Professional Documents
Culture Documents
2020
Transmission
Capability Statement
(2020-2024)
Page | 0
Five-Year Annual Transmission Capability Statement (2020 - 2024)
Preface
This Transmission Capability Statement is provided by the Oman Electricity Transmission Company (OETC)
according to the Transmission and Dispatch Licence Condition number 27 and the Grid Code (Planning Code). The
Statement describes in detail the Main Interconnected System (MIS) and Dhofar Transmission System capability
over the coming five years 2020-2024. The Statement provides up-to-date transmission system data in order to
identify those parts of the system, which offer opportunities for future development of existing and potential users
of the system. In this Capability Statement, the results of load flow and short circuit analyses are presented based
on the planned system expansion reinforcement to meet the generation plan provided by Oman Power and Water
Procurement Company (OPWP) and the demand forecast provided by the Distribution Companies (MEDC, MJEC,
MZEC, DPC and RAEC). OETC grid model has been updated to include new projects schedule, demand forecast,
generation data and transmission system data. Thirty transmission projects at MIS and Dhofar System are planned
over the coming five-year period. Most of the projects designed to increase the transmission system capacity so that
it can meet future growth in demand, connect new generation and satisfy the security criteria.
The existing and planned development in the generation and transmission systems are described, including the
completion of projects in different voltage levels. The first 50 MW Wind Farm project in the Sultanate of Oman
commissioned in Dhofar transmission system in Q3 2019. Moreover, the transmission project of connecting the
first 500 MW Solar PV IPP in the Sultanate of Oman to the 220kV system at Ibri will be completed by Q4 2020.
In addition, transmission project of connecting 1000 MW Solar IPP in Manah is expected to be completed by Q2
2022. Each 500MW Solar plant at Manah will be connected to the transmission grid by Q2 2023 and Q2 2024.
Furthermore, a new generation connection to the Waste to Energy Plant (maximum capacity of 160MW) is
estimated to be completed by Q2 2024. Further, OPWP is proposing a 300MW of Wind plants to be connected to
the transmission system by Q2 2024. The proposed plants sites that considered by OETC and according to OPWP
sites selection are Jalan Bani Bu Ali and Duqm (maximum capacity of 100MW and 200MW respectively) to be
connected to the grid by Q2 2024. Moreover, RAEC has submitted two connection applications on 6th of January
2019 requesting for new grid stations at Mahout and Duqm areas. Further, PDO has submitted two connection
applications for Barik and Suwaihat sites on 12th of June 2019 requesting for 500MW export and import power at
each grid station. In addition, the new 400kV interconnection project will facilitate the connection to PDO system,
Duqm and Mahout Systems. Currently the project is in the design stage. The execution of the project will be in two
phases: the first phase will include constructing Suwaihat, Duqm and Mahout grid stations in order to displace the
diesel generation in Duqm and Mahout areas by Q2 2023. The second phase will be required for completing the
400kV OHL from Nahadah to Suwaihat with the construction of a new 400/132kV grid station at Barik area and
the expected completion date will be end of Q4 2024. Currently, OETC is carrying out a long term study (Master
Plan 2020-2040) to evaluate the future plan which includes transmission system reinforcements, connecting future
Renewable Energy Sources and future 400kV North – South Interconnector with Dhofar System. It is one of
OETC’s strategic planning concepts to introduce the 400kV system as a backbone to allow the power evacuation
from the centralized power plants and future Renewable Energy Resources. Major developments in the MIS include
the installation and operation of new 400kV transmission lines with associated new 400/132kV, 400/132/33kV and
400/33kV grid stations. In addition, the developments include the installation of 220kV and 132kV transmission
lines with associated new 220/132kV and 132/33kV grid stations at MIS and Dhofar system. OETC’s strategy is to
operate the 400kV system as a backbone, 220kV as a transmission system and 132kV as sub-transmission system.
Contents
Preface 1
List of Figures 5
List of Tables 7
Document History and Status 8
Distribution of Copies 8
Glossary 9
1. Executive Summary 10
2. Introduction 24
2.1 Licence conditions, Codes and Standards 24
2.2 2020 System Development since the 2019-2023 Statement 24
2.3 Improvements in the preparation of the Statement 25
3. Technical requirements for compliance with the Grid Code and Licence 26
3.1 Security of Supply 28
Page | 3
Five-Year Annual Transmission Capability Statement (2020 - 2024)
Page | 4
Five-Year Annual Transmission Capability Statement (2020 - 2024)
List of Figures
Figure 1: Summary of Planned Developments on OETC Transmission Systems (2020- 2024) 23
Figure 2: Number of Grid Stations at MITS by end of 2019 32
Figure 3: OHL & UGC Lengths (circuit/km) at MITS by end of 2019 33
Figure 4: Transformers Capacity (MVA) at MITS by end of 2019 33
Figure 5: Shunt Reactors (MVAr) at MITS by end of 2019 33
Figure 6: OETC transmission system at Dhofar by end of 2019 34
Figure 7: The existing private customers with 220kV Connections 35
Figure 8: The existing private customers with 132kV Connections 36
Figure 9: The Future private customers will be connected to OETC System 36
Figure 10: Existing MITS in Peak 2020 40
Figure 11: MITS expected development in Peak 2021 41
Figure 12: MITS expected development in Peak 2022 42
Figure 13: MITS expected development in Peak 2023 43
Figure 14: MITS expected development in Peak 2024 44
Figure 15: Dhofar existing transmission system in Peak 2020 45
Figure 16: Dhofar expected transmission system in Peak 2021 46
Figure 17: Dhofar expected transmission system in Peak 2022 47
Figure 18: Dhofar expected transmission system in Peak 2023 48
Figure 19: Dhofar expected transmission system in Peak 2024 49
Figure 20: Generation Percentage 2020 for both MIS & Dhofar 56
Figure 21: Generation Percentage 2024 for both MIS & Dhofar 56
Figure 22: MIS Load on 2019 Peak Day 62
Figure 23: Dhofar System Load on 2019 Peak Day 63
Figure 24: MIS Load on 2019 Minimum Load Day 65
Figure 25: Dhofar System Load on 2019 Minimum Load Day 65
Figure 26: Number of out-of-firm 132/33kV grid stations of MIS during 2020-2024 82
Figure 27: MIS Peak & off Peak Voltage profile at 400kV, 220kV, and 132kV and 33kV busbars in 2020 84
Figure 28: MIS Peak & off Peak Voltage profile at 400kV, 220kV, 132kV and 33kV busbars in 2024 85
Figure 29: DTS Peak & off Peak Voltage profile at 132kV and 33kV busbars in 2020 86
Figure 30: DTS Peak & off Peak Voltage profile at 132kV and 33kV busbars in 2024 87
Figure 31: Transmission power losses at peak demand of MIS of the years 2020-2024 88
Figure 32: Transmission power losses at peak demand of DTS of the years 2020-2024 89
Figure 33: Peak load growth of MITS System over the period 2020-2024 90
Figure 34: Peak load growth of Dhofar System over the period 2020-2024 90
Figure 35: Future Oman Electrical systems 93
Figure 36: Generation and load balance in Muscat area 99
Page | 5
Five-Year Annual Transmission Capability Statement (2020 - 2024)
Figure 37: Generation and load balance in Al Batinah South area 100
Figure 38: Generation and load balance in Al Batinah North area 101
Figure 39: Generation and load balance in Al Buraimi area 101
Figure 40: Generation and load balance in Al Dhahirah area 102
Figure 41: Generation and load balance in Al Dakhiliah area 103
Figure 42: Generation and load balance in Al Sharqiyah area 103
Figure 43: Generation and load balance in Al Wusta area 104
Figure 44: Generation and load balance in Dhofar area 105
Figure 45: Used and available MVA in Muscat area at 2024 peak demand 108
Figure 46: (Continued) Used and available MVA in Muscat area at 2024 peak demand 108
Figure 47: (Continued) Used and available MVA in Muscat area at 2024 peak demand 109
Figure 48: Used and available MVA in Al Batinah South area at 2024 peak demand 109
Figure 49: Used and available MVA in Al Batinah North area at 2024 peak demand 110
Figure 50: Used and available MVA in Al Buraimi and Al Dhahirah areas at 2024 peak demand 110
Figure 51: Used and available MVA in Al Dakhiliah area at 2024 peak demand 111
Figure 52: Used and available MVA in Al Sharqiyah area at 2024 peak demand 111
Figure 53: Used and available MVA in Al Wusta area at 2024 peak demand 112
Figure 54: Used and available MVA in Dhofar area at 2024 peak demand 112
Figure C. 1: MIS 2020 Max. Load Flow Condition 205
Figure C. 2: MIS 2021Max. Load Flow Condition 206
Figure C. 3: MIS 2022 Max. Load Flow Condition 207
Figure C. 4: MIS 2023 Max. Load Flow Condition 208
Figure C. 5: MIS 2024 Max. Load Flow Condition 209
Figure C. 6: Dhofar System 2020 Max. Load Flow Condition 210
Figure C. 7: Dhofar System 2021 Max. Load Flow Condition 211
Figure C. 8: Dhofar System 2022 Max. Load Flow Condition 212
Figure C. 9: Dhofar System 2023 Max. Load Flow Condition 213
Figure C. 10: Dhofar System 2024 Max. Load Flow Condition 214
Page | 6
Five-Year Annual Transmission Capability Statement (2020 - 2024)
List of Tables
Table 1: Summary of Planned Developments on OETC Transmission System (2020 - 2024) 14
Table 2: OETC Licensed Transmission System, System Parameter Values 27
Table 3: Demand Connections – Demand Class Specification 28
Table 4: Existing and committed future generating capacity 53
Table 5: New Contracted and Planned Generating Capacity 58
Table 6: Non-Contracted Generating Capacity 59
Table 7: Centrally Dispatchable and Non-Dispatchable Generating Capacity on OETC Transmission Systems 59
Table 8: Historic Growth in Peak Demand and Transmission Losses (2003 – 2019) 63
Table 9: Expected Load Transfers between Grid Supply Points (2020-2024) 67
Table 10: OETC Transmission System Net Demand Forecast by Grid Station 70
Table 11: Comparison of Net Demand Forecast with Available Generating Capacity including Planned
Retirements 75
Table 12: Comparison of Net Demand Forecast with Available Generating Capacity and Non-Contracted
Generation in service 76
Table 13: Summary of Connected Generation Used in Load Flow Studies of Maximum Demand 78
Table 14: Summary of Connected Generation Used in Load Flow Studies of Minimum Demand 79
Table 15: Estimated Power Surplus and Power Deficit on an Area Basis (2020-2024) 94
Table 16: Available Grid Station Capacity of more than 10 MVA in 2024 106
Table 17: Potential Generation Connections for 2024 115
Table 18: Expected Over headlines/Cable, which will not comply with Transmission Security Standard (First
Outage) at Peak Demand in 2020 118
Table 19: Expected Grid stations 132/33kV, which will not comply with Transmission Security Standard (First
Outage) at Peak Demand in 2020 119
Table 20: Expected Grid stations 132/33kV, which will not comply with Transmission Security Standard at
Maintenance Period in 2020. 120
Table B. 1: Load and Capacitor Data for Grid Station (2020-2024) 128
Table B. 2: 2020 Branch Data Listing 136
Table B. 3: Progressive Change to Branch Circuit Data for 2020-2024 141
Table B. 4: Grid Station Transformers Data at 2020 Peak 145
Table B. 5: Grid Station Transformers Data from 2020 to 2024 154
Table C. 1: Transformers Loading (%) at Grid Stations (2020-2024) 158
Table C. 2: Available Capacity at Grid Stations (2020-2024) for Connection of New Demand 163
Table C. 3: Overhead Line and Cable Circuit Loadings (%) at Peak Demand (2020-2024) 168
Table C. 4: Transmission System Voltage Profile at Peak Demand (2020-2024) 175
Table C. 5: Transmission System Voltage Profile at Minimum Demand (2020-2024) 183
Table C. 6: Estimation of Transmission Losses and Generation Margin at Peak Demand (2020-2024) 191
Table C. 7: Maximum 3-Phase Short Circuit Fault Levels 192
Table C. 8: Maximum 1-Phase Short Circuit Fault Levels 200
Page | 7
Five-Year Annual Transmission Capability Statement (2020 - 2024)
Network Planning
D.2 20/02/2020 Department CEO 29/02/2020 Final draft
Network Planning
D.3 05/03/2020 AER 07/04/2020 Final draft
Department
Distribution of Copies
Printed: 09/04/2020
Document ve rsion: V.0 As Approved by the Authority for Electricity Regulation on April 2020
Page | 8
Five-Year Annual Transmission Capability Statement (2020 - 2024)
Glossary
AAAC All Aluminium Alloy Conductor
AER Authority for Electricity Regulation, Oman
AIS Air Insulated Switchgear
CEO Chief Executive Officer
DISCOs Distribution Companies
DTS Dhofar Transmission System
DPC Dhofar Power Company (SAOC)
GCCIA Gulf Cooperation Council Interconnection Authority
GIS Gas Insulated Switchgear
GS Grid Station
GT Gas Turbine
HV High Voltage
IPP Independent Power Producer
IWP Independent Water Producer
IWPP Independent Water and Power Producer
kV kilovolt
LILO Line In Line Out
LV Low Voltage
MEDC Muscat Electricity Distribution Company (SAOC)
MV Medium Voltage
MIS Main Interconnected System
MITS Main Interconnected Transmission System
MJEC Majan Electricity Company (SAOC)
MVA Mega Volt Ampere
MVAr Mega Volt Ampere reactive
MW Megawatt(s)
MWh Megawatt hour(s) = (1,000) kWh
MZEC Mazoon Electricity Company (SAOC)
NPV Net Present Value
OES Oman Electrical Standard
OETC Oman Electricity Transmission Company (SAOC)
OHL Overhead Line
OPWP Oman Power and Water Procurement Company (SAOC)
PAW Public Authority for Water
PDO Petroleum Development Oman (LLC)
PS Power Station
PV Photovoltaic
RAEC Rural Areas Electricity Company (SAOC)
SCADA Supervisory Control and Data Acquisition
SF6 Sulfur Hexafluoride
ST Steam Turbine
SVC Static Var Compensator
TSS Transmission Security Standard
UAE United Arab Emirates
UGC Underground Cable
WTE Waste To Energy
Page | 9
Five-Year Annual Transmission Capability Statement (2020 - 2024)
1. Executive Summary
This Capability Statement presents the Oman Electricity Transmission Company’s development plans for the
400kV, 220kV and 132kV transmission systems for the years 2020 to 2024 in both Main Interconnected
Transmission System (MITS) and Dhofar Transmission System (DTS). DTS has been transferred to Oman
Electricity Transmission Company (OETC) on 1st of January 2014. This document describes the development plans
for both MITS and DTS.
The Statement includes data for the generators, loads, overhead lines, cables, transformers, reactive power
compensators and capacitor banks used in the development of transmission system models. In addition, the
Statement includes the demand and generation forecast. The power system studies undertaken by OETC’s
DIgSILENT Power Factory software, version 17.0.4, in preparation of this Capability Statement. The Statement
also includes the results of power system analysis of the transmission system that defines system performance when
operating under the extreme system peak (summer season) and system off peak (winter season) in each of the five
years. From this analysis, assessment has been made of the opportunities for the connection of new generation, new
demand and reinforcement on the system.
Table 1 lists the schedule for committed and planned system development projects on the 400kV, 220kV and 132kV
transmission systems, although it should be noted that not all of the planned projects listed have full authorisation
at this time. The 400kV system development in MITS, includes the installation of 400kV systems to the existing
220/132kV and 132/33kV grid stations. Furthermore, one 400/132/33kV, five 400/132kV and one 400/33kV grid
station will be installed during the period of this Capability Statement. In addition, two 220/132kV and seven
132/33kV grid stations in MITS will be energized during the period of this Capability Statement.The total number
of both MITS and DTS of 400kV, 220kV and 132kV grid stations will also increase from ninety nine by the end of
2020 to hundred and fifteen by the peak of 2024.
It is one of OETC’s strategic planning concepts to introduce the 400kV system as a backbone to allow the power
evacuation from the centralized power plants towards the demand. Furthermore, OETC has installed 220kV double
circuit lines around northern Oman to supply and support the 132kV system. In 2010, the 220kV connections
between Sohar Interconnector Station (SIS) and Mahadha (Al-Wasit) were completed to support linking Oman
(OETC) network with the GCCIA Grid through UAE (Transco Abu Dhabi) network. In addition, Khaborah
Interconnection Station (KIS) is expected to be completed by August 2020 to increase the system reliability within
Al Batinah North region. Eventually, Nizwa 220/132kV grid station will be connected via 220kV OHL to New Izki
grid station by peak 2024. The purpose of this project is to maintain transmission security standard requirements
and to increase the system reliability within Al Dhakilyah region.
OETC has introduced the first 400kV system including 400kV connection between Jahloot grid station and Sur
power station and line between Sur power station and New Izki grid stations in 2016. In 2018, OETC introduced a
new 400kV OHL from Ibri IPP to New Izki grid stations and a new 400/220kV grid station at Ibri. Furthermore,
400kV transmission lines have been installed in 2019, between Sohar Free Zone – Shinas (operated as 132kV) and
Sohar Free Zone-SIS, Sohar Free Zone-Mahadha (operated as 220kV). In the same year, 400kV connections of
Sohar-3 IPP and Sohar Free Zone 400kV grid station were energised. Moreover, a LILO connection from Sur-New
Izki 400kV line at Qabel area with introduction of a new 400/132kV grid station. Furthermore, New Izki-Misfah
400kV OHL is expected to be completed by peak 2021. In peak 2022, the connection of Manah Solar IPP through
LILO Ibri IPP – New Izki 400kV OHL will be completed. Construction of Al Jefnen 400/132kV and New Rustaq
Page | 10
Five-Year Annual Transmission Capability Statement (2020 - 2024)
400/132kV grid stations will be completed by peak 2023 and 2024 respectively. In addition, the North – South
interconnection project (part 1 until Duqm and Mahout) will include new 400kV grid stations at Suwaihat, Mahout
and Duqm area with associated lines for phase-1. Whereas, phase 2 will include construction of Barik grid station
and the connection of it to Nahadah and Suwaihat 400kV grid stations and this phase is expected to be completed
by December 2024. Accordingly, the MITS will have sixteen 400kV grid stations at Sur, Jahloot, New Izki, Misfah,
Ibri IPP, Sohar III IPP, Sohar Free Zone, SIS, Qabel, Al Jefnen, Manah Solar IPP, New Rustaq, Suwaihat, Nahadah,
Mahout and Duqm by peak 2024. The total installed capacity of 400kV grid stations will be around 20,250 MVA
in peak 2024. In accordance with Condition 27 of OETC’s Transmission and Dispatch Licence, the power flow
studies presented in this Capability Statement are based on updated demand forecast data provided by Distribution
Companies (DISCOs) and the updated generation forecast by Oman Power and Water Procurement Company
(OPWP).
To be able to perform the studies and produce the results presented in this Statement, the deadlines to receive data
from the various parties (OPWP and DISCOs) are as per the Grid Code requirements. For the demand forecast,
DISCOs have an obligation to submit the data by end of September. Regarding the generation data, OPWP has an
obligation to submit the data by end of October. Any information received after the deadlines will be included in
the next Five-Year Annual Transmission Capability Statement (2021-2025).
The introduction of Cost Reflective Tariff (CRT) in 2017 has affected the major customer’s consumptions and
expected to have more influence in the coming years on the demand forecast. “The Authority’s view is that Cost
Reflective Tariffs are required to moderate and help in managing expected increases in electricity subsidy as a result
of: significant growth in electricity demand and the investment needed to supply it, increasing electricity intensity
of consumption, the requirement to use more expensive alternatives to local natural gas, and certain technical
deficiencies of existing Permitted Tariffs”. The forecast average annual growth in the system demand is about 5%
for MITS and 9.7% for DTS, which drives many of the planned grid station reinforcements over the period from
2020 to 2024. The high growth DTS is due to operation of Salalah Methanol plant and increasing in suppling bulky
customers in 33kV level as well as extending the DTS to supply Saih Al Khairat load (which was supplied by
RAEC previously). To meet security of supply requirements and provide load relief to the loaded grid stations, it
will be necessary to transfer excess load to the new or existing grid stations.
Moreover, RAEC has submitted a connection application dated 25th of December 2014 for the first Wind Farm
Plant to be connected to DTS with 50 MW installed capacity and it was energised in Q3 2019. OPWP has submitted
a connection application dated 20th of November 2017 for the first Solar PV IPP to MITS with a 500 MW installed
capacity in Ibri and it will be in service by peak 2022. In addition, OETC also has received an application from
OPWP regarding the connection of 1000 MW Solar IPP in Manah, which is expected to be in service by peak 2023
for phase 1 and peak 2024 for phase 2. Furthermore, OPWP has proposed a new type of generation plant (Waste to
Energy Plant) which is expected to be in service by peak 2024. Eventually, OPWP has mentioned two wind projects
in their generation plan (2020-2024) with a total capacity of 300 MW in Duqm and JBB Ali (expected to be in
service by peak 2024).
As the demand grows, there is a greater need to extend the transmission system and to establish new 400kV network
as a backbone to transmit the bulk power from power plants. This will reduce the overload at the 220kV and 132kV
networks and subsequently improve voltages and reduce power losses. Consequently, the 220kV will be operated
as a transmission system and the 132kV as a sub-transmission system.
Page | 11
Five-Year Annual Transmission Capability Statement (2020 - 2024)
Table 1 shows thirty transmission projects that are planned over the five-year period. Most of the projects are
designed to increase the transmission system capacity. This is a major programme of capital investment that will
be spread across the whole network to improve transmission system performance in northern and southern Oma n.
Power system studies presented in this Statement confirmed that the planned investment in 400kV, 220kV and
132kV grid stations and transmission circuits will provide substantial spare capacity on the transmission systems.
From 2020 to 2024, the fault levels across the transmission system are within the corresponding switchgear short
circuit ratings. The major technical issue identified in the studies was the high short circuit fault levels on the 132kV
busbars at six grid stations in Muscat area from 2020 to 2024. The grid stations are Mobella, Seeb Main, Rusail,
Airport Heights, Mawalleh South and Madinat Sultan Qaboos (MSQ). During the period from 2020 to 2024, OETC
will address this problem in the short–term by splitting the 132kV bus bars or opening some of the 132kV lines at
Muscat region without affecting the security requirements. Therefore, there will be a need for 132kV busbars
splitting to reduce the short circuit level at Seeb Main grid station from 2020 to 2023, Ghala Heights grid station in
2020 and Mawalleh South grid station in 2021 and 2023 due to the network development and reconfiguration works.
In addition, some of the 132kV lines will still be opened to reduce the infeed short circuit contribution and this is a
part of OETC long-term strategy to operate 400kV and 220kV as the main transmission system. The strategy is
implemented with zero cost and risk. There will be no investment required to reduce the fault level as system can
be operated safely and meeting the Transmission Security Standard requirements.
Load flow studies have confirmed that the voltage levels across the transmission system will be maintained within
the limits. The 400kV voltage will be maintained in the system within the allowable limit ±5%. In addition, as
defined in the Grid Code, the 220kV and 132kV will be maintained within ±10% and the 33kV will be maintained
within ±6%. Furthermore, the load flow has presented the issue of overvoltage during the winter peak time due to
the 400kV lines. Accordingly, OETC has initiated a number of projects to install shunt reactors in the 400kV lines
to overcome the overvoltage issue during winter peak time. All shunt reactors at the 400kV circuits have been
installed and working efficiently to absorb the MVAr from the network during the winter and off peak time.
The Statement has reviewed the opportunities for the connection of new generation and new demand and therefore
identified those grid stations with substantial spare capacity where it should be possible to connect new demand to
the system.
Section 2 of the Statement provides an introduction to the document, identifying the main related documentation
and the key changes that have taken place on the transmission system since the previous issue of the Statement.
Section 3 identifies the technical requirements of the Grid Code and the Transmission Licence with specific
attention to system voltage, frequency and security of supply.
Section 4 describes the main engineering standards used by OETC in its planning and design of the transmission
system.
Section 5 describes the existing transmission system and summarises the planned developments in each year over
the period from 2020 to 2024.
Section 6 identifies the existing and planned developments in generation and describes the interconnections both
inside Oman and internationally, i.e. PDO, RAEC and the GCCIA respectively.
Section 7 presents the comparison of demand forecast with the generation capacity available.
Page | 12
Five-Year Annual Transmission Capability Statement (2020 - 2024)
Section 8 discusses transmission systems performance and presents the results of load flow and short circuits studies
that show the performance of the transmission system at both peak and off peak demand in each year from 2020 to
2024.
Section 9 identifies the development opportunities for the connection of new demand and new generating plants to
the transmission systems.
Section 10 presents the areas of the network that will be operating above the firm capacity and non-compliance
with Transmission Security Standard in 2020.
Page | 13
Five-Year Annual Transmission Capability Statement (2020 - 2024)
Expected
S.N Project Completion Status Main Equipment Purpose
Date
Peak 2020
Page | 14
Five-Year Annual Transmission Capability Statement (2020 - 2024)
Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2020 - 2024)
Expected
S.N Project Completion Status Main Equipment Purpose
Date
Peak 2020
Peak 2021
Page | 15
Five-Year Annual Transmission Capability Statement (2020 - 2024)
Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2020 - 2024)
Expected
S.N Project Completion Status Main Equipment Purpose
Date
Peak 2021
Page | 16
Five-Year Annual Transmission Capability Statement (2020 - 2024)
Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2020 - 2024)
Expected
S.N Project Completion Status Main Equipment Purpose
Date
Peak 2021
Page | 17
Five-Year Annual Transmission Capability Statement (2020 - 2024)
Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2020 - 2024)
Expected
S.N Project Completion Status Main Equipment Purpose
Date
Peak 2022
Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2020 - 2024)
Expected
S.N Project Completion Status Main Equipment Purpose
Date
Peak 2023
Page | 19
Five-Year Annual Transmission Capability Statement (2020 - 2024)
Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2020 - 2024)
Expected
S.N Project Completion Status Main Equipment Purpose
Date
Peak 2023
Page | 20
Five-Year Annual Transmission Capability Statement (2020 - 2024)
Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2020 - 2024)
Expected
S.N Project Completion Status Main Equipment Purpose
Date
Peak 2024
. 5 no. 132kV GIS at WTE grid station .To meet Transmission Security
June Standard
26 Connection of WTE IPP Design . 2 no. 132kV GIS at Madinat Barka grid station
2024 . To evacuate power coming from WTE
. 3.6 km OHL WTE IPP – Madinat Barka grid station IPP
Page | 21
Five-Year Annual Transmission Capability Statement (2020 - 2024)
Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2020 - 2024)
Expected
S.N Project Completion Status Main Equipment Purpose
Date
Peak 2024
. 2x500 MVA, 220/132kV Transformers at Nizwa grid station
. 1x500 MVA, 400/220kV Transformer at New Izki grid station
. 6 no. 220kV GIS at Nizwa grid station ·To maintain Transmission Security
June . 2 no. 220kV GIS at New Izki grid station Standard requirements
28 Nizwa 220/132kV grid station Planning
2024 . 2 no. 132kV AIS at Nizwa grid station · To increase the system reliability
. 1.1 km 220kV UGC (New Izki – Nizwa) from Nizwa side within Al Dhakilyah region
. 3.6 km 220kV UGC (New Izki – Nizwa) from New Izki side
. 53.9 km 220kV OHL (New Izki – Nizwa)
. 6 no. 132kV GIS at Duqm wind farm · To evacuate power coming from
June Duqm Wind Farm
29 Duqm wind farm connection Planning . 2 no. 132kV GIS at Duqm grid station
2024 · To meet Transmission Security
. 49.7 km 132kV OHL (Duqm wind farm – Duqm) Standard
. 6 no. 132kV GIS at JBB Ali wind farm · To evacuate power coming from JBB
June Ali Wind Farm
30 JBB Ali wind farm connection Planning . 2 no. 132kV GIS at Al Jawabi grid station
2024 · To meet Transmission Security
· 9 km 132kV OHL from Al Jawabi to JBB Ali wind farm Standard
Page | 22
Five-Year Annual Transmission Capability Statement (2020 - 2024)
Figure 1 shows the summary of planned developments on OETC Transmission Systems (2020-2024).
6
Number of Projects
0
Peak 2020 Peak 2021 Peak 2022 Peak 2023 Peak 2024
Yea r
Page | 23
Five-Year Annual Transmission Capability Statement (2020 - 2024)
2. Introduction
The purpose of the Statement is to provide up-to-date transmission system data for potential and existing
users of the transmission system so they can identify those parts of the transmission system that offer the
opportunity for future development. The Statement should be updated annually so that existing and new
users of the transmission system are furnished with the latest information.
New users of the transmission system should be aware of the following main documents that influence the
planning and future development of the transmission system infrastructure:
i) The Electricity Transmission and Dispatch Licence granted to OETC by the AER.
iv) The Statement of Charges for Connection and Use of System to OETC Electricity
Transmission System (Condition 25 of OETC’s Transmission and Dispatch Licence).
2. 400kV line connections between Sohar Free Zone – Mahadha and Sohar Free Zone – SIS grid
stations.
5. Construction of a new 400kV OHL from Sohar Free Zone GS to Shinas GS.
6. Adding third & fourth transformers 132/33kV at Airport Heights grid station.
Page | 24
Five-Year Annual Transmission Capability Statement (2020 - 2024)
i. Updating the demand forecast data according to the received information from the DISCOs.
ii. Updating the generation plan according to the received information from the OPWP.
iii. Updating the operational limits of generating units according to the received information
from the OPWP.
iv. Updating the transmission system data for the new projects as per the actual parameters.
v. Updating the new generating units data as per the actual parameters.
vi. Introducing a new 400kV OHL which is part of North-South Interconnector that connects
PDO and RAEC areas.
vii. Introducing results for the losses per voltage level and voltage profile for all grid stations.
viii. Introducing a new section regarding potential generation connection (section 9.3).
ix. Introducing PDO network in OETC system models of the northern part.
x. Modelling of Renewable Energy Resources that includes Solar, Wind and Waste to Energy
plants.
The improvements in the demand forecast and the power system modelling should result in similar
improvements being achieved in the accuracy of the power system studies upon which network
development planning is based.
Page | 25
Five-Year Annual Transmission Capability Statement (2020 - 2024)
3. Technical requirements for compliance with the Grid Code and Licence
The Grid Code is designed to permit the development, maintenance and operation of an efficient,
economical and coordinated electricity transmission system. It facilitates competition in the generation and
supply of electricity and promotes the security and efficiency of the system as a whole.
The Transmission Security Standard required the capacity of the Transmission System to transmit
electricity and shall not be reduced in the event that a single electric line, transformer or breaker and/or
associated plant is not in service. The operating voltage of the Transmission System shall be maintained
within the limit specified in the Grid Code and TSS.
In order to comply with Condition 26 of the Electricity Transmission and Dispatch Licence the transmission
system must be planned, designed and operated to provide a secure, efficient and economic supply of
electricity that is of an acceptable quality to its users. Subject as provided in the Grid Code, OETC shall
ensure that the Electricity Transmission System complies with the following technical, design and
operational criteria in relation to the part of the Electricity Transmission System at the Connection Site with
a User (unless otherwise specified in the Grid Code). Although in relation to operational criteria, OETC
may not be able to comply with this obligation to the extent that others parties are not complying with the
Grid Code. Each User shall ensure compliance with the criteria set out in the Grid Code (CC.6.1.5). Whilst
Condition 26 specifically sets out the Security of Supply requirements, the most important characteristics
that determine the quality of supply are frequency and voltage. The requirements for maintaining
transmission system frequency and voltage within specified operating limits are set out in the Grid Code,
and most clearly defined under conditions CC.6.1.1 and CC.6.1.2 respectively of the Connection Conditions
Code.
Grid Code establishes the historic frequency and voltage performances of the transmission system,
specifically in relation to operation at abnormal voltages and frequencies. It considers how future generation
and demand changes may affect transmission system performance in these areas. It establishes the relevant
generation design criteria and standards, and the impacts of operation at abnormal voltages and frequencies
on generating units. It considers whether the current Grid Code frequency and voltage requirements are
appropriate, taking into account of the system security requirements, the capabilities of generating units,
and the industry costs and benefits of implementing them.
For the purposes of the TSS and in respect of frequency and voltage, four conditions are identified for
determining system parameter values, as follows:
Normal conditions – being conditions that apply on a continuous basis; these are the preferred
conditions of the OETC licensed transmission system
Disturbed conditions – being conditions in which the voltages are the same as for normal
conditions, but the frequency limits have been changed and include, as a lower limit, the Normal
Infeed Loss Risk frequency limit
Page | 26
Five-Year Annual Transmission Capability Statement (2020 - 2024)
Time limited Stretched Conditions that may only be experienced for no more than sixty
continuous seconds
Unacceptable Conditions – being conditions that are never allowed in planning, design or operation
Transient frequency deviations that occur outside the limits of continuous operation Stretched Conditions
and last less than sixty seconds shall only occur at reasonably infrequent intervals. This governs all relevant
TSS criteria. Table 2 sets out the required values for the system parameters.
Unacceptable conditions
Stretched conditions
Disturbed conditions
Parameter
Normal conditions
Low High Low High Low High Low High Low High
Target
˂ ≥ ˂ ≥ ˂ ≥ ≤ > ≤ > ≤ >
During some system’s disturbances, such as where short circuits occur, the voltage could collapse
transiently to zero at the point of fault until the fault is cleared. Voltage regulation requires both active and
reactive power flows across the transmission system to be carefully controlled. The physical characteristics
of the plant on the transmission system also give rise to the generation and absorption of reactive power.
Reactive power flows across the transmission system can give rise to substantial voltage differences and it
is therefore necessary to maintain reactive power balances between sources of capacity and demand on a
“zone” basis.
Unlike frequency, which is consistent across an interconnected transmission system, voltages at different
points on an interconnected system are determined by the local sources of demand and capacity, by the
prevailing network configuration and the reactive power flows across the network. The management of
voltage requires control of reactive power that can be provided by generation units, transformer tap-
changers, capacitor banks at 33kV or below, shunt reactors, series capacitor or by means of static VAR
compensator (SVC).
Page | 27
Five-Year Annual Transmission Capability Statement (2020 - 2024)
Demand Connections
Demand Class definition and supply restoration times
Demand Class
Demand Class
Repair time of
A 0 2 No requirement
faulted circuit
B 2 6 3 hours No requirement
Return time of
C 6 20 15 minutes Maintenance
Planned Outage
Total Group Period Demand
Demand for the Demand
M omentary Group
Return time of
D 20 115 Interruption
Planned Outage
allowed1
M omentary M omentary
E 115 300 Interruption Interruption
allowed allowed
F 300 No loss of supply for the Secured Events described in the M ITS design criteria
1
The duration of M omentary Interruption allowed is one minute
Page | 28
Five-Year Annual Transmission Capability Statement (2020 - 2024)
In addition to the technical requirements of the Transmission Licence and the Grid Code, the principal
electrical standards used by OETC in its planning and design of the 400kV, 220kV and 132kV transmission
systems are:
Page | 29
Five-Year Annual Transmission Capability Statement (2020 - 2024)
The standard covers the operation parameters of outdoor transmission assets and defines the worst-case
conditions for system design purposes by the following:
Page | 30
Five-Year Annual Transmission Capability Statement (2020 - 2024)
4.13 Standard specification for Underground Cable Circuits above 33kV up to 150kV
(OETC-AMP-O-AMT-M-022):
The standard covers the design requirements for 33kV up to 150kV underground XLPE cable circuits and
accessories.
4.14 Standard specification for Underground Cable Circuits above 150kV up to 400kV
(OETC-AMP-O-AMT-M-021):
The standard covers the design requirements for more than 150kV up to 400kV underground XLPE cable
circuits and accessories.
