You are on page 1of 215

Five-Year Annual

2020
Transmission
Capability Statement
(2020-2024)

As Approved by the Authority for Electricity Regulation, April 2020

Page | 0
Five-Year Annual Transmission Capability Statement (2020 - 2024)

Preface

This Transmission Capability Statement is provided by the Oman Electricity Transmission Company (OETC)
according to the Transmission and Dispatch Licence Condition number 27 and the Grid Code (Planning Code). The
Statement describes in detail the Main Interconnected System (MIS) and Dhofar Transmission System capability
over the coming five years 2020-2024. The Statement provides up-to-date transmission system data in order to
identify those parts of the system, which offer opportunities for future development of existing and potential users
of the system. In this Capability Statement, the results of load flow and short circuit analyses are presented based
on the planned system expansion reinforcement to meet the generation plan provided by Oman Power and Water
Procurement Company (OPWP) and the demand forecast provided by the Distribution Companies (MEDC, MJEC,
MZEC, DPC and RAEC). OETC grid model has been updated to include new projects schedule, demand forecast,
generation data and transmission system data. Thirty transmission projects at MIS and Dhofar System are planned
over the coming five-year period. Most of the projects designed to increase the transmission system capacity so that
it can meet future growth in demand, connect new generation and satisfy the security criteria.

The existing and planned development in the generation and transmission systems are described, including the
completion of projects in different voltage levels. The first 50 MW Wind Farm project in the Sultanate of Oman
commissioned in Dhofar transmission system in Q3 2019. Moreover, the transmission project of connecting the
first 500 MW Solar PV IPP in the Sultanate of Oman to the 220kV system at Ibri will be completed by Q4 2020.
In addition, transmission project of connecting 1000 MW Solar IPP in Manah is expected to be completed by Q2
2022. Each 500MW Solar plant at Manah will be connected to the transmission grid by Q2 2023 and Q2 2024.
Furthermore, a new generation connection to the Waste to Energy Plant (maximum capacity of 160MW) is
estimated to be completed by Q2 2024. Further, OPWP is proposing a 300MW of Wind plants to be connected to
the transmission system by Q2 2024. The proposed plants sites that considered by OETC and according to OPWP
sites selection are Jalan Bani Bu Ali and Duqm (maximum capacity of 100MW and 200MW respectively) to be
connected to the grid by Q2 2024. Moreover, RAEC has submitted two connection applications on 6th of January
2019 requesting for new grid stations at Mahout and Duqm areas. Further, PDO has submitted two connection
applications for Barik and Suwaihat sites on 12th of June 2019 requesting for 500MW export and import power at
each grid station. In addition, the new 400kV interconnection project will facilitate the connection to PDO system,
Duqm and Mahout Systems. Currently the project is in the design stage. The execution of the project will be in two
phases: the first phase will include constructing Suwaihat, Duqm and Mahout grid stations in order to displace the
diesel generation in Duqm and Mahout areas by Q2 2023. The second phase will be required for completing the
400kV OHL from Nahadah to Suwaihat with the construction of a new 400/132kV grid station at Barik area and
the expected completion date will be end of Q4 2024. Currently, OETC is carrying out a long term study (Master
Plan 2020-2040) to evaluate the future plan which includes transmission system reinforcements, connecting future
Renewable Energy Sources and future 400kV North – South Interconnector with Dhofar System. It is one of
OETC’s strategic planning concepts to introduce the 400kV system as a backbone to allow the power evacuation
from the centralized power plants and future Renewable Energy Resources. Major developments in the MIS include
the installation and operation of new 400kV transmission lines with associated new 400/132kV, 400/132/33kV and
400/33kV grid stations. In addition, the developments include the installation of 220kV and 132kV transmission
lines with associated new 220/132kV and 132/33kV grid stations at MIS and Dhofar system. OETC’s strategy is to
operate the 400kV system as a backbone, 220kV as a transmission system and 132kV as sub-transmission system.

Eng. Masoud Salam Al Reyami


Acting Chief Executive Officer
Oman Electricity Transmission Company
Page | 1
Five-Year Annual Transmission Capability Statement (2020 - 2024)

Contents

Preface 1
List of Figures 5
List of Tables 7
Document History and Status 8
Distribution of Copies 8
Glossary 9
1. Executive Summary 10
2. Introduction 24
2.1 Licence conditions, Codes and Standards 24
2.2 2020 System Development since the 2019-2023 Statement 24
2.3 Improvements in the preparation of the Statement 25
3. Technical requirements for compliance with the Grid Code and Licence 26
3.1 Security of Supply 28

4. OETC System Design and Planning Standards 29


4.1 Oman Electrical Standard OES 11 29
4.2 Oman Electrical Standard OES 25A and 25B 29
4.3 Oman Electrical Standard OES 27 29
4.4 Oman Electrical Standard OES 32 29
4.5 OETC Standard Specifications 29
4.6 Standard specification for 132/33kV Substations (OETC-AMP-O-AMT-M-041): 30
4.7 Standard specification for 220/132/33kV Substations (OETC-AMP-O-AMT-M-042): 30
4.8 Standard specification for 400/220/33kV Substations (OETC-AMP-O-AMT-M-043): 30
4.9 Standard specification for 400/132/33kV Substations (OETC-AMP-O-AMT-M-044): 30
4.10 Standard specification for 132kV Overhead Lines (OETC-AMP-O-AMT-M-001): 30
4.11 Standard specification for 220kV Overhead Lines (OETC-AMP-O-AMT-M-002): 30
4.12 Standard specification for 400kV Overhead Lines (OETC-AMP-O-AMT-M-003): 31
4.13 Standard specification for Underground Cable Circuits above 33kV up to 150kV (OETC-AMP-O-AMT-
M-022): 31
4.14 Standard specification for Underground Cable Circuits above 150kV up to 400kV (OETC-AMP-O-AMT-
M-021): 31

5. OETC Transmission System 32


5.1 Existing Transmission System 32
5.2 Future System Development Projects 37
5.3 Projects completed to meet the 2020 peak demand 37
Page | 2
Five-Year Annual Transmission Capability Statement (2020 - 2024)

5.4 Projects expected to be completed to meet the 2021 peak demand 37


5.5 Projects expected to be completed to meet the 2022 peak demand 38
5.6 Projects expected to be completed in time to meet the 2023 peak demand 38
5.7 Projects expected to be completed in time to meet the 2024 peak demand 39
5.8 Summary 39

6. Existing and Planned Developments in Generation 50


6.1 Existing Generation 50
6.1.1 Existing generation of MIS 50
6.1.2 Existing generation of Dhofar 52
6.2 Planned Retirements of Existing Plant 57
6.3 Planned Future Generation (2020-2024) 57
6.3.1 Planned Future Generation at MIS 57
6.3.2 Planned Future Generation at Dhofar 58
6.4 Non-Contracted Generating Capacity 58
6.5 Interconnections 60
6.5.1 Interconnection with the GCCIA Grid through UAE (Transco Abu Dhabi) 60
6.5.2 Interconnection with PDO 60
6.5.3 400kV North-South Interconnection 60
6.6 Economic Dispatch 61
6.7 Spinning Reserve 61
7. Demand Forecast and Generation Availability 62
7.1 System Demand 62
7.2 Demand Forecast 66
7.3 System Maximum Net Demand Forecast and Generation Availability 70

8. Transmission System Performance 77


8.1 Power Flow and Voltage Profiles 77
8.1.1 Power Flow and Voltage Profiles of MITS & DTS 77
8.2 Fault levels for MIS and Dhofar System 91
9. Development Opportunities 92
9.1 Review of the Generation Versus Load Balance on an Area Basis 92
9.2 Available grid station capacity 105
9.3 Potential Generation Connections 113

10. Non-compliances 116

Page | 3
Five-Year Annual Transmission Capability Statement (2020 - 2024)

Appendix A: Review of Future Developments 121


A.1 Summary of Projects to be completed between 2020-2024 Peak Demands 121
A.2 Projects expected to be completed to meet the 2020 peak demand 121
A.3 Projects expected to be completed to meet the 2021 peak demand 122
A.4 Projects expected to be completed to meet the 2022 peak demand 124
A.5 Projects expected to be completed to meet the 2023 peak demand 124
A.6 Projects expected to be completed to meet the 2024 peak demand 125
Appendix B: Transmission System Data 127
B.1 Substations Loads and Capacitor data 127
B.2 Overhead Line Circuit Capacities and Parameters 127
B.3 Transformer data 127

Appendix C: Power System Studies 157


C.1 Summary of Load Flow Study results 157
C.2 Summary of Fault Level Study results 157
C.3 Diagrams of the model for the Load Flow Study Results 157

Page | 4
Five-Year Annual Transmission Capability Statement (2020 - 2024)

List of Figures
Figure 1: Summary of Planned Developments on OETC Transmission Systems (2020- 2024) 23
Figure 2: Number of Grid Stations at MITS by end of 2019 32
Figure 3: OHL & UGC Lengths (circuit/km) at MITS by end of 2019 33
Figure 4: Transformers Capacity (MVA) at MITS by end of 2019 33
Figure 5: Shunt Reactors (MVAr) at MITS by end of 2019 33
Figure 6: OETC transmission system at Dhofar by end of 2019 34
Figure 7: The existing private customers with 220kV Connections 35
Figure 8: The existing private customers with 132kV Connections 36
Figure 9: The Future private customers will be connected to OETC System 36
Figure 10: Existing MITS in Peak 2020 40
Figure 11: MITS expected development in Peak 2021 41
Figure 12: MITS expected development in Peak 2022 42
Figure 13: MITS expected development in Peak 2023 43
Figure 14: MITS expected development in Peak 2024 44
Figure 15: Dhofar existing transmission system in Peak 2020 45
Figure 16: Dhofar expected transmission system in Peak 2021 46
Figure 17: Dhofar expected transmission system in Peak 2022 47
Figure 18: Dhofar expected transmission system in Peak 2023 48
Figure 19: Dhofar expected transmission system in Peak 2024 49
Figure 20: Generation Percentage 2020 for both MIS & Dhofar 56
Figure 21: Generation Percentage 2024 for both MIS & Dhofar 56
Figure 22: MIS Load on 2019 Peak Day 62
Figure 23: Dhofar System Load on 2019 Peak Day 63
Figure 24: MIS Load on 2019 Minimum Load Day 65
Figure 25: Dhofar System Load on 2019 Minimum Load Day 65
Figure 26: Number of out-of-firm 132/33kV grid stations of MIS during 2020-2024 82
Figure 27: MIS Peak & off Peak Voltage profile at 400kV, 220kV, and 132kV and 33kV busbars in 2020 84
Figure 28: MIS Peak & off Peak Voltage profile at 400kV, 220kV, 132kV and 33kV busbars in 2024 85
Figure 29: DTS Peak & off Peak Voltage profile at 132kV and 33kV busbars in 2020 86
Figure 30: DTS Peak & off Peak Voltage profile at 132kV and 33kV busbars in 2024 87
Figure 31: Transmission power losses at peak demand of MIS of the years 2020-2024 88
Figure 32: Transmission power losses at peak demand of DTS of the years 2020-2024 89
Figure 33: Peak load growth of MITS System over the period 2020-2024 90
Figure 34: Peak load growth of Dhofar System over the period 2020-2024 90
Figure 35: Future Oman Electrical systems 93
Figure 36: Generation and load balance in Muscat area 99
Page | 5
Five-Year Annual Transmission Capability Statement (2020 - 2024)

Figure 37: Generation and load balance in Al Batinah South area 100
Figure 38: Generation and load balance in Al Batinah North area 101
Figure 39: Generation and load balance in Al Buraimi area 101
Figure 40: Generation and load balance in Al Dhahirah area 102
Figure 41: Generation and load balance in Al Dakhiliah area 103
Figure 42: Generation and load balance in Al Sharqiyah area 103
Figure 43: Generation and load balance in Al Wusta area 104
Figure 44: Generation and load balance in Dhofar area 105
Figure 45: Used and available MVA in Muscat area at 2024 peak demand 108
Figure 46: (Continued) Used and available MVA in Muscat area at 2024 peak demand 108
Figure 47: (Continued) Used and available MVA in Muscat area at 2024 peak demand 109
Figure 48: Used and available MVA in Al Batinah South area at 2024 peak demand 109
Figure 49: Used and available MVA in Al Batinah North area at 2024 peak demand 110
Figure 50: Used and available MVA in Al Buraimi and Al Dhahirah areas at 2024 peak demand 110
Figure 51: Used and available MVA in Al Dakhiliah area at 2024 peak demand 111
Figure 52: Used and available MVA in Al Sharqiyah area at 2024 peak demand 111
Figure 53: Used and available MVA in Al Wusta area at 2024 peak demand 112
Figure 54: Used and available MVA in Dhofar area at 2024 peak demand 112
Figure C. 1: MIS 2020 Max. Load Flow Condition 205
Figure C. 2: MIS 2021Max. Load Flow Condition 206
Figure C. 3: MIS 2022 Max. Load Flow Condition 207
Figure C. 4: MIS 2023 Max. Load Flow Condition 208
Figure C. 5: MIS 2024 Max. Load Flow Condition 209
Figure C. 6: Dhofar System 2020 Max. Load Flow Condition 210
Figure C. 7: Dhofar System 2021 Max. Load Flow Condition 211
Figure C. 8: Dhofar System 2022 Max. Load Flow Condition 212
Figure C. 9: Dhofar System 2023 Max. Load Flow Condition 213
Figure C. 10: Dhofar System 2024 Max. Load Flow Condition 214

Page | 6
Five-Year Annual Transmission Capability Statement (2020 - 2024)

List of Tables
Table 1: Summary of Planned Developments on OETC Transmission System (2020 - 2024) 14
Table 2: OETC Licensed Transmission System, System Parameter Values 27
Table 3: Demand Connections – Demand Class Specification 28
Table 4: Existing and committed future generating capacity 53
Table 5: New Contracted and Planned Generating Capacity 58
Table 6: Non-Contracted Generating Capacity 59
Table 7: Centrally Dispatchable and Non-Dispatchable Generating Capacity on OETC Transmission Systems 59
Table 8: Historic Growth in Peak Demand and Transmission Losses (2003 – 2019) 63
Table 9: Expected Load Transfers between Grid Supply Points (2020-2024) 67
Table 10: OETC Transmission System Net Demand Forecast by Grid Station 70
Table 11: Comparison of Net Demand Forecast with Available Generating Capacity including Planned
Retirements 75
Table 12: Comparison of Net Demand Forecast with Available Generating Capacity and Non-Contracted
Generation in service 76
Table 13: Summary of Connected Generation Used in Load Flow Studies of Maximum Demand 78
Table 14: Summary of Connected Generation Used in Load Flow Studies of Minimum Demand 79
Table 15: Estimated Power Surplus and Power Deficit on an Area Basis (2020-2024) 94
Table 16: Available Grid Station Capacity of more than 10 MVA in 2024 106
Table 17: Potential Generation Connections for 2024 115
Table 18: Expected Over headlines/Cable, which will not comply with Transmission Security Standard (First
Outage) at Peak Demand in 2020 118
Table 19: Expected Grid stations 132/33kV, which will not comply with Transmission Security Standard (First
Outage) at Peak Demand in 2020 119
Table 20: Expected Grid stations 132/33kV, which will not comply with Transmission Security Standard at
Maintenance Period in 2020. 120
Table B. 1: Load and Capacitor Data for Grid Station (2020-2024) 128
Table B. 2: 2020 Branch Data Listing 136
Table B. 3: Progressive Change to Branch Circuit Data for 2020-2024 141
Table B. 4: Grid Station Transformers Data at 2020 Peak 145
Table B. 5: Grid Station Transformers Data from 2020 to 2024 154
Table C. 1: Transformers Loading (%) at Grid Stations (2020-2024) 158
Table C. 2: Available Capacity at Grid Stations (2020-2024) for Connection of New Demand 163
Table C. 3: Overhead Line and Cable Circuit Loadings (%) at Peak Demand (2020-2024) 168
Table C. 4: Transmission System Voltage Profile at Peak Demand (2020-2024) 175
Table C. 5: Transmission System Voltage Profile at Minimum Demand (2020-2024) 183
Table C. 6: Estimation of Transmission Losses and Generation Margin at Peak Demand (2020-2024) 191
Table C. 7: Maximum 3-Phase Short Circuit Fault Levels 192
Table C. 8: Maximum 1-Phase Short Circuit Fault Levels 200
Page | 7
Five-Year Annual Transmission Capability Statement (2020 - 2024)

Document History and Status

Re vision Date issued Prepared by Approved by Date approved Revision type

Network Planning Network Planning


D.0 04/02/2020 13/02/2020 First draft
Department Department

Network Planning Asset Management &


D.1 17/02/2020 Department Planning Department 20/02/2020 Second draft

Network Planning
D.2 20/02/2020 Department CEO 29/02/2020 Final draft

Network Planning
D.3 05/03/2020 AER 07/04/2020 Final draft
Department

Distribution of Copies

Re vision Copy no Q uantity Date Issued to


V.0 1 1 29/02/2020 CEO

Printed: 09/04/2020

Last saved: 09/04/2020 03:08 P.M

Author: Network Planning Department

Name of organisation: Oman Electricity Transmission Company S.A.O.C

Name of document: Five-Year Annual T ransmission Capability Statement (2020- 2024)

Document ve rsion: V.0 As Approved by the Authority for Electricity Regulation on April 2020

Page | 8
Five-Year Annual Transmission Capability Statement (2020 - 2024)

Glossary
AAAC All Aluminium Alloy Conductor
AER Authority for Electricity Regulation, Oman
AIS Air Insulated Switchgear
CEO Chief Executive Officer
DISCOs Distribution Companies
DTS Dhofar Transmission System
DPC Dhofar Power Company (SAOC)
GCCIA Gulf Cooperation Council Interconnection Authority
GIS Gas Insulated Switchgear
GS Grid Station
GT Gas Turbine
HV High Voltage
IPP Independent Power Producer
IWP Independent Water Producer
IWPP Independent Water and Power Producer
kV kilovolt
LILO Line In Line Out
LV Low Voltage
MEDC Muscat Electricity Distribution Company (SAOC)
MV Medium Voltage
MIS Main Interconnected System
MITS Main Interconnected Transmission System
MJEC Majan Electricity Company (SAOC)
MVA Mega Volt Ampere
MVAr Mega Volt Ampere reactive
MW Megawatt(s)
MWh Megawatt hour(s) = (1,000) kWh
MZEC Mazoon Electricity Company (SAOC)
NPV Net Present Value
OES Oman Electrical Standard
OETC Oman Electricity Transmission Company (SAOC)
OHL Overhead Line
OPWP Oman Power and Water Procurement Company (SAOC)
PAW Public Authority for Water
PDO Petroleum Development Oman (LLC)
PS Power Station
PV Photovoltaic
RAEC Rural Areas Electricity Company (SAOC)
SCADA Supervisory Control and Data Acquisition
SF6 Sulfur Hexafluoride
ST Steam Turbine
SVC Static Var Compensator
TSS Transmission Security Standard
UAE United Arab Emirates
UGC Underground Cable
WTE Waste To Energy

Page | 9
Five-Year Annual Transmission Capability Statement (2020 - 2024)

1. Executive Summary

This Capability Statement presents the Oman Electricity Transmission Company’s development plans for the
400kV, 220kV and 132kV transmission systems for the years 2020 to 2024 in both Main Interconnected
Transmission System (MITS) and Dhofar Transmission System (DTS). DTS has been transferred to Oman
Electricity Transmission Company (OETC) on 1st of January 2014. This document describes the development plans
for both MITS and DTS.

The Statement includes data for the generators, loads, overhead lines, cables, transformers, reactive power
compensators and capacitor banks used in the development of transmission system models. In addition, the
Statement includes the demand and generation forecast. The power system studies undertaken by OETC’s
DIgSILENT Power Factory software, version 17.0.4, in preparation of this Capability Statement. The Statement
also includes the results of power system analysis of the transmission system that defines system performance when
operating under the extreme system peak (summer season) and system off peak (winter season) in each of the five
years. From this analysis, assessment has been made of the opportunities for the connection of new generation, new
demand and reinforcement on the system.

Table 1 lists the schedule for committed and planned system development projects on the 400kV, 220kV and 132kV
transmission systems, although it should be noted that not all of the planned projects listed have full authorisation
at this time. The 400kV system development in MITS, includes the installation of 400kV systems to the existing
220/132kV and 132/33kV grid stations. Furthermore, one 400/132/33kV, five 400/132kV and one 400/33kV grid
station will be installed during the period of this Capability Statement. In addition, two 220/132kV and seven
132/33kV grid stations in MITS will be energized during the period of this Capability Statement.The total number
of both MITS and DTS of 400kV, 220kV and 132kV grid stations will also increase from ninety nine by the end of
2020 to hundred and fifteen by the peak of 2024.

It is one of OETC’s strategic planning concepts to introduce the 400kV system as a backbone to allow the power
evacuation from the centralized power plants towards the demand. Furthermore, OETC has installed 220kV double
circuit lines around northern Oman to supply and support the 132kV system. In 2010, the 220kV connections
between Sohar Interconnector Station (SIS) and Mahadha (Al-Wasit) were completed to support linking Oman
(OETC) network with the GCCIA Grid through UAE (Transco Abu Dhabi) network. In addition, Khaborah
Interconnection Station (KIS) is expected to be completed by August 2020 to increase the system reliability within
Al Batinah North region. Eventually, Nizwa 220/132kV grid station will be connected via 220kV OHL to New Izki
grid station by peak 2024. The purpose of this project is to maintain transmission security standard requirements
and to increase the system reliability within Al Dhakilyah region.

OETC has introduced the first 400kV system including 400kV connection between Jahloot grid station and Sur
power station and line between Sur power station and New Izki grid stations in 2016. In 2018, OETC introduced a
new 400kV OHL from Ibri IPP to New Izki grid stations and a new 400/220kV grid station at Ibri. Furthermore,
400kV transmission lines have been installed in 2019, between Sohar Free Zone – Shinas (operated as 132kV) and
Sohar Free Zone-SIS, Sohar Free Zone-Mahadha (operated as 220kV). In the same year, 400kV connections of
Sohar-3 IPP and Sohar Free Zone 400kV grid station were energised. Moreover, a LILO connection from Sur-New
Izki 400kV line at Qabel area with introduction of a new 400/132kV grid station. Furthermore, New Izki-Misfah
400kV OHL is expected to be completed by peak 2021. In peak 2022, the connection of Manah Solar IPP through
LILO Ibri IPP – New Izki 400kV OHL will be completed. Construction of Al Jefnen 400/132kV and New Rustaq

Page | 10
Five-Year Annual Transmission Capability Statement (2020 - 2024)

400/132kV grid stations will be completed by peak 2023 and 2024 respectively. In addition, the North – South
interconnection project (part 1 until Duqm and Mahout) will include new 400kV grid stations at Suwaihat, Mahout
and Duqm area with associated lines for phase-1. Whereas, phase 2 will include construction of Barik grid station
and the connection of it to Nahadah and Suwaihat 400kV grid stations and this phase is expected to be completed
by December 2024. Accordingly, the MITS will have sixteen 400kV grid stations at Sur, Jahloot, New Izki, Misfah,
Ibri IPP, Sohar III IPP, Sohar Free Zone, SIS, Qabel, Al Jefnen, Manah Solar IPP, New Rustaq, Suwaihat, Nahadah,
Mahout and Duqm by peak 2024. The total installed capacity of 400kV grid stations will be around 20,250 MVA
in peak 2024. In accordance with Condition 27 of OETC’s Transmission and Dispatch Licence, the power flow
studies presented in this Capability Statement are based on updated demand forecast data provided by Distribution
Companies (DISCOs) and the updated generation forecast by Oman Power and Water Procurement Company
(OPWP).

To be able to perform the studies and produce the results presented in this Statement, the deadlines to receive data
from the various parties (OPWP and DISCOs) are as per the Grid Code requirements. For the demand forecast,
DISCOs have an obligation to submit the data by end of September. Regarding the generation data, OPWP has an
obligation to submit the data by end of October. Any information received after the deadlines will be included in
the next Five-Year Annual Transmission Capability Statement (2021-2025).

The introduction of Cost Reflective Tariff (CRT) in 2017 has affected the major customer’s consumptions and
expected to have more influence in the coming years on the demand forecast. “The Authority’s view is that Cost
Reflective Tariffs are required to moderate and help in managing expected increases in electricity subsidy as a result
of: significant growth in electricity demand and the investment needed to supply it, increasing electricity intensity
of consumption, the requirement to use more expensive alternatives to local natural gas, and certain technical
deficiencies of existing Permitted Tariffs”. The forecast average annual growth in the system demand is about 5%
for MITS and 9.7% for DTS, which drives many of the planned grid station reinforcements over the period from
2020 to 2024. The high growth DTS is due to operation of Salalah Methanol plant and increasing in suppling bulky
customers in 33kV level as well as extending the DTS to supply Saih Al Khairat load (which was supplied by
RAEC previously). To meet security of supply requirements and provide load relief to the loaded grid stations, it
will be necessary to transfer excess load to the new or existing grid stations.

Moreover, RAEC has submitted a connection application dated 25th of December 2014 for the first Wind Farm
Plant to be connected to DTS with 50 MW installed capacity and it was energised in Q3 2019. OPWP has submitted
a connection application dated 20th of November 2017 for the first Solar PV IPP to MITS with a 500 MW installed
capacity in Ibri and it will be in service by peak 2022. In addition, OETC also has received an application from
OPWP regarding the connection of 1000 MW Solar IPP in Manah, which is expected to be in service by peak 2023
for phase 1 and peak 2024 for phase 2. Furthermore, OPWP has proposed a new type of generation plant (Waste to
Energy Plant) which is expected to be in service by peak 2024. Eventually, OPWP has mentioned two wind projects
in their generation plan (2020-2024) with a total capacity of 300 MW in Duqm and JBB Ali (expected to be in
service by peak 2024).

As the demand grows, there is a greater need to extend the transmission system and to establish new 400kV network
as a backbone to transmit the bulk power from power plants. This will reduce the overload at the 220kV and 132kV
networks and subsequently improve voltages and reduce power losses. Consequently, the 220kV will be operated
as a transmission system and the 132kV as a sub-transmission system.

Page | 11
Five-Year Annual Transmission Capability Statement (2020 - 2024)

Table 1 shows thirty transmission projects that are planned over the five-year period. Most of the projects are
designed to increase the transmission system capacity. This is a major programme of capital investment that will
be spread across the whole network to improve transmission system performance in northern and southern Oma n.
Power system studies presented in this Statement confirmed that the planned investment in 400kV, 220kV and
132kV grid stations and transmission circuits will provide substantial spare capacity on the transmission systems.

From 2020 to 2024, the fault levels across the transmission system are within the corresponding switchgear short
circuit ratings. The major technical issue identified in the studies was the high short circuit fault levels on the 132kV
busbars at six grid stations in Muscat area from 2020 to 2024. The grid stations are Mobella, Seeb Main, Rusail,
Airport Heights, Mawalleh South and Madinat Sultan Qaboos (MSQ). During the period from 2020 to 2024, OETC
will address this problem in the short–term by splitting the 132kV bus bars or opening some of the 132kV lines at
Muscat region without affecting the security requirements. Therefore, there will be a need for 132kV busbars
splitting to reduce the short circuit level at Seeb Main grid station from 2020 to 2023, Ghala Heights grid station in
2020 and Mawalleh South grid station in 2021 and 2023 due to the network development and reconfiguration works.
In addition, some of the 132kV lines will still be opened to reduce the infeed short circuit contribution and this is a
part of OETC long-term strategy to operate 400kV and 220kV as the main transmission system. The strategy is
implemented with zero cost and risk. There will be no investment required to reduce the fault level as system can
be operated safely and meeting the Transmission Security Standard requirements.

Load flow studies have confirmed that the voltage levels across the transmission system will be maintained within
the limits. The 400kV voltage will be maintained in the system within the allowable limit ±5%. In addition, as
defined in the Grid Code, the 220kV and 132kV will be maintained within ±10% and the 33kV will be maintained
within ±6%. Furthermore, the load flow has presented the issue of overvoltage during the winter peak time due to
the 400kV lines. Accordingly, OETC has initiated a number of projects to install shunt reactors in the 400kV lines
to overcome the overvoltage issue during winter peak time. All shunt reactors at the 400kV circuits have been
installed and working efficiently to absorb the MVAr from the network during the winter and off peak time.

The Statement has reviewed the opportunities for the connection of new generation and new demand and therefore
identified those grid stations with substantial spare capacity where it should be possible to connect new demand to
the system.

Section 2 of the Statement provides an introduction to the document, identifying the main related documentation
and the key changes that have taken place on the transmission system since the previous issue of the Statement.

Section 3 identifies the technical requirements of the Grid Code and the Transmission Licence with specific
attention to system voltage, frequency and security of supply.

Section 4 describes the main engineering standards used by OETC in its planning and design of the transmission
system.

Section 5 describes the existing transmission system and summarises the planned developments in each year over
the period from 2020 to 2024.

Section 6 identifies the existing and planned developments in generation and describes the interconnections both
inside Oman and internationally, i.e. PDO, RAEC and the GCCIA respectively.

Section 7 presents the comparison of demand forecast with the generation capacity available.

