You are on page 1of 225

Five-Year Annual

2017
Transmission
Capability Statement
(2017-2021)

Issue: May 2017

As Approved by the Authority for Electricity Regulation


Five-Year Annual Transmission Capability Statement (2017 - 2021)

Preface
This Transmission Capability Statement is provided by the Oman Electricity Transmission
Company according to Transmission and Dispatch Licence Condition number 27 and the Grid
Code (Planning Code). The Statement describes in detail the MIS and Dhofar transmission systems
capability over the coming five years 2017-2021. The Statement provides up-to-date transmission
system data in order to identify those parts of the system, which offer the opportunity for future
development of existing and potential users of the system.
In this Capability Statement, the results of load flow and short circuit analysis are presented based
on the planned system expansion reinforcement to meet the generation plan provided by Oman
Power and Water Procurement Company and the demand forecast provided by the Distribution
Companies (MEDC, MJEC, MZEC and DPC). The OETC grid model has been updated to include
new projects schedule, demand foecast, generation data and transmission system data. Total of 68
transmission projects at MIS and Dhofar are planned over the five years period. Most of projects
are designed to increase the transmission system capacity so that it can meet future growth in
demand and satisfy the security criteria.
The existing and planned development in the generation and transmission system is described,
including the compeletion of 400kV transmission network to connect the 2000MW Sur power
plant in 2017. This is in addition to the introduction of three new power plants at Ibri in 2018 with
capacity of 1508MW, at Sohar in 2019 with capacity of 1708MW and at Misfah in 2021 with
capacity of 1000MW. In addition, Salalah 2 IPP Power Plant is expected to be in service in 2018
and it will be connected to Dhofar transmission system. Also, the first 50 MW Wind Farm project
in the Sultanate of Oman will be connected to Dhofar transmission system in 2019.
It is one of OETC’s strategic planning concepts to introduce the 400kV system as a backbone to
allow the power evacuation from the centralized power plants. Major developments in the MIS
transmission system include the installation and operation of new 400kV transmission lines with
associated new 400/220kV and 400/132kV grid stations. In addition, the developments include the
installation of 220kV and 132kV transmission lines with associated new 220/132kV and 132/33kV
grid stations at MIS and Dhofar systems. The OETC strategy to operate the 400kV as backbone,
220kV as transmission and 132kV as subtransmission systems.
OETC has made an effort in reveiwing and updating the Transmission Secuirty Standard to cover
the recent development in generation, 400kV Transmission System and Renewable Energy. The
Authority for Electricity Regulation has granted the approval of the second edition of the
Transmission Secuirty Standard in July 2016.

Eng. Ali Said Al Hadabi


Chief Executive Officer
Oman Electricity Transmission Company

Page | 1
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Contents
Preface 1
List of Figures 5
List of Tables 7
Document History and Status 8
Distribution of Copies 8
Glossary 9
1. Executive Summary 0
2. Introduction 22
2.1 Licence conditions, Codes and Standards 22

2.2 2017 System Development since the 2016-2020 Statement 22


2.3 Improvements in the preparation of the Statement 23

3. Technical requirements for compliance with the Grid Code and Licence 24
3.1 System Frequency 24
3.2 System Voltage 25

3.3 Security of Supply 26

4. OETC System Design and Planning Standards 27


4.1 Oman Electrical Standard OES 11 27
4.2 Oman Electrical Standard OES 25A and 25B 27

4.3 Oman Electrical Standard OES 27 27


4.4 Oman Electrical Standard OES 32 27

4.5 Other Standards 27

5. OETC Transmission System 28


5.1 Existing Transmission System 28

5.2 Future System Development Projects 31

5.2.1 Projects completed to meet the 2017 peak demand 31

5.2.2 Projects expected to be completed to meet the 2018 peak demand 32


5.2.3 Projects expected to be completed to meet the 2019 peak demand 33

5.2.4 Projects expected to be completed in time to meet the 2020 peak demand 33

5.2.5 Projects expected to be completed in time to meet the 2021 peak demand 33
5.3 Summary 34

6. Existing and Planned Developments in Generation 45


6.1 Existing Generation 45

6.1.1 Existing generation of MIS 45

6.1.2 Existing generation of Dhofar 47


6.2 Planned Retirements of Existing Plant 52

Page | 2
Five-Year Annual Transmission Capability Statement (2017 - 2021)

6.3 Planned Future Generation (2017-2021) 52

6.3.1 Planned Future Generation at MIS 52

6.3.2 Planned Future Generation at Dhofar 53

6.3.3 Wind Farm Plant 53


6.4 Non-Contracted Generating Capacity 53
6.5 Interconnections 55

6.5.1 Interconnection with the GCCIA Grid through UAE (Transco Abu Dhabi) 55

6.5.2 Interconnection with PDO 55


6.6 Economic Dispatch 55

6.7 Spinning Reserve 55

7. Demand Forecast and Generation Availability 56


7.1 System Demand 56
7.2 Demand Forecast 60

7.3 System Maximum Demand Forecast and Generation Availability 66

8. Transmission System Performance 73


8.1 Power Flow and Voltage Profiles 73

8.1.1 Power Flow and Voltage Profiles of MIS 73

8.1.2 Power Flow and Voltage Profiles of Dhofar 74


8.2 Fault levels for MIS and Dhofar Systems 89

9. Development Opportunities 91
9.1 Review of the Generation Versus Load Balance on an Area Basis 91

9.2 Available grid station capacity 104

10. Non-compliances 111


Appendix A: Review of Future Developments 116
A.1 Summary of Projects to be completed between 2017-2021 Peak Demands 116
A.2 Projects expected to be completed to meet the 2017 peak demand 116

A.3 Projects expected to be completed to meet the 2018 peak demand 120
A.4 Projects expected to be completed to meet the 2019 peak demand 123

A.5 Projects expected to be completed to meet the 2020 peak demand 127

A.6 Projects expected to be completed to meet the 2021 peak demand 127

Appendix B: Transmission System Data 129


B.1 Substations Loads and Capacitor data 129

B.2 Overhead Line Circuit Capacities and Parameters 129


B.3 Transformer data 129

Appendix C: Power System Studies 157


C.1 Summary of Load Flow Study results 157

Page | 3
Five-Year Annual Transmission Capability Statement (2017 - 2021)

C.2 Summary of Fault Level Study results 157

C.3 Diagrames of the model for the Load Flow Study Results 157

Page | 4
Five-Year Annual Transmission Capability Statement (2017 - 2021)

List of Figures
Figure 1: Existing MITS in Peak 2017 35
Figure 2: Existing MITS in Peak 2018 36
Figure 3: MITS expected development by Peak 2019 37
Figure 4: MITS expected development by Peak 2020 38
Figure 5: MITS expected development by Peak 2021 39
Figure 6: Dhofar existing transmission system in Peak 2017 40
Figure 7: Dhofar System expected development by Peak 2018 41
Figure 8: Dhofar System expected development by Peak 2019 42
Figure 9: Dhofar System expected development by Peak 2020 43
Figure 10: Dhofar System expected development by Peak 2021 44
Figure 11: MIS Load on 2016 Peak Day 56
Figure 12: Dhofar System Load on 2016 Peak Day 57
Figure 13: MIS Load on 2016 Minimum Load Day 59
Figure 14: Dhofar System Load on 2016 Minimum Load Day 59
Figure 15: Number of out-of-firm grid stations during 2017-2021 of MIS 79
Figure 16: Number of out-of-firm grid stations during 2017-2021 of Dhofar 79
Figure 17: Voltage profile at 400kV busbars in p.u. 81
Figure 18: Voltage profile (p.u.) at Airport Heights Grid Station 82
Figure 19: Voltage profile (p.u.) at MIS Grid Station 83
Figure 20: Voltage profile (p.u.) at Salalah Free Zone Grid Station 84
Figure 21: Voltage profile (p.u.) at Ittin Grid Station 85
Figure 22: Voltage profile (p.u.) at Al Qarm Grid Station 86
Figure 23: Transmission power losses at peak demand of the years 2017-2021 of MIS 87
Figure 24: Transmission power losses at peak demand of the years 2017-2021 of Dhofar 87
Figure 25: Peak load growth over the period 2017-2021 of MIS 88
Figure 26: Peak load growth over the period 2017-2021 of Dhofar 89
Figure 27: Future OETC MIS Transmission System (2021) 92
Figure 28: Future OETC Dhofar Transmission System (2021) 93
Figure 29: Generation and load balance in Muscat area 99
Figure 30: Generation and load balance in Al Batinah South area 100
Figure 31: Generation and load balance in Al Batinah North area 100
Figure 32: Generation and load balance in Al Bureimi area 101
Figure 33: Generation and load balance in Al Dhahirah area 102
Figure 34: Generation and load balance in Al Dakhiliah area 102
Figure 35: Generation and load balance in Al Sharqiyah area 103
Figure 36: Generation and load balance in Dhofar area 104
Figure 37: Used and available MVA in Muscat area at 2021 peak demand 106
Page | 5
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Figure 38: Used and available MVA in Muscat area at 2021 peak demand 107
Figure 39: Used and available MVA in Muscat area at 2021 peak demand 107
Figure 40: Used and available MVA in Al Batinah South area at 2021 peak demand 108
Figure 41: Used and available MVA in Al Batinah North area at 2021 peak demand 108
Figure 42: Used and available MVA in Al Bureimi and Al Dhahiriah area at 2021 peak demand 109
Figure 43: Used and available MVA in Al Dakhiliah area at 2021 peak demand 109
Figure 44: Used and available MVA in Al Sharqiyah area at 2021 peak demand 110
Figure 45: Used and available MVA in Dhofar area at 2021 peak demand 110
Figure C 1: MIS 2017 Max. Load Flow Condition 205
Figure C 2: MIS 2018 Max. Load Flow Condition 206
Figure C 3: MIS 2019 Max. Load Flow Condition 207
Figure C 4: MIS 2020 Max. Load Flow Condition 208
Figure C 5: MIS 2021 Max. Load Flow Condition 209
Figure C 6: Dhofar System 2017 Max. Load Flow Condition 210
Figure C 7: Dhofar System 2018 Max. Load Flow Condition 211
Figure C 8: Dhofar System 2019 Max. Load Flow Condition 212
Figure C 9: Dhofar System 2020 Max. Load Flow Condition 213
Figure C 10: Dhofar System 2021 Max. Load Flow Condition 214

Page | 6
Five-Year Annual Transmission Capability Statement (2017 - 2021)

List of Tables
Table 1: Summary of Planned Developments on OETC Transmission System (2017 - 2021) 3
Table 2: Demand Connections – Demand Class Sepecification 26
Table 3: Existing and committed future generating capacity 48
Table 4: New Contracted and Planned Generating Capacity 53
Table 5: Non-Contracted Generating Capacity 54
Table 6: Centrally Dispatched Generating Capacity on OETC Transmission System 54
Table 7: Historic Growth in Peak Demand and Transmission Losses (2003 – 2016) 57
Table 8: Expected Load Transfers between Grid Supply Points (2017-2021) 62
Table 9: OETC Transmission System Demand Forecast by Grid Station 66
Table 10: Comparison of Demand Forecast with Available Generating Capacity including Planned Retirements 71
Table 11: Comparison of Demand Forecast with Available Generating Capacity and Non-Contracted Generation
in service 72
Table 12: Summary of Connected Generation Used in Load Flow Studies of Maximum Demand 75
Table 13: Summary of Connected Generation Used in Load Flow Studies of Minimum Demand 76
Table 14: Estimated Power Surplus and Power Deficit on an Area Basis (2017-2021) 94
Table 15: Available Grid Station Capacity of More than 10 MVA in 2021 105
Table 16: Expected Over headlines/ Cables Which will not omply with Transmission Security Standard (First
Outage) at Peak Demand in 2017 113
Table 17: Expected Grid stations 132/33kV, which will not comply with Transmission Security Standard (First
Outage) at Peak Demand in 2017 114
Table 18: Expected Grid stations 132/33kV, which will not comply with Transmission Security Standard at
Maintenance Period in 2017. 115
Table B 1: Load and Capacitor Data for Grid Station (2017-2021) 130

Table B 2: 2017 Branch Data Listing 136


Table B 3: Progressive Change to Branch Circuit Data for 2018-20121 140
Table B 4: Grid Station Transformers Data at 2017 Peak 145
Table B 5: Grid Station Transformers Data from 2018 to 2021 152
Table C 1: Transformers Loading (%) at Grid Stations (2017-2021) 158

Table C 2: Available Capacity at Grid Stations (2017-2021) for Connection of New Demand 163
Table C 3: Overhead Line and Cable Circuit Loadings (%) at Peak Demand (2017-2021) 168
Table C 4: Transmission System Voltage Profile at Peak Demand (2017-2021) 177
Table C 5: Transmission System Voltage Profile at Minimum Demand (2017-2021) 184
Table C 6: Estimation of Transmission Losses and Generation Margin at Peak Demand (2017-2021) 191
Table C 7: Maximum 3-Phase Short Circuit Fault Levels 192
Table C 8: Maximum 1-Phase Short Circuit Fault Levels 200

Page | 7
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Document History and Status

Revision Date issued Prepared by Approved by Date approved Revision type

Network Planning Network Planning


D.0 15/02/2017 21/02/2017 First draft
Department Department

Network Planning Asset Manegment &


D.1 21/02/2017 22/02/2017 Second draft
Department Planning Department

Network Planning
D.2 22/02/2017 CEO 23/02/2017 Final draft
Department

Network Planning
D.3 23/02/2017 AER 04/05/2017 Final draft
Department

Distribution of Copies
Revision Copy no Quantity Date Issued to
V.0 1 1 17/02/2017 Eng. Ali Al Hadabi

Printed: 17/02/2017

Last saved: 04 May 2017 03:40 PM

Author: Network Planning Department

Name of organisation: Oman Electricity Transmission Company S.A.O.C

Name of document: Five-Year Annual Transmission Capability Statement (2017- 2021)

Document version: V.1 As Approved by the Authority for Electricity Regulation

Page | 8
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Glossary
AER Authority for Electricity Regulation, Oman
AIS Air Insulated Switchgear
DISCOs Distribution Companies
DPC Dhofar Power Company (SAOC)
GCCIA Gulf Cooperation Council Interconnection Authority
GIS Gas Insulated Switchgear
GPDC Al Ghubrah Power and Desalination Company (SAOC)
GS Grid Station
GT Gas Turbine
IPP Independent power project
IWP Independent water project
IWPP Independent water and power project
kV kiloVolt
LILO Line In Line Out
MEDC Muscat Electricity Distribution Company (SAOC)
MITS Main Interconnected Transmission System
MJEC Majan Electricity Company (SAOC)
MVA Mega Volt Ampere
MVAr Mega Volt Ampere reactive
MW Megawatt(s)
MWh Megawatt hour(s) = (1,000) kWh
MZEC Mazoon Electricity Company (SAOC)
OES Oman Electrical Standard
OETC Oman Electricity Transmission Company (SAOC)
OHL Over Head Line
OPWP Oman Power and Water Procurement Company (SAOC)
PAEW Public Authority for Electricity and Water
PDO Petroleum Development Oman (LLC)
PS Power Station
RAEC Rural Areas Electricity Company (SAOC)
ST Steam Turbine
SVC Static Var Compensator
TSS Transmission Security Standard
UAE United Arab Emirates
UGC Underground Cable

Page | 9
1. Executive Summary

This Capability Statement presents the Oman Electricity Transmission Company’s development plans for the
400kV, 220kV and 132kV transmission systems for the years 2017 to 2021. Dhofar system has been transferred to
the Oman Electricity Transmission Company (OETC) on 1st January 2014. This document describes the
development plans for both MITS and Dhofar Transmission Systems.

The Statement includes data for the generators, loads, overhead lines, cables, transformers, reactive power
compensators and capacitor banks used in the development of transmission system models. In addition, the
Statement includes the demand and generation forecast. The power system studies undertaken by OETC’s
DIgSILENT PowerFactory software, version 15.2, in preparation of this Capability Statement. The Statement also
includes the results of power system analysis of the transmission system that defines system performance when
operating under the extreme peak (summer season) and off peak (winter season) in each of the five years. From this
analysis an assessment has been made of the opportunities for the connection of new generation, new demand and
reinforcement on the system.

Table 1 lists the schedule for committed and planned system development projects on the 400kV, 220kV and 132kV
transmission systems, although it should be noted that not all of the projects listed have full authorisation at this
time. The 400kV system development in MITS, includes the installation of two 400/220kV interconnection grid
stations, four 400/220/132/33kV grid stations, one 400/220/132kV and two 400/132kV grid stations. In addition,
the number of 220kV grid stations in MITS will increase from sixteen in peak of 2017 to nineteen in peak of 2021.
After adding Barka-3 PS grid station in peak of 2018, there will be two 220/33kV grid stations. The total number
of both MITS and Dhofar transmission system of 132/33kV grid stations will also increase from fifty-four in peak
of 2017 to seventy-one by peak of 2021.

It is one of OETC’s strategic planning concepts to introduce the 400kV system as a backbone to allow the power
evacuation from the centralized power plants. Furthermore, OETC installed 220kV double circuit lines around
northern Oman to supply and support the 132kV system. In 2010, the 220kV connection between the Sohar
Interconnector Station (SIS) and Mahadha (Al-Wasit) was completed to support linking Oman (OETC) with the
GCCIA Grid through UAE (Transco Abu Dhabi) network. In 2013, the 220kV transmission system was extended
from Misfah in the Muscat area to Jahloot. In addition, a 220kV line between Mahadha and Ibri was energize in
2012 to support the voltage, meet the expected growth in the area and meet the Transmission System Security
Standard.

Moreover, OETC has introduced the first 400kV system that includes 400kV connection between Jahloot grid
station and Sur power station and line between Sur power station and New Izki grid stations in 2016. Other 400kV
transmission lines will be installed between New Izki-Misfah, Ibri-New Izki, Sohar-3 IPP-Sohar Free Zone, Sohar
Free Zone-SIS, Sohar Free Zone-Mahadha (will be operated as 220kV) and Misfah-Rusail Industrial grid stations.
Furthermore, there will be a LILO connection from the Sur- New Izki 400kV line at Qabel grid station through a
400/132kV grid station. Accordingly, a total of nine 400kV grid stations will be commissioned at Sur, Jahloot, New
Izki, Misfah, Ibri, Sohar Free Zone, SIS, Qabel and Rusail Industrial. The total installed capacity of 400kV grid
substations will be around 15,250 MVA in 2021.
Five-Year Annual Transmission Capability Statement (2017 - 2021)

In accordance with Condition 27 of OETC’s Transmission and Dispatch Licence, the power flow studies presented
in this Capability Statement are based on updated demand forecast data provided by Distribution companies
(DISCOs) and the updated generation forecast by Oman Power and Water Procurement Company (OPWP).

To be able to perform the studies and produce the results presented in this statement, the deadline to receive data
from various parties (OPWP, DISCOs) is as per the Grid Code. Any information received after the deadline will be
included in the next Five-Year Annual Transmission Capability Statement (2018-2022).

The forecast average annual growth in system demand of about 6.34% for MITS and 9.0% for Dhofar system is
over the period 2017-2021 drives many of the planned grid station reinforcements. To meet security of supply
requirements and provide load relief to the loaded grid stations, it will be necessary to transfer excess load to the
new or existing grid stations. Furthermore, OPWP has submitted a connection application dated 16 February 2014
for connection of new power plants to the MITS at Ibri and Sohar. The recent updated generation data is shown a
total of 1508MW at Ibri and 1708MW at Sohar Power Plants. Also, there is another connection application
submitted by OPWP dated 31 August 2014 for connection of 400MW (Salalah-2 IPP) at Dhofar transmission
network. The recent updated generation data is shown a total of 437.8MW from new Salalah-2 IPP in 2018. In
addition, OPWP has submitted a connection application dated 19 October 2016 for a new generation of 1000MW
at Misfah. Moreover, Rural Area Electricity Company (RAEC) has submitted a connection application dated 25
December 2014 for the first Wind Farm Plant to Dhofar Transmission System with 50MW installed capacity and it
will be ready by 2019.

As the demand grows, there is a greater need to extend the transmission systems and to establish new 400kV
network as a backbone to transmit the bulk power from power plants. This will reduce the overload at the 220kV
and 132kV networks and subsequently improve voltages and reduce power losses. Consequently, the 220kV will
be operated as a transmission system and the 132kV as sub-transmission system.

From Table 1, a total of 67 transmission projects are planned over the five years period. Most of projects are
designed to increase the transmission system capacity, so that it can meet future demand growth and satisfy the
Transmission Security Standard. This is a major programme of capital investment that will be spread across the
whole network to improve transmission system performance in northern and southern of Oman. Power system
studies presented in this statement confirmed that the planned investment in 400kV, 220kV and 132kV grid stations
and transmission circuits will provide substantial spare capacity on the transmission systems.

The major technical issue identified in the studies was with high short-circuit fault levels on the 132kV busbars at
three grid stations in the Muscat area. The grid stations at Ghubrah, Rusail, Bousher and Madinat Sultan Qaboos
(MSQ) were all shown in earlier studies to have high 132kV fault levels. During 2017-2018, OETC has taken
appropriate remedial action to address this problem in the short–term by splitting the 132kV busbars and opening
some of 132kV lines at Muscat region without impacting the security requirements. From 2019, there will be no
longer need for busbars splitting due to the network development and reconfiguration works. Therefore, all busbars
will be returned to normal operation. However, some 132kV lines will still be needed to be kept open to reduce the
infeed short circuit contribution and this is a part of OETC long term strategy to operate the 400kV and 220kV as
the main transmission voltages.

Load flow studies have confirmed that the voltage levels across the transmission system will be maintain within the
limits. The 400kV voltage will be maintained in the system within the allowable limit ±5%. In addition, as defined
in the Grid Code the 220kV and 132kV will be maintained within ±10% and the 33kV will be maintained within
±6%. Also, the load flow has presented the issue of overvoltage during the winter peak time due to the 400kV lines.
Page | 1
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Accordingly, OETC is initiating a project to install a shunt reactors at the 400kV lines to overcome the overvoltage
issue during winter peak time.

The Statement has reviewed the opportunities for the connection of new generation and new demand and identified
those grid stations with substantial spare capacity where it should be possible to connect new demand to the system.

Section 2 of the Statement provides an introduction to the document, identifying the main related documentation
and the key changes that have taken place on the transmission system since the previous issue of the Statement.

Section 3 identifies the technical requirements of the Grid Code and the Transmission Licence with specific
attention to system voltage, frequency and security of supply.

Section 4 describes the main engineering standards used by OETC in its planning and design of the transmission
system.

Section 5 describes the existing transmission system and summarises the planned developments in each year over
the period 2017 to 2021.

Section 6 identifies the existing and planned developments in generation and describes the interconnections both
inside Oman and internationally, i.e. PDO and the GCCIA respectively.

Section 7 presents the comparison of demand forecast with the generation capacity available.

Section 8 discusses transmission systems performance and presents the results of load flow and short-circuits
studies that show the performance of the transmission system at both peak and off peak demand in each year from
2017 to 2021.

Section 9 identifies the development opportunities for the connection of new demand and new generating plants to
the transmission systems.

Section 10 presents the areas of the network that will be operating above the firm capacity and not compliance with
Transmission Security Standard in 2017.

Page | 2
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Table 1: Summary of Planned Developments on OETC Transmission System (2017 - 2021)


Expected
S.N Project Completion Status Main Equipment Purpose
Date

Peak 2017

· 2x 125MVA transformers
· To cater for the load growth at Barka area
Madinat Barka 132/33kV grid 29th March · 10 no. 132kV GIS
1 Energized · To meet Transmission Security Standard
station (TX1 & TX2) 2016 · 0.13 km LILO of 132kV OHL from Filaj to
· Load transfer from Barka Main
Mualdah

· 2 x 125 MVA transformers


· 8 no. 132kV GIS · To cater for the new demand in the area
2 New Izki 132/33kV grid station 4th July 2016 Energized
· 2x0.62 km of Izki – Mudhaibi 132kV UGC · Load Transfer from Izki grid station
LILO

· To evacuate the power from Sur Generation

·2 x 500 MVA transformers(220/132kV) · To support the voltage and power flow to Al


th
3 New Izki 220kV grid station 4 July 2016 Energized Dakhliah area
·7 no. 220kV GIS
·To comply with Transmission Security Standards
requirements
· To evacuate the power from Sur Generation

New Izki 400/220 kV grid · 2 x 500 MVA transformers (400/220kV) · To support the voltage and power flow to Al
4 4th July 2016 Energized Dakhliah area
station · 12 no. 400kV GIS
· To comply with Transmission Security Standards
requirements

Page | 3
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2017 - 2021)
Expected
S.N Project Completion Status Main Equipment Purpose
Date

Peak 2017

· 6 no. 132kV GIS


· To meet load growth requirements
10th July · 28 km 132kV OHL route length between
5 Ibra 132/33kV grid station Energized · To meet Transmission Security Standard
2016 Mudhairib and Ibra grid stations
· Load transfer from Mudhairib
· 2 x 125MVA transformers

· 3 x 500MVA transformers (400/220kV)


29th · To support the evacuation of Sur power plant
6 Upgrading Misfah grid station to · 11 no. 400kV GIS
September Energized
400kV ·To maintain the security requirement
2016
· 3 no. 220kV GIS
· 2 x 125 MVA transformers
13th · Load transfer from existing JBB Ali grid station
JBB Hassan 132/33kV grid · 10 no. 132kV GIS
7 December Energized · To meet load growth requirements in the area
station · 2x16 km LILO of Al Kamil -Sur 132kV OHL
2016 · To meet Transmission Security Standard
· 7 no. 132kV AIS at JBB Ali grid station

· 2 x 50 MVA (shifted from the Mawalleh North


grid station)
21st · 4 km OHL from Quriyat grid station · To supply the new IWP at Quriyat
8 Daghmar 132/11kV grid station December Energized
2016 · 2 no. 132kV GIS at existing Quriyat grid
station
· 7 no. 132kV GIS at Daghmar

Page | 4
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2017 - 2021)

Expected
S.N Project Completion Status Main Equipment Purpose
Date

Peak 2017

· 2 x 125 MVA · To cater for the new demand within the area
End of Under
9 Dreez 132/33kV grid station · 30 km 132kV OHL from Ibri · Load transfer from Ibri and Al Hayl grid stations
March 2017 Construction
· 8 no. 132kV GIS

· 2 x 125 MVA transformers


Adding third & fourth Mid of · To meet load growth requirements
10 transformers 132/33kV at January Energized · 2 no. 132kV GIS
Muladah grid station 2017 · To meet Transmission Security Standard
· 4 no. 33kV GIS Interlink
· 2 x 125 MVA transformers
Adding third & fourth Mid of · To cater for the new demand in the area
11 transformers 132/33kV at Liwa February Energized · 2 no. 132kV GIS
grid station 2017 · To meet Transmission Security Standard
· 4 no. 33kV GIS Interlink
· 2x0.17 km LILO Wadi Al Jizzi – Liwa
132kV OHL · To cope with the load growth.
· 2 x 500 MVA transformers · To meet Transmission Security Standard
Sohar Free Zone 220/132/33kV End of Under · 11 no. 220kV GIS · To supply the free zone area industrial loads
12
grid station March 2017 Construction · 2x 0.48 km 220kV UGC as LILO of
220kV OHL Sohar 2 PS -SIS
· 2 x 125MVA transformers
· 20 no.132kV GIS

Page | 5
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2017 - 2021)

Expected
S.N Project Completion Status Main Equipment Purpose
Date

Peak 2017

To replace the existing AIS to GIS due to:


· Lightening

Replacement of Mahadha End of · Maintenance Issus


13 Energized · 14 no. 132kV GIS
132kV AIS to GIS March 2017 · Old Assets
· System reliability
· System security

33kV busbars Interlinking at End of June Under · 8 no. of 33kV GIS at Bousher & ·To meet Transmission Security Standard
14 Bousher & Mawalleh South 2017 Construction Mawalleh South
grid stations

· 4 x 125MVA Transformers
· To meet load growth requirements
· 10 no. of 132kV GIS
End of June Under · To meet Transmission Security Standard
15 S’aadah 132/33kV grid station · 4 no. 33kV GIS Interlink
2017 Construction · Load Transfer from Al Qarm, Ittin and Awqad grid
· 13 km LILO from Ashoor- stations
Awqad132kV UGC

Page | 6
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2017 - 2021)

Expected
S.N Project Completion Status Main Equipment Purpose
Date

Peak 2017

Connection of Salalah-2 IPP & · To connected the new Salalah-2 IPP Power Plant
Adding third & fourth End of June Under · 16 no. of 132kV GIS
16 · To meet load growth requirements
transformers to Salalah Free 2017 Construction · 2 x 125MVA transformers
Zone grid station · To meet Transmission Security Standard

· One circuit of 3 km 132kV UGC (2500mm2)


between Muttrah-Al Falaj grid stations
132kV Linking System between · One circuit consist of 1.5 km 132kV OHL · To secure the loads and meet Transmission
Al Falaj, Muttrah and Wadi (Twin YEW) and 2 km UGC 132kV between Security Standard.
End of June Under
17 Kabir Grid stations & Adding Muttrah-Wadi Kabair grid stations
2017 Construction · Safety clearance and environment issues
Fourth 125MVA transformer at
· 10 no. 132kV GIS at Wadi Kabair grid station · To cater for the new demand in the area
Wadi Kabir grid station
· 8 no. 132 GIS at Al Falaj
· 1 x 125MVA transformer at Wadi Kabir

Page | 7
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2017 - 2021)

Expected
S.N Project Completion Status Main Equipment Purpose
Date

Peak 2017

· 2 x 125 MVA transformers · To cater for the new demand in the area
End of June Under
18 Jebreen 132/33kV grid station · 2x0.5 km LILO of Nizwa - Ibri 132kV OHL · Load Transfer from Bahla grid station
2017 Construction
· 8 no. 132kV GIS · To meet Transmission Security Standard

Peak 2018

End of · To support the evacuation of Sur power


19 400 kV OHL between New Under · 100 km OHL 400kV plant
September
Izki and Misfah Construction
2017 · To meet Transmission Security Standard

· To cater for the new demand in the area


End of · 2 x 125 MVA transformers
Dil Abdusalam 132/33kV grid Under · Load Transfer from Saham & Khaborah grid
20 September · 2x8 km LILO of Saham-Khaborah132kV OHL
station Construction stations
2017 · 8 no. 132kV GIS
· To meet Transmission Security Standard

Adding third & fourth End of


Under · 2 x 125 MVA transformers · To meet Transmission Security Standard
21 transformers 132/33kV at September
Construction · 4 no. 33kV GIS Interlink · To cater for the load growth in the area
Khadhra grid station 2017

Adding third & fourth End of


Under · 2 x 125 MVA transformers · To meet Transmission Security Standard
22 transformers 132/33kV at September
Construction · 4 no. 33kV GIS Interlink · To cater for the load growth in the area
Madinat Barka grid station 2017

Page | 8
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2017 - 2021)

Expected
S.N Project Completion Status Main Equipment Purpose
Date

Peak 2018

· 2 x 125 MVA transformers · To cater for the new demand in the area
End of Under
23 Suwaiq 132/33kV grid station · 2x0.2 km LILO of MIS-Khadhra 132kV OHL · To meet Transmission Security Standard
September 2017 Construction
· 8 no. 132kV GIS · Load Transfer from MIS grid station

· 2 x 125 MVA transformers


· 24.06 km 132kV OHL from Shinas to Madinat · To cater for the new demand in the area
Madinat Shinas 132/33kV End of Under Shinas
24 · Load Transfer from Shinas grid station
grid station September 2017 Construction
· 2 no. 132kV GIS at Shinas · To meet Transmission Security Standard
· 6 no. 132kV GIS at Madinat Shinas

· 2 x 125 MVA transformers · To cater for the new demand in the area
End of Under · 2x15 km LILO of New Izki - Mudhaibi 132kV · Load transfer from Mudhaibi
25 Sinaw 132/33kV grid station
September 2017 Construction OHL · Solve the issue of voltage drop of 33kV lines
· 8 no. 132kV GIS · To meet Transmission Security Standard

Upgrading of Mawalleh North · To cater for the new demand in the area
grid station from 3x50MVA End of Under · To support the 33kV network in the Seeb area
26 · 2 x 125 MVA transformers
(132/11kV) to 2 x 125 MVA September 2017 Construction and enable to transfer more load from
(132/33kV) transformers neighbouring grid stations (Seeb & Mawalleh)
Daghmar 132/11kV grid End of Under · 1 x 50 MVA (shifted from the Mawalleh North
27 · To supply the new IWP at Quriyat
station September 2017 Construction grid station)

Page | 9
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2017 - 2021)

Expected
S.N Project Completion Status Main Equipment Purpose
Date

Peak 2018

· 2 x 500MVA transformers
End of · 2x0.5 km LILO of Al Filaj-Airport
Upgrading Mobella grid station Under · Supporting Mobella demand
28 September Heights 220kV OHL
to 220kV Construction · Securing of the supply within the area
2017 · 8 no. 220kV GIS
· 2 no. 132kV GIS

Adding 2x125MVA End of


Under · 2 x 125 MVA transformers · To Supply the Barka IWP
29 transformers 220/33kV at September
Construction · 2 no. 220kV GIS · Load Transfer from Barka Main grid station
Barka-3 PS grid station 2017

· 2 x 35 MVAr reactors at end of 400kV


line between Sur-Jahloot
End of
Under · 4 x 40 MVAr reactors at end of 400kV · To maintain the voltage within the range during the
30 Adding 400kV reactors December
Construction line between Sur-New Izki winter time
2017
· 2 x 30 MVAr reactors at end of 400kV
line between New Izki-Misfah

Page | 10
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2017 - 2021)
Expected
S.N Project Completion Status Main Equipment Purpose
Date

Peak 2018

· 3 x 500 MVA transformers (400/220kV) · To evacuate power coming from Ibri


End of
Ibri IPP 400/220kV grid Under · 19 No. 400kV GIS at Ibri IPP IPP Power Plant and supply Ibri area
31 December
station Construction · 10 No. 220kV GIS at Ibri IPP · To maintain Transmission Security
2017
· 2x4.3 km LILO of 220kV OHL Ibri – Mahadha Standard

· 4 x 125 MVA transformers · To cater for the new demand in the


End of March Under · 2x5 km LILO of Sohar-SIS 132kV OHL area
32 Uwaynat 132/33kV grid station
2018 Construction · 10 no. 132kV GIS · Load Transfer from the existing
· 4 no. 33kV GIS Interlink Saham and Sohar grid stations

· To maintain Transmission Security


Upgrading of Adam grid
End of March Under · 2 x 125 MVA transformers Standard
33 station from 2x40MVA to
2018 Construction · 6 no. 132kV GIS · To cater for the new demand in the
2x125MVA transformers
area

· 3 no. 132kV GIS at SIA


· To meet Transmission Security
End of June Under · 1 no. of 220kV GIS at SPSS
34 Security of SIA grid station Standard at SIA during maintenance
2018 Construction · 1x500MVA transformer, 220/132kV
period
· 3.2 km UGC of 220kV SPS 1 – SIA

Page | 11
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2017 - 2021)

Expected
S.N Project Completion Status Main Equipment Purpose
Date

Peak 2018

. 4 no. circuits from 400kV Sohar IPP-3 to 400 kV Sohar


Free Zone consisting of :
. 2 no. circuits of 10.25 km 400kV UGC
· 2 no. circuits with: · To develop 400kV network
400kV line connection between - 3.3 km 400kV UGC from Sohar IPP-3 to Terminal · To evacuate full power from Sohar
35 End of June Under
Sohar IPP-3– 400kV Sohar Tower III IPP
2018 Construction
Free Zone · To maintain Transmission Security
- 6 km OHL from Terminal Tower to Sohar Free
Zone Terminal Standard
- 0.9 km 400kV Cable from Sohar Free Zone
Terminal Tower to 400kV Sohar Free Zone grid
station
· To evacuate power coming from Ibri
400kV connection line to Ibri End of June Under · 250 km 400kV OHL between Ibri to New Izki IPP Power Plant and supply Ibri area
36
IPP Power Plant 2018 Construction · Adding 4 x 100 MVAr reactors at 400kV line ends · To maintain Transmission Security
Standard
· 63 km 400kV OHL between Sohar Free Zone to Mahadha · To develop 400kV network
(Operate as 220kV)
400kV line connection between · To evacuate full power from Sohar
End of June Under · 1 km 220kV UGC between Sohar Free Zone to Mahadha
37 Sohar Free Zone – Mahadha & III IPP
2018 Construction
Sohar Free Zone – SIS · 42 km 400kV OHL between Sohar Free Zone to SIS · To maintain Transmission Security
. 2 no. 220kV GIS at Sohar Free Zone 220kV Standard

Page | 12
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2017 - 2021)

Expected
S.N Project Completion Status Main Equipment Purpose
Date

Peak 2018

· 1 x 125MVA transformer
Installing 220kV GIS and · To meet load growth requirements
End of June Under · 6 no. of 220kV GIS
38 adding fourth 125MVA · To meet Transmission Security Standard
2018 Construction · 8 no. of 132kV GIS
transformer at MSQ grid station · To cater for the new demand in the area
· 4 no. 33kV GIS Interlink

Peak 2019

Upgrading of Seeb Main grid


station from 2 x 63 MVA to 2 x End of · To maintain Transmission Security
· 2 x 125 MVA transformers
39 125 MVA transformers and September Design Standard
· 4 no. 33kV GIS Interlink
installing 33kV busbars 2018 · To cater for the new demand in the area
Interlinking

· 3 x 500 MVA transformers (400/220kV) at Sohar


Free Zone
· 3 x 500 MVA transformers (400/220kV) at SIS
End of · To evacuate power coming from Sohar III
Sohar Free Zone 400kV grid Under · 16 no. 400kV GIS at Sohar III IPP grid station
40 September IPP Power Plant and to supply area
station Construction · 17 no. 400kV GIS at Sohar Free Zone
2018 · To maintain Transmission Security Standard
. 11 no 400kV GIS at SIS
. 2 x 50 MVAr reactors at Sohar Free Zone
. 3 no. 220kV GIS at SIS

Page | 13
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2017 - 2021)

Expected
S.N Project Completion Status Main Equipment Purpose
Date

Peak 2019

New 132kV double circuits · 2 no 132kV GIS at Nakhal


lines from Rustaq-Wadi bani End of · 2 no 132kV AIS at Rustaq · To meet Transmission Security Standard at
Under
41 Auwf-Nakhal with a new December · 85 km 132kV OHL Rustaq during maintenance period
Construction
Wadi bani Auwf 132/33 kV 2018 · 2 x 125 MVA at Wadi bani Auwf · Load Transfer from Rustaq grid station
grid station · 8 no. of 132kV GIS at Wadi bani Auwf
· 4 x 125 MVA transformers
· To cater for the new demand in the area
End of · 14 no. of 132kV GIS
Ghala Heights 132/33kV grid
42 December Design · 7 km 132kV UGC from Ghala to Ghala Heights · Load transfer from Bousher
station
2018 · 7 km 132kV UGC from Ghala Heights to Bousher
· To meet Transmission Security Standard
· 4 no. 33kV GIS Interlink

· 2 no. 132kV GIS at Shinas


Construction of a new 132kV
End of · 2 no. 132kV GIS at Sohar Free Zone
43 OHL from Sohar Free Zone to Design · To meet Transmission Security Standard
March 2019 · 30 km 132kV OHL from Sohar Free Zone to
Shinas
Shinas (Design as 400kV)

· 2 x 63 MVA transformers (shifted from Mudhaibi


End of June Under grid station) · To cater for the new demand in the area
44 Samad 132/33kV grid station
2019 Construction · 38.5 km 132kV OHL from Mudhaibi · Load transfer from Mudhaibi grid station
· 6 no. 132kV GIS

Page | 14
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2017 - 2021)
Expected
S.N Project Completion Status Main Equipment Purpose
Date

Peak 2019

Adding third & fourth transformers End of June · To meet Transmission Security Standard
· 2 x 125 MVA transformers
45 Design
132/33kV at Ghala grid station 2019 · 4 no. 33kV GIS Interlink · To meet load growth in the area

Reactive Power Compensation End of June · SVC at Hamriyah · To maintain the voltage within the range
46 Planning
Requirements (SVC) 2019 · SVC at Airport Heights during the transient at the winter time

Adding third & fourth transformers End of June · 2 x 125 MVA transformers · To meet Transmission Security Standard
47 Design · 2 no. 132kV GIS
132/33kV at Amerat grid station 2019 · To meet load growth in the area
· 4 no. 33kV GIS Interlink
· 2 x 125 MVA transformers
Adding third & fourth transformers End of June · To meet Transmission Security Standard
48 Design · 2 no. 132kV GIS
132/33kV at A'salam grid station 2019 · To meet load growth in the area
· 4 no. 33kV GIS Interlink

Adding third & fourth transformers


End of June · 2 x 125 MVA transformers · To meet Transmission Security Standard
49 132/33kV at Airport Heights grid Design
2019 · 4 no. 33kV GIS Interlink · To meet load growth in the area
station

Page | 15
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2017 - 2021)

Expected
S.N Project Completion Status Main Equipment Purpose
Date

Peak 2019

· 4 x 125 MVA transformers · To cater for the new demand in


the area
End of June · 10 no. 132kV GIS
50 Halban 132/33kV grid station Design · Load transfer from Mobella &
2019 · 4 no. 33kV GIS Interlink Barka Main grid stations
· 2x0.4 km LILO 132kV UGC Barka Main – Mobella

· 2 x 125 MVA transformers


· 16.2 km LILO of Rusail-Sumail 132kV OHL · To cater for the new demand in
Sumail Industrial 132/33kV End of June the area
51 Design . 2x14.6 km 132kV OHL
grid station 2019 · Load transfer from Sumail grid
. 4x1.6 km 132kV UGC station
· 8 no. 132kV GIS

Adding third & fourth · 2 x 125 MVA transformers · To meet Transmission Security
52 End of June Standard
transformers 132/33kV at Design · 2 no. 132kV GIS
2019
Sohar Free Zone grid station · 4 no. 33kV GIS Interlink · To meet load growth in the area

· 2 x 125 MVA transformers · To cater for the new demand in


End of June the area
53 Bedyah 132/33kV grid station Design · 0.45 km LILO of Mudhairib – Al Kamil 132 kV OHL
2019
· 8 no. 132kV GIS · Load transfer from Mudhairib

Page | 16
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2017 - 2021)

Expected
S.N Project Completion Status Main Equipment Purpose
Date

Peak 2019

· 2 x 125 MVA transformers


· To cater for the new demand in the area
54 Birkat Al Mouz 132/33kV grid End of June · 8 no. 132kV GIS
Design · Load transfer from Nizwa & Madinat Nizwa grid
station 2019 · 2x2.6 km LILO of Izki- Nizwa 132 kV stations
OHL
· 2 x 500 MVA transformers
(400/132kV)
· To increase the system reliability within Sharqia area
· 2x0.2 km LILO of 400kV OHL Sur –
when Al Kamil IPP is retired
New Izki
End of June
55 Qabel 400/132kV grid station Design · 2x0.2 km LILO of 132kV OHL · To increase and maintain the system security of 132kV
2019
Mudhairib – Ibra lines within the area
· 10 no. of 400kV GIS at Qabel grid
· To evacuate power coming from Sur Power Plant
station
· 8 no. 132kV GIS at Qabel grid station
· 2 x 500 MVA transformers
· 10 no. of 220kV GIS
· 2x0.1 km LILO of 220kV OHL SIS – · To cater for the new demand in the area
56 Khaborah Interconnection End of June
Design MIS · To increase the system reliability within Al Batinah
Station (KIS) 2019
· 2x0.15 km LILO of 132kV OHL DAS North
– Khaborah
· 8 no 132kV GIS

Page | 17
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2017 - 2021)

Expected
S.N Project Completion Status Main Equipment Purpose
Date

Peak 2019

· To maintain Transmission Security Standard


. a new circuit of 32.9km 132kV OHL requirements
End of June and 5.5 UGC between Mahadha – · To meet load growth requirements
57 Securing Bureimi area Design
2019 Bureimi
· To increase the system reliability within Al Bureimi
· 1 no 132kV AIS at Bureimi grid station
area

· 2 x 125 MVA transformers · To meet Transmission Security Standard


Adding third & fourth
End of June
58 transformers 132/33kV at Design · 2 no. 132kV GIS · To meet load growth in the area
2019
Bureimi Industrial grid station · 4 no. 33kV GIS Interlink · Load transfer from Bureimi grid station

Peak 2020

· 2 x 125 MVA transformers


· To cater for the new demand in the area
End of June · 8 no. 132kV GIS
59 Yanqul 132/33kV grid station Design · Load transfer from Al Hayl grid station
2020 · 2x4.6 km LILO 132kV OHL Dank -
· To maintain the 33kV OHL losses
Al Hayl

Page | 18
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2017 - 2021)
Expected
S.N Project Completion Status Main Equipment Purpose
Date

Peak 2020
· 4 x 125 MVA transformers
· 10 no. 132kV GIS
End of June · To cater for the new demand in the area
60 Khoudh 132/33kV grid station Design · LILO 132kV Mawalleh South – Rusail
2020 · Load transfer from Mawalleh South grid station
Industrial
· 4 no. 33kV GIS Interlink

Adding third & fourth · 2 x 125 MVA transformers · To meet Transmission Security Standard
End of June
61 transformers 132/33kV at Planning · 2 no. 132kV GIS · To meet load growth in the area
2020
Ghubrah grid station · 4 no. 33kV GIS Interlink

Peak 2021

· 2 x 500 MVA transformers (220/132kV) at


Misfah grid station
· 12 no. 220kV GIS at Misfah IPP grid station
· 2 no. 132kV GIS at Misfah grid station · To evacuate power coming from Misfah IPP
End of
62 Misfah IPP 220kV Connection
January 2021
Design . Diversion of 2x0.92 km Misfah - Wadi Adai Power Plant and to supply area
132kV UGC in Misfah IPP Location · To maintain Transmission Security Standard
. Diversion of Misfah - MSQ 2x0.7 km 220kV
OHL to 220kV UGC in Misfah IPP Location
. LILO 220kV Misfah – MSQ

Page | 19
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2017 - 2021)
Expected
S.N Project Completion Status Main Equipment Purpose
Date

Peak 2021
· 3 x 500 MVA transformers (400/132kV) at Rusail
Industrial
. 7 no. 400kV GIS at Rusail Industrial . To evacuate power coming from Misfah IPP
Upgrading Rusail Industrial to End of June Power Plant and to supply area
63 Planning . 2 no. 400kV GIS at Misfah
400kV 2021
. 3 no. 132kV GIS at Rusail Industrial · To maintain Transmission Security Standard
. Upgrading 132kV OHL between Rusail Industrial
-Misfah to 400kV

· 2 x 125 MVA transformers


Falaj Al Qabail 132/33kV grid End of June · To meet Transmission Security Standard
64 Planning · 8 no. 132kV GIS
station 2021 · To meet load growth in the area
· 8 km LILO 132kV OHL Sohar – Wadi Jizzi

· 2 x 125 MVA transformers


Madinat Ibri 132/33kV grid End of June · To meet Transmission Security Standard
65 Planning · 8 no. 132kV GIS
station 2021 · To meet load growth in the area
· LILO 132kV OHL Ibri - Jebreen
Upgrading Thumrait from · To meet Transmission Security Standard
End of June
66 2x30MVA to 2x125MVA Planning · 2 x 125 MVA transformers
2021 · To meet load growth in the area
transformers
· 2 x 125 MVA transformers
End of June · To cater for the new demand in the area
67 Khuwair 132/33kV grid station Planning · 10 no. 132kV GIS
2021 · Load transfer from MSQ grid station
· LILO 132kV MSQ – Ghubrah

Page | 20
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2017 - 2021)
Expected
S.N Project Completion Status Main Equipment Purpose
Date

Peak 2021
· 1 x 500 MVA transformer
Adding third transformer End of June · To meet Transmission Security Standard
68 Planning · 1 no. 220kV GIS
220/132kV at Airport Heights 2021 · To meet load growth in the area
. 1 no. 132kV GIS

Page | 21
Five-Year Annual Transmission Capability Statement (2017 - 2021)

2. Introduction

2.1 Licence conditions, Codes and Standards


This Transmission System Five-Year Capability Statement covers the period 2017-2021 which has been
prepared by the Oman Electricity Transmission Company S.A.O.C. (OETC). This Statement is prepared in
accordance with the requirements set down under Licence Condition 27 of the Electricity Transmission and
Dispatch Licence granted to the Company on 1 May 2005 by the Authority of Electricity Regulation (AER).
The Licence has been granted under the powers invested in the Authority by Article (2) of the Law for the
Regulation and Privatisation of the Electricity and Related Water Sector promulgated by Royal Decree
78/2004.

The purpose of the Statement is to provide up-to-date transmission system data for potential and existing
users of the transmission system so they can identify those parts of the transmission system which offer the
opportunity for future development. The Statement is required to be updated annually so that existing and
new users of the transmission system are furnished with the latest information.

New users of the transmission system should be aware of the following main documents that influence the
planning and future development of the transmission system infrastructure:

i) The Grid Code for the Sultanate of Oman.

ii) The Electricity Transmission and Dispatch Licence granted to OETC by the AER.

iii) The approved Transmission Security Standards prepared in accordance with


Condition 26 of OETC’s Transmission and Dispatch Licence which defines the
requirements for the Security Standards and maintaining of an efficient and economic
Transmission System.

iv) The Statement of Charges for Connection and use of system to OETC Electricity
Transmission System.

2.2 2017 System Development since the 2016-2020 Statement


Since the issue of the previous Capability Statement, covering the period 2016-2020, the following
projects have been or will be completed and energized in time to meet 2017 system peak demand:

1. Madinat Barka 132/33kV grid station (TX1 & TX2)

2. New Izki 400/220/132/33kV grid station

3. Ibra 132/33kV grid station

4. Upgrading Misfah grid station to 400kV

5. JBB Hassan 132/33kV grid station

Page | 22
Five-Year Annual Transmission Capability Statement (2017 - 2021)

6. Replacement of Mahadha 132kV AIS to GIS

7. Dreez 132/33kV grid station

8. Adding third & fourth transformers 132/33kV at Muladah grid station

9. Adding third & fourth transformers 132/33kV at Liwa grid station

10. Sohar Free Zone 220/132/33kV grid station

11. 33kV busbars Interlinking at Bousher & Mawalleh South grid stations

12. S’aadah 132/33kV grid station

13. Connection of Salalah-2 IPP & Adding third & fourth transformers to Salalah Free Zone grid
station

14. 132kV Linking System between Al Falaj, Muttrah and Wadi Kabir Grid stations & Adding
Fourth 125MVA transformer at Wadi Kabir grid station

15. Daghmar 132/11kV grid station

16. Jebreen 132/33kV grid station

2.3 Improvements in the preparation of the Statement


Since the issue of the Transmission System Capability Statement for 2016-2020 there have been a number
of improvements in the data and the power system modelling upon which the studies that are discussed in
the Statement are based. The most significant of these are:

i. Updating the demand forecast data according to the received information from the DISCOs.

ii. Updating the generation plan according to the received information from the OPWP.

iii. Updating the operational limits of generating units according to the received information
from the OPWP.

iv. Updating the transmission system data for the new projects as per the actual parameters.

v. Updating the new generating units data as per the actual parameters.

The improvements in the demand forecast and the power system modelling should result in similar
improvements being achieved in the accuracy of the power system studies upon which network
development planning is based.

Page | 23
Five-Year Annual Transmission Capability Statement (2017 - 2021)

3. Technical requirements for compliance with the Grid Code and Licence

The Grid Code is designed to permit the development, maintenance and operation of an efficient,
economical and coordinated electricity transmission system. It facilitates competition in the generation and
supply of electricity and promotes the security and efficiency of the system as a whole.

The Transmission Security Standard required the capacity of the Transmission System to transmit
electricity and shall not be reduced in the event that a single electric line, transformer or breaker and/or
associated plant is not in service. The operating voltage of the Transmission System shall be maintain within
the limit specified in the Grid Code and TSS.

In order to comply with Condition 26 of the Electricity Transmission and Dispatch Licence the transmission
system must be planned, designed and operated to provide a secure, efficient and economic supply of
electricity that is of an acceptable quality to its users.

OETC shall ensure that, subject as provided in the Grid Code, the Electricity Transmission System complies
with the following technical, design and operational criteria in relation to the part of the Electricity
Transmission System at the Connection Site with a User (unless otherwise specified in the Grid Code).
Although in relation to operational criteria, OETC may not be able to comply with this obligation to the
extent that others parties are not comply with the Grid Code. Each User shall ensure complies with the
criteria set out in the Grid Code (CC.6.1.5).

Whilst Condition 26 specifically sets out the Security of Supply requirements, the most important
characteristics that determine the quality of supply are frequency and voltage. The requirements for
maintaining transmission system frequency and voltage within specified operating limits are set out in the
Grid Code, and most clearly defined under conditions CC.6.1.1 and CC.6.1.2 respectively of the Connection
Conditions Code.

Grid Code establishes the historic frequency and voltage performance of the transmission system,
specifically in relation to operation at abnormal voltages and frequencies. Consider how future generation
and demand changes may affect transmission system performance in these areas. It establishes the relevant
generation design criteria and standards, and the impacts of operation at abnormal voltages and frequencies
on generating units. It considers whether the current Grid Code frequency and voltage requirements are
appropriate, taking into account of system security requirements, the capabilities of generating units, the
industry costs and benefits of implementing them.

3.1 System Frequency


In accordance with condition CC.6.1.1 of the Connection Conditions Code, OETC is required to maintain
System Frequency within the following limits:

a) During normal operating conditions, the nominal system frequency of the transmission
system shall be 50.00Hz and will be controlled normally between 49.95Hz and 50.05Hz.

Page | 24
Five-Year Annual Transmission Capability Statement (2017 - 2021)

b) During exceptional steady state conditions, frequency deviations will not exceed 49.90Hz
to 50.10Hz unless disturbed circumstances prevail.

c) Under disturbed conditions, system frequency could rise transiently to 51.50 Hz or fall to
47.5 Hz, but not exceed these limits.

As CC.6.1.1 points out, the frequency of the total system is responsive to changes in the balance between
the active power demand and total available generation capacity. OETC must therefore ensure that
sufficient generation capacity and demand is available and connected to the system at all times to respond
automatically to active power imbalances and correct any frequency change.

3.2 System Voltage


In accordance with condition CC.6.1.2 of the Connection Conditions Code, OETC is required to control
system voltage within the following limits:

a) The voltage on the 220kV and 132kV parts of the Transmission System at each site with
a user connection will remain within the limits of ±10% of the nominal voltage level.

b) The voltage on the 66kV, 33kV and 11 kV sides of transmission transformers at


Connection Sites with Users will normally remain within the limits of ±6% of the nominal
value unless abnormal conditions prevail.

As there is no specifications for voltage limits for the 400kV system in the Grid Code, OETC adopted a
value of ±5% limits for this voltage level to be in accordance with international standards and design
specification. The internal OETC standard specifications and the Transmission Security Standard include
the limit mention for the 400kV system.

During some system disturbances, such as where short circuits occur, the voltage could collapse transiently
to zero at the point of fault until the fault is cleared. Voltage regulation requires both active and reactive
power flows across the transmission system to be carefully controlled. The physical characteristics of the
plant on the transmission system also give rise to the generation and absorption of reactive power. Reactive
power flows across the transmission system can give rise to substantial voltage differences and it is therefore
necessary to maintain reactive power balances between sources of capacity and demand on a “zone” basis.

Unlike frequency, which is consistent across an interconnected transmission system, voltages at different
points on an interconnected system are determined by the local sources of demand and capacity, by the
prevailing network configuration and by the reactive power flows across the network. The management of
voltage requires control of reactive power can be provided by generation units, transformer tap-changers,
capacitor banks at 33kV or below, shunt reactors or by means of static VAR compensator (SVC).

Page | 25
Five-Year Annual Transmission Capability Statement (2017 - 2021)

3.3 Security of Supply


In accordance with Condition 26 of OETC Transmission and Dispatch Licence, the capacity of the
Transmission System to transmit electricity shall not be reduced in the event that a single electric line,
cable, transformer, circuit breaker and/or associated plant is not in service. During a period of which such
equipment is out of service, the operating voltage of the Transmission System may reduce to any level
specified for such purposes in the Grid Code. In effect, the transmission system should be planned and
operated to meet the Transmission Security Standard requirements. Table 2 from the Transmission Security
Standard document shows Demand connections, Demand Class definition and supply restoration times.
The table illustrates and explains boundaries of each demand classes and the security level requirements
during the outage for restricted and a maintenance periods.

Table 2: Demand Connections – Demand Class Sepecification

Demand Connections
Demand Class definition and supply restoration times

OETC licensed transmission system configuration

Demand Class
Demand Class

Boundaries A Planned Outage followed by


Following a system outage during the
a single Fault Outage
Restricted Period
during the Maintenance Period

Low High Required level of Required level of


MW MW served demand Time to restore served demand Time to restore
served demand served demand
> ≤ MW MW

Repair time of
A 0 2 No requirement
faulted circuit

B 2 6 3 hours No requirement

Return time of
C 6 20 15 minutes Maintenance
Planned Outage
Total Group Period Demand
Demand for the Demand
Momentary Group
Return time of
D 20 115 Interruption
Planned Outage
allowed

Momentary Momentary
E 115 300 Interruption Interruption
allowed allowed

No loss of supply for the Secured Events described in


F 300
the MITS design criteria

Page | 26
Five-Year Annual Transmission Capability Statement (2017 - 2021)

4. OETC System Design and Planning Standards

In addition to the technical requirements of the Transmission Licence and the Grid Code, the principal
electrical standards used by OETC in its planning and design of the 400kV, 220kV and 132kV transmission
systems are:

4.1 Oman Electrical Standard OES 11


The standard covers the topic “General Specifications for Electrical Materials and Equipment” and defines
the worst case conditions for system design purposes by the following parameters:

a) Maximum ambient temperature (50˚C)


b) Maximum surface temperature for metal surfaces (80˚C)
c) altitude (between sea level and 300 metres above sea level)
d) Maximum wind velocity (125km per hour)
e) Average annual rainfall (117mm)
f) Maximum relative humidity (100%)
The standard also defines the design parameters for the 132kV systems in terms of highest voltage, design
fault level and the requirement that the system be solidly earthed. Currently it does not specify
corresponding figures for the 400kV and 220kV systems.

4.2 Oman Electrical Standard OES 25A and 25B


These standards define the requirements for aluminium conductor steel reinforced and aluminium alloy
conductor overhead lines and aluminium alloy stranded conductor overhead lines.

4.3 Oman Electrical Standard OES 27


Volume 1 of the standard covers the design requirements for a 132/33kV, 2x125 MVA substation with
132kV gas insulated switchgear, including the 33kV switchgear. Volume 2 covers similar requirements
for the 132/33kV, 2x63 MVA substation with 132kV outdoor SF6 switchgear.

4.4 Oman Electrical Standard OES 32


The standard covers the design requirements for 132kV double circuit overhead transmission lines with
400mm2 All Aluminium Alloy Twin-Yew Conductors (AAAC) on lattice steel towers that are deployed
across much of the 132kV transmission system.

4.5 Other Standards


In cases where an Oman Electrical Standard is not applicable it is usual OETC practice to adopt the
appropriate related standards. This applies to the design of the 400kV, 220kV and 132kV transmission
systems. The internal OETC standard specifications include all others design requirements which are
currently not exist in above Oman Electrical Standard.

Page | 27
Five-Year Annual Transmission Capability Statement (2017 - 2021)

5. OETC Transmission System

5.1 Existing Transmission System


The Oman Electricity Transmission Company is authorized to undertake all regulated activities of
electricity transmission and dispatch in northern Oman and Dhofar at voltages of 132kV and above. The
existing transmission system in northern Oman has two operating voltages, i.e. 220kV and 132kV while in
Dhofar has only one operating voltage, i.e. 132kV. In 2016, the transmission system in northern Oman will
also have 400kV operating voltage .The existing transmission system extends across the whole of northern
Oman and interconnects bulk consumers and generators of electricity located in the Governorates of
Muscat, Batinah South, Batinah North, Dhahirah, Buraimi, Dakhliyah, Sharquiya South and Sharqiya
North.

The transmission system was first established under the Ministry of Electricity and Water (MEW) in 1983
and underwent rapid expansion during the 1990s. Consequently much of it has less than 15 year service
experience. After the electrical sector was unbundled, the OETC took over the operation of the MITS on
1st of May 2005 and Dhofar Transmission System on 1st of January 2014.

The present OETC transmission system at MITS consists of:

 884 circuit-km of 400kV overhead transmission lines

 1601.47 circuit-km of 220kV overhead transmission lines

 3394.89 circuit-km of 132kV overhead transmission lines

 67 circuit-km of 220kV underground cables

 153.83 circuit-km of 132kV underground cables

 8250 MVA of 400/220kV transformer capacity

 13630 MVA of 220/132kV transformer capacity

 320 MVA of 220/33kV transformer capacity

 16059 MVA of 132/33kV transformer capacity

 150 MVA of 132/11 kV transformer capacity

 Two 400/220kV interconnection grid stations

 Two 400/220/132/33kV grid stations

 Four 220kV interconnection grid stations

 Three 220/132kV grid stations

Page | 28
Five-Year Annual Transmission Capability Statement (2017 - 2021)

 One 220/33kV grid station

 Eight 220/132/33kV grid stations

 Forty Six 132/33kV grid stations

 Two 132/11 kV grid stations

In addition, the present OETC transmission system at Dhofar consists of:

 503.99 circuit-km of 132kV overhead transmission lines

 33.64 circuit-km of 132kV cables

 2062 MVA of 132/33kV transformer capacity

 Eight 132/33kV grid stations

The transmission system is interconnected with the transmission system of GCCIA Grid through UAE
(Transco Abu Dhabi) at Mahadha (Al Wasit) grid station through 220kV. The interconnection links the
electricity supply systems of Kuwait, Saudi Arabia, Bahrain, Qatar, UAE and Oman. This should increase
the security of supply and benefits to the member countries in the form of cost savings from the sharing of
reserve capacity and energy resources. The 220kV interconnector between OETC and Transco Abu Dhabi
has been energised and brought into service since 14th of November 2011. Oman recently has signed
officially the agreement with the GCCIA in November 2014 and became a member of GCC grid.

The OETC transmission system is also interconnected with the Sohar Aluminium system at 220kV via a
double circuit cable that runs between SPS on the OETC system and Sohar Aluminium 220kV busbar.
Under normal conditions the power transfer across the interconnection is forecasted to be negligible, but in
the event of an emergency on either network the interconnection can facilitate a power transfer of up to
300 MW to address the shortfall.