Page | 31
Five-Year Annual Transmission Capability Statement (2020 - 2024)
The transmission system was first established under the Ministry of Electricity and Water (MEW) in 1983
and underwent rapid expansion during the 1990s. Consequently, most of it has less than 15 years of service
experience. After the electrical sector was unbundled, the OETC took over the operation of the MITS on
1st of May 2005 and Dhofar Transmission System on 1st of January 2014.
Figure 2 to Figure 5 show the OETC transmission system at MITS by the end of 2019 while Figure 6 shows
the transmission system at Dhofar.
Page | 32
Five-Year Annual Transmission Capability Statement (2020 - 2024)
3685.1
4000
3000
ci rcui t-Km
1743.2
2000 1291.2
0
400kV 220kV 132kV
OHL UGC
25000 21020
20000 14130
12750
15000
MVA
10000
5000 1000 570 150
0
400/220kV 400/132kV 220/132kV 220/33kV 132/33kV 132/11kV
Transformers Capacity
Page | 33
Five-Year Annual Transmission Capability Statement (2020 - 2024)
The OETC transmission system at MITS is also interconnected with the Sohar Aluminium system at 220kV
via a double circuit cable that run between SPS-1 on the OETC system and Sohar Aluminium 220kV busbar.
The import or export schedule will vary on a yearly basis as per OPWP and Sohar Aluminium Company
agreement and this can reach up to 300MW.
The OETC transmission system at MITS is also interconnected with the PDO transmission network at
132kV via a single circuit overhead line that runs between Nizwa on the OETC system and Nahadah on the
PDO system. This single circuit is owned, operated and maintained by PDO. In addition, OETC
transmission system at Dhofar is also interconnected with the PDO transmission network at 132kV via a
single circuit overhead line that runs between Dhofar Wind Farm at OETC system and Harweel at PDO
system. This single circuit is owned, operated and maintained by OETC. Under normal conditions, the
power transfer across the PDO interconnection is forecasted to be negligible, but in the event of an
emergency on either network, the interconnection can facilitate a power transfer to address the shortfall.
Page | 34
Five-Year Annual Transmission Capability Statement (2020 - 2024)
The transmission system at MITS area is supplied with electricity generated from eleven gas-based power
stations located at Rusail IPP, Manah IPP, Al Kamil IPP, Barka I Power & Desalination Plant (ACWA),
Barka II IPP (SMN), Barka III IPP, Sohar I Power & Desalination Plant, Sohar II IPP, Sohar III IPP, Sur
IPP and Ibri IPP. In addition, the transmission system may be supplied from direct customers, such as Sohar
Aluminium. The transmission system at Dhofar area is supplied with electricity generated from three gas-
based power stations located at NPS, Salalah Power & Desalination Plant and Salalah II IPP and new wind
farm located at Harweel area with a capacity of 50MW.
Four Distribution and Supply License holders, i.e. Muscat Electricity Distribution Company (MEDC),
Mazoon Electricity Company (MZEC), Majan Electricity Company (MJEC) and Dhofar Power Company
(DPC), take the bulk of the power transmitted through the main grid stations to supply the Distribution
system. In the near future, OETC will also transmit the power to RAEC in order to supply some of their
areas.
In addition to the four Distribution Companies, large private customers are directly connected to the
transmission system. The existing private customers with 220kV Connections are as shown in Figure 7
while Figure 8 shows the customers with 132kV Connections.
Page | 35
Five-Year Annual Transmission Capability Statement (2020 - 2024)
The new customers that will be directly connected during the period covered by the Statement is as shown
in Figure 9.
In 2019, MIS gross peak demand was 6539.75MW, which occurred at 14:55:29 hours on 30th of June; and
represented an increase of 3.2% on the 2018 peak demand. During 2019, the electric energy delivered to
the MIS from connected generating plants and other generators was 32,584.45 GWh whilst the exported
energy from the MIS to the Distribution Companies was 32,054.70 GWh resulting in transmission system
energy losses of 529.74 GWh, which equates to a transmission system energy loss of 1.63%.
Page | 36
Five-Year Annual Transmission Capability Statement (2020 - 2024)
In 2019, Dhofar system gross peak demand was 594.48MW, which occurred at 04:04:45 hours on 14th of
June; and represented an increase of 4.9% on the 2018 peak demand. During 2019, the electric energy
delivered to the Dhofar transmission system from connected generating plants and other generators was
3,418.62 GWh whilst the exported energy from Dhofar system to Dhofar Power Company was 3,397.19
GWh resulting in transmission system energy losses of 21.44 GWh, which equates to transmission system
energy losses of 0.63%.
The power system studies presented later in this Capability Statement used to define the constraints and
opportunities that exist on the transmission system over the next five years. The power system studies have
been performed on the basis that the committed and planned development projects detailed in Appendix A
and summarized below will proceed as planned and be completed to the current schedule.
Figure 10 and Figure 15 show in a geographic map the system arrangement to meet the 2020 peak demand
of MITS and DTS respectively. In section 2.2 of this Statement, it was noted that a number of projects had
been completed since the published Capability Statement 2019-2023, so that they were available to meet
the peak demand of summer 2020. Reinforcement projects such as adding third and fourth 132/33kV 125
MVA transformers with four 33kV GIS interlink at Airport Heights grid station was energized to meet the
Transmission Security Standard and load growth in the area. In addition, two 400kV lines were energized
61.78km from Sohar Free Zone to Mahadha grid stations (operate as 220kV) and 33.34km from Sohar Free
Zone to SIS grid stations. Moreover, 1x500 MVA transformer added at SIA grid station with 3.7km 220kV
UGC from SPS to SIA to meet TSS at SIA during maintenance period. Furthermore, new 132/33kV grid
station at Birkat Al Mouz was energized with 2x125 MVA transformers and connected via 2.6km 132kV
OHL LILO of Izki - Nizwa. New 30km 400kV OHL was constructed from Sohar Free Zone to Shinas grid
station that and operated as 132kV to meet TSS requirements. Moreover, Sumail Industrial 132/33kV grid
station will be constructed with 2x125 MVA transformers that will be connected via 132kV LILO Rusail -
Sumail (2x14.6km OHL and 4x1.6km UGC) to cater for the new demand in the area.
Figure 11 and Figure 16 show in a geographic map the system development plan to meet the 2021 system
peak demand of MITS and DTS respectively. The main investment to meet the 2021 peak in Muscat area
is the new 100km of 400kV OHL between New Izki and Misfah which is intended to evacuate the generated
power from Sur power plant. In addition, 220/132kV 2x500 MVA transformers will be constructed at
Khaborah Interconnection Station (KIS) to cater for the new demand in the area and to increase system
reliability within Al Batinah North. The projects designed to meet the 2021 system peak demand include
the construction of new 132/33kV, 2x125 MVA transformers at Yanqul that will be connected via 2x0.6km
Page | 37
Five-Year Annual Transmission Capability Statement (2020 - 2024)
132kV OHL by LILO of Dank - Al Hayl 132kV line. In addition, new 132/33kV, 4x125 MVA transformers
grid station at Khoudh with four 33kV GIS interlink will be in service. Further, the connection of Ibri Solar-
PV IPP Generation via 220kV OHL from Ibri IPP grid stationwill be completed to evacuate power coming
from Ibri Solar-PV IPP. In addition, the development in Dhofar region will be a construction of a new
132/33kV, 2x63 MVA transformers grid station at Mirbat with 32km 132kV double circuit lines between
Mirbat and Ashoor grid stations. Furthermore, new 2x125MVA, 132/33kV grid station will be constructed
at Wadi bani Auwf with new 54.6km of 132kV OHL from Nakhal to Wadi Bani Auwf and 33.4km of
132kV OHL from Rustaq to Wadi Bani Auwf. Finally, the development in Dhofar will cover upgrading
2x30 MVA transformers to 2x63 MVA transformers at Thumrait grid station to meet the Transmission
Security Standard and load growth.
5.6 Projects expected to be completed in time to meet the 2023 peak demand
Figure 13 and Figure 18 show in a geographic map the system arrangement to meet the 2023 peak demand
of MITS and DTS respectively. New 2x500 MVA, 400/132 kV grid station at Nahadah will be constructed
along with associated 1km of 400kV OHL by LILO of Ibri IPP– Manah 400kV OHL. Moreover, first new
connection to RAEC will be through construction of 132/33 kV grid station at Saih Al Khairat area along
with associated 88km of 132kV OHL from Thumrait to Saih Al Khairat grid stations. In addition,
installation of third 500 MVA transformer at Airport Heights and 3.8 km of 132kV UGC between Airport
Heights and Ghala grid stations will be energized to meet load growth in the area. Furthermore, one of
planned project is construction of new Al Jefnen 3x500MVA 400/132kV grid station with associated 8.3km
of 400kV OHL from Misfah to Al Jefnen grid stations. Moreover, construction of new 400/33kV grid
station at Mahout area and new 400/132/33kV grid station at Duqm area are planned to supply RAEC load
instead of using diesel generators. Furthermore, One of the development of 400kV network is North-South
Interconnector (MIS-Duqm Phase-1) which includes 152km of 400kV OHL between Duqm and Mahout
and 187km of 400kV OHL between Duqm and Suwaihat along with 6x(25-75) MVAr Shunt Reactors and
2x393 MVAr of Series Capacitors at 400kV OHL between Duqm and Mahout grid stations.
Page | 38
Five-Year Annual Transmission Capability Statement (2020 - 2024)
5.7 Projects expected to be completed in time to meet the 2024 peak demand
Figure 14 and Figure 19 show in a geographic map the system arrangement to meet the 2024 peak demand
of MITS and DTS respectively. One of the development of 400kV network in Al Batinah is construction
of new 400/132 kV grid station at Rustaq area with 3x500 MVA, 400/132kV transformers along with
associated 159.8km of 400kV OHL from New Rustaq to Ibri IPP grid stations and 85.2km of 400kV OHL
from New Rustaq to Al Jefnen grid stations. Furthermore, Securing Bureimi area includes construction of
32.9km of 132kV OHL and 5.5km of 132kV UGC between Mahadha and Bureimi Industrial grid stations.
In addition, first new waste to energy (WTE) project will be constructed at Barka area with associated of
3.6km 132kV OHL between WTE IPP and Madinat Barka grid stations. Moreover, construction of new
132/33kV Al Jawabi grid station with 2x125MVA transformers and 14 km of 132kV OHL from JBB Ali
to Al Jawabi grid stations is planned to meet load growth in the area. Further, JBB Ali Wind Farm
connection includes construction of 9 km of 132kV OHL from Al Jawabi to JBB Ali Wind Farm to evacuate
power coming from JBB Ali Wind Farm. In addition, Duqm Wind Farm will be connected to Duqm grid
station via 49.7km of 132kV OHL to evacuate power coming from Duqm Wind Farm. Finally, construction
of Nizwa 220/132kV grid station with 2x500MVA transformers is planned to increase the system reliability
within Al Dhakilyah region. The grid station will be connected via 220kV line from New Izki grid station
including 53.9km OHL, 1.1km UGC from Nizwa side and 3.6km UGC from New Izki side.
5.8 Summary
Table 1 in the Executive Summary has summarized the development plans for the OETC Transmission
System on a project-by-project basis at the time of this statement. The table identifies the committed
projects by OETC that are considered likely to be proceed with. The power system studies presented in this
Capability Statement is to show the expected performance of the transmission system over the period 2020-
2024. In addition, the studies have been performed on the basis that the committed and planned development
projects in Table 1 and detailed in Appendix A will proceed as planned and to be completed on schedule.
The system studies are used to identify areas of the transmission system where there are opportunities for
connecting new demand and new generation and where constraints should be applied to further
development.
Page | 39
Five-Year Annual Transmission Capability Statement (2020 - 2024)
Page | 40
Five-Year Annual Transmission Capability Statement (2020 - 2024)
Page | 41
Five-Year Annual Transmission Capability Statement (2020 - 2024)
Page | 42
Five-Year Annual Transmission Capability Statement (2020 - 2024)
Page | 43
Five-Year Annual Transmission Capability Statement (2020 - 2024)
Page | 44
Five-Year Annual Transmission Capability Statement (2020 - 2024)
Page | 45
Five-Year Annual Transmission Capability Statement (2020 - 2024)
Page | 46
Five-Year Annual Transmission Capability Statement (2020 - 2024)
Page | 47
Five-Year Annual Transmission Capability Statement (2020 - 2024)
Page | 48
Five-Year Annual Transmission Capability Statement (2020 - 2024)
Page | 49
Five-Year Annual Transmission Capability Statement (2020 - 2024)
Eleven gas-based power stations supply MIS transmission system in summer 2020 as follows:
Rusail IPP in Muscat governorate.
Barka I Power & Desalination Plant (ACWA), Barka II IPP (SMN) and Barka III IPP in Al Batinah
South governorate.
Sohar I Power & Desalination Plant, Sohar II IPP and Sohar III IPP in North Al Batinah
governorate.
Ibri IPP at Al Dhahirah governorate
The eleven power stations are described briefly below:
a) Rusail IPP
Rusail IPP is located in the Rusail Industrial Estate. The power station has eight Frame 9E gas turbines
installed and are operating in open-cycle. The gross site rating of the units varies from 82.3 MW to 96.9
MW. The units were installed progressively between 1984 and 2000. The net generation capacity of the
power station is approximately 693.5 MW.
b) Manah IPP
Manah IPP is owned by the United Power Company and was the first Independent Power Project (IPP)
built in Oman and commissioned in 1996. The station comprises three GE PG6541B gas turbines (each site
rated at 27 MW) and two GE PG9171E gas turbines (site ratings of 91.1 MW). In 2020 OPWP is planning
to operate GT2A >2B with net generation capacity of 182.2 MW and retire the three GE PG6541B gas
turbines.
c) Al Kamil IPP
Al Kamil IPP was commissioned in 2002. The station comprises three GE PG9171E gas turbines (site
rating 97.1 MW) operating in open cycle and the net generation capacity is approximately 291.4 MW.
Page | 50
Five-Year Annual Transmission Capability Statement (2020 - 2024)
2. Barka II IPP (SMN) was commissioned in 2009. There are three gas turbines of 122.8 MW capacity
each and two steam turbines of 160 MW capacity each. The net generation capacity is approximately
688.5 MW.
3. Barka III IPP was commissioned in 2012. There are two gas turbines of 247.5 MW capacity each and
a steam turbine of 270.4 MW capacity are available in 2020. The net generation capacity is
approximately 765.5 MW.
h) Sur IPP
Sur IPP was commissioned in 2014. There are five gas turbines of 248.6 MW capacity and three steam
turbines (ST1& ST2) with a capacity of 310 MW while the capacity of ST3 is 155 MW. In 2020, the total
capacity will reach approximately 2018.2 MW working in a combined cycle.
I) Ibri IPP
Ibri IPP awarded in December 2015 to Ad Dhahirah Power Generation Company; the plant was
commissioned in 2019. There are four gas turbines of 242.7 MW capacity each and two steam turbines of
(ST1= 285 MW and ST2 = 286 MW) capacity. The total generation capacity is approximately 1541.7 MW.
Page | 51
Five-Year Annual Transmission Capability Statement (2020 - 2024)
Three gas-based power stations and a renewable power plant supply Dhofar transmission system in summer
2020 as follows:
NPS
Table 4 lists on a yearly basis the existing and committed future generating capacity over the period 2020-
2024. The table presents the gross and net maximum capacity for each generating unit at each power station
and takes into account the desalination load where appropriate.
Page | 52
Five-Year Annual Transmission Capability Statement (2020 - 2024)
Page | 53
Five-Year Annual Transmission Capability Statement (2020 - 2024)
2
Solar PV output at Peak (3-4 pm during summer) expected to be about 90% of the total installed capacity (90% of 500 MW)
3
Solar PV output at Peak (3-4 pm during summer) expected to be about 30% of the total installed capacity (30% of 1000 MW)
Page | 54
Five-Year Annual Transmission Capability Statement (2020 - 2024)
4
As per OPWP data, the unit capacities and locations for Pow er 2022 and Pow er 2024 w ill be provided after aw arding.
5
It is part of OPWP w ind 2024. Wind turbines output expected to be about 20% of the total installed capacity (20% of 100 MW) .
6
It is part of OPWP w ind 2024. Wind turbines output expected to be about 35% of the total installed capacity (35% of 200 MW) .
7
As per OPWP data, the exact capacity of Demand Response w ill be determine after finalizing the Demand Response Project.
Page | 55
Five-Year Annual Transmission Capability Statement (2020 – 2024)
Reference to Figure 20 and Figure 21, the generation mix has been divided into three types: Gas IPP,
Combined Cycle IPPs and Renewable. Further, comparison has been carried out between year 2020 and
2024 for the generation percentage of MIS and Dhofar System.
13.25%
Gas IPPs
Combined Cycle IPPs
86.58% Renewable
Figure 20: Generation Percentage 2020 for both MIS & Dhofar
10% 5%
Gas IPPs
Combined Cycle IPPs
Renewable
85%
Figure 21: Generation Percentage 2024 for both MIS & Dhofar
Page | 56
Five-Year Annual Transmission Capability Statement (2020 – 2024)
a) Rusail IPP
At the end of 2021, it is planned to retire all existing generating units.
Page | 57
Five-Year Annual Transmission Capability Statement (2020 – 2024)
at the time of preparing this Capability Statement, OETC has distributed this power in the system according
to the transmission system performance requirements.
e) Duqm Wind Farm
It is proposed to be located in Duqm area. As per OPWP generation plan, it is expected to be commissioned
by peak 2024. The total capacity for the plant is expected to be 200MW.
f) JBB Ali Wind Farm
As per OPWP generation plan, the proposed location is in JBB Ali area in Al Sharqiyah South governorate
with a total capacity of 100MW and expected to be connected to the system by peak 2024.
g) Barka Waste to Energy Plant
This plant will be the first of its type in Oman. It will be connected to Madinat Barka 132/33kV grid station
via a new 132kV OHL of about 3.6km with maximum capacity of 160MW.
Page | 58
Five-Year Annual Transmission Capability Statement (2020 – 2024)
Table 7 summarises the Centrally Dispatched Net Generation Capacity available over the period 2019–
2024, with the new generation at Ibri IPP and Sohar III IPP in service. It covers the planned retirement of
generating units at Rusail IPP, Kamil IPP, Barka I Power & Desalination Plant, Sohar I Power &
Desalination Plant, Barka II Power & Desalination Plant and Manah power plant.
Table 7: Centrally Dispatchable and Non-Dispatchable Generating Capacity on OETC System
Net Generating Capacity (MW)
Power Stations
2019 2020 2021 2022 2023 2024
MIS System
Rusail IPP 693.5 693.5 693.5 0.0 0.0 0.0
Manah IPP 263.2 182.2 182.2 182.2 182.2 182.2
Al Kamil IPP 291.4 291.4 291.4 0.0 0.0 0.0
Barka I Power & Desalination Plant 397.5 397.5 397.5 0.0 0.0 0.0
Barka II IPP 688.5 688.5 688.5 688.5 688.5 0.0
Barka III IPP 765.5 765.5 765.5 765.5 765.5 765.5
Sohar I Power & Desalination Plant 566.0 566.0 566.0 0.0 0.0 0.0
Sohar II IPP 765.5 765.5 765.5 765.5 765.5 765.5
Sohar III IPP 1745.0 1743.1 1741.8 1739.3 1740.7 1739.7
Sur IPP 2018.2 2018.2 2018.2 2018.2 2018.2 2018.2
Ibri IPP 1543.0 1541.7 1540.6 1539.6 1538.5 1537.7
Ibri Solar PV IPP 0.0 0.0 0.0 450.0 450.0 450.0
Manah Solar PV IPP 0.0 0.0 0.0 0.0 150.0 300.0
Power 2022 0.0 0.0 0.0 600.0 600.0 600.0
Power 2024 0.0 0.0 0.0 0.0 0.0 700.0
Duqm Wind Farm 0.0 0.0 0.0 0.0 0.0 68.5
JBB Ali Wind Farm 0.0 0.0 0.0 0.0 0.0 19.0
Barka Waste to Energy Plant 0.0 0.0 0.0 0.0 0.0 100.0
Demand Response 0.0 0.0 30.0 40.0 50.0 70.0
Total Generating Capacity (MW) 9737.3 9653.1 9680.8 8788.8 8949.2 9316.4
Retirements 0.0 81.0 0.0 1948.4 0.0 688.5
Dhofar System
NPS 273.0 273.0 273.0 273.0 273.0 273.0
Salalah Power & Desalination Plant 430.0 430.0 430.0 430.0 430.0 430.0
Salalah II IPP 446.0 445.0 444.0 443.0 442.0 442.0
Dhofar Wind Farm 0.0 18.0 18.0 18.0 18.0 18.0
Total Generating Capacity (MW) 1148.0 1165.0 1164.0 1163.0 1163.0 1163.0
Retirements 0.0 0.0 0.0 0.0 0.0 0.0
Page | 59
Five-Year Annual Transmission Capability Statement (2020 – 2024)
6.5 Interconnections
6.5.1 Interconnection with the GCCIA Grid through UAE (Transco Abu Dhabi)
The 220kV transmission interconnection with the United Arab Emirates (Transco Abu Dhabi) was
completed in the first quarter of 2007. The interconnection connects Mahadha grid station in Oman
(Al Wasit) to Al oha grid station in Al Ain in the UAE. In the longer term, the principal technical benefit
to be obtained from connecting Oman to the GCCIA Grid is in the reduction of spinning reserve
requirement, which will be shared between the members of the GCCIA Grid and will help to reduce the
installed capacity from the generation. However, operation of the interconnection will allow Oman to
import/export power from the GCCIA Grid to meet any potential generation shortfall. Oman has signed
officially the agreement with the GCCIA in November 2014 and became a part of the state members.
OETC transmission system is interconnected with the transmission system of the Petroleum Development
Oman (PDO), which provides electricity to its concession areas across the central region of Oman for the
purpose of oil exploration and development. The interconnection is made at 132kV between Nizwa grid
station on the MIS and Nahadah 132kV station on the PDO 132kV network by 67 km overhead line. The
overhead line is owned by PDO. Under normal conditions, the power transfer between the two networks
is allowed to float around zero MW, with power transfers balanced out over a period.
In addition, Dhofar transmission system is interconnected with the transmission system of the PDO. The
interconnection is made at 132kV between Thumrait grid station on the Dhofar system, Dhofar Wind Farm
and Harweel 132kV grid station on the PDO network (132kV OHL Thurmrait-Wind Farm 76.5 km &
132kV OHL Wind Farm-Harweel 30 km). The interconnection essentially allows OETC and PDO to supply
limited power to each other in emergency conditions on either system.
OETC has received a new connection application from PDO on 3rd of July 2018. OETC has studied the
connection application and it was found that a new 400kV injection point at Nahadah 132kV station via
LILO the existing Ibri – New Izki 400kV OHL is the preferred option. In addition, there will be two new
injection points in PDO system at Barik and Suwaihat. Having new interconnection points via the 400kV
system between OETC and PDO will enhance the security of supply of both networks as well as maximizing
other benefits such as capacity saving and reducing the spinning reserve etc.
The feasibility study for the 400kV North to South Interconnection was completed by mid of 2018. The
objective of this project is to assess the technical and economic feasibility of a new 400kV interconnection
between MIS-PDO-Dhofar and the isolated region of Duqm. This study has assessed different options and
highlighted the benefits of this project. The feasibility study has concluded that the interconnection project
has a positive economic Net Present Value (NPV) considering all main objectives that were identified by
Page | 60
Five-Year Annual Transmission Capability Statement (2020 – 2024)
OETC, OPWP, PDO and RAEC. The expected benefits include fuel savings due to improved dispatch
coordination among the power systems, access to areas with renewable energy potential, sharing of spinning
reserves (reducing operating costs), and improved grid security.
RAEC has submitted two connection applications on 6th of January 2019 for constructing two grid stations
at Mahout and Duqm. Further, PDO has submitted two connection applications for Barik and Suwaihat on
12th of June 2019 requesting for 500 MW export and import power at each grid station. In addition, the new
400kV interconnection project will facilitate the connection to PDO system, Duqm and Mahout Systems
and currently the project is in the design stage. The execution of the project will be in two phases: the first
phase will include constructing Suwaihat, Duqm and Mahout grid stations in order to displace the diesel
generation in Duqm and Mahout areas by Q2 2023. The second phase will be completing the 400kV
backbone from Nahadah to Barik and Suwaihat grid stations and the expected completion date will be end
of Q4 2024.
Page | 61
Five-Year Annual Transmission Capability Statement (2020 – 2024)
4000
3000
2000
1000
Time (hrs)
Page | 62
Five-Year Annual Transmission Capability Statement (2020 – 2024)
400
300
200
100
Time (hrs)
Table 8: Historic Growth in Peak Demand and Transmission Losses (2003 – 2019)
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019
MIS S ystem
S ystem Max
Demand
(MW) based 2232 2371 2495 2613 2773 3139 3546 3614 4000 4448 4634 5269 5744 6105 6305 6335 6540
on gross
demand
Annual
growth rate
based on --- 6.23 5.23 4.73 6.12 13.20 12.97 1.92* 10.69 11.19 4.18 13.70 9.01 6.28 3.28 0.48 3.23
gross demand
(%)
S ystem Max
Demand
(MW) based 2139 2294 2395 2505 2662 3033 3342 3504 3765 4247 4328 4872 5472 5826 6016 6036 6166
on net
demand
Transmission
S ystem
Losses (MW) 35 38 40 37 40 61 80 60 62 54 115 165 93 95 101 133 187
at system
peak
Transmission
S ystem 1.64 1.66 1.67 1.47 1.5 2 2 1.7 1.6 1.3 2.64 3.4 1.7 1.6 1.7 2.1 2.86
Losses (%)
*T he reduction in the annual growth is due to the Phet Cyclone
Page | 63
Five-Year Annual Transmission Capability Statement (2020 – 2024)
Table 8 (continued): Historic Growth in Peak Demand and Transmission Losses (2003 – 2019)
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019
Dhofar S ystem
S ystem Max
Demand
(MW) based 178.3 180.9 199.3 232.3 253 260.4 297.4 336.2 348 389.3 421.7 438.9 495 523 577 567 594.5
on gross
demand
Annual
growth rate
based on --- 1.46 10.17 16.56 8.91 2.92 14.21 13.05 3.51 11.87 8.32 4.08 12.78 5.66 10.24 -1.73 4.85
gross
demand (%)
S ystem Max
Demand
(MW) based --- --- --- --- --- --- --- --- --- --- --- 427 473 513 531 517 540.2
on net
demand
Transmissio
n S ystem
Losses (MW) --- --- --- --- --- --- --- --- --- --- --- 4 15 2 21 23 8.7
at system
peak
Transmissio
n S ystem --- --- --- --- --- --- --- --- --- --- --- 0.8 3.1 0.4 3.7 4.4 1.46
Losses (%)
Minimum demand generally occurs on the transmission system during night-time in winter months
(December/January) when electricity consumption in all major load categories is reduced. In 2019, the MIS
system minimum demand was 1735.57 MW and this occurred on 27/12/2019 at 03:40 AM while 2019
Dhofar system minimum demand was 216.7 MW and this occurred on 12/01/2019 at 07:30 AM. The 2019
system minimum demand at MIS system was about 26.54% and at Dhofar system was about 36.45% of the
2019 system peak demand. The 24-hour profile for the day of minimum demand is shown in Figure 24 and
Figure 25 for the MIS and Dhofar system respectively.
Page | 64
Five-Year Annual Transmission Capability Statement (2020 – 2024)
2500
2000
Load (MW)
1500
1000
500
Time (hrs)
200
150
100
50
Time (hrs)
Page | 65
Five-Year Annual Transmission Capability Statement (2020 – 2024)
“The Licensee shall, when preparing the Capability Statement ensure that the forecasts of electricity flows
and loading on each part of the Transmission System are consistent with the prevailing electricity demand
forecasts prepared and used by the OPWP for the purposes of the Statement of future capacity requirements
required by Condition 5 of the OPWP licence”.
The OPWP demand forecast is based on data supplied to them by the four Distribution Companies (i.e.
MEDC, MZEC, MJEC and DPC) and RAEC which also includes demand forecasts for the major customers
that are, or will be, directly connected to OETC transmission system at either 220kV or 132kV in their
respective supply areas. In addition, Distribution Companies have provided demand forecast data to OETC
taking into account the individual load at each supply connection points. The Distribution Companies
forecast is provided in terms of:
The supplied forecast to OPWP relates to the total for all Distribution Companies and RAEC and do not
indicate how this load is allocated to the individual grid supply points. The forecast data provided to OPWP
includes major future connections and the cumulative increase in load over the seven-year period covered
by the OPWP Statement. OPWP has then reviewed this data and taken a view on the probability that the
individual schemes will proceed and if so, the rate at which it’s load will develop. The outcome of this
review is presented as OPWP demand forecast in it’s Seven-Year Statement.
The OPWP demand forecast was therefore taken as the starting point for developing the demand forecast
presented in this OETC Capability Statement. The OETC forecast, however, is required to identify the
future demand at individual grid station at the system peak for each year over the period 2020 to 2024, since
this information is required for the system studies.
Analysis of the demand forecast data (Expected Case) submitted by OPWP identified basic annual
percentage rates of 4.4% for the growth in peak demand in the MZEC, MEDC ,MJEC and RAEC supply
areas and 6.9% for the growth in peak demand in the DPC supply area. It should be noted that the peak
growth forecast provided by OPWP is also including the estimated transmission losses (2%) whilst, OETC
peak growth forecast does not include the transmission losses, but it is calculated in an annual basis based
on the simulations system studies. These rates have been applied to the grid station demands in the
respective supply areas as noted by the OETC Load Dispatch Centre at the 2019 MIS system peak (i.e.
30/06/2019, 14:55 hour) and 2019 Dhofar system peak (i.e.14/06/2019, 04:04 hour). The demand associated
Page | 66
Five-Year Annual Transmission Capability Statement (2020 – 2024)
with major industrial and tourism projects as assessed by OPWP (with diversity taken into account) was
then superimposed on to the steady growth in the basic demand to produce a basic forecast. Peak demand
is expected to grow at a lower rate than energy demand due to the introduction of Cost-Reflective Tariffs
(CRT) for large commercial, government, and industrial consumers in 2017. The CRT is time-
differentiated, where the tariff is more representative of the actual cost of supply at the different periods
during the year, noting higher costs during peak and summer periods, and lower costs during off-peak and
winter periods. Some large customers are expected to shift their demand in response to the new tariff.
Section 5 of this Statement has identified a number of new grid supply points that are scheduled to come
into service to meet the summer peak demands from 2020 onwards. These gird stations will provide a load
relief to the most heavily loaded grid stations and in some cases supply new loads.
The Distribution Companies’ plans for load transfers from existing grid stations that are heavily loaded to
new grid stations are one of the most important elements of the demand forecast. Table 9 summarises the
load transfers adopted in the studies based on consideration of what is required and what OETC has
considered viable. However, OETC acknowledges that this aspect of the forecast needs to be improved in
future and believes that it would be helpful if Distribution Companies were to give greater consideration to
feasible load transfers when planning their distribution networks, and to develop proposals for load transfers
in coordination with OETC. In addition, the TSS requirement shall be considered at every grid supply point
and all new requirements shall be indicated clearly.