Page | 12
Five-Year Annual Transmission Capability Statement (2020 - 2024)

Section 8 discusses transmission systems performance and presents the results of load flow and short circuits studies
that show the performance of the transmission system at both peak and off peak demand in each year from 2020 to
2024.

Section 9 identifies the development opportunities for the connection of new demand and new generating plants to
the transmission systems.

Section 10 presents the areas of the network that will be operating above the firm capacity and non-compliance
with Transmission Security Standard in 2020.

Page | 13
Five-Year Annual Transmission Capability Statement (2020 - 2024)

Table 1: Summary of Planned Developments on OETC Transmission System (2020 - 2024)

Expected
S.N Project Completion Status Main Equipment Purpose
Date

Peak 2020

· To meet Transmission Security


Adding third & fourth · 2x125 MVA transformers
1 September Energized Standard
transformers 132/33kV at
2019 · 4 no. 33kV GIS Interlink
Airport Heights grid station · To meet load growth in the area

. 2 no. 220kV GIS at Sohar Free Zone


. 2 no.220kV GIS at SFZ for Moon Steel.
· To develop 400kV network
· 61.78 km of 400kV OHL from Sohar Free Zone to
Mahadha (Operate as 220kV) · To evacuate full power from Sohar
400kV line connection between III IPP
2 Sohar Free Zone – Mahadha December Energized
. 220kV Monopole 1.12 km from 400kV SFZ to 220kV SFZ
· To maintain Transmission Security
& Sohar Free Zone – SIS grid for Mahadha – SFZ OHL
stations 2019 Standard
· 33.34 km of 400kV OHL between Sohar Free Zone and
SIS . Connect Moon Steel to 220 kV SFZ
. 0.26 km of 220kV UGC each circuits at Mahadha End. grid station.

. 0.250 km of UGC each circuits at SFZ end


· 1x500 MVA transformer, 220/132kV at SIA
· 3 no. 132kV GIS at SIA · To meet Transmission Security
March
3 Security of SIA grid station Energized Standard at SIA during maintenance
2020 · 1 no. 220kV GIS at SPS period
· 3.7 km UGC of 220kV SPS – SIA

Page | 14
Five-Year Annual Transmission Capability Statement (2020 - 2024)

Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2020 - 2024)

Expected
S.N Project Completion Status Main Equipment Purpose
Date

Peak 2020

· 2x125 MVA transformers · To cater for the new demand in the


Birkat Al Mouz 132/33kV grid March · 10 no. 132kV GIS area
4 Energized
station 2020 · 2.6 km LILO of Izki- Nizwa 132kV OHL (1.2 km Izki- · Load transfer from Nizwa &
Birkat Al Mouz, 1.4 km Birkat Al Mouz – Nizwa) Madinat Nizwa grid stations

· To meet Transmission Security


Construction of a new 400kV March · 30 km 400kV OHL from Sohar Free Zone to Shinas
5 OHL between Sohar Free Zone Energized Standard
2020 (operated as 132kV)
- Shinas grid stations · To meet future 400kV expansion

· 2x125 MVA transformers · To cater for the new demand in the


June · 8 no. 132kV GIS area
6 Sumail Industrial 132/33kV Under
grid station 2020 Construction . 2x14.6 km OHL, LILO of 132kV Rusail-Sumail · Load transfer from Sumail grid
. 4x1.6 km UGC circuits, LILO of 132kV Rusail-Sumail station

Peak 2021

· To support the evacuation of Sur


400kV OHL between New Izki August Under · 100 km of 400kV OHL between New Izki and Misfah grid power plant
7
and Misfah 2020 Construction stations · To meet Transmission Security
Standard

Page | 15
Five-Year Annual Transmission Capability Statement (2020 - 2024)

Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2020 - 2024)

Expected
S.N Project Completion Status Main Equipment Purpose
Date

Peak 2021

· 2x500 MVA transformers


· To cater for the new demand in the
· 10 no. 220kV GIS
Khaborah Interconnection August Under area
8 · 8 no 132kV GIS
Station (KIS) 2020 Construction · To increase the system reliability
· 2x0.1 km LILO of 220kV OHL SIS – MIS within Al Batinah North
· 2x0.15 km LILO of 132kV OHL DAS – Khaborah

· 2x125 MVA transformers · To cater for the new demand in the


December Under area
9 Yanqul 132/33kV grid station · 8 no. 132kV GIS
2020 Construction · Load transfer from Al Hayl grid
· 2x0.6 km LILO 132kV OHL Dank - Al Hayl station

· To cater for the new demand in the


· 4x125 MVA Transformers area
Construction of 132/33kV December · 10 no. 132kV GIS . Refurbishment & reconnection of
Under
10 Khoudh grid station with 4x125 · 132kV UGC Rusail Industrial – Mawalleh South LILO 132kV OHL at Rusail Industrial &
2020 Construction
MVA Transformers works (0.7 km) Mawalleh South GS
· 4 no. 33kV GIS Interlink · Load transfer from Mawalleh
South grid station
· 6 no. 220kV GIS at Ibri Solar IPP GS ·To evacuate power coming from
Connection of Ibri Solar-PV December Under
11 · 2 no. 220kV GIS at Ibri IPP GS Ibri Solar-PV IPP
IPP Generation 2020 Construction
· 3 km 220kV OHL Ibri Solar IPP- Ibri IPP ·To meet load growth in the area

Page | 16
Five-Year Annual Transmission Capability Statement (2020 - 2024)

Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2020 - 2024)

Expected
S.N Project Completion Status Main Equipment Purpose
Date

Peak 2021

· 2x63 MVA Transformers


Construction of 132/33kV March . To reinforce the supply capacity
Under · 6 nos. 132kV GIS at Mirbat
12 Mirbat grid station with 2x63 in Ashoor Area
2021 Construction · 2 nos. 132kV GIS at Ashoor
MVA Transformers · To meet load growth in Area
· 32 km 132kV OHL between Mirbat and Ashoor
· 2x125 MVA transformers at Wadi bani Auwf
New 132kV double circuits · 2 no 132kV GIS at Nakhal · To meet Transmission Security
between Rustaq-Wadi bani May Standard at Rustaq during
Under · 2 no 132kV AIS at Rustaq
13 Auwf-Nakhal grid stations with a maintenance period
2021 Construction · 8 no. of 132kV GIS at Wadi bani Auwf
new Wadi bani Auwf 132/33 kV · Load Transfer from Rustaq grid
grid station · 54.6 km 132kV OHL Nakhal to Wadi Bani Auwf station
. 33.4 km 132kV OHL Rustaq to Wadi Bani Auwf

Upgrading Thumrait grid June · To meet Transmission Security


14 station from 2x30 MVA to 2x63 Design · 2x63 MVA transformers Standard
MVA transformers 2021 · To meet load growth in the area

Page | 17
Five-Year Annual Transmission Capability Statement (2020 - 2024)

Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2020 - 2024)

Expected
S.N Project Completion Status Main Equipment Purpose
Date

Peak 2022

· 4x125 MVA transformers · To cater for the new demand in the


Mobella Industrial 132/33kV area
December · 10 no. 132kV GIS
15 grid station & associated LILO Design · Load transfer from Mobella &
2021 · 4 no. 33kV GIS Interlink
works Barka Main grid stations
· 2x0.75 km LILO 132kV OHL Barka Main – Mobella

· To meet Transmission Security


Connection of Manah 1000 Standard
June . 10 no. 400kV GIS at Manah
16 MW Solar-PV IPP generation Design · To meet load growth in the area
2022 · 2x3 km LILO New Izki - Ibri 400kV OHL at Manah
· To evacuate power coming from
Manah Solar-PV IPP Generation
Peak 2023
. 2x500 MVA transformers at Nahadah (400/132kV)
. 12 no. 400kV GIS · To meet Transmission Security
Standard
400/132KV Nahadah grid September . 8 no. 132kV GIS
17 Design · To introduce a new
station 2022 . 2 no. 400kV GIS for (25-75) MVAr shunt reactors interconnection point with PDO
. 1 km 400kV OHL LILO of Ibri IPP – Manah Solar PV IPP at
Nahadah

· 2x125MVA transformer (132/33kV) · To meet Transmission Security


Standard
Construction of new 132/33kV December · 6 no. 132kV GIS at Saih Al Khairat
18 Design · To meet load growth in the area
Saih Al Khairat grid station 2022 · 2 no. 132kV AIS at Thumrait
· To supply RAEC load instead of
· 88 km 132kV OHL from Thumrait to Saih Al Khairat using diesel generator
Page | 18
Five-Year Annual Transmission Capability Statement (2020 - 2024)

Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2020 - 2024)

Expected
S.N Project Completion Status Main Equipment Purpose
Date

Peak 2023

· 1 no. 500 MVA transformer (220/132kV) at Airport


Installation of third 500 MVA Heights
transformer at Airport Heights March · To meet Transmission Security
. 4 no. 220kV GIS
19 and new 132kV UGC circuit Design Standard
2023 . 4 no. 132kV GIS
between Airport Heights and · To meet load growth in the area
Ghala grid stations . 3.8 km of UGC between Airport Heights and Ghala grid
stations

. 3x500 MVA transformers (400/132kV) at Al Jefnen grid


station
. 2x500 MVA transformers (220/132kV) at Misfah grid
Construction of new Al Jefnen station (will be ready by June 2022)
400/132kV grid station with . 11 no. 400kV GIS at Al Jefnen · To meet Transmission Security
associated OHL and addition of March
20 Design . 11 no. 132kV GIS at Al Jefnen Standard
2x500 MVA 220/132kV 2023
. 8.3 km 400kV OHL Misfah - Al Jefnen · To meet load growth in the area
transformers at Misfah grid
. 0.85 km 132kV OHL for reconnection of Sumail industrial
station and Rusail Industrial with Al Jefnen
. 6.4 km 132kV UGC for reconnection of Rusail Industrial
with Al Jefnen

Page | 19
Five-Year Annual Transmission Capability Statement (2020 - 2024)

Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2020 - 2024)

Expected
S.N Project Completion Status Main Equipment Purpose
Date

Peak 2023

· To meet Transmission Security


June . 6 no. 400kV GIS at Mahout Standard
21 Mahout 400/33kV grid station Design
2023 . 2x125 MVA, 400/33kV transformers · To supply RAEC load instead of using
diesel generator

. 10 no. 400kV GIS at Duqm · To meet Transmission Security


Duqm 400/132/33kV grid June Standard
22 Design . 8 no. 132kV GIS at Duqm
station 2023 · To supply RAEC load instead of using
. 4x125 MVA, 132/33kV transformers diesel generator
· 152 km 400kV OHL Duqm – Mahout
. 187 km 400kV OHL Duqm – Suwaihat
. 6 x (25-75) MVAr Shunt Reactors at Duqm to . To meet Transmission Security
Mahout 400kV DC OHL Standard
400kV North South
June . 2x393MVAr Series Capacitors at Duqm to · To meet load growth in the area
23 Interconnector between MIS- Design
2023 Mahout 400kV DC OHL To supply PDO load
Duqm (Phase-1)
. 12 no. 132kV GIS at Suwaihat
. 4x(25-75) MVAr Shunt Reactors at Suwaihat
. 2x500 MVA transformer at Suwaihat (400/132kV)
. 2x500 MVA transformer at Duqm (400/132kV)

Page | 20
Five-Year Annual Transmission Capability Statement (2020 - 2024)

Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2020 - 2024)

Expected
S.N Project Completion Status Main Equipment Purpose
Date

Peak 2024

. 3x500 MVA 400/132kV transformers


. 9 no. 400kV GIS at New Rustaq ·To meet Transmission Security
New Rustaq 400/132kV grid June Standard
24 Design . 13 no. 132kV GIS at New Rustaq
station 2024 ·To overcome loading issues in Al
. 159.8 km OHL New Rustaq- Ibri IPP Batinah area
. 85.2 km OHL New Rustaq – Al Jefnen

·To maintain Transmission Security


June Standard requirements
25 Securing Bureimi area Planning · 2 no. 132kV GIS at Bureimi Industrial grid station
· To meet load growth requirements
2024 . 32.9 km 132kV OHL between Mahadha – Bureimi Industrial
· To increase the system reliability
. 5.5 km 132kV UGC between Mahadha – Bureimi Industrial
within Al Bureimi area

. 5 no. 132kV GIS at WTE grid station .To meet Transmission Security
June Standard
26 Connection of WTE IPP Design . 2 no. 132kV GIS at Madinat Barka grid station
2024 . To evacuate power coming from WTE
. 3.6 km OHL WTE IPP – Madinat Barka grid station IPP

· 2x125 MVA transformers


June · To meet Transmission Security
27 Al Jawabi 132/33kV grid station Planning . 6 no. 132kV GIS at Al Jawabi grid station
Standard
2024 . 2 no. 132kV AIS at JBB Ali grid station
· 14 km 132kV OHL from JBB Ali to Al Jawabi · To meet load growth in the area

Page | 21
Five-Year Annual Transmission Capability Statement (2020 - 2024)

Table 1 (Continued): Summary of Planned Developments on OETC Transmission System (2020 - 2024)

Expected
S.N Project Completion Status Main Equipment Purpose
Date

Peak 2024
. 2x500 MVA, 220/132kV Transformers at Nizwa grid station
. 1x500 MVA, 400/220kV Transformer at New Izki grid station
. 6 no. 220kV GIS at Nizwa grid station ·To maintain Transmission Security
June . 2 no. 220kV GIS at New Izki grid station Standard requirements
28 Nizwa 220/132kV grid station Planning
2024 . 2 no. 132kV AIS at Nizwa grid station · To increase the system reliability
. 1.1 km 220kV UGC (New Izki – Nizwa) from Nizwa side within Al Dhakilyah region

. 3.6 km 220kV UGC (New Izki – Nizwa) from New Izki side
. 53.9 km 220kV OHL (New Izki – Nizwa)

. 6 no. 132kV GIS at Duqm wind farm · To evacuate power coming from
June Duqm Wind Farm
29 Duqm wind farm connection Planning . 2 no. 132kV GIS at Duqm grid station
2024 · To meet Transmission Security
. 49.7 km 132kV OHL (Duqm wind farm – Duqm) Standard

. 6 no. 132kV GIS at JBB Ali wind farm · To evacuate power coming from JBB
June Ali Wind Farm
30 JBB Ali wind farm connection Planning . 2 no. 132kV GIS at Al Jawabi grid station
2024 · To meet Transmission Security
· 9 km 132kV OHL from Al Jawabi to JBB Ali wind farm Standard

Page | 22
Five-Year Annual Transmission Capability Statement (2020 - 2024)

Figure 1 shows the summary of planned developments on OETC Transmission Systems (2020-2024).

Project Status for period (2020-2024)


8

6
Number of Projects

0
Peak 2020 Peak 2021 Peak 2022 Peak 2023 Peak 2024
Yea r

Planning Design Under Construction Energized

Figure 1: Summary of Planned Developments on OETC Transmission Systems (2020- 2024)

Page | 23
Five-Year Annual Transmission Capability Statement (2020 - 2024)

2. Introduction

2.1 Licence conditions, Codes and Standards


This Five-Year Annual Transmission Capability Statement covers the period from 2020 to 2024 that is
prepared by the Oman Electricity Transmission Company (OETC). The Statement is prepared in
accordance with the requirements set down under Licence Condition 27 of the Electricity Transmission and
Dispatch Licence granted to the Company on 1st of May 2005 by the Authority of Electricity Regulation,
Oman (AER). The Licence has been granted under the power invested in the Authority by Article (2) of
the Law for the Regulation and Privatisation of the Electricity and Related Water Sector promulgated by
Royal Decree 78/2004.

The purpose of the Statement is to provide up-to-date transmission system data for potential and existing
users of the transmission system so they can identify those parts of the transmission system that offer the
opportunity for future development. The Statement should be updated annually so that existing and new
users of the transmission system are furnished with the latest information.

New users of the transmission system should be aware of the following main documents that influence the
planning and future development of the transmission system infrastructure:

i) The Electricity Transmission and Dispatch Licence granted to OETC by the AER.

ii) The Grid Code for the Sultanate of Oman (PC.4.5).

iii) The approved Transmission Security Standards prepared in accordance with


Condition 26 of OETC’s Transmission and Dispatch Licence, which defines the
requirements for the Security Standards and maintaining of an efficient and economic
Transmission System.

iv) The Statement of Charges for Connection and Use of System to OETC Electricity
Transmission System (Condition 25 of OETC’s Transmission and Dispatch Licence).

2.2 2020 System Development since the 2019-2023 Statement


Since the issue of the previous Capability Statement, covering the period 2019-2023, the following projects
have been or will be completed and energized in time to meet 2020 system peak demand:

1. Security of SIA grid station.

2. 400kV line connections between Sohar Free Zone – Mahadha and Sohar Free Zone – SIS grid
stations.

3. Birkat Al Mouz 132/33kV grid station.

4. Sumail Industrial 132/33kV grid station.

5. Construction of a new 400kV OHL from Sohar Free Zone GS to Shinas GS.

6. Adding third & fourth transformers 132/33kV at Airport Heights grid station.

Page | 24
Five-Year Annual Transmission Capability Statement (2020 - 2024)

2.3 Improvements in the preparation of the Statement


Since the issue of the Transmission System Capability Statement for 2019-2023 there have been a number
of improvements in the data and the power system modelling upon which the studies that discussed in the
Statement are based. The most significant of these are:

i. Updating the demand forecast data according to the received information from the DISCOs.

ii. Updating the generation plan according to the received information from the OPWP.

iii. Updating the operational limits of generating units according to the received information
from the OPWP.

iv. Updating the transmission system data for the new projects as per the actual parameters.

v. Updating the new generating units data as per the actual parameters.

vi. Introducing a new 400kV OHL which is part of North-South Interconnector that connects
PDO and RAEC areas.

vii. Introducing results for the losses per voltage level and voltage profile for all grid stations.

viii. Introducing a new section regarding potential generation connection (section 9.3).

ix. Introducing PDO network in OETC system models of the northern part.

x. Modelling of Renewable Energy Resources that includes Solar, Wind and Waste to Energy
plants.

The improvements in the demand forecast and the power system modelling should result in similar
improvements being achieved in the accuracy of the power system studies upon which network
development planning is based.

Page | 25
Five-Year Annual Transmission Capability Statement (2020 - 2024)

3. Technical requirements for compliance with the Grid Code and Licence

The Grid Code is designed to permit the development, maintenance and operation of an efficient,
economical and coordinated electricity transmission system. It facilitates competition in the generation and
supply of electricity and promotes the security and efficiency of the system as a whole.

The Transmission Security Standard required the capacity of the Transmission System to transmit
electricity and shall not be reduced in the event that a single electric line, transformer or breaker and/or
associated plant is not in service. The operating voltage of the Transmission System shall be maintained
within the limit specified in the Grid Code and TSS.

In order to comply with Condition 26 of the Electricity Transmission and Dispatch Licence the transmission
system must be planned, designed and operated to provide a secure, efficient and economic supply of
electricity that is of an acceptable quality to its users. Subject as provided in the Grid Code, OETC shall
ensure that the Electricity Transmission System complies with the following technical, design and
operational criteria in relation to the part of the Electricity Transmission System at the Connection Site with
a User (unless otherwise specified in the Grid Code). Although in relation to operational criteria, OETC
may not be able to comply with this obligation to the extent that others parties are not complying with the
Grid Code. Each User shall ensure compliance with the criteria set out in the Grid Code (CC.6.1.5). Whilst
Condition 26 specifically sets out the Security of Supply requirements, the most important characteristics
that determine the quality of supply are frequency and voltage. The requirements for maintaining
transmission system frequency and voltage within specified operating limits are set out in the Grid Code,
and most clearly defined under conditions CC.6.1.1 and CC.6.1.2 respectively of the Connection Conditions
Code.

Grid Code establishes the historic frequency and voltage performances of the transmission system,
specifically in relation to operation at abnormal voltages and frequencies. It considers how future generation
and demand changes may affect transmission system performance in these areas. It establishes the relevant
generation design criteria and standards, and the impacts of operation at abnormal voltages and frequencies
on generating units. It considers whether the current Grid Code frequency and voltage requirements are
appropriate, taking into account of the system security requirements, the capabilities of generating units,
and the industry costs and benefits of implementing them.

For the purposes of the TSS and in respect of frequency and voltage, four conditions are identified for
determining system parameter values, as follows:

 Normal conditions – being conditions that apply on a continuous basis; these are the preferred
conditions of the OETC licensed transmission system

 Disturbed conditions – being conditions in which the voltages are the same as for normal
conditions, but the frequency limits have been changed and include, as a lower limit, the Normal
Infeed Loss Risk frequency limit

 Stretched Conditions – being conditions that have two parts:

Page | 26
Five-Year Annual Transmission Capability Statement (2020 - 2024)

 Continuous Stretched Conditions that are not time dependant

 Time limited Stretched Conditions that may only be experienced for no more than sixty
continuous seconds

 Unacceptable Conditions – being conditions that are never allowed in planning, design or operation

Transient frequency deviations that occur outside the limits of continuous operation Stretched Conditions
and last less than sixty seconds shall only occur at reasonably infrequent intervals. This governs all relevant
TSS criteria. Table 2 sets out the required values for the system parameters.

Table 2: OETC Licensed Transmission System, System Parameter Values


Quality of Supply – System Parameter values

Unacceptable conditions

Stretched conditions

Disturbed conditions
Parameter
Normal conditions

Low High Low High Low High Low High Low High
Target
˂ ≥ ˂ ≥ ˂ ≥ ≤ > ≤ > ≤ >

47.50 49.50 50.50 51.50


Frequency
47.50 49.50 49.95 49.95 50.00 50.05 50.05 50.50 51.50
Hz Less than Less than
60 seconds 60 seconds

380 380 390 400 410 420 420


Voltage
198 198 209 220 231 242 242
kV

119 119 125 132 139 145 145

During some system’s disturbances, such as where short circuits occur, the voltage could collapse
transiently to zero at the point of fault until the fault is cleared. Voltage regulation requires both active and
reactive power flows across the transmission system to be carefully controlled. The physical characteristics
of the plant on the transmission system also give rise to the generation and absorption of reactive power.
Reactive power flows across the transmission system can give rise to substantial voltage differences and it
is therefore necessary to maintain reactive power balances between sources of capacity and demand on a
“zone” basis.

Unlike frequency, which is consistent across an interconnected transmission system, voltages at different
points on an interconnected system are determined by the local sources of demand and capacity, by the
prevailing network configuration and the reactive power flows across the network. The management of
voltage requires control of reactive power that can be provided by generation units, transformer tap-
changers, capacitor banks at 33kV or below, shunt reactors, series capacitor or by means of static VAR
compensator (SVC).

Page | 27
Five-Year Annual Transmission Capability Statement (2020 - 2024)

3.1 Security of Supply


In accordance with Condition 26 of OETC Transmission and Dispatch Licence, the capacity of the
Transmission System to transmit electricity shall not be reduced in the event that a single electric line,
cable, transformer, circuit breaker and/or associated plant is not in service. During a period of which such
equipment is out of service, the operating voltage of the Transmission System may reduce to any level
specified for such purposes in the Grid Code. In fact, the transmission system should be planned and
operated to meet the Transmission Security Standard requirements. Table 3 from the Transmission Security
Standard document shows Demand Connections, Demand Class definition and supply restoration times.
The table illustrates and explains boundaries of each demand classes and the security level requirements
during the outage for restricted and a maintenance period.

Table 3: Demand Connections – Demand Class Specification

Demand Connections
Demand Class definition and supply restoration times

OETC licensed transmission system configuration

Demand Class
Demand Class

Boundaries A Planned Outage followed by


Following a system outage during the
a single Fault Outage
Restricted Period
during the M aintenance Period

Low High Required level of Required level of


MW MW served demand Time to restore served demand Time to restore
served demand served demand
> ≤ MW MW

Repair time of
A 0 2 No requirement
faulted circuit

B 2 6 3 hours No requirement

Return time of
C 6 20 15 minutes Maintenance
Planned Outage
Total Group Period Demand
Demand for the Demand
M omentary Group
Return time of
D 20 115 Interruption
Planned Outage
allowed1

M omentary M omentary
E 115 300 Interruption Interruption
allowed allowed

F 300 No loss of supply for the Secured Events described in the M ITS design criteria

1
The duration of M omentary Interruption allowed is one minute

Page | 28
Five-Year Annual Transmission Capability Statement (2020 - 2024)

4. OETC System Design and Planning Standards

In addition to the technical requirements of the Transmission Licence and the Grid Code, the principal
electrical standards used by OETC in its planning and design of the 400kV, 220kV and 132kV transmission
systems are:

4.1 Oman Electrical Standard OES 11


The standard covers the topic “General Specifications for Electrical Materials and Equipment” and defines
the worst-case conditions for system design purposes by the following parameters:

a) Maximum ambient temperature (50˚C)


b) Maximum surface temperature for metal surfaces (80˚C)
c) altitude (between sea level and 300 metres above sea level)
d) Maximum wind velocity (125km per hour)
e) Average annual rainfall (117mm)
f) Maximum relative humidity (100%)
The standard also defines the design parameters for the 132kV systems in terms of highest voltage, design
fault level and the requirement that the system be solidly earthed. Currently it does not specify
corresponding figures for the 400kV and 220kV systems where OETC has developed its own technical
standards for 220kV and 400kV systems based on best practice and international standards.

4.2 Oman Electrical Standard OES 25A and 25B


These standards define the requirements for Aluminium conductor steel reinforced and Aluminium alloy
conductor overhead lines and Aluminium alloy stranded conductor overhead lines.

4.3 Oman Electrical Standard OES 27


Volume 1 of the standard covers the design requirements for a 132/33kV, 2x125 MVA substation with
132kV gas insulated switchgear, including the 33kV switchgear. Volume 2 covers similar requirements
for the 132/33kV, 2x63 MVA substation with 132kV outdoor SF6 switchgear.

4.4 Oman Electrical Standard OES 32


The standard covers the design requirements for 132kV double circuit overhead transmission lines with
400mm2 All Aluminium Alloy Twin-Yew Conductors (AAAC) on lattice steel towers that are deployed
across much of the 132kV transmission system.

4.5 OETC Standard Specifications


In cases where an Oman Electrical Standard is not applicable it is usual OETC practice to adopt the
appropriate related standards. This applies to the design of the 400kV, 220kV and 132kV transmission
systems. The internal OETC standard specifications include all others design requirements that are currently
not exist in above Oman Electrical Standard.

Page | 29
Five-Year Annual Transmission Capability Statement (2020 - 2024)

The standard covers the operation parameters of outdoor transmission assets and defines the worst-case
conditions for system design purposes by the following:

a) Average Minimum ambient temperature 12º C


b) Design Minimum ambient temperature 5° C
c) Average Maximum ambient temperature 38º C
d) Design Maximum ambient temperature 50° C
e) Maximum temperature of metal surface in direct sunlight 80º C
f) Mean relative humidity (max/avg.) 86 % / 72 %
g) Maximum relative humidity 100 %
h) Minimum relative humidity 15 %
i) Average annual rainfall 145mm
j) Highest annual rainfall 638mm

4.6 Standard specification for 132/33kV Substations (OETC-AMP-O-AMT-M-041):


The standard consists of 27 sections cover the design requirements for a 132/33kV Substation, including
General Requirements, Transformers, Shunt Reactors, HV Switchgears, MV Switchgears, Protection and
Control, SCADA and telecommunication, and all other auxiliary assets inside the Substation.

4.7 Standard specification for 220/132/33kV Substations (OETC-AMP-O-AMT-M-042):


The standard consists of 27 sections that cover the design requirements for a 220/132/33kV Substation,
including General Requirements, Transformers, Shunt Reactors, HV Switchgears, MV Switchgears,
Protection and Control, SCADA and telecommunication, and all other auxiliary assets inside the Substation.

4.8 Standard specification for 400/220/33kV Substations (OETC-AMP-O-AMT-M-043):


The standard consists of 27 sections which cover the design requirements for a 400/220/33kV Substation,
including General Requirements, Transformers, Shunt Reactors, HV Switchgears, MV Switchgears,
Protection and Control, SCADA and telecommunication, and all other auxiliary assets inside the Substation.

4.9 Standard specification for 400/132/33kV Substations (OETC-AMP-O-AMT-M-044):


The standard consists of 27 sections that cover the design requirements for a 400/132/33kV Substation,
including General Requirements, Transformers, Shunt Reactors, HV Switchgears, MV Switchgears,
Protection and Control, SCADA and telecommunication, and all other auxiliary assets inside the Substation.

4.10 Standard specification for 132kV Overhead Lines (OETC-AMP-O-AMT-M-001):


The standard covers the design requirements for 132kV double circuit overhead transmission lines with 479
mm2 All Aluminum Alloy Twin-Yew Conductors (AAAC) on lattice steel towers.

4.11 Standard specification for 220kV Overhead Lines (OETC-AMP-O-AMT-M-002):


The standard covers the design requirements for 220kV double circuit overhead transmission lines with 821
mm2 All Aluminum Alloy Twin-Araucaria Conductors (AAAC) on lattice steel towers.