The OETC transmission system is also interconnected with the PDO transmission network at 132kV via a
single circuit overhead line that runs between Nizwa on the OETC system and Nahada on the PDO system.
Under normal conditions the power transfer across the interconnection is forecasted to be negligible, but in
the event of an emergency on either network the interconnection can facilitate a power transfer to address
the shortfall. In addition, OETC transmission system at Dhofar is also interconnected with the PDO
transmission network at 132kV via a single circuit overhead line that runs between Thumarit at OETC
system and Harweel at PDO system.

The transmission system at MIS area is supplied with electricity generated from eleven gas-based power
stations located at Ghubrah, Rusail, Wadi Jizzi, Manah, Al Kamil, Barka (ACWA), Barka SMN, Barka III,
Sohar I, Sohar II and Sur IPP. In addition, the transmission system may be supplied from direct customers,

Page | 29
Five-Year Annual Transmission Capability Statement (2017 - 2021)

such as Sohar Aluminium and PDO. The transmission system at Dhofar area is supplied with electricity
generated from two gas-based power stations located at NPS and Salalah-1 IWPP.

Four Distribution and Supply Licence holders, i.e. Muscat Electricity Distribution Company (MEDC),
Mazoon Electricity Company (MZEC), Majan Electricity Company (MJEC) and Dhofar Power Company
(DPC), take the bulk of the power transmitted through the main grid stations to supply the Distribution
system.

In addition to the four distribution companies, twelve large private customers are directly connected to the
transmission system. The existing private customers are:

 220kV Connections

i. Sohar Aluminium Smelter (connected to SPS)

ii. Jindal Shadeed Steel (connected to SIA)

 132kV Connections

i. Sohar Steel (connected to SIA)

ii. PDO (connected to Nizwa and Thumrait)

iii. Aromatics (connected to SIA)

iv. OMIFCO (connected to Sur)

v. VALE (connected to SIA)

vi. The New Muscat International Airport (connected to Airport Heights)

vii. Muscat Steel (connected to Rusail Industrial)

viii. Modern Steel (connected to Rusail Industrial)

ix. R.O Ghoubrah (connected to Ghoubrah)

x. Oman Alum. Rolling (connected to Liwa)

xi. Salalah International Airport (connected to Ittin)

The following new customers will be directly connected during the period covered by the Statement:

 Oman International Petrochemical Industrials Company will be connected to 132kV SIP-


A grid station in 2018.

 Orpic Plastic Company will be connected to 220kV SPS-2 grid station in 2018.

Page | 30
Five-Year Annual Transmission Capability Statement (2017 - 2021)

 Moon Steel Company will be connected to 220kV Sohar Free Zone in 2019.

 Salalah Methanol Company will be connected to 132kV Salalah Free Zone in 2019.

In 2016, MIS gross peak demand was 6105 MW which occurred at 15:30 hours on 12th June, an increase
of 6.28% on the 2015 peak demand. During 2016, the electric energy delivered to the MIS from connected
generating plants & other generators was 29,548.940 GWh whilst that exported from the MIS to the
Distribution Companies was 29,074.490 GWh resulting in transmission system energy losses of 474.450
GWh, which equates to a transmission system energy loss of 1.6 %.

In 2016, Dhofar system gross peak demand was 523 MW which occurred at 15:09 hours on 26th May, an
increase of 5.62% on the 2015 peak demand. During 2016, the electric energy delivered to the Dhofar
transmission system from connected generating plants & other generators was 3,057.166 GWh whilst that
exported from Dhofar system to Dhofar Power Company was 3,017.481 GWh resulting in transmission
system energy losses of 39.685 GWh, which equates to a transmission system energy loss of 1.3%.

5.2 Future System Development Projects


The power system studies presented later in this Capability Statement used to define the constraints and
opportunities that exist on the transmission system over the next five years. The power system studies have
been performed on the basis that the committed and planned development projects detailed in Appendix A
and summarised below will proceed as planned and be completed to the current schedule.

5.2.1 Projects completed to meet the 2017 peak demand


A geo-schematic diagram of the existing transmission system in 2017 is shown in Figure 1. In section 2.2
of this Statement it was noted that a number of projects had been completed since the published Capability
Statement 2016–2020, so that they were available to meet the peak demand of summer 2017. These projects
will provide load relief to some of the heavily loaded grid stations and transmission circuits in addition to
improving the voltage profile. The major planned projects to meet the 2017 peak are the new 220/132/33kV
grid station at Sohar Free Zone to supply the industrial loads in the area and a new 400/220/132/33kV grid
station at New Izki to support the voltage and power flow to Al Dakhliyah system from Sur Power Plant.
Furthermore, upgrading of Misfah from 220kV to 400kV to evacuate the generated power from Sur power
plant. In addition, number of projects are commissioned to meet the summer peak of 2017 which include
new 132/33kV grid station at Madinat Barka, Ibra, JBB Hassan, Dreez, S’aadah and Jebreen. Furthermore,
reinforcements projects such as adding third and fourth 132/33kV 125 MVA transformers at Liwa, Salalah
Free Zone and Muladah and replacing Mahadha 132kV AIS bays by new 132kV GIS bays are planned to
meet the Transmission Security Standard and the growth demand. Other projects that required to meet the
security standard in 2017 are the 33kV GIS linking of Bousher & Mawalleh South grid stations and the
linking project of Al Falaj, Muttrah and Wadi Kabir grid stations by one circuit of 132kV and adding fourth
transformer at Wadi Al Kabir grid station. Moreover, adding the 132kV GIS at Salalah Free Zone grid

Page | 31
Five-Year Annual Transmission Capability Statement (2017 - 2021)

station to connect the new Salalah-2 IPP power plant. Also, the construction of new 2x50 MVA 132/11kV
grid station at Daghmar to supply the new IWP at Quriyat.

5.2.2 Projects expected to be completed to meet the 2018 peak demand


Figure 2 shows in geo-schematic form the system development plan to meet the demand in 2018 peak
demand. The main investment to meet the 2018 peak in Muscat area is the new 400kV line of 100 km
between New Izki and Misfah is intended to evacuate the generated power from Sur power plant. The
projects designed to meet the 2018 system peak demand include the construction of new 132/33kV grid
stations at Uwaynat, Dil Abdusalam, Madinat Shinas, Suwaiq and Sinaw. Furthermore, upgrading of
Mawalleh North grid station from 3x50MVA (132/11kV) to 2x125MVA (132/33kV) transformers to
supply the area at Mawalleh. In addition, shifting 1x50 MVA transformer from Mawalleh North to Daghmar
132/11kV grid station to supply the new IWP at Quriyat. Furthermore, reinforcements at Madinate Barka
and Khadra are by adding the third and fourth 132/33kV transformers. Moreover, reinforcements at Barka-
3 PS grid station by adding 220/33kV 2x125 MVA transformers to supply the new Barka IWP. As a result
of reactive power compension study conducted by OETC, there is a need of shunt reactors to be installed
at the 400kV lines to control the voltage during the winter time where there the demand is low. Those
reactors are installed as follows; 2x40 MVAr at the “New Izki 400kV” end of the New Izki – Sur PS
400kV line, 2x30 MVAr at the “New Izki 400kV” end of the New Izki – Misfah 400kV line, 2x35 MVAr
at the “Sur PS” end of the Sur PS – Jahloot 400kV line. These reactors will support maintaining the voltage
within the allowable limit during the off peak time. The major investments to meet the 2018 peak are linked
to the connection of the new power plants at Ibri and Sohar. The main development projects are the new
400/220 kV grid station at Ibri and the 400kV line of 250km between Ibri and New Izki. In addition, the
220kV LILO to Ibri IPP from the line between Mahadha and Ibri grid stations. Also, adding four 400kV
circuits from Sohar III IPP to Sohar Free Zone, 400kV lines between Sohar Free Zone and SIS grid stations
and new 400kV line between Sohar Free Zone and Mahadha (will be operate at 220kV) grid stations to
evacuate power coming from New Sohar III IPP. Furthermore, upgrading projects are also required at
Mobella to 220kV to support Mobella demand and securing the area. In addition, upgrading Adam from
2x40MVA to 2x125 MVA to maintain the Transmission Security Standard requirements. Furthermore, to
meet the Transmission Security Standard at SIA grid station during the maintenance time, a new 220kV
circuit will be constructed with additional a 500MVA transformer. Moreover, a new 220kV GIS and fourth
125 MVA transformer will be installed at MSQ to cater the new demand and meet Transmission Security
Standard.

Page | 32
Five-Year Annual Transmission Capability Statement (2017 - 2021)

5.2.3 Projects expected to be completed to meet the 2019 peak demand


Figure 3 shows in geo-schematic form the system development plan to meet the 2019 system peak demand.
The new scheduled projects to meet the summer peak demand in 2019 are at various stages of development.
The projects planned to support 2019 network system include new 132/33kV grid stations at Ghala Heights,
Samad, Bedyah, Halban, Samail Industrial, Birkat Al Mouz, Wadi Bani Auwf with new 132kV double
circuit lines from Rustaq-Wadi Bani Auwf-Nakhal grid stations. Furthmore, adding third and fourth
transformers to meet the Transmission Security Standard & load growth will be at Ghala, Amerat, A’salam,
Bureimi Industrail, Sohar Free Zone and Airport Heights grid stations. In addition, upgrading Seeb from
2x63 MVA to 2x125 MVA transformers with 33kV GIS interlink. Furthermore, a new 220kV
Interconnection station will be added at Khabourah to meet the Transmission Security Standard
requirements. In addition, the development of the 400kV transmission systems includes upgrading of SIS
and Sohar Free Zone to 400kV with associate 132kV line between Sohar Free Zone to Shinas (Design as
400kV) and new Qabel 400kV by LILO Sur-New Izki 400kV OHL to the 400/132kV grid station at Qabel.
Also, Securing Bureimi demand group includes adding new 132kV line between Mahadha and Bureimi
grid stations. In addition, reactive power compensation (SVC) will be required to be installed at Muscat
area to maintain the voltage within the acceptable range during the disturbance.

5.2.4 Projects expected to be completed in time to meet the 2020 peak demand
Figure 4 shows in geo-schematic form the system arrangement to meet the 2020 peak demand. The new
projects planned to meet the summer peak demand in 2020 are at various stages of development. These
projects include new 132/33kV grid stations at Yanqul and Khoudh to cater the demand growth in these
areas. Furthermore, adding third and fourth 125MVA transformers to meet the Transmission Security
Standard and load growth will be at Ghubrah grid station.

5.2.5 Projects expected to be completed in time to meet the 2021 peak demand
Figure 5 shows in geo-schematic form the system arrangement to meet the 2021 peak demand. The new
projects planned to meet the summer peak demand in 2021 are at various stages of development. These
projects include new 132/33kV grid stations at Falaj Al Qabail, Madinat Ibri and Khuwair to cater the
demand growth in these areas. Furthermore, upgrading 2x30MVA transformers to 2x125MVA
transformers at Thumrait grid station to meet the Transmission Security Standard and load growth. In
addition, the developments to evacuate the power coming from Misfah IPP Power Plant include a new
220kV connection at Misfah IPP, LILO the existing 220kV line between MSQ and Misfah grid stations and
adding 220/132kV, 2x500MVA transformers at existing Misfah grid station. Also, the projects

Page | 33
Five-Year Annual Transmission Capability Statement (2017 - 2021)

development of 2021 include upgrading Rusail Industrial grid station to 400kV and adding third 220/132kV
transformer at Airport Heights grid station.

5.3 Summary
Table 1 in the Executive Summary has summarised the development plans for the OETC Transmission
System on a project by project basis at the time of this statement. The table identifies the projects to which
OETC are already committed and those projects that are considered likely to proceed. The power system
studies presented in this capability statement is to show the expected performance of the transmission
system over the period 2017-2021. In addition, the studies have been performed on the basis that the
committed and planned development projects in Table 1 and detailed in Appendix A will proceed as planned
and to be completed on schedule. The system studies are used to identify areas of the transmission system
where there are opportunities for connecting new demand and new generation and where constraints should
be applied to further development.

Page | 34
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Figure 1: Existing MITS in Peak 2017

Page | 35
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Figure 2: Existing MITS in Peak 2018

Page | 36
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Figure 3: MITS expected development by Peak 2019

Page | 37
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Figure 4: MITS expected development by Peak 2020

Page | 38
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Figure 5: MITS expected development by Peak 2021

Page | 39
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Figure 6: Dhofar existing transmission system in Peak 2017

Page | 40
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Figure 7: Dhofar System expected development by Peak 2018

Page | 41
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Figure 8: Dhofar System expected development by Peak 2019

Page | 42
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Figure 9: Dhofar System expected development by Peak 2020

Page | 43
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Figure 10: Dhofar System expected development by Peak 2021

Page | 44
Five-Year Annual Transmission Capability Statement (2017 - 2021)

6. Existing and Planned Developments in Generation

6.1 Existing Generation


6.1.1 Existing generation of MIS

Eleven gas-based power stations supply MIS transmission system in 2017:

 Ghubrah and Rusail in Muscat region

 Barka (ACWA), Barka SMN and Barka III in Al Batinah South region

 Manah in Al Dakhilya region

 Al Kamil and Sur IPP in Al Sharqiyah region

 Sohar I and Sohar II in North Al Batinah region

 Wadi Jizzi in Al Bureimi region


The eleven power stations are described briefly below:
a) Ghubrah Power and Desalination Plant
The initial development of Ghubrah Power Station started in 1976 and the installation of the power and
desalination plant was accomplished in six phases, four of which included the commissioning of new
generating units. The layout of the site is complex and is a mixture of ten gas turbines and two steam
turbines currently running of various ratings. The net generation capacity is approximately 405 MW.
b) Rusail Power Station
Rusail Power Station is located in the Rusail Industrial Estate. The power station has eight Frame 9E gas
turbines installed and operating in open-cycle. The gross site rating of the units varies from 82 MW to 96
MW. The units were installed progressively between 1984 and 2000. The net generation capacity of the
power station is approximately 689 MW.
c) Wadi Jizzi Power Station
Wadi Jizzi Power Station comprises eleven gas turbines (with gross site ratings in the range of 18 - 35 MW)
where are all operating in open cycle. The units were installed progressively from 1982 and the net
generation capacity is approximately 326 MW.
d) Manah Power Station
Manah Power Station is owned by the United Power Company and when commissioned in 1996 was the
first Independent Power Project (IPP) to be built in Oman. The station comprises three GE PG6541B gas
turbines (each site rated at 28MW) and two GE PG9171E gas turbines (site ratings of 91 MW). The net
generation capacity is approximately 264 MW.

Page | 45
Five-Year Annual Transmission Capability Statement (2017 - 2021)

e) Al Kamil Power Station


Al Kamil Power Station is another IPP and was commissioned in 2002. The station comprises three GE
PG9171E gas turbines (site rating 93MW) operating in open cycle and the net generation capacity is
approximately 280 MW.
f) Barka Power Plants
There are three power stations in Barka:
1. The BarkaI Power and Desalination Plant was commissioned in 2003 by AES (ACWA
recently) and was developed as an Independent Water & Power Plant (IWPP). The power
plant comprises two Ansaldo V94.2 gas turbines with capacity of 108 MW and a steam
turbine operating in combined cycle with capacity of 220 MW. The net generation capacity
is approximately 435 MW.
2. The Barka II SMN plant is an Independent Water & Power Plant (IWPP) and was
commissioned in 2009. There are three gas turbines of 123 MW capacity each and two
steam turbines of 160 MW capacity each. The net generation capacity is approximately
663MW.
3. Barka III Power Plant is an Independent Power Plant (IPP) and was commissioned in 2012.
There are two gas turbines of 254 MW capacity each and a steam turbine of 247 MW
capacity each is available in 2017. The net generation capacity is approximately 754 MW
in 2017.
g) Sohar Power Plants
1. Sohar I Power and Desalination Plant was also developed as an IWPP by the Sohar Power
Company. The plant consists of three Siemens V 94.2 gas turbines (site rating 126 MW),
a steam turbine (site rating 220 MW) and four desalination units. The three gas turbines
came into service during summer 2006. The net power plant capacity is approximately 597
MW.
2. Sohar II Power Plant is an Independent Power Plant (IPP) and was commissioned in 2012.
There are two gas turbines of 254 MW capacity each are and a steam turbine of 247 MW
capacity each is available in 2017. The total generation capacity is approximately 754 MW
in 2017.
h) Sur Power Plants
Sur Independent Power Plant (IPP), which was commissioned in 2014. There are five gas turbines of 243
MW capacity and three steam turbines (ST1& ST2) with capacity of 309 MW while the capacity of ST3 is
155 MW. In 2017 the total capacity will reach approximately 1988MW working in a combined cycle.

Page | 46
Five-Year Annual Transmission Capability Statement (2017 - 2021)

6.1.2 Existing generation of Dhofar

Two gas-based power stations supply Dhofar transmission system in 2017:

 NPS Power Plant

 Salalah IWPP Power Plant


The two power stations are described briefly below:
a) NPS Power Plant
The initial development of NPS Power Plant started in 2002. The power plant has eight gas turbines which
six of them connectd to 132kV system while the other two are connected to 33kV system. They are
operating in open-cycle and the gross site rating of the units varies from 19.9 MW to 37 MW. The net
generation capacity of the power station is approximately 273.4 MW.
b) Salalah IWPP
Salalah Power Plant was commissioned in 2010 and developed as an Independent Water and Power Plant
(IWPP). It has five gas turbines installed with rate of 56 MW and two steam turbines with rate of 82 MW.
The net generation capacity of the power station is approximately 429 MW.

Page | 47
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Table 3 lists on a yearly basis the existing and committed future generating capacity over the period 2017-
2021. The table presents the gross and net maximum capacity for each generating unit at each power station
and takes account of the desalination load where appropriate.

Table 3: Existing and committed future generating capacity


Net Generating Capacity (MW)
Power Station Type Unit
2017 2018 2019 2020 2021
MIS
Steam
ST 4 0 0 0 0 0
Turbine
Steam
ST 5 32 0 0 0 0
Turbine
Steam
ST 6 31 0 0 0 0
Turbine
Gas Turbine GT1 17 17 0 0 0
Gas Turbine GT2 18 18 0 0 0
Gas Turbine GT3 18 18 0 0 0
Gas Turbine GT4 18 18 0 0 0
Gas Turbine GT5 0 0 0 0 0
Al-Ghubrah Power & Desalination Gas Turbine GT6 18 18 0 0 0
Gas Turbine GT7 18 18 0 0 0
Gas Turbine GT8 0 0 0 0 0
Gas Turbine GT9 18 18 0 0 0
Gas Turbine GT10 27 27 0 0 0
Gas Turbine GT11 0 0 0 0 0
Gas Turbine GT12 96 96 0 0 0
Gas Turbine GT13 96 96 0 0 0
Gen sub-total 405 341 0 0 0
Desalination load 28 0 0 0 0
Net Generation 377 341 0 0 0
Gas Turbine GT 1 82 82 82 82 82
Gas Turbine GT 2 82 82 82 82 82
Gas Turbine GT 3 82 82 82 82 82
Gas Turbine GT 4 84 84 84 84 84
Rusail IPP Gas Turbine GT 5 84 84 84 84 84
Gas Turbine GT 6 84 84 84 84 84
Gas Turbine GT 7 96 96 96 96 96
Gas Turbine GT 8 95 95 95 95 95
Net Generation 689 689 689 689 689

Page | 48
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Table 3 (continued): Existing and committed future generating capacity


Net Generating Capacity (MW)
Power Station Type Unit
2017 2018 2019 2020 2021
MIS
Gas Turbine GT3 18 18 0 0 0
Gas Turbine GT4 29 29 0 0 0
Gas Turbine GT5 28 28 0 0 0
Gas Turbine GT6 28 28 0 0 0
Gas Turbine GT7 28 28 0 0 0
Gas Turbine GT8 29 29 0 0 0
Wadi Al-Jizzi
Gas Turbine GT9 33 33 0 0 0
Gas Turbine GT10 33 33 0 0 0
Gas Turbine GT11 32 32 0 0 0
Gas Turbine GT12 35 35 0 0 0
Gas Turbine GT13 34 34 0 0 0
Net Generation 326 326 0 0 0
Gas Turbine GT1A 28 28 28 28 28
Gas Turbine GT1B 28 28 28 28 28
Gas Turbine GT1C 28 28 28 28 28
Manah IPP
Gas Turbine GT2A 91 91 91 91 91
Gas Turbine GT2B 91 91 91 91 91
Net Generation 264 264 264 264 264
Gas Turbine GT 1A 93 93 93 93 93
Gas Turbine GT 1B 93 93 93 93 93
Al Kamil IPP
Gas Turbine GT 1C 93 93 93 93 93
Net Generation 280 280 280 280 280
Gas Turbine GT 1 108 108 96 96 96
Gas Turbine GT 2 108 108 96 96 96
Steam
ST 220 220 196 196 196
Barka I Power & Desalination Turbine
Gen sub-total 435 435 388 388 388
Desalination load 25 25 0 0 0
Net Generation 410 410 388 388 388
Gas Turbine GT 1 123 123 123 123 123
Gas Turbine GT 2 123 123 123 123 123
Gas Turbine GT 3 123 123 123 123 123
Steam
ST1 160 160 160 160 160
Turbine
Barka II Power & Desalination
Steam
ST2 160 160 160 160 160
Turbine
Gen sub-total 688 688 688 688 688
RO load 25 25 25 25 25
Net Generation 663 663 663 663 663

Page | 49
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Table 3 (continued): Existing and committed future generating capacity


Net Generating Capacity (MW)
Power Station Type Unit
2017 2018 2019 2020 2021
MIS
Gas Turbine GT 1 254 254 254 254 254
Gas Turbine GT 2 254 254 254 254 254
Barka III Power & Desalination Steam
ST 247 247 247 247 247
Turbine
Net Generation 754 754 754 754 754
Gas Turbine GT 1 126 126 126 126 126
Gas Turbine GT 2 126 126 126 126 126
Gas Turbine GT 3 126 126 126 126 126
Steam
Sohar Power & Desalination ST 220 220 220 220 220
Turbine
Gen sub-total 597 597 597 597 597
Desalination load 31 31 31 31 31
Net Generation 566 566 566 566 566
Gas Turbine GT 1 254 254 254 254 254
Gas Turbine GT 2 254 254 254 254 254
Sohar II Power & Desalination Steam
ST 247 247 247 247 247
Turbine
Net Generation 754 754 754 754 754
Gas Turbine GT 1 243 243 242 242 242
Gas Turbine GT 2 243 243 242 242 242
Steam
ST1 309 309 309 308 308
Turbine
Gas Turbine GT 3 243 243 242 242 242
Sur IPP Gas Turbine GT 4 243 243 242 242 242
Steam
ST2 309 309 309 308 308
Turbine
Gas Turbine GT 5 243 243 242 242 242
Steam
ST3 155 155 155 155 155
Turbine
Net Generation 1988 1985 1983 1982 1982
Gas Turbine GT 1 0 235 235 235 235
Gas Turbine GT 2 0 235 235 235 235
Steam
ST1 0 0 284 284 284
Turbine
Ibri IPP Gas Turbine GT 3 0 235 235 235 235
Gas Turbine GT 4 0 235 235 235 235
Steam
ST2 0 0 284 284 284
Turbine
Net Generation 0 940 1508 1508 1508

Page | 50
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Table 3 (continued): Existing and committed future generating capacity


Net Generating Capacity (MW)
Power Station Type Unit
2017 2018 2019 2020 2021
MIS
Gas Turbine GT 1 0 0 264 264 264
Gas Turbine GT 2 0 0 264 264 264
Steam
ST1 0 0 326 326 326
Turbine
Sohar III IPP Gas Turbine GT 3 0 0 264 264 264
Gas Turbine GT 4 0 0 264 264 264
Steam
ST2 0 0 326 326 326
Turbine
Net Generation 0 0 1708 1708 1708
Combine Cycle 0 0 0 0 1000
Misfah IPP
Net Generation 0 0 0 0 1000
Dhofar
Gas Turbine GT1 37 37 37 37 37
Gas Turbine GT2 37 37 37 37 37
Gas Turbine GT3 37 37 37 37 37
Gas Turbine GT4 37 37 37 37 37
NPS IPP Gas Turbine GT5 37 37 37 37 37
Gas Turbine GT6 37 37 37 37 37
Gas Turbine GT7 20 20 20 20 20
Gas Turbine GT8 31 31 31 31 31
Net Generation 273 273 273 273 273
Gas Turbine GT 1 56 56 56 56 56
Gas Turbine GT 2 56 56 56 56 56
Gas Turbine GT 3 56 56 56 56 56
Gas Turbine GT 4 56 56 56 56 56
Gas Turbine GT 5 56 56 56 56 56
Salalah IWPP Steam
ST1 82 82 82 82 82
Turbine
Steam
ST2 82 82 82 82 82
Turbine
Gen sub-total 444 444 444 444 444
Desalination load 15 15 15 15 15
Net Generation 429 429 429 429 429
Gas Turbine GT 1 0 69 69 69 69
Gas Turbine GT 2 0 69 69 69 69
Steam
ST1 0 84 84 84 84
Turbine
Salalah-2 IPP Gas Turbine GT 3 0 68 68 68 68
Gas Turbine GT 4 0 68 68 68 68
Steam
ST2 0 80 80 80 80
Turbine
Net Generation 0 438 438 438 438

Page | 51
Five-Year Annual Transmission Capability Statement (2017 - 2021)

6.2 Planned Retirements of Existing Plant


There are a number of planned retirements of the existing units from 2017 to 2021. The planned retirements
are as follows:

a) Ghubrah Power and Desalination Plant

Four generating units has been retired in 2015 (ST4, GT5, GT8, and GT11). In addition, it is planned to
retire two units (ST5 and ST6) by end of 2017 and the remining existing generating units will be retire by
end of 2018.

b) Wadi Al-Jizzi Power Plant

At end of 2018, it is planned to retire all existing generating units.

6.3 Planned Future Generation (2017-2021)

6.3.1 Planned Future Generation at MIS


There are three main generation developments planned for the period 2017 to 2021:

a) Ibri Power Station (IPP)

Ibri Independent Power Plant (IPP) will be commissioned in 2018 & 2019. In 2018 the total capacity will
reach 940 MW working in a combined cycle. Ibri Independent Power Plant (IPP) will reach the full power
of 1508 MW in 2019.

b) Sohar III Power Station (IPP)

Sohar III Independent Power Plant (IPP) will be commissioned in 2019. In 2019, the total capacity will
reach 1708 MW working in a combined cycle.

c) Misfah IPP

Misfah Independent Power Plant (IPP) will be commissioned in 2020. In 2021, the total estimated capacity
will reach 1000 MW working in a combined cycle.

Page | 52
Five-Year Annual Transmission Capability Statement (2017 - 2021)

6.3.2 Planned Future Generation at Dhofar


The main generation development planned for the period 2017 to 2021:

a) Salalah-2 (IPP)

Salalah-2 Independent Power Plant (IPP) will be commissione in 2018. The total capacity will reach 437.8
MW working in a combined cycle.

6.3.3 Wind Farm Plant


The wind farm plant will be commissione in 2019 with the total capacity of 50 MW. This wind farm will
be located at Thumrait area and will connect to the transmission system of Dhofar.

Table 4 summarises the net capacity of the additional future generating plant over the period 2017 to 2021.

Table 4: New Contracted and Planned Generating Capacity


Net Generating Capacity (MW)
Power Station Type
2017 2018 2019 2020 2021
MIS System

Ibri IPP Net Generation 0 940 1508 1508 1508

Sohar III IPP Net Generation 0 0 1708 1708 1708

Misfah IPP Net Generation 0 0 0 0 1000

Dhofar System

Salalah-2 IPP Net Generation 0 437.8 437.8 437.8 437.8

Wind Farm Net Generation 0 0 50 50 50

6.4 Non-Contracted Generating Capacity


There are a number of private industrial customers directly connected to the transmission system that either
operate or plan to operate their own on-site generation. The largest generating plant among these is Sohar
Aluminium, which may export up to 300 MW during the summer period and import the same during the
winter time. The interconnected system and the private customer generating plants can be made available
with the customer’s agreement to support the contracted generation under emergency conditions in order
to avoid power cuts in northern Oman. These generators are termed “non-contracted” generating plants.

Table 5 shows the non-contracted generating capacity for the period 2017 to 2021.

Page | 53
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Table 5: Non-Contracted Generating Capacity


Net Generating Capacity (MW)
Power Station
2017 2018 2019 2020 2021
MIS
UAE Interconnector 200 200 200 200 200
PDO 60 60 60 60 60
Sohar Aluminium 300 300 300 300 300
Oman Cement Company (OCC) 0-5 0-5 0-5 0-5 0-5
Ministry of Defense 0-5 0-5 0-5 0-5 0-5
Oman India Fertilizer CO 0-5 0-5 0-5 0-5 0-5
Net Generation 575 575 575 575 575

Table 6 summarises the Centrally Dispatched Net Generation Capacity available over the period 2016–
2021, with the new generation at Salalah-2 IPP, Ibri IPP, Sohar III and Misfah IPP plant in service with the
planned retirement of generating units at Ghubrah and Wadi Al-Jizzi Power Plants.

Table 6: Centrally Dispatched Generating Capacity on OETC Transmission System


Net Generating Capacity (MW)
Power Stations
2016 2017 2018 2019 2020 2021
MIS System
Ghubrah Power & Desalination 377 377 341 0 0 0
Rusail 689 689 689 689 689 689
Wadi Al-Jizzi 326 326 326 0 0 0
Manah 264 264 264 264 264 264
Al Kamil 280 280 280 280 280 280
Barka I Power & Desalination 410 410 410 388 388 388
Sohar I Power & Desalination 566 566 566 566 566 566
Barka II 663 663 663 663 663 663
Barka III 754 754 754 754 754 754
Sohar II 754 754 754 754 754 754
Sur 1988 1988 1985 1983 1982 1982
Sohar III IPP 0 0 0 1708 1708 1708
Ibri IPP 0 0 940 1508 1508 1508
Misfah IPP 0 0 0 0 0 1000
Total Generating Capacity (MW) 7072 7072 7974 9559 9557 10557
Retirements 0 0 36 667 0 0
Dhofar System
Salalah IWPP 429 429 429 429 429 429
NPS 273 273 273 273 273 273
Salalah-2 IPP 0 0 437.8 437.8 437.8 437.8
Total Generating Capacity (MW) 702 702 1140 1140 1140 1140
Retirements 0 0 0 0 0 0

Page | 54
Five-Year Annual Transmission Capability Statement (2017 - 2021)

6.5 Interconnections
6.5.1 Interconnection with the GCCIA Grid through UAE (Transco Abu Dhabi)

The 220kV transmission interconnection with the United Arab Emirates (Transco Abu Dhabi) was
completed in the first quarter of 2007. The interconnection connects Mahadha grid station in Oman
(Al Wasit) to Auha grid station in Al Ain in the UAE. In the longer term, the principal technical benefit to
be obtained from connecting Oman to the GCCIA Grid is in a reduced spinning reserve requirement, which
will be shared between the members of the GCCIA Grid. However, operation of the interconnection will
allow Oman to import/export power from the GCCIA Grid to meet any potential generation shortfall. Oman
has singed officially the agreement with the GCCIA in November 2014 and become a part of state members.

6.5.2 Interconnection with PDO

OETC transmission system is interconnected with the transmission system of the Petroleum Development
Oman (PDO) which provides electricity to its sites across the central region of Oman for the purpose of oil
exploration and development. The interconnection is made at 132kV between Nizwa grid station on the
OETC system and Nahda 132kV station on PDO 132kV network by a 67 km overhead line. The overhead
line is owned by PDO. Under normal conditions the power transfer between the two networks is allowed
to float around zero MW, with power transfers balanced out over a period.
In addition, Dhofar transmission system is interconnected with the transmission system of the Petroleum
Development Oman (PDO). The interconnection is made at 132kV between Thumrait grid station on the
Dhofar system and Harweel 132kV station on PDO 132kV network by 84.5 km overhead line. The
interconnection essentially allows OETC and PDO to supply limited power to each other in emergency
conditions on either system.

6.6 Economic Dispatch


The Load Dispatch Centre of OETC dispatches generation based on its availability as stated by the
Generator on a day-ahead basis, and its price as listed by the Oman Power and Water Procurement Company
(OPWP). Under circumstances where the system frequency is seen to stray outside the specified limits,
LDC will issue dispatch instructions to Generators based on Merit Order to rectify the situation.

6.7 Spinning Reserve


The Load Dispatch Centre strives to maintain a spinning reserve equal to the rating of the largest generating
unit connected to the transmission system. In case of combined cycle power plant, the spinning reserve
equals the largest gas turbine unit plus its share in the steam turbine unit.

Page | 55
Five-Year Annual Transmission Capability Statement (2017 - 2021)

7. Demand Forecast and Generation Availability

7.1 System Demand


Maximum demand usually occurs on the OETC transmission system on weekdays in the summer months
(May, June or July), during a period of particularly high temperature and humidity. The growth in air
conditioning equipment in domestic and commercial premises in Oman has ensured that peak demand
usually occurs during the early morning or afternoon. Figures 11 and 12 show the 24-hour demand profile
for the transmission system on the day of the 2016 system peak demand (i.e. 12/06/2016 MIS System and
26/05/2016 Dhofar System). The 2016 MIS system peak demand of 6105 MW was recorded at 15:30 hours
and 2016 Dhofar system peak demand of 523 MW was recorded at 15:09 hours by OETC Load Dispatch
Centre. The historic growth in system peak demand over the period (2003-2016) is shown in Table 7.

Max Demand Profile


7000

6000

5000
Load (MW)

4000

3000

2000

1000

Time (hrs)

Figure 11: MIS Load on 2016 Peak Day

Page | 56
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Max Demand Profile


600

500

400
Load (MW)

300

200

100

Time (hrs)

Figure 12: Dhofar System Load on 2016 Peak Day

Table 7: Historic Growth in Peak Demand and Transmission Losses (2003 – 2016)

2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

MIS System
System Max
Demand
(MW) based 2232 2371 2495 2613 2773 3139 3546 3614 4000.3 4448 4634 5269 5744 6105
on gross
demand
Annual
growth rate
based on - 6.2 5.2 4.7 6.1 13 12.9 1.9* 10.7 11.2 4.18 13.7 9.015 6.28
gross
demand (%)
System Max
Demand
(MW) based 2139 2294 2395 2505 2662 3033 3342 3504 3765.1 4247.34 4327.9 4872 5472 5826
on net
demand
Transmission
System
Losses (MW) 35 38 40 37 40 61 80 60 61.9 53.8 114.6 165 93.2 94.5
at system
peak
Transmission
System 1.64 1.66 1.67 1.47 1.5 2 2 1.7 1.6 1.3 2.64 3.4 1.7 1.6
Losses (%)
*The reduction in the annual growth is due to the Phet Cyclone

Page | 57
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Table 7 (continued): Historic Growth in Peak Demand and Transmission Losses (2003 – 2016)

2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Dhofar System
System Max
Demand
(MW) based 178.3 180.9 199.3 232.3 253 260.4 297.4 336.2 348 389.3 421.7 438.9 495 523
on gross
demand
Annual
growth rate
based on - 1.40 10.23 16.56 8.91 2.92 8.99 18.75 3.26 11.87 8.32 3.8 12.78 5.6
gross
demand (%)
System Max
Demand
(MW) based - - - - - - - - - - - 427 472.9 513.3
on net
demand
Transmission
System
Losses (MW) - - - - - - - - - - - 3.6 14.5 2
at system
peak
Transmission
System - - - - - - - - - - - 0.84 3.066 0.390
Losses (%)

Minimum demand generally occurs on the transmission system during night-time in winter month
(December/January) when electricity consumption in all major load categories is reduced. In 2016, the
MIS system minimum demand was 1917 MW and this occurred on 01/01/2016 at 07:06 AM and 2016
Dhofar system minimum demand was 181 MW and this occurred on 06/02/2016 at 07:14 AM. The 2016
system minimum demand at MIS system was about 31.40 % and at Dhofar system was about 34.60 % of
2016 system peak demand. The 24-hour profile for the day of minimum demand is shown in Figures 13 &
14.

Page | 58
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Min Demand Profile


3000
2500
2000
Load (MW)

1500
1000
500

Time (hrs)

Figure 13: MIS Load on 2016 Minimum Load Day

Min Demand Profile


300

250

200
Load (MW)

150

100

50

Time (hrs)

Figure 14: Dhofar System Load on 2016 Minimum Load Day

Page | 59
Five-Year Annual Transmission Capability Statement (2017 - 2021)

7.2 Demand Forecast


Under clause 3 of Condition 27 of OETC Transmission and Dispatch Licence it is stated that:

“The Licensee shall, when preparing the Capability Statement ….ensure that the forecasts of electricity
flows and loading on each part of the Transmission System are consistent with the prevailing electricity
demand forecasts prepared and used by the OPWP for the purposes of the Statement of future capacity
requirements required by Condition 5 of the OPWP licence”.

The OPWP demand forecast is based on data supplied to them by the four Distribution Companies (i.e.
Muscat EDC, Mazoon EC, Majan EC and Dhofar PC) which also includes demand forecasts for the major
customers that are, or will be, directly connected to OETC transmission system at either 220kV or 132kV
in their respective supply areas. In addition, Distribution Companies have provided demand forecast data
to OETC taking into account the individual load at each supply connection points. The Distribution
Companies forecast are provided in terms of:

a) The growth in major industrial loads

b) The growth in major tourism loads

c) The annual domestic growth

d) The growth in major commercial loads

The forecast supplied to OPWP relate to the total for each Distribution Company and do not indicate how
this load is allocated to the individual grid supply points. The forecast data provided to OPWP includes
major future connections and the cumulative increase in load over the seven-year period covered by the
OPWP Statement. OPWP has then reviewed this data and taken a view as to the probability that the
individual schemes will proceed and if so, the rate at which their load will develop. The outcome of this
review is presented as OPWP demand forecast in its Seven-Year Statement.

The OPWP demand forecast was therefore taken as the starting point for developing the demand forecast
presented in this OETC Capability Statement. The OETC forecast, however, is required to identify the
future demand at individual grid stations at the system peak for each year over the period 2017 to 2021,
since this information is required for the power flow studies.

Analysis of the demand forecast data used by OPWP in developing its Seven-Year Statement (2016-2022)
identified basic annual percentage rates of 8 % for the growth in peak demand in the Mazoon EC, Muscat
EDC and Majan EC supply areas and 9 % for the growth in peak demand in the DPC supply area. These
rates have been applied to the grid station demands in the respective supply areas as noted by the OETC
Load Dispatch Centre at the 2016 MIS system peak (i.e. 12/06/2016, 15:30 hour) and 2016 Dhofar system
peak (i.e.26/05/2016, 15:09 hour). The demand associated with major industrial and tourism projects as
assessed by OPWP (with diversity taken into account) was then superimposed on to the steady growth in
the basic demand to produce a basic forecast. Section 5 identified a number of new grid supply points that

Page | 60
Five-Year Annual Transmission Capability Statement (2017 - 2021)

are scheduled to come into service to meet the summer peak demands from 2016 onwards. These gird
stations will provide load relief to the more heavily loaded grid stations and in some cases supply new
loads.

The Distribution Companies’s plans for load transfers from existing grid stations that are heavily loaded to
new grid stations are one of the most important elements of the demand forecast. Table 8 summarises the
load transfers adopted in the studies based on consideration of what is required and what OETC has
considered viable. However, OETC acknowledges that this aspect of the forecast needs to be improved in
future and believes that it would be helpful if distribution companies were to give greater consideration to
feasible load transfers when planning their distribution networks, and to develop proposals for load transfers
in coordination with OETC. Also, the TSS requirement shall be considered at every grid supply point and
all new requirements shall be indicated clearly.

Page | 61
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Table 8: Expected Load Transfers between Grid Supply Points (2017-2021)


Load Transfer (MW)
From Grid Station To Grid Station
2017 2018 2019 2020 2021
Muscat Area
Rusail Industrial TX-1 & TX-2 Rusail Industrial TX-3 & TX-4 72
Rusail Industrial TX-1 & TX-2 Khoud TX-3 & TX-4 30
Rusail Industrial TX-3 & TX-4 Khoud TX-1 & TX-2 20
Ghubrah 2x42 MVA Ghubrah TX-1 & TX-2 7
Ghubrah TX-1 & TX-2 Ghubrah TX-3 & TX-4 60
Wadi Adai Amerat TX-3 & TaX-4 15
Wadi Kabir TX-1 & TX-2 Wadi Kabir TX-3 & TX-4 25
Wadi Kabir TX-1 & TX-2 Mutrrah 2
Wadi Kabir TX-3 Wadi Kabir TX-3 & TX-4 54.6
Al Falaj Mutrrah 5
MSQ TX-1 & TX-2 Qurum 23
MSQ TX-1 & TX-2 Ghubrah TX-1 & TX-2 2
MSQ TX-1 & TX-2 MSQ TX-3 & TX-4 39
MSQ TX-3 Qurum 3
MSQ TX-3 MSQ TX-1 & TX-2 5
MSQ TX-3 Bousher TX-1 & TX-2 5
MSQ TX-3 MSQ TX-3 & TX-4 35.4
Mawalleh South TX-1 & TX-2 Mawalleh South TX-3 & TX-4 30 25
Mawalleh South TX-1 & TX-2 Seeb Main 2x63MVA 6
Mawalleh South TX-1 & TX-2 Mawalleh North 2X125MVA 33
Mawalleh South TX-1 & TX-2 Khoud TX-1 & TX-2 22
Mawalleh South TX-3 & TX-4 Seeb Main 2x63MVA 4
Mawalleh South TX-3 & TX-4 Seeb Main TX-3 & TX-4 12
Mawalleh South TX-3 & TX-4 Mawalleh North 2X125MVA 18
Mawalleh South TX-3 & TX-4 Seeb Main TX-3 & TX-4 6
Mawalleh South TX-3 & TX-4 Khoud TX-1 & TX-2 28
Seeb Main 2x63 MVA Mawalleh North 2X125MVA 17
Seeb Main 2x63 MVA Seeb Main TX-3 & TX-4 69.8
Seeb Main TX-1 & TX-2 Seeb Main TX-3 & TX-4 28
Seeb Main TX-1 & TX-2 Khoud TX-3 & TX-4 15
Seeb Main TX-3 & TX-4 Khoud TX-3 & TX-4 25
Mawalleh North 3X50MVA Mawalleh North 1X50MVA 21.1
Mawalleh North 1X50MVA Mawalleh North 2X125MVA 21.9
Bousher TX-1 & TX-2 Ghubrah TX-1 & TX-2 4
Bousher TX-1 & TX-2 MSQ TX-1 & TX-2 5 3
Bousher TX-1 & TX-2 Ghala TX-1 & TX-2 38
Bousher TX-1 & TX-2 Ghala Hieght TX-1 & TX-2 50
Bousher TX-1 & TX-2 Khuwair 25
Bousher TX-3 & TX-4 Ghubrah TX-1 & TX-2 6 10
Bousher TX-3 & TX-4 Ghala TX-1 & TX-2 20
Bousher TX-3 & TX-4 Bousher TX-1 & TX-2 10
Bousher TX-3 & TX-4 Ghala Hieght TX-3 & TX-4 52
Bousher TX-3 & TX-4 Khuwair 25
Mobella A'ssalam TX-1 & TX-2 24
Mobella Halban TX-1 & TX-2 39
A'ssalam TX-1 & TX-2 A'ssalam TX-3 & TX-4 15

Page | 62
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Table 8 (continued): Expected Load Transfers between Grid Supply Points (2017-2021)
Load Transfer (MW)
From Grid Station To Grid Station
2017 2018 2019 2020 2021
Muscat Area
A'ssalam TX-1 & TX-2 Halban TX-3 & TX-4 60
A'ssalam TX-3 & TX-4 Halban TX-1 & TX-2 20
Airport Heights TX-1 & TX-2 Ghala TX-1 & TX-2 22
Airport Heights TX-1 & TX-2 Airport Heights TX-3 & TX-4 53
Ghala TX-1 & TX-2 Ghala TX-3 & TX-4 45
Amerat TX-1 & TX-2 Amerat TX-3 & TX-4 60
Total (MW) 364.7 227.3 528.8 200.0 50.0
Mazoon Area
Barka Main TX-1 & TX-2 Madinat Barka TX-1 & TX-2 46.5
Barka Main TX-1 & TX-2 A'ssalam TX-1 & TX-2 9
Barka Main TX-1 & TX-2 Barka IPP 31
Barka Main TX-1 & TX-2 Madinat Barka TX-3 & TX-4 37
Barka Main TX-1 & TX-2 A'ssalam TX-3 & TX-4 64
Barka Main TX-3 Barka Main TX-1 & TX-2 58.9
Muladah TX-1 & TX-2 Muladah TX-3 & TX-4 54.8 15
MIS Khadhra TX-3 & TX-4 54
MIS Suwaiq 68.1
Rustaq Wadi Bani Auwf 53
Sumail 2X63MVA Sumail Industrial Area 10
Sumail 2X125MVA Sumail 2X63MVA 10
Sumail 2X125MVA Sumail Industrial Area 50
Izki 2X125MVA New Izki 14 23
Nizwa Birkat Al Mouz 62.6
Bahla Jebreen 60.4
Adam 2X40MVA Adam 2X125MVA 55.6
Mudhaibi 2X125MVA Sinaw 50
Mudhaibi 2X125MVA Samad 31.3
Mudhairib Ibra 76.6
Mudhairib Bedyah 35
JBB Ali JBB Hassan 87.6
Total (MW) 348.9 402.6 305.9 0 0

Page | 63
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Table 8 (continued): Expected Load Transfers between Grid Supply Points (2017-2021)
Load Transfer (MW)
From Grid Station To Grid Station
2017 2018 2019 2020 2021
Majan Area
Ibri 2X63MVA Dreez 23.9
Ibri 2X63MVA Ibri 2X125MVA 4 2 15.8
Ibri 2X63MVA Madinat Ibri 18.8
Ibri 2X125MVA Dreez 34.1
Ibri 2X125MVA Madinat Ibri 30
Al Hayl Dreez 16.5
Al Hayl Dank 4
Al Hayl Yanqual 32.9 4
Dreez Madinat Ibri 15.2
Mahadah Wadi Sa'a 6.8
Bureimi Buriami Industrial TX-1 & TX-2 3
Bureimi Buriami Industrial TX-3 & TX-4 38.3
Buriami Industrial TX-1 &
Buriami Industrial TX-3 & TX-4 15.4
TX-2
Shinas 2X125MVA Liwa TX-1 & TX-2 6
Shinas 2X125MVA Madinat Shinas 61.3
Liwa TX-1 & TX-2 SIP 2
Liwa TX-1 & TX-2 Liwa TX-3 & TX-4 55
Liwa TX-1 & TX-2 SoharFree Zone TX-1 & TX-2 67.9 52.2
Liwa TX-1 & TX-2 Shinas 2X125MVA 3
SIP Liwa TX-1 & TX-2 10 27.7 8
SIP Liwa TX-3 & TX-4
SIP Shinas 2X125MVA 4
SIP Falaj Al Qabail 16.5
SoharFree Zone TX-1 & TX-2 SIP 2
SoharFree Zone TX-1 & TX-2 Liwa TX-1 & TX-2 9
SoharTX-1 & TX-2 SoharTX-3 & TX-4 8
SoharTX-1 & TX-2 Saham 9
SoharTX-1 & TX-2 Uwaynat TX-1 & TX-2 37.6
SoharTX-1 & TX-2 Uwaynat TX-3 & TX-4 40.5
SoharTX-1 & TX-2 Falaj Al Qabail 24.2
SoharTX-3 & TX-4 Liwa TX-1 & TX-2 4
SoharTX-3 & TX-4 SoharTX-1 & TX-2 30
SoharTX-3 & TX-4 Uwaynat TX-3 & TX-4 13.2
SoharTX-3 & TX-4 SoharFree Zone TX-1 & TX-2 2
SoharTX-3 & TX-4 Falaj Al Qabail 24.2
Khaborah Khadhra TX-1 & TX-2 24
Khaborah Dil Abdusalam 25.7
Uwaynat TX-1 & TX-2 Uwaynat TX-3 & TX-4 2
Saham SoharTX-1 & TX-2 17.5
Saham SoharTX-3 & TX-4
Saham Uwaynat TX-1 & TX-2 16.6 13.9
Saham Uwaynat TX-3 & TX-4 16.4
Saham Dil Abdusalam 62.1
Dil Abdusalam Saham 14.1
Total (MW) 273.9 326.7 117.9 59.7 196.1

Page | 64
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Table 8 (continued): Expected Load Transfers between Grid Supply Points (2017-2021)
Load Transfer (MW)
From Grid Station To Grid Station
2017 2018 2019 2020 2021
Dhofar System

NPS 2X63MVA Salalah Free Zone TX-3 & TX-4 7.4 10 1

NPS 2X63MVA Awaqad 4 2.5

NPS 2X63MVA Ittin 3


Salalah Free Zone TX-1 & TX-
Awaqad 2
2
Salalah Free Zone TX-1 & TX-
Salalah Free Zone TX-3 & TX-4 5 9 15.8 3
2
Salalah Free Zone TX-1 & TX-
NPS 2X63MVA 2.5 1
2
Salalah Free Zone TX-3 & TX-
Awaqad 3
4
Salalah Free Zone TX-3 & TX-
NPS 2X63MVA 1
4
Awaqad Ittin 3 9 8 4.5 3

Awaqad NPS 2X63MVA 2

Awaqad Sa'adah TX-1 & TX-2 16.7

Awaqad Salalah Free Zone TX-3 & TX-4 8

Ittin Awaqad 10.3 7

Ittin Al Qarm 3

Ittin Sa'adah TX-1 & TX-2 15.5

Ittin Sa'adah TX-3 & TX-4 19.8 14.8

Ittin Salalah Free Zone TX-3 & TX-4 17 4

Sa'adah TX-1 & TX-2 Al Qarm 3

Sa'adah TX-3 & TX-4 Ittin 2

Al Qarm Sa'adah TX-1 & TX-2 32 13

Al Qarm Sa'adah TX-3 & TX-4 32 6.5 2

Thumrait 2X30MVA Thumrait 2X125MVA 29

Total (MW) 113.5 62.7 75.5 24.3 59.3

Page | 65
Five-Year Annual Transmission Capability Statement (2017 - 2021)

7.3 System Maximum Demand Forecast and Generation Availability


Table 9 shows the grid stations demand forecast for the period 2017– 2021 with prospective load transfers
taken into account and the forecast developed in accordance with the methodology described in sub-section
7.2.

Table 9: OETC Transmission System Demand Forecast by Grid Station


Actual Forecast (MW)
Grid Station
2016 2017 2018 2019 2020 2021
MUSCAT AREA
TX-1 & TX-2 153.7 92.5 98.0 103.9 80.1 84.9
Rusail Industrial
TX-3 & TX-4 0.0 72.0 76.3 80.9 65.8 69.7
2X42MVA 7.0 7.0 7.0 0.0 0.0 0.0
Ghubrah TX-1 & TX-2 98.3 114.2 128.8 141.0 86.6 90.1
TX-3 & TX-4 0.0 0.0 0.0 0.0 60.0 62.4
Wadi Adai 95.2 98.1 86.0 88.6 91.2 94.0
Tx-1 & Tx-2 86.3 62.8 65.3 67.9 70.6 73.4
Wadi Kabir Tx-3 53.0 0.0 0.0 0.0 0.0 0.0
Tx-3 & Tx-4 0.0 79.6 82.8 86.1 89.5 93.1
Al Falaj 98.5 96.5 99.3 102.3 105.4 108.6
TX-1 & TX-2 117.6 107.3 75.6 78.6 81.8 85.0
MSQ Tx-3 45.2 34.0 0.0 0.0 0.0 0.0
TX-3 & TX-4 0.0 0.0 74.4 77.4 80.5 83.7
Khuwair 0.0 0.0 0.0 0.0 0.0 50.0
Jahloot 39.0 40.6 42.2 43.9 45.2 46.5
TX-1 & TX-2 184.1 157.3 107.2 111.5 93.9 97.7
Mawalleh South
TX-3 & TX-4 84.1 102.3 114.4 113.0 89.5 93.1
TX-1 & TX-2 0.0 0.0 0.0 0.0 70.0 72.8
Khoud
TX-3 & TX-4 0.0 0.0 0.0 0.0 70.0 72.8
2X63MVA 71.2 83.0 68.1 0.0 0.0 0.0
Seeb Main TX-1 & TX-2 103.1 119.2 124.0 101.0 90.0 93.6
TX-3 & TX-4 0.0 0.0 0.0 102.1 81.2 84.4
1X50MVA 0.0 21.1 0.0 0.0 0.0 0.0
Mawalleh North 3X50MVA 20.5 0.0 0.0 0.0 0.0 0.0
2X125MVA 0.0 0.0 89.9 93.5 97.2 101.1
TX-1 & TX-2 145.3 110.6 123.1 79.2 83.2 62.4
Bousher
TX-3 & TX-4 158.6 140.5 127.6 81.9 86.0 65.3
TX-1 & TX-2 0.0 0.0 0.0 50.0 52.5 55.1
Ghala Heights
TX-3 & TX-4 0.0 0.0 0.0 52.0 54.6 57.3
Mobella 105.4 109.6 114.0 55.6 57.8 60.1

Page | 66
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Table 9 (continued): OETC Transmission System Demand Forecast by Grid Station


Actual Forecast (MW)
Grid Station
2016 2017 2018 2019 2020 2021
MUSCAT AREA
TX-1 & TX-2 90.1 104.5 110.8 66.4 70.4 74.6
A'salam
TX-3 & TX-4 0.0 0.0 0.0 59.0 62.5 66.3
TX-1 & TX-2 0.0 0.0 0.0 59.0 62.5 66.3
Halban
TX-3 & TX-4 0.0 0.0 0.0 60.0 63.6 67.4
Muttrah 70.0 79.1 81.5 83.9 85.6 87.3
TX-1 & TX-2 113.3 97.0 101.8 53.9 56.6 58.9
Airport Heights
TX-3 & TX-4 0.0 0.0 0.0 53.0 55.7 57.9
Qurum 72.6 100.8 103.8 106.9 109.1 111.2
Yitti 9.9 10.9 12.0 13.2 14.5 15.9
Quriat 48.4 50.3 52.3 54.4 56.6 58.9
Daghmar 3x50MVA 0.0 52.0 52.0 52.0 52.0 52.0
Misfah 30.9 32.1 33.4 34.8 36.1 37.6
TX-1 & TX-2 0.0 80.0 84.8 44.9 47.6 50.0
Ghala
TX-3 & TX-4 0.0 0.0 0.0 45.0 47.7 50.1
TX-1 & TX-2 89.0 93.5 113.1 58.8 61.7 64.8
Amerat
TX-3 & TX-4 0.0 0.0 0.0 60.0 63.0 66.2
Muscat Airport 14.2 25.0 25.0 25.0 25.0 25.0
Muscat Steel 0.0 20.0 20.0 20.0 20.0 20.0
Modran Steel 0.0 20.0 20.0 20.0 20.0 20.0
R.O Ghoubrah 17.1 40.0 40.0 40.0 40.0 40.0
Total 2221.6 2453.2 2554.5 2720.4 2832.8 2947.5
Growth (%) 5.95% 10.43% 4.13% 6.50% 4.13% 4.05%
MAZOON AREA
TX-1 & TX-2 164.5 118.9 116.9 59.9 63.5 67.3
Barka Main
Tx-3 57.7 58.3 0.0 0.0 0.0 0.0
TX-1 & TX-2 0.0 46.5 49.3 52.2 55.4 58.7
Madinat Barka
TX-3 & TX-4 0.0 0.0 37.0 39.2 41.6 44.1
Barka IPP 0.0 0.0 91.0 93.7 96.5 99.4
TX-1 & TX-2 131.9 85.0 74.3 78.0 81.1 84.3
Muladah
TX-3 & TX-4 0.0 54.8 72.5 76.2 79.2 82.4
MIS 164.4 172.6 59.2 62.1 64.6 67.2
Blue City 88.3 92.7 97.4 102.2 106.3 110.6
Rustaq 3X125MVA 137.6 143.1 148.8 101.8 105.9 110.1
Wadi Bani Auwf 0.0 0.0 0.0 53.0 55.1 57.3
Nakhal 67.6 70.3 73.1 76.0 78.3 80.7

Page | 67
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Table 9 (continued): OETC Transmission System Demand Forecast by Grid Station


Actual Forecast (MW)
Grid Station
2016 2017 2018 2019 2020 2021
MAZOON AREA
TX-1 & TX-2 40.0 66.0 69.3 72.8 75.7 78.7
Khadhra
TX-3 & TX-4 0.0 0.0 54.0 56.7 59.0 61.3
Suwaiq 0.0 0.0 68.1 71.5 74.4 77.3
2X63MVA 34.0 35.7 47.5 39.4 41.0 42.6
Sumail
2X125MVA 100.9 105.9 101.2 55.3 57.5 59.8
Sumail Industrial Area 0.0 0.0 0.0 60.0 66.0 72.6
Izki 84.9 74.3 54.3 56.4 58.1 59.9
New Izki 0.0 14.0 37.7 39.6 41.6 43.6
Nizwa 104.4 110.7 117.3 61.7 64.8 68.1
Madinat Nizwa 51.3 53.4 55.5 57.7 59.4 61.2
Birkat Al Mouz 0.0 0.0 0.0 62.6 65.7 69.0
Bahla 105.7 50.6 53.1 55.8 58.6 61.5
Jebreen 0.0 60.4 63.4 66.6 69.9 73.4
2X40MVA 48.6 52.0 0.0 0.0 0.0 0.0
Adam
2X125MVA 0.0 0.0 55.6 58.9 61.9 65.0
Mudhaibi 122.7 130.1 87.9 61.8 64.9 68.2
Mudhairib 169.2 101.1 106.1 76.4 80.2 84.3
Bedyah 0.0 0.0 0.0 35.0 36.4 37.9
Sinaw 0.0 0.0 50.0 53.0 55.7 58.4
Samad 0.0 0.0 0.0 31.3 32.2 33.2
Ibra 0.0 76.6 81.2 86.1 90.4 94.9
JBB Ali 171.8 92.8 97.4 102.3 106.4 110.6
JBB Hassan 0.0 87.6 92.0 96.6 100.4 104.5
Sur 85.3 88.7 92.3 96.0 99.8 103.8
Ayjah 63.5 66.0 68.7 71.4 74.3 77.3
Total 1994.3 2108.0 2272.0 2319.3 2421.8 2529.1
Growth (%) 9.40% 5.70% 7.78% 2.08%* 4.42% 4.43%
MAJAN AREA
2X63MVA 56.5 31.4 32.7 32.0 33.3 0.0
Ibri
2X125MVA 87.6 63.6 68.1 74.9 80.1 71.5
Madinat Ibri 0.0 0.0 0.0 0.0 0.0 64.0
Dank 27.4 28.2 33.1 34.1 35.1 36.1
Al Hayl 62.1 48.7 47.1 49.5 19.1 16.0
Yanqual 0.0 0.0 0.0 0.0 32.9 38.5
Dreez 0.0 74.5 78.2 82.1 86.2 75.4
* The reduction in growth % in 2019 due to load transfer from Barka Main to A’ssalam grid stations.

Page | 68
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Table 9 (continued): OETC Transmission System Demand Forecast by Grid Station


Actual Forecast (MW)
Grid Station
2016 2017 2018 2019 2020 2021
MAJAN AREA
Mahadha 25.4 26.4 27.5 28.3 22.3 23.0
Wadi Sa'a 9.8 10.3 10.8 11.3 18.7 19.6
Bureimi 78.9 84.4 90.3 58.4 62.4 63.8
TX-1 & TX-2 47.4 50.7 54.3 42.7 45.7 51.8
Buriami Industrial
TX-3 & TX-4 0.0 0.0 0.0 53.7 57.5 61.5
Shinas 106.0 112.4 51.8 58.9 65.4 69.4
Madinat Shinas 0.0 0.0 61.3 65.0 68.9 73.0
TX-1 & TX-2 159.5 61.8 99.8 52.6 70.3 75.2
Liwa
TX-3 & TX-4 0.0 55.0 58.9 63.0 67.4 72.1
SIP 76.1 71.4 72.7 81.8 79.5 68.6
TX-1 & TX-2 0.0 67.9 72.7 80.0 79.0 86.9
SoharFree Zone
TX-3 & TX-4 0.0 0.0 0.0 54.2 59.6 65.6
TX-1 & TX-2 106.4 114.3 74.3 79.5 85.0 66.8
Sohar
TX-3 & TX-4 98.4 109.3 73.7 76.9 82.3 63.8
Falaj Al Qabail 0.0 0.0 0.0 0.0 0.0 64.9
Khaborah 126.1 109.7 90.5 96.0 101.7 107.8
TX-1 & TX-2 0.0 0.0 54.2 55.5 58.8 76.2
Uwaynat
TX-3 & TX-4 0.0 0.0 53.7 58.9 62.5 82.6
Saham 162.6 163.9 95.0 100.7 106.7 96.9
Dil Abdusalam 0.0 0.0 87.8 93.1 98.7 90.5
Aromatics connected to 132kV (SIP-A) 19.0 22.0 22.0 22.0 22.0 22.0
SoharSteel connected to 132kV(SIP-A) 6.4 90.0 96.0 96.0 96.0 96.0
Jindal Shadeed connected to 220 (SIP-A) 202.9 260.0 270.0 275.0 275.0 275.0
VALE connected to 132kV (SIP-A) 79.7 85.0 85.0 85.0 85.0 85.0
Oman Alum (ARMS) connected to Liwa
8.6 8.6 8.6 8.6 8.6 8.6
132kV
OMPET Connected ti SIP 132kV 0.0 0.0 27.0 27.0 27.0 27.0
Orpic (Liwa Plastic) 220kV SPS-2 0.0 0.0 200.0 200.0 200.0 200.0
Moon Iron & Steel Co connected to
0.0 0.0 0.0 185.0 185.0 185.0
220KV SFZ
Total 1546.8 1749.5 2097.0 2381.3 2477.6 2580.2
Growth (%) -0.05%* 13.11% 19.86% 13.56% 4.04% 4.14%
* The reduction in growth % in 2016 due to load transfer from Khaborah to Khadhra grid stations.