Page | 67
Five-Year Annual Transmission Capability Statement (2020 – 2024)
Table 9 (continued): Expected Load Transfers between Grid Supply Points (2020-2024)
Load Transfer (MW)
From Grid Station To Grid Station
2020 2021 2022 2023 2024
Muscat Area
Mawalleh South TX-1 & TX-2 Khoudh TX-1 & TX-2 10
Mawalleh South TX-3 & TX-4 Khoudh TX-1 & TX-2 20
Mawalleh South TX-3 & TX-4 Khoudh TX-3 & TX-4 25
Mobella A'salam TX-3 & TX-4 10 8
Mobella Mobella Industrial TX-3 & TX-4 60
Seeb Main TX-1 & TX-2 Seeb Main TX-3 & TX-4 8
Seeb Main TX-1 & TX-2 Khoudh TX-3 & TX-4 35
Total (MW) 285.0 147.0 105.0 0.0 45.0
Mazoon Area
Barka Main TX-1 & TX-2 Hay Asim 30
Barka Main TX-1 & TX-2 Madinat Barka TX-3 & TX-4 25
Barka Main Tx-3 Mobella Industrial 8 17 12.8
Izki 2X125MVA Birkat Al Mouz 8.9
JBB Ali Al Jawabi 80
Khadhra TX-1 & TX-2 Khadhra TX-3 & TX-4 30
Madinat Barka TX-1 & TX-2 Madinat Barka TX-3 & TX-4 24
Mudhaibi 2X125MVA Sinaw 35
Mudhaibi 2X125MVA Samad 25
Mudhairib Bedyah 49.8
Muladah TX-1 & TX-2 Muladah TX-3 & TX-4 23
Nizwa Birkat Al Mouz 41.9
Rustaq Wadi Bani Auwf 49
Sumail 2X125MVA Sumail Industrial Area 53.6
Total (MW) 223.6 196.6 12.8 0 80
Majan Area
Al Hayl Yanqul 33.5
Bureimi Buriami Industrial TX-3 & TX-4 34.6 1.4
Buriami Industrial TX-1 & TX-2 Buriami Industrial TX-3 & TX-4 15.8 0.5 0.4 0.4 0.6
Ibri 2x63MVA Dreez 2
Ibri TX-1 & TX-2 Dank 2.3
Liwa TX-1 & TX-2 Sohar Free Zone TX-1 & TX-2 24.8
Liwa TX-1 & TX-2 Sohar Free Zone TX-3 & TX-4 49.1
Page | 68
Five-Year Annual Transmission Capability Statement (2020 – 2024)
Table 9 (continued): Expected Load Transfers between Grid Supply Points (2020-2024)
Load Transfer (MW)
From Grid Station To Grid Station
2020 2021 2022 2023 2024
Majan Area
Liwa TX-1 & TX-2 Shinas 6 1
Mahadah Buriami Industrial TX-3 & TX-4 7.8 0.4 0.2 0.3
Saham Uwaynat TX-1 & TX-2 3
Saham Dil Abdusalam 1 3 0.1 0.1 0.1
Shinas 2X125MVA Madinat Shinas 4
SIA Liwa TX-1 & TX-2 3 0.1 0.1 0.1
Sohar TX-1 & TX-2 Uwaynat TX-3 & TX-4 8.1 0.3 0.3 0.3 0.4
Sohar TX-1 & TX-2 Sohar TX-3 & TX-4 8 1 1 0.5 0.4
Sohar TX-3 & TX-4 Sohar TX-1 & TX-2 4 18.7 0.8
Uwaynat TX-1 & TX-2 Uwaynat TX-3 & TX-4 2
Uwaynat TX-3 & TX-4 Uwaynat TX-1 & TX-2 3
Total (MW) 149.7 50.2 12.3 27.2 5.1
Dhofar System
Al Qarm Sa'adah TX-3 & TX-4 9 9
Ashoor Mirbat (2x63MVA) 19.9 1
Ittin Sa'adah TX-1 & TX-2 4.64 8
Ittin Salalah Free Zone TX-3 & TX-4 2
Ittin Shaha'aon (2X125MVA) 3 5
NPS 2X63MVA Sa'adah TX-1 & TX-2 3
NPS 2X63MVA Salalah Free Zone TX-1 & TX-2 2
Sa'adah TX-1 & TX-2 Al Qarm 2
Sa'adah TX-1 & TX-2 NPS 2X63MVA 1
Sa'adah TX-1 & TX-2 Sa'adah TX-3 & TX-4 8 5 3
Sa'adah TX-1 & TX-2 Ittin 3
Sa'adah TX-3 & TX-4 Sa'adah TX-1 & TX-2 4.5
Raysut NPS 2X63MVA 1
Raysut Salalah-IPP 5.6 16.23 15 2 2
Raysut Sa'adah TX-1 & TX-2 1 10
Raysut Sa'adah TX-3 & TX-4 10
Salalah-IPP Raysut 2
Shaha'aon (2X125MVA) Sa'adah TX-3 & TX-4 3
Shaha'aon (2X125MVA) Ittin 1 2
Shaha'aon (2X125MVA) Sa'adah TX-1 & TX-2 3.5 16.25
Shaha'aon (2X125MVA) Salalah-IPP 7.5 2
Thumrait 2X30MVA Thumrait 2X63MVA 28.8
Total (MW) 25.7 112.9 45.0 36.3 2.0
Page | 69
Five-Year Annual Transmission Capability Statement (2020 – 2024)
Page | 70
Five-Year Annual Transmission Capability Statement (2020 – 2024)
Table 10 (continued): OETC Transmission System Net Demand Forecast by Grid Station
Actual Forecast (MW)
Grid Station
2019 2020 2021 2022 2023 2024
MUSCAT AREA
Muttrah 70.5 71.2 71.2 71.2 71.2 71.2
Qurum 91.4 93.2 95.1 97.0 98.9 100.9
Quryiat 50.4 51.9 53.5 55.1 56.7 58.4
TX-1 & TX-2 50.1 54.1 58.4 61.9 65.7 69.6
Rusail Industrial
TX-3 & TX-4 81.8 88.3 95.4 101.1 107.2 113.6
TX-1 & TX-2 130.4 128.9 100.4 104.4 108.6 112.9
Seeb Main
TX-3 & TX-4 73.4 85.1 89.3 92.9 96.6 100.5
Wadi Adai 79.7 81.3 82.9 84.6 86.3 88.0
TX-1 & TX-2 68.4 69.1 69.1 69.1 69.1 69.1
Wadi Kabir
TX-3 & TX-4 59.0 59.6 59.6 59.6 59.6 59.6
Yitti 16.9 17.2 17.6 17.9 18.3 18.7
Muscat Airport 30.4 30.4 30.4 30.4 30.4 30.4
Muscat Steel 0.0 0.0 0.0 0.0 0.0 0.0
Modern Steel 0.0 0.0 0.0 0.0 0.0 0.0
R.O Ghoubrah 22.3 22.0 22.0 22.0 22.0 22.0
Total 2463.2 2626.5 2796.1 2941.7 3075.6 3193.1
Growth (% ) 9.1% 6.6% 6.5% 5.2% 4.6% 3.8%
MAZOON AREA
Adam 2x125M VA 50.0 52.5 55.1 57.9 60.8 62.6
Al Jawabi 0.0 0.0 0.0 0.0 0.0 80.0
Ayjah 69.9 72.7 74.9 89.3 91.6 94.0
Bahla 71.3 74.9 78.6 82.5 86.7 90.1
TX-1 & TX-2 105.9 56.2 59.0 62.0 65.1 67.0
Barka Main
TX-3 35.5 28.6 12.4 0.0 0.0 0.0
Bedyah 0.0 49.8 51.8 53.9 56.0 58.3
Birkat Al Mouz 0.0 50.8 53.8 57.1 60.5 64.1
Blue City 119.5 124.3 128.0 140.8 144.8 148.9
Hay Asim 22.3 53.2 66.6 83.2 84.9 86.7
Ibra 73.6 79.9 83.0 86.2 89.5 92.1
2x40MVA 0.0 0.0 0.0 0.0 0.0 0.0
Izki
2x125M VA 87.5 81.2 87.5 90.0 91.7 93.5
JBB Ali 115.4 120.0 146.8 151.8 157.0 82.4
JBB Hassan 70.4 73.2 83.1 86.2 89.4 92.7
Jebreen 61.5 64.0 66.5 69.2 71.9 74.1
TX-1 & TX-2 106.8 111.1 85.5 88.9 92.5 95.3
Khadhra
TX-3 & TX-4 33.0 34.3 65.7 68.3 71.1 73.2
Page | 71
Five-Year Annual Transmission Capability Statement (2020 – 2024)
Table 10 (continued): OETC Transmission System Net Demand Forecast by Grid Station
Actual Forecast (MW)
Grid Station
2019 2020 2021 2022 2023 2024
MAZOON AREA
TX-1 & TX-2 107.4 111.7 92.2 100.9 103.8 106.7
Madinat Barka
TX-3 & TX-4 0.0 25.0 50.0 52.0 54.1 55.7
Madinat Nizwa 60.8 63.2 65.8 68.4 71.1 73.3
MIS 43.6 45.3 47.2 48.6 50.0 51.5
Mudhaibi 102.9 47.0 48.9 55.7 57.7 59.3
Mudhairib 102.2 56.5 64.7 67.1 69.5 71.4
TX-1 & TX-2 100.7 104.7 85.9 100.2 103.7 106.5
Muladah
TX-3 & TX-4 21.8 22.7 46.6 48.4 50.4 51.9
Nakhal 73.6 76.5 85.6 88.0 90.5 93.0
New Izki 19.8 20.6 21.4 22.3 23.2 23.9
Nizwa 122.1 85.1 96.6 109.3 112.0 114.8
Rustaq 3x125M VA 153.3 159.4 116.8 121.5 126.3 130.1
Samad 0.0 25.0 25.8 26.5 27.3 28.1
Sinaw 0.0 35.0 36.8 38.2 39.7 40.9
2x63MVA 50.9 52.4 54.0 55.1 56.2 57.3
Sumail
2x125M VA 104.7 108.9 59.6 62.0 63.9 65.8
Sumail Industrial Area 0.0 0.0 53.6 55.2 56.9 58.6
Sur 87.9 94.0 96.8 99.6 102.4 105.4
Suwaiq 58.8 61.2 67.9 77.6 80.3 82.4
Wadi Bani Auwf 0.0 0.0 49.0 51.0 53.0 54.6
OMIFCo 3.3 0.0 0.0 0.0 0.0 0.0
Total 2236.4 2321.0 2463.5 2614.8 2705.4 2786.0
Growth (% ) -2.8% 3.8% 6.1% 6.1% 3.5% 3.0%
MAJAN AREA
Al Hayl 39.5 40.5 7.6 7.7 7.8 8.0
Bureimi 81.0 48.4 51.3 53.3 55.5 56.9
TX-1 & TX-2 54.3 40.2 41.0 42.0 43.1 44.6
Buriami Industrial
TX-3 & TX-4 0.0 50.4 59.6 61.2 62.9 66.4
Dank 34.2 38.1 42.6 47.7 51.3 52.2
Dil Abdusalam 70.3 73.3 78.3 80.6 82.3 87.2
Dreez 77.5 79.3 81.5 83.7 88.2 90.7
2x63MVA 37.7 38.9 40.1 41.3 40.6 41.9
Ibri
2x125M VA 78.6 78.2 80.2 82.2 84.3 86.8
Khaborah 85.4 88.0 91.2 95.4 99.7 104.3
Page | 72
Five-Year Annual Transmission Capability Statement (2020 – 2024)
Table 10 (continued): OETC Transmission System Net Demand Forecast by Grid Station
Actual Forecast (MW)
Grid Station
2019 2020 2021 2022 2023 2024
MAJAN AREA
TX-1 & TX-2 124.4 56.1 59.8 56.7 59.9 63.0
Liwa
TX-3 & TX-4 61.5 67.2 73.0 76.4 79.8 82.1
Madinat Shinas 59.1 64.5 73.7 78.9 82.9 86.6
Mahadah 23.3 24.1 17.2 17.4 17.8 18.0
Saham 83.9 86.2 87.4 90.0 90.2 95.1
Shinas 59.8 64.8 67.3 79.6 84.3 91.7
SIA 71.2 76.8 84.4 84.9 85.4 86.1
TX-1 & TX-2 69.2 55.7 58.6 68.2 90.0 94.4
Sohar
TX-3 & TX-4 98.0 108.7 112.9 112.8 97.5 100.7
TX-1 & TX-2 5.1 36.6 41.0 44.9 41.2 42.2
Sohar Free Zone
TX-3 & TX-4 0.0 49.1 50.4 51.4 52.6 54.3
TX-1 & TX-2 47.7 52.2 53.8 55.5 58.2 60.0
Uwaynat
TX-3 & TX-4 54.4 60.8 62.9 64.7 68.7 71.1
Wadi Sa'a 12.0 14.1 16.5 18.1 20.4 22.6
Yanqul 0.0 0.0 33.5 34.4 35.4 36.7
Sohar Refinery (132kV SIA) 23.9 0.0 0.0 0.0 0.0 0.0
Sohar Steel (SSSRM) (132kV SIa) 2.8 0.0 0.0 0.0 0.0 0.0
Jindal Shadeed (220kV SIA) 21.6 60.0 60.0 100.0 100.0 100.0
VALE (132kV SIA) 65.7 85.0 85.0 85.0 85.0 85.0
ARMS (132kV Liwa) 4.2 4.2 4.2 4.2 4.2 4.2
OMPET (132kV SIA) 0.0 0.0 4.0 4.0 4.0 4.0
Orpic (Liwa Plastic) (220kV SPS-2) 5.0 25.0 25.0 25.0 25.0 25.0
Moon Iron & Steel Co. (220KV SFZ) 0.0 15.0 15.0 15.0 15.0 15.0
Al Taman INDSIL (132kV SFZ) 14.9 8.0 8.0 8.0 8.0 8.0
Total 1466.2 1589.3 1666.9 1770.2 1821.2 1885.1
Growth (% ) -0.7% 8.4% 4.9% 6.2% 2.9% 3.5%
DPC AREA
Al Qarm (2x63M VA) 32.7 34.4 33.2 36.0 27.7 28.5
Ashoor (2X125MVA) 49.0 68.7 55.8 56.7 56.7 57.7
Ittin (2X125MVA) 90.5 78.4 71.8 74.8 83.5 87.1
Mirbat 2x63 MVA 0.0 0.0 20.9 24.9 26.9 29.1
NPS (2x63MVA) 37.9 39.7 38.8 41.9 43.1 44.7
TX-1 & TX-2 52.6 65.0 80.6 88.5 101.9 105.5
S'aadah
TX-3 & TX-4 40.3 44.3 66.5 87.2 102.3 105.9
Raysut 92.1 101.7 111.5 109.0 108.3 108.5
Salalah-IPP 20.7 39.7 69.0 101.1 107.5 112.0
Page | 73
Five-Year Annual Transmission Capability Statement (2020 – 2024)
Table 10 (continued): OETC Transmission System Net Demand Forecast by Grid Station
Actual Forecast (MW)
Grid Station
2019 2020 2021 2022 2023 2024
DPC AREA
Shaha'aon (2X125MVA) 96.1 95.3 99.4 98.3 81.9 85.0
2x30 MVA 21.6 24.2 0.0 0.0 0.0 0.0
Thumrait
2x63 MVA 0.0 0.0 28.8 32.6 33.6 34.6
Salalah Airport 6.8 7.0 8.0 8.0 8.0 8.0
Salalah Methanol Company 0.0 0.0 35.0 35.0 35.0 35.0
Total 540.2 598.2 719.3 794.1 816.4 841.5
Growth (% ) 3.6% 10.7% 20.2% 10.4% 2.8% 3.1%
RAEC AREA
TX-1 & TX-2 0.0 0.0 0.0 0.0 60.8 61.8
Duqm
TX-3 & TX-4 0.0 0.0 0.0 0.0 53.4 54.3
Mahout (2X125MVA) 0.0 0.0 0.0 0.0 23.9 24.9
Saih Al Khairat (2x125M VA) 0.0 0.0 0.0 0.0 44.2 45.8
Total 0.0 0.0 0.0 0.0 182.2 186.9
Growth (% ) - - - - - 2.6%
MEDC 2463.2 2626.5 2796.1 2941.7 3075.6 3193.1
MZEC 2236.4 2321.0 2463.5 2614.8 2705.4 2786.0
MJEC 1466.2 1589.3 1666.9 1770.2 1821.2 1885.1
DPC 540.2 598.2 719.3 794.1 816.4 841.5
RAEC 0.0 0.0 0.0 0.0 182.2 186.9
Total MIS (MW) 6165.8 6536.8 6926.5 7326.7 7740.2 8005.2
Growth (% ) 2.2% 6.0% 6.0% 5.8% 5.6% 3.4%
Total Dhofar System (MW) 540.2 598.2 719.3 794.1 860.6 887.3
Growth (% ) 3.6% 10.7% 20.2% 8 10.4% 9 8.4% 3.1%
8
DPC growth in 2021 is 20.2% due to Salalah Methanol Load (35 MW).
9
DPC growth in 2022 is 10.4% due to increased number of customers on 33kV side.
Page | 74
Five-Year Annual Transmission Capability Statement (2020 – 2024)
Table 11 compares the total net demand forecast with the available generating capacity from Table 7
including planned retirements.
Table 11: Comparison of Net Demand Forecast with Available Generating Capacity including Planned
Retirements
Page | 75
Five-Year Annual Transmission Capability Statement (2020 – 2024)
Table 12 compares the total net demand forecast with the available generating capacity from Table 7.
Table 12: Comparison of Net Demand Forecast with Available Generating Capacity and Non-Contracted
Generation in service
Power Stations 2019 2020 2021 2022 2023 2024
MIS
Rusail IPP 693.5 693.5 693.5 0.0 0.0 0.0
Manah IPP 263.2 182.2 182.2 182.2 182.2 182.2
Al Kamil IPP 291.4 291.4 291.4 0.0 0.0 0.0
Barka I Power & Desalination Plant 397.5 397.5 397.5 0.0 0.0 0.0
Barka II IPP 688.5 688.5 688.5 688.5 688.5 0.0
Barka III IPP 765.5 765.5 765.5 765.5 765.5 765.5
Sohar I Power & Desalination Plant 566.0 566.0 566.0 0.0 0.0 0.0
Sohar II IPP 765.5 765.5 765.5 765.5 765.5 765.5
Sohar III IPP 1745.0 1743.1 1741.8 1739.3 1740.7 1739.7
Sur IPP 2018.2 2018.2 2018.2 2018.2 2018.2 2018.2
Ibri IPP 1543.0 1541.7 1540.6 1539.6 1538.5 1537.7
Ibri Solar PV IPP 0.0 0.0 0.0 450.0 450.0 450.0
Manah Solar PV IPP 0.0 0.0 0.0 0.0 150.0 300.0
Power 2022 0.0 0.0 0.0 600.0 600.0 600.0
Power 2024 0.0 0.0 0.0 0.0 0.0 700.0
Duqm Wind Farm 0.0 0.0 0.0 0.0 0.0 68.5
JBB Ali Wind Farm 0.0 0.0 0.0 0.0 0.0 19.0
Barka Waste to Energy Plant 0.0 0.0 0.0 0.0 0.0 100.0
Demand Response 0.0 0.0 30.0 40.0 50.0 70.0
Total Generating Capacity (MW) 9737.3 9653.1 9680.8 8788.8 8949.2 9316.4
Demand Forecast (MW) 6165.8 6536.8 6926.5 7326.7 7740.2 8005.2
Calculated Losses (MW) 187.0 129.0 127.1 171.4 171.4 150.4
Surplus/Deficit Capacity (MW) 1037.6 1160.7
3384.5 2987.4 2627.2 1290.7
(Generation-Demand-Losses)
Non-Contracted Generating Capacity (MW) 775.0 775.0 775.0 775.0 775.0 775.0
Surplus/Deficit Capacity (MW) 1812.6 1935.7
4159.5 3762.4 3402.2 2065.7
Including Non-Contracted Generation
Retirements 0.0 81.0 0.0 1948.4 0.0 688.5
Dhofar System
NPS 273.0 273.0 273.0 273.0 273.0 273.0
Salalah Power & Desalination Plant 430.0 430.0 430.0 430.0 430.0 430.0
Salalah II IPP 445.0 444.0 443.0 442.0 442.0 442.0
Dhofar Wind Farm 0.0 18.0 18.0 18.0 18.0 18.0
Total Generating Capacity (MW) 1148.0 1165.0 1164.0 1163.0 1163.0 1163.0
Demand Forecast (MW) 540.2 598.2 719.3 794.1 860.6 887.3
Calculated Losses (MW) 8.7 2.4 3.0 3.5 5.0 5.2
Surplus/Deficit Capacity (MW)
599.0 598.4 441.7 365.3 297.4 270.4
(Generation-Demand-Losses)
Non-Contracted Generating Capacity (MW) 0.0 0.0 0.0 0.0 0.0 0.0
Surplus/Deficit Capacity (MW)
599.0 598.4 441.7 365.3 297.4 270.4
Including Non-Contracted Generation
Retirements 0.0 0.0 0.0 0.0 0.0 0.0
Page | 76
Five-Year Annual Transmission Capability Statement (2020 – 2024)
The transmission system data used in the power system studies to determine the system performance over
the period from 2020 to 2024 is presented in Appendix B of this document.
Table 14 shows the power plants forecasted to be in service at minimum load in each year of the study at
MITS and DTS. Under minimum load condition, it is assumed that all capacitor banks at 33kV system are
switched out by DISCOs to avoid overvoltage due to excessive reactive power.
Page | 77
Five-Year Annual Transmission Capability Statement (2020 – 2024)
Table 13: Summary of Connected Generation Used in Load Flow Studies of Maximum Demand
2020 2021 2022 2023 2024
Power Stations
Total Spare Gen Total Spare Gen Total Spare Gen Total Spare Gen Total Spare Gen
MIS
Al-Kamil (IPP) 291.4 90.4 201.0 291.4 75.1 216.2 - - - - - - - - -
Barka I (IWPP) 397.5 46.9 350.6 397.5 102.5 295.0 - - - - - - - - -
Barka II (IWPP) 688.5 143.2 545.3 688.5 143.2 545.3 688.5 93.9 594.6 688.5 62.7 625.7 - - -
Barka III (IPP) 765.5 213.3 552.2 765.5 182.9 582.6 765.5 104.4 661.1 765.5 69.9 695.6 765.5 32.4 733.1
Ibri (IPP) 1542.0 479.2 1062.8 1541.0 398.6 1142.4 1540.0 210.0 1330.0 1539.0 141.3 1397.7 1539.0 66.5 1472.5
Manah (IPP) 182.2 56.4 125.8 182.2 7.7 174.5 182.2 1.6 180.6 182.2 16.6 165.6 182.2 182.2 0.0
Rusail (IPP) 693.5 214.9 478.6 693.5 163.1 530.4 - - - - - - - - -
Sohar I (IWPP) 597.0 184.9 412.1 597.0 190.5 406.5 - - - - - - - - -
Sohar II (IPP) 765.5 237.3 528.3 765.5 207.7 557.8 765.5 104.4 661.1 765.5 69.9 695.6 765.5 32.4 733.1
Sohar III (IPP) 1743.1 539.7 1203.4 1741.8 448.8 1293.1 1739.3 234.7 1504.6 1740.7 158.2 1582.5 1739.7 73.1 1666.5
Sur (IPP) 2018.2 625.5 1392.7 2018.2 521.1 1497.1 2018.2 275.0 1743.2 2018.2 184.4 1833.8 2018.2 85.7 1932.5
Ibri Solar PV IPP - - - - - - 500.0 50.0 450.0 500.0 50.0 450.0 500.0 50.0 450.0
Power 2022 - - - - - - 600.0 76.0 524.0 600.0 154.3 445.7 600.0 221.4 378.6
Power 2024 - - - - - - - - - - - - 700.0 265.9 434.1
Manah Solar PV IPP - - - - - - - - - 500.0 350.0 150.0 1000.0 700.0 300.0
Waste-to-Energy Plant - - - - - - - - - - - - 160.0 60.0 100.0
JBB Ali wind farm - - - - - - - - - - - - 100.0 81.0 19.0
Duqm wind farm - - - - - - - - - - - - 200.0 131.5 68.5
Total Gen (MW) 9684.4 2831.8 6852.7 9682.1 2441.3 7240.8 8799.2 1150.2 7649.0 9299.7 1257.4 8042.2 10270.1 1982.3 8287.9
Gross Load (MW) 6852.7 7240.8 7649.0 8042.2 8287.9
Dhofar
NPS 273.0 273.0 0.0 273.0 273.0 0.0 273.0 209.4 63.6 273.0 144.6 128.4 273.0 113.3 159.7
Salalah Power & Desalination
445.0 119.1 325.9 445.0 69.6 375.4 445.0 63.4 381.6 445.0 59.7 385.3 445.0 61.7 383.3
Plant
Salalah II IPP 444.0 141.6 302.4 443.0 68.5 374.5 442.0 62.1 379.9 442.0 58.5 383.5 442.0 60.4 381.6
Dhofar Wind Farm 50.0 32.0 18.0 50.0 32.0 18.0 50.0 32.0 18.0 50.0 32.0 18.0 50.0 32.0 18.0
Total Gen (MW) 1212.0 565.7 646.3 1211.0 443.1 767.9 1210.0 366.9 843.1 1210.0 294.7 915.3 1210.0 267.4 942.5
Gross Load (MW) 646.3 767.9 843.1 915.3 942.5
Page | 78
Five-Year Annual Transmission Capability Statement (2020 – 2024)
Table 14: Summary of Connected Generation Used in Load Flow Studies of Minimum Demand
2020 2021 2022 2023 2024
Power Stations
Total Spare Gen Total Spare Gen Total Spare Gen Total Spare Gen Total Spare Gen
MIS
Al-Kamil (IPP) 291.4 291.4 0.0 291.4 291.4 0.0 291.4 291.4 0.0 - - - - - -
Barka I (IWPP) 397.5 397.5 0.0 397.5 397.5 0.0 397.5 397.5 0.0 - - - - - -
Barka II (IWPP) 688.5 688.5 0.0 688.5 688.5 0.0 688.5 688.5 0.0 688.5 688.5 0.0 - - -
Barka III (IPP) 765.5 354.1 411.4 765.5 340.0 425.6 765.5 345.1 420.4 765.5 394.5 371.1 765.5 400.8 364.7
Ibri (IPP) 1542.0 902.2 639.8 1541.0 879.2 661.8 1540.0 885.9 654.1 1539.0 961.8 577.2 1539.0 972.0 567.0
Manah (IPP) 182.2 182.2 0.0 182.2 182.2 0.0 182.2 182.2 0.0 182.2 182.2 0.0 182.2 182.2 0.0
Rusail (IPP) 693.5 693.5 0.0 693.5 693.5 0.0 693.5 693.5 0.0 - - - - - -
Sohar I (IWPP) 597.0 597.0 0.0 597.0 597.0 0.0 597.0 597.0 0.0 - - - - - -
Sohar II (IPP) 765.5 354.2 411.4 765.5 340.0 425.6 765.5 345.1 420.4 765.5 394.5 371.1 765.5 400.8 364.7
Sohar III (IPP) 1743.1 1018.6 724.5 1741.8 991.4 750.4 1739.3 766.1 973.2 1740.7 881.7 859.0 1739.7 895.7 844.0
Sur (IPP) 2018.2 934.2 1084.0 2018.2 897.0 1121.2 2018.2 910.0 1108.2 2018.2 1040.2 978.0 2018.2 1057.3 960.9
Ibri Solar PV IPP - - - - - - - - - 450.0 0.0 450.0 500.0 50.0 450.0
Power 2022 - - - - - - - - - 600.0 600.0 0.0 600.0 600.0 0.0
Manah Solar PV IPP - - - - - - - - - 0.0 0.0 0.0 500.0 350.0 150.0
Total Gen (MW) 9684.4 6413.4 3271.0 9682.1 6297.6 3384.5 9678.6 6102.3 3576.3 8749.7 5143.4 3606.3 8610.1 4908.8 3701.3
Gross Load (MW) 3271.0 3384.5 3576.3 3606.3 3701.3
Dhofar
NPS 273.0 273.0 0.0 273.0 273.0 0.0 273.0 273.0 0.0 273.0 273.0 0.0 273.0 273.0 0.0
Salalah Power & Desalination
445.0 368.4 76.6 445.0 322.6 122.4 445.0 284.1 160.9 445.0 272.8 172.2 445.0 246.0 199.0
Plant
Salalah II IPP 444.0 245.1 198.9 443.0 231.6 211.4 442.0 234.1 207.9 442.0 219.4 222.6 442.0 236.2 205.8
Dhofar Wind Farm 50.0 32.0 18.0 50.0 32.0 18.0 50.0 32.0 18.0 50.0 32.0 18.0 50.0 32.0 18.0
Total Gen (MW) 1212.0 918.5 293.5 1211.0 859.2 351.7 1210.0 823.2 386.8 1210.0 797.2 412.8 1210.0 787.2 422.8
Gross Load (MW) 293.5 351.7 386.8 412.8 422.8
Page | 79
Five-Year Annual Transmission Capability Statement (2020-2024)
The key results of the load flow and fault level studies on OETC transmission system are presented in detail
in Appendix C for each year over the period from 2020 to 2024. System diagrams from C.1 to C.10 show
the results of the peak demand for MIS and Dhofar System. Load flows have been produced and are
available for both MIS and Dhofar System in Appendix C.
The results for MIS and Dhofar System include the following:
Table C.1 shows the transformer percentage loading of all grid stations at system peak demand.
Table C.2 shows the available spare capacity at each grid station in relation to firm capacity at system
peak demand. It should be noted that although spare MVA capacities are available at some individua l
grid stations, there is no guarantee that all can be exploited simultaneously. Lack of available
generation and/or voltage level limits may restrict simultaneous utilization of all spare MVA capacities.
Table C.3 shows the percentage loading of each overhead line and underground cable in the
transmission system at system peak demand.
Tables C.4 and C.5 show the voltage profile at each 400kV, 220kV, 132kV and 33kV bus-bar at
maximum and minimum load respectively.
Table C.6 shows the calculated transmission losses and generation margin at peak demand.
Tables C.7 and C.8 show the maximum three-phase and single-phase to earth short circuit currents
respectively.
Page | 80
Five-Year Annual Transmission Capability Statement (2020-2024)
conditions at some locations. The number will decrease to one 132/33kV at the summer peak of 2022
and 2023.
d) The numbers of out-of-firm 132/33kV grid stations during the period 2020 to 2024 are as follows. The
same is also shown graphically in Figure 26
2020 – 6
2021 – 3
2022 – 1
2023 – 1
2024 – 0
e) In the summer peak of 2020, there is one transformer temporarily supplying their individual loads in
order to mitigate over firm issues and provide additional capacity at Barka Main 132/33kV grid station.
From 2022, there will be no transformer operating individually
f) Two 132kV overhead transmission lines and underground cables are exceeding their corresponding
firm capacity in 2020 and four in 2022.
g) All 220kV overhead transmission lines and underground cables are within their corresponding firm
capacity over the years 2020 to 2024 except one 220kV OHL will be exceeding its corresponding firm
capacity in 2020 and 2022.
h) All 400kV overhead transmission lines and underground cables are well within their corresponding
firm capacity over the years 2020 to 2024.
i) Implementation of the development projects described in Section 5 and the updated load transfer
programme of Table 9 will restore the full system to be in compliance with Transmission Security
Standard requirements.
Page | 81
Five-Year Annual Transmission Capability Statement (2020-2024)
0
2020 2021 2022 2023 2024
Figure 26: Number of out-of-firm 132/33kV grid stations of MIS during 2020-2024
Page | 82
Five-Year Annual Transmission Capability Statement (2020-2024)
e) The voltage at 220kV and 132kV busbars is maintained within the allowable range (depending
on the load), whereas the voltage at the grid supply points is well regulated at almost 33kV (1.0
p.u.).
Page | 83
Five-Year Annual Transmission Capability Statement (2020-2024)
Peak Voltage Profile Off Peak Voltage Profile Max Limit Min Limit
Peak Voltage Profile Off Peak Voltage Profile Max Limit Min Limit
Peak Voltage Profile Off Peak Voltage Profile Max Limit Min Limit
1.03
1.00
0.97
0.94
Peak Voltage Profile Off Peak Voltage Profile Max Limit Min Limit
Figure 27: MIS Peak & off Peak Voltage profile at 400kV, 220kV, and 132kV and 33kV busbars in 2020
Page | 84
Five-Year Annual Transmission Capability Statement (2020-2024)
Peak Voltage Profile Off Peak Voltage Profile Max Limit Min Limit
1.05
1.00
0.95
0.90
Peak Voltage Profile Off Peak Voltage Profile Max Limit Min Limit
1.05
1.00
0.95
0.90
Peak Voltage Profile Off Peak Voltage Profile Max Limit Min Limit
1.03
1.00
0.97
0.94
Peak Voltage Profile Off Peak Voltage Profile Max Limit Min Limit
Figure 28: MIS Peak & off Peak Voltage profile at 400kV, 220kV, 132kV and 33kV busbars in 2024
Page | 85
Five-Year Annual Transmission Capability Statement (2020-2024)
Peak Voltage Profile Off Peak Voltage Profile Max Limit Min Limit
1.06
1.04
1.02
1.00
0.98
0.96
0.94
Peak Voltage Profile Off Peak Voltage Profile Max Limit Min Limit
Figure 29: DTS Peak & off Peak Voltage profile at 132kV and 33kV busbars in 2020
Page | 86
Five-Year Annual Transmission Capability Statement (2020-2024)
Peak Voltage Profile Off Peak Voltage Profile Max Limit Min Limit
1.04
1.02
1.00
0.98
0.96
0.94
Peak Voltage Profile Off Peak Voltage Profile Max Limit Min Limit
Figure 30: DTS Peak & off Peak Voltage profile at 132kV and 33kV busbars in 2024
Page | 87
Five-Year Annual Transmission Capability Statement (2020-2024)
2.00
1.50
1.00
0.50
0.00
2020 2021 2022 2023 2024
Figure 31: Transmission power losses at peak demand of MIS of the years 2020-2024
Page | 88
Five-Year Annual Transmission Capability Statement (2020-2024)
0.50%
0.40%
0.30%
0.20%
0.10%
0.00%
2020 2021 2022 2023 2024
Figure 32: Transmission power losses at peak demand of DTS of the years 2020-2024
Page | 89
Five-Year Annual Transmission Capability Statement (2020-2024)
8000
7000
6000
5000
4000
3000
2000
1000
0
2020 2021 2022 2023 2024
Figure 33: Peak load growth of MITS System over the period 2020-2024
1000
800
600
400
200
0
2020 2021 2022 2023 2024
Figure 34: Peak load growth of Dhofar System over the period 2020-2024
The load flow studies show that the planned 400kV, 220kV and 132kV transmission developments will add
substantial new capacity to the transmission system that will enable the transmission system as a whole to
cope with new demand in compliance with the Transmission Security Standard. Consequently,
opportunities for the connection of new load should be available where spare capacity exists.
Page | 90
Five-Year Annual Transmission Capability Statement (2020-2024)
All of the 400kV busbars have fault levels well within the corresponding switchgear ratings.
All of the 220kV busbars have fault levels within the corresponding switchgear ratings.
All of the 132kV busbars have fault levels within the corresponding switchgear ratings.
All of the 33kV busbars have fault levels within the corresponding switchgear ratings.
Page | 91
Five-Year Annual Transmission Capability Statement (2020-2024)
9. Development Opportunities
From the results of the load flow and fault level studies, and from analysis of the magnitude and location s
of generation and demand on the transmission system it is possible to give some indications as to where
future generation and demand can be connected to the transmission system without causing any critical
technical issues.
Figure 35 shows the future connectivity of Oman electrical systems with introduction of proposed North-
South Interconnector which will connect MIS with PDO, Duqm, Mahout and Dhofar systems. The future
integrated system extends over the northern regions of Oman, from Madinat Shinas grid station to the south
reaching Mirbat grid station with direct distance of 875km. To assess how generation and load are
distributed over the transmission system the whole supply area has been split into nine geographic areas:
a) Muscat
b) Al Batinah South
c) Al Batinah North
d) Al Buraimi
e) Al Dhahirah
f) Al Dakhiliah
g) Al Sharqiyah
h) Al Wusta
i) Dhofar
Page | 92
Five-Year Annual Transmission Capability Statement (2020-2024)
Page | 93
Five-Year Annual Transmission Capability Statement (2020-2024)
Table 15 compares the generation capacity installed in each of the nine areas with the forecast demand at
the grid stations at the annual system peak over the period from 2020 to 2024.