Page | 30
Five-Year Annual Transmission Capability Statement (2020 - 2024)

4.12 Standard specification for 400kV Overhead Lines (OETC-AMP-O-AMT-M-003):


The standard covers the design requirements for 400kV double circuit overhead transmission lines with 479
mm2 All Aluminum Alloy Quad-Yew Conductors (AAAC) on lattice steel towers.

4.13 Standard specification for Underground Cable Circuits above 33kV up to 150kV
(OETC-AMP-O-AMT-M-022):
The standard covers the design requirements for 33kV up to 150kV underground XLPE cable circuits and
accessories.

4.14 Standard specification for Underground Cable Circuits above 150kV up to 400kV
(OETC-AMP-O-AMT-M-021):
The standard covers the design requirements for more than 150kV up to 400kV underground XLPE cable
circuits and accessories.

Page | 31
Five-Year Annual Transmission Capability Statement (2020 - 2024)

5. OETC Transmission System

5.1 Existing Transmission System


The Oman Electricity Transmission Company is authorized to undertake all regulated activities of
electricity transmission and dispatch in northern Oman and Dhofar at voltages of 132kV and above. The
existing transmission system in northern Oman has three operating voltages, i.e. 400kV, 220kV and 132kV
while in Dhofar it has only one operating voltage which is 132kV. The existing transmission system extends
across the whole north of Oman and interconnects bulk consumers and generators of electricity located in
the Governorates of Muscat, Batinah South, Batinah North, Dhahirah, Buraimi, Dakhliyah, Sharquiya
South and Sharqiya North.

The transmission system was first established under the Ministry of Electricity and Water (MEW) in 1983
and underwent rapid expansion during the 1990s. Consequently, most of it has less than 15 years of service
experience. After the electrical sector was unbundled, the OETC took over the operation of the MITS on
1st of May 2005 and Dhofar Transmission System on 1st of January 2014.

Figure 2 to Figure 5 show the OETC transmission system at MITS by the end of 2019 while Figure 6 shows
the transmission system at Dhofar.

Figure 2: Number of Grid Stations at MITS by end of 2019

Page | 32
Five-Year Annual Transmission Capability Statement (2020 - 2024)

MITS Lines (2019)

3685.1
4000

3000
ci rcui t-Km

1743.2
2000 1291.2

1000 29.2 71.7 179.8

0
400kV 220kV 132kV

OHL UGC

Figure 3: OHL & UGC Lengths (circuit/km) at MITS by end of 2019

MITS Transformers Capacity (2019)

25000 21020
20000 14130
12750
15000
MVA

10000
5000 1000 570 150
0
400/220kV 400/132kV 220/132kV 220/33kV 132/33kV 132/11kV

Transformers Capacity

Figure 4: Transformers Capacity (MVA) at MITS by end of 2019

New Izki Grid Station


•2x40 MVAr for 400kV OHL New Izki-Qabel Line
•2x100 MVAr for 400kV OHL New Izki-Ibri Line
Sur Grid Station
•2x40 MVAr for 400kV OHL Sur-Qabel Line
•2x35 MVAr for 400kV OHL Sur-Jahloot Line

Ibri Grid Station


•2x100 MVAr for 400kV OHL New Izki-Ibri Line

SFZ Grid Station


•2x50 MVAr for 400kV OHL SFZ-SIS Line

Figure 5: Shunt Reactors (MVAr) at MITS by end of 2019

Page | 33
Five-Year Annual Transmission Capability Statement (2020 - 2024)

Figure 6: OETC transmission system at Dhofar by end of 2019


OETC transmission system at MITS is interconnected with the transmission system of GCCIA Grid through
UAE (Transco Abu Dhabi) at Mahadha (Al Wasit) grid station through 220kV system. The interconnection
links the electricity supply systems of Kuwait, Saudi Arabia, Bahrain, Qatar, UAE and Oman. This should
increase the security of supply and benefits to the members’ countries in the form of cost savings from the
sharing of reserve capacity and energy resources. The 220kV interconnector between OETC and GCCIA
has been energized and brought into service on 14th of November 2011. Oman has signed officially the
agreement with the GCCIA in November 2014 and became a member of GCCIA Grid.

The OETC transmission system at MITS is also interconnected with the Sohar Aluminium system at 220kV
via a double circuit cable that run between SPS-1 on the OETC system and Sohar Aluminium 220kV busbar.
The import or export schedule will vary on a yearly basis as per OPWP and Sohar Aluminium Company
agreement and this can reach up to 300MW.

The OETC transmission system at MITS is also interconnected with the PDO transmission network at
132kV via a single circuit overhead line that runs between Nizwa on the OETC system and Nahadah on the
PDO system. This single circuit is owned, operated and maintained by PDO. In addition, OETC
transmission system at Dhofar is also interconnected with the PDO transmission network at 132kV via a
single circuit overhead line that runs between Dhofar Wind Farm at OETC system and Harweel at PDO
system. This single circuit is owned, operated and maintained by OETC. Under normal conditions, the
power transfer across the PDO interconnection is forecasted to be negligible, but in the event of an
emergency on either network, the interconnection can facilitate a power transfer to address the shortfall.

Page | 34
Five-Year Annual Transmission Capability Statement (2020 - 2024)

The transmission system at MITS area is supplied with electricity generated from eleven gas-based power
stations located at Rusail IPP, Manah IPP, Al Kamil IPP, Barka I Power & Desalination Plant (ACWA),
Barka II IPP (SMN), Barka III IPP, Sohar I Power & Desalination Plant, Sohar II IPP, Sohar III IPP, Sur
IPP and Ibri IPP. In addition, the transmission system may be supplied from direct customers, such as Sohar
Aluminium. The transmission system at Dhofar area is supplied with electricity generated from three gas-
based power stations located at NPS, Salalah Power & Desalination Plant and Salalah II IPP and new wind
farm located at Harweel area with a capacity of 50MW.

Four Distribution and Supply License holders, i.e. Muscat Electricity Distribution Company (MEDC),
Mazoon Electricity Company (MZEC), Majan Electricity Company (MJEC) and Dhofar Power Company
(DPC), take the bulk of the power transmitted through the main grid stations to supply the Distribution
system. In the near future, OETC will also transmit the power to RAEC in order to supply some of their
areas.

In addition to the four Distribution Companies, large private customers are directly connected to the
transmission system. The existing private customers with 220kV Connections are as shown in Figure 7
while Figure 8 shows the customers with 132kV Connections.

Figure 7: The existing private customers with 220kV Connections

Page | 35
Five-Year Annual Transmission Capability Statement (2020 - 2024)

Figure 8: The existing private customers with 132kV Connections

The new customers that will be directly connected during the period covered by the Statement is as shown
in Figure 9.

Figure 9: The Future private customers will be connected to OETC System

In 2019, MIS gross peak demand was 6539.75MW, which occurred at 14:55:29 hours on 30th of June; and
represented an increase of 3.2% on the 2018 peak demand. During 2019, the electric energy delivered to
the MIS from connected generating plants and other generators was 32,584.45 GWh whilst the exported
energy from the MIS to the Distribution Companies was 32,054.70 GWh resulting in transmission system
energy losses of 529.74 GWh, which equates to a transmission system energy loss of 1.63%.

Page | 36
Five-Year Annual Transmission Capability Statement (2020 - 2024)

In 2019, Dhofar system gross peak demand was 594.48MW, which occurred at 04:04:45 hours on 14th of
June; and represented an increase of 4.9% on the 2018 peak demand. During 2019, the electric energy
delivered to the Dhofar transmission system from connected generating plants and other generators was
3,418.62 GWh whilst the exported energy from Dhofar system to Dhofar Power Company was 3,397.19
GWh resulting in transmission system energy losses of 21.44 GWh, which equates to transmission system
energy losses of 0.63%.

5.2 Future System Development Projects

The power system studies presented later in this Capability Statement used to define the constraints and
opportunities that exist on the transmission system over the next five years. The power system studies have
been performed on the basis that the committed and planned development projects detailed in Appendix A
and summarized below will proceed as planned and be completed to the current schedule.

5.3 Projects completed to meet the 2020 peak demand

Figure 10 and Figure 15 show in a geographic map the system arrangement to meet the 2020 peak demand
of MITS and DTS respectively. In section 2.2 of this Statement, it was noted that a number of projects had
been completed since the published Capability Statement 2019-2023, so that they were available to meet
the peak demand of summer 2020. Reinforcement projects such as adding third and fourth 132/33kV 125
MVA transformers with four 33kV GIS interlink at Airport Heights grid station was energized to meet the
Transmission Security Standard and load growth in the area. In addition, two 400kV lines were energized
61.78km from Sohar Free Zone to Mahadha grid stations (operate as 220kV) and 33.34km from Sohar Free
Zone to SIS grid stations. Moreover, 1x500 MVA transformer added at SIA grid station with 3.7km 220kV
UGC from SPS to SIA to meet TSS at SIA during maintenance period. Furthermore, new 132/33kV grid
station at Birkat Al Mouz was energized with 2x125 MVA transformers and connected via 2.6km 132kV
OHL LILO of Izki - Nizwa. New 30km 400kV OHL was constructed from Sohar Free Zone to Shinas grid
station that and operated as 132kV to meet TSS requirements. Moreover, Sumail Industrial 132/33kV grid
station will be constructed with 2x125 MVA transformers that will be connected via 132kV LILO Rusail -
Sumail (2x14.6km OHL and 4x1.6km UGC) to cater for the new demand in the area.

5.4 Projects expected to be completed to meet the 2021 peak demand

Figure 11 and Figure 16 show in a geographic map the system development plan to meet the 2021 system
peak demand of MITS and DTS respectively. The main investment to meet the 2021 peak in Muscat area
is the new 100km of 400kV OHL between New Izki and Misfah which is intended to evacuate the generated
power from Sur power plant. In addition, 220/132kV 2x500 MVA transformers will be constructed at
Khaborah Interconnection Station (KIS) to cater for the new demand in the area and to increase system
reliability within Al Batinah North. The projects designed to meet the 2021 system peak demand include
the construction of new 132/33kV, 2x125 MVA transformers at Yanqul that will be connected via 2x0.6km

Page | 37
Five-Year Annual Transmission Capability Statement (2020 - 2024)

132kV OHL by LILO of Dank - Al Hayl 132kV line. In addition, new 132/33kV, 4x125 MVA transformers
grid station at Khoudh with four 33kV GIS interlink will be in service. Further, the connection of Ibri Solar-
PV IPP Generation via 220kV OHL from Ibri IPP grid stationwill be completed to evacuate power coming
from Ibri Solar-PV IPP. In addition, the development in Dhofar region will be a construction of a new
132/33kV, 2x63 MVA transformers grid station at Mirbat with 32km 132kV double circuit lines between
Mirbat and Ashoor grid stations. Furthermore, new 2x125MVA, 132/33kV grid station will be constructed
at Wadi bani Auwf with new 54.6km of 132kV OHL from Nakhal to Wadi Bani Auwf and 33.4km of
132kV OHL from Rustaq to Wadi Bani Auwf. Finally, the development in Dhofar will cover upgrading
2x30 MVA transformers to 2x63 MVA transformers at Thumrait grid station to meet the Transmission
Security Standard and load growth.

5.5 Projects expected to be completed to meet the 2022 peak demand


Figure 12 and Figure 17 show in a geographic map the system arrangement to meet the 2022 peak demand
of MITS and DTS respectively. The projects planned to support 2022 network system include new
4x125MVA 132/33kV grid station at Mobella Industrial with four 33kV GIS interlink and this grid station
will be connected via 132kV OHL LILO of Barka Main – Mobella grid stations. One of the major planned
projects to meet the 2022 peak is the 400kV Connection of Manah Solar-PV IPP that will be connected via
2x3km LILO from New Izki – Ibri IPP 40kV OHL. Further, construction of 2x500 MVA, 220/132kV
transformers at Misfah grid station project will be ready as part of other project “construction of new Al
Jefnen 400/132kV grid station” that will be described in section 5.6 below.

5.6 Projects expected to be completed in time to meet the 2023 peak demand
Figure 13 and Figure 18 show in a geographic map the system arrangement to meet the 2023 peak demand
of MITS and DTS respectively. New 2x500 MVA, 400/132 kV grid station at Nahadah will be constructed
along with associated 1km of 400kV OHL by LILO of Ibri IPP– Manah 400kV OHL. Moreover, first new
connection to RAEC will be through construction of 132/33 kV grid station at Saih Al Khairat area along
with associated 88km of 132kV OHL from Thumrait to Saih Al Khairat grid stations. In addition,
installation of third 500 MVA transformer at Airport Heights and 3.8 km of 132kV UGC between Airport
Heights and Ghala grid stations will be energized to meet load growth in the area. Furthermore, one of
planned project is construction of new Al Jefnen 3x500MVA 400/132kV grid station with associated 8.3km
of 400kV OHL from Misfah to Al Jefnen grid stations. Moreover, construction of new 400/33kV grid
station at Mahout area and new 400/132/33kV grid station at Duqm area are planned to supply RAEC load
instead of using diesel generators. Furthermore, One of the development of 400kV network is North-South
Interconnector (MIS-Duqm Phase-1) which includes 152km of 400kV OHL between Duqm and Mahout
and 187km of 400kV OHL between Duqm and Suwaihat along with 6x(25-75) MVAr Shunt Reactors and
2x393 MVAr of Series Capacitors at 400kV OHL between Duqm and Mahout grid stations.

Page | 38
Five-Year Annual Transmission Capability Statement (2020 - 2024)

5.7 Projects expected to be completed in time to meet the 2024 peak demand
Figure 14 and Figure 19 show in a geographic map the system arrangement to meet the 2024 peak demand
of MITS and DTS respectively. One of the development of 400kV network in Al Batinah is construction
of new 400/132 kV grid station at Rustaq area with 3x500 MVA, 400/132kV transformers along with
associated 159.8km of 400kV OHL from New Rustaq to Ibri IPP grid stations and 85.2km of 400kV OHL
from New Rustaq to Al Jefnen grid stations. Furthermore, Securing Bureimi area includes construction of
32.9km of 132kV OHL and 5.5km of 132kV UGC between Mahadha and Bureimi Industrial grid stations.
In addition, first new waste to energy (WTE) project will be constructed at Barka area with associated of
3.6km 132kV OHL between WTE IPP and Madinat Barka grid stations. Moreover, construction of new
132/33kV Al Jawabi grid station with 2x125MVA transformers and 14 km of 132kV OHL from JBB Ali
to Al Jawabi grid stations is planned to meet load growth in the area. Further, JBB Ali Wind Farm
connection includes construction of 9 km of 132kV OHL from Al Jawabi to JBB Ali Wind Farm to evacuate
power coming from JBB Ali Wind Farm. In addition, Duqm Wind Farm will be connected to Duqm grid
station via 49.7km of 132kV OHL to evacuate power coming from Duqm Wind Farm. Finally, construction
of Nizwa 220/132kV grid station with 2x500MVA transformers is planned to increase the system reliability
within Al Dhakilyah region. The grid station will be connected via 220kV line from New Izki grid station
including 53.9km OHL, 1.1km UGC from Nizwa side and 3.6km UGC from New Izki side.

5.8 Summary
Table 1 in the Executive Summary has summarized the development plans for the OETC Transmission
System on a project-by-project basis at the time of this statement. The table identifies the committed
projects by OETC that are considered likely to be proceed with. The power system studies presented in this
Capability Statement is to show the expected performance of the transmission system over the period 2020-
2024. In addition, the studies have been performed on the basis that the committed and planned development
projects in Table 1 and detailed in Appendix A will proceed as planned and to be completed on schedule.
The system studies are used to identify areas of the transmission system where there are opportunities for
connecting new demand and new generation and where constraints should be applied to further
development.

Page | 39
Five-Year Annual Transmission Capability Statement (2020 - 2024)

Figure 10: Existing MITS in Peak 2020

Page | 40
Five-Year Annual Transmission Capability Statement (2020 - 2024)

Figure 11: MITS expected development in Peak 2021

Page | 41
Five-Year Annual Transmission Capability Statement (2020 - 2024)

Figure 12: MITS expected development in Peak 2022

Page | 42
Five-Year Annual Transmission Capability Statement (2020 - 2024)

Figure 13: MITS expected development in Peak 2023

Page | 43
Five-Year Annual Transmission Capability Statement (2020 - 2024)

Figure 14: MITS expected development in Peak 2024

Page | 44
Five-Year Annual Transmission Capability Statement (2020 - 2024)

Figure 15: Dhofar existing transmission system in Peak 2020

Page | 45
Five-Year Annual Transmission Capability Statement (2020 - 2024)

Figure 16: Dhofar expected transmission system in Peak 2021

Page | 46
Five-Year Annual Transmission Capability Statement (2020 - 2024)

Figure 17: Dhofar expected transmission system in Peak 2022

Page | 47
Five-Year Annual Transmission Capability Statement (2020 - 2024)

Figure 18: Dhofar expected transmission system in Peak 2023

Page | 48
Five-Year Annual Transmission Capability Statement (2020 - 2024)

Figure 19: Dhofar expected transmission system in Peak 2024

Page | 49
Five-Year Annual Transmission Capability Statement (2020 - 2024)

6. Existing and Planned Developments in Generation

6.1 Existing Generation


6.1.1 Existing generation of MIS

Eleven gas-based power stations supply MIS transmission system in summer 2020 as follows:
 Rusail IPP in Muscat governorate.

 Barka I Power & Desalination Plant (ACWA), Barka II IPP (SMN) and Barka III IPP in Al Batinah
South governorate.

 Manah IPP in Al Dakhilya governorate.


 Al Kamil and Sur IPPs in Al Sharqiyah South governorate.

 Sohar I Power & Desalination Plant, Sohar II IPP and Sohar III IPP in North Al Batinah
governorate.
 Ibri IPP at Al Dhahirah governorate
The eleven power stations are described briefly below:

a) Rusail IPP
Rusail IPP is located in the Rusail Industrial Estate. The power station has eight Frame 9E gas turbines
installed and are operating in open-cycle. The gross site rating of the units varies from 82.3 MW to 96.9
MW. The units were installed progressively between 1984 and 2000. The net generation capacity of the
power station is approximately 693.5 MW.

b) Manah IPP
Manah IPP is owned by the United Power Company and was the first Independent Power Project (IPP)
built in Oman and commissioned in 1996. The station comprises three GE PG6541B gas turbines (each site
rated at 27 MW) and two GE PG9171E gas turbines (site ratings of 91.1 MW). In 2020 OPWP is planning
to operate GT2A &GT2B with net generation capacity of 182.2 MW and retire the three GE PG6541B gas
turbines.
c) Al Kamil IPP
Al Kamil IPP was commissioned in 2002. The station comprises three GE PG9171E gas turbines (site
rating 97.1 MW) operating in open cycle and the net generation capacity is approximately 291.4 MW.

d) Barka Power Plants


There are three power plants in Barka:
1. Barka I Power & Desalination Plant was commissioned in 2003 by AES (ACWA recently) and was
developed as an Independent Water and Power Plant (IWPP). The power plant comprises two Ansaldo
V94.2 gas turbines with a capacity of 99.4 MW and a steam turbine operating in combined cycle with
a capacity of 198.7 MW. The net generation capacity is approximately 397.5 MW.

Page | 50
Five-Year Annual Transmission Capability Statement (2020 - 2024)

2. Barka II IPP (SMN) was commissioned in 2009. There are three gas turbines of 122.8 MW capacity
each and two steam turbines of 160 MW capacity each. The net generation capacity is approximately
688.5 MW.
3. Barka III IPP was commissioned in 2012. There are two gas turbines of 247.5 MW capacity each and
a steam turbine of 270.4 MW capacity are available in 2020. The net generation capacity is
approximately 765.5 MW.

g) Sohar Power Plants


1. Sohar I Power & Desalination Plant was developed by Sohar Power Company. The plant consists of
three Siemens V 94.2 gas turbines (site rating 125.7 MW), a steam turbine (site rating 220 MW) and
four desalination units. The three gas turbines came into service during summer 2006. The gross power
plant capacity is approximately 597 MW.
2. Sohar II IPP was commissioned in 2012. There are two gas turbines of 247.5 MW capacity each and a
steam turbine of 270.4 MW capacity are available in 2020. The total generation capacity is
approximately 765.5 MW.
3. Sohar III IPP was commissioned in 2019. There are four gas turbines of 272.5 MW capacity each and
two steam turbines of (ST1= 327 MW and ST2 = 326 MW) capacity. The total generation capacity is
approximately 1743.1 MW.

h) Sur IPP
Sur IPP was commissioned in 2014. There are five gas turbines of 248.6 MW capacity and three steam
turbines (ST1& ST2) with a capacity of 310 MW while the capacity of ST3 is 155 MW. In 2020, the total
capacity will reach approximately 2018.2 MW working in a combined cycle.

I) Ibri IPP
Ibri IPP awarded in December 2015 to Ad Dhahirah Power Generation Company; the plant was
commissioned in 2019. There are four gas turbines of 242.7 MW capacity each and two steam turbines of
(ST1= 285 MW and ST2 = 286 MW) capacity. The total generation capacity is approximately 1541.7 MW.

Page | 51
Five-Year Annual Transmission Capability Statement (2020 - 2024)

6.1.2 Existing generation of Dhofar

Three gas-based power stations and a renewable power plant supply Dhofar transmission system in summer
2020 as follows:
 NPS

 Salalah Power & Desalination Plant


 Salalah II IPP
 Dhofar Wind Farm

The four power stations are described briefly below:


a) NPS
The initial development of NPS started in 2002. The power plant has eight gas turbines where six of them
are connected to 132kV system while the other two are connected to 33kV system. They are operating in
open-cycle and the gross site rating of the units varies from 19.8 MW to 37 MW. The net generation
capacity of the power station is approximately 272.9 MW.
b) Salalah Power & Desalination Plant
Salalah Power & Desalination Plant was commissioned in 2010. It has five gas turbines installed with a
rate of 56.2 MW and two steam turbines with a rate of 82 MW. The gross generation capacity of the power
station is approximately 445 MW.
c) Salalah II IPP
Salalah II IPP was completed in January 2018. It has five gas turbines installed with a rate of 69 MW and
two steam turbines with a rate of 84 MW. The gross generation capacity of the power station is
approximately 444 MW.
d) Dhofar Wind Farm
This plant is considered as the first renewable energy power plant and was commissioned in Q3 2019. It
consists of 13 turbines, each turbine produces about 3.85MW and the total capacity for the plant is 50 MW.

Table 4 lists on a yearly basis the existing and committed future generating capacity over the period 2020-
2024. The table presents the gross and net maximum capacity for each generating unit at each power station
and takes into account the desalination load where appropriate.

Page | 52
Five-Year Annual Transmission Capability Statement (2020 - 2024)

Table 4: Existing and committed future generating capacity


Net Generating Capacity (MW)
Power Station Type Unit
2020 2021 2022 2023 2024
MIS
Gas Turbine GT 1 82.3 82.3 0.0 0.0 0.0
Gas Turbine GT 2 82.3 82.3 0.0 0.0 0.0
Gas Turbine GT 3 82.3 82.3 0.0 0.0 0.0
Gas Turbine GT 4 84.8 84.8 0.0 0.0 0.0
Rusail IPP Gas Turbine GT 5 84.8 84.8 0.0 0.0 0.0
Gas Turbine GT 6 84.8 84.8 0.0 0.0 0.0
Gas Turbine GT 7 96.9 96.9 0.0 0.0 0.0
Gas Turbine GT 8 95.6 95.6 0.0 0.0 0.0
Net Generation 693.5 693.5 0.0 0.0 0.0
Gas Turbine GT1A 0.0 0.0 0.0 0.0 0.0
Gas Turbine GT1B 0.0 0.0 0.0 0.0 0.0
Gas Turbine GT1C 0.0 0.0 0.0 0.0 0.0
Manah IPP
Gas Turbine GT2A 91.1 91.1 91.1 91.1 91.1
Gas Turbine GT2B 91.1 91.1 91.1 91.1 91.1
Net Generation 182.2 182.2 182.2 182.2 182.2
Gas Turbine GT 1A 97.1 97.1 0.0 0.0 0.0
Gas Turbine GT 1B 97.1 97.1 0.0 0.0 0.0
Al Kamil Power Plant
Gas Turbine GT 1C 97.1 97.1 0.0 0.0 0.0
Net Generation 291.4 291.4 0.0 0.0 0.0
Gas Turbine GT 1 99.4 99.4 0.0 0.0 0.0
Gas Turbine GT 2 99.4 99.4 0.0 0.0 0.0
Barka I Power & Desalination Plant
Steam Turbine ST 198.7 198.7 0.0 0.0 0.0
Net Generation 397.5 397.5 0.0 0.0 0.0
Gas Turbine GT 1 122.8 122.8 122.8 122.8 0.0
Gas Turbine GT 2 122.8 122.8 122.8 122.8 0.0
Gas Turbine GT 3 122.8 122.8 122.8 122.8 0.0
Barka II IPP
Steam Turbine ST1 160.0 160.0 160.0 160.0 0.0
Steam Turbine ST2 160.0 160.0 160.0 160.0 0.0
Net Generation 688.5 688.5 688.5 688.5 0.0
Gas Turbine GT 1 247.5 247.5 247.5 247.5 247.5
Gas Turbine GT 2 247.5 247.5 247.5 247.5 247.5
Barka III IPP
Steam Turbine ST 270.4 270.4 270.4 270.4 270.4
Net Generation 765.5 765.5 765.5 765.5 765.5

Page | 53
Five-Year Annual Transmission Capability Statement (2020 - 2024)

Table 4 (continued): Existing and committed future generating capacity


Net Generating Capacity (MW)
Power Station Type Unit
2020 2021 2022 2023 2024
MIS
Gas Turbine GT 1 125.7 125.7 0.0 0.0 0.0
Gas Turbine GT 2 125.7 125.7 0.0 0.0 0.0
Gas Turbine GT 3 125.7 125.7 0.0 0.0 0.0
Sohar I Power & Desalination Plant Steam Turbine ST 220.0 220.0 0.0 0.0 0.0
Gross Generation 597.0 597.0 0.0 0.0 0.0
Desalination load 31.0 31.0 0.0 0.0 0.0
Net Generation 566.0 566.0 0.0 0.0 0.0
Gas Turbine GT 1 247.5 247.5 247.5 247.5 247.5
Gas Turbine GT 2 247.5 247.5 247.5 247.5 247.5
Sohar II IPP
Steam Turbine ST 270.4 270.4 270.4 270.4 270.4
Net Generation 765.5 765.5 765.5 765.5 765.5
Gas Turbine GT 1 272.5 272.2 271.6 271.9 271.7
Gas Turbine GT 2 272.5 272.2 271.6 271.9 271.7
Steam Turbine ST1 327.0 327.0 327.0 327.0 327.0
Sohar III IPP Gas Turbine GT 3 272.5 272.2 271.6 271.9 271.7
Gas Turbine GT 4 272.5 272.2 271.6 271.9 271.7
Steam Turbine ST2 326.0 326.0 326.0 326.0 326.0
Net Generation 1743.1 1741.8 1739.3 1740.7 1739.7
Gas Turbine GT 1 248.6 248.6 248.6 248.6 248.6
Gas Turbine GT 2 248.6 248.6 248.6 248.6 248.6
Steam Turbine ST1 310.0 310.0 310.0 310.0 310.0
Gas Turbine GT 3 248.6 248.6 248.6 248.6 248.6
Sur IPP Gas Turbine GT 4 248.6 248.6 248.6 248.6 248.6
Steam Turbine ST2 310.0 310.0 310.0 310.0 310.0
Gas Turbine GT 5 248.6 248.6 248.6 248.6 248.6
Steam Turbine ST3 155.0 155.0 155.0 155.0 155.0
Net Generation 2018.2 2018.2 2018.2 2018.2 2018.2
Gas Turbine GT 1 242.7 242.4 242.1 241.9 241.7
Gas Turbine GT 2 242.7 242.4 242.1 241.9 241.7
Steam Turbine ST1 285.0 285.0 285.0 285.0 285.0
Ibri IPP Gas Turbine GT 3 242.7 242.4 242.1 241.9 241.7
Gas Turbine GT 4 242.7 242.4 242.1 241.9 241.7
Steam Turbine ST2 286.0 286.0 286.0 286.0 286.0
Net Generation 1541.7 1540.6 1539.6 1538.5 1537.7
Photovoltaic Technology 0.0 0.0 450.0 450.0 450.0
Ibri Solar PV IPP2
Net Generation 0.0 0.0 450.0 450.0 450.0
Photovoltaic Technology 0.0 0.0 0.0 150.0 300.0
Manah Solar PV IPP3
Net Generation 0.0 0.0 0.0 150.0 300.0

2
Solar PV output at Peak (3-4 pm during summer) expected to be about 90% of the total installed capacity (90% of 500 MW)
3
Solar PV output at Peak (3-4 pm during summer) expected to be about 30% of the total installed capacity (30% of 1000 MW)

Page | 54
Five-Year Annual Transmission Capability Statement (2020 - 2024)

Table 4 (continued): Existing and committed future generating capacity


Net Generating Capacity (MW)
Power Station Type Unit
2020 2021 2022 2023 2024
MIS
Combined Cycle 0.0 0.0 600.0 600.0 600.0
Power 2022 4
Net Generation 0.0 0.0 600.0 600.0 600.0
Combined Cycle 0.0 0.0 0.0 0.0 700.0
Power 2024 4
Net Generation 0.0 0.0 0.0 0.0 700.0
Doubly Fed Induction
0.0 0.0 0.0 0.0 19.0
JBB Ali Wind Farm5 Technology
Net Generation 0.0 0.0 0.0 0.0 19.0
Doubly Fed Induction
0.0 0.0 0.0 0.0 68.5
Duqm Wind Farm6 Technology
Net Generation 0.0 0.0 0.0 0.0 68.5
Barka Waste to Energy Plant Net Generation 0.0 0.0 0.0 0.0 100.0

Demand Response7 Net Generation 0.0 30.0 40.0 50.0 70.0


Dhofar
Gas Turbine GT1 37.0 37.0 37.0 37.0 37.0
Gas Turbine GT2 37.0 37.0 37.0 37.0 37.0
Gas Turbine GT3 37.0 37.0 37.0 37.0 37.0
Gas Turbine GT4 37.0 37.0 37.0 37.0 37.0
NPS Gas Turbine GT5 37.0 37.0 37.0 37.0 37.0
Gas Turbine GT6 37.0 37.0 37.0 37.0 37.0
Gas Turbine GT7 19.8 19.8 19.8 19.8 19.8
Gas Turbine GT8 31.0 31.0 31.0 31.0 31.0
Net Generation 273.0 273.0 273.0 273.0 273.0
Gas Turbine GT 1 56.2 56.2 56.2 56.2 56.2
Gas Turbine GT 2 56.2 56.2 56.2 56.2 56.2
Gas Turbine GT 3 56.2 56.2 56.2 56.2 56.2
Gas Turbine GT 4 56.2 56.2 56.2 56.2 56.2
Salalah Power & Desalination Gas Turbine GT 5 56.2 56.2 56.2 56.2 56.2
Plant Steam Turbine ST1 82.0 82.0 82.0 82.0 82.0
Steam Turbine ST2 82.0 82.0 82.0 82.0 82.0
Gross Generation 445.0 445.0 445.0 445.0 445.0
Desalination load 15.0 15.0 15.0 15.0 15.0
Net Generation 430.0 430.0 430.0 430.0 430.0
Gas Turbine GT 1 69.0 68.8 68.5 68.5 68.5
Gas Turbine GT 2 69.0 68.8 68.5 68.5 68.5
Steam Turbine ST1 84.0 84.0 84.0 84.0 84.0
Salalah II IPP Gas Turbine GT 3 69.0 68.8 68.5 68.5 68.5
Gas Turbine GT 4 69.0 68.8 68.5 68.5 68.5
Steam Turbine ST2 84.0 84.0 84.0 84.0 84.0
Net Generation 444.0 443.0 442.0 442.0 442.0
Doubly Fed Induction
18.0 18.0 18.0 18.0 18.0
Dhofar Wind Farm Technology
Net Generation 18.0 18.0 18.0 18.0 18.0

4
As per OPWP data, the unit capacities and locations for Pow er 2022 and Pow er 2024 w ill be provided after aw arding.
5
It is part of OPWP w ind 2024. Wind turbines output expected to be about 20% of the total installed capacity (20% of 100 MW) .
6
It is part of OPWP w ind 2024. Wind turbines output expected to be about 35% of the total installed capacity (35% of 200 MW) .
7
As per OPWP data, the exact capacity of Demand Response w ill be determine after finalizing the Demand Response Project.

