhead Line and Cable Circuit Loadings (%) at Peak Demand (2017-2021) 168
Table C 4: Transmission System Voltage Profile at Peak Demand (2017-2021) 177
Table C 5: Transmission System Voltage Profile at Minimum Demand (2017-2021) 184
Table C 6: Estimation of Transmission Losses and Generation Margin at Peak Demand (2017-2021) 191
Table C 7: Maximum 3-Phase Short Circuit Fault Levels 192
Table C 8: Maximum 1-Phase Short Circuit Fault Levels 200
Page | 7
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Network Planning
D.2 22/02/2017 CEO 23/02/2017 Final draft
Department
Network Planning
D.3 23/02/2017 AER 04/05/2017 Final draft
Department
Distribution of Copies
Revision Copy no Quantity Date Issued to
V.0 1 1 17/02/2017 Eng. Ali Al Hadabi
Printed: 17/02/2017
Page | 8
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Glossary
AER Authority for Electricity Regulation, Oman
AIS Air Insulated Switchgear
DISCOs Distribution Companies
DPC Dhofar Power Company (SAOC)
GCCIA Gulf Cooperation Council Interconnection Authority
GIS Gas Insulated Switchgear
GPDC Al Ghubrah Power and Desalination Company (SAOC)
GS Grid Station
GT Gas Turbine
IPP Independent power project
IWP Independent water project
IWPP Independent water and power project
kV kiloVolt
LILO Line In Line Out
MEDC Muscat Electricity Distribution Company (SAOC)
MITS Main Interconnected Transmission System
MJEC Majan Electricity Company (SAOC)
MVA Mega Volt Ampere
MVAr Mega Volt Ampere reactive
MW Megawatt(s)
MWh Megawatt hour(s) = (1,000) kWh
MZEC Mazoon Electricity Company (SAOC)
OES Oman Electrical Standard
OETC Oman Electricity Transmission Company (SAOC)
OHL Over Head Line
OPWP Oman Power and Water Procurement Company (SAOC)
PAEW Public Authority for Electricity and Water
PDO Petroleum Development Oman (LLC)
PS Power Station
RAEC Rural Areas Electricity Company (SAOC)
ST Steam Turbine
SVC Static Var Compensator
TSS Transmission Security Standard
UAE United Arab Emirates
UGC Underground Cable
Page | 9
1. Executive Summary
This Capability Statement presents the Oman Electricity Transmission Company’s development plans for the
400kV, 220kV and 132kV transmission systems for the years 2017 to 2021. Dhofar system has been transferred to
the Oman Electricity Transmission Company (OETC) on 1st January 2014. This document describes the
development plans for both MITS and Dhofar Transmission Systems.
The Statement includes data for the generators, loads, overhead lines, cables, transformers, reactive power
compensators and capacitor banks used in the development of transmission system models. In addition, the
Statement includes the demand and generation forecast. The power system studies undertaken by OETC’s
DIgSILENT PowerFactory software, version 15.2, in preparation of this Capability Statement. The Statement also
includes the results of power system analysis of the transmission system that defines system performance when
operating under the extreme peak (summer season) and off peak (winter season) in each of the five years. From this
analysis an assessment has been made of the opportunities for the connection of new generation, new demand and
reinforcement on the system.
Table 1 lists the schedule for committed and planned system development projects on the 400kV, 220kV and 132kV
transmission systems, although it should be noted that not all of the projects listed have full authorisation at this
time. The 400kV system development in MITS, includes the installation of two 400/220kV interconnection grid
stations, four 400/220/132/33kV grid stations, one 400/220/132kV and two 400/132kV grid stations. In addition,
the number of 220kV grid stations in MITS will increase from sixteen in peak of 2017 to nineteen in peak of 2021.
After adding Barka-3 PS grid station in peak of 2018, there will be two 220/33kV grid stations. The total number
of both MITS and Dhofar transmission system of 132/33kV grid stations will also increase from fifty-four in peak
of 2017 to seventy-one by peak of 2021.
It is one of OETC’s strategic planning concepts to introduce the 400kV system as a backbone to allow the power
evacuation from the centralized power plants. Furthermore, OETC installed 220kV double circuit lines around
northern Oman to supply and support the 132kV system. In 2010, the 220kV connection between the Sohar
Interconnector Station (SIS) and Mahadha (Al-Wasit) was completed to support linking Oman (OETC) with the
GCCIA Grid through UAE (Transco Abu Dhabi) network. In 2013, the 220kV transmission system was extended
from Misfah in the Muscat area to Jahloot. In addition, a 220kV line between Mahadha and Ibri was energize in
2012 to support the voltage, meet the expected growth in the area and meet the Transmission System Security
Standard.
Moreover, OETC has introduced the first 400kV system that includes 400kV connection between Jahloot grid
station and Sur power station and line between Sur power station and New Izki grid stations in 2016. Other 400kV
transmission lines will be installed between New Izki-Misfah, Ibri-New Izki, Sohar-3 IPP-Sohar Free Zone, Sohar
Free Zone-SIS, Sohar Free Zone-Mahadha (will be operated as 220kV) and Misfah-Rusail Industrial grid stations.
Furthermore, there will be a LILO connection from the Sur- New Izki 400kV line at Qabel grid station through a
400/132kV grid station. Accordingly, a total of nine 400kV grid stations will be commissioned at Sur, Jahloot, New
Izki, Misfah, Ibri, Sohar Free Zone, SIS, Qabel and Rusail Industrial. The total installed capacity of 400kV grid
substations will be around 15,250 MVA in 2021.
Five-Year Annual Transmission Capability Statement (2017 - 2021)
In accordance with Condition 27 of OETC’s Transmission and Dispatch Licence, the power flow studies presented
in this Capability Statement are based on updated demand forecast data provided by Distribution companies
(DISCOs) and the updated generation forecast by Oman Power and Water Procurement Company (OPWP).
To be able to perform the studies and produce the results presented in this statement, the deadline to receive data
from various parties (OPWP, DISCOs) is as per the Grid Code. Any information received after the deadline will be
included in the next Five-Year Annual Transmission Capability Statement (2018-2022).
The forecast average annual growth in system demand of about 6.34% for MITS and 9.0% for Dhofar system is
over the period 2017-2021 drives many of the planned grid station reinforcements. To meet security of supply
requirements and provide load relief to the loaded grid stations, it will be necessary to transfer excess load to the
new or existing grid stations. Furthermore, OPWP has submitted a connection application dated 16 February 2014
for connection of new power plants to the MITS at Ibri and Sohar. The recent updated generation data is shown a
total of 1508MW at Ibri and 1708MW at Sohar Power Plants. Also, there is another connection application
submitted by OPWP dated 31 August 2014 for connection of 400MW (Salalah-2 IPP) at Dhofar transmission
network. The recent updated generation data is shown a total of 437.8MW from new Salalah-2 IPP in 2018. In
addition, OPWP has submitted a connection application dated 19 October 2016 for a new generation of 1000MW
at Misfah. Moreover, Rural Area Electricity Company (RAEC) has submitted a connection application dated 25
December 2014 for the first Wind Farm Plant to Dhofar Transmission System with 50MW installed capacity and it
will be ready by 2019.
As the demand grows, there is a greater need to extend the transmission systems and to establish new 400kV
network as a backbone to transmit the bulk power from power plants. This will reduce the overload at the 220kV
and 132kV networks and subsequently improve voltages and reduce power losses. Consequently, the 220kV will
be operated as a transmission system and the 132kV as sub-transmission system.
From Table 1, a total of 67 transmission projects are planned over the five years period. Most of projects are
designed to increase the transmission system capacity, so that it can meet future demand growth and satisfy the
Transmission Security Standard. This is a major programme of capital investment that will be spread across the
whole network to improve transmission system performance in northern and southern of Oman. Power system
studies presented in this statement confirmed that the planned investment in 400kV, 220kV and 132kV grid stations
and transmission circuits will provide substantial spare capacity on the transmission systems.
The major technical issue identified in the studies was with high short-circuit fault levels on the 132kV busbars at
three grid stations in the Muscat area. The grid stations at Ghubrah, Rusail, Bousher and Madinat Sultan Qaboos
(MSQ) were all shown in earlier studies to have high 132kV fault levels. During 2017-2018, OETC has taken
appropriate remedial action to address this problem in the short–term by splitting the 132kV busbars and opening
some of 132kV lines at Muscat region without impacting the security requirements. From 2019, there will be no
longer need for busbars splitting due to the network development and reconfiguration works. Therefore, all busbars
will be returned to normal operation. However, some 132kV lines will still be needed to be kept open to reduce the
infeed short circuit contribution and this is a part of OETC long term strategy to operate the 400kV and 220kV as
the main transmission voltages.
Load flow studies have confirmed that the voltage levels across the transmission system will be maintain within the
limits. The 400kV voltage will be maintained in the system within the allowable limit ±5%. In addition, as defined
in the Grid Code the 220kV and 132kV will be maintained within ±10% and the 33kV will be maintained within
±6%. Also, the load flow has presented the issue of overvoltage during the winter peak time due to the 400kV lines.
Page | 1
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Accordingly, OETC is initiating a project to install a shunt reactors at the 400kV lines to overcome the overvoltage
issue during winter peak time.
The Statement has reviewed the opportunities for the connection of new generation and new demand and identified
those grid stations with substantial spare capacity where it should be possible to connect new demand to the system.
Section 2 of the Statement provides an introduction to the document, identifying the main related documentation
and the key changes that have taken place on the transmission system since the previous issue of the Statement.
Section 3 identifies the technical requirements of the Grid Code and the Transmission Licence with specific
attention to system voltage, frequency and security of supply.
Section 4 describes the main engineering standards used by OETC in its planning and design of the transmission
system.
Section 5 describes the existing transmission system and summarises the planned developments in each year over
the period 2017 to 2021.
Section 6 identifies the existing and planned developments in generation and describes the interconnections both
inside Oman and internationally, i.e. PDO and the GCCIA respectively.
Section 7 presents the comparison of demand forecast with the generation capacity available.
Section 8 discusses transmission systems performance and presents the results of load flow and short-circuits
studies that show the performance of the transmission system at both peak and off peak demand in each year from
2017 to 2021.
Section 9 identifies the development opportunities for the connection of new demand and new generating plants to
the transmission systems.
Section 10 presents the areas of the network that will be operating above the firm capacity and not compliance with
Transmission Security Standard in 2017.
Page | 2
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Peak 2017
· 2x 125MVA transformers
· To cater for the load growth at Barka area
Madinat Barka 132/33kV grid 29th March · 10 no. 132kV GIS
1 Energized · To meet Transmission Security Standard
station (TX1 & TX2) 2016 · 0.13 km LILO of 132kV OHL from Filaj to
· Load transfer from Barka Main
Mualdah
New Izki 400/220 kV grid · 2 x 500 MVA transformers (400/220kV) · To support the voltage and power flow to Al
4 4th July 2016 Energized Dakhliah area
station · 12 no. 400kV GIS
· To comply with Transmission Security Standards
requirements
Page | 3
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2017 - 2021)
Expected
S.N Project Completion Status Main Equipment Purpose
Date
Peak 2017
Page | 4
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2017 - 2021)
Expected
S.N Project Completion Status Main Equipment Purpose
Date
Peak 2017
· 2 x 125 MVA · To cater for the new demand within the area
End of Under
9 Dreez 132/33kV grid station · 30 km 132kV OHL from Ibri · Load transfer from Ibri and Al Hayl grid stations
March 2017 Construction
· 8 no. 132kV GIS
Page | 5
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2017 - 2021)
Expected
S.N Project Completion Status Main Equipment Purpose
Date
Peak 2017
33kV busbars Interlinking at End of June Under · 8 no. of 33kV GIS at Bousher & ·To meet Transmission Security Standard
14 Bousher & Mawalleh South 2017 Construction Mawalleh South
grid stations
· 4 x 125MVA Transformers
· To meet load growth requirements
· 10 no. of 132kV GIS
End of June Under · To meet Transmission Security Standard
15 S’aadah 132/33kV grid station · 4 no. 33kV GIS Interlink
2017 Construction · Load Transfer from Al Qarm, Ittin and Awqad grid
· 13 km LILO from Ashoor- stations
Awqad132kV UGC
Page | 6
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2017 - 2021)
Expected
S.N Project Completion Status Main Equipment Purpose
Date
Peak 2017
Connection of Salalah-2 IPP & · To connected the new Salalah-2 IPP Power Plant
Adding third & fourth End of June Under · 16 no. of 132kV GIS
16 · To meet load growth requirements
transformers to Salalah Free 2017 Construction · 2 x 125MVA transformers
Zone grid station · To meet Transmission Security Standard
Page | 7
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2017 - 2021)
Expected
S.N Project Completion Status Main Equipment Purpose
Date
Peak 2017
· 2 x 125 MVA transformers · To cater for the new demand in the area
End of June Under
18 Jebreen 132/33kV grid station · 2x0.5 km LILO of Nizwa - Ibri 132kV OHL · Load Transfer from Bahla grid station
2017 Construction
· 8 no. 132kV GIS · To meet Transmission Security Standard
Peak 2018
Page | 8
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2017 - 2021)
Expected
S.N Project Completion Status Main Equipment Purpose
Date
Peak 2018
· 2 x 125 MVA transformers · To cater for the new demand in the area
End of Under
23 Suwaiq 132/33kV grid station · 2x0.2 km LILO of MIS-Khadhra 132kV OHL · To meet Transmission Security Standard
September 2017 Construction
· 8 no. 132kV GIS · Load Transfer from MIS grid station
· 2 x 125 MVA transformers · To cater for the new demand in the area
End of Under · 2x15 km LILO of New Izki - Mudhaibi 132kV · Load transfer from Mudhaibi
25 Sinaw 132/33kV grid station
September 2017 Construction OHL · Solve the issue of voltage drop of 33kV lines
· 8 no. 132kV GIS · To meet Transmission Security Standard
Upgrading of Mawalleh North · To cater for the new demand in the area
grid station from 3x50MVA End of Under · To support the 33kV network in the Seeb area
26 · 2 x 125 MVA transformers
(132/11kV) to 2 x 125 MVA September 2017 Construction and enable to transfer more load from
(132/33kV) transformers neighbouring grid stations (Seeb & Mawalleh)
Daghmar 132/11kV grid End of Under · 1 x 50 MVA (shifted from the Mawalleh North
27 · To supply the new IWP at Quriyat
station September 2017 Construction grid station)
Page | 9
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2017 - 2021)
Expected
S.N Project Completion Status Main Equipment Purpose
Date
Peak 2018
· 2 x 500MVA transformers
End of · 2x0.5 km LILO of Al Filaj-Airport
Upgrading Mobella grid station Under · Supporting Mobella demand
28 September Heights 220kV OHL
to 220kV Construction · Securing of the supply within the area
2017 · 8 no. 220kV GIS
· 2 no. 132kV GIS
Page | 10
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2017 - 2021)
Expected
S.N Project Completion Status Main Equipment Purpose
Date
Peak 2018
Page | 11
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2017 - 2021)
Expected
S.N Project Completion Status Main Equipment Purpose
Date
Peak 2018
Page | 12
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2017 - 2021)
Expected
S.N Project Completion Status Main Equipment Purpose
Date
Peak 2018
· 1 x 125MVA transformer
Installing 220kV GIS and · To meet load growth requirements
End of June Under · 6 no. of 220kV GIS
38 adding fourth 125MVA · To meet Transmission Security Standard
2018 Construction · 8 no. of 132kV GIS
transformer at MSQ grid station · To cater for the new demand in the area
· 4 no. 33kV GIS Interlink
Peak 2019
Page | 13
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2017 - 2021)
Expected
S.N Project Completion Status Main Equipment Purpose
Date
Peak 2019
Page | 14
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2017 - 2021)
Expected
S.N Project Completion Status Main Equipment Purpose
Date
Peak 2019
Adding third & fourth transformers End of June · To meet Transmission Security Standard
· 2 x 125 MVA transformers
45 Design
132/33kV at Ghala grid station 2019 · 4 no. 33kV GIS Interlink · To meet load growth in the area
Reactive Power Compensation End of June · SVC at Hamriyah · To maintain the voltage within the range
46 Planning
Requirements (SVC) 2019 · SVC at Airport Heights during the transient at the winter time
Adding third & fourth transformers End of June · 2 x 125 MVA transformers · To meet Transmission Security Standard
47 Design · 2 no. 132kV GIS
132/33kV at Amerat grid station 2019 · To meet load growth in the area
· 4 no. 33kV GIS Interlink
· 2 x 125 MVA transformers
Adding third & fourth transformers End of June · To meet Transmission Security Standard
48 Design · 2 no. 132kV GIS
132/33kV at A'salam grid station 2019 · To meet load growth in the area
· 4 no. 33kV GIS Interlink
Page | 15
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2017 - 2021)
Expected
S.N Project Completion Status Main Equipment Purpose
Date
Peak 2019
Adding third & fourth · 2 x 125 MVA transformers · To meet Transmission Security
52 End of June Standard
transformers 132/33kV at Design · 2 no. 132kV GIS
2019
Sohar Free Zone grid station · 4 no. 33kV GIS Interlink · To meet load growth in the area
Page | 16
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2017 - 2021)
Expected
S.N Project Completion Status Main Equipment Purpose
Date
Peak 2019
Page | 17
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2017 - 2021)
Expected
S.N Project Completion Status Main Equipment Purpose
Date
Peak 2019
Peak 2020
Page | 18
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2017 - 2021)
Expected
S.N Project Completion Status Main Equipment Purpose
Date
Peak 2020
· 4 x 125 MVA transformers
· 10 no. 132kV GIS
End of June · To cater for the new demand in the area
60 Khoudh 132/33kV grid station Design · LILO 132kV Mawalleh South – Rusail
2020 · Load transfer from Mawalleh South grid station
Industrial
· 4 no. 33kV GIS Interlink
Adding third & fourth · 2 x 125 MVA transformers · To meet Transmission Security Standard
End of June
61 transformers 132/33kV at Planning · 2 no. 132kV GIS · To meet load growth in the area
2020
Ghubrah grid station · 4 no. 33kV GIS Interlink
Peak 2021
Page | 19
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2017 - 2021)
Expected
S.N Project Completion Status Main Equipment Purpose
Date
Peak 2021
· 3 x 500 MVA transformers (400/132kV) at Rusail
Industrial
. 7 no. 400kV GIS at Rusail Industrial . To evacuate power coming from Misfah IPP
Upgrading Rusail Industrial to End of June Power Plant and to supply area
63 Planning . 2 no. 400kV GIS at Misfah
400kV 2021
. 3 no. 132kV GIS at Rusail Industrial · To maintain Transmission Security Standard
. Upgrading 132kV OHL between Rusail Industrial
-Misfah to 400kV
Page | 20
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2017 - 2021)
Expected
S.N Project Completion Status Main Equipment Purpose
Date
Peak 2021
· 1 x 500 MVA transformer
Adding third transformer End of June · To meet Transmission Security Standard
68 Planning · 1 no. 220kV GIS
220/132kV at Airport Heights 2021 · To meet load growth in the area
. 1 no. 132kV GIS
Page | 21
Five-Year Annual Transmission Capability Statement (2017 - 2021)
2. Introduction
The purpose of the Statement is to provide up-to-date transmission system data for potential and existing
users of the transmission system so they can identify those parts of the transmission system which offer the
opportunity for future development. The Statement is required to be updated annually so that existing and
new users of the transmission system are furnished with the latest information.
New users of the transmission system should be aware of the following main documents that influence the
planning and future development of the transmission system infrastructure:
ii) The Electricity Transmission and Dispatch Licence granted to OETC by the AER.
iv) The Statement of Charges for Connection and use of system to OETC Electricity
Transmission System.
Page | 22
Five-Year Annual Transmission Capability Statement (2017 - 2021)
11. 33kV busbars Interlinking at Bousher & Mawalleh South grid stations
13. Connection of Salalah-2 IPP & Adding third & fourth transformers to Salalah Free Zone grid
station
14. 132kV Linking System between Al Falaj, Muttrah and Wadi Kabir Grid stations & Adding
Fourth 125MVA transformer at Wadi Kabir grid station
i. Updating the demand forecast data according to the received information from the DISCOs.
ii. Updating the generation plan according to the received information from the OPWP.
iii. Updating the operational limits of generating units according to the received information
from the OPWP.
iv. Updating the transmission system data for the new projects as per the actual parameters.
v. Updating the new generating units data as per the actual parameters.
The improvements in the demand forecast and the power system modelling should result in similar
improvements being achieved in the accuracy of the power system studies upon which network
development planning is based.
Page | 23
Five-Year Annual Transmission Capability Statement (2017 - 2021)
3. Technical requirements for compliance with the Grid Code and Licence
The Grid Code is designed to permit the development, maintenance and operation of an efficient,
economical and coordinated electricity transmission system. It facilitates competition in the generation and
supply of electricity and promotes the security and efficiency of the system as a whole.
The Transmission Security Standard required the capacity of the Transmission System to transmit
electricity and shall not be reduced in the event that a single electric line, transformer or breaker and/or
associated plant is not in service. The operating voltage of the Transmission System shall be maintain within
the limit specified in the Grid Code and TSS.
In order to comply with Condition 26 of the Electricity Transmission and Dispatch Licence the transmission
system must be planned, designed and operated to provide a secure, efficient and economic supply of
electricity that is of an acceptable quality to its users.
OETC shall ensure that, subject as provided in the Grid Code, the Electricity Transmission System complies
with the following technical, design and operational criteria in relation to the part of the Electricity
Transmission System at the Connection Site with a User (unless otherwise specified in the Grid Code).
Although in relation to operational criteria, OETC may not be able to comply with this obligation to the
extent that others parties are not comply with the Grid Code. Each User shall ensure complies with the
criteria set out in the Grid Code (CC.6.1.5).
Whilst Condition 26 specifically sets out the Security of Supply requirements, the most important
characteristics that determine the quality of supply are frequency and voltage. The requirements for
maintaining transmission system frequency and voltage within specified operating limits are set out in the
Grid Code, and most clearly defined under conditions CC.6.1.1 and CC.6.1.2 respectively of the Connection
Conditions Code.
Grid Code establishes the historic frequency and voltage performance of the transmission system,
specifically in relation to operation at abnormal voltages and frequencies. Consider how future generation
and demand changes may affect transmission system performance in these areas. It establishes the relevant
generation design criteria and standards, and the impacts of operation at abnormal voltages and frequencies
on generating units. It considers whether the current Grid Code frequency and voltage requirements are
appropriate, taking into account of system security requirements, the capabilities of generating units, the
industry costs and benefits of implementing them.
a) During normal operating conditions, the nominal system frequency of the transmission
system shall be 50.00Hz and will be controlled normally between 49.95Hz and 50.05Hz.
Page | 24
Five-Year Annual Transmission Capability Statement (2017 - 2021)
b) During exceptional steady state conditions, frequency deviations will not exceed 49.90Hz
to 50.10Hz unless disturbed circumstances prevail.
c) Under disturbed conditions, system frequency could rise transiently to 51.50 Hz or fall to
47.5 Hz, but not exceed these limits.
As CC.6.1.1 points out, the frequency of the total system is responsive to changes in the balance between
the active power demand and total available generation capacity. OETC must therefore ensure that
sufficient generation capacity and demand is available and connected to the system at all times to respond
automatically to active power imbalances and correct any frequency change.
a) The voltage on the 220kV and 132kV parts of the Transmission System at each site with
a user connection will remain within the limits of ±10% of the nominal voltage level.
As there is no specifications for voltage limits for the 400kV system in the Grid Code, OETC adopted a
value of ±5% limits for this voltage level to be in accordance with international standards and design
specification. The internal OETC standard specifications and the Transmission Security Standard include
the limit mention for the 400kV system.
During some system disturbances, such as where short circuits occur, the voltage could collapse transiently
to zero at the point of fault until the fault is cleared. Voltage regulation requires both active and reactive
power flows across the transmission system to be carefully controlled. The physical characteristics of the
plant on the transmission system also give rise to the generation and absorption of reactive power. Reactive
power flows across the transmission system can give rise to substantial voltage differences and it is therefore
necessary to maintain reactive power balances between sources of capacity and demand on a “zone” basis.
Unlike frequency, which is consistent across an interconnected transmission system, voltages at different
points on an interconnected system are determined by the local sources of demand and capacity, by the
prevailing network configuration and by the reactive power flows across the network. The management of
voltage requires control of reactive power can be provided by generation units, transformer tap-changers,
capacitor banks at 33kV or below, shunt reactors or by means of static VAR compensator (SVC).
Page | 25
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Demand Connections
Demand Class definition and supply restoration times
Demand Class
Demand Class
Repair time of
A 0 2 No requirement
faulted circuit
B 2 6 3 hours No requirement
Return time of
C 6 20 15 minutes Maintenance
Planned Outage
Total Group Period Demand
Demand for the Demand
Momentary Group
Return time of
D 20 115 Interruption
Planned Outage
allowed
Momentary Momentary
E 115 300 Interruption Interruption
allowed allowed
Page | 26
Five-Year Annual Transmission Capability Statement (2017 - 2021)
In addition to the technical requirements of the Transmission Licence and the Grid Code, the principal
electrical standards used by OETC in its planning and design of the 400kV, 220kV and 132kV transmission
systems are:
Page | 27
Five-Year Annual Transmission Capability Statement (2017 - 2021)
The transmission system was first established under the Ministry of Electricity and Water (MEW) in 1983
and underwent rapid expansion during the 1990s. Consequently much of it has less than 15 year service
experience. After the electrical sector was unbundled, the OETC took over the operation of the MITS on
1st of May 2005 and Dhofar Transmission System on 1st of January 2014.
Page | 28
Five-Year Annual Transmission Capability Statement (2017 - 2021)
The transmission system is interconnected with the transmission system of GCCIA Grid through UAE
(Transco Abu Dhabi) at Mahadha (Al Wasit) grid station through 220kV. The interconnection links the
electricity supply systems of Kuwait, Saudi Arabia, Bahrain, Qatar, UAE and Oman. This should increase
the security of supply and benefits to the member countries in the form of cost savings from the sharing of
reserve capacity and energy resources. The 220kV interconnector between OETC and Transco Abu Dhabi
has been energised and brought into service since 14th of November 2011. Oman recently has signed
officially the agreement with the GCCIA in November 2014 and became a member of GCC grid.
The OETC transmission system is also interconnected with the Sohar Aluminium system at 220kV via a
double circuit cable that runs between SPS on the OETC system and Sohar Aluminium 220kV busbar.
Under normal conditions the power transfer across the interconnection is forecasted to be negligible, but in
the event of an emergency on either network the interconnection can facilitate a power transfer of up to
300 MW to address the shortfall.
The OETC transmission system is also interconnected with the PDO transmission network at 132kV via a
single circuit overhead line that runs between Nizwa on the OETC system and Nahada on the PDO system.
Under normal conditions the power transfer across the interconnection is forecasted to be negligible, but in
the event of an emergency on either network the interconnection can facilitate a power transfer to address
the shortfall. In addition, OETC transmission system at Dhofar is also interconnected with the PDO
transmission network at 132kV via a single circuit overhead line that runs between Thumarit at OETC
system and Harweel at PDO system.
The transmission system at MIS area is supplied with electricity generated from eleven gas-based power
stations located at Ghubrah, Rusail, Wadi Jizzi, Manah, Al Kamil, Barka (ACWA), Barka SMN, Barka III,
Sohar I, Sohar II and Sur IPP. In addition, the transmission system may be supplied from direct customers,
Page | 29
Five-Year Annual Transmission Capability Statement (2017 - 2021)
such as Sohar Aluminium and PDO. The transmission system at Dhofar area is supplied with electricity
generated from two gas-based power stations located at NPS and Salalah-1 IWPP.
Four Distribution and Supply Licence holders, i.e. Muscat Electricity Distribution Company (MEDC),
Mazoon Electricity Company (MZEC), Majan Electricity Company (MJEC) and Dhofar Power Company
(DPC), take the bulk of the power transmitted through the main grid stations to supply the Distribution
system.
In addition to the four distribution companies, twelve large private customers are directly connected to the
transmission system. The existing private customers are:
220kV Connections
132kV Connections
The following new customers will be directly connected during the period covered by the Statement:
Orpic Plastic Company will be connected to 220kV SPS-2 grid station in 2018.
Page | 30
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Moon Steel Company will be connected to 220kV Sohar Free Zone in 2019.
Salalah Methanol Company will be connected to 132kV Salalah Free Zone in 2019.
In 2016, MIS gross peak demand was 6105 MW which occurred at 15:30 hours on 12th June, an increase
of 6.28% on the 2015 peak demand. During 2016, the electric energy delivered to the MIS from connected
generating plants & other generators was 29,548.940 GWh whilst that exported from the MIS to the
Distribution Companies was 29,074.490 GWh resulting in transmission system energy losses of 474.450
GWh, which equates to a transmission system energy loss of 1.6 %.
In 2016, Dhofar system gross peak demand was 523 MW which occurred at 15:09 hours on 26th May, an
increase of 5.62% on the 2015 peak demand. During 2016, the electric energy delivered to the Dhofar
transmission system from connected generating plants & other generators was 3,057.166 GWh whilst that
exported from Dhofar system to Dhofar Power Company was 3,017.481 GWh resulting in transmission
system energy losses of 39.685 GWh, which equates to a transmission system energy loss of 1.3%.
Page | 31
Five-Year Annual Transmission Capability Statement (2017 - 2021)
station to connect the new Salalah-2 IPP power plant. Also, the construction of new 2x50 MVA 132/11kV
grid station at Daghmar to supply the new IWP at Quriyat.
Page | 32
Five-Year Annual Transmission Capability Statement (2017 - 2021)
5.2.4 Projects expected to be completed in time to meet the 2020 peak demand
Figure 4 shows in geo-schematic form the system arrangement to meet the 2020 peak demand. The new
projects planned to meet the summer peak demand in 2020 are at various stages of development. These
projects include new 132/33kV grid stations at Yanqul and Khoudh to cater the demand growth in these
areas. Furthermore, adding third and fourth 125MVA transformers to meet the Transmission Security
Standard and load growth will be at Ghubrah grid station.
5.2.5 Projects expected to be completed in time to meet the 2021 peak demand
Figure 5 shows in geo-schematic form the system arrangement to meet the 2021 peak demand. The new
projects planned to meet the summer peak demand in 2021 are at various stages of development. These
projects include new 132/33kV grid stations at Falaj Al Qabail, Madinat Ibri and Khuwair to cater the
demand growth in these areas. Furthermore, upgrading 2x30MVA transformers to 2x125MVA
transformers at Thumrait grid station to meet the Transmission Security Standard and load growth. In
addition, the developments to evacuate the power coming from Misfah IPP Power Plant include a new
220kV connection at Misfah IPP, LILO the existing 220kV line between MSQ and Misfah grid stations and
adding 220/132kV, 2x500MVA transformers at existing Misfah grid station. Also, the projects
Page | 33
Five-Year Annual Transmission Capability Statement (2017 - 2021)
development of 2021 include upgrading Rusail Industrial grid station to 400kV and adding third 220/132kV
transformer at Airport Heights grid station.