Table 15: Estimated Power Surplus and Power Deficit on an Area Basis (2020-2024)
Page | 94
Five-Year Annual Transmission Capability Statement (2020-2024)
Table 15 (continued): Estimated Power Surplus and Power Deficit on an Area Basis (2020-2024)
Grid Station loads at System Peak Demand
Area Grid & Power Stations
2020 2021 2022 2023 2024
Qurum 93.2 95.1 97.0 98.9 100.9
Quryiat 51.9 53.5 55.1 56.7 58.4
TX-1 & TX-2 54.1 58.4 61.9 65.7 69.6
Rusail Industrial
TX-3 & TX-4 88.3 95.4 101.1 107.2 113.6
TX-1 & TX-2 128.9 100.4 104.4 108.6 112.9
Seeb Main
TX-3 & TX-4 85.1 89.3 92.9 96.6 100.5
Wadi Adai 81.3 82.9 84.6 86.3 88.0
TX-1 & TX-2 69.1 69.1 69.1 69.1 69.1
Muscat Wadi Kabir
TX-3 & TX-4 59.6 59.6 59.6 59.6 59.6
Yitti 17.2 17.6 17.9 18.3 18.7
Muscat Airport 30.4 30.4 30.4 30.4 30.4
Muscat Steel 0.0 0.0 0.0 0.0 0.0
Modern Steel 0.0 0.0 0.0 0.0 0.0
R.O Ghoubrah 22.0 22.0 22.0 22.0 22.0
Total Load (MW) 2626.5 2796.1 2941.7 3075.6 3193.1
Power Surplus/Deficit (MW) -1933.0 -2102.6 -2341.7 -2475.6 -2593.1
Barka I Power & Desalination Plant 397.5 397.5 0.0 0.0 0.0
Barka II IPP 688.5 688.5 688.5 688.5 0.0
Barka III IPP 765.5 765.5 765.5 765.5 765.5
Barka WTE 0.0 0.0 0.0 0.0 100.0
Power 2024 0.0 0.0 0.0 0.0 700.0
Total Generation (MW) 1851.5 1851.5 1454.0 1454.0 1565.5
TX-1 & TX-2 56.2 59.0 62.0 65.1 67.0
Barka Main
TX-3 28.6 12.4 0.0 0.0 0.0
Blue City 124.3 128.0 140.8 144.8 148.9
Hay Asim 53.2 66.6 83.2 84.9 86.7
TX-1 & TX-2 111.1 85.5 88.9 92.5 95.3
Al Batinah South Khadhra
TX-3 & TX-4 34.3 65.7 68.3 71.1 73.2
TX-1 & TX-2 111.7 92.2 100.9 103.8 106.7
Madinat Barka
TX-3 & TX-4 25.0 50.0 52.0 54.1 55.7
MIS 45.3 47.2 48.6 50.0 51.5
TX-1 & TX-2 104.7 85.9 100.2 103.7 106.5
Muladah
TX-3 & TX-4 22.7 46.6 48.4 50.4 51.9
Nakhal 76.5 85.6 88.0 90.5 93.0
Rustaq 3x125MVA 159.4 116.8 121.5 126.3 130.1
Suwaiq 61.2 67.9 77.6 80.3 82.4
Wadi Bani Auwf 0.0 49.0 51.0 53.0 54.6
Total Load (MW) 1014.2 1058.4 1131.5 1170.4 1203.4
Power Surplus/Deficit (MW) 837.3 793.1 322.5 283.6 362.1
Page | 95
Five-Year Annual Transmission Capability Statement (2020-2024)
Table 15 (continued): Estimated Power Surplus and Power Deficit on an Area Basis (2020-2024)
Grid Station loads at System Peak Demand
Area Grid & Power Stations
2020 2021 2022 2023 2024
Sohar I Power & Desalination Plant 566.0 566.0 0.0 0.0 0.0
Sohar II IPP 765.5 765.5 765.5 765.5 765.5
Sohar III IPP 1743.1 1741.8 1739.3 1740.7 1739.7
Total Generation (MW) 3074.6 3073.4 2504.8 2506.3 2505.2
Dil Abdusalam 73.3 78.3 80.6 82.3 87.2
Khaborah 88.0 91.2 95.4 99.7 104.3
TX-1 & TX-2 56.1 59.8 56.7 59.9 63.0
Liwa
TX-3 & TX-4 67.2 73.0 76.4 79.8 82.1
Madinat Shinas 64.5 73.7 78.9 82.9 86.6
Saham 86.2 87.4 90.0 90.2 95.1
Shinas 64.8 67.3 79.6 84.3 91.7
SIA 76.8 84.4 84.9 85.4 86.1
TX-1 & TX-2 55.7 58.6 68.2 90.0 94.4
Sohar
TX-3 & TX-4 108.7 112.9 112.8 97.5 100.7
Al Batinah North TX-1 & TX-2 36.6 41.0 44.9 41.2 42.2
Sohar Free Zone
TX-3 & TX-4 49.1 50.4 51.4 52.6 54.3
TX-1 & TX-2 52.2 53.8 55.5 58.2 60.0
Uwaynat
TX-3 & TX-4 60.8 62.9 64.7 68.7 71.1
Sohar Refinery (132kV SIA) 0.0 0.0 0.0 0.0 0.0
Sohar Steel (SSSRM) (132kV SIA) 0.0 0.0 0.0 0.0 0.0
Jindal Shadeed (220kV SIA) 60.0 60.0 100.0 100.0 100.0
VALE (132kV SIA) 85.0 85.0 85.0 85.0 85.0
ARMS (132kV Liwa) 4.2 4.2 4.2 4.2 4.2
OMPET (132kV SIA) 0.0 4.0 4.0 4.0 4.0
Orpic (Liwa Plastic) (220kV SPS-2) 25.0 25.0 25.0 25.0 25.0
Moon Iron & Steel Co. (220KV SFZ) 15.0 15.0 15.0 15.0 15.0
Al Tamam INDSIL (132kV SFZ) 8.0 8.0 8.0 8.0 8.0
Total Load (MW) 1137.0 1195.8 1281.1 1313.9 1360.2
Power Surplus/Deficit (MW) 1937.6 1877.5 1223.7 1192.3 1145.0
Total Generation (MW) 0.0 0.0 0.0 0.0 0.0
Bureimi 48.4 51.3 53.3 55.5 56.9
TX-1 & TX-2 40.2 41.0 42.0 43.1 44.6
Buriami Industrial
TX-3 & TX-4 50.4 59.6 61.2 62.9 66.4
Al Bureimi
Mahadah 24.1 17.2 17.4 17.8 18.0
Wadi Sa'a 14.1 16.5 18.1 20.4 22.6
Total Load (MW) 177.2 185.6 192.1 199.7 208.6
Power Surplus/Deficit (MW) -177.2 -185.6 -192.1 -199.7 -208.6
Page | 96
Five-Year Annual Transmission Capability Statement (2020-2024)
Table 15 (continued): Estimated Power Surplus and Power Deficit on an Area Basis (2020-2024)
Grid Station loads at System Peak Demand
Area Grid & Power Stations
2020 2021 2022 2023 2024
Ibri IPP 1541.7 1540.6 1539.6 1538.5 1537.7
Ibri Solar PV IPP 0.0 0.0 450.0 450.0 450.0
Total Generation (MW) 1541.7 1540.6 1989.6 1988.5 1987.7
Al Hayl 40.5 7.6 7.7 7.8 8.0
Dank 38.1 42.6 47.7 51.3 52.2
Al Dhahirah Dreez 79.3 81.5 83.7 88.2 90.7
2x63MVA 38.9 40.1 41.3 40.6 41.9
Ibri
2x125MVA 78.2 80.2 82.2 84.3 86.8
Yanqul 0.0 33.5 34.4 35.4 36.7
Total Load (MW) 275.1 285.5 297.0 307.6 316.3
Power Surplus/Deficit (MW) 1266.6 1255.2 1692.6 1680.9 1671.4
Manah IPP 182.2 182.2 182.2 182.2 182.2
Manah Solar PV IPP 0.0 0.0 0.0 150.0 300.0
Total Generation (MW) 182.2 182.2 182.2 332.2 482.2
Adam 52.5 55.1 57.9 60.8 62.6
Bahla 74.9 78.6 82.5 86.7 90.1
Birkat Al Mouz 50.8 53.8 57.1 60.5 64.1
Izki 81.2 87.5 90.0 91.7 93.5
Jebreen 64.0 66.5 69.2 71.9 74.1
Al Dakhiliah
Madinat Nizwa 63.2 65.8 68.4 71.1 73.3
New Izki 20.6 21.4 22.3 23.2 23.9
Nizwa 85.1 96.6 109.3 112.0 114.8
2x63MVA 52.4 54.0 55.1 56.2 57.3
Sumail
2x125MVA 108.9 59.6 62.0 63.9 65.8
Sumail Industrial Area 0.0 53.6 55.2 56.9 58.6
Total Load (MW) 653.6 692.6 728.9 754.8 778.0
Power Surplus/Deficit (MW) -471.4 -510.4 -546.7 -422.6 -295.8
Al Kamil IPP 291.4 291.4 0.0 0.0 0.0
Sur IPP 2018.2 2018.2 2018.2 2018.2 2018.2
JBB Ali Wind Farm 0.0 0.0 0.0 0.0 19.0
Total Generation (MW) 2309.6 2309.6 2018.2 2018.2 2037.2
Al Jawabi 0.0 0.0 0.0 0.0 80.0
Al Sharqiyah
Ayjah 72.7 74.9 89.3 91.6 94.0
Bedyah 49.8 51.8 53.9 56.0 58.3
Ibra 79.9 83.0 86.2 89.5 92.1
JBB Ali 120.0 146.8 151.8 157.0 82.4
JBB Hassan 73.2 83.1 86.2 89.4 92.7
Page | 97
Five-Year Annual Transmission Capability Statement (2020-2024)
Table 15 (continued): Estimated Power Surplus and Power Deficit on an Area Basis (2020-2024)
Grid Station loads at System Peak Demand
Area Grid & Power Stations
2020 2021 2022 2023 2024
Mudhaibi 47.0 48.9 55.7 57.7 59.3
Mudhairib 56.5 64.7 67.1 69.5 71.4
Samad 25.0 25.8 26.5 27.3 28.1
Al Sharqiyah Sinaw 35.0 36.8 38.2 39.7 40.9
Sur 94.0 96.8 99.6 102.4 105.4
Total Load (MW) 653.2 712.5 754.4 780.2 804.6
Power Surplus/Deficit (MW) 1656.3 1597.0 1263.8 1238.0 1232.6
Duqm Wind Farm 0.0 0.0 0.0 0.0 68.5
Total Generation (MW) 0.0 0.0 0.0 0.0 68.5
TX-1 & TX-2 0.0 0.0 0.0 60.8 61.8
Duqm
Al Wusta TX-3 & TX-4 0.0 0.0 0.0 53.4 54.3
Mahout (2X125MVA) 0.0 0.0 0.0 23.9 24.9
Total Load (MW) 0.0 0.0 0.0 138.0 141.0
Power Surplus/Deficit (MW) 0.0 0.0 0.0 -138.0 -72.5
NPS 273.0 273.0 273.0 273.0 273.0
Salalah Power & Desalination Plant 430.0 430.0 430.0 430.0 430.0
Salalah II IPP 444.0 443.0 442.0 442.0 442.0
Dhofar Wind Farm 18 18 18 18 18
Total Generation (MW) 1165.0 1164.0 1163.0 1163.0 1163.0
Al Qarm (2x63MVA) 34.4 33.2 36.0 27.7 28.5
Ashoor (2X125MVA) 68.7 55.8 56.7 56.7 57.7
Saih Al Khairat (2x125MVA) 0.0 0.0 0.0 44.2 45.8
Ittin (2X125MVA) 78.4 71.8 74.8 83.5 87.1
Mirbat 2x63 MVA 0.0 20.9 24.9 26.9 29.1
NPS (2x63MVA) 39.7 38.8 41.9 43.1 44.7
Dhofar
TX-1 & TX-2 65.0 80.6 88.5 101.9 105.5
S'aadah
TX-3 & TX-4 44.3 66.5 87.2 102.3 105.9
Raysut 101.7 111.5 109.0 108.3 108.5
Salalah-IPP 39.7 69.0 101.1 107.5 112.0
Shaha'aon (2X125MVA) 95.3 99.4 98.3 81.9 85.0
2x30 MVA 24.2 0.0 0.0 0.0 0.0
Thumrait
2x63 MVA 0.0 28.8 32.6 33.6 34.6
Salalah Airport 7.0 8.0 8.0 8.0 8.0
Salalah Methanol Company 0.0 35.0 35.0 35.0 35.0
Total Load (MW) 598.2 719.3 794.1 860.6 887.3
Power Surplus/Deficit (MW) 566.7 444.7 368.8 302.4 275.6
Page | 98
Five-Year Annual Transmission Capability Statement (2020-2024)
Figure 36 to Figure 44 show graphically the generation and load in each of the nine areas. The significant
differences in generation and load imbalance in areas such as Muscat, Al Batinah North, Al Dhahirah and
Al Sharqiyah necessitate high development and investment in the transmission system to facilitate power
transfer among the different areas in order to supply the growing loads.
Muscat area, although geographically the smallest area, is by far the most heavily populated, with the
highest demand (2626.5 MW in 2020, rising to 3193.1 MW in 2024) and with a limited amount of connected
generation (693.5 MW in 2020 and will be retired by end of 2021). This will result in power deficits of
1933 MW in 2020 and 3193.1 MW in 2024. Muscat area has one power plant; Rusail IPP (693.5 MW in
2020 and will be retired by end of 2021). In addition Power 2022 proposed to be in Muscat (600 MW from
2022 to 2024). As observed from Figure 36, there is a high gap between the installed generation capacity
and load in Muscat area and it will keep increasing if no new generation is installed in Muscat area. This
situation will have significant adverse impacts on the system operation performance and security. These
impacts are reflected in a massive power been imported from the far generation such as Sur, Ibri and Barka
to supply Muscat load, which has resulted in an increase of transmission power losses. Moreover, the
absence of sufficient generation capacity in Muscat area has led to a shortage of the reactive power support,
which may lead OETC to invest in expensive reactive power compensations to overcome this issue and
maintain the voltage system stability. Furthermore, in order to secure the power supply in Muscat area,
OETC has to reinforce and extend the 400kV and 220kV transmission systems, which has high cost
implication. Therefore, there is a high need to plan the new generation to be located in Muscat vicinity.
Muscat Area
3500
3000
Power (MW)
2500
2000
500
0
2020 2021 2022 2023 2024
Page | 99
Five-Year Annual Transmission Capability Statement (2020-2024)
Al Batinah South area covers the coastal strip between Barka on the western outskirts of the Muscat area
and Sohar. This area is likely to develop as Muscat, since the main road link between Muscat and Sohar
runs through it. Currently, there are three power plants in Al Batiniah South; Barka Phase-I (397.5 MW and
it is planned to be retired by end of 2021), Barka Phase-II (688.5 MW and it is planned to be retired by end
of 2023) and Barka Phase-III (765.5 MW).Further, Waste to Energy plant and Power 2024 will be
introduced in 2024 (100 MW and 700 MW respectively). As shown in Table 15, the load in this area rises
from 1014.2 MW in 2020 to 1203.4 MW in 2024. The power surplus is 837.3 MW in the summer peak of
2020 and 362.1 MW in the summer peak of 2024.
2000
1800
1600
Power (MW)
1400
1200
1000
800 Total Generation (MW)
600 Total Load (MW)
400
200
0
2020 2021 2022 2023 2024
Al Batinah North area is rapidly developing around the new port at Sohar with new industries seeking
connections to the OETC transmission system or the distribution system of Majan Electricity Company.
Some of the largest industrial customers in the area, such as Sohar Aluminium Company operates their own
generating plant and on occasions supply power to the transmission system on a non-contracted basis. The
load in Al Batinah North area significantly increases from 1137 MW in 2020 to 1360.2 MW in 2024, as
shown in Table 15. Al Batinah North area has three power plants; Sohar-I (566 MW and it is planned to be
retired by end of 2021), Sohar-II (with total 765.5 MW power during the period 2020-2024) and Sohar-III
IPP with a power capacity of 1743.1 MW. In 2020, the generation surplus in this area will be 1937.6 MW
and will decrease to 1145 MW in 2024 due to the retirement of Sohar-I power plant.
Page | 100
Five-Year Annual Transmission Capability Statement (2020-2024)
3500
3000
2500
Power (MW)
2000
Total Generation (MW)
1500
Total Load (MW)
1000
500
0
2020 2021 2022 2023 2024
The transmission system in the Al Buraimi area provides interconnection with the GCCIA through UAE
(Abu Dhabi Transco) supplies a number of grid stations that feed Majan Distribution System. This area has
no generation and depends on the transmission interconnections with Al Batinah North and Al Dhahirah
regions to supply its loads. The load in Al Buraimi area increases from 177.2 MW in 2020 to 208.6 MW in
2024, as shown in Table 15. The deficiency in generation rises from 177.2 MW in 2020 to 208.6 MW in
2024.
Al Buraimi Area
250
200
Power (MW)
150
Total Generation (MW)
50
0
2020 2021 2022 2023 2024
Page | 101
Five-Year Annual Transmission Capability Statement (2020-2024)
There is a generation power plant at Al Dhahirah that is Ibri IPP with a power capacity of 1541.7 MW and
new Ibri Solar PV IPP will be in the service in 2022 with a power capacity of 450 MW. The load in this
area will increase from 275.1 MW in 2020 to 316.3 MW in 2024, as shown in Table 15. The 220kV systems
from Mahadha in Buraimi area to Ibri have produced an improvement in the voltage quality and increased
the security of supply. Moreover, the voltage profile and supply security have further improved by the
introduction of Ibri IPP in 2019 and Ibri Solar PV IPP in 2022. In 2020, the surplus in generation will be
1266.6 MW and will increase to reach 1671.4 MW in 2024.
2500
2000
Power (MW)
1500
Total Generation (MW)
500
0
2020 2021 2022 2023 2024
Al Dakhiliah area with its provincial load centres is exhibiting moderate growth up and has a local
generating power plant at Manah (182.2 MW) connected to the 132kV transmission system. There will be
a new generartion at Al Dakhiliah (Manah Solar PV IPP) where first phase will be in the service in 2023
with a power capacity of 150 MW while second phase will be in service in 2024 with a power capacity of
150 MW. A connection between OETC and PDO is available in the area through the 132kV Nizwa- Nahada
transmission line. Another connection will be introduced between these two systems via line in line out Ibri
IPP – New Izki 400kV overhead line at Nahada area and it is expected to be in service by Q3 2022.The
deficiency in generation will decrease from 471.4 MW in 2020 to 295.8 MW in 2024.
Page | 102
Five-Year Annual Transmission Capability Statement (2020-2024)
900
800
700
Power (MW)
600
500
400
Total Generation (MW)
300
200 Total Load (MW)
100
0
2020 2021 2022 2023 2024
2500
2000
Power (MW)
1500
Total Generation (MW)
1000 Total Load (MW)
500
0
2020 2021 2022 2023 2024
Page | 103
Five-Year Annual Transmission Capability Statement (2020-2024)
Currently, OETC has no transmission system in the Al Wusta area and the loads are supplied by RAEC by
using diesel generation. In 2023, phase one of 400kV interconnection line project will be ready including
connecting PDO and RAEC systems via Suwaihat, Duqm and Mahout grid stations. RAEC loads will be
supplied via PDO system and this area will depend on the new 400kV transmission interconnection line
with Al Dakhiliah governorate once it is ready by end of 2024. Further, a new wind farm will be constructed
in Duqm (68.5MW and will be ready by 2024).The load in Al Wusta area is expected to be 138 MW and
141MW in 2023 and 2024 respectively. In addition, Table 15 shows that the deficiency in generation in
2023 will be 138 MW and will decrease in 2024 to be 72.5 MW.
Al Wusta Area
160
140
120
Power (MW)
100
40
20
0
2020 2021 2022 2023 2024
The transmission system in the Dhofar area provides another interconnection with PDO and supplies a
number of grid stations that feed DPC Distribution System to supply Salalah city, and a number of towns
and villages in Dhofar area. Currently, there are four power plants in Dhofar area; NPS Power Plant (273
MW), Salalah IPP Power Plant (430 MW), Salalah II IPP (444 MW) and Dhofar wind farm with a power
capacity of 18 MW. As shown in Table 15, the load in Dhofar area will rise from 598.2 MW in 2020 to
887.3 MW in 2024. The generation surplus will decrease from 566.7 MW in 2020 to 275.6 MW in 2024
due to new bulk loads.
Page | 104
Five-Year Annual Transmission Capability Statement (2020-2024)
Dhofar Area
1400
1200
1000
Power (MW)
800
200
0
2020 2021 2022 2023 2024
Page | 105
Five-Year Annual Transmission Capability Statement (2020-2024)
Table 16: Available Grid Station Capacity of more than 10 MVA in 2024
Available Capacity Available Capacity
Region Grid Station Name Grid Station Name
(MVA) (MVA)
Airport Heights (TX-1 & TX-2) 23.12 Khoudh (TX-3 & TX-4) 51.89
Airport Heights (TX-3 & TX-4) 73.85 Mawalleh North 18.00
Al Falaj 36.01 Mawalleh South (TX-1 & TX-2) 16.08
Amerat (TX-1 & TX-2) 12.83 Mawalleh South (TX-3 & TX-4) 40.34
Amerat (TX-3 & TX-4) 20.62 Misfah 38.88
A'salam (TX-1 & TX-2) 24.76 Mobella 42.19
A'salam (TX-3 & TX-4) 26.52 MSQ (TX-1 & TX-2) 26.64
Bousher (TX-3 & TX-4) 11.75 MSQ (TX-3 & TX-4) 28.76
Muscat Daghmar 66.32 Muttrah 50.05
Ghala (TX-1 & TX-2) 13.34 Qurum 18.78
Ghala (TX-3 & TX-4) 65.76 Quryiat 63.50
Ghala Heights (TX-1 & TX-2) 34.33 Rusail Industrial (TX-1 & TX-2) 51.74
Ghala Heights (TX-3 & TX-4) 38.15 Seeb Main (TX-3 & TX-4) 19.23
Mobella Industrial (TX-1 & TX-2) 53.37 Wadi Adai 32.37
Mobella Industrial (TX-3 & TX-4) 32.31 Wadi Kabir (TX-1 & TX-2) 52.28
Jahloot 71.29 Wadi Kabir (TX-3 & TX-4) 62.27
Khoudh (TX-1 & TX-2) 72.65 Yitti 105.36
Barka Main 54.47 Muladah (TX-1 & TX-2) 12.88
Hay Asim 33.77 Muladah (TX-3 & TX-4) 70.38
khadhra (TX-1 & TX-2) 24.72 Nakhal 27.12
Al Batinah
khadhra (TX-3 & TX-4) 47.96 Rustaq 3x125M VA 113.02
South
Madinat Barka (TX-1 & TX-2) 12.67 Suwaiq 38.31
Madinat Barka (TX-3 & TX-4) 66.37 Wadi Bani Auwf 67.54
MIS 70.76
Dil Abdusalam 33.23 SIA 34.39
Khaborah 15.16 Sohar (TX-1 & TX-2) 25.59
Liwa (TX-1 & TX-2) 58.69 Sohar (TX-3 & TX-4) 18.97
Al Batinah
Liwa (TX-3 & TX-4) 38.54 Sohar Free Zone (TX-1 & TX-2) 80.54
North
Madinat Shinas 33.80 Sohar Free Zone (TX-3 & TX-4) 67.84
Saham 24.90 Uwaynat (TX-1 & TX-2) 61.83
Shinas 28.49 Uwaynat(TX-3 & TX-4) 50.13
Bureimi 65.08 Mahadah 11.02
Al Buraimi Bureimi Industrial(TX-1&TX-2) 78.06 Wadi Sa'a 39.17
Bureimi Industrial(TX-3&TX-4) 55.08
Al Hayl 31.58 Ibri 2x125MVA 33.66
Al Dhahirah Dreez 29.49 Yanqul 86.34
Ibri 2x63MVA 18.91
Page | 106
Five-Year Annual Transmission Capability Statement (2020-2024)
Table 16 (continued): Available Grid Station Capacity of more than 10 MVA in 2024
Jebreen 47.00
Dhofar Saih Al Khairat (2x125M VA) 76.79 S’aadah (TX-3 & TX-4) 13.51
Shaha'aon (2X125MVA) 35.49 Raysut 10.79
Ittin (2X125MVA) 33.37 Thumrait 2x63 MVA 26.58
Page | 107
Five-Year Annual Transmission Capability Statement (2020-2024)
125
100
75
S(MVA)
Available MVA
50
Used MVA
25
Grid Station
Figure 45: Used and available MVA in Muscat area at 2024 peak demand
125
100
75
S(MVA)
50 Available MVA
25 Used MVA
Grid Station
Figure 46: (Continued) Used and available MVA in Muscat area at 2024 peak demand
Page | 108
Five-Year Annual Transmission Capability Statement (2020-2024)
125
100
75
50
S(MVA)
25 Available MVA
0 Used MVA
Grid Station
Figure 47: (Continued) Used and available MVA in Muscat area at 2024 peak demand
250
225
200
175
150
S(MVA)
125
100
75 Available MVA
50 Used MVA
25
0
Grid Station
Figure 48: Used and available MVA in Al Batinah South area at 2024 peak demand
Page | 109
Five-Year Annual Transmission Capability Statement (2020-2024)
125
100
75
S(MVA)
50
Available MVA
Used MVA
25
Grid Station
Figure 49: Used and available MVA in Al Batinah North area at 2024 peak demand
125
100
75
50
S(MVA)
25 Available MVA
Used MVA
0
Grid Station
Figure 50: Used and available MVA in Al Buraimi and Al Dhahirah areas at 2024 peak demand
Page | 110
Five-Year Annual Transmission Capability Statement (2020-2024)
125
100
75
S(MVA)
50
Available MVA
25
Used MVA
Grid Station
Figure 51: Used and available MVA in Al Dakhiliah area at 2024 peak demand
125
100
S(MVA)
75
50
Available MVA
25
Used MVA
0
Grid Station
Figure 52: Used and available MVA in Al Sharqiyah area at 2024 peak demand
Page | 111
Five-Year Annual Transmission Capability Statement (2020-2024)
125
100
S(MVA)
75
50 Available MVA
Used MVA
25
0
Duqm (TX-1&TX-2) Duqm (TX-3&TX-4) Mahout (2X125MVA)
Grid Station
Figure 53: Used and available MVA in Al Wusta area at 2024 peak demand
125
100
75
S(MVA)
50
Available MVA
25
Used MVA
0
Grid Station
Figure 54: Used and available MVA in Dhofar area at 2024 peak demand
Page | 112
Five-Year Annual Transmission Capability Statement (2020-2024)
For power 2024, five potential sites has been considered: Misfah, Barka, Ghubrah, Sohar,Manah and Al
Kamil. Misfah site was recommended for power 2022, however OPWP has postponed the project. This
investment would require constructing 220kV GIS, diversion of Misfah - Wadi Adai 132kV UGC in Misfah
generation location, diversion of Misfah - MSQ 220kV OHL to 220kV UGC in Misfah generation location
and LILO 220kV Misfah – MSQ OHL at Misfah generation location. Proposing such generation in Muscat
area close to the load will improve the voltage profile and provide security of supply within the area.
Further, it will minimize the losses produced from importing power from other governorates to Muscat.
Moreover, Muscat governorate would experience issues in voltage recovery after faults and having Misfah
generation would resolve all issues and avoid installation of reactive power compensation (i.e. SVC or
STATCOM).
Having power 2024 in Barka will help in exporting power towards Muscat governorate and to supply load
within the area. This site can accommodate up to 360MW without the need for system reinforcement and
700MW with additional reinforcement (additional 2x220kV OHL Filaj-Mobella). Furthermore, the system
studies assumed that the existing nearby generation in Barka is dispatched fully.
Similar to Misfah, Ghubrah location is close to Muscat load centre and having generation at the site will
provide reactive support to improve voltage profile and resolve voltage recovery issues. This site can
accommodate up to 700MW with minor reinforcements (additional 1x132kV GIS bay and modification of
1x132kV GIS bay at New Ghubrah).
Sohar site is proposed to accommodate power 2024, having additional capacity in Sohar would require a
huge investment in the transmission network. The investment includes additional 2x400kV bays and
2x400kV OHL SIS-Rustaq (126km). Sohar site can accommodate up to 450MW without the need for
system reinforcement and 700MW with additional reinforcement at Sohar area.
The last sites are Manah and Al kamil will be considered to share the 700MW of power 2024. The two sites
do not require any reinforcement to evacuate the proposed capacity. However, these sites are far from
Muscat load centre.
Page | 113
Five-Year Annual Transmission Capability Statement (2020-2024)
In terms of technical and financial ranking, Barka provides a good technical performance, however Barka
location considered to be little far from load centre of Muscat and it financially requires investments in
220kV system. Also, Ghubrah site provides a good technical performance and location which is closer to
Muscat. In addition, it requires minor reinforcements which makes it very attractive financially. Further,
Misfah provides a strategic location and good performance, however it requires new investments in the
transmission network which impact it is financial ranking. On the other hand, Sohar does not provide an
attractive option technically and financially. Furthermore, Manah and Al Kamil sites does not provide a
good technical performance and their locations which are from Muscat load centre. In terms of overall
ranking, Ghubrah ranked as the most preferred option while Sohar ranked as non-preferred option
considering both technical and financial ranking. Table 17 shows the potential generation connection and
the Technical and Financial rankings.
Page | 114
Five-Year Annual Transmission Capability Statement (2020-2024)
Power 2024
Constructing 220kV GIS, diversion of Misfah - Wadi
Having a generation in Muscat
Adai 132kV UGC in Misfah generation location,
area close to the load centre would
1 Misfah 700 220 diversion of Misfah - MSQ 220kV OHL to 220kV UGC 3 4
improve the voltage profile and
in Misfah generation location and LILO 220kV Misfah
provide security of supply.
– MSQ OHL at Misfah generation location.
This Site can accommodate up to
Additional 2x220kV bays and 2x220kV OHL Filaj- 360MW without the need for
2 Barka 700 220 1 3
Mobella (10 km) system reinforcement and 700MW
with additional reinforcement.
This Site is close to Muscat load
Additional 1x132kV GIS bay and modification of
3 Ghubrah 700 132 2 2 centre and can accommodate up
1x132kV GIS bay at New Ghubrah
700MW with minor reinforcement
This Site can accommodate up to
Additional 2x400kV bays and 2x400kV OHL SIS- 450MW without the need for
4 Sohar 700 220 5 5
Rustaq (126 km) system reinforcement and 700MW
with additional reinforcement
The two sites do not require any
Manah and Al
5 700 132 No requirements 4 1 reinforcement to accommodate
Kamil
700MW in total.
Page | 115
Five-Year Annual Transmission Capability Statement (2020-2024)
10. Non-compliances
The load flow studies summarised in Appendix C and discussed in Sections 8 and 9 of this Statement
indicate a number of out of firm grid stations and circuits in the early years of the Statement. In this final
section, a review of each grid station / circuit, which is currently failing to meet the Transmission Security
Standards, is presented. In addition, a description of the development activities that OETC is undertaking
to address this non-compliance and indicates the expected time by which, in each instance, full
Transmission Security Standards compliance should be achieved are presented.
It should be noted that the level of the security requirements on the transmission system would change in
future as the demand on the system increases and as the system configuration changes. It is possible that
further non-compliances will arise in the future until the overall system becomes substantially more robust
through interconnection. OETC will keep this situation under review, and the non-compliance status will
be updated in the 2021 Capability Statement.
As indicated in sections 8, 9 and summarized in Table 18,Table 19 and Table 20, there are some overhead
lines/cables and grid stations, which do not comply with the Transmission Security Standard. Therefore, it
will be necessary for a further location and duration for specific derogations to be prepared by OETC and
approved by the authority for each of the out of firm grid stations which do not comply with the
Transmission Security Standard at peak and maintenance time noted in Table 18,Table 19 and Table 20.
The following points should be noted:
1) The loading results that are shown in Tables C1 and C3 (Appendix C), are those at the peak load
conditions. The system peak lasts only for a period of less than one hour in one day during the
relevant year.
2) According to the most recent OPWP data, there are two forecast cases: (i) expected case, and (ii)
high case. The difference between the high and expected cases in 2020 for MIS is 260 MW and for
Dhofar System is 10 MW at the peak time. This difference will increase in the subsequent years
where it will reach 1480 MW for MIS and 130 MW for Dhofar System in 2024, indicating
uncertainty in the forecast over the coming years especially with regards to new industrial loads.
OETC intends to monitor closely the situation, in coordination with OPWP, in order to assess the
probability associated with the high case projection and the effect of the approved Cost Reflected
Tariff (CRT).
3) It is not prudent to invest in uncertain expansion. OETC will initiate new projects as new demand
becomes more certain. Therefore, Table 18 shows conditions at the summer peak of 2020.
4) The modelling reflects all load transfer schemes that have been formally accepted by the relevant
Distribution Company, which are included in their load forecasts.
Page | 116
Five-Year Annual Transmission Capability Statement (2020-2024)
OETC has adopted a two-fold approach to address these out of firm situations:
1) Reinforcement plans: strategic upgrading to add new circuits and/or to increase the capacity of grid
stations within a minimum of three to five years. This will not just solve the problem, but it will
also strengthen the transmission system for future development. This type of solution can only be
applied as a longer-term solution because of the time taken to implement. Reinforcement is the
most robust long-term solution for secure system development, but may not necessarily be the least
cost effective solution to address the immediate out of firm conditions on the network.
2) Load Transfer: through agreement with Distribution Companies, load can be transferred from
heavily loaded grid stations to more lightly loaded grid stations over the next years. This would
reduce the loading issues and balance the system during peak time. This is a mid-term solution,
which could be implemented by Distribution Companies in certain cases. Given the uncertainty of
mid-term load forecasts in Oman at present, this is in some circumstances the most appropriate and
economic action to address out of firm conditions on the network.
Table 18 and Table 19 indicate a number of overhead lines/cables and grid stations on the system that will
be out of firm in 2020. Table 20 shows the grid stations which are classified as group E (>115 MW) that
are not complying with the Transmission Security Standard (Second Outage) at 2020 maintenance period.
Page | 117
Five-Year Annual Transmission Capability Statement (2020-2024)
Table 18: Expected Over headlines/Cable, which will not comply with Transmission Security Standard (First Outage) at Peak Demand in 2020
Indicative
Date for full
Circuit Circuit Compliance
Sending Receiving Voltage No. of Circuit Conductor Loading
No. length Rating with the Remarks
Bus Bus (kV) Circuit Type Size/Type (% )
(Km) (MVA) Transmission
Security
Standard
Page | 118
Five-Year Annual Transmission Capability Statement (2020-2024)
Table 19: Expected Grid stations 132/33kV, which will not comply with Transmission Security Standard (First Outage) at Peak Demand in 2020
1 JBB Ali 2x125 125 52.61 June 2024 Load transfer to new Al Jawabi grid station
Majan
1 Al Hayl 2x40 40 53.62 December 2020 Load transfer to new Yanqul grid station
Page | 119
Five-Year Annual Transmission Capability Statement (2020-2024)
Table 20: Expected Grid stations 132/33kV, which will not comply with Transmission Security Standard at Maintenance Period in 2020.
Transferable
Demand
Peak Load in case of Transmission
Tx No. Forecast
Grid Station Demand Transformer Second Outage Security
No. capacity of During Remarks
Name Forecast Loading (% ) During Standard
(MVA) Txs Maintenance
(MW) Maintenance Compliant
(MW)
(MW)
Muscat
Transformer capacity has been provided
in Seeb Main grid station (TX-3&Tx-4).
1 Seeb Main 125 2 128.9 55.67 85.9 7 No
DISCO’s load transfer will solve the
non-compliance.
Transformer capacity has been provided
in Ghala Height grid station. DISCO’s
2 Bousher 125 2 124.6 55.53 83.06 38 No
load transfer will solve the non-
compliance.
Transformer capacity has been provided
in A'salam grid station (TX-3&Tx-4).
3 A'salam 125 2 124.5 53.81 83 40 No
DISCO’s load transfer will solve the
non-compliance.
Load transfer to new Mobella Industrial
4 Mobella 125 2 122.1 52.69 81.4 7 No
grid station.
Mazoon
MZEC to resolve this issue via either
1 Blue City 160 2 124.3 41.93 82.86 40 No load transfer or applying for connection
for additional capacity.
Page | 120
Five-Year Annual Transmission Capability Statement (2020-2024)
There are a significant number of projects required to meet the annual peak demands over the period of this
Statement (2020-2024). These projects are considered below under the following categories:
• Projects that are at the tender evaluation stage prior to appointment of the successful EPC
Contractor.
• Projects planned for future developments that represent the least cost options to address
problems with system growth, voltage profile, and non-compliance with the Transmission
Security Standard.
The entire programme of ongoing and future projects, which are planned for implementation over the period
2020 to 2024 are listed and described below. It should be noted that the project numbers referred in this
Appendix are identical to those in Table 1 of the Executive Summary. It should also be noted that not all of
the projects described have full authorisation at this time and they should be supported by pre investment
appraisals document to approve and to select the proper option for each project.
Project #1: Adding third and fourth 132/33kV transformer at Airport Heights
The Third and fourth 125 MVA transformers with 4x33kV GIS interlink will be added at Airport Heights
grid station to meet the Transmission Security Standard requirements and to cater for the high demand
growth within the area. This project was energised in September 2019.
Project #2: 400kV line connection between Sohar Free Zone – Mahadha & Sohar Free Zone – SIS
This project is intended to support the power evacuation from Sohar-III IPP based on the Transmission
Security Standard requirements and to support 400kV backbone network development. The construction of
this project consists of 33km of 400kV OHL from Sohar Free Zone to SIS, 62km of 400kV line connected
from Sohar Free Zone to Mahadha operated as 220kV, 1km Monopole from 400kV SFZ to 220kV SFZ,
0.26km of 220kV UGC each circuit at Mahadha end and 2x220kV GIS at Sohar Free Zone. This project
was completed in December 2019.
Page | 121
Five-Year Annual Transmission Capability Statement (2020-2024)
Project #5: Construction of a new 400kV OHL from Sohar Free Zone to Shinas
New 400kV line will be constructed between Sohar Free Zone and Shinas grid stations (operated as 132kV).
The purpose of this new line is to secure existing Shinas and new Madinat Shinas grid stations as per
Transmission Security Standard requirements during the second forced outage. This project consists of
construction of 30km of 400kV OHL (Operated as 132kV) from Sohar Free Zone grid station to Shinas
grid station with 132kV circuit breakers at Sohar Free zone and Shinas grid stations. This project was in
service by March 2020.
Page | 122
Five-Year Annual Transmission Capability Statement (2020-2024)
Project #12: Construction of 132/33kV Mirbat grid station with 2x63 MVA Transformers
The objective of this project is to construct a new 132/33kV, 2x63 MVA transformers grid station with
8x132kV GIS (6 in Mirbat & 2 in Ashoor) and 32km OHL between Mirbat and Ashoor to reinforce the
supply capacity in Ashoor Area and meet the load growth in area. This project is expected to be in service
by March 2021.