Page | 55
Five-Year Annual Transmission Capability Statement (2020 – 2024)

Reference to Figure 20 and Figure 21, the generation mix has been divided into three types: Gas IPP,
Combined Cycle IPPs and Renewable. Further, comparison has been carried out between year 2020 and
2024 for the generation percentage of MIS and Dhofar System.

Generation Percentage 2020 for both MIS


& Dhofar
0.17%

13.25%

Gas IPPs
Combined Cycle IPPs
86.58% Renewable

Figure 20: Generation Percentage 2020 for both MIS & Dhofar

Generation Percentage 2024 for both MIS


& Dhofar

10% 5%

Gas IPPs
Combined Cycle IPPs
Renewable
85%

Figure 21: Generation Percentage 2024 for both MIS & Dhofar

Page | 56
Five-Year Annual Transmission Capability Statement (2020 – 2024)

6.2 Planned Retirements of Existing Plant


There are a number of planned retirements of the existing units from 2020 to 2024 as per OPWP generation
data. The planned retirements are as follows:

a) Rusail IPP
At the end of 2021, it is planned to retire all existing generating units.

b) Al Kamil Power Plant


At the end of 2021, it is planned to retire all existing generating units.

c) Barka I Power & Desalination Plant


At the end of 2021, it is planned to retire all existing generating units.

d) Manah Power Plant


By 2020, GT1 (A, B&C) units will be retired and only GT2A & GT2B will be in operation.

e) Sohar I Power & Desalination Plant


By end of 2021, it is planned to retire all existing generating units.

f) Barka II Power & Desalination Plant


At the end of 2023, it is planned to retire all existing generating units.

6.3 Planned Future Generation (2020-2024)

6.3.1 Planned Future Generation at MIS


There are four main generation developments planned for the period from 2020 to 2024:

a) Ibri Solar PV IPP


The solar plant will be commissioned in 2022 with a total installed capacity of 500 MW. This solar plant
will be located at Ibri area and will be connected to the MITS 220kV transmission system.
b) Manah Solar PV IPP
The first phase of Manah solar plant will be commissioned in 2023 with a total capacity of 500 MW while
the second phase will be commissioned in 2024 with a total capacity of 500 MW. This solar plant will be
located at Manah area and will be connected to the MITS 400kV transmission system.
c) Power 2022
Power 2022 has a total amount of around 600MW in MIS. The awarded bidders will be announced by Q2
2020. Power 2022 is planned to be covered by retaining some or all of the planned retired generating units
at existing IPPs (Rusail, Barka I, Al Kamil and Sohar I). As there is no firm confirmation about the location
and capacity of power 2022 at the time of preparing this Capability Statement, OETC has distributed this
power in the system according to the transmission system performance requirements.
d) Power 2024
Power 2024 has a total amount of around 700MW in MIS. Unsuccessful bidders in Power 2022 will
compete for Power 2024. As there is no firm confirmation about the location and capacity of power 2024

Page | 57
Five-Year Annual Transmission Capability Statement (2020 – 2024)

at the time of preparing this Capability Statement, OETC has distributed this power in the system according
to the transmission system performance requirements.
e) Duqm Wind Farm
It is proposed to be located in Duqm area. As per OPWP generation plan, it is expected to be commissioned
by peak 2024. The total capacity for the plant is expected to be 200MW.
f) JBB Ali Wind Farm
As per OPWP generation plan, the proposed location is in JBB Ali area in Al Sharqiyah South governorate
with a total capacity of 100MW and expected to be connected to the system by peak 2024.
g) Barka Waste to Energy Plant
This plant will be the first of its type in Oman. It will be connected to Madinat Barka 132/33kV grid station
via a new 132kV OHL of about 3.6km with maximum capacity of 160MW.

6.3.2 Planned Future Generation at Dhofar


There will be no future generation plants in Dhofar area within years 2020-2024.
Table 5 summarises the net capacity of the additional future generating plants over the period from 2020 to
2024.
Table 5: New Contracted and Planned Generating Capacity
Net Generating Capacity (MW)
Power Station Type
2020 2021 2022 2023 2024
MIS System
Ibri Solar PV IPP Net Generation 0.0 0.0 450.0 450.0 450.0
Manah Solar PV IPP Net Generation 0.0 0.0 0.0 150.0 300.0
Power 2022 Net Generation 0.0 0.0 600.0 600.0 600.0
Power 2024 Net Generation 0.0 0.0 0.0 0.0 700.0
JBB Ali Wind Farm Net Generation 0.0 0.0 0.0 0.0 19.0
Duqm Wind Farm Net Generation 0.0 0.0 0.0 0.0 68.5
Barka Waste to Energy Plant Net Generation 0.0 0.0 0.0 0.0 100.0

6.4 Non-Contracted Generating Capacity


There are a number of private industrial customers that are directly connected to the transmission system
and they are either operating or planning to operate their own on-site generation. The largest generating
plant among these is Sohar Aluminium, which may export up to 300 MW during the summer period and
import the same during the winter time. The interconnected system and the private customer generating
plants can be made available with the customer’s agreement to support the contracted generation under
emergency conditions in order to avoid power cuts in northern Oman. These generators are termed as “non-
contracted” generating plants. Table 6 shows the non-contracted generating capacity for the period from
2020 to 2024.

Page | 58
Five-Year Annual Transmission Capability Statement (2020 – 2024)

Table 6: Non-Contracted Generating Capacity


Net Non-Contracted Generating Capacity (MW)
Power Station
2020 2021 2022 2023 2024
MIS
GCCIA through UAE (Transco Abu Dhabi) 400 400 400 400 400
PDO 60 60 60 60 60
Sohar Aluminium 300 300 300 300 300
Oman Cement Company (OCC) 0-5 0-5 0-5 0-5 0-5
Ministry of Defense 0-5 0-5 0-5 0-5 0-5
Oman India Fertilizer CO 0-5 0-5 0-5 0-5 0-5
Net Generation 775 775 775 775 775

Table 7 summarises the Centrally Dispatched Net Generation Capacity available over the period 2019–
2024, with the new generation at Ibri IPP and Sohar III IPP in service. It covers the planned retirement of
generating units at Rusail IPP, Kamil IPP, Barka I Power & Desalination Plant, Sohar I Power &
Desalination Plant, Barka II Power & Desalination Plant and Manah power plant.
Table 7: Centrally Dispatchable and Non-Dispatchable Generating Capacity on OETC System
Net Generating Capacity (MW)
Power Stations
2019 2020 2021 2022 2023 2024
MIS System
Rusail IPP 693.5 693.5 693.5 0.0 0.0 0.0
Manah IPP 263.2 182.2 182.2 182.2 182.2 182.2
Al Kamil IPP 291.4 291.4 291.4 0.0 0.0 0.0
Barka I Power & Desalination Plant 397.5 397.5 397.5 0.0 0.0 0.0
Barka II IPP 688.5 688.5 688.5 688.5 688.5 0.0
Barka III IPP 765.5 765.5 765.5 765.5 765.5 765.5
Sohar I Power & Desalination Plant 566.0 566.0 566.0 0.0 0.0 0.0
Sohar II IPP 765.5 765.5 765.5 765.5 765.5 765.5
Sohar III IPP 1745.0 1743.1 1741.8 1739.3 1740.7 1739.7
Sur IPP 2018.2 2018.2 2018.2 2018.2 2018.2 2018.2
Ibri IPP 1543.0 1541.7 1540.6 1539.6 1538.5 1537.7
Ibri Solar PV IPP 0.0 0.0 0.0 450.0 450.0 450.0
Manah Solar PV IPP 0.0 0.0 0.0 0.0 150.0 300.0
Power 2022 0.0 0.0 0.0 600.0 600.0 600.0
Power 2024 0.0 0.0 0.0 0.0 0.0 700.0
Duqm Wind Farm 0.0 0.0 0.0 0.0 0.0 68.5
JBB Ali Wind Farm 0.0 0.0 0.0 0.0 0.0 19.0
Barka Waste to Energy Plant 0.0 0.0 0.0 0.0 0.0 100.0
Demand Response 0.0 0.0 30.0 40.0 50.0 70.0
Total Generating Capacity (MW) 9737.3 9653.1 9680.8 8788.8 8949.2 9316.4
Retirements 0.0 81.0 0.0 1948.4 0.0 688.5
Dhofar System
NPS 273.0 273.0 273.0 273.0 273.0 273.0
Salalah Power & Desalination Plant 430.0 430.0 430.0 430.0 430.0 430.0
Salalah II IPP 446.0 445.0 444.0 443.0 442.0 442.0
Dhofar Wind Farm 0.0 18.0 18.0 18.0 18.0 18.0
Total Generating Capacity (MW) 1148.0 1165.0 1164.0 1163.0 1163.0 1163.0
Retirements 0.0 0.0 0.0 0.0 0.0 0.0

Page | 59
Five-Year Annual Transmission Capability Statement (2020 – 2024)

6.5 Interconnections
6.5.1 Interconnection with the GCCIA Grid through UAE (Transco Abu Dhabi)

The 220kV transmission interconnection with the United Arab Emirates (Transco Abu Dhabi) was
completed in the first quarter of 2007. The interconnection connects Mahadha grid station in Oman
(Al Wasit) to Al oha grid station in Al Ain in the UAE. In the longer term, the principal technical benefit
to be obtained from connecting Oman to the GCCIA Grid is in the reduction of spinning reserve
requirement, which will be shared between the members of the GCCIA Grid and will help to reduce the
installed capacity from the generation. However, operation of the interconnection will allow Oman to
import/export power from the GCCIA Grid to meet any potential generation shortfall. Oman has signed
officially the agreement with the GCCIA in November 2014 and became a part of the state members.

6.5.2 Interconnection with PDO

OETC transmission system is interconnected with the transmission system of the Petroleum Development
Oman (PDO), which provides electricity to its concession areas across the central region of Oman for the
purpose of oil exploration and development. The interconnection is made at 132kV between Nizwa grid
station on the MIS and Nahadah 132kV station on the PDO 132kV network by 67 km overhead line. The
overhead line is owned by PDO. Under normal conditions, the power transfer between the two networks
is allowed to float around zero MW, with power transfers balanced out over a period.
In addition, Dhofar transmission system is interconnected with the transmission system of the PDO. The
interconnection is made at 132kV between Thumrait grid station on the Dhofar system, Dhofar Wind Farm
and Harweel 132kV grid station on the PDO network (132kV OHL Thurmrait-Wind Farm 76.5 km &
132kV OHL Wind Farm-Harweel 30 km). The interconnection essentially allows OETC and PDO to supply
limited power to each other in emergency conditions on either system.

OETC has received a new connection application from PDO on 3rd of July 2018. OETC has studied the
connection application and it was found that a new 400kV injection point at Nahadah 132kV station via
LILO the existing Ibri – New Izki 400kV OHL is the preferred option. In addition, there will be two new
injection points in PDO system at Barik and Suwaihat. Having new interconnection points via the 400kV
system between OETC and PDO will enhance the security of supply of both networks as well as maximizing
other benefits such as capacity saving and reducing the spinning reserve etc.

6.5.3 400kV North-South Interconnection

The feasibility study for the 400kV North to South Interconnection was completed by mid of 2018. The
objective of this project is to assess the technical and economic feasibility of a new 400kV interconnection
between MIS-PDO-Dhofar and the isolated region of Duqm. This study has assessed different options and
highlighted the benefits of this project. The feasibility study has concluded that the interconnection project
has a positive economic Net Present Value (NPV) considering all main objectives that were identified by

Page | 60
Five-Year Annual Transmission Capability Statement (2020 – 2024)

OETC, OPWP, PDO and RAEC. The expected benefits include fuel savings due to improved dispatch
coordination among the power systems, access to areas with renewable energy potential, sharing of spinning
reserves (reducing operating costs), and improved grid security.
RAEC has submitted two connection applications on 6th of January 2019 for constructing two grid stations
at Mahout and Duqm. Further, PDO has submitted two connection applications for Barik and Suwaihat on
12th of June 2019 requesting for 500 MW export and import power at each grid station. In addition, the new
400kV interconnection project will facilitate the connection to PDO system, Duqm and Mahout Systems
and currently the project is in the design stage. The execution of the project will be in two phases: the first
phase will include constructing Suwaihat, Duqm and Mahout grid stations in order to displace the diesel
generation in Duqm and Mahout areas by Q2 2023. The second phase will be completing the 400kV
backbone from Nahadah to Barik and Suwaihat grid stations and the expected completion date will be end
of Q4 2024.

6.6 Economic Dispatch


The Load Dispatch Centre (LDC) of OETC dispatches generation based on its availability as stated by the
Generator on a day-ahead basis, and its price is as listed by the Oman Power and Water Procurement
Company (OPWP). Under circumstances where the system frequency is seen to stray outside the specified
limits, LDC will issue dispatch instructions to Generators based on Merit Order to rectify the situation.

6.7 Spinning Reserve


The new spinning reserve mechanism has been approved by AER in Price Control-5. The target spinning
reserve is 250MW with 130MW up margin. Therefore, Load Dispatch Centre has to maintain the acceptable
spinning reserve which is between 250 MW to 380 MW. OETC has to be in the acceptable range for 67%
of total hours of the year in order to maintain compliance with AER mechanism.

Page | 61
Five-Year Annual Transmission Capability Statement (2020 – 2024)

7. Demand Forecast and Generation Availability

7.1 System Demand


Maximum demand usually occurs on the OETC transmission system on weekdays in the summer months
(May, June or July), during a period of particularly high temperature and humidity. The growth in air
conditioning equipment in domestic and commercial premises in Oman has ensured that peak demand
usually occurs during the early morning or afternoon. Figure 22 and Figure 23 show the 24-hour demand
profile for the transmission system on the day of the 2019 system gross peak demand (i.e. 30/06/2019 MIS
System and 14/06/2019 Dhofar System). The 2019 MIS system gross peak demand of 6539.75 MW was
recorded at 14:55 hours and 2019 Dhofar system gross peak demand of 594.48 MW was recorded at 04:04
hours by OETC Load Dispatch Centre. The historic growth in system gross peak demand over the period
(2003-2019) is shown in Table 8.

Max Demand Profile


7000
6000
5000
Load (MW)

4000
3000
2000
1000

Time (hrs)

Figure 22: MIS Load on 2019 Peak Day

Page | 62
Five-Year Annual Transmission Capability Statement (2020 – 2024)

Max Demand Profile


700
600
500
Load (MW)

400
300
200
100

Time (hrs)

Figure 23: Dhofar System Load on 2019 Peak Day

Table 8: Historic Growth in Peak Demand and Transmission Losses (2003 – 2019)

2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019
MIS S ystem
S ystem Max
Demand
(MW) based 2232 2371 2495 2613 2773 3139 3546 3614 4000 4448 4634 5269 5744 6105 6305 6335 6540
on gross
demand
Annual
growth rate
based on --- 6.23 5.23 4.73 6.12 13.20 12.97 1.92* 10.69 11.19 4.18 13.70 9.01 6.28 3.28 0.48 3.23
gross demand
(%)
S ystem Max
Demand
(MW) based 2139 2294 2395 2505 2662 3033 3342 3504 3765 4247 4328 4872 5472 5826 6016 6036 6166
on net
demand
Transmission
S ystem
Losses (MW) 35 38 40 37 40 61 80 60 62 54 115 165 93 95 101 133 187
at system
peak
Transmission
S ystem 1.64 1.66 1.67 1.47 1.5 2 2 1.7 1.6 1.3 2.64 3.4 1.7 1.6 1.7 2.1 2.86
Losses (%)
*T he reduction in the annual growth is due to the Phet Cyclone

Page | 63
Five-Year Annual Transmission Capability Statement (2020 – 2024)

Table 8 (continued): Historic Growth in Peak Demand and Transmission Losses (2003 – 2019)
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019
Dhofar S ystem
S ystem Max
Demand
(MW) based 178.3 180.9 199.3 232.3 253 260.4 297.4 336.2 348 389.3 421.7 438.9 495 523 577 567 594.5
on gross
demand
Annual
growth rate
based on --- 1.46 10.17 16.56 8.91 2.92 14.21 13.05 3.51 11.87 8.32 4.08 12.78 5.66 10.24 -1.73 4.85
gross
demand (%)
S ystem Max
Demand
(MW) based --- --- --- --- --- --- --- --- --- --- --- 427 473 513 531 517 540.2
on net
demand
Transmissio
n S ystem
Losses (MW) --- --- --- --- --- --- --- --- --- --- --- 4 15 2 21 23 8.7
at system
peak
Transmissio
n S ystem --- --- --- --- --- --- --- --- --- --- --- 0.8 3.1 0.4 3.7 4.4 1.46
Losses (%)

Minimum demand generally occurs on the transmission system during night-time in winter months
(December/January) when electricity consumption in all major load categories is reduced. In 2019, the MIS
system minimum demand was 1735.57 MW and this occurred on 27/12/2019 at 03:40 AM while 2019
Dhofar system minimum demand was 216.7 MW and this occurred on 12/01/2019 at 07:30 AM. The 2019
system minimum demand at MIS system was about 26.54% and at Dhofar system was about 36.45% of the
2019 system peak demand. The 24-hour profile for the day of minimum demand is shown in Figure 24 and
Figure 25 for the MIS and Dhofar system respectively.

Page | 64
Five-Year Annual Transmission Capability Statement (2020 – 2024)

Min Demand Profile


3000

2500

2000
Load (MW)

1500

1000

500

Time (hrs)

Figure 24: MIS Load on 2019 Minimum Load Day

Min Demand Profile


350
300
250
Load (MW)

200
150
100
50

Time (hrs)

Figure 25: Dhofar System Load on 2019 Minimum Load Day

Page | 65
Five-Year Annual Transmission Capability Statement (2020 – 2024)

7.2 Demand Forecast


Under clause 3 of Condition 27 of OETC Transmission and Dispatch Licence it is stated that:

“The Licensee shall, when preparing the Capability Statement ensure that the forecasts of electricity flows
and loading on each part of the Transmission System are consistent with the prevailing electricity demand
forecasts prepared and used by the OPWP for the purposes of the Statement of future capacity requirements
required by Condition 5 of the OPWP licence”.

The OPWP demand forecast is based on data supplied to them by the four Distribution Companies (i.e.
MEDC, MZEC, MJEC and DPC) and RAEC which also includes demand forecasts for the major customers
that are, or will be, directly connected to OETC transmission system at either 220kV or 132kV in their
respective supply areas. In addition, Distribution Companies have provided demand forecast data to OETC
taking into account the individual load at each supply connection points. The Distribution Companies
forecast is provided in terms of:

a) The growth in major industrial loads

b) The growth in major tourism loads

c) The annual domestic growth

d) The growth in major commercial loads

The supplied forecast to OPWP relates to the total for all Distribution Companies and RAEC and do not
indicate how this load is allocated to the individual grid supply points. The forecast data provided to OPWP
includes major future connections and the cumulative increase in load over the seven-year period covered
by the OPWP Statement. OPWP has then reviewed this data and taken a view on the probability that the
individual schemes will proceed and if so, the rate at which it’s load will develop. The outcome of this
review is presented as OPWP demand forecast in it’s Seven-Year Statement.

The OPWP demand forecast was therefore taken as the starting point for developing the demand forecast
presented in this OETC Capability Statement. The OETC forecast, however, is required to identify the
future demand at individual grid station at the system peak for each year over the period 2020 to 2024, since
this information is required for the system studies.

Analysis of the demand forecast data (Expected Case) submitted by OPWP identified basic annual
percentage rates of 4.4% for the growth in peak demand in the MZEC, MEDC ,MJEC and RAEC supply
areas and 6.9% for the growth in peak demand in the DPC supply area. It should be noted that the peak
growth forecast provided by OPWP is also including the estimated transmission losses (2%) whilst, OETC
peak growth forecast does not include the transmission losses, but it is calculated in an annual basis based
on the simulations system studies. These rates have been applied to the grid station demands in the
respective supply areas as noted by the OETC Load Dispatch Centre at the 2019 MIS system peak (i.e.
30/06/2019, 14:55 hour) and 2019 Dhofar system peak (i.e.14/06/2019, 04:04 hour). The demand associated

Page | 66
Five-Year Annual Transmission Capability Statement (2020 – 2024)

with major industrial and tourism projects as assessed by OPWP (with diversity taken into account) was
then superimposed on to the steady growth in the basic demand to produce a basic forecast. Peak demand
is expected to grow at a lower rate than energy demand due to the introduction of Cost-Reflective Tariffs
(CRT) for large commercial, government, and industrial consumers in 2017. The CRT is time-
differentiated, where the tariff is more representative of the actual cost of supply at the different periods
during the year, noting higher costs during peak and summer periods, and lower costs during off-peak and
winter periods. Some large customers are expected to shift their demand in response to the new tariff.
Section 5 of this Statement has identified a number of new grid supply points that are scheduled to come
into service to meet the summer peak demands from 2020 onwards. These gird stations will provide a load
relief to the most heavily loaded grid stations and in some cases supply new loads.

The Distribution Companies’ plans for load transfers from existing grid stations that are heavily loaded to
new grid stations are one of the most important elements of the demand forecast. Table 9 summarises the
load transfers adopted in the studies based on consideration of what is required and what OETC has
considered viable. However, OETC acknowledges that this aspect of the forecast needs to be improved in
future and believes that it would be helpful if Distribution Companies were to give greater consideration to
feasible load transfers when planning their distribution networks, and to develop proposals for load transfers
in coordination with OETC. In addition, the TSS requirement shall be considered at every grid supply point
and all new requirements shall be indicated clearly.

Table 9: Expected Load Transfers between Grid Supply Points (2020-2024)


Load Transfer (MW)
From Grid Station To Grid Station
2020 2021 2022 2023 2024
Muscat Area
Airport Heights TX-1 & TX-2 Airport Heights TX-3 & TX-4 30
Amerat TX-1 & TX-2 Amerat TX-3 & TX-4 20 7
A'salam TX-1 & TX-2 A'salam TX-3 & TX-4 30 12
A'salam TX-1 & TX-2 Mobella Industrial TX-1 & TX-2 45
A'salam TX-3 & TX-4 Mobella Industrial TX-3 & TX-4 20
Bousher TX-1 & TX-2 Ghala Hieghts TX-1 & TX-2 55
Bousher TX-1 & TX-2 MSQ TX-3 & TX-4 5
Bousher TX-3 & TX-4 Ghala Hieghts TX-3 & TX-4 55
Bousher TX-3 & TX-4 Bousher TX-1 & TX-2 25
Bousher TX-3 & TX-4 Ghala Hieghts TX-1 & TX-2 10
Ghala TX-1 & TX-2 Ghala TX-3 & TX-4 50
Ghubrah Ghala Hieghts TX-1 & TX-2 12
Jahloot Amerat TX-3 & TX-4 10
Mawalleh North 2X125MVA Khoudh TX-1 & TX-2 15
Mawalleh South TX-1 & TX-2 Mawalleh South TX-3 & TX-4 5

Page | 67
Five-Year Annual Transmission Capability Statement (2020 – 2024)

Table 9 (continued): Expected Load Transfers between Grid Supply Points (2020-2024)
Load Transfer (MW)
From Grid Station To Grid Station
2020 2021 2022 2023 2024
Muscat Area
Mawalleh South TX-1 & TX-2 Khoudh TX-1 & TX-2 10
Mawalleh South TX-3 & TX-4 Khoudh TX-1 & TX-2 20
Mawalleh South TX-3 & TX-4 Khoudh TX-3 & TX-4 25
Mobella A'salam TX-3 & TX-4 10 8
Mobella Mobella Industrial TX-3 & TX-4 60
Seeb Main TX-1 & TX-2 Seeb Main TX-3 & TX-4 8
Seeb Main TX-1 & TX-2 Khoudh TX-3 & TX-4 35
Total (MW) 285.0 147.0 105.0 0.0 45.0
Mazoon Area
Barka Main TX-1 & TX-2 Hay Asim 30
Barka Main TX-1 & TX-2 Madinat Barka TX-3 & TX-4 25
Barka Main Tx-3 Mobella Industrial 8 17 12.8
Izki 2X125MVA Birkat Al Mouz 8.9
JBB Ali Al Jawabi 80
Khadhra TX-1 & TX-2 Khadhra TX-3 & TX-4 30
Madinat Barka TX-1 & TX-2 Madinat Barka TX-3 & TX-4 24
Mudhaibi 2X125MVA Sinaw 35
Mudhaibi 2X125MVA Samad 25
Mudhairib Bedyah 49.8
Muladah TX-1 & TX-2 Muladah TX-3 & TX-4 23
Nizwa Birkat Al Mouz 41.9
Rustaq Wadi Bani Auwf 49
Sumail 2X125MVA Sumail Industrial Area 53.6
Total (MW) 223.6 196.6 12.8 0 80
Majan Area
Al Hayl Yanqul 33.5
Bureimi Buriami Industrial TX-3 & TX-4 34.6 1.4
Buriami Industrial TX-1 & TX-2 Buriami Industrial TX-3 & TX-4 15.8 0.5 0.4 0.4 0.6
Ibri 2x63MVA Dreez 2
Ibri TX-1 & TX-2 Dank 2.3
Liwa TX-1 & TX-2 Sohar Free Zone TX-1 & TX-2 24.8
Liwa TX-1 & TX-2 Sohar Free Zone TX-3 & TX-4 49.1

Page | 68
Five-Year Annual Transmission Capability Statement (2020 – 2024)