Page | 69
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Table 9 (continued): OETC Transmission System Demand Forecast by Grid Station


Actual Forecast (MW)
Grid Station
2016 2017 2018 2019 2020 2021
DHOFAR AREA
NPS 2X63MVA 54.1 45.9 40.7 42.2 44.3 45.1
TX-1 & TX-2 89.4 94.6 97.1 93.4 85.1 87.9
Salalah Free Zone
TX-3 & TX-4 0.0 7.4 23.0 55.8 76.1 89.2
Awaqad 2X125MVA 92.5 110.4 95.2 87.0 86.9 90.7
Ittin 2X125MVA 121.0 99.4 108.3 94.4 107.5 99.2
TX-1 & TX-2 0.0 32.0 63.9 80.9 86.6 92.6
S'aadah
TX-3 & TX-4 0.0 51.8 55.4 65.8 70.4 90.1
Al Qarm 2X63MVA 86.0 30.2 19.0 16.6 15.6 16.5
Ashoor 2X125MVA 43.2 46.2 49.5 75.4 80.0 84.8
2X30MVA 21.7 23.0 24.4 25.8 27.4 0.0
Thumrait
2X125MVA 0.0 0.0 0.0 0.0 0.0 29.0
Salalah Airport 5.4 11.0 13.5 14.9 15.0 15.0
Salalah Methanol Company 0.0 0.0 0.0 50.0 50.0 50.0
Total 513.3 551.9 590.1 702.4 744.8 790.2
Growth (%) 8.54% 7.52% 6.93% 19.03% 6.04% 6.09%
MEDC 2221.6 2453.2 2554.5 2720.4 2832.8 2947.5
MZEC 2057.8* 2108.0 2272.0 2319.3 2421.8 2529.1
MJEC 1546.8 1749.5 2097.0 2381.3 2477.6 2580.2
DPC 513.3 551.9 590.1 702.4 744.8 790.2
Total MIS System (MW) 5825.8 6310.7 6923.5 7421.1 7732.2 8056.8
Total Dhofar System (MW) 513.3 551.9 590.1 702.4 744.8 790.2
*MZEC demand was 1994.3MW plus 63.5MW exporing to PDO (57.4MW) and OMIFCO (6.1MW).

Page | 70
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Table 10 compares the total demand forecast with the available generating capacity from Table 6 including
planned retirements.
Table 10: Comparison of Demand Forecast with Available Generating Capacity including Planned
Retirements

Power Station 2016 2017 2018 2019 2020 2021


MIS System
Al-Ghubrah Power & Desalination 377 377 341 0 0 0
Rusail 689 689 689 689 689 689
Wadi Al-Jizzi 326 326 326 0 0 0
Manah 264 264 264 264 264 264
Al Kamil 280 280 280 280 280 280
Barka I Power & Desalination 410 410 410 388 388 388
Sohar I Power & Desalination 566 566 566 566 566 566
Barka II Power & Desalination 663 663 663 663 663 663
Barka III Power & Desalination 754 754 754 754 754 754
Sohar II Power & Desalination 754 754 754 754 754 754
Sur IPP 1988 1988 1985 1983 1982 1982
Ibri IPP 0 0 940 1508 1508 1508
Sohar III IPP 0 0 0 1708 1708 1708
Misfah IPP 0 0 0 0 0 1000
Total Generating Capacity (MW) 7072 7072 7974 9559 9557 10557
Demand Forecast (MW) 5826 6311 6923 7421 7732 8057
Calculated Losses (MW) 94.5 106 101 106 113 115
Surplus/Deficit Capacity (MW)
1151 655 949 2032 1712 2385
(Generation-Demand-Losses)
Retirements 0 0 36 667 0 0
Dhofar System
NPS 273 273 273 273 273 273
Salalah IPP 429 429 429 429 429 429
Salalah 2 IPP 0 0 438 438 438 438
Total Generating Capacity (MW) 702 702 1140 1140 1140 1140
Demand Forecast (MW) 513 552 590 702 745 790
Calculated Losses (MW) 2 3 2 2 2 3
Surplus/Deficit Capacity (MW)
187 148 548 436 393 347
(Generation-Demand-Losses)
Retirements 0 0 0 0 0 0

Page | 71
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Table 11 compares the total demand forecast with the available generating capacity from Table 6.
Table 11: Comparison of Demand Forecast with Available Generating Capacity and Non-Contracted
Generation in service
Power Station 2016 2017 2018 2019 2020 2021
MIS System
Al-Ghubrah Power & Desalination 377 377 341 0 0 0
Rusail 689 689 689 689 689 689
Wadi Al-Jizzi 326 326 326 0 0 0
Manah 264 264 264 264 264 264
Al Kamil 280 280 280 280 280 280
Barka I Power & Desalination 410 410 410 388 388 388
Sohar I Power & Desalination 566 566 566 566 566 566
Barka II Power & Desalination 663 663 663 663 663 663
Barka III Power & Desalination 754 754 754 754 754 754
Sohar II Power & Desalination 754 754 754 754 754 754
Sur IPP 1988 1988 1985 1983 1982 1982
Ibri IPP 0 0 940 1508 1508 1508
Sohar III IPP 0 0 0 1708 1708 1708
Misfah IPP 0 0 0 0 0 1000
Total Generating Capacity (MW) 7072 7072 7974 9559 9557 10557
Demand Forecast (MW) 5826 6311 6923 7421 7732 8057
Calculated Losses (MW) 94.5 106 101 106 113 115
Surplus/Deficit Capacity (MW)
1151 655 949 2032 1712 2385
(Generation-Demand-Losses)
Non-Contracted Generating Capacity (MW) 575 575 575 575 575 575
Surplus/Deficit Capacity (MW)
1726 1230 1524 2607 2287 2960
Including Non-Contracted Generation
Retirements 0 0 36 667 0 0
Dhofar System
NPS 273 273 273 273 273 273
Salalah IPP 429 429 429 429 429 429
Salalah 2 IPP 0 0 438 438 438 438
Total Generating Capacity (MW) 702 702 1140 1140 1140 1140
Demand Forecast (MW) 513 552 590 702 745 790
Calculated Losses (MW) 2 3 2 2 2 3
Surplus/Deficit Capacity (MW)
187 148 548 436 393 347
(Generation-Demand-Losses)
Non-Contracted Generating Capacity (MW) 0 0 0 0 0 0
Surplus/Deficit Capacity (MW)
187 148 548 436 393 347
Including Non-Contracted Generation
Retirements 0 0 0 0 0 0

Page | 72
Five-Year Annual Transmission Capability Statement (2017 - 2021)

8. Transmission System Performance

8.1 Power Flow and Voltage Profiles

The transmission system data used in the power system studies to determine the system performance over
the period from 2017 to 2021 is presented in Appendix B of this document.

8.1.1 Power Flow and Voltage Profiles of MIS

The extreme cases of maximum (summer) and minimum (winter) system demand are used to define the
performance of OETC transmission system when it is most heavily stressed. From the studies of these
extreme conditions it is possible to identify where the system is strong and has capacity to spare and,
conversely, where it is weak and will need strengthening before new connections could be considered. The
peak demand case identifies where there is a risk of overloading, of operation above firm capacity, or of
system voltages falling below the voltage limits as defined in the Grid Code.

The system data described and presented in Appendix B has been used in a series of load flow studies to
establish the performance of OETC transmission system at peak demand in each year from 2017 to 2021
inclusive. The studies were undertaken on the basis that all circuits and plant will be available at system
peak in each of the five years and that the system will be developed in accordance with the plans described
in Section 5 of the Statement. The studies also assume that the demand will grow in accordance with the
demand forecast and that sufficient generation will be available from both Contracted and Non-Contracted
power producers to meet each annual system peak as indicated in OPWP 7 Year Statement.

Table 12 shows a summary of the power plants forecasted to be in service at peak load in each year of the
study from 2017 to 2021. Under peak load condition it is assumed that reactive power support will be
switched on, i.e. capacitor banks at 33kV grid stations are properly adjusted to provide required reactive
power and voltage support. In the studies, generator terminal voltage and generator-transformer taps are
normally set at their corresponding nominal values, however, when necessary the settings are adjusted to
control the voltage on the transmission system to be within the allowable limits.

A second series of load flow studies were undertaken with the transmission system supplying minimum
demand. The minimum demand case identifies where there is a risk of the busbar voltages rising above the
voltage limits defined in the Grid Code and where additional generation has to be operated to absorb excess
reactive power, where there are no shunt reactors connected to the system in peak 2017. However, in 2018
and 2019 several shunt reactors will be installed to absorb excessive amount of reactive power that been
generated by the lightly loaded 400kV lines. At the system minimum demand, the generation is reduced to
a level that provides the necessary margin of reserve capacity that is consistent with the operational practices
adopted by OETC to handle minimum load condition. Table 13 shows the power plants forecasted to be in
service at minimum load in each year of the study. Under minimum load condition, it is assumed that all
capacitor banks are switched out to avoid overvoltage due to excessive reactive power.

Page | 73
Five-Year Annual Transmission Capability Statement (2017 - 2021)

8.1.2 Power Flow and Voltage Profiles of Dhofar

The extreme cases of maximum and minimum system demand are used to define the performance of OETC
transmission system when it is most heavily stressed. From the studies of these extreme conditions it is
possible to identify where the system is strong and has capacity to spare and, conversely, where it is weak
and will need strengthening before new connections could be considered. The peak demand case identifies
where there is a risk of overloading, of operation above firm capacity, or of system voltages falling below
the voltage limits as defined in the Grid Code.

The system data described and presented in Appendix B has been used in a series of load flow studies to
establish the performance of OETC transmission system at peak demand in each year from 2017 to 2021
inclusive. The studies were undertaken on the basis that all circuits and plant will be available at system
peak in each of the five years and that the system will be developed in accordance with the plans described
in Section 5 of the Statement. The studies also assume that the demand will grow in accordance with the
demand forecast and that sufficient generation will be available from contracted power plants to meet each
annual system peak as indicated in OPWP 7 Year Statement.

Table 12 shows a summary of the power plants forecasted to be in service at peak load in each year of the
study from 2017 to 2021. Under peak load condition it is assumed that capacitive support will be switched
on, i.e. capacitor banks at 33kV grid stations are properly adjusted to provide required reactive power and
voltage support. In the studies, generator terminal voltage and generator-transformer taps are normally set
at their corresponding nominal values, however, when necessary the settings are adjusted to control the
voltage on the transmission system to be within the allowable limits.

A second series of load flow studies were undertaken with the transmission system supplying minimum
demand. At the system minimum demand, the generation is reduced to a level that provides the necessary
margin of reserve capacity that is consistent with the operational practices adopted by OETC to handle
minimum load condition. Table 12 shows the power plants forecasted to be in service at maximum load in
each year of the study. Under minimum load condition, it is assumed that all capacitor banks are switched
out to avoid overvoltage due to excessive reactive power. Table 13 shows the power plants forecasted to be
in service at minimum load in each year of the study

Page | 74
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Table 12: Summary of Connected Generation Used in Load Flow Studies of Maximum Demand
2017 2018 2019 2020 2021
Power Stations
Total Spare Gen Total Spare Gen Total Spare Gen Total Spare Gen Total Spare Gen

MIS
Ghubrah 405 17 388 341 37 304 - - - - - - - - -
Rusail 689 13 676 689 76 613 689 142 547 689 119 570 689 610 79
Wadi Al-Jizzi 326 27 299 326 34 292 - - - - - - - - -
Manah 264 38 226 264 29 235 264 54 210 264 45 219 264 46 218
Al Kamil 280 49 231 280 30 250 280 57 223 280 48 232 280 48 232
Barka I 435 100 335 435 47 388 388 80 308 388 66 322 388 67 321
Sohar I 597 12 585 597 64 533 597 123 474 597 102 495 597 103 494
Barka II 688 168 520 688 73 615 688 141 547 688 118 570 688 118 570
Barka III 754 109 645 754 81 673 754 167 587 754 129 625 754 130 624
Sohar II 754 30 724 754 71 683 754 155 599 754 129 625 754 130 624
Sur IPP 1988 220 1768 1985 271 1714 1983 396 1587 1982 340 1642 1982 344 1638
Ibri IPP - - - 940 - 860 1508 310 1198 1508 259 1249 1508 261 1247
Sohar III IPP - - - - - - 1708 350 1358 1708 293 1415 1708 296 1412
Misfah IPP - - - - - - - - - - - - 1000 174 826
External Sources 180 0 180 0 0 0 0 0 0 0 0 0 0 0 0
Total Gen (MW) 7360 783 6577 8053 893 7160 9614 1976 7638 9613 1649 7964 10613 2328 8285
Grid Load (MW) 6473 7067 7538 7848 8183
Dhofar
NPS 273 52 221 273 125 148 273 99 174 273 89 184 273 78 195
Salalah IWP 444 84 360 444 204 240 444 161 283 444 144 300 444 127 317
Salalah-2 IPP − − - 437.8 201 237 437.8 158.8 279 438 143 295 438 125 313
External Sources 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Total Gen (MW) 717 136 581 1155 530 625 1155 419 736 1155 376 779 1155 330 825
Grid Load (MW) 579 623 735 778 823

Page | 75
Five-Year Annual Transmission Capability Statement (2017 - 2021)

Table 13: Summary of Connected Generation Used in Load Flow Studies of Minimum Demand
2017 2018 2019 2020 2021
Power Stations
Total Spare Gen Total Spare Gen Total Spare Gen Total Spare Gen Total Spare Gen
MIS
Ghubrah 405 185 220 405 242 163 - - - - - - - - -
Rusail 689 689 0 689 689 0 689 689 0 689 689 0 689 689 0
Wadi Al-Jizzi 326 326 0 326 326 0 - - - - - - - - -
Manah 264 108 156 264 110 154 264 107 157 264 264 0 264 264 0
Al Kamil 280 280 0 280 280 0 280 280 0 280 280 0 280 280 0
Barka I 435 153 282 435 158 277 388 51 337 388 132 256 388 129 259
Sohar I 597 192 405 597 198 399 597 188 409 597 184 413 597 179 418
Barka II 688 339 349 688 344 344 688 336 352 688 333 355 688 329 359
Barka III 754 536 218 754 539 215 754 534 220 754 532 222 754 529 225
Sohar II 754 536 218 754 539 215 754 534 220 754 532 222 754 529 225
Sur IPP 1988 1304 684 1985 1106 879 1983 1084 899 1982 1076 906 1982 1280 702
Ibri IPP - - - - - - 940 532 408 1508 1097 411 1508 1092 416
Sohar III IPP - - - - - - - - - 1708 1246 462 1708 951 757
Misfah IPP - - - - - - - - - - - - - - -
External Sources 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Total Gen (MW) 7180 4648 2532 7177 4531 2646 7338 4336 3002 9613 6366 3247 9613 6252 3361
Grid Load (MW) 2498 2615 2945 3213 3326
Dhofar
NPS 273 228 45 273 216 57 273 238 35 273 248 25 273 234 39
Salalah IWP 444 327 117 444 327 118 444 376 68 444 368 77 444 367 77
Salalah-2 IPP − − - − − - 438 348 90 438 286 152 438 290 148
External Sources 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Total Gen (MW) 717 555 162 717 543 174 1155 962 193 1155 901 254 1155 890 265
Grid Load (MW) 162 174 193 254 264

Page | 76
Five-Year Annual Transmission Capability Statement (2017-2021)

The key results of the load flow and fault level studies on OETC transmission system are presented in detail
in Appendix C for each year over the period 2017 to 2021. System diagrams from C.1 to C.10 are showing
the results of the peak demand for MIS and Dhofar. Load flows have also been produced and are available
for both MIS and Dhofar in Appendix C.

The results for MIS and Dhofar include the following:

 Table C.1 shows the transformer percentage loading of all grid stations at system peak demand.

 Table C.2 shows the available spare capacity at each grid station in relation to firm capacity at system
peak demand. It should be noted that although spare MVA capacities are available at some individual
grid stations, there is no guarantee that all can be exploited simultaneously. Lack of available
generation and/or voltage level limits may restrict simultaneous utilization of all spare MVA capacities.

 Table C.3 shows the percentage loading of each overhead line and underground cable in the
transmission system at system peak demand.

 Tables C.4 (a) and C.4 (b) show the voltage profile at each 400kV, 220kV, and 132kV and 33kV bus-
bar at maximum and minimum load respectively.

 Table C.5 shows the calculated transmission losses and generation margin at peak demand.

 Tables C.6 and C.7 show the maximum three-phase and single-phase to earth short-circuit currents
respectively.

The principal findings from the power system studies are:

 Grid Stations Firm Capacities of MIS


a) All 400/220kV, and 400/132kV grid stations developed during 2017 to 2021 will have firm capacities
as indicated in Table C.1. Moreover, these grid stations will have appreciable amount of spare
transformer capacities during the same period as indicated in Table C.2 and for future needs.
b) Most of the 220/132kV grid stations have adequate amounts of spare capacity available over the period
from 2017 to 2021 to cope with growth in demand. Some of these grid stations might be out of firm at
the summer peak in some years as indicated in tables C.1 and C.2, but will have adequate capacity by
2021. The three new 220/132kV grid stations that will be commissioned over the period 2017-2021 at
Mobella, Khaborah and Muladah, will substantially increase the amount of grid transformer capacity
connected to the transmission system to facilitate further development of the transmission system.
c) Some of 132/33kV grid stations show lack of capacity from 2017 to 2019. For example, at summer
peak of 2017, thirteen grid stations will operate above their firm capacity. At summer peak of 2018,
eight grid stations will operate above their firm capacity but none of the grid stations will be overloaded.
During 2017 to 2021, a number of 132/33kV grid stations will be upgraded and new ones are introduced
to remove none-firm conditions at some locations. The number will decrease to two 132/33 kV at
summer peak of 2019. All 132/33kV grid stations will be operating within their firm capacity in 2020.

Page | 77
Five-Year Annual Transmission Capability Statement (2017-2021)

d) The number of out-of-firm grid stations during the period 2017 to 2021 are (this is shown graphically
in Figure 15):
 2017 – 13
 2018 – 8
 2019 – 2
 2020 – 0
 2021 – 0
e) In summer peak of 2017, there are three transformers temporally supplying their individual loads in
order to mitigate over firm issues and provide additional capacity at some 132/33kV grid stations. From
2018, there will be no transformer operating individually.
f) The number of 132kV overhead lines operating above firm capacity over the summer peak period 2017-
2021 will be as follows:
 2017 – 1
 2018 – 2
 2019 – 0
 2020 – 1
 2021 – 0
g) All 220kV overhead transmission lines are within their corresponding firm capacity over the years 2017
to 2021.
h) All 400kV overhead transmission lines are well within their corresponding firm capacity over the years
2017 to 2021.
i) Implementation of the development projects described in Section 5 and the updated load transfer
programme of Table 8 will restore the full system to be in compliance with Transmission Security
Standard requirements.
 Grid Stations Firm Capacities of Dhofar
a) Awqad 132/33kV grid station shows lack of capacity in 2017. During 2018 and 2019, all
132/33kV grid stations will be within the firm capacity. In 2020, Thumrait grid station will
operate above it firm capacity. In 2021, all 132/33kV grid stations will be operating within their
firm capacity.
b) The number of out-of-firm grid stations during the period 2017 to 2021 are (this is shown
graphically in Figure 16):
 2017 – 1
 2018 – 0
 2019 – 0
 2020 – 1
 2021 – 0

Page | 78
Five-Year Annual Transmission Capability Statement (2017-2021)

c) All 132kV overhead lines and underground cables are within their corresponding firm capacity
over the period 2017-2021.
d) Implementation of the development projects described in Section 5 and the updated load transfer
programme of Table 8 will restore the full system to be in compliance with Transmission System
Security Standard requirements.

No. of Out-of-Firm Grid Stations VS Year


14

12

10

0
2017 2018 2019 2020 2021

Figure 15: Number of out-of-firm grid stations during 2017-2021 of MIS

Figure 16: Number of out-of-firm grid stations during 2017-2021 of Dhofar

Page | 79
Five-Year Annual Transmission Capability Statement (2017-2021)

 Voltage Profile of MIS


a) The voltage at the 400kV busbars will be maintained within the ±5 % voltage limit at the extremes
of maximum and minimum demand during the study period. Figure 17 shows comparisons of
400kV busbar voltages at minimum and maximum demand conditions in years 2019 and 2020.
b) The voltage at the 220kV and 132kV busbars will be maintained within the ±10 % voltage limit
at the extremes of maximum and minimum demand during years 2017-2021.
c) The 33kV busbar voltages at all grid stations will be maintained within ±6 % of nominal voltage
during these extreme load conditions of maximum and minimum demand, i.e. all 33kV busbars
will be within the acceptable operating range specified in the Grid Code. In fact, the voltage at
33kV busbars is well regulated to be within around 1.0 p.u. in all cases by exploiting the
automatic on-load tap-changer of the 132/33kV transformers.
d) Figures 18 and 19 show samples of voltage profiles at Airport Heights and MIS grid stations.
These grid stations have three voltage levels: 220kV, 132kV and 33kV. Although the voltage at
220kV and 132kV busbars can change within the allowable range (depending on the load), the
voltage at the grid supply points is well regulated at almost 33kV level (1.0 p.u.).

 Voltage Profile of Dhofar


a) The voltage at the 132kV busbars will be maintained within the ±10 % voltage limit at the extremes
of maximum and minimum demand during years 2017-2021.
b) The 33kV busbar voltages at all grid stations will be maintained within ±6 % of nominal voltage
during these extreme load conditions of maximum and minimum demand, i.e. all 33kV busbars
will be within the acceptable operating range specified in the Grid Code. In fact, the voltage at
33kV busbars is well regulated to be within around 1.0 p.u. in all cases by exploiting the automatic
on-load tap-changer of the 132/33kV transformers.
c) Figures 20, 21 and 22 show samples of voltage profiles at SFZ, Ittin and Al Qarm grid stations.
These grid stations have two voltage levels: 132kV and 33kV. Although the voltage at 132kV
busbars can change within the allowable range (depending on the load), the voltage at the grid
supply points is well regulated at almost 33kV level (1.0 p.u.).

Page | 80
Five-Year Annual Transmission Capability Statement (2017-2021)

Figure 17: Voltage profile at 400kV busbars in p.u.

Page | 81
Five-Year Annual Transmission Capability Statement (2017-2021)

Figure 18: Voltage profile (p.u.) at Airport Heights Grid Station

Page | 82
Five-Year Annual Transmission Capability Statement (2017-2021)

220kV Busbar

132kV Busbar

33kV Busbar

Figure 19: Voltage profile (p.u.) at MIS Grid Station

Page | 83
Five-Year Annual Transmission Capability Statement (2017-2021)

33kV Busbar

Figure 20: Voltage profile (p.u.) at Salalah Free Zone Grid Station

Page | 84
Five-Year Annual Transmission Capability Statement (2017-2021)

Figure 21: Voltage profile (p.u.) at Ittin Grid Station

Page | 85
Five-Year Annual Transmission Capability Statement (2017-2021)

Figure 22: Voltage profile (p.u.) at Al Qarm Grid Station

Page | 86
Five-Year Annual Transmission Capability Statement (2017-2021)

 Transmission Losses of MIS


The calculated active power loss on the transmission system at peak demand over the period from
2017 to 2021 ranges between 1.61 and 1.38 of respective total generation as shown in Table C.5 and
Figure 23. The average power loss is about 1.44% which is well within international norms.

 Transmission Losses of Dhofar


The calculated active power loss on the transmission system at peak demand over the period from
2017 to 2021 ranges between 0.47 % and 0.32% of respective total generation as shown in Table C.5
and Figure 24. The average power loss is about 0.34%, which is still within international norms.

Figure 23: Transmission power losses at peak demand of the years 2017-2021 of MIS

Figure 24: Transmission power losses at peak demand of the years 2017-2021 of Dhofar

Page | 87
Five-Year Annual Transmission Capability Statement (2017-2021)

 Load Growth of MIS


The high growth rate of the existing load coupled with major new industrial developments in many
areas and major tourism projects around the coast to the east and west of Muscat presents a major
challenge to OETC in providing the capacity needed to satisfy demand over the next five years. Table
C.5 shows the expected peak load increases from 6473 MW in 2017 to 8183 MW in 2021 which
amounts to an increase of about 26.42% during the study period. Figure 25 shows the expected peak
load growth from 2017 to 2021. This peak load includes grid stations and industrial loads, but excludes
transmission losses and including the Aux and desalination of the power plants.

 Load Growth of Dhofar


The high growth rate of the existing load coupled with major new industrial developments in many
areas and major tourism projects around the coast of Dhofar presents a major challenge to OETC in
providing the capacity needed to satisfy demand over the next five years. Table C.5 shows that the
expected peak load increases from 579 MW in 2017 to 823 MW in 2021 which amounts to an increase
of about 42.14% during the study period. Figure 26 shows the expected peak load growth from 2017
to 2021. This peak load includes grid, industrial, auxiliary and desalination loads, but excludes
transmission losses and including the Aux and desalination of the power plants.

Figure 25: Peak load growth over the period 2017-2021 of MIS

Page | 88
Five-Year Annual Transmission Capability Statement (2017-2021)

Figure 26: Peak load growth over the period 2017-2021 of Dhofar

The load flow studies show that the planned 400kV, 220kV and 132kV transmission developments will add
substantial new capacity to the transmission system that will enable the transmission system as a whole to
cope with new demand in compliance with the Transmission Security Standard. Consequently opportunities
for the connection of new load should be available where spare capacity exists.

8.2 Fault levels for MIS and Dhofar Systems


a)- Three-Phase Short Circuit Studies
The maximum 3-Phase and Single-Phase short-circuit current have been determined in accordance with
IEC 60909 and as such the calculation excludes the contribution to fault level from sources at lower
voltages, e.g. from induction motors connected at 11 kV or below. The method is valid and consistent with
that followed by other transmission companies in the absence of data from the Distribution Companies for
short-circuit back-feeds to the grid station 33kV busbars. Table C.6 summarises the results of the 3-phase
fault studies over the period 2017-2021 for both systems MIS and Dhofar:

 All of the 400kV busbars have fault levels well within the corresponding switchgear ratings.

 All of the 220kV busbars have fault levels within the corresponding switchgear ratings.

 All the 132kV buses have fault levels within the corresponding switchgear ratings.

 The 3-phase short-circuit level at all 33kV busbars does not exceed the switchgear rating.

Page | 89
Five-Year Annual Transmission Capability Statement (2017-2021)

b) - Single-Phase Short Circuit Studies


Table C.7 summarises the results of maximum single-phase short circuit studies for years from 2017 to
2021 for both systems MIS and Dhofar. In the years from 2017 to 2021 the fault levels across the
transmission system are within the corresponding switchgear short-circuit ratings. Only for MIS system,
the major technical issue identified in the studies was with high short-circuit fault levels on the 132kV bus
bars at four grid stations in the Muscat area. The grid stations at Ghubrah, Bousher, Rusail and Madinat
Sultan Qaboos (MSQ) were all shown in earlier studies to have high 132kV fault levels. During 2017-2018,
OETC has taken appropriate remedial action to address this problem in the short–term by spliting the 132kV
bus bars or opening some of 132kV lines at Muscat region without impacting the security requirements.
From 2019, there will be no longer need for busbars splitting due to the network development and
reconfiguration works. Therefore all busbars will be returned to normal operation. However, some 132kV
lines will still be needed to be kept open to reduce the infeed short circuit contribution and this is a part of
OETC long term strategy to operate the 400kV and 220kV as the main transmission voltages.

Page | 90
Five-Year Annual Transmission Capability Statement (2017-2021)

9. Development Opportunities

From the results of the load flow and fault level studies, and from analysis of the magnitude and location
of generation and demand on the transmission system it is possible to give some indications as to where
future generation and demand can be connected to the transmission system without causing any critical
technical issues.

9.1 Review of the Generation Versus Load Balance on an Area Basis


The performance of the transmission system is affected by the transfer of power, both real and reactive,
from one region to another. Large power transfers between regions over long distances increase the voltage
drop across the transmission system. They also increase the power losses and reduce the efficiency of the
system. Ideally, if the balance between generation and demand is maintained on a regional or area basis
then power transfers over long distances can be minimised, thus leading to improvement of the transmission
system efficiency and voltage regulation.

Figure 27 shows the connectivity of the OETC transmission system at MIS area in 2021 as it extends over
the northern regions of Oman, a distance of around 550 km from Madinat Shinas in the North West to JBB
Ali in the southeast. Figure 28 shows the connectivity of the OETC transmission system at Dhofar area in
2021 as it extends over the northern regions of Dhofar, a distance of around 67 km from NPS grid station
in the North West to Ashoor grid station in the south-west. To assess how generation and load is distributed
over the transmission system the whole supply area has been split into eight geographic areas:

a) Muscat
b) Al Batinah South
c) Al Batinah North
d) Al Bureimi
e) Al Dhahirah
f) Al Dakhiliah
g) Al Sharqiyah
h) Dhofar

Page | 91
Five-Year Annual Transmission Capability Statement (2017-2021)

Figure 27: Future OETC MIS Transmission System (2021)

Page | 92
Five-Year Annual Transmission Capability Statement (2017-2021)

Figure 28: Future OETC Dhofar Transmission System (2021)

Page | 93
Five-Year Annual Transmission Capability Statement (2017-2021)

Table 14 compares the generation capacity installed in each of the eight areas with the forecast demand at
the grid stations at the annual system peak over the period 2017 to 2021.

Table 14: Estimated Power Surplus and Power Deficit on an Area Basis (2017-2021)
Grid Station loads at System Peak
Area Grid & Power Stations Demand
2017 2018 2019 2021 2021
Al-Ghubrah Power & Desalination 377 341 0 0 0
Rusail IPP 689 689 689 689 689
Misfah IPP 0 0 0 0 1000
Total Generation (MW) 1066 1030 689 689 1689
TX-1 & TX-2 92.5 98.0 103.9 80.1 84.9
Rusail Industrial
TX-3 & TX-4 72.0 76.3 80.9 65.8 69.7
2X42MVA 7.0 7.0 0.0 0.0 0.0
Ghubrah TX-1 & TX-2 114.2 128.8 141.0 86.6 90.1
TX-3 & TX-4 0.0 0.0 0.0 60.0 62.4
Wadi Adai 98.1 86.0 88.6 91.2 94.0
TX-1 & TX-2 62.8 65.3 67.9 70.6 73.4
Wadi Kabir Tx-3 0.0 0.0 0.0 0.0 0.0
TX-3 & TX-4 79.6 82.8 86.1 89.5 93.1
Al Falaj 96.5 99.3 102.3 105.4 108.6
TX-1 & TX-2 107.3 75.6 78.6 81.8 85.0
MSQ Tx-3 34.0 0.0 0.0 0.0 0.0
TX-3 & TX-4 0.0 74.4 77.4 80.5 83.7
Muscat Khuwair 0.0 0.0 0.0 0.0 50.0
Jahloot 40.6 42.2 43.9 45.2 46.5
TX-1 & TX-2 157.3 107.2 111.5 93.9 97.7
Mawalleh South
TX-3 & TX-4 102.3 114.4 113.0 89.5 93.1
TX-1 & TX-2 0.0 0.0 0.0 70.0 72.8
Khoud
TX-3 & TX-4 0.0 0.0 0.0 70.0 72.8
2X63MVA 83.0 68.1 0.0 0.0 0.0
Seeb Main TX-1 & TX-2 119.2 124.0 101.0 90.0 93.6
TX-3 & TX-4 0.0 0.0 102.1 81.2 84.4
1X50 MVA 21.1 0.0 0.0 0.0 0.0
Mawalleh North
2X125 MVA 0.0 89.9 93.5 97.2 101.1
TX-1 & TX-2 110.6 123.1 79.2 83.2 62.4
Bousher
TX-3 & TX-4 140.5 127.6 81.9 86.0 65.3
TX-1 & TX-2 0.0 0.0 50.0 52.5 55.1
Ghala Heights
TX-3 & TX-4 0.0 0.0 52.0 54.6 57.3
Mobella 109.6 114.0 55.6 57.8 60.1
TX-1 & TX-2 104.5 110.8 66.4 70.4 74.6
A'salam
TX-3 & TX-4 0.0 0.0 59.0 62.5 66.3

Page | 94
Five-Year Annual Transmission Capability Statement (2017-2021)

Table 14 (continued): Estimated Power Surplus and Power Deficit on an Area Basis (2017-2021)
Grid Station loads at System Peak Demand
Area Grid & Power Stations
2017 2018 2019 2021 2021
TX-1 & TX-2 0.0 0.0 59.0 62.5 66.3
Halban
TX-3 & TX-4 0.0 0.0 60.0 63.6 67.4
Muttrah 79.1 81.5 83.9 85.6 87.3
TX-1 & TX-2 97.0 101.8 53.9 56.6 58.9
Airport Heights
TX-3 & TX-4 0.0 0.0 53.0 55.7 57.9
Qurum 100.8 103.8 106.9 109.1 111.2
Yitti 10.9 12.0 13.2 14.5 15.9
Quryiat 50.3 52.3 54.4 56.6 58.9
Daghmar 52.0 52.0 52.0 52.0 52.0
Misfah 32.1 33.4 34.8 36.1 37.6
Muscat
TX-1 & TX-2 80.0 84.8 44.9 47.6 50.0
Ghala
TX-3 & TX-4 0.0 0.0 45.0 47.7 50.1
TX-1 & TX-2 93.5 113.1 58.8 61.7 64.8
Amerat
TX-3 & TX-4 0.0 0.0 60.0 63.0 66.2
Muscat Airport 25.0 25.0 25.0 25.0 25.0
Muscat Steel 20.0 20.0 20.0 20.0 20.0
Modren Steel 20.0 20.0 20.0 20.0 20.0
R.O Ghubrah 40.0 40.0 40.0 40.0 40.0
Total Load (MW) 2453.2 2554.5 2720.4 2832.8 2947.5
Power Surplus/Deficit (MW) -1387 -1524 -2031 -2144 -1258
Barka I Power & Desalination 410 410 388 388 388
Barka II Power & Desalination 663 663 663 663 663
Barka III Power & Desalination 754 754 754 754 754
Total Generation (MW) 1828 1828 1806 1806 1806
TX-1 & TX-2 118.9 116.9 59.9 63.5 67.3
Barka Main
TX-3 58.3 0.0 0.0 0.0 0.0
TX-1 & TX-2 46.5 49.3 52.2 55.4 58.7
Al Batinah South Madinat Barka
TX-3 & TX-4 0.0 37.0 39.2 41.6 44.1
Barka IPP 0.0 91.0 93.7 96.5 99.4
TX-1 & TX-2 85.0 74.3 78.0 81.1 84.3
Muladah
TX-3 & TX-4 54.8 72.5 76.2 79.2 82.4
MIS 172.6 59.2 62.1 64.6 67.2
Blue City 92.7 97.4 102.2 106.3 110.6
Rustaq 3X125MVA 143.1 148.8 101.8 105.9 110.1

Page | 95
Five-Year Annual Transmission Capability Statement (2017-2021)

Table 14 (continued): Estimated Power Surplus and Power Deficit on an Area Basis (2017-2021)
Grid Station loads at System Peak Demand
Area Grid & Power Stations
2017 2018 2019 2021 2021
Wadi Bani Auwf 0.0 0.0 53.0 55.1 57.3
Nakhal 70.3 73.1 76.0 78.3 80.7
TX-1 & TX-2 66.0 69.3 72.8 75.7 78.7
Khadhra
Al Batinah South TX-3 & TX-4 0.0 54.0 56.7 59.0 61.3
Suwaiq 0.0 68.1 71.5 74.4 77.3
Total Load (MW) 908.2 1010.8 995.3 1036.5 1079.4
Power Surplus/Deficit (MW) 920 817 810 769 726
Sohar I Power & Desalination 566 566 566 566 566
Sohar II Power & Desalination 754 754 754 754 754
Sohar III IPP 0 0 1708 1708 1708
Total Generation (MW) 1320 1320 3028 3028 3028
Shinas 112.4 51.8 58.9 65.4 69.4
Madinat Shinas 0.0 61.3 65.0 68.9 73.0
TX-1 & TX-2 61.8 99.8 52.6 70.3 75.2
Liwa
TX-3 & TX-4 55.0 58.9 63.0 67.4 72.1
Sohar Industrial Area (SIA) 71.4 72.7 81.8 79.5 68.6
Sohar Free Zone TX-1 & TX-2 67.9 72.7 80.0 79.0 86.9
(SFZ) TX-3 & TX-4 0.0 0.0 54.2 59.6 65.6
TX-1 & TX-2 114.3 74.3 79.5 85.0 66.8
Sohar
TX-3 & TX-4 109.3 73.7 76.9 82.3 63.8
Falaj Al Qabail 0.0 0.0 0.0 0.0 64.9
Khaborah 109.7 90.5 96.0 101.7 107.8
Al Batinah North TX-1 & TX-2 0.0 54.2 55.5 58.8 76.2
Uwaynat
TX-3 & TX-4 0.0 53.7 58.9 62.5 82.6
Saham 163.9 95.0 100.7 106.7 96.9
Dil Abdusalam 0.0 87.8 93.1 98.7 90.5
Aromatics connected to 132kV (SIP-A) 22.0 22.0 22.0 22.0 22.0
Sohar Steel connected to 132kV(SIP-A) 90.0 96.0 96.0 96.0 96.0
Jindal Shadeed connected to 220 (SIP-A) 260.0 270.0 275.0 275.0 275.0
VALE connected to 132kV (SIP-A) 85.0 85.0 85.0 85.0 85.0
Oman Alum (ARMS) connected to Liwa
8.6 8.6 8.6 8.6 8.6
132kV
OMPET Connected ti SIP 132kV 0.0 27.0 27.0 27.0 27.0
Orpic (Liwa Plastic) 220kV SPS-2 0.0 200.0 200.0 200.0 200.0
Moon Iron & Steel Co connected to
0.0 0.0 185.0 185.0 185.0
220KV SFZ
Total Load (MW) 1331.2 1655.0 1914.4 1984.3 2058.8
Power Surplus/Deficit (MW) -11.2 -335.0 1113.6 1043.7 969.2

Page | 96
Five-Year Annual Transmission Capability Statement (2017-2021)

Table 14 (continued): Estimated Power Surplus and Power Deficit on an Area Basis (2017-2021)
Grid Station loads at System Peak Demand
Area Grid & Power Stations
2017 2018 2019 2021 2021
Wadi Al-Jizzi Power Plant 326 326 0 0 0
Total Generation (MW) 326 326 0 0 0
Mahadha 26.4 27.5 28.3 22.3 23.0
Wadi Sa'a 10.3 10.8 11.3 18.7 19.6
Al Buraimi Bureimi 84.4 90.3 58.4 62.4 63.8
TX-1 & TX-2 50.7 54.3 42.7 45.7 51.8
Bureimi Industrial
TX-3 & TX-4 0.0 0.0 53.7 57.5 61.5
Total Load (MW) 171.8 182.9 194.4 206.6 219.8
Power Surplus/Deficit (MW) 153.9 142.9 -194.4 -206.6 -219.8
Ibri IPP 0 940 1508 1508 1508
Total Generation (MW) 0 940 1508 1508 1508
2X63MVA 31.4 32.7 32.0 33.3 0.0
Ibri
2X125MVA 63.6 68.1 74.9 80.1 71.5
Madinat Ibri 0.0 0.0 0.0 0.0 64.0
Al Dhahirah Dank 28.2 33.1 34.1 35.1 36.1
Al Hayl 48.7 47.1 49.5 19.1 16.0
Yanqual 0.0 0.0 0.0 32.9 38.5
Dreez 74.5 78.2 82.1 86.2 75.4
Total Load (MW) 246.5 259.2 272.5 286.7 301.6
Power Surplus/Deficit (MW) -246.5 680.8 1235.5 1221.3 1206.4
Manah IPP 264 264 264 264 264
Total Generation (MW) 264 264 264 264 264
2X63MVA 35.7 47.5 39.4 41.0 42.6
Sumail
2X125MVA 105.9 101.2 55.3 57.5 59.8
Sumail Industrial Area 0.0 0.0 60.0 66.0 72.6
Izki 74.3 54.3 56.4 58.1 59.9
New Izki 14.0 37.7 39.6 41.6 43.6
Nizwa 110.7 117.3 61.7 64.8 68.1
Al Dakhiliah
Madinat Nizwa 53.4 55.5 57.7 59.4 61.2
Birkat Al Mouz 0.0 0.0 62.6 65.7 69.0
Bahla 50.6 53.1 55.8 58.6 61.5
Jebreen 60.4 63.4 66.6 69.9 73.4
2X40MVA 52.0 0.0 0.0 0.0 0.0
Adam
2X125MVA 0.0 55.6 58.9 61.9 65.0
Total Load (MW) 556.9 585.7 614.1 644.6 676.7
Power Surplus/Deficit (MW) -292.7 -321.4 -349.9 -380.3 -412.5

Page | 97
Five-Year Annual Transmission Capability Statement (2017-2021)

Table 14 (continued): Estimated Power Surplus and Power Deficit on an Area Basis (2017-2021)
Grid Station loads at System Peak
Area Grid & Power Stations Demand
2017 2018 2019 2021 2021
Al Kamil IPP 280 280 280 280 280
Sur IPP 1988 1985 1983 1982 1982
Total Generation (MW) 2268 2265 2264 2262 2262
Mudhaibi 130.1 87.9 61.8 64.9 68.2
Mudhairib 101.1 106.1 76.4 80.2 84.3
Bidayah 0.0 0.0 35.0 36.4 37.9
Sinaw 0.0 50.0 53.0 55.7 58.4
Al Sharqiyah Samad 0.0 0.0 31.3 32.2 33.2
Ibra 76.6 81.2 86.1 90.4 94.9
JBB Ali 92.8 97.4 102.3 106.4 110.6
JBB Hasan 87.6 92.0 96.6 100.4 104.5
Sur 88.7 92.3 96.0 99.8 103.8
Ayjah 66.0 68.7 71.4 74.3 77.3
Total Load (MW) 642.9 675.5 709.9 740.7 773.0
Power Surplus/Deficit (MW) 1625 1590 1554 1521 1489
NPS Power Plant 273 273 273 273 273
Salalah IPP 429 429 429 429 429
Salalah 2 IPP 0 438 438 438 438
Total Generation (MW) 702 1140 1140 1140 1140
NPS 2x63MVA 45.9 40.7 42.2 44.3 45.1
TX-1 & TX-2 94.6 97.1 93.4 85.1 87.9
Salalah Free Zone
TX-3 & TX-4 7.4 23.0 55.8 76.1 89.2
Awaqad 2X125MVA 110.4 95.2 87.0 86.9 90.7
Ittin 2X125MVA 99.4 108.3 94.4 107.5 99.2
Dhofar TX-1 & TX-2 32.0 63.9 80.9 86.6 92.6
S’aadah
TX-3 & TX-4 51.8 55.4 65.8 70.4 90.1
Al Qarm 2x63MVA 30.2 19.0 16.6 15.6 16.5
Ashoor 2X125MVA 46.2 49.5 75.4 80.0 84.8
2X30MVA 23.0 24.4 25.8 27.4 0.0
Thumrait
2X125MVA 0.0 0.0 0.0 0.0 29.0
Salalah Airport 11.0 13.5 14.9 15.0 15.0
Salalah Methanol Company 0.0 0.0 50.0 50.0 50.0
Total Load (MW) 551.9 590.1 702.4 744.8 790.2
Power Surplus/Deficit (MW) 151 550 438 395 350

Page | 98
Five-Year Annual Transmission Capability Statement (2017-2021)

Figures 29 to 36 show graphically the generation and load in each of the eight areas. The significant
differences in generation and load imbalance in areas such as Muscat, Al Batinah North, and Al Sharqiyah
necessitate high development and investment in the transmission system to facilitate power transfer among
the different areas in order to supply the growing loads.

Muscat area, although geographically the smallest area, is by far the most heavily populated, with the
highest demand (2453.2MW in 2017, rising to 2947.3MW in 2021) and with limited amount of connected
generation (1066MW in 2017, increasing to 1689MW in 2021).This will result in power deficits of
1387MW in 2017 and 1258MW in 2021. Muscat area has three power plants; Ghubrah (377MW in 2017
and will be retired by 2019), Rusail (689MW during the period 2017-2021) and new Misfah IPP (1000MW
in 2021) .The reduction in the generation of Muscat area from 2019 is due to planned retirement of all
generating units of Ghubrah power plant after peak of 2018. However, the new generation in Muscat area
at Misfah will compensate the reduction in generation and meet the demand growth.

Muscat Area
3500

3000

2500
Power (MW)

2000 Total Generation (MW)


1500 Total Load (MW)

1000

500

0
2017 2018 2019 2020 2021

Figure 29: Generation and load balance in Muscat area


Al Batinah South area covers the coastal strip between Barka on the western outskirts of the Muscat area
and Sohar. This area is likely to develop as Muscat, since the main road link between Muscat and Sohar
runs through it. Currently, there are three power plants in Al Batiniah South; Barka Phase-I (410MW),
Barka Phase-II (663MW) and Barka Phase-III (754MW). As shown in Table 14, the load in this area rises
from 908.2MW in 2017 to 1079.4MW in 2021. The power surplus decreases from 920MW in summer peak
of 2017 to 726MW in summer peak of 2021. This area having enough generations to supply the local
demand and exporting to others regions. In 2019, the load at Al Batinah South will be reduce due to the
load transfer from Barka Main to Halban and Mobella grid stations.

Page | 99
Five-Year Annual Transmission Capability Statement (2017-2021)

2000
1800
1600
1400
1200
Power
(MW)

1000 Total Generation (MW)


800 Total Load (MW)
600
400
200
0
2017 2018 2019 2020 2021

Figure 30: Generation and load balance in Al Batinah South area


Al Batinah North area is rapidly developing around the new port at Sohar with new industry seeking
connections to the OETC transmission system or the distribution system of Majan Electricity Company.
Some of the largest industrial customers in the area, such as Sohar Aluminium Company operates their own
generating plant and on occasions supply power to the transmission system on a non-contracted basis. The
load in Al Batinah North area significantly increases from 1331.2MW in 2017 to 2058.8 MW in 2021, as
shown in Table 14. Al Batinah North area has three power plants; Sohar-I (566MW during the period 2017-
2021), Sohar-II (with total 754MW power during the period 2017-2021) and Sohar-III IPP will be in the
service in 2019 with power capacity of 1708MW. In 2017, the generation defecit in this area will be
11.2MW and will increase to reach 335.0MW in 2018. In 2019 Sohar-III IPP will be in service and the
generation surplus will be 1113.6MW. In 2021 the generation surplus is expected to be 969.2MW.

3500

3000

2500

2000
Total Generation (MW)
Power

1500
(MW)

Total Load (MW)


1000

500

0
2017 2018 2019 2020 2021

Figure 31: Generation and load balance in Al Batinah North area

Page | 100
Five-Year Annual Transmission Capability Statement (2017-2021)

The transmission system in the Al Bureimi area provides the interconnection with the GCCIA through UAE
(Abu Dhabi Transco) supplies a number of grid stations that feed Majan Distribution System. Wadi Al Jizzi
power plant is the only generation in Al Bureimi area with power capacity of 326MW (during the period
2017-2019) and planned to retire all the gerenating untis after peak of 2018. In 2017 and 2018, the
generation surplus is 153.9MW and 142.9MW respectively. In 2019, 2020 and 2021 the deficiency in
generation will be 194.4MW, 206.6MW and 219.8MW respectively.

350

300

250
Power (MW)

200
Total Generation (MW)
150 Total Load (MW)
100

50

0
2017 2018 2019 2020 2021

Figure 32: Generation and load balance in Al Bureimi area


There will be one new generartion at Al Dhahirah (Ibri IPP) and it will be in the service in 2018 with power
capacity of 940MW. The capacity of Ibri IPP will reach 1508MW in 2019. The load in this area will increase
from 246.5MW in 2017 to 301.6MW in 2021, as shown in Table 14. Power is transmitted from Wadi Al
Jizzi generating plant over long distance to supply the grid stations at Ibri, Dank and Al Hayl grid stations.
However, the 220kV systems from Mahadha in Bureimi area to Ibri produced an improvement in the
voltage quality and increase the security of supply. In 2017, the deficiency in generation will be 246.5MW.
In 2018, 2019, 2020 and 2021 the generation surplus is 680.8MW, 1235.5MW, 1221.3MW and 1206.4MW
respectively due to the presence of Ibri IPP power plant.

Page | 101
Five-Year Annual Transmission Capability Statement (2017-2021)

1600
1400
1200
Power (MW)

1000
800 Total Generation (MW)

600 Total Load (MW)

400
200
0
2017 2018 2019 2020 2021

Figure 33: Generation and load balance in Al Dhahirah area

Al Dakhiliah area with its provincial load centres is exhibiting moderate growth up and has a local
generating power plant at Manah (264MW) connected to the 132kV transmission system. A connection
between OETC and PDO is available in the area through the 132kV Nizwa-Nahada transmission line. The
deficiency in generation rises from 292.7MW in 2017 to 412.5MW in 2021.

800
700
600
Power (MW)

500
400 Total Generation (MW)
300 Total Load (MW)
200
100
0
2017 2018 2019 2020 2021

Figure 34: Generation and load balance in Al Dakhiliah area

Page | 102
Five-Year Annual Transmission Capability Statement (2017-2021)

Al Sharqiyah area has a provincial load centre that is exhibiting moderate growth up. Al Sharqiyah area has
two power plants; Al-Kamil IPP (280MW during the period 2017-2021) and Sur IPP (with total 1988MW
power in 2017 and 1982MW in 2021). The power surplus in this area will be 1625MW, 1590MW,
1554MW, 1521MW and 1489MW in 2017, 2018, 2019, 2020 and 2021 respectively. Compared to other
areas in Oman, Al Sharqiyah area with Sur power plant will have the largest surplus generating power. This
area is well connected through a 400kV system with Muscat and Al Dakhiliah areas which offered a power
transfer and supply the load there.

2500

2000
Power (MW)

1500
Total Generation (MW)
1000 Total Load (MW)

500

0
2017 2018 2019 2020 2021

Figure 35: Generation and load balance in Al Sharqiyah area

The transmission system in the Dhofar area provides the interconnection with the PDO and supplies a
number of grid stations that feed DPC Distribution System to supply Salalah city, a number of towns and
villages in Dhofar area. Currently, there are two power plants in Dhofar area; NPS Power Plant (273MW)
and Salalah IPP Power Plant (429MW).

In addition, there will be a new generartion (Salalah-2 IPP) at Dhofar and it will be in the service in 2018
with power capacity of 438MW. Furthermore, there will be a Wind Farm at Dhofar area and it will be in
the service in 2019 with power capacity of 50MW. However, this Wind Farm is not centrally dispatched
generating units and will be treated as a load disturbance. As shown in Table 14, the load in Dhofar area
rises from 551.9MW in 2017 to 790.2MW in 2021. In 2017, the generation surplus is 151MW. In 2018,
Salalah-2 IPP Power Plant will be in service and the generation surplus is 550MW and will decrease to
350MW in 2021 due to the load growth.

Page | 103
Five-Year Annual Transmission Capability Statement (2017-2021)

Dhofar Area
1200

1000

800
Power (MW)

600 Total Generation (MW)


Total Load (MW)
400

200

0
2017 2018 2019 2020 2021

Figure 36: Generation and load balance in Dhofar area

9.2 Available grid station capacity


Table C.2 in Appendix C identifies the available capacity at the grid stations for the connection of new
demand over the period 2017 to 2021. Table 15, lists the grid stations where spare grid transformer capacity
of more than 10 MVA is available to supply new demand, on the same area basis as that presented in sub-
section 9.1. The MVA figures quoted refer to the available capacity in 2021. The available capacity was
determined in relation to the firm capacity of the substation. Figures 37 to 45 show graphical representation
of available capacities.

Page | 104
Five-Year Annual Transmission Capability Statement (2017-2021)

Table 15: Available Grid Station Capacity of More than 10 MVA in 2021
Available
Region Grid Station Capacity Grid Station Available
(MVA) Capacity (MVA)
Rusail (TX-1 & TX-2) 35.60 Bousher (TX-3 & TX-4) 56.23
Rusail (TX-3 & TX-4) 51.63 Ghala Heights (TX-1 & TX-2) 66.97
Ghubrah (TX-1 & TX-2) 30.21 Ghala Heights (TX-3 & TX-4) 64.65
Ghubrah (TX-3 & TX-4) 59.32 Mobella 61.74
Wadi Adai 26.08 A'ssalam (TX-1 & TX-2) 46.44
Wadi Kabir(TX-1& TX-2) 47.73 A'ssalam (TX-3 & TX-4) 55.22
Wadi Kabir(TX-3& TX-4) 26.98 Halban (TX-1 & TX-2) 55.22
Al Falaj 10.73 Halban (TX-3 & TX-4) 54.04
MSQ (TX-1 & TX-2) 35.49 Muttrah 33.10
MSQ (TX-3 & TX-4) 36.91 Airport Heights (TX-1 & TX-2) 63.04
Muscat
Khuwair 72.37 Airport Heights (TX-3 & TX-4) 64.08
Jahloot 76.01 Yitti 108.22
Mawalleh South (TX-1 & TX-2) 22.19 Quryiat 63.01
Mawalleh South (TX-3 & TX-4) 27.00 Daghmar 45.26
Khoud (TX-1 & TX-2) 48.37 Misfah 85.43
Khoud (TX-3 & TX-4) 48.37 Ghala (TX-1 & TX-2) 72.41
Seeb Main (TX-1 & TX-2) 26.48 Ghala (TX-3 & TX-4) 72.28
Seeb Main (TX-3 & TX-4) 36.12 Amerat (TX-1 & TX-2) 56.79
Mawalleh North 18.55 Amerat (TX-3 & TX-4) 55.37
Bousher (TX-1 & TX-2) 59.35
Barka Main (TX-1 & TX-2) 54.13 Blue City 43.62
Madinat Barka (TX-1 & TX-2) 63.21 Rustaq 134.12
Madinat Barka (TX-3 & TX-4) 78.61 Wadi Bani Auwf 64.66
Al Batinah
Barka IPP 20.33 Nakhal 40.08
South
Muladah (TX-1 & TX-2) 36.22 Khadhra (TX-1 & TX-2) 42.16
Muladah (TX-3 & TX-4) 38.28 Khadhra (TX-3 & TX-4) 60.45
MIS 54.29 Suwaiq 43.59
Shinas (2X125MVA) 51.98 Sohar (TX-3 & TX-4) 57.80
Madinat Shinas 48.15 Falaj Al Qabail 56.68
Liwa(TX-1 & TX-2) 45.87 Khaborah 11.48
Al Batinah Liwa(TX-3 & TX-4) 49.11 Uwaynat(TX-1 & TX-2) 44.78
North Sohar Industrial Area 52.78 Uwaynat(TX-3 & TX-4) 38.05
Sohar Free Zone(TX-1 & TX-2) 33.58 Saham 22.97
Sohar Free Zone(TX-3 & TX-4) 55.97 Dil Abdusalam 29.77
Sohar(TX-1 & TX-2) 54.72

Page | 105
Five-Year Annual Transmission Capability Statement (2017-2021)

Table 15 (continued): Available Grid Station Capacity of more than 10 MVA in 2021
Available Available
Region Grid Station Name Capacity Grid Station Name Capacity
(MVA) (MVA)
Wadi Sa'a 42.32 Bureimi Industrial(TX-1&TX-2) 70.42
Al Buraimi
Bureimi 57.83 Bureimi Industrial(TX-3&TX-4) 60.28
Ibri(2X125MVA) 49.74 Al Hayl 23.13
Al Dhahirah Madinat Ibri 57.63 Yanqual 84.43
Dank 24.96 Dreez 45.68
Sumail (2X63MVA) 18.16 Madinat Nizwa 60.56
Sumail (2X125MVA) 62.05 Birkat Al Mouz 52.35
Sumail Industrial Area 48.58 Bahla 60.28
Al Dakhiliah
Izki 61.97 Jebreen 47.72
New Izki 79.06 Adam (2X125MVA) 56.60
Nizwa 53.35
Mudhaibi 53.24 Ibra 25.12
Mudhairib 36.31 JBB Hasan 15.04
Al Sharqiyah Bidayah 85.15 Sur 15.76
Sinaw 63.49 Ayjah 43.68
Samad 28.05
NPS (2X63MVA) 15.56 S’aadah (TX-1 & TX-2) 27.48
Salalah Free Zone (TX-1 & TX-2) 32.51 S’aadah (TX-3 & TX-4) 30.11
Dhofar Salalah Free Zone (TX-3 & TX-4) 31.12 Al Qarm 45.59
Awaqad(2X125MVA) 29.52 Ashoor 35.79
Ittin (2X125MVA) 20.53 Thumrait 94.47

125

100
S(MVA)

75

50

25 Available MVA
Used MVA
0

Grid Station

Figure 37: Used and available MVA in Muscat area at 2021 peak demand

Page | 106
Five-Year Annual Transmission Capability Statement (2017-2021)

125

100

75
S(MVA)

50

25 Available MVA
Used MVA
0

Grid Station

Figure 38: Used and available MVA in Muscat area at 2021 peak demand

125

100

75
S(MVA)

50

25 Available MVA
Used MVA
0

Grid Station

Figure 39: Used and available MVA in Muscat area at 2021 peak demand

Page | 107
Five-Year Annual Transmission Capability Statement (2017-2021)

250
225
200
175
150
S(MVA)

125
100
75 Available MVA
50 Used MVA
25
0

Grid Station

Figure 40: Used and available MVA in Al Batinah South area at 2021 peak demand

125

100

75
S(MVA)

50

Available MVA
25
Used MVA

Grid Station

Figure 41: Used and available MVA in Al Batinah North area at 2021 peak demand

Page | 108
Five-Year Annual Transmission Capability Statement (2017-2021)

125

100

75
S(MVA)

50

Available MVA
25 Used MVA

Grid Station
Figure 42: Used and available MVA in Al Bureimi and Al Dhahiriah area at 2021 peak demand

125

100

75
S(MVA)

50
Available MVA
25 Used MVA

Grid Station

Figure 43: Used and available MVA in Al Dakhiliah area at 2021 peak demand

Page | 109
Five-Year Annual Transmission Capability Statement (2017-2021)

125

100
S(MVA)

75

50
Available MVA

25 Used MVA

Grid Station

Figure 44: Used and available MVA in Al Sharqiyah area at 2021 peak demand

125

100

75
S(MVA)

50

Available MVA
25 Used MVA

Grid Station
Figure 45: Used and available MVA in Dhofar area at 2021 peak demand

Page | 110
Five-Year Annual Transmission Capability Statement (2017-2021)

10. Non-compliances

The load flow studies summarised in Appendix C and discussed in Sections 8 and 9 of this Statement
indicate a number of out-of firm grid stations and circuits in the early years of the Statement. In this final
section, a review of each grid station / circuit, which is currently failing to meet the Transmission Security
Standards are preseneted. In addition, a describition of the development activities that OETC is undertaking
to address this non-compliance and indicates the expected time by which, in each instance, full
Transmission Security Standards compliance should be achieved are preseneted.
It should be noted that the level of the security requirements on the transmission system would change in
future as the demand on the system increases and as the system configuration changes. It is possible that
further non-compliances might arise in the future until the overall system becomes substantially more robust
through interconnection. OETC will keep this situation under review, and the non-compliance status will
be updated in the 2018 Capability Statement.
As indicated in sections 8, 9 and summarized in Tables 16, 17 and 18, there are some grid stations and
overhead lines/cables, which do not comply with the Transmission Security Standard. Therefore, it will be
necessary for a further location and duration for specific derogations to be put in place by the authority for
each of the noted out of firm circuits in Table 16 and for each of the grid stations which do not comply with
the Transmission Security Standard at peak and maintenance time noted in Table 17 and 18 respectively.
The following points should be noted:
1- The loading results show in Tables C1 and C3 (Appendix C), are those at the peak load conditions. The
system peak lasts only for a period of less than one hour in one day during the relevant year.
2- According to the most recent OPWP data, there are two forecast cases: (i) expected case, and (ii) high
case. The difference between the high and expected case in 2017 for MIS system is 403 MW and for Dhofar
system is 24 MW at the peak. This difference increases in the subsequent years and reaches 1085 MW for
MIS system and 238 MW for Dhofar system in 2021, indicating uncertainty in the forecast over the coming
years especially with regards to new industrial loads. OETC intends to monitor closely, in coordination
with OPWP, the situation in order to assess the probability associated with the high case projection and the
effect of the approved Cost Reflected Tariff (CRT).
3- It is not prudent to invest in uncertain expansion. OETC will initiate new projects as new demand
becomes more certain. Therefore, Tables 16 and 17 shown conditions at the summer peak of 2017.
4- The modelling reflects all load transfer schemes that have been formally accepted by the relevant
Distribution Company and included in their load forecasts.
OETC has adopted a two-fold approach to addressing these out of firm situations:
1) Reinforcement plans: strategic upgrading to add new circuits and/or to increase the capacity of grid
stations within a minimum of three to five years. This will not just solve the problem but it will
also strengthen the transmission system for future development. This type of solution can only be
applied as a longer-term solution because of the time taken to implement. Reinforcement is the
most robust long-term solution for secure system development, but may not necessarily be the least
cost solution to address the immediate out of firm conditions on the network.

Page | 111
Five-Year Annual Transmission Capability Statement (2017-2021)

2) Load Transfer: through agreement with Distribution Companies, load can be transferred from
heavily loaded grid stations to more lightly loaded grid stations over the next years. This would
reduce the loading issues and balance the system during peak time. This is a mid-term solution
which could be implemented by Distribution Companies in certain cases. Given the uncertainty of
mid-term load forecasts in Oman at present, this is in some circumstances the most appropriate and
economic action to address out of firm conditions on the network.

Tables 16 and 17 indicate a number of circuits and grid stations on the system where, in 2017, the out of
firm condition is shown to exist. Table 18 shows the grid stations which are classified as group E (>115
MW) and not comply with Transmission Security Standard (Second Outage) at 2017 maintenance period.