Project #13: New 132kV double circuits between Nakhal- Wadi Bani Auwf- Rustaq with a new
Wadi Bani Auwf 132/33 kV grid station
This project is including the construction of a new 86km of 132kV double circuit OHL between Nakhal
and Rustaq grid stations and a new 132/33kV grid station at Wadi Bani Auwf. This project aims to provide
additional capacity in order to relieve Rustaq grid station since the load forecast expected by Mazoon
Electricity Company that Rustaq grid will exceed the firm capacity. Also, this project will secure Rustaq
grid station since it is fed by radial 132kV double circuits and its load will be more than 100MW which fall
in Class E, according to Transmission Security Standard. Moreover, high load growth is expected between
Rustaq and Wadi Bani Auwf, so the best location for this grid station is proposed to be close to Mazoon
primary substations. This project is expected to be completed in May 2021.
Project #14: Upgrading Thumrait from 2x30 MVA to 2x63 MVA transformers
The objective of this project is to upgrade the existing Thumrait grid station from 2x30 MVA to 2x63 MVA
transformers due to high demand growth in the area. This project is expected to be in service by June 2021.
Page | 123
Five-Year Annual Transmission Capability Statement (2020-2024)
Project #18: Construction of new 132/33 kV Grid Station at Saih Al Khairat, along with associated
OHL from Thumrait to Saih Al Khairat
The objective of this project is to meet the Transmission Security Standard, to cater for the load growth in
the area and to supply RAEC load instead of using diesel generators. The project consists of 2x125 MVA
transformers (132/33kV), 6x132kV GIS in Saih Al Khairat, 2x132kV AIS at Thumrait and 88km of OHL
from Thumrait to Saih Al Khairat. The grid station is expected to be energized in December 2022.
Project #19: Installation of Third 500 MVA Transformer at Airport Heights and New 132kV UGC
circuit between Airport Heights and Ghala grid stations
The objective of this project is to maintain Transmission Security Standard and meet load growth in the
area. The project consists of 500 MVA transformer (220/132 kV) at Airport Heights, 4x220kV GIS and
4x132kV GIS. This project is expected to be completed by March 2023.
Page | 124
Five-Year Annual Transmission Capability Statement (2020-2024)
Project #20: Construction of new Al Jefnen 400/132kV grid station with associated OHL and
addition of 2x500 MVA 220/132kV transformers at Misfah grid station
The objective of this project is to secure the demand group at Rusail area considering the future planned
retirements of Rusail IPP. The project will consist of new 3x500 MVA 400/132kV transformers and
upgrading the existing 132kV OHL between Misfah and Rusail Industrial from 132kV to 400kV and 4x1km
132kV UGC between New Rusail-Rusail Industrial. This project is expected to be in service by March
2023.In addition, the scope will include adding 2x500MVA 220/132kV Transformers at Misfah grid station
(which is expected to be ready by June 2022).
Page | 125
Five-Year Annual Transmission Capability Statement (2020-2024)
Page | 126
Five-Year Annual Transmission Capability Statement (2020-2024)
Although the thermal rating of an overhead line is affected by climatic conditions, for the purpose of
assessing spare capacity on the transmission system, the key climatic condition that limits the circuit rating
is the summer rating when the temperature is at its highest level and the solar radiation is at its peak. This
also corresponds to when the electricity demand is at or near to its peak.
The circuit data presented in Table B.2 for the first year of the Statement period (2020) comprises the
voltage, resistance, reactance, susceptance and thermal rating of the line and cable circuits. It also shows
the circuit length and the type of overhead conductor or underground cable for each circuit.
Table B.3 shows the changes to the circuit data required in each of the other four years covered by the
Statement.
10
T he 33kV busbars at the grid supply points and the capacitors connected to them are owned and operated by the Distr ibution Companies.
Page | 127
Five-Year Annual Transmission Capability Statement (2020-2024)
G rid Stations P
P Load Q Load Caps Q Load Caps P Load Q Load Caps P Load Q Load Caps P Load Q Load Caps
Load
(MW) (MVAr) (MVAr) (MVAr) (MVAr) (MW) (MVAr) (MVAr) (MW) (MVAr) (MVAr) (MW) (MVAr) (MVAr)
(MW)
MUSCAT AREA
TX-1 & TX-2 82.7 27.2 40 86.0 28.3 40 89.5 29.4 40 93.1 30.6 40 96.8 31.8 40
Airport Heights
TX-3 & TX-4 33.0 10.8 40 35.4 11.6 40 44.3 14.6 40 46.4 15.3 40 48.6 16.0 40
Al Falaj 78.5 25.8 40 84.5 27.8 40 84.5 27.8 40 84.5 27.8 40 84.5 27.8 40
TX-1 & TX-2 95.8 31.5 40 96.5 31.7 40 104.2 34.3 40 112.6 37.0 40 106.6 35.0 40
Amerat
TX-3 & TX-4 51.1 16.8 40 63.2 20.8 40 69.6 22.9 40 76.5 25.1 40 99.2 32.6 40
TX-1 & TX-2 124.5 40.9 40 121.3 39.9 40 84.8 27.9 40 89.8 29.5 40 95.2 31.3 40
A'salam
TX-3 & TX-4 48.0 15.8 40 89.3 29.4 40 97.4 32.0 40 105.1 34.6 40 93.6 30.8 40
TX-1 & TX-2 75.9 25.0 40 99.0 32.5 40 102.9 33.8 40 107.0 35.2 40 111.3 36.6 40
Bousher
TX-3 & TX-4 124.6 40.9 40 104.5 34.4 40 108.7 35.7 40 113.1 37.2 40 107.6 35.4 40
Daghmar 32.0 10.5 18 32.0 10.5 18 32.0 10.5 18 32.0 10.5 18 32.0 10.5 18
TX-1 & TX-2 73.4 24.1 40 94.7 31.1 40 96.1 31.6 40 104.6 34.4 40 106.1 34.9 40
Ghala
TX-3 & TX-4 50.0 16.4 40 51.5 16.9 40 53.0 17.4 40 54.6 18.0 40 56.3 18.5 40
TX-1 & TX-2 67.0 22.0 40 69.7 22.9 40 71.8 23.6 40 73.9 24.3 40 86.1 28.3 40
Ghala Heights
TX-3 & TX-4 55.0 18.1 40 67.2 22.1 40 68.9 22.7 40 80.7 26.5 40 82.5 27.1 40
Ghubrah TX-1 & TX-2 103.9 34.1 - 107.0 35.2 - 110.2 36.2 - 112.4 36.9 - 114.7 37.7 -
TX-1 & TX-2 - - - - - - 60.0 19.7 40 64.2 21.1 40.0 68.1 22.4 40
Mobella
Industrial
TX-3 & TX-4 - - - - - - 60.0 19.7 40 64.2 21.1 40.0 88.1 28.9 40
Jahloot 42.0 13.8 40 44.1 14.5 40.0 46.3 15.2 40 48.6 16.0 40.0 51.0 16.8 40
TX-1 & TX-2 - - - 30.0 9.9 40.0 31.5 10.4 40 33.1 10.9 40.0 49.7 16.3 40
Khoudh
TX-3 & TX-4 - - - 60.0 19.7 40.0 63.0 20.7 40 66.2 21.7 40.0 69.5 22.8 40
Mawalleh North 2x125 MVA 81.5 26.8 40 86.8 28.5 40 103.4 34.0 40 112.0 36.8 40 101.6 33.4 40
Page | 128
Five-Year Annual Transmission Capability Statement (2020-2024)
Table B. 1: (Continued) Load and Capacitor Data for Grid Station (2020-2024)
2020 2021 2022 2023 2024
G rid Stations P
P Load Q Load Caps Q Load Caps P Load Q Load Caps P Load Q Load Caps P Load Q Load Caps
Load
(MW) (MVAr) (MVAr) (MVAr) (MVAr) (MW) (MVAr) (MVAr) (MW) (MVAr) (MVAr) (MW) (MVAr) (MVAr)
(MW)
TX-1 & TX-2 98.1 32.2 40 92.0 30.2 40 95.7 31.4 40 99.5 32.7 40 103.5 34.0 40
Mawalleh South
TX-3 & TX-4 112.0 36.8 40 71.5 23.5 40 74.4 24.4 40 77.3 25.4 40 80.4 26.4 40
Misfah 67.3 22.1 - 70.7 23.2 - 74.2 24.4 - 77.9 25.6 - 81.8 26.9 -
Mobella 122.1 40.1 40 122.7 40.3 40 70.0 23.0 40 74.2 24.4 40 78.7 25.9 40
TX-1 & TX-2 79.2 26.0 40 87.1 28.6 40 90.2 29.6 40 91.8 30.2 40 93.4 30.7 40
MSQ
TX-3 & TX-4 76.4 25.1 40 84.5 27.8 40 87.9 28.9 40 89.6 29.5 40 91.4 30.1 40
Muttrah 71.2 23.4 - 71.2 23.4 - 71.2 23.4 - 71.2 23.4 - 71.2 23.4 -
Qurum 93.2 30.6 40 95.1 31.3 40 97.0 31.9 40 98.9 32.5 40 100.9 33.2 40
Quryiat 51.9 17.1 40 53.5 17.6 40 55.1 18.1 40 56.7 18.6 40 58.4 19.2 40
TX-1 & TX-2 54.1 17.8 - 58.4 19.2 - 61.9 20.4 - 65.7 21.6 - 69.6 22.9 -
Rusail Industrial
TX-3 & TX-4 88.3 29.0 - 95.4 31.4 - 101.1 33.2 - 107.2 35.2 - 113.6 37.4 -
TX-1 & TX-2 128.9 42.4 - 100.4 33.0 - 104.4 34.3 - 108.6 35.7 - 112.9 37.1 -
Seeb Main
TX-3 & TX-4 85.1 28.0 - 89.3 29.4 - 92.9 30.5 - 96.6 31.8 - 100.5 33.0 -
Wadi Adai 81.3 26.7 40 82.9 27.3 40 84.6 27.8 40 86.3 28.4 40 88.0 28.9 40
Tx-1 & Tx-2 69.1 22.7 40 69.1 22.7 40 69.1 22.7 40 69.1 22.7 40 69.1 22.7 40
Wadi Kabir
Tx-3 & Tx-4 59.6 19.6 40 59.6 19.6 40 59.6 19.6 40 59.6 19.6 40 59.6 19.6 40
Yitti 17.2 5.7 - 17.6 5.8 - 17.9 5.9 - 18.3 6.0 - 18.7 6.1 -
Total Muscat 33kV Load 2574.1 846.1 1018 2743.7 901.8 1098 2889.3 949.7 1178 3023.2 993.7 1178 3140.7 1032.3 1178
Muscat Airport 30.4 10.0 - 30.4 10.0 - 30.4 10.0 - 30.4 10.0 - 30.4 10.0 -
Muscat Steel 0.0 0.0 - 0.0 0.0 - 0.0 0.0 - 0.0 0.0 - 0.0 0.0 -
Modran Steel 0.0 0.0 - 0.0 0.0 - 0.0 0.0 - 0.0 0.0 - 0.0 0.0 -
R.O Ghoubrah 22.0 7.2 - 22.0 7.2 - 22.0 7.2 - 22.0 7.2 - 22.0 7.2 -
Total Muscat 2626.5 863.3 1018 2796.1 919.0 1098 2941.7 966.9 1178 3075.6 1010.9 1178 3193.1 1049.5 1178
Page | 129
Five-Year Annual Transmission Capability Statement (2020-2024)
Table B. 1: (Continued) Load and Capacitor Data for Grid Station (2020-2024)
2020 2021 2022 2023 2024
G rid Stations P
P Load Q Load Caps Q Load Caps P Load Q Load Caps P Load Q Load Caps P Load Q Load Caps
Load
(MW) (MVAr) (MVAr) (MVAr) (MVAr) (MW) (MVAr) (MVAr) (MW) (MVAr) (MVAr) (MW) (MVAr) (MVAr)
(MW)
MAZOON AREA
Adam 2X125MVA 52.5 17.3 48 55.1 18.1 48 57.9 19.0 48 60.8 20.0 48 62.6 20.6 48
Ayjah 72.7 23.9 20 74.9 24.6 20 89.3 29.4 20 91.6 30.1 20 94.0 30.9 20
Bahla 74.9 24.6 - 78.6 25.8 - 82.5 27.1 - 86.7 28.5 - 90.1 29.6 -
TX-1 & TX-2 56.2 18.5 40 59.0 19.4 40 62.0 20.4 40 65.1 21.4 40 67.0 22.0 40
Barka Main
Tx-3 28.6 9.4 - 12.4 4.1 - 0.0 0.0 - 0.0 0.0 - 0.0 0.0 -
Bedyah 49.8 16.4 40 51.8 17.0 40 53.9 17.7 40 56.0 18.4 40 58.3 19.1 40
Birkat Al Mouz 50.8 16.7 40 53.8 17.7 40 57.1 18.8 40 60.5 19.9 40 64.1 21.1 40
Blue City 124.3 40.8 48 128.0 42.1 48 140.8 46.3 48 144.8 47.6 48 148.9 48.9 48
Hay Asim 53.2 17.5 40 66.6 21.9 40 83.2 27.4 40 84.9 27.9 40 86.7 28.5 40
Ibra 79.9 26.3 40 83.0 27.3 40 86.2 28.3 40 89.5 29.4 40 92.1 30.3 40
Izki 2X125MVA 81.2 26.7 40 87.5 28.7 40 90.0 29.6 40 91.7 30.1 40 93.5 30.7 40
JBB Ali TX-1 & TX-2 120.0 39.4 48 146.8 48.3 48 151.8 49.9 48 157.0 51.6 48 82.4 27.1 48
JBB Hassan 73.2 24.1 40 83.1 27.3 40 86.2 28.3 40 89.4 29.4 40 92.7 30.5 40
Jebreen 64.0 21.0 40 66.5 21.9 40 69.2 22.7 40 71.9 23.6 40 74.1 24.4 40
TX-1 & TX-2 111.1 36.5 40 85.5 28.1 40 88.9 29.2 40 92.5 30.4 40 95.3 31.3 40
Khadhra
TX-3 & TX-4 34.3 11.3 40 65.7 21.6 40 68.3 22.5 40 71.1 23.4 40 73.2 24.1 40
TX-1 & TX-2 111.7 36.7 40 92.2 30.3 40 100.9 33.2 40 103.8 34.1 40 106.7 35.1 40
Madinat Barka
TX-3 & TX-4 25.0 8.2 40 50.0 16.4 40 52.0 17.1 40 54.1 17.8 40 55.7 18.3 40
Madinat Nizwa 63.2 20.8 40 65.8 21.6 40 68.4 22.5 40 71.1 23.4 40 73.3 24.1 40
MIS 45.3 14.9 - 47.2 15.5 - 48.6 16.0 - 50.0 16.4 - 51.5 16.9 -
Mudhaibi 2X125MVA 47.0 15.5 40 48.9 16.1 40 55.7 18.3 40 57.7 19.0 40 59.3 19.5 40
Page | 130
Five-Year Annual Transmission Capability Statement (2020-2024)
Table B. 1: (Continued) Load and Capacitor Data for Grid Station (2020-2024)
2020 2021 2022 2023 2024
G rid Stations P
P Load Q Load Caps Q Load Caps P Load Q Load Caps P Load Q Load Caps P Load Q Load Caps
Load
(MW) (MVAr) (MVAr) (MVAr) (MVAr) (MW) (MVAr) (MVAr) (MW) (MVAr) (MVAr) (MW) (MVAr) (MVAr)
(MW)
Mudhairib 56.5 18.6 40 64.7 21.3 40 67.1 22.1 40 69.5 22.9 40 71.4 23.5 40
TX-1 & TX-2 104.7 34.4 40 85.9 28.2 40 100.2 32.9 40 103.7 34.1 40 106.5 35.0 40
Muladah
TX-3 & TX-4 22.7 7.5 40 46.6 15.3 40 48.4 15.9 40 50.4 16.6 40 51.9 17.1 40
Nakhal 76.5 25.2 40 85.6 28.1 40 88.0 28.9 40 90.5 29.7 40 93.0 30.6 40
New Izki 20.6 6.8 40 21.4 7.0 40 22.3 7.3 40 23.2 7.6 40 23.9 7.8 40
Nizwa 85.1 28.0 40 96.6 31.8 40 109.3 35.9 40 112.0 36.8 40 114.8 37.7 40
Rustaq 3X125MVA 159.4 52.4 40 116.8 38.4 40 121.5 39.9 40 126.3 41.5 40 130.1 42.8 40
Samad 25.0 8.2 40 25.8 8.5 40 26.5 8.7 40 27.3 9.0 40 28.1 9.2 40
Sinaw 35.0 11.5 40 36.8 12.1 40 38.2 12.6 40 39.7 13.1 40 40.9 13.5 40
2X63MVA 52.4 17.2 40 54.0 17.7 40 55.1 18.1 40 56.2 18.5 40 57.3 18.8 40
Sumail
2X125MVA 108.9 35.8 40 59.6 19.6 40 62.0 20.4 40 63.9 21.0 40 65.8 21.6 40
Sumail Industrial Area - - - 53.6 17.6 40 55.2 18.1 40 56.9 18.7 40 58.6 19.3 40
Sur TX-1 & TX-2 94.0 30.9 48 96.8 31.8 48 99.6 32.7 48 102.4 33.7 48 105.4 34.6 48
Suwaiq 61.2 20.1 40 67.9 22.3 40 77.6 25.5 40 80.3 26.4 40 82.4 27.1 40
Wadi Bani Auwf 0.0 0.0 - 49.0 16.1 40 51.0 16.7 40 53.0 17.4 40 54.6 17.9 40
Total Mazoon 33kV Load 2321.0 762.9 1252 2463.5 809.7 1332 2614.8 859.4 1332 2705.4 889.2 1332 2786.0 915.7 1372
Total Mazoon 2321.0 762.9 1252 2463.5 809.7 1332 2614.8 859.4 1332 2705.4 889.2 1332 2786.0 915.7 1372
Page | 131
Five-Year Annual Transmission Capability Statement (2020-2024)
Table B. 1: (Continued) Load and Capacitor Data for Grid Station (2020-2024)
2020 2021 2022 2023 2024
G rid Stations P
P Load Q Load Caps Q Load Caps P Load Q Load Caps P Load Q Load Caps P Load Q Load Caps
Load
(MW) (MVAr) (MVAr) (MVAr) (MVAr) (MW) (MVAr) (MVAr) (MW) (MVAr) (MVAr) (MW) (MVAr) (MVAr)
(MW)
MAJAN AREA
Al Hayl 40.5 13.3 10 7.6 2.5 10 7.7 2.5 10 7.8 2.6 10 8.0 2.6 10
Bureimi 48.4 15.9 40 51.3 16.8 40 53.3 17.5 40 55.5 18.2 40 56.9 18.7 40
TX-1 & TX-2 40.2 13.2 40 41.0 13.5 40 42.0 13.8 40 43.1 14.2 40 44.6 14.7 40
Buriami Industrial
TX-3 & TX-4 50.4 16.6 - 59.6 19.6 40 61.2 20.1 40 62.9 20.7 40 66.4 21.8 40
Dank 38.1 12.5 10 42.6 14.0 10 47.7 15.7 10 51.3 16.9 10 52.2 17.1 10
Dil Abdusalam 73.3 24.1 40 78.3 25.7 40 80.6 26.5 40 82.3 27.1 40 87.2 28.7 40
Dreez 79.3 26.1 40 81.5 26.8 40 83.7 27.5 40 88.2 29.0 40 90.7 29.8 40
2X63MVA 38.9 12.8 10 40.1 13.2 10 41.3 13.6 10 40.6 13.3 10 41.9 13.8 10
Ibri
2X125MVA 78.2 25.7 40 80.2 26.4 40 82.2 27.0 40 84.3 27.7 40 86.8 28.5 40
Khaborah 88.0 28.9 40 91.2 30.0 40 95.4 31.4 40 99.7 32.8 40 104.3 34.3 40
TX-1 & TX-2 56.1 18.5 40 59.8 19.6 40 56.7 18.7 40 59.9 19.7 40 63.0 20.7 40
Liwa
TX-3 & TX-4 67.2 22.1 40 73.0 24.0 40 76.4 25.1 40 79.8 26.2 40 82.1 27.0 40
Madinat Shinas 64.5 21.2 40 73.7 24.2 40 78.9 25.9 40 82.9 27.3 40 86.6 28.5 40
Mahadah 24.1 7.9 10 17.2 5.7 10 17.4 5.7 10 17.8 5.9 10 18.0 5.9 10
Saham 86.2 28.3 40 87.4 28.7 40 90.0 29.6 40 90.2 29.6 40 95.1 31.3 40
Shinas TX-1 & TX-2 64.8 21.3 40 67.3 22.1 40 79.6 26.2 40 84.3 27.7 40 91.7 30.1 40
SIA 76.8 25.2 - 84.4 27.8 - 84.9 27.9 - 85.4 28.1 - 86.1 28.3 -
TX-1 & TX-2 55.7 18.3 40 58.6 19.3 40 68.2 22.4 40 90.0 29.6 40 94.4 31.0 40
Sohar
TX-3 & TX-4 108.7 35.7 40 112.9 37.1 40 112.8 37.1 40 97.5 32.1 40 100.7 33.1 40
TX-1 & TX-2 36.6 12.0 40 41.0 13.5 40 44.9 14.7 40 41.2 13.5 40 42.2 13.9 40
Sohar Free Zone
TX-3 & TX-4 49.1 16.1 - 50.4 16.6 40 51.4 16.9 40 52.6 17.3 40 54.3 17.8 40
Page | 132
Five-Year Annual Transmission Capability Statement (2020-2024)
Table B. 1: (Continued) Load and Capacitor Data for Grid Station (2020-2024)
2020 2021 2022 2023 2024
G rid Stations P
P Load Q Load Caps Q Load Caps P Load Q Load Caps P Load Q Load Caps P Load Q Load Caps
Load
(MW) (MVAr) (MVAr) (MVAr) (MVAr) (MW) (MVAr) (MVAr) (MW) (MVAr) (MVAr) (MW) (MVAr) (MVAr)
(MW)
TX-1 & TX-2 52.2 17.2 40 53.8 17.7 40 55.5 18.2 40 58.2 19.1 40 60.0 19.7 40
Uwaynat
TX-3 & TX-4 60.8 20.0 40 62.9 20.7 40 64.7 21.3 40 68.7 22.6 40 71.1 23.4 40
Wadi Sa'a 14.1 4.6 - 16.5 5.4 - 18.1 6.0 - 20.4 6.7 - 22.6 7.4 -
Yanqul 0.0 0.0 - 33.5 11.0 40 34.4 11.3 40.0 35.4 11.6 40.0 36.7 12.1 40
Total Majan 33kV Load 1392.1 457.6 680 1465.7 481.7 800 1529.0 502.6 800 1580.0 519.3 800 1643.9 540.3 800
Aromatics connected to 132kV (SIA) 0.0 0.0 - 0.0 0.0 - 0.0 0.0 - 0.0 0.0 - 0.0 0.0 -
Sohar Refinery 0.0 0.0 - 0.0 0.0 - 0.0 0.0 - 0.0 0.0 - 0.0 0.0 -
Jindal Shadeed connected to 220 (SIA) 60.0 19.7 - 60.0 19.7 - 100.0 32.9 - 100.0 32.9 - 100.0 32.9 -
VALE connected to 132kV (SIA) 85.0 27.9 - 85.0 27.9 - 85.0 27.9 - 85.0 27.9 - 85.0 27.9 -
OMP ET Connected ti SIA 132kV 0.0 0.0 - 4.0 1.3 - 4.0 1.3 - 4.0 1.3 - 4.0 1.3 -
Orpic (Liwa P lastic) 220kV SP S-2 25.0 8.2 - 25.0 8.2 - 25.0 8.2 - 25.0 8.2 - 25.0 8.2 -
Sohar Aluminum 0.0 0.0 - 0.0 0.0 - 0.0 0.0 - 0.0 0.0 - 0.0 0.0 -
Al Tamam INDSIL 8.0 2.6 - 8.0 2.6 - 8.0 2.6 - 8.0 2.6 - 8.0 2.6 -
Total Majan 1589.3 522.4 680.0 1666.9 547.9 800.0 1770.2 581.8 800.0 1821.2 598.6 800.0 1885.1 619.6 800.0
Page | 133
Five-Year Annual Transmission Capability Statement (2020-2024)
Table B. 1: (Continued) Load and Capacitor Data for Grid Station (2020-2024)
2020 2021 2022 2023 2024
G rid Stations P
P Load Q Load Caps Q Load Caps P Load Q Load Caps P Load Q Load Caps P Load Q Load Caps
Load
(MW) (MVAr) (MVAr) (MVAr) (MVAr) (MW) (MVAr) (MVAr) (MW) (MVAr) (MVAr) (MW) (MVAr) (MVAr)
(MW)
DPC AREA
Al Qarm 34.4 11.3 - 33.2 10.9 - 36.0 11.8 - 27.7 9.1 - 28.5 9.4 -
Ashoor 68.7 22.6 - 55.8 18.3 - 56.7 18.7 - 56.7 18.6 - 57.7 19.0 -
Ittin 78.4 25.8 40 71.8 23.6 40 74.8 24.6 40 83.5 27.5 40 87.1 28.6 40
Mirbat 0.0 0.0 40 20.9 6.9 40 24.9 8.2 40 26.9 8.8 40 29.1 9.5 40
NP S 39.7 13.0 - 38.8 12.8 - 41.9 13.8 - 43.1 14.2 - 44.7 14.7 -
TX-1 & TX-2 65.0 21.4 40 80.6 26.5 40 88.5 29.1 40 101.9 33.5 40 105.5 34.7 40
S'aadah
TX-3 & TX-4 44.3 14.6 40 66.5 21.8 40 87.2 28.7 40 102.3 33.6 40 105.9 34.8 40
Raysut 101.7 33.4 40 111.5 36.7 40 109.0 35.8 40 108.3 35.6 40 108.5 35.7 40
Salalah-IP P 39.7 13.1 40 69.0 22.7 40 101.1 33.2 40 107.5 35.3 40 112.0 36.8 40
Shaha'aon 95.3 31.3 40 99.4 32.7 40 98.3 32.3 40 81.9 26.9 40 85.0 27.9 40
Total Dhof ar 33kV Load 591.2 194.3 286.0 676.3 222.3 286.0 751.1 246.9 286.0 773.4 254.2 286.0 798.5 262.5 286.0
Salalah Airport 7.0 2.3 - 8.0 2.6 - 8.0 2.6 - 8.0 2.6 - 8.0 2.6 -
Salalah Methanol Company 0.0 0.0 - 35.0 11.5 - 35.0 11.5 - 35.0 11.5 - 35.0 11.5 -
Total DPC 598.2 196.6 286.0 719.3 236.4 286.0 794.1 261.0 286.0 816.4 268.3 286.0 841.5 276.6 286.0
Page | 134
Five-Year Annual Transmission Capability Statement (2020-2024)
Table B. 1: (Continued) Load and Capacitor Data for Grid Station (2020-2024)
2020 2021 2022 2023 2024
G rid Stations P
P Load Q Load Caps Q Load Caps P Load Q Load Caps P Load Q Load Caps P Load Q Load Caps
Load
(MW) (MVAr) (MVAr) (MVAr) (MVAr) (MW) (MVAr) (MVAr) (MW) (MVAr) (MVAr) (MW) (MVAr) (MVAr)
(MW)
RAEC AREA
TX-1 & TX-2 0.0 0.0 - 0.0 0.0 - 0.0 0.0 - 60.8 20.0 40 61.8 20.3 40
Duqm
TX-3 & TX-4 0.0 0.0 - 0.0 0.0 - 0.0 0.0 - 53.4 17.5 40 54.3 17.9 40
Mahout 0.0 0.0 - 0.0 0.0 - 0.0 0.0 - 23.9 7.8 40 24.9 8.2 40
Saih Al Khairat 0.0 0.0 - 0.0 0.0 - 0.0 0.0 - 44.2 14.5 40 45.8 15.1 40
Total RAEC 33kV Load 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 182.2 59.9 160.0 186.8 61.4 160.0
Page | 135
Five-Year Annual Transmission Capability Statement (2020-2024)
MIS
Sur P S Jahloot 400 2 Quad YEW 119.6 0.0211 0.2578 5.18 1774 − − − − − −
Ibri IP P New Izki 400 2 Quad YEW 264.4 0.0210914 0.2577821 5.18 1774 − − − − − −
Sohar IP P -3 Sohar Free Zone 400 2 − − − − − − 2500mm2 XLP E cable 10.2 0.01074 0.321 91.10619 2273
Sohar Free Zone
2500mm2 XLP E cable 3.524 0.01074 0.321 91.10619 2273
Sohar IP P -3 (P ortion 1) 400 2 Quad YEW 5.5 0.0210914 0.2577821 5.184822 1774
Sohar Free Zone
2500mm2 XLP E cable 0.9 0.01074 0.321 91.10619 2273
(P ortion 2)
Sohar Free Zone SIS 400 2 Quad YEW 33.3 0.0210914 0.2577821 5.18 1774 − − − − − −
Sur P S Qabel 400 2 Quad YEW 116.5 0.0210914 0.2577821 5.184822 1774 − − − − − −
Qabel New Izki 400 2 Quad YEW 106.2 0.0210914 0.2577821 5.184822 1774 − − − − − −
Sohar IP P -2 Sohar Free Zone 220 2 ARCURIA x 2 6.0 0.0258 0.321 3.82 673 2500mm2 XLP E cable 3.5 0.01074 0.321 91.11 625
Sohar Free Zone SIS 220 2 ARCURIA x 2 33.9 0.0258 0.321 3.82 673 2500mm2 XLP E cable 0.5 0.01074 0.321 91.11 625
SIA Sohar-1 P S 220 3 − − − − − − 2500mm2 XLP E cable 3.7 0.01074 0.321 91.11 625
Mahadha Al Oha (UAE) 220 2 ARCURIA x 2 51.4 0.0258 0.321 3.82 673 − − − − − −
Barka P ower station Filaj 220 2 ARCURIA x 2 10.0 0.0258 0.321 3.82 673 − − − − − −
Barka P ower station Filaj 220 2 ARCURIA x 2 9.2 0.0258 0.321 3.82 673 2500mm2 XLP E cable 0.8 0.01074 0.321 91.11 625
Filaj Mobella 220 2 ARCURIA x 2 9.8 0.0258 0.321 3.82 673 − − − − − −
Mobella Airport Heights 220 2 ARCURIA x 2 25.3 0.0258 0.321 3.82 673 − − − − − −
Airport Heights Misfah 220 2 ARCURIA x 2 15.5 0.0258 0.321 3.82 673 − − − − − −
Misfah MSQ 220 2 ARCURIA x 2 26.1 0.0258 0.321 3.82 673 − − − − − −
Misfah Jahloot 220 2 ARCURIA x 2 76.0 0.0258 0.321 3.82 673 − − − − − −
MIS SIS 220 2 ARCURIA x 2 107.2 0.0258 0.321 3.82 673 − − − − − −
SP S SIS 220 2 ARCURIA x 2 37.4 0.0258 0.321 3.82 673 2500mm2 XLP E cable 2.9 0.01074 0.312 91.11 625
Mahadha SIS 220 2 ARCURIA x 2 66.5 0.0258 0.321 3.82 673 − − − − − −
Blue City MIS 220 2 ARCURIA x 2 45.6 0.0258 0.321 3.82 673 2500mm2 XLP E cable 5.8 0.01074 0.321 91.11 475
Filaj Blue City 220 2 ARCURIA x 2 33.2 0.0258 0.321 3.82 673 2500mm2 XLP E cable 5.8 0.01074 0.312 91.11 475
Ibri Ibri IP P 220 2 ARCURIA x 2 32.1 0.0258 0.321 3.82 673 − − − − − −
Ibri IP P Mahadha 220 2 ARCURIA x 2 123.2 0.0258 0.321 3.82 673 − − − − − −
Page | 136
Five-Year Annual Transmission Capability Statement (2020-2024)
MIS
Barka IP P -3 Misfah 220 2 ARCURIA x 2 54.9 0.0258 0.321 3.82 673 2500mm2 XLP E cable 10.5 0.01074 0.321 91.11 625
Sur JBB Hassan 132 2 YEW x 2 60.9 0.04283 0.2821 3.98 293 − − − − − −
Barka Main Filaj 132 2 YEW x 2 6.2 0.04283 0.2821 3.98 293 − − − − − −
Mudhaibi Sinaw 132 2 YEW x 2 29.4 0.04283 0.2821 3.98 293 − − − − − −
Sinaw New Izki 132 2 YEW x 2 51.1 0.04283 0.2821 3.98 293 2500mm2 XLP E cable 0.62 0.01074 0.321 91.11 625
Manah Nizwa 132 2 YEW x 2 20.0 0.04283 0.2821 3.98 183 − − − − − −
Mawalleh Rusail Industrial 132 2 − − − − − − 2500mm2 XLP E cable 6.2 0.04282 0.08361 122.522 375
Mobella Barka Main 132 2 YEW x 2 11.5 0.04283 0.2821 3.98 293 − − − − − −
MSQ Wadi Adai 132 2 YEW x 2 8.4 0.04283 0.2821 3.98 293 − − − − − −
Mudhaibi Mudhairib 132 2 YEW x 2 60.0 0.04283 0.2821 3.98 293 − − − − − −
Muladah MIS 132 2 YEW x 2 11.5 0.04283 0.2821 3.98 293 − − − − − −
Nizwa Nahda (P DO) 132 1 ELM x1 67.4 0.1944 0.4207 2.71 89 − − − − − −
Nizwa Bahla 132 2 YEW x1 31.9 0.0857 0.3948 2.85 146 − − − − − −
Rusail Mobella 132 2 YEW x 2 13.1 0.04283 0.2821 3.98 293 − − − − − −
Rusail Sumail 132 2 YEW x 2 34.6 0.04283 0.2821 3.98 293 − − − − − −
Rustaq Muladah 132 2 YEW x 2 29.4 0.04283 0.2821 3.98 293 − − − − − −
Page | 137
Five-Year Annual Transmission Capability Statement (2020-2024)
MIS
Sohar Wadi Jizzi 132 2 YEW x 2 28.3 0.04283 0.2821 3.98 293 − − − − − −
Wadi Adai Al Falaj 132 2 YEW x 2 2.7 0.04283 0.2821 3.98 293 − − − − − −
Wadi Jizzi Mahadha 132 2 ELM x 2 36.2 0.0972 0.3168 3.8 179 − − − − − −
New Ghubrah Bousher 132 3 − − − − − − 2500mm2 XLP E cable 2 0.04 0.08 122.52 375
Bousher MSQ 132 1 YEW x 2 2.1 0.04283 0.2821 3.98 293 2500mm2 XLP E cable 2.7 0.04 0.08 122.52 375
New Ghubrah MSQ 132 3 YEW x 2 2.1 0.04283 0.2821 3.98 293 2500mm2 XLP E cable 4.3 0.04 0.08 122.52 375
Airport Heights Mawalleh North 132 2 − − − − − − 2500mm2 XLP E cable 8.6 0.04 0.08 122.52 375
Shinas Madinat Shinas 132 2 YEW x 2 24.1 0.04283 0.2821 3.98 293 − − − − − −
Mahadha Wadi Sa'a 132 2 YEW x 2 31.5 0.04283 0.2821 3.98 293 − − − − − −