5.3 Summary
Table 1 in the Executive Summary has summarised the development plans for the OETC Transmission
System on a project by project basis at the time of this statement. The table identifies the projects to which
OETC are already committed and those projects that are considered likely to proceed. The power system
studies presented in this capability statement is to show the expected performance of the transmission
system over the period 2017-2021. In addition, the studies have been performed on the basis that the
committed and planned development projects in Table 1 and detailed in Appendix A will proceed as planned
and to be completed on schedule. The system studies are used to identify areas of the transmission system
where there are opportunities for connecting new demand and new generation and where constraints should
be applied to further development.
Page | 34
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Page | 35
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Page | 36
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Page | 37
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Page | 38
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Page | 39
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Page | 40
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Page | 41
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Page | 42
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Page | 43
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Page | 44
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Barka (ACWA), Barka SMN and Barka III in Al Batinah South region
Page | 45
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Page | 46
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Page | 47
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Table 3 lists on a yearly basis the existing and committed future generating capacity over the period 2017-
2021. The table presents the gross and net maximum capacity for each generating unit at each power station
and takes account of the desalination load where appropriate.
Page | 48
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Page | 49
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Page | 50
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Page | 51
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Four generating units has been retired in 2015 (ST4, GT5, GT8, and GT11). In addition, it is planned to
retire two units (ST5 and ST6) by end of 2017 and the remining existing generating units will be retire by
end of 2018.
Ibri Independent Power Plant (IPP) will be commissioned in 2018 & 2019. In 2018 the total capacity will
reach 940 MW working in a combined cycle. Ibri Independent Power Plant (IPP) will reach the full power
of 1508 MW in 2019.
Sohar III Independent Power Plant (IPP) will be commissioned in 2019. In 2019, the total capacity will
reach 1708 MW working in a combined cycle.
c) Misfah IPP
Misfah Independent Power Plant (IPP) will be commissioned in 2020. In 2021, the total estimated capacity
will reach 1000 MW working in a combined cycle.
Page | 52
Five-Year Annual Transmission Capability Statement (2017 - 2021)
a) Salalah-2 (IPP)
Salalah-2 Independent Power Plant (IPP) will be commissione in 2018. The total capacity will reach 437.8
MW working in a combined cycle.
Table 4 summarises the net capacity of the additional future generating plant over the period 2017 to 2021.
Dhofar System
Table 5 shows the non-contracted generating capacity for the period 2017 to 2021.
Page | 53
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Table 6 summarises the Centrally Dispatched Net Generation Capacity available over the period 2016–
2021, with the new generation at Salalah-2 IPP, Ibri IPP, Sohar III and Misfah IPP plant in service with the
planned retirement of generating units at Ghubrah and Wadi Al-Jizzi Power Plants.
Page | 54
Five-Year Annual Transmission Capability Statement (2017 - 2021)
6.5 Interconnections
6.5.1 Interconnection with the GCCIA Grid through UAE (Transco Abu Dhabi)
The 220kV transmission interconnection with the United Arab Emirates (Transco Abu Dhabi) was
completed in the first quarter of 2007. The interconnection connects Mahadha grid station in Oman
(Al Wasit) to Auha grid station in Al Ain in the UAE. In the longer term, the principal technical benefit to
be obtained from connecting Oman to the GCCIA Grid is in a reduced spinning reserve requirement, which
will be shared between the members of the GCCIA Grid. However, operation of the interconnection will
allow Oman to import/export power from the GCCIA Grid to meet any potential generation shortfall. Oman
has singed officially the agreement with the GCCIA in November 2014 and become a part of state members.
OETC transmission system is interconnected with the transmission system of the Petroleum Development
Oman (PDO) which provides electricity to its sites across the central region of Oman for the purpose of oil
exploration and development. The interconnection is made at 132kV between Nizwa grid station on the
OETC system and Nahda 132kV station on PDO 132kV network by a 67 km overhead line. The overhead
line is owned by PDO. Under normal conditions the power transfer between the two networks is allowed
to float around zero MW, with power transfers balanced out over a period.
In addition, Dhofar transmission system is interconnected with the transmission system of the Petroleum
Development Oman (PDO). The interconnection is made at 132kV between Thumrait grid station on the
Dhofar system and Harweel 132kV station on PDO 132kV network by 84.5 km overhead line. The
interconnection essentially allows OETC and PDO to supply limited power to each other in emergency
conditions on either system.
Page | 55
Five-Year Annual Transmission Capability Statement (2017 - 2021)
6000
5000
Load (MW)
4000
3000
2000
1000
Time (hrs)
Page | 56
Five-Year Annual Transmission Capability Statement (2017 - 2021)
500
400
Load (MW)
300
200
100
Time (hrs)
Table 7: Historic Growth in Peak Demand and Transmission Losses (2003 – 2016)
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016
MIS System
System Max
Demand
(MW) based 2232 2371 2495 2613 2773 3139 3546 3614 4000.3 4448 4634 5269 5744 6105
on gross
demand
Annual
growth rate
based on - 6.2 5.2 4.7 6.1 13 12.9 1.9* 10.7 11.2 4.18 13.7 9.015 6.28
gross
demand (%)
System Max
Demand
(MW) based 2139 2294 2395 2505 2662 3033 3342 3504 3765.1 4247.34 4327.9 4872 5472 5826
on net
demand
Transmission
System
Losses (MW) 35 38 40 37 40 61 80 60 61.9 53.8 114.6 165 93.2 94.5
at system
peak
Transmission
System 1.64 1.66 1.67 1.47 1.5 2 2 1.7 1.6 1.3 2.64 3.4 1.7 1.6
Losses (%)
*The reduction in the annual growth is due to the Phet Cyclone
Page | 57
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Table 7 (continued): Historic Growth in Peak Demand and Transmission Losses (2003 – 2016)
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016
Dhofar System
System Max
Demand
(MW) based 178.3 180.9 199.3 232.3 253 260.4 297.4 336.2 348 389.3 421.7 438.9 495 523
on gross
demand
Annual
growth rate
based on - 1.40 10.23 16.56 8.91 2.92 8.99 18.75 3.26 11.87 8.32 3.8 12.78 5.6
gross
demand (%)
System Max
Demand
(MW) based - - - - - - - - - - - 427 472.9 513.3
on net
demand
Transmission
System
Losses (MW) - - - - - - - - - - - 3.6 14.5 2
at system
peak
Transmission
System - - - - - - - - - - - 0.84 3.066 0.390
Losses (%)
Minimum demand generally occurs on the transmission system during night-time in winter month
(December/January) when electricity consumption in all major load categories is reduced. In 2016, the
MIS system minimum demand was 1917 MW and this occurred on 01/01/2016 at 07:06 AM and 2016
Dhofar system minimum demand was 181 MW and this occurred on 06/02/2016 at 07:14 AM. The 2016
system minimum demand at MIS system was about 31.40 % and at Dhofar system was about 34.60 % of
2016 system peak demand. The 24-hour profile for the day of minimum demand is shown in Figures 13 &
14.
Page | 58
Five-Year Annual Transmission Capability Statement (2017 - 2021)
1500
1000
500
Time (hrs)
250
200
Load (MW)
150
100
50
Time (hrs)
Page | 59
Five-Year Annual Transmission Capability Statement (2017 - 2021)
“The Licensee shall, when preparing the Capability Statement ….ensure that the forecasts of electricity
flows and loading on each part of the Transmission System are consistent with the prevailing electricity
demand forecasts prepared and used by the OPWP for the purposes of the Statement of future capacity
requirements required by Condition 5 of the OPWP licence”.
The OPWP demand forecast is based on data supplied to them by the four Distribution Companies (i.e.
Muscat EDC, Mazoon EC, Majan EC and Dhofar PC) which also includes demand forecasts for the major
customers that are, or will be, directly connected to OETC transmission system at either 220kV or 132kV
in their respective supply areas. In addition, Distribution Companies have provided demand forecast data
to OETC taking into account the individual load at each supply connection points. The Distribution
Companies forecast are provided in terms of:
The forecast supplied to OPWP relate to the total for each Distribution Company and do not indicate how
this load is allocated to the individual grid supply points. The forecast data provided to OPWP includes
major future connections and the cumulative increase in load over the seven-year period covered by the
OPWP Statement. OPWP has then reviewed this data and taken a view as to the probability that the
individual schemes will proceed and if so, the rate at which their load will develop. The outcome of this
review is presented as OPWP demand forecast in its Seven-Year Statement.
The OPWP demand forecast was therefore taken as the starting point for developing the demand forecast
presented in this OETC Capability Statement. The OETC forecast, however, is required to identify the
future demand at individual grid stations at the system peak for each year over the period 2017 to 2021,
since this information is required for the power flow studies.
Analysis of the demand forecast data used by OPWP in developing its Seven-Year Statement (2016-2022)
identified basic annual percentage rates of 8 % for the growth in peak demand in the Mazoon EC, Muscat
EDC and Majan EC supply areas and 9 % for the growth in peak demand in the DPC supply area. These
rates have been applied to the grid station demands in the respective supply areas as noted by the OETC
Load Dispatch Centre at the 2016 MIS system peak (i.e. 12/06/2016, 15:30 hour) and 2016 Dhofar system
peak (i.e.26/05/2016, 15:09 hour). The demand associated with major industrial and tourism projects as
assessed by OPWP (with diversity taken into account) was then superimposed on to the steady growth in
the basic demand to produce a basic forecast. Section 5 identified a number of new grid supply points that
Page | 60
Five-Year Annual Transmission Capability Statement (2017 - 2021)
are scheduled to come into service to meet the summer peak demands from 2016 onwards. These gird
stations will provide load relief to the more heavily loaded grid stations and in some cases supply new
loads.
The Distribution Companies’s plans for load transfers from existing grid stations that are heavily loaded to
new grid stations are one of the most important elements of the demand forecast. Table 8 summarises the
load transfers adopted in the studies based on consideration of what is required and what OETC has
considered viable. However, OETC acknowledges that this aspect of the forecast needs to be improved in
future and believes that it would be helpful if distribution companies were to give greater consideration to
feasible load transfers when planning their distribution networks, and to develop proposals for load transfers
in coordination with OETC. Also, the TSS requirement shall be considered at every grid supply point and
all new requirements shall be indicated clearly.
Page | 61
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Page | 62
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Table 8 (continued): Expected Load Transfers between Grid Supply Points (2017-2021)
Load Transfer (MW)
From Grid Station To Grid Station
2017 2018 2019 2020 2021
Muscat Area
A'ssalam TX-1 & TX-2 Halban TX-3 & TX-4 60
A'ssalam TX-3 & TX-4 Halban TX-1 & TX-2 20
Airport Heights TX-1 & TX-2 Ghala TX-1 & TX-2 22
Airport Heights TX-1 & TX-2 Airport Heights TX-3 & TX-4 53
Ghala TX-1 & TX-2 Ghala TX-3 & TX-4 45
Amerat TX-1 & TX-2 Amerat TX-3 & TX-4 60
Total (MW) 364.7 227.3 528.8 200.0 50.0
Mazoon Area
Barka Main TX-1 & TX-2 Madinat Barka TX-1 & TX-2 46.5
Barka Main TX-1 & TX-2 A'ssalam TX-1 & TX-2 9
Barka Main TX-1 & TX-2 Barka IPP 31
Barka Main TX-1 & TX-2 Madinat Barka TX-3 & TX-4 37
Barka Main TX-1 & TX-2 A'ssalam TX-3 & TX-4 64
Barka Main TX-3 Barka Main TX-1 & TX-2 58.9
Muladah TX-1 & TX-2 Muladah TX-3 & TX-4 54.8 15
MIS Khadhra TX-3 & TX-4 54
MIS Suwaiq 68.1
Rustaq Wadi Bani Auwf 53
Sumail 2X63MVA Sumail Industrial Area 10
Sumail 2X125MVA Sumail 2X63MVA 10
Sumail 2X125MVA Sumail Industrial Area 50
Izki 2X125MVA New Izki 14 23
Nizwa Birkat Al Mouz 62.6
Bahla Jebreen 60.4
Adam 2X40MVA Adam 2X125MVA 55.6
Mudhaibi 2X125MVA Sinaw 50
Mudhaibi 2X125MVA Samad 31.3
Mudhairib Ibra 76.6
Mudhairib Bedyah 35
JBB Ali JBB Hassan 87.6
Total (MW) 348.9 402.6 305.9 0 0
Page | 63
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Table 8 (continued): Expected Load Transfers between Grid Supply Points (2017-2021)
Load Transfer (MW)
From Grid Station To Grid Station
2017 2018 2019 2020 2021
Majan Area
Ibri 2X63MVA Dreez 23.9
Ibri 2X63MVA Ibri 2X125MVA 4 2 15.8
Ibri 2X63MVA Madinat Ibri 18.8
Ibri 2X125MVA Dreez 34.1
Ibri 2X125MVA Madinat Ibri 30
Al Hayl Dreez 16.5
Al Hayl Dank 4
Al Hayl Yanqual 32.9 4
Dreez Madinat Ibri 15.2
Mahadah Wadi Sa'a 6.8
Bureimi Buriami Industrial TX-1 & TX-2 3
Bureimi Buriami Industrial TX-3 & TX-4 38.3
Buriami Industrial TX-1 &
Buriami Industrial TX-3 & TX-4 15.4
TX-2
Shinas 2X125MVA Liwa TX-1 & TX-2 6
Shinas 2X125MVA Madinat Shinas 61.3
Liwa TX-1 & TX-2 SIP 2
Liwa TX-1 & TX-2 Liwa TX-3 & TX-4 55
Liwa TX-1 & TX-2 SoharFree Zone TX-1 & TX-2 67.9 52.2
Liwa TX-1 & TX-2 Shinas 2X125MVA 3
SIP Liwa TX-1 & TX-2 10 27.7 8
SIP Liwa TX-3 & TX-4
SIP Shinas 2X125MVA 4
SIP Falaj Al Qabail 16.5
SoharFree Zone TX-1 & TX-2 SIP 2
SoharFree Zone TX-1 & TX-2 Liwa TX-1 & TX-2 9
SoharTX-1 & TX-2 SoharTX-3 & TX-4 8
SoharTX-1 & TX-2 Saham 9
SoharTX-1 & TX-2 Uwaynat TX-1 & TX-2 37.6
SoharTX-1 & TX-2 Uwaynat TX-3 & TX-4 40.5
SoharTX-1 & TX-2 Falaj Al Qabail 24.2
SoharTX-3 & TX-4 Liwa TX-1 & TX-2 4
SoharTX-3 & TX-4 SoharTX-1 & TX-2 30
SoharTX-3 & TX-4 Uwaynat TX-3 & TX-4 13.2
SoharTX-3 & TX-4 SoharFree Zone TX-1 & TX-2 2
SoharTX-3 & TX-4 Falaj Al Qabail 24.2
Khaborah Khadhra TX-1 & TX-2 24
Khaborah Dil Abdusalam 25.7
Uwaynat TX-1 & TX-2 Uwaynat TX-3 & TX-4 2
Saham SoharTX-1 & TX-2 17.5
Saham SoharTX-3 & TX-4
Saham Uwaynat TX-1 & TX-2 16.6 13.9
Saham Uwaynat TX-3 & TX-4 16.4
Saham Dil Abdusalam 62.1
Dil Abdusalam Saham 14.1
Total (MW) 273.9 326.7 117.9 59.7 196.1
Page | 64
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Table 8 (continued): Expected Load Transfers between Grid Supply Points (2017-2021)
Load Transfer (MW)
From Grid Station To Grid Station
2017 2018 2019 2020 2021
Dhofar System
Ittin Al Qarm 3
Page | 65
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Page | 66
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Page | 67
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Page | 68
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Page | 69
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Page | 70
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Table 10 compares the total demand forecast with the available generating capacity from Table 6 including
planned retirements.
Table 10: Comparison of Demand Forecast with Available Generating Capacity including Planned
Retirements
Page | 71
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Table 11 compares the total demand forecast with the available generating capacity from Table 6.
Table 11: Comparison of Demand Forecast with Available Generating Capacity and Non-Contracted
Generation in service
Power Station 2016 2017 2018 2019 2020 2021
MIS System
Al-Ghubrah Power & Desalination 377 377 341 0 0 0
Rusail 689 689 689 689 689 689
Wadi Al-Jizzi 326 326 326 0 0 0
Manah 264 264 264 264 264 264
Al Kamil 280 280 280 280 280 280
Barka I Power & Desalination 410 410 410 388 388 388
Sohar I Power & Desalination 566 566 566 566 566 566
Barka II Power & Desalination 663 663 663 663 663 663
Barka III Power & Desalination 754 754 754 754 754 754
Sohar II Power & Desalination 754 754 754 754 754 754
Sur IPP 1988 1988 1985 1983 1982 1982
Ibri IPP 0 0 940 1508 1508 1508
Sohar III IPP 0 0 0 1708 1708 1708
Misfah IPP 0 0 0 0 0 1000
Total Generating Capacity (MW) 7072 7072 7974 9559 9557 10557
Demand Forecast (MW) 5826 6311 6923 7421 7732 8057
Calculated Losses (MW) 94.5 106 101 106 113 115
Surplus/Deficit Capacity (MW)
1151 655 949 2032 1712 2385
(Generation-Demand-Losses)
Non-Contracted Generating Capacity (MW) 575 575 575 575 575 575
Surplus/Deficit Capacity (MW)
1726 1230 1524 2607 2287 2960
Including Non-Contracted Generation
Retirements 0 0 36 667 0 0
Dhofar System
NPS 273 273 273 273 273 273
Salalah IPP 429 429 429 429 429 429
Salalah 2 IPP 0 0 438 438 438 438
Total Generating Capacity (MW) 702 702 1140 1140 1140 1140
Demand Forecast (MW) 513 552 590 702 745 790
Calculated Losses (MW) 2 3 2 2 2 3
Surplus/Deficit Capacity (MW)
187 148 548 436 393 347
(Generation-Demand-Losses)
Non-Contracted Generating Capacity (MW) 0 0 0 0 0 0
Surplus/Deficit Capacity (MW)
187 148 548 436 393 347
Including Non-Contracted Generation
Retirements 0 0 0 0 0 0
Page | 72
Five-Year Annual Transmission Capability Statement (2017 - 2021)
The transmission system data used in the power system studies to determine the system performance over
the period from 2017 to 2021 is presented in Appendix B of this document.
The extreme cases of maximum (summer) and minimum (winter) system demand are used to define the
performance of OETC transmission system when it is most heavily stressed. From the studies of these
extreme conditions it is possible to identify where the system is strong and has capacity to spare and,
conversely, where it is weak and will need strengthening before new connections could be considered. The
peak demand case identifies where there is a risk of overloading, of operation above firm capacity, or of
system voltages falling below the voltage limits as defined in the Grid Code.
The system data described and presented in Appendix B has been used in a series of load flow studies to
establish the performance of OETC transmission system at peak demand in each year from 2017 to 2021
inclusive. The studies were undertaken on the basis that all circuits and plant will be available at system
peak in each of the five years and that the system will be developed in accordance with the plans described
in Section 5 of the Statement. The studies also assume that the demand will grow in accordance with the
demand forecast and that sufficient generation will be available from both Contracted and Non-Contracted
power producers to meet each annual system peak as indicated in OPWP 7 Year Statement.
Table 12 shows a summary of the power plants forecasted to be in service at peak load in each year of the
study from 2017 to 2021. Under peak load condition it is assumed that reactive power support will be
switched on, i.e. capacitor banks at 33kV grid stations are properly adjusted to provide required reactive
power and voltage support. In the studies, generator terminal voltage and generator-transformer taps are
normally set at their corresponding nominal values, however, when necessary the settings are adjusted to
control the voltage on the transmission system to be within the allowable limits.
A second series of load flow studies were undertaken with the transmission system supplying minimum
demand. The minimum demand case identifies where there is a risk of the busbar voltages rising above the
voltage limits defined in the Grid Code and where additional generation has to be operated to absorb excess
reactive power, where there are no shunt reactors connected to the system in peak 2017. However, in 2018
and 2019 several shunt reactors will be installed to absorb excessive amount of reactive power that been
generated by the lightly loaded 400kV lines. At the system minimum demand, the generation is reduced to
a level that provides the necessary margin of reserve capacity that is consistent with the operational practices
adopted by OETC to handle minimum load condition. Table 13 shows the power plants forecasted to be in
service at minimum load in each year of the study. Under minimum load condition, it is assumed that all
capacitor banks are switched out to avoid overvoltage due to excessive reactive power.
Page | 73
Five-Year Annual Transmission Capability Statement (2017 - 2021)
The extreme cases of maximum and minimum system demand are used to define the performance of OETC
transmission system when it is most heavily stressed. From the studies of these extreme conditions it is
possible to identify where the system is strong and has capacity to spare and, conversely, where it is weak
and will need strengthening before new connections could be considered. The peak demand case identifies
where there is a risk of overloading, of operation above firm capacity, or of system voltages falling below
the voltage limits as defined in the Grid Code.
The system data described and presented in Appendix B has been used in a series of load flow studies to
establish the performance of OETC transmission system at peak demand in each year from 2017 to 2021
inclusive. The studies were undertaken on the basis that all circuits and plant will be available at system
peak in each of the five years and that the system will be developed in accordance with the plans described
in Section 5 of the Statement. The studies also assume that the demand will grow in accordance with the
demand forecast and that sufficient generation will be available from contracted power plants to meet each
annual system peak as indicated in OPWP 7 Year Statement.
Table 12 shows a summary of the power plants forecasted to be in service at peak load in each year of the
study from 2017 to 2021. Under peak load condition it is assumed that capacitive support will be switched
on, i.e. capacitor banks at 33kV grid stations are properly adjusted to provide required reactive power and
voltage support. In the studies, generator terminal voltage and generator-transformer taps are normally set
at their corresponding nominal values, however, when necessary the settings are adjusted to control the
voltage on the transmission system to be within the allowable limits.
A second series of load flow studies were undertaken with the transmission system supplying minimum
demand. At the system minimum demand, the generation is reduced to a level that provides the necessary
margin of reserve capacity that is consistent with the operational practices adopted by OETC to handle
minimum load condition. Table 12 shows the power plants forecasted to be in service at maximum load in
each year of the study. Under minimum load condition, it is assumed that all capacitor banks are switched
out to avoid overvoltage due to excessive reactive power. Table 13 shows the power plants forecasted to be
in service at minimum load in each year of the study
Page | 74
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Table 12: Summary of Connected Generation Used in Load Flow Studies of Maximum Demand
2017 2018 2019 2020 2021
Power Stations
Total Spare Gen Total Spare Gen Total Spare Gen Total Spare Gen Total Spare Gen
MIS
Ghubrah 405 17 388 341 37 304 - - - - - - - - -
Rusail 689 13 676 689 76 613 689 142 547 689 119 570 689 610 79
Wadi Al-Jizzi 326 27 299 326 34 292 - - - - - - - - -
Manah 264 38 226 264 29 235 264 54 210 264 45 219 264 46 218
Al Kamil 280 49 231 280 30 250 280 57 223 280 48 232 280 48 232
Barka I 435 100 335 435 47 388 388 80 308 388 66 322 388 67 321
Sohar I 597 12 585 597 64 533 597 123 474 597 102 495 597 103 494
Barka II 688 168 520 688 73 615 688 141 547 688 118 570 688 118 570
Barka III 754 109 645 754 81 673 754 167 587 754 129 625 754 130 624
Sohar II 754 30 724 754 71 683 754 155 599 754 129 625 754 130 624
Sur IPP 1988 220 1768 1985 271 1714 1983 396 1587 1982 340 1642 1982 344 1638
Ibri IPP - - - 940 - 860 1508 310 1198 1508 259 1249 1508 261 1247
Sohar III IPP - - - - - - 1708 350 1358 1708 293 1415 1708 296 1412
Misfah IPP - - - - - - - - - - - - 1000 174 826
External Sources 180 0 180 0 0 0 0 0 0 0 0 0 0 0 0
Total Gen (MW) 7360 783 6577 8053 893 7160 9614 1976 7638 9613 1649 7964 10613 2328 8285
Grid Load (MW) 6473 7067 7538 7848 8183
Dhofar
NPS 273 52 221 273 125 148 273 99 174 273 89 184 273 78 195
Salalah IWP 444 84 360 444 204 240 444 161 283 444 144 300 444 127 317
Salalah-2 IPP − − - 437.8 201 237 437.8 158.8 279 438 143 295 438 125 313
External Sources 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Total Gen (MW) 717 136 581 1155 530 625 1155 419 736 1155 376 779 1155 330 825
Grid Load (MW) 579 623 735 778 823
Page | 75
Five-Year Annual Transmission Capability Statement (2017 - 2021)
Table 13: Summary of Connected Generation Used in Load Flow Studies of Minimum Demand
2017 2018 2019 2020 2021
Power Stations
Total Spare Gen Total Spare Gen Total Spare Gen Total Spare Gen Total Spare Gen
MIS
Ghubrah 405 185 220 405 242 163 - - - - - - - - -
Rusail 689 689 0 689 689 0 689 689 0 689 689 0 689 689 0
Wadi Al-Jizzi 326 326 0 326 326 0 - - - - - - - - -
Manah 264 108 156 264 110 154 264 107 157 264 264 0 264 264 0
Al Kamil 280 280 0 280 280 0 280 280 0 280 280 0 280 280 0
Barka I 435 153 282 435 158 277 388 51 337 388 132 256 388 129 259
Sohar I 597 192 405 597 198 399 597 188 409 597 184 413 597 179 418
Barka II 688 339 349 688 344 344 688 336 352 688 333 355 688 329 359
Barka III 754 536 218 754 539 215 754 534 220 754 532 222 754 529 225
Sohar II 754 536 218 754 539 215 754 534 220 754 532 222 754 529 225
Sur IPP 1988 1304 684 1985 1106 879 1983 1084 899 1982 1076 906 1982 1280 702
Ibri IPP - - - - - - 940 532 408 1508 1097 411 1508 1092 416
Sohar III IPP - - - - - - - - - 1708 1246 462 1708 951 757
Misfah IPP - - - - - - - - - - - - - - -
External Sources 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Total Gen (MW) 7180 4648 2532 7177 4531 2646 7338 4336 3002 9613 6366 3247 9613 6252 3361
Grid Load (MW) 2498 2615 2945 3213 3326
Dhofar
NPS 273 228 45 273 216 57 273 238 35 273 248 25 273 234 39
Salalah IWP 444 327 117 444 327 118 444 376 68 444 368 77 444 367 77
Salalah-2 IPP − − - − − - 438 348 90 438 286 152 438 290 148
External Sources 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Total Gen (MW) 717 555 162 717 543 174 1155 962 193 1155 901 254 1155 890 265
Grid Load (MW) 162 174 193 254 264
Page | 76
Five-Year Annual Transmission Capability Statement (2017-2021)
The key results of the load flow and fault level studies on OETC transmission system are presented in detail
in Appendix C for each year over the period 2017 to 2021. System diagrams from C.1 to C.10 are showing
the results of the peak demand for MIS and Dhofar. Load flows have also been produced and are available
for both MIS and Dhofar in Appendix C.
Table C.1 shows the transformer percentage loading of all grid stations at system peak demand.
Table C.2 shows the available spare capacity at each grid station in relation to firm capacity at system
peak demand. It should be noted that although spare MVA capacities are available at some individual
grid stations, there is no guarantee that all can be exploited simultaneously. Lack of available
generation and/or voltage level limits may restrict simultaneous utilization of all spare MVA capacities.
Table C.3 shows the percentage loading of each overhead line and underground cable in the
transmission system at system peak demand.
Tables C.4 (a) and C.4 (b) show the voltage profile at each 400kV, 220kV, and 132kV and 33kV bus-
bar at maximum and minimum load respectively.
Table C.5 shows the calculated transmission losses and generation margin at peak demand.
Tables C.6 and C.7 show the maximum three-phase and single-phase to earth short-circuit currents
respectively.
Page | 77
Five-Year Annual Transmission Capability Statement (2017-2021)
d) The number of out-of-firm grid stations during the period 2017 to 2021 are (this is shown graphically
in Figure 15):
2017 – 13
2018 – 8
2019 – 2
2020 – 0
2021 – 0
e) In summer peak of 2017, there are three transformers temporally supplying their individual loads in
order to mitigate over firm issues and provide additional capacity at some 132/33kV grid stations. From
2018, there will be no transformer operating individually.
f) The number of 132kV overhead lines operating above firm capacity over the summer peak period 2017-
2021 will be as follows:
2017 – 1
2018 – 2
2019 – 0
2020 – 1
2021 – 0
g) All 220kV overhead transmission lines are within their corresponding firm capacity over the years 2017
to 2021.
h) All 400kV overhead transmission lines are well within their corresponding firm capacity over the years
2017 to 2021.
i) Implementation of the development projects described in Section 5 and the updated load transfer
programme of Table 8 will restore the full system to be in compliance with Transmission Security
Standard requirements.
Grid Stations Firm Capacities of Dhofar
a) Awqad 132/33kV grid station shows lack of capacity in 2017. During 2018 and 2019, all
132/33kV grid stations will be within the firm capacity. In 2020, Thumrait grid station will
operate above it firm capacity. In 2021, all 132/33kV grid stations will be operating within their
firm capacity.
b) The number of out-of-firm grid stations during the period 2017 to 2021 are (this is shown
graphically in Figure 16):
2017 – 1
2018 – 0
2019 – 0
2020 – 1
2021 – 0
Page | 78
Five-Year Annual Transmission Capability Statement (2017-2021)
c) All 132kV overhead lines and underground cables are within their corresponding firm capacity
over the period 2017-2021.
d) Implementation of the development projects described in Section 5 and the updated load transfer
programme of Table 8 will restore the full system to be in compliance with Transmission System
Security Standard requirements.
12
10
0
2017 2018 2019 2020 2021
Page | 79
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 80
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 81
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 82
Five-Year Annual Transmission Capability Statement (2017-2021)
220kV Busbar
132kV Busbar
33kV Busbar
Page | 83
Five-Year Annual Transmission Capability Statement (2017-2021)
33kV Busbar
Figure 20: Voltage profile (p.u.) at Salalah Free Zone Grid Station
Page | 84
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 85
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 86
Five-Year Annual Transmission Capability Statement (2017-2021)
Figure 23: Transmission power losses at peak demand of the years 2017-2021 of MIS
Figure 24: Transmission power losses at peak demand of the years 2017-2021 of Dhofar
Page | 87
Five-Year Annual Transmission Capability Statement (2017-2021)
Figure 25: Peak load growth over the period 2017-2021 of MIS
Page | 88
Five-Year Annual Transmission Capability Statement (2017-2021)
Figure 26: Peak load growth over the period 2017-2021 of Dhofar
The load flow studies show that the planned 400kV, 220kV and 132kV transmission developments will add
substantial new capacity to the transmission system that will enable the transmission system as a whole to
cope with new demand in compliance with the Transmission Security Standard. Consequently opportunities
for the connection of new load should be available where spare capacity exists.