Page | 112
Five-Year Annual Transmission Capability Statement (2017-2021)

Table 16: Expected Over headlines/ Cables Which will not omply with Transmission Security Standard (First Outage) at Peak Demand in 2017

Indicative
Date for full
Send Circuit
Conductor Circuit Loading Compliance
Receive Voltage No. of Circuit length
No Bus Rating with the Remarks
Bus (kV) Circuits Type Size/Type (%)
(km) (MVA) Transmission
Security
Standard

Russail 2500 mm2 • Connecting the 4th circuit between


1 Russail 132 3 UGC 0.192 375 52.16 Q3 2017 Rusail and Rusail Industrail.
Industrail XLPE

Page | 113
Five-Year Annual Transmission Capability Statement (2017-2021)

Table 17: Expected Grid stations 132/33kV, which will not comply with Transmission Security Standard (First Outage) at Peak Demand in 2017

Total Substation Indicative Date for


Transformer Firm Loading full Compliance with
No Location Remarks
Capacity Capacity (%) the Transmission
(MVA) (MVA) Security Standard

Muscat
Transformer capacity has been provided in Ghala grid
1 Bousher - B 2x125 125 61 Q2 2019 station. DISCOs load transfer will solve the non-
compliance.
Mawalleh South
2 2x125 125 68 Q3 2017 Load transfer to Mawalleh North grid station.
-A
3 Seeb Main 2x125 125 52.75 Q3 2018 Upgarde the 2x63MVA to 125 MVA Transfomers
4 Seeb Main 2x63 63 73.88 Q3 2018 Upgarde the 2x63MVA to 125 MVA Transfomers
Mazoon
5 Adam 2x40 40 71.99 Q1 2018 Upgrading the tranformers from 2x40MVA to 2x125MVA
Transformer capacity has been provided in Khadhra grid
6 MIS 2x125 125 78.91 Q3 2017 station. DISCOs load transfer will solve the non-
compliance.
7 Mudhaibi 2x125 125 58.01 Q3 2017 Load transfer to Sinaw grid station.
Transformer capacity has been provided in Madinat Barka
8 Barka Main 2x125 125 52.55 Q2 2019 and A’ssalam grid stations. DISCOs load transfer will solve
the non-compliance.
Transformer capacity has been provided in Madinat Barka
Barka Main (3rd
9 1x125 125 51.34 Q1 2018 and A’ssalam grid stations. DISCOs load transfer will solve
Tx)
the non-compliance.
Majan
10 Al Hayl 2x40 40 69.65 Q2 2020 Load transfer to new Yanqual grid station
11 Saham 2x125 125 73.19 Q3 2017 Load transfer to Uwaynat and Dil Abdusalam grid stations

Page | 114
Five-Year Annual Transmission Capability Statement (2017-2021)

Table 18: Expected Grid stations 132/33kV, which will not comply with Transmission Security Standard at Maintenance Period in 2017.

Transferable
Tx Peak Demand Load in case Transmissi
Grid No Demand Transform
capacit Forecast of Second on Security
NO Station of Forecast er Loading Remarks
y During Outage Standard
Name Txs (MW) (%)
(MVA) Maintenance During Compliant
Maintenance

Muscat
Upgrading of Seeb Main grid station from 2 x
1 Seeb Main 125 2 119 52.75 79.3 60 No 63 MVA to 2 x125 MVA transformers and
installing 33kV busbars Interlinking in Q3 2018
Mazoon
Load transfer to Swaiq and Khadhra grid
2 MIS 125 2 173 78.91 115.3 40 No
stations in Q3 2017
3 Mudhaibi 125 2 130 58.01 86.6 40 No Load transfer to Sinaw grid station in Q3 2017
Barka
4 125 2 119 52.55 79.3 60 No Load transfer to Madinate Barka in Q3 2017
Main
Majan
Load transfer to Dil Abdusalam grid station in
Q3 2017
5 Saham 125 2 164 73.19 109.3 40 No
Load transfer to Uwaynat grid station in Q1
2018

Page | 115
Five-Year Annual Transmission Capability Statement (2017-2021)

Appendix A: Review of Future Developments


A.1 Summary of Projects to be completed between 2017-2021 Peak Demands
The OETC transmission network is undergoing widespread and rapid development due to the expansion
requirements of distribution companies, large private customers, and new generation requirements based
on the yearly demand growth and further reinforcements on the transmission network to ensure the security,
quality, reliability and availability of the system.

There are a significant number of projects required to meet the annual peak demands over the period of this
Statement (2017-2021). These projects are considered below under the following categories:

• Projects commissioned or under construction to meet 2017 peak demand.

• Projects that are at design stage.

• Projects that are at the tender evaluation stage prior to appointment of the successful EPC
Contractor.

• Projects planned for future developments that represent the least cost options to address
problems with system growth, voltage profile, and non-compliance with the Transmission Security
Standard.

The entire programme of ongoing and future projects which are planned for implementation over the period
2017 to 2021 are listed and described below. It should be noted that the project numbers referred in this
Appendix are identical to those in Table 1 of the Executive Summary, and it should also be noted that not
all of the projects described have full authorisation at this time and to be supported by pre investment
appraisals document to approve and to select the proper option for each project.

A.2 Projects expected to be completed to meet the 2017 peak demand


Project #1: Madinat Barka 132/33kV grid station (Tx1 & Tx2)
New grid station will be constructed at Barka area (Batinah South) as 132/33kV, 2x125MVA transformers
grid station and it will be connected by 0.13km LILO of Filaj-Muladah 132kV OHL. This project will
secure load at this high growth area, maintain Transmission Security Standard requirement and to transfer
load from Barka Main grid station. This project has been in service since 29th March 2016.

Project #2: New Izki 132/33kV grid station


This project is consisted of construction new 132/33kV grid station in New Izki (Al Dhakiliah
Governorate). This grid station will be 2x125MVA and 8x132kV GIS bays. It will be supplied via 2x0.62
km UGC LILO to the 132kV of Izki-Mudhaib line. Also, this grid station will be connected directly to New
Izki 400/220kV grid station which is located in the same location. This station will serve the new demand,
load growth and load transfer from the nearby grid stations like Nizwa and Izki. This project has been in
service since 4th July 2016.
Project #3: New Izki 220kV grid station
New grid station will be constructed at New Izki (2x500MVA transformers and 7x220kV GIS bays). The
purpose of this project is to evacuate the power from Sur power plant, support the voltage and power flow

Page | 116
Five-Year Annual Transmission Capability Statement (2017-2021)

to Al Dakhaliah and Al Sharqiyah area and to comply with the Transmission Security Standard
requirements. This project has been in service since 4th July 2016.

Project #4: New Izki 400/220kV grid station


To accommodate the 400kV lines coming from Sur power plant to New Izki, New Izki 400kV grid station
will be upgraded to 400kV. So, the project includes construction of 12x400kV GIS bays and 2x500MVA
transformers at New Izki 400kV grid station. Additionally, upgrading of New Izki 220kV to 400kV system
will facilitate connection of Dahkhliah area to Muscat governorate via Misfah 400/220kV grid station. This
project has been in service since 4th July 2016.

Project #5: Ibra 132/33kV grid station


New grid station will be constructed at Ibra area as 132/33kV, 2x125MVA transformers and it will be
connected from Mudhairib grid station by a 132kV double circuit line around 28km. The purpose of this
project is to meet the load growth, decrease voltage drop at Dema Wa Al Tayeen area and to meet
Transmission Security Standard requirements. This project has been in service since 10th July 2016.

Project #6: Upgrading Misfah grid station to 400kV


This project consists of construction of installation of 11x400kV GIS bays, 3x220kV bays and 3x500MVA
transformers 400/220kV at Misfah. This project is implemented to support the power evacuation from Sur
power plant and for maintaining the Transmission Security Standard requirements during outage of the
Sur–Jahloot 400kV line. Also this project is required to complete the 400kV backbone by connecting all
the regions. This project has been in service since 29th September 2016.

Project #7: JBB Hassan 132/33kV grid station


Construct a new grid station 2x125MVA transformers at Al Kamil area by LILO (2x16km) of Al Kamil-
Sur OHL. This is required to meet load growth in that area and release the loading at JBB Ali grid station.
This project has been in service since 13th December 2016.

Project #8: Daghmar 132/11kV grid station


New grid station will be constructed in Quriyat (IWP). This project will consist of installation of 132/11kV,
2x132kV GIS at existing Quriyat grid station, 7x132kV GIS at Daghmar and 2x50MVA transformers
shifting from the Mawalleh North grid station with associated 132kV GIS. It will be connected radially
from Quriyat grid station by around 4km OHL. This project has been in service since 21st December 2016.

Page | 117
Five-Year Annual Transmission Capability Statement (2017-2021)

Project #9: Dreez 132/33kV grid station


The new 132/33kV, 2x125 MVA transformers grid station is required to supply the load in Al Dreez and
Hajarmat areas as per the request from Majan Electricity Company. This gird station will be supplied by
30km of 132kV double circuit overhead line from Ibri grid station. Also, this project is required as indicated
by Majan- to resolve the issue of severe voltage drop due to the long lengths of 11kV and 33kV lines in the
area that are fed from Al Hayl and Dank grid stations. It comes also to cater for new demand within the
area and to transfer load from Ibri grid station. The project is expected to be completed by end of March
2017.

Project #10: Adding third & fourth transformers 132/33kV at Muladah grid station
This project consists of constructing a new 132/33kV, 2x125MVA transformers with 2x132kV GIS and
4x33kV GIS interlink with the existing 132/33kV Muladah grid station. This project will ensure
Transmission Security Standard compliance and meet the demand growth at Muladah area. This project has
been in service since Mid of January 2017.

Project #11: Adding third & fourth transformers 132/33kV at Liwa grid station
Liwa area and Industrial Sohar Free Zone is experienced high load growth in addition to new heavy
industrial loads. Therefore, MJEC requested two grid stations, one is Sohar Free Zone (Ref. Project #12)
and the second is reinforcing the existing Liwa grid station by adding third and fourth 125MVA
transformers with 2x132kV GIS and 4x33kV GIS interlink to relief the load from existing Liwa grid station.
This project has been in service since Mid of February 2017.

Project #12: Sohar Free Zone 220/132/33kV grid station


New grid station will be constructed at Sohar Free Zone as 220/132/33kV, 2x500MVA and 2x125MVA
transformers with the associated 220kV and 132kV GIS. It will be connected to the existing SPS-2 – SIS
220kV line by LILO arrangement. Moreover, to secure both Liwa and Sohar Free Zone, the 132kV line
Wadi Al Jizzi- Liwa will be lined in and out to Sohar Free Zone. This project is requested by Majan
Electricity Company to supply the expected new industrial load at Sohar Free Zone area. This project is
expected to be in service by end of March 2017.

Project #13: Replacement of Mahadha 132kV AIS to GIS


The existing 14x132kV Outdoor Air insulated switchgear (AIS) is expected to be replaced by indoor
14x132kV GIS. This will solve the problems of heavy fog and mist during winter and summer which
causing frequent tripping of busbar due to flash over of equipment insulators. This project is expected to be
completed by end of March 2017.

Project #14: 33kV busbars Interlinking of Bousher & Mawalleh South grid stations
The mainly purpose of this project is to interlink the two groups of transformers (TX1 with TX3) and (TX2
with TX4) at Bousher and Mawalleh grid stations. The project will includes an installation of 4x33kV
circuit breakers to each grid station at Bousher and Mawalleh. It is expected to be in service by end of June
2017.

Page | 118
Five-Year Annual Transmission Capability Statement (2017-2021)

Project #15: S’aadah 132/33kV grid station


The objective of this project is to construct a new 132/33kV, 4x125MVA transformers at S’aadah which
will be connected by LILO (13 km) to the existing 132kV Awqad-Ashoor line. This grid station will release
load from Ittin, Al Qarm and Awqad grid stations. The location of this grid station was selected in
coordination with DPC Company. This project is expected to be completed by end of June 2017.

Project #16: Connection of Salalah-2 IPP & adding third & fourth transformers at Salalah Free
Zone
This project is implemented to support the power evacuation from Salalah-2 IPP power plant and for
maintaining the Transmission Security Standard requirements. The construction of this project consists of
16x132kV GIS at Salalah Free Zone grid station in order to connect to Salalah-2 IPP and 2x125MVA
transformers at existing Salalah Free Zone grid station. This new capacity at Salalah Free Zone grid station
will release load from the existing transformers and can be used to transfer load from NPS grid station. The
location of this grid station was selected in coordination with DPC Company. This project is expected to
be in service by end of June 2017.

Project #17: 132kV linking system between Al Falaj, Mattrah and Wadi Al Kabair grid stations
and adding fourth 125MVA transformer at Wadi Kabair grid station
The objective of this project is to construct a 132kV single circuit UGC (2500mm2) between Mattarh and
Al Falaj grid stations and also 132kV single circuit OHL and UGC between Mattarh and Wadi Kabair grid
stations. Moreover, to cope with load growth and secure the load at Wadi Kabair grid station, a fourth
125MVA transformer will be installed and will operate in parallel with existing third transformer as one
group. This linking system and installation of the fourth transformer will require an installation of new
132kV GIS at Al Falaj grid station and additional bays at Wadi Kabair grid station. The purpose of this
project is to maintain the Transmission Security Standard requirements for the three grid stations (Al Falaj,
Muttrah and Wadi Kabir). This project is expected to be in service by end of June 2017.

Project #18: Jebreen 132/33kV grid station


Due to the load growth and new load in Bahla and Jebreen area, MZEC request a new grid station 132/33kV,
2x125MVA transformers with associated 132kV GIS. Also, this station will assist Bahla grid station by
providing the capability of load transfer. This new grid station will be connected by LILO from 132kV
Nizwa-Ibri OHL. This project is expected to be in service by end of June 2017.

Page | 119
Five-Year Annual Transmission Capability Statement (2017-2021)

A.3 Projects expected to be completed to meet the 2018 peak demand

Project #19: 400 kV OHL between New Izki to Misfah


This project will be used to evacuate the power from Sur power plant to Al Dahkhliah and Al Sharqiyah
area. The length of the line is 100km of 400kV OHL between Misfah and New Izki 400kV grid station. In
addition, this 400kV line will support the voltage in Al Sharqiyah and Al Dakhliah area. Also, this line will
be an infrastructure for future development. This project is expected to be in service by end of September
2017.

Project #20: Dil Abdusalam 132/33kV grid station


This project is consisting of construction a new grid station 132/33kV, 2x125MVA and 8x132kV GIS. This
new grid station will be connected by 2x8km LILO from the existing 132kV Saham-Khaborah OHL. This
station will serve both new load in the area and load transfer from Khaborah grid station. This project is
expected to be completed by end of September 2017.

Project #21: Adding third and fourth transformers 132/33kV at Khadhra grid station
The third and fourth 132/33kV, 2x125MVA transformers with 4x33kV GIS interlink will be installed in
the existing Khadhra grid station. The purpose of this project is to cope with load growth at Al Khadhra
area and provide the opportunity for the load transfer from the loaded nearby grid stations. This project is
expected to be service by end of September 2017.

Project #22: Adding third and fourth transformers 132/33kV at Madinat Barka grid station
This project consists of installing a new 132/33kV, 2x125MVA transformers with 4x33kV GIS interlink,
at the Madinat Barka 132/33kV grid station. This project will ensure Transmission Security Standard
compliance and meet the increased load in Barka area. This project is expected to be in service by end of
September 2017.

Project #23: Suwaiq 132/33kV grid station


This project is consisting of construction new 132/33kV grid station with 2x125MVA transformers and
associated 132kV GIS. This new grid station will be fed by LILO from the MIS- Khadhra 132kV line. As
indicated by Mazoon Electricity Company, there is new load and high load growth in Suwaiq area and new
grid station is required to cater for this load. This project is expected to be in service by end of September
2017.

Project #24: Madinat Shinas 132/33kV grid station


New grid station will be constructed in Shinas to cater for the new demand in Shinas area and to provide
load transfer capability from existing Shinas 132/33 grid station. This project is consisting of construction
a new 132/33kV, 2x125MVA transformers with associated 132kV GIS. This new grid station will be fed
from existing Shinas grid station by 132kV double circuit OHL around 24.06 km. This project is expected
to be in service by end of September 2017.

Page | 120
Five-Year Annual Transmission Capability Statement (2017-2021)

Project #25: Sinaw 132/33kV grid station


New grid station will be constructed in Sinaw (Al Sharqiyah North Governorate). This project will consist
of installation 132/33kV, 2x125MVA transformers with associated 132kV GIS. It will be connected by
LILO from New Izki – Mudhaibi 132kV line. The purpose of this project is to cope with new load and load
growth at Sinaw area. Also, it will relief Mudhaibi grid station by transferring some load. Moreover, the
33kV network is suffering from the voltage drop as indicated by MEZC and this project will support the
voltage at this area. This project is expected to be in service by end of September 2017.

Project #26: Upgrading of Mawalleh North grid station from 3x50MVA at 132/11kV to
2x125MVA transformers at 132/33kV
The main purpose of this project is to provide additional capacity in Mawalleh area to accommodate the
new developments and to address the technical issue at the existing transformers (3x50MVA) which is
related to the vector group. This project consists of installing 2x125MVA transformers at Mawalleh North.
As indicated by Muscat Electricity Distribution Company, there is new load and high load growth in
Mawalleh area and the upgrading of this grid stations is required to cater for this load. This project is
expected to be in service by end of September 2017.

Project #27: Daghmar 132/11kV grid station


This project will shift the 1x50MVA transformer from the Mawalleh North grid station with associated
132kV GIS to Daghmar 132/11kV grid station. This project is aimed to supply the new IWP Quriyat. It is
expected to be in service by end of September 2017.

Project #28: Upgrading Mobella grid station to 220kV


Upgrading of Mobella to 220kV system is by adding 2x500MVA transformers, 2x132kV GIS and 8x220kV
GIS. It will be connected to 220kV Filaj-Airport Heights line by LILO connection. This will support
Mobella demand and securing the supply within the area. This project is expected to be in service by end
of September 2017.

Project #29: Adding 2x125MVA transformers 220/33kV at Barka-3 PS grid station


This project consists of installing a new 220/33kV, 2x125MVA transformers 220/33kV at Barka-3 IPP grid
station. This project is aimed to supply Braka IWP. This project is expected to be in service by end of
September 2017.

Project#30: Adding 400kV reactors


The objective of this project is to maintain the voltage within the range during the winter time. The
construction of this project consists of 8x400kV reactors at Sur to Jahloot (2x35MVAr), Sur to New Izki
400kV (4x40MVAr), and New Izki 400kV to Misfah (2x30MVAr) lines. It is expected to be in service by
end of December 2017.

Page | 121
Five-Year Annual Transmission Capability Statement (2017-2021)

Project #31: Ibri IPP 400/220kV grid station


This project is implemented to support the power evacuation from Ibri power plant and maintaining the
Transmission Security Standard requirements. The construction of this project consists of 3x500MVA
transformers, 19x400kV GIS, 10x220kV GIS at Ibri IPP and 220kV line by LILO arrangement of Mahadha-
Ibri. This project is expected to be in service by end of December 2017.

Project #32: Uwaynat 132/33kV grid station


The objective of this project is to cater for the demand in Uwaynat Area (between Saham and Sohar) and
to relief Saham and Sohar grid station from the high loads. This project is consisting of 4x125MVA
transformers with associated 10x132kV GIS and 4x33kV GIS interlink. This station will be connected to
the 132kV Sohar-SIS line by LILO arrangement. This project is expected to be completed by end of March
2018.

Project #33: Upgrading of Adam grid station from 2x40 MVA to 2x125 MVA transformers
The existing grid station at Adam is with 2x40MVA transformers and due to high demand growth in the
area, it will be upgraded to 2x125MVA transformers to meet the Transmission Security Standard
requirements and to cater for the new demand in the area. This project is expected to be in service by end
of March 2018.

Project #34: Security of SIA 132kV


One single circuit underground cable will be installed between SPS and SIA grid stations. The project will
include laying around 3.2 km 2500mm2 underground cable of 220kV and installing 1x500MVA,
220/132kV at SIA. The main purpose of this project is to secure the load at SIA during the second circuit
outage since this grid station is fed by redial 220kV double circuits. This project is expected to be completed
by end of June 2018.

Project #35: 400kV line connection between Sohar III IPP – Sohar Free Zone
This project is implemented to support the power evacuation from Sohar-III IPP and maintaining the
Transmission Security Standard requirements. The construction of this project consists four 400kV circuits
from Sohar-II to Sohar Free Zone. These circuits are as follow, two circuits will be 4.2km 400kV UGC and
6km 400kV OHL while the other two circuits will be 10.2km 400kV UGC. This project is expected to be
in service by end of June 2018.

Project #36: 400kV Connection Line to Ibri IPP Power Plant


This project is implemented to support the power evacuation from Ibri power plant toward Dhakailah and
Muscat areas and to fulfil the Transmission Security Standard requirements. The construction of this project
consists of 400kV line connected from Ibri to New Izki 400kV by around 250km. Furthermore,
4x100MVAr shunt reactors will be installed at New Izki and Ibri 400kV lines. This project is expected to
be in service by end of June 2018.

Page | 122
Five-Year Annual Transmission Capability Statement (2017-2021)

Project #37: 400kV line connection between Sohar Free Zone – Mahadha & Sohar Free Zone – SIS
This project is intended to support the power evacuation from Sohar-III IPP based on the Transmission
Security Standard requirements and to support 400kV backbone network development. The construction of
this project consists of 400kV OHL connected from Sohar Free Zone to SIS by around 42km, 400kV line
connected from Sohar Free Zone to Mahadha operate as 220kV (around 61km 400kV OHL and 1km 220kV
UGC) and 2x220kV GIS at Sohar Free Zone. This project is expected to be in service by end of June 2018.

Project #38: Installing 220kV GIS & adding fourth 125MVA transformer at MSQ grid station
A fourth transformer will be added within MSQ grid station as new group demand connected to the existing
third transformer. This group will be operated separately from the existing transformers (TX1&2) at 33kV
voltage level by shifting part of the existing load between two groups. The two groups will be connected at
the 132kV busbar. Also, new 220KV GIS will be installed to MSQ grid station as the existing 220/132kV
transformers are transformers feeder. The main purposes of this project are to meet load growth
requirements, to cater for the new demand in the area, to meet Transmission Security Standard and to relief
the load from the existing MSQ grid station. This project is expected to be in service by end of June 2018.

A.4 Projects expected to be completed to meet the 2019 peak demand


Project #39: Upgrading of Seeb grid station from 2x63 MVA to 2x125 MVA transformers and
installing 33kV busbar interlink
The existing grid station at Seeb Main consists of 2x63MVA and 2x125MVA transformers and due to high
demand growth in the area it will be upgraded from 2x63MVA to 2x125MVA transformers to cater for the
new demand in the area. Furthermore, this project includes the 33kV GIS interlink between two groups of
transformers number one and three and transformers number two and four to meet the Transmission
Security Standard requirements. This project is expected to be in service by end of September 2018.
Project #40: Sohar Free Zone 400kV grid station
This project is implemented to support the power evacuation from Sohar-III IPP and maintaining the
Transmission Security Standard requirements. The construction of this project consists of 3x500MVA
400/220kV transformers at each Sohar Free Zone and SIS. Also, the construction includes 16x400kV GIS
at Sohar-III IPP grid station, 17x400kV GIS Sohar Free Zone grid station, 11x400kV GIS at SIS and
3x220kV GIS at SIS. In addition, the construction of this project consists of 2x400kV reactors at Sohar
Free Zone (2x50MVAr). This project is expected to be in service by end of September 2018.

Page | 123
Five-Year Annual Transmission Capability Statement (2017-2021)

Project #41: New 132kV double circuits between Nakhal- Wadi Bani Auwf- Rustaq with a new
Wadi Bani Auwf 132/33 kV grid station
This project is including the construction of new 132kV double circuit OHL around 88 km between Nakhal
and Rustaq grid stations and new 132/33 kV grid station at Wadi Bani Auwf. This project aimes to provide
additional capacity in order to relieve Rustaq grid station since the load forecast expected by Mazoon
Electricity Company that Rustaq grid will exceed the firm capacity. Also, this project will secure Rustaq
grid station since, it is fed by redial 132kV double circuits and its load will be more than 100MW which
fall in Class E, according Transmission Security Standard. Moreover, high load growth is expected between
Rustaq and Wadi Bani Auwf, so the best location for this grid station is proposed to be close to Mazoon
primary substations. This project is expected to be completed in end of December 2018.

Project #42: Ghala Heights 132/33kV grid station


The main purpose of this project is to cater for the new demand in the area of Bousher, Azaibah,Ghubrah
and to accommodate the bulky load applications in those areas. This investment will provide a surplus
capacity that will cope with the load growth and security of supply for long term. In addition, this grid
station will relief the load on Bousher by transferring some of the loads from this grid station. The
construction of this project consist of 4x125MVA, 14x132kV GIS, 4x33kV GIS interlink and new 132kV
cable from Ghala to Ghala Heights and Ghala Heights to Bousher. This project is expected to be in service
by end of December 2018.

Project #43: Construction of a new 132kV OHL from Sohar Free Zone to Shinas
New 132kV line will be constructed between Sohar Free Zone and Shinas grid stations (Design as 400kV).
The purpose of this new line is to secure existing Shinas and new Madinat Shinas grid stations as per
Transmission Security Standard requirements during the second forced outage. This project consists of
construction of 30km of 132kV OHL(Design as 400kV) from Sohar Free Zone grid station to Shinas grid
station with associated 132kV circuit breakers at Sohar Free zone and Shinas grid stations. This project is
expected to be in service by end of March 2019.

Project #44: Samad 132/33kV grid station


The objective of this project is to cater for the load growth due to the expansion of commercial and domestic
loads since Mudhaibi grid and the primary substations are experiencing significant growth in load and in
many cases are approaching the limits of their firm capacity. In addition, the construction of this new grid
station will relief Mudhaibi grid station and improve the voltage profile of 33kV networks at Samad area.
This project will consist of 2x63MVA and 6x132kV GIS. It is expected to be in service by end of June
2019.

Page | 124
Five-Year Annual Transmission Capability Statement (2017-2021)

Project #45: Adding third and fourth 132/33kV transformer at Ghala


Third and fourth 125 MVA transformers with 4x33kV GIS interlink will be added at Ghala grid station to
meet the Transmission Security Standard requirements and to cater for the high demand growth within the
area. This project is expected to be in service by end of June 2019.

Project #46: Reactive Power Compensation Requirements (SVC)


Reactive power compensation will be required at Muscat area to maintain the voltage within the range
during the transient event at summer time. The issue will be appeared at heavily loaded area due the AC
load and that will cause the voltage instability and cannot be recovered during the short circuit condition. A
Static Var Compensation (SVC) will be installed at Hamriyah and Airport Heights grid stations in Muscat
area. This project is expected to be in service by end of June 2019.

Project #47: Adding third and fourth 132/33kV transformer at Amerat


Third and fourth 125 MVA transformers with 2x132kV GIS and 4x33kV GIS interlink will be added at
Amerat grid station to meet the Transmission Security Standard requirements and to cater for the high
demand growth within the area. This project is expected to be in service by end of June 2019.

Project #48: Adding third and fourth 132/33kV transformer at A’salam


Third and fourth 125MVA transformers with 2x132kV GIS and 4x33kV GIS interlink will be added at
A’salam grid station to meet the Transmission Security Standard requirements and to cater for the high
demand growth within the area. This project is expected to be in service by end of June 2019.

Project #49: Adding third and fourth 132/33kV transformer at Airport Heights
Third and fourth 125 MVA transformers with 4x33kV GIS interlink will be added at Airport Heights grid
station to meet the Transmission Security Standard requirements and to cater for the high demand growth
within the area. This project is expected to be in service by end of June 2019.

Project #50: Halban 132/33kV grid station


The objective of this project is to cater for the new load to accommodate the new developments in Mobella
area. Furthermore, the load growth and the security of supply are the primary drivers behind the investment
in Mobella. As indicated by Muscat Electricity Distribution Company that Mobella witness a high load
growth and expecting the same load growth for the upcoming years. The construction of this project is
required 4x125MVA, 10x132kV GIS and 4x33kV GIS interlink .It will be connected via LILO 132kV from
Barka Main-Mobella. It is expected to be in service by end of June 2019.

Project #51: Sumail Industrial 132/33kV grid station


As raised by MZEC that new industrial area has been established in Sumail and Sumail grid station itself
is suffering from load growth. Hence, new grid station will be constructed as 132/33kV, 2x125MVA
transformers and 8x132kV GIS. This station will be supplied via 132kV double circuit OHL by LILO
around 12km from the line of Rusail- Sumail. This project is expected to be in service by end of June 2019.

Page | 125
Five-Year Annual Transmission Capability Statement (2017-2021)

Project #52: Adding third and fourth 132/33kV transformer at Sohar Free Zone
Third and fourth 125 MVA transformers 2x132kV GIS and 4x33kV GIS interlink will be added at Sohar
Free Zone grid station to meet the Transmission Security Standard requirements and to cater for the high
demand growth within the area. This project is expected to be in service by end of June 2019.

Project #53: Bedyah 132/33kV grid station


The objective of this project of constructing a new 132/33kV, 2x125MVA transformers grid station is to
meet the load growth in that area and accommodate load transfer from Mudhairib grid station. It will be
LILO of Mudhairib- Al Kamil 132kV OHL. This grid station will cater for load growth in the area. This
project is expected to be in service by end of June 2019.

Project #54: Birkat Al Mouz 132/33kV grid station


The objective of this project is to construct a new 132/33kV, 2x125MVA transformers grid station to meet
the load growth in the area. It will be LILO of Izki to Nizwa 132kV OHL. This grid station will provide a
surplus capacity for load transfer from nearby grid stations like Nizwa and Madinat Nizwa. This project is
expected to be in service by end of June 2019.

Project #55: Qabel 400/132kV grid station


The objective of this project is to support the 132kV voltage profile, reliability and security of the 132kV
network in Al Sharqiyah region especially, once Al Kamil power plant is phased out. Also, this project will
assist the evacuation of generated power in Sur power plant and relief 132kV lines. This project will consist
of 2x500MVA transformers, 8x132kV GIS and 10x400kV GIS. It will be connected to the 400kV system
through 400kV OHL between Sur-New Izki by LILO arrangement and to the 132kV system through 132kV
OHL Mudhairib – Ibra by LILO arrangement. This project is expected to be in service by end of June 2019.

Project #56: Khaborah Interconnection Station (KIS)


This projects is consist of 2x500MVA transformers, 8x132kV GIS and 10x220kV GIS. The 220kV system
will be connected to 220kV OHL MIS-SIS by LILO connection and the 132kV system will be connected
to 132kV OHL DAS- Khabourah by LILO connection. This will support voltage profile and the security of
the supply within in Al Batinah South and North. Moreover, it will reduce load stress in the 132kV networks
due to new grid stations that are been connected to the 132kV network as LILO. This project is expected to
be in service by end of June 2019.

Project #57: Securing Bureimi area


This project consist of constriction of a new 132kV circuit (32.9km OHL and 5.5 UGC) between Mahadha
and Bureimi with one 132kV AIS at Bureimi grid station. This will support the security and reliability of
the supply within Al Bureimi area. This project is expected to be in service by end of June 2019.

Page | 126
Five-Year Annual Transmission Capability Statement (2017-2021)

Project #58: Adding third and fourth 132/33kV transformers at Bureimi Industrial
Third and fourth 125MVA transformers with 2x132kV GIS and 4x33kV GIS interlink will be added at
Bureimi Industrial grid station to meet the Transmission Security Standard requirements and to cater for
the high demand growth within the area. This project is expected to be in service by end of June 2019.

A.5 Projects expected to be completed to meet the 2020 peak demand

Project #59: Yanqul 132/33kV grid station


This project is consisting of constructing a new 132/33kV, 2x125MVA transformers grid station to meet
the load growth in area. It will be LILO of Dank- Al Hayl 132kV OHL. This grid station will provide a
surplus capacity for load transfer from Al Hayl grid station and reduce the 33kV OHL losses. This project
is expected to be in service by end of June 2020.

Project #60: Khoudh 132/33kV grid station


The objective of this project is to construct a new 132/33kV, 4x125MVA transformers grid station with
10x132kV GIS and 4x33kV GIS interlink to meet the load growth in area. It will be LILO of Mawalleh
South to Rusail Industrial 132kV OHL. Also, this grid station will accommodate the load transfer from
Mawalleh South. This project is expected to be in service by end of June 2020.

Project #61: Adding third and fourth 132/33kV transformer at Ghubrah


Third and fourth 125MVA transformers with 2x132kV GIS and 4x33kV GIS interlink will be added at
Ghubrah grid station to meet the Transmission Security Standard requirements and to cater for the high
demand growth within the area. This project is expected to be in service by end of June 2020.

A.6 Projects expected to be completed to meet the 2021 peak demand

Project #62: Misfah IPP 220kV Connection


The objective of this project is to construct a new 220kV substation at Misfah IPP with LILO of the existing
220kV OHL between Misfah and MSQ grid stations. In addition, diversion of the existing 132 kV OHL
between Misfah and Wadi Adi grid stations to 132kV UGC. Furthermore, diversion of the existing 220kV
OHL between Misfah and MSQ to 220kV UGC. Moreover, the projects consist of adding 2x500MVA
220/132kV transformers with 2x132kV GIS at Misfah grid station and 12x220kV GIS at Misfah IPP. This
project is expected to be in service by end of June 2021.

Project #63: Upgrading Rusail Industrial to 400kV


The objective of this project is to secure the demand group at Rusail area considering in the future the
planned retirments of Rusail IPP. The project will consist of upgrading the existing Rusail Industrial grid
station from 132kV to 400kV by 3x500MVA 400/132kV transformers. Also, this project will consist of
upgrading the existing 132kV OHL between Misfah and Rusail Industrial from 132kV to 400kV. This
project is expected to be in service by end of June 2021.

Page | 127
Five-Year Annual Transmission Capability Statement (2017-2021)

Project #64: Falaj Al Qabail 132/33kV grid station


The objective of this project is to construct a new 132/33kV, 2x125MVA transformers grid station with
8x132kV GIS to meet the load growth in area. It will be LILO of Sohar to Wadi Jizzi 132kV OHL. Also,
this grid station will accommodate the load transfer from Sohar. This project is expected to be in service by
end of June 2021.

Project #65: Madinat Ibri 132/33kV grid station


The objective of this project is to construct a new 132/33kV, 2x125MVA transformers grid station with
8x132kV GIS to meet the load growth in area. It will be LILO of Ibri to Jebreen 132kV OHL. Also, this
grid station will accommodate the load transfer from Ibri. This project is expected to be in service by end
of June 2021.

Project #66: Upgrading Thumrait from 2x30MVA to 2x125MVA transformers


The objective of this project is to upgrade the existing Thumrait grid station from 2x30MVA to 2x125MVA
transformers due to high demand growth in the area. This project is expected to be in service by end of June
2021.

Project #67: Khuwair 132/33kV grid station


The objective of this project is to construct a new 132/33kV, 2x125MVA transformers grid station to meet
the load growth in Bousher, Khuwair and MSQ areas. Also, this grid station will support the load transfer
from MSQ grid station as it experiences from high load growth. It will be supplied by LILO 132kV MSQ-
Ghubrah OHL. This project is expected to be in service by end of June 2021.

Project #68: Adding third transformer 220/132kV at Airport Heights


The objective of this project is to meet Transmission Security Standard and load growth in the Airport
Heights area. This project will consist of a third 500MVA transformer 220/132kV at Airport Heights with
1x132kV GIS and 1x220kV GIS. This project is expected to be in service by end of June 2021.

Page | 128
Five-Year Annual Transmission Capability Statement (2017-2021)

Appendix B: Transmission System Data


B.1 Substations Loads and Capacitor data
The grid station real and reactive power load at system peak demand for the period 2017 to 2021 and the
respective reactive power support from capacitor banks connected at the grid station 33kV busbars is shown
in Table B.1.1This data was used in the power flow studies of system peak demand presented in Section 8
of this Capability Statement.

B.2 Overhead Line Circuit Capacities and Parameters


The continuous thermal rating of a circuit is the maximum power flow that can be carried by that circuit on
a continuous basis. The thermal rating of an overhead line is the power flow that can be carried by that line
without infringing the statutory clearances and causing a risk to public safety and to the line itself. The
thermal rating of an underground cable, however, is the maximum power flow that the cable can carry
without either causing the cable to fail or to effectively reduce its projected lifespan through a deterioration
of the cable insulation.

Although the thermal rating of an overhead line is affected by climatic conditions, for the purpose of
assessing spare capacity on the transmission system the key climatic condition that limits the circuit rating
is the summer rating when the temperature is at its highest and the solar radiation is at its peak. This also
corresponds to when the electricity demand is at or near to its peak.

The circuit data presented in Table B.2 for the first year of the Statement period (2017) comprises the
voltage, resistance, reactance, susceptance and thermal rating of the line and cable circuits. It also shows
the circuit length and the type of overhead conductor or underground cable for each circuit.

Table B.3 shows the changes to the circuit data required in each of the other four years covered by the
Statement.

B.3 Transformer data


The data used to model the grid supply point transformers in the power flow studies of the 2017 summer
peak demand condition is listed in Table B.4. The data comprises the transformer voltage ratio, the
resistance and reactance, the tap range and step size. Table B.5 lists changes to the transformer data for the
remaining four year of the statement.

1
The 33kV busbars at the grid supply points and the capacitors connected to them are owned and operated by the distribution companies.

Page | 129
Five-Year Annual Transmission Capability Statement (2017-2021)

Table B 1: Load and Capacitor Data for Grid Station (2017-2021)


2017 2018 2019 2020 2021

Grid Stations P P P P P
Q Load Caps Q Load Caps Q Load Caps Q Load Caps Q Load Caps
Load Load Load Load Load
(MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr)
(MW) (MW) (MW) (MW) (MW)

MIS System
2X40MVA 52.0 17.1 - - - - - - - - - - - - -
Adam
2X125MVA - - - 55.6 18.3 48 58.9 19.4 48 61.9 20.3 48 65.0 21.4 48
TX-1 & TX-2 97.0 31.9 40 101.8 33.5 40 53.9 17.7 40 56.6 18.6 40 58.9 19.3 40
Airport Heights
TX-3 & TX-4 - - - - - - 53.0 17.4 40 55.7 18.3 40 57.9 19.0 40
Al Falaj 96.5 31.7 40 99.3 32.7 40 102.3 33.6 40 105.4 34.6 40 108.6 35.7 40
Al Hayl 48.7 16.0 10 47.1 15.5 10 49.5 16.3 10 19.1 6.3 10 16.0 5.3 10
TX-1 & TX-2 93.5 30.7 40 113.1 37.2 40 58.8 19.3 40 61.7 20.3 40 64.8 21.3 40
Amerat
TX-3 & TX-4 - - - - - - 60.0 19.7 40 63.0 20.7 40 66.2 21.7 40
TX-1 & TX-2 104.5 34.3 40 110.8 36.4 40 66.4 21.8 40 70.4 23.1 40 74.6 24.5 40
A'salam
TX-3 & TX-4 - - - - - - 59.0 19.4 40 62.5 20.6 40 66.3 21.8 40
Ayjah 66.0 21.7 20 68.7 22.6 20 71.4 23.5 20 74.3 24.4 20 77.3 25.4 20
Bahla 50.6 16.6 - 53.1 17.5 - 55.8 18.3 - 58.6 19.2 - 61.5 20.2 -
Barka IPP - - - 91.0 29.9 40 93.7 30.8 40 96.5 31.7 40 99.4 32.7 40
TX-1 & TX-2 118.9 39.1 40 116.9 38.4 40 59.9 19.7 40 63.5 20.9 40 67.3 22.1 40
Barka Main
Tx-3 58.3 19.2 - - - - - - - - - - - - -
Bedyah - - - - - - 35.0 11.5 40 36.4 12.0 40 37.9 12.4 40
Birkat Al Mouz - - - - - - 62.6 20.6 40 65.7 21.6 40 69.0 22.7 40
Blue City 92.7 30.5 48 97.4 32.0 48 102.2 33.6 48 106.3 34.9 48 110.6 36.3 48
TX-1 & TX-2 110.6 36.3 40 123.1 40.5 40 79.2 26.0 40 83.2 27.3 40 62.4 20.5 40
Bousher
TX-3 & TX-4 140.5 46.2 40 127.6 41.9 40 81.9 26.9 40 86.0 28.3 40 65.3 21.5 40
Bureimi 84.4 27.7 40 90.3 29.7 40 58.4 19.2 40 62.4 20.5 40 63.8 21.0 40
TX-1 & TX-2 50.7 16.7 40 54.3 17.8 40 42.7 14.0 40 45.7 15.0 40 51.8 17.0 40
Buriami Industrial
TX-3 & TX-4 - - - - - - 53.7 17.7 40 57.5 18.9 40 61.5 20.2 40

Page | 130
Five-Year Annual Transmission Capability Statement (2017-2021)

Table B. 1 (Continued): Load and Capacitor Data for Grid Station (2017-2021)
2017 2018 2019 2020 2021

Grid Stations P P P P P
Q Load Caps Q Load Caps Q Load Caps Q Load Caps Q Load Caps
Load Load Load Load Load
(MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr)
(MW) (MW) (MW) (MW) (MW)
MIS System
Daghmar 52.0 17.1 18 52.0 17.1 18 52.0 17.1 18 52.0 17.1 18 52.0 17.1 18
Dank 28.2 9.3 20 33.1 10.9 20 34.1 11.2 20 35.1 11.5 20 36.1 11.9 20
Dil Abdusalam - - - 87.8 28.9 40 93.1 30.6 40 98.7 32.4 40 90.5 29.7 40
Dreez 74.5 24.5 40 78.2 25.7 40 82.1 27.0 40 86.2 28.3 40 75.4 24.8 40
Falaj Al Qbail - - - - - - - - - - - - 64.9 21.3 40
TX-1 & TX-2 80.0 26.3 40 84.8 27.9 40 44.9 14.8 40 47.6 15.6 40 50.0 16.4 40
Ghala
TX-3 & TX-4 - - - - - - 45.0 14.8 40 47.7 15.7 40 50.1 16.5 40
TX-1 & TX-2 - - - - - - 50.0 16.4 40 52.5 17.3 40 55.1 18.1 40
Ghala Heights
TX-3 & TX-4 - - - - - - 52.0 17.1 40 54.6 17.9 40 57.3 18.8 40
2X42MVA 7.0 2.3 - - - - - - - - - - - - -
Ghubrah TX-1 & TX-2 114.2 37.5 - 128.8 42.3 - 141.0 46.3 - 86.6 28.5 - 90.1 29.6 -
TX-3 & TX-4 - - - - - - - - - 60.0 19.7 - 62.4 20.5 -
TX-1 & TX-2 - - - - - - 59.0 19.4 40 62.5 20.6 40 66.3 21.8 40
Halban
TX-3 & TX-4 - - - - - - 60.0 19.7 40 63.6 20.9 40 67.4 22.2 40
Ibra 76.6 25.2 40 81.2 26.7 40 86.1 28.3 40 90.4 29.7 40 94.9 31.2 40
2X63MVA 31.4 10.3 - 32.7 10.7 - 32.0 10.5 - 33.3 10.9 - 0.0 0.0 -
Ibri
2X125MVA 63.6 20.9 40 68.1 22.4 40 74.9 24.6 40 80.1 26.3 40 71.5 23.5 40
2X40MVA - - - - - - - - - - - - - - -
Izki
2X125MVA 74.3 24.4 40 54.3 17.8 40 56.4 18.6 40 58.1 19.1 40 59.9 19.7 40
Jahloot 40.6 13.3 40 42.2 13.9 40 43.9 14.4 40 45.2 14.9 40 46.5 15.3 40
JBB Ali 92.8 30.5 - 97.4 32.0 - 102.3 33.6 - 106.4 35.0 - 110.6 36.4 -
JBB Hassan 87.6 28.8 40 92.0 30.2 40 96.6 31.7 40 100.4 33.0 40 104.5 34.3 40
Jebreen 60.4 19.9 40 63.4 20.8 40 66.6 21.9 40 69.9 23.0 40 73.4 24.1 40

Page | 131
Five-Year Annual Transmission Capability Statement (2017-2021)

Table B. 1 (Continued): Load and Capacitor Data for Grid Station (2017-2021)
2017 2018 2019 2020 2021

Grid Stations P P P P P
Q Load Caps Q Load Caps Q Load Caps Q Load Caps Q Load Caps
Load Load Load Load Load
(MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr)
(MW) (MW) (MW) (MW) (MW)
MIS System
Khaborah 109.7 36.0 40 90.5 29.8 40 96.0 31.5 40 101.7 33.4 40 107.8 35.4 40
TX-1 & TX-2 66.0 21.7 40 69.3 22.8 40 72.8 23.9 40 75.7 24.9 40 78.7 25.9 40
Khadhra
TX-3 & TX-4 - - - 54.0 17.7 40 56.7 18.6 40 59.0 19.4 40 61.3 20.2 40
TX-1 & TX-2 - - - - - - - - - 70.0 23.0 40 72.8 23.9 40
Khoud
TX-3 & TX-4 - - - - - - - - - 70.0 23.0 40 72.8 23.9 40
Khuwair - - - - - - - - - - - - 50.0 16.4 40
TX-1 & TX-2 61.8 20.3 40 99.8 32.8 40 52.6 17.3 40 70.3 23.1 40 75.2 24.7 40
Liwa
TX-3 & TX-4 55.0 18.1 40 58.9 19.3 40 63.0 20.7 40 67.4 22.1 40 72.1 23.7 40
TX-1 & TX-2 46.5 15.3 40 49.3 16.2 40 52.2 17.2 40 55.4 18.2 40 58.7 19.3 40
Madinat Barka
TX-3 & TX-4 - - - 37.0 12.2 40 39.2 12.9 40 41.6 13.7 40 44.1 14.5 40
Madinat Ibri - - - - - - - - - - - - 64.0 21.0 40
Madinat Nizwa 53.4 17.5 40 55.5 18.2 40 57.7 19.0 40 59.4 19.5 40 61.2 20.1 40
Madinat Shinas - - - 61.3 20.1 40 65.0 21.4 40 68.9 22.6 40 73.0 24.0 40
Mahadah 26.4 8.7 10 27.5 9.0 10 28.3 9.3 10 22.3 7.3 10 23.0 7.6 10
3X50MVA 21.1 6.9 36 - - - - - - - - - - - -
Mawalleh North
2X125MVA - - - 90.0 29.6 40 93.6 30.8 40 97.3 32.0 40 101.2 33.3 40
TX-1 & TX-2 157.3 51.7 40 107.2 35.2 40 111.5 36.6 40 93.9 30.9 40 97.7 32.1 40
Mawalleh South
TX-3 & TX-4 102.3 33.6 40 114.4 37.6 40 113.0 37.1 40 89.5 29.4 40 93.1 30.6 40
MIS 172.6 56.7 - 59.2 19.4 - 62.1 20.4 - 64.6 21.2 - 67.2 22.1 -
Misfah 32.1 10.6 - 33.4 11.0 - 34.8 11.4 - 36.1 11.9 - 37.6 12.4 -
Mobella 109.6 36.0 40 114.0 37.5 40 55.6 18.3 40 57.8 19.0 40 60.1 19.8 40
TX-1 & TX-2 107.3 35.3 40 75.6 24.8 40 78.6 25.8 40 81.8 26.9 40 85.0 27.9 40
MSQ Tx-3 34.0 11.2 - - - - - - - - - - - - -
TX-3 & TX-4 - - - 74.4 24.5 40 77.4 25.4 40 80.5 26.4 40 83.7 27.5 40

Page | 132
Five-Year Annual Transmission Capability Statement (2017-2021)

Table B. 1 (Continued): Load and Capacitor Data for Grid Station (2017-2021)
2017 2018 2019 2020 2021

Grid Stations P P P P P
Q Load Caps Q Load Caps Q Load Caps Q Load Caps Q Load Caps
Load Load Load Load Load
(MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr)
(MW) (MW) (MW) (MW) (MW)
MIS System
Mudhaibi 2X125MVA 130.1 42.7 40 87.9 28.9 40 61.8 20.3 40 64.9 21.3 40 68.2 22.4 40
Mudhairib 101.1 33.2 48 106.1 34.9 48 76.4 25.1 48 80.2 26.4 48 84.3 27.7 48
TX-1 & TX-2 85.0 27.9 40 74.3 24.4 40 78.0 25.6 40 81.1 26.7 40 84.3 27.7 40
Muladah
TX-3 & TX-4 54.8 18.0 40 72.5 23.8 40 76.2 25.0 40 79.2 26.0 40 82.4 27.1 40
Muttrah 79.1 26.0 - 81.5 26.8 - 83.9 27.6 - 85.6 28.1 - 87.3 28.7 -
Nakhal 70.3 23.1 40 73.1 24.0 40 76.0 25.0 40 78.3 25.7 40 80.7 26.5 40
Nizwa 110.7 36.4 10 117.3 38.6 10 61.7 20.3 10 64.8 21.3 10 68.1 22.4 10
New Izki 14.0 4.6 40 37.7 12.4 40 39.6 13.0 40 41.6 13.7 40 43.6 14.3 40
Qurum 100.8 33.1 40 103.8 34.1 40 106.9 35.1 40 109.1 35.8 40 111.2 36.6 40
Quryiat 50.3 16.5 40 52.3 17.2 40 54.4 17.9 40 56.6 18.6 40 58.9 19.4 40
TX-1 & TX-2 92.5 30.4 - 98.0 32.2 - 103.9 34.1 - 80.1 26.3 - 84.9 27.9 -
Rusail Industrial
TX-3 & TX-4 72.0 23.7 - 76.3 25.1 - 80.9 26.6 - 65.8 21.6 - 69.7 22.9 -
2X63MVA - - - - - - - - - - - - - - -
Rustaq
3X125MVA 143.1 47.0 40 148.8 48.9 40 101.8 33.5 40 105.9 34.8 40 110.1 36.2 40
Saham 163.9 53.9 - 95.0 31.2 - 100.7 33.1 - 106.7 35.1 - 96.9 31.9 -
Samad - - - - - - 31.3 10.3 40 32.2 10.6 40 33.2 10.9 40
2X63MVA 83.0 27.3 - - - - - - - - - - - - -
Seeb Main TX-1 & TX-2 119.2 39.2 - 96.0 31.6 - 99.8 32.8 - 88.8 29.2 - 92.4 30.4 -
TX-3 & TX-4 - - - 96.1 31.6 - 105.9 34.8 - 85.2 28.0 - 88.6 29.1 -
Shinas 2X125MVA 112.4 36.9 40 51.8 17.0 40 58.9 19.4 40 65.4 21.5 40 69.4 22.8 40
Sinaw - - - 50.0 16.4 40 53.0 17.4 40 55.7 18.3 40 58.4 19.2 40
SIP 71.4 23.5 - 72.7 23.9 - 81.8 26.9 - 79.5 26.1 - 68.6 22.6 -
TX-1 & TX-2 114.3 37.6 40 74.3 24.4 40 79.5 26.1 40 85.0 27.9 40 66.8 21.9 40
Sohar
TX-3 & TX-4 109.3 35.9 40 73.7 24.2 40 76.9 25.3 40 82.3 27.0 40 63.8 21.0 40

Page | 133
Five-Year Annual Transmission Capability Statement (2017-2021)

Table B. 1 (Continued): Load and Capacitor Data for Grid Station (2017-2021)
2017 2018 2019 2020 2021

Grid Stations P P P
P Load Q Load Caps P Load Q Load Caps Q Load Caps Q Load Caps Q Load Caps
Load Load Load
(MW) (MVAr) (MVAr) (MW) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr) (MVAr)
(MW) (MW) (MW)

MIS System
TX-1 & TX-2 67.9 22.3 40 72.7 23.9 40 80.0 26.3 40 79.0 26.0 40 86.9 28.5 40
Sohar Free Zone
TX-3 & TX-4 - - - - - - 54.2 17.8 40 59.6 19.6 40 65.6 21.6 40

2X63MVA 35.7 11.7 - 47.5 15.6 - 39.4 12.9 - 41.0 13.5 - 42.6 14.0 -
Sumail
2X125MVA 105.9 34.8 40 101.2 33.3 40 55.3 18.2 40 57.5 18.9 40 59.8 19.7 40

Sumail Industrial Area - - - - - - 60.0 19.7 40 66.0 21.7 40 72.6 23.9 40

Sur 88.7 29.2 48 92.3 30.3 48 96.0 31.5 48 99.8 32.8 48 103.8 34.1 48

Suwaiq - - - 68.1 22.4 40 71.5 23.5 40 74.4 24.4 40 77.3 25.4 40

TX-1 & TX-2 - - - 54.2 17.8 40 55.5 18.2 40 58.8 19.3 40 76.2 25.0 40
Uwaynat
TX-3 & TX-4 - - - 53.7 17.7 40 58.9 19.4 40 62.5 20.5 40 82.6 27.2 40

Wadi Adai 98.1 32.2 40 86.0 28.3 40 88.6 29.1 40 91.2 30.0 40 94.0 30.9 40

Wadi Bani Auwf - - - - - - 53.0 17.4 40 55.1 18.1 40 57.3 18.8 40

Tx-1 & Tx-2 62.8 20.6 40 65.3 21.5 40 67.9 22.3 40 70.6 23.2 40 73.4 24.1 40

Wadi Kabir Tx-3 - - - - - - - - - - - - - - -

Tx-3 & Tx-4 79.6 26.2 40 82.8 27.2 40 86.1 28.3 40 89.5 29.4 40 93.1 30.6 40

Wadi Sa'a 10.3 3.4 - 10.8 3.6 - 11.3 3.7 - 18.7 6.2 - 19.6 6.5 -

Yanqual - - - - - - - - - 32.9 10.8 40 38.5 12.7 40

Yitti 10.9 3.6 - 12.0 3.9 - 13.2 4.3 - 14.5 4.8 - 15.9 5.2 -
6103. 6420. 6731. 7056.
Total 33 kV load 5740.2 1886.7 1988.0 2006.0 2440.0 2110.3 3040.0 2212.6 3160.0 2319.3 3280.0
0 3 6 3
Aromatics connected to 132kV (SIP-A) 22.0 7.2 - 22.0 7.2 - 22.0 7.2 - 22.0 7.2 - 22.0 7.2 -
Sohar Steel (SSSRM) connected to
90 29.6 - 96 31.6 - 96 31.6 - 96 31.6 - 96.0 31.6 -
132kV (SIP-A)
Jindal Shadeed connected to 220 (SIP-A) 260.0 85.5 - 270.0 88.7 - 275.0 90.4 - 275.0 90.4 - 275.0 90.4 -

VALE connected to 132kV (SIP-A) 85 27.9 - 85 27.9 - 85 27.9 - 85 27.9 - 85 27.9 -


Oman Alum. Rolling Co.LLC (ARMS)
8.6 2.8 - 8.6 2.8 - 8.6 2.8 - 8.6 2.8 - 8.6 2.8 -
connected to Liwa 132kV

Page | 134
Five-Year Annual Transmission Capability Statement (2017-2021)

Table B. 1 (Continued): Load and Capacitor Data for Grid Station (2017-2021)
2017 2018 2019 2020 2021
Grid Stations P Caps
P Load Q Load Caps Q Load Caps P Load Q Load P Load Q Load Caps P Load Q Load Caps
Load (MV
(MW) (MVAr) (MVAr) (MVAr) (MVAr) (MW) (MVAr) (MW) (MVAr) (MVAr) (MW) (MVAr) (MVAr)
(MW) Ar)
MIS System
OMPET Connected ti SIP 132kV - - - 27.0 8.9 - 27.0 8.9 - 27.0 8.9 - 27.0 8.9 -
Orpic (Liwa Plastic) 220kV SPS-2 - - - 200.0 65.7 - 200.0 65.7 - 200.0 65.7 - 200.0 65.7 -
Moon Iron & Steel Co connected to 220KV
- - - - - - 175.0 57.5 - 175.0 57.5 - 175.0 57.5 -
SFZ
Muscat Airport 25 8.2 - 25 8.2 - 25 8.2 - 25 8.2 - 25 8.2 -
Muscat Steel 20 6.6 - 20 6.6 - 20 6.6 - 20 6.6 - 20 6.6 -
Modern Steel 20 6.6 - 20 6.6 - 20 6.6 - 20 6.6 - 20 6.6 -
R.O Ghoubrah 40 13.1 - 40 13.1 - 40 13.1 - 40 13.1 - 40 13.1 -
Total 570.6 187.5 0.0 813.6 267.4 0.0 993.6 326.6 0.0 993.6 326.6 0.0 993.6 326.6 0.0
6916. 304
Grand Total 6310.8 2074.2 1988.0 2273.4 2440.0 7413.9 2436.8 7725.1 2539.1 3160.0 8049.9 2645.9 3280.0
6 0.0
Dhofar System
Al Qarm (2x63MVA) 30.2 9.9 - 19.0 6.2 - 16.6 5.5 - 15.6 5.1 - 16.5 5.4 -
Ashoor (2X125MVA) 46.2 15.2 - 49.5 16.3 - 75.4 24.8 - 80.0 26.3 - 84.8 27.9 -
Awaqad (2X125MVA) 110.4 36.3 40 95.2 31.3 40 84.0 27.6 40 83.7 27.5 40 87.4 28.7 40
Ittin (2X125MVA) 99.4 32.7 40 108.3 35.6 40 94.4 31.0 40 107.5 35.3 40 99.2 32.6 40
NPS (2x63MVA) 45.9 15.1 - 40.7 13.4 - 42.2 13.9 - 44.3 14.6 - 45.1 14.8 -
TX-1 & TX-2 32.0 10.5 40 63.9 21.0 40 80.9 26.6 40 86.6 28.5 40 92.6 30.4 40
S'aadah
TX-3 & TX-4 51.8 17.0 40 55.4 18.2 40 65.8 21.6 40 70.4 23.1 40 90.1 29.6 40
TX-1 & TX-2 94.6 31.1 40 97.1 31.9 40 93.4 30.7 40 85.1 28.0 40 87.9 28.9 40
Salalah Free Zone
TX-3 & TX-4 7.4 2.4 40 23.0 7.6 40 55.8 18.4 40 76.1 25.0 40 89.2 29.3 40
2x30 MVA 23.0 7.6 6 24.4 8.0 6 25.8 8.5 6 27.4 9.0 6 0.0 0.0 6
Thumrait
2x125 MVA - - - - - - - - - - - - 29.0 9.5 40.0
246
Total 540.9 177.8 246.0 576.6 189.5 246.0 634.5 208.5 676.7 222.4 246.0 721.9 237.3 286.0
.0
Salalah Airport 11.0 3.6 - 13.5 4.5 14.9 4.9 - 15.0 4.9 - 15.0 4.9 -

Salalah Methanol Company - - - - - - 50.0 16.4 - 50.0 16.4 - 50.0 16.4 -

Total 11.0 3.6 0.0 13.5 4.5 0.0 64.9 21.3 0.0 65.0 21.4 0.0 65.0 21.4 0.0
246
Grand Total 551.9 181.4 246.0 590.1 194.0 246.0 699.4 229.9 741.7 243.8 246.0 786.9 258.6 286.0
.0

Page | 135
Five-Year Annual Transmission Capability Statement (2017-2021)

Table B 2: 2017 Branch Data Listing


From To Voltage No. Conductor Length Rating Conductor Length Rating
R[Ω/km] X[Ω/km] B[MS/km] R[Ω/km] X[Ω/km] B[MS/km]
Substation Substation (kV Circuits Type (OHL) (Km) (MVA) Type (Cable) (Km) (MVA)

Sur PS Jahloot 400 2 Quad YEW 119.50 0.0211 0.2578 5.18 1774 − − − − − −

Sur PS New Izki 400 2 Quad YEW 222.5 0.0211 0.2578 5.18 1774 − − − − − −

Sohar IPP-2 Sohar Free Zone 220 2 ARCURIA x 2 6.0 0.0258 0.321 3.82 673 2500mm2 XLPE cable 3.5 0.01074 0.321 91.11 625

Sohar Free Zone SIS 220 2 ARCURIA x 2 33.2 0.0258 0.321 3.82 673 2500mm2 XLPE cable 0.5 0.01074 0.321 91.11 625

SIP-A Sohar-1 PS 220 2 − − − − − − 2500mm2 XLPE cable 3.7 0.01074 0.321 91.11 625

Mahadha Al Oha (UAE) 220 2 ARCURIA x 2 51.4 0.0258 0.321 3.82 673 − − − − − −

Barka Power station Filaj 220 2 ARCURIA x 2 10.0 0.0258 0.321 3.82 673 − − − − − −

Barka Power station Filaj 220 2 ARCURIA x 2 9.2 0.0258 0.321 3.82 673 2500mm2 XLPE cable 0.8 0.01074 0.321 91.11 625

Filaj Airport Heights 220 2 ARCURIA x 2 35.2 0.0258 0.321 3.82 673 − − − − − −

Airport Heights Misfah 220 2 ARCURIA x 2 15.5 0.0258 0.321 3.82 673 − − − − − −

Misfah MSQ 220 2 ARCURIA x 2 26.1 0.0258 0.321 3.82 673 − − − − − −

Misfah Jahloot 220 2 ARCURIA x 2 76.0 0.0258 0.321 3.82 673 − − − − − −

MIS SIS 220 2 ARCURIA x 2 107.2 0.0258 0.321 3.82 673 − − − − − −

SPS SIS 220 2 ARCURIA x 2 37.4 0.0258 0.321 3.82 673 2500mm2 XLPE cable 2.9 0.01074 0.312 91.11 625

Mahadha SIS 220 2 ARCURIA x 2 66.5 0.0258 0.321 3.82 673 − − − − − −

Blue City MIS 220 2 ARCURIA x 2 45.6 0.0258 0.321 3.82 673 2500mm2 XLPE cable 5.8 0.01074 0.321 91.11 475

Filaj Blue City 220 2 ARCURIA x 2 33.3 0.0258 0.321 3.82 673 2500mm2 XLPE cable 5.8 0.01074 0.312 91.11 475

Mahadha Ibri 220 2 ARCURIA x 2 146.8 0.0258 0.321 3.82 673 − − − − − −

Barka IPP-3 Misfah 220 2 ARCURIA x 2 55.0 0.0258 0.321 3.82 673 2500mm2 XLPE cable 10.5 0.01074 0.321 91.11 625

Sur 3 PS Sur 2 GS 220 2 ARCURIA x 2 12.6 0.0258 0.321 3.82 673 − − − − − −

Jahloot Al Hamriyah 220 2 ARCURIA x 2 33.7 0.0258 0.321 3.82 673 − − − − − −

Sur 1 GS Sur 2 GS 132 1 − − − − − − 2500mm2 XLPE cable 0.10 0.01074 0.321 91.11 343

Sur 1 GS Sur 2 GS 132 1 − − − − − − 2500mm2 XLPE cable 0.186 0.01074 0.321 91.11 343

Al Kamil JBB Ali 132 2 YEW x 2 54.8 0.04283 0.2821 3.98 293 − − − − − −

Al Kamil Mudhairib 132 2 YEW x 2 51.2 0.04283 0.2821 3.98 293 − − − − − −

Al Kamil JBB Hassan 132 2 YEW x 2 43.5 0.04283 0.2821 3.98 293 − − − − − −

Page | 136
Five-Year Annual Transmission Capability Statement (2017-2021)