Wadi Sa'a Dank 132 2 225 AAAC 58.4 0.04283 0.2821 3.98 89 − − − − − −
Misfah Wadi Adai 132 2 YEW x 2 34.0 0.04283 0.2821 3.98 293 − − − − − −
Page | 138
Five-Year Annual Transmission Capability Statement (2020-2024)
Conductor
From To Voltage No. Length R X B Rating Conductor Length Rating
Type R[Ω/km] X[Ω/km] B [MS/km]
Substation Substation (kV) Circuits (Km) [Ω/km] [Ω/km] [MS/km] (MVA) Type (Cable) (Km) (MVA)
(OHL)
MIS
Jahloot Quriyat 132 2 YEW x 2 48.7 0.04283 0.2821 3.98 293 − − − − − −
Nizwa Madinata Nizwa 132 2 YEW x2 12.4 0.04283 0.2821 3.98 293 − − − − − −
Wadi Kabir Al Hamriyah 132 2 YEW x1 1.9 0.0857 0.3948 2.85 146 1200mm2 1C CU XLP E cable 1.15 0.03 0.12 64.70 171
Al Hamriyah Muttrah 132 2 YEW x 2 2.7 0.04283 0.2821 3.98 293 2500mm2 XLP E cable 3.2 0.04 0.08 122.52 300
Filaj Madinata Barka 132 2 YEW x2 11.5 0.04283 0.2821 3.98 293 − − − − − −
Madinata Barka Muladah 132 2 YEW x2 34.9 0.04283 0.2821 3.98 293 − − − − − −
Dank Al Hayl 132 2 YEW x 2 52.4 0.04283 0.2821 3.98 293 − − − − − −
Airport Heights Mawalleh South 132 2 − − − − − − 2500mm2 XLP E cable 9.1 0.04 0.08 122.52 375
Airport Heights Ghala 132 2 − − − − − − 2500mm2 XLP E cable 3.7 0.04 0.08 122.52 375
MIS Suwaiq 132 2 YEW x 2 7.0 0.04283 0.2821 3.98 293 − − − − − −
Suwaiq Al Khadhra 132 2 YEW x 2 18.8 0.04283 0.2821 3.98 293 − − − − − −
Al Khadhra Khaborah 132 2 YEW x 2 27.9 0.04283 0.2821 3.98 293 − − − − − −
Mahadha Bureimi Industrial 132 2 YEW x2 32.8 0.04283 0.2821 3.98 293 − − − − − −
Bureimi Industrial Bureimi 132 2 YEW x2 0.3 0.04283 0.2821 3.98 293 2500mm2 XLP E cable 5.6 0.04 0.08 122.52 375
Mawalleh South-B Seeb Main 132 2 − − − − − − 2500mm2 XLP E cable 7.8 0.04 0.08 122.52 375
Mobella A'salam 132 2 − − − − − − 2500mm2 XLP E cable 8.6 0.04 0.08 122.52 375
Ibri Dreez 132 2 YEW x 2 28.1 0.04283 0.2821 3.98 293 − − − − − −
Sohar Free Zone Liwa 132 2 YEW x 2 2.3 0.04283 0.2821 3.98 293 − − − − − −
Wadi Jizzi Sohar Free Zone 132 2 YEW x 2 27.2 0.04283 0.2821 3.98 293 − − − − − −
Page | 139
Five-Year Annual Transmission Capability Statement (2020-2024)
MIS
Muttrah Al Falaj 132 1 − − − − − − 2500mm2 XLP E cable 3 0.04282 0.08361 122.522 300
Muttrah Wadi Kabair 132 1 YEW x2 1.3 0.04283 0.2821 3.98 293 2500mm2 XLP E cable 2 0.04282 0.08361 122.522 375
Quriyat Daghmar 132 2 YEW x 2 3.7 0.04283 0.2821 3.98 293 − − − − − −
Nizwa Jebreen 132 2 YEW x 2 24.4 0.04283 0.2821 3.98 293 − − − − − −
Jebreen Ibri 132 2 YEW x 2 99.4 0.04283 0.2821 3.98 293 − − − − − −
Mudhairib Bedyah 132 2 YEW x 2 14.7 0.04283 0.2821 3.98 293 − − − − − −
Bedyah Al Kamil 132 2 YEW x 2 36.5 0.04283 0.2821 3.98 293 − − − − − −
Mudhaibi Samad 132 2 YEW x 2 36.4 0.04283 0.2821 3.98 293 − − − − − −
Ghala Ghala Heights 132 2 − − − − − − 2500mm2 XLP E cable 7 0.04 0.08 122.52 375
Ghala Heights Bousher 132 2 − − − − − − 2500mm2 XLP E cable 7 0.04 0.08 122.52 375
Nizwa Birkat Al Mouz 132 2 YEW x 2 15.6 0.04283 0.2821 3.98 293 − − − − − −
Birkat Al Mouz Izki 132 2 YEW x 2 16.7 0.04283 0.2821 3.98 293 − − − − − −
Mudhairib Qabel 132 2 YEW x 2 6.0 0.04283 0.2821 3.98 293 − − − − − −
Qabel Ibra 132 2 YEW x 2 22.0 0.04283 0.2821 3.98 293 − − − − − −
Mawalleh Rusail Industrial 132 2 240 ZTACIR 9.0 0.0261 0.075 0.0153 250 2500mm2 XLP E cable 6 0.04 0.08 122.52 375
Sohar Free Zone Shinas 132 2 Quad YEW 30.0 0.0210914 0.2577821 5.184822 585 − − − − − −
Rusail Sumail Industrial Area 132 2 YEW x 2 40.2 0.04283 0.2821 3.98 293 2500mm2 XLP E cable 1.6 0.04282 0.08361 122.522 375
Sumail Industrial
Sumail 132 2 YEW x 2 22.6 0.04283 0.2821 3.98 293 2500mm2 XLP E cable 1.6 0.04282 0.08361 122.522 375
Area
Dhof ar System
Thumrait Ittin 132 2 ELM x 2 61.2 0.0900 0.3000 3.00 183 − − − − − −
Ittin Al Qurum 132 2 YEW x 2 22.7 0.0388 0.289 1.43 359 − − − − − −
Ittin SFZ 132 2 YEW x 2 25.4 0.0388 0.289 1.429 359 − − − − − −
SFZ Shaha'aon 132 2 YEW x 2 18.8 0.0388 0.289 1.429 359 − − − − − −
Ashoor Al Qurum 132 2 YEW x 2 23.3 0.0388 0.289 1.429 359 2500mm2 XLP E cable 2.52 0.01075 0.141 91.1 279
SFZ NP S 132 2 YEW x 2 0.7 0.0388 0.289 1.43 359 2500mm2 XLP E cable 0.1 0.01075 0.141 91.1 279
Shaha'aon A'saada 132 2 YEW x 2 15.0 0.0388 0.289 1.429 330 2500mm2 XLP E cable 6.5 0.01075 0.141 91.1 300
A'saada Ashoor (P ortion-1) 132 2 YEW x 2 8.5 0.0388 0.289 1.429 330 2500mm2 XLP E cable 1.2 0.01075 0.141 91.10 279
A'saada Ashoor (P ortion-2) 132 2 YEW x 2 33.3 0.0388 0.289 1.429 330 2500mm2 XLP E cable 6.5 0.01075 0.141 91.10 300
Thumrait Wind Farm (P ortion-1) 132 1 ELM x 2 65.5 0.09 0.3 3.00 183 − − − − − −
Thumrait Wind Farm (P ortion-2) 132 1 YEW x 2 11.0 0.09 0.3 3.00 359 − − − − − −
Wind Farm
Harweel 132 1 ELM x 2 19.0 0.09 0.3 3.00 183 − − − − − −
(P ortion-1)
Wind Farm
Harweel 132 1 YEW x 2 11.0 0.09 0.3 3.00 359 − − − − − −
(P ortion-2)
Page | 140
Five-Year Annual Transmission Capability Statement (2020-2024)
Mawalleh Rusail Industrial 132 2 240 ZTACIR 8.0 0.0261 0.075 0.0153 250 2500mm2 XLP E cable 6 0.04 0.08 122.52 375
2021 Additions
MIS
New Izki Misfah 400 2 Quad YEW 100.0 0.0211 0.2578 5.18 1775 − − − − − −
Ibri IP P Ibri Solar IP P 220 2 ARCURIA x 2 3.0 0.0258 0.321 3.82 673 − − − − − −
Nakhal Wadi Bani Awf 132 2 YEW x 2 52.3 0.04283 0.2821 3.98 293 − − − − − −
Wadi Bani Awf Rustaq 132 2 YEW x 2 34.1 0.04283 0.2821 3.98 293 − − − − − −
Mawalleh Khoudh 132 2 240 ZTACIR 1.3 0.0261 0.075 0.0153 250 2500mm2 XLP E cable 0.7 0.04 0.08 122.52 375
Khoudh Rusail Industrial 132 2 240 ZTACIR 6.0 0.0261 0.075 0.0153 250 − − − − − −
Dhof ar System
Page | 141
Five-Year Annual Transmission Capability Statement (2020-2024)
2022 Deletions
Conductor
From To Voltage No. Length Rating Conductor Length Rating
Type R[Ω/km] X[Ω/km] B [MS/km] R[Ω/km] X[Ω/km] B [MS/km]
Substation Substation (kV) Circuits (Km) (MVA) Type (Cable) (Km) (MVA)
(OHL)
Ibri IP P New Izki 400 2 Quad YEW 264.4 0.0210914 0.2577821 5.18 1774 − − − − − −
Mobella Barka Main 132 2 YEW x 2 11.5 0.04283 0.2821 3.98 293 − − − − − −
2022 Additions
Conductor
From To Voltage No. Length Rating Conductor Length Rating
Type R[Ω/km] X[Ω/km] B [MS/km] R[Ω/km] X[Ω/km] B [MS/km]
Substation Substation (kV) Circuits (Km) (MVA) Type (Cable) (Km) (MVA)
(OHL)
New Izki Manah Solar IP P 400 2 Quad YEW 25.0 0.0210914 0.2577821 5.18 1774 − − − − − −
Manah Solar IP P Ibri IP P 400 2 Quad YEW 245.0 0.0210914 0.2577821 5.18 1774 − − − − − −
Mobella Mobella Industrial 132 2 YEW x 2 2.8 0.04283 0.2821 3.98 293 − − − − − −
Mobella Industrial Barka Main 132 2 YEW x 2 10.2 0.04283 0.2821 3.98 293 − − − − − −
Page | 142
Five-Year Annual Transmission Capability Statement (2020-2024)
2023 Deletions
Manah Solar
Ibri IP P 400 2 Quad YEW 245.0 0.0210914 0.2577821 5.18 1774 − − − − − −
IP P
Rusail
Rusail 132 4 − − − − − − 2500mm2 XLP E cable 0.192 0.04 0.08 122.52 375
Industrial
Sumail
Rusail 132 2 YEW x 2 40.6 0.04283 0.2821 3.98 293 2500mm2 XLP E cable 1.6 0.04 0.08 122.52 375
Industrial Area
2023 Additions
MIS
Mahout Duqm 400 2 Quad YEW 152.0 0.0210914 0.2577821 5.184822 1774 − − − − − −
Duqm Suwaihat 400 2 Quad YEW 187.0 0.0210914 0.2577821 5.184822 1774 − − − − − −
Manah Solar IP P Nahadah 400 2 Quad YEW 80.5 0.0210914 0.2577821 5.18 1774 − − − − − −
Nahadah Ibri IP P 400 2 Quad YEW 166.5 0.0210914 0.2577821 5.18 1774 − − − − − −
Al Jefnen Misfah 400 2 Quad YEW 8.3 0.0210914 0.2577821 5.184822 1774 − − − − − −
Airport Heights Ghala 132 1 − − − − − − 2500mm2 XLP E cable 3.8 0.04 0.08 122.52 375
Rusail
Al Jefnen 132 4 − − − − − − 2500mm2 XLP E cable 6.4 0.04 0.08 122.52 375
Industrial
Sumail
Al Jefnen 132 2 YEW x 2 36.4 0.04283 0.2821 3.98 293 2500mm2 XLP E cable 1.6 0.04 0.08 122.52 375
Industrial
Dhof ar System
Saih Al
Thumrait 132 2 YEW x 2 88.0 0.04283 0.2821 3.98 293 − − − − − −
Khairat
Page | 143
Five-Year Annual Transmission Capability Statement (2020-2024)
2024 Additions
Rustaq Ibri IP P 400 2 Quad YEW 159.8 0.0210914 0.2577821 5.184822 1774 − − − − − −
Rustaq Al Jefnen 400 2 Quad YEW 85.2 0.0210914 0.2577821 5.184822 1774 − − − − − −
New Izki Nizwa 220 2 ARCURIA x 2 53.9 0.0258 0.321 3.82 673 2500mm2 XLP E cable 4.7 0.01074 0.321 91.11 625
Mahadha Bureimi 132 2 YEW x 2 32.9 0.04283 0.2821 3.98 293 2500mm2 XLP E cable 5.5 0.04282 0.08361 122.522 375
WTE IP P Madinat Barka 132 2 YEW x2 3.6 0.04283 0.2821 3.98 293 − − − − − −
Al Jawabi JBB Ali Wind 132 2 YEW x 2 9 0.04283 0.2821 3.98 293 − − − − − −
Duqm Duqm Wind 132 2 YEW x 2 49.7 0.04283 0.2821 3.98 293 − − − − − −
Page | 144
Five-Year Annual Transmission Capability Statement (2020-2024)
MIS
1 500 400/220 YNa0d1 HV 1.25 11 21 1 12.50 -12.50 21.59
Ibri IP P
2 500 400/220 YNa0d1 HV 1.25 11 21 1 12.50 -12.50 21.58
3 500 400/220 YNa0d1 HV 1.25 11 21 1 12.50 -12.50 21.47
1 500 400/220 YNa0d1 HV 1.25 11 21 1 12.50 -12.50 22.35
Page | 145
Five-Year Annual Transmission Capability Statement (2020-2024)
MIS
Sohar Free Zone 1 500 220/132 YNa0d1 HV 1.10 6 20 1 5.55 -15.54 21.23
Page | 146
Five-Year Annual Transmission Capability Statement (2020-2024)
MIS
Page | 147
Five-Year Annual Transmission Capability Statement (2020-2024)
MIS
1 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.26
Page | 148
Five-Year Annual Transmission Capability Statement (2020-2024)
MIS
Page | 149
Five-Year Annual Transmission Capability Statement (2020-2024)
MIS
1 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.69
Page | 150
Five-Year Annual Transmission Capability Statement (2020-2024)
MIS
Samail Industrial Area 1 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.26
Page | 151
Five-Year Annual Transmission Capability Statement (2020-2024)
MIS
Page | 152
Five-Year Annual Transmission Capability Statement (2020-2024)
MIS
1 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.31
Page | 153
Five-Year Annual Transmission Capability Statement (2020-2024)
Dhof ar System
Wadi Bani Awf 1 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.26
2 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.26
Dhof ar System
Page | 154
Five-Year Annual Transmission Capability Statement (2020-2024)
MIS
Barka Main Third Tx 3 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.6
MIS
1 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.26
Page | 155
Five-Year Annual Transmission Capability Statement (2020-2024)
MIS
Page | 156
Five-Year Annual Transmission Capability Statement (2020-2024)
Table C.2 – Available capacity at Grid Stations for connection of new demand (2020-2024)
Table C.3 – Overhead line and cable circuit loadings at peak demand (2020-2024)
Table C.6 – Estimation of transmission losses and generation margin at peak demand (2020-2024).
C.3 Diagrams of the model for the Load Flow Study Results
The result of peak demand load flow studies for both MIS and Dhofar systems for the years 2020 to 2024 are presented
as Figures C.1 to C.10 respectively.
Page | 157
Five-Year Annual Transmission Capability Statement (2020-2024)
MIS Area
400/220 kV Transformers
2 x 500 500 44.29 43.46 45.95 39.75
New Izki
3 x 500 1000 45.89
Ibri IPP 3 x 500 1000 30.38 26.39 20.04 20.42 15.26
M isfah 3 x 500 1000 0.29 37.41 55.23 46.16 28.89
SIS 3 x 500 1000 46.32 46.67 55.29 59.42 60.20
Sohar Free Zone 3 x 500 1000 39.71 43.12 45.53 51.10 54.73
Jahloot 4 x 500 1500 63.46 51.76 56.48 55.95 53.45
Sur 5 x 750 3000 32.99 33.54 41.22 42.08 43.07
400/132 kV Transformers
Duqm 2 x 500 500 12.44 6.53
Nahadah(PDO) 2 x 500 500 14.95 7.60
Qabel 2 x 500 500 24.62 15.62 41.94 40.36 31.65
Al Jefnen 3 x 500 1000 26.05 50.69
New Rustaq 3 x 500 1000 25.63
Suwaihat 2 x 500 500 13.79 8.01
400/33 kV Transformers
M ahout 2 x 125 125 10.02 10.48
220/132 kV Transformers
M ahadha 2 x 315 315 45.03 48.38 50.19 50.73 52.04
Airport Heights 2 x 500 500 41.38 48.22 61.32
Airport Heights 3 x 500 1000 47.92 42.89
Al Filaj 2 x 500 500 50.93 44.72 47.43 52.62 33.64
Al Hamriyah 2 x 500 500 52.77 52.02 49.17 43.68 43.59
Ibri 2 x 500 500 42.86 43.73 50.93 52.78 46.17
Jahloot 2 x 500 500 46.74 43.90 47.56 43.62 43.35
KIS 2 x 500 500 27.11 25.17 12.88 25.07
M IS 2 x 500 500 44.17 36.89 40.47 55.83 27.87
M SQ 2 x 500 500 45.80 59.24 53.91 42.06 43.36
M isfah 2 x 500 500 37.06 29.49 31.39
M obella 2 x 500 500 42.32 36.51 42.36 46.29 26.00
New Izki 2 x 500 500 42.09 41.83 41.21 35.22 37.12
Nizwa 2 x 500 500 29.55
SIS 2 x 500 500 49.04 42.82 47.09 47.12 48.60
Sohar Free Zone 2 x 500 500 45.40 49.37 51.07 53.53 56.88
Sur 2 x 500 500 25.29 26.11 41.41 42.84 41.80
SIA 3 x 500 1000 11.21 11.69 11.92 11.99 12.20
Page | 158
Five-Year Annual Transmission Capability Statement (2020-2024)
MIS Area
132/33 kV Transformers
Tx (1&2) 2 x 125 125 53.81 52.20 36.07 39.32 41.58
A'salam
Tx (3&4) 2 x 125 125 20.43 38.14 41.55 46.16 40.87
Adam 2 x 125 125 23.28 23.55 25.37 26.07 26.63
Page | 159
Five-Year Annual Transmission Capability Statement (2020-2024)
MIS Area
132/33 kV Transformers
Ibra 2 x 125 125 33.98 34.83 36.94 38.33 38.82
63M VA 2 x 63 63 32.45 33.42 34.66 33.70 35.20
Ibri
125M VA 2 x 125 125 32.86 33.68 34.77 35.24 36.32
Izki 2 x 125 125 34.77 37.29 38.85 39.01 39.27
JBB Ali 2 x 125 125 52.61 64.42 71.44 73.94 36.80
JBB Hassan 2 x 125 125 30.99 35.08 37.85 39.08 39.83
Jahloot 2 x 125 125 17.71 18.62 19.49 20.55 21.51
Jebreen 2 x 125 125 27.84 28.45 30.24 30.79 31.33
Khaborah 2 x 125 125 39.53 39.44 40.95 43.47 45.22
Tx (1&2) 2 x 125 125 49.64 37.37 38.72 40.83 41.81
Khadra
Tx (3&4) 2 x 125 125 15.41 28.61 29.63 31.89 31.96
Tx (1&2) 2 x 125 125 12.53 13.34 14.10 20.91
Khoudh
Tx (3&4) 2 x 125 125 25.26 26.80 28.35 29.07
Tx (1&2) 2 x 125 125 23.69 25.18 23.73 25.18 26.63
Liwa
Tx (3&4) 2 x 125 125 28.15 30.86 32.16 33.37 34.63
M IS 2 x 125 125 19.72 20.34 20.91 22.17 22.21
Tx (1&2) 2 x 125 125 34.64 37.76 39.39 40.01 40.44
M SQ
Tx (3&4) 2 x 125 125 33.35 36.56 38.31 38.97 39.49
M adinat Tx (1&2) 2 x 125 125 48.48 39.29 43.49 46.08 46.91
Barka Tx (3&4) 2 x 125 125 10.74 21.14 22.18 23.71 24.18
M adinat Nizwa 2 x 125 125 27.87 28.40 30.18 30.77 31.02
M adinat Shinas 2 x 125 125 27.15 31.23 33.13 34.62 37.02
M ahadha 2 x 30 30 42.01 30.46 30.74 31.42 31.60
M awalleh North 2 x 125 125 34.42 37.34 44.31 48.01 44.66
M awalleh Tx (1&2) 2 x 125 125 41.21 38.86 41.16 43.09 43.46
South Tx (3&4) 2 x 125 125 47.08 30.00 31.77 33.23 33.75
M isfah 2 x 125 125 28.26 29.73 31.27 32.89 34.34
M obella Tx (1&2) 2 x 125 125 35.56 27.73 29.25
Industrial Tx (3&4) 2 x 125 125 24.47 27.73 38.03
M obella 2 x 125 125 52.70 52.77 29.64 32.30 34.23
M udhaibi 2 x 125 125 19.87 20.82 23.80 24.49 24.93
M udhairib 2 x 125 125 23.84 27.13 28.51 29.47 30.14
Tx (1&2) 2 x 125 125 46.46 37.46 43.95 46.91 46.76
M uladah
Tx (3&4) 2 x 125 125 9.97 20.13 20.94 22.48 22.45
Page | 160
Five-Year Annual Transmission Capability Statement (2020-2024)
MIS Area
132/33 kV Transformers
M uttrah 2 x 125 125 31.09 30.70 30.81 30.82 30.52
Nakhal 2 x 125 125 32.78 36.16 38.09 40.27 40.28
New Ghubrah 2 x 125 125 45.91 46.82 48.65 49.48 50.10
New Izki 2 x 125 125 8.62 8.96 9.37 9.72 10.01
Nizwa 2 x 125 125 37.48 41.74 48.41 48.67 48.56
Quriyat 2 x 125 125 22.40 23.13 23.66 24.57 25.25
Qurum 2 x 125 125 40.91 41.27 42.34 43.16 43.63
Tx (1&2) 2 x 125 125 22.58 24.58 26.46 28.24 29.09
Rusail Industrial
Tx (3&4) 2 x 125 125 37.22 40.33 43.57 46.50 47.75
Rustaq Tx (1,2&3) 3 x 125 250 48.22 34.13 35.62 38.30 37.21
SIA 2 x 125 125 33.14 35.29 36.24 36.54 37.35
Saham 2 x 125 125 37.07 37.79 37.73 38.11 40.44
Samad 2 x 63 63 20.99 21.82 22.49 23.01 23.49
Tx (1&2) 2 x 125 125 55.68 42.88 44.50 47.66 47.55
Seeb M ain
Tx (3&4) 2 x 125 125 35.93 38.40 39.85 41.19 42.54
Shinas 2 x 125 125 27.10 28.39 33.55 35.32 38.90
Sinaw 2 x 125 125 14.74 15.58 16.22 16.70 17.18
Tx (1&2) 2 x 125 125 15.42 17.22 18.78 17.27 17.77
Sohar Free Zone
Tx (3&4) 2 x 125 125 20.52 21.22 21.54 22.12 22.94
Tx (1&2) 2 x 125 125 23.49 25.08 28.75 37.94 40.36
Sohar
Tx (3&4) 2 x 125 125 46.28 49.09 47.19 40.98 43.26
Sumail Industrial 2 x 125 125 0.29 22.70 23.83 24.48 24.65
Page | 161
Five-Year Annual Transmission Capability Statement (2020-2024)
MIS Area
132/33 kV Transformers
Tx (1&2) 2 x 125 125 30.16 29.78 29.89 29.90 29.61
Wadi Kabair
Tx (3&4) 2 x 125 125 25.99 25.67 25.75 25.77 25.52
Wadi Sa'a 2 x 63 63 11.76 13.69 15.11 17.01 18.85
Yanqul 2 x 125 125 14.07 14.50 14.78 15.55
Yitti 2 x 125 125 7.29 7.47 7.57 7.77 7.91
132/11 kV Transformers
Daghmar 3 x 50 100 23.22 23.25 23.08 23.30 23.23
Dhofar Area
132/33 kV Transformers
Ashoor 2 x 125 125 31.40 25.56 25.99 25.92 26.31
2 x 30 30 46.19
Thumrait
2 x 63 63 26.20 29.70 29.44 30.52
Page | 162
Five-Year Annual Transmission Capability Statement (2020-2024)
Table C.2: Available Capacity at Grid Stations (2020-2024) for Connection of New Demand
Available Capacity (MVA)
Total Transformer S ubstation Firm
Location
Capacity (MVA) Capacity (MVA) 2020 2021 2022 2023 2024
MIS Area
400/220 kV Transformers
2 x 500 500 57.12 65.41 40.60 102.51
New Izki
3 x 500 1000 311.66
Ibri IPP 3 x 500 1000 544.32 604.17 699.40 693.64 771.03
M isfah 3 x 500 1000 995.59 438.78 171.85 307.61 566.66
SIS 3 x 500 1000 305.16 300.02 170.80 108.69 97.05
Sohar Free Zone 3 x 500 1000 404.29 353.20 317.05 233.44 179.10
Jahloot 4 x 500 1500 230.78 464.79 370.60 381.06 431.09
Sur 5 x 750 3000 1762.76 1742.26 1454.63 1421.84 1384.69
400/132 kV Transformers
Duqm 2 x 500 500 375.62 434.66
Nahadah(PDO) 2 x 500 500 350.48 424.02
Qabel 2 x 500 500 253.81 343.79 80.60 96.39 183.52
Al Jefnen 3 x 500 1000 609.18 239.60
New Rustaq 3 x 500 1000 615.52
Suwaihat 2 x 500 500 362.10 419.85
400/33 kV Transformers
M ahout 2x125 125 99.95 98.79
220/132 kV Transformers
M ahadha 2 x 315 315 31.34 10.23 -1.13 -4.61 -12.83
Airport Height 2 x 500 500 86.20 17.77 -113.10
Airport Height 3 x 500 1000 281.13 356.58
Al Filaj 2 x 500 500 -9.32 52.78 26.20 -26.16 163.61
Al Hamriyah 2 x 500 500 -27.66 -20.22 8.40 63.23 64.08
Ibri 2 x 500 500 71.42 62.70 -9.30 -27.80 38.25
Jahloot 2 x 500 500 32.62 61.02 24.50 63.83 66.49
KIS 2 x 500 500 228.93 248.30 371.16 249.34
M IS 2 x 500 500 58.26 131.11 95.50 -58.35 221.28
M SQ 2 x 500 500 42.04 -92.44 -39.00 79.40 66.39
M isfah 2 x 500 500 129.50 205.08 186.07
M obella 2 x 500 500 76.80 134.92 77.00 37.14 240.02
New Izki 2 x 500 500 79.10 81.72 87.90 147.80 128.82
Nizwa 2 x 500 500 204.45
SIS 2 x 500 500 9.57 71.84 29.20 28.81 13.97
Sohar Free Zone 2 x 500 500 45.97 6.33 -10.70 -35.28 -68.77
Sur 2 x 500 500 247.06 238.91 86.00 71.63 82.00
SIA 3 x 500 1000 831.80 824.72 821.20 820.19 816.96
Page | 163
Five-Year Annual Transmission Capability Statement (2020-2024)
Table C.2: (continued) Available Capacity at Grid Stations (2020-2024) for Connection of New Demand
Available Capacity (MVA)
Total Transformer S ubstation Firm
Location
Capacity (MVA) Capacity (MVA) 2020 2021 2022 2023 2024
MIS Area
220/33 kV Transformers
Barka-3 PS 2 x 125 125 68.97 55.27 37.15 36.03 33.90
Blue City 2 x 160 160 25.82 24.11 8.16 0.30 -1.97
132/33 kV Transformers
Tx (1&2) 2 x 125 125 -9.54 -5.50 34.85 26.71 21.04
A'salam
Tx (3&4) 2 x 125 125 73.92 29.65 21.18 9.60 22.83
Adam 2 x 125 125 66.81 66.14 61.58 59.81 58.43
Tx (1&2) 2 x 125 125 37.80 32.00 28.95 25.21 18.37
Airport Height
Tx (3&4) 2 x 125 125 90.43 87.06 77.90 75.76 72.01
Al Falaj 2 x 125 125 97.44 95.67 95.58 95.57 95.83
Al Hayl 2 x 40 40 -94.07 14.84 14.68 14.27 13.38
Al Jawabi 2 x 125 125 34.96
Tx (1&2) 2 x 125 125 20.01 19.69 11.03 0.97 8.32
Amerat
Tx (3&4) 2 x 125 125 69.51 56.53 49.50 41.52 16.65
Ayjah 2 x 125 125 48.50 46.07 29.68 28.01 26.46
Bahla 2 x 125 125 41.30 38.96 32.50 29.54 28.46
Tx (1&2) 2 x 125 125 65.76 62.64 37.08 54.64 53.57
Barka M ain
Tx (3) 1 x 125 Nil -30.25 -13.03
Bedyah 2 x 125 125 72.49 70.74 67.23 65.09 63.68
Birkat Al M ouz 2 x 125 125 70.14 67.68 63.10 60.52 57.80
Tx (1&2) 2 x 125 125 41.82 17.10 11.80 7.61 3.78
Bousher
Tx (3&4) 2 x 125 125 -13.85 10.46 4.73 0.17 7.43
Page | 164
Five-Year Annual Transmission Capability Statement (2020-2024)
Table C.2: (continued) Available Capacity at Grid Stations (2020-2024) for Connection of New Demand
Available Capacity (MVA)
Total Transformer S ubstation Firm
Location
Capacity (MVA) Capacity (MVA) 2020 2021 2022 2023 2024
MIS Area
132/33 kV Transformers
63M VA 2 x 63 63 22.11 20.89 19.33 20.53 18.65
Ibri
Tx (1&2) 2 x 125 125 42.85 40.81 38.10 36.89 34.20
Izki 2 x 125 125 38.08 31.77 27.88 27.48 26.82
JBB Ali 2 x 125 125 -6.53 -36.05 -53.60 -59.85 33.00
JBB Hassan 2 x 125 125 47.52 37.30 30.38 27.29 25.43
Jahloot 2 x 125 125 80.72 78.46 76.28 73.62 71.23
Jebreen 2 x 125 125 55.40 53.87 49.40 48.03 46.67
Khaborah 2 x 125 125 26.18 26.40 22.65 16.32 11.94
Tx (1&2) 2 x 125 125 0.91 31.57 28.18 22.92 20.48
Khadra
Tx (3&4) 2 x 125 125 86.48 53.47 50.95 45.26 45.11
Tx (1&2) 2 x 125 125 93.66 91.65 89.74 72.72
Khoudh
Tx (3&4) 2 x 125 125 61.84 58.00 54.12 52.33
Tx (1&2) 2 x 125 125 65.78 62.06 65.68 62.05 58.43
Liwa
Tx (3&4) 2 x 125 125 54.63 47.86 44.60 41.59 38.42
M IS 2 x 125 125 75.69 74.16 72.75 69.58 69.48
Tx (1&2) 2 x 125 125 38.40 30.59 26.55 24.98 23.91
M SQ
Tx (3&4) 2 x 125 125 41.63 33.61 29.25 27.56 26.28
Tx (1&2) 2 x 125 125 3.80 26.78 16.33 9.81 7.73
M adinat Barka
Tx (3&4) 2 x 125 125 98.16 72.16 69.58 65.72 64.56
M adinat Nizwa 2 x 125 125 55.33 53.99 49.55 48.08 47.45
M adinat Shinas 2 x 125 125 57.13 46.93 42.18 38.46 32.44
M ahadha 2 x 30 30 4.80 11.72 11.56 11.15 11.04
M awalleh North 2 x 125 125 38.96 31.64 14.25 4.98 13.35
M awalleh Tx (1&2) 2 x 125 125 21.97 27.84 22.13 17.27 16.35
South Tx (3&4) 2 x 125 125 7.31 49.99 45.60 41.93 40.63
M isfah 2 x 125 125 54.36 50.67 46.85 42.77 39.16
M obella Tx (1&2) 2 x 125 125 62.03 55.68 51.87
Industrial Tx (3&4) 2 x 125 125 61.55 55.68 29.94
M obella 2 x 125 125 -6.75 -6.94 50.95 44.26 39.43
M udhaibi 2 x 125 125 75.31 72.96 65.50 63.77 62.68
M udhairib 2 x 125 125 65.40 57.17 53.73 51.31 49.66
Tx (1&2) 2 x 125 125 8.85 31.36 15.15 7.72 8.10
M uladah
Tx (3&4) 2 x 125 125 100.07 74.69 72.65 68.79 68.87
M uttrah 2 x 125 125 47.28 48.25 48.00 47.95 48.69
Nakhal 2 x 125 125 43.04 34.60 29.83 24.31 24.30
Page | 165
Five-Year Annual Transmission Capability Statement (2020-2024)
Table C.2: (continued) Available Capacity at Grid Stations (2020-2024) for Connection of New Demand
Available Capacity (MVA)
Total Transformer S ubstation Firm
Location
Capacity (MVA) Capacity (MVA) 2020 2021 2022 2023 2024
MIS Area
132/33 kV Transformers
New Ghubrah 2 x 125 125 10.22 7.95 3.40 1.31 -0.25
New Izki 2 x 125 125 103.45 102.60 101.58 100.69 99.99
Nizwa 2 x 125 125 31.30 20.66 4.00 3.32 3.61
Quriyat 2 x 125 125 68.99 67.17 65.85 63.56 61.87
Qurum 2 x 125 125 22.72 21.83 19.15 17.09 15.94
Sohar Free Tx (1&2) 2 x 125 125 86.46 81.95 78.05 81.82 80.57