All of the 400kV busbars have fault levels well within the corresponding switchgear ratings.
All of the 220kV busbars have fault levels within the corresponding switchgear ratings.
All the 132kV buses have fault levels within the corresponding switchgear ratings.
The 3-phase short-circuit level at all 33kV busbars does not exceed the switchgear rating.
Page | 89
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 90
Five-Year Annual Transmission Capability Statement (2017-2021)
9. Development Opportunities
From the results of the load flow and fault level studies, and from analysis of the magnitude and location
of generation and demand on the transmission system it is possible to give some indications as to where
future generation and demand can be connected to the transmission system without causing any critical
technical issues.
Figure 27 shows the connectivity of the OETC transmission system at MIS area in 2021 as it extends over
the northern regions of Oman, a distance of around 550 km from Madinat Shinas in the North West to JBB
Ali in the southeast. Figure 28 shows the connectivity of the OETC transmission system at Dhofar area in
2021 as it extends over the northern regions of Dhofar, a distance of around 67 km from NPS grid station
in the North West to Ashoor grid station in the south-west. To assess how generation and load is distributed
over the transmission system the whole supply area has been split into eight geographic areas:
a) Muscat
b) Al Batinah South
c) Al Batinah North
d) Al Bureimi
e) Al Dhahirah
f) Al Dakhiliah
g) Al Sharqiyah
h) Dhofar
Page | 91
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 92
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 93
Five-Year Annual Transmission Capability Statement (2017-2021)
Table 14 compares the generation capacity installed in each of the eight areas with the forecast demand at
the grid stations at the annual system peak over the period 2017 to 2021.
Table 14: Estimated Power Surplus and Power Deficit on an Area Basis (2017-2021)
Grid Station loads at System Peak
Area Grid & Power Stations Demand
2017 2018 2019 2021 2021
Al-Ghubrah Power & Desalination 377 341 0 0 0
Rusail IPP 689 689 689 689 689
Misfah IPP 0 0 0 0 1000
Total Generation (MW) 1066 1030 689 689 1689
TX-1 & TX-2 92.5 98.0 103.9 80.1 84.9
Rusail Industrial
TX-3 & TX-4 72.0 76.3 80.9 65.8 69.7
2X42MVA 7.0 7.0 0.0 0.0 0.0
Ghubrah TX-1 & TX-2 114.2 128.8 141.0 86.6 90.1
TX-3 & TX-4 0.0 0.0 0.0 60.0 62.4
Wadi Adai 98.1 86.0 88.6 91.2 94.0
TX-1 & TX-2 62.8 65.3 67.9 70.6 73.4
Wadi Kabir Tx-3 0.0 0.0 0.0 0.0 0.0
TX-3 & TX-4 79.6 82.8 86.1 89.5 93.1
Al Falaj 96.5 99.3 102.3 105.4 108.6
TX-1 & TX-2 107.3 75.6 78.6 81.8 85.0
MSQ Tx-3 34.0 0.0 0.0 0.0 0.0
TX-3 & TX-4 0.0 74.4 77.4 80.5 83.7
Muscat Khuwair 0.0 0.0 0.0 0.0 50.0
Jahloot 40.6 42.2 43.9 45.2 46.5
TX-1 & TX-2 157.3 107.2 111.5 93.9 97.7
Mawalleh South
TX-3 & TX-4 102.3 114.4 113.0 89.5 93.1
TX-1 & TX-2 0.0 0.0 0.0 70.0 72.8
Khoud
TX-3 & TX-4 0.0 0.0 0.0 70.0 72.8
2X63MVA 83.0 68.1 0.0 0.0 0.0
Seeb Main TX-1 & TX-2 119.2 124.0 101.0 90.0 93.6
TX-3 & TX-4 0.0 0.0 102.1 81.2 84.4
1X50 MVA 21.1 0.0 0.0 0.0 0.0
Mawalleh North
2X125 MVA 0.0 89.9 93.5 97.2 101.1
TX-1 & TX-2 110.6 123.1 79.2 83.2 62.4
Bousher
TX-3 & TX-4 140.5 127.6 81.9 86.0 65.3
TX-1 & TX-2 0.0 0.0 50.0 52.5 55.1
Ghala Heights
TX-3 & TX-4 0.0 0.0 52.0 54.6 57.3
Mobella 109.6 114.0 55.6 57.8 60.1
TX-1 & TX-2 104.5 110.8 66.4 70.4 74.6
A'salam
TX-3 & TX-4 0.0 0.0 59.0 62.5 66.3
Page | 94
Five-Year Annual Transmission Capability Statement (2017-2021)
Table 14 (continued): Estimated Power Surplus and Power Deficit on an Area Basis (2017-2021)
Grid Station loads at System Peak Demand
Area Grid & Power Stations
2017 2018 2019 2021 2021
TX-1 & TX-2 0.0 0.0 59.0 62.5 66.3
Halban
TX-3 & TX-4 0.0 0.0 60.0 63.6 67.4
Muttrah 79.1 81.5 83.9 85.6 87.3
TX-1 & TX-2 97.0 101.8 53.9 56.6 58.9
Airport Heights
TX-3 & TX-4 0.0 0.0 53.0 55.7 57.9
Qurum 100.8 103.8 106.9 109.1 111.2
Yitti 10.9 12.0 13.2 14.5 15.9
Quryiat 50.3 52.3 54.4 56.6 58.9
Daghmar 52.0 52.0 52.0 52.0 52.0
Misfah 32.1 33.4 34.8 36.1 37.6
Muscat
TX-1 & TX-2 80.0 84.8 44.9 47.6 50.0
Ghala
TX-3 & TX-4 0.0 0.0 45.0 47.7 50.1
TX-1 & TX-2 93.5 113.1 58.8 61.7 64.8
Amerat
TX-3 & TX-4 0.0 0.0 60.0 63.0 66.2
Muscat Airport 25.0 25.0 25.0 25.0 25.0
Muscat Steel 20.0 20.0 20.0 20.0 20.0
Modren Steel 20.0 20.0 20.0 20.0 20.0
R.O Ghubrah 40.0 40.0 40.0 40.0 40.0
Total Load (MW) 2453.2 2554.5 2720.4 2832.8 2947.5
Power Surplus/Deficit (MW) -1387 -1524 -2031 -2144 -1258
Barka I Power & Desalination 410 410 388 388 388
Barka II Power & Desalination 663 663 663 663 663
Barka III Power & Desalination 754 754 754 754 754
Total Generation (MW) 1828 1828 1806 1806 1806
TX-1 & TX-2 118.9 116.9 59.9 63.5 67.3
Barka Main
TX-3 58.3 0.0 0.0 0.0 0.0
TX-1 & TX-2 46.5 49.3 52.2 55.4 58.7
Al Batinah South Madinat Barka
TX-3 & TX-4 0.0 37.0 39.2 41.6 44.1
Barka IPP 0.0 91.0 93.7 96.5 99.4
TX-1 & TX-2 85.0 74.3 78.0 81.1 84.3
Muladah
TX-3 & TX-4 54.8 72.5 76.2 79.2 82.4
MIS 172.6 59.2 62.1 64.6 67.2
Blue City 92.7 97.4 102.2 106.3 110.6
Rustaq 3X125MVA 143.1 148.8 101.8 105.9 110.1
Page | 95
Five-Year Annual Transmission Capability Statement (2017-2021)
Table 14 (continued): Estimated Power Surplus and Power Deficit on an Area Basis (2017-2021)
Grid Station loads at System Peak Demand
Area Grid & Power Stations
2017 2018 2019 2021 2021
Wadi Bani Auwf 0.0 0.0 53.0 55.1 57.3
Nakhal 70.3 73.1 76.0 78.3 80.7
TX-1 & TX-2 66.0 69.3 72.8 75.7 78.7
Khadhra
Al Batinah South TX-3 & TX-4 0.0 54.0 56.7 59.0 61.3
Suwaiq 0.0 68.1 71.5 74.4 77.3
Total Load (MW) 908.2 1010.8 995.3 1036.5 1079.4
Power Surplus/Deficit (MW) 920 817 810 769 726
Sohar I Power & Desalination 566 566 566 566 566
Sohar II Power & Desalination 754 754 754 754 754
Sohar III IPP 0 0 1708 1708 1708
Total Generation (MW) 1320 1320 3028 3028 3028
Shinas 112.4 51.8 58.9 65.4 69.4
Madinat Shinas 0.0 61.3 65.0 68.9 73.0
TX-1 & TX-2 61.8 99.8 52.6 70.3 75.2
Liwa
TX-3 & TX-4 55.0 58.9 63.0 67.4 72.1
Sohar Industrial Area (SIA) 71.4 72.7 81.8 79.5 68.6
Sohar Free Zone TX-1 & TX-2 67.9 72.7 80.0 79.0 86.9
(SFZ) TX-3 & TX-4 0.0 0.0 54.2 59.6 65.6
TX-1 & TX-2 114.3 74.3 79.5 85.0 66.8
Sohar
TX-3 & TX-4 109.3 73.7 76.9 82.3 63.8
Falaj Al Qabail 0.0 0.0 0.0 0.0 64.9
Khaborah 109.7 90.5 96.0 101.7 107.8
Al Batinah North TX-1 & TX-2 0.0 54.2 55.5 58.8 76.2
Uwaynat
TX-3 & TX-4 0.0 53.7 58.9 62.5 82.6
Saham 163.9 95.0 100.7 106.7 96.9
Dil Abdusalam 0.0 87.8 93.1 98.7 90.5
Aromatics connected to 132kV (SIP-A) 22.0 22.0 22.0 22.0 22.0
Sohar Steel connected to 132kV(SIP-A) 90.0 96.0 96.0 96.0 96.0
Jindal Shadeed connected to 220 (SIP-A) 260.0 270.0 275.0 275.0 275.0
VALE connected to 132kV (SIP-A) 85.0 85.0 85.0 85.0 85.0
Oman Alum (ARMS) connected to Liwa
8.6 8.6 8.6 8.6 8.6
132kV
OMPET Connected ti SIP 132kV 0.0 27.0 27.0 27.0 27.0
Orpic (Liwa Plastic) 220kV SPS-2 0.0 200.0 200.0 200.0 200.0
Moon Iron & Steel Co connected to
0.0 0.0 185.0 185.0 185.0
220KV SFZ
Total Load (MW) 1331.2 1655.0 1914.4 1984.3 2058.8
Power Surplus/Deficit (MW) -11.2 -335.0 1113.6 1043.7 969.2
Page | 96
Five-Year Annual Transmission Capability Statement (2017-2021)
Table 14 (continued): Estimated Power Surplus and Power Deficit on an Area Basis (2017-2021)
Grid Station loads at System Peak Demand
Area Grid & Power Stations
2017 2018 2019 2021 2021
Wadi Al-Jizzi Power Plant 326 326 0 0 0
Total Generation (MW) 326 326 0 0 0
Mahadha 26.4 27.5 28.3 22.3 23.0
Wadi Sa'a 10.3 10.8 11.3 18.7 19.6
Al Buraimi Bureimi 84.4 90.3 58.4 62.4 63.8
TX-1 & TX-2 50.7 54.3 42.7 45.7 51.8
Bureimi Industrial
TX-3 & TX-4 0.0 0.0 53.7 57.5 61.5
Total Load (MW) 171.8 182.9 194.4 206.6 219.8
Power Surplus/Deficit (MW) 153.9 142.9 -194.4 -206.6 -219.8
Ibri IPP 0 940 1508 1508 1508
Total Generation (MW) 0 940 1508 1508 1508
2X63MVA 31.4 32.7 32.0 33.3 0.0
Ibri
2X125MVA 63.6 68.1 74.9 80.1 71.5
Madinat Ibri 0.0 0.0 0.0 0.0 64.0
Al Dhahirah Dank 28.2 33.1 34.1 35.1 36.1
Al Hayl 48.7 47.1 49.5 19.1 16.0
Yanqual 0.0 0.0 0.0 32.9 38.5
Dreez 74.5 78.2 82.1 86.2 75.4
Total Load (MW) 246.5 259.2 272.5 286.7 301.6
Power Surplus/Deficit (MW) -246.5 680.8 1235.5 1221.3 1206.4
Manah IPP 264 264 264 264 264
Total Generation (MW) 264 264 264 264 264
2X63MVA 35.7 47.5 39.4 41.0 42.6
Sumail
2X125MVA 105.9 101.2 55.3 57.5 59.8
Sumail Industrial Area 0.0 0.0 60.0 66.0 72.6
Izki 74.3 54.3 56.4 58.1 59.9
New Izki 14.0 37.7 39.6 41.6 43.6
Nizwa 110.7 117.3 61.7 64.8 68.1
Al Dakhiliah
Madinat Nizwa 53.4 55.5 57.7 59.4 61.2
Birkat Al Mouz 0.0 0.0 62.6 65.7 69.0
Bahla 50.6 53.1 55.8 58.6 61.5
Jebreen 60.4 63.4 66.6 69.9 73.4
2X40MVA 52.0 0.0 0.0 0.0 0.0
Adam
2X125MVA 0.0 55.6 58.9 61.9 65.0
Total Load (MW) 556.9 585.7 614.1 644.6 676.7
Power Surplus/Deficit (MW) -292.7 -321.4 -349.9 -380.3 -412.5
Page | 97
Five-Year Annual Transmission Capability Statement (2017-2021)
Table 14 (continued): Estimated Power Surplus and Power Deficit on an Area Basis (2017-2021)
Grid Station loads at System Peak
Area Grid & Power Stations Demand
2017 2018 2019 2021 2021
Al Kamil IPP 280 280 280 280 280
Sur IPP 1988 1985 1983 1982 1982
Total Generation (MW) 2268 2265 2264 2262 2262
Mudhaibi 130.1 87.9 61.8 64.9 68.2
Mudhairib 101.1 106.1 76.4 80.2 84.3
Bidayah 0.0 0.0 35.0 36.4 37.9
Sinaw 0.0 50.0 53.0 55.7 58.4
Al Sharqiyah Samad 0.0 0.0 31.3 32.2 33.2
Ibra 76.6 81.2 86.1 90.4 94.9
JBB Ali 92.8 97.4 102.3 106.4 110.6
JBB Hasan 87.6 92.0 96.6 100.4 104.5
Sur 88.7 92.3 96.0 99.8 103.8
Ayjah 66.0 68.7 71.4 74.3 77.3
Total Load (MW) 642.9 675.5 709.9 740.7 773.0
Power Surplus/Deficit (MW) 1625 1590 1554 1521 1489
NPS Power Plant 273 273 273 273 273
Salalah IPP 429 429 429 429 429
Salalah 2 IPP 0 438 438 438 438
Total Generation (MW) 702 1140 1140 1140 1140
NPS 2x63MVA 45.9 40.7 42.2 44.3 45.1
TX-1 & TX-2 94.6 97.1 93.4 85.1 87.9
Salalah Free Zone
TX-3 & TX-4 7.4 23.0 55.8 76.1 89.2
Awaqad 2X125MVA 110.4 95.2 87.0 86.9 90.7
Ittin 2X125MVA 99.4 108.3 94.4 107.5 99.2
Dhofar TX-1 & TX-2 32.0 63.9 80.9 86.6 92.6
S’aadah
TX-3 & TX-4 51.8 55.4 65.8 70.4 90.1
Al Qarm 2x63MVA 30.2 19.0 16.6 15.6 16.5
Ashoor 2X125MVA 46.2 49.5 75.4 80.0 84.8
2X30MVA 23.0 24.4 25.8 27.4 0.0
Thumrait
2X125MVA 0.0 0.0 0.0 0.0 29.0
Salalah Airport 11.0 13.5 14.9 15.0 15.0
Salalah Methanol Company 0.0 0.0 50.0 50.0 50.0
Total Load (MW) 551.9 590.1 702.4 744.8 790.2
Power Surplus/Deficit (MW) 151 550 438 395 350
Page | 98
Five-Year Annual Transmission Capability Statement (2017-2021)
Figures 29 to 36 show graphically the generation and load in each of the eight areas. The significant
differences in generation and load imbalance in areas such as Muscat, Al Batinah North, and Al Sharqiyah
necessitate high development and investment in the transmission system to facilitate power transfer among
the different areas in order to supply the growing loads.
Muscat area, although geographically the smallest area, is by far the most heavily populated, with the
highest demand (2453.2MW in 2017, rising to 2947.3MW in 2021) and with limited amount of connected
generation (1066MW in 2017, increasing to 1689MW in 2021).This will result in power deficits of
1387MW in 2017 and 1258MW in 2021. Muscat area has three power plants; Ghubrah (377MW in 2017
and will be retired by 2019), Rusail (689MW during the period 2017-2021) and new Misfah IPP (1000MW
in 2021) .The reduction in the generation of Muscat area from 2019 is due to planned retirement of all
generating units of Ghubrah power plant after peak of 2018. However, the new generation in Muscat area
at Misfah will compensate the reduction in generation and meet the demand growth.
Muscat Area
3500
3000
2500
Power (MW)
1000
500
0
2017 2018 2019 2020 2021
Page | 99
Five-Year Annual Transmission Capability Statement (2017-2021)
2000
1800
1600
1400
1200
Power
(MW)
3500
3000
2500
2000
Total Generation (MW)
Power
1500
(MW)
500
0
2017 2018 2019 2020 2021
Page | 100
Five-Year Annual Transmission Capability Statement (2017-2021)
The transmission system in the Al Bureimi area provides the interconnection with the GCCIA through UAE
(Abu Dhabi Transco) supplies a number of grid stations that feed Majan Distribution System. Wadi Al Jizzi
power plant is the only generation in Al Bureimi area with power capacity of 326MW (during the period
2017-2019) and planned to retire all the gerenating untis after peak of 2018. In 2017 and 2018, the
generation surplus is 153.9MW and 142.9MW respectively. In 2019, 2020 and 2021 the deficiency in
generation will be 194.4MW, 206.6MW and 219.8MW respectively.
350
300
250
Power (MW)
200
Total Generation (MW)
150 Total Load (MW)
100
50
0
2017 2018 2019 2020 2021
Page | 101
Five-Year Annual Transmission Capability Statement (2017-2021)
1600
1400
1200
Power (MW)
1000
800 Total Generation (MW)
400
200
0
2017 2018 2019 2020 2021
Al Dakhiliah area with its provincial load centres is exhibiting moderate growth up and has a local
generating power plant at Manah (264MW) connected to the 132kV transmission system. A connection
between OETC and PDO is available in the area through the 132kV Nizwa-Nahada transmission line. The
deficiency in generation rises from 292.7MW in 2017 to 412.5MW in 2021.
800
700
600
Power (MW)
500
400 Total Generation (MW)
300 Total Load (MW)
200
100
0
2017 2018 2019 2020 2021
Page | 102
Five-Year Annual Transmission Capability Statement (2017-2021)
Al Sharqiyah area has a provincial load centre that is exhibiting moderate growth up. Al Sharqiyah area has
two power plants; Al-Kamil IPP (280MW during the period 2017-2021) and Sur IPP (with total 1988MW
power in 2017 and 1982MW in 2021). The power surplus in this area will be 1625MW, 1590MW,
1554MW, 1521MW and 1489MW in 2017, 2018, 2019, 2020 and 2021 respectively. Compared to other
areas in Oman, Al Sharqiyah area with Sur power plant will have the largest surplus generating power. This
area is well connected through a 400kV system with Muscat and Al Dakhiliah areas which offered a power
transfer and supply the load there.
2500
2000
Power (MW)
1500
Total Generation (MW)
1000 Total Load (MW)
500
0
2017 2018 2019 2020 2021
The transmission system in the Dhofar area provides the interconnection with the PDO and supplies a
number of grid stations that feed DPC Distribution System to supply Salalah city, a number of towns and
villages in Dhofar area. Currently, there are two power plants in Dhofar area; NPS Power Plant (273MW)
and Salalah IPP Power Plant (429MW).
In addition, there will be a new generartion (Salalah-2 IPP) at Dhofar and it will be in the service in 2018
with power capacity of 438MW. Furthermore, there will be a Wind Farm at Dhofar area and it will be in
the service in 2019 with power capacity of 50MW. However, this Wind Farm is not centrally dispatched
generating units and will be treated as a load disturbance. As shown in Table 14, the load in Dhofar area
rises from 551.9MW in 2017 to 790.2MW in 2021. In 2017, the generation surplus is 151MW. In 2018,
Salalah-2 IPP Power Plant will be in service and the generation surplus is 550MW and will decrease to
350MW in 2021 due to the load growth.
Page | 103
Five-Year Annual Transmission Capability Statement (2017-2021)
Dhofar Area
1200
1000
800
Power (MW)
200
0
2017 2018 2019 2020 2021
Page | 104
Five-Year Annual Transmission Capability Statement (2017-2021)
Table 15: Available Grid Station Capacity of More than 10 MVA in 2021
Available
Region Grid Station Capacity Grid Station Available
(MVA) Capacity (MVA)
Rusail (TX-1 & TX-2) 35.60 Bousher (TX-3 & TX-4) 56.23
Rusail (TX-3 & TX-4) 51.63 Ghala Heights (TX-1 & TX-2) 66.97
Ghubrah (TX-1 & TX-2) 30.21 Ghala Heights (TX-3 & TX-4) 64.65
Ghubrah (TX-3 & TX-4) 59.32 Mobella 61.74
Wadi Adai 26.08 A'ssalam (TX-1 & TX-2) 46.44
Wadi Kabir(TX-1& TX-2) 47.73 A'ssalam (TX-3 & TX-4) 55.22
Wadi Kabir(TX-3& TX-4) 26.98 Halban (TX-1 & TX-2) 55.22
Al Falaj 10.73 Halban (TX-3 & TX-4) 54.04
MSQ (TX-1 & TX-2) 35.49 Muttrah 33.10
MSQ (TX-3 & TX-4) 36.91 Airport Heights (TX-1 & TX-2) 63.04
Muscat
Khuwair 72.37 Airport Heights (TX-3 & TX-4) 64.08
Jahloot 76.01 Yitti 108.22
Mawalleh South (TX-1 & TX-2) 22.19 Quryiat 63.01
Mawalleh South (TX-3 & TX-4) 27.00 Daghmar 45.26
Khoud (TX-1 & TX-2) 48.37 Misfah 85.43
Khoud (TX-3 & TX-4) 48.37 Ghala (TX-1 & TX-2) 72.41
Seeb Main (TX-1 & TX-2) 26.48 Ghala (TX-3 & TX-4) 72.28
Seeb Main (TX-3 & TX-4) 36.12 Amerat (TX-1 & TX-2) 56.79
Mawalleh North 18.55 Amerat (TX-3 & TX-4) 55.37
Bousher (TX-1 & TX-2) 59.35
Barka Main (TX-1 & TX-2) 54.13 Blue City 43.62
Madinat Barka (TX-1 & TX-2) 63.21 Rustaq 134.12
Madinat Barka (TX-3 & TX-4) 78.61 Wadi Bani Auwf 64.66
Al Batinah
Barka IPP 20.33 Nakhal 40.08
South
Muladah (TX-1 & TX-2) 36.22 Khadhra (TX-1 & TX-2) 42.16
Muladah (TX-3 & TX-4) 38.28 Khadhra (TX-3 & TX-4) 60.45
MIS 54.29 Suwaiq 43.59
Shinas (2X125MVA) 51.98 Sohar (TX-3 & TX-4) 57.80
Madinat Shinas 48.15 Falaj Al Qabail 56.68
Liwa(TX-1 & TX-2) 45.87 Khaborah 11.48
Al Batinah Liwa(TX-3 & TX-4) 49.11 Uwaynat(TX-1 & TX-2) 44.78
North Sohar Industrial Area 52.78 Uwaynat(TX-3 & TX-4) 38.05
Sohar Free Zone(TX-1 & TX-2) 33.58 Saham 22.97
Sohar Free Zone(TX-3 & TX-4) 55.97 Dil Abdusalam 29.77
Sohar(TX-1 & TX-2) 54.72
Page | 105
Five-Year Annual Transmission Capability Statement (2017-2021)
Table 15 (continued): Available Grid Station Capacity of more than 10 MVA in 2021
Available Available
Region Grid Station Name Capacity Grid Station Name Capacity
(MVA) (MVA)
Wadi Sa'a 42.32 Bureimi Industrial(TX-1&TX-2) 70.42
Al Buraimi
Bureimi 57.83 Bureimi Industrial(TX-3&TX-4) 60.28
Ibri(2X125MVA) 49.74 Al Hayl 23.13
Al Dhahirah Madinat Ibri 57.63 Yanqual 84.43
Dank 24.96 Dreez 45.68
Sumail (2X63MVA) 18.16 Madinat Nizwa 60.56
Sumail (2X125MVA) 62.05 Birkat Al Mouz 52.35
Sumail Industrial Area 48.58 Bahla 60.28
Al Dakhiliah
Izki 61.97 Jebreen 47.72
New Izki 79.06 Adam (2X125MVA) 56.60
Nizwa 53.35
Mudhaibi 53.24 Ibra 25.12
Mudhairib 36.31 JBB Hasan 15.04
Al Sharqiyah Bidayah 85.15 Sur 15.76
Sinaw 63.49 Ayjah 43.68
Samad 28.05
NPS (2X63MVA) 15.56 S’aadah (TX-1 & TX-2) 27.48
Salalah Free Zone (TX-1 & TX-2) 32.51 S’aadah (TX-3 & TX-4) 30.11
Dhofar Salalah Free Zone (TX-3 & TX-4) 31.12 Al Qarm 45.59
Awaqad(2X125MVA) 29.52 Ashoor 35.79
Ittin (2X125MVA) 20.53 Thumrait 94.47
125
100
S(MVA)
75
50
25 Available MVA
Used MVA
0
Grid Station
Figure 37: Used and available MVA in Muscat area at 2021 peak demand
Page | 106
Five-Year Annual Transmission Capability Statement (2017-2021)
125
100
75
S(MVA)
50
25 Available MVA
Used MVA
0
Grid Station
Figure 38: Used and available MVA in Muscat area at 2021 peak demand
125
100
75
S(MVA)
50
25 Available MVA
Used MVA
0
Grid Station
Figure 39: Used and available MVA in Muscat area at 2021 peak demand
Page | 107
Five-Year Annual Transmission Capability Statement (2017-2021)
250
225
200
175
150
S(MVA)
125
100
75 Available MVA
50 Used MVA
25
0
Grid Station
Figure 40: Used and available MVA in Al Batinah South area at 2021 peak demand
125
100
75
S(MVA)
50
Available MVA
25
Used MVA
Grid Station
Figure 41: Used and available MVA in Al Batinah North area at 2021 peak demand
Page | 108
Five-Year Annual Transmission Capability Statement (2017-2021)
125
100
75
S(MVA)
50
Available MVA
25 Used MVA
Grid Station
Figure 42: Used and available MVA in Al Bureimi and Al Dhahiriah area at 2021 peak demand
125
100
75
S(MVA)
50
Available MVA
25 Used MVA
Grid Station
Figure 43: Used and available MVA in Al Dakhiliah area at 2021 peak demand
Page | 109
Five-Year Annual Transmission Capability Statement (2017-2021)
125
100
S(MVA)
75
50
Available MVA
25 Used MVA
Grid Station
Figure 44: Used and available MVA in Al Sharqiyah area at 2021 peak demand
125
100
75
S(MVA)
50
Available MVA
25 Used MVA
Grid Station
Figure 45: Used and available MVA in Dhofar area at 2021 peak demand
Page | 110
Five-Year Annual Transmission Capability Statement (2017-2021)
10. Non-compliances
The load flow studies summarised in Appendix C and discussed in Sections 8 and 9 of this Statement
indicate a number of out-of firm grid stations and circuits in the early years of the Statement. In this final
section, a review of each grid station / circuit, which is currently failing to meet the Transmission Security
Standards are preseneted. In addition, a describition of the development activities that OETC is undertaking
to address this non-compliance and indicates the expected time by which, in each instance, full
Transmission Security Standards compliance should be achieved are preseneted.
It should be noted that the level of the security requirements on the transmission system would change in
future as the demand on the system increases and as the system configuration changes. It is possible that
further non-compliances might arise in the future until the overall system becomes substantially more robust
through interconnection. OETC will keep this situation under review, and the non-compliance status will
be updated in the 2018 Capability Statement.
As indicated in sections 8, 9 and summarized in Tables 16, 17 and 18, there are some grid stations and
overhead lines/cables, which do not comply with the Transmission Security Standard. Therefore, it will be
necessary for a further location and duration for specific derogations to be put in place by the authority for
each of the noted out of firm circuits in Table 16 and for each of the grid stations which do not comply with
the Transmission Security Standard at peak and maintenance time noted in Table 17 and 18 respectively.
The following points should be noted:
1- The loading results show in Tables C1 and C3 (Appendix C), are those at the peak load conditions. The
system peak lasts only for a period of less than one hour in one day during the relevant year.
2- According to the most recent OPWP data, there are two forecast cases: (i) expected case, and (ii) high
case. The difference between the high and expected case in 2017 for MIS system is 403 MW and for Dhofar
system is 24 MW at the peak. This difference increases in the subsequent years and reaches 1085 MW for
MIS system and 238 MW for Dhofar system in 2021, indicating uncertainty in the forecast over the coming
years especially with regards to new industrial loads. OETC intends to monitor closely, in coordination
with OPWP, the situation in order to assess the probability associated with the high case projection and the
effect of the approved Cost Reflected Tariff (CRT).
3- It is not prudent to invest in uncertain expansion. OETC will initiate new projects as new demand
becomes more certain. Therefore, Tables 16 and 17 shown conditions at the summer peak of 2017.
4- The modelling reflects all load transfer schemes that have been formally accepted by the relevant
Distribution Company and included in their load forecasts.
OETC has adopted a two-fold approach to addressing these out of firm situations:
1) Reinforcement plans: strategic upgrading to add new circuits and/or to increase the capacity of grid
stations within a minimum of three to five years. This will not just solve the problem but it will
also strengthen the transmission system for future development. This type of solution can only be
applied as a longer-term solution because of the time taken to implement. Reinforcement is the
most robust long-term solution for secure system development, but may not necessarily be the least
cost solution to address the immediate out of firm conditions on the network.
Page | 111
Five-Year Annual Transmission Capability Statement (2017-2021)
2) Load Transfer: through agreement with Distribution Companies, load can be transferred from
heavily loaded grid stations to more lightly loaded grid stations over the next years. This would
reduce the loading issues and balance the system during peak time. This is a mid-term solution
which could be implemented by Distribution Companies in certain cases. Given the uncertainty of
mid-term load forecasts in Oman at present, this is in some circumstances the most appropriate and
economic action to address out of firm conditions on the network.
Tables 16 and 17 indicate a number of circuits and grid stations on the system where, in 2017, the out of
firm condition is shown to exist. Table 18 shows the grid stations which are classified as group E (>115
MW) and not comply with Transmission Security Standard (Second Outage) at 2017 maintenance period.