Table 9 (continued): Expected Load Transfers between Grid Supply Points (2020-2024)
Load Transfer (MW)
From Grid Station To Grid Station
2020 2021 2022 2023 2024
Majan Area
Liwa TX-1 & TX-2 Shinas 6 1
Mahadah Buriami Industrial TX-3 & TX-4 7.8 0.4 0.2 0.3
Saham Uwaynat TX-1 & TX-2 3
Saham Dil Abdusalam 1 3 0.1 0.1 0.1
Shinas 2X125MVA Madinat Shinas 4
SIA Liwa TX-1 & TX-2 3 0.1 0.1 0.1
Sohar TX-1 & TX-2 Uwaynat TX-3 & TX-4 8.1 0.3 0.3 0.3 0.4
Sohar TX-1 & TX-2 Sohar TX-3 & TX-4 8 1 1 0.5 0.4
Sohar TX-3 & TX-4 Sohar TX-1 & TX-2 4 18.7 0.8
Uwaynat TX-1 & TX-2 Uwaynat TX-3 & TX-4 2
Uwaynat TX-3 & TX-4 Uwaynat TX-1 & TX-2 3
Total (MW) 149.7 50.2 12.3 27.2 5.1
Dhofar System
Al Qarm Sa'adah TX-3 & TX-4 9 9
Ashoor Mirbat (2x63MVA) 19.9 1
Ittin Sa'adah TX-1 & TX-2 4.64 8
Ittin Salalah Free Zone TX-3 & TX-4 2
Ittin Shaha'aon (2X125MVA) 3 5
NPS 2X63MVA Sa'adah TX-1 & TX-2 3
NPS 2X63MVA Salalah Free Zone TX-1 & TX-2 2
Sa'adah TX-1 & TX-2 Al Qarm 2
Sa'adah TX-1 & TX-2 NPS 2X63MVA 1
Sa'adah TX-1 & TX-2 Sa'adah TX-3 & TX-4 8 5 3
Sa'adah TX-1 & TX-2 Ittin 3
Sa'adah TX-3 & TX-4 Sa'adah TX-1 & TX-2 4.5
Raysut NPS 2X63MVA 1
Raysut Salalah-IPP 5.6 16.23 15 2 2
Raysut Sa'adah TX-1 & TX-2 1 10
Raysut Sa'adah TX-3 & TX-4 10
Salalah-IPP Raysut 2
Shaha'aon (2X125MVA) Sa'adah TX-3 & TX-4 3
Shaha'aon (2X125MVA) Ittin 1 2
Shaha'aon (2X125MVA) Sa'adah TX-1 & TX-2 3.5 16.25
Shaha'aon (2X125MVA) Salalah-IPP 7.5 2
Thumrait 2X30MVA Thumrait 2X63MVA 28.8
Total (MW) 25.7 112.9 45.0 36.3 2.0

Page | 69
Five-Year Annual Transmission Capability Statement (2020 – 2024)

7.3 System Maximum Net Demand Forecast and Generation Availability


Table 10 shows the grid stations demand forecast for the period 2020–2024 with prospective load transfers
taken into account and the forecast developed in accordance with the methodology described in sub-section
7.2. The introduction of Cost-Reflective Tariffs (CRT) for large commercial, government, and industrial
consumers in 2017 has forced some large customers to manage their demand consumption by either
reducing it or switching off their load during the peak-hours periods in response to the new tariff as shown
in Table 10.
Table 10: OETC Transmission System Net Demand Forecast by Grid Station
Actual Forecast (MW)
Grid Station
2019 2020 2021 2022 2023 2024
MUSCAT AREA
TX-1 & TX-2 108.4 82.7 86.0 89.5 93.1 96.8
Airport Heights
TX-3 & TX-4 0.0 33.0 35.4 44.3 46.4 48.6
Al Falaj 73.8 78.5 84.5 84.5 84.5 84.5
TX-1 & TX-2 105.3 95.8 96.5 104.2 112.6 106.6
Amerat
TX-3 & TX-4 19.2 51.1 63.2 69.6 76.5 99.2
TX-1 & TX-2 143.1 124.5 121.3 84.8 89.8 95.2
A'salam
TX-3 & TX-4 0.0 48.0 89.3 97.4 105.1 93.6
TX-1 & TX-2 124.7 75.9 99.0 102.9 107.0 111.3
Bousher
TX-3 & TX-4 171.0 124.6 104.5 108.7 113.1 107.6
Daghmar 32.0 32.0 32.0 32.0 32.0 32.0
TX-1 & TX-2 92.6 73.4 94.7 96.1 104.6 106.1
Ghala
TX-3 & TX-4 0.0 50.0 51.5 53.0 54.6 56.3
TX-1 & TX-2 0.0 67.0 69.7 71.8 73.9 86.1
Ghala Heights
TX-3 & TX-4 0.0 55.0 67.2 68.9 80.7 82.5
Ghubrah 2x125M VA 112.5 103.9 107.0 110.2 112.4 114.7
TX-1 & TX-2 0.0 0.0 0.0 60.0 64.2 68.1
Mobella Industrial
TX-3 & TX-4 0.0 0.0 0.0 60.0 64.2 88.1
Jahloot 49.5 42.0 44.1 46.3 48.6 51.0
TX-1 & TX-2 0.0 0.0 30.0 31.5 33.1 49.7
Khoudh
TX-3 & TX-4 0.0 0.0 60.0 63.0 66.2 69.5
Mawalleh North 74.3 81.5 86.8 103.4 112.0 101.6
TX-1 & TX-2 99.1 98.1 92.0 95.7 99.5 103.5
Mawalleh South
TX-3 & TX-4 102.9 112.0 71.5 74.4 77.3 80.4
Misfah 64.1 67.3 70.7 74.2 77.9 81.8
Mobella 121.2 122.1 122.7 70.0 74.2 78.7
TX-1 & TX-2 71.3 79.2 87.1 90.2 91.8 93.4
MSQ
TX-3 & TX-4 73.5 76.4 84.5 87.9 89.6 91.4

Page | 70
Five-Year Annual Transmission Capability Statement (2020 – 2024)

Table 10 (continued): OETC Transmission System Net Demand Forecast by Grid Station
Actual Forecast (MW)
Grid Station
2019 2020 2021 2022 2023 2024
MUSCAT AREA
Muttrah 70.5 71.2 71.2 71.2 71.2 71.2
Qurum 91.4 93.2 95.1 97.0 98.9 100.9
Quryiat 50.4 51.9 53.5 55.1 56.7 58.4
TX-1 & TX-2 50.1 54.1 58.4 61.9 65.7 69.6
Rusail Industrial
TX-3 & TX-4 81.8 88.3 95.4 101.1 107.2 113.6
TX-1 & TX-2 130.4 128.9 100.4 104.4 108.6 112.9
Seeb Main
TX-3 & TX-4 73.4 85.1 89.3 92.9 96.6 100.5
Wadi Adai 79.7 81.3 82.9 84.6 86.3 88.0
TX-1 & TX-2 68.4 69.1 69.1 69.1 69.1 69.1
Wadi Kabir
TX-3 & TX-4 59.0 59.6 59.6 59.6 59.6 59.6
Yitti 16.9 17.2 17.6 17.9 18.3 18.7
Muscat Airport 30.4 30.4 30.4 30.4 30.4 30.4
Muscat Steel 0.0 0.0 0.0 0.0 0.0 0.0
Modern Steel 0.0 0.0 0.0 0.0 0.0 0.0
R.O Ghoubrah 22.3 22.0 22.0 22.0 22.0 22.0
Total 2463.2 2626.5 2796.1 2941.7 3075.6 3193.1
Growth (% ) 9.1% 6.6% 6.5% 5.2% 4.6% 3.8%
MAZOON AREA
Adam 2x125M VA 50.0 52.5 55.1 57.9 60.8 62.6
Al Jawabi 0.0 0.0 0.0 0.0 0.0 80.0
Ayjah 69.9 72.7 74.9 89.3 91.6 94.0
Bahla 71.3 74.9 78.6 82.5 86.7 90.1
TX-1 & TX-2 105.9 56.2 59.0 62.0 65.1 67.0
Barka Main
TX-3 35.5 28.6 12.4 0.0 0.0 0.0
Bedyah 0.0 49.8 51.8 53.9 56.0 58.3
Birkat Al Mouz 0.0 50.8 53.8 57.1 60.5 64.1
Blue City 119.5 124.3 128.0 140.8 144.8 148.9
Hay Asim 22.3 53.2 66.6 83.2 84.9 86.7
Ibra 73.6 79.9 83.0 86.2 89.5 92.1
2x40MVA 0.0 0.0 0.0 0.0 0.0 0.0
Izki
2x125M VA 87.5 81.2 87.5 90.0 91.7 93.5
JBB Ali 115.4 120.0 146.8 151.8 157.0 82.4
JBB Hassan 70.4 73.2 83.1 86.2 89.4 92.7
Jebreen 61.5 64.0 66.5 69.2 71.9 74.1
TX-1 & TX-2 106.8 111.1 85.5 88.9 92.5 95.3
Khadhra
TX-3 & TX-4 33.0 34.3 65.7 68.3 71.1 73.2

Page | 71
Five-Year Annual Transmission Capability Statement (2020 – 2024)

Table 10 (continued): OETC Transmission System Net Demand Forecast by Grid Station
Actual Forecast (MW)
Grid Station
2019 2020 2021 2022 2023 2024
MAZOON AREA
TX-1 & TX-2 107.4 111.7 92.2 100.9 103.8 106.7
Madinat Barka
TX-3 & TX-4 0.0 25.0 50.0 52.0 54.1 55.7
Madinat Nizwa 60.8 63.2 65.8 68.4 71.1 73.3
MIS 43.6 45.3 47.2 48.6 50.0 51.5
Mudhaibi 102.9 47.0 48.9 55.7 57.7 59.3
Mudhairib 102.2 56.5 64.7 67.1 69.5 71.4
TX-1 & TX-2 100.7 104.7 85.9 100.2 103.7 106.5
Muladah
TX-3 & TX-4 21.8 22.7 46.6 48.4 50.4 51.9
Nakhal 73.6 76.5 85.6 88.0 90.5 93.0
New Izki 19.8 20.6 21.4 22.3 23.2 23.9
Nizwa 122.1 85.1 96.6 109.3 112.0 114.8
Rustaq 3x125M VA 153.3 159.4 116.8 121.5 126.3 130.1
Samad 0.0 25.0 25.8 26.5 27.3 28.1
Sinaw 0.0 35.0 36.8 38.2 39.7 40.9
2x63MVA 50.9 52.4 54.0 55.1 56.2 57.3
Sumail
2x125M VA 104.7 108.9 59.6 62.0 63.9 65.8
Sumail Industrial Area 0.0 0.0 53.6 55.2 56.9 58.6
Sur 87.9 94.0 96.8 99.6 102.4 105.4
Suwaiq 58.8 61.2 67.9 77.6 80.3 82.4
Wadi Bani Auwf 0.0 0.0 49.0 51.0 53.0 54.6
OMIFCo 3.3 0.0 0.0 0.0 0.0 0.0
Total 2236.4 2321.0 2463.5 2614.8 2705.4 2786.0
Growth (% ) -2.8% 3.8% 6.1% 6.1% 3.5% 3.0%
MAJAN AREA
Al Hayl 39.5 40.5 7.6 7.7 7.8 8.0
Bureimi 81.0 48.4 51.3 53.3 55.5 56.9
TX-1 & TX-2 54.3 40.2 41.0 42.0 43.1 44.6
Buriami Industrial
TX-3 & TX-4 0.0 50.4 59.6 61.2 62.9 66.4
Dank 34.2 38.1 42.6 47.7 51.3 52.2
Dil Abdusalam 70.3 73.3 78.3 80.6 82.3 87.2
Dreez 77.5 79.3 81.5 83.7 88.2 90.7
2x63MVA 37.7 38.9 40.1 41.3 40.6 41.9
Ibri
2x125M VA 78.6 78.2 80.2 82.2 84.3 86.8
Khaborah 85.4 88.0 91.2 95.4 99.7 104.3

Page | 72
Five-Year Annual Transmission Capability Statement (2020 – 2024)

Table 10 (continued): OETC Transmission System Net Demand Forecast by Grid Station
Actual Forecast (MW)
Grid Station
2019 2020 2021 2022 2023 2024
MAJAN AREA
TX-1 & TX-2 124.4 56.1 59.8 56.7 59.9 63.0
Liwa
TX-3 & TX-4 61.5 67.2 73.0 76.4 79.8 82.1
Madinat Shinas 59.1 64.5 73.7 78.9 82.9 86.6
Mahadah 23.3 24.1 17.2 17.4 17.8 18.0
Saham 83.9 86.2 87.4 90.0 90.2 95.1
Shinas 59.8 64.8 67.3 79.6 84.3 91.7
SIA 71.2 76.8 84.4 84.9 85.4 86.1
TX-1 & TX-2 69.2 55.7 58.6 68.2 90.0 94.4
Sohar
TX-3 & TX-4 98.0 108.7 112.9 112.8 97.5 100.7
TX-1 & TX-2 5.1 36.6 41.0 44.9 41.2 42.2
Sohar Free Zone
TX-3 & TX-4 0.0 49.1 50.4 51.4 52.6 54.3
TX-1 & TX-2 47.7 52.2 53.8 55.5 58.2 60.0
Uwaynat
TX-3 & TX-4 54.4 60.8 62.9 64.7 68.7 71.1
Wadi Sa'a 12.0 14.1 16.5 18.1 20.4 22.6
Yanqul 0.0 0.0 33.5 34.4 35.4 36.7
Sohar Refinery (132kV SIA) 23.9 0.0 0.0 0.0 0.0 0.0
Sohar Steel (SSSRM) (132kV SIa) 2.8 0.0 0.0 0.0 0.0 0.0
Jindal Shadeed (220kV SIA) 21.6 60.0 60.0 100.0 100.0 100.0
VALE (132kV SIA) 65.7 85.0 85.0 85.0 85.0 85.0
ARMS (132kV Liwa) 4.2 4.2 4.2 4.2 4.2 4.2
OMPET (132kV SIA) 0.0 0.0 4.0 4.0 4.0 4.0
Orpic (Liwa Plastic) (220kV SPS-2) 5.0 25.0 25.0 25.0 25.0 25.0
Moon Iron & Steel Co. (220KV SFZ) 0.0 15.0 15.0 15.0 15.0 15.0
Al Taman INDSIL (132kV SFZ) 14.9 8.0 8.0 8.0 8.0 8.0
Total 1466.2 1589.3 1666.9 1770.2 1821.2 1885.1
Growth (% ) -0.7% 8.4% 4.9% 6.2% 2.9% 3.5%
DPC AREA
Al Qarm (2x63M VA) 32.7 34.4 33.2 36.0 27.7 28.5
Ashoor (2X125MVA) 49.0 68.7 55.8 56.7 56.7 57.7
Ittin (2X125MVA) 90.5 78.4 71.8 74.8 83.5 87.1
Mirbat 2x63 MVA 0.0 0.0 20.9 24.9 26.9 29.1
NPS (2x63MVA) 37.9 39.7 38.8 41.9 43.1 44.7
TX-1 & TX-2 52.6 65.0 80.6 88.5 101.9 105.5
S'aadah
TX-3 & TX-4 40.3 44.3 66.5 87.2 102.3 105.9
Raysut 92.1 101.7 111.5 109.0 108.3 108.5
Salalah-IPP 20.7 39.7 69.0 101.1 107.5 112.0

Page | 73
Five-Year Annual Transmission Capability Statement (2020 – 2024)

Table 10 (continued): OETC Transmission System Net Demand Forecast by Grid Station
Actual Forecast (MW)
Grid Station
2019 2020 2021 2022 2023 2024
DPC AREA
Shaha'aon (2X125MVA) 96.1 95.3 99.4 98.3 81.9 85.0
2x30 MVA 21.6 24.2 0.0 0.0 0.0 0.0
Thumrait
2x63 MVA 0.0 0.0 28.8 32.6 33.6 34.6
Salalah Airport 6.8 7.0 8.0 8.0 8.0 8.0
Salalah Methanol Company 0.0 0.0 35.0 35.0 35.0 35.0
Total 540.2 598.2 719.3 794.1 816.4 841.5
Growth (% ) 3.6% 10.7% 20.2% 10.4% 2.8% 3.1%
RAEC AREA
TX-1 & TX-2 0.0 0.0 0.0 0.0 60.8 61.8
Duqm
TX-3 & TX-4 0.0 0.0 0.0 0.0 53.4 54.3
Mahout (2X125MVA) 0.0 0.0 0.0 0.0 23.9 24.9
Saih Al Khairat (2x125M VA) 0.0 0.0 0.0 0.0 44.2 45.8
Total 0.0 0.0 0.0 0.0 182.2 186.9
Growth (% ) - - - - - 2.6%
MEDC 2463.2 2626.5 2796.1 2941.7 3075.6 3193.1
MZEC 2236.4 2321.0 2463.5 2614.8 2705.4 2786.0
MJEC 1466.2 1589.3 1666.9 1770.2 1821.2 1885.1
DPC 540.2 598.2 719.3 794.1 816.4 841.5
RAEC 0.0 0.0 0.0 0.0 182.2 186.9
Total MIS (MW) 6165.8 6536.8 6926.5 7326.7 7740.2 8005.2
Growth (% ) 2.2% 6.0% 6.0% 5.8% 5.6% 3.4%
Total Dhofar System (MW) 540.2 598.2 719.3 794.1 860.6 887.3
Growth (% ) 3.6% 10.7% 20.2% 8 10.4% 9 8.4% 3.1%

8
DPC growth in 2021 is 20.2% due to Salalah Methanol Load (35 MW).
9
DPC growth in 2022 is 10.4% due to increased number of customers on 33kV side.

Page | 74
Five-Year Annual Transmission Capability Statement (2020 – 2024)

Table 11 compares the total net demand forecast with the available generating capacity from Table 7
including planned retirements.
Table 11: Comparison of Net Demand Forecast with Available Generating Capacity including Planned
Retirements

Power Stations 2019 2020 2021 2022 2023 2024


MIS
Rusail IPP 693.5 693.5 693.5 0.0 0.0 0.0
Manah IPP 263.2 182.2 182.2 182.2 182.2 182.2
Al Kamil IPP 291.4 291.4 291.4 0.0 0.0 0.0
Barka I Power & Desalination Plant 397.5 397.5 397.5 0.0 0.0 0.0
Barka II IPP 688.5 688.5 688.5 688.5 688.5 0.0
Barka III IPP 765.5 765.5 765.5 765.5 765.5 765.5
Sohar I Power & Desalination Plant 566.0 566.0 566.0 0.0 0.0 0.0
Sohar II IPP 765.5 765.5 765.5 765.5 765.5 765.5
Sohar III IPP 1745.0 1743.1 1741.8 1739.3 1740.7 1739.7
Sur IPP 2018.2 2018.2 2018.2 2018.2 2018.2 2018.2
Ibri IPP 1543.0 1541.7 1540.6 1539.6 1538.5 1537.7
Ibri Solar PV IPP 0.0 0.0 0.0 450.0 450.0 450.0
Manah Solar PV IPP 0.0 0.0 0.0 0.0 150.0 300.0
Power 2022 0.0 0.0 0.0 600.0 600.0 600.0
Power 2024 0.0 0.0 0.0 0.0 0.0 700.0
Duqm Wind Farm 0.0 0.0 0.0 0.0 0.0 68.5
JBB Ali Wind Farm 0.0 0.0 0.0 0.0 0.0 19.0
Barka Waste to Energy Plant 0.0 0.0 0.0 0.0 0.0 100.0
Demand Response 0.0 0.0 30.0 40.0 50.0 70.0
Total Generating Capacity (MW) 9737.3 9653.1 9680.8 8788.8 8949.2 9316.4
Demand Forecast (MW) 6165.8 6536.8 6926.5 7326.7 7740.2 8005.2
Calculated Losses (MW) 187.0 129.0 127.1 171.4 171.4 150.4
Surplus/Deficit Capacity (MW)
3384.5 2987.4 2627.2 1290.7 1037.6 1160.7
(Generation-Demand-Losses)
Retirements 0.0 81 0.0 1948.4 0.0 688.5
Dhofar System
NPS 273.0 273.0 273.0 273.0 273.0 273.0
Salalah Power & Desalination Plant 430.0 430.0 430.0 430.0 430.0 430.0
Salalah II IPP 445.0 444.0 443.0 442.0 442.0 442.0
Dhofar Wind Farm 0.0 18.0 18.0 18.0 18.0 18.0
Total Generating Capacity (MW) 1148.0 1165.0 1164.0 1163.0 1163.0 1163.0
Demand Forecast (MW) 540.2 598.2 719.3 794.1 860.6 887.3
Calculated Losses (MW) 8.7 2.4 3.0 3.5 5.0 5.2
Surplus/Deficit Capacity (MW)
599.0 564.3 441.7 365.3 297.5 270.4
(Generation-Demand-Losses)
Retirements 0.0 0.0 0.0 0.0 0.0 0.0

Page | 75
Five-Year Annual Transmission Capability Statement (2020 – 2024)

Table 12 compares the total net demand forecast with the available generating capacity from Table 7.

Table 12: Comparison of Net Demand Forecast with Available Generating Capacity and Non-Contracted
Generation in service
Power Stations 2019 2020 2021 2022 2023 2024
MIS
Rusail IPP 693.5 693.5 693.5 0.0 0.0 0.0
Manah IPP 263.2 182.2 182.2 182.2 182.2 182.2
Al Kamil IPP 291.4 291.4 291.4 0.0 0.0 0.0
Barka I Power & Desalination Plant 397.5 397.5 397.5 0.0 0.0 0.0
Barka II IPP 688.5 688.5 688.5 688.5 688.5 0.0
Barka III IPP 765.5 765.5 765.5 765.5 765.5 765.5
Sohar I Power & Desalination Plant 566.0 566.0 566.0 0.0 0.0 0.0
Sohar II IPP 765.5 765.5 765.5 765.5 765.5 765.5
Sohar III IPP 1745.0 1743.1 1741.8 1739.3 1740.7 1739.7
Sur IPP 2018.2 2018.2 2018.2 2018.2 2018.2 2018.2
Ibri IPP 1543.0 1541.7 1540.6 1539.6 1538.5 1537.7
Ibri Solar PV IPP 0.0 0.0 0.0 450.0 450.0 450.0
Manah Solar PV IPP 0.0 0.0 0.0 0.0 150.0 300.0
Power 2022 0.0 0.0 0.0 600.0 600.0 600.0
Power 2024 0.0 0.0 0.0 0.0 0.0 700.0
Duqm Wind Farm 0.0 0.0 0.0 0.0 0.0 68.5
JBB Ali Wind Farm 0.0 0.0 0.0 0.0 0.0 19.0
Barka Waste to Energy Plant 0.0 0.0 0.0 0.0 0.0 100.0
Demand Response 0.0 0.0 30.0 40.0 50.0 70.0
Total Generating Capacity (MW) 9737.3 9653.1 9680.8 8788.8 8949.2 9316.4
Demand Forecast (MW) 6165.8 6536.8 6926.5 7326.7 7740.2 8005.2
Calculated Losses (MW) 187.0 129.0 127.1 171.4 171.4 150.4
Surplus/Deficit Capacity (MW) 1037.6 1160.7
3384.5 2987.4 2627.2 1290.7
(Generation-Demand-Losses)
Non-Contracted Generating Capacity (MW) 775.0 775.0 775.0 775.0 775.0 775.0
Surplus/Deficit Capacity (MW) 1812.6 1935.7
4159.5 3762.4 3402.2 2065.7
Including Non-Contracted Generation
Retirements 0.0 81.0 0.0 1948.4 0.0 688.5
Dhofar System
NPS 273.0 273.0 273.0 273.0 273.0 273.0
Salalah Power & Desalination Plant 430.0 430.0 430.0 430.0 430.0 430.0
Salalah II IPP 445.0 444.0 443.0 442.0 442.0 442.0
Dhofar Wind Farm 0.0 18.0 18.0 18.0 18.0 18.0
Total Generating Capacity (MW) 1148.0 1165.0 1164.0 1163.0 1163.0 1163.0
Demand Forecast (MW) 540.2 598.2 719.3 794.1 860.6 887.3
Calculated Losses (MW) 8.7 2.4 3.0 3.5 5.0 5.2
Surplus/Deficit Capacity (MW)
599.0 598.4 441.7 365.3 297.4 270.4
(Generation-Demand-Losses)
Non-Contracted Generating Capacity (MW) 0.0 0.0 0.0 0.0 0.0 0.0
Surplus/Deficit Capacity (MW)
599.0 598.4 441.7 365.3 297.4 270.4
Including Non-Contracted Generation
Retirements 0.0 0.0 0.0 0.0 0.0 0.0

Page | 76
Five-Year Annual Transmission Capability Statement (2020 – 2024)

8. Transmission System Performance

8.1 Power Flow and Voltage Profiles

The transmission system data used in the power system studies to determine the system performance over
the period from 2020 to 2024 is presented in Appendix B of this document.

8.1.1 Power Flow and Voltage Profiles of MITS and DTS


The extreme cases of maximum (summer) and minimum (winter) system demand are used to define the
performance of OETC transmission system when it is most heavily stressed. From the studies of these
extreme conditions, it is possible to identify where the system is strong and has spare capacity and
conversely where it is weak and will need strengthening before new connections could be considered. The
peak demand case identifies where there is a risk of overloading, of operation above firm capacity, or of
system voltages falling below the voltage limits as defined in the Grid Code and TSS.
The system data described and presented in Appendix B has been used in a series of load flow studies to
establish the performance of OETC transmission system at peak demand in each year from 2020 to 2024
inclusive. The studies were undertaken on the basis that all circuits and plants will be available at system
peak in each of the five years and that the system will be developed in accordance with the plans described
in Section 5 of the Statement. The studies also assume that the demand will grow in accordance with the
demand forecast and that sufficient generation will be available from both Contracted and Non-Contracted
power producers to meet each annual system peak as indicated in OPWP 7 Year Statement.
Table 13 shows a summary of the power plants forecasted to be in service at peak load in each year of the
study from 2020 to 2024 at MITS and DTS. Under peak load condition, it is assumed that reactive power
support will be switched on by DISCOs, i.e. capacitor banks at 33kV grid stations and properly adjusted to
provide required reactive power and voltage support. In the load flow studies, generators terminal voltage
and generator-transformer taps are normally set at their corresponding nominal values, however, when
necessary the settings are adjusted to control the voltage on the transmission system to be within the
allowable limits.
A second series of load flow studies were undertaken with the transmission system supplying minimum
demand. The minimum demand case identifies where there is a risk of the busbar voltages rising above the
voltage limits defined in the Grid Code and TSS and where additional generation has to be operated to
absorb excess reactive power. However, several shunt reactors will be in operation to absorb excessive
amount of reactive power that been generated by the lightly loaded 400kV lines at MITS. Also, it should
be noted that the 400kV shunt reactors are only operated during the winter period except summer 2023 due
to the introduction of the 400kV OHL Suwaihat – Duqm – Mahout. At the system minimum demand, the
generation is reduced to a level that provides the necessary margin of reserve capacity that is consistent
with the operational practices adopted by OETC to handle minimum load condition.

Table 14 shows the power plants forecasted to be in service at minimum load in each year of the study at
MITS and DTS. Under minimum load condition, it is assumed that all capacitor banks at 33kV system are
switched out by DISCOs to avoid overvoltage due to excessive reactive power.