Zone Tx (3&4) 2 x 125 125 73.70 71.95 71.15 69.70 67.64
Tx (1&2) 2 x 125 125 66.27 62.31 53.13 30.15 24.09
Sohar
Tx (3&4) 2 x 125 125 2.27 5.65 22.55 16.84
Sumail Industrial 2 x 125 125 124.27 68.24 65.43 63.80 63.36
Page | 166
Five-Year Annual Transmission Capability Statement (2020-2024)
Table C.2: (continued) Available Capacity at Grid Stations (2020-2024) for Connection of New Demand
Available Capacity (MVA)
Total Transformer S ubstation Firm
Location
Capacity (MVA) Capacity (MVA) 2020 2021 2022 2023 2024
Dhofar Area
132/33 kV Transformers
Ashoor 2 x 125 125 46.51 61.09 60.01 60.19 59.23
Ittin 2 x 125 125 34.96 43.11 38.98 29.40 25.64
Tx (1&2) 2 x 125 125 59.66 38.59 29.99 16.13 12.63
Sa'adah
Tx (3&4) 2 x 125 125 80.51 53.99 31.41 15.67 12.17
Raysut 2 x 125 125 16.31 5.26 8.91 10.55 11.04
Salalah-IPP 2 x 125 125 83.32 51.87 17.64 11.48 7.30
Saih Al Khairat 2 x 125 125 69.86 67.26
Shaha'aon 2x 125 125 15.45 11.43 11.94 31.20 28.04
Al Qarm 2 x 63 63 23.73 25.07 21.87 31.17 30.37
M irbat 2 x 63 63 34.49 32.24 29.78
NPS 2 x 63 63 17.37 18.36 15.04 13.51 11.94
2 x 30 30 2.29
Thumrait
2 x 63 63 29.99 25.57 25.91 24.54
Page | 167
Five-Year Annual Transmission Capability Statement (2020-2024)
Table C.3: Overhead Line and Cable Circuit Loadings (%) at Peak Demand (2020-2024)
Circuit Circuit Loading at Max Demand (%)
Voltage No. of
Line Type Rating
(kV) Circuits 2020 2021 2022 2023 2024
(MVA)
MIS Area
Al Jefnen M isfah OHL 400 2 1774 11.02 4.02
Al Jefnen New Rustaq OHL 400 2 1774 17.42
Duqm M ahout OHL 400 2 1774 3.19 4.61
Duqm Suwaihat OHL 400 2 1774 5.67 5.79
Ibri M anah Solar OHL 400 2 1774 30.60
Ibri New Izki OHL 400 2 1774 17.31 21.00
Ibri IPP Nahadah(PDO) OHL 400 2 1774 33.22 15.54
Ibri New Rustaq OHL 400 2 1774 27.51
Jahloot Sur PS OHL 400 2 1774 35.78 29.18 31.84 31.54 30.13
M anah Solar New Izki OHL 400 2 1774 30.84 34.13 22.56
M anah Solar Nahadah(PDO) OHL 400 2 1774 29.77 14.48
M isfah New Izki OHL 400 2 1774 15.82 23.35 30.14 16.16
New Izki Qabel OHL 400 2 1774 7.44 7.27 8.01 8.48 11.11
Qabel Sur PS OHL 400 2 1774 2.72 9.89 14.36 15.73 18.47
SIS Sohar Free Zone OHL 400 2 1774 19.59 19.73 23.38 25.13 25.45
Sohar Free Zone Sohar-3 IPP3&4 OHL 400 2 1774 18.01 19.11 21.77 23.69 24.79
Sohar-1 IPP
Sohar Free Zone OHL 400 2 1774 13.67 14.22 15.86 17.44 18.09
1&2
Sohar Free Zone Sohar-3 IPP3&4 UGC 400 2 2273 14.00 14.87 16.95 18.44 19.30
Sohar Free Zone Sohar-3 IPP3&4 UGC 400 2 2273 14.27 15.10 17.13 18.69 19.53
Airport Heights M isfah OHL 220 2 673 4.99 20.25 22.55 36.76 15.46
Airport Heights M obella OHL 220 2 673 25.75 16.62 23.15 17.27 32.54
Al Filaj Barka PS 1&2 OHL 220 2 673 43.28 40.76 46.58 46.06 38.00
Al Filaj Barka PS 3&4 OHL 220 2 673 43.49 40.97 46.81 46.28 38.20
Al Filaj Barka PS 3&4 OHL 220 2 673 43.15 40.62 46.47 45.94 37.89
Al Filaj Blue City OHL 220 2 673 14.30 8.54 7.74 10.44 7.06
Al Filaj M obella OHL 220 2 673 56.78 43.10 54.13 50.49 51.63
Al Hamriyah Jahloot OHL 220 2 673 39.15 38.60 36.48 32.41 32.34
Barka-3 PS M isfah OHL 220 2 673 26.33 23.58 31.12 32.67 32.75
Blue City M IS OHL 220 2 673 24.76 14.37 15.05 18.68 16.47
Ibri IPP Ibri OHL 220 2 673 31.84 32.49 37.84 39.22 34.31
Ibri IPP Ibri Solar OHL 220 2 673 0.09 31.07 31.28 31.78
Ibri IPP M ahadha OHL 220 2 673 2.83 3.99 12.25 9.37 7.80
Page | 168
Five-Year Annual Transmission Capability Statement (2020-2024)
Table C.3: (continued) Overhead Line and Cable Circuit Loadings (%) at Peak Demand (2020-2024)
Circuit Circuit Loading at Max Demand (%)
Voltage No. of
Line Type Rating
(kV) Circuits
(MVA) 2020 2021 2022 2023 2024
MIS Area
Jahloot M isfah OHL 220 2 673 13.29 5.43 4.19 10.38 9.24
M ahadha SIS OHL 220 2 673 3.98 6.50 4.36 4.42 7.55
M ahadha Sohar Free Zone OHL 220 2 673 10.61 13.19 9.89 11.57 17.10
SIS Sohar Free Zone OHL 220 2 673 16.80 16.03 28.32 29.36 25.19
SIS Sohar-1 PS OHL 220 2 673 23.42 22.12 8.20 6.74 5.12
Sohar Free Zone Sohar-2 PS OHL 220 2 673 23.37 25.32 31.61 31.50 33.35
Sur PS Sur OHL 220 2 673 18.77 19.37 30.72 31.78 31.01
Al Filaj Barka PS 3&4 UGC 220 2 625 46.75 44.03 50.32 49.75 41.06
Al Filaj Blue City UGC 220 2 475 23.73 17.31 16.34 20.10 15.35
Barka-3 PS M isfah UGC 220 2 625 27.38 24.80 32.54 34.24 34.48
Blue City M IS UGC 220 2 475 34.22 18.75 19.93 25.17 22.20
M ahadha Sohar Free Zone UGC 220 2 500 20.64 25.63 18.98 22.53 33.42
SIA Sohar-1 PS UGC 220 3 625 11.93 12.56 14.55 14.77 14.84
SIS Sohar Free Zone UGC 220 2 625 17.89 17.16 30.27 31.38 26.91
SIS Sohar-1 PS UGC 220 2 625 25.05 23.75 7.86 6.31 4.58
Sohar Free Zone Sohar-2 PS UGC 220 2 625 25.18 27.30 34.18 33.98 35.97
Sohar Free Zone Sohar-2 PS UGC 220 2 625 25.17 27.25 33.97 33.89 35.89
Adam M anah OHL 132 2 293 9.94 10.06 10.84 11.14 11.37
Al Falaj Wadi Adai OHL 132 2 293 2.92 3.00 10.05 10.49 9.67
Al Filaj Barka M ain OHL 132 2 293 20.01 27.79 30.12 27.34 46.13
Al Filaj M adinat Barka OHL 132 2 293 48.96 32.01 27.56 33.75 0.27
Al Filaj Nakhal OHL 132 2 293 13.92 15.85 23.64 26.96 10.20
Page | 169
Five-Year Annual Transmission Capability Statement (2020-2024)
Table C.3: (continued) Overhead Line and Cable Circuit Loadings (%) at Peak Demand (2020-2024)
Circuit Circuit Loading at Max Demand (%)
Voltage No. of
Line Type Rating
(kV) Circuits
(MVA) 2020 2021 2022 2023 2024
MIS Area
Al Hamriyah M uttrah OHL 132 2 293 22.83 22.73 18.25 18.04 18.32
Al Hamriyah Qurum OHL 132 2 293 17.08 16.59 28.20 21.68 18.63
Al Hamriyah Wadi Adai OHL 132 2 146 39.80 39.10 20.17 19.15 21.69
Al Hamriyah Wadi Kabair OHL 132 2 146 50.79 50.43 45.65 45.39 45.53
Al Kamil Bedyah OHL 132 2 293 12.30 10.74 14.92 14.66 13.96
Al Kamil JBB Ali OHL 132 2 293 22.47 27.52 30.51 31.58 27.77
Al Kamil JBB Hassan OHL 132 2 293 2.31 4.41 17.50 18.60 16.28
Amerat Jahloot OHL 132 2 293 49.91 46.91 49.90 44.00 42.82
Ayjah Sur OHL 132 2 293 13.07 13.38 16.28 16.57 16.84
Bahla Nizwa OHL 132 2 146 28.60 29.40 31.61 32.62 32.99
Barka M ain M obella Industrial OHL 132 2 293 16.66 15.99 34.25
Bedyah M udhairib OHL 132 2 293 4.86 4.80 23.44 23.55 22.88
Birkat Al M ouz Izki OHL 132 2 293 24.13 12.34 16.34 15.58 9.84
Birkat Al M ouz Nizwa OHL 132 2 293 16.88 6.24 14.44 8.90 5.47
Dank Ibri OHL 132 2 293 5.47 6.32 6.70 7.95 10.43
Dank Wadi Sa'a OHL 132 2 89 32.89 44.69 31.49 31.02 54.36
Page | 170
Five-Year Annual Transmission Capability Statement (2020-2024)
Table C.3: (continued) Overhead Line and Cable Circuit Loadings (%) at Peak Demand (2020-2024)
Circuit Circuit Loading at Max Demand (%)
Voltage No. of
Line Type Rating
(kV) Circuits
(MVA) 2020 2021 2022 2023 2024
MIS Area
Dil Abdusalam KIS OHL 132 2 293 19.63 21.45 16.86 12.18
Dil Abdusalam Saham OHL 132 2 293 36.76 29.85 35.12 31.37 26.11
Dreez Ibri OHL 132 2 293 14.15 14.54 15.04 15.51 16.15
Duqm Wind
Duqm OHL 132 2 293 11.60
Farm
Ibra Qabel OHL 132 2 293 14.51 14.80 15.78 16.37 16.48
Ibri Jebreen OHL 132 2 293 31.37 33.85 43.90 42.17 33.99
Izki New Izki OHL 132 2 293 65.59 45.72 59.00 44.76 35.46
Izki Sumail OHL 132 2 293 33.14 20.23 35.86 14.78 10.55
JBB Hassan Sur OHL 132 2 293 11.92 13.68 33.16 34.83 32.60
Jahloot Quriyat OHL 132 2 293 15.43 15.75 15.93 16.38 16.65
Jahloot Yitti OHL 132 2 403 2.26 2.31 2.33 2.40 2.45
Jebreen Nizwa OHL 132 2 293 19.86 22.70 32.08 29.96 22.65
Khaborah Khadra OHL 132 2 293 6.58 38.04 43.96 17.44 30.90
Khadra Suwaiq OHL 132 2 293 21.20 14.93 18.42 13.62 8.03
Khoudh M awalleh South OHL 132 2 250 8.57 13.29 9.41 27.73
Khoudh Rusail Industrial OHL 132 2 250 27.33 7.39 30.59 52.31
Liwa Shinas OHL 132 2 293 11.60 12.81 14.04 15.07 16.59
Liwa Sohar Free Zone OHL 132 2 293 33.94 37.02 37.41 39.93 43.11
Page | 171
Five-Year Annual Transmission Capability Statement (2020-2024)
Table C.3: (continued) Overhead Line and Cable Circuit Loadings (%) at Peak Demand (2020-2024)
Circuit Circuit Loading at Max Demand (%)
Voltage No. of
Line Type Rating
(kV) Circuits
(MVA) 2020 2021 2022 2023 2024
MIS Area
M SQ Wadi Adai OHL 132 2 293 3.93 2.07 31.36 17.68 21.09
M adinat Barka M uladah OHL 132 2 293 23.99 13.35 12.37 10.92 11.10
Waste to Energy
M adinat Barka OHL 132 2 293 19.95
Plant
M adinat Nizwa Nizwa OHL 132 2 293 11.90 12.13 12.89 13.14 13.19
M adinat Shinas Shinas OHL 132 2 293 11.55 13.34 13.78 14.71 15.81
M ahadha Wadi Al Jazzi OHL 132 2 178 13.88 13.82 19.82 18.17 9.35
M ahadha Wadi Sa'a OHL 132 2 293 12.33 16.27 12.23 12.72 20.02
M anah Nizwa OHL 132 2 293 20.22 37.68 36.75 34.69 17.99
M isfah Wadi Adai OHL 132 2 293 0.79 0.80 46.90 34.39 36.34
M udhaibi M udhairib OHL 132 2 293 21.94 1.44 19.53 16.21 1.46
M udhaibi Samad OHL 132 2 293 4.52 4.70 4.84 4.95 5.03
M udhaibi Sinaw OHL 132 2 293 10.94 12.93 7.74 6.80 14.95
M udhairib Qabel OHL 132 2 293 27.82 11.82 52.19 49.05 34.98
M uttrah Wadi Kabair OHL 132 1 293 4.11 3.87 1.54 2.06 0.91
Nakhal Wadi Bani Auwf OHL 132 2 293 7.75 8.71 10.78 12.41
New Izki Sinaw OHL 132 2 293 7.77 19.36 7.43 9.92 21.99
Rustaq Wadi Bani Auwf OHL 132 2 293 8.49 4.99 4.28
SIS Saham OHL 132 2 293 52.20 44.15 50.62 47.23 42.70
SIS Uwaynat OHL 132 2 293 27.55 29.57 26.35 29.55 37.88
Page | 172
Five-Year Annual Transmission Capability Statement (2020-2024)
Table C.3: (continued) Overhead Line and Cable Circuit Loadings (%) at Peak Demand (2020-2024)
Circuit Circuit Loading at Max Demand (%)
Voltage No. of
Line Type Rating
(kV) Circuits 2020 2021 2022 2023 2024
(MVA)
MIS Area
Shinas Sohar Free Zone OHL 132 2 585 5.65 6.21 6.67 7.14 7.82
Sohar Free Zone Wadi Al Jazzi OHL 132 2 293 13.95 15.22 14.74 15.44 17.33
Sohar Uwaynat OHL 132 2 293 8.18 8.71 6.52 7.71 15.06
Sohar Wadi Al Jazzi OHL 132 2 293 22.60 23.81 26.80 26.57 21.98
Sumail Industrial Sumail OHL 132 2 293 16.84 6.79 17.77 7.87 11.90
A'salam M obella UGC 132 2 375 41.84 42.95 39.27 42.96 27.45
A'salam Seeb M ain UGC 132 2 375 18.56 14.30 14.83 15.89 4.18
Airport Heights M awaleh South UGC 132 2 375 5.34 12.81 42.92 13.48 5.13
Airport Heights M awalleh North UGC 132 2 375 11.38 12.45 14.77 16.00 14.89
Al Falaj M uttrah UGC 132 1 300 24.08 24.72 11.13 10.19 12.86
Al Hamriyah M uttrah UGC 132 2 375 18.29 18.31 14.81 14.60 14.96
Al Hamriyah Wadi Kabair UGC 132 2 172 43.56 43.28 39.19 38.96 39.11
Bousher Ghala Heights UGC 132 2 375 9.81 18.75 41.30 4.04 3.98
Bousher New Ghubrah UGC 132 3 375 14.16 18.20 29.01 11.37 10.49
Bureimi Industrial Bureimi UGC 132 2 375 3.32 3.39 3.45 3.64 5.49
Ghala Ghala Heights UGC 132 2 375 7.68 3.96 21.97 20.81 24.70
Izki New Izki UGC 132 2 375 51.08 35.57 45.91 34.75 27.52
Khoudh M awalleh South UGC 132 2 375 5.87 8.88 6.44 18.61
M SQ New Ghubrah UGC 132 3 375 26.07 30.26 41.51 24.01 23.28
M awalleh South Rusail Industrial UGC 132 2 375 39.39 17.11 3.75 19.05 34.25
M awalleh South Seeb M ain UGC 132 2 375 11.75 12.80 13.28 13.73 28.56
M uttrah Wadi Kabair UGC 132 1 300 4.38 3.84 2.47 2.99 1.44
M uttrah Wadi Kabair UGC 132 1 300 4.01 3.82 1.48 1.99 0.95
New Izki Sinaw UGC 132 2 375 5.23 14.89 4.84 6.92 16.91
Page | 173
Five-Year Annual Transmission Capability Statement (2020-2024)
Table C.3: (continued) Overhead Line and Cable Circuit Loadings (%) at Peak Demand (2020-2024)
Ashoor Al-Qarm OHL 132 2 359 14.43 16.21 15.48 16.01 15.39
Ashoor S'aadah (Portion-1) OHL 132 2 330 17.68 21.51 22.22 22.03 21.66
Ashoor S'aadah (Portion-2) OHL 132 2 330 17.53 21.64 22.32 22.20 21.83
Harwail Wind Farm(Portion-1) OHL 132 1 183 0.55 0.55 0.55 0.55 0.56
Harwail Wind Farm(Portion-2) OHL 132 1 359 0.36 0.36 0.36 0.36 0.36
Ittin Thumrait OHL 132 2 183 2.03 3.16 4.41 17.91 18.59
NPS Salalah Free Zone OHL 132 2 359 5.93 5.81 3.78 12.58 17.69
Salalah Free
Ittin OHL 132 2 359 7.04 2.86 5.63 10.46 12.04
Zone
Salalah Free
Shaha'aon OHL 132 2 359 13.22 15.40 19.09 20.27 22.01
Zone
Shaha'aon S'aadah OHL 132 2 330 1.83 0.91 4.71 8.88 10.30
Thumrait Wind Farm (Portion-1) OHL 132 1 359 5.08 5.13 5.00 5.15 5.26
Thumrait Wind Farm (Portion-2) OHL 132 1 183 10.51 10.71 10.21 10.76 11.13
Ashoor Al-Qarm UGC 132 2 279 18.60 20.78 19.85 20.51 19.72
Ashoor S'aadah (Portion-1) UGC 132 2 279 20.97 25.65 26.47 26.30 25.86
Ashoor S'aadah (Portion-2) UGC 132 2 300 19.31 24.60 25.24 25.41 24.98
NPS Salalah Free Zone UGC 132 2 279 7.62 7.45 4.85 16.17 22.74
Shaha'aon S'aadah UGC 132 2 300 1.91 3.01 7.44 11.16 12.78
Page | 174
Five-Year Annual Transmission Capability Statement (2020-2024)
Page | 175
Five-Year Annual Transmission Capability Statement (2020-2024)
Table C.4: (continued) Transmission System Voltage Profile at Peak Demand (2020-2024)
Busbar Voltage at Maximum Demand (per unit)
Location
2020 2021 2022 2023 2024
MIS Area
220 kV Busbars
Nizwa 1.02
SIA 1.05 1.05 1.06 1.05 1.05
SIS 1.04 1.04 1.05 1.04 1.04
Sohar Free Zone 1.05 1.05 1.06 1.05 1.05
Sohar-1 PS 1.05 1.05 1.06 1.05 1.05
Sohar-2 PS 1.05 1.05 1.07 1.06 1.05
Sur 1.01 1.04 1.01 1.02 1.03
Sur PS 1.02 1.04 1.02 1.03 1.04
132 kV Busbars
A'salam 1.01 1.02 1.02 0.99 1.00
Adam 0.97 1.01 0.98 1.01 1.01
Airport Height 1.03 1.01 1.02 1.02 0.99
Al Falaj 0.99 1.00 1.00 1.00 1.00
Al Filaj 1.02 1.03 1.02 1.00 1.02
Al Hamriyah 0.99 1.00 1.00 1.00 1.01
Al Hayl 1.02 1.02 1.03 1.04 1.02
Al Jawabi 0.96
Al Jefnen 1.01 1.04
Al Kamil 1.03 1.04 0.98 0.98 1.01
Amerat 0.99 1.00 1.00 0.99 1.00
Ayjah 1.02 1.03 1.01 1.02 1.03
Bahla 0.97 0.99 0.96 0.98 1.01
Barka M ain 1.02 1.03 1.02 1.00 1.01
Bedyah 1.02 1.04 1.00 1.00 1.03
Birkat Al M ouz 0.99 1.01 0.99 1.01 1.03
Bousher 0.98 0.99 0.99 0.99 1.00
Bureimi 1.03 1.02 1.06 1.04 1.01
Bureimi Industrial 1.03 1.03 1.06 1.04 1.01
Daghmar 1.00 1.00 1.01 1.00 1.00
Dank 1.03 1.03 1.04 1.05 1.02
Dil Abdusalam (DAS) 0.98 1.01 1.03 1.01 1.02
Dreez 1.03 1.03 1.03 1.05 1.04
Duqm 1.01 1.01
Duqm Wind Farm 1.01
Ghala 1.03 1.01 0.98 1.02 0.99
Ghala Heights 0.99 0.98 1.01 0.99
132kV Ghala Heights BB-1 0.98
132kV Ghala Heights BB-2 1.03
Ibra 1.02 1.04 1.01 1.01 1.04
Ibri 1.04 1.04 1.04 1.06 1.05
Page | 176
Five-Year Annual Transmission Capability Statement (2020-2024)
Table C.4: (continued) Transmission System Voltage Profile at Peak Demand (2020-2024)
Busbar Voltage at Maximum Demand (per unit)
Location
2020 2021 2022 2023 2024
MIS Area
132 kV Busbars
Izki 1.01 1.02 1.00 1.02 1.04
JBB Ali 1.00 1.00 0.94 0.94 0.97
JBB Ali Wind Farm 0.96
JBB Hassan 1.02 1.03 0.99 0.99 1.01
Jahloot 1.02 1.02 1.02 1.02 1.02
Jebreen 0.99 1.00 0.98 1.01 1.03
KIS 1.02 1.03 1.01 1.02
Khaborah 0.96 1.00 1.01 1.00 1.00
Khadra 0.99 1.00 0.99
Khadra-1 0.98 0.98
Khadra-2 0.96 0.96
Khoudh 1.03 1.01 1.00 1.04
Liwa 1.04 1.03 1.07 1.06 1.03
M IS 0.99 1.00 1.00 0.97 1.00
M SQ-1 0.99 1.00 0.99 0.99 1.00
M SQ-2 0.99 1.00 0.99 0.99 1.00
M adinat Barka 1.01 1.02 1.01 0.98 0.99
M adinat Nizwa 0.98 1.00 0.98 1.00 1.03
M adinat Shinas 1.03 1.02 1.06 1.04 1.01
M ahadha 1.04 1.04 1.07 1.06 1.02
M anah 0.98 1.02 1.00 1.02 1.03
M awalleh North 1.03 1.01 1.01 1.02 0.99
M awalleh South-1 1.04 1.03 1.01 1.00 1.04
M awalleh South-2 1.04 1.01 1.01 1.02 1.04
M isfah 1.04 1.02 1.03 1.02 1.03
M obella 1.02 1.02 1.02 1.00 1.00
M obella Industrial 1.02 0.99 1.00
M udhaibi 1.02 1.01 1.01 1.02 1.03
M udhairib 1.02 1.04 1.01 1.02 1.04
M uladah 1.00 1.00 0.97 1.00
M uladah-1 0.99
M uladah-2 0.98
M uttrah 0.99 1.00 1.00 1.00 1.01
Nakhal 1.01 1.03 1.01 0.98 1.01
New Ghubrah 0.98 0.99 0.99 0.99 1.00
New Izki 1.04 1.04 1.03 1.04 1.06
New Rustaq 1.01
Nahadah(PDO) 0.99 1.01 0.99 0.98 1.03
Nizwa 0.98 1.00 0.98 1.00 1.03
Page | 177
Five-Year Annual Transmission Capability Statement (2020-2024)
Table C.4: (continued) Transmission System Voltage Profile at Peak Demand (2020-2024)
Busbar Voltage at Maximum Demand (per unit)
Location
2020 2021 2022 2023 2024
MIS Area
132 kV Busbars
Qabel 1.03 1.05 1.02 1.02 1.05
Quriyat 1.00 1.00 1.01 1.00 1.00
Qurum 0.99 1.00 0.99 0.99 1.00
Rusail 1.05 1.03 1.01
Rusail Industrial 1.05 1.03 1.01 1.00 1.04
Rustaq 0.96 0.99 0.98 0.95 1.01
SIA 1.01 1.04 1.02 1.02 1.00
SIS 1.04 1.02 1.07 1.05 1.04
Saham 1.01 1.01 1.05 1.03 1.03
Samad 1.02 1.01 1.00 1.01 1.03
Seeb M ain 1.03
Seeb M ain-1 1.04 1.00 1.01 1.02
Seeb M ain-2 1.01 1.02 1.02 0.99
Shinas 1.04 1.03 1.07 1.05 1.02
Sinaw 1.02 1.02 1.01 1.02 1.04
Sohar 1.02 1.00 1.05 1.03 1.01
Sohar Free Zone 1.04 1.04 1.07 1.06 1.03
Sohar Refinery 1.01 1.04 1.02 1.02 1.00
Sumail 1.01 1.01 0.99 0.99 1.02
Sumail Industrial 1.02 1.01 0.99 1.00 1.03
Sur 1.03 1.04 1.03 1.04 1.05
Sur-2 1.03 1.04 1.03 1.04 1.05
Suwaiq 0.99 1.00 1.00 0.97 1.00
Suwaihat(PDO) 1.02 1.00
Uwaynat 1.03 1.01 1.06 1.04 1.02
Wadi Adai 0.99 1.00 1.00 1.00 1.00
Wadi Al Jazzi 1.04 1.02 1.07 1.05 1.02
Wadi Bani Auwf 0.99 0.99 0.96 1.00
Wadi Kabair 0.99 1.00 1.00 1.00 1.01
Wadi Sa'a 1.04 1.04 1.07 1.06 1.02
Waste to Energy Plant 1.00
Yanqul 1.02 1.03 1.04 1.02
Yitti 1.02 1.02 1.02 1.01 1.02
33 kV Busbars
Tx (1&2) 1.00 1.00 1.00 1.00 1.00
A'salam
Tx (3&4) 1.00 1.00 1.00 1.01 1.00
Adam 1.00 1.00 1.00 1.00 1.00
Page | 178
Five-Year Annual Transmission Capability Statement (2020-2024)
Table C.4: (continued) Transmission System Voltage Profile at Peak Demand (2020-2024)
Busbar Voltage at Maximum Demand (per unit)
Location
2020 2021 2022 2023 2024
MIS Area
33 kV Busbars
Tx (1&2) 1.00 1.00 1.00 1.00 1.00
Airport Height
Tx (3&4) 1.00 1.00 1.00 1.00 0.99
Al Falaj 1.00 1.01 1.00 1.00 1.00
Al Hayl 1.00 1.00 1.00 1.00 1.00
Al Jawabi 1.00
Tx (1&2) 1.00 1.00 1.00 0.99 1.00
Amerat
Tx (3&4) 1.00 1.00 1.00 0.99 1.00
Ayjah 1.00 1.00 1.00 1.00 1.01
Bahla 1.00 1.00 1.00 0.99 1.00
Tx 3 1.00 1.01
Barka M ain
Tx (1&2) 1.00 1.00 1.00 1.00 0.99
Barka-3 PS 1.00 1.01 1.00 1.00 1.00
Bedyah 1.00 1.00 1.00 1.00 1.00
Birkat Al M ouz 0.99 0.99 1.00 1.00 1.00
Blue City 1.00 1.01 1.00 1.00 1.00
Tx (1&2) 1.00 1.00 1.00 1.00 1.00
Bousher
Tx (3&4) 0.99 1.00 1.00 0.99 1.00
Bureimi 1.00 1.01 1.01 1.00 1.00
Tx (1&2) 1.01 1.00 1.00 1.01 1.00
Bureimi Industrial
Tx (3&4) 1.01 1.01 1.00 1.00 1.01
Dank 1.00 1.00 1.00 1.00 1.00
Dil Abdusalam(DAS) 0.99 1.00 1.00 1.00 1.00
Dreez 1.00 1.00 1.00 1.00 1.00
Tx (1&2) 1.00 1.00
Duqm
Tx (3&4) 0.99 1.00
Tx (1&2) 1.00 1.00 1.00 1.01 1.00
Ghala Heights
Tx (3&4) 1.00 1.00 1.00 1.00 1.00
Tx (1&2) 1.00 1.00 1.00 1.00 0.99
Ghala
Tx (3&4) 1.00 1.00 1.00 1.00 1.00
Ibra 1.00 1.00 1.00 1.00 1.00
125M VA 1.00 1.00 1.00 1.01 1.01
Ibri
63M VA 1.00 1.00 1.00 1.01 0.99
Page | 179
Five-Year Annual Transmission Capability Statement (2020-2024)
Table C.4: (continued) Transmission System Voltage Profile at Peak Demand (2020-2024)
Busbar Voltage at Maximum Demand (per unit)
Location
2020 2021 2022 2023 2024
MIS Area
33 kV Busbars
Izki 1.00 1.00 1.00 0.99 1.00
JBB Ali 1.00 0.99 1.00 0.99 1.00
JBB Hassan 1.00 1.00 1.00 1.00 1.00
Jahloot 1.01 1.00 1.00 1.00 1.00
Jebreen 0.99 1.00 1.00 1.00 1.00
Khaborah 1.01 0.99 1.00 1.00 1.01
Tx (1&2) 1.00 1.00 0.99 0.99 1.00
Khadra
Tx (3&4) 0.99 1.00 1.00 1.00 1.00
Tx (1&2) 1.01 1.00 1.01 1.00
Khoudh
Tx (3&4) 1.00 1.00 1.00 1.01
Tx (1&2) 1.00 1.00 1.01 1.00 1.00
Liwa
Tx (3&4) 1.01 1.00 1.00 1.01 1.00
M IS 1.00 0.99 1.00 1.00 1.00
Tx (1&2) 1.00 0.99 1.00 1.00 0.99
M SQ
Tx (3&4) 1.00 1.00 1.00 1.00 1.00
Tx (1&2) 1.00 0.99 1.00 0.99 0.99
M adinat Barka
Tx (3&4) 1.00 1.01 1.00 1.00 0.99
M adinat Nizwa 0.99 0.99 0.99 1.00 0.99
M adinat Shinas 1.00 1.00 1.00 1.01 1.00
M ahadha 1.01 0.99 0.99 0.99 1.01
M ahout 1.00 1.00
M awalleh North 1.00 1.00 1.00 1.00 1.00
Tx (1&2) 1.00 1.00 0.99 1.00 1.01
M awalleh South
Tx (3&4) 1.00 1.01 1.00 1.01 1.00
M isfah 1.00 1.01 1.00 1.00 1.01
M obella 1.00 1.00 1.00 1.00 1.01
Tx (1&2) 1.01 1.00 1.01
M obella Industrial
Tx (3&4) 1.00 1.00 1.00
M udhaibi 1.01 1.00 1.00 1.00 1.00
M udhairib 1.00 1.00 1.00 1.00 1.00
Tx (1&2) 1.00 1.00 1.00 1.00 0.99
M uladah
Tx (3&4) 1.00 1.00 0.99 1.00 0.99
M uttrah 1.00 1.00 1.00 1.00 1.00
Nakhal 1.01 1.00 1.00 1.00 1.00
New Ghubrah 1.00 1.00 1.00 0.99 1.00
Page | 180
Five-Year Annual Transmission Capability Statement (2020-2024)
Table C.4: (continued) Transmission System Voltage Profile at Peak Demand (2020-2024)
Busbar Voltage at Maximum Demand (per unit)
Location
2020 2021 2022 2023 2024
MIS Area
33 kV Busbars
New Izki 1.01 1.01 1.00 1.00 1.01
Nizwa 0.99 1.00 1.00 0.99 1.00
Quriyat 1.00 1.00 1.00 1.00 1.00
Qurum 1.01 1.01 1.00 1.00 1.00
Tx (1&2) 1.01 1.00 1.00 1.00 1.01
Rusail Industrial
Tx (3&4) 1.00 1.00 1.00 1.00 1.01
Rustaq-A 1.00 1.01 1.00 1.00 1.00
Rustaq-B 0.99 1.00 1.00 1.00 1.01
SIA 1.00 1.01 1.00 1.01 1.00
Saham 0.99 1.00 1.00 1.00 1.00
Samad 1.00 1.01 1.00 1.01 1.00
Tx (1&2) 1.00 1.00 1.00 1.00 1.00
Seeb M ain
Tx (3&4) 1.00 1.00 1.00 1.00 0.99
Shinas 1.01 1.00 1.00 1.00 1.00
Sinaw 1.00 1.00 1.00 1.00 1.00
Tx (1&2) 1.00 1.00 1.01 1.00 1.00
Sohar Free Zone
Tx (3&4) 1.01 1.00 1.00 1.00 1.00
Tx (1&2) 1.00 1.00 1.00 1.00 1.00
Sohar
Tx (3&4) 1.00 0.99 0.99 1.01 1.00
Sumail Industrial 1.00 1.00 1.00 0.99 1.00
125M VA 1.00 1.00 1.00 1.00 1.00
Sumail
63M VA 0.99 1.00 0.99 1.00 0.99
Sur 1.00 1.00 1.00 1.01 1.01
Suwaiq 0.99 1.00 1.00 0.99 1.00
Tx (1&2) 1.00 1.00 1.00 1.00 1.00
Uwaynat
Tx (3&4) 1.00 1.00 1.00 1.00 1.00
Wadi Adai 1.00 1.00 1.00 0.99 1.00
Wadi Bani Auwf 1.00 1.00 0.99 1.00
Tx (1&2) 1.00 1.00 1.00 1.00 1.00
Wadi Kabair
Tx (3&4) 0.99 0.99 1.00 1.00 1.00
Wadi Sa'a 1.00 1.01 1.00 1.00 1.00
Yanqul 1.00 1.00 1.01 1.01
Yitti 1.00 1.00 1.00 1.00 1.00
11 kV Busbars
Daghmar 1.00 0.99 1.00 0.99 1.00
Page | 181
Five-Year Annual Transmission Capability Statement (2020-2024)
Table C.4: (continued) Transmission System Voltage Profile at Peak Demand (2020-2024)
Busbar Voltage at Maximum Demand (per unit)
Location
2020 2021 2022 2023 2024
Dhofar Area
132 kV Busbars
Al Qarm 1.00 1.01 1.01 1.02 1.03
Ashoor 1.00 1.02 1.02 1.03 1.03
Ittin 1.00 1.01 1.01 1.02 1.02
M irbat 1.02 1.01 1.03 1.03
NPS 1.01 1.01 1.02 1.03 1.03
Raysut 1.01 1.01 1.02 1.03 1.03
Saih Al Khairat 0.99 0.99
Salalah IPP 1.01 1.01 1.02 1.03 1.03
Shaha'aon 1.01 1.00 1.01 1.02 1.02
S’aadah 1.01 1.00 1.00 1.01 1.02
Thumrait 1.00 1.01 1.01 1.00 1.01
Wind Farm 1.02 1.02 1.02 1.02 1.02
33 kV Busbars
Al Qarm 1.01 1.01 1.01 1.00 1.00
Ashoor 1.01 1.00 1.00 1.00 1.01
Ittin 1.00 1.01 1.00 1.00 1.01
M irbat 1.00 1.00 1.00 1.01
NPS 1.00 1.00 1.00 1.00 1.01
Raysut 1.00 0.99 1.00 1.00 1.00
Tx (1&2) 0.99 0.99 0.99 1.00 1.00
S’aadah
Tx (3&4) 1.00 1.00 0.99 1.00 1.00
Saih Al Khairat 1.01 1.00
Salalah IPP 1.00 1.00 1.00 1.00 1.00
Shaha'aon 1.00 1.01 1.00 1.00 1.01
Thumrait 1.00 1.00 1.00 1.01 1.00
Page | 182
Five-Year Annual Transmission Capability Statement (2020-2024)
Page | 183
Five-Year Annual Transmission Capability Statement (2020-2024)
Table C.5: (continued) Transmission System Voltage Profile at Minimum Demand (2020-2024)
Busbar Voltage at Minimum Demand (per unit)
Location
2020 2021 2022 2023 2024
MIS Area
220 kV Busbars
Sur 1.00 1.01 1.00 1.00 1.00
Sur PS 1.00 1.01 1.00 1.00 1.00
132 kV Busbars