Page | 112
Five-Year Annual Transmission Capability Statement (2017-2021)
Table 16: Expected Over headlines/ Cables Which will not omply with Transmission Security Standard (First Outage) at Peak Demand in 2017
Indicative
Date for full
Send Circuit
Conductor Circuit Loading Compliance
Receive Voltage No. of Circuit length
No Bus Rating with the Remarks
Bus (kV) Circuits Type Size/Type (%)
(km) (MVA) Transmission
Security
Standard
Page | 113
Five-Year Annual Transmission Capability Statement (2017-2021)
Table 17: Expected Grid stations 132/33kV, which will not comply with Transmission Security Standard (First Outage) at Peak Demand in 2017
Muscat
Transformer capacity has been provided in Ghala grid
1 Bousher - B 2x125 125 61 Q2 2019 station. DISCOs load transfer will solve the non-
compliance.
Mawalleh South
2 2x125 125 68 Q3 2017 Load transfer to Mawalleh North grid station.
-A
3 Seeb Main 2x125 125 52.75 Q3 2018 Upgarde the 2x63MVA to 125 MVA Transfomers
4 Seeb Main 2x63 63 73.88 Q3 2018 Upgarde the 2x63MVA to 125 MVA Transfomers
Mazoon
5 Adam 2x40 40 71.99 Q1 2018 Upgrading the tranformers from 2x40MVA to 2x125MVA
Transformer capacity has been provided in Khadhra grid
6 MIS 2x125 125 78.91 Q3 2017 station. DISCOs load transfer will solve the non-
compliance.
7 Mudhaibi 2x125 125 58.01 Q3 2017 Load transfer to Sinaw grid station.
Transformer capacity has been provided in Madinat Barka
8 Barka Main 2x125 125 52.55 Q2 2019 and A’ssalam grid stations. DISCOs load transfer will solve
the non-compliance.
Transformer capacity has been provided in Madinat Barka
Barka Main (3rd
9 1x125 125 51.34 Q1 2018 and A’ssalam grid stations. DISCOs load transfer will solve
Tx)
the non-compliance.
Majan
10 Al Hayl 2x40 40 69.65 Q2 2020 Load transfer to new Yanqual grid station
11 Saham 2x125 125 73.19 Q3 2017 Load transfer to Uwaynat and Dil Abdusalam grid stations
Page | 114
Five-Year Annual Transmission Capability Statement (2017-2021)
Table 18: Expected Grid stations 132/33kV, which will not comply with Transmission Security Standard at Maintenance Period in 2017.
Transferable
Tx Peak Demand Load in case Transmissi
Grid No Demand Transform
capacit Forecast of Second on Security
NO Station of Forecast er Loading Remarks
y During Outage Standard
Name Txs (MW) (%)
(MVA) Maintenance During Compliant
Maintenance
Muscat
Upgrading of Seeb Main grid station from 2 x
1 Seeb Main 125 2 119 52.75 79.3 60 No 63 MVA to 2 x125 MVA transformers and
installing 33kV busbars Interlinking in Q3 2018
Mazoon
Load transfer to Swaiq and Khadhra grid
2 MIS 125 2 173 78.91 115.3 40 No
stations in Q3 2017
3 Mudhaibi 125 2 130 58.01 86.6 40 No Load transfer to Sinaw grid station in Q3 2017
Barka
4 125 2 119 52.55 79.3 60 No Load transfer to Madinate Barka in Q3 2017
Main
Majan
Load transfer to Dil Abdusalam grid station in
Q3 2017
5 Saham 125 2 164 73.19 109.3 40 No
Load transfer to Uwaynat grid station in Q1
2018
Page | 115
Five-Year Annual Transmission Capability Statement (2017-2021)
There are a significant number of projects required to meet the annual peak demands over the period of this
Statement (2017-2021). These projects are considered below under the following categories:
• Projects that are at the tender evaluation stage prior to appointment of the successful EPC
Contractor.
• Projects planned for future developments that represent the least cost options to address
problems with system growth, voltage profile, and non-compliance with the Transmission Security
Standard.
The entire programme of ongoing and future projects which are planned for implementation over the period
2017 to 2021 are listed and described below. It should be noted that the project numbers referred in this
Appendix are identical to those in Table 1 of the Executive Summary, and it should also be noted that not
all of the projects described have full authorisation at this time and to be supported by pre investment
appraisals document to approve and to select the proper option for each project.
Page | 116
Five-Year Annual Transmission Capability Statement (2017-2021)
to Al Dakhaliah and Al Sharqiyah area and to comply with the Transmission Security Standard
requirements. This project has been in service since 4th July 2016.
Page | 117
Five-Year Annual Transmission Capability Statement (2017-2021)
Project #10: Adding third & fourth transformers 132/33kV at Muladah grid station
This project consists of constructing a new 132/33kV, 2x125MVA transformers with 2x132kV GIS and
4x33kV GIS interlink with the existing 132/33kV Muladah grid station. This project will ensure
Transmission Security Standard compliance and meet the demand growth at Muladah area. This project has
been in service since Mid of January 2017.
Project #11: Adding third & fourth transformers 132/33kV at Liwa grid station
Liwa area and Industrial Sohar Free Zone is experienced high load growth in addition to new heavy
industrial loads. Therefore, MJEC requested two grid stations, one is Sohar Free Zone (Ref. Project #12)
and the second is reinforcing the existing Liwa grid station by adding third and fourth 125MVA
transformers with 2x132kV GIS and 4x33kV GIS interlink to relief the load from existing Liwa grid station.
This project has been in service since Mid of February 2017.
Project #14: 33kV busbars Interlinking of Bousher & Mawalleh South grid stations
The mainly purpose of this project is to interlink the two groups of transformers (TX1 with TX3) and (TX2
with TX4) at Bousher and Mawalleh grid stations. The project will includes an installation of 4x33kV
circuit breakers to each grid station at Bousher and Mawalleh. It is expected to be in service by end of June
2017.
Page | 118
Five-Year Annual Transmission Capability Statement (2017-2021)
Project #16: Connection of Salalah-2 IPP & adding third & fourth transformers at Salalah Free
Zone
This project is implemented to support the power evacuation from Salalah-2 IPP power plant and for
maintaining the Transmission Security Standard requirements. The construction of this project consists of
16x132kV GIS at Salalah Free Zone grid station in order to connect to Salalah-2 IPP and 2x125MVA
transformers at existing Salalah Free Zone grid station. This new capacity at Salalah Free Zone grid station
will release load from the existing transformers and can be used to transfer load from NPS grid station. The
location of this grid station was selected in coordination with DPC Company. This project is expected to
be in service by end of June 2017.
Project #17: 132kV linking system between Al Falaj, Mattrah and Wadi Al Kabair grid stations
and adding fourth 125MVA transformer at Wadi Kabair grid station
The objective of this project is to construct a 132kV single circuit UGC (2500mm2) between Mattarh and
Al Falaj grid stations and also 132kV single circuit OHL and UGC between Mattarh and Wadi Kabair grid
stations. Moreover, to cope with load growth and secure the load at Wadi Kabair grid station, a fourth
125MVA transformer will be installed and will operate in parallel with existing third transformer as one
group. This linking system and installation of the fourth transformer will require an installation of new
132kV GIS at Al Falaj grid station and additional bays at Wadi Kabair grid station. The purpose of this
project is to maintain the Transmission Security Standard requirements for the three grid stations (Al Falaj,
Muttrah and Wadi Kabir). This project is expected to be in service by end of June 2017.
Page | 119
Five-Year Annual Transmission Capability Statement (2017-2021)
Project #21: Adding third and fourth transformers 132/33kV at Khadhra grid station
The third and fourth 132/33kV, 2x125MVA transformers with 4x33kV GIS interlink will be installed in
the existing Khadhra grid station. The purpose of this project is to cope with load growth at Al Khadhra
area and provide the opportunity for the load transfer from the loaded nearby grid stations. This project is
expected to be service by end of September 2017.
Project #22: Adding third and fourth transformers 132/33kV at Madinat Barka grid station
This project consists of installing a new 132/33kV, 2x125MVA transformers with 4x33kV GIS interlink,
at the Madinat Barka 132/33kV grid station. This project will ensure Transmission Security Standard
compliance and meet the increased load in Barka area. This project is expected to be in service by end of
September 2017.
Page | 120
Five-Year Annual Transmission Capability Statement (2017-2021)
Project #26: Upgrading of Mawalleh North grid station from 3x50MVA at 132/11kV to
2x125MVA transformers at 132/33kV
The main purpose of this project is to provide additional capacity in Mawalleh area to accommodate the
new developments and to address the technical issue at the existing transformers (3x50MVA) which is
related to the vector group. This project consists of installing 2x125MVA transformers at Mawalleh North.
As indicated by Muscat Electricity Distribution Company, there is new load and high load growth in
Mawalleh area and the upgrading of this grid stations is required to cater for this load. This project is
expected to be in service by end of September 2017.
Page | 121
Five-Year Annual Transmission Capability Statement (2017-2021)
Project #33: Upgrading of Adam grid station from 2x40 MVA to 2x125 MVA transformers
The existing grid station at Adam is with 2x40MVA transformers and due to high demand growth in the
area, it will be upgraded to 2x125MVA transformers to meet the Transmission Security Standard
requirements and to cater for the new demand in the area. This project is expected to be in service by end
of March 2018.
Project #35: 400kV line connection between Sohar III IPP – Sohar Free Zone
This project is implemented to support the power evacuation from Sohar-III IPP and maintaining the
Transmission Security Standard requirements. The construction of this project consists four 400kV circuits
from Sohar-II to Sohar Free Zone. These circuits are as follow, two circuits will be 4.2km 400kV UGC and
6km 400kV OHL while the other two circuits will be 10.2km 400kV UGC. This project is expected to be
in service by end of June 2018.
Page | 122
Five-Year Annual Transmission Capability Statement (2017-2021)
Project #37: 400kV line connection between Sohar Free Zone – Mahadha & Sohar Free Zone – SIS
This project is intended to support the power evacuation from Sohar-III IPP based on the Transmission
Security Standard requirements and to support 400kV backbone network development. The construction of
this project consists of 400kV OHL connected from Sohar Free Zone to SIS by around 42km, 400kV line
connected from Sohar Free Zone to Mahadha operate as 220kV (around 61km 400kV OHL and 1km 220kV
UGC) and 2x220kV GIS at Sohar Free Zone. This project is expected to be in service by end of June 2018.
Project #38: Installing 220kV GIS & adding fourth 125MVA transformer at MSQ grid station
A fourth transformer will be added within MSQ grid station as new group demand connected to the existing
third transformer. This group will be operated separately from the existing transformers (TX1&2) at 33kV
voltage level by shifting part of the existing load between two groups. The two groups will be connected at
the 132kV busbar. Also, new 220KV GIS will be installed to MSQ grid station as the existing 220/132kV
transformers are transformers feeder. The main purposes of this project are to meet load growth
requirements, to cater for the new demand in the area, to meet Transmission Security Standard and to relief
the load from the existing MSQ grid station. This project is expected to be in service by end of June 2018.
Page | 123
Five-Year Annual Transmission Capability Statement (2017-2021)
Project #41: New 132kV double circuits between Nakhal- Wadi Bani Auwf- Rustaq with a new
Wadi Bani Auwf 132/33 kV grid station
This project is including the construction of new 132kV double circuit OHL around 88 km between Nakhal
and Rustaq grid stations and new 132/33 kV grid station at Wadi Bani Auwf. This project aimes to provide
additional capacity in order to relieve Rustaq grid station since the load forecast expected by Mazoon
Electricity Company that Rustaq grid will exceed the firm capacity. Also, this project will secure Rustaq
grid station since, it is fed by redial 132kV double circuits and its load will be more than 100MW which
fall in Class E, according Transmission Security Standard. Moreover, high load growth is expected between
Rustaq and Wadi Bani Auwf, so the best location for this grid station is proposed to be close to Mazoon
primary substations. This project is expected to be completed in end of December 2018.
Project #43: Construction of a new 132kV OHL from Sohar Free Zone to Shinas
New 132kV line will be constructed between Sohar Free Zone and Shinas grid stations (Design as 400kV).
The purpose of this new line is to secure existing Shinas and new Madinat Shinas grid stations as per
Transmission Security Standard requirements during the second forced outage. This project consists of
construction of 30km of 132kV OHL(Design as 400kV) from Sohar Free Zone grid station to Shinas grid
station with associated 132kV circuit breakers at Sohar Free zone and Shinas grid stations. This project is
expected to be in service by end of March 2019.
Page | 124
Five-Year Annual Transmission Capability Statement (2017-2021)
Project #49: Adding third and fourth 132/33kV transformer at Airport Heights
Third and fourth 125 MVA transformers with 4x33kV GIS interlink will be added at Airport Heights grid
station to meet the Transmission Security Standard requirements and to cater for the high demand growth
within the area. This project is expected to be in service by end of June 2019.
Page | 125
Five-Year Annual Transmission Capability Statement (2017-2021)
Project #52: Adding third and fourth 132/33kV transformer at Sohar Free Zone
Third and fourth 125 MVA transformers 2x132kV GIS and 4x33kV GIS interlink will be added at Sohar
Free Zone grid station to meet the Transmission Security Standard requirements and to cater for the high
demand growth within the area. This project is expected to be in service by end of June 2019.
Page | 126
Five-Year Annual Transmission Capability Statement (2017-2021)
Project #58: Adding third and fourth 132/33kV transformers at Bureimi Industrial
Third and fourth 125MVA transformers with 2x132kV GIS and 4x33kV GIS interlink will be added at
Bureimi Industrial grid station to meet the Transmission Security Standard requirements and to cater for
the high demand growth within the area. This project is expected to be in service by end of June 2019.
Page | 127
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 128
Five-Year Annual Transmission Capability Statement (2017-2021)
Although the thermal rating of an overhead line is affected by climatic conditions, for the purpose of
assessing spare capacity on the transmission system the key climatic condition that limits the circuit rating
is the summer rating when the temperature is at its highest and the solar radiation is at its peak. This also
corresponds to when the electricity demand is at or near to its peak.
The circuit data presented in Table B.2 for the first year of the Statement period (2017) comprises the
voltage, resistance, reactance, susceptance and thermal rating of the line and cable circuits. It also shows
the circuit length and the type of overhead conductor or underground cable for each circuit.
Table B.3 shows the changes to the circuit data required in each of the other four years covered by the
Statement.
1
The 33kV busbars at the grid supply points and the capacitors connected to them are owned and operated by the distribution companies.
Page | 129
Five-Year Annual Transmission Capability Statement (2017-2021)
Grid Stations P P P P P
Q Load Caps Q Load Caps Q Load Caps Q Load Caps Q Load Caps
Load Load Load Load Load
(MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr)
(MW) (MW) (MW) (MW) (MW)
MIS System
2X40MVA 52.0 17.1 - - - - - - - - - - - - -
Adam
2X125MVA - - - 55.6 18.3 48 58.9 19.4 48 61.9 20.3 48 65.0 21.4 48
TX-1 & TX-2 97.0 31.9 40 101.8 33.5 40 53.9 17.7 40 56.6 18.6 40 58.9 19.3 40
Airport Heights
TX-3 & TX-4 - - - - - - 53.0 17.4 40 55.7 18.3 40 57.9 19.0 40
Al Falaj 96.5 31.7 40 99.3 32.7 40 102.3 33.6 40 105.4 34.6 40 108.6 35.7 40
Al Hayl 48.7 16.0 10 47.1 15.5 10 49.5 16.3 10 19.1 6.3 10 16.0 5.3 10
TX-1 & TX-2 93.5 30.7 40 113.1 37.2 40 58.8 19.3 40 61.7 20.3 40 64.8 21.3 40
Amerat
TX-3 & TX-4 - - - - - - 60.0 19.7 40 63.0 20.7 40 66.2 21.7 40
TX-1 & TX-2 104.5 34.3 40 110.8 36.4 40 66.4 21.8 40 70.4 23.1 40 74.6 24.5 40
A'salam
TX-3 & TX-4 - - - - - - 59.0 19.4 40 62.5 20.6 40 66.3 21.8 40
Ayjah 66.0 21.7 20 68.7 22.6 20 71.4 23.5 20 74.3 24.4 20 77.3 25.4 20
Bahla 50.6 16.6 - 53.1 17.5 - 55.8 18.3 - 58.6 19.2 - 61.5 20.2 -
Barka IPP - - - 91.0 29.9 40 93.7 30.8 40 96.5 31.7 40 99.4 32.7 40
TX-1 & TX-2 118.9 39.1 40 116.9 38.4 40 59.9 19.7 40 63.5 20.9 40 67.3 22.1 40
Barka Main
Tx-3 58.3 19.2 - - - - - - - - - - - - -
Bedyah - - - - - - 35.0 11.5 40 36.4 12.0 40 37.9 12.4 40
Birkat Al Mouz - - - - - - 62.6 20.6 40 65.7 21.6 40 69.0 22.7 40
Blue City 92.7 30.5 48 97.4 32.0 48 102.2 33.6 48 106.3 34.9 48 110.6 36.3 48
TX-1 & TX-2 110.6 36.3 40 123.1 40.5 40 79.2 26.0 40 83.2 27.3 40 62.4 20.5 40
Bousher
TX-3 & TX-4 140.5 46.2 40 127.6 41.9 40 81.9 26.9 40 86.0 28.3 40 65.3 21.5 40
Bureimi 84.4 27.7 40 90.3 29.7 40 58.4 19.2 40 62.4 20.5 40 63.8 21.0 40
TX-1 & TX-2 50.7 16.7 40 54.3 17.8 40 42.7 14.0 40 45.7 15.0 40 51.8 17.0 40
Buriami Industrial
TX-3 & TX-4 - - - - - - 53.7 17.7 40 57.5 18.9 40 61.5 20.2 40
Page | 130
Five-Year Annual Transmission Capability Statement (2017-2021)
Table B. 1 (Continued): Load and Capacitor Data for Grid Station (2017-2021)
2017 2018 2019 2020 2021
Grid Stations P P P P P
Q Load Caps Q Load Caps Q Load Caps Q Load Caps Q Load Caps
Load Load Load Load Load
(MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr)
(MW) (MW) (MW) (MW) (MW)
MIS System
Daghmar 52.0 17.1 18 52.0 17.1 18 52.0 17.1 18 52.0 17.1 18 52.0 17.1 18
Dank 28.2 9.3 20 33.1 10.9 20 34.1 11.2 20 35.1 11.5 20 36.1 11.9 20
Dil Abdusalam - - - 87.8 28.9 40 93.1 30.6 40 98.7 32.4 40 90.5 29.7 40
Dreez 74.5 24.5 40 78.2 25.7 40 82.1 27.0 40 86.2 28.3 40 75.4 24.8 40
Falaj Al Qbail - - - - - - - - - - - - 64.9 21.3 40
TX-1 & TX-2 80.0 26.3 40 84.8 27.9 40 44.9 14.8 40 47.6 15.6 40 50.0 16.4 40
Ghala
TX-3 & TX-4 - - - - - - 45.0 14.8 40 47.7 15.7 40 50.1 16.5 40
TX-1 & TX-2 - - - - - - 50.0 16.4 40 52.5 17.3 40 55.1 18.1 40
Ghala Heights
TX-3 & TX-4 - - - - - - 52.0 17.1 40 54.6 17.9 40 57.3 18.8 40
2X42MVA 7.0 2.3 - - - - - - - - - - - - -
Ghubrah TX-1 & TX-2 114.2 37.5 - 128.8 42.3 - 141.0 46.3 - 86.6 28.5 - 90.1 29.6 -
TX-3 & TX-4 - - - - - - - - - 60.0 19.7 - 62.4 20.5 -
TX-1 & TX-2 - - - - - - 59.0 19.4 40 62.5 20.6 40 66.3 21.8 40
Halban
TX-3 & TX-4 - - - - - - 60.0 19.7 40 63.6 20.9 40 67.4 22.2 40
Ibra 76.6 25.2 40 81.2 26.7 40 86.1 28.3 40 90.4 29.7 40 94.9 31.2 40
2X63MVA 31.4 10.3 - 32.7 10.7 - 32.0 10.5 - 33.3 10.9 - 0.0 0.0 -
Ibri
2X125MVA 63.6 20.9 40 68.1 22.4 40 74.9 24.6 40 80.1 26.3 40 71.5 23.5 40
2X40MVA - - - - - - - - - - - - - - -
Izki
2X125MVA 74.3 24.4 40 54.3 17.8 40 56.4 18.6 40 58.1 19.1 40 59.9 19.7 40
Jahloot 40.6 13.3 40 42.2 13.9 40 43.9 14.4 40 45.2 14.9 40 46.5 15.3 40
JBB Ali 92.8 30.5 - 97.4 32.0 - 102.3 33.6 - 106.4 35.0 - 110.6 36.4 -
JBB Hassan 87.6 28.8 40 92.0 30.2 40 96.6 31.7 40 100.4 33.0 40 104.5 34.3 40
Jebreen 60.4 19.9 40 63.4 20.8 40 66.6 21.9 40 69.9 23.0 40 73.4 24.1 40
Page | 131
Five-Year Annual Transmission Capability Statement (2017-2021)
Table B. 1 (Continued): Load and Capacitor Data for Grid Station (2017-2021)
2017 2018 2019 2020 2021
Grid Stations P P P P P
Q Load Caps Q Load Caps Q Load Caps Q Load Caps Q Load Caps
Load Load Load Load Load
(MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr)
(MW) (MW) (MW) (MW) (MW)
MIS System
Khaborah 109.7 36.0 40 90.5 29.8 40 96.0 31.5 40 101.7 33.4 40 107.8 35.4 40
TX-1 & TX-2 66.0 21.7 40 69.3 22.8 40 72.8 23.9 40 75.7 24.9 40 78.7 25.9 40
Khadhra
TX-3 & TX-4 - - - 54.0 17.7 40 56.7 18.6 40 59.0 19.4 40 61.3 20.2 40
TX-1 & TX-2 - - - - - - - - - 70.0 23.0 40 72.8 23.9 40
Khoud
TX-3 & TX-4 - - - - - - - - - 70.0 23.0 40 72.8 23.9 40
Khuwair - - - - - - - - - - - - 50.0 16.4 40
TX-1 & TX-2 61.8 20.3 40 99.8 32.8 40 52.6 17.3 40 70.3 23.1 40 75.2 24.7 40
Liwa
TX-3 & TX-4 55.0 18.1 40 58.9 19.3 40 63.0 20.7 40 67.4 22.1 40 72.1 23.7 40
TX-1 & TX-2 46.5 15.3 40 49.3 16.2 40 52.2 17.2 40 55.4 18.2 40 58.7 19.3 40
Madinat Barka
TX-3 & TX-4 - - - 37.0 12.2 40 39.2 12.9 40 41.6 13.7 40 44.1 14.5 40
Madinat Ibri - - - - - - - - - - - - 64.0 21.0 40
Madinat Nizwa 53.4 17.5 40 55.5 18.2 40 57.7 19.0 40 59.4 19.5 40 61.2 20.1 40
Madinat Shinas - - - 61.3 20.1 40 65.0 21.4 40 68.9 22.6 40 73.0 24.0 40
Mahadah 26.4 8.7 10 27.5 9.0 10 28.3 9.3 10 22.3 7.3 10 23.0 7.6 10
3X50MVA 21.1 6.9 36 - - - - - - - - - - - -
Mawalleh North
2X125MVA - - - 90.0 29.6 40 93.6 30.8 40 97.3 32.0 40 101.2 33.3 40
TX-1 & TX-2 157.3 51.7 40 107.2 35.2 40 111.5 36.6 40 93.9 30.9 40 97.7 32.1 40
Mawalleh South
TX-3 & TX-4 102.3 33.6 40 114.4 37.6 40 113.0 37.1 40 89.5 29.4 40 93.1 30.6 40
MIS 172.6 56.7 - 59.2 19.4 - 62.1 20.4 - 64.6 21.2 - 67.2 22.1 -
Misfah 32.1 10.6 - 33.4 11.0 - 34.8 11.4 - 36.1 11.9 - 37.6 12.4 -
Mobella 109.6 36.0 40 114.0 37.5 40 55.6 18.3 40 57.8 19.0 40 60.1 19.8 40
TX-1 & TX-2 107.3 35.3 40 75.6 24.8 40 78.6 25.8 40 81.8 26.9 40 85.0 27.9 40
MSQ Tx-3 34.0 11.2 - - - - - - - - - - - - -
TX-3 & TX-4 - - - 74.4 24.5 40 77.4 25.4 40 80.5 26.4 40 83.7 27.5 40
Page | 132
Five-Year Annual Transmission Capability Statement (2017-2021)
Table B. 1 (Continued): Load and Capacitor Data for Grid Station (2017-2021)
2017 2018 2019 2020 2021
Grid Stations P P P P P
Q Load Caps Q Load Caps Q Load Caps Q Load Caps Q Load Caps
Load Load Load Load Load
(MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr)
(MW) (MW) (MW) (MW) (MW)
MIS System
Mudhaibi 2X125MVA 130.1 42.7 40 87.9 28.9 40 61.8 20.3 40 64.9 21.3 40 68.2 22.4 40
Mudhairib 101.1 33.2 48 106.1 34.9 48 76.4 25.1 48 80.2 26.4 48 84.3 27.7 48
TX-1 & TX-2 85.0 27.9 40 74.3 24.4 40 78.0 25.6 40 81.1 26.7 40 84.3 27.7 40
Muladah
TX-3 & TX-4 54.8 18.0 40 72.5 23.8 40 76.2 25.0 40 79.2 26.0 40 82.4 27.1 40
Muttrah 79.1 26.0 - 81.5 26.8 - 83.9 27.6 - 85.6 28.1 - 87.3 28.7 -
Nakhal 70.3 23.1 40 73.1 24.0 40 76.0 25.0 40 78.3 25.7 40 80.7 26.5 40
Nizwa 110.7 36.4 10 117.3 38.6 10 61.7 20.3 10 64.8 21.3 10 68.1 22.4 10
New Izki 14.0 4.6 40 37.7 12.4 40 39.6 13.0 40 41.6 13.7 40 43.6 14.3 40
Qurum 100.8 33.1 40 103.8 34.1 40 106.9 35.1 40 109.1 35.8 40 111.2 36.6 40
Quryiat 50.3 16.5 40 52.3 17.2 40 54.4 17.9 40 56.6 18.6 40 58.9 19.4 40
TX-1 & TX-2 92.5 30.4 - 98.0 32.2 - 103.9 34.1 - 80.1 26.3 - 84.9 27.9 -
Rusail Industrial
TX-3 & TX-4 72.0 23.7 - 76.3 25.1 - 80.9 26.6 - 65.8 21.6 - 69.7 22.9 -
2X63MVA - - - - - - - - - - - - - - -
Rustaq
3X125MVA 143.1 47.0 40 148.8 48.9 40 101.8 33.5 40 105.9 34.8 40 110.1 36.2 40
Saham 163.9 53.9 - 95.0 31.2 - 100.7 33.1 - 106.7 35.1 - 96.9 31.9 -
Samad - - - - - - 31.3 10.3 40 32.2 10.6 40 33.2 10.9 40
2X63MVA 83.0 27.3 - - - - - - - - - - - - -
Seeb Main TX-1 & TX-2 119.2 39.2 - 96.0 31.6 - 99.8 32.8 - 88.8 29.2 - 92.4 30.4 -
TX-3 & TX-4 - - - 96.1 31.6 - 105.9 34.8 - 85.2 28.0 - 88.6 29.1 -
Shinas 2X125MVA 112.4 36.9 40 51.8 17.0 40 58.9 19.4 40 65.4 21.5 40 69.4 22.8 40
Sinaw - - - 50.0 16.4 40 53.0 17.4 40 55.7 18.3 40 58.4 19.2 40
SIP 71.4 23.5 - 72.7 23.9 - 81.8 26.9 - 79.5 26.1 - 68.6 22.6 -
TX-1 & TX-2 114.3 37.6 40 74.3 24.4 40 79.5 26.1 40 85.0 27.9 40 66.8 21.9 40
Sohar
TX-3 & TX-4 109.3 35.9 40 73.7 24.2 40 76.9 25.3 40 82.3 27.0 40 63.8 21.0 40
Page | 133
Five-Year Annual Transmission Capability Statement (2017-2021)
Table B. 1 (Continued): Load and Capacitor Data for Grid Station (2017-2021)
2017 2018 2019 2020 2021
Grid Stations P P P
P Load Q Load Caps P Load Q Load Caps Q Load Caps Q Load Caps Q Load Caps
Load Load Load
(MW) (MVAr) (MVAr) (MW) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr)
(MW) (MW) (MW)
MIS System
TX-1 & TX-2 67.9 22.3 40 72.7 23.9 40 80.0 26.3 40 79.0 26.0 40 86.9 28.5 40
Sohar Free Zone
TX-3 & TX-4 - - - - - - 54.2 17.8 40 59.6 19.6 40 65.6 21.6 40
2X63MVA 35.7 11.7 - 47.5 15.6 - 39.4 12.9 - 41.0 13.5 - 42.6 14.0 -
Sumail
2X125MVA 105.9 34.8 40 101.2 33.3 40 55.3 18.2 40 57.5 18.9 40 59.8 19.7 40
Sur 88.7 29.2 48 92.3 30.3 48 96.0 31.5 48 99.8 32.8 48 103.8 34.1 48
TX-1 & TX-2 - - - 54.2 17.8 40 55.5 18.2 40 58.8 19.3 40 76.2 25.0 40
Uwaynat
TX-3 & TX-4 - - - 53.7 17.7 40 58.9 19.4 40 62.5 20.5 40 82.6 27.2 40
Wadi Adai 98.1 32.2 40 86.0 28.3 40 88.6 29.1 40 91.2 30.0 40 94.0 30.9 40
Tx-1 & Tx-2 62.8 20.6 40 65.3 21.5 40 67.9 22.3 40 70.6 23.2 40 73.4 24.1 40
Tx-3 & Tx-4 79.6 26.2 40 82.8 27.2 40 86.1 28.3 40 89.5 29.4 40 93.1 30.6 40
Wadi Sa'a 10.3 3.4 - 10.8 3.6 - 11.3 3.7 - 18.7 6.2 - 19.6 6.5 -
Yitti 10.9 3.6 - 12.0 3.9 - 13.2 4.3 - 14.5 4.8 - 15.9 5.2 -
6103. 6420. 6731. 7056.