Table B. 2 (Continued): 2017 Branch Data Listing


Conductor
From To Voltage No. Length Rating Conductor Length Rating
Type R[Ω/km] X[Ω/km] B[MS/km] R[Ω/km] X[Ω/km] B[MS/km]
Substation Substation (kV Circuits (Km) (MVA) Type (Cable) (Km) (MVA)
(OHL)

Sur JBB Hassan 132 2 YEW x 2 61.0 0.04283 0.2821 3.98 293 − − − − − −

Barka Main Filaj 132 2 YEW x 2 6.3 0.04283 0.2821 3.98 293 − − − − − −

New Izki Mudhaibi 132 2 YEW x 2 34.0 0.04283 0.2821 3.98 293 2500mm2 XLPE cable 0.62 0.01074 0.321 91.11 375

Izki Nizwa 132 2 YEW x 2 31.0 0.04283 0.2821 3.98 293 − − − − − −

Manah Nizwa 132 2 YEW x 2 20.0 0.04283 0.2821 3.98 293 − − − − − −

Mawalleh Rusail Industrial 132 2 − − − − − − 2500mm2 XLPE cable 6.2 0.04282 0.08361 122.522 375

Mobella Barka Main 132 2 YEW x 2 11.5 0.04283 0.2821 3.98 293 − − − − − −

MSQ Wadi Adai 132 2 YEW x 2 8.4 0.04283 0.2821 3.98 293 − − − − − −

Mudhaibi Mudhairib 132 2 YEW x 2 60.0 0.04283 0.2821 3.98 293 − − − − − −

Muladah MIS 132 2 YEW x 2 11.5 0.04283 0.2821 3.98 293 − − − − − −

Nizwa Nahda (PDO) 132 1 ELM x1 67.4 0.1944 0.4207 2.71 89 − − − − − −

Nizwa Bahla 132 2 YEW x1 32.0 0.0857 0.3948 2.85 146 − − − − − −

Rusail Mobella 132 2 YEW x 2 13.5 0.04283 0.2821 3.98 293 − − − − − −

Rusail Sumail 132 2 YEW x 2 34.5 0.04283 0.2821 3.98 293 − − − − − −

Rustaq Muladah 132 2 YEW x 2 29.5 0.04283 0.2821 3.98 293 − − − − − −

SIS Sohar Grid 132 2 YEW x 2 27.5 0.04283 0.2821 3.98 293 − − − − − −

Sohar Grid Wadi Jizzi 132 2 YEW x 2 28.3 0.04283 0.2821 3.98 293 − − − − − −

Sumail Izki 132 2 YEW x 2 60.8 0.04283 0.2821 3.98 293 − − − − − −

Wadi Adai Al Falaj 132 2 YEW x 2 2.7 0.04283 0.2821 3.98 293 − − − − − −

Wadi Jizzi Mahadha 132 2 ELM x 2 36.4 0.0972 0.3168 3.8 178 − − − − − −

Manah Adam 132 2 YEW x 2 48.7 0.04283 0.2821 3.98 293 − − − − − −

New Ghubrah Bousher 132 3 − − − − − − 2500mm2 XLPE cable 2 0.04 0.08 122.52 375

Bousher MSQ 132 1 YEW x 2 2.0 0.04283 0.2821 3.98 293 2500mm2 XLPE cable 2.7 0.04 0.08 122.52 375

New Ghubrah MSQ 132 3 YEW x 2 2.0 0.04283 0.2821 3.98 293 2500mm2 XLPE cable 4.3 0.04 0.08 122.52 375

Ghubrah old Ghubrah new 132 2 − − − − − − 2500mm2 XLPE cable 0.8 0.04 0.08 122.52 375

Airport Heights Mawalleh North 132 2 − − − − − − 2500mm2 XLPE cable 8.6 0.04 0.08 122.52 375

Page | 137
Five-Year Annual Transmission Capability Statement (2017-2021)

Table B. 2 (Continued): 2017 Branch Data Listing

From To Voltage No. Conductor Length Rating Conductor Length Rating


R[Ω/km] X[Ω/km] B[MS/km] R[Ω/km] X[Ω/km] B[MS/km]
Substation Substation (kV Circuits Type (OHL) (Km) (MVA) Type (Cable) (Km) (MVA)

Liwa Shinas 132 2 YEW x 2 19.5 0.04283 0.2821 3.98 293 − − − − − −

Khaborah Saham 132 2 YEW x 2 53.8 0.04283 0.2821 3.98 293 − − − − − −

Saham SIS 132 2 YEW x 2 23.3 0.04283 0.2821 3.98 293 − − − − − −

Mahadha Wadi Sa'a 132 2 YEW x 2 31.5 0.04283 0.2821 3.98 293 − − − − − −

Wadi Sa'a Dank 132 2 225 AAAC 58.3 0.04283 0.2821 3.98 89 − − − − − −

Jahloot Yitti 132 2 ARCURIA x 2 25.1 0.0258 0.321 3.82 404 − − − − − −

Rusail Misfah 132 2 YEW x 2 12.8 0.04283 0.2821 3.98 293 − − − − − −

Misfah Wadi Adai 132 2 YEW x 2 33.9 0.04283 0.2821 3.98 293 − − − − − −

Filaj Nakhal 132 2 YEW x 2 24.1 0.04283 0.2821 3.98 293 − − − − − −

Mahadha Bureimi 132 2 ELM x 2 36.9 0.0972 0.3168 3.8 89 − − − − − −

MSQ Qurum 132 2 YEW x 2 9.9 0.04283 0.2821 3.98 293 − − − − − −

Ibri Dank 132 2 YEW x 2 55.5 0.04283 0.2821 3.98 293 − − − − − −

Jahloot Quriyat 132 2 YEW x 2 48.7 0.04283 0.2821 3.98 293 − − − − − −

Nizwa Madinata Nizwa 132 2 YEW x2 12.4 0.04283 0.2821 3.98 293 − − − − − −

Wadi Kabir Al Hamriyah 132 2 YEW x1 1.8 0.0857 0.3948 2.85 146 1200mm2 1CCUXLPE cable 1.15 0.03 0.12 64.70 172

Al Hamriyah Muttrah 132 2 YEW x 2 2.8 0.04283 0.2821 3.98 293 2500mm2 XLPE cable 3.2 0.04 0.08 122.52 375

Sur Ayjah 132 2 YEW x2 34.5 0.04283 0.2821 3.98 293 − − − − − −

Al Hamryah Wadi Adai 132 2 YEW x1 3.7 0.0857 0.3948 2.85 146 − − − − − −

Qurum Al Hamryah 132 2 YEW x 2 7.6 0.04283 0.2821 3.98 293 − − − − − −

Rusail Rusail Industrial 132 4 − − − − − − 2500mm2 XLPE cable 0.192 0.04 0.08 122.52 375

Filaj Madinata Barka 132 2 YEW x2 11.5 0.04283 0.2821 3.98 293 − − − − − −

Madinata Barka Muladah 132 2 YEW x2 35.2 0.04283 0.2821 3.98 293 − − − − − −

Dank Al Hayl 132 2 YEW x 2 52.4 0.04283 0.2821 3.98 293 − − − − − −

Airport Height Mawalleh South 132 2 − − − − − − 2500mm2 XLPE cable 9.1 0.04 0.08 122.52 375

Airport Height Ghala 132 2 − − − − − − 2500mm2 XLPE cable 3.7 0.04 0.08 122.52 375

MIS Al Khadhra 132 2 YEW x 2 25.7 0.04283 0.2821 3.98 293 − − − − − −

Page | 138
Five-Year Annual Transmission Capability Statement (2017-2021)

Table B. 2 (Continued): 2017 Branch Data Listing


Conductor
From To Voltage No. Length Rating Conductor Length Rating
Type R[Ω/km] X[Ω/km] B[MS/km] R[Ω/km] X[Ω/km] B[MS/km]
Substation Substation (kV Circuits (Km) (MVA) Type (Cable) (Km) (MVA)
(OHL)

Al Khadhra Khaborah 132 2 YEW x 2 27.9 0.04283 0.2821 3.98 293 − − − − − −


Mahadha Bureimi Industrial 132 2 YEW x2 32.9 0.04283 0.2821 3.98 293 − − − − − −
Bureimi Industrial Bureimi 132 2 YEW x2 0.3 0.04283 0.2821 3.98 293 2500mm2 XLPE cable 5.6 0.04 0.08 122.52 375
Mawalleh South-B Seeb Main 132 2 − − − − − − 2500mm2 XLPE cable 7.8 0.04 0.08 122.52 375
Amerat Jahloot 132 2 YEW x2 23.3 0.04283 0.2821 3.98 293 − − − − − −
MSQ Amerat 132 2 YEW x2 25 0.04283 0.2821 3.98 293 − − − − − −
Mudhairib Ibra 132 2 YEW x 2 28 0.04283 0.2821 3.98 293 − − − − − −
New Izki Izki 132 2 YEW x 2 15 0.04283 0.2821 3.98 293 2500mm2 XLPE cable 0.62 0.04 0.08 122.52 375
A'salam Seeb Main 132 2 − − − − − − 2500mm2 XLPE cable 7.1 0.04 0.08 122.52 375
Mobella A'salam 132 2 − − − − − − 2500mm2 XLPE cable 8.6 0.04 0.08 122.52 375
Ibri Dreez 132 2 YEW x 2 30 0.04283 0.2821 3.98 293 − − − − − −
Sohar Free Zone Liwa 132 2 YEW x 2 2.3 0.04283 0.2821 3.98 293 − − − − − −
Wadi Jizzi Sohar Free Zone 132 2 YEW x 2 27.3 0.04283 0.2821 3.98 293 − − − − − −
Muttrah Al Falaj 132 1 − − − − − − 2500mm2 XLPE cable 3 0.04282 0.08361 122.522 300
Muttrah Wadi Kabair 132 1 YEW x2 1.5 0.04283 0.2821 3.98 293 2500mm2 XLPE cable 2 0.04282 0.08361 122.522 375
Quriyat Daghmar 132 2 YEW x 2 4 0.04283 0.2821 3.98 293 − − − − − −
Nizwa Jebreen 132 2 YEW x 2 24.5 0.04283 0.2821 3.98 293 − − − − − −

Jebreen Ibri 132 2 YEW x 2 90.5 0.04283 0.2821 3.98 293 − − − − − −

Dhofar System

Thumrait Ittin 132 2 ELM x 2 61.2 0.09 0.3 3.00 183 − − − − − −

Ittin Al Qurum 132 2 YEW x 2 22.63 0.0388 0.289 1.43 359 − − − − − −

Ittin SFZ 132 2 YEW x 2 25.32 0.0388 0.289 1.43 359 − − − − − −

SFZ Awqad 132 2 YEW x 2 18.8 0.0388 0.289 1.43 359 − − − − − −

Ashoor Al Qurum 132 2 YEW x 2 24.45 0.0388 0.289 1.43 359 2500mm2 XLPE cable 2.52 0.01075 0.141 91.1 279

SFZ NPS 132 2 YEW x 2 0.546 0.0388 0.289 1.43 359 2500mm2 XLPE cable 0.1 0.01075 0.141 91.1 279

Thumrait Harweel 132 1 ELM x 2 84.5 0.09 0.3 3.00 183 − − − − − −

Awqad A'saada 132 2 YEW x 2 15 0.0388 0.289 1.43 330 2500mm2 XLPE cable 6.5 0.01075 0.141 91.1 300

132 2 YEW x 2 8.5 0.0388 0.289 1.43 330 2500mm2 XLPE cable 1.2 0.01075 0.141 91.1 279
A'saada Ashoor (Portion-1)
132 2 YEW x 2 33.3 0.0388 0.289 1.43 330 2500mm2 XLPE cable 6.5 0.01075 0.141 91.1 300
A'saada Ashoor (Portion-2)

Page | 139
Five-Year Annual Transmission Capability Statement (2017-2021)

2018 Delesions

Table B 3: Progressive Change to Branch Circuit Data for 2018-20121


From To Voltage No. Conductor Length Rating Conductor Length Rating
R[Ω/km] X[Ω/km] B[MS/km] R[Ω/km] X[Ω/km] B[MS/km]
Substation Substation (kV Circuits Type (OHL) (Km) (MVA) Type (Cable) (Km) (MVA)

Mahadha Ibri 220 2 ARCURIA x 2 146.8 0.0258 0.321 3.82 673 − − − − − −

Filaj Airport Heights 220 2 ARCURIA x 2 35.2 0.0258 0.321 3.82 673 − − − − − −

Khaborah Saham 132 2 YEW x 2 53.8 0.04283 0.2821 3.98 293 − − − − − −

MIS Al Khadhra 132 2 YEW x 2 25.7 0.04283 0.2821 3.98 293 − − − − − −

New Izki Mudhaibi 132 2 YEW x 2 34.0 0.04283 0.2821 3.98 293 2500mm2 XLPE cable 0.62 0.01074 0.321 91.11 625

SIS Sohar Grid 132 2 YEW x 2 27.5 0.04283 0.2821 3.98 293 − − − − − −

2018 Additions

From To Voltage No. Conductor Length Rating Conductor Length Rating


R[Ω/km] X[Ω/km] B[MS/km] R[Ω/km] X[Ω/km] B[MS/km]
Substation Substation (kV Circuits Type (OHL) (Km) (MVA) Type (Cable) (Km) (MVA)

Ibri IPP New Izki 400 2 Quad YEW 250 0.0210914 0.2577821 5.18 1774 − − − − − −
New Izki Misfah 400 2 Quad YEW 100 0.0211 0.2578 5.18 1774 − − − − − −
Sohar Free Zone SIS 220 2 Quad YEW 42 0.0210914 0.2577821 5.18 975 − − − − − −
Sohar Free Zone Mahadha 400 2 Quad YEW 63 0.0210914 0.2577821 5.18 1774 − − − − − −
Sohar Free Zone
2500mm2 XLPE cable 3.3 0.01074 0.321 91.10619 2273
(Portion 1)
Sohar IPP-3 400 2 Quad YEW 6 0.0210914 0.2577821 5.184822 1774
Sohar Free Zone
2500mm2 XLPE cable 0.9 0.01074 0.321 91.10619 2273
(Portion 2)
Sohar IPP-3 Sohar Free Zone 400 2 − − − − − − 2500mm2 XLPE cable 10.2 0.01074 0.321 91.10619 2273
Ibri Ibri IPP 220 2 ARCURIA x 2 32 0.0258 0.321 3.82 673 − − − − − −
Ibri IPP Mahadha 220 2 ARCURIA x 2 124 0.0258 0.321 3.82 673 − − − − − −

SIP-A SPS 220 1 − − − − − − 2500mm2 XLPE cable 3.2 0.01074 0.321 91.10619 625

Filaj Mobella 220 2 ARCURIA x 2 10.22 0.0258 0.321 3.82 673 − − − − − −

Mobailah Airport Heights 220 2 ARCURIA x 2 25.5 0.0258 0.321 3.82 673 − − − − − −

Khaborah DAS 132 2 YEW x 2 33 0.04283 0.2821 3.98 293 − − − − − −

DAS Saham 132 2 YEW x 2 26 0.04283 0.2821 3.98 293 − − − − − −

Shinas Madinat Shinas 132 2 YEW x 2 24.06 0.04283 0.2821 3.98 293 − − − − − −

MIS Swauiq 132 2 YEW x 2 7.2 0.04283 0.2821 3.98 293 − − − − − −

Page | 140
Five-Year Annual Transmission Capability Statement (2017-2021)

Table B. 3 (Continued): Progressive Change to Branch Circuit Data for 2018-20121


2018 Additions
Conductor
From To Voltage No. Length Rating Conductor Length Rating
Type R[Ω/km] X[Ω/km] B[MS/km] R[Ω/km] X[Ω/km] B[MS/km]
Substation Substation (kV Circuits (Km) (MVA) Type (Cable) (Km) (MVA)
(OHL)

Swauiq Al Khadhra 132 2 YEW x 2 18.9 0.04283 0.2821 3.98 293 − − − − − −


Mudhaibi Sinaw 132 2 YEW x 2 30.6 0.04283 0.2821 3.98 293 − − − − − −
Sinaw New Izki 132 2 YEW x 2 53.3 0.04283 0.2821 3.98 293 2500mm2 XLPE cable 0.62 0.01074 0.321 91.11 625
SIS Uwaynat 132 2 YEW x 2 17 0.04283 0.2821 3.98 293 − − − − − −
Uwaynat Sohar Grid 132 2 YEW x 2 19 0.04283 0.2821 3.98 293 − − − − − −

2019 Delesions

From To Voltage No. Conductor Length Rating Conductor Length Rating


R[Ω/km] X[Ω/km] B[MS/km] R[Ω/km] X[Ω/km] B[MS/km]
Substation Substation (kV Circuits Type (OHL) (Km) (MVA) Type (Cable) (Km) (MVA)

Sur PS New Izki 400 2 Quad YEW 223.0 0.0210914 0.2577821 5.184822 975 − − − − − −
New Izki Misfah 400 2 Quad YEW 100 0.0211 0.2578 5.18 975 − − − − − −
MIS SIS 220 2 ARCURIA x 2 107.0 0.0258 0.321 3.82 673 − − − − − −
Mobella Barka Main 132 2 YEW x 2 11.5 0.04283 0.2821 3.98 293 − − − − − −
Rusail Sumail 132 2 YEW x 2 34.5 0.04283 0.2821 3.98 293 − − − − − −
Izki Nizwa 132 2 YEW x 2 31.0 0.04283 0.2821 3.98 293 − − − − − −
Mudhairib Ibra 132 2 YEW x 2 28 0.04283 0.2821 3.98 293 − − − − − −
Al Kamil Mudhairib 132 2 YEW x 2 51.2 0.04283 0.2821 3.98 293 − − − − − −
Khaborah DAS 132 2 YEW x 2 33 0.04283 0.2821 3.98 293 − − − − − −

Dhofar System

Thumrait Harweel 132 1 ELM x 2 84.5 0.09 0.3 3.00 183 − − − − − −

Page | 141
Five-Year Annual Transmission Capability Statement (2017-2021)

Table B. 3 (Continued): Progressive Change to Branch Circuit Data for 2018-20121


2019 Additions

From To Voltage No. Conductor Length Rating Conductor Length Rating


R[Ω/km] X[Ω/km] B[MS/km] R[Ω/km] X[Ω/km] B[MS/km]
Substation Substation (kV Circuits Type (OHL) (Km) (MVA) Type (Cable) (Km) (MVA)

Sur PS Qabil 400 2 Quad YEW 116.54 0.0210914 0.2577821 5.184822 1774 − − − − − −

Qabil New Izki 400 2 Quad YEW 106.18 0.0210914 0.2577821 5.184822 1774 − − − − − −

Sohar Free Zone Shinas 132 2 Quad YEW 30 0.0210914 0.2577821 5.184822 585 − − − − − −

MIS KIS 220 2 ARCURIA x 2 53.5 0.0258 0.321 3.82 673 − − − − − −

KIS SIS 220 2 ARCURIA x 2 70.8 0.0258 0.321 3.82 673 − − − − − −

Nakhal Wadi Bani Awf 132 2 YEW x 2 54.5 0.04283 0.2821 3.98 293 − − − − − −

Wadi Bani Awf Rustaq 132 2 YEW x 2 33.2 0.04283 0.2821 3.98 293 − − − − − −

Ghala Ghala Height 132 2 − − − − − − 2500mm2 XLPE cable 7 0.04 0.08 122.52 375

Ghala Height Bousher 132 2 − − − − − − 2500mm2 XLPE cable 7 0.04 0.08 122.52 375

Mudhaibi Samad 132 2 YEW x 2 38.5 0.04283 0.2821 3.98 293 − − − − − −

Mobella Halban 132 2 YEW x 2 4.62 0.04283 0.2821 3.98 293 − − − − − −

Halban Barka Main 132 2 YEW x 2 7.74 0.04283 0.2821 3.98 293 − − − − − −
Sumail Industrial
Rusail 132 2 YEW x 2 40.6 0.04283 0.2821 3.98 293 2500mm2 XLPE cable 1.6 0.04 0.08 122.52 375
Area
Sumail Industrial Area Sumail 132 2 YEW x 2 22.8 0.04283 0.2821 3.98 293 2500mm2 XLPE cable 1.6 0.04 0.08 122.52 375

Mudhairib Bedyah 132 2 YEW x 2 14.7 0.04283 0.2821 3.98 293 − − − − − −

Bedyah Al Kamil 132 2 YEW x 2 36.7 0.04283 0.2821 3.98 293 − − − − − −

Nizwa Birkat Al Mouz 132 2 YEW x 2 15.5 0.04283 0.2821 3.98 293 − − − − − −

Birkat Al Mouz Izki 132 2 YEW x 2 16.5 0.04283 0.2821 3.98 293 − − − − − −

DAS KIS 132 2 YEW x 2 16 0.04283 0.2821 3.98 293 − − − − − −

KIS Khaborah 132 2 YEW x 2 17 0.04283 0.2821 3.98 293 − − − − − −

Mudhairib Qabil 132 2 YEW x 2 6 0.04283 0.2821 3.98 293 − − − − − −

Qabil Ibra 132 2 YEW x 2 22 0.04283 0.2821 3.98 293 − − − − − −

Mahadha Bureimi 132 2 YEW x 2 32.9 0.04283 0.2821 3.98 293 2500mm2 XLPE cable 5.5 0.04 0.08 122.52 375

Page | 142
Five-Year Annual Transmission Capability Statement (2017-2021)

Table B. 3 (Continued): Progressive Change to Branch Circuit Data for 2018-20121


2019 Additions
Conductor Conductor
From To Voltage No. Length Rating Length Rating
Type R[Ω/km] X[Ω/km] B[MS/km] Type R[Ω/km] X[Ω/km] B[MS/km]
Substation Substation (kV Circuits (Km) (MVA) (Km) (MVA)
(OHL) (Cable)

Dhofar System

Thumrait Wind Farm 132 1 ELM x 2 65.5 0.09 0.3 3.00 183 − − − − − −

Thumrait Wind Farm 132 1 YEW x 2 10 0.0388 0.289 1.43 359 − − − − − −

Wind Farm Harweel 132 1 ELM x 2 19 0.09 0.3 3.00 183 − − − − − −

Wind Farm Harweel 132 1 YEW x 2 10 0.0388 0.289 1.43 359 − − − − − −

2020 Delesions

Conductor
From To Voltage No. Length Rating Conductor Length Rating
Type R[Ω/km] X[Ω/km] B[MS/km] R[Ω/km] X[Ω/km] B[MS/km]
Substation Substation (kV Circuits (Km) (MVA) Type (Cable) (Km) (MVA)
(OHL)

Dank Al Hayl 132 2 YEW x 2 51.8 0.04283 0.2821 3.98 293 − − − − − −

Mawalleh Rusail Industrial 132 2 − − − − − − 2500mm2 XLPE cable 6 0.04 0.08 122.52 375

2020 Additions

From To Voltage No. Conductor Length Rating Conductor Length Rating


R[Ω/km] X[Ω/km] B[MS/km] R[Ω/km] X[Ω/km] B[MS/km]
Substation Substation (kV Circuits Type (OHL) (Km) (MVA) Type (Cable) (Km) (MVA)

Dank Yanqual 132 2 YEW x 2 38.4 0.04283 0.2821 3.98 293 − − − − − −

Yanqual Al Hayl 132 2 YEW x 2 20 0.04283 0.2821 3.98 293 − − − − − −

Mawalleh Khoudh 132 2 240 ZTACIR 2.5 0.0261 0.075 0.0153 250 2500mm2 XLPE cable 0.5 0.04 0.08 122.52 375

Khoudh Rusail Industrial 132 2 240 ZTACIR 6 0.0261 0.075 0.0153 250 − − − − − −

Page | 143
Five-Year Annual Transmission Capability Statement (2017-2021)

Table B. 3 (Continued): Progressive Change to Branch Circuit Data for 2018-20121


2021 Deletions
From To Voltage No. Conductor Length Rating Conductor Length Rating
R[Ω/km] X[Ω/km] B[MS/km] R[Ω/km] X[Ω/km] B[MS/km]
Substation Substation (kV Circuits Type (OHL) (Km) (MVA) Type (Cable) (Km) (MVA)

Misfah MSQ 220 2 ARCURIA x 2 26.1 0.0258 0.321 3.82 673 − − − − − −

Rusail Misfah 132 2 YEW x 2 12.8 0.04283 0.2821 3.98 293 − − − − − −

Misfah Wadi Adai 132 2 YEW x 2 33.9 0.04283 0.2821 3.98 293 − − − − − −

New Ghubrah MSQ 132 3 YEW x 2 2.0 0.04283 0.2821 3.98 293 2500mm2 XLPE cable 4.3 0.04 0.08 122.52 375

Jebreen Ibri 132 2 YEW x 2 90.5 0.04283 0.2821 3.98 293 − − − − − −

Sohar Grid Wadi Jizzi 132 2 YEW x 2 28.3 0.04283 0.2821 3.98 293 − − − − − −

2021 Additions

From To Voltage No. Conductor Length Rating Conductor Length Rating


R[Ω/km] X[Ω/km] B[MS/km] R[Ω/km] X[Ω/km] B[MS/km]
Substation Substation (kV Circuits Type (OHL) (Km) (MVA) Type (Cable) (Km) (MVA)

Rusail Misfah 400 2 Quad YEW 12.3 0.0210914 0.2577821 5.184822 1774 − − − − − −

Misfah Misfah IPP 220 2 ARCURIA x 2 3.0 0.0258 0.321 3.82 673 − − − − − −

Misfah IPP MSQ 220 2 ARCURIA x 2 22.5 0.0258 0.321 3.82 673 2500mm2 XLPE cable 0.7 0.01074 0.321 91.10619 625

Misfah Wadi Adai 132 2 YEW x 2 33.0 0.04283 0.2821 3.98 293 2500mm2 XLPE cable 0.92 0.04 0.08 122.52 375

MSQ Khuwair 132 2 YEW x 2 2 0.04283 0.2821 3.98 293 − − − − − −

Khuwair New Ghubrah 132 2 − − − − − − 2500mm2 XLPE cable 4.6 0.04 0.08 122.52 375

Jebreen Madinat Ibri 132 2 YEW x 2 45 0.04283 0.2821 3.98 293 − − − − − −

Madinat Ibri Ibri 132 2 YEW x 2 45 0.04283 0.2821 3.98 293 − − − − − −

Sohar Grid Falaj Al Qabail 132 2 YEW x 2 16 0.04283 0.2821 3.98 293 − − − − − −

Falaj Al Qabail Wadi Al Jizzi 132 2 YEW x 2 28 0.04283 0.2821 3.98 293 − − − − − −

Page | 144
Five-Year Annual Transmission Capability Statement (2017-2021)

Table B 4: Grid Station Transformers Data at 2017 Peak


Rating Voltage Vector Tap Tap Step Neutral Min Max Off-Nominal Tap range Reactance
Substation Tx. No
(MVA) (kV) Group Side (%) Tap Tap Tap Upper (pu) Lower (pu) (% on rating)
1 750 400/220 YNa0d1 HV 1.25 11 1 21 12.50 -12.50 21.95
2 750 400/220 YNa0d1 HV 1.25 11 1 21 12.50 -12.50 21.96
Sur IPP 3 750 400/220 YNa0d1 HV 1.25 11 1 21 12.50 -12.50 21.90
4 750 400/220 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 23.00
5 750 400/220 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 22.08
3 500 400/220 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 22.08
4 500 400/220 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 22.08
Jahloot
5 500 400/220 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 22.08
6 500 400/220 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 22.08
1 500 400/220 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 22.08
2 500 400/220 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 22.08
New Izki
1 500 220/132 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 23.28
2 500 220/132 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 23.28
1 500 220/132 YNa0d1 LV 1.11 6 1 20 5.55 -15.54 23.25
Filaj
2 500 220/132 YNa0d1 LV 1.11 6 1 20 5.55 -15.54 23.26
1 500 220/132 YNa0d1 LV 1.11 6 1 20 5.55 -15.54 23.30
MSQ
2 500 220/132 YNa0d1 LV 1.11 6 1 20 5.55 -15.54 23.24
1 500 220/132 YNa0d1 HV 1.10 6 1 20 5.50 -15.40 21.23
Sohar Industrial Area
2 500 220/132 YNa0d1 HV 1.10 6 1 20 5.50 -15.40 21.24
1 500 220/132 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 21.37
SIS
2 500 220/132 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 21.38
1 500 220/132 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 21.35
MIS
2 500 220/132 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 21.43
1 500 220/132 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 23.81
Airport Hight
2 500 220/132 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 23.90
1 500 220/132 YNa0d1 HV 1.10 6 1 20 5.50 -15.40 23.28
Ibri
2 500 220/132 YNa0d1 HV 1.10 6 1 20 5.50 -15.40 23.30
1 500 220/132 YNa0d1 HV 1.10 6 1 20 5.50 -15.40 22.10
Sur
2 500 220/132 YNa0d1 HV 1.10 6 1 20 5.50 -15.40 22.15

Page | 145
Five-Year Annual Transmission Capability Statement (2017-2021)

Table B. 4 (Continued): Grid Station Transformers Data at 2017 Peak


Rating Voltage Vector Tap Tap Step Neutral Min Max Off-Nominal Tap range Reactance
Substation Tx. No
(MVA) (kV) Group Side (%) Tap Tap Tap Upper (pu) Lower (pu) (% on rating)

1 500 400/220 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 22.08


2 500 400/220 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 22.08
Misfah 3 500 400/220 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 22.08
1 500 220/132 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 23.28
2 500 220/132 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 23.28
1 500 220/132 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 23.15
Hamryah
2 500 220/132 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 2274.00
1 500 220/132 YNa0d1 HV 1.11 6 1 20 5.50 -15.54 22.02
Jahloot
2 500 220/132 YNa0d1 HV 1.11 6 1 20 5.50 -15.54 22.19
1 315 220/132 YNa0d1 HV 1.10 6 1 20 5.50 -15.40 13.96
Mahadha
2 315 220/132 YNa0d1 HV 1.10 6 1 20 5.50 -15.40 13.98
1 160 220/33 YNd5 HV 1.10 5 1 19 4.42 -15.45 18.11
Blue City
2 160 220/33 YNd5 HV 1.10 5 1 19 4.42 -15.45 18.57
1 40 132/33 YNd5 HV 1.11 6 1 19 5.55 -14.43 11.79
Adam
2 40 132/33 YNd5 HV 1.11 6 1 19 5.55 -14.43 11.72
1 125 132/33 YNd5 HV 1.10 5 1 19 4.42 -15.46 18.31
Airport Hight
2 125 132/33 YNd5 HV 1.10 5 1 19 4.42 -15.46 18.37
1 125 132/33 YNd5 HV 1.67 4 1 13 5.00 -15.00 19.56
Al Falaj
2 125 132/33 YNd5 HV 1.67 4 1 13 5.00 -15.00 19.49
1 40 132/33 YNd11 HV 1.25 5 1 17 5.00 -15.00 11.92
Al Hayl
2 40 132/33 YNd11 HV 1.11 5 1 17 5.00 -15.00 11.69
1 125 132/33 YNd5 HV 1.25 5 1 19 4.44 -15.54 17.73
Amerat
2 125 132/33 YNd5 HV 1.25 5 1 19 4.44 -15.54 17.65
1 125 132/33 YNd5 HV 1.11 5 1 19 4.44 -15.54 17.51
A'salam
2 125 132/33 YNd5 HV 1.11 5 1 19 4.44 -15.54 17.61
1 125 132/33 YNd5 HV 1.11 5 1 19 4.44 -15.54 18.39
Ayjah
1 125 132/33 YNd5 HV 1.11 5 1 19 4.44 -15.54 18.39
1 125 132/33 YNd5 HV 1.11 6 1 19 5.50 -14.30 18.02
Bahla
2 125 132/33 YNd5 HV 1.11 6 1 19 5.50 -14.30 18.20

Page | 146
Five-Year Annual Transmission Capability Statement (2017-2021)

Table B. 4 (Continued): Grid Station Transformers Data at 2017 Peak


Rating Voltage Vector Tap Tap Step Neutral Min Max Off-Nominal Tap range Reactance
Substation Tx. No (% on
(MVA) (kV) Group Side (%) Tap Tap Tap Upper (pu) Lower (pu) rating)
1 125 132/33 YNd5 HV 1.67 4 1 5 4.00 -15.00 17.00
Barka Main 2 125 132/33 YNd5 HV 1.67 4 1 5 4.00 -15.00 17.00
3 125 132/33 YNd5 HV 1.11 5 1 19 4.44 -15.54 17.60
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.44
Boushar
3 125 132/33 YNd5 HV 1.10 5 1 19 4.42 -15.46 18.56
4 125 132/33 YNd5 HV 1.10 5 1 19 4.42 -15.46 18.12
1 125 132/33 YNd5 HV 1.10 5 1 19 4.42 -15.46 18.87
Bureimi
2 125 132/33 YNd5 HV 1.10 5 1 19 4.42 -15.46 18.91
1 125 132/33 YNd5 HV 1.11 5 1 19 4.44 -15.54 18.59
Bureimi Industrial
2 125 132/33 YNd5 HV 1.11 5 1 19 4.44 -15.54 18.57
1 63 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 14.56
Dank
2 63 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 14.56
1 125 132/33 YNd5 HV 1.11 5 1 19 4.44 -15.54 17.66
Ghala
2 125 132/33 YNd5 HV 1.11 5 1 19 4.44 -15.54 17.75
1 42 132/33 YNd5 HV 1.35 10 1 19 12.17 -12.17 13.30
2 42 132/33 YNd5 HV 1.35 10 1 19 12.17 -12.17 13.20
Ghubrah
1 125 132/33 YNd5 HV 2.22 5 1 19 4.44 -15.54 17.37
2 125 132/33 YNd5 HV 1.11 5 1 19 4.44 -15.54 17.31
1 125 132/33 YNd5 HV 1.11 5 1 19 4.44 -15.54 18.38
Ibra
2 125 132/33 YNd5 HV 1.11 5 1 19 4.44 -15.54 17.95
1 125 132/33 YNd5 HV 1.10 5 1 19 4.42 -15.46 18.44
2 125 132/33 YNd5 HV 1.10 5 1 19 4.42 -15.46 18.38
Ibri
1 63 132/33 YNd11 HV 1.21 5 1 17 5.00 -15.00 11.80
2 63 132/33 YNd11 HV 1.21 5 1 17 5.00 -15.00 11.97
1 125 132/33 YNd5 HV 1.11 5 1 19 4.44 -15.54 17.68
Izki
2 125 132/33 YNd5 HV 1.11 5 1 19 4.44 -15.54 17.31
1 125 132/33 YNd5 HV 1.10 7 2 21 5.50 -15.40 19.03
Jahloot
2 125 132/33 YNd5 HV 1.10 7 2 21 5.50 -15.40 19.27
1 125 132/33 YNd5 HV 1.10 7 2 21 5.50 -15.40 17.84
JBB Ali
2 125 132/33 YNd5 HV 1.10 7 2 21 5.50 -15.40 17.76

Page | 147
Five-Year Annual Transmission Capability Statement (2017-2021)

Table B. 4 (Continued): Grid Station Transformers Data at 2017 Peak


Rating Voltage Vector Tap Tap Step Neutral Min Max Off-Nominal Tap range Reactance
Substation Tx. No
(MVA) (kV) Group Side (%) Tap Tap Tap Upper (pu) Lower (pu) (% on rating)
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
JBB Hassan
2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
1 125 132/33 YNd5 HV 1.67 4 1 13 5.00 -15.00 18.21
Khaburah
2 125 132/33 YNd5 HV 1.67 4 1 13 5.00 -15.00 18.03
1 125 132/33 YNd5 HV 1.11 5 1 19 4.44 -15.54 17.76
Khadhra
2 125 132/33 YNd5 HV 1.11 5 1 19 4.44 -15.54 17.74
1 125 132/33 YNd5 HV 1.10 5 1 19 4.42 -15.46 18.01
2 125 132/33 YNd5 HV 1.10 5 1 19 4.42 -15.46 18.24
Liwa
3 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
4 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
1 125 132/33 YNd5 HV 1.11 5 1 19 4.44 -15.54 18.59
Madinat Nizwa
2 125 132/33 YNd5 HV 1.11 6 1 20 4.44 -15.54 18.37
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Madinata Barka
2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
1 30 132/33 YNd11 HV 1.67 7 1 13 10.00 -10.00 12.33
Mahadha
2 30 132/33 YNd11 HV 1.67 7 1 13 10.00 -10.00 12.49
Mawalleh North 1 50 132/11 YNd1 HV 1.11 5 1 19 4.42 -15.47 32.21
1 125 132/33 YNd5 HV 1.25 5 1 17 5.00 -15.00 18.70
2 125 132/33 YNd5 HV 1.25 5 1 17 5.00 -15.00 18.70
Mawalleh South
3 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.24
4 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.24
1 125 132/33 YNd5 HV 1.10 5 1 19 4.42 -15.46 18.44
MIS
2 125 132/33 YNd5 HV 1.10 5 1 19 4.42 -15.46 18.64
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.39
Misfah
2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.39
1 125 132/33 YNd5 HV 1.10 5 1 19 4.42 -15.46 18.35
Mobella
2 125 132/33 YNd5 HV 1.10 5 1 19 4.42 -15.46 18.35
1 125 132/33 YNd5 HV 1.67 4 1 13 4.42 -15.47 17.44
MSQ 2 125 132/33 YNd5 HV 1.67 4 1 13 4.42 -15.47 17.62
3 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.29
1 125 132/33 YNd5 HV 1.11 5 1 19 4.44 -15.54 17.62
Mudhaibi
2 125 132/33 YNd5 HV 1.10 5 1 19 4.42 -15.46 15.32

Page | 148
Five-Year Annual Transmission Capability Statement (2017-2021)

Table B. 4 (Continued): Grid Station Transformers Data at 2017 Peak


Rating Voltage Vector Tap Tap Step Neutral Min Max Off-Nominal Tap range Reactance
Substation Tx. No
(MVA) (kV) Group Side (%) Tap Tap Tap Upper (pu) Lower (pu) (% on rating)
1 125 132/33 YNd5 HV 1.10 7 2 21 5.50 -15.40 17.81
Mudhairib
2 125 132/33 YNd5 HV 1.10 7 2 21 5.50 -15.40 17.79
1 125 132/33 YNd5 HV 1.10 5 1 19 4.42 -15.46 18.43
2 125 132/33 YNd5 HV 1.10 5 1 19 4.42 -15.46 18.44
Muladah
3 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
4 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.50
Muttrah
2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.32
1 125 132/33 YNd5 HV 1.10 5 1 19 4.42 -15.46 18.06
Nakhal
2 125 132/33 YNd5 HV 1.10 5 1 19 4.42 -15.46 18.07
1 125 132/33 YNd5 HV 1.10 6 1 19 5.50 -14.30 18.64
Nizwa
2 125 132/33 YNd5 HV 1.10 6 1 19 5.50 -14.30 17.92
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
New Izki
2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
1 125 132/33 YNd5 HV 1.10 5 1 19 4.42 -15.46 18.44
Quriyat
2 125 132/33 YNd5 HV 1.10 5 1 19 4.42 -15.46 18.41
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.28
Qurum
2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.51
1 125 132/33 YNd5 HV 1.11 5 1 19 4.44 -15.54 17.99
2 125 132/33 YNd5 HV 1.11 5 1 19 4.44 -15.54 17.92
Rusail Industrial
3 125 132/33 YNd5 HV 1.11 5 1 19 4.44 -15.54 17.83
4 125 132/33 YNd5 HV 1.11 5 1 19 4.44 -15.54 17.26
1 125 132/33 YNd5 HV 1.11 5 1 19 4.44 -15.54 17.52
Rustaq 2 125 132/33 YNd5 HV 1.11 5 1 19 4.44 -15.54 17.52
3 125 132/33 YNd5 HV 1.11 5 1 19 4.44 -15.54 17.51
1 125 132/33 YNd5 HV 1.10 5 1 19 4.42 -15.46 18.31
Saham
2 125 132/33 YNd5 HV 1.10 5 1 19 4.42 -15.46 18.27
1 63 132/34.8 YNd5 HV 1.10 6 1 19 5.50 -14.30 15.38
2 63 132/34.8 YNd5 HV 1.10 6 1 19 5.50 -14.30 15.57
Seeb Main
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.46
2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.42

Page | 149
Five-Year Annual Transmission Capability Statement (2017-2021)

Table B. 4 (Continued): Grid Station Transformers Data at 2017 Peak


Rating Voltage Vector Tap Tap Step Neutral Min Max Off-Nominal Tap range Reactance
Substation Tx. No
(MVA) (kV) Group Side (%) Tap Tap Tap Upper (pu) Lower (pu) (% on rating)
1 125 132/33 YNd5 HV 1.11 5 1 19 4.44 -15.54 17.76
Shinas
2 125 132/33 YNd5 HV 1.11 5 1 19 4.44 -15.54 17.59
1 125 132/33 YNd5 HV 1.10 6 1 19 5.50 -14.30 17.78
2 125 132/33 YNd5 HV 1.10 6 1 19 5.50 -14.30 17.81
Sohar
3 125 132/33 YNd5 HV 1.11 5 1 19 4.44 -15.54 18.42
4 125 132/33 YNd5 HV 1.11 5 1 19 4.44 -15.54 18.35
1 125 132/33 YNd5 HV 1.10 5 1 19 4.42 -15.46 18.70
Sohar Industrial Area
2 125 132/33 YNd5 HV 1.10 5 1 19 4.42 -15.46 18.59
1 63 132/33 YNd5 HV 1.11 6 1 19 5.55 -15.54 14.87
2 63 132/33 YNd5 HV 1.11 6 1 19 5.55 -15.54 14.74
Sumail
1 125 132/33 YNd5 HV 1.13 5 1 19 4.44 -15.54 17.47
2 125 132/33 YNd5 HV 1.13 5 1 19 4.44 -15.54 17.45
1 125 132/33 YNd5 HV 1.10 7 2 21 5.50 -15.40 17.85
Sur
2 125 132/33 YNd5 HV 1.10 7 2 21 5.50 -15.40 17.72
1 125 132/33 YNd5 HV 1.11 6 1 19 5.55 -14.45 17.94
Wadi Adai
2 125 132/33 YNd5 HV 1.11 6 1 19 5.55 -14.45 17.88
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.31
2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.61
Wadi Kabir
3 125 132/33 YNd5 HV 1.14 6 1 19 5.53 -14.47 18.40
4 125 132/33 YNd5 HV 1.14 6 1 19 5.70 -14.82 18.40
1 63 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 15.34
Wadi Sa'a
2 63 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 15.30
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.45
Yitti
2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.45
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Dreez
2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
1 500 220/132 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 23.28
2 500 220/132 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 23.28
Sohar Free Zone
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
1 50 132/11 YNd1 HV 1.11 5 1 19 4.42 -15.47 32.21
Daghmar
2 50 132/11 YNd1 HV 1.11 5 1 19 4.42 -15.47 32.21
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Jebreen
2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26

Page | 150
Five-Year Annual Transmission Capability Statement (2017-2021)

Table B. 4 (Continued): Grid Station Transformers Data at 2017 Peak


Rating Voltage Vector Tap Tap Step Neutral Min Max Off-Nominal Tap range
Reactance (%
Substation Tx. No
on rating)
(MVA) (kV) Group Side (%) Tap Tap Tap Upper (pu) Lower (pu)

Dhofar System
1 63 132/36 YNd5 HV 1.11 10 1 19 9.99 -9.99 15.37
Al Qarm
2 63 132/36 YNd5 HV 1.11 10 1 19 9.99 -9.99 15.37

5 1 19
1 125 132/33 YNd5 HV 1.10 4.42 -15.46 18.265
Ashoor
2 125 132/33 YNd5 HV 1.10 5 1 19 4.42 -15.46 18.257
1 125 132/33 YNd5 HV 1.11 5 1 19 4.44 -15.54 17.299
Awaqad
2 125 132/33 YNd5 HV 1.11 5 1 19 4.44 -15.54 17.284

1 125 132/33 YNd5 HV 1.67 10 1 19 5.00 -15.00 17.72


Ittin
2 125 132/33 YNd5 HV 1.67 10 1 19 5.00 -15.00 17.72

1 63 132/33 YNd0 HV 1.11 10 1 19 5.55 -15.54 14.5


NPS
2 63 132/33 YNd0 HV 1.11 10 1 19 5.55 -15.54 14.5

1 125 132/33 YNd5 HV 1.10 5 1 19


4.42 -15.46 18.28
2 125 132/33 YNd5 HV 1.10 5 1 19 4.42 -15.46 18.416
Salalah Free Zone
3 125 132/33 YNd5 HV 1.11 5 1 19 5.55 -15.54 16.47
4 125 132/33 YNd5 HV 1.11 5 1 19 5.55 -15.54 16.47
1 30 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 12.5
Thumrait
2 30 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 12.5

1 125 132/33 YNd5 HV 1.11 5 1 19 5.55 -15.54 16.47

2 125 132/33 YNd5 HV 1.11 5 1 19 5.55 -15.54 16.47


Sa'adah
3 125 132/33 YNd5 HV 1.11 5 1 19 5.55 -15.54 16.47

4 125 132/33 YNd5 HV 1.11 5 1 19 5.55 -15.54 16.47

Page | 151
Five-Year Annual Transmission Capability Statement (2017-2021)

Table B 5: Grid Station Transformers Data from 2018 to 2021


2018 Changes Deletions
Rating Voltage Vector Tap Tap Step Neutral Min Max Off-Nominal Tap range Reactance (%
Substation Tx. No
(MVA) (kV) Group Side (%) Tap Tap Tap Upper (pu) Lower (pu) on rating)

MIS System
1 40 132/33 YNd5 HV 1.11 6 1 19 5.55 -14.43 11.79
Adam
2 40 132/33 YNd5 HV 1.11 6 1 19 5.55 -14.43 11.72
Mawalleh North 3 50 132/11 YNd1 HV 1.11 5 1 19 4.42 -15.47 32.21
1 63 132/34.8 YNd5 HV 1.10 6 1 19 5.50 -14.30 15.38
Seeb
2 63 132/34.8 YNd5 HV 1.10 6 1 19 5.50 -14.30 15.57
Barka Third Tx 3 125 132/33 YNd5 HV 1.11 5 1 19 4.44 -15.54 17.6

2018 Changes Additions


Rating Voltage Vector Tap Tap Step Neutral Min Max Off-Nominal Tap range Reactance (%
Substation Tx. No
(MVA) (kV) Group Side (%) Tap Tap Tap Upper (pu) Lower (pu) on rating)

MIS System
1 500 400/220 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 22.08
Ibri IPP 2 500 400/220 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 22.08
3 500 400/220 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 22.08
SIA 3 500 220/132 YNa0d1 HV 1.10 6 1 20 5.50 -15.40 21.23
1 500 220/132 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 23.28
Mobella 220kV
2 500 220/132 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 23.28
1 125 220/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.50
Barka IPP
2 125 220/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.50
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Adam
2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
3 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Al Khadhra
4 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26

Dil Abdusalam 2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26


3 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Madinate Barka
4 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Madinat Shinas
2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26

Page | 152
Five-Year Annual Transmission Capability Statement (2017-2021)

Table B. 5 (Continued): Grid Station Transformers Data from 2018 to 2021


2018 Changes Additions
Rating Voltage Vector Tap Tap Step Neutral Min Max Off-Nominal Tap range Reactance (%
Substation Tx. No
(MVA) (kV) Group Side (%) Tap Tap Tap Upper (pu) Lower (pu) on rating)

MIS System
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Mawalleh North
2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
MSQ 4 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.40 17.29
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Sinaw
2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Swauiq
2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Uwaynat
3 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
4 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Daghmar 3 50 132/11 YNd1 HV 1.11 5 1 19 4.42 -15.47 32.25

2019 Changes Additions


Rating Voltage Vector Tap Tap Step Neutral Min Max Off-Nominal Tap range Reactance
Substation Tx. No
(MVA) (kV) Group Side (%) Tap Tap Tap Upper (pu) Lower (pu) (% on rating)
MIS System
1 500 400/220 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 22.08
SIS 2 500 400/220 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 22.08
3 500 400/220 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 22.08
1 500 400/220 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 22.08
Sohar Free Zone 2 500 400/220 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 22.08
3 500 400/220 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 22.08
Mahadha 3 315 220/132 YNa0d1 HV 1.10 6 1 20 5.50 -15.40 13.96
1 500 400/132 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 23.28
Qabil
2 500 400/132 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 23.28
1 500 220/132 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 23.28
KIS
2 500 220/132 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 23.28

Page | 153
Five-Year Annual Transmission Capability Statement (2017-2021)

Table B. 5 (Continued): Grid Station Transformers Data from 2018 to 2021


2019 Changes Additions
Rating Voltage Vector Tap Tap Step Neutral Min Max Off-Nominal Tap range Reactance
Substation Tx. No
(MVA) (kV) Group Side (%) Tap Tap Tap Upper (pu) Lower (pu) (% on rating)
MIS System
3 125 132/33 YNd5 HV 1.10 5 1 19 4.42 -15.46 18.31
Airport Hight
4 125 132/33 YNd5 HV 1.10 5 1 19 4.42 -15.46 18.37
3 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Amerat
4 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
3 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
A'salam
4 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Bedyah
2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Birkat Al Mouz
2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
3 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Bureimi Industrial
4 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
3 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Ghala 4 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Ghala Heights
3 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
4 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Halban
3 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
4 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
1 63 132/33 YNd5 HV 1.11 6 1 19 5.55 -15.54 16.97
Samad
2 63 132/33 YNd5 HV 1.11 6 1 19 5.55 -15.54 16.97
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Samail Industrial Area
2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
3 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Sohar Free Zone
4 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26

Page | 154
Five-Year Annual Transmission Capability Statement (2017-2021)

Table B. 5 (Continued): Grid Station Transformers Data from 2018 to 2021


2019 Changes Additions
Rating Voltage Vector Tap Tap Step Neutral Min Max Off-Nominal Tap range Reactance
Substation Tx. No
(MVA) (kV) Group Side (%) Tap Tap Tap Upper (pu) Lower (pu) (% on rating)
MIS System
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Seeb
2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Wadi Bani Awf
2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26

2020 Changes Additions


Rating Voltage Vector Tap Tap Step Neutral Min Max Off-Nominal Tap range Reactance
Substation Tx. No
(MVA) (kV) Group Side (%) Tap Tap Tap Upper (pu) Lower (pu) (% on rating)
MIS System
3 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Ghubrah
4 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Khoudh
3 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
4 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Yanqual
2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26

2021 Changes Deletions


Tap Off-Nominal Tap
Rating Voltage Vector Tap Neutral Min Max
Step range Reactance (%
Substation Tx. No
Upper Lower on rating)
(MVA) (kV) Group Side (%) Tap Tap Tap
(pu) (pu)
Dhofar System
1 30 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 12.5
Thumrait
2 30 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 12.5

Page | 155
Five-Year Annual Transmission Capability Statement (2017-2021)

Table B. 5 (Continued): Grid Station Transformers Data from 2018 to 2021


2021 Changes Additions
Rating Voltage Vector Tap Tap Step Neutral Min Max Off-Nominal Tap range Reactance
Substation Tx. No
(MVA) (kV) Group Side (%) Tap Tap Tap Upper (pu) Lower (pu) (% on rating)
1 500 400/132 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 23.28
Rusail Industrial 2 500 400/132 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 23.28
3 500 400/132 YNa0d1 HV 1.11 6 1 20 5.55 -15.54 23.28
1 500 220/132 YNa0d1 LV 1.11 6 1 20 5.55 -15.54 23.25
Misfah IPP
2 500 220/132 YNa0d1 LV 1.11 6 1 20 5.55 -15.54 23.26
Airport Heights 3 500 220/132 YNa0d1 LV 1.11 6 1 20 5.55 -15.54 23.26
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Khuwair
2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Madinat Ibri
2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
1 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Falaj Al Qabail
2 125 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 17.26
Dhofar System
1 125 132/33 YNd5 HV 1.11 5 1 19 5.55 -15.54 16.47
Thumrait
2 125 132/33 YNd5 HV 1.11 5 1 19 5.55 -15.54 16.47

Page | 156
Five-Year Annual Transmission Capability Statement (2017-2021)

Appendix C: Power System Studies


C.1 Summary of Load Flow Study results
The expected performance of the system at peak and minimum demand for each year from 2017 to 2021
are summarised in a series of tables and presented pictorially.

The study results are presented in the following tables:

Table C.1 – Grid transformer loadings at Peak Demand (2017-2021)

Table C.2 – Available capacity at Grid Stations (2017-2021) for connection of new demand

Table C.3 – Overhead line and cable circuit loadings at peak demand (2017-2021)

Table C.4– Transmission system voltage profile at peak demand (2017-2021)

Table C.5 – Transmission system voltage profile at minimum demand (2017-2021)

Table C.6 – Estimation of transmission losses and generation margin at peak demand (2017-2021)

C.2 Summary of Fault Level Study results


The expected maximum busbar 3-phase and single phase fault levels are presented in tabular form as
follows:

Table C.7 – Maximum 3-Phase Short Circuit Fault Levels (2017-2021)

Table C.8 – Maximum Single-Phase Short Circuit Fault Levels (2017-2021).

C.3 Diagrames of the model for the Load Flow Study Results
The result of peak demand load flow studies for both MIS and Dhofar systems for the years 2017 through
to 2021 are presented as Figures C.1 to C.10 respectively.

Page | 157
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C 1: Transformers Loading (%) at Grid Stations (2017-2021)


Total Substation Transformer loading (%)
Transformer Firm
Location
Capacity Capacity 2017 2018 2019 2020 2021
(MVA) (MVA)
MIS Area
400/220 kV Transformers
New Izki 2 x 500 500 34.03 36.80 27.21 31.16 34.52
Ibri IPP 3 x 500 1000 46.32 37.87 39.36 39.99
Misfah 3 x 500 1000 32.07 42.94 43.12 9.47
SIS 3 x 500 1000 47.66 49.02 47.82
Sohar Free Zone 3 x 500 1000 50.32 52.42 52.33
Jahloot 4 x 500 1500 62.43 44.24 48.88 50.66 42.31
Sur 5 x 750 3000 38.45 35.42 35.74 37.71 36.62
400/132 kV Transformers
Qabel 2 x 500 500 26.13 28.30 28.60
Rusail Industrial 3 x 500 1000 40.59
220/132 kV Transformers
Mahadha 2 x 315 315 14.57 34.67 43.58 46.62 50.17
Airport Height 2 x 500 500 59.05 31.41 43.60 46.17
Airport Height 3 x 500 1000 31.44
Al Filaj 2 x 500 500 62.33 49.75 45.35 46.56 51.87
Al Hamriyah 2 x 500 500 40.03 40.53 49.14 52.31 41.03
Ibri 2 x 500 500 28.23 31.70 39.72 42.89 42.63
Jahloot 2 x 500 500 36.81 37.84 45.45 46.85 42.32
MIS 2 x 500 500 46.02 45.07 36.44 37.94 37.12
Misfah 2 x 500 500 29.42
MSQ 2 x 500 500 32.50 39.26 56.38 58.53 49.15
Mobella 2 x 500 500 50.95 45.99 45.86 49.09
New Izki 2 x 500 500 33.18 34.75 26.86 30.79 32.95
KIS 2 x 500 500 24.76 26.38 27.74
SIP-A 2 x 500 500 27.43
SIP-A 3 x 500 1000 20.64 21.87 21.42 20.35
SIS 2 x 500 500 36.29 36.10 40.14 43.85 46.57
Sohar Free Zone 2 x 500 500 32.93 26.12 43.31 48.81 52.27
Sur 2 x 500 500 33.10 37.46 27.73 28.97 31.06

Page | 158
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C.1 (countinued): Transformers Loading (%) at Grid Stations (2017-2021)


Total Substation Transformer loading (%)
Transformer Firm
Location
Capacity Capacity 2017 2018 2019 2020 2021
(MVA) (MVA)
MIS Area
220/33 kV Transformers
Barka-3 PS 2 x 125 125 38.28 39.50 40.39 41.77
Blue City 2 x 160 160 31.22 32.92 34.32 35.87 37.14
132/33 kV Transformers
Tx (1&2) 2 x 125 125 46.62 48.46 28.39 30.22 31.75
A'salam
Tx (3&4) 2 x 125 125 25.19 26.79 28.18
40MVA 2 x 40 40 71.99
Adam
125MVA 2 x 125 125 24.06 25.23 26.64 28.24
Tx (1&2) 2 x 125 125 42.66 44.02 23.27 24.66 25.13
Airport Height
Tx (3&4) 2 x 125 125 22.88 24.27 24.70
Al Falaj 2 x 125 125 43.12 43.14 46.02 47.60 47.75
Al Hayl 2 x 40 40 69.65 63.62 66.89 25.60 21.20
Tx (1&2) 2 x 125 125 41.44 49.05 25.85 27.31 28.10
Amerat
Tx (3&4) 2 x 125 125 26.39 27.90 28.71
Ayjah 2 x 125 125 27.79 28.82 30.46 31.95 33.29
Bahla 2 x 125 125 22.63 23.07 24.21 25.59 26.96
Tx (1&2) 2 x 125 125 52.55 51.10 25.43 27.10 28.43
Barka Main
Tx (3) 1 x 125 Nill 51.34
Bedyah 2 x 125 125 14.66 15.32 16.01
Birkat Al Mouz 2 x 125 125 26.92 28.42 29.80
Tx (1&2) 2 x 125 125 47.76 52.39 35.25 37.20 27.12
Bousher
Tx (3&4) 2 x 125 125 61.66 54.82 36.72 38.76 28.58
Tx (1&2) 2 x 125 125 22.95 23.09 17.85 19.08 21.78
Bureimi Industrial
Tx (3&4) 2 x 125 125 22.51 24.08 25.93
Bureimi 2 x 125 125 38.18 38.81 24.35 26.29 26.87
Dank 2 x 63 63 24.64 27.81 28.61 29.64 30.14
Dil Abdusalam 2 x 125 125 39.25 40.07 42.77 38.95
Dreez 2 x 125 125 33.16 33.02 34.63 36.64 31.80
Falaj Al Qabail 2 x 125 125 27.87
Tx (1&2) 2 x 125 125 21.57 22.86 23.50
Ghala Heights
Tx (3&4) 2 x 125 125 22.44 23.78 24.44
Tx (1&2) 2 x 125 125 34.92 36.39 19.34 20.69 21.28
Ghala
Tx (3&4) 2 x 125 125 19.39 20.73 21.32

Page | 159
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C.1 (countinued): Transformers Loading (%) at Grid Stations (2017-2021)


Total Substation Transformer loading (%)
Transformer Firm
Location
Capacity Capacity 2017 2018 2019 2020 2021
(MVA) (MVA)
MIS Area
Tx (1&2) 2 x 125 125 24.98 26.60 27.96
Halban
Tx (3&4) 2 x 125 125 25.42 27.07 28.43
Ibra 2 x 125 125 34.57 36.89 36.46 38.48 40.61
63MVA 2 x 63 63 26.78 28.46 27.77 29.10
Ibri
125MVA 2 x 125 125 28.17 28.64 31.47 33.91 30.05
Izki 2 x 125 125 32.15 22.99 24.23 25.09 25.68
JBB Ali 2 x 125 125 40.79 43.18 44.43 46.50 48.60
JBB Hasan 2 x 125 125 37.88 39.65 41.50 43.40 45.34
Jahloot 2 x 125 125 17.53 17.71 18.73 19.43 19.62
Jebreen 2 x 125 125 26.48 27.16 28.50 30.11 31.72
Khaborah 2 x 125 125 49.34 40.94 41.65 44.48 46.93
Tx (1&2) 2 x 125 125 29.34 31.29 31.80 33.32 34.61
Khadra
Tx (3&4) 2 x 125 125 24.32 24.70 25.89 26.87
Tx (1&2) 2 x 125 125 29.50 31.54
Khoudh
Tx (3&4) 2 x 125 125 29.50 31.54
Khuwair 2 x 125 125 21.60
Tx (1&2) 2 x 125 125 26.14 42.94 22.26 29.90 32.21
Liwa
Tx (3&4) 2 x 125 125 23.16 25.09 26.57 28.65 30.86
MIS 2 x 125 125 78.91 26.29 26.93 28.21 29.13
Tx-3 1 x 125 Nill 28.92
MSQ Tx (1&2) 2 x 125 125 45.93 31.74 34.87 36.47 37.02
Tx (3&4) 2 x 125 125 31.22 34.33 35.86 36.43
Tx (1&2) 2 x 125 125 20.55 21.60 22.39 23.91 25.11
Madinat Barka
Tx (3&4) 2 x 125 125 16.21 16.81 17.94 18.84
Madinat Ibri 2 x 125 125 27.19
Madinat Nizwa 2 x 125 125 23.41 23.99 24.90 25.77 26.63
Madinat Shinas 2 x 125 125 26.45 27.64 29.55 31.56
Mahadha 2 x 30 30 48.14 48.17 49.35 39.00 40.44
Mawalleh North 2 x 125 125 38.62 40.59 42.59 43.44
Tx (1&2) 2 x 125 125 68.20 45.71 47.64 39.62 42.72
Mawalleh South
Tx (3&4) 2 x 125 125 43.49 48.76 48.18 37.64 40.58
Misfah 2 x 125 125 13.46 14.03 14.61 15.08 15.80

Page | 160
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C.1 (countinued): Transformers Loading (%) at Grid Stations (2017-2021)