Page | 77
Five-Year Annual Transmission Capability Statement (2020 – 2024)

Table 13: Summary of Connected Generation Used in Load Flow Studies of Maximum Demand
2020 2021 2022 2023 2024
Power Stations
Total Spare Gen Total Spare Gen Total Spare Gen Total Spare Gen Total Spare Gen
MIS
Al-Kamil (IPP) 291.4 90.4 201.0 291.4 75.1 216.2 - - - - - - - - -
Barka I (IWPP) 397.5 46.9 350.6 397.5 102.5 295.0 - - - - - - - - -
Barka II (IWPP) 688.5 143.2 545.3 688.5 143.2 545.3 688.5 93.9 594.6 688.5 62.7 625.7 - - -
Barka III (IPP) 765.5 213.3 552.2 765.5 182.9 582.6 765.5 104.4 661.1 765.5 69.9 695.6 765.5 32.4 733.1
Ibri (IPP) 1542.0 479.2 1062.8 1541.0 398.6 1142.4 1540.0 210.0 1330.0 1539.0 141.3 1397.7 1539.0 66.5 1472.5
Manah (IPP) 182.2 56.4 125.8 182.2 7.7 174.5 182.2 1.6 180.6 182.2 16.6 165.6 182.2 182.2 0.0
Rusail (IPP) 693.5 214.9 478.6 693.5 163.1 530.4 - - - - - - - - -
Sohar I (IWPP) 597.0 184.9 412.1 597.0 190.5 406.5 - - - - - - - - -
Sohar II (IPP) 765.5 237.3 528.3 765.5 207.7 557.8 765.5 104.4 661.1 765.5 69.9 695.6 765.5 32.4 733.1
Sohar III (IPP) 1743.1 539.7 1203.4 1741.8 448.8 1293.1 1739.3 234.7 1504.6 1740.7 158.2 1582.5 1739.7 73.1 1666.5
Sur (IPP) 2018.2 625.5 1392.7 2018.2 521.1 1497.1 2018.2 275.0 1743.2 2018.2 184.4 1833.8 2018.2 85.7 1932.5
Ibri Solar PV IPP - - - - - - 500.0 50.0 450.0 500.0 50.0 450.0 500.0 50.0 450.0
Power 2022 - - - - - - 600.0 76.0 524.0 600.0 154.3 445.7 600.0 221.4 378.6
Power 2024 - - - - - - - - - - - - 700.0 265.9 434.1
Manah Solar PV IPP - - - - - - - - - 500.0 350.0 150.0 1000.0 700.0 300.0
Waste-to-Energy Plant - - - - - - - - - - - - 160.0 60.0 100.0
JBB Ali wind farm - - - - - - - - - - - - 100.0 81.0 19.0
Duqm wind farm - - - - - - - - - - - - 200.0 131.5 68.5
Total Gen (MW) 9684.4 2831.8 6852.7 9682.1 2441.3 7240.8 8799.2 1150.2 7649.0 9299.7 1257.4 8042.2 10270.1 1982.3 8287.9
Gross Load (MW) 6852.7 7240.8 7649.0 8042.2 8287.9
Dhofar
NPS 273.0 273.0 0.0 273.0 273.0 0.0 273.0 209.4 63.6 273.0 144.6 128.4 273.0 113.3 159.7
Salalah Power & Desalination
445.0 119.1 325.9 445.0 69.6 375.4 445.0 63.4 381.6 445.0 59.7 385.3 445.0 61.7 383.3
Plant
Salalah II IPP 444.0 141.6 302.4 443.0 68.5 374.5 442.0 62.1 379.9 442.0 58.5 383.5 442.0 60.4 381.6
Dhofar Wind Farm 50.0 32.0 18.0 50.0 32.0 18.0 50.0 32.0 18.0 50.0 32.0 18.0 50.0 32.0 18.0
Total Gen (MW) 1212.0 565.7 646.3 1211.0 443.1 767.9 1210.0 366.9 843.1 1210.0 294.7 915.3 1210.0 267.4 942.5
Gross Load (MW) 646.3 767.9 843.1 915.3 942.5

Page | 78
Five-Year Annual Transmission Capability Statement (2020 – 2024)

Table 14: Summary of Connected Generation Used in Load Flow Studies of Minimum Demand
2020 2021 2022 2023 2024
Power Stations
Total Spare Gen Total Spare Gen Total Spare Gen Total Spare Gen Total Spare Gen
MIS
Al-Kamil (IPP) 291.4 291.4 0.0 291.4 291.4 0.0 291.4 291.4 0.0 - - - - - -
Barka I (IWPP) 397.5 397.5 0.0 397.5 397.5 0.0 397.5 397.5 0.0 - - - - - -
Barka II (IWPP) 688.5 688.5 0.0 688.5 688.5 0.0 688.5 688.5 0.0 688.5 688.5 0.0 - - -
Barka III (IPP) 765.5 354.1 411.4 765.5 340.0 425.6 765.5 345.1 420.4 765.5 394.5 371.1 765.5 400.8 364.7
Ibri (IPP) 1542.0 902.2 639.8 1541.0 879.2 661.8 1540.0 885.9 654.1 1539.0 961.8 577.2 1539.0 972.0 567.0
Manah (IPP) 182.2 182.2 0.0 182.2 182.2 0.0 182.2 182.2 0.0 182.2 182.2 0.0 182.2 182.2 0.0
Rusail (IPP) 693.5 693.5 0.0 693.5 693.5 0.0 693.5 693.5 0.0 - - - - - -
Sohar I (IWPP) 597.0 597.0 0.0 597.0 597.0 0.0 597.0 597.0 0.0 - - - - - -
Sohar II (IPP) 765.5 354.2 411.4 765.5 340.0 425.6 765.5 345.1 420.4 765.5 394.5 371.1 765.5 400.8 364.7
Sohar III (IPP) 1743.1 1018.6 724.5 1741.8 991.4 750.4 1739.3 766.1 973.2 1740.7 881.7 859.0 1739.7 895.7 844.0
Sur (IPP) 2018.2 934.2 1084.0 2018.2 897.0 1121.2 2018.2 910.0 1108.2 2018.2 1040.2 978.0 2018.2 1057.3 960.9
Ibri Solar PV IPP - - - - - - - - - 450.0 0.0 450.0 500.0 50.0 450.0
Power 2022 - - - - - - - - - 600.0 600.0 0.0 600.0 600.0 0.0
Manah Solar PV IPP - - - - - - - - - 0.0 0.0 0.0 500.0 350.0 150.0
Total Gen (MW) 9684.4 6413.4 3271.0 9682.1 6297.6 3384.5 9678.6 6102.3 3576.3 8749.7 5143.4 3606.3 8610.1 4908.8 3701.3
Gross Load (MW) 3271.0 3384.5 3576.3 3606.3 3701.3
Dhofar
NPS 273.0 273.0 0.0 273.0 273.0 0.0 273.0 273.0 0.0 273.0 273.0 0.0 273.0 273.0 0.0
Salalah Power & Desalination
445.0 368.4 76.6 445.0 322.6 122.4 445.0 284.1 160.9 445.0 272.8 172.2 445.0 246.0 199.0
Plant
Salalah II IPP 444.0 245.1 198.9 443.0 231.6 211.4 442.0 234.1 207.9 442.0 219.4 222.6 442.0 236.2 205.8
Dhofar Wind Farm 50.0 32.0 18.0 50.0 32.0 18.0 50.0 32.0 18.0 50.0 32.0 18.0 50.0 32.0 18.0
Total Gen (MW) 1212.0 918.5 293.5 1211.0 859.2 351.7 1210.0 823.2 386.8 1210.0 797.2 412.8 1210.0 787.2 422.8
Gross Load (MW) 293.5 351.7 386.8 412.8 422.8

Page | 79
Five-Year Annual Transmission Capability Statement (2020-2024)

The key results of the load flow and fault level studies on OETC transmission system are presented in detail
in Appendix C for each year over the period from 2020 to 2024. System diagrams from C.1 to C.10 show
the results of the peak demand for MIS and Dhofar System. Load flows have been produced and are
available for both MIS and Dhofar System in Appendix C.

The results for MIS and Dhofar System include the following:

 Table C.1 shows the transformer percentage loading of all grid stations at system peak demand.

 Table C.2 shows the available spare capacity at each grid station in relation to firm capacity at system
peak demand. It should be noted that although spare MVA capacities are available at some individua l
grid stations, there is no guarantee that all can be exploited simultaneously. Lack of available
generation and/or voltage level limits may restrict simultaneous utilization of all spare MVA capacities.

 Table C.3 shows the percentage loading of each overhead line and underground cable in the
transmission system at system peak demand.

 Tables C.4 and C.5 show the voltage profile at each 400kV, 220kV, 132kV and 33kV bus-bar at
maximum and minimum load respectively.

 Table C.6 shows the calculated transmission losses and generation margin at peak demand.

 Tables C.7 and C.8 show the maximum three-phase and single-phase to earth short circuit currents
respectively.

The principal findings from the power system studies are:

 Grid Stations Firm Capacities of MITS


a) All 400/220kV, 400/132kV and 400/33kV grid stations developed during 2020 to 2024 will have
sufficient capacities as indicated in Table C.1. Moreover, these grid stations will have appreciable
amount of spare transformer capacities during the same period as indicated in Table C.2 and for future
needs.
b) All 220/132kV grid stations have adequate amounts of spare capacity available over the period from
2020 to 2024 to cope with growth in demand except one 220/132kV grid station in 2022 as indicated
in Tables C.1 and C.2. The three new 220/132kV grid stations that will be commissioned over the
period 2020-2024 at KIS, Misfah and Nizwa with addition of one 220/132kV transformer in Airport
Heights will substantially increase the amount of grid transformer capacity connected to the
transmission system to facilitate further development of the transmission system.
c) Some of the 132/33kV grid stations show a lack of capacity from 2020 to 2023. For example, at the
summer peak of 2020, six grid stations will operate above their firm capacity. At the summer peak of
2021, three grid stations will operate above their firm capacity. During 2020 to 2024, a number of
132/33kV grid stations will be upgraded and new ones will be introduced to remove none-firm

Page | 80
Five-Year Annual Transmission Capability Statement (2020-2024)

conditions at some locations. The number will decrease to one 132/33kV at the summer peak of 2022
and 2023.
d) The numbers of out-of-firm 132/33kV grid stations during the period 2020 to 2024 are as follows. The
same is also shown graphically in Figure 26
 2020 – 6
 2021 – 3
 2022 – 1
 2023 – 1
 2024 – 0
e) In the summer peak of 2020, there is one transformer temporarily supplying their individual loads in
order to mitigate over firm issues and provide additional capacity at Barka Main 132/33kV grid station.
From 2022, there will be no transformer operating individually
f) Two 132kV overhead transmission lines and underground cables are exceeding their corresponding
firm capacity in 2020 and four in 2022.
g) All 220kV overhead transmission lines and underground cables are within their corresponding firm
capacity over the years 2020 to 2024 except one 220kV OHL will be exceeding its corresponding firm
capacity in 2020 and 2022.
h) All 400kV overhead transmission lines and underground cables are well within their corresponding
firm capacity over the years 2020 to 2024.
i) Implementation of the development projects described in Section 5 and the updated load transfer
programme of Table 9 will restore the full system to be in compliance with Transmission Security
Standard requirements.

 Grid Stations Firm Capacities of Dhofar Transmission System


a) During next five years from 2020-2024, all 132/33kV grid stations will be within the firm
capacity. Upgrading Thumrait 132/33kV grid station will add a new capacity to the network in
2021 peak. Construction of Mirbat grid station in 2021 will relief the loading issue at Shaha'aon
grid station and reserve new capacity for any bulk customer will be connected the system in
future. In addition, OETC will introduce new connection with RAEC by 2023 at Saih Al Khairat
grid station that will be connected to DTS.
b) The numbers of out-of-firm 132/33kV grid stations during the period 2020 to 2024 are nil.
c) All 132kV overhead lines and underground cables are within their corresponding firm capacity
over the period 2020-2024.
d) Implementation of the development projects described in Section 5 and the updated load transfer
programme of Table 9 will restore the full system to comply with Transmission System Security
Standard requirements.

Page | 81
Five-Year Annual Transmission Capability Statement (2020-2024)

No. of Out-of-Firm Grid Stations


6

0
2020 2021 2022 2023 2024

Figure 26: Number of out-of-firm 132/33kV grid stations of MIS during 2020-2024

 Voltage Profile of MITS


a) The voltage at the 400kV busbars will be maintained within the ±5% voltage limit at the extremes
of maximum and minimum demands during the study period. In addition, some busbars in 2020
were close to reach the upper limit (1.05p.u), the reason behind that is to improve the voltage at
some 132kV busbars.
b) The voltage at the 220kV and 132kV busbars will be maintained within the ±10% voltage limit
at the extremes of maximum and minimum demands during years 2020-2024.
c) The 33kV busbar voltages at all grid stations will be maintained within ±6 % of nominal voltage
during these extreme load conditions of maximum and minimum demands, i.e. all 33kV busbars
will be within the acceptable operating range specified in the Grid Code and TSS. In fact, the
voltage at 33kV busbars is well regulated to be within around 1.0 p.u. in all cases by exploiting
the automatic on-load tap-changer of the 132/33kV transformers.
d) Figure 27& Figure 28 show the peak and off peak voltage profiles at 400kV, 220kV, 132kV and
33kV grid stations in 2020 and 2024 respectively.
- In peak 2020 and 2024, the figures show that the maximum voltage at some 400kV busbars
will reach 1.04 pu which is close to the limit of + 5% because of the connection of the busbar
closer to the generation. So, it will be required to increase the voltage at these 400kV busbars
to improve voltage at far 132kV busbars in the system.
- In off peak 2020 and 2024, the voltage profile for all voltage levels will be close to 1.00 p.u
due to low reactive power consumption of loads. The reactive power will be controlled via
shunt reactors, hence the voltage will be operated within the limit.

Page | 82
Five-Year Annual Transmission Capability Statement (2020-2024)

e) The voltage at 220kV and 132kV busbars is maintained within the allowable range (depending
on the load), whereas the voltage at the grid supply points is well regulated at almost 33kV (1.0
p.u.).

 Voltage Profile of DTS


a) The voltage at the 132kV busbars will be maintained within the ±10 % voltage limit at the extremes
of maximum and minimum demands during years 2020-2024.
b) The 33kV busbar voltages at all grid stations will be maintained within ±6 % of nominal voltage
during these extreme load conditions of maximum and minimum demands, i.e. all 33kV busbars
will be within the acceptable operating range specified in the Grid Code and TSS. In fact, the
voltage at 33kV busbars is well regulated to be within around 1.0 p.u. in all cases by exploiting
the automatic on-load tap-changer of the 132/33kV transformers.
c) Figure 29 and Figure 30 show voltage profiles at DTS for both Peak and Off-Peak from 2020 to
2024. All grid stations have two voltage levels: 132kV and 33kV. Although the voltage at 132kV
busbars can change within the allowable range depending on the load, the voltage at the grid
supply points is well regulated at almost 33kV (1.0 p.u.).

Page | 83
Five-Year Annual Transmission Capability Statement (2020-2024)

Peak & Off Peak Voltage Profile at 400kV busbar in 2020


1.05
1.03
1.01
0.99
0.97
0.95

Peak Voltage Profile Off Peak Voltage Profile Max Limit Min Limit

Peak & Off Peak Voltage Profile at 220kV busbar 2020


1.10
1.05
1.00
0.95
0.90

Peak Voltage Profile Off Peak Voltage Profile Max Limit Min Limit

Peak & Off Peak Voltage Profile at 132kV busbar 2020


1.10
1.05
1.00
0.95
0.90

Peak Voltage Profile Off Peak Voltage Profile Max Limit Min Limit

Peak & Off Peak Voltage Profile at 33kV busbar 2020


1.06

1.03

1.00

0.97

0.94

Peak Voltage Profile Off Peak Voltage Profile Max Limit Min Limit

Figure 27: MIS Peak & off Peak Voltage profile at 400kV, 220kV, and 132kV and 33kV busbars in 2020

Page | 84
Five-Year Annual Transmission Capability Statement (2020-2024)

Peak & Off Peak Voltage Profile at 400kV busbar 2024


1.05
1.03
1.01
0.99
0.97
0.95

Peak Voltage Profile Off Peak Voltage Profile Max Limit Min Limit

Peak & Off Peak Voltage Profile at 220kV busbar 2024


1.10

1.05

1.00

0.95

0.90

Peak Voltage Profile Off Peak Voltage Profile Max Limit Min Limit

Peak & Off Peak Voltage Profile at 132kV busbar 2024


1.10

1.05

1.00

0.95

0.90

Peak Voltage Profile Off Peak Voltage Profile Max Limit Min Limit

Peak & Off Peak Voltage Profile at 33kV busbar 2024


1.06

1.03

1.00

0.97

0.94

Peak Voltage Profile Off Peak Voltage Profile Max Limit Min Limit

Figure 28: MIS Peak & off Peak Voltage profile at 400kV, 220kV, 132kV and 33kV busbars in 2024

Page | 85
Five-Year Annual Transmission Capability Statement (2020-2024)

Peak & Off Peak Voltage Profile at 132kV busbar in 2020


1.10
1.08
1.06
1.04
1.02
1.00
0.98
0.96
0.94
0.92
0.90

Peak Voltage Profile Off Peak Voltage Profile Max Limit Min Limit

Peak & Off Peak Voltage Profile at 33kV busbar in 2020

1.06

1.04

1.02

1.00

0.98

0.96

0.94

Peak Voltage Profile Off Peak Voltage Profile Max Limit Min Limit

Figure 29: DTS Peak & off Peak Voltage profile at 132kV and 33kV busbars in 2020

Page | 86
Five-Year Annual Transmission Capability Statement (2020-2024)

Peak & Off Peak Voltage Profile at 132kV busbar in 2024


1.10
1.08
1.06
1.04
1.02
1.00
0.98
0.96
0.94
0.92
0.90

Peak Voltage Profile Off Peak Voltage Profile Max Limit Min Limit

Peak & Off Peak Voltage Profile at 33kV busbar in 2024


1.06

1.04

1.02

1.00

0.98

0.96

0.94

Peak Voltage Profile Off Peak Voltage Profile Max Limit Min Limit

Figure 30: DTS Peak & off Peak Voltage profile at 132kV and 33kV busbars in 2024

Page | 87
Five-Year Annual Transmission Capability Statement (2020-2024)

 Transmission Losses of MITS


The active power losses on the MITS for different voltage level has been calculated at peak demand
over the period from 2020 to 2024. The losses percentage at 400kV level ranges between 0.44% and
0.72%. At 220kV level the losses percentage ranges between 0.52% and 0.64% and for 132kV level
it ranges between 0.71% and 0.97% of respective total generation as shown in Table C.6 and Figure
31. The total average power loss is about 1.96%, which is well within international norms. The increase
in the losses percentage is due to the retirement of power plants such as Rusail IPP, Al Kamil IPP,
Barka I IPP and Sohar IPP in 2022. Consequently, the power will be transmitted over long distance to
the load centre. In 2024, the losses will be decreased due to introduction of 400kV reinforcements in
the system. The transmission losses are higher in 132kV level comparing to 220kV and 400kV.

% of Power Losses (MIS)


2.50

2.00

1.50

1.00

0.50

0.00
2020 2021 2022 2023 2024

400kV 220kV 132kV Total %

Figure 31: Transmission power losses at peak demand of MIS of the years 2020-2024

 Transmission Losses of DTS


The calculated active power losses percentage on Dhofar Transmission System at peak demand over
the period from 2020 to 2024 ranges between 0.37% and 0.55% of respective total generation as shown
in Table C.6 and Figure 32. The average power losses percentage is about 0.46%, which is still within
international norms. The increase in the losses percentage in 2023 is due to the long 132kV OHL to
connect new Saih Al Khairat grid station.

Page | 88
Five-Year Annual Transmission Capability Statement (2020-2024)

% of Power Losses (DTS)


0.60%

0.50%

0.40%

0.30%

0.20%

0.10%

0.00%
2020 2021 2022 2023 2024

Figure 32: Transmission power losses at peak demand of DTS of the years 2020-2024

 Load Growth of MITS


The high growth rate of the existing load coupled with major new industrial developments in many
areas and major tourism projects around the coast to the east and west of Muscat presents a major
challenge to OETC in providing the capacity needed to satisfy demand over the next five years. Table
C.6 shows the expected gross peak load increases from 6852.7 MW in 2020 to 8287.9 MW in 2024,
which represents an increase of about 20.94 % during the study period. Figure 33 shows the expected
peak load growth from 2020 to 2024. This peak load includes grid stations, industrial, auxiliaries ’
desalination loads and transmission losses.

 Load Growth of DTS


The high growth rate of the existing load coupled with major new industrial developments in many
areas and major tourism projects around the coast of Dhofar presents a major challenge to OETC in
providing the capacity needed to satisfy demand over the next five years. Table C.6 shows that the
expected gross peak load increases from 646.39 MW in 2020 to 942.60 MW in 2024, which represents
an increase of about 45.83% during the study period. Figure 34 shows the expected peak load growth
from 2020 to 2024. This peak load includes grid stations, industrial, auxiliaries’ desalination loads and
transmission losses.

Page | 89
Five-Year Annual Transmission Capability Statement (2020-2024)

Peak Load Growth (MW)

8000
7000
6000
5000
4000
3000
2000
1000
0
2020 2021 2022 2023 2024

Figure 33: Peak load growth of MITS System over the period 2020-2024

Peak Load Growth (MW)

1000

800

600

400

200

0
2020 2021 2022 2023 2024

Figure 34: Peak load growth of Dhofar System over the period 2020-2024
The load flow studies show that the planned 400kV, 220kV and 132kV transmission developments will add
substantial new capacity to the transmission system that will enable the transmission system as a whole to
cope with new demand in compliance with the Transmission Security Standard. Consequently,
opportunities for the connection of new load should be available where spare capacity exists.

Page | 90
Five-Year Annual Transmission Capability Statement (2020-2024)

8.2 Fault levels for MIS and Dhofar System


The maximum 3-Phase and Single-Phase short circuit currents have been determined in accordance with
IEC 60909 and as such the calculation excludes the contribution to fault level from sources at lower
voltages, e.g. from induction motors connected at 11kV or below. The method is valid and consistent with
that followed by other transmission companies in the absence of data from the Distribution Companies for
short circuit back-feeds to the grid station 33kV busbars.

a) Three-Phase Short Circuit Studies


Table C.7 summarises the results of the 3-phase fault studies over the period 2020-2024 for both systems
MIS and Dhofar System:

 All of the 400kV busbars have fault levels well within the corresponding switchgear ratings.

 All of the 220kV busbars have fault levels within the corresponding switchgear ratings.

 All of the 132kV busbars have fault levels within the corresponding switchgear ratings.

 All of the 33kV busbars have fault levels within the corresponding switchgear ratings.

b) Single-Phase Short Circuit Studies


Table C.8 summarises the results of maximum single-phase short circuit studies for both systems MIS and
Dhofar System for years from 2020 to 2024. In the years from 2020 to 2024, the fault levels across the
transmission system are within the corresponding switchgear short circuit ratings.
Only for MIS system, the major technical issue identified in the studies was the high short circuit fault
levels on the 132kV busbars at six grid stations in Muscat area from 2020 to 2024. The grid stations are
Mobella, Seeb Main, Rusail, Airport Heights Mawalleh South and Madinat Sultan Qaboos (MSQ). In
addition, Bousher grid station will experience high short circuit fault level from 2021 to 2024, Wadi Adai
grid station in 2021, 2023 and 2024. Also high short circuit fault will appear in Rusail Industrial and Al
Jefnen grid station in 2023 and 2024 due to Power 2022. During 2020 and 2024, OETC has taken
appropriate remedial action to address this problem by splitting the 132kV busbars or opening some of
132kV lines at Muscat governorate without affecting the security requirements. The studies show that there
will be a need for busbars splitting at Seeb Main grid station from 2020 to 2023, Ghala Heights grid station
in 2020 and Mawalleh South grid station in 2021 and 2023 due to the network development and
reconfiguration works. However, some of 132kV lines will be kept open to reduce the infeed short circuit
contribution and this is a part of OETC long-term strategy to operate 400kV and 220kV as the main
transmission system. The strategy is implemented with zero cost. There will be no investment required to
reduce the fault level as system can be operated safely and meeting the Transmission Security Standard
requirements. Those 132kV lines are Wadi Adai-Misfah in 2020-2021, Airport Height-Mawalleh South in
2020 and 2024, Ghala-Ghala Heights in 2021, Ghala-Airport Height in 2022 and Bousher-Ghala Height
from 2023 to 2024. An alternative solution has been studied by installing Short Circuit limiters, however
this solution is considered to be expensive compering to the implemented solution.

Page | 91
Five-Year Annual Transmission Capability Statement (2020-2024)

9. Development Opportunities

From the results of the load flow and fault level studies, and from analysis of the magnitude and location s
of generation and demand on the transmission system it is possible to give some indications as to where
future generation and demand can be connected to the transmission system without causing any critical
technical issues.

9.1 Review of the Generation Versus Load Balance on an Area Basis


The performance of the transmission system is affected by the transfer of power, both real and reactive,
from one region to another. Large power transfers between regions over long distances increase the voltage
drop across the transmission system. They also increase the power losses and reduce the efficiency of the
system. Ideally, if the balance between generation and demand is maintained on a regional or area basis
then power transfers over long distances can be minimised, thus leading to improvement of the transmission
system efficiency and voltage regulation.

Figure 35 shows the future connectivity of Oman electrical systems with introduction of proposed North-
South Interconnector which will connect MIS with PDO, Duqm, Mahout and Dhofar systems. The future
integrated system extends over the northern regions of Oman, from Madinat Shinas grid station to the south
reaching Mirbat grid station with direct distance of 875km. To assess how generation and load are
distributed over the transmission system the whole supply area has been split into nine geographic areas:

a) Muscat

b) Al Batinah South
c) Al Batinah North
d) Al Buraimi
e) Al Dhahirah
f) Al Dakhiliah
g) Al Sharqiyah
h) Al Wusta
i) Dhofar

Page | 92
Five-Year Annual Transmission Capability Statement (2020-2024)

Figure 35: Future Oman Electrical systems

Page | 93
Five-Year Annual Transmission Capability Statement (2020-2024)

Table 15 compares the generation capacity installed in each of the nine areas with the forecast demand at
the grid stations at the annual system peak over the period from 2020 to 2024.
Table 15: Estimated Power Surplus and Power Deficit on an Area Basis (2020-2024)

Grid Station loads at System Peak Demand


Area Grid & Power Stations
2020 2021 2022 2023 2024
Power 2022 0.0 0.0 600.0 600.0 600.0
Rusail IPP 693.5 693.5 0.0 0.0 0.0
Total Generation (MW) 693.5 693.5 600.0 600.0 600.0
TX-1 & TX-2 82.7 86.0 89.5 93.1 96.8
Airport Heights
TX-3 & TX-4 33.0 35.4 44.3 46.4 48.6
Al Falaj 78.5 84.5 84.5 84.5 84.5
TX-1 & TX-2 95.8 96.5 104.2 112.6 106.6
Amerat
TX-3 & TX-4 51.1 63.2 69.6 76.5 99.2
TX-1 & TX-2 124.5 121.3 84.8 89.8 95.2
A'salam
TX-3 & TX-4 48.0 89.3 97.4 105.1 93.6
TX-1 & TX-2 75.9 99.0 102.9 107.0 111.3
Bousher
TX-3 & TX-4 124.6 104.5 108.7 113.1 107.6
Daghmar 32.0 32.0 32.0 32.0 32.0
TX-1 & TX-2 73.4 94.7 96.1 104.6 106.1
Ghala
TX-3 & TX-4 50.0 51.5 53.0 54.6 56.3
Muscat TX-1 & TX-2 67.0 69.7 71.8 73.9 86.1
Ghala Heights
TX-3 & TX-4 55.0 67.2 68.9 80.7 82.5
Ghubrah 2x125MVA 103.9 107.0 110.2 112.4 114.7
TX-1 & TX-2 0.0 0.0 60.0 64.2 68.1
Mobella Industrial
TX-3 & TX-4 0.0 0.0 60.0 64.2 88.1
Jahloot 42.0 44.1 46.3 48.6 51.0
TX-1 & TX-2 0.0 30.0 31.5 33.1 49.7
Khoudh
TX-3 & TX-4 0.0 60.0 63.0 66.2 69.5
Mawalleh North 81.5 86.8 103.4 112.0 101.6
TX-1 & TX-2 98.1 92.0 95.7 99.5 103.5
Mawalleh South
TX-3 & TX-4 112.0 71.5 74.4 77.3 80.4
Misfah 67.3 70.7 74.2 77.9 81.8
Mobella 122.1 122.7 70.0 74.2 78.7
TX-1 & TX-2 79.2 87.1 90.2 91.8 93.4
MSQ
TX-3 & TX-4 76.4 84.5 87.9 89.6 91.4
Muttrah 71.2 71.2 71.2 71.2 71.2

Page | 94
Five-Year Annual Transmission Capability Statement (2020-2024)

Table 15 (continued): Estimated Power Surplus and Power Deficit on an Area Basis (2020-2024)
Grid Station loads at System Peak Demand
Area Grid & Power Stations
2020 2021 2022 2023 2024
Qurum 93.2 95.1 97.0 98.9 100.9
Quryiat 51.9 53.5 55.1 56.7 58.4
TX-1 & TX-2 54.1 58.4 61.9 65.7 69.6
Rusail Industrial
TX-3 & TX-4 88.3 95.4 101.1 107.2 113.6
TX-1 & TX-2 128.9 100.4 104.4 108.6 112.9
Seeb Main
TX-3 & TX-4 85.1 89.3 92.9 96.6 100.5
Wadi Adai 81.3 82.9 84.6 86.3 88.0
TX-1 & TX-2 69.1 69.1 69.1 69.1 69.1
Muscat Wadi Kabir
TX-3 & TX-4 59.6 59.6 59.6 59.6 59.6
Yitti 17.2 17.6 17.9 18.3 18.7
Muscat Airport 30.4 30.4 30.4 30.4 30.4
Muscat Steel 0.0 0.0 0.0 0.0 0.0
Modern Steel 0.0 0.0 0.0 0.0 0.0
R.O Ghoubrah 22.0 22.0 22.0 22.0 22.0
Total Load (MW) 2626.5 2796.1 2941.7 3075.6 3193.1
Power Surplus/Deficit (MW) -1933.0 -2102.6 -2341.7 -2475.6 -2593.1
Barka I Power & Desalination Plant 397.5 397.5 0.0 0.0 0.0
Barka II IPP 688.5 688.5 688.5 688.5 0.0
Barka III IPP 765.5 765.5 765.5 765.5 765.5
Barka WTE 0.0 0.0 0.0 0.0 100.0
Power 2024 0.0 0.0 0.0 0.0 700.0
Total Generation (MW) 1851.5 1851.5 1454.0 1454.0 1565.5
TX-1 & TX-2 56.2 59.0 62.0 65.1 67.0
Barka Main
TX-3 28.6 12.4 0.0 0.0 0.0
Blue City 124.3 128.0 140.8 144.8 148.9
Hay Asim 53.2 66.6 83.2 84.9 86.7
TX-1 & TX-2 111.1 85.5 88.9 92.5 95.3
Al Batinah South Khadhra
TX-3 & TX-4 34.3 65.7 68.3 71.1 73.2
TX-1 & TX-2 111.7 92.2 100.9 103.8 106.7
Madinat Barka
TX-3 & TX-4 25.0 50.0 52.0 54.1 55.7
MIS 45.3 47.2 48.6 50.0 51.5
TX-1 & TX-2 104.7 85.9 100.2 103.7 106.5
Muladah
TX-3 & TX-4 22.7 46.6 48.4 50.4 51.9
Nakhal 76.5 85.6 88.0 90.5 93.0
Rustaq 3x125MVA 159.4 116.8 121.5 126.3 130.1
Suwaiq 61.2 67.9 77.6 80.3 82.4
Wadi Bani Auwf 0.0 49.0 51.0 53.0 54.6
Total Load (MW) 1014.2 1058.4 1131.5 1170.4 1203.4
Power Surplus/Deficit (MW) 837.3 793.1 322.5 283.6 362.1