Total 33 kV load 5740.2 1886.7 1988.0 2006.0 2440.0 2110.3 3040.0 2212.6 3160.0 2319.3 3280.0
0 3 6 3
Aromatics connected to 132kV (SIP-A) 22.0 7.2 - 22.0 7.2 - 22.0 7.2 - 22.0 7.2 - 22.0 7.2 -
Sohar Steel (SSSRM) connected to
90 29.6 - 96 31.6 - 96 31.6 - 96 31.6 - 96.0 31.6 -
132kV (SIP-A)
Jindal Shadeed connected to 220 (SIP-A) 260.0 85.5 - 270.0 88.7 - 275.0 90.4 - 275.0 90.4 - 275.0 90.4 -
Page | 134
Five-Year Annual Transmission Capability Statement (2017-2021)
Table B. 1 (Continued): Load and Capacitor Data for Grid Station (2017-2021)
2017 2018 2019 2020 2021
Grid Stations P Caps
P Load Q Load Caps Q Load Caps P Load Q Load P Load Q Load Caps P Load Q Load Caps
Load (MV
(MW) (MVAr) (MVAr) (MVAr) (MVAr) (MW) (MVAr) (MW) (MVAr) (MVAr) (MW) (MVAr) (MVAr)
(MW) Ar)
MIS System
OMPET Connected ti SIP 132kV - - - 27.0 8.9 - 27.0 8.9 - 27.0 8.9 - 27.0 8.9 -
Orpic (Liwa Plastic) 220kV SPS-2 - - - 200.0 65.7 - 200.0 65.7 - 200.0 65.7 - 200.0 65.7 -
Moon Iron & Steel Co connected to 220KV
- - - - - - 175.0 57.5 - 175.0 57.5 - 175.0 57.5 -
SFZ
Muscat Airport 25 8.2 - 25 8.2 - 25 8.2 - 25 8.2 - 25 8.2 -
Muscat Steel 20 6.6 - 20 6.6 - 20 6.6 - 20 6.6 - 20 6.6 -
Modern Steel 20 6.6 - 20 6.6 - 20 6.6 - 20 6.6 - 20 6.6 -
R.O Ghoubrah 40 13.1 - 40 13.1 - 40 13.1 - 40 13.1 - 40 13.1 -
Total 570.6 187.5 0.0 813.6 267.4 0.0 993.6 326.6 0.0 993.6 326.6 0.0 993.6 326.6 0.0
6916. 304
Grand Total 6310.8 2074.2 1988.0 2273.4 2440.0 7413.9 2436.8 7725.1 2539.1 3160.0 8049.9 2645.9 3280.0
6 0.0
Dhofar System
Al Qarm (2x63MVA) 30.2 9.9 - 19.0 6.2 - 16.6 5.5 - 15.6 5.1 - 16.5 5.4 -
Ashoor (2X125MVA) 46.2 15.2 - 49.5 16.3 - 75.4 24.8 - 80.0 26.3 - 84.8 27.9 -
Awaqad (2X125MVA) 110.4 36.3 40 95.2 31.3 40 84.0 27.6 40 83.7 27.5 40 87.4 28.7 40
Ittin (2X125MVA) 99.4 32.7 40 108.3 35.6 40 94.4 31.0 40 107.5 35.3 40 99.2 32.6 40
NPS (2x63MVA) 45.9 15.1 - 40.7 13.4 - 42.2 13.9 - 44.3 14.6 - 45.1 14.8 -
TX-1 & TX-2 32.0 10.5 40 63.9 21.0 40 80.9 26.6 40 86.6 28.5 40 92.6 30.4 40
S'aadah
TX-3 & TX-4 51.8 17.0 40 55.4 18.2 40 65.8 21.6 40 70.4 23.1 40 90.1 29.6 40
TX-1 & TX-2 94.6 31.1 40 97.1 31.9 40 93.4 30.7 40 85.1 28.0 40 87.9 28.9 40
Salalah Free Zone
TX-3 & TX-4 7.4 2.4 40 23.0 7.6 40 55.8 18.4 40 76.1 25.0 40 89.2 29.3 40
2x30 MVA 23.0 7.6 6 24.4 8.0 6 25.8 8.5 6 27.4 9.0 6 0.0 0.0 6
Thumrait
2x125 MVA - - - - - - - - - - - - 29.0 9.5 40.0
246
Total 540.9 177.8 246.0 576.6 189.5 246.0 634.5 208.5 676.7 222.4 246.0 721.9 237.3 286.0
.0
Salalah Airport 11.0 3.6 - 13.5 4.5 14.9 4.9 - 15.0 4.9 - 15.0 4.9 -
Total 11.0 3.6 0.0 13.5 4.5 0.0 64.9 21.3 0.0 65.0 21.4 0.0 65.0 21.4 0.0
246
Grand Total 551.9 181.4 246.0 590.1 194.0 246.0 699.4 229.9 741.7 243.8 246.0 786.9 258.6 286.0
.0
Page | 135
Five-Year Annual Transmission Capability Statement (2017-2021)
Sur PS Jahloot 400 2 Quad YEW 119.50 0.0211 0.2578 5.18 1774 − − − − − −
Sur PS New Izki 400 2 Quad YEW 222.5 0.0211 0.2578 5.18 1774 − − − − − −
Sohar IPP-2 Sohar Free Zone 220 2 ARCURIA x 2 6.0 0.0258 0.321 3.82 673 2500mm2 XLPE cable 3.5 0.01074 0.321 91.11 625
Sohar Free Zone SIS 220 2 ARCURIA x 2 33.2 0.0258 0.321 3.82 673 2500mm2 XLPE cable 0.5 0.01074 0.321 91.11 625
SIP-A Sohar-1 PS 220 2 − − − − − − 2500mm2 XLPE cable 3.7 0.01074 0.321 91.11 625
Mahadha Al Oha (UAE) 220 2 ARCURIA x 2 51.4 0.0258 0.321 3.82 673 − − − − − −
Barka Power station Filaj 220 2 ARCURIA x 2 10.0 0.0258 0.321 3.82 673 − − − − − −
Barka Power station Filaj 220 2 ARCURIA x 2 9.2 0.0258 0.321 3.82 673 2500mm2 XLPE cable 0.8 0.01074 0.321 91.11 625
Filaj Airport Heights 220 2 ARCURIA x 2 35.2 0.0258 0.321 3.82 673 − − − − − −
Airport Heights Misfah 220 2 ARCURIA x 2 15.5 0.0258 0.321 3.82 673 − − − − − −
SPS SIS 220 2 ARCURIA x 2 37.4 0.0258 0.321 3.82 673 2500mm2 XLPE cable 2.9 0.01074 0.312 91.11 625
Blue City MIS 220 2 ARCURIA x 2 45.6 0.0258 0.321 3.82 673 2500mm2 XLPE cable 5.8 0.01074 0.321 91.11 475
Filaj Blue City 220 2 ARCURIA x 2 33.3 0.0258 0.321 3.82 673 2500mm2 XLPE cable 5.8 0.01074 0.312 91.11 475
Barka IPP-3 Misfah 220 2 ARCURIA x 2 55.0 0.0258 0.321 3.82 673 2500mm2 XLPE cable 10.5 0.01074 0.321 91.11 625
Sur 1 GS Sur 2 GS 132 1 − − − − − − 2500mm2 XLPE cable 0.10 0.01074 0.321 91.11 343
Sur 1 GS Sur 2 GS 132 1 − − − − − − 2500mm2 XLPE cable 0.186 0.01074 0.321 91.11 343
Al Kamil JBB Ali 132 2 YEW x 2 54.8 0.04283 0.2821 3.98 293 − − − − − −
Al Kamil JBB Hassan 132 2 YEW x 2 43.5 0.04283 0.2821 3.98 293 − − − − − −
Page | 136
Five-Year Annual Transmission Capability Statement (2017-2021)
Sur JBB Hassan 132 2 YEW x 2 61.0 0.04283 0.2821 3.98 293 − − − − − −
Barka Main Filaj 132 2 YEW x 2 6.3 0.04283 0.2821 3.98 293 − − − − − −
New Izki Mudhaibi 132 2 YEW x 2 34.0 0.04283 0.2821 3.98 293 2500mm2 XLPE cable 0.62 0.01074 0.321 91.11 375
Mawalleh Rusail Industrial 132 2 − − − − − − 2500mm2 XLPE cable 6.2 0.04282 0.08361 122.522 375
Mobella Barka Main 132 2 YEW x 2 11.5 0.04283 0.2821 3.98 293 − − − − − −
MSQ Wadi Adai 132 2 YEW x 2 8.4 0.04283 0.2821 3.98 293 − − − − − −
SIS Sohar Grid 132 2 YEW x 2 27.5 0.04283 0.2821 3.98 293 − − − − − −
Sohar Grid Wadi Jizzi 132 2 YEW x 2 28.3 0.04283 0.2821 3.98 293 − − − − − −
Wadi Adai Al Falaj 132 2 YEW x 2 2.7 0.04283 0.2821 3.98 293 − − − − − −
Wadi Jizzi Mahadha 132 2 ELM x 2 36.4 0.0972 0.3168 3.8 178 − − − − − −
New Ghubrah Bousher 132 3 − − − − − − 2500mm2 XLPE cable 2 0.04 0.08 122.52 375
Bousher MSQ 132 1 YEW x 2 2.0 0.04283 0.2821 3.98 293 2500mm2 XLPE cable 2.7 0.04 0.08 122.52 375
New Ghubrah MSQ 132 3 YEW x 2 2.0 0.04283 0.2821 3.98 293 2500mm2 XLPE cable 4.3 0.04 0.08 122.52 375
Ghubrah old Ghubrah new 132 2 − − − − − − 2500mm2 XLPE cable 0.8 0.04 0.08 122.52 375
Airport Heights Mawalleh North 132 2 − − − − − − 2500mm2 XLPE cable 8.6 0.04 0.08 122.52 375
Page | 137
Five-Year Annual Transmission Capability Statement (2017-2021)
Mahadha Wadi Sa'a 132 2 YEW x 2 31.5 0.04283 0.2821 3.98 293 − − − − − −
Wadi Sa'a Dank 132 2 225 AAAC 58.3 0.04283 0.2821 3.98 89 − − − − − −
Misfah Wadi Adai 132 2 YEW x 2 33.9 0.04283 0.2821 3.98 293 − − − − − −
Nizwa Madinata Nizwa 132 2 YEW x2 12.4 0.04283 0.2821 3.98 293 − − − − − −
Wadi Kabir Al Hamriyah 132 2 YEW x1 1.8 0.0857 0.3948 2.85 146 1200mm2 1CCUXLPE cable 1.15 0.03 0.12 64.70 172
Al Hamriyah Muttrah 132 2 YEW x 2 2.8 0.04283 0.2821 3.98 293 2500mm2 XLPE cable 3.2 0.04 0.08 122.52 375
Al Hamryah Wadi Adai 132 2 YEW x1 3.7 0.0857 0.3948 2.85 146 − − − − − −
Rusail Rusail Industrial 132 4 − − − − − − 2500mm2 XLPE cable 0.192 0.04 0.08 122.52 375
Filaj Madinata Barka 132 2 YEW x2 11.5 0.04283 0.2821 3.98 293 − − − − − −
Madinata Barka Muladah 132 2 YEW x2 35.2 0.04283 0.2821 3.98 293 − − − − − −
Airport Height Mawalleh South 132 2 − − − − − − 2500mm2 XLPE cable 9.1 0.04 0.08 122.52 375
Airport Height Ghala 132 2 − − − − − − 2500mm2 XLPE cable 3.7 0.04 0.08 122.52 375
Page | 138
Five-Year Annual Transmission Capability Statement (2017-2021)
Dhofar System
Ashoor Al Qurum 132 2 YEW x 2 24.45 0.0388 0.289 1.43 359 2500mm2 XLPE cable 2.52 0.01075 0.141 91.1 279
SFZ NPS 132 2 YEW x 2 0.546 0.0388 0.289 1.43 359 2500mm2 XLPE cable 0.1 0.01075 0.141 91.1 279
Awqad A'saada 132 2 YEW x 2 15 0.0388 0.289 1.43 330 2500mm2 XLPE cable 6.5 0.01075 0.141 91.1 300
132 2 YEW x 2 8.5 0.0388 0.289 1.43 330 2500mm2 XLPE cable 1.2 0.01075 0.141 91.1 279
A'saada Ashoor (Portion-1)
132 2 YEW x 2 33.3 0.0388 0.289 1.43 330 2500mm2 XLPE cable 6.5 0.01075 0.141 91.1 300
A'saada Ashoor (Portion-2)
Page | 139
Five-Year Annual Transmission Capability Statement (2017-2021)
2018 Delesions
Filaj Airport Heights 220 2 ARCURIA x 2 35.2 0.0258 0.321 3.82 673 − − − − − −
New Izki Mudhaibi 132 2 YEW x 2 34.0 0.04283 0.2821 3.98 293 2500mm2 XLPE cable 0.62 0.01074 0.321 91.11 625
SIS Sohar Grid 132 2 YEW x 2 27.5 0.04283 0.2821 3.98 293 − − − − − −
2018 Additions
Ibri IPP New Izki 400 2 Quad YEW 250 0.0210914 0.2577821 5.18 1774 − − − − − −
New Izki Misfah 400 2 Quad YEW 100 0.0211 0.2578 5.18 1774 − − − − − −
Sohar Free Zone SIS 220 2 Quad YEW 42 0.0210914 0.2577821 5.18 975 − − − − − −
Sohar Free Zone Mahadha 400 2 Quad YEW 63 0.0210914 0.2577821 5.18 1774 − − − − − −
Sohar Free Zone
2500mm2 XLPE cable 3.3 0.01074 0.321 91.10619 2273
(Portion 1)
Sohar IPP-3 400 2 Quad YEW 6 0.0210914 0.2577821 5.184822 1774
Sohar Free Zone
2500mm2 XLPE cable 0.9 0.01074 0.321 91.10619 2273
(Portion 2)
Sohar IPP-3 Sohar Free Zone 400 2 − − − − − − 2500mm2 XLPE cable 10.2 0.01074 0.321 91.10619 2273
Ibri Ibri IPP 220 2 ARCURIA x 2 32 0.0258 0.321 3.82 673 − − − − − −
Ibri IPP Mahadha 220 2 ARCURIA x 2 124 0.0258 0.321 3.82 673 − − − − − −
SIP-A SPS 220 1 − − − − − − 2500mm2 XLPE cable 3.2 0.01074 0.321 91.10619 625
Mobailah Airport Heights 220 2 ARCURIA x 2 25.5 0.0258 0.321 3.82 673 − − − − − −
Shinas Madinat Shinas 132 2 YEW x 2 24.06 0.04283 0.2821 3.98 293 − − − − − −
Page | 140
Five-Year Annual Transmission Capability Statement (2017-2021)
2019 Delesions
Sur PS New Izki 400 2 Quad YEW 223.0 0.0210914 0.2577821 5.184822 975 − − − − − −
New Izki Misfah 400 2 Quad YEW 100 0.0211 0.2578 5.18 975 − − − − − −
MIS SIS 220 2 ARCURIA x 2 107.0 0.0258 0.321 3.82 673 − − − − − −
Mobella Barka Main 132 2 YEW x 2 11.5 0.04283 0.2821 3.98 293 − − − − − −
Rusail Sumail 132 2 YEW x 2 34.5 0.04283 0.2821 3.98 293 − − − − − −
Izki Nizwa 132 2 YEW x 2 31.0 0.04283 0.2821 3.98 293 − − − − − −
Mudhairib Ibra 132 2 YEW x 2 28 0.04283 0.2821 3.98 293 − − − − − −
Al Kamil Mudhairib 132 2 YEW x 2 51.2 0.04283 0.2821 3.98 293 − − − − − −
Khaborah DAS 132 2 YEW x 2 33 0.04283 0.2821 3.98 293 − − − − − −
Dhofar System
Page | 141
Five-Year Annual Transmission Capability Statement (2017-2021)
Sur PS Qabil 400 2 Quad YEW 116.54 0.0210914 0.2577821 5.184822 1774 − − − − − −
Qabil New Izki 400 2 Quad YEW 106.18 0.0210914 0.2577821 5.184822 1774 − − − − − −
Sohar Free Zone Shinas 132 2 Quad YEW 30 0.0210914 0.2577821 5.184822 585 − − − − − −
Nakhal Wadi Bani Awf 132 2 YEW x 2 54.5 0.04283 0.2821 3.98 293 − − − − − −
Wadi Bani Awf Rustaq 132 2 YEW x 2 33.2 0.04283 0.2821 3.98 293 − − − − − −
Ghala Ghala Height 132 2 − − − − − − 2500mm2 XLPE cable 7 0.04 0.08 122.52 375
Ghala Height Bousher 132 2 − − − − − − 2500mm2 XLPE cable 7 0.04 0.08 122.52 375
Halban Barka Main 132 2 YEW x 2 7.74 0.04283 0.2821 3.98 293 − − − − − −
Sumail Industrial
Rusail 132 2 YEW x 2 40.6 0.04283 0.2821 3.98 293 2500mm2 XLPE cable 1.6 0.04 0.08 122.52 375
Area
Sumail Industrial Area Sumail 132 2 YEW x 2 22.8 0.04283 0.2821 3.98 293 2500mm2 XLPE cable 1.6 0.04 0.08 122.52 375
Nizwa Birkat Al Mouz 132 2 YEW x 2 15.5 0.04283 0.2821 3.98 293 − − − − − −
Birkat Al Mouz Izki 132 2 YEW x 2 16.5 0.04283 0.2821 3.98 293 − − − − − −
Mahadha Bureimi 132 2 YEW x 2 32.9 0.04283 0.2821 3.98 293 2500mm2 XLPE cable 5.5 0.04 0.08 122.52 375
Page | 142
Five-Year Annual Transmission Capability Statement (2017-2021)
Dhofar System
Thumrait Wind Farm 132 1 ELM x 2 65.5 0.09 0.3 3.00 183 − − − − − −
2020 Delesions
Conductor
From To Voltage No. Length Rating Conductor Length Rating
Type R[Ω/km] X[Ω/km] B[MS/km] R[Ω/km] X[Ω/km] B[MS/km]
Substation Substation (kV Circuits (Km) (MVA) Type (Cable) (Km) (MVA)
(OHL)
Mawalleh Rusail Industrial 132 2 − − − − − − 2500mm2 XLPE cable 6 0.04 0.08 122.52 375
2020 Additions
Mawalleh Khoudh 132 2 240 ZTACIR 2.5 0.0261 0.075 0.0153 250 2500mm2 XLPE cable 0.5 0.04 0.08 122.52 375
Khoudh Rusail Industrial 132 2 240 ZTACIR 6 0.0261 0.075 0.0153 250 − − − − − −
Page | 143
Five-Year Annual Transmission Capability Statement (2017-2021)
Misfah Wadi Adai 132 2 YEW x 2 33.9 0.04283 0.2821 3.98 293 − − − − − −
New Ghubrah MSQ 132 3 YEW x 2 2.0 0.04283 0.2821 3.98 293 2500mm2 XLPE cable 4.3 0.04 0.08 122.52 375
Sohar Grid Wadi Jizzi 132 2 YEW x 2 28.3 0.04283 0.2821 3.98 293 − − − − − −
2021 Additions
Rusail Misfah 400 2 Quad YEW 12.3 0.0210914 0.2577821 5.184822 1774 − − − − − −
Misfah Misfah IPP 220 2 ARCURIA x 2 3.0 0.0258 0.321 3.82 673 − − − − − −
Misfah IPP MSQ 220 2 ARCURIA x 2 22.5 0.0258 0.321 3.82 673 2500mm2 XLPE cable 0.7 0.01074 0.321 91.10619 625
Misfah Wadi Adai 132 2 YEW x 2 33.0 0.04283 0.2821 3.98 293 2500mm2 XLPE cable 0.92 0.04 0.08 122.52 375
Khuwair New Ghubrah 132 2 − − − − − − 2500mm2 XLPE cable 4.6 0.04 0.08 122.52 375
Sohar Grid Falaj Al Qabail 132 2 YEW x 2 16 0.04283 0.2821 3.98 293 − − − − − −
Falaj Al Qabail Wadi Al Jizzi 132 2 YEW x 2 28 0.04283 0.2821 3.98 293 − − − − − −
Page | 144
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 145
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 146
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 147
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 148
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 149
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 150
Five-Year Annual Transmission Capability Statement (2017-2021)
Dhofar System
1 63 132/36 YNd5 HV 1.11 10 1 19 9.99 -9.99 15.37
Al Qarm
2 63 132/36 YNd5 HV 1.11 10 1 19 9.99 -9.99 15.37
5 1 19
1 125 132/33 YNd5 HV 1.10 4.42 -15.46 18.265
Ashoor
2 125 132/33 YNd5 HV 1.10 5 1 19 4.42 -15.46 18.257
1 125 132/33 YNd5 HV 1.11 5 1 19 4.44 -15.54 17.299
Awaqad
2 125 132/33 YNd5 HV 1.11 5 1 19 4.44 -15.54 17.284
Page | 151
Five-Year Annual Transmission Capability Statement (2017-2021)
MIS System
1 40 132/33 YNd5 HV 1.11 6 1 19 5.55 -14.43 11.79
Adam
2 40 132/33 YNd5 HV 1.11 6 1 19 5.55 -14.43 11.72
Mawalleh North 3 50 132/11 YNd1 HV 1.11 5 1 19 4.42 -15.47 32.21
1 63 132/34.8 YNd5 HV 1.10 6 1 19 5.50 -14.30 15.38
Seeb
2 63 132/34.8 YNd5 HV 1.10 6 1 19 5.50 -14.30 15.57
Barka Third Tx 3 125 132/33 YNd5 HV 1.11 5 1 19 4.44 -15.54 17.6
MIS System
1 500 400/220 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 22.08
Ibri IPP 2 500 400/220 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 22.08
3 500 400/220 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 22.08
SIA 3 500 220/132 YNa0d1 HV 1.10 6 1 20 5.50 -15.40 21.23
1 500 220/132 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 23.28
Mobella 220kV
2 500 220/132 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 23.28
1 125 220/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.50
Barka IPP
2 125 220/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.50
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Adam
2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
3 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Al Khadhra
4 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Page | 152
Five-Year Annual Transmission Capability Statement (2017-2021)
MIS System
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Mawalleh North
2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
MSQ 4 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.40 17.29
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Sinaw
2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Swauiq
2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Uwaynat
3 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
4 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Daghmar 3 50 132/11 YNd1 HV 1.11 5 1 19 4.42 -15.47 32.25
Page | 153
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 154
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 155
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 156
Five-Year Annual Transmission Capability Statement (2017-2021)
Table C.2 – Available capacity at Grid Stations (2017-2021) for connection of new demand
Table C.3 – Overhead line and cable circuit loadings at peak demand (2017-2021)
Table C.6 – Estimation of transmission losses and generation margin at peak demand (2017-2021)
C.3 Diagrames of the model for the Load Flow Study Results
The result of peak demand load flow studies for both MIS and Dhofar systems for the years 2017 through
to 2021 are presented as Figures C.1 to C.10 respectively.