Total Substation Transformer loading (%)
Transformer Firm
Location
Capacity Capacity 2017 2018 2019 2020 2021
(MVA) (MVA)
MIS Area
Mobella 2 x 125 125 49.08 49.84 23.66 24.70 25.46
Mudhaibi 2 x 125 125 58.01 39.06 26.56 28.06 29.39
Mudhairib 2 x 125 125 45.01 47.83 32.07 33.84 35.73
Tx (1&2) 2 x 125 125 38.19 33.47 34.20 35.82 37.17
Muladah
Tx (3&4) 2 x 125 125 24.49 32.54 33.30 34.87 36.21
Muttrah 2 x 125 125 34.84 35.13 37.43 38.31 38.04
Nakhal 2 x 125 125 30.78 32.11 33.02 34.25 34.97
Tx (1&2) 2 x 125 125 49.15 54.97 63.82 38.83 39.46
New Ghubrah
Tx (3&4) 2 x 125 125 26.66 27.07
New Izki 2 x 125 125 6.09 15.89 16.88 17.82 18.37
Nizwa 2 x 125 125 49.40 51.14 26.48 27.97 29.49
Old Ghubrah 2 x 42 42 48.69 48.16
Quriyat 2 x 125 125 22.04 22.52 23.93 25.11 25.67
Qurum 2 x 125 125 44.75 44.96 47.93 49.11 48.78
Tx (1&2) 2 x 125 125 39.11 41.60 44.20 33.66 37
Rusail Industrial
Tx (3&4) 2 x 125 125 30.49 32.24 34.24 27.69 30.27
Rustaq 3 x 125 250 43.64 45.76 29.88 31.33 32.45
SIP 2 x 125 125 30.02 30.37 34.81 33.37 28.50
Saham 2 x 125 125 73.19 41.80 43.40 46.30 41.84
Samad 2 x 63 63 26.75 27.70 28.45
63MVA 2 x 63 63 73.88 59.92
Seeb Main Tx (1&2) 2 x 125 125 52.75 54.38 43.47 38.74 39.44
Tx (3&4) 2 x 125 125 43.90 34.84 37.74
Shinas 2 x 125 125 48.08 22.19 24.86 27.84 29.75
Sinaw 2 x 125 125 21.72 22.79 24.10 25.06
Tx (1&2) 2 x 125 125 28.63 30.73 33.53 33.33 36.93
Sohar Free Zone
Tx (3&4) 2 x 125 125 22.75 25.03 27.75
Tx (1&2) 2 x 125 125 49.02 31.68 33.89 36.53 28.82
Sohar
Tx (3&4) 2 x 125 125 46.96 31.53 32.87 35.46 27.61
Sumail Industrial 2 x 125 125 25.61 28.17 31.74
63MVA 2 x 63 63 30.81 40.43 33.74 35.17 37.09
Sumail
125MVA 2 x 125 125 46.25 43.65 23.87 24.86 26.23

Page | 161
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C.1 (countinued): Transformers Loading (%) at Grid Stations (2017-2021)


Total Substation Transformer loading (%)
Transformer Firm
Location
Capacity Capacity 2017 2018 2019 2020 2021
(MVA) (MVA)
MIS Area
Sur 2 x 125 125 37.37 38.60 40.82 42.76 44.55
Swauiq 2 x 125 125 30.40 31.08 32.58 33.85
Tx (1&2) 2 x 125 125 23.08 23.54 25.08 32.81
Uwaynat
Tx (3&4) 2 x 125 125 22.86 24.99 26.67 35.62
Wadi Adai 2 x 125 125 43.44 37.12 39.59 40.90 41.01
Wadi Bani Auwf 2 x 125 125 23.10 24.19 25.01
Tx (1&2) 2 x 125 125 27.70 28.06 30.21 31.51 31.91
Wadi Kabair
Tx (3&4) 2 x 125 125 35.35 35.75 38.50 40.16 40.70
Wadi Sa'a 2 x 63 63 8.80 9.01 9.38 15.54 16.36
Yanqul 2 x 125 125 14.02 16.23
Yitti 2 x 125 125 4.77 5.08 5.69 6.28 6.75
132/11 kV Transformers
2 x 50 50 60.04
Daghmar
3 x 50 100 38.23 39.05 39.35 38.65
Mawalleh North 3 x 50 100 47.23
Dhofar Area
132/33 kV Transformers
Ashoor 2 x 125 125 21.15 22.72 34.35 36.54 38.95
Awaqad 2 x 125 125 50.87 43.79 40.08 39.69 41.61
Ittin 2 x 125 125 45.63 49.54 43.56 49.49 45.54
TX-1&2 2 x 125 125 14.60 29.31 37.16 39.54 42.61
Sa'adah
TX-3&4 2 x 125 125 23.78 25.34 30.06 32.32 41.42
TX-1&2 2 x 125 125 43.54 44.41 42.83 38.99 40.30
Salalah Free Zone
TX-3&4 2 x 125 125 3.38 10.47 25.54 34.77 40.93
2 x 30 30 44.18 46.57 49.62 52.33 -
Thumrait
2 x 125 125 - - - - 13.22
Al Qarm 2 x 63 63 27.46 17.20 15.08 14.20 14.93
NPS 2 x 63 63 18.78 20.90 19.62 20.80 20.46

Page | 162
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C 2: Available Capacity at Grid Stations (2017-2021) for Connection of New Demand
Total Substation Available Capacity (MVA)
Transformer Firm
Location
Capacity Capacity 2017 2018 2019 2020 2021
(MVA) (MVA)
MIS Area
400/220 kV Transformers
New Izki 2 x 500 500 159.72 132.01 227.94 188.35 154.78
Ibri IPP 3 x 500 1000 536.80 432.01 409.56 400.10
Misfah 3 x 500 1000 518.90 355.90 353.18 858.02
SIS 3 x 500 1000 285.13 264.76 282.68
Sohar Free Zone 3 x 500 1000 245.13 213.74 214.99
Jahloot 4 x 500 1500 251.40 615.26 522.43 486.75 653.71
Sur 5 x 750 3000 1558.25 1671.68 1659.77 1585.76 1626.61
400/132 kV Transformers
Qabel 2 x 500 500 238.70 216.95 213.98
Rusail Industrial 3 x 500 1000 391.13
220/132 kV Transformers
Mahadha 2 x 315 315 223.21 96.58 40.45 21.28 -1.08
Airport Height 2 x 500 500 -90.53 185.91 64.01 38.34
Airport Height 3 x 500 1000 528.43
Al Filaj 2 x 500 500 -123.26 2.50 46.51 34.38 -18.74
Al Hamriyah 2 x 500 500 99.74 94.68 8.57 -23.06 89.69
Ibri 2 x 500 500 217.72 183.04 102.77 71.10 73.65
Jahloot 2 x 500 500 131.88 121.56 45.53 31.50 76.78
MIS 2 x 500 500 39.75 49.32 135.59 120.58 128.77
Misfah 2 x 500 500 205.77
MSQ 2 x 500 500 175.00 107.35 -63.80 -85.28 8.46
Mobella 2 x 500 500 -9.45 40.10 41.36 9.14
New Izki 2 x 500 500 168.18 152.53 231.37 192.09 170.54
KIS 2 x 500 500 252.42 236.17 222.63
SIP-A 2 x 500 500 225.74
SIP-A 3 x 500 1000 690.37 671.88 678.76 694.82
SIS 2 x 500 500 137.11 138.98 98.62 61.52 34.25
Sohar Free Zone 2 x 500 500 170.72 238.79 66.86 11.86 -22.68
Sur 2 x 500 500 169.03 125.36 222.73 210.34 189.37

Page | 163
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C.2 (continued): Available Capacity at Grid Stations (2017-2021) for Connection of New Demand
Total Substation Available Capacity (MVA)
Transformer Firm
Location
Capacity Capacity 2017 2018 2019 2020 2021
(MVA) (MVA)
MIS Area
220/33 kV Transformers
Barka-3 PS 2 x 125 125 29.31 26.25 24.03 20.59
Blue City 2 x 160 160 60.09 54.66 50.17 45.23 41.14
132/33 kV Transformers
Tx (1&2) 2 x 125 125 8.45 3.84 54.03 49.45 45.62
A'salam
Tx (3&4) 2 x 125 125 62.02 58.03 54.56
40MVA 2 x 40 40 -17.59
Adam
125MVA 2 x 125 125 64.86 61.94 58.40 54.39
Tx (1&2) 2 x 125 125 18.34 14.95 66.83 63.34 62.16
Airport Height
Tx (3&4) 2 x 125 125 64.33 63.24
Al Falaj 2 x 125 125 17.19 17.16 9.95 6.00 5.58
Al Hayl 2 x 40 40 -15.72 -10.90 -13.51 19.52 23.04
Tx (1&2) 2 x 125 125 21.39 2.38 60.36 56.72 54.76
Amerat
Tx (3&4) 2 x 125 125 59.03 55.26 53.22
Ayjah 2 x 125 125 55.53 52.95 48.84 45.14 41.75
Bahla 2 x 125 125 68.42 67.33 64.48 61.01 57.59
Tx (1&2) 2 x 125 125 -6.38 -2.74 61.43 57.24 53.94
Barka Main
Tx (3) 1 x 125 0 -64.18
Bedyah 2 x 125 125 88.34 86.70 84.98
Birkat Al Mouz 2 x 125 125 57.69 53.95 50.49
Tx (1&2) 2 x 125 125 5.61 -5.97 36.87 31.99 57.21
Bousher
Tx (3&4) 2 x 125 125 -29.15 -12.06 33.20 28.10 53.55
Tx (1&2) 2 x 125 125 67.62 67.28 80.38 77.31 70.56
Bureimi Industrial
Tx (3&4) 2 x 125 125 68.72 64.79 60.18
Bureimi 2 x 125 125 29.54 27.97 64.12 59.27 57.84
Dank 2 x 63 63 31.95 27.96 26.95 25.65 25.02
Dil Abdusalam 2 x 125 125 26.89 24.81 18.08 27.55
Dreez 2 x 125 125 42.11 42.45 38.43 33.40 45.49
Falaj Al Qabail 2 x 125 125 55.34
Tx (1&2) 2 x 125 125 71.06 67.85 66.25
Ghala Heights
Tx (3&4) 2 x 125 125 68.90 65.55 63.89

Page | 164
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C.2 (continued): Available Capacity at Grid Stations (2017-2021) for Connection of New Demand
Total Substation Available Capacity (MVA)
Transformer Firm
Location
Capacity Capacity 2017 2018 2019 2020 2021
(MVA) (MVA)
MIS Area
Tx (1&2) 2 x 125 125 37.70 34.03 76.64 73.28 71.80
Ghala
Tx (3&4) 2 x 125 125 76.54 73.17 71.69
Tx (1&2) 2 x 125 125 62.54 58.50 55.09
Halban
Tx (3&4) 2 x 125 125 61.45 57.32 53.92
Ibra 2 x 125 125 38.59 32.78 33.85 28.79 23.44
63MVA 2 x 63 63 29.26 27.14 28.01 26.33
Ibri
125MVA 2 x 125 125 54.57 53.40 46.33 40.22 49.87
Izki 2 x 125 125 44.63 67.52 64.42 62.27 60.80
JBB Ali 2 x 125 125 23.03 17.06 13.92 8.76 3.50
JBB Hasan 2 x 125 125 30.30 25.87 21.25 16.49 11.65
Jahloot 2 x 125 125 81.19 80.72 78.18 76.44 75.93
Jebreen 2 x 125 125 58.80 57.10 53.74 49.72 45.69
Khaborah 2 x 125 125 1.66 22.64 20.88 13.79 7.32
Tx (1&2) 2 x 125 125 51.66 46.79 45.49 41.71 38.47
Khadra
Tx (3&4) 2 x 125 125 64.20 63.25 60.28 57.82
Tx (1&2) 2 x 125 125 51.24 46.14
Khoudh
Tx (3&4) 2 x 125 125 51.24 46.14
Khuwair 2 x 125 125 70.97
Tx (1&2) 2 x 125 125 59.65 17.65 69.36 50.24 44.48
Liwa
Tx (3&4) 2 x 125 125 67.11 62.28 58.58 53.37 47.85
MIS 2 x 125 125 -72.28 59.27 57.68 54.48 51.61
Tx-3 1 x 125 0 -36.15
MSQ Tx (1&2) 2 x 125 125 10.18 45.65 37.82 33.83 32.46
Tx (3&4) 2 x 125 125 46.94 39.17 35.34 33.92
Tx (1&2) 2 x 125 125 73.61 71.01 69.02 65.23 62.24
Madinat Barka
Tx (3&4) 2 x 125 125 84.47 82.97 80.15 77.90
Madinat Ibri 2 x 125 125 57.03
Madinat Nizwa 2 x 125 125 66.48 65.01 62.76 60.57 58.41
Madinat Shinas 2 x 125 125 58.87 55.89 51.12 46.13
Mahadha 2 x 30 30 1.12 1.10 0.39 6.60 5.74
Mawalleh North 2 x 125 125 28.45 23.54 18.51 16.33

Page | 165
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C.2 (continued): Available Capacity at Grid Stations (2017-2021) for Connection of New Demand
Total Substation Available Capacity (MVA)
Transformer Firm
Location
Capacity Capacity 2017 2018 2019 2020 2021
(MVA) (MVA)
MIS Area
Tx (1&2) 2 x 125 125 -45.50 10.73 5.91 25.96 18.21
Mawalleh South
Tx (3&4) 2 x 125 125 16.28 3.10 4.55 30.89 23.54
Misfah 2 x 125 125 91.35 89.92 88.49 87.29 85.48
Mobella 2 x 125 125 2.31 0.41 65.85 63.25 61.36
Mudhaibi 2 x 125 125 -20.03 27.35 58.60 54.84 51.52
Mudhairib 2 x 125 125 12.47 5.43 44.81 40.41 35.69
Tx (1&2) 2 x 125 125 29.54 41.33 39.51 35.44 32.09
Muladah
Tx (3&4) 2 x 125 125 63.77 43.64 41.74 37.82 34.48
Muttrah 2 x 125 125 37.90 37.17 31.41 29.21 29.91
Nakhal 2 x 125 125 48.05 44.71 42.44 39.37 37.58
Tx (1&2) 2 x 125 125 2.14 -12.42 -34.56 27.93 26.35
New Ghubrah
Tx (3&4) 2 x 125 125 58.36 57.32
New Izki 2 x 125 125 109.77 85.27 82.80 80.45 79.07
Nizwa 2 x 125 125 1.51 -2.86 58.80 55.08 51.26
Old Ghubrah 2 x 42 42 1.10 1.55
Quriyat 2 x 125 125 69.91 68.70 65.17 62.22 60.83
Qurum 2 x 125 125 13.14 12.60 5.18 2.23 3.05
Tx (1&2) 2 x 125 125 27.22 21.00 14.49 40.84 32.51
Rusail Industrial
Tx (3&4) 2 x 125 125 48.78 44.39 39.39 55.76 49.32
Rustaq 3 x 125 250 -77.30 -93.22 25.92 15.06 6.62
SIP 2 x 125 125 49.94 49.07 37.97 41.59 53.75
Saham 2 x 125 125 -57.99 20.50 16.50 9.25 20.40
Samad 2 x 63 63 29.29 28.10 27.15
63MVA 2 x 63 63 -30.09 -12.50
Seeb Main Tx (1&2) 2 x 125 125 -6.87 -10.96 16.33 28.16 26.39
Tx (3&4) 2 x 125 125 15.25 37.89 30.66
Shinas 2 x 125 125 4.79 69.53 62.85 55.40 50.63
Sinaw 2 x 125 125 70.71 68.02 64.74 62.35
Tx (1&2) 2 x 125 125 53.43 48.18 41.18 41.68 32.67
Sohar Free Zone
Tx (3&4) 2 x 125 125 68.12 62.41 55.62
Tx (1&2) 2 x 125 125 2.45 45.80 40.28 33.68 52.95
Sohar
Tx (3&4) 2 x 125 125 7.60 46.18 42.82 36.35 55.97

Page | 166
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C.2 (continued): Available Capacity at Grid Stations (2017-2021) for Connection of New Demand
Total Substation Available Capacity (MVA)
Transformer Firm
Location
Capacity Capacity 2017 2018 2019 2020 2021
(MVA) (MVA)
MIS Area
Sumail Industrial 2 x 125 125 60.98 54.58 45.66
63MVA 2 x 63 63 24.18 12.06 20.49 18.69 16.27
Sumail
125MVA 2 x 125 125 9.37 15.87 65.32 62.86 59.44
Sur 2 x 125 125 31.59 28.49 22.96 18.09 13.62
Swauiq 2 x 125 125 49.00 47.30 43.56 40.37
Tx (1&2) 2 x 125 125 67.30 66.16 62.30 42.98
Uwaynat
Tx (3&4) 2 x 125 125 67.84 62.53 58.32 35.96
Wadi Adai 2 x 125 125 16.39 32.19 26.03 22.75 22.49
Wadi Bani Auwf 2 x 125 125 67.25 64.52 62.47
Tx (1&2) 2 x 125 125 55.74 54.84 49.48 46.23 45.23
Wadi Kabair
Tx (3&4) 2 x 125 125 36.61 35.61 28.76 24.60 23.24
Wadi Sa'a 2 x 63 63 51.91 51.64 51.19 43.42 42.38
Yanqul 2 x 125 125 89.95 84.42
Yitti 2 x 125 125 113.08 112.30 110.79 109.31 108.12
132/11 kV Transformers
2 x 50 50 -10.04
Daghmar
3 x 50 100 -14.70 -17.14 -18.05 -15.94
Mawalleh North 3 x 50 100 -41.68
Dhofar Area
132/33 kV Transformers
Ashoor 2 x 125 125 72.13 68.19 39.13 33.66 27.62
Awaqad 2 x 125 125 -2.19 15.54 24.79 25.78 20.98
Ittin 2 x 125 125 10.92 1.16 16.10 1.29 11.15
TX-1&2 2 x 125 125 88.51 51.72 32.10 26.16 18.47
Sa'adah
TX-3&4 2 x 125 125 65.55 61.66 49.85 44.19 21.44
TX-1&2 2 x 125 125 16.15 13.97 17.91 27.53 24.26
Salalah Free Zone
TX-3&4 2 x 125 125 116.55 98.82 61.14 38.08 22.68
2 x 30 30 3.49 2.06 0.23 -1.40 -
Thumrait
2 x 125 125 - - - - 91.96
Al Qarm 2 x 63 63 28.40 41.33 43.99 45.11 44.18
NPS 2 x 63 63 39.34 36.66 38.28 36.79 37.22

Page | 167
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C 3: Overhead Line and Cable Circuit Loadings (%) at Peak Demand (2017-2021)
Circuit Circuit Loading at Max Demand (%)
Voltag No. of
Line Type Rating
e (kV) Circuits 2017 2018 2019 2020 2021
(MVA)

MIS Area
Ibri IPP New Izki OHL 400 2 1774 7.68 17.97 18.84 18.77

Jahloot Sur PS OHL 400 2 1774 35.20 24.94 27.56 28.56 23.84

Misfah New Izki OHL 400 2 1774 13.56 18.16 18.23 20.67
Rusail
Misfah 400 2 1774 17.17
Industrial OHL
New Izki Qabel OHL 400 2 1774 6.51 6.93 10.04

New Izki Sur PS OHL 400 2 1774 9.59 15.37


Sohar Free
SIS 400 2 1774 20.15 20.73 20.25
Zone OHL
Sohar Free Sohar-3 IPP
400 2 1774 20.56 21.37 21.20
Zone 3&4 OHL
Sur PS Qabel OHL 400 2 1774 12.16 13.05 16.66
Sohar Free Sohar-3 IPP
400 2 2273 31.29 32.35 31.94
Zone 1&2 UGC
Sohar Free Sohar-3 IPP
400 2 2273 32.48 33.24 32.98
Zone 3&4 UGC

Airport Height Al Filaj OHL 220 2 673 13.65

Airport Height Misfah OHL 220 2 673 43.62 37.55 29.62 29.18 40.71

Airport Height Mobella OHL 220 2 673 14.41 3.02 5.32 6.32

Al Filaj Barka PS 1&2 OHL 220 2 673 41.86 46.22 41.81 43.79 43.95

Al Filaj Barka PS 3&4 OHL 220 2 673 42.06 46.41 42.01 43.99 44.16

Al Filaj Blue City OHL 220 2 673 34.40 33.60 13.92 14.71 18.77

Al Filaj Mobella OHL 220 2 673 24.14 36.80 39.05 31.44

Al Hamriyah Jahloot OHL 220 2 673 29.70 30.07 36.46 38.81 30.43

Alw(UAE) Mahadha OHL 220 2 673 1.43 1.44 1.46 1.46 1.45

Barka-3 PS Misfah OHL 220 2 673 34.63 27.08 26.05 27.82 23.34

Page | 168
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C.3 (continued): Overhead Line and Cable Circuit Loadings (%) at Peak Demand (2017-2021)
Circuit Circuit Loading at Max Demand (%)
Voltage No. of
Line Type Rating
(kV) Circuits
(MVA) 2017 2018 2019 2020 2021

MIS Area
Blue City MIS OHL 220 2 673 29.19 28.03 12.66 12.99 14.42

Ibri IPP Ibri 220 2 673 23.55 29.51 31.87 31.65


OHL
Ibri IPP Mahadha 220 2 673 27.27 12.27 11.51 12.60
OHL
Ibri Mahadha 220 2 673 20.97
OHL
Jahloot Misfah 220 2 673 34.74 7.69 5.03 5.63 4.89
OHL
MIS KIS 220 2 673 18.88 19.47 15.12
OHL
MIS SIS 220 2 673 9.59 9.38
OHL
MSQ Misfah 220 2 673 24.15 29.17 41.89 43.49
OHL
MSQ Misfah IPP 220 2 673 36.52
OHL
Mahadha SIS 220 2 975 21.96 11.51 3.66 2.82 2.05
OHL
Sohar Free
Mahadha 220 2 673 6.32 6.35 6.10
Zone OHL
Misfah IPP Misfah 220 2 673 30.72
OHL
KIS SIS 220 2 673 36.16 37.97 34.12
OHL
Sohar Free
SIS 220 2 673 14.62 2.25 12.83 12.11 10.16
Zone OHL
SIS Sohar-1 PS 220 2 673 35.12 20.96 6.12 6.46 10.88
OHL
Sohar Free
Sohar-2 PS 220 2 673 38.33 20.65 13.75 14.99 15.00
Zone OHL
Sur PS Sur 220 2 673 24.56 27.80 20.57 21.49 23.05
OHL
Barka PS
220 2 625 45.22 49.92 45.16 47.30 47.48
Al Filaj 3&4 UGC
Blue City 220 2 475 49.77 48.65 22.51 23.61 28.48
Al Filaj UGC
Misfah 220 2 625 36.64 28.56 27.04 28.99 24.65
Barka-3 PS UGC

Page | 169
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C.3 (continued): Overhead Line and Cable Circuit Loadings (%) at Peak Demand (2017-2021)
Circuit Circuit Loading at Max Demand (%)
Voltage No. of
Line Type Rating
(kV) Circuits
(MVA) 2017 2018 2019 2020 2021

MIS Area
Blue City MIS 220 2 475 40.79 39.14 16.35 16.84 19.20
UGC
MSQ Misfah IPP 220 2 625 38.97
UGC
Mahadha Sohar Free Zone 220 2 500 12.49 12.53 12.02
UGC
Misfah IPP Misfah 220 2 625 33.06
UGC
220 625 42.88 31.06 32.70 32.14 31.11
SIP-A Sohar-1 PS UGC 3
SIS Sohar Free Zone 220 2 625 15.26 1.69 13.45 12.79 10.89
UGC
SIS 220 625 37.34 21.60 8.34 6.56 10.82
Sohar-1 PS UGC 2
Sohar
220 625 41.44 22.41 14.83 16.17 16.19
FreeZone Sohar-2 PS UGC 2
Adam Manah 132 2 293 9.84 10.27 10.77 11.38 12.06
OHL
Al Falaj Wadi Adai 132 2 293 11.54 11.86 10.42 10.24 23.50
OHL
Al Falaj Barka Main 132 2 293 47.39 16.37 26.08 24.63 22.52
OHL
Al Falaj Madinat Barka 132 2 293 43.30 56.25 26.82 29.17 35.71
OHL
Al Filaj Nakhal 132 2 293 13.07 13.64 24.30 25.64 28.09
OHL
Al Hamriyah Muttrah 132 2 293 21.06 21.03 24.37 25.31 16.51
OHL
Al Hamriyah Qurum 132 2 293 5.59 6.55 11.44 11.82 25.13
OHL
Al Hamriyah Wadi Adai 132 2 146 23.63 23.05 32.40 33.81 8.00
OHL
Al Hamriyah Wadi Kabair 132 2 146 52.25 52.57 58.34 60.82 52.31
OHL
Al Hayl Dank 132 2 293 9.52 8.70 9.14
OHL
Al Hayl Yanqul 132 2 293 3.50 2.90
OHL

Page | 170
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C.3 (continued): Overhead Line and Cable Circuit Loadings (%) at Peak Demand (2017-2021)
Circuit Circuit Loading at Max Demand (%)
Voltag No. of
Line Type Rating
e (kV) Circuits 2017 2018 2019 2020 2021
(MVA)

MIS Area
Al Kamil Bedyah OHL 132 2 293 19.47 20.37 20.95

Al Kamil JBB Ali OHL 132 2 293 17.42 18.44 18.98 19.86 20.76

Al Kamil JBB Hasan OHL 132 2 293 13.32 16.21 6.67 7.48 7.84

Al Kamil Mudhairib OHL 132 2 293 36.69 42.59

Amerat Jahloot OHL 132 2 293 30.96 32.64 43.41 44.56 36.86

Amerat MSQ OHL 132 2 293 13.54 12.08 21.34 21.33 12.88

Ayjah 293 11.87 12.22 13.01 13.64 14.22


Sur OHL 132 2
Bahla Nizwa OHL 132 2 146 19.33 19.71 20.68 21.86 23.04

Barka Main Halban OHL 132 2 293 16.57 14.87 11.35

Barka Main Mobella OHL 132 2 293 14.08 13.58

Bedyah Mudhairib OHL 132 2 293 14.23 14.89 15.19


Birkat Al
Izki 132 2 293 10.18 9.18 18.10
Mouz OHL
Birkat Al
Nizwa 132 2 293 2.80 3.40 5.64
Mouz OHL
Bousher MSQ OHL 132 1 293 23.16 30.05 36.74 38.27 36.42
Bureimi
Mahadha 132 2 293 24.83 25.09 13.12 14.20 15.33
Industrial OHL
Bureimi
Bureimi 132 2 293 15.18 15.40 5.91 6.05 6.64
Industrial OHL
Bureimi Mahadha OHL 132 2 293 12.43 13.36 14.38

Daghmar Quriyat OHL 132 2 293 10.26 9.80 10.01 10.09 9.90

Dank Ibri OHL 132 2 293 14.41 14.26 14.87 15.43 15.88

Dank Wadi Sa'a OHL 132 2 89 0.00 0.00 0.00 0.00 0.00

Dank Yanqul OHL 132 2 293 9.33 9.67

Page | 171
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C.3 (continued): Overhead Line and Cable Circuit Loadings (%) at Peak Demand (2017-2021)
Circuit Circuit Loading at Max Demand (%)
Voltage No. of
Line Type Rating
(kV) Circuits 2017 2018 2019 2020 2021
(MVA)

MIS Area
Dil
Khaborah 132 2 293 11.35
Abdusalam(DAS) OHL
Dil
Saham 132 2 293 27.29 22.52 22.72 17.76
Abdusalam(DAS) OHL
Dil
KIS 132 2 293 9.34 8.77 6.91
Abdusalam(DAS) OHL
Dreez Ibri OHL 132 2 293 14.16 14.10 14.79 15.65 13.48

Falaj Al Qabail Sohar OHL 132 2 293 10.27

Falaj Al Qabail Wadi Al Jazzi OHL 132 2 293 22.04

Halban Mobella OHL 132 2 293 12.91 15.74 15.73

Ibra Mudhairib OHL 132 2 293 14.76 15.76

Ibra Qabel OHL 132 2 293 15.57 16.44 17.35

Ibri Jebreen OHL 132 2 293 0.00 8.51 18.03 20.52

Ibri Madinat Ibri OHL 132 2 293 27.91

Izki New Izki OHL 132 2 293 29.51 30.07 37.28 44.86 42.59

Izki Nizwa OHL 132 2 293 20.72 17.64

Izki Sumail OHL 132 2 293 4.75 4.47 17.44 26.08 14.29

JBB Hasan Sur OHL 132 2 293 28.03 32.48 16.77 17.54 19.68

Jahloot Quriyat OHL 132 2 293 19.55 19.32 20.13 20.71 20.76

Jahloot Yitti OHL 132 2 403 1.48 1.57 1.76 1.94 2.09

Jebreen Madinat Ibri OHL 132 2 293 16.63

Jebreen Nizwa OHL 132 2 293 11.31 6.35 6.15 8.25 3.31

Khaborah Khadra OHL 132 2 293 8.71 8.01 26.95 27.52 24.71

Khaborah KIS OHL 132 2 293 44.28 46.06 44.54

Khaborah Saham OHL 132 2 293 14.05

Page | 172
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C.3 (continued): Overhead Line and Cable Circuit Loadings (%) at Peak Demand (2017-2021)
No. of Circuit Circuit Loading at Max Demand (%)
Voltage
Line Type Circuit Rating
(kV) 2017 2018 2019 2020 2021
s (MVA)

MIS Area
Khadra MIS OHL 132 2 293 20.53

Khadra Suwaiq OHL 132 2 293 30.76 7.37 7.17 4.37


Mawalleh
Khoudh 132 2 250 6.15 6.71
South OHL
Rusail
Khoudh 132 2 250 35.34 38.14
Industrial OHL

Khuwair MSQ OHL 132 3 293 31.93

Liwa Shinas OHL 132 2 293 20.54 20.57 11.26 12.22 13.06
Sohar Free
Liwa 132 2 293 42.79 50.82 33.29 38.44 41.22
Zone OHL
MIS Muladah OHL 132 2 293 23.08 21.42 36.70 37.40 32.71

MIS Suwaiq OHL 132 2 293 43.57 13.16 14.14 16.62


New Ghubrah-
293 15.45 21.85
MSQ-A A OHL 132 2
New Ghubrah-
293 36.59 34.06
MSQ-B B OHL 132 1

MSQ New Ghubrah OHL 132 3 293 29.62 30.82

MSQ Qurum OHL 132 2 293 13.53 12.65 9.94 9.33 6.67

MSQ Wadi Adai OHL 132 2 293 18.26 16.18 12.29 11.08 0.00
Madinat
Nizwa 132 2 293 10.00 10.25 10.63 11.01 11.38
Nizwa OHL
Madinat
132 2 293 11.30 11.81 12.62 13.48
Shinas Shinas OHL
Mahadha Wadi Al Jazzi OHL 132 2 178 49.85 9.21 29.94 25.15 27.23

Mahadha Wadi Sa'a OHL 132 2 293 1.89 1.93 1.99 3.31 3.48

Manah Nizwa OHL 132 2 293 49.10 47.36 43.91 46.50 42.10

Misfah Rusail OHL 132 2 293 5.75 5.98 6.24 6.43

Misfah Wadi Adai OHL 132 2 293 0.00 0.00 0.00 0.00 42.58

Mobella Rusail OHL 132 2 293 0.00 0.00 0.00 0.00 0.00

Page | 173
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C.3 (continued): Overhead Line and Cable Circuit Loadings (%) at Peak Demand (2017-2021)
Circui Circuit Loading at Max Demand (%)
t
Voltag No. of Ratin
Line Type 202
e (kV) Circuits g 2017 2018 2019 2021
(MVA 0
)

MIS Area
Mudhaibi Mudhairib OHL 132 2 293 5.83 10.23 24.80 27.36 27.22

Mudhaibi New Izki OHL 132 2 293 22.28

Mudhaibi Samad OHL 132 2 293 5.76 5.96 6.13

Mudhaibi Sinaw OHL 132 2 293 12.90 8.48 10.31 10.58

Mudhairib Qabel OHL 132 2 293 27.85 30.55 30.05

Muladah Madinat Barka OHL 132 2 293 34.80 40.47 10.93 12.09 17.94

Muladah Rustaq OHL 132 2 293 27.96 29.32 18.06 18.64 17.67

Muttrah Wadi Kabair OHL 132 1 293 1.40 1.74 2.55 1.81 9.05
Wadi Bani
Nakhal 132 2 293 10.82 11.63 13.84
Auwf OHL
New Izki Sinaw OHL 132 2 293 20.65 3.71 4.26 7.37

Rusail Sumail OHL 132 2 293 30.61 23.96


Sumail
Rusail 132 2 293 12.21 12.33 17.88
Industrial OHL
Wadi Bani
Rustaq 132 2 293 2.29 2.48 4.24
Auwf OHL
SIS Saham OHL 132 2 293 44.15 44.66 40.18 41.64 34.79

SIS Sohar OHL 132 2 293 15.28

SIS Uwaynat OHL 132 2 293 14.40 26.78 31.40 42.98

Shinas Sohar Free Zone OHL 132 2 585 5.49 6.06 6.48

Sohar Free Zone Wadi Al Jazzi OHL 132 2 293 2.86 21.14 3.87 5.81 5.27

Sohar Uwaynat OHL 132 2 293 7.75 6.42 9.55 13.95

Sohar Wadi Al Jazzi OHL 132 2 293 26.67 33.24 22.37 21.32

Sumail Industrial Sumail OHL 132 2 293 7.14 13.59 5.09

A'salam Mobella UGC 132 2 375 5.66 42.83 45.60 42.19 44.32

Page | 174
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C.3 (continued): Overhead Line and Cable Circuit Loadings (%) at Peak Demand (2017-2021)
Circuit Circuit Loading at Max Demand (%)
Voltage No. of
Line Type Rating
(kV) Circuits 2017 2018 2019 2020 2021
(MVA)

MIS Area
A'salam Seeb Main UGC 132 2 375 19.47 28.11 29.13 24.53 25.73

Airport Height Ghala UGC 132 2 375 11.64 12.13 26.40 28.16 28.95

Airport Height Mawaleh South-B UGC 132 2 375 47.18 0.00 0.00 0.00 0.00

Airport Height Mawalleh North UGC 132 2 375 4.49 12.88 13.53 14.20 14.49

Al Falaj Muttrah UGC 132 1 300 13.44 12.82 18.87 19.88 9.27

Al Hamriyah Muttrah UGC 132 2 375 17.00 16.97 19.49 20.27 13.65

Al Hamriyah Wadi Kabair UGC 132 2 172 44.83 45.10 50.01 52.14 44.92

Bousher Ghala Heights UGC 132 2 375 0.00 0.00 0.00

Bousher MSQ UGC 132 1 375 18.60 23.94 29.18 30.36 28.89

Bousher New Ghubrah UGC 132 3 375 18.04 15.80 6.23 6.73 2.75

Bureimi Industrial Bureimi UGC 132 2 375 12.66 12.87 4.61 4.72 5.18

Bureimi Mahadha UGC 132 2 375 10.37 11.13 11.97

Ghala Ghala Heights UGC 132 2 375 14.68 15.55 15.98

Izki New Izki UGC 132 2 375 22.92 23.33 29.06 34.99 33.13
Mawalleh South-
Khoudh 132 2 375 4.26 4.63
A UGC
Khuwair New Ghubrah UGC 132 3 375 20.88

MSQ-A New Ghubrah-A UGC 132 2 375 12.68 17.65

MSQ-B New Ghubrah-B UGC 132 1 375 28.54 26.56

MSQ New Ghubrah UGC 132 3 375 23.85 24.75

Mawalleh South-A Rusail Industrial UGC 132 2 375 37.23 31.49 31.94 21.58 23.24

Mawalleh South-B Seeb Main UGC 132 2 375 48.03 0.00 0.00 0.00 0.00

Mudhaibi New Izki UGC 132 2 375 17.04

Muttrah Wadi Kabair UGC 132 1 300 2.37 2.70 3.45 2.71 9.15

Page | 175
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C.3 (continued): Overhead Line and Cable Circuit Loadings (%) at Peak Demand (2017-2021)

No. of Circuit Circuit Loading at Max Demand (%)


Voltage
Line Type Circuit Rating
(kV)
s (MVA) 2017 2018 2019 2020 2021

MIS Area

New Ghubrah Old Ghubrah 132 2 375 22.20 16.33


UGC
New Izki Sinaw 132 2 375 15.47 1.92 2.35 4.75
UGC
Rusail Rusail Industrial 132 3 375 94.15
UGC
Rusail Rusail Industrial 132 4 375 65.93 68.09 76.29 5.52
UGC
Rusail Sumail Industrial 132 2 375 10.16 10.52 14.13
UGC
Sumail
Sumail 132 2 375 5.16 10.28 4.00
Industrial UGC
Sur-2 Sur-1 132 2 343 28.55 29.80 32.31
UGC 37.11 41.304
Dhofar System
Al Qarm Ittin OHL 132 2 359 17.03 9.33 9.68 10.77 10.11
Ashoor Al-Qarm OHL 132 2 359 21.40 12.02 12.04 12.99 12.50
S'aadah (Portion-
Ashoor OHL 132 2 330 20.93 13.71 16.31 17.31 19.34
1)
S'aadah (Portion-
Ashoor OHL 132 2 330 21.01 13.92 16.53 17.54 19.56
2)
Awqad S'aadah OHL 132 2 330 9.00 5.44 6.45 7.01 8.77
Ittin Thumrait OHL 132 2 183 6.45 6.81 7.24 7.73 8.12
NPS Salalah Free Zone OHL 132 2 359 27.00 15.35 19.24 20.52 23.79
Salalah Free
Awaqad OHL 132 2 359 8.50 17.48 18.08 18.78 21.55
Zone
Salalah Free
Ittin OHL 132 2 359 4.37 12.29 10.22 11.47 10.93
Zone
Ashoor Al-Qarm UGC 132 2 279 27.44 15.34 15.37 16.59 15.98
S'aadah (Portion-
Ashoor UGC 132 2 279 24.92 16.45 19.55 20.75 23.15
1)
S'aadah (Portion-
Ashoor UGC 132 2 300 23.74 16.65 19.49 20.61 22.71
2)
Awqad S'aadah UGC 132 2 300 9.90 5.94 7.09 7.75 10.46
NPS Salalah Free Zone UGC 132 2 279 34.71 19.74 24.73 26.38 30.58

Page | 176
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C 4: Transmission System Voltage Profile at Peak Demand (2017-2021)


Busbar Voltage at Maximum Demand (per unit)
Location
2017 2018 2019 2020 2021
MIS
400 kV Busbars
Ibri IPP 1.03 1.04 1.03 1.03
Jahloot 0.98 0.99 0.99 0.99 0.99
Misfah 1.01 1.00 1.00 1.00
New Izki 1.02 1.02 1.02 1.02 1.01
Qabel 1.03 1.03 1.02
Rusail Industrial 0.99
SIS 1.01 1.01 1.01
Sohar Free Zone 1.02 1.02 1.02
Sohar-3 IPP 1.03 1.03 1.02
Sur PS 1.03 1.03 1.04 1.04 1.03
220 kV Busbars
Airport Height 1.00 1.01 1.01 1.00 1.01
Al Filaj 1.02 1.01 1.02 1.01 1.02
Al Hamriyah 0.97 0.99 0.98 0.96 0.98
Alw(UAE) 1.02 1.02 1.03 1.03 1.03
Barka PS 1.03 1.02 1.03 1.02 1.03
Barka-3 PS 1.04 1.05 1.06 1.06 1.04
Blue City 1.00 1.00 1.00 1.00 1.01
Ibri 0.96 1.03 1.03 1.03 1.02
Ibri IPP 1.04 1.05 1.05 1.04
Jahloot 0.99 1.01 1.00 0.99 1.01
MIS 0.98 0.97 0.98 0.97 0.99
MSQ 0.98 1.00 0.98 0.98 1.00
Mahadha 1.01 1.02 1.03 1.03 1.03
Misfah 1.00 1.02 1.01 1.01 1.02
Misfah IPP 1.02
Mobella 1.00 1.01 1.00 1.01
New Izki 0.99 1.03 1.02 1.01 1.01
KIS 0.98 0.98 0.99
SIP-A 1.05 1.04 1.02 1.03 1.04
SIS 1.02 1.01 1.02 1.03 1.03

Page | 177
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C4 (countinued): Transmission System Voltage Profile at Peak Demand (2017-2021)


Busbar Voltage at Maximum Demand (per unit)
Location
2017 2018 2019 2020 2021
MIS
Sohar Free Zone 1.03 1.01 1.03 1.03 1.03
Sohar-1 PS 1.05 1.04 1.02 1.03 1.04
Sohar-2 PS 1.04 1.02 1.03 1.03 1.03
Sur 1.03 1.02 1.02 1.01 1.01
Sur PS 1.04 1.03 1.02 1.02 1.02
132 kV Busbars
A'salam 0.98 1.00 1.01 1.01 1.02
Adam 0.98 1.00 1.01 1.00 0.99
Airport Height 0.99 1.01 1.00 0.99 1.01
Al Falaj 0.98 1.00 0.97 0.96 0.99
Al Filaj 0.99 1.00 1.01 1.01 1.02
Al Hamriyah 0.98 1.00 0.97 0.97 0.99
Al Hayl 0.96 1.00 1.01 1.00 1.01
Al Kamil 1.01 1.00 1.03 1.02 1.02
Amerat 0.99 1.01 0.98 0.98 1.00
Ayjah 1.02 1.03 1.01 1.00 1.00
Bahla 0.97 0.99 0.99 0.98 0.98
Barka Main 0.99 1.00 1.01 1.01 1.02
Bedyah 1.03 1.02 1.02
Birkat Al Mouz 1.00 1.00 1.00
Bousher 1.01 1.02 0.97 0.97 0.99
Bureimi 0.96 1.01 1.04 1.03 1.03
Bureimi Industrial 0.96 1.01 1.04 1.03 1.03
Daghmar 0.98 1.00 0.98 0.97 0.99
Dank 0.97 1.01 1.02 1.01 1.02
Dil Abdusalam (DAS) 0.97 1.01 1.00 1.01
Dreez 0.97 1.02 1.02 1.02 1.03
Falaj Al Qabail 1.00
Ghala 0.99 1.01 1.00 0.99 1.01
Ghala Heights 1.00 0.99 1.01
Halban 1.01 1.01 1.02
Ibra 0.96 0.95 1.02 1.02 1.02
Ibri 0.98 1.03 1.03 1.03 1.04
Izki 0.99 1.02 1.00 1.00 1.01
JBB Ali 0.99 0.98 1.00 0.99 0.99
JBB Hasan 1.01 1.01 1.01 1.01 1.00
Jahloot 1.00 1.03 1.01 1.00 1.02
Jebreen 0.97 1.00 1.00 1.00 1.00
Khaborah 0.97 0.96 1.00 0.99 1.00
Khadra 0.97 0.96 0.99 0.98 0.98
Khoudh 1.03 0.99
Khuwair 0.99

Page | 178
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C4 (countinued): Transmission System Voltage Profile at Peak Demand (2017-2021)


Busbar Voltage at Maximum Demand (per unit)
Location
2017 2018 2019 2020 2021
MIS
Liwa 1.03 1.02 1.03 1.02 1.01
MIS 0.98 0.97 1.00 0.99 0.99
MSQ-A 1.01 1.03
MSQ-B 0.98 1.01
MSQ 0.97 0.97 0.99
Madinat Barka 0.99 0.98 1.00 1.00 1.01
Madinat Ibri 1.01
Madinat Nizwa 0.98 1.00 1.00 0.99 0.99
Madinat Shinas 1.00 1.02 1.01 1.00
Mahadha 0.97 1.03 1.05 1.04 1.03
Manah 0.99 1.01 1.02 1.01 1.01
Mawalleh North 0.99 1.01 1.00 0.99 1.01
Mawalleh South-A 1.02 1.02 1.02 1.03 0.99
Mawalleh South-B 0.99 0.00 0.00 0.00 0.00
Misfah 1.02 1.02 1.02 1.03 1.02
Mobella 0.98 1.00 1.02 1.01 1.02
Mudhaibi 0.98 0.98 1.00 1.00 1.00
Mudhairib 0.97 0.96 1.03 1.02 1.02
Muladah 0.97 0.96 0.99 0.98 0.99
Muttrah 0.98 1.00 0.97 0.97 0.99
Nakhal 0.99 0.99 1.00 0.99 1.00
New Ghubrah-A 1.01 1.03
New Ghubrah-B 0.99 1.01
New Ghubrah 0.97 0.97 0.99
New Izki 1.01 1.03 1.01 1.01 1.02
KIS 1.01 1.01 1.01
Niheda(PDO) 0.98 1.00 1.01 1.00 1.00
Nizwa 0.98 1.00 1.00 1.00 1.00
Old Ghubrah 1.01 1.03
Qabel 1.03 1.03 1.03
Quriyat 0.98 1.00 0.98 0.97 0.99
Qurum 0.98 1.00 0.97 0.97 0.99
Rusail 1.02 1.02 1.02 1.03 1.00
Rusail Industrial 1.02 1.02 1.02 1.03 1.00
Rustaq 0.95 0.94 0.98 0.97 0.98
SIP-A 1.03 1.04 1.02 1.04 1.05
SIS 1.03 1.02 1.03 1.03 1.02
Saham 1.00 0.99 1.01 1.01 1.01
Samad 1.00 0.99 1.00
Seeb Main 0.98 1.00 1.01 1.01 1.01
Shinas 1.02 1.01 1.02 1.01 1.01
Sinaw 0.99 1.00 1.00 1.01

Page | 179
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C4 (countinued): Transmission System Voltage Profile at Peak Demand (2017-2021)


Busbar Voltage at Maximum Demand (per unit)
Location
2017 2018 2019 2020 2021
MIS
Sohar 1.01 1.01 1.01 1.01 1.00
Sohar Free Zone 1.03 1.02 1.03 1.02 1.02
Sohar Refinery 1.03 1.04 1.02 1.04 1.05
Sumail 1.00 1.01 1.00 1.00 0.98
Sumail Industrial 1.01 1.01 0.98
Sur 1.03 1.04 1.02 1.01 1.01
Sur-2 1.03 1.04 1.02 1.01 1.01
Suwaiq 0.97 0.99 0.99 0.99
Uwaynat 1.01 1.02 1.01 1.00
Wadi Adai 0.98 1.00 0.97 0.97 0.99
Wadi Al Jazzi 1.03 1.03 1.03 1.02 1.01
Wadi Bani Auwf 0.98 0.98 0.98
Wadi Kabair 0.98 1.00 0.97 0.97 0.99
Wadi Sa'a 0.97 1.03 1.05 1.04 1.03
Yanqul 1.00 1.01
Yitti 1.00 1.03 1.01 1.00 1.02
33 kV busbars
Tx (1&2) 1.00 1.00 1.00 1.00 1.01
A'salam
Tx (3&4) 1.01 1.00 1.01
Adam 1.00 1.00 1.00 1.00 1.00
Tx (1&2) 0.99 1.00 1.00 0.99 1.00
Airport Height
Tx (3&4) 1.00 0.99 1.00
Al Falaj 1.00 1.01 1.01 1.00 0.99
Al Hayl 0.99 1.00 1.00 1.00 1.00
Tx (1&2) 0.99 1.00 1.00 0.99 1.00
Amerat
Tx (3&4) 1.00 0.99 1.00
Ayjah 1.00 1.00 1.00 1.00 1.00
Bahla 1.00 1.00 1.00 0.99 1.00
Tx (3) 1.00
Barka Main
Tx (1&2) 1.01 1.00 1.00 0.99 1.00
Barka-3 PS 1.00 1.00 1.01 1.00
Bedyah 1.00 1.00 1.00
Birkat Al Mouz 0.99 1.00 1.00
Blue City 0.99 1.00 0.99 1.00 1.00
Tx (1&2) 1.00 1.00 0.99 1.00 1.00
Bousher
Tx (3&4) 1.00 0.99 1.00 0.99 1.00
Bureimi 1.00 1.01 1.01 1.00 1.00
Bureimi Tx (1&2) 1.00 1.00 1.01 1.01 1.00
Industrial Tx (3&4) 1.00 1.01 1.00

Page | 180
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C4 (countinued): Transmission System Voltage Profile at Peak Demand (2017-2021)


Busbar Voltage at Maximum Demand (per unit)
Location
2017 2018 2019 2020 2021
MIS
Dank 1.00 1.00 1.00 0.99 1.01
Dil Abdusalam(DAS) 0.99 0.99 1.00 0.99
Dreez 1.00 1.00 1.00 1.00 1.00
Falaj Al Qabail BB 0.99
Tx (1&2) 1.00 1.00 1.00
Ghala Heights
Tx (3&4) 1.00 1.00 1.00
Tx (1&2) 0.99 1.00 1.00 1.00 1.00
Ghala
Tx (3&4) 1.00 1.00 1.00
Tx (1&2) 1.01 1.00 1.00
Halban
Tx (3&4) 1.00 1.00 1.00
Ibra 1.00 1.00 1.00 0.99 1.00
125MVA 0.99 1.01 1.01 1.00 1.00
Ibri
63MVA 1.00 1.00 1.00 1.00
Izki 1.00 1.00 1.00 0.99 1.00
JBB Ali 1.00 1.00 0.99 1.00 0.99
JBB Hasan 0.99 0.99 1.00 1.00 1.00
Jahloot 1.00 1.00 1.01 1.00 1.00
Jebreen 0.99 1.00 1.00 1.00 1.00
Khaborah 0.99 1.00 1.01 1.00 1.00
Tx (1&2) 1.00 0.99 0.99 1.00 0.99
Khadra
Tx (3&4) 1.00 1.00 1.00 1.00
Tx (1&2) 1.00 1.00
Khoudh
Tx (3&4) 1.00 1.00
Khuwair 1.00
Tx (1&2) 1.00 0.99 1.00 0.99 1.00
Liwa
Tx (3&4) 1.01 1.00 1.00 1.00 1.00
MIS 0.99 1.00 1.00 1.00 1.00
Tx (1&2) 1.00 1.01 1.00 1.00 1.00
MSQ
Tx (3&4) 1.01 1.01 1.00 1.00 1.00
Tx (1&2) 1.01 1.00 1.01 1.00 0.99
Madinat Barka
Tx (3&4) 1.01 0.99 1.00 1.00
Madinat Ibri 0.99
Madinat Nizwa 0.99 0.99 0.99 1.00 1.00
Madinat Shinas 1.01 1.00 1.00 1.00
Mahadha 1.00 1.01 1.01 1.00 1.00
Mawalleh North 1.00 1.00 1.00 1.00
Mawalleh Tx (1&2) 1.00 1.00 1.00 1.00 1.00
South Tx (3&4) 1.00 1.00 1.00 1.00 1.00
Misfah 1.01 1.00 1.00 1.01 1.01
Mobella 1.00 1.00 1.01 1.00 1.00

Page | 181
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C4 (countinued): Transmission System Voltage Profile at Peak Demand (2017-2021)


Busbar Voltage at Maximum Demand (per unit)
Location
2017 2018 2019 2020 2021
MIS
Mudhaibi 0.99 1.00 1.00 1.00 0.99
Mudhairib 0.99 0.99 1.01 1.00 1.00
Tx (1&2) 1.00 0.99 1.00 1.00 1.00
Muladah
Tx (3&4) 1.00 1.00 0.99 1.00 1.00
Muttrah 1.00 1.00 1.00 1.00 1.00
Nakhal 1.01 1.01 1.01 1.00 1.00
Tx (1&2) 1.00 1.00 1.00 1.00 1.00
New Ghubrah
Tx (3&4) 1.00 1.00
New Izki 1.00 1.00 1.00 0.99 1.00
Nizwa 0.99 1.00 1.00 1.00 1.00
Old Ghubrah 1.00 1.00
Quriyat 0.99 0.99 1.00 1.00 0.99
Qurum 1.00 1.00 1.00 0.99 1.01
Rusail Tx (1&2) 1.01 1.01 1.01 1.01 0.99
Industrial Tx (3&4) 1.00 1.00 1.00 1.00 1.00
Rustaq 1.00 0.99 1.00 1.00 1.00
SIP-A 1.01 1.01 1.00 1.01 1.01
Saham 1.00 0.99 1.00 1.00 1.00
Samad 1.01 1.00 1.00
Tx (1&2) 1.00 1.00 1.00 1.00 1.00
Seeb Main
Tx (3&4) 1.00 1.00 1.00 0.99 1.00
Shinas 1.00 1.00 1.01 1.00 1.00
Sinaw 1.00 1.00 0.99 1.00
Sohar Free Tx (1&2) 1.00 1.00 1.01 1.00 1.00
Zone Tx (3&4) 1.00 1.01 1.00
Tx (1&2) 1.00 1.00 1.00 0.99 1.00
Sohar
Tx (3&4) 1.00 1.00 1.00 0.99 1.00
Sumail Industrial 1.00 1.00 1.00
125MVA 0.99 1.00 0.99 0.99 1.00
Sumail
63MVA 1.00 1.00 1.00 1.00 1.00
Sur 1.01 1.01 1.00 1.00 0.99
Suwaiq 0.99 1.00 1.00 1.00
Tx (1&2) 1.00 1.00 1.00 0.99
Uwaynat
Tx (3&4) 1.00 1.00 0.99 1.00
Wadi Adai 1.00 1.00 1.00 1.00 1.00
Wadi Bani Auwf 0.99 1.00 1.00
Tx (1&2) 1.00 1.00 0.99 0.99 1.00
Wadi Kabair
Tx (3&4) 0.99 1.00 1.00 1.00 1.00
Wadi Sa'a 1.00 1.00 1.01 1.01 1.00

Page | 182
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C4 (countinued): Transmission System Voltage Profile at Peak Demand (2017-2021)


Busbar Voltage at Maximum Demand (per unit)
Location
2017 2018 2019 2020 2021
MIS
Yanqul 1.01 1.00
Yitti 1.00 1.00 1.00 0.99 1.00
11 kV busbars
Daghmar 1.00 0.99 0.99 1.00 0.99
Mawalleh North 0.99
Dhofar Area
132 kV Busbars
Al Qarm 1.01 1.01 1.01 1.01 1.01
Ashoor 1.02 1.02 1.02 1.02 1.01
Awaqad 1.00 1.01 1.00 1.00 1.00
Ittin 1.00 1.01 1.00 1.00 1.00
NPS 1.01 1.01 1.01 1.01 1.01
BB-1 1.01 1.01 1.01 1.01 1.01
Salalah Free Zone
BB-2 1.01 1.01 1.01 1.01 1.01
S’aadah 1.00 1.01 1.00 1.00 1.00
Thumrait 0.99 1.00 1.00 0.99 0.99
Wind Farm 1.00 1.00 1.00
33 kV busbars
Al Qarm 1.00 1.01 1.00 1.00 1.01
Ashoor 1.00 1.00 1.01 1.01 1.00
Awaqad 1.00 1.00 1.00 1.01 1.00
Ittin 1.00 1.00 1.00 1.00 1.00
NPS 1.01 1.01 1.00 1.01 1.01
TX-1&2 1.01 1.00 1.00 1.01 1.00
S’aadah
TX-3&4 1.00 1.00 1.01 1.00 1.00
TX-1&2 1.00 1.00 1.00 1.00 1.00
Salalah Free Zone
TX-3&4 1.01 1.01 1.00 1.01 1.00
Thumrait 1.00 1.00 1.00 1.00 1.01

Page | 183
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C 5: Transmission System Voltage Profile at Minimum Demand (2017-2021)


Busbar Voltage at Miniimum Demand (per unit)
Location
2017 2018 2019 2020 2021
MIS
400 kV Busbars
Ibri IPP 1.00 1.01 1.01
Jahloot 1.01 1.00 1.01 1.01 1.01
Misfah 1.01 1.00 1.01 1.03
New Izki 1.02 1.01 1.00 1.01 1.02
Qabel 1.02 1.03
SIS 1.02 1.02
Sohar Free Zone 1.01 1.02
Sohar-3 IPP 1.01 1.02
Sur PS 1.02 1.00 1.01 1.02 1.02
220 kV Busbars
Airport Height 1.02 1.02 1.02 1.02 1.04
Al Filaj 1.01 1.01 1.02 1.02 1.03
Al Hamriyah 1.00 1.01 1.00 1.02 1.03
Alw(UAE) 1.02 1.03 1.02 1.03 1.03
Barka PS 1.01 1.01 1.02 1.02 1.03
Barka-3 PS 1.03 1.03 1.02 1.03 1.04
Blue City 1.02 1.02 1.02 1.03 1.04
Ibri 1.02 1.02 1.01 1.02 1.02
Ibri IPP 1.01 1.02 1.03
Jahloot 1.02 1.01 1.01 1.02 1.04
MIS 1.02 1.01 1.02 1.02 1.03
MSQ 1.02 1.02 1.01 1.01 1.03
Mahadha 1.02 1.02 1.01 1.03 1.03
Misfah 1.02 1.02 1.02 1.02 1.04
Mobella 1.02 1.02 1.04
New Izki 1.03 1.02 1.01 1.01 1.02
KIS 1.02 1.02
SIP-A 1.02 1.01 1.01 1.00 1.00
SIS 1.02 1.02 1.01 1.02 1.02
Sohar Free Zone 1.02 1.01 1.02 1.02
Sohar-1 PS 1.02 1.01 1.01 1.00 1.01
Sohar-2 PS 1.03 1.02 1.01 1.02 1.02
Sur 1.02 1.03 1.01 1.01 1.02
Sur PS 1.02 1.04 1.01 1.01 1.03
132 kV Busbars
A'salam 1.03 1.02 1.03 1.03 1.04
Adam 1.02 1.01 1.01 1.01 1.01
Airport Height 1.03 1.02 1.03 1.03 1.04
Al Falaj 1.02 1.01 1.01 1.02 1.04
Al Filaj 1.02 1.02 1.02 1.02 1.03

Page | 184
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C 5 (continued): Transmission System Voltage Profile at Minimum Demand (2017-2021)


Busbar Voltage at Miniimum Demand (per unit)
Location
2017 2018 2019 2020 2021
MIS
Al Hamriyah 1.02 1.01 1.02 1.02 1.04
Al Hayl 1.03 1.01 1.00 1.01 1.02
Al Kamil 1.01 1.00 0.99 1.01 1.02
Amerat 1.02 1.01 1.01 1.03 1.04
Ayjah 1.00 1.02 1.00 1.00 1.02
Bahla 1.02 1.01 1.01 1.01 1.01
Barka Main 1.02 1.02 1.03 1.03 1.04
Bedyah 1.01 1.02
Birkat Al Mouz 1.02 1.01
Bousher 1.01 1.01 1.02 1.03 1.04
Bureimi 1.04 1.02 1.01 1.03 1.03
Bureimi Industrial 1.04 1.02 1.01 1.03 1.03
Daghmar 1.00 1.00 1.00 1.01 1.02
Dank 1.03 1.01 1.00 1.01 1.02
Dil Abdusalam (DAS) 1.00 1.01 1.02
Dreez 1.01 1.00 1.01 1.02
Ghala 1.03 1.02 1.03 1.03 1.04
Ghala Heights 1.03 1.04
Halban 1.03 1.04
Ibra 1.01 1.00 0.99 1.01 1.02
Ibri 1.04 1.01 1.01 1.02 1.02
Izki 1.03 1.01 1.02 1.03 1.02
JBB Ali 1.00 1.00 0.98 1.00 1.01
JBB Hasan 1.00 1.01 0.99 1.00 1.01
Jahloot 1.02 1.02 1.01 1.03 1.03
Jebreen 1.01 1.01 1.02 1.01
Khaborah 1.01 1.01 1.00 1.01 1.02
Khadra 1.01 1.01 1.00 1.01 1.02
Khoudh 1.01
Liwa 1.00 1.01 1.00 1.02 1.01
MIS 1.02 1.02 1.01 1.02 1.02
MSQ 1.01 1.01 1.02 1.03 1.04
Madinat Barka 1.02 1.02 1.02 1.02 1.03
Madinat Nizwa 1.02 1.01 1.01 1.02 1.01
Madinat Shinas 1.00 1.02 1.01
Mahadha 1.04 1.02 1.01 1.03 1.03
Manah 1.03 1.01 1.02 1.02 1.01
Mawalleh North 1.03 1.02 1.03 1.03 1.04
Mawalleh South-A 1.00 0.98 0.99 1.00 1.01
Mawalleh South-B 1.03 1.02 1.03 1.03 1.04

Page | 185
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C 5 (continued): Transmission System Voltage Profile at Minimum Demand (2017-2021)


Busbar Voltage at Miniimum Demand (per unit)
Location
2017 2018 2019 2020 2021
MIS
Misfah 1.00 0.99 1.00 1.01 1.02
Mobella 1.03 1.02 1.03 1.03 1.04
Mudhaibi 1.03 1.01 1.00 1.02 1.02
Mudhairib 1.01 1.00 0.99 1.01 1.02
Muladah 1.01 1.01 1.01 1.01 1.02
Muttrah 1.02 1.01 1.01 1.02 1.04
Nakhal 1.02 1.02 1.02 1.02 1.03
New Ghubrah 1.01 1.01 1.02 1.03 1.04
New Izki 1.04 1.01 1.03 1.04 1.02
KIS 1.01 1.02
Niheda(PDO) 1.03 1.01 1.02 1.02 1.01
Nizwa 1.03 1.01 1.01 1.02 1.01
Old Ghubrah 1.01 1.01
Qabel 1.02 1.02
Quriyat 1.00 1.00 1.00 1.02 1.02
Qurum 1.02 1.01 1.01 1.03 1.04
Rusail 1.00 0.98 1.00 1.01 1.01
Rusail Industrial 1.00 0.98 1.00 1.01 1.01
Rustaq 1.01 1.01 1.00 1.01 1.02
SIP-A 1.00 1.01 1.00 1.00 1.00
SIS 1.02 1.01 1.01 1.01 1.01
Saham 1.01 1.01 1.00 1.01 1.01
Samad 1.02 1.02
Seeb Main 1.03 1.02 1.03 1.03 1.04
Shinas 1.00 1.01 1.00 1.02 1.01
Sinaw 1.01 1.03 1.02
Sohar 1.01 1.01 1.00 1.01 1.01
Sohar Free Zone 1.01 1.00 1.02 1.01
Sohar Refinery 1.00 1.01 1.00 1.00 1.00
Sumail 1.01 0.99 1.00 1.01 1.01
Sumail Industrial 1.01 1.01
Sur 1.01 1.02 1.00 1.01 1.02
Sur-2 1.01 1.02 1.00 1.01 1.02
Suwaiq 1.00 1.01 1.02
Uwaynat 1.00 1.01 1.01
Wadi Adai 1.02 1.01 1.01 1.02 1.04
Wadi Al Jazzi 1.01 1.01 1.00 1.02 1.02
Wadi Bani Auwf 1.02 1.02
Wadi Kabair 1.02 1.01 1.01 1.02 1.04
Wadi Sa'a 1.04 1.02 1.01 1.03 1.03

Page | 186
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C 5 (continued): Transmission System Voltage Profile at Minimum Demand (2017-2021)