A'salam 1.02 1.02 1.01 1.01 1.02
Adam 1.01 1.00 1.01 1.00 1.00
Airport Height 1.02 1.02 1.01 1.01 1.02
Al Falaj 1.01 1.02 1.01 1.01 1.02
Al Filaj 1.01 1.02 1.00 1.01 1.02
Al Hamriyah 1.01 1.02 1.01 1.01 1.02
Al Hayl 1.03 1.02 1.02 1.03 1.02
Al Jefnen 1.03
Al Kamil 1.02 1.01 1.01 1.01 1.01
Amerat 1.02 1.02 1.01 1.01 1.02
Ayjah 1.01 1.01 1.00 1.01 1.01
Bahla 1.01 1.00 1.01 1.00 1.00
Barka M ain 1.01 1.02 1.01 1.01 1.02
Bedyah 1.02 1.02 1.02 1.02 1.01
Birkat Al M ouz 1.01 1.01 1.01 1.01 1.01
Bousher 1.01 1.02 1.01 1.01 1.02
Bureimi 1.02 1.01 1.02 1.02 1.01
Bureimi Industrial 1.02 1.01 1.02 1.02 1.01
Daghmar 1.01 1.01 1.01 1.01 1.01
Dank 1.03 1.02 1.02 1.03 1.02
Dil Abdusalam (DAS) 1.00 1.01 1.02 1.01 1.02
Dreez 1.02 1.01 1.02 1.03 1.02
Duqm 1.01
Ghala 1.02 1.02 1.01 1.01 1.02
Ghala Heights 1.01 1.02 1.01 1.01 1.02
Ibra 1.02 1.02 1.02 1.02 1.01
Ibri 1.03 1.02 1.02 1.03 1.03
Izki 1.02 1.01 1.02 1.01 1.01
JBB Ali 1.01 1.00 1.00 1.00 1.01
JBB Hassan 1.01 1.01 1.01 1.01 1.01
Jahloot 1.02 1.02 1.02 1.02 1.02
Page | 184
Five-Year Annual Transmission Capability Statement (2020-2024)
Table C.5: (continued) Transmission System Voltage Profile at Minimum Demand (2020-2024)
Busbar Voltage at Minimum Demand (per unit)
Location
2020 2021 2022 2023 2024
MIS Area
132 kV Busbars
Jebreen 1.01 1.01 1.01 1.01 1.01
KIS 1.02 1.02 1.02 1.02
Khaborah 1.00 1.01 1.01 1.01 1.02
Khadra 1.00 1.01 1.01 1.01 1.01
Khoudh 1.01 1.01 1.01 1.02
Liwa 1.00 1.01 1.01 1.01 1.00
M IS 1.01 1.01 1.01 1.01 1.02
M SQ-1 1.01 1.02 1.01 1.01 1.02
M SQ-2 1.01 1.02 1.01 1.01 1.02
M adinat Barka 1.01 1.01 1.00 1.01 1.02
M adinat Nizwa 1.01 1.00 1.01 1.01 1.00
M adinat Shinas 1.00 1.01 1.00 1.00 1.00
M ahadha 1.02 1.01 1.02 1.02 1.01
M anah 1.01 1.00 1.01 1.01 1.01
M awalleh North 1.02 1.02 1.01 1.01 1.02
M awalleh South-1 1.01 1.01 1.01 1.01 1.02
M awalleh South-2 1.01 1.01 1.01 1.01 1.02
M isfah 1.01 1.01 1.01 1.01 1.02
M obella 1.02 1.02 1.01 1.01 1.02
M obella Industrial 1.01 1.01 1.02
M udhaibi 1.02 1.02 1.02 1.02 1.01
M udhairib 1.02 1.02 1.02 1.02 1.01
M uladah 1.01 1.01 1.00 1.01 1.02
M uttrah 1.01 1.02 1.01 1.01 1.02
Nakhal 1.01 1.01 1.01 1.01 1.02
New Ghubrah 1.01 1.02 1.01 1.01 1.02
New Izki 1.02 1.02 1.03 1.02 1.02
Nahadah(PDO) 1.01 1.01 1.01 1.01 1.02
Nizwa 1.01 1.00 1.01 1.01 1.01
Qabel 1.03 1.02 1.03 1.03 1.01
Quriyat 1.01 1.01 1.01 1.01 1.01
Qurum 1.01 1.02 1.01 1.01 1.02
Rusail 1.01 1.01 1.01 1.01
Rusail Industrial 1.01 1.01 1.01 1.01 1.02
Rustaq 1.00 1.00 1.01 1.00 1.01
SIA 1.01 1.01 1.01 1.01 1.01
Page | 185
Five-Year Annual Transmission Capability Statement (2020-2024)
Table C.5: (continued) Transmission System Voltage Profile at Minimum Demand (2020-2024)
Busbar Voltage at Minimum Demand (per unit)
Location
2020 2021 2022 2023 2024
MIS Area
132 kV Busbars
SIS 1.01 1.01 1.01 1.02 1.02
Saham 1.00 1.01 1.01 1.02 1.02
Samad 1.02 1.02 1.02 1.02 1.01
Seeb M ain 1.02 1.01 1.01 1.01 1.02
Shinas 1.00 1.01 1.01 1.01 1.00
Sinaw 1.02 1.02 1.03 1.02 1.02
Sohar 1.00 1.01 1.01 1.01 1.01
Sohar Free Zone 1.01 1.01 1.01 1.01 1.01
Sohar Refinery 1.01 1.01 1.01 1.01 1.01
Sumail 1.01 1.01 1.01 1.01 1.02
Sumail Industrial 1.01 1.01 1.01 1.02
Sur 1.01 1.01 1.01 1.01 1.02
Sur-2 1.01 1.01 1.01 1.01 1.02
Suwaiq 1.01 1.01 1.01 1.01 1.02
Swaihat(PDO) 1.00
Uwaynat 1.00 1.01 1.01 1.01 1.01
Wadi Adai 1.01 1.02 1.01 1.01 1.02
Wadi Al Jazzi 1.01 1.01 1.01 1.01 1.01
Wadi Bani Auwf 1.02 1.00 1.01
Wadi Kabair 1.01 1.02 1.01 1.01 1.02
Wadi Sa'a 1.02 1.01 1.02 1.02 1.01
Yanqul 1.02 1.02 1.03 1.02
Yitti 1.02 1.02 1.02 1.02 1.02
33 kV Busbars
Page | 186
Five-Year Annual Transmission Capability Statement (2020-2024)
Table C.5: (continued) Transmission System Voltage Profile at Minimum Demand (2020-2024)
Busbar Voltage at Minimum Demand (per unit)
Location
2020 2021 2022 2023 2024
MIS Area
33 kV Busbars
Tx (1&2) 1.00 1.00 1.00 1.00 1.00
Airport Height
Tx (3&4) 1.00 1.00 1.00 1.00 1.00
Al Falaj 1.00 1.01 1.00 1.00 1.00
Al Hayl 1.01 1.00 1.01 1.00 1.01
Tx (1&2) 1.00 1.01 1.00 1.00 1.00
Amerat
Tx (3&4) 1.00 1.00 1.01 1.00 1.00
Ayjah 1.00 1.00 1.00 1.00 1.01
Bahla 1.00 0.99 1.00 0.99 0.99
Tx (3) 1.01 1.00
Barka M ain
Tx (1&2) 0.99 0.99 1.00 1.00 1.00
Barka-3 PS 1.00 1.00 1.00 1.00 1.00
Bedyah 1.01 1.00 1.01 1.00 1.01
Birkat Al M ouz 1.00 1.00 1.00 1.00 1.00
Blue City 1.00 1.00 1.00 1.00 1.01
Tx (1&2) 1.00 1.00 1.00 1.00 1.00
Bousher
Tx (3&4) 1.00 1.00 1.00 1.00 1.00
Bureimi 1.00 1.00 1.00 1.00 1.00
Tx (1&2) 1.00 1.00 1.00 1.01 1.01
Bureimi Industrial
Tx (3&4) 1.00 1.01 1.00 1.01 1.00
Dank 1.00 1.00 1.00 1.00 1.00
Dil Abdusalam(DAS) 0.99 1.00 1.00 1.00 1.00
Dreez 1.01 1.00 1.00 1.00 1.00
Tx (1&2) 1.00
Duqm
Tx (3&4) 1.00
Tx (1&2) 1.00 1.00 1.00 1.00 1.00
Ghala Heights
Tx (3&4) 1.00 1.00 1.00 1.00 1.00
Tx (1&2) 1.00 1.00 1.00 1.00 1.00
Ghala
Tx (3&4) 1.00 1.00 1.00 1.00 1.01
Ibra 1.01 1.00 1.01 1.00 1.00
125M VA 1.00 1.00 1.01 1.01 1.00
Ibri
63M VA 1.00 1.00 1.00 1.00 1.00
Izki 1.00 1.00 1.00 1.01 1.01
JBB Ali 1.00 1.00 1.00 1.00 1.00
JBB Hassan 1.01 1.00 1.00 1.00 1.00
Page | 187
Five-Year Annual Transmission Capability Statement (2020-2024)
Table C.5: (continued) Transmission System Voltage Profile at Minimum Demand (2020-2024)
Busbar Voltage at Minimum Demand (per unit)
Location
2020 2021 2022 2023 2024
MIS Area
33 kV Busbars
Jahloot 1.00 1.00 1.00 1.00 1.01
Jebreen 1.00 1.00 1.00 1.00 1.00
Khaborah 0.99 1.00 1.00 1.00 1.01
Tx (1&2) 1.00 1.00 1.00 1.00 1.01
Khadra
Tx (3&4) 1.00 1.00 1.00 1.00 1.00
Tx (1&2) 1.00 1.00 1.00 1.01
Khoudh
Tx (3&4) 1.00 1.01 1.00 1.01
Tx (1&2) 0.99 1.00 1.00 1.00 1.00
Liwa
Tx (3&4) 1.00 1.00 0.99 0.99 1.00
M IS 1.00 1.00 1.00 1.00 1.00
Tx (1&2) 1.01 0.99 1.01 1.00 1.00
M SQ
Tx (3&4) 1.01 1.01 1.01 1.00 1.00
Tx (1&2) 0.99 0.99 0.99 1.00 1.00
M adinat Barka
Tx (3&4) 1.01 1.01 1.00 1.00 0.99
M adinat Nizwa 1.00 1.00 1.00 1.00 1.00
M adinat Shinas 1.01 1.00 1.00 1.01 1.00
M ahadha 1.00 0.99 1.00 1.00 1.01
M ahout 1.00
M awalleh North 1.00 1.00 1.00 1.00 1.00
Tx (1&2) 1.01 1.01 1.00 1.00 1.00
M awalleh South
Tx (3&4) 1.01 1.01 1.00 1.00 1.01
M isfah 1.01 1.01 1.00 1.01 1.00
M obella 1.00 1.00 1.00 1.01 1.01
Tx (1&2) 1.00 1.00 1.00
M obella Industrial
Tx (3&4) 1.00 1.00 1.00
M udhaibi 1.01 1.00 1.01 1.01 1.00
M udhairib 1.01 1.01 1.01 1.01 1.01
Tx (1&2) 1.01 1.00 1.00 1.00 1.00
M uladah
Tx (3&4) 1.00 1.00 1.00 1.00 1.00
M uttrah 1.01 1.01 1.01 1.00 1.00
Nakhal 1.01 1.00 1.01 1.00 1.00
New Ghubrah 1.01 1.00 1.00 1.00 1.00
New Izki 1.00 1.00 1.00 1.01 1.00
Nizwa 1.00 1.00 1.00 1.00 1.00
Quriyat 1.00 1.00 1.00 1.00 1.00
Qurum 1.00 1.01 1.00 1.00 1.00
Tx (1&2) 1.01 1.01 1.00 1.00 1.01
Rusail Industrial
Tx (3&4) 1.01 1.01 1.00 1.00 1.00
Page | 188
Five-Year Annual Transmission Capability Statement (2020-2024)
Table C.5: (continued) Transmission System Voltage Profile at Minimum Demand (2020-2024)
Busbar Voltage at Minimum Demand (per unit)
Location
2020 2021 2022 2023 2024
MIS Area
33 kV Busbars
Rustaq 1.01 1.00 1.00 1.01 1.00
SIA 1.01 1.00 1.01 1.01 1.01
Saham 1.00 1.00 1.00 1.00 1.00
Samad 1.01 1.00 1.01 1.01 1.01
Tx (1&2) 1.01 1.01 1.00 1.00 1.00
Seeb M ain
Tx (3&4) 1.00 1.00 1.00 1.00 1.00
Shinas 1.00 1.00 1.00 1.00 1.01
Sinaw 1.00 1.00 1.00 1.00 1.00
Tx (1&2) 1.00 1.00 1.00 1.00 1.00
Sohar Free Zone
Tx (3&4) 1.00 1.01 1.00 1.00 1.00
Tx (1&2) 1.00 1.00 1.00 1.00 1.00
Sohar
Tx (3&4) 1.00 1.00 1.00 1.00 1.00
Sumail Industrial 1.00 1.00 1.00 1.01
125M VA 1.00 1.00 1.00 1.00 1.00
Sumail
63M VA 1.00 1.00 1.00 1.00 1.00
Sur 1.00 1.00 1.00 1.00 1.00
Suwaiq 1.00 1.00 1.00 1.00 1.00
Tx (1&2) 1.00 1.00 1.01 1.00 1.01
Uwaynat
Tx (3&4) 1.00 1.00 1.00 1.00 1.00
Wadi Adai 1.01 1.00 1.00 1.00 1.00
Wadi Bani Auwf 1.00 1.00 1.00
Tx (1&2) 1.01 1.00 1.01 1.00 1.00
Wadi Kabair
Tx (3&4) 1.01 1.00 1.01 1.00 1.00
Wadi Sa'a 1.01 1.00 1.01 1.01 1.01
Yanqul 1.00 1.01 1.00 1.01
Yitti 1.00 1.01 1.01 1.01 1.00
11 kV Busbars
Daghmar 1.00 0.99 0.99 0.99 1.00
Dhofar Area
132 kV Busbars
Al Qarm 1.00 1.00 1.00 1.00 1.00
Ashoor 1.00 1.00 1.01 1.00 1.00
Ittin 1.00 1.00 1.00 1.00 1.00
M irbat 1.01 1.00 1.00
NPS 1.00 1.00 1.00 1.00 1.00
Page | 189
Five-Year Annual Transmission Capability Statement (2020-2024)
Table C.5: (continued) Transmission System Voltage Profile at Minimum Demand (2020-2024)
Busbar Voltage at Minimum Demand (per unit)
Location
2020 2021 2022 2023 2024
Dhofar Area
132 kV Busbars
Raysut 1.00 1.00 1.00 1.00 1.00
Saih Al Khairat 1.00 1.00
Salalah IPP 1.00 1.00 1.00 1.00 1.00
Shaha'aon 1.00 1.00 1.00 1.00 1.00
S’aadah 1.00 1.00 1.00 1.00 1.00
Thumrait 1.00 1.00 1.00 1.00 1.00
Wind Farm 1.01 1.01 1.02 1.01 1.01
33 kV Busbars
Al Qarm 1.00 1.01 1.00 1.00 1.00
Ashoor 1.00 1.00 1.00 1.00 1.00
Ittin 1.00 1.00 1.00 1.00 1.00
M irbat 1.01 1.00 1.00
NPS 1.00 1.00 1.00 1.00 1.01
Raysut 1.00 1.00 1.00 1.00 1.00
TX-1&2 1.00 0.99 1.00 1.00 1.00
S’aadah
TX-3&4 1.00 1.00 1.00 1.00 1.00
Saih Al Khairat 1.01 1.01
Salalah IPP 0.99 0.99 1.00 1.00 1.00
Shaha'aon 1.00 1.00 1.00 1.00 1.01
Thumrait 1.00 1.00 1.00 1.00 1.00
Page | 190
Five-Year Annual Transmission Capability Statement (2020-2024)
Table C.6: Estimation of Transmission Los ses and Generation Margin at Peak Demand (2020-2024)
Page | 191
Five-Year Annual Transmission Capability Statement (2020-2024)
Page | 192
Five-Year Annual Transmission Capability Statement (2020-2024)
Voltage S witchgear Fault Rating Max Three-Phase S hort Circuit Ik" (kA)
S ubstations
(kV) (kA) 2020 2021 2022 2023 2024
MIS Area
220 kV Busbars
Sohar Free Zone 220 50 35.20 35.56 34.57 34.36 34.65
Sohar-1 PS 220 40 30.01 30.14 22.95 22.87 23.01
Sohar-2 PS 220 50 28.68 28.89 28.31 28.19 28.36
Sur 220 50 26.04 26.05 25.30 25.37 25.42
Sur PS 220 50 38.97 39.04 38.04 38.18 38.38
132 kV Busbars
A'salam 132 31.5 18.63 20.74 21.03 20.39 20.40
Adam 132 40 6.12 6.07 6.11 6.10 5.40
Airport Height 132 31.5 13.42 14.43 21.13 18.52 18.70
Al Falaj 132 31.5 16.93 17.96 21.42 21.29 21.28
Al Filaj 132 31.5 20.63 25.30 25.94 24.73 24.51
Al Hamriyah 132 40 17.61 18.70 22.11 21.98 21.51
Al Hayl 132 31.5 5.20 4.94 4.94 4.93 4.93
Al Jawabi 132 40 4.57
Al Jefnen 132 40 23.83 24.42
Al Kamil 132 31.5 16.05 15.66 10.25 10.25 9.82
Amerat 132 40 14.63 15.28 16.25 16.20 16.32
Ayjah 132 40 8.86 8.85 8.62 8.62 8.60
Bahla 132 31.5 6.88 6.80 6.86 6.84 6.89
Barka M ain 132 31.5 19.86 23.38 23.84 22.89 22.78
Bedyah 132 40 16.57 15.52 13.76 13.77 12.60
Birkat Al M ouz 132 40 15.11 14.51 14.99 14.84 13.93
Bousher 132 31.5 17.66 18.88 21.39 21.26 21.19
Bureimi 132 31.5 11.09 11.13 11.08 11.07 14.00
Bureimi Industrial 132 40 11.32 11.37 11.32 11.30 14.51
Daghmar 132 40 6.58 6.67 6.77 6.77 6.80
Dank 132 31.5 9.69 9.70 9.69 9.68 9.66
Dil Abdusalam (DAS) 132 40 6.91 16.53 16.45 14.78 16.90
Dreez 132 40 9.13 9.15 9.14 9.13 9.10
Duqm 132 40 2.63 2.63
Duqm Wind Farm 132 40 2.15
Ghala 132 40 13.08 14.04 18.50 18.09 18.27
Page | 193
Five-Year Annual Transmission Capability Statement (2020-2024)
Page | 194
Five-Year Annual Transmission Capability Statement (2020-2024)
Voltage S witchgear Fault Rating Max Three-Phase S hort Circuit Ik" (kA)
S ubstations
(kV) (kA) 2020 2021 2022 2023 2024
MIS Area
132 kV Busbars
New Rustaq 132 40 30.03
Nahadah (PDO) 132 31.5 2.28 2.28 2.28 15.00 15.01
Nizwa 132 31.5 14.61 14.22 14.53 14.42 14.60
Qabel 132 31.5 20.75 19.40 19.02 19.05 17.28
Quriyat 132 31.5 6.86 6.97 7.08 7.07 7.11
Qurum 132 31.5 16.65 17.67 20.29 20.18 16.84
Rusail 132 31.5 21.94 21.86 20.32
Rusail Industrial 132 31.5 21.91 21.84 20.33 23.25 23.64
Rustaq 132 31.5 6.44 9.95 12.09 11.41 29.14
SIA 132 31.5 20.70 20.74 18.47 18.44 18.49
SIS 132 31.5 21.55 25.09 24.60 24.05 24.79
Saham 132 31.5 11.64 17.03 16.85 16.13 17.06
Samad 132 40 6.42 3.83 6.31 6.30 3.79
Seeb M ain-1 132 31.5 18.91 12.83 18.95 15.95
Seeb M ain-2 132 31.5 17.43 19.25 19.50 18.96
Seeb M ain 132 31.5 20.81
Shinas 132 31.5 15.34 15.46 15.34 15.30 15.35
Sinaw 132 40 10.80 6.71 10.62 10.56 6.59
Sohar 132 31.5 16.17 16.96 16.78 16.64 16.82
Sohar Free Zone 132 40 22.42 22.67 22.41 22.33 22.43
Sohar Refinery 132 31.5 20.28 20.31 18.14 18.11 18.16
Sumail 132 31.5 11.75 11.55 11.36 11.46 11.13
Sumail Industrial 132 40 12.68 12.54 12.16 12.55 12.37
Sur 132 31.5 18.78 18.74 17.70 17.72 17.63
Sur-2 132 40 18.79 18.76 17.71 17.73 17.65
Suwaiq 132 40 10.26 17.76 18.18 14.59 20.90
Swaihat(PDO) 132 40 3.77 3.77
Uwaynat 132 40 17.22 18.71 18.46 18.22 18.53
Wadi Adai 132 31.5 17.35 18.45 22.36 22.22 22.41
Wadi Al Jazzi 132 31.5 20.37 20.82 20.59 20.49 20.62
Wadi Bani Auwf 132 40 6.84 10.47 10.07 15.71
Wadi Kabair 132 40 16.73 17.72 20.83 20.71 20.41
Wadi Sa'a 132 31.5 12.62 12.66 12.61 12.59 12.59
Waste to Energy Plant 132 40 12.92
Yanqul 132 40 5.94 5.93 5.93 5.92
Yitti 132 31.5 8.98 9.17 9.36 9.35 9.41
Page | 195
Five-Year Annual Transmission Capability Statement (2020-2024)
Voltage S witchgear Fault Rating Max Three-Phase S hort Circuit Ik" (kA)
S ubstations
(kV) (kA) 2020 2021 2022 2023 2024
MIS Area
33 kV Busbars
Tx (1&2) 33 25 20.85 21.46 21.54 21.37 21.37
A'salam
Tx (3&4) 33 25 20.85 21.46 21.54 21.37 21.37
Adam 33 25 13.31 13.24 13.29 13.28 12.40
Tx (1&2) 33 25 18.38 18.82 20.97 20.26 20.32
Airport Height
Tx (3&4) 33 25 18.38 18.82 20.97 20.26 20.32
Al Falaj 33 25 18.97 19.28 20.15 20.13 20.12
Al Hayl 33 25 8.15 7.99 7.98 7.98 7.98
Al Jawabi 33 25 11.26
Tx (1&2) 33 25 18.48 18.73 19.08 19.06 19.10
Amerat
Tx (3&4) 33 25 18.48 18.73 19.08 19.06 19.10
Ayjah 33 25 15.76 15.76 15.56 15.57 15.55
Bahla 33 25 13.93 13.84 13.91 13.89 13.93
Tx (3) 33 25 12.28 12.57
Barka M ain
Tx (1&2) 33 25 21.70 22.63 22.73 22.51 22.48
Barka-3 PS 33 25 21.20 21.58 21.63 21.60 21.66
Bedyah 33 25 20.02 19.61 18.86 18.86 18.28
Birkat Al M ouz 33 25 19.18 18.93 19.13 19.07 18.67
Blue City 33 31.5 26.70 27.01 27.07 26.91 27.32
Tx (1&2) 33 25 20.67 21.07 21.79 21.75 21.74
Bousher
Tx (3&4) 33 25 19.83 20.20 20.86 20.82 20.81
Bureimi 33 25 17.20 17.22 17.19 17.18 18.67
Page | 196
Five-Year Annual Transmission Capability Statement (2020-2024)
Page | 197
Five-Year Annual Transmission Capability Statement (2020-2024)
Voltage S witchgear Fault Rating Max Three-Phase S hort Circuit Ik" (kA)
S ubstations
(kV) (kA) 2020 2021 2022 2023 2024
MIS Area
33 kV Busbars
New Ghubrah 33 25 20.73 21.14 21.86 21.82 21.80
New Izki 33 25 20.71 20.05 20.70 20.61 19.77
Nizwa 33 25 18.97 18.81 18.94 18.89 18.96
Quriyat 33 25 13.90 14.00 14.11 14.11 14.14
Qurum 33 25 20.31 20.68 21.49 21.46 20.39
Tx (1&2) 33 25 21.42 21.40 21.02 21.72 21.81
Rusail Industrial
Tx (3&4) 33 25 21.42 21.40 21.02 21.72 21.81
Tx (1&2) 33 25 13.64 16.77 22.77 22.15 23.17
Rustaq
Tx 3 33 25 9.29 10.65 22.77 22.15 12.91
SIA 33 25 20.86 20.87 20.25 20.24 20.26
Saham 33 25 17.48 19.81 19.75 19.50 19.82
Samad 33 25 9.51 7.61 9.45 9.44 7.57
Tx (1&2) 33 25 20.61 21.21 21.28 21.11 21.64
Seeb M ain
Tx (3&4) 33 25 21.21 18.72 21.22 20.16 21.76
Shinas 33 25 19.39 19.44 19.39 19.38 19.40
Sinaw 33 25 17.13 13.80 17.02 16.98 13.66
Tx (1&2) 33 25 22.17 22.23 22.16 22.14 22.17
Sohar Free Zone
Tx (3&4) 33 25 22.17 22.23 22.16 22.14 22.17
Tx (1&2) 33 25 19.87 20.16 20.09 20.04 20.11
Sohar
Tx (3&4) 33 25 19.48 19.76 19.70 19.65 19.72
Sumail Industrial 33 25 18.64 18.57 18.36 18.57 18.47
125M VA 33 25 17.97 17.86 17.74 17.80 17.60
Sumail
63M VA 33 25 12.24 12.19 12.14 12.16 12.07
Sur 33 25 20.74 20.73 20.40 20.41 20.38
Suwaiq 33 25 16.76 20.26 20.40 19.08 21.17
Tx (1&2) 33 25 20.42 20.92 20.84 20.76 20.86
Uwaynat
Tx (3&4) 33 25 20.56 21.06 20.98 20.90 21.00
Wadi Adai 33 25 20.19 20.55 21.60 21.57 21.61
Wadi Bani Auwf 33 25 14.20 17.31 17.03 20.07
Tx (1&2) 33 25 20.34 20.69 21.64 21.61 21.53
Wadi Kabair
Tx (3&4) 33 25 19.64 19.96 20.84 20.81 20.74
Wadi Sa'a 33 25 12.47 12.48 12.47 12.47 12.47
Yanqul 33 25 13.18 13.17 13.17 13.16
Yitti 33 25 16.12 16.27 16.42 16.41 16.46
Page | 198
Five-Year Annual Transmission Capability Statement (2020-2024)
Voltage S witchgear Fault Rating Max Three-Phase S hort Circuit Ik" (kA)
S ubstations
(kV) (kA) 2020 2021 2022 2023 2024
Dhofar Area
132kV Busbars
Al Qarm 132 31.5 12.82 14.16 14.70 15.18 15.63
Ashoor 132 31.5 16.17 18.48 19.06 19.57 20.05
Ittin 132 31.5 12.98 14.37 15.17 15.90 16.62
M irbat 132 31.5 9.22 9.21 9.33 9.44
NPS 132 31.5 14.70 16.93 18.79 20.66 22.63
Saih Al Khairat 132 40 3.47 3.49
Raysut 132 31.5 14.98 17.31 19.17 21.02 23.03
Salalah IPP 132 40 14.98 17.31 19.17 21.02 23.03
Shaha'aon 132 31.5 12.23 13.61 14.50 15.32 16.14
S’aadah 132 40 11.46 12.60 13.19 13.71 14.22
Thumrait 132 31.5 6.68 6.93 7.05 7.17 7.27
Wind Farm 132 31.5 4.99 5.04 5.05 5.11 5.12
33kV Busbars
Al Qarm 33 25 10.49 10.74 10.83 10.90 10.97
Ashoor 33 25 16.39 17.04 17.18 17.30 17.41
Ittin 33 25 15.34 15.88 16.16 16.40 16.62
M irbat 33 25 11.05 9.28 9.32 9.35
NPS 33 25 9.60 9.85 10.02 10.17 10.30
Saih Al Khairat 33 25 7.83 7.86
Raysut 33 25 18.98 19.82 20.39 20.88 21.34
Salalah-IPP 33 25 17.76 20.40 21.00 21.52 22.00
Shaha'aon 33 25 17.71 16.04 16.39 16.69 16.97
TX-1&2 33 25 19.51 18.40 18.71 18.97 19.20
S'aadah
TX-3&4 33 25 15.43 18.35 18.65 18.91 19.15
Thumrait 33 25 5.83 8.52 8.58 9.43 9.48
Page | 199
Five-Year Annual Transmission Capability Statement (2020-2024)
Voltage S witchgear Fault Rating Max S ingle-Phase Short Circuit Ik" (kA)
S ubstations
(kV) (kA) 2020 2021 2022 2023 2024
MIS Area
400 kV Busbars
Al Jefnen 400 63 13.94 17.91
Duqm 400 63 1.33 1.33
Ibri IPP 400 63 23.92 24.58 24.40 24.45 27.14
Jahloot 400 63 10.27 10.31 10.32 10.35 10.45
M ahout 400 63 1.33 1.33
M anah Solar 400 63 11.35 11.82 12.42
M isfah 400 63 5.81 11.00 11.34 14.45 17.96
New Izki 400 63 10.04 13.21 13.00 13.71 14.82
New Rustaq 400 63 14.61
Nahadah (PDO) 400 63 9.81 9.95
Qabel 400 63 11.64 12.40 12.14 12.31 12.47
SIS 400 63 18.56 18.67 18.37 18.32 18.40
Sohar Free Zone 400 63 27.21 27.34 26.91 26.83 26.95
Sohar-3 IPP 400 63 27.68 27.80 27.39 27.31 27.43
Sur PS 400 63 18.88 18.96 18.59 18.69 18.88
Suwaihat 400 63 1.33 1.33
220 kV Busbars
Airport Height 220 40 21.16 24.63 27.17 26.74 26.98
Al Filaj 220 40 31.54 33.85 34.73 33.65 32.92
Al Hamriyah 220 50 12.81 13.23 13.79 13.75 13.79
Al Oha(UAE) 220 50 22.66 22.68 22.62 22.61 22.64
Barka PS 220 40 34.90 37.16 37.92 36.73 35.35
Barka-3 PS 220 50 16.17 17.25 17.41 17.35 17.53
Blue City 220 40 15.97 16.56 16.66 16.42 17.09
Ibri 220 50 13.76 13.83 13.79 13.78 13.84
Ibri IPP 220 50 21.50 21.67 21.58 21.58 21.96
Ibri Solar 220 50 18.85 18.78 18.78 19.06
Jahloot 220 50 17.64 18.26 18.62 18.61 18.88
KIS 220 50 14.02 13.96 13.76 14.34
M IS 220 40 13.13 15.22 15.30 15.05 16.24
M SQ 220 40 15.05 17.05 17.56 17.30 17.52
M ahadha 220 40 24.49 24.59 24.32 24.27 24.74
M isfah 220 50 19.46 25.32 28.10 29.50 30.98
M obella 220 50 25.71 27.98 29.13 28.26 27.90
New Izki 220 50 12.17 13.03 13.14 13.20 15.89
Nizwa 220 50 9.94
SIA 220 40 33.17 33.27 24.75 24.68 24.79
Page | 200
Five-Year Annual Transmission Capability Statement (2020-2024)
Voltage S witchgear Fault Rating Max S ingle-Phase Short Circuit Ik" (kA)
S ubstations
(kV) (kA) 2020 2021 2022 2023 2024
MIS Area
220 kV Busbars
SIS 220 40 35.29 35.86 34.13 33.87 34.33
Sohar Free Zone 220 50 38.50 38.80 37.95 37.79 38.04
Sohar-1 PS 220 40 35.43 35.55 25.96 25.89 26.01
Sohar-2 PS 220 50 30.55 30.71 30.24 30.15 30.29
Sur 220 50 23.51 23.52 23.09 23.13 23.16
Sur PS 220 50 46.45 46.52 45.54 45.68 45.89
132 kV Busbars
A'salam 132 31.5 23.67 25.94 26.65 26.04 25.35
Adam 132 40 7.24 7.19 7.23 7.21 6.52
Airport Height 132 31.5 18.09 19.37 28.27 24.93 24.86
Al Falaj 132 31.5 22.01 23.19 27.07 26.91 26.84
Al Filaj 132 31.5 24.80 29.17 29.77 28.76 27.00
Al Hamriyah 132 40 22.74 23.98 27.74 27.57 26.89
Al Hayl 132 31.5 5.56 5.81 5.80 5.80 5.80
Al Jawabi 132 40 5.93
Al Jefnen 132 40 30.60 31.85
Al Kamil 132 31.5 17.55 17.24 9.49 9.50 9.33
Amerat 132 40 17.35 17.97 18.85 18.79 18.90
Ayjah 132 40 9.84 9.83 9.63 9.63 9.62
Bahla 132 31.5 7.97 7.90 7.96 7.94 8.02
Barka M ain 132 31.5 23.45 26.65 26.80 26.05 25.52
Bedyah 132 40 17.43 16.58 14.99 15.00 14.02
Birkat Al M ouz 132 40 16.78 16.27 16.69 16.56 15.89
Bousher 132 31.5 23.50 25.27 28.70 27.25 26.94
Bureimi 132 31.5 13.89 13.93 13.87 13.86 17.01
Bureimi Industrial 132 40 14.22 14.27 14.21 14.19 17.68
Daghmar 132 40 7.77 7.86 7.96 7.95 7.98
Dank 132 31.5 10.16 10.49 10.48 10.47 10.46
Dil Abdusalam (DAS) 132 40 8.49 16.92 16.86 15.65 17.17
Dreez 132 40 10.29 10.30 10.29 10.28 10.27
Duqm 132 40 3.67 3.67
Duqm Wind Farm 132 40 2.31
Ghala 132 40 17.65 18.82 24.64 24.37 24.33
Ghala Heights-1 132 40 21.92
Ghala Heights-2 132 40 16.77
Ghala Heights 132 40 23.54 26.63 22.77 22.76
Ibra 132 40 12.53 12.19 12.09 12.10 11.59
Ibri 132 31.5 19.04 19.09 19.06 19.04 18.98
Page | 201
Five-Year Annual Transmission Capability Statement (2020-2024)
Page | 202
Five-Year Annual Transmission Capability Statement (2020-2024)
Voltage S witchgear Fault Rating Max S ingle-Phase Short Circuit Ik" (kA)
S ubstations
(kV) (kA) 2020 2021 2022 2023 2024
MIS Area
132 kV Busbars
Quriyat 132 31.5 8.31 8.42 8.52 8.52 8.55
Qurum 132 31.5 20.15 21.19 23.69 23.49 18.59
Rusail 132 31.5 28.47 28.52 27.27
Rusail Industrial 132 31.5 28.44 28.49 27.29 30.11 31.12
Rustaq 132 31.5 8.11 12.09 14.12 13.51 30.87
SIA 132 31.5 24.47 24.50 21.65 21.62 21.66
SIS 132 31.5 23.62 26.34 25.93 25.52 26.07
Saham 132 31.5 13.04 17.11 16.98 16.49 17.12
Samad 132 40 7.01 4.68 6.92 6.91 4.65
Seeb M ain-1 132 31.5 24.31 17.00 25.29 21.05
Seeb M ain-2 132 31.5 22.07 24.02 24.62 24.09
Seeb M ain 132 31.5 27.34
Shinas 132 31.5 17.41 17.51 17.40 17.37 17.41
Sinaw 132 40 11.99 8.24 11.85 11.79 8.13
Sohar 132 31.5 18.79 19.50 19.33 19.21 19.36
Sohar Free Zone 132 40 28.36 28.62 28.33 28.24 28.36
Sohar Refinery 132 31.5 23.92 23.95 21.22 21.20 21.24
Sumail 132 31.5 13.66 13.48 13.37 13.46 13.17
Sumail Industrial 132 40 13.85 13.74 13.53 13.85 13.72
Sur 132 31.5 21.05 21.02 20.12 20.13 20.06
Sur-2 132 40 21.06 21.03 20.13 20.15 20.08
Suwaiq 132 40 12.59 19.93 20.28 16.91 22.42
Suwaihat(PDO) 132 40 4.49 4.49
Uwaynat 132 40 20.33 21.69 21.45 21.24 21.52
Wadi Adai 132 31.5 22.30 23.54 27.98 27.77 27.96
Wadi Al Jazzi 132 31.5 17.19 17.40 17.29 17.24 17.33
Wadi Bani Auwf 132 40 8.15 11.69 11.37 15.73
Wadi Kabair 132 40 21.58 22.70 26.10 25.96 25.56
Wadi Sa'a 132 31.5 11.95 11.98 11.95 11.94 11.97
Waste to Energy Plant 132 40 14.66
Yanqul 132 40 7.42 7.42 7.41 7.41
Yitti 132 31.5 10.10 10.26 10.42 10.41 10.46
Page | 203
Five-Year Annual Transmission Capability Statement (2020-2024)
Page | 204
Five-Year Annual Transmission Capability Statement (2020-2024)
Page | 208
Five-Year Annual Transmission Capability Statement (2020-2024)
Page | 212
Five-Year Annual Transmission Capability Statement (2020-2024)
Page | 214