Page | 95
Five-Year Annual Transmission Capability Statement (2020-2024)

Table 15 (continued): Estimated Power Surplus and Power Deficit on an Area Basis (2020-2024)
Grid Station loads at System Peak Demand
Area Grid & Power Stations
2020 2021 2022 2023 2024
Sohar I Power & Desalination Plant 566.0 566.0 0.0 0.0 0.0
Sohar II IPP 765.5 765.5 765.5 765.5 765.5
Sohar III IPP 1743.1 1741.8 1739.3 1740.7 1739.7
Total Generation (MW) 3074.6 3073.4 2504.8 2506.3 2505.2
Dil Abdusalam 73.3 78.3 80.6 82.3 87.2
Khaborah 88.0 91.2 95.4 99.7 104.3
TX-1 & TX-2 56.1 59.8 56.7 59.9 63.0
Liwa
TX-3 & TX-4 67.2 73.0 76.4 79.8 82.1
Madinat Shinas 64.5 73.7 78.9 82.9 86.6
Saham 86.2 87.4 90.0 90.2 95.1
Shinas 64.8 67.3 79.6 84.3 91.7
SIA 76.8 84.4 84.9 85.4 86.1
TX-1 & TX-2 55.7 58.6 68.2 90.0 94.4
Sohar
TX-3 & TX-4 108.7 112.9 112.8 97.5 100.7
Al Batinah North TX-1 & TX-2 36.6 41.0 44.9 41.2 42.2
Sohar Free Zone
TX-3 & TX-4 49.1 50.4 51.4 52.6 54.3
TX-1 & TX-2 52.2 53.8 55.5 58.2 60.0
Uwaynat
TX-3 & TX-4 60.8 62.9 64.7 68.7 71.1
Sohar Refinery (132kV SIA) 0.0 0.0 0.0 0.0 0.0
Sohar Steel (SSSRM) (132kV SIA) 0.0 0.0 0.0 0.0 0.0
Jindal Shadeed (220kV SIA) 60.0 60.0 100.0 100.0 100.0
VALE (132kV SIA) 85.0 85.0 85.0 85.0 85.0
ARMS (132kV Liwa) 4.2 4.2 4.2 4.2 4.2
OMPET (132kV SIA) 0.0 4.0 4.0 4.0 4.0
Orpic (Liwa Plastic) (220kV SPS-2) 25.0 25.0 25.0 25.0 25.0
Moon Iron & Steel Co. (220KV SFZ) 15.0 15.0 15.0 15.0 15.0
Al Tamam INDSIL (132kV SFZ) 8.0 8.0 8.0 8.0 8.0
Total Load (MW) 1137.0 1195.8 1281.1 1313.9 1360.2
Power Surplus/Deficit (MW) 1937.6 1877.5 1223.7 1192.3 1145.0
Total Generation (MW) 0.0 0.0 0.0 0.0 0.0
Bureimi 48.4 51.3 53.3 55.5 56.9
TX-1 & TX-2 40.2 41.0 42.0 43.1 44.6
Buriami Industrial
TX-3 & TX-4 50.4 59.6 61.2 62.9 66.4
Al Bureimi
Mahadah 24.1 17.2 17.4 17.8 18.0
Wadi Sa'a 14.1 16.5 18.1 20.4 22.6
Total Load (MW) 177.2 185.6 192.1 199.7 208.6
Power Surplus/Deficit (MW) -177.2 -185.6 -192.1 -199.7 -208.6

Page | 96
Five-Year Annual Transmission Capability Statement (2020-2024)

Table 15 (continued): Estimated Power Surplus and Power Deficit on an Area Basis (2020-2024)
Grid Station loads at System Peak Demand
Area Grid & Power Stations
2020 2021 2022 2023 2024
Ibri IPP 1541.7 1540.6 1539.6 1538.5 1537.7
Ibri Solar PV IPP 0.0 0.0 450.0 450.0 450.0
Total Generation (MW) 1541.7 1540.6 1989.6 1988.5 1987.7
Al Hayl 40.5 7.6 7.7 7.8 8.0
Dank 38.1 42.6 47.7 51.3 52.2
Al Dhahirah Dreez 79.3 81.5 83.7 88.2 90.7
2x63MVA 38.9 40.1 41.3 40.6 41.9
Ibri
2x125MVA 78.2 80.2 82.2 84.3 86.8
Yanqul 0.0 33.5 34.4 35.4 36.7
Total Load (MW) 275.1 285.5 297.0 307.6 316.3
Power Surplus/Deficit (MW) 1266.6 1255.2 1692.6 1680.9 1671.4
Manah IPP 182.2 182.2 182.2 182.2 182.2
Manah Solar PV IPP 0.0 0.0 0.0 150.0 300.0
Total Generation (MW) 182.2 182.2 182.2 332.2 482.2
Adam 52.5 55.1 57.9 60.8 62.6
Bahla 74.9 78.6 82.5 86.7 90.1
Birkat Al Mouz 50.8 53.8 57.1 60.5 64.1
Izki 81.2 87.5 90.0 91.7 93.5
Jebreen 64.0 66.5 69.2 71.9 74.1
Al Dakhiliah
Madinat Nizwa 63.2 65.8 68.4 71.1 73.3
New Izki 20.6 21.4 22.3 23.2 23.9
Nizwa 85.1 96.6 109.3 112.0 114.8
2x63MVA 52.4 54.0 55.1 56.2 57.3
Sumail
2x125MVA 108.9 59.6 62.0 63.9 65.8
Sumail Industrial Area 0.0 53.6 55.2 56.9 58.6
Total Load (MW) 653.6 692.6 728.9 754.8 778.0
Power Surplus/Deficit (MW) -471.4 -510.4 -546.7 -422.6 -295.8
Al Kamil IPP 291.4 291.4 0.0 0.0 0.0
Sur IPP 2018.2 2018.2 2018.2 2018.2 2018.2
JBB Ali Wind Farm 0.0 0.0 0.0 0.0 19.0
Total Generation (MW) 2309.6 2309.6 2018.2 2018.2 2037.2
Al Jawabi 0.0 0.0 0.0 0.0 80.0
Al Sharqiyah
Ayjah 72.7 74.9 89.3 91.6 94.0
Bedyah 49.8 51.8 53.9 56.0 58.3
Ibra 79.9 83.0 86.2 89.5 92.1
JBB Ali 120.0 146.8 151.8 157.0 82.4
JBB Hassan 73.2 83.1 86.2 89.4 92.7

Page | 97
Five-Year Annual Transmission Capability Statement (2020-2024)

Table 15 (continued): Estimated Power Surplus and Power Deficit on an Area Basis (2020-2024)
Grid Station loads at System Peak Demand
Area Grid & Power Stations
2020 2021 2022 2023 2024
Mudhaibi 47.0 48.9 55.7 57.7 59.3
Mudhairib 56.5 64.7 67.1 69.5 71.4
Samad 25.0 25.8 26.5 27.3 28.1
Al Sharqiyah Sinaw 35.0 36.8 38.2 39.7 40.9
Sur 94.0 96.8 99.6 102.4 105.4
Total Load (MW) 653.2 712.5 754.4 780.2 804.6
Power Surplus/Deficit (MW) 1656.3 1597.0 1263.8 1238.0 1232.6
Duqm Wind Farm 0.0 0.0 0.0 0.0 68.5
Total Generation (MW) 0.0 0.0 0.0 0.0 68.5
TX-1 & TX-2 0.0 0.0 0.0 60.8 61.8
Duqm
Al Wusta TX-3 & TX-4 0.0 0.0 0.0 53.4 54.3
Mahout (2X125MVA) 0.0 0.0 0.0 23.9 24.9
Total Load (MW) 0.0 0.0 0.0 138.0 141.0
Power Surplus/Deficit (MW) 0.0 0.0 0.0 -138.0 -72.5
NPS 273.0 273.0 273.0 273.0 273.0
Salalah Power & Desalination Plant 430.0 430.0 430.0 430.0 430.0
Salalah II IPP 444.0 443.0 442.0 442.0 442.0
Dhofar Wind Farm 18 18 18 18 18
Total Generation (MW) 1165.0 1164.0 1163.0 1163.0 1163.0
Al Qarm (2x63MVA) 34.4 33.2 36.0 27.7 28.5
Ashoor (2X125MVA) 68.7 55.8 56.7 56.7 57.7
Saih Al Khairat (2x125MVA) 0.0 0.0 0.0 44.2 45.8
Ittin (2X125MVA) 78.4 71.8 74.8 83.5 87.1
Mirbat 2x63 MVA 0.0 20.9 24.9 26.9 29.1
NPS (2x63MVA) 39.7 38.8 41.9 43.1 44.7
Dhofar
TX-1 & TX-2 65.0 80.6 88.5 101.9 105.5
S'aadah
TX-3 & TX-4 44.3 66.5 87.2 102.3 105.9
Raysut 101.7 111.5 109.0 108.3 108.5
Salalah-IPP 39.7 69.0 101.1 107.5 112.0
Shaha'aon (2X125MVA) 95.3 99.4 98.3 81.9 85.0
2x30 MVA 24.2 0.0 0.0 0.0 0.0
Thumrait
2x63 MVA 0.0 28.8 32.6 33.6 34.6
Salalah Airport 7.0 8.0 8.0 8.0 8.0
Salalah Methanol Company 0.0 35.0 35.0 35.0 35.0
Total Load (MW) 598.2 719.3 794.1 860.6 887.3
Power Surplus/Deficit (MW) 566.7 444.7 368.8 302.4 275.6

Page | 98
Five-Year Annual Transmission Capability Statement (2020-2024)

Figure 36 to Figure 44 show graphically the generation and load in each of the nine areas. The significant
differences in generation and load imbalance in areas such as Muscat, Al Batinah North, Al Dhahirah and
Al Sharqiyah necessitate high development and investment in the transmission system to facilitate power
transfer among the different areas in order to supply the growing loads.

Muscat area, although geographically the smallest area, is by far the most heavily populated, with the
highest demand (2626.5 MW in 2020, rising to 3193.1 MW in 2024) and with a limited amount of connected
generation (693.5 MW in 2020 and will be retired by end of 2021). This will result in power deficits of
1933 MW in 2020 and 3193.1 MW in 2024. Muscat area has one power plant; Rusail IPP (693.5 MW in
2020 and will be retired by end of 2021). In addition Power 2022 proposed to be in Muscat (600 MW from
2022 to 2024). As observed from Figure 36, there is a high gap between the installed generation capacity
and load in Muscat area and it will keep increasing if no new generation is installed in Muscat area. This
situation will have significant adverse impacts on the system operation performance and security. These
impacts are reflected in a massive power been imported from the far generation such as Sur, Ibri and Barka
to supply Muscat load, which has resulted in an increase of transmission power losses. Moreover, the
absence of sufficient generation capacity in Muscat area has led to a shortage of the reactive power support,
which may lead OETC to invest in expensive reactive power compensations to overcome this issue and
maintain the voltage system stability. Furthermore, in order to secure the power supply in Muscat area,
OETC has to reinforce and extend the 400kV and 220kV transmission systems, which has high cost
implication. Therefore, there is a high need to plan the new generation to be located in Muscat vicinity.

Muscat Area
3500

3000
Power (MW)

2500

2000

1500 Total Generation (MW)

1000 Total Load (MW)

500

0
2020 2021 2022 2023 2024

Figure 36: Generation and load balance in Muscat area

Page | 99
Five-Year Annual Transmission Capability Statement (2020-2024)

Al Batinah South area covers the coastal strip between Barka on the western outskirts of the Muscat area
and Sohar. This area is likely to develop as Muscat, since the main road link between Muscat and Sohar
runs through it. Currently, there are three power plants in Al Batiniah South; Barka Phase-I (397.5 MW and
it is planned to be retired by end of 2021), Barka Phase-II (688.5 MW and it is planned to be retired by end
of 2023) and Barka Phase-III (765.5 MW).Further, Waste to Energy plant and Power 2024 will be
introduced in 2024 (100 MW and 700 MW respectively). As shown in Table 15, the load in this area rises
from 1014.2 MW in 2020 to 1203.4 MW in 2024. The power surplus is 837.3 MW in the summer peak of
2020 and 362.1 MW in the summer peak of 2024.

2000
1800
1600
Power (MW)

1400
1200
1000
800 Total Generation (MW)
600 Total Load (MW)
400
200
0
2020 2021 2022 2023 2024

Figure 37: Generation and load balance in Al Batinah South area

Al Batinah North area is rapidly developing around the new port at Sohar with new industries seeking
connections to the OETC transmission system or the distribution system of Majan Electricity Company.
Some of the largest industrial customers in the area, such as Sohar Aluminium Company operates their own
generating plant and on occasions supply power to the transmission system on a non-contracted basis. The
load in Al Batinah North area significantly increases from 1137 MW in 2020 to 1360.2 MW in 2024, as
shown in Table 15. Al Batinah North area has three power plants; Sohar-I (566 MW and it is planned to be
retired by end of 2021), Sohar-II (with total 765.5 MW power during the period 2020-2024) and Sohar-III
IPP with a power capacity of 1743.1 MW. In 2020, the generation surplus in this area will be 1937.6 MW
and will decrease to 1145 MW in 2024 due to the retirement of Sohar-I power plant.

Page | 100
Five-Year Annual Transmission Capability Statement (2020-2024)

3500

3000

2500
Power (MW)

2000
Total Generation (MW)
1500
Total Load (MW)
1000

500

0
2020 2021 2022 2023 2024

Figure 38: Generation and load balance in Al Batinah North area

The transmission system in the Al Buraimi area provides interconnection with the GCCIA through UAE
(Abu Dhabi Transco) supplies a number of grid stations that feed Majan Distribution System. This area has
no generation and depends on the transmission interconnections with Al Batinah North and Al Dhahirah
regions to supply its loads. The load in Al Buraimi area increases from 177.2 MW in 2020 to 208.6 MW in
2024, as shown in Table 15. The deficiency in generation rises from 177.2 MW in 2020 to 208.6 MW in
2024.

Al Buraimi Area
250

200
Power (MW)

150
Total Generation (MW)

100 Total Load (MW)

50

0
2020 2021 2022 2023 2024

Figure 39: Generation and load balance in Al Buraimi area

Page | 101
Five-Year Annual Transmission Capability Statement (2020-2024)

There is a generation power plant at Al Dhahirah that is Ibri IPP with a power capacity of 1541.7 MW and
new Ibri Solar PV IPP will be in the service in 2022 with a power capacity of 450 MW. The load in this
area will increase from 275.1 MW in 2020 to 316.3 MW in 2024, as shown in Table 15. The 220kV systems
from Mahadha in Buraimi area to Ibri have produced an improvement in the voltage quality and increased
the security of supply. Moreover, the voltage profile and supply security have further improved by the
introduction of Ibri IPP in 2019 and Ibri Solar PV IPP in 2022. In 2020, the surplus in generation will be
1266.6 MW and will increase to reach 1671.4 MW in 2024.

2500

2000
Power (MW)

1500
Total Generation (MW)

1000 Total Load (MW)

500

0
2020 2021 2022 2023 2024

Figure 40: Generation and load balance in Al Dhahirah area

Al Dakhiliah area with its provincial load centres is exhibiting moderate growth up and has a local
generating power plant at Manah (182.2 MW) connected to the 132kV transmission system. There will be
a new generartion at Al Dakhiliah (Manah Solar PV IPP) where first phase will be in the service in 2023
with a power capacity of 150 MW while second phase will be in service in 2024 with a power capacity of
150 MW. A connection between OETC and PDO is available in the area through the 132kV Nizwa- Nahada
transmission line. Another connection will be introduced between these two systems via line in line out Ibri
IPP – New Izki 400kV overhead line at Nahada area and it is expected to be in service by Q3 2022.The
deficiency in generation will decrease from 471.4 MW in 2020 to 295.8 MW in 2024.

Page | 102
Five-Year Annual Transmission Capability Statement (2020-2024)

900
800
700
Power (MW)

600
500
400
Total Generation (MW)
300
200 Total Load (MW)

100
0
2020 2021 2022 2023 2024

Figure 41: Generation and load balance in Al Dakhiliah area


Al Sharqiyah area has a provincial load centre that is exhibiting moderate growth up. Al Sharqiyah area has
two power plants; Al-Kamil IPP (291.4 MW and it is planned to be retired by end of 2021) and Sur IPP
with a total power capacity of 2018.2 MW during the period 2020-2024). In addition, a new wind farm that
is planned to be constructed in JBB Ali (19MW and will be in service in 2024). The power surplus in this
area will be decreased from 1656.3 MW in 2020 to 1232.6 MW in 2024 due to retirement of Al-Kamil IPP.
This area is well connected through a 400kV system with Muscat and Al Dakhiliah areas, which offers a
power transfer to other Governorates.

2500

2000
Power (MW)

1500
Total Generation (MW)
1000 Total Load (MW)

500

0
2020 2021 2022 2023 2024

Figure 42: Generation and load balance in Al Sharqiyah area

Page | 103
Five-Year Annual Transmission Capability Statement (2020-2024)

Currently, OETC has no transmission system in the Al Wusta area and the loads are supplied by RAEC by
using diesel generation. In 2023, phase one of 400kV interconnection line project will be ready including
connecting PDO and RAEC systems via Suwaihat, Duqm and Mahout grid stations. RAEC loads will be
supplied via PDO system and this area will depend on the new 400kV transmission interconnection line
with Al Dakhiliah governorate once it is ready by end of 2024. Further, a new wind farm will be constructed
in Duqm (68.5MW and will be ready by 2024).The load in Al Wusta area is expected to be 138 MW and
141MW in 2023 and 2024 respectively. In addition, Table 15 shows that the deficiency in generation in
2023 will be 138 MW and will decrease in 2024 to be 72.5 MW.

Al Wusta Area
160

140

120
Power (MW)

100

80 Total Generation (MW)


60 Total Load (MW)

40

20

0
2020 2021 2022 2023 2024

Figure 43: Generation and load balance in Al Wusta area

The transmission system in the Dhofar area provides another interconnection with PDO and supplies a
number of grid stations that feed DPC Distribution System to supply Salalah city, and a number of towns
and villages in Dhofar area. Currently, there are four power plants in Dhofar area; NPS Power Plant (273
MW), Salalah IPP Power Plant (430 MW), Salalah II IPP (444 MW) and Dhofar wind farm with a power
capacity of 18 MW. As shown in Table 15, the load in Dhofar area will rise from 598.2 MW in 2020 to
887.3 MW in 2024. The generation surplus will decrease from 566.7 MW in 2020 to 275.6 MW in 2024
due to new bulk loads.

Page | 104
Five-Year Annual Transmission Capability Statement (2020-2024)

Dhofar Area
1400

1200

1000
Power (MW)

800

600 Total Generation (MW)


Total Load (MW)
400

200

0
2020 2021 2022 2023 2024

Figure 44: Generation and load balance in Dhofar area

9.2 Available grid station capacity


Table C.2 in Appendix C identifies the available capacity at the grid stations for the connection of new
demand over the period 2020 to 2024. Table 16, lists the grid stations where spare grid transformer capacity
of more than 10 MVA is available to supply new demand, on the same area basis as that presented in sub-
section 9.1. The MVA figures quoted refer to the available capacity in 2024. The available capacity was
determined in relation to the firm capacity of the substation. Figure 45 to Figure 54 show graphical
representation of available capacities.

Page | 105
Five-Year Annual Transmission Capability Statement (2020-2024)

Table 16: Available Grid Station Capacity of more than 10 MVA in 2024
Available Capacity Available Capacity
Region Grid Station Name Grid Station Name
(MVA) (MVA)
Airport Heights (TX-1 & TX-2) 23.12 Khoudh (TX-3 & TX-4) 51.89
Airport Heights (TX-3 & TX-4) 73.85 Mawalleh North 18.00
Al Falaj 36.01 Mawalleh South (TX-1 & TX-2) 16.08
Amerat (TX-1 & TX-2) 12.83 Mawalleh South (TX-3 & TX-4) 40.34
Amerat (TX-3 & TX-4) 20.62 Misfah 38.88
A'salam (TX-1 & TX-2) 24.76 Mobella 42.19
A'salam (TX-3 & TX-4) 26.52 MSQ (TX-1 & TX-2) 26.64
Bousher (TX-3 & TX-4) 11.75 MSQ (TX-3 & TX-4) 28.76
Muscat Daghmar 66.32 Muttrah 50.05
Ghala (TX-1 & TX-2) 13.34 Qurum 18.78
Ghala (TX-3 & TX-4) 65.76 Quryiat 63.50
Ghala Heights (TX-1 & TX-2) 34.33 Rusail Industrial (TX-1 & TX-2) 51.74
Ghala Heights (TX-3 & TX-4) 38.15 Seeb Main (TX-3 & TX-4) 19.23
Mobella Industrial (TX-1 & TX-2) 53.37 Wadi Adai 32.37
Mobella Industrial (TX-3 & TX-4) 32.31 Wadi Kabir (TX-1 & TX-2) 52.28
Jahloot 71.29 Wadi Kabir (TX-3 & TX-4) 62.27
Khoudh (TX-1 & TX-2) 72.65 Yitti 105.36
Barka Main 54.47 Muladah (TX-1 & TX-2) 12.88
Hay Asim 33.77 Muladah (TX-3 & TX-4) 70.38
khadhra (TX-1 & TX-2) 24.72 Nakhal 27.12
Al Batinah
khadhra (TX-3 & TX-4) 47.96 Rustaq 3x125M VA 113.02
South
Madinat Barka (TX-1 & TX-2) 12.67 Suwaiq 38.31
Madinat Barka (TX-3 & TX-4) 66.37 Wadi Bani Auwf 67.54
MIS 70.76
Dil Abdusalam 33.23 SIA 34.39
Khaborah 15.16 Sohar (TX-1 & TX-2) 25.59
Liwa (TX-1 & TX-2) 58.69 Sohar (TX-3 & TX-4) 18.97
Al Batinah
Liwa (TX-3 & TX-4) 38.54 Sohar Free Zone (TX-1 & TX-2) 80.54
North
Madinat Shinas 33.80 Sohar Free Zone (TX-3 & TX-4) 67.84
Saham 24.90 Uwaynat (TX-1 & TX-2) 61.83
Shinas 28.49 Uwaynat(TX-3 & TX-4) 50.13
Bureimi 65.08 Mahadah 11.02
Al Buraimi Bureimi Industrial(TX-1&TX-2) 78.06 Wadi Sa'a 39.17
Bureimi Industrial(TX-3&TX-4) 55.08
Al Hayl 31.58 Ibri 2x125MVA 33.66
Al Dhahirah Dreez 29.49 Yanqul 86.34
Ibri 2x63MVA 18.91

Page | 106
Five-Year Annual Transmission Capability Statement (2020-2024)

Table 16 (continued): Available Grid Station Capacity of more than 10 MVA in 2024

Available Capacity Available Capacity


Region Grid Station Name Grid Station Name
(MVA) (MVA)
Adam 59.11 Madinat Nizwa 47.88
Bahla 30.12 New Izki 99.89

Al Dakhiliah Birkat Al Mouz 57.49 Sumail 2x125M VA 55.73

Izki 26.63 Sumail Industrial Area 63.35

Jebreen 47.00

Al Jawabi 40.79 Mudhaibi 62.61


Ayjah 26.03 Mudhairib 49.79

Bedyah 63.67 Samad 33.38


Al Sharqiyah
Ibra 28.07 Sinaw 81.90
JBB Ali 38.26 Sur 14.05

JBB Hassan 27.47

Duqm (TX-1&TX-2) 60.00 Mahout (2X125MVA) 98.74


Al Wusta
Duqm (TX-3&TX-4) 67.80

Al Qarm (2x63M VA) 32.96 NPS (2x63MVA) 15.98


Ashoor (2X125MVA) 64.30 S’aadah (TX-1 & TX-2) 13.91

Dhofar Saih Al Khairat (2x125M VA) 76.79 S’aadah (TX-3 & TX-4) 13.51
Shaha'aon (2X125MVA) 35.49 Raysut 10.79
Ittin (2X125MVA) 33.37 Thumrait 2x63 MVA 26.58

Mirbat 2x63 MVA 32.42

Page | 107
Five-Year Annual Transmission Capability Statement (2020-2024)

125

100

75
S(MVA)

Available MVA
50
Used MVA
25

Grid Station
Figure 45: Used and available MVA in Muscat area at 2024 peak demand

125

100

75
S(MVA)

50 Available MVA

25 Used MVA

Grid Station
Figure 46: (Continued) Used and available MVA in Muscat area at 2024 peak demand

Page | 108
Five-Year Annual Transmission Capability Statement (2020-2024)

125

100

75

50
S(MVA)

25 Available MVA

0 Used MVA

Grid Station
Figure 47: (Continued) Used and available MVA in Muscat area at 2024 peak demand

250
225
200
175
150
S(MVA)

125
100
75 Available MVA
50 Used MVA
25
0

Grid Station

Figure 48: Used and available MVA in Al Batinah South area at 2024 peak demand

Page | 109
Five-Year Annual Transmission Capability Statement (2020-2024)

125

100

75
S(MVA)

50
Available MVA
Used MVA
25

Grid Station

Figure 49: Used and available MVA in Al Batinah North area at 2024 peak demand

125

100

75

50
S(MVA)

25 Available MVA
Used MVA
0

Grid Station

Figure 50: Used and available MVA in Al Buraimi and Al Dhahirah areas at 2024 peak demand

Page | 110
Five-Year Annual Transmission Capability Statement (2020-2024)

125

100

75
S(MVA)

50

Available MVA
25
Used MVA

Grid Station

Figure 51: Used and available MVA in Al Dakhiliah area at 2024 peak demand

125

100
S(MVA)

75

50
Available MVA
25
Used MVA
0

Grid Station

Figure 52: Used and available MVA in Al Sharqiyah area at 2024 peak demand

Page | 111
Five-Year Annual Transmission Capability Statement (2020-2024)

125

100
S(MVA)

75

50 Available MVA
Used MVA
25

0
Duqm (TX-1&TX-2) Duqm (TX-3&TX-4) Mahout (2X125MVA)

Grid Station
Figure 53: Used and available MVA in Al Wusta area at 2024 peak demand

125

100

75
S(MVA)

50

Available MVA
25
Used MVA
0

Grid Station

Figure 54: Used and available MVA in Dhofar area at 2024 peak demand

Page | 112
Five-Year Annual Transmission Capability Statement (2020-2024)

9.3 Potential Generation Connections


This section aims to provide an overview of the potential generation connections to the main grid for Power
2024. In OPWP’s Seven Years Statement, generation plans are provided in terms of installed capacities,
preferred generation technology, areas of potential generation and expected completion time. OETC as
Transmission Operator is providing nominated generation connections from grid point of view, taken into
consideration the generation output power, voltage level of generation connection, required assets for
connection or system reinforcement and technical and financial ranking of generation points. Each
generation connection point will be evaluated technically in terms of grid losses, loading issues, short circuit
violations and location from Muscat load centre. Further, the financial evaluation includes ranking in terms
of cost of connection or system reinforcement required to evacuate the generation point.

For power 2024, five potential sites has been considered: Misfah, Barka, Ghubrah, Sohar,Manah and Al
Kamil. Misfah site was recommended for power 2022, however OPWP has postponed the project. This
investment would require constructing 220kV GIS, diversion of Misfah - Wadi Adai 132kV UGC in Misfah
generation location, diversion of Misfah - MSQ 220kV OHL to 220kV UGC in Misfah generation location
and LILO 220kV Misfah – MSQ OHL at Misfah generation location. Proposing such generation in Muscat
area close to the load will improve the voltage profile and provide security of supply within the area.
Further, it will minimize the losses produced from importing power from other governorates to Muscat.
Moreover, Muscat governorate would experience issues in voltage recovery after faults and having Misfah
generation would resolve all issues and avoid installation of reactive power compensation (i.e. SVC or
STATCOM).

Having power 2024 in Barka will help in exporting power towards Muscat governorate and to supply load
within the area. This site can accommodate up to 360MW without the need for system reinforcement and
700MW with additional reinforcement (additional 2x220kV OHL Filaj-Mobella). Furthermore, the system
studies assumed that the existing nearby generation in Barka is dispatched fully.

Similar to Misfah, Ghubrah location is close to Muscat load centre and having generation at the site will
provide reactive support to improve voltage profile and resolve voltage recovery issues. This site can
accommodate up to 700MW with minor reinforcements (additional 1x132kV GIS bay and modification of
1x132kV GIS bay at New Ghubrah).