Busbar Voltage at Miniimum Demand (per unit)
Location
2017 2018 2019 2020 2021
MIS
Yanqul 1.02
Yitti 1.02 1.02 1.01 1.03 1.03
33 kV busbars
Tx (1&2) 1.01 1.01 1.01 1.00 1.00
A'salam
Tx (3&4) 1.00 1.00
Adam 1.00 1.00 1.00 1.00 1.00
Tx (1&2) 1.01 1.00 1.01 1.00 1.00
Airport Height
Tx (3&4) 1.00 1.00
Al Falaj 1.01 1.00 1.00 1.00 1.00
Al Hayl 1.01 1.00 1.01 1.00 1.00
Tx (1&2) 1.01 1.00 1.00 1.00 1.01
Amerat
Tx (3&4) 1.00 1.01
Ayjah 1.00 1.00 1.00 1.00 1.00
Bahla 1.00 1.00 0.99 1.00 1.00
Tx (3) 1.00
Barka Main
Tx (1&2) 1.00 1.00 1.00 1.00 1.00
Barka-3 PS 1.01 1.01 1.00
Bedyah 1.00 1.01
Birkat Al Mouz 1.00 1.00
Blue City 1.00 1.00 1.01 1.00 1.00
Tx (1&2) 1.00 1.00 1.00 1.00 1.00
Bousher
Tx (3&4) 1.00 0.99 1.00 1.00 1.00
Bureimi 1.00 1.01 1.00 1.00 1.01
Tx (1&2) 1.01 1.01 1.00 1.01 1.00
Bureimi Industrial
Tx (3&4) 1.01 1.00
Dank 1.01 1.00 1.00 1.00 1.00
Dil Abdusalam(DAS) 1.00 1.00 1.00
Dreez 1.01 1.00 1.01 1.00
Tx (1&2) 1.00 1.00
Ghala Heights
Tx (3&4) 1.00 1.00
Tx (1&2) 1.00 1.00 1.00 1.00 1.00
Ghala
Tx (3&4) 1.00 1.00
Tx (1&2) 1.01 1.01
Halban
Tx (3&4) 1.00 1.00
Ibra 1.00 1.00 1.00 1.00 1.00
125MVA 1.00 1.00 1.00 1.00 1.00
Ibri
63MVA 1.00 1.00 1.00 1.00 1.00
Izki 1.00 1.00 1.00 1.00 1.00
JBB Ali 1.00 1.00 0.99 1.00 1.00
JBB Hasan 1.00 1.00 1.00 0.99 1.00

Page | 187
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C 5 (continued): Transmission System Voltage Profile at Minimum Demand (2017-2021)


Busbar Voltage at Miniimum Demand (per unit)
Location
2017 2018 2019 2020 2021
MIS
Jahloot 1.00 1.00 1.00 1.00 1.01
Jebreen 1.00 1.00 1.00 1.01
Khaborah 1.00 1.00 1.01 1.00 1.01
Tx (1&2) 0.99 1.00 0.99 1.00 1.00
Khadra
Tx (3&4) 0.99 0.99 1.00
Tx (1&2) 1.01
Khoudh
Tx (3&4) 1.01
Tx (1&2) 1.00 0.99 1.00 1.00 1.00
Liwa
Tx (3&4) 1.00 1.00 1.00 1.00
MIS 0.99 0.99 1.00 1.00 1.00
Tx (1&2) 1.01 1.00 0.99 1.00 1.00
MSQ
Tx (3&4) 1.01 1.00 1.01 1.01 1.01
Tx (1&2) 1.00 0.99 1.00 1.00 1.01
Madinat Barka
Tx (3&4) 1.00 1.00 1.01
Madinat Nizwa 1.00 1.00 1.00 1.00 1.00
Madinat Shinas 1.00 1.00 1.00
Mahadha 1.00 1.00 0.99 0.99 1.00
Mawalleh North 1.00 1.00 1.00
Tx (1&2) 1.00 1.00 1.00 0.99 1.00
Mawalleh South
Tx (3&4) 1.00 1.00 1.00 1.01 1.00
Misfah 1.00 1.01 1.01 1.01 1.00
Mobella 1.00 1.00 1.00 1.01 1.01
Mudhaibi 1.00 1.01 1.01 1.00 1.00
Mudhairib 1.00 1.00 1.00 1.00 1.00
Tx (1&2) 1.01 1.01 1.00 1.00 1.01
Muladah
Tx (3&4) 0.99 1.00 1.00 1.00
Muttrah 1.00 1.01 1.01 1.01 1.01
Nakhal 1.01 1.00 1.01 1.01 1.01
Tx (1&2) 1.00 1.00 1.00 1.00 1.00
New Ghubrah
Tx (3&4) 1.00
New Izki 1.00 1.00 1.00 1.00 1.01
Nizwa 1.00 1.00 1.00 1.00 1.00
Old Ghubrah 1.00 1.00
Quriyat 1.00 1.00 1.00 1.00 1.00
Qurum 1.00 1.00 1.01 1.01 1.00
Tx (1&2) 1.00 1.00 1.00 1.01 1.00
Rusail Industrial
Tx (3&4) 1.00 1.00 1.00 1.00 1.01
Rustaq 1.01 1.01 1.00 1.01 1.00
SIP-A 1.00 1.01 1.01 1.01 1.00
Saham 1.00 1.00 1.00 1.00 1.00
Samad 1.00 1.00

Page | 188
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C 5 (continued): Transmission System Voltage Profile at Minimum Demand (2017-2021)


Busbar Voltage at Miniimum Demand (per unit)
Location
2017 2018 2019 2020 2021
MIS
Tx (1&2) 1.00 1.00 1.01 1.00 1.00
Seeb Main
Tx (3&4) 1.02 1.00 1.02 1.00 1.00
Shinas 1.00 1.01 1.01 1.00 1.00
Sinaw 1.00 1.00 1.00
Tx (1&2) 1.00 1.00 1.00 1.01
Sohar Free Zone
Tx (3&4) 1.01 1.01
Tx (1&2) 1.00 0.99 0.99 1.00 1.00
Sohar
Tx (3&4) 1.00 1.00 1.00 1.01 1.00
Sumail Industrial 1.00 1.00
125MVA 1.00 1.00 1.00 1.00 1.00
Sumail
63MVA 1.00 0.99 1.00 1.00 1.01
Sur 1.00 1.00 1.00 1.00 1.00
Suwaiq 1.00 1.00 1.00
Tx (1&2) 1.00 1.00 1.00
Uwaynat
Tx (3&4) 1.00 1.00 1.00
Wadi Adai 1.00 1.00 1.01 1.00 1.00
Wadi Bani Auwf 1.00 1.00
Tx (1&2) 1.00 1.00 1.00 1.01 1.00
Wadi Kabair
Tx (3&4) 1.01 1.00 1.00 1.00 1.00
Wadi Sa'a 1.00 1.01 1.00 1.00 1.00
Yanqul 1.00
Yitti 1.01 1.01 1.00 1.01 1.00
11 kV Busbars
Daghmar 1.00 1.00 1.00 0.99 1.00
Mawalleh North 1.00 1.00
Dhofar Area
132 kV Busbars
Al Qarm 1.01 1.01 1.01 1.00 1.00
Ashoor 1.01 1.01 1.01 1.00 1.00
Awaqad 1.01 1.01 1.01 1.00 1.00
Ittin 1.01 1.01 1.00 1.00 1.00
NPS 1.01 1.01 1.00 1.00 1.00
Salalah Free Zone-1 1.01 1.01 1.00 1.00 1.00
Salalah Free Zone-2 1.01 1.01 1.00 1.00 1.00
S’aadah 1.01 1.01 1.01 1.01 1.00
Thumrait 1.01 1.01 1.01 1.00 1.00
Wind Farm 1.01 1.00

Page | 189
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C 5 (continued): Transmission System Voltage Profile at Minimum Demand (2017-2021)


Busbar Voltage at Miniimum Demand (per unit)
Location
2017 2018 2019 2020 2021
Dhofar Area
33 kV Busbars
Al Qarm 1.01 1.01 1.01 1.00 1.00
Ashoor 1.01 1.01 1.00 1.00 1.01
Awaqad 1.00 1.00 1.00 1.01 1.01
Ittin 1.00 1.00 1.00 1.00 1.00
NPS 1.00 1.00 1.00 1.01 1.01
TX-1&2 1.01 1.01 1.00 1.01
S'aadah
TX-3&4 1.00 1.01 1.00 1.01
TX-1&2 1.00 1.00 1.00 1.01 1.00
Salalah Free Zone
TX-3&4 1.01 1.00 1.01 1.00
Thumrait 1.00 1.01 1.00 1.00 1.01

Page | 190
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C 6: Estimation of Transmission Losses and Generation Margin at Peak Demand (2017-2021)
2017 2018 2019 2020 2021
MW Mvar MW Mvar MW Mvar MW Mvar MW Mvar
Transmission Losses & Generation margin of MITS
Generation 6398 3280 7168 2910 7643 2703 7962 3070 8297 3167
External Infeed 180 0 0 0 0 0 0 0 0 0
Total Generation 6578 3280 7168 2910 7643 2703 7962 3070 8297 3167
Load (Grid+Industrial+Auxiliary+ Desalination) 6473 2127 7067 2327 7538 2482 7848 2584 8183 2690
Compensation Capacitor 0 0 0 0 0
Grid Losses 106 1152 101 583 106 221 113 486 115 477
Grid Active Power Losses as a Percentage of Total Generation (%) 1.61 1.42 1.38 1.43 1.38
Installed Capacity 8251 9366 10834 10834 11158
Generation 6398 7168 7643 7962 8297
Load Growth Rate (%) --- 9.18 6.66 4.12 4.26
Margin 1853 2198 3191 2873 2861
Margin (%) 22.5 23.5 29.5 26.5 25.64
Transmission Losses & Generation Margin of Dhofar System
Generation 582 219 625 217 737 273 780 301 826 331
External Infeed 0 0 0 0 0 0 0 0 0 0
Total Generation 582 219 625 217 737 273 780 301 826 331
Load (Grid+Industrial+Auxiliary+ Desalination) 579 190 623 205 735 242 778 256 823 271
Compensation Capacitor 0 0 0 0 0 0 0 0 0 0
Grid Losses 3 28 2 13 2 31 2 45 3 60
Grid Active Power Losses as a Percentage of Total Generation (%) 0.47 0.30 0.28 0.31 0.33
Dhofar Generation Margin
Installed Capacity 1026 1536 1586 1586 1586
Generation 582 625 737 780 826
Load Growth Rate (%) 11 19 41 49 57
Margin 444 911 848 805 760
Margin (%) 43 59 53 51 48

Page | 191
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C 7: Maximum 3-Phase Short Circuit Fault Levels


Voltage Switchgear Fault Rating Max Three-Phase Short Circuit Ik" (kA)
Substations
(kV) (kA) 2017 2018 2019 2020 2021

MIS
400 kV Busbars
Ibri IPP 400 63 14.47 17.82 17.82 17.99
Jahloot 400 63 10.28 10.90 11.03 11.03 12.01
Misfah 400 63 12.35 12.24 12.24 14.67
New Izki 400 63 7.00 14.90 15.35 15.35 16.51
Qabel 400 63 14.31 14.31 15.02
Rusail Industrial 400 63 13.43
SIS 400 63 16.82 16.82 16.84
Sohar Free Zone 400 63 20.12 20.12 20.14
Sohar-3 IPP 400 63 20.26 20.26 20.27
Sur PS 400 63 14.43 16.94 17.24 17.24 18.17
220 kV Busbars
Airport Height 220 40 23.49 26.02 24.86 24.86 31.43
Al Filaj 220 40 30.46 31.87 31.43 31.43 33.83
Al Hamriyah 220 50 11.11 11.36 12.41 12.41 14.31
Alw(UAE) 220 50 22.07 23.50 25.00 25.00 25.01
Barka PS 220 40 31.80 33.03 32.65 32.65 34.69
Barka-3 PS 220 50 14.38 15.16 14.88 14.88 16.23
Blue City 220 40 17.11 17.37 17.25 17.25 17.77
Ibri 220 50 4.48 11.74 12.38 12.38 12.38
Ibri IPP 220 50 17.30 18.95 18.95 18.99
Jahloot 220 50 16.78 17.39 17.80 17.80 20.64
MIS 220 40 15.51 15.65 15.74 15.74 16.00
MSQ 220 50 15.90 17.45 16.61 16.61 20.22
Mahadha 220 40 18.59 22.97 29.33 29.33 29.34
Misfah 220 50 23.32 28.62 26.58 26.58 39.62
Misfah IPP 220 50 38.60
Mobella 220 50 28.46 27.91 27.91 30.95
New Izki 220 50 9.89 13.11 13.01 13.01 16.80
KIS 220 50 16.68 16.68 27.89
SIP-A 220 40 24.71 26.12 27.88 27.88 36.80
SIS 220 40 27.06 28.34 36.73 36.73 33.76
Sohar Free Zone 220 50 20.25 20.78 33.74 33.74 29.80
Sohar-1 PS 220 40 27.40 27.78 29.79 29.79 31.43

Page | 192
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C 7 (continued): Maximum 3-Phase Short Circuit Fault Levels


Voltage Switchgear Fault Rating Max Three-Phase Short Circuit Ik" (kA)
Substations
(kV) (kA) 2017 2018 2019 2020 2021

MIS
Sohar-2 PS 220 50 18.81 19.21 27.82 27.82 27.84
Sur 220 50 24.64 26.13 26.09 26.09 26.55
Sur PS 220 50 35.67 38.97 39.06 39.06 40.14
132 kV Busbars
A'salam 132 31.5 20.50 20.79 20.69 20.69 21.42
Adam 132 40 6.37 6.77 6.75 6.75 6.72
Airport Height 132 31.5 20.91 14.63 14.40 14.40 20.29
Al Falaj 132 31.5 13.36 13.55 17.92 17.92 21.91
Al Filaj 132 31.5 24.53 25.28 25.56 25.56 26.47
Al Hamriyah 132 40 13.90 14.11 18.67 18.67 23.42
Al Hayl 132 31.5 2.78 3.87 3.90 3.75 3.74
Al Kamil 132 31.5 12.97 12.51 16.15 16.15 16.21
Amerat 132 40 12.70 12.88 15.26 15.26 17.17
Ayjah 132 40 8.84 8.92 8.95 8.95 8.98
Bahla 132 31.5 6.77 7.49 7.44 7.44 7.39
Barka Main 132 31.5 22.22 23.37 23.45 23.45 24.27
Bedyah 132 40 16.83 16.83 16.93
Birkat Al Mouz 132 40 17.12 17.12 16.75
Bousher 132 31.5 17.79 17.31 18.84 18.84 22.23
Bureimi 132 31.5 8.95 9.26 12.74 12.74 12.69
Bureimi Industrial 132 40 9.24 9.57 12.75 12.75 12.70
Daghmar 132 40 6.37 6.42 6.65 6.65 6.93
Dank 132 31.5 3.70 5.90 5.97 5.97 5.96
Dil Abdusalam (DAS) 132 40 11.81 17.07 17.07 17.07
Dreez 132 40 4.40 7.93 8.05 8.05 8.04
Falaj Al Qabail 132 40 15.10
Ghala 132 40 20.10 14.24 14.02 14.02 19.54
Ghala Heights 132 40 13.35 13.35 18.26
Halban 132 40 22.57 22.57 23.40
Ibra 132 40 6.57 6.10 11.88 11.88 11.96
Ibri 132 31.5 5.67 13.29 13.64 13.64 13.62
Izki 132 31.5 17.12 19.60 18.95 18.95 18.30
JBB Ali 132 31.5 5.87 5.78 6.45 6.45 6.46
JBB Hasan 132 40 11.15 11.07 12.10 12.10 12.14
Jahloot 132 31.5 14.82 15.08 16.42 16.42 18.28

Page | 193
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C 7 (continued): Maximum 3-Phase Short Circuit Fault Levels


Voltage Switchgear Fault Rating Max Three-Phase Short Circuit Ik" (kA)
Substations
(kV) (kA) 2017 2018 2019 2020 2021
MIS
Jebreen 132 31.5 8.89 12.77 12.72 12.72 12.62
Khaborah 132 31.5 11.60 11.38 15.98 15.98 16.06
Khadra 132 40 13.38 13.24 15.23 15.23 15.35
Khoudh 132 40 21.22 21.95
Khuwair 132 40 22.83
Liwa 132 31.5 19.62 19.93 20.38 20.38 20.19
MIS 132 31.5 19.38 19.43 20.58 20.58 20.88
MSQ-A 132 31.5 18.13 17.75
MSQ-B 132 31.5 13.70 13.89
MSQ 132 31.5 19.98 19.98 23.86
Madinat Barka 132 40 19.73 20.09 20.02 20.02 20.53
Madinat Ibri 132 40 10.80
Madinat Nizwa 132 40 10.89 12.86 12.73 12.73 12.59
Madinat Shinas 132 40 8.05 9.36 9.36 9.32
Mahadha 132 31.5 19.13 20.58 20.43 20.43 20.29
Manah 132 31.5 13.49 15.42 15.29 15.29 15.17
Mawalleh North 132 40 19.12 13.75 13.55 13.55 18.63
Mawalleh South-A 132 31.5 21.04 21.25 20.57 21.18 21.90
Mawalleh South-B 132 40 20.66 0.00 0.00 0.00 0.00
Misfah 132 31.5 15.15 15.26 14.91 14.91 22.35
Mobella 132 31.5 20.54 22.91 22.78 22.78 23.67
Mudhaibi 132 31.5 11.13 8.40 10.80 10.80 10.76
Mudhairib 132 31.5 9.56 8.60 20.18 20.18 20.35
Muladah 132 31.5 17.47 17.55 18.90 18.90 19.21
Muttrah 132 31.5 13.46 13.65 18.01 18.01 22.20
Nakhal 132 31.5 12.24 12.43 14.31 14.31 14.58
New Ghubrah-A 132 40 17.91 17.41
New Ghubrah-B 132 40 12.44 12.59
New Ghubrah 132 40 18.95 18.95 22.37
New Izki 132 40 17.02 19.56 19.45 19.45 18.90
KIS 132 40 20.05 20.05 20.13
Niheda(PDO) 132 31.5 4.20 4.28 4.27 4.27 4.27
Nizwa 132 31.5 14.13 17.64 17.39 17.39 17.15
Old Ghubrah 132 26 17.86 17.34
Qabel 132 31.5 21.35 21.35 21.60
Quriyat 132 31.5 6.66 6.71 6.96 6.96 7.28

Page | 194
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C 7 (continued): Maximum 3-Phase Short Circuit Fault Levels


Voltage Switchgear Fault Rating Max Three-Phase Short Circuit Ik" (kA)
Substations
(kV) (kA) 2017 2018 2019 2020 2021
MIS
Qurum 132 31.5 12.99 13.16 17.64 17.64 22.61
Rusail 132 31.5 22.59 22.82 22.04 22.04 22.79
Rusail Industrial 132 31.5 22.55 22.80 22.02 22.02 22.80
Rustaq 132 31.5 9.31 9.33 12.02 12.02 12.16
SIP-A 132 31.5 15.70 20.15 20.73 20.73 20.74
SIS 132 31.5 22.84 22.80 24.88 24.88 24.43
Saham 132 31.5 14.70 14.60 17.43 17.43 17.32
Samad 132 40 6.33 6.33 6.31
Seeb Main 132 31.5 20.54 19.30 19.22 19.22 19.84
Shinas 132 31.5 11.89 12.00 15.17 15.17 15.07
Sinaw 132 40 9.61 10.95 10.95 10.86
Sohar 132 31.5 18.45 17.77 16.63 16.63 15.23
Sohar Free Zone 132 40 21.24 21.61 22.05 22.05 21.83
Sohar Refinery 132 31.5 15.46 19.75 20.30 20.30 20.31
Sumail 132 31.5 14.33 14.75 12.03 12.03 11.65
Sumail Industrial 132 40 12.86 12.86 12.57
Sur 132 31.5 18.29 18.64 18.80 18.80 18.92
Sur-2 132 40 18.31 18.67 18.83 18.83 18.95
Suwaiq 132 40 16.86 18.11 18.11 18.32
Uwaynat 132 40 18.32 18.45 18.45 17.65
Wadi Adai 132 31.5 13.55 13.74 18.41 18.41 22.34
Wadi Al Jazzi 132 31.5 25.56 25.94 20.04 20.04 19.37
Wadi Bani Auwf 132 40 10.38 10.38 10.49
Wadi Kabair 132 40 13.30 13.49 17.66 17.66 21.78
Wadi Sa'a 132 31.5 9.45 9.79 9.76 9.76 9.73
Yanqul 132 40 4.29 4.29
Yitti 132 31.5 8.64 8.73 9.17 9.17 9.72
33 kV busbars
Tx
33 25 20.72 20.80 20.77 20.77 20.95
(1&2)
A'salam
Tx
33 25 20.77 20.77 20.95
(3&4)
Adam 33 25 8.80 14.04 14.01 14.01 13.98
Tx
33 25 20.92 18.90 18.81 18.81 20.75
(1&2)
Airport Height
Tx
33 25 18.81 18.81 20.75
(3&4)
Al Falaj 33 25 17.65 17.73 19.27 19.27 20.26
Al Hayl 33 25 6.07 7.18 7.20 7.07 7.07

Page | 195
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C 7 (continued): Maximum 3-Phase Short Circuit Fault Levels


Voltage Switchgear Fault Rating Max Three-Phase Short Circuit Ik" (kA)
Substations
(kV) (kA) 2017 2018 2019 2020 2021

MIS
Tx
33 25 17.63 17.72 18.72 18.72 19.38
(1&2)
Amerat
Tx
33 25 18.72 18.72 19.38
(3&4)
Ayjah 33 25 15.74 15.81 15.84 15.84 15.86
Bahla 33 25 13.82 14.53 14.49 14.49 14.44
Tx (3) 33 25 12.48
Barka Main Tx
33 25 22.35 22.63 22.64 22.64 22.83
(1&2)
Barka-3 PS 33 25 21.65 21.57 21.57 21.96
Bedyah 33 25 20.11 20.11 20.15
Birkat Al Mouz 33 25 19.92 19.92 19.79
Blue City 33 31.5 26.95 27.04 27.00 27.00 27.30
Tx
33 25 20.72 20.55 21.06 21.06 22.00
(1&2)
Bousher
Tx
33 25 20.05 19.89 20.36 20.36 21.23
(3&4)
Bureimi 33 25 15.75 15.98 18.07 18.07 18.04
Tx
33 25 15.80 16.03 17.89 17.89 17.87
Bureimi (1&2)
Industrial Tx
33 25 17.89 17.89 17.87
(3&4)
Dank 33 25 7.95 9.96 10.00 10.00 10.00
Dil Abdusalam(DAS) 33 25 17.73 20.04 20.04 20.04
Dreez 33 25 11.02 15.28 15.39 15.39 15.38
Falaj Al Qabail BB 33 25 19.72
Tx
33 25 18.52 18.52 20.42
(1&2)
Ghala Heights
Tx
33 25 18.52 18.52 20.42
(3&4)
Tx
33 25 20.96 18.92 18.83 18.83 20.80
(1&2)
Ghala
Tx
33 25 18.83 18.83 20.80
(3&4)
Tx
33 25 22.20 22.20 22.40
(1&2)
Halban
Tx
33 25 22.20 22.20 22.40
(3&4)
Ibra 33 25 13.54 13.03 17.57 17.57 17.61

Page | 196
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C 7 (continued): Maximum 3-Phase Short Circuit Fault Levels


Voltage Switchgear Fault Rating Max Three-Phase Short Circuit Ik" (kA)
Substations
(kV) (kA) 2017 2018 2019 2020 2021

MIS
125MVA 33 25 12.57 18.32 18.48 18.48 18.47
Ibri
63MVA 33 25 10.88 15.01 15.12 15.12
Izki 33 25 20.41 21.20 21.01 21.01 20.81
JBB Ali 33 25 12.93 12.81 13.59 13.59 13.60
JBB Hasan 33 25 17.63 17.58 18.20 18.20 18.22
Jahloot 33 25 18.46 18.56 19.04 19.04 19.62
Jebreen 33 25 16.13 18.70 18.67 18.67 18.61
Khaborah 33 25 17.55 17.42 19.57 19.57 19.62
Tx (1&2) 33 25 18.54 18.48 19.35 19.35 19.40
Khadra
Tx (3&4) 33 25 18.48 19.35 19.35 19.40
Tx (1&2) 33 25 21.86 22.05
Khoudh
Tx (3&4) 33 25 21.86 22.05
Khuwair 33 25 22.26
Tx (1&2) 33 25 20.58 20.67 20.78 20.78 20.73
Liwa
Tx (3&4) 33 25 20.58 20.67 20.78 20.78 20.73
MIS 33 25 20.52 20.53 20.84 20.84 21.20
Tx (1&2) 33 25 20.73 20.60 21.29 21.29 22.26
MSQ
Tx (3&4) 33 25 12.16 20.70 21.40 21.40 22.38
Tx (1&2) 33 25 21.34 21.44 21.42 21.42 21.56
Madinat Barka
Tx (3&4) 33 25 21.44 21.42 21.42 21.56
Madinat Ibri 33 25 17.53
Madinat Nizwa 33 25 17.19 18.29 18.22 18.22 18.16
Madinat Shinas 33 25 15.09 16.15 16.15 16.12
Mahadha 33 25 8.51 8.57 8.56 8.56 8.56
Mawalleh North 33 25 19.01 18.91 18.91 20.90
Mawalleh Tx (1&2) 33 25 20.67 20.72 20.55 20.70 20.87
South Tx (3&4) 33 25 21.70 21.76 21.57 21.73 21.92
Misfah 33 25 19.73 19.77 19.62 19.62 22.02
Mobella 33 25 20.83 21.37 21.35 21.35 21.58
Mudhaibi 33 25 17.60 15.60 17.39 17.39 17.36
Mudhairib 33 25 16.40 15.66 21.15 21.15 21.20
Tx (1&2) 33 25 19.95 19.98 20.39 20.39 20.47
Muladah
Tx (3&4) 33 25 19.86 19.88 20.29 20.29 20.38
Muttrah 33 25 18.95 19.04 20.79 20.79 22.00
Nakhal 33 25 17.81 17.91 18.79 18.79 19.07
Tx (1&2) 33 25 20.78 20.61 21.12 21.12 22.06
New Ghubrah
Tx (3&4) 33 25 21.20 22.16

Page | 197
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C 7 (continued): Maximum 3-Phase Short Circuit Fault Levels


Voltage Switchgear Fault Rating Max Three-Phase Short Circuit Ik" (kA)
Substations
(kV) (kA) 2017 2018 2019 2020 2021
MIS
New Izki 33 25 20.37 21.19 21.16 21.16 20.99
Nizwa 33 25 18.77 20.09 20.01 20.01 19.93
Old Ghubrah 33 25 15.47 15.42
Quriyat 33 25 13.69 13.74 14.00 14.00 14.31
Qurum 33 25 18.71 18.80 20.67 20.67 22.09
Rusail Tx (1&2) 33 25 21.57 21.62 21.44 21.44 21.62
Industrial Tx (3&4) 33 25 21.57 21.62 21.44 21.44 21.62
Rustaq 33 25 20.10 20.13 22.88 22.88 23.00
Saham 33 25 18.95 18.91 19.94 19.94 19.91
Samad 33 25 9.46 9.46 9.45
Tx (1&2) 33 25 21.57 21.22 21.20 21.20 21.43
Seeb Main
Tx (3&4) 33 25 12.35 12.22 21.31 21.31 21.55
SIP-A 33 25 19.33 20.72 20.87 20.87 20.87
Shinas 33 25 17.77 17.84 19.32 19.32 19.28
Sinaw 33 25 16.33 17.23 17.23 17.17
Sohar Free Tx (1&2) 33 25 21.87 21.97 22.07 22.07 22.02
Zone Tx (3&4) 33 25 22.07 22.07 22.02
Tx (1&2) 33 25 20.64 20.43 20.04 20.04 19.50
Sohar
Tx (3&4) 33 25 20.16 19.96 19.58 19.58 19.07
Sumail Industrial 33 25 18.74 18.74 18.59
125MVA 33 25 19.29 19.48 18.13 18.13 17.91
Sumail
63MVA 33 25 12.84 12.93 12.32 12.32 12.22
Sur 33 25 20.59 20.70 20.75 20.75 20.79
Suwaiq 33 25 19.96 20.38 20.38 20.45
Tx (1&2) 33 25 20.45 20.49 20.49 20.23
Uwaynat
Tx (3&4) 33 25 20.45 20.49 20.49 20.23
Wadi Adai 33 25 18.67 18.76 20.54 20.54 21.60
Wadi Bani Auwf 33 25 17.24 17.24 17.32
Tx (1&2) 33 25 18.87 18.96 20.67 20.67 21.89
Wadi Kabair
Tx (3&4) 33 25 18.26 18.35 19.94 19.94 21.07
Wadi Sa'a 33 25 11.52 11.64 11.63 11.63 11.62
Yanqul 33 25 10.86 10.86
Yitti 33 25 15.84 15.91 16.27 16.27 16.69
Dhofar
Al Qarm 132 31.5 13.04 15.69 15.74 15.70 15.70
Ashoor 132 31.5 17.25 20.08 20.13 20.09 20.09
Awaqad 132 31.5 12.18 16.65 16.73 16.65 16.65

Page | 198
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C 7 (continued): Maximum 3-Phase Short Circuit Fault Levels


Voltage Switchgear Fault Rating Max Three-Phase Short Circuit Ik" (kA)
Substations
(kV) (kA) 2017 2018 2019 2020 2021
Dhofar
Ittin 132 31.5 12.97 16.96 17.04 16.97 16.97
NPS 132 31.5 14.63 24.17 24.40 24.18 24.18
Salalah Free BB-1 132 14.63 24.41 24.64 24.43 24.43 24.85
Zone BB-2 132 14.63 24.41 24.64 24.43 24.43 24.85
S’aadah 132 11.58 14.50 14.56 14.51 14.51 14.87
Thumrait 132 31.5 6.66 7.28 7.28 7.28 7.28
Wind Farm 132 31.5 4.95 4.95 4.95
Al Qarm 33 25 10.18 10.59 10.60 10.59 10.59
Ashoor 33 25 16.71 17.42 17.43 17.42 17.42
Awaqad 33 25 14.93 16.54 16.57 16.54 16.54
Ittin 33 25 15.29 16.65 16.66 16.64 16.64
NPS 33 25 13.41 14.42 14.44 14.42 14.42
TX-1&2 33 14.66 15.85 15.87 15.85 15.85 15.98
S'aadah
TX-3&4 33 14.66 15.85 15.87 15.85 15.85 15.98
Salalah Free TX-1&2 33 15.90 18.25 18.29 18.25 18.25 18.32
Zone TX-3&4 33 15.90 18.25 18.29 18.25 18.25 18.32
Thumrait 33 25 5.85 5.98 5.96 5.96 12.12

Page | 199
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C 8: Maximum 1-Phase Short Circuit Fault Levels


Max Single-Phase Short Circuit Ik"
Substations Voltage (kV) Switchgear Fault Rating (kA) (kA)
2017 2018 2019 2020 2021
MIS
400 kV Busbars
Ibri IPP 400 63 16.01 20.62 20.62 20.78
Jahloot 400 63 9.79 10.16 10.29 10.29 10.88
Misfah 400 63 10.82 10.94 10.95 15.91
New Izki 400 63 6.06 12.39 13.15 13.16 14.42
Qabel 400 63 12.49 12.49 12.96
Rusail Industrial 400 63 14.55
SIS 400 63 16.22 16.22 16.23
Sohar Free Zone 400 63 23.57 23.57 23.59
Sohar-3 IPP 400 63 23.77 23.77 23.79
Sur PS 400 63 16.29 18.45 18.89 18.89 19.67
220 kV Busbars
Airport Height 220 40 22.69 24.20 24.75 24.76 31.45
Al Filaj 220 40 32.01 33.98 33.95 33.95 35.86
Al Hamriyah 220 50 12.07 12.27 13.20 13.21 14.53
Alw(UAE) 220 50 20.72 21.57 22.55 22.55 22.55
Barka PS 220 40 36.01 37.39 37.16 37.16 38.98
Barka-3 PS 220 50 15.90 17.47 17.22 17.22 18.49
Blue City 220 40 16.33 16.57 16.54 16.54 16.86
Ibri 220 50 5.33 11.91 12.43 12.44 12.04
Ibri IPP 220 50 18.11 20.07 20.07 20.04
Jahloot 220 50 17.41 17.86 18.24 18.24 20.24
MIS 220 40 14.46 14.92 15.27 15.27 15.44
MSQ 220 50 15.79 17.06 16.83 16.93 19.84
Mahadha 220 40 16.01 18.25 24.13 24.13 24.14
Misfah 220 50 20.99 25.95 25.23 25.26 44.52
Misfah IPP 220 50 44.00
Mobella 220 50 27.89 28.25 28.25 30.48
New Izki 220 50 9.92 13.34 13.46 13.47 13.58
KIS 220 50 14.03 14.03 14.09
SIP-A 220 40 29.97 31.50 33.25 33.25 33.26
SIS 220 40 23.36 24.47 34.10 34.10 34.15

Page | 200
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C 8 (continued): Maximum 1-Phase Short Circuit Fault Levels


Max Single-Phase Short Circuit Ik"
Switchgear Fault Rating (kA)
Substations Voltage (kV)
(kA)
2017 2018 2019 2020 2021
MIS
400 kV Busbars
Sohar Free Zone 220 50 21.52 21.96 37.00 37.00 37.02
Sohar-1 PS 220 40 32.80 33.24 35.20 35.20 35.21
Sohar-2 PS 220 50 20.86 21.21 29.77 29.77 29.78
Sur 220 50 22.69 23.54 23.54 23.54 23.80
Sur PS 220 50 43.00 46.29 46.54 46.54 47.60
132 kV Busbars
A'salam 132 31.5 26.18 25.75 26.88 26.88 27.94
Adam 132 40 6.55 7.88 7.86 7.86 7.84
Airport Height 132 31.5 26.57 18.42 19.59 19.59 26.81
Al Falaj 132 31.5 17.65 17.87 23.10 23.12 27.04
Al Filaj 132 31.5 28.13 28.89 29.43 29.43 30.93
Al Hamriyah 132 40 18.25 18.49 23.91 23.93 28.69
Al Hayl 132 31.5 3.42 4.44 4.47 4.64 4.64
Al Kamil 132 31.5 14.82 14.42 17.64 17.64 17.69
Amerat 132 40 14.19 14.34 17.94 17.94 19.67
Ayjah 132 40 9.83 9.90 9.92 9.92 9.95
Bahla 132 31.5 7.89 8.53 8.49 8.49 8.46
Barka Main 132 31.5 25.61 25.75 26.48 26.48 27.60
Bedyah 132 40 17.63 17.63 17.71
Birkat Al Mouz 132 40 18.49 18.49 18.22
Bousher 132 31.5 23.50 22.86 24.46 24.87 28.93
Bureimi 132 31.5 10.95 11.25 15.73 15.73 15.68
Bureimi Industrial 132 40 11.26 11.58 15.82 15.82 15.77
Daghmar 132 40 7.41 7.60 7.82 7.82 8.08
Dank 132 31.5 4.65 6.78 6.84 7.03 7.02
Dil Abdusalam (DAS) 132 40 13.05 17.53 17.53 17.55
Dreez 132 40 5.66 9.18 9.30 9.30 9.26
Falaj Al Qabail 132 40 16.31
Ghala 132 40 25.48 17.93 19.11 19.11 25.91
Ghala Heights 132 40 18.14 18.14 24.12
Halban 132 40 27.47 27.47 28.61
Ibra 132 40 7.90 7.44 12.68 12.68 12.75
Ibri 132 31.5 7.56 16.14 16.51 16.52 15.82

Page | 201
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C 8 (continued): Maximum 1-Phase Short Circuit Fault Levels


Max Single-Phase Short Circuit
Voltage Ik" (kA)
Substations Switchgear Fault Rating (kA)
(kV)
2017 2018 2019 2020 2021
MIS
Izki 132 31.5 18.40 20.38 20.37 20.37 19.90
JBB Ali 132 31.5 7.01 6.92 7.55 7.55 7.56
JBB Hasan 132 40 12.05 11.99 12.78 12.78 12.81
Jahloot 132 31.5 17.86 18.12 19.51 19.51 21.26
Jebreen 132 31.5 10.14 13.64 13.62 13.62 13.79
Khaborah 132 31.5 12.59 12.75 16.78 16.78 16.84
Khadra 132 40 14.51 16.00 17.89 17.89 18.00
Khoudh 132 40 25.66 26.83
Khuwair 132 40 29.62
Liwa 132 31.5 23.67 24.06 25.20 25.20 25.00
MIS 132 31.5 21.65 22.52 23.65 23.65 23.92
MSQ-A 132 31.5 23.30 23.01
MSQ-B 132 31.5 16.55 16.74
MSQ 132 31.5 26.22 26.49 30.82
Madinat Barka 132 40 20.58 22.82 22.79 22.79 23.23
Madinat Ibri 132 40 11.89
Madinat Nizwa 132 40 12.34 14.00 13.95 13.95 13.85
Madinat Shinas 132 40 9.28 10.48 10.48 10.44
Mahadha 132 31.5 19.78 20.90 22.21 22.21 22.10
Manah 132 31.5 15.93 17.81 17.71 17.71 17.60
Mawalleh North 132 40 24.00 17.31 18.27 18.27 24.37
Mawalleh South-A 132 31.5 26.97 27.23 26.40 27.47 28.42
Mawalleh South-B 132 40 26.39 0.00 0.00 0.00 0.00
Misfah 132 31.5 16.10 16.19 15.90 15.93 25.36
Mobella 132 31.5 25.91 28.00 29.25 29.25 30.25
Mudhaibi 132 31.5 12.17 9.81 12.34 12.34 12.30
Mudhairib 132 31.5 11.22 10.33 22.01 22.01 22.17
Muladah 132 31.5 20.64 20.84 22.13 22.13 22.42
Muttrah 132 31.5 17.82 18.05 23.27 23.28 27.48
Nakhal 132 31.5 12.78 12.92 14.95 14.95 15.14
New Ghubrah-A 132 40 23.66 23.00
New Ghubrah-B 132 40 14.15 14.29
New Ghubrah 132 40 24.59 25.02 29.13
New Izki 132 40 18.66 21.37 21.44 21.44 21.11

Page | 202
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C 8 (continued): Maximum 1-Phase Short Circuit Fault Levels


Max Single-Phase Short Circuit Ik"
Voltage (kA)
Substations Switchgear Fault Rating (kA)
(kV)
2017 2018 2019 2020 2021
MIS
KIS 132 40 19.50 19.50 19.55
Niheda(PDO) 132 31.5 3.58 3.62 3.62 3.62 3.62
Nizwa 132 31.5 17.07 20.43 20.50 20.50 20.30
Old Ghubrah 132 26 23.57 22.90
Qabel 132 31.5 22.88 22.88 23.13
Quriyat 132 31.5 8.01 8.16 8.41 8.41 8.72
Qurum 132 31.5 15.96 16.13 21.09 21.13 25.74
Rusail 132 31.5 29.04 29.33 28.37 28.73 29.58
Rusail Industrial 132 31.5 29.00 29.30 28.34 28.70 29.60
Rustaq 132 31.5 11.10 11.13 14.07 14.07 14.20
SIP-A 132 31.5 18.81 23.94 24.49 24.49 24.49
SIS 132 31.5 22.61 23.36 26.04 26.04 25.72
Saham 132 31.5 15.05 15.49 17.62 17.62 17.55
Samad 132 40 6.90 6.90 6.89
Seeb Main 132 31.5 26.36 23.97 24.93 24.93 25.65
Shinas 132 31.5 12.85 13.69 17.25 17.25 17.16
Sinaw 132 40 10.92 12.08 12.08 12.01
Sohar 132 31.5 20.47 20.24 19.07 19.07 18.11
Sohar Free Zone 132 40 25.59 26.01 27.92 27.92 27.68
Sohar Refinery 132 31.5 18.49 23.42 23.95 23.95 23.95
Sumail 132 31.5 15.79 16.14 13.92 13.92 13.67
Sumail Industrial 132 40 14.00 14.00 13.91
Sur 132 31.5 20.63 20.94 21.08 21.08 21.19
Sur-2 132 40 20.66 20.97 21.10 21.10 21.21
Suwaiq 132 40 19.15 20.22 20.22 20.41
Uwaynat 132 40 20.97 21.17 21.17 20.49
Wadi Adai 132 31.5 17.61 17.83 23.44 23.47 26.68
Wadi Al Jazzi 132 31.5 28.28 28.63 17.00 17.00 16.49
Wadi Bani Auwf 132 40 11.62 11.62 11.72
Wadi Kabair 132 40 17.49 17.71 22.57 22.58 26.74
Wadi Sa'a 132 31.5 9.32 9.55 9.60 9.60 9.58
Yanqul 132 40 5.62 5.61

Page | 203
Five-Year Annual Transmission Capability Statement (2017-2021)

Table C 8 (continued): Maximum 1-Phase Short Circuit Fault Levels

Voltage Max Single-Phase Short Circuit Ik" (kA)


Substations Switchgear Fault Rating (kA)
(kV) 2017 2018 2019 2020 2021
MIS
Yitti 132 31.5 9.81 9.88 10.26 10.26 10.71
Dhofar
Al Qarm 132 31.5 13.33 15.04 15.04 15.03 15.04
Ashoor 132 31.5 21.95 24.86 24.87 24.85 24.85
Awaqad 132 31.5 14.05 17.74 17.76 17.74 17.74
Ittin 132 31.5 14.29 17.28 17.28 17.26 17.37
NPS 132 31.5 18.80 29.97 30.04 29.96 29.96
Salalah Free BB-1 132 18.83 30.62 30.69 30.60 30.60 31.05
Zone BB-2 132 18.83 30.62 30.69 30.60 30.60 31.05
S’aadah 132 40 14.03 16.72 16.73 16.71 16.71
Thumrait 132 31.5 6.21 6.55 6.50 6.50 8.08
Wind Farm 132 31.5 5.00 5.00 5.02

Page | 204
Five-Year Annual Transmission Capability Statement (2017-2021)

DIgSILENT
Sohar Aluminum PS
~ ~
Sohar-1 PS G
1.00
180.00
10.13
G
0.00
0.00
Sohar-2 PS Barka-2 PS Barka-1 PS Barka-3 PS 0.42
1.00
-137.66
0.41
1.00
-136.16
0.41
1.00
-114.78
0.42
1.00
-112.25
0.41
1.00
-125.75
0.42
1.00
-126.10
40.06 -3.84
~ ~ 1.28 ~ ~ ~ ~ ~ ~ ~ ~ ~ ~
G G -1.00 G G G G G G G G G G

-460.82
0 0 0 0 0 0 0 0

367.36
124.91
0.94

-65.56
29.19

34.40
-179.58 472.98 0.86 0.84 0.83 0.82 0.85 0.95 0.95 -1.00 -1.00 0.95 -1.00 -1.00 0.95 -1.00 -1.00 -1.00 0.95 -1.00 -1.00 -1.00 0.95 -1.00 -1.00 0.95 -1.00 -1.00
0.89 0.83 1.10 0.87 0.84 0.86 270.00 205.00 220.00 220.00
375.00 210.00 244.00 240.00 245.24 250.00 160.00 175.00 81.77 83.00 -0.00
1.00 -0.00
1.00 119.00 -0.00 -0.00 157.00 -0.00
1.00 -0.00 -0.00 102.00 -0.00
1.00 -0.00 -0.00 98.00 -0.00
1.00 -0.00
1.00 97.00 -0.00 -0.00
42.94 -0.00 240.00 157.46 158.79 109.47 123.11 125.65 75.79 27.28 -0.00 -0.00 39.11 0.00 0.00 51.60 -0.00 0.00 0.00 33.53 0.00 0.00 0.00 32.21 0.00 -0.00 31.88 0.00 0.00
189.39 138.40 135.67
0.87 154.23 144.35 38.33 -367.36 460.82 69.03 0.00 0.00 0.00 0.00 0.00 0.00
1.00 -0.00 59.54 72.99 60.96 76.42 74.90 72.49 3 0.00 3 0.00 3 0.00 3 0.00 3 0.00 3 0.00
78.23 91.46 -3.84 86.97
244.00 88.87 82.37 -124.91 65.56 -0.00 0.00 0.00 -0.00 -0.00 -0.00
180.00 7 40.79 49.77 0.85 0.00 0.00 0.00 0.00 0.00 0.00
10.13 8 0.03
1.58 135.67 -472.98 205.00
42.94 0.14 87.93 0.95 0.94
4.41 -245.24 125.65 220.00
41.19 0.86 0.84 0.83 0.82 75.73 220.00 33.09 -0.95 -0.95 -0.95 -0.95
1.58 18 75.79 81.77 32.89 32.91
0.84 0.86 270.00 250.00 160.00 175.00 1.00 -157.00 33.06 -102.00 -98.00 33.01 -97.00
20 157.46 158.79 109.47 123.11 73.29 66.53 1.00 -51.60 32.87 -33.53 1.00 -32.21 -31.88
240.00 240.00 -167.66 1.00 1.00
0.89 0.83 60.40 74.04 60.96 76.42 -0.95 -0.95 -166.16 68.20 1.00 -142.25 43.49 -155.75 43.44 43.12
375.00 210.00 230.52 154.23 144.35 -83.00 -119.00 -156.10
89.85 79.38 -0.90 16 -0.89 16 -0.86 16 -0.86 16 -0.91 17 -0.98 17 -0.97 0.91 0.92 11 -144.78 14 0.92 10 0.92
189.39 138.40 1.05 215.18 -365.51 367.45 -460.68 -269.58 -250.00 -159.75 -174.70 141.55 -344.13 -27.28
83.31 -39.11
119.27 345.35 -345.35 98.22 -96.90 97.22
13 11
74.69
-0.93
15 91.26
-0.90
17
-6.56 1.00
0.00
-0.00
179.45
-5.51
37.47
1.00
0.00
-0.00
-0.93
-243.53 20 -0.90 19 -0.91
0.98
-9.74
-118.38
29.19
76.23
40.79
Blue City -113.07
49.77
220.73
1.00
-6.20
-129.15
60.40
-125.90
74.04
-94.11
60.96
-101.86
76.42
-204.53
-95.96
75.73
-219.52
-47.83
73.29
-219.52
-55.94
66.53
-4.90
19.47
-83.95
48.03
129.81
0.98
-11.55
73.88
37.95
73.88
52.75
50.90
52.75
53.98
48.03
-53.98
47.18
130.42
0.99
-11.21
0.91 0.92
40.66
43.44
129.20
0.98
-1.82
-39.37
18.26
7 40.81
43.12
-374.36 -209.55 -179.42 473.07 157.40 102.23
134.20
1.02
Shinas -143.59
74.69
-103.48
91.26
-5.34
37.47
-96.10
87.93 228.21
1.04
-239.54
-113.00
89.85
-239.53
-108.31
79.38
219.34
41.19
MIS 73.01
68.20
Mawalleh South-A 42.31
43.49
Al Falaj
-13.49 -7.88 0.84 225.94 229.30 433.03 134.33
378.30 1.03 129.10
243.98 510.96 1.04 101.80 1.02
-2.00 0.98
230.49
1.05
-12.79
-125.60
9.59
46.02
20
0.93
93.23
36.84
0.95
6.00
1.97
0.95
25.00
8.22
510.60
268.24
41.86
266.56
41.74
0.95
6.00
1.97
4.00 0.95
6.00
1.97
36.64
-432.81
Seeb Main Mawalleh South-B -259.63
-115.32
37.23
11.68 -62.93
-24.94
23.63
Wadi Adai 61.61
23.65
11.54
-61.60
-23.91
11.54
-1.90
-35.62
-16.91
13.44
-112.30 0.92 -6.61 0.95 0.95 528.56 441.31 0.95 129.27 32.81 14 31.22 -195.32
-48.22 112.30 14 31.00 6.00 153.87 182.47 6.00 0.98 -0.89 0.99 -0.95 36.64
20.54 48.22 10.19 1.97 42.88 37.34 1.97 -14.83 -377.84 -159.25 -93.00
32.86 48.08 -197.85 -30.57 432.81
1.00 -0.95 195.32
46.02 31.22 34.63
-167.98 -112.00
-36.81 130.03 134.58
48.08 1.00 -510.65 219.39 1.02
0.00 0.99
-264.13 1.00
1.00
115.60
18.73
0.90
173.47
-0.95 9
88.76
96.56
-1.00
0.00
-0.00
3 0.95
93.00
-1.00
-0.00
-1.00
-0.00
-11.94
Madinat Barka 41.74 -0.97 Misfah 11.68
Wadi Kabair

34.63
-177.37
-429.67
20.53 82.57 23.08 0.00
0.00 30.57 0.00 0.00
-1.00 -1.00 0.95 0.00
-1.00 3 -173.00 0.94
-0.00 78.91
-56.86 32.68 0.00 510.65
-0.00 -0.00 112.00 -0.00 0.99 0 0 264.13 32.12 129.14
0.00 0.00 36.81 0.00
0.00 78.91 12.06 0.98
-171.88 197.89 0.93 -245.02 45.22 298.29 -453.34 584.73 -32.12 -141.79 0.93 0.93 -1.53
0.00 13.46 -1.88
0 0 0.41 29.35 47.13
-0.95 8 -47.77 117.47 87.91 -28.00 -12.06 15 -50.17 63.15 12 80.18 11 -6.77
-441.24 0.99
-208.51 34.80 18.42
-47.00 43.30 24.15 34.74 43.62 5.75 44.83 24.56 32.38 2.37
-129.25 33.20 20.55
-15.45 19 27.70 32.85 35.35 32.68
0.41 37.34 33.37
1.00 1.01 20.55 -0.95 -0.95 1.00 -0.95 0.99
1.00 1.01 -32.00 -63.00 -80.00
-137.98 0.00
-1.00 3 0.95 -163.76 -139.55 -154.36 -155.23
441.24 0.00
-0.00 173.00 -10.52 -20.71 -26.29
208.51 0.00
-0.00 56.86 -510.62 13.46 27.70 35.35
35.12 0.00 -270.69
1.00 45.22 1.00 1.00 1.00
0.41 0.00
-1.00 3 0.95 -1.00 -1.00 0.00
-1.00 3 0.95 0.00 MW 0.00
-1.00 3 0.95 -1.00 -1.00 0.00
-1.00 3 0.95 -1.00 -1.00
-0.00
-0.00 510.62 0.00
-0.00 -0.00
-0.00 -0.00
-0.00
173.68 -472.55 0.99 47.00 -0.00 -0.00 270.69 32.00 0.00 Mvar 63.00 -0.00 -0.00 80.00 -0.00 -0.00
0.00
0.00 15.45 0.00 0.00 0.00
0.00 1.00 0.00
-0.00 0.00 0.00 0.00
-0.00 0.00 0.00
91.40 -242.32 -141.88 42.06 10.52 20.71 26.29
0.00 0.00 0.00 0.00
14.62 38.33 0 0 0 0 0 0
0.42 0.42 0.41 0.41
-173.68 472.55 1.01 1.01 1.00 0.99
-91.40 242.32 1.53
-133.76 -109.55 55.64 54.77 3.71
15.26 41.44
2.37

OCC -1.53
-3.71
1.40
1.53
3.61
1.40

-1.53
-3.61
1.34

141.83

173.69 -472.54
0.95
260.00 -528.45 -439.04
223.78
1.02 -173.35 13.14 462.72 -509.75 -12.06
Rusail PS 47.80
44.83

226.42
1.03
86.79
15.26
-246.56
41.44
85.46 -186.26
42.88
230.02
1.05
-195.85
35.12
-9.66 -100.12
14.62
90.41
9.59
76.56
34.40
-261.61
41.86 -510.15
173.13
13.65 ~ ~ ~ ~ Hamriyah -141.83
-47.80
-8.64 -6.94 -266.97 G
0.93 G
0.92 G
0.90 G
0.88 52.25
42.06 249.00 93.00 212.44
240.00 94.00
96.04 109.71 46.39 50.89 0.97
0.94 0.81 0.90 223.76 85.77 90.61 3.54

-116.40
62.90 69.88

116.40
-31.95
21.06

31.95
17.00
268.45 298.85 569.25
18

1.02
100.80 216.68 278.89
0.95
0.88
298.85
-0.91
27.43
15
300.40
-11.13
36.29
-0.85 20
Sohar Al Filaj 62.33
18
-2.89
0.93
240.00
0.92
249.00
0.90
94.00
0.88
93.00 0.91
112.64 8.60 -238.53 238.70 159.78
-298.53 -0.00 0.00 21.96 -298.49 -115.15 -70.16 -251.67 252.26 70.33 245.92 -141.37 96.04 109.71 3 46.39 50.89 32.13 464.65 -464.62 260.20 350.95 62.97 141.93 116.46 -116.34 1.53 35.63
47.66
20.54
135.53
1.03
-12.57
2.83 -96.05
42.79
96.88
42.79
32.93
-134.67
32.93
SFZ 135.34
1.03
-0.00
1.28
-9.87
1.28 -0.96 Sohar Industrial Area (SIA) -187.60
36.29
Interconnection SS 128.24
0.97
-19.13
20.53
130.14
0.99
-11.40
-27.74
13.07
130.11
0.99
-11.35
-106.80
47.39
Barka Main 109.87
47.39
25.59
13.07
52.18
43.30 131.11
0.99
-0.95
129.62
0.98
-11.69
-24.02
19.47
3 63.83
-0.95
65.72
-0.94
4 76.24
-0.94
4 84.54
-0.92
10.33
5.75
168.19
94.15
-169.40
94.15
Rusail Industrial 88.93
37.23
134.78
1.02
-350.95
-160.64
29.70
-0.95 20
160.64
-350.44
40.03
-117.34
24.79
23.63
48.11
52.25
31.92
21.06
-44.92
17.00
2.58
1.34
10.80
13.44
129.27
0.98
-268.16 -16.24 -568.52 -239.57 -248.59 -93.75 -92.70 11.85
Liwa -10.12
-83.03
27.43 (SIS) Khadra Nakhal -10.65 -187.64
62.33
A'salam -76.24
63.83
-90.76
65.72
-35.52
76.24
-39.07
84.54
40.03
Qurum -1.78

0.93 0.93 0.92 0.92 0.93 129.16


62.15 135.85 70.16 58.13 134.80 92.23 72.18 0.98
24.27 135.60 27.74 24.96 1.02 38.23 29.09 129.41
1.03 -1.87
26.14
15
0.93
55.14 15
21.29
-12.35 -8.23
11.13
2.86
0.93
68.06
-0.95 16
26.66
0.00 MW
-0.00 ..
1.00
135.33
1.03
-10.12
0.93
71.16 14
28.15
0.95
90.00
29.58
0.95
85.00
27.94
0.95
22.00
7.23
70.38
55.09
15.28
1.03
-13.34
228.11
132.51
44.15
0.93
66.17
-0.95 10
26.47
48.98
-7.34
8.71
30.78
-0.95 11
51.34
11
0.92
119.27 7
50.45
74.26
31.39
14.08
36.09
-20.88
5.66
0.92
105.27 10
44.90
170.82
60.77
30.60
0.95
7.00
2.30
11.85 39.11
14
30.49
15
0.95
20.00
6.57
0.95
20.00
6.57
0.98
-1.68
29.09
12.53
5.59
0.93
79.18
-0.95 11
31.53
Muttrah -29.08
-13.47
5.59
0.92
101.23 11
41.89
-72.15
-28.41
13.53
33.19 -68.00 -66.00 -70.00 -79.00
33.13 23.16 28.63
-22.35 33.00 30.02 29.34
-21.69 32.95 -23.01 33.21 32.98 33.21 52.55 32.89 46.62 34.84
-25.97 44.75 32.92
1.01 33.37 1.01 33.22 33.03 1.00
1.00 -0.95 -0.95 28.63 1.00 -0.95 29.34 1.00 30.78 1.01 1.00 -0.95 -0.95 1.00 -0.95 1.01 -0.95 -0.95 1.00 34.84 -0.95
-165.12 -62.00 -55.00 -164.82 -164.98 -71.00 1.01 -168.91 -164.25 -58.00 -165.77 -119.00 -105.00 -92.00 -72.00 -101.00 -155.70
-162.99 -165.85 14.00 -141.79 -141.04
-20.38 -18.08 -23.34 -19.06 -39.11 -34.51 -30.24 -23.67 -33.20
26.14 23.16 30.02 51.34 52.55 46.62 39.11 30.49 44.75

1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 33.10 1.00 1.00
0.00
-1.00 3 0.00
-1.00 3 -1.00 -1.00 0.00
-1.00 3 -1.00 3 0.00
-1.00 3 0.00
-1.00 3 0.00
-1.00 3 0.00
-1.00 3 0.00
-1.00 3 0.00
-1.00 3 0.00
-1.00 3 0.00
-1.00 3 0.00
-1.00 3
0.95 -1.00 -1.00 -1.00 -1.00 0.95 0.95 1.00
-0.00 0.95 0.95 -1.00 -1.00 -1.00 -1.00 0.95 0.95 0.95 -1.00 -1.00 0.95 1.00 1.00 0.95 0.95 1.00 0.95 -1.00 -1.00 0.95
0.00
-0.00 62.00 -0.00 -0.00 -0.00 -0.00 55.00 -0.00
-0.00 -0.00 -0.00 68.00 0.00
-0.00 0.00 71.00 0.00
-0.00 66.00 -0.00 -0.00 -0.00 -0.00 70.00 0.00
-0.00 58.00 0.00
-0.00 -0.00
-0.00 119.00 -0.00 -0.00 0.00
-0.00 105.00 0.00 0.00 92.00 -0.00
-0.00 72.00 -0.00
-0.00 79.00 0.00
-0.00 -0.00 -0.00 101.00 -0.00
-0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -154.93 0.00 0.00
-0.00 20.38 0.00 0.00 0.00 0.00 18.08 0.00 0.00 0.00 22.35 -0.00 -0.00 23.34 -0.00 21.69 0.00 0.00 0.00 0.00 23.01 -0.00 19.06 0.00 -0.00 39.11 0.00 0.00 -0.00 34.51 0.00 0.00 30.24 0.00 23.67 0.00 25.97 0.00 0.00 0.00 33.20 0.00
0.00
0 0 0 0
0.00
0 0
0.00
Sohar Refinery 0.00
0.00 0.00

0.41
0 0 0 0
0.00 0.00

0.42
0.00
0 0
0.00

0.41
0 0
0.42
0.00 0.00

0.42
0.00

0.42
0 0
0.00

0.41
0.42 0.42 0.42 0.41
0.42 1.00 0.42 1.00 1.01 1.00 1.01 1.00 1.00 1.00
1.00 1.01 1.00 1.01 1.01
-132.99 -138.91 -135.85 -135.77 44.00 -111.79 -111.04 -124.93 -125.70
-135.12 -134.82 -134.98 -134.25

-583.30 219.24
40.01 1.00
43.62 -2.71

0.97
570.94
142.65
12.36 59.05
-182.66 -0.99 17 0.95
127.88 13.65
-70.12 61.78 -61.36 -48.89 -88.51 -196.10 144.27 -143.30 -74.17 -36.08 -570.27 25.00 346.73
133.67
1.01
-14.09
-57.32
15.28
-226.21
-123.30
44.15
Saham 46.66
14.05
-51.10
14.05
4.27
8.71
Khaborah -96.39
23.08
-22.21
34.80
Muladah 0.97
-15.25 62.10
27.96
-59.52
27.96
Rustaq -32.31
14.08
-14.48
5.66
Mobella 131.04
0.99
-58.56
59.05
Airport Height 8.22 18.56
47.18
130.96
0.99
Sohar 131.60
1.00
-15.53
-10.79 -10.82
Ghala
0.92 0.92 0.91 0.92 0.92 0.92 0.93
109.28 114.26 164.43 110.25 128.19 125.16 143.30 110.25 129.58 80.20
46.81 48.44 76.65 46.83 0.97 0.95 59.52 46.79 0.98 32.77
46.96 49.02 -153.42 73.19 49.34 -16.92 0.93 0.93 -17.25 43.64 49.08 -11.73 21.09 0.92 80.23 -80.20 34.92
-0.95 12 -0.95 12 -37.93 -0.95 10 7 55.15 85.19 -0.95 8 -0.95 10 -25.93 97.22 12 17.27 -32.77 -0.95 12
-109.00 -114.00 26.67 -164.00 33.01 21.84 34.66 -143.00 -110.00 4.49 40.44 11.64 11.64 -80.00
33.12 -35.83 -37.47 33.13 -53.90 1.00 24.49 10 38.19 10 -47.00 33.07 33.06
-36.16 32.78 42.66 -26.29
32.70 1.00 32.74
1.00 46.96 49.02 1.00 73.19 -172.10 -0.95
0.99
-0.95 -0.95 43.64 1.00
-166.20 49.08 0.99 -0.95
0.99 34.92 ~
11.49 -168.55 -110.00
-36.16 -171.42 32.93 -55.00
-18.08
-85.00
-27.94 32.86
-170.95 -164.81 -97.00
-31.88 -164.08
G
0.97
1.00 1.00 0.42
49.34 12.46 24.49 38.19 42.66 48.00
-168.77 1.00 11.19
-123.07
54.76
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.97
0.00
-1.00
-0.00
-0.00
0.00
0.00
0.00
3 0.95
109.00
35.83
1.00
0.00
0.00
1.00
0.00
0.00
0.00
-1.00
-0.00
-0.00
0.00
-0.00
0.00
3 0.95
114.00
37.47
-1.00
-0.00
0.00
-1.00
-0.00
0.00
0.95
164.00
53.90
0.00
-1.00
-0.00
-0.00
0.00
0.00
0.00
3 -1.00
-0.00
0.00
-1.00
-0.00
0.00
0.95
110.00
36.16
0.00
-1.00
0.00
-0.00
0.00
-0.00
0.00
3

-1.00
1.00 3 0.95 1.00 1.00 -1.00
1.00 3 0.95 -1.00 -1.00
-1.00
-0.00
0.00
-1.00
-0.00
0.00
0.95
143.00
47.00
0.00
-1.00
-0.00
-0.00
0.00
0.00
0.00
3 0.00
-1.00
0.00
-0.00
0.00
0.00
0.00
3 0.95
110.00
36.16
-1.00
-0.00
0.00
-1.00
-0.00
0.00
-1.00
-0.00
0.00
-1.00
-0.00
0.00
0.95
97.00
31.88
0.00
-1.00
-0.00
-0.00
0.00
0.00
0.00
3 0.00
-1.00
0.00
-0.00
0.00
-0.00
0.00
4 0.95
80.00
26.29
-1.00
-0.00
0.00
-1.00
-0.00
0.00
-1.00
-0.00
-0.00
0.00
48.00
11.19
67.06 Ghubrah PS
0 0 0 0 0 0 -0.00
0.00 55.00 0.00 0.00 -0.00
0.00 85.00 -0.00 -0.00 0 0 0 0 0 0 0 0 1.00 0.95 4 ~ ~ ~
GCCIA Interconnection
0.00 18.08 0.00 0.00 -0.00
0.00 27.94 0.00 0.00
0.42 0.41 0.00 0.00 0.42 0.41 0.41 3
0.00
0.00
7.00
2.30
-0.99
-47.85
G
0.84
G G
0.90
1.00 0.42 0.99 0 0 0 0 1.00 0.99 0.99 0.96 62.00
0.42 1.00 0.42 0.00 -6.24 64.00
41.49 1.00 -141.42 -140.95 1.00 -134.81 -134.08 67.06 41.13 26.00 30.16
-142.10 0.41 0.41 -136.20 7.99 84.60
-138.55 63.40
1.00 1.00 57.87
42.46 -138.77
0.90
33.12 0.84 0.96 62.00
1.00 64.00 26.00 30.16
1.00 41.13 7.99
-153.07 40.85 91.93
3.94 5 47.55 4 33.09 4 -0.93
-0.87 -0.97
11 48.69 133.51 -63.88 -25.97 -61.73
-1.00 1.01 -35.91 -6.77 -24.40
-40.71 -6.73 47.55 33.09 91.93
-1.07
48.69