Page | 157
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 158
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 159
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 160
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 161
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 162
Five-Year Annual Transmission Capability Statement (2017-2021)
Table C 2: Available Capacity at Grid Stations (2017-2021) for Connection of New Demand
Total Substation Available Capacity (MVA)
Transformer Firm
Location
Capacity Capacity 2017 2018 2019 2020 2021
(MVA) (MVA)
MIS Area
400/220 kV Transformers
New Izki 2 x 500 500 159.72 132.01 227.94 188.35 154.78
Ibri IPP 3 x 500 1000 536.80 432.01 409.56 400.10
Misfah 3 x 500 1000 518.90 355.90 353.18 858.02
SIS 3 x 500 1000 285.13 264.76 282.68
Sohar Free Zone 3 x 500 1000 245.13 213.74 214.99
Jahloot 4 x 500 1500 251.40 615.26 522.43 486.75 653.71
Sur 5 x 750 3000 1558.25 1671.68 1659.77 1585.76 1626.61
400/132 kV Transformers
Qabel 2 x 500 500 238.70 216.95 213.98
Rusail Industrial 3 x 500 1000 391.13
220/132 kV Transformers
Mahadha 2 x 315 315 223.21 96.58 40.45 21.28 -1.08
Airport Height 2 x 500 500 -90.53 185.91 64.01 38.34
Airport Height 3 x 500 1000 528.43
Al Filaj 2 x 500 500 -123.26 2.50 46.51 34.38 -18.74
Al Hamriyah 2 x 500 500 99.74 94.68 8.57 -23.06 89.69
Ibri 2 x 500 500 217.72 183.04 102.77 71.10 73.65
Jahloot 2 x 500 500 131.88 121.56 45.53 31.50 76.78
MIS 2 x 500 500 39.75 49.32 135.59 120.58 128.77
Misfah 2 x 500 500 205.77
MSQ 2 x 500 500 175.00 107.35 -63.80 -85.28 8.46
Mobella 2 x 500 500 -9.45 40.10 41.36 9.14
New Izki 2 x 500 500 168.18 152.53 231.37 192.09 170.54
KIS 2 x 500 500 252.42 236.17 222.63
SIP-A 2 x 500 500 225.74
SIP-A 3 x 500 1000 690.37 671.88 678.76 694.82
SIS 2 x 500 500 137.11 138.98 98.62 61.52 34.25
Sohar Free Zone 2 x 500 500 170.72 238.79 66.86 11.86 -22.68
Sur 2 x 500 500 169.03 125.36 222.73 210.34 189.37
Page | 163
Five-Year Annual Transmission Capability Statement (2017-2021)
Table C.2 (continued): Available Capacity at Grid Stations (2017-2021) for Connection of New Demand
Total Substation Available Capacity (MVA)
Transformer Firm
Location
Capacity Capacity 2017 2018 2019 2020 2021
(MVA) (MVA)
MIS Area
220/33 kV Transformers
Barka-3 PS 2 x 125 125 29.31 26.25 24.03 20.59
Blue City 2 x 160 160 60.09 54.66 50.17 45.23 41.14
132/33 kV Transformers
Tx (1&2) 2 x 125 125 8.45 3.84 54.03 49.45 45.62
A'salam
Tx (3&4) 2 x 125 125 62.02 58.03 54.56
40MVA 2 x 40 40 -17.59
Adam
125MVA 2 x 125 125 64.86 61.94 58.40 54.39
Tx (1&2) 2 x 125 125 18.34 14.95 66.83 63.34 62.16
Airport Height
Tx (3&4) 2 x 125 125 64.33 63.24
Al Falaj 2 x 125 125 17.19 17.16 9.95 6.00 5.58
Al Hayl 2 x 40 40 -15.72 -10.90 -13.51 19.52 23.04
Tx (1&2) 2 x 125 125 21.39 2.38 60.36 56.72 54.76
Amerat
Tx (3&4) 2 x 125 125 59.03 55.26 53.22
Ayjah 2 x 125 125 55.53 52.95 48.84 45.14 41.75
Bahla 2 x 125 125 68.42 67.33 64.48 61.01 57.59
Tx (1&2) 2 x 125 125 -6.38 -2.74 61.43 57.24 53.94
Barka Main
Tx (3) 1 x 125 0 -64.18
Bedyah 2 x 125 125 88.34 86.70 84.98
Birkat Al Mouz 2 x 125 125 57.69 53.95 50.49
Tx (1&2) 2 x 125 125 5.61 -5.97 36.87 31.99 57.21
Bousher
Tx (3&4) 2 x 125 125 -29.15 -12.06 33.20 28.10 53.55
Tx (1&2) 2 x 125 125 67.62 67.28 80.38 77.31 70.56
Bureimi Industrial
Tx (3&4) 2 x 125 125 68.72 64.79 60.18
Bureimi 2 x 125 125 29.54 27.97 64.12 59.27 57.84
Dank 2 x 63 63 31.95 27.96 26.95 25.65 25.02
Dil Abdusalam 2 x 125 125 26.89 24.81 18.08 27.55
Dreez 2 x 125 125 42.11 42.45 38.43 33.40 45.49
Falaj Al Qabail 2 x 125 125 55.34
Tx (1&2) 2 x 125 125 71.06 67.85 66.25
Ghala Heights
Tx (3&4) 2 x 125 125 68.90 65.55 63.89
Page | 164
Five-Year Annual Transmission Capability Statement (2017-2021)
Table C.2 (continued): Available Capacity at Grid Stations (2017-2021) for Connection of New Demand
Total Substation Available Capacity (MVA)
Transformer Firm
Location
Capacity Capacity 2017 2018 2019 2020 2021
(MVA) (MVA)
MIS Area
Tx (1&2) 2 x 125 125 37.70 34.03 76.64 73.28 71.80
Ghala
Tx (3&4) 2 x 125 125 76.54 73.17 71.69
Tx (1&2) 2 x 125 125 62.54 58.50 55.09
Halban
Tx (3&4) 2 x 125 125 61.45 57.32 53.92
Ibra 2 x 125 125 38.59 32.78 33.85 28.79 23.44
63MVA 2 x 63 63 29.26 27.14 28.01 26.33
Ibri
125MVA 2 x 125 125 54.57 53.40 46.33 40.22 49.87
Izki 2 x 125 125 44.63 67.52 64.42 62.27 60.80
JBB Ali 2 x 125 125 23.03 17.06 13.92 8.76 3.50
JBB Hasan 2 x 125 125 30.30 25.87 21.25 16.49 11.65
Jahloot 2 x 125 125 81.19 80.72 78.18 76.44 75.93
Jebreen 2 x 125 125 58.80 57.10 53.74 49.72 45.69
Khaborah 2 x 125 125 1.66 22.64 20.88 13.79 7.32
Tx (1&2) 2 x 125 125 51.66 46.79 45.49 41.71 38.47
Khadra
Tx (3&4) 2 x 125 125 64.20 63.25 60.28 57.82
Tx (1&2) 2 x 125 125 51.24 46.14
Khoudh
Tx (3&4) 2 x 125 125 51.24 46.14
Khuwair 2 x 125 125 70.97
Tx (1&2) 2 x 125 125 59.65 17.65 69.36 50.24 44.48
Liwa
Tx (3&4) 2 x 125 125 67.11 62.28 58.58 53.37 47.85
MIS 2 x 125 125 -72.28 59.27 57.68 54.48 51.61
Tx-3 1 x 125 0 -36.15
MSQ Tx (1&2) 2 x 125 125 10.18 45.65 37.82 33.83 32.46
Tx (3&4) 2 x 125 125 46.94 39.17 35.34 33.92
Tx (1&2) 2 x 125 125 73.61 71.01 69.02 65.23 62.24
Madinat Barka
Tx (3&4) 2 x 125 125 84.47 82.97 80.15 77.90
Madinat Ibri 2 x 125 125 57.03
Madinat Nizwa 2 x 125 125 66.48 65.01 62.76 60.57 58.41
Madinat Shinas 2 x 125 125 58.87 55.89 51.12 46.13
Mahadha 2 x 30 30 1.12 1.10 0.39 6.60 5.74
Mawalleh North 2 x 125 125 28.45 23.54 18.51 16.33
Page | 165
Five-Year Annual Transmission Capability Statement (2017-2021)
Table C.2 (continued): Available Capacity at Grid Stations (2017-2021) for Connection of New Demand
Total Substation Available Capacity (MVA)
Transformer Firm
Location
Capacity Capacity 2017 2018 2019 2020 2021
(MVA) (MVA)
MIS Area
Tx (1&2) 2 x 125 125 -45.50 10.73 5.91 25.96 18.21
Mawalleh South
Tx (3&4) 2 x 125 125 16.28 3.10 4.55 30.89 23.54
Misfah 2 x 125 125 91.35 89.92 88.49 87.29 85.48
Mobella 2 x 125 125 2.31 0.41 65.85 63.25 61.36
Mudhaibi 2 x 125 125 -20.03 27.35 58.60 54.84 51.52
Mudhairib 2 x 125 125 12.47 5.43 44.81 40.41 35.69
Tx (1&2) 2 x 125 125 29.54 41.33 39.51 35.44 32.09
Muladah
Tx (3&4) 2 x 125 125 63.77 43.64 41.74 37.82 34.48
Muttrah 2 x 125 125 37.90 37.17 31.41 29.21 29.91
Nakhal 2 x 125 125 48.05 44.71 42.44 39.37 37.58
Tx (1&2) 2 x 125 125 2.14 -12.42 -34.56 27.93 26.35
New Ghubrah
Tx (3&4) 2 x 125 125 58.36 57.32
New Izki 2 x 125 125 109.77 85.27 82.80 80.45 79.07
Nizwa 2 x 125 125 1.51 -2.86 58.80 55.08 51.26
Old Ghubrah 2 x 42 42 1.10 1.55
Quriyat 2 x 125 125 69.91 68.70 65.17 62.22 60.83
Qurum 2 x 125 125 13.14 12.60 5.18 2.23 3.05
Tx (1&2) 2 x 125 125 27.22 21.00 14.49 40.84 32.51
Rusail Industrial
Tx (3&4) 2 x 125 125 48.78 44.39 39.39 55.76 49.32
Rustaq 3 x 125 250 -77.30 -93.22 25.92 15.06 6.62
SIP 2 x 125 125 49.94 49.07 37.97 41.59 53.75
Saham 2 x 125 125 -57.99 20.50 16.50 9.25 20.40
Samad 2 x 63 63 29.29 28.10 27.15
63MVA 2 x 63 63 -30.09 -12.50
Seeb Main Tx (1&2) 2 x 125 125 -6.87 -10.96 16.33 28.16 26.39
Tx (3&4) 2 x 125 125 15.25 37.89 30.66
Shinas 2 x 125 125 4.79 69.53 62.85 55.40 50.63
Sinaw 2 x 125 125 70.71 68.02 64.74 62.35
Tx (1&2) 2 x 125 125 53.43 48.18 41.18 41.68 32.67
Sohar Free Zone
Tx (3&4) 2 x 125 125 68.12 62.41 55.62
Tx (1&2) 2 x 125 125 2.45 45.80 40.28 33.68 52.95
Sohar
Tx (3&4) 2 x 125 125 7.60 46.18 42.82 36.35 55.97
Page | 166
Five-Year Annual Transmission Capability Statement (2017-2021)
Table C.2 (continued): Available Capacity at Grid Stations (2017-2021) for Connection of New Demand
Total Substation Available Capacity (MVA)
Transformer Firm
Location
Capacity Capacity 2017 2018 2019 2020 2021
(MVA) (MVA)
MIS Area
Sumail Industrial 2 x 125 125 60.98 54.58 45.66
63MVA 2 x 63 63 24.18 12.06 20.49 18.69 16.27
Sumail
125MVA 2 x 125 125 9.37 15.87 65.32 62.86 59.44
Sur 2 x 125 125 31.59 28.49 22.96 18.09 13.62
Swauiq 2 x 125 125 49.00 47.30 43.56 40.37
Tx (1&2) 2 x 125 125 67.30 66.16 62.30 42.98
Uwaynat
Tx (3&4) 2 x 125 125 67.84 62.53 58.32 35.96
Wadi Adai 2 x 125 125 16.39 32.19 26.03 22.75 22.49
Wadi Bani Auwf 2 x 125 125 67.25 64.52 62.47
Tx (1&2) 2 x 125 125 55.74 54.84 49.48 46.23 45.23
Wadi Kabair
Tx (3&4) 2 x 125 125 36.61 35.61 28.76 24.60 23.24
Wadi Sa'a 2 x 63 63 51.91 51.64 51.19 43.42 42.38
Yanqul 2 x 125 125 89.95 84.42
Yitti 2 x 125 125 113.08 112.30 110.79 109.31 108.12
132/11 kV Transformers
2 x 50 50 -10.04
Daghmar
3 x 50 100 -14.70 -17.14 -18.05 -15.94
Mawalleh North 3 x 50 100 -41.68
Dhofar Area
132/33 kV Transformers
Ashoor 2 x 125 125 72.13 68.19 39.13 33.66 27.62
Awaqad 2 x 125 125 -2.19 15.54 24.79 25.78 20.98
Ittin 2 x 125 125 10.92 1.16 16.10 1.29 11.15
TX-1&2 2 x 125 125 88.51 51.72 32.10 26.16 18.47
Sa'adah
TX-3&4 2 x 125 125 65.55 61.66 49.85 44.19 21.44
TX-1&2 2 x 125 125 16.15 13.97 17.91 27.53 24.26
Salalah Free Zone
TX-3&4 2 x 125 125 116.55 98.82 61.14 38.08 22.68
2 x 30 30 3.49 2.06 0.23 -1.40 -
Thumrait
2 x 125 125 - - - - 91.96
Al Qarm 2 x 63 63 28.40 41.33 43.99 45.11 44.18
NPS 2 x 63 63 39.34 36.66 38.28 36.79 37.22
Page | 167
Five-Year Annual Transmission Capability Statement (2017-2021)
Table C 3: Overhead Line and Cable Circuit Loadings (%) at Peak Demand (2017-2021)
Circuit Circuit Loading at Max Demand (%)
Voltag No. of
Line Type Rating
e (kV) Circuits 2017 2018 2019 2020 2021
(MVA)
MIS Area
Ibri IPP New Izki OHL 400 2 1774 7.68 17.97 18.84 18.77
Jahloot Sur PS OHL 400 2 1774 35.20 24.94 27.56 28.56 23.84
Misfah New Izki OHL 400 2 1774 13.56 18.16 18.23 20.67
Rusail
Misfah 400 2 1774 17.17
Industrial OHL
New Izki Qabel OHL 400 2 1774 6.51 6.93 10.04
Airport Height Misfah OHL 220 2 673 43.62 37.55 29.62 29.18 40.71
Airport Height Mobella OHL 220 2 673 14.41 3.02 5.32 6.32
Al Filaj Barka PS 1&2 OHL 220 2 673 41.86 46.22 41.81 43.79 43.95
Al Filaj Barka PS 3&4 OHL 220 2 673 42.06 46.41 42.01 43.99 44.16
Al Filaj Blue City OHL 220 2 673 34.40 33.60 13.92 14.71 18.77
Al Hamriyah Jahloot OHL 220 2 673 29.70 30.07 36.46 38.81 30.43
Alw(UAE) Mahadha OHL 220 2 673 1.43 1.44 1.46 1.46 1.45
Barka-3 PS Misfah OHL 220 2 673 34.63 27.08 26.05 27.82 23.34
Page | 168
Five-Year Annual Transmission Capability Statement (2017-2021)
Table C.3 (continued): Overhead Line and Cable Circuit Loadings (%) at Peak Demand (2017-2021)
Circuit Circuit Loading at Max Demand (%)
Voltage No. of
Line Type Rating
(kV) Circuits
(MVA) 2017 2018 2019 2020 2021
MIS Area
Blue City MIS OHL 220 2 673 29.19 28.03 12.66 12.99 14.42
Page | 169
Five-Year Annual Transmission Capability Statement (2017-2021)
Table C.3 (continued): Overhead Line and Cable Circuit Loadings (%) at Peak Demand (2017-2021)
Circuit Circuit Loading at Max Demand (%)
Voltage No. of
Line Type Rating
(kV) Circuits
(MVA) 2017 2018 2019 2020 2021
MIS Area
Blue City MIS 220 2 475 40.79 39.14 16.35 16.84 19.20
UGC
MSQ Misfah IPP 220 2 625 38.97
UGC
Mahadha Sohar Free Zone 220 2 500 12.49 12.53 12.02
UGC
Misfah IPP Misfah 220 2 625 33.06
UGC
220 625 42.88 31.06 32.70 32.14 31.11
SIP-A Sohar-1 PS UGC 3
SIS Sohar Free Zone 220 2 625 15.26 1.69 13.45 12.79 10.89
UGC
SIS 220 625 37.34 21.60 8.34 6.56 10.82
Sohar-1 PS UGC 2
Sohar
220 625 41.44 22.41 14.83 16.17 16.19
FreeZone Sohar-2 PS UGC 2
Adam Manah 132 2 293 9.84 10.27 10.77 11.38 12.06
OHL
Al Falaj Wadi Adai 132 2 293 11.54 11.86 10.42 10.24 23.50
OHL
Al Falaj Barka Main 132 2 293 47.39 16.37 26.08 24.63 22.52
OHL
Al Falaj Madinat Barka 132 2 293 43.30 56.25 26.82 29.17 35.71
OHL
Al Filaj Nakhal 132 2 293 13.07 13.64 24.30 25.64 28.09
OHL
Al Hamriyah Muttrah 132 2 293 21.06 21.03 24.37 25.31 16.51
OHL
Al Hamriyah Qurum 132 2 293 5.59 6.55 11.44 11.82 25.13
OHL
Al Hamriyah Wadi Adai 132 2 146 23.63 23.05 32.40 33.81 8.00
OHL
Al Hamriyah Wadi Kabair 132 2 146 52.25 52.57 58.34 60.82 52.31
OHL
Al Hayl Dank 132 2 293 9.52 8.70 9.14
OHL
Al Hayl Yanqul 132 2 293 3.50 2.90
OHL
Page | 170
Five-Year Annual Transmission Capability Statement (2017-2021)
Table C.3 (continued): Overhead Line and Cable Circuit Loadings (%) at Peak Demand (2017-2021)
Circuit Circuit Loading at Max Demand (%)
Voltag No. of
Line Type Rating
e (kV) Circuits 2017 2018 2019 2020 2021
(MVA)
MIS Area
Al Kamil Bedyah OHL 132 2 293 19.47 20.37 20.95
Al Kamil JBB Ali OHL 132 2 293 17.42 18.44 18.98 19.86 20.76
Al Kamil JBB Hasan OHL 132 2 293 13.32 16.21 6.67 7.48 7.84
Amerat Jahloot OHL 132 2 293 30.96 32.64 43.41 44.56 36.86
Amerat MSQ OHL 132 2 293 13.54 12.08 21.34 21.33 12.88
Daghmar Quriyat OHL 132 2 293 10.26 9.80 10.01 10.09 9.90
Dank Ibri OHL 132 2 293 14.41 14.26 14.87 15.43 15.88
Dank Wadi Sa'a OHL 132 2 89 0.00 0.00 0.00 0.00 0.00
Page | 171
Five-Year Annual Transmission Capability Statement (2017-2021)
Table C.3 (continued): Overhead Line and Cable Circuit Loadings (%) at Peak Demand (2017-2021)
Circuit Circuit Loading at Max Demand (%)
Voltage No. of
Line Type Rating
(kV) Circuits 2017 2018 2019 2020 2021
(MVA)
MIS Area
Dil
Khaborah 132 2 293 11.35
Abdusalam(DAS) OHL
Dil
Saham 132 2 293 27.29 22.52 22.72 17.76
Abdusalam(DAS) OHL
Dil
KIS 132 2 293 9.34 8.77 6.91
Abdusalam(DAS) OHL
Dreez Ibri OHL 132 2 293 14.16 14.10 14.79 15.65 13.48
Izki New Izki OHL 132 2 293 29.51 30.07 37.28 44.86 42.59
Izki Sumail OHL 132 2 293 4.75 4.47 17.44 26.08 14.29
JBB Hasan Sur OHL 132 2 293 28.03 32.48 16.77 17.54 19.68
Jahloot Quriyat OHL 132 2 293 19.55 19.32 20.13 20.71 20.76
Jahloot Yitti OHL 132 2 403 1.48 1.57 1.76 1.94 2.09
Jebreen Nizwa OHL 132 2 293 11.31 6.35 6.15 8.25 3.31
Khaborah Khadra OHL 132 2 293 8.71 8.01 26.95 27.52 24.71
Page | 172
Five-Year Annual Transmission Capability Statement (2017-2021)
Table C.3 (continued): Overhead Line and Cable Circuit Loadings (%) at Peak Demand (2017-2021)
No. of Circuit Circuit Loading at Max Demand (%)
Voltage
Line Type Circuit Rating
(kV) 2017 2018 2019 2020 2021
s (MVA)
MIS Area
Khadra MIS OHL 132 2 293 20.53
Liwa Shinas OHL 132 2 293 20.54 20.57 11.26 12.22 13.06
Sohar Free
Liwa 132 2 293 42.79 50.82 33.29 38.44 41.22
Zone OHL
MIS Muladah OHL 132 2 293 23.08 21.42 36.70 37.40 32.71
MSQ Qurum OHL 132 2 293 13.53 12.65 9.94 9.33 6.67
MSQ Wadi Adai OHL 132 2 293 18.26 16.18 12.29 11.08 0.00
Madinat
Nizwa 132 2 293 10.00 10.25 10.63 11.01 11.38
Nizwa OHL
Madinat
132 2 293 11.30 11.81 12.62 13.48
Shinas Shinas OHL
Mahadha Wadi Al Jazzi OHL 132 2 178 49.85 9.21 29.94 25.15 27.23
Mahadha Wadi Sa'a OHL 132 2 293 1.89 1.93 1.99 3.31 3.48
Manah Nizwa OHL 132 2 293 49.10 47.36 43.91 46.50 42.10
Misfah Wadi Adai OHL 132 2 293 0.00 0.00 0.00 0.00 42.58
Mobella Rusail OHL 132 2 293 0.00 0.00 0.00 0.00 0.00
Page | 173
Five-Year Annual Transmission Capability Statement (2017-2021)
Table C.3 (continued): Overhead Line and Cable Circuit Loadings (%) at Peak Demand (2017-2021)
Circui Circuit Loading at Max Demand (%)
t
Voltag No. of Ratin
Line Type 202
e (kV) Circuits g 2017 2018 2019 2021
(MVA 0
)
MIS Area
Mudhaibi Mudhairib OHL 132 2 293 5.83 10.23 24.80 27.36 27.22
Muladah Madinat Barka OHL 132 2 293 34.80 40.47 10.93 12.09 17.94
Muladah Rustaq OHL 132 2 293 27.96 29.32 18.06 18.64 17.67
Muttrah Wadi Kabair OHL 132 1 293 1.40 1.74 2.55 1.81 9.05
Wadi Bani
Nakhal 132 2 293 10.82 11.63 13.84
Auwf OHL
New Izki Sinaw OHL 132 2 293 20.65 3.71 4.26 7.37
Shinas Sohar Free Zone OHL 132 2 585 5.49 6.06 6.48
Sohar Free Zone Wadi Al Jazzi OHL 132 2 293 2.86 21.14 3.87 5.81 5.27
Sohar Wadi Al Jazzi OHL 132 2 293 26.67 33.24 22.37 21.32
A'salam Mobella UGC 132 2 375 5.66 42.83 45.60 42.19 44.32
Page | 174
Five-Year Annual Transmission Capability Statement (2017-2021)
Table C.3 (continued): Overhead Line and Cable Circuit Loadings (%) at Peak Demand (2017-2021)
Circuit Circuit Loading at Max Demand (%)
Voltage No. of
Line Type Rating
(kV) Circuits 2017 2018 2019 2020 2021
(MVA)
MIS Area
A'salam Seeb Main UGC 132 2 375 19.47 28.11 29.13 24.53 25.73
Airport Height Ghala UGC 132 2 375 11.64 12.13 26.40 28.16 28.95
Airport Height Mawaleh South-B UGC 132 2 375 47.18 0.00 0.00 0.00 0.00
Airport Height Mawalleh North UGC 132 2 375 4.49 12.88 13.53 14.20 14.49
Al Falaj Muttrah UGC 132 1 300 13.44 12.82 18.87 19.88 9.27
Al Hamriyah Muttrah UGC 132 2 375 17.00 16.97 19.49 20.27 13.65
Al Hamriyah Wadi Kabair UGC 132 2 172 44.83 45.10 50.01 52.14 44.92
Bousher MSQ UGC 132 1 375 18.60 23.94 29.18 30.36 28.89
Bousher New Ghubrah UGC 132 3 375 18.04 15.80 6.23 6.73 2.75
Bureimi Industrial Bureimi UGC 132 2 375 12.66 12.87 4.61 4.72 5.18
Izki New Izki UGC 132 2 375 22.92 23.33 29.06 34.99 33.13
Mawalleh South-
Khoudh 132 2 375 4.26 4.63
A UGC
Khuwair New Ghubrah UGC 132 3 375 20.88
Mawalleh South-A Rusail Industrial UGC 132 2 375 37.23 31.49 31.94 21.58 23.24
Mawalleh South-B Seeb Main UGC 132 2 375 48.03 0.00 0.00 0.00 0.00
Muttrah Wadi Kabair UGC 132 1 300 2.37 2.70 3.45 2.71 9.15
Page | 175
Five-Year Annual Transmission Capability Statement (2017-2021)
Table C.3 (continued): Overhead Line and Cable Circuit Loadings (%) at Peak Demand (2017-2021)
MIS Area
Page | 176
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 177
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 178
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 179
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 180
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 181
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 182
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 183
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 184
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 185
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 186
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 187
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 188
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 189
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 190
Five-Year Annual Transmission Capability Statement (2017-2021)
Table C 6: Estimation of Transmission Losses and Generation Margin at Peak Demand (2017-2021)
2017 2018 2019 2020 2021
MW Mvar MW Mvar MW Mvar MW Mvar MW Mvar
Transmission Losses & Generation margin of MITS
Generation 6398 3280 7168 2910 7643 2703 7962 3070 8297 3167
External Infeed 180 0 0 0 0 0 0 0 0 0
Total Generation 6578 3280 7168 2910 7643 2703 7962 3070 8297 3167
Load (Grid+Industrial+Auxiliary+ Desalination) 6473 2127 7067 2327 7538 2482 7848 2584 8183 2690
Compensation Capacitor 0 0 0 0 0
Grid Losses 106 1152 101 583 106 221 113 486 115 477
Grid Active Power Losses as a Percentage of Total Generation (%) 1.61 1.42 1.38 1.43 1.38
Installed Capacity 8251 9366 10834 10834 11158
Generation 6398 7168 7643 7962 8297
Load Growth Rate (%) --- 9.18 6.66 4.12 4.26
Margin 1853 2198 3191 2873 2861
Margin (%) 22.5 23.5 29.5 26.5 25.64
Transmission Losses & Generation Margin of Dhofar System
Generation 582 219 625 217 737 273 780 301 826 331
External Infeed 0 0 0 0 0 0 0 0 0 0
Total Generation 582 219 625 217 737 273 780 301 826 331
Load (Grid+Industrial+Auxiliary+ Desalination) 579 190 623 205 735 242 778 256 823 271
Compensation Capacitor 0 0 0 0 0 0 0 0 0 0
Grid Losses 3 28 2 13 2 31 2 45 3 60
Grid Active Power Losses as a Percentage of Total Generation (%) 0.47 0.30 0.28 0.31 0.33
Dhofar Generation Margin
Installed Capacity 1026 1536 1586 1586 1586
Generation 582 625 737 780 826
Load Growth Rate (%) 11 19 41 49 57
Margin 444 911 848 805 760
Margin (%) 43 59 53 51 48
Page | 191
Five-Year Annual Transmission Capability Statement (2017-2021)
MIS
400 kV Busbars
Ibri IPP 400 63 14.47 17.82 17.82 17.99
Jahloot 400 63 10.28 10.90 11.03 11.03 12.01
Misfah 400 63 12.35 12.24 12.24 14.67
New Izki 400 63 7.00 14.90 15.35 15.35 16.51
Qabel 400 63 14.31 14.31 15.02
Rusail Industrial 400 63 13.43
SIS 400 63 16.82 16.82 16.84
Sohar Free Zone 400 63 20.12 20.12 20.14
Sohar-3 IPP 400 63 20.26 20.26 20.27
Sur PS 400 63 14.43 16.94 17.24 17.24 18.17
220 kV Busbars
Airport Height 220 40 23.49 26.02 24.86 24.86 31.43
Al Filaj 220 40 30.46 31.87 31.43 31.43 33.83
Al Hamriyah 220 50 11.11 11.36 12.41 12.41 14.31
Alw(UAE) 220 50 22.07 23.50 25.00 25.00 25.01
Barka PS 220 40 31.80 33.03 32.65 32.65 34.69
Barka-3 PS 220 50 14.38 15.16 14.88 14.88 16.23
Blue City 220 40 17.11 17.37 17.25 17.25 17.77
Ibri 220 50 4.48 11.74 12.38 12.38 12.38
Ibri IPP 220 50 17.30 18.95 18.95 18.99
Jahloot 220 50 16.78 17.39 17.80 17.80 20.64
MIS 220 40 15.51 15.65 15.74 15.74 16.00
MSQ 220 50 15.90 17.45 16.61 16.61 20.22
Mahadha 220 40 18.59 22.97 29.33 29.33 29.34
Misfah 220 50 23.32 28.62 26.58 26.58 39.62
Misfah IPP 220 50 38.60
Mobella 220 50 28.46 27.91 27.91 30.95
New Izki 220 50 9.89 13.11 13.01 13.01 16.80
KIS 220 50 16.68 16.68 27.89
SIP-A 220 40 24.71 26.12 27.88 27.88 36.80
SIS 220 40 27.06 28.34 36.73 36.73 33.76
Sohar Free Zone 220 50 20.25 20.78 33.74 33.74 29.80
Sohar-1 PS 220 40 27.40 27.78 29.79 29.79 31.43
Page | 192
Five-Year Annual Transmission Capability Statement (2017-2021)
MIS
Sohar-2 PS 220 50 18.81 19.21 27.82 27.82 27.84
Sur 220 50 24.64 26.13 26.09 26.09 26.55
Sur PS 220 50 35.67 38.97 39.06 39.06 40.14
132 kV Busbars
A'salam 132 31.5 20.50 20.79 20.69 20.69 21.42