Mawalleh North
0.00 MW
-0.00 .. 223.38 0.95 0.95 157.30
1.02 28.00 7.00 56.65
1.00 9.20 2.30 22.20
-13.35

-21.08
131.03 -10.25
0.99 4.49
-0.00 -10.82
-0.00
1.43

0.90
21.08 10
10.25
47.23
-0.95
10.94
0.99
-48.24
New Ghubrah
-21.00
-6.90
47.23 ~ ~
G G
0.89
0.89
1.00 94.00 94.00
0.00
-1.00 3 0.95 1.00 1.00 48.90 48.22

Figure C.1 OETC Transmission System


-0.00
-0.00 21.00 0.00 0.00 88.67 88.41
0.00
0.00 6.90 -0.00 -0.00
OMCO 0.00
0 0
-187.18 187.25
0.89
94.00
-0.92 -157.27
0.89
94.00
48.22
-83.88 70.92 48.90 -60.09 67.72
0.41 133.41 -93.85 -0.92
18.04 18.04 3 66.22
-40.06 22.20 2 -93.85
0.99 1.01
-18.24 -6.77 Bousher 66.22 -39.43
67.72

2017 Max. load Flow Condition


0.00 -298.86 251.74
-19.55 5.01 87.85 223.02 0.92 0.91 0.92
1.01 111.25 141.34 114.28 130.21
1.43 21.96 20.97 46.71 63.43 133.48
-13.34 -65.41 1.01 0.95 48.75 -90.41 93.85 0.99
47.76 61.66 49.15 -1.20
-26.26 13 12 -6.75 40.00 12 -32.67 39.43
18.60 13.15 12.68 28.54
33.12
1.00 -0.95 -0.95 -0.95 33.09
32.93 1.00
0.54 -161.02 -111.00 -141.00 1.00 -114.00
-36.48 -46.34 -162.49 -37.47 -161.10
47.12
-73.30 65.44 47.76 61.66 49.15 90.45 -93.74
20.43 13.97 -48.12
126.48
14.57 10
-0.53
-47.01
Mahadha 18.60
1.00 1.00 -1.00
12.68 28.54
0.96
-16.06 Bureimi Industrial -135.39
-32.55
24.83
136.24
33.88
24.83
75.94
14.57
128.44
0.97
-13.92
-125.43
-119.90
49.85
128.60
125.42
49.85
8.24
-15.08
2.86
154.27
39.39
26.67
0.00 MW
0.00 Mvar
1.00
135.51
1.03
-12.22 Wadi Al Jazzi -65.44
-20.43
23.16
0.00
-1.00
0.00
-0.00
0.00
0.00
0.00
4 0.95
111.00
36.48
-1.00
-0.00
0.00
-1.00
-0.00
0.00
-1.00
-0.00
0.00
-1.00
-0.00
0.00
0.95
141.00
46.34
0.00
-1.00
-0.00
-0.00
0.00
0.00
0.00
4 0.95
114.00
37.47
3
-0.00
1.00
-0.00
0.00
0.00
0.00
0.00
-90.45
-13.97
15.45
93.74
48.12
36.59
0 0 0 0
0.93 0.42
26.11 0.41
1.00 1.00 0.42
10.40 -297.57 -131.02 1.00
0.93 84.25 10.10 48.14 0.95 -0.90 -0.91 -0.89 -0.90 -0.88 -0.91 -0.87 -132.49
51.14 12.36 -0.31 7.00 -16.91 -51.93 -51.37 -26.09 -59.53 -28.98 -63.30 -117.90 216.67 -131.10
4 24.15 0.98
20.19 15.18 1.89 2.30 -8.32 -24.17 -25.76 -12.34 -32.82 -13.19 -35.43
22.95 10 33.09 68.47 13 81.96 14 74.47 8 73.10 13 80.82 7 73.53 14 84.74 15 -2.43
-0.95 -0.95 1.00
-51.00 -26.00 13.11 0.93
32.99 -16.76 -8.55 297.57
22.95 48.14 0.87 0.86 0.85 0.87 0.84 0.88 0.83
1.00 17.00 52.20 51.60 26.20 59.80 29.10 63.60 131.71 117.90
-168.20 9.85 30.32 31.72 14.75 38.68 15.75 42.09 1.00 32.50
1.00 1.00 68.47 81.96 74.47 73.10 80.82 73.53 84.74 9.32 20
0.00 0.00 -27.06 27.11 -169.47 65.47 90.47 -93.68 72.23 97.02
1.00
-1.00
0.00
-0.00
0.00
-0.00
3 -1.00
-0.00
-0.00
0.00
0.00
3 0.95
26.00
8.55
1.00
0.00
0.00
1.00
0.00
0.00
131.32
0.99
Izki -5.79
4.75
-2.21
4.75
-56.76
30.60 -0.95 MSQ 20.44
23.16
133.63
1.01
13.82
15.45
129.69
0.98
-1.45
-47.88
36.59
27.59 39.02
13.53 18.26
0.00 -297.26
-1.00
-0.00
0.00
-1.00
-0.00
0.00
0.95
51.00
16.76
-1.00
0.00
-0.00
0.00
0.00
3 0.00 0.00
0 0
0.87
17.00
9.85
0.86
52.20
30.32
0.85
51.60
31.72
0.87
26.20
14.75
0.84
59.80
38.68
0.88
29.10
15.75
0.83
63.60
42.09
8.56
Sumail -92.44
32.50
-6.62

0.00 0.42 0.42 61.88 86.83 83.89 80.17 91.90 88.24 82.45 0.93 0.92 0.93
0 0 1.00 1.00 74.16 107.24 34.08
43.11 43.11 G G G G G G G 29.89 44.85 13.33
0.41
1.00
~ ~ ~ ~ ~ ~ ~ 110.25
44.86
32.15 -157.36
-68.96
0.92
106.23 13
0.93
36.13
45.93 28.92 -75.57
-18.73
-0.95 13 -0.95 -0.95
-138.20 20.72 -74.00 29.51 32.70 45.02 13.95 -107.00 -34.00 13.54
32.91 -24.32 0.99 46.25 1.00 30.81 13 9 -35.17 33.02 14 -11.18
1.00 -144.87 -0.95 0.00 33.12 33.20
32.15 45.93 1.00 28.92 1.01
-144.36 -106.00 -0.00 -0.95 1.00 -160.78
-34.84 0.00 -36.00 -143.11 -159.24
46.25 -11.83
30.81
1.00 1.00 3 1.00 1.00
0.00
-1.00 4 0.95 -1.00 -1.00 0.00
-1.00 3 0.95 -1.00 -1.00 -1.00 0.00
-1.00 -1.00 -1.00 0.00
-1.00 -1.00 -1.00
-0.00 -0.00 -0.00 0.95 -0.00 0.95
-0.00 74.00 -0.00 -0.00 -0.00 106.00 -0.00 -0.00 -0.00 0.95 -0.00 107.00 -0.00 -0.00 -0.00 -0.00 -0.00
0.00
-0.00 24.32 0.00 0.00 0.00
-0.00 34.84 0.00 0.00 0.00 36.00 3 0.00
-0.00 35.17 0.00 0.00 3 0.00
-0.00 34.00 0.00 0.00
0.00 0.00 0.00 11.83 0.00 0.00 11.18
0 0 0 0 0 0 0 0
0.41 0.41
1.00 0.99 0.42 0.42
0.42 1.00 1.01
-114.36 -114.87 1.00 -130.78 -129.24
-113.11

-84.24
-12.38 0.42 0.42
15.18 1.00 1.00
-120.58 -120.58

84.24 0.42 0 0
1.00 157.90 -1.00 -1.00 0.95 -1.00 -1.00
12.38 -0.00 -0.00 41.00
12.66 -110.96 70.48 -0.00
1.00 -0.00
1.00
29.51 0.00 0.00 13.48 0.00
0.00 0.00
0.00
3 0.00
-0.00 3 0.00
-0.00
0 0 0.00 0.00
-1.00 -1.00 0.95 -1.00
-0.00 -0.00 14.00 -0.00
1.00
0.00 0.00 4.60 0.00
0.00 -157.90
4 0.00 33.07 33.12
-0.00 1.00 -70.48 1.00
0.00 22.92 -0.95
-140.96 -150.58 -41.00
0.93
-13.48
41.12 170.93
-0.95 15 15.66
17.53
-14.00 59.32
-4.60 17.53 132.57 30.96
-169.99 75.76 52.22 -52.21
6.09
1.00
1.18 -56.37
30.96
16.62
13.54
130.48
0.99
132.46
129.39
0.98
26.61
10.26
-27.03
10.26
Daghmar 129.24
157.93 -0.58 -1.02
New Izki 15
0.92 132.85
67.84
22.92 -0.94 Amerat 1.00
1.03 Yitti Quriyat 0.98
-1.12
14.09 1.01 457.74 352.37 -326.27
0.90 103.12 11.10 0.93
6.01 9.59 -60.87 166.38 -120.36
326.76
6.09 34.74 29.70 20 158.21 44.26 1.12 0.92 11.10
217.27 36.81 19.55 1.48 4.46
0.99 36.81 94.24 -11.10 -102.35 0.93 0.89
39.76 4.77
5.81 -4.46 -45.86 50.13 52.21
-0.89 41.44 12 1.48
15
19.55
-0.95 12
19.25
-0.95
27.03
7
-278.44 -50.00 -52.00
106.42
69.52
17.04
0.85 20
-143.37
278.89
33.18
175.34 218.72 -0.97 Jahloot 32.76
0.99
-0.95
-94.00
-0.95
33.01
32.81
0.99
-153.12
22.04
-16.43
22.04
60.04
-17.09
60.04
11.03
1.00
-40.04
0.99 -1136.87
0.93 -154.61 -11.00
33.18 -30.90 -3.62 1.00
13.51 -263.72
1138.03 391.00 41.44 -149.40
20 441.03
62.43 0.98 4.77
62.43 13.68
-0.85 1.00 1.00 1.00 1.00
-278.89
0.81 17 0.00
-1.00 3 0.95 -1.00 -1.00 0.00
-1.00 3 0.95 -1.00 -1.00 0.95 0.00
-1.00 3 0.00
-1.00 3 0.95 1.00 1.00
-175.34
279.06 -0.00
-0.00 94.00 -0.00 -0.00 0.00
-0.00 11.00 -0.00 -0.00 50.00 0.00
-0.00 0.00
-0.00 52.00 0.00 0.00
34.03 406.16 0.00 0.00 0.00 0.00
203.74 1.02 -0.00 30.90 0.00 0.00 -0.00 3.62 0.00 0.00 16.43 -0.00 -0.00 17.09 -0.00 -0.00
34.03 17.06 -1138.03 0.00 0.00 0.00 0.00
-441.03 0 0 0 0 0 0
35.20
0.41 0.42
0.41 1.00
0.99 0.42 0.99
-123.12 -10.04
-279.06 -124.61 1.00
-203.74 -119.40
9.59

-106.41

106.41
-72.17
17.04

72.17
22.28
-84.19 -51.13 -60.04 51.38 129.25 -109.70 -105.71
-34.19
12.66
Bureimi 126.26
0.96
127.78
0.97
6.00
-19.63
19.33
128.41
0.97
6.36
-23.29
11.31
60.17
20.90
11.31
17.76
19.33
Nizwa 0.98
7.04
-45.41
20.72
-72.24
22.28
129.60
0.98
8.07
127.32
0.96
7.86
-27.12
Al Hayl Bahla Jebreen Mudhaibi Ibra
126.35 0.93 0.92 0.93 0.92 0.92 0.93
0.96 84.19 49.19 60.04 111.25 130.30 77.19
-16.13 34.19 20.52 23.29 47.36 57.41 31.44
38.18 -49.19 69.65 0.93 26.48 53.20 0.00 49.40 -166.30 58.01 -24.59 34.57 -77.19
-0.95 9 -20.52 -0.95 8 51.13 10 12 19.65 -3.05 10 -57.21 -0.95 11 14.83 10 -31.44
-84.00 9.52 -49.00 19.63 10.00 3.49 49.10 -130.00 5.83 14.76
22.63 32.75 32.70 32.97
-27.61 -16.11 32.70 32.95 32.69 0.99 -42.73 1.00
32.86 0.99 -0.95 1.00 -0.95 -0.95 0.99 -0.95
38.18 1.00 69.65 0.99 -147.50 58.01 -147.04 -145.30
-1.18 -51.00 -146.09 -60.00 -146.01 -111.00 -77.00
-169.61 -16.76 -19.72 -36.48 -25.31
22.63 26.48 49.40 34.57

1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00


-1.00
-0.00
0.00
-1.00
-0.00
0.00
0.95
84.00
27.61
0.00
-1.00
0.00
-0.00
0.00
-0.00
0.00
3 1.00
0.00
-0.00
1.00
0.00
-0.00
0.95
49.00
16.11
0.00
-1.00
0.00
-0.00
0.00
0.00
0.00
3 0.00
-1.00
-0.00
-0.00
0.00
0.00
0.00
3 0.00
-1.00
-0.00
-0.00
0.00
0.00
0.00
4 0.95
51.00
16.76
-1.00
-0.00
0.00
-1.00
-0.00
0.00
0.95
60.00
19.72
0.00
-1.00
-0.00
-0.00
0.00
0.00
0.00
4 0.00
-1.00
-0.00
-0.00
0.00
0.00
0.00
4 0.95
111.00
36.48
-1.00
-0.00
0.00
-1.00
-0.00
0.00
Manah PS 0.00
-1.00
-0.00
-0.00
0.00
-0.00
0.00
3 0.95
130.00
42.73
-1.00
-0.00
0.00
-1.00
-0.00
0.00
-1.00
-0.00
0.00
-1.00
-0.00
0.00
0.95
77.00
25.31
0.00
-1.00
-0.00
-0.00
0.00
0.00
0.00
4
Sur PS
0 0 0 0 0 0 0 0 0 0 0 0
0.41 0.41 0.41 0.41 0.41 0.41 0.41 0.41
1.00 0.99 0.99 1.00 0.99 0.99 ~ ~ 0.99 1.00 ~ ~ ~
-139.61 -31.18 -31.18 -116.09 -116.01 -117.50 G G -117.04 -115.30 G G G
0.86 0.94
60.00 166.00 280.19 1149.78 0.92 0.92 0.88
35.15 62.70 411.19 1075.00 555.78 138.00
-110.15 414.95 1.03
59.82 53.77 9.59 35.20 455.19 233.19 73.89
19.78 72.06 70.83 73.84

0.86 0.94 -0.98 0.92 0.92 0.88


60.00 166.00 -1429.97 1075.00 -0.96
555.78 -0.92
138.00
35.15 62.70 -304.80 455.19 -554.82
233.19 -138.00
73.89
-53.14 167.09 24.66 128.62 77.45
128.86
0.98
-20.96
10.00
59.71
49.10
131.06
0.99
4 51.51
-0.89
10 59.69
-0.96
-22.31
5.83
Mudhairib 0.97
8.87
29.46
14.76
134.82
1.02
14 38.45
0.96
-0.96
17 71.84
-1072.59
-330.82
17 -168.27
72.62
72.62
18 -57.40
75.26
75.26
8.54 -59.88 -165.61 1430.51
6.74
Madinat Nizwa -30.85
51.51
-47.27
59.69
18.65
Ayjah 441.25
38.45
71.84

0.93
53.14 228.43
20.96 1.04 0.95
23.41 0.95 52.39 0.92 -203.34 0.93 -66.05 24.43 322.90 12.00
-0.95 12 6.00 16.44 101.23
-0.95 12 -49.30 66.05 17 -25.92 111.29 3.94
-53.00 1.97 9.84 42.15
-101.00 32.71 36.69 25.92 11.87 24.56
-17.42 32.83 45.01
-33.20 0.99 27.79 33.11
23.41 0.99 45.01 -145.19 -0.95 1.00
-145.43 -66.00 -133.99
-21.69
27.79

1.00 1.00 1.00


-1.00
-0.00
0.00
-1.00
-0.00
0.00
0.95
53.00
17.42
0.00
-1.00
-0.00
-0.00
0.00
0.00
0.00
4 0.00
-1.00
0.00
-0.00
0.00
-0.00
0.00
3 0.95
101.00
33.20
-1.00
-0.00
0.00
-1.00
-0.00
0.00
Al Kamil PS -1.00
-0.00
0.00
-1.00
-0.00
0.00
0.95
66.00
21.69
0.00
-1.00
-0.00
-0.00
0.00
0.00
0.00
3

0 0 0 0 0 0
0.41 0.41 0.42
0.99 0.99 ~ 1.00
-115.43 -115.19 G -103.99 -322.53
-111.75
227.21
0.85 1.03
24.56 23.73
231.00
145.44
75.04
-248.81
-104.15 210.22 0.94
0.96 322.53
20.97 111.75
-20.34
33.10
0.85
-0.90 0.95 17
-0.00 -52.20 -93.21 93.89 206.22 231.00 6.00 -76.04 76.36 -164.58 166.59 -255.78 255.81 66.25
Wadi Sa'a 0.92
248.81
104.15
-0.00
3.49
129.58
0.98
129.63
0.98
Adam -21.77
9.84
-38.22
17.42
35.12
17.42
61.27
36.69
133.39
1.01
13.61 8
-230.07
145.44
-113.04
78.47
78.47
1.97 14.68
13.32
-18.72
13.32
-17.57
28.03
22.00
28.03
-58.21
37.11
56.96
37.11
22.20
11.87
Sur-2 -0.97
-322.06

128.33 -10.09 49.38 -77.49 -75.07 75.32 77.97


28.23
-0.95 20
-248.55
Ibri 6.97 7.40
JBB Ali JBB Hasan Sur-1 -79.16
33.10
0.97
-14.07
-3.79
1.89
Dank 15.05
9.52
-25.64
14.41
128.58
0.97
-29.73
14.16
27.39
14.16
21.43
14.41
-85.57
28.23
129.89
0.98
0.92
52.20
21.77
130.41
0.99
133.15
1.01
136.03
1.03
136.05
1.03
-24.92 0.92 19.60
Dreez -23.89 0.00 MW
0.00 Mvar
1.00
71.99
-0.95 10
11.37 0.93
93.21 13
38.22
88.22
36.29 14
15.17 0.93
89.20 16
36.21
0.00 MW
0.00 Mvar
1.00
19.60

-52.00 37.88
0.93 0.93 0.94 -17.09 40.79 -0.95 37.37
127.73 75.07 64.15 31.12 32.90 32.81 -88.00 33.21
71.99 32.87 -0.95 0.99 -0.95 1.01
0.97 29.73 25.18 11.57 1.00 -93.00 -28.92 -89.00
0.94 -25.89 0.94 -146.83 1.00 -138.30 -133.89
33.16 28.17 26.78 -142.34 -30.57 37.88 -29.25
10.09 28.11 11 -0.95 11 -0.95 12 -0.95 11
3.79 10.59 40.79 37.37
33.01 -75.00 -64.00 32.93 -31.00
8.80 12 24.64 1.00 -24.65 32.99 32.80
-21.04 1.00 -10.19
-0.95 -0.95 1.00 0.99 1.00 1.00 1.00 1.00
-177.73 33.16 -176.56 28.17 4.46 26.78 0.95
-10.00 -28.00 -177.82 0.00
-1.00 3 0.00 3 0.95 0.00
-1.00 3 0.00
-1.00 3 -1.00 -1.00
33.03 -3.29 -9.20 0.95 -1.00 -1.00 93.00 -1.00 -1.00 0.95
-0.00
-0.00 52.00 -0.00 -0.00 0.00 30.57 -0.00 -0.00 88.00 0.00
-0.00 0.00
-0.00 89.00 -0.00 -0.00
1.00 8.80 24.64 0.00 0.00 28.92 0.00 0.00
0.00 17.09 0.00 0.00 0.00 0.00 -0.00 -0.00 29.25 0.00 0.00
-164.76
1.00
0.00
-1.00 3 0.95 -1.00 -1.00 -1.00 -1.00 0.95
1.00
0.00
-1.00 4
1.00
0.00
-1.00 3 0.95 -1.00 -1.00
1.00
0.00
-1.00 3 0.95
PDO 0.00
0 0
-1.00
-0.00
-0.00
0 0
0.00 0.00
0 0

0.00 0.00 0.00 0.00 0.41 0.41


0.00 0.41 0.42
1.00 -0.00 28.00 -0.00 -0.00 -0.00 -0.00 75.00 -0.00 -0.00 64.00 -0.00 -0.00 -0.00 31.00 1.00 1.00 0.99 1.01
0.00
0.00 9.20 0.00 0.00 0.00 0.00 24.65 0.00
-0.00 0.00
0.00 21.04 0.00 0.00 0.00
-0.00 10.19 -116.83 -112.34 -108.30 -103.89
0.00
-1.00 3 0.95
0.00 0.00 0.00 0.00 0.00
-0.00 10.00 0 0 0 0 0 0
0.00
0.00 3.29
0.00 0.42 0.41 0.41 0.41
1.00 1.00 0.99 1.00
152.27 -147.82 -146.56 -25.54
0.42
1.00
2017 Peak Load in OETC Network Project: 2017
-134.76
OETC
Summer Peak Load Graphic: Expanded Grid
Network Plan
Studied areas: Majan, Mazoon and Muscat Date: 2/9/2017
PowerFactory 15.2.6 (Master Model) OMIFCO
Annex: OETC

Figure C 1: MIS 2017 Max. Load Flow Condition

Page | 205
Five-Year Annual Transmission Capability Statement (2017-2021)

DIgSILENT
Sohar Aluminum PS
~ ~
Sohar-1 PS G
0.02
0.36
-16.71
G
0.00
-0.00
Sohar-2 PS Barka-2 PS Barka-1 PS Barka-3 PS 0.42
1.00
-124.13
0.41
1.00
-123.87
0.42
1.00
-115.79
0.42
1.00
-115.77
0.42
1.00
-119.88
0.42
1.01
-120.78
3.71 6.44
~ ~ 2.15 ~ ~ ~ ~ ~ ~ ~ ~ ~ ~
G G G G G G G G G G G G

-447.13
0 0 0 0 0 0 0 0

349.28
122.20
0.96

-65.61
28.03

33.60
249.53 0.91 0.88 0.89 0.86 0.95 0.96 0.95 -1.00 -1.00 0.95 -1.00 -1.00 0.95 -1.00 -1.00 -1.00 0.95 -1.00 -1.00 -1.00 0.95 -1.00 -1.00 0.95 -1.00 -1.00
0.86 0.81 0.85 0.88 0.90 329.10 226.50 226.50 220.70
336.90 196.60 226.50 226.50 129.85 286.00 192.40 196.60 66.15 68.10 -0.00
1.00 -0.00
1.00 124.00 -0.00 -0.00 107.20 -0.00
1.00 -0.00 -0.00 114.40 -0.00
1.00 -0.00 -0.00 86.00 -0.00
1.00 -0.00
1.00 99.30 -0.00 -0.00
-0.00 230.00 146.80 151.41 100.64 115.72 73.81 62.42 22.38 -0.00 -0.00 40.76 0.00 0.00 35.23 -0.00 0.00 0.00 37.60 0.00 0.00 0.00 28.27 -0.00 0.00 32.64 0.00 0.00
202.02 144.51 -0.01 141.75
0.85 124.49 110.79 20.65 -349.28 447.13 67.76 0.00 0.00 0.00 0.00 0.00 0.00
0.02 -0.00 68.64 79.75 68.28 81.47 74.21 73.19 3 0.00 3 0.00 3 0.00 3 0.00 3 0.00 3 0.00
73.15 88.73 -0.13 6.44 10 83.24
226.50 80.52 75.09 -122.20 65.61 0.00 0.00 0.00 -0.00 0.00 -0.00
0.36
17.64 39.14 48.65 0.95 0.00 0.00 0.00 0.00 0.00 0.00
-16.71 10 0.02
2.22 141.75 -249.53 226.50
4.08 0.13 84.16 0.96 0.96
4.08 -129.85 73.81
-5.86 226.50 220.70
22.15 0.91 0.88 0.89 0.86 15 75.03 66.15 33.04 -0.95 -0.95 -0.95 -0.95
2.22 329.10 286.00 192.40 196.60 62.42 32.85 -107.20 33.10 -114.40 33.04 -86.00 -99.30
0.88 0.90 65.31 1.00 33.05 33.19
20 146.80 151.41 100.64 115.72 74.00 1.00 -35.23 1.00 1.00 -37.60 1.00 -28.27 -32.64
226.50 230.00 -154.13 -153.87 -149.88 1.01
0.86 0.81 69.63 80.90 68.28 81.47 -0.95 -0.95 45.71 -145.79 -145.77 48.76 37.12 43.14
336.90 196.60 238.33 124.49 110.79 -68.10 -124.00 -150.78
81.40 72.36 -0.95 15 -0.93 15 -0.92 15 -0.91 15 -0.98 17 -0.99 17 -0.98 0.92 0.92 12 14 0.93 12 0.92
202.02 144.51 1.08 213.96 -347.57 349.37 -447.00 -328.55 -286.00 -192.08 -196.25 -192.62 -22.38
68.33 -40.76
124.29 86.19 -87.07 99.52
15 12
69.84
-0.90
15 88.53
-0.87
17
29.99 1.00
0.00
0.00
0.00
-11.78
2.38
1.00
0.00
0.00
-0.91 17 -0.93 16 -0.94
0.97
1.42
-117.30
28.03
73.90
39.14
Blue City -112.69
48.65
219.41
1.00
4.83
-109.17
69.63
-112.14
80.90
-81.37
68.28
-91.56
81.47
-226.02
-44.57
75.03
-226.01
-33.93
74.00
-220.21
-41.18
65.31
-83.21
28.11
131.38
1.00
0.94
59.92
29.70
59.92
54.38
53.51
54.38
0.00
0.00
0.00
0.92 0.92
34.91
37.12
132.27
1.00
3.55
-37.67
16.18
8 41.87
43.14
61.59 -61.46 -336.34 -196.17 -0.00 249.55 107.44 114.66
132.83
1.01
Shinas 21.90
11.30
132.00
1.00
-24.42
11.30
-161.97
69.84
-111.58
88.53
0.00
2.38
-226.03
-105.41
84.16
223.76
1.02
-226.03
-90.38
81.40
-229.52
-80.56
72.36
103.23
22.15
MIS 45.50
45.71
Mawalleh South-A 48.46
48.76
Al Falaj
-2.41 -3.06
Madinat Shinas 2.18 0.84
367.79
238.40
224.27
1.02 596.34
230.93
1.05
0.93
91.27
37.22
348.96
35.91
134.79
1.02 132.16
9.14 1.00
229.50
1.04
-20.22
-121.10
9.38
45.07
20
0.93
97.63
38.78
0.95
6.00
1.97
0.95
25.00
8.22
595.56
214.05
46.22
212.59
46.18
0.95
6.00
1.97
13.79 0.95
6.00
1.97
38.28 28.56
-348.82
Seeb Main Mawalleh South-B -222.10
-93.96
31.49
8.62 -63.47
-23.21
23.05
Wadi Adai 64.35
25.97
11.86
-64.34
-26.24
11.86
3.47
-35.19
-15.63
12.82
-113.53 0.93 0.93 2.60 573.30 0.95 0.95 148.25 0.95 0.95 128.61 32.96 13 32.92 17 -133.67
-42.34 51.94 14 61.46
-0.95 13 155.16 6.00 31.00 211.64 200.00 6.00 0.97 -0.88 1.00 -0.95 -0.95 28.56
20.57 20.44 24.42
-61.30 31.06 1.97 10.19 21.60 65.74 1.97 -3.58 -367.35 -97.40 -91.00 33.03
-148.34 1.00 348.82
33.10 22.19 26.45
-20.15 -194.14 -32.01 -29.91
1.00 -0.95 33.18 137.03 -139.97 133.67
26.45 1.04 45.07 32.92 38.28 27.08
-154.50 -51.80 1.01
-17.03 -155.50 -0.01 129.82 134.95
22.19 1.00 0.98 -595.96 1.00 223.98 1.02 132.20
0.00 -0.06 -209.27 0.00 1.02 1.00
1.00 1.00
0.93
59.34
-0.95 11
237.18
73.06
70.83
97.98
-1.00
-0.00
-0.00
3 0.95
97.40
-1.00
-0.00
-1.00
-0.00 Madinat Barka 46.18
-1.00
-0.00
-1.00
-0.00
0.95
91.00
-1.00
0.00
-0.00
3
9.87 Misfah 8.60
3.49 Wadi Kabair

27.08
-131.59
-346.91
23.10 43.57 21.42 0.00
0.00 32.01 0.00 0.00 0.00 0.00 29.91 0.00
0.00
-1.00 -1.00 0.95 0.00
-1.00 3 -1.00 -1.00 0.95 0.00
-1.00 3 -59.20 0.94
-0.00 -0.00 26.29
-19.46 32.91 0.00 595.96 0.00
-0.00 -0.00 51.80 -0.00 -0.00 -0.00 61.30 -0.00 1.00 0 0 209.27 0 0 33.51
0.00 0.00 17.03 0.00
0.00 0.00 0.00 20.15 0.00
0.00 26.29 12.60
-0.00 0.00 MW -156.04 229.14 0.93 0.93 -315.69 49.92 367.95 -86.88 491.68 -0.91 -33.51 -146.16 0.93 0.93 -2.28
0.00 0.00 14.03
0 0 0 0 0.00 -0.00 .. 0.41 38.18 49.43
-0.95 8 37.12
-0.95 8 -72.03 0.42 146.70 31.06 146.04 -425.84
0.88 19 -12.60 16 -51.33 65.45 14 82.99 12 -7.79
-148.23 1.00
1.30 1.00 -238.79 40.47 19.35
-49.30 14.49
-37.00 56.25 1.00 29.17 7.69 37.55 -192.21
426.07 5.98 45.10 25.55 33.57 2.70
0.42
1.00
0.42
1.01
21.60
1.00
-118.34 33.13
1.00
21.60
-16.20
21.60
33.24
1.01
-151.49
16.21
-12.16
16.21
Barka IPP -109.97
402.78
1.01
13.52
32.07
230.55
32.07
33.08
1.00
-0.95
28.06
-0.95
32.85
1.00
35.75
-0.95
33.05
1.00
0.00
-1.00 3 0.95 -151.97 -33.40 -65.30 -149.08 -82.80 -149.90
-124.50 -125.50 -0.00 -142.71 -10.98 -21.46 -27.22
148.23 -0.00 59.20
238.79 0.00
-0.00 19.46 -595.92 14.03 28.06 35.75
20.96 0.00 -215.56
1.00 1.00 49.92 1.00 1.00 1.00
0.41 0.00
-1.00 3 0.95 -1.00 -1.00 0.00
-1.00 3 0.95 -1.00 -1.00 -426.07 0.00
-1.00 3 0.95 0.00 MW 0.00
-1.00 3 0.95 -1.00 -1.00 0.00
-1.00 3 0.95 -1.00 -1.00
-0.00
-0.00 -0.00
-0.00 595.92 -0.00
-0.00 0.00
-0.00 -0.00
-0.00
17.21 -249.40 1.00 49.30 -0.00 -0.00 37.00 -0.00 -0.00 215.56 -230.55 33.40 0.00 Mvar 65.30 -0.00 -0.00 82.80 -0.00 -0.00
0.00
0.00 16.20 0.00 0.00 0.00
-0.00 12.16 0.00 0.00 13.56 0.00
0.00 1.00 0.00
-0.00 0.00 0.00 0.00
-0.00 0.00 0.00
12.78
2.25
-130.61
20.65 Sohar Refinery -126.04
0.00

0.42
0 0
0.00

0.42
0 0
46.41

0.42
0.00
10.98

0.41
0.00
21.46
0 0
0.00

0.42
27.22
0 0

-17.21 249.40 1.00 1.01 1.00 1.00 1.00


-12.78 130.61 2.28
-121.97 -121.49 -112.71 60.92 60.10 4.57
1.69 22.41
2.70

-2.28
-4.57
1.74
2.28

OCC 4.47
1.74

-2.28
-4.47
1.67

146.19

222.80
17.21
8.26
-249.40
-135.00
0.95
270.00
88.74
-573.22
-198.90 229.22
-147.47
-243.89
222.31
1.01
1.67
-17.20
-25.27
20.55
86.28
448.94
75.67
-594.53
-205.06 222.42
Rusail PS 48.84
45.10

1.04 -146.19
1.01 1.69 22.41 31.06 20.96 2.25 9.38 33.60 46.22 -595.35 1.01 ~ ~ ~ ~ -48.84
1.77 2.40 -210.54 8.08 G G G G
46.41 0.93
219.30
0.92
225.60
98.20
0.89
85.90
0.96
84.80
25.14
Hamriyah 217.15
0.99
52.57
Muttrah
0.88 0.94 0.82 0.96 85.91 43.13
77.56 75.60 8.87

-119.22
57.31 64.08

119.22
-31.69
21.03

31.69
16.97
232.19 303.22 298.36 483.01
126.74 110.15 209.90 140.32
26.12
18
20.64
16
-154.24
-27.02
36.10
-0.85 20
Sohar 49.75
16
257.93
199.61
0.93
219.30
0.92
225.60
0.89
85.90
0.96
84.80 0.91
113.87 -281.54 281.79 0.00 11.51 -298.01 -167.58 168.33 -236.60 -73.27 -91.73 91.80 73.45 317.23 24.14 192.99 85.91 98.20 3 43.13 25.14 33.53 437.27 -437.25 222.51 365.20 63.51 146.29 119.27 -119.16 2.28 35.20
41.85 134.06
1.02
-109.44 110.76 SFZ -0.90
-10.12
-0.95 Sohar Industrial Area (SIA) -181.12 Interconnection SS -40.29 126.35 42.81 -70.22 127.75
130.35
0.99
-29.11 25.40
131.45
1.00 Barka Main -25.80 27.05 80.55
-0.99 Al Filaj 131.75
1.00 53.82 3 58.15
-0.95
59.43 4
-0.94
69.91
-0.93
3 70.53
-0.98
10.86 150.65
65.93
-152.32 Rusail Industrial 67.08 135.16
1.02
-365.20
-161.96
-0.95 20
161.96
-364.67 23.03 49.15 31.65 -45.29 3.40 9.23 132.31
20.57
-1.46
Liwa
50.82 50.82
-231.93
1.30
-302.87
36.10

Khadra
30.76 0.96
-5.91
30.76 43.57
Suwauiq 0.97
-4.38
0.82
Nakhal
13.64 16.37 1.32 16.37 13.64 56.25
-482.48 1.09
A'salam
28.11
-218.94 -225.26 -85.69 -84.59
5.98 65.93 31.49
8.77 30.07 40.53
-117.42 23.05 52.57 21.03 16.97 1.67 12.82

Qurum
1.00
3.57
-110.61
26.12
-94.37
20.64 (SIS) -81.80
49.75
-69.48
58.15
-82.71
59.43
-34.00
69.91
-16.91
70.53
40.53

0.92 0.93 0.93 0.92 0.92 0.93 0.93


100.02 134.42 72.87 134.82 73.27 117.17 131.37 135.17 98.25 76.49 81.68 132.22
41.83 1.02 28.90 1.02 29.11 49.53 1.00 1.02 41.09 31.01 132.47 32.66 1.00
42.94 0.95 0.93 -122.63 0.93 137.03 30.37 0.95 0.95 0.95 0.95 -2.05 65.04 232.98 0.93 0.93 43.96 0.93 32.11 51.10 -25.44 1.61 -304.08 0.92 136.68 0.95 8.78 41.60 32.24 0.95 0.95 1.00 35.59 35.13 3.50 -35.58 0.92 -68.45
-1.19 1.04
14 8.60 59.04 14 -28.87 72.76
-0.95 15 15 96.00 85.00 22.00 27.00 53.94 127.19 54.15
-0.95 9 69.48
-0.95 9 -9.01 68.27 10 -0.95 11 -0.95 8 -74.93 -101.60 111.09 11 39.28 7.00 14 15 20.00 20.00 3.69 13.60 -0.95 13 -14.57 104.03 13 -28.69
2.83 22.94 21.14 28.72
-72.70 -0.00 31.55 27.94 7.23 8.87 14.40 44.66 21.36
-54.00 27.94
-69.30 8.01 27.41 -73.10 -116.90 13.58 42.83 47.79 23.96 2.30 6.57 6.57 6.55 -81.50 6.55 43.26 12.65
25.09 33.16 30.73 32.98 24.32 31.29 32.80 30.40 32.79 32.97 48.46 44.96 32.90
32.75 -23.90 32.95 -17.75 -22.78 0.99 -24.03 33.23 -38.42 33.00 33.26 33.08 33.09 -26.79
0.99 -0.95 -0.95 1.00 30.73 1.00 -0.95 33.40 1.00 24.32 31.29 0.99 -0.95 32.11 1.01 1.00 51.10 -0.95 -0.95 -0.95 35.13 -0.95 1.00
-153.88 1.01 -157.16 -153.09 1.00 1.01 1.00 1.00
-155.60 -99.80 -58.90 -154.00 -72.70 -158.10 -158.74 -68.10 -152.15 26.57 -110.80 -145.08 -98.00 -76.30 -149.66 -103.80 -150.46
-32.80 -19.36 -23.90 -152.93 -22.38 -36.42 -32.21 -25.08 -144.28 -34.12
42.94 25.09 30.37 30.40 48.46 41.60 32.24 44.96

1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
0.00
-1.00 3 0.00
-1.00 3 -1.00 -1.00 0.00
-1.00 3 -1.00 3 0.00
-1.00 3 0.00
-1.00 3 0.00
-1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.95 -1.00 -1.00 -1.00 -1.00 0.95 0.95 1.00
-0.00 0.95 0.95 -1.00 -1.00 0.95 -1.00 -1.00 -1.00 -1.00 0.95 0.41 3 -1.00 -1.00 0.95 -1.00 3 -1.00 3 0.95 -1.00 -1.00 -1.00 3 0.95 1.00 1.00 0.95 -1.00 3 0.95 -1.00 3 0.95 -1.00 3 -1.00 -1.00 0.95 -1.00 3
0.00
-0.00 99.80 -0.00 -0.00 -0.00 -0.00 58.90 -0.00
-0.00 -0.00 -0.00 72.70 0.00
-0.00 0.00 72.70 0.00
-0.00 54.00 -0.00 -0.00 0.00
-0.00 69.30 -0.00 -0.00 -0.00 -0.00 68.10 -0.00
-0.00
0.99 -0.00 -0.00 73.10 0.00
-0.00 -0.00
-0.00 116.90 -0.00 -0.00 0.00
-0.00 110.80 0.00 0.00 98.00 -0.00
-0.00 76.30 0.00
-0.00 81.50 0.00
-0.00 -0.00 -0.00 103.80 0.00
-0.00
0.00
0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00
-0.00 0.00
-0.00 0.00
-0.00 0.00
-0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
-0.00 0.00
-0.00 0.00
-0.00
32.80 0.00 0.00 0.00 0.00 19.36 23.90 0.00
0.00 23.90 17.75 0.00 0.00 22.78 0.00 0.00 0.00 0.00 22.38 -127.16 0.00 0.00 24.03 38.42 0.00 0.00 36.42 0.00 0.00 32.21 25.08 26.79 0.00 0.00 34.12
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

0.42 0.41 0.41 0.41 0.41 0.42 0.42 0.42 0.41


0.41 0.41 0.42 1.00 0.99 0.42 1.00 1.00 1.01 1.00 1.00 1.00
0.99 1.00 1.00 1.01 -128.10 -128.74 1.01 -123.09 56.57 -115.08 -114.28 -119.66 -120.46
-125.60 -123.88 -124.00 -122.93 -122.15

-257.65 -490.63
220.79 -199.89 221.95
1.00 24.14 -138.84 1.01
7.61 37.55 8.49

0.87 0.95
445.46 302.56
250.95 94.19 ~
0.96

43.35 -43.30 -64.89 135.82 -135.01 46.99 -43.88 -70.61 -226.72 127.23 150.18 -149.12 25.52 305.14
50.95
20
-187.81
-51.05
14.41
188.07
44.65
14.41
31.41
-0.97 17
-302.25
0.95
25.00
0.41
1.00
G
46.80
14.46
54.43 Ghubrah PS
133.52
1.01
-15.11
7.75
12.73
7.75
133.67
1.01
-55.42
14.40
-231.03
-117.65
44.66
Saham 130.92
78.18
27.29
-76.34
27.29
39.93
11.35
-46.82
-43.05
11.35
5.95
8.01
Khaborah -98.03
21.42
-26.86
40.47
Muladah 0.96
-3.90
65.71
29.32
-62.46
29.32
Rustaq 73.91
13.58
66.90
42.83 -0.92 Mobella 133.41
1.01
-69.70
31.41
Airport Height 8.22 133.33
1.01
-113.41
~ ~
-2.09 0.99 -444.92 G
0.92 G
0.86
Sohar Uwaynat -2.49 -4.33 DAS 126.37
0.96
-6.55
-189.70
50.95
4.35 4.32
Ghala -1.00 0.95
0.96
46.80
14.46
-0.98
62.40
26.09
24.10
14.04
0.93 0.93 0.93 0.93 0.92 0.92 0.93 0.92 0.92 0.92 -0.00
1.00 7.00 56.36 59.34
0.00 2.30 4 66.64
-46.65
73.89 74.47 54.35 53.85 95.21 128.15 88.02 90.70 124.35 149.12 114.26 132.41 85.01 0.00
3 0.00
-0.00 -9.56
29.96 29.53 21.45 21.24 39.47 0.97 36.41 37.10 0.94 62.46 48.89 1.00 34.94 66.64
31.53 31.68 -191.70 23.08 22.86 41.80 -5.88 39.25 40.94 0.93 0.93 -6.01 45.76 49.84 1.40 90.18 0.92 85.05 -85.01 36.39 0.00
-0.95 13 -0.95 13 -44.37 -0.95 15 -0.95 15 -0.95 12 -0.95 11 6 72.68 74.47 -0.95 8 -0.95 12 -0.12 102.03 13 18.88 -34.94 -0.95 13 0.92 0.86
-73.70 -74.30 33.24 -54.20 -53.70 -95.00 32.77 -87.80 29.43 29.75 -148.80 -114.00 12.88 42.72 12.13 12.13 -84.80 62.40 24.10
32.92 32.54 9 33.47 10 32.81 32.96 44.02
33.05 -24.22 -24.42 33.09 32.91 -17.81 -17.65 -31.22 0.99 -28.86 33.02 -48.91 1.00 -37.47 32.96 -27.87 26.09 14.04
1.00 -0.95 -0.95 -0.95 0.99 -0.95 32.92 0.98 42.27 33.93
1.00 31.53 31.68 1.00 1.00 23.08 22.86 41.80 -158.27 32.70 39.25 1.00 45.76 -153.25 49.84 1.00 1.00 36.39 32.89 5 5
-154.67 0.99 -90.50 32.99 -72.50 -74.30 -159.92 -149.82 -101.80 1.00 39.65
-0.99 -0.94 -0.88
24.88 -155.04 -154.69 -160.20 32.79 -149.10 -62.31 -24.07
-159.46 -29.75 1.00 -23.83 -24.42 -33.46 -143.41 7.26
-39.52 135.38
40.94 32.54 33.47 0.99 44.02 13 48.16 1.03 -21.97 -12.76
23.11 -157.00 -4.46
48.16 2.98 42.27 33.93
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
0.00
-1.00 3 0.95 1.00 1.00 0.00
-1.00 3 0.95 -1.00 -1.00 0.00
-1.00 3 0.95 -1.00 -1.00 -1.00 -1.00 0.95 0.00
-1.00 3 0.95 0.00
-1.00 3 -1.00 -1.00 0.95 0.00
-1.00 3 -1.00 -1.00 0.95 0.00
-1.00 3 -1.00 -1.00 0.95 0.00
-1.00 3 0.00
-1.00 3 0.95 -1.00 -1.00 -1.00 -1.00 0.95 0.00
-1.00 3 0.00
-1.00 4 0.95 -1.00 -1.00
-0.00
-0.00 73.70 0.00 0.00 0.00
-0.00 74.30 -0.00 -0.00 -0.00
-0.00 54.20 -0.00 -0.00 -0.00 -0.00 53.70 0.00
-0.00 95.00 -0.00
-0.00 -0.00 -0.00 87.80 0.00
-0.00 -0.00 -0.00 90.50 0.00
-0.00 -0.00 -0.00 148.80 0.00
-0.00 0.00
-0.00 114.00 -0.00 -0.00 -0.00 -0.00 101.80 0.00
-0.00 -0.00
-0.00 84.80 -0.00 -0.00
0.00
0.00 24.22 0.00 0.00 0.00
-0.00 24.42 0.00 0.00 0.00
0.00 17.81 0.00 0.00 0.00 0.00 17.65 0.00
-0.00 31.22 0.00
0.00 0.00 0.00 28.86 0.00
-0.00 0.00 0.00 29.75 0.00
-0.00 0.00 0.00 48.91 0.00
0.00 0.00
-0.00 37.47 0.00 0.00 0.00 0.00 33.46 0.00
-0.00 0.00
0.00 27.87 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 -1.00
1.00 3 0.95 1.00 1.00 -1.00
1.00 3 0.95 -1.00 -1.00 0.00 0.00 0.00 0.00 0.95 118.89
0 0 0 0 0 0 0 0 0 0 0 0 -0.00
0.00 72.50 0.00 0.00 -0.00
0.00 74.30 -0.00 -0.00 0 0 0 0 0 0 0 0 7.00 36.89

GCCIA Interconnection
0.00
-0.00 23.83 0.00 0.00 0.00 24.42 0.00 0.00 2.30 16.33
0.42 0.41 0.41 0.41 0.42 0.00 0.00 0.41 0.41 0.41
1.00 1.00 1.00 0.41 0.99 1.00 0 0 0 0 0.99 1.00 1.00
0.42 0.99 0.41
54.88 1.00 -124.69 -124.67 -129.46 -130.20 -129.92 1.00 -119.82 -119.10
-128.27 0.41 0.41 -123.25
-125.04
1.00 0.99
53.11 -127.00

New Ghubrah
~ ~
G G
Mawalleh North 0.81
85.80
0.86
86.10
0.00 MW 61.47
0.00 Mvar 224.08 50.64
88.32 83.59
1.00 1.02
3.54 0.81 0.86
0.95 85.80 86.10
-90.09 -164.68 164.73 40.00 61.47 -118.88 50.64
133.24 -37.17 -78.02 64.65 13.15 4 65.97 -40.45 3 62.43
-0.90
1.01 12.88 135.30 15.80 15.80 -0.85 16.33 -85.97
1.02 -85.65
-0.00
-0.00
1.44
4.26
2.94 Bousher -52.70
65.97
-42.78
62.43
0.92 0.92 0.92
123.39 127.90 129.13 133.24
52.88 56.19 135.36
0.92 -86.61 1.03 56.42 -129.33 85.97 1.01
52.39 54.82 54.97 4.08
90.09 14 -31.06 14 14 2.97 13 -41.06 42.78
37.17 23.94 17.64 26.56
38.62 32.87 33.10
-0.95 1.00 1.00 -0.95 -0.95 -0.95 33.04
32.78 1.00
-89.90 -149.28 -151.76 -123.10 -127.60 0.99 -128.80
-29.55 -40.46 -41.94 -152.30 -42.33 -151.95
38.62 52.39 54.82 54.97

1.00 1.00 1.00 -1.00


0.00
-1.00 4 0.00
-1.00 4 0.00
-1.00 4 -0.00
0.95 -1.00 -1.00 0.95 -1.00 -1.00 -1.00 -1.00 0.95 0.95 1.00
0.00
-0.00
-0.00 89.90 -0.00 -0.00 0.00
-0.00 123.10 -0.00 -0.00 -0.00 -0.00 127.60 0.00
-0.00 128.80 0.00
0.00
0.00 29.55 0.00 0.00 0.00
-0.00 40.46 0.00 0.00 0.00 0.00 41.94 0.00
-0.00 42.33 0.00
-0.00
OMCO 0.00
0 0
0.00
0 0 0 0
0.00 3 0.00

0.42 0.41
0.41 1.00 0.42
1.00 0.99
-121.76 -122.30 1.00
-119.28 -121.95
0.00 154.65 -371.69
-19.67 6.94 -34.46
1.44 11.51 27.27 86.66 129.42 -85.87
25.10 21.91 -51.92
223.72 23.94 17.64 26.56
1.02
3.55
-86.66 -129.42 85.87
-25.10 -21.91 51.92
0.98
Wadi Al Jazzi 30.05 21.85 34.06

Figure C.2 OETC Transmission System


217.03
47.20

133.92
34.67
-0.99 17
-216.83
Mahadha
-145.01 145.88 32.43 -32.33 123.14 193.01 0.00 MW
1.01
-1.18 Bureimi Industrial -34.13
25.09
35.06
25.09
-35.67
34.67
135.87
1.03
-9.94
9.21
5.18
9.21
28.26
21.14
48.92
33.24
0.00 Mvar
1.00
135.77
1.03
0.24
0.86

0.93
54.45
21.57
23.09 15
-0.95
90.56
12.56
15.40
10.90
-0.52
1.93
0.93
27.62
11.06
48.17

-0.95
7

33.22
1.01
0.95
7.00
2.30
-0.89
-15.92
-7.95
-0.98
-50.78
-9.92
64.53 13 72.09 12
-0.95
-50.59
-17.36
69.18 7
-0.96
-25.50
-7.25
-0.94
-57.97
-20.59
66.18 12 73.00 6
-0.97
-28.30
-7.38
-0.97
-61.77
-14.23
66.56 13 72.11 13
2018 Max. load Flow Condition -366.88
-143.33
29.17
220.69
1.00
8.14

-54.30 -27.50 27.75 0.93


32.96 -17.85 -9.04 366.88
23.09 48.17 0.86 0.96 0.91 0.94 0.92 0.95 0.96
1.00 16.00 51.00 50.80 25.60 58.20 28.40 62.00 133.00 143.33
-153.46 9.32 14.76 22.43 9.26 25.34 9.52 19.18 1.01 39.26
1.00 1.00 64.53 72.09 69.18 66.18 73.00 66.56 72.11 6.76 20
0.00 0.00 13.26 -13.22 -135.85 86.70 129.46 -85.82 68.52 87.17
1.00
-1.00
0.00
-0.00
0.00
0.00
3 -1.00
0.00
-0.00
0.00
0.00
3 0.95
27.50
9.04
1.00
0.00
0.00
1.00
0.00
0.00
134.33
1.02
Izki 14.38
4.47
-22.78
4.47
-38.78
23.96 -0.96 MSQ 25.20
30.05
135.58
1.03
21.88
21.85
-51.74
34.06
132.72
1.01
27.74
12.65
37.10
16.18
0.00 -366.50
-1.00
-0.00
0.00
-1.00
-0.00
0.00
0.95
54.30
17.85
-1.00
0.00
-0.00
0.00
-0.00
3 0.00 0.00
0 0
0.86
16.00
G
9.32
0.96
51.00
G
14.76
0.91
50.80
G
22.43
0.94
25.60
G
9.26
0.92
58.20
G
25.34
0.95
28.40
G
9.52
0.96
62.00
G
19.18
7.04
Sumail -106.55
39.26
3.14 3.86

0 0
0.00 0.42
1.01
0.42
1.01
~
58.32 ~
76.37 ~
76.91 ~
72.59 ~
81.91 ~
79.87 ~
70.16 0.93
54.43
0.93
75.77
0.93
74.57
57.75 57.75 21.41 30.01 29.45
0.41 86.90 22.99 -154.59 0.92 0.93 31.74 31.22 -69.87
1.00 54.68 -0.95 15 -90.47 101.42 13 47.66 -0.95 -0.95 -13.10
-123.46 17.64 -54.30 30.07 33.09 42.49 19.06 -75.60 -74.40 12.08
33.10 -17.85 1.00 43.65 1.00 40.43 14 10 -24.85 15 -24.45
1.00 22.99 -147.16 -0.95 0.00 32.88 31.74 31.22
-145.09 -101.20 0.00 -0.95 1.00
-33.26 0.00 -47.50 -146.48
43.65 -15.61
40.43
1.00 1.00 3 33.23
1.00 1.00 33.25
0.00 0.00 1.01
0.00 0.00 1.01
-1.00 4 0.95 -1.00 -1.00 -1.00 3 0.95 -1.00 -1.00 -1.00 -1.00 0.95 -1.00 -1.00 -1.00 -1.00 -1.00
-149.72
0.00
-0.00 -0.00
-0.00 -0.00 -0.00 -0.00 0.95 -149.79
-0.00
-0.00 -0.00
-0.00 0.95
54.30 -0.00 -0.00 101.20 75.60 -0.00 -0.00 -0.00 -0.00
0.00
-0.00 17.85 0.00 0.00 0.00
0.00 33.26 0.00 0.00 -0.00 47.50 3 0.00
-0.00 24.85 0.00 0.00 3 0.00
-0.00 74.40 0.00 0.00
0.00 0.00 0.00 15.61 0.00 0.00 24.45
0 0 0 0 0 0 0 0
0.42 0.42
1.00 1.00 0.42 0.42
0.41 1.01 1.01
-115.09 -117.16 1.00 -119.79 -119.72
-116.48

-90.56
-12.58 0.42 0.42
1.00 1.00

427.41
101.61
15.40

13.56
-115.35 -115.35

90.56 0.41 -427.41 0 0


-1.00 -1.00 0.95 -1.00 -1.00

0
12.58 1.00 155.16 -101.61
12.87
Ibri IPP 0 0
-113.51 92.02
30.07
12.11
-0.00
0.00
-0.00
0.00
42.20
13.87
3
-0.00
1.00
0.00
0.00
0.00
-0.00
0.00
3
-0.00
1.00
0.00
0.00
0.00
-0.00
0.00
-1.00 -1.00 0.95 -1.00
-0.00 -0.00 37.70 -0.00
1.00
0 0.00 0.00 12.39 0.00
0.00 -155.16
~ 4 0.00
-0.00
32.96
-92.02 33.11
G 0 0.00
1.00
-143.51 23.33
1.00
-145.35
-0.95
0.97 -42.20
0.93
860.00 -13.87
42.32 184.45
200.75 -0.95 17 16.14
17.71
-37.70 63.43
70.65 -12.39 17.71 135.51 32.64
-183.41 70.02 52.22 -52.20
15.89
1.03
133.31 132.49
Daghmar
-176.51

-150.57

-176.01
-215.95
150.57

176.51

0.97 6.46 -59.93 10.58 23.66 -24.11


1.01 1.00
6.34

7.68

7.68
860.00 32.64 12.08 135.39 9.80 9.80
155.18 4.64 4.30 132.35
200.75
67.93 176.01
215.95
New Izki 17
0.93 136.16
89.25
23.33 -0.94 Amerat 1.03
6.31 Yitti Quriyat 1.00
4.21
15 37.81 1.03 87.06 366.65 -344.29
0.90 105.40 12.10 0.93
7.68 14.77 -57.59 167.63
7.99 -122.72
344.79 41.83 1.32 12.10
-0.99 15.89 7.69 30.07 221.93 20 162.65
37.84 0.92
-858.04 176.51 19.32 1.57 113.40 4.80
1.01 37.84 -12.10 5.08 -104.65 0.93 0.91
-110.99 -150.79 11.14 49.35 -4.80 -43.86 52.43 52.20
67.93 6.34 413.04 -0.85 49.05 13 1.57
17
19.32
-0.95 14
20.20
-0.95 12
24.11
-284.36 -52.30 -52.00
1.03
17.27
225.59
0.80 20
-178.44
284.84
34.75
213.20
91.36
74.42
15.47
-0.95 Jahloot 32.90
1.00
-0.95
-113.10
-0.95
33.00
32.82
0.99
-147.89
22.52
-17.19
22.52
38.23
-17.09
38.23
10.91
0.99
-32.01
0.93 1.03 -798.51
0.91 -150.14 -12.00
34.75 -37.17 -3.94 1.00
669.53 11.76 -272.69
799.09 397.10 49.05 -144.16
0.95 20 364.56
44.24 0.99 5.08
257.83
46.32 12.00 44.24 16.46
-0.96 3.94 -0.80 1.00 1.00 1.00 1.00
376.11 -669.04 -176.01 -284.84
0.76 20 427.42 0.00
-1.00 3 0.95 -1.00 -1.00 0.00
-1.00 3 0.95 -1.00 -1.00 0.95 0.00
-1.00 3 0.00
-1.00 3 0.95 1.00 1.00
40.74 19 -182.29 -216.16 101.41
-213.20
285.04 0.00
-0.00 113.10 -0.00 -0.00 0.00
-0.00 12.00 -0.00 -0.00 52.30 0.00
-0.00 0.00
-0.00 52.00 0.00 0.00
27.27 46.32 7.68 36.80 409.20 12.11 0.00 0.00 0.00 0.00
245.92 1.02 0.00 37.17 0.00 0.00 -0.00 3.94 0.00 0.00 17.19 0.00 -0.00 17.09 -0.00 -0.00
36.80 15.37 -799.09 0.00 0.00 0.00 0.00
-364.56 0 0 0 0 0 0
24.94
0.41 0.41
0.41 0.99
1.00 0.41 0.99
229.71 -117.89 -2.01
292.94 -536.44 -120.14 1.00
141.55 1.04 -131.17 -114.16
23.55 11.81 15.22

536.45
130.98

-536.45
-130.98

-150.73

-540.51
540.51

150.73
15.22

15.37

15.37

15.37
0
0

-90.50 -53.24 -32.62 53.49 132.07 -86.51 128.75


-37.05
12.87
Bureimi 132.65
1.00
130.57
0.99
4.91
-20.50
19.71
132.36
1.00
5.54
14.59
6.35
32.66
-17.74
6.35
18.54
19.71
Nizwa 1.00
5.94
-56.44
17.64
0.98
5.62
125.93
0.95
6.09
804.83
-91.35
3.61
Al Hayl Bahla Jebreen Mudhaibi Ibra 262.29

0
-77.21 24.94
15.47
133.79 0.93 0.92 0.93 0.92 0.92 0.93
1.01 90.50 47.28 63.45 117.57 88.09 81.40 -804.83
-1.25 37.05 19.51 24.70 50.42 36.23 33.37 -262.29
38.81 -47.28 63.62 0.93 -30.83 27.16 55.70 0.00 51.14 -172.92 -40.09 39.06 -48.00 36.89 -81.40 23.19
-0.95 13 -19.51 -0.95 11 53.24 12 -39.29 14 20.64 -3.19 11 -12.24 91.35 -61.78 -0.95 11 9 -33.37
77.21 25.55
-90.30 8.70 -47.10 20.50 8.51 10.25 3.56 47.36 12.90 -87.90 10.23 15.76
23.07 33.04 20.65 32.89 32.96
-29.68 -15.48 33.09 32.90 32.92 1.00 -28.89 1.00
33.17 1.00 -0.95 1.00 -0.95 -0.95 1.00 -0.95
38.81 1.01 63.62 1.00 -148.77 39.06 -147.84 -147.24
29.80 -53.10 -147.28 -63.40 -146.93 -117.30 -81.20
-154.92 -17.45 -20.84 -38.55 -26.69
23.07 27.16 51.14 36.89

1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00


-1.00
-0.00
0.00
-1.00
-0.00
0.00
0.95
90.30
29.68
0.00
-1.00
-0.00
-0.00
0.00
0.00
0.00
3 1.00
0.00
0.00
1.00
0.00
0.00
0.95
47.10
15.48
0.00
-1.00
0.00
-0.00
0.00
-0.00
0.00
3 0.00
-1.00
0.00
-0.00
0.00
0.00
0.00
3 0.00
-1.00
0.00
-0.00
0.00
0.00
0.00
4 0.95
53.10
17.45
-1.00
-0.00
0.00
-1.00
-0.00
0.00
0.95
63.40
20.84
0.00
-1.00
-0.00
-0.00
0.00
-0.00
0.00
4 0.00
-1.00
-0.00
-0.00
0.00
0.00
0.00
4 0.95
117.30
38.55
-1.00
-0.00
0.00
-1.00
-0.00
0.00
Manah PS 0.00
-1.00
-0.00
-0.00
0.00
0.00
0.00
3 0.95
87.90
28.89
-1.00
-0.00
0.00
-1.00
-0.00
0.00
-1.00
-0.00
0.00
-1.00
-0.00
0.00
0.95
81.20
26.69
0.00
-1.00
-0.00
-0.00
0.00
0.00
0.00
4
Sur PS
0 0 0 0 0 0 0 0 0 0 0 0
0.42 0.42 0.42 0.41 0.41 0.42 0.41 0.41
1.01 1.00 1.00 1.00 1.00 1.00 ~ ~ 1.00 1.00 ~ ~ ~
-124.92 -0.20 -0.20 -117.28 -116.93 -118.77 G G -117.84 -117.24 G G G
0.96 0.98
74.10 162.00 540.51 804.83 411.67 0.96 0.91 0.96
20.18 31.46 -150.92 262.14 1.03 1083.50 492.13 138.50
66.06 50.01 15.37 23.19 20.66 305.98 219.27 38.15
69.50 63.31 67.76

Sinaw
0.96 0.98 -1.00 0.96 0.91 0.96
74.10 162.00 -1345.34 1083.50 -0.95
492.13 -0.99
138.50
20.18 31.46 -111.22 305.98 -491.17
219.27 -138.50
38.15
-55.65 173.66 -90.43 40.29 48.24 127.33 81.69
131.68
1.00
-22.00
10.25
14.30
47.36
132.91
1.01
4 56.89
-0.98
10 55.58
-0.99
130.96
0.99
6.07
-78.73
20.65
59.02
12.90
-31.76
10.23
Mudhairib 0.96
7.17
31.69
15.76
136.44
1.03
14 35.42
0.99
-0.98
15 69.28
-1081.06
-189.62
16 -166.63
64.91
64.91
15 -24.26
69.07
69.07
7.51 -73.95 -161.64 1345.80
5.63
Madinat Nizwa -14.94
56.89

You might also like