Adam 132 40 6.37 6.77 6.75 6.75 6.72
Airport Height 132 31.5 20.91 14.63 14.40 14.40 20.29
Al Falaj 132 31.5 13.36 13.55 17.92 17.92 21.91
Al Filaj 132 31.5 24.53 25.28 25.56 25.56 26.47
Al Hamriyah 132 40 13.90 14.11 18.67 18.67 23.42
Al Hayl 132 31.5 2.78 3.87 3.90 3.75 3.74
Al Kamil 132 31.5 12.97 12.51 16.15 16.15 16.21
Amerat 132 40 12.70 12.88 15.26 15.26 17.17
Ayjah 132 40 8.84 8.92 8.95 8.95 8.98
Bahla 132 31.5 6.77 7.49 7.44 7.44 7.39
Barka Main 132 31.5 22.22 23.37 23.45 23.45 24.27
Bedyah 132 40 16.83 16.83 16.93
Birkat Al Mouz 132 40 17.12 17.12 16.75
Bousher 132 31.5 17.79 17.31 18.84 18.84 22.23
Bureimi 132 31.5 8.95 9.26 12.74 12.74 12.69
Bureimi Industrial 132 40 9.24 9.57 12.75 12.75 12.70
Daghmar 132 40 6.37 6.42 6.65 6.65 6.93
Dank 132 31.5 3.70 5.90 5.97 5.97 5.96
Dil Abdusalam (DAS) 132 40 11.81 17.07 17.07 17.07
Dreez 132 40 4.40 7.93 8.05 8.05 8.04
Falaj Al Qabail 132 40 15.10
Ghala 132 40 20.10 14.24 14.02 14.02 19.54
Ghala Heights 132 40 13.35 13.35 18.26
Halban 132 40 22.57 22.57 23.40
Ibra 132 40 6.57 6.10 11.88 11.88 11.96
Ibri 132 31.5 5.67 13.29 13.64 13.64 13.62
Izki 132 31.5 17.12 19.60 18.95 18.95 18.30
JBB Ali 132 31.5 5.87 5.78 6.45 6.45 6.46
JBB Hasan 132 40 11.15 11.07 12.10 12.10 12.14
Jahloot 132 31.5 14.82 15.08 16.42 16.42 18.28
Page | 193
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 194
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 195
Five-Year Annual Transmission Capability Statement (2017-2021)
MIS
Tx
33 25 17.63 17.72 18.72 18.72 19.38
(1&2)
Amerat
Tx
33 25 18.72 18.72 19.38
(3&4)
Ayjah 33 25 15.74 15.81 15.84 15.84 15.86
Bahla 33 25 13.82 14.53 14.49 14.49 14.44
Tx (3) 33 25 12.48
Barka Main Tx
33 25 22.35 22.63 22.64 22.64 22.83
(1&2)
Barka-3 PS 33 25 21.65 21.57 21.57 21.96
Bedyah 33 25 20.11 20.11 20.15
Birkat Al Mouz 33 25 19.92 19.92 19.79
Blue City 33 31.5 26.95 27.04 27.00 27.00 27.30
Tx
33 25 20.72 20.55 21.06 21.06 22.00
(1&2)
Bousher
Tx
33 25 20.05 19.89 20.36 20.36 21.23
(3&4)
Bureimi 33 25 15.75 15.98 18.07 18.07 18.04
Tx
33 25 15.80 16.03 17.89 17.89 17.87
Bureimi (1&2)
Industrial Tx
33 25 17.89 17.89 17.87
(3&4)
Dank 33 25 7.95 9.96 10.00 10.00 10.00
Dil Abdusalam(DAS) 33 25 17.73 20.04 20.04 20.04
Dreez 33 25 11.02 15.28 15.39 15.39 15.38
Falaj Al Qabail BB 33 25 19.72
Tx
33 25 18.52 18.52 20.42
(1&2)
Ghala Heights
Tx
33 25 18.52 18.52 20.42
(3&4)
Tx
33 25 20.96 18.92 18.83 18.83 20.80
(1&2)
Ghala
Tx
33 25 18.83 18.83 20.80
(3&4)
Tx
33 25 22.20 22.20 22.40
(1&2)
Halban
Tx
33 25 22.20 22.20 22.40
(3&4)
Ibra 33 25 13.54 13.03 17.57 17.57 17.61
Page | 196
Five-Year Annual Transmission Capability Statement (2017-2021)
MIS
125MVA 33 25 12.57 18.32 18.48 18.48 18.47
Ibri
63MVA 33 25 10.88 15.01 15.12 15.12
Izki 33 25 20.41 21.20 21.01 21.01 20.81
JBB Ali 33 25 12.93 12.81 13.59 13.59 13.60
JBB Hasan 33 25 17.63 17.58 18.20 18.20 18.22
Jahloot 33 25 18.46 18.56 19.04 19.04 19.62
Jebreen 33 25 16.13 18.70 18.67 18.67 18.61
Khaborah 33 25 17.55 17.42 19.57 19.57 19.62
Tx (1&2) 33 25 18.54 18.48 19.35 19.35 19.40
Khadra
Tx (3&4) 33 25 18.48 19.35 19.35 19.40
Tx (1&2) 33 25 21.86 22.05
Khoudh
Tx (3&4) 33 25 21.86 22.05
Khuwair 33 25 22.26
Tx (1&2) 33 25 20.58 20.67 20.78 20.78 20.73
Liwa
Tx (3&4) 33 25 20.58 20.67 20.78 20.78 20.73
MIS 33 25 20.52 20.53 20.84 20.84 21.20
Tx (1&2) 33 25 20.73 20.60 21.29 21.29 22.26
MSQ
Tx (3&4) 33 25 12.16 20.70 21.40 21.40 22.38
Tx (1&2) 33 25 21.34 21.44 21.42 21.42 21.56
Madinat Barka
Tx (3&4) 33 25 21.44 21.42 21.42 21.56
Madinat Ibri 33 25 17.53
Madinat Nizwa 33 25 17.19 18.29 18.22 18.22 18.16
Madinat Shinas 33 25 15.09 16.15 16.15 16.12
Mahadha 33 25 8.51 8.57 8.56 8.56 8.56
Mawalleh North 33 25 19.01 18.91 18.91 20.90
Mawalleh Tx (1&2) 33 25 20.67 20.72 20.55 20.70 20.87
South Tx (3&4) 33 25 21.70 21.76 21.57 21.73 21.92
Misfah 33 25 19.73 19.77 19.62 19.62 22.02
Mobella 33 25 20.83 21.37 21.35 21.35 21.58
Mudhaibi 33 25 17.60 15.60 17.39 17.39 17.36
Mudhairib 33 25 16.40 15.66 21.15 21.15 21.20
Tx (1&2) 33 25 19.95 19.98 20.39 20.39 20.47
Muladah
Tx (3&4) 33 25 19.86 19.88 20.29 20.29 20.38
Muttrah 33 25 18.95 19.04 20.79 20.79 22.00
Nakhal 33 25 17.81 17.91 18.79 18.79 19.07
Tx (1&2) 33 25 20.78 20.61 21.12 21.12 22.06
New Ghubrah
Tx (3&4) 33 25 21.20 22.16
Page | 197
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 198
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 199
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 200
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 201
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 202
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 203
Five-Year Annual Transmission Capability Statement (2017-2021)
Page | 204
Five-Year Annual Transmission Capability Statement (2017-2021)
DIgSILENT
Sohar Aluminum PS
~ ~
Sohar-1 PS G
1.00
180.00
10.13
G
0.00
0.00
Sohar-2 PS Barka-2 PS Barka-1 PS Barka-3 PS 0.42
1.00
-137.66
0.41
1.00
-136.16
0.41
1.00
-114.78
0.42
1.00
-112.25
0.41
1.00
-125.75
0.42
1.00
-126.10
40.06 -3.84
~ ~ 1.28 ~ ~ ~ ~ ~ ~ ~ ~ ~ ~
G G -1.00 G G G G G G G G G G
-460.82
0 0 0 0 0 0 0 0
367.36
124.91
0.94
-65.56
29.19
34.40
-179.58 472.98 0.86 0.84 0.83 0.82 0.85 0.95 0.95 -1.00 -1.00 0.95 -1.00 -1.00 0.95 -1.00 -1.00 -1.00 0.95 -1.00 -1.00 -1.00 0.95 -1.00 -1.00 0.95 -1.00 -1.00
0.89 0.83 1.10 0.87 0.84 0.86 270.00 205.00 220.00 220.00
375.00 210.00 244.00 240.00 245.24 250.00 160.00 175.00 81.77 83.00 -0.00
1.00 -0.00
1.00 119.00 -0.00 -0.00 157.00 -0.00
1.00 -0.00 -0.00 102.00 -0.00
1.00 -0.00 -0.00 98.00 -0.00
1.00 -0.00
1.00 97.00 -0.00 -0.00
42.94 -0.00 240.00 157.46 158.79 109.47 123.11 125.65 75.79 27.28 -0.00 -0.00 39.11 0.00 0.00 51.60 -0.00 0.00 0.00 33.53 0.00 0.00 0.00 32.21 0.00 -0.00 31.88 0.00 0.00
189.39 138.40 135.67
0.87 154.23 144.35 38.33 -367.36 460.82 69.03 0.00 0.00 0.00 0.00 0.00 0.00
1.00 -0.00 59.54 72.99 60.96 76.42 74.90 72.49 3 0.00 3 0.00 3 0.00 3 0.00 3 0.00 3 0.00
78.23 91.46 -3.84 86.97
244.00 88.87 82.37 -124.91 65.56 -0.00 0.00 0.00 -0.00 -0.00 -0.00
180.00 7 40.79 49.77 0.85 0.00 0.00 0.00 0.00 0.00 0.00
10.13 8 0.03
1.58 135.67 -472.98 205.00
42.94 0.14 87.93 0.95 0.94
4.41 -245.24 125.65 220.00
41.19 0.86 0.84 0.83 0.82 75.73 220.00 33.09 -0.95 -0.95 -0.95 -0.95
1.58 18 75.79 81.77 32.89 32.91
0.84 0.86 270.00 250.00 160.00 175.00 1.00 -157.00 33.06 -102.00 -98.00 33.01 -97.00
20 157.46 158.79 109.47 123.11 73.29 66.53 1.00 -51.60 32.87 -33.53 1.00 -32.21 -31.88
240.00 240.00 -167.66 1.00 1.00
0.89 0.83 60.40 74.04 60.96 76.42 -0.95 -0.95 -166.16 68.20 1.00 -142.25 43.49 -155.75 43.44 43.12
375.00 210.00 230.52 154.23 144.35 -83.00 -119.00 -156.10
89.85 79.38 -0.90 16 -0.89 16 -0.86 16 -0.86 16 -0.91 17 -0.98 17 -0.97 0.91 0.92 11 -144.78 14 0.92 10 0.92
189.39 138.40 1.05 215.18 -365.51 367.45 -460.68 -269.58 -250.00 -159.75 -174.70 141.55 -344.13 -27.28
83.31 -39.11
119.27 345.35 -345.35 98.22 -96.90 97.22
13 11
74.69
-0.93
15 91.26
-0.90
17
-6.56 1.00
0.00
-0.00
179.45
-5.51
37.47
1.00
0.00
-0.00
-0.93
-243.53 20 -0.90 19 -0.91
0.98
-9.74
-118.38
29.19
76.23
40.79
Blue City -113.07
49.77
220.73
1.00
-6.20
-129.15
60.40
-125.90
74.04
-94.11
60.96
-101.86
76.42
-204.53
-95.96
75.73
-219.52
-47.83
73.29
-219.52
-55.94
66.53
-4.90
19.47
-83.95
48.03
129.81
0.98
-11.55
73.88
37.95
73.88
52.75
50.90
52.75
53.98
48.03
-53.98
47.18
130.42
0.99
-11.21
0.91 0.92
40.66
43.44
129.20
0.98
-1.82
-39.37
18.26
7 40.81
43.12
-374.36 -209.55 -179.42 473.07 157.40 102.23
134.20
1.02
Shinas -143.59
74.69
-103.48
91.26
-5.34
37.47
-96.10
87.93 228.21
1.04
-239.54
-113.00
89.85
-239.53
-108.31
79.38
219.34
41.19
MIS 73.01
68.20
Mawalleh South-A 42.31
43.49
Al Falaj
-13.49 -7.88 0.84 225.94 229.30 433.03 134.33
378.30 1.03 129.10
243.98 510.96 1.04 101.80 1.02
-2.00 0.98
230.49
1.05
-12.79
-125.60
9.59
46.02
20
0.93
93.23
36.84
0.95
6.00
1.97
0.95
25.00
8.22
510.60
268.24
41.86
266.56
41.74
0.95
6.00
1.97
4.00 0.95
6.00
1.97
36.64
-432.81
Seeb Main Mawalleh South-B -259.63
-115.32
37.23
11.68 -62.93
-24.94
23.63
Wadi Adai 61.61
23.65
11.54
-61.60
-23.91
11.54
-1.90
-35.62
-16.91
13.44
-112.30 0.92 -6.61 0.95 0.95 528.56 441.31 0.95 129.27 32.81 14 31.22 -195.32
-48.22 112.30 14 31.00 6.00 153.87 182.47 6.00 0.98 -0.89 0.99 -0.95 36.64
20.54 48.22 10.19 1.97 42.88 37.34 1.97 -14.83 -377.84 -159.25 -93.00
32.86 48.08 -197.85 -30.57 432.81
1.00 -0.95 195.32
46.02 31.22 34.63
-167.98 -112.00
-36.81 130.03 134.58
48.08 1.00 -510.65 219.39 1.02
0.00 0.99
-264.13 1.00
1.00
115.60
18.73
0.90
173.47
-0.95 9
88.76
96.56
-1.00
0.00
-0.00
3 0.95
93.00
-1.00
-0.00
-1.00
-0.00
-11.94
Madinat Barka 41.74 -0.97 Misfah 11.68
Wadi Kabair
34.63
-177.37
-429.67
20.53 82.57 23.08 0.00
0.00 30.57 0.00 0.00
-1.00 -1.00 0.95 0.00
-1.00 3 -173.00 0.94
-0.00 78.91
-56.86 32.68 0.00 510.65
-0.00 -0.00 112.00 -0.00 0.99 0 0 264.13 32.12 129.14
0.00 0.00 36.81 0.00
0.00 78.91 12.06 0.98
-171.88 197.89 0.93 -245.02 45.22 298.29 -453.34 584.73 -32.12 -141.79 0.93 0.93 -1.53
0.00 13.46 -1.88
0 0 0.41 29.35 47.13
-0.95 8 -47.77 117.47 87.91 -28.00 -12.06 15 -50.17 63.15 12 80.18 11 -6.77
-441.24 0.99
-208.51 34.80 18.42
-47.00 43.30 24.15 34.74 43.62 5.75 44.83 24.56 32.38 2.37
-129.25 33.20 20.55
-15.45 19 27.70 32.85 35.35 32.68
0.41 37.34 33.37
1.00 1.01 20.55 -0.95 -0.95 1.00 -0.95 0.99
1.00 1.01 -32.00 -63.00 -80.00
-137.98 0.00
-1.00 3 0.95 -163.76 -139.55 -154.36 -155.23
441.24 0.00
-0.00 173.00 -10.52 -20.71 -26.29
208.51 0.00
-0.00 56.86 -510.62 13.46 27.70 35.35
35.12 0.00 -270.69
1.00 45.22 1.00 1.00 1.00
0.41 0.00
-1.00 3 0.95 -1.00 -1.00 0.00
-1.00 3 0.95 0.00 MW 0.00
-1.00 3 0.95 -1.00 -1.00 0.00
-1.00 3 0.95 -1.00 -1.00
-0.00
-0.00 510.62 0.00
-0.00 -0.00
-0.00 -0.00
-0.00
173.68 -472.55 0.99 47.00 -0.00 -0.00 270.69 32.00 0.00 Mvar 63.00 -0.00 -0.00 80.00 -0.00 -0.00
0.00
0.00 15.45 0.00 0.00 0.00
0.00 1.00 0.00
-0.00 0.00 0.00 0.00
-0.00 0.00 0.00
91.40 -242.32 -141.88 42.06 10.52 20.71 26.29
0.00 0.00 0.00 0.00
14.62 38.33 0 0 0 0 0 0
0.42 0.42 0.41 0.41
-173.68 472.55 1.01 1.01 1.00 0.99
-91.40 242.32 1.53
-133.76 -109.55 55.64 54.77 3.71
15.26 41.44
2.37
OCC -1.53
-3.71
1.40
1.53
3.61
1.40
-1.53
-3.61
1.34
141.83
173.69 -472.54
0.95
260.00 -528.45 -439.04
223.78
1.02 -173.35 13.14 462.72 -509.75 -12.06
Rusail PS 47.80
44.83
226.42
1.03
86.79
15.26
-246.56
41.44
85.46 -186.26
42.88
230.02
1.05
-195.85
35.12
-9.66 -100.12
14.62
90.41
9.59
76.56
34.40
-261.61
41.86 -510.15
173.13
13.65 ~ ~ ~ ~ Hamriyah -141.83
-47.80
-8.64 -6.94 -266.97 G
0.93 G
0.92 G
0.90 G
0.88 52.25
42.06 249.00 93.00 212.44
240.00 94.00
96.04 109.71 46.39 50.89 0.97
0.94 0.81 0.90 223.76 85.77 90.61 3.54
-116.40
62.90 69.88
116.40
-31.95
21.06
31.95
17.00
268.45 298.85 569.25
18
1.02
100.80 216.68 278.89
0.95
0.88
298.85
-0.91
27.43
15
300.40
-11.13
36.29
-0.85 20
Sohar Al Filaj 62.33
18
-2.89
0.93
240.00
0.92
249.00
0.90
94.00
0.88
93.00 0.91
112.64 8.60 -238.53 238.70 159.78
-298.53 -0.00 0.00 21.96 -298.49 -115.15 -70.16 -251.67 252.26 70.33 245.92 -141.37 96.04 109.71 3 46.39 50.89 32.13 464.65 -464.62 260.20 350.95 62.97 141.93 116.46 -116.34 1.53 35.63
47.66
20.54
135.53
1.03
-12.57
2.83 -96.05
42.79
96.88
42.79
32.93
-134.67
32.93
SFZ 135.34
1.03
-0.00
1.28
-9.87
1.28 -0.96 Sohar Industrial Area (SIA) -187.60
36.29
Interconnection SS 128.24
0.97
-19.13
20.53
130.14
0.99
-11.40
-27.74
13.07
130.11
0.99
-11.35
-106.80
47.39
Barka Main 109.87
47.39
25.59
13.07
52.18
43.30 131.11
0.99
-0.95
129.62
0.98
-11.69
-24.02
19.47
3 63.83
-0.95
65.72
-0.94
4 76.24
-0.94
4 84.54
-0.92
10.33
5.75
168.19
94.15
-169.40
94.15
Rusail Industrial 88.93
37.23
134.78
1.02
-350.95
-160.64
29.70
-0.95 20
160.64
-350.44
40.03
-117.34
24.79
23.63
48.11
52.25
31.92
21.06
-44.92
17.00
2.58
1.34
10.80
13.44
129.27
0.98
-268.16 -16.24 -568.52 -239.57 -248.59 -93.75 -92.70 11.85
Liwa -10.12
-83.03
27.43 (SIS) Khadra Nakhal -10.65 -187.64
62.33
A'salam -76.24
63.83
-90.76
65.72
-35.52
76.24
-39.07
84.54
40.03
Qurum -1.78
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 33.10 1.00 1.00
0.00
-1.00 3 0.00
-1.00 3 -1.00 -1.00 0.00
-1.00 3 -1.00 3 0.00
-1.00 3 0.00
-1.00 3 0.00
-1.00 3 0.00
-1.00 3 0.00
-1.00 3 0.00
-1.00 3 0.00
-1.00 3 0.00
-1.00 3 0.00
-1.00 3
0.95 -1.00 -1.00 -1.00 -1.00 0.95 0.95 1.00
-0.00 0.95 0.95 -1.00 -1.00 -1.00 -1.00 0.95 0.95 0.95 -1.00 -1.00 0.95 1.00 1.00 0.95 0.95 1.00 0.95 -1.00 -1.00 0.95
0.00
-0.00 62.00 -0.00 -0.00 -0.00 -0.00 55.00 -0.00
-0.00 -0.00 -0.00 68.00 0.00
-0.00 0.00 71.00 0.00
-0.00 66.00 -0.00 -0.00 -0.00 -0.00 70.00 0.00
-0.00 58.00 0.00
-0.00 -0.00
-0.00 119.00 -0.00 -0.00 0.00
-0.00 105.00 0.00 0.00 92.00 -0.00
-0.00 72.00 -0.00
-0.00 79.00 0.00
-0.00 -0.00 -0.00 101.00 -0.00
-0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -154.93 0.00 0.00
-0.00 20.38 0.00 0.00 0.00 0.00 18.08 0.00 0.00 0.00 22.35 -0.00 -0.00 23.34 -0.00 21.69 0.00 0.00 0.00 0.00 23.01 -0.00 19.06 0.00 -0.00 39.11 0.00 0.00 -0.00 34.51 0.00 0.00 30.24 0.00 23.67 0.00 25.97 0.00 0.00 0.00 33.20 0.00
0.00
0 0 0 0
0.00
0 0
0.00
Sohar Refinery 0.00
0.00 0.00
0.41
0 0 0 0
0.00 0.00
0.42
0.00
0 0
0.00
0.41
0 0
0.42
0.00 0.00
0.42
0.00
0.42
0 0
0.00
0.41
0.42 0.42 0.42 0.41
0.42 1.00 0.42 1.00 1.01 1.00 1.01 1.00 1.00 1.00
1.00 1.01 1.00 1.01 1.01
-132.99 -138.91 -135.85 -135.77 44.00 -111.79 -111.04 -124.93 -125.70
-135.12 -134.82 -134.98 -134.25
-583.30 219.24
40.01 1.00
43.62 -2.71
0.97
570.94
142.65
12.36 59.05
-182.66 -0.99 17 0.95
127.88 13.65
-70.12 61.78 -61.36 -48.89 -88.51 -196.10 144.27 -143.30 -74.17 -36.08 -570.27 25.00 346.73
133.67
1.01
-14.09
-57.32
15.28
-226.21
-123.30
44.15
Saham 46.66
14.05
-51.10
14.05
4.27
8.71
Khaborah -96.39
23.08
-22.21
34.80
Muladah 0.97
-15.25 62.10
27.96
-59.52
27.96
Rustaq -32.31
14.08
-14.48
5.66
Mobella 131.04
0.99
-58.56
59.05
Airport Height 8.22 18.56
47.18
130.96
0.99
Sohar 131.60
1.00
-15.53
-10.79 -10.82
Ghala
0.92 0.92 0.91 0.92 0.92 0.92 0.93
109.28 114.26 164.43 110.25 128.19 125.16 143.30 110.25 129.58 80.20
46.81 48.44 76.65 46.83 0.97 0.95 59.52 46.79 0.98 32.77
46.96 49.02 -153.42 73.19 49.34 -16.92 0.93 0.93 -17.25 43.64 49.08 -11.73 21.09 0.92 80.23 -80.20 34.92
-0.95 12 -0.95 12 -37.93 -0.95 10 7 55.15 85.19 -0.95 8 -0.95 10 -25.93 97.22 12 17.27 -32.77 -0.95 12
-109.00 -114.00 26.67 -164.00 33.01 21.84 34.66 -143.00 -110.00 4.49 40.44 11.64 11.64 -80.00
33.12 -35.83 -37.47 33.13 -53.90 1.00 24.49 10 38.19 10 -47.00 33.07 33.06
-36.16 32.78 42.66 -26.29
32.70 1.00 32.74
1.00 46.96 49.02 1.00 73.19 -172.10 -0.95
0.99
-0.95 -0.95 43.64 1.00
-166.20 49.08 0.99 -0.95
0.99 34.92 ~
11.49 -168.55 -110.00
-36.16 -171.42 32.93 -55.00
-18.08
-85.00
-27.94 32.86
-170.95 -164.81 -97.00
-31.88 -164.08
G
0.97
1.00 1.00 0.42
49.34 12.46 24.49 38.19 42.66 48.00
-168.77 1.00 11.19
-123.07
54.76
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.97
0.00
-1.00
-0.00
-0.00
0.00
0.00
0.00
3 0.95
109.00
35.83
1.00
0.00
0.00
1.00
0.00
0.00
0.00
-1.00
-0.00
-0.00
0.00
-0.00
0.00
3 0.95
114.00
37.47
-1.00
-0.00
0.00
-1.00
-0.00
0.00
0.95
164.00
53.90
0.00
-1.00
-0.00
-0.00
0.00
0.00
0.00
3 -1.00
-0.00
0.00
-1.00
-0.00
0.00
0.95
110.00
36.16
0.00
-1.00
0.00
-0.00
0.00
-0.00
0.00
3
-1.00
1.00 3 0.95 1.00 1.00 -1.00
1.00 3 0.95 -1.00 -1.00
-1.00
-0.00
0.00
-1.00
-0.00
0.00
0.95
143.00
47.00
0.00
-1.00
-0.00
-0.00
0.00
0.00
0.00
3 0.00
-1.00
0.00
-0.00
0.00
0.00
0.00
3 0.95
110.00
36.16
-1.00
-0.00
0.00
-1.00
-0.00
0.00
-1.00
-0.00
0.00
-1.00
-0.00
0.00
0.95
97.00
31.88
0.00
-1.00
-0.00
-0.00
0.00
0.00
0.00
3 0.00
-1.00
0.00
-0.00
0.00
-0.00
0.00
4 0.95
80.00
26.29
-1.00
-0.00
0.00
-1.00
-0.00
0.00
-1.00
-0.00
-0.00
0.00
48.00
11.19
67.06 Ghubrah PS
0 0 0 0 0 0 -0.00
0.00 55.00 0.00 0.00 -0.00
0.00 85.00 -0.00 -0.00 0 0 0 0 0 0 0 0 1.00 0.95 4 ~ ~ ~
GCCIA Interconnection
0.00 18.08 0.00 0.00 -0.00
0.00 27.94 0.00 0.00
0.42 0.41 0.00 0.00 0.42 0.41 0.41 3
0.00
0.00
7.00
2.30
-0.99
-47.85
G
0.84
G G
0.90
1.00 0.42 0.99 0 0 0 0 1.00 0.99 0.99 0.96 62.00
0.42 1.00 0.42 0.00 -6.24 64.00
41.49 1.00 -141.42 -140.95 1.00 -134.81 -134.08 67.06 41.13 26.00 30.16
-142.10 0.41 0.41 -136.20 7.99 84.60
-138.55 63.40
1.00 1.00 57.87
42.46 -138.77
0.90
33.12 0.84 0.96 62.00
1.00 64.00 26.00 30.16
1.00 41.13 7.99
-153.07 40.85 91.93
3.94 5 47.55 4 33.09 4 -0.93
-0.87 -0.97
11 48.69 133.51 -63.88 -25.97 -61.73
-1.00 1.01 -35.91 -6.77 -24.40
-40.71 -6.73 47.55 33.09 91.93
-1.07
48.69
Mawalleh North
0.00 MW
-0.00 .. 223.38 0.95 0.95 157.30
1.02 28.00 7.00 56.65
1.00 9.20 2.30 22.20
-13.35
-21.08
131.03 -10.25
0.99 4.49
-0.00 -10.82
-0.00
1.43
0.90
21.08 10
10.25
47.23
-0.95
10.94
0.99
-48.24
New Ghubrah
-21.00
-6.90
47.23 ~ ~
G G
0.89
0.89
1.00 94.00 94.00
0.00
-1.00 3 0.95 1.00 1.00 48.90 48.22
0.00 0.42 0.42 61.88 86.83 83.89 80.17 91.90 88.24 82.45 0.93 0.92 0.93
0 0 1.00 1.00 74.16 107.24 34.08
43.11 43.11 G G G G G G G 29.89 44.85 13.33
0.41
1.00
~ ~ ~ ~ ~ ~ ~ 110.25
44.86
32.15 -157.36
-68.96
0.92
106.23 13
0.93
36.13
45.93 28.92 -75.57
-18.73
-0.95 13 -0.95 -0.95
-138.20 20.72 -74.00 29.51 32.70 45.02 13.95 -107.00 -34.00 13.54
32.91 -24.32 0.99 46.25 1.00 30.81 13 9 -35.17 33.02 14 -11.18
1.00 -144.87 -0.95 0.00 33.12 33.20
32.15 45.93 1.00 28.92 1.01
-144.36 -106.00 -0.00 -0.95 1.00 -160.78
-34.84 0.00 -36.00 -143.11 -159.24
46.25 -11.83
30.81
1.00 1.00 3 1.00 1.00
0.00
-1.00 4 0.95 -1.00 -1.00 0.00
-1.00 3 0.95 -1.00 -1.00 -1.00 0.00
-1.00 -1.00 -1.00 0.00
-1.00 -1.00 -1.00
-0.00 -0.00 -0.00 0.95 -0.00 0.95
-0.00 74.00 -0.00 -0.00 -0.00 106.00 -0.00 -0.00 -0.00 0.95 -0.00 107.00 -0.00 -0.00 -0.00 -0.00 -0.00
0.00
-0.00 24.32 0.00 0.00 0.00
-0.00 34.84 0.00 0.00 0.00 36.00 3 0.00
-0.00 35.17 0.00 0.00 3 0.00
-0.00 34.00 0.00 0.00
0.00 0.00 0.00 11.83 0.00 0.00 11.18
0 0 0 0 0 0 0 0
0.41 0.41
1.00 0.99 0.42 0.42
0.42 1.00 1.01
-114.36 -114.87 1.00 -130.78 -129.24
-113.11
-84.24
-12.38 0.42 0.42
15.18 1.00 1.00
-120.58 -120.58
84.24 0.42 0 0
1.00 157.90 -1.00 -1.00 0.95 -1.00 -1.00
12.38 -0.00 -0.00 41.00
12.66 -110.96 70.48 -0.00
1.00 -0.00
1.00
29.51 0.00 0.00 13.48 0.00
0.00 0.00
0.00
3 0.00
-0.00 3 0.00
-0.00
0 0 0.00 0.00
-1.00 -1.00 0.95 -1.00
-0.00 -0.00 14.00 -0.00
1.00
0.00 0.00 4.60 0.00
0.00 -157.90
4 0.00 33.07 33.12
-0.00 1.00 -70.48 1.00
0.00 22.92 -0.95
-140.96 -150.58 -41.00
0.93
-13.48
41.12 170.93
-0.95 15 15.66
17.53
-14.00 59.32
-4.60 17.53 132.57 30.96
-169.99 75.76 52.22 -52.21
6.09
1.00
1.18 -56.37
30.96
16.62
13.54
130.48
0.99
132.46
129.39
0.98
26.61
10.26
-27.03
10.26
Daghmar 129.24
157.93 -0.58 -1.02
New Izki 15
0.92 132.85
67.84
22.92 -0.94 Amerat 1.00
1.03 Yitti Quriyat 0.98
-1.12
14.09 1.01 457.74 352.37 -326.27
0.90 103.12 11.10 0.93
6.01 9.59 -60.87 166.38 -120.36
326.76
6.09 34.74 29.70 20 158.21 44.26 1.12 0.92 11.10
217.27 36.81 19.55 1.48 4.46
0.99 36.81 94.24 -11.10 -102.35 0.93 0.89
39.76 4.77
5.81 -4.46 -45.86 50.13 52.21
-0.89 41.44 12 1.48
15
19.55
-0.95 12
19.25
-0.95
27.03
7
-278.44 -50.00 -52.00
106.42
69.52
17.04
0.85 20
-143.37
278.89
33.18
175.34 218.72 -0.97 Jahloot 32.76
0.99
-0.95
-94.00
-0.95
33.01
32.81
0.99
-153.12
22.04
-16.43
22.04
60.04
-17.09
60.04
11.03
1.00
-40.04
0.99 -1136.87
0.93 -154.61 -11.00
33.18 -30.90 -3.62 1.00
13.51 -263.72
1138.03 391.00 41.44 -149.40
20 441.03
62.43 0.98 4.77
62.43 13.68
-0.85 1.00 1.00 1.00 1.00
-278.89
0.81 17 0.00
-1.00 3 0.95 -1.00 -1.00 0.00
-1.00 3 0.95 -1.00 -1.00 0.95 0.00
-1.00 3 0.00
-1.00 3 0.95 1.00 1.00
-175.34
279.06 -0.00
-0.00 94.00 -0.00 -0.00 0.00
-0.00 11.00 -0.00 -0.00 50.00 0.00
-0.00 0.00
-0.00 52.00 0.00 0.00
34.03 406.16 0.00 0.00 0.00 0.00
203.74 1.02 -0.00 30.90 0.00 0.00 -0.00 3.62 0.00 0.00 16.43 -0.00 -0.00 17.09 -0.00 -0.00
34.03 17.06 -1138.03 0.00 0.00 0.00 0.00
-441.03 0 0 0 0 0 0
35.20
0.41 0.42
0.41 1.00
0.99 0.42 0.99
-123.12 -10.04
-279.06 -124.61 1.00
-203.74 -119.40
9.59
-106.41
106.41
-72.17
17.04
72.17
22.28
-84.19 -51.13 -60.04 51.38 129.25 -109.70 -105.71
-34.19
12.66
Bureimi 126.26
0.96
127.78
0.97
6.00
-19.63
19.33
128.41
0.97
6.36
-23.29
11.31
60.17
20.90
11.31
17.76
19.33
Nizwa 0.98
7.04
-45.41
20.72
-72.24
22.28
129.60
0.98
8.07
127.32
0.96
7.86
-27.12
Al Hayl Bahla Jebreen Mudhaibi Ibra
126.35 0.93 0.92 0.93 0.92 0.92 0.93
0.96 84.19 49.19 60.04 111.25 130.30 77.19
-16.13 34.19 20.52 23.29 47.36 57.41 31.44
38.18 -49.19 69.65 0.93 26.48 53.20 0.00 49.40 -166.30 58.01 -24.59 34.57 -77.19
-0.95 9 -20.52 -0.95 8 51.13 10 12 19.65 -3.05 10 -57.21 -0.95 11 14.83 10 -31.44
-84.00 9.52 -49.00 19.63 10.00 3.49 49.10 -130.00 5.83 14.76
22.63 32.75 32.70 32.97
-27.61 -16.11 32.70 32.95 32.69 0.99 -42.73 1.00
32.86 0.99 -0.95 1.00 -0.95 -0.95 0.99 -0.95
38.18 1.00 69.65 0.99 -147.50 58.01 -147.04 -145.30
-1.18 -51.00 -146.09 -60.00 -146.01 -111.00 -77.00
-169.61 -16.76 -19.72 -36.48 -25.31
22.63 26.48 49.40 34.57
0.93
53.14 228.43
20.96 1.04 0.95
23.41 0.95 52.39 0.92 -203.34 0.93 -66.05 24.43 322.90 12.00
-0.95 12 6.00 16.44 101.23
-0.95 12 -49.30 66.05 17 -25.92 111.29 3.94
-53.00 1.97 9.84 42.15
-101.00 32.71 36.69 25.92 11.87 24.56
-17.42 32.83 45.01
-33.20 0.99 27.79 33.11
23.41 0.99 45.01 -145.19 -0.95 1.00
-145.43 -66.00 -133.99
-21.69
27.79
0 0 0 0 0 0
0.41 0.41 0.42
0.99 0.99 ~ 1.00
-115.43 -115.19 G -103.99 -322.53
-111.75
227.21
0.85 1.03
24.56 23.73
231.00
145.44
75.04
-248.81
-104.15 210.22 0.94
0.96 322.53
20.97 111.75
-20.34
33.10
0.85
-0.90 0.95 17
-0.00 -52.20 -93.21 93.89 206.22 231.00 6.00 -76.04 76.36 -164.58 166.59 -255.78 255.81 66.25
Wadi Sa'a 0.92
248.81
104.15
-0.00
3.49
129.58
0.98
129.63
0.98
Adam -21.77
9.84
-38.22
17.42
35.12
17.42
61.27
36.69
133.39
1.01
13.61 8
-230.07
145.44
-113.04
78.47
78.47
1.97 14.68
13.32
-18.72
13.32
-17.57
28.03
22.00
28.03
-58.21
37.11
56.96
37.11
22.20
11.87
Sur-2 -0.97
-322.06
-52.00 37.88
0.93 0.93 0.94 -17.09 40.79 -0.95 37.37
127.73 75.07 64.15 31.12 32.90 32.81 -88.00 33.21
71.99 32.87 -0.95 0.99 -0.95 1.01
0.97 29.73 25.18 11.57 1.00 -93.00 -28.92 -89.00
0.94 -25.89 0.94 -146.83 1.00 -138.30 -133.89
33.16 28.17 26.78 -142.34 -30.57 37.88 -29.25
10.09 28.11 11 -0.95 11 -0.95 12 -0.95 11
3.79 10.59 40.79 37.37
33.01 -75.00 -64.00 32.93 -31.00
8.80 12 24.64 1.00 -24.65 32.99 32.80
-21.04 1.00 -10.19
-0.95 -0.95 1.00 0.99 1.00 1.00 1.00 1.00
-177.73 33.16 -176.56 28.17 4.46 26.78 0.95
-10.00 -28.00 -177.82 0.00
-1.00 3 0.00 3 0.95 0.00
-1.00 3 0.00
-1.00 3 -1.00 -1.00
33.03 -3.29 -9.20 0.95 -1.00 -1.00 93.00 -1.00 -1.00 0.95
-0.00
-0.00 52.00 -0.00 -0.00 0.00 30.57 -0.00 -0.00 88.00 0.00
-0.00 0.00
-0.00 89.00 -0.00 -0.00
1.00 8.80 24.64 0.00 0.00 28.92 0.00 0.00
0.00 17.09 0.00 0.00 0.00 0.00 -0.00 -0.00 29.25 0.00 0.00
-164.76
1.00
0.00
-1.00 3 0.95 -1.00 -1.00 -1.00 -1.00 0.95
1.00
0.00
-1.00 4
1.00
0.00
-1.00 3 0.95 -1.00 -1.00
1.00
0.00
-1.00 3 0.95
PDO 0.00
0 0
-1.00
-0.00
-0.00
0 0
0.00 0.00
0 0
Page | 205
Five-Year Annual Transmission Capability Statement (2017-2021)
DIgSILENT
Sohar Aluminum PS
~ ~
Sohar-1 PS G
0.02
0.36
-16.71
G
0.00
-0.00
Sohar-2 PS Barka-2 PS Barka-1 PS Barka-3 PS 0.42
1.00
-124.13
0.41
1.00
-123.87
0.42
1.00
-115.79
0.42
1.00
-115.77
0.42
1.00
-119.88
0.42
1.01
-120.78
3.71 6.44
~ ~ 2.15 ~ ~ ~ ~ ~ ~ ~ ~ ~ ~
G G G G G G G G G G G G
-447.13
0 0 0 0 0 0 0 0
349.28
122.20
0.96
-65.61
28.03
33.60
249.53 0.91 0.88 0.89 0.86 0.95 0.96 0.95 -1.00 -1.00 0.95 -1.00 -1.00 0.95 -1.00 -1.00 -1.00 0.95 -1.00 -1.00 -1.00 0.95 -1.00 -1.00 0.95 -1.00 -1.00
0.86 0.81 0.85 0.88 0.90 329.10 226.50 226.50 220.70
336.90 196.60 226.50 226.50 129.85 286.00 192.40 196.60 66.15 68.10 -0.00
1.00 -0.00
1.00 124.00 -0.00 -0.00 107.20 -0.00
1.00 -0.00 -0.00 114.40 -0.00
1.00 -0.00 -0.00 86.00 -0.00
1.00 -0.00
1.00 99.30 -0.00 -0.00
-0.00 230.00 146.80 151.41 100.64 115.72 73.81 62.42 22.38 -0.00 -0.00 40.76 0.00 0.00 35.23 -0.00 0.00 0.00 37.60 0.00 0.00 0.00 28.27 -0.00 0.00 32.64 0.00 0.00
202.02 144.51 -0.01 141.75
0.85 124.49 110.79 20.65 -349.28 447.13 67.76 0.00 0.00 0.00 0.00 0.00 0.00
0.02 -0.00 68.64 79.75 68.28 81.47 74.21 73.19 3 0.00 3 0.00 3 0.00 3 0.00 3 0.00 3 0.00
73.15 88.73 -0.13 6.44 10 83.24
226.50 80.52 75.09 -122.20 65.61 0.00 0.00 0.00 -0.00 0.00 -0.00
0.36
17.64 39.14 48.65 0.95 0.00 0.00 0.00 0.00 0.00 0.00
-16.71 10 0.02
2.22 141.75 -249.53 226.50
4.08 0.13 84.16 0.96 0.96
4.08 -129.85 73.81
-5.86 226.50 220.70
22.15 0.91 0.88 0.89 0.86 15 75.03 66.15 33.04 -0.95 -0.95 -0.95 -0.95
2.22 329.10 286.00 192.40 196.60 62.42 32.85 -107.20 33.10 -114.40 33.04 -86.00 -99.30
0.88 0.90 65.31 1.00 33.05 33.19
20 146.80 151.41 100.64 115.72 74.00 1.00 -35.23 1.00 1.00 -37.60 1.00 -28.27 -32.64
226.50 230.00 -154.13 -153.87 -149.88 1.01
0.86 0.81 69.63 80.90 68.28 81.47 -0.95 -0.95 45.71 -145.79 -145.77 48.76 37.12 43.14
336.90 196.60 238.33 124.49 110.79 -68.10 -124.00 -150.78
81.40 72.36 -0.95 15 -0.93 15 -0.92 15 -0.91 15 -0.98 17 -0.99 17 -0.98 0.92 0.92 12 14 0.93 12 0.92
202.02 144.51 1.08 213.96 -347.57 349.37 -447.00 -328.55 -286.00 -192.08 -196.25 -192.62 -22.38
68.33 -40.76
124.29 86.19 -87.07 99.52
15 12
69.84
-0.90
15 88.53
-0.87
17
29.99 1.00
0.00
0.00
0.00
-11.78
2.38
1.00
0.00
0.00
-0.91 17 -0.93 16 -0.94
0.97
1.42
-117.30
28.03
73.90
39.14
Blue City -112.69
48.65
219.41
1.00
4.83
-109.17
69.63
-112.14
80.90
-81.37
68.28
-91.56
81.47
-226.02
-44.57
75.03
-226.01
-33.93
74.00
-220.21
-41.18
65.31
-83.21
28.11
131.38
1.00
0.94
59.92
29.70
59.92
54.38
53.51
54.38
0.00
0.00
0.00
0.92 0.92
34.91
37.12
132.27
1.00
3.55
-37.67
16.18
8 41.87
43.14
61.59 -61.46 -336.34 -196.17 -0.00 249.55 107.44 114.66
132.83
1.01
Shinas 21.90
11.30
132.00
1.00
-24.42
11.30
-161.97
69.84
-111.58
88.53
0.00
2.38
-226.03
-105.41
84.16
223.76
1.02
-226.03
-90.38
81.40
-229.52
-80.56
72.36
103.23
22.15
MIS 45.50
45.71
Mawalleh South-A 48.46
48.76
Al Falaj
-2.41 -3.06
Madinat Shinas 2.18 0.84
367.79
238.40
224.27
1.02 596.34
230.93
1.05
0.93
91.27
37.22
348.96
35.91
134.79
1.02 132.16
9.14 1.00
229.50
1.04
-20.22
-121.10
9.38
45.07
20
0.93
97.63
38.78
0.95
6.00
1.97
0.95
25.00
8.22
595.56
214.05
46.22
212.59
46.18
0.95
6.00
1.97
13.79 0.95
6.00
1.97
38.28 28.56
-348.82
Seeb Main Mawalleh South-B -222.10
-93.96
31.49
8.62 -63.47
-23.21
23.05
Wadi Adai 64.35
25.97
11.86
-64.34
-26.24
11.86
3.47
-35.19
-15.63
12.82
-113.53 0.93 0.93 2.60 573.30 0.95 0.95 148.25 0.95 0.95 128.61 32.96 13 32.92 17 -133.67
-42.34 51.94 14 61.46
-0.95 13 155.16 6.00 31.00 211.64 200.00 6.00 0.97 -0.88 1.00 -0.95 -0.95 28.56
20.57 20.44 24.42
-61.30 31.06 1.97 10.19 21.60 65.74 1.97 -3.58 -367.35 -97.40 -91.00 33.03
-148.34 1.00 348.82
33.10 22.19 26.45
-20.15 -194.14 -32.01 -29.91
1.00 -0.95 33.18 137.03 -139.97 133.67
26.45 1.04 45.07 32.92 38.28 27.08
-154.50 -51.80 1.01
-17.03 -155.50 -0.01 129.82 134.95
22.19 1.00 0.98 -595.96 1.00 223.98 1.02 132.20
0.00 -0.06 -209.27 0.00 1.02 1.00
1.00 1.00
0.93
59.34
-0.95 11
237.18
73.06
70.83
97.98
-1.00
-0.00
-0.00
3 0.95
97.40
-1.00
-0.00
-1.00
-0.00 Madinat Barka 46.18
-1.00
-0.00
-1.00
-0.00
0.95
91.00
-1.00
0.00
-0.00
3
9.87 Misfah 8.60
3.49 Wadi Kabair
27.08
-131.59
-346.91
23.10 43.57 21.42 0.00
0.00 32.01 0.00 0.00 0.00 0.00 29.91 0.00
0.00
-1.00 -1.00 0.95 0.00
-1.00 3 -1.00 -1.00 0.95 0.00
-1.00 3 -59.20 0.94
-0.00 -0.00 26.29
-19.46 32.91 0.00 595.96 0.00
-0.00 -0.00 51.80 -0.00 -0.00 -0.00 61.30 -0.00 1.00 0 0 209.27 0 0 33.51
0.00 0.00 17.03 0.00
0.00 0.00 0.00 20.15 0.00
0.00 26.29 12.60
-0.00 0.00 MW -156.04 229.14 0.93 0.93 -315.69 49.92 367.95 -86.88 491.68 -0.91 -33.51 -146.16 0.93 0.93 -2.28
0.00 0.00 14.03
0 0 0 0 0.00 -0.00 .. 0.41 38.18 49.43
-0.95 8 37.12
-0.95 8 -72.03 0.42 146.70 31.06 146.04 -425.84
0.88 19 -12.60 16 -51.33 65.45 14 82.99 12 -7.79
-148.23 1.00
1.30 1.00 -238.79 40.47 19.35
-49.30 14.49
-37.00 56.25 1.00 29.17 7.69 37.55 -192.21
426.07 5.98 45.10 25.55 33.57 2.70
0.42
1.00
0.42
1.01
21.60
1.00
-118.34 33.13
1.00
21.60
-16.20
21.60
33.24
1.01
-151.49
16.21
-12.16
16.21
Barka IPP -109.97
402.78
1.01
13.52
32.07
230.55
32.07
33.08
1.00
-0.95
28.06
-0.95
32.85
1.00
35.75
-0.95
33.05
1.00
0.00
-1.00 3 0.95 -151.97 -33.40 -65.30 -149.08 -82.80 -149.90
-124.50 -125.50 -0.00 -142.71 -10.98 -21.46 -27.22
148.23 -0.00 59.20
238.79 0.00
-0.00 19.46 -595.92 14.03 28.06 35.75
20.96 0.00 -215.56
1.00 1.00 49.92 1.00 1.00 1.00
0.41 0.00
-1.00 3 0.95 -1.00 -1.00 0.00
-1.00 3 0.95 -1.00 -1.00 -426.07 0.00
-1.00 3 0.95 0.00 MW 0.00
-1.00 3 0.95 -1.00 -1.00 0.00
-1.00 3 0.95 -1.00 -1.00
-0.00
-0.00 -0.00
-0.00 595.92 -0.00
-0.00 0.00
-0.00 -0.00
-0.00
17.21 -249.40 1.00 49.30 -0.00 -0.00 37.00 -0.00 -0.00 215.56 -230.55 33.40 0.00 Mvar 65.30 -0.00 -0.00 82.80 -0.00 -0.00
0.00
0.00 16.20 0.00 0.00 0.00
-0.00 12.16 0.00 0.00 13.56 0.00
0.00 1.00 0.00
-0.00 0.00 0.00 0.00
-0.00 0.00 0.00
12.78
2.25
-130.61
20.65 Sohar Refinery -126.04
0.00
0.42
0 0
0.00
0.42
0 0
46.41
0.42
0.00
10.98
0.41
0.00
21.46
0 0
0.00
0.42
27.22
0 0
-2.28
-4.57
1.74
2.28
OCC 4.47
1.74
-2.28
-4.47
1.67
146.19
222.80
17.21
8.26
-249.40
-135.00
0.95
270.00
88.74
-573.22
-198.90 229.22
-147.47
-243.89
222.31
1.01
1.67
-17.20
-25.27
20.55
86.28
448.94
75.67
-594.53
-205.06 222.42
Rusail PS 48.84
45.10
1.04 -146.19
1.01 1.69 22.41 31.06 20.96 2.25 9.38 33.60 46.22 -595.35 1.01 ~ ~ ~ ~ -48.84
1.77 2.40 -210.54 8.08 G G G G
46.41 0.93
219.30
0.92
225.60
98.20
0.89
85.90
0.96
84.80
25.14
Hamriyah 217.15
0.99
52.57
Muttrah
0.88 0.94 0.82 0.96 85.91 43.13
77.56 75.60 8.87
-119.22
57.31 64.08
119.22
-31.69
21.03
31.69
16.97
232.19 303.22 298.36 483.01
126.74 110.15 209.90 140.32
26.12
18
20.64
16
-154.24
-27.02
36.10
-0.85 20
Sohar 49.75
16
257.93
199.61
0.93
219.30
0.92
225.60
0.89
85.90
0.96
84.80 0.91
113.87 -281.54 281.79 0.00 11.51 -298.01 -167.58 168.33 -236.60 -73.27 -91.73 91.80 73.45 317.23 24.14 192.99 85.91 98.20 3 43.13 25.14 33.53 437.27 -437.25 222.51 365.20 63.51 146.29 119.27 -119.16 2.28 35.20
41.85 134.06
1.02
-109.44 110.76 SFZ -0.90
-10.12
-0.95 Sohar Industrial Area (SIA) -181.12 Interconnection SS -40.29 126.35 42.81 -70.22 127.75
130.35
0.99
-29.11 25.40
131.45
1.00 Barka Main -25.80 27.05 80.55
-0.99 Al Filaj 131.75
1.00 53.82 3 58.15
-0.95
59.43 4
-0.94
69.91
-0.93
3 70.53
-0.98
10.86 150.65
65.93
-152.32 Rusail Industrial 67.08 135.16
1.02
-365.20
-161.96
-0.95 20
161.96
-364.67 23.03 49.15 31.65 -45.29 3.40 9.23 132.31
20.57
-1.46
Liwa
50.82 50.82
-231.93
1.30
-302.87
36.10
Khadra
30.76 0.96
-5.91
30.76 43.57
Suwauiq 0.97
-4.38
0.82
Nakhal
13.64 16.37 1.32 16.37 13.64 56.25
-482.48 1.09
A'salam
28.11
-218.94 -225.26 -85.69 -84.59
5.98 65.93 31.49
8.77 30.07 40.53
-117.42 23.05 52.57 21.03 16.97 1.67 12.82
Qurum
1.00
3.57
-110.61
26.12
-94.37
20.64 (SIS) -81.80
49.75
-69.48
58.15
-82.71
59.43
-34.00
69.91
-16.91
70.53
40.53
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
0.00
-1.00 3 0.00
-1.00 3 -1.00 -1.00 0.00
-1.00 3 -1.00 3 0.00
-1.00 3 0.00
-1.00 3 0.00
-1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.95 -1.00 -1.00 -1.00 -1.00 0.95 0.95 1.00
-0.00 0.95 0.95 -1.00 -1.00 0.95 -1.00 -1.00 -1.00 -1.00 0.95 0.41 3 -1.00 -1.00 0.95 -1.00 3 -1.00 3 0.95 -1.00 -1.00 -1.00 3 0.95 1.00 1.00 0.95 -1.00 3 0.95 -1.00 3 0.95 -1.00 3 -1.00 -1.00 0.95 -1.00 3
0.00
-0.00 99.80 -0.00 -0.00 -0.00 -0.00 58.90 -0.00
-0.00 -0.00 -0.00 72.70 0.00
-0.00 0.00 72.70 0.00
-0.00 54.00 -0.00 -0.00 0.00
-0.00 69.30 -0.00 -0.00 -0.00 -0.00 68.10 -0.00
-0.00
0.99 -0.00 -0.00 73.10 0.00
-0.00 -0.00
-0.00 116.90 -0.00 -0.00 0.00
-0.00 110.80 0.00 0.00 98.00 -0.00
-0.00 76.30 0.00
-0.00 81.50 0.00
-0.00 -0.00 -0.00 103.80 0.00
-0.00
0.00
0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00
-0.00 0.00
-0.00 0.00
-0.00 0.00
-0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
-0.00 0.00
-0.00 0.00
-0.00
32.80 0.00 0.00 0.00 0.00 19.36 23.90 0.00
0.00 23.90 17.75 0.00 0.00 22.78 0.00 0.00 0.00 0.00 22.38 -127.16 0.00 0.00 24.03 38.42 0.00 0.00 36.42 0.00 0.00 32.21 25.08 26.79 0.00 0.00 34.12
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
-257.65 -490.63
220.79 -199.89 221.95
1.00 24.14 -138.84 1.01
7.61 37.55 8.49
0.87 0.95
445.46 302.56
250.95 94.19 ~
0.96
43.35 -43.30 -64.89 135.82 -135.01 46.99 -43.88 -70.61 -226.72 127.23 150.18 -149.12 25.52 305.14
50.95
20
-187.81
-51.05
14.41
188.07
44.65
14.41
31.41
-0.97 17
-302.25
0.95
25.00
0.41
1.00
G
46.80
14.46
54.43 Ghubrah PS
133.52
1.01
-15.11
7.75
12.73
7.75
133.67
1.01
-55.42
14.40
-231.03
-117.65
44.66
Saham 130.92
78.18
27.29
-76.34
27.29
39.93
11.35
-46.82
-43.05
11.35
5.95
8.01
Khaborah -98.03
21.42
-26.86
40.47
Muladah 0.96
-3.90
65.71
29.32
-62.46
29.32
Rustaq 73.91
13.58
66.90
42.83 -0.92 Mobella 133.41
1.01
-69.70
31.41
Airport Height 8.22 133.33
1.01
-113.41
~ ~
-2.09 0.99 -444.92 G
0.92 G
0.86
Sohar Uwaynat -2.49 -4.33 DAS 126.37
0.96
-6.55
-189.70
50.95
4.35 4.32
Ghala -1.00 0.95
0.96
46.80
14.46
-0.98
62.40
26.09
24.10
14.04
0.93 0.93 0.93 0.93 0.92 0.92 0.93 0.92 0.92 0.92 -0.00
1.00 7.00 56.36 59.34
0.00 2.30 4 66.64
-46.65
73.89 74.47 54.35 53.85 95.21 128.15 88.02 90.70 124.35 149.12 114.26 132.41 85.01 0.00
3 0.00
-0.00 -9.56
29.96 29.53 21.45 21.24 39.47 0.97 36.41 37.10 0.94 62.46 48.89 1.00 34.94 66.64
31.53 31.68 -191.70 23.08 22.86 41.80 -5.88 39.25 40.94 0.93 0.93 -6.01 45.76 49.84 1.40 90.18 0.92 85.05 -85.01 36.39 0.00
-0.95 13 -0.95 13 -44.37 -0.95 15 -0.95 15 -0.95 12 -0.95 11 6 72.68 74.47 -0.95 8 -0.95 12 -0.12 102.03 13 18.88 -34.94 -0.95 13 0.92 0.86
-73.70 -74.30 33.24 -54.20 -53.70 -95.00 32.77 -87.80 29.43 29.75 -148.80 -114.00 12.88 42.72 12.13 12.13 -84.80 62.40 24.10
32.92 32.54 9 33.47 10 32.81 32.96 44.02
33.05 -24.22 -24.42 33.09 32.91 -17.81 -17.65 -31.22 0.99 -28.86 33.02 -48.91 1.00 -37.47 32.96 -27.87 26.09 14.04
1.00 -0.95 -0.95 -0.95 0.99 -0.95 32.92 0.98 42.27 33.93
1.00 31.53 31.68 1.00 1.00 23.08 22.86 41.80 -158.27 32.70 39.25 1.00 45.76 -153.25 49.84 1.00 1.00 36.39 32.89 5 5
-154.67 0.99 -90.50 32.99 -72.50 -74.30 -159.92 -149.82 -101.80 1.00 39.65
-0.99 -0.94 -0.88
24.88 -155.04 -154.69 -160.20 32.79 -149.10 -62.31 -24.07
-159.46 -29.75 1.00 -23.83 -24.42 -33.46 -143.41 7.26
-39.52 135.38
40.94 32.54 33.47 0.99 44.02 13 48.16 1.03 -21.97 -12.76
23.11 -157.00 -4.46
48.16 2.98 42.27 33.93
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
0.00
-1.00 3 0.95 1.00 1.00 0.00
-1.00 3 0.95 -1.00 -1.00 0.00
-1.00 3 0.95 -1.00 -1.00 -1.00 -1.00 0.95 0.00
-1.00 3 0.95 0.00
-1.00 3 -1.00 -1.00 0.95 0.00
-1.00 3 -1.00 -1.00 0.95 0.00
-1.00 3 -1.00 -1.00 0.95 0.00
-1.00 3 0.00
-1.00 3 0.95 -1.00 -1.00 -1.00 -1.00 0.95 0.00
-1.00 3 0.00
-1.00 4 0.95 -1.00 -1.00
-0.00
-0.00 73.70 0.00 0.00 0.00
-0.00 74.30 -0.00 -0.00 -0.00
-0.00 54.20 -0.00 -0.00 -0.00 -0.00 53.70 0.00
-0.00 95.00 -0.00
-0.00 -0.00 -0.00 87.80 0.00
-0.00 -0.00 -0.00 90.50 0.00
-0.00 -0.00 -0.00 148.80 0.00
-0.00 0.00
-0.00 114.00 -0.00 -0.00 -0.00 -0.00 101.80 0.00
-0.00 -0.00
-0.00 84.80 -0.00 -0.00
0.00
0.00 24.22 0.00 0.00 0.00
-0.00 24.42 0.00 0.00 0.00
0.00 17.81 0.00 0.00 0.00 0.00 17.65 0.00
-0.00 31.22 0.00
0.00 0.00 0.00 28.86 0.00
-0.00 0.00 0.00 29.75 0.00
-0.00 0.00 0.00 48.91 0.00
0.00 0.00
-0.00 37.47 0.00 0.00 0.00 0.00 33.46 0.00
-0.00 0.00
0.00 27.87 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 -1.00
1.00 3 0.95 1.00 1.00 -1.00
1.00 3 0.95 -1.00 -1.00 0.00 0.00 0.00 0.00 0.95 118.89
0 0 0 0 0 0 0 0 0 0 0 0 -0.00
0.00 72.50 0.00 0.00 -0.00
0.00 74.30 -0.00 -0.00 0 0 0 0 0 0 0 0 7.00 36.89
GCCIA Interconnection
0.00
-0.00 23.83 0.00 0.00 0.00 24.42 0.00 0.00 2.30 16.33
0.42 0.41 0.41 0.41 0.42 0.00 0.00 0.41 0.41 0.41
1.00 1.00 1.00 0.41 0.99 1.00 0 0 0 0 0.99 1.00 1.00
0.42 0.99 0.41
54.88 1.00 -124.69 -124.67 -129.46 -130.20 -129.92 1.00 -119.82 -119.10
-128.27 0.41 0.41 -123.25
-125.04
1.00 0.99
53.11 -127.00
New Ghubrah
~ ~
G G
Mawalleh North 0.81
85.80
0.86
86.10
0.00 MW 61.47
0.00 Mvar 224.08 50.64
88.32 83.59
1.00 1.02
3.54 0.81 0.86
0.95 85.80 86.10
-90.09 -164.68 164.73 40.00 61.47 -118.88 50.64
133.24 -37.17 -78.02 64.65 13.15 4 65.97 -40.45 3 62.43
-0.90
1.01 12.88 135.30 15.80 15.80 -0.85 16.33 -85.97
1.02 -85.65
-0.00
-0.00
1.44
4.26
2.94 Bousher -52.70
65.97
-42.78
62.43
0.92 0.92 0.92
123.39 127.90 129.13 133.24
52.88 56.19 135.36
0.92 -86.61 1.03 56.42 -129.33 85.97 1.01
52.39 54.82 54.97 4.08
90.09 14 -31.06 14 14 2.97 13 -41.06 42.78
37.17 23.94 17.64 26.56
38.62 32.87 33.10
-0.95 1.00 1.00 -0.95 -0.95 -0.95 33.04
32.78 1.00
-89.90 -149.28 -151.76 -123.10 -127.60 0.99 -128.80
-29.55 -40.46 -41.94 -152.30 -42.33 -151.95
38.62 52.39 54.82 54.97
0.42 0.41
0.41 1.00 0.42
1.00 0.99
-121.76 -122.30 1.00
-119.28 -121.95
0.00 154.65 -371.69
-19.67 6.94 -34.46
1.44 11.51 27.27 86.66 129.42 -85.87
25.10 21.91 -51.92
223.72 23.94 17.64 26.56
1.02
3.55
-86.66 -129.42 85.87
-25.10 -21.91 51.92
0.98
Wadi Al Jazzi 30.05 21.85 34.06
133.92
34.67
-0.99 17
-216.83
Mahadha
-145.01 145.88 32.43 -32.33 123.14 193.01 0.00 MW
1.01
-1.18 Bureimi Industrial -34.13
25.09
35.06
25.09
-35.67
34.67
135.87
1.03
-9.94
9.21
5.18
9.21
28.26
21.14
48.92
33.24
0.00 Mvar
1.00
135.77
1.03
0.24
0.86
0.93
54.45
21.57
23.09 15
-0.95
90.56
12.56
15.40
10.90
-0.52
1.93
0.93
27.62
11.06
48.17
-0.95
7
33.22
1.01
0.95
7.00
2.30
-0.89
-15.92
-7.95
-0.98
-50.78
-9.92
64.53 13 72.09 12
-0.95
-50.59
-17.36
69.18 7
-0.96
-25.50
-7.25
-0.94
-57.97
-20.59
66.18 12 73.00 6
-0.97
-28.30
-7.38
-0.97
-61.77
-14.23
66.56 13 72.11 13
2018 Max. load Flow Condition -366.88
-143.33
29.17
220.69
1.00
8.14
0 0
0.00 0.42
1.01
0.42
1.01
~
58.32 ~
76.37 ~
76.91 ~
72.59 ~
81.91 ~
79.87 ~
70.16 0.93
54.43
0.93
75.77
0.93
74.57
57.75 57.75 21.41 30.01 29.45
0.41 86.90 22.99 -154.59 0.92 0.93 31.74 31.22 -69.87
1.00 54.68 -0.95 15 -90.47 101.42 13 47.66 -0.95 -0.95 -13.10
-123.46 17.64 -54.30 30.07 33.09 42.49 19.06 -75.60 -74.40 12.08
33.10 -17.85 1.00 43.65 1.00 40.43 14 10 -24.85 15 -24.45
1.00 22.99 -147.16 -0.95 0.00 32.88 31.74 31.22
-145.09 -101.20 0.00 -0.95 1.00
-33.26 0.00 -47.50 -146.48
43.65 -15.61
40.43
1.00 1.00 3 33.23
1.00 1.00 33.25
0.00 0.00 1.01
0.00 0.00 1.01
-1.00 4 0.95 -1.00 -1.00 -1.00 3 0.95 -1.00 -1.00 -1.00 -1.00 0.95 -1.00 -1.00 -1.00 -1.00 -1.00
-149.72
0.00
-0.00 -0.00
-0.00 -0.00 -0.00 -0.00 0.95 -149.79
-0.00
-0.00 -0.00
-0.00 0.95
54.30 -0.00 -0.00 101.20 75.60 -0.00 -0.00 -0.00 -0.00
0.00
-0.00 17.85 0.00 0.00 0.00
0.00 33.26 0.00 0.00 -0.00 47.50 3 0.00
-0.00 24.85 0.00 0.00 3 0.00
-0.00 74.40 0.00 0.00
0.00 0.00 0.00 15.61 0.00 0.00 24.45
0 0 0 0 0 0 0 0
0.42 0.42
1.00 1.00 0.42 0.42
0.41 1.01 1.01
-115.09 -117.16 1.00 -119.79 -119.72
-116.48
-90.56
-12.58 0.42 0.42
1.00 1.00
427.41
101.61
15.40
13.56
-115.35 -115.35
0
12.58 1.00 155.16 -101.61
12.87
Ibri IPP 0 0
-113.51 92.02
30.07
12.11
-0.00
0.00
-0.00
0.00
42.20
13.87
3
-0.00
1.00
0.00
0.00
0.00
-0.00
0.00
3
-0.00
1.00
0.00
0.00
0.00
-0.00
0.00
-1.00 -1.00 0.95 -1.00
-0.00 -0.00 37.70 -0.00
1.00
0 0.00 0.00 12.39 0.00
0.00 -155.16
~ 4 0.00
-0.00
32.96
-92.02 33.11
G 0 0.00
1.00
-143.51 23.33
1.00
-145.35
-0.95
0.97 -42.20
0.93
860.00 -13.87
42.32 184.45
200.75 -0.95 17 16.14
17.71
-37.70 63.43
70.65 -12.39 17.71 135.51 32.64
-183.41 70.02 52.22 -52.20
15.89
1.03
133.31 132.49
Daghmar
-176.51
-150.57
-176.01
-215.95
150.57
176.51
7.68
7.68
860.00 32.64 12.08 135.39 9.80 9.80
155.18 4.64 4.30 132.35
200.75
67.93 176.01
215.95
New Izki 17
0.93 136.16
89.25
23.33 -0.94 Amerat 1.03
6.31 Yitti Quriyat 1.00
4.21
15 37.81 1.03 87.06 366.65 -344.29
0.90 105.40 12.10 0.93
7.68 14.77 -57.59 167.63
7.99 -122.72
344.79 41.83 1.32 12.10
-0.99 15.89 7.69 30.07 221.93 20 162.65
37.84 0.92
-858.04 176.51 19.32 1.57 113.40 4.80
1.01 37.84 -12.10 5.08 -104.65 0.93 0.91
-110.99 -150.79 11.14 49.35 -4.80 -43.86 52.43 52.20
67.93 6.34 413.04 -0.85 49.05 13 1.57
17
19.32
-0.95 14
20.20
-0.95 12
24.11
-284.36 -52.30 -52.00
1.03
17.27
225.59
0.80 20
-178.44
284.84
34.75
213.20
91.36
74.42
15.47
-0.95 Jahloot 32.90
1.00
-0.95
-113.10
-0.95
33.00
32.82
0.99
-147.89
22.52
-17.19
22.52
38.23
-17.09
38.23
10.91
0.99
-32.01
0.93 1.03 -798.51
0.91 -150.14 -12.00
34.75 -37.17 -3.94 1.00
669.53 11.76 -272.69
799.09 397.10 49.05 -144.16
0.95 20 364.56
44.24 0.99 5.08
257.83
46.32 12.00 44.24 16.46
-0.96 3.94 -0.80 1.00 1.00 1.00 1.00
376.11 -669.04 -176.01 -284.84
0.76 20 427.42 0.00
-1.00 3 0.95 -1.00 -1.00 0.00
-1.00 3 0.95 -1.00 -1.00 0.95 0.00
-1.00 3 0.00
-1.00 3 0.95 1.00 1.00
40.74 19 -182.29 -216.16 101.41
-213.20
285.04 0.00
-0.00 113.10 -0.00 -0.00 0.00
-0.00 12.00 -0.00 -0.00 52.30 0.00
-0.00 0.00
-0.00 52.00 0.00 0.00
27.27 46.32 7.68 36.80 409.20 12.11 0.00 0.00 0.00 0.00
245.92 1.02 0.00 37.17 0.00 0.00 -0.00 3.94 0.00 0.00 17.19 0.00 -0.00 17.09 -0.00 -0.00
36.80 15.37 -799.09 0.00 0.00 0.00 0.00
-364.56 0 0 0 0 0 0
24.94
0.41 0.41
0.41 0.99
1.00 0.41 0.99
229.71 -117.89 -2.01
292.94 -536.44 -120.14 1.00
141.55 1.04 -131.17 -114.16
23.55 11.81 15.22
536.45
130.98
-536.45
-130.98
-150.73
-540.51
540.51
150.73
15.22
15.37
15.37
15.37
0
0
0
-77.21 24.94
15.47
133.79 0.93 0.92 0.93 0.92 0.92 0.93
1.01 90.50 47.28 63.45 117.57 88.09 81.40 -804.83
-1.25 37.05 19.51 24.70 50.42 36.23 33.37 -262.29
38.81 -47.28 63.62 0.93 -30.83 27.16 55.70 0.00 51.14 -172.92 -40.09 39.06 -48.00 36.89 -81.40 23.19
-0.95 13 -19.51 -0.95 11 53.24 12 -39.29 14 20.64 -3.19 11 -12.24 91.35 -61.78 -0.95 11 9 -33.37
77.21 25.55
-90.30 8.70 -47.10 20.50 8.51 10.25 3.56 47.36 12.90 -87.90 10.23 15.76
23.07 33.04 20.65 32.89 32.96
-29.68 -15.48 33.09 32.90 32.92 1.00 -28.89 1.00
33.17 1.00 -0.95 1.00 -0.95 -0.95 1.00 -0.95
38.81 1.01 63.62 1.00 -148.77 39.06 -147.84 -147.24
29.80 -53.10 -147.28 -63.40 -146.93 -117.30 -81.20
-154.92 -17.45 -20.84 -38.55 -26.69
23.07 27.16 51.14 36.89
Sinaw
0.96 0.98 -1.00 0.96 0.91 0.96
74.10 162.00 -1345.34 1083.50 -0.95
492.13 -0.99
138.50
20.18 31.46 -111.22 305.98 -491.17
219.27 -138.50
38.15
-55.65 173.66 -90.43 40.29 48.24 127.33 81.69
131.68
1.00
-22.00
10.25
14.30
47.36
132.91
1.01
4 56.89
-0.98
10 55.58
-0.99
130.96
0.99
6.07
-78.73
20.65
59.02
12.90
-31.76
10.23
Mudhairib 0.96
7.17
31.69
15.76
136.44
1.03
14 35.42
0.99
-0.98
15 69.28
-1081.06
-189.62
16 -166.63
64.91
64.91
15 -24.26
69.07
69.07
7.51 -73.95 -161.64 1345.80
5.63
Madinat Nizwa -14.94
56.89