Sohar site is proposed to accommodate power 2024, having additional capacity in Sohar would require a
huge investment in the transmission network. The investment includes additional 2x400kV bays and
2x400kV OHL SIS-Rustaq (126km). Sohar site can accommodate up to 450MW without the need for
system reinforcement and 700MW with additional reinforcement at Sohar area.

The last sites are Manah and Al kamil will be considered to share the 700MW of power 2024. The two sites
do not require any reinforcement to evacuate the proposed capacity. However, these sites are far from
Muscat load centre.

Page | 113
Five-Year Annual Transmission Capability Statement (2020-2024)

In terms of technical and financial ranking, Barka provides a good technical performance, however Barka
location considered to be little far from load centre of Muscat and it financially requires investments in
220kV system. Also, Ghubrah site provides a good technical performance and location which is closer to
Muscat. In addition, it requires minor reinforcements which makes it very attractive financially. Further,
Misfah provides a strategic location and good performance, however it requires new investments in the
transmission network which impact it is financial ranking. On the other hand, Sohar does not provide an
attractive option technically and financially. Furthermore, Manah and Al Kamil sites does not provide a
good technical performance and their locations which are from Muscat load centre. In terms of overall
ranking, Ghubrah ranked as the most preferred option while Sohar ranked as non-preferred option
considering both technical and financial ranking. Table 17 shows the potential generation connection and
the Technical and Financial rankings.

Page | 114
Five-Year Annual Transmission Capability Statement (2020-2024)

Table 17: Potential Generation Connections for 2024

Potential Voltage Technical Financial


Sr. Capacity Required Assets for Connection or System
Generation Level Preference Preference Remarks
No (MW) Reinforcement
Point (KV) Ranking Ranking

Power 2024
Constructing 220kV GIS, diversion of Misfah - Wadi
Having a generation in Muscat
Adai 132kV UGC in Misfah generation location,
area close to the load centre would
1 Misfah 700 220 diversion of Misfah - MSQ 220kV OHL to 220kV UGC 3 4
improve the voltage profile and
in Misfah generation location and LILO 220kV Misfah
provide security of supply.
– MSQ OHL at Misfah generation location.
This Site can accommodate up to
Additional 2x220kV bays and 2x220kV OHL Filaj- 360MW without the need for
2 Barka 700 220 1 3
Mobella (10 km) system reinforcement and 700MW
with additional reinforcement.
This Site is close to Muscat load
Additional 1x132kV GIS bay and modification of
3 Ghubrah 700 132 2 2 centre and can accommodate up
1x132kV GIS bay at New Ghubrah
700MW with minor reinforcement
This Site can accommodate up to
Additional 2x400kV bays and 2x400kV OHL SIS- 450MW without the need for
4 Sohar 700 220 5 5
Rustaq (126 km) system reinforcement and 700MW
with additional reinforcement
The two sites do not require any
Manah and Al
5 700 132 No requirements 4 1 reinforcement to accommodate
Kamil
700MW in total.

Page | 115
Five-Year Annual Transmission Capability Statement (2020-2024)

10. Non-compliances

The load flow studies summarised in Appendix C and discussed in Sections 8 and 9 of this Statement
indicate a number of out of firm grid stations and circuits in the early years of the Statement. In this final
section, a review of each grid station / circuit, which is currently failing to meet the Transmission Security
Standards, is presented. In addition, a description of the development activities that OETC is undertaking
to address this non-compliance and indicates the expected time by which, in each instance, full
Transmission Security Standards compliance should be achieved are presented.
It should be noted that the level of the security requirements on the transmission system would change in
future as the demand on the system increases and as the system configuration changes. It is possible that
further non-compliances will arise in the future until the overall system becomes substantially more robust
through interconnection. OETC will keep this situation under review, and the non-compliance status will
be updated in the 2021 Capability Statement.
As indicated in sections 8, 9 and summarized in Table 18,Table 19 and Table 20, there are some overhead
lines/cables and grid stations, which do not comply with the Transmission Security Standard. Therefore, it
will be necessary for a further location and duration for specific derogations to be prepared by OETC and
approved by the authority for each of the out of firm grid stations which do not comply with the
Transmission Security Standard at peak and maintenance time noted in Table 18,Table 19 and Table 20.
The following points should be noted:
1) The loading results that are shown in Tables C1 and C3 (Appendix C), are those at the peak load
conditions. The system peak lasts only for a period of less than one hour in one day during the
relevant year.
2) According to the most recent OPWP data, there are two forecast cases: (i) expected case, and (ii)
high case. The difference between the high and expected cases in 2020 for MIS is 260 MW and for
Dhofar System is 10 MW at the peak time. This difference will increase in the subsequent years
where it will reach 1480 MW for MIS and 130 MW for Dhofar System in 2024, indicating
uncertainty in the forecast over the coming years especially with regards to new industrial loads.
OETC intends to monitor closely the situation, in coordination with OPWP, in order to assess the
probability associated with the high case projection and the effect of the approved Cost Reflected
Tariff (CRT).
3) It is not prudent to invest in uncertain expansion. OETC will initiate new projects as new demand
becomes more certain. Therefore, Table 18 shows conditions at the summer peak of 2020.
4) The modelling reflects all load transfer schemes that have been formally accepted by the relevant
Distribution Company, which are included in their load forecasts.

Page | 116
Five-Year Annual Transmission Capability Statement (2020-2024)

OETC has adopted a two-fold approach to address these out of firm situations:
1) Reinforcement plans: strategic upgrading to add new circuits and/or to increase the capacity of grid
stations within a minimum of three to five years. This will not just solve the problem, but it will
also strengthen the transmission system for future development. This type of solution can only be
applied as a longer-term solution because of the time taken to implement. Reinforcement is the
most robust long-term solution for secure system development, but may not necessarily be the least
cost effective solution to address the immediate out of firm conditions on the network.
2) Load Transfer: through agreement with Distribution Companies, load can be transferred from
heavily loaded grid stations to more lightly loaded grid stations over the next years. This would
reduce the loading issues and balance the system during peak time. This is a mid-term solution,
which could be implemented by Distribution Companies in certain cases. Given the uncertainty of
mid-term load forecasts in Oman at present, this is in some circumstances the most appropriate and
economic action to address out of firm conditions on the network.
Table 18 and Table 19 indicate a number of overhead lines/cables and grid stations on the system that will
be out of firm in 2020. Table 20 shows the grid stations which are classified as group E (>115 MW) that
are not complying with the Transmission Security Standard (Second Outage) at 2020 maintenance period.

Page | 117
Five-Year Annual Transmission Capability Statement (2020-2024)

Table 18: Expected Over headlines/Cable, which will not comply with Transmission Security Standard (First Outage) at Peak Demand in 2020

Indicative
Date for full
Circuit Circuit Compliance
Sending Receiving Voltage No. of Circuit Conductor Loading
No. length Rating with the Remarks
Bus Bus (kV) Circuit Type Size/Type (% )
(Km) (MVA) Transmission
Security
Standard

The project of 400kV OHL between


1 Al Filaj Mobella 220 2 OHL ARCURIA 9.8 673 56.78 August 2020 New Izki and Misfah is delayed than
previous expected date (March 2020)

The project of Khaborah


Interconnection Station (KIS) is
2 SIS Saham 132 2 OHL YEWx2 23.3 293 52.19 August 2020
delayed than previous expected date
(June 2020)

The project of 400kV OHL between


3 Izki New Izki 132 2 OHL YEWx2 17.05 293 65.58 August 2020 New Izki and Misfah is delayed than
previous expected date (March 2020)

Page | 118
Five-Year Annual Transmission Capability Statement (2020-2024)

Table 19: Expected Grid stations 132/33kV, which will not comply with Transmission Security Standard (First Outage) at Peak Demand in 2020

Indicative Date for full


Total Substation
Loading Compliance with the
No. Location Transformer Firm Capacity Remarks
(% ) Transmission Security
Capacity (MVA) (MVA)
Standard
Muscat
Transformer capacity has been provided in Seeb Main grid
1 Seeb Main 2x125 125 55.67 June 2021 station (TX-3&Tx-4) since September 2018. DISCO’s load
transfer will solve the non-compliance in June 2021.
Transformer capacity has been provided in Ghala Height
2 Bousher 2x125 125 55.53 June 2021 grid station since March 2019. DISCO’s load transfer will
solve the non-compliance in June 2021.
Transformer capacity has been provided in A'salam grid
station (TX-3&Tx-4) since November 2018. DISCO’s load
3 A'salam 2x125 125 53.81 December 2022 transfer will solve the non-compliance in June 2022. In
addition, load transfer to new Mobella Industrial grid
station will be in December 2021.
4 Mobella 2x125 125 52.69 December 2021 Load transfer to new Mobella Industrial grid station.
Mazoon

1 JBB Ali 2x125 125 52.61 June 2024 Load transfer to new Al Jawabi grid station

Majan

1 Al Hayl 2x40 40 53.62 December 2020 Load transfer to new Yanqul grid station

Page | 119
Five-Year Annual Transmission Capability Statement (2020-2024)

Table 20: Expected Grid stations 132/33kV, which will not comply with Transmission Security Standard at Maintenance Period in 2020.
Transferable
Demand
Peak Load in case of Transmission
Tx No. Forecast
Grid Station Demand Transformer Second Outage Security
No. capacity of During Remarks
Name Forecast Loading (% ) During Standard
(MVA) Txs Maintenance
(MW) Maintenance Compliant
(MW)
(MW)
Muscat
Transformer capacity has been provided
in Seeb Main grid station (TX-3&Tx-4).
1 Seeb Main 125 2 128.9 55.67 85.9 7 No
DISCO’s load transfer will solve the
non-compliance.
Transformer capacity has been provided
in Ghala Height grid station. DISCO’s
2 Bousher 125 2 124.6 55.53 83.06 38 No
load transfer will solve the non-
compliance.
Transformer capacity has been provided
in A'salam grid station (TX-3&Tx-4).
3 A'salam 125 2 124.5 53.81 83 40 No
DISCO’s load transfer will solve the
non-compliance.
Load transfer to new Mobella Industrial
4 Mobella 125 2 122.1 52.69 81.4 7 No
grid station.
Mazoon
MZEC to resolve this issue via either
1 Blue City 160 2 124.3 41.93 82.86 40 No load transfer or applying for connection
for additional capacity.

Page | 120
Five-Year Annual Transmission Capability Statement (2020-2024)

Appendix A: Review of Future Developments


A.1 Summary of Projects to be completed between 2020 and 2024 Peak Demands
The OETC transmission network is undergoing widespread and rapid development due to the expansion
requirements of Distribution Companies, large private customers, and new generation requirements based
on the yearly demand growth and further reinforcements on the transmission network to ensure the security,
quality, reliability and availability of the system.

There are a significant number of projects required to meet the annual peak demands over the period of this
Statement (2020-2024). These projects are considered below under the following categories:

• Projects commissioned or under construction to meet 2020 peak demand.

• Projects that are at design stage.

• Projects that are at the tender evaluation stage prior to appointment of the successful EPC
Contractor.

• Projects planned for future developments that represent the least cost options to address
problems with system growth, voltage profile, and non-compliance with the Transmission
Security Standard.

The entire programme of ongoing and future projects, which are planned for implementation over the period
2020 to 2024 are listed and described below. It should be noted that the project numbers referred in this
Appendix are identical to those in Table 1 of the Executive Summary. It should also be noted that not all of
the projects described have full authorisation at this time and they should be supported by pre investment
appraisals document to approve and to select the proper option for each project.

A.2 Projects expected to be completed to meet the 2020 peak demand

Project #1: Adding third and fourth 132/33kV transformer at Airport Heights
The Third and fourth 125 MVA transformers with 4x33kV GIS interlink will be added at Airport Heights
grid station to meet the Transmission Security Standard requirements and to cater for the high demand
growth within the area. This project was energised in September 2019.

Project #2: 400kV line connection between Sohar Free Zone – Mahadha & Sohar Free Zone – SIS
This project is intended to support the power evacuation from Sohar-III IPP based on the Transmission
Security Standard requirements and to support 400kV backbone network development. The construction of
this project consists of 33km of 400kV OHL from Sohar Free Zone to SIS, 62km of 400kV line connected
from Sohar Free Zone to Mahadha operated as 220kV, 1km Monopole from 400kV SFZ to 220kV SFZ,
0.26km of 220kV UGC each circuit at Mahadha end and 2x220kV GIS at Sohar Free Zone. This project
was completed in December 2019.

Page | 121
Five-Year Annual Transmission Capability Statement (2020-2024)

Project #3: Security of SIA 132kV


One single circuit underground cable will be installed between SPS-1 and SIA grid stations. The project
will include laying around 3.7 km 2500mm2 underground cable of 220kV and installing 1x500 MVA
transformer 220/132kV at SIA. The main purpose of this project is to secure the load at SIA during the
second circuit outage since this grid station is fed by radial 220kV double circuits. This project was
energized in March 2020.

Project #4: Birkat Al Mouz 132/33kV grid station


The objective of this project is to construct a new 132/33kV, 2x125 MVA transformers grid station to meet
the load growth in the area. It will be LILO of Izki to Nizwa 132kV OHL. This grid station will provide a
surplus capacity for load transfer from nearby grid stations like Nizwa and Madinat Nizwa. This project
was in service by March 2020.

Project #5: Construction of a new 400kV OHL from Sohar Free Zone to Shinas
New 400kV line will be constructed between Sohar Free Zone and Shinas grid stations (operated as 132kV).
The purpose of this new line is to secure existing Shinas and new Madinat Shinas grid stations as per
Transmission Security Standard requirements during the second forced outage. This project consists of
construction of 30km of 400kV OHL (Operated as 132kV) from Sohar Free Zone grid station to Shinas
grid station with 132kV circuit breakers at Sohar Free zone and Shinas grid stations. This project was in
service by March 2020.

Project #6: Sumail Industrial 132/33kV grid station


As raised by MZEC, the new industrial area has been established in Sumail and Sumail grid station itself is
suffering from load growth. Hence, new grid station will be constructed as 132/33kV, 2x125 MVA
transformers and 8x132kV GIS. This station will be supplied via 132kV double circuit OHL by LILO
around 14.6km from the line of Rusail- Sumail. This project is expected to be in service by June 2020.

A.3 Projects expected to be completed to meet the 2021 peak demand

Project #7: 400 kV OHL between New Izki to Misfah


This project will be used to evacuate the power from Sur power plant to Al Dahkhliah and Al Sharqiyah
areas. The length of the line is 100km of 400kV OHL between Misfah and New Izki 400kV grid station. In
addition, this 400kV line will support the voltage in Al Sharqiyah and Al Dakhliah area. Also, this line will
be an infrastructure for future development. This project is expected to be in service by August 2020.

Project #8: Khaborah Interconnection Station (KIS)


This project consists of 2x500 MVA transformers, 8x132kV GIS and 10x220kV GIS. The 220kV system
will be connected to 220kV OHL MIS-SIS by LILO connection and the 132kV system will be connected
to 132kV OHL Dil Abdusalam- Khabourah by LILO connection. This will support voltage profile and the
security of the supply within Al Batinah South and North regions. This project is expected to be in service
by August 2020.

Page | 122
Five-Year Annual Transmission Capability Statement (2020-2024)

Project #9: Yanqul 132/33kV grid station


This project consists of constructing a new 132/33kV, 2x125 MVA transformers grid station to meet the
load growth in the area. It will be LILO of Dank- Al Hayl 132kV OHL. This grid station will provide a
surplus capacity for load transfer from Al Hayl grid station and reduce the 33kV OHL losses. This project
is expected to be in service by December 2020.

Project #10: Khoudh 132/33kV grid station


The objective of this project is to construct a new 132/33kV, 4x125 MVA transformers grid station with
10x132kV GIS and 4x33kV GIS interlink to meet the load growth in the area. It will be LILO of Mawalleh
South to Rusail Industrial 132kV OHL. Also, this grid station will accommodate the load transfer from
Mawalleh South. This project is expected to be in service by December 2020.

Project #11: Connection of Ibri Solar-PV IPP Generation


Ibri Solar-PV IPP is considered as the first Solar project connected to OETC grid. The objective of this
project is to evacuate power coming from Ibri Solar-PV IPP. This project includes construction of 6 no.
220kV GIS at Ibri Solar IPP and 2 x 3 km 220kV OHL between Ibri Solar IPP and Ibri IPP. In addition, the
scope will include addition of 1 x 500 MVA transformer at Ibri (220/132kV) and 2 no. 220kV GIS at Ibri
IPP GS to meet load growth in the area. This project is expected to be in service by December 2020.

Project #12: Construction of 132/33kV Mirbat grid station with 2x63 MVA Transformers
The objective of this project is to construct a new 132/33kV, 2x63 MVA transformers grid station with
8x132kV GIS (6 in Mirbat & 2 in Ashoor) and 32km OHL between Mirbat and Ashoor to reinforce the
supply capacity in Ashoor Area and meet the load growth in area. This project is expected to be in service
by March 2021.

Project #13: New 132kV double circuits between Nakhal- Wadi Bani Auwf- Rustaq with a new
Wadi Bani Auwf 132/33 kV grid station
This project is including the construction of a new 86km of 132kV double circuit OHL between Nakhal
and Rustaq grid stations and a new 132/33kV grid station at Wadi Bani Auwf. This project aims to provide
additional capacity in order to relieve Rustaq grid station since the load forecast expected by Mazoon
Electricity Company that Rustaq grid will exceed the firm capacity. Also, this project will secure Rustaq
grid station since it is fed by radial 132kV double circuits and its load will be more than 100MW which fall
in Class E, according to Transmission Security Standard. Moreover, high load growth is expected between
Rustaq and Wadi Bani Auwf, so the best location for this grid station is proposed to be close to Mazoon
primary substations. This project is expected to be completed in May 2021.

Project #14: Upgrading Thumrait from 2x30 MVA to 2x63 MVA transformers
The objective of this project is to upgrade the existing Thumrait grid station from 2x30 MVA to 2x63 MVA
transformers due to high demand growth in the area. This project is expected to be in service by June 2021.

Page | 123
Five-Year Annual Transmission Capability Statement (2020-2024)

A.4 Projects expected to be completed to meet the 2022 peak demand

Project #15: Mobella Industrial 132/33kV grid station


The objective of this project is to cater for the new load to accommodate the new developments in Mobella
area. Furthermore, the load growth and the security of supply are the primary drivers behind the investment
in Mobella. As indicated by Muscat Electricity Distribution Company that Mobella witness a high load
growth and expecting the same load growth for the upcoming years. The construction of this project is
required 4x125 MVA, 10x132kV GIS and 4x33kV GIS interlink. It will be connected via LILO 132kV
from Barka Main-Mobella. It is expected to be in service by December 2021.

Project #16: Connection of Manah 1000 MW Solar-PV IPP Generation


The aim of this project is to meet the Transmission Security Standards and to cater the load growth in the
area. In addition it will be to evacuate power coming from Manah Solar-PV 1000MW IPP Generation
towards Batinah and Muscat Regions. This project consists of 10 no. 400kV GIS and will be connected via
3 km 400kV OHL LILO New Izki – Ibri. It is expected to be completed in June 2022.

A.5 Projects expected to be completed to meet the 2023 peak demand

Project #17: 400/132 KV Nahadah Grid Station


The aim of this project is to meet load growth in the area, to meet Transmission Security Standard and
future planned connection with PDO power network. This project is consisting of 2x500 MVA transformer
at Nahada (400/132kV), 12x400kV GIS, 8x132kV GIS and 1km of 400kV OHL – LILO of Ibri-Manah
Solar IPP. It is expected to be completed in September 2022.

Project #18: Construction of new 132/33 kV Grid Station at Saih Al Khairat, along with associated
OHL from Thumrait to Saih Al Khairat
The objective of this project is to meet the Transmission Security Standard, to cater for the load growth in
the area and to supply RAEC load instead of using diesel generators. The project consists of 2x125 MVA
transformers (132/33kV), 6x132kV GIS in Saih Al Khairat, 2x132kV AIS at Thumrait and 88km of OHL
from Thumrait to Saih Al Khairat. The grid station is expected to be energized in December 2022.

Project #19: Installation of Third 500 MVA Transformer at Airport Heights and New 132kV UGC
circuit between Airport Heights and Ghala grid stations
The objective of this project is to maintain Transmission Security Standard and meet load growth in the
area. The project consists of 500 MVA transformer (220/132 kV) at Airport Heights, 4x220kV GIS and
4x132kV GIS. This project is expected to be completed by March 2023.

Page | 124
Five-Year Annual Transmission Capability Statement (2020-2024)

Project #20: Construction of new Al Jefnen 400/132kV grid station with associated OHL and
addition of 2x500 MVA 220/132kV transformers at Misfah grid station
The objective of this project is to secure the demand group at Rusail area considering the future planned
retirements of Rusail IPP. The project will consist of new 3x500 MVA 400/132kV transformers and
upgrading the existing 132kV OHL between Misfah and Rusail Industrial from 132kV to 400kV and 4x1km
132kV UGC between New Rusail-Rusail Industrial. This project is expected to be in service by March
2023.In addition, the scope will include adding 2x500MVA 220/132kV Transformers at Misfah grid station
(which is expected to be ready by June 2022).

Project #21: Mahout 400/33kV grid station


This project is to construct a new 2x125 MVA transformers grid station with 6x400kV GIS bays. The aim
of this project is to meet transmission security standard and meet the load growth in Mahout area. This
project is expected to be in service by June 2023.

Project #22: Duqm 400/132/33kV grid station


This project is to install a new 4x125 MVA transformers grid station with 10x400kV GIS bays and 8x132kV
GIS bays. The aim of this project is to meet transmission security standard and meet the load growth in
Duqm area. This project is expected to be energized by June 2023.

Project #23: North South Interconnector (Phase-1 MIS-Duqm)


North and south interconnection project is considered as one of the biggest projects in the coming 5 years.
The objective of the project is to fulfil the Transmission Security Standard and to meet the load growth in
the area. Phase-1 of the project consists of 2x500MVA transformers in Suwaihat, 2x500 MVA transformers
in Duqm with associated 400kV OHL works to link them. In addition, shunt reactors and series capacitors
will be used in DC OHL lines. The proposed project expected to be energized in June 2023.

A.6 Projects expected to be completed to meet the 2024 peak demand

Project #24: New Rustaq 400/132kV grid station


This project consists of 3x500 MVA transformers, 9x400kV GIS and 13x132kV GIS at New Rustaq grid
station. In addition of that, 159.8 km of 400kV OHL from New Rustaq to Ibri IPP and 85.2 km of 400kV
OHL between New Rustaq and Al Jefnen. The purpose of this project is to meet Transmission Security
Standard and to overcome loading issues in Al Batinah area.

Project #25: Securing Bureimi area


The purpose of this project is to maintain the Transmission Security Standard and to meet the load growth
in Bureimi area. Furthermore, it is required to increase the system reliability within Al Bureimi area. This
project consists of 32.9km of 132kV OHL and 5.5km 132kV UGC between Mahadha-Bureimi Industrial
and 2x132kV GIS at Bureimi Industrial grid station. The project is expected to be completed in June 2024.

Page | 125
Five-Year Annual Transmission Capability Statement (2020-2024)

Project #26: Connection of WTE IPP


WTE IPP in Barka is considered as the first Waste to Energy project that will be connected to OETC grid.
The objective of this project is to evacuate power coming from WTE IPP. This project includes the
construction of 5 no. 132kV GIS at WTE IPP, 2 no. of 132kV GIS at existing Madinat Barka grid station
and 3.6 km 132kV OHL to connect WTE IPP with Madinat Barka grid station. This project is expected to
be in service by June 2024.

Project #27: Al Jawabi 132/33kV grid station


The objective of this project is to construct a new 132/33kV grid station, 2x125 MVA transformers, 6 no.
132kV GIS at Al Jawabi grid station, 2 no. 132kV AIS at JBB Ali grid station and 14km of 132kV OHL
between JBB Ali and Al Jawabi grid stations to meet the Transmission Security Standard requirements and
to cater for the high demand growth within the area as per MZEC load forecast. This project is expected to
be in service by June 2024.

Project #28: Nizwa 220/132kV grid station


This project consists of 2x500MVA transformers, 6x220kV GIS and 2 no. 132kV AIS at Nizwa grid station.
In addition, 1x500 MVA, 400/220kV transformer and 2x220kV GIS at the existing New Izki grid station.
The grid station will be connected via 220kV line from New Izki including 53.9km OHL, 1.1km UGC from
Nizwa side and 3.6km UGC from New Izki side. The objective of this project is to increase the system
reliability within Al Dhakilyah region. This project is expected to be ready by June 2024.

Project #29: Duqm Wind Farm connection


The total capacity for the wind farm will be around 200MW and it will be connected via 49.7 km 132kV
OHL to Duqm 400/132kV grid station. The project will have 6 no. 132kV GIS at Duqm wind farm and 2
no. 132kV GIS at Duqm grid station. The project is expected to be completed by June 2024.

Project #30: JBB Ali Wind Farm connection


The total capacity for the wind farm will be around 100MW and it will be connected via 9 km 132kV OHL
from Al Jawabi 132/33kV grid station. The project will have 6 no. 132kV GIS at JBB Ali wind farm and 2
no. 132kV GIS at Al Jawabi grid station. The project is expected to be completed by June 2024.

Page | 126
Five-Year Annual Transmission Capability Statement (2020-2024)

Appendix B: Transmission System Data


B.1 Substations Loads and Capacitor data
The grid station real and reactive power loads at system peak demand for the period from 2020 to 2024 and
the respective reactive power support from capacitor banks connected at the grid station 33kV busbars is
shown in Table B.1.10 This data was used in the power flow studies of system peak demand presented in
Section 8 of this Capability Statement.

B.2 Overhead Line Circuit Capacities and Parameters


The continuous thermal rating of a circuit is the maximum power flow that can be carried by that circuit on
a continuous basis. The thermal rating of an overhead line is the power flow that can be carried by that line
without infringing the statutory clearances and causing a risk to public safety and to the line itself. The
thermal rating of an underground cable, however, is the maximum power flow that the cable can carry
without either causing the cable to fail or effectively reducing its projected lifespan through a deterioration
of the cable insulation.

Although the thermal rating of an overhead line is affected by climatic conditions, for the purpose of
assessing spare capacity on the transmission system, the key climatic condition that limits the circuit rating
is the summer rating when the temperature is at its highest level and the solar radiation is at its peak. This
also corresponds to when the electricity demand is at or near to its peak.

The circuit data presented in Table B.2 for the first year of the Statement period (2020) comprises the
voltage, resistance, reactance, susceptance and thermal rating of the line and cable circuits. It also shows
the circuit length and the type of overhead conductor or underground cable for each circuit.

Table B.3 shows the changes to the circuit data required in each of the other four years covered by the
Statement.

B.3 Transformer data


The data used to model the grid supply point transformers in the power flow studies of the 2020 summer
peak demand condition is shown in Table B.4. The data comprises the transformer voltage ratio, the
resistance and reactance, the tap range and step size. Table B.5 lists changes to the transformer data for the
remaining four year of the Statement.

10
T he 33kV busbars at the grid supply points and the capacitors connected to them are owned and operated by the Distr ibution Companies.

Page | 127
Five-Year Annual Transmission Capability Statement (2020-2024)

Table B. 1: Load and Capacitor Data for Grid Station (2020-2024)


2020 2021 2022 2023 2024

G rid Stations P
P Load Q Load Caps Q Load Caps P Load Q Load Caps P Load Q Load Caps P Load Q Load Caps
Load
(MW) (MVAr) (MVAr) (MVAr) (MVAr) (MW) (MVAr) (MVAr) (MW) (MVAr) (MVAr) (MW) (MVAr) (MVAr)
(MW)

MUSCAT AREA

TX-1 & TX-2 82.7 27.2 40 86.0 28.3 40 89.5 29.4 40 93.1 30.6 40 96.8 31.8 40
Airport Heights
TX-3 & TX-4 33.0 10.8 40 35.4 11.6 40 44.3 14.6 40 46.4 15.3 40 48.6 16.0 40

Al Falaj 78.5 25.8 40 84.5 27.8 40 84.5 27.8 40 84.5 27.8 40 84.5 27.8 40

TX-1 & TX-2 95.8 31.5 40 96.5 31.7 40 104.2 34.3 40 112.6 37.0 40 106.6 35.0 40
Amerat
TX-3 & TX-4 51.1 16.8 40 63.2 20.8 40 69.6 22.9 40 76.5 25.1 40 99.2 32.6 40

TX-1 & TX-2 124.5 40.9 40 121.3 39.9 40 84.8 27.9 40 89.8 29.5 40 95.2 31.3 40
A'salam
TX-3 & TX-4 48.0 15.8 40 89.3 29.4 40 97.4 32.0 40 105.1 34.6 40 93.6 30.8 40

TX-1 & TX-2 75.9 25.0 40 99.0 32.5 40 102.9 33.8 40 107.0 35.2 40 111.3 36.6 40
Bousher
TX-3 & TX-4 124.6 40.9 40 104.5 34.4 40 108.7 35.7 40 113.1 37.2 40 107.6 35.4 40

Daghmar 32.0 10.5 18 32.0 10.5 18 32.0 10.5 18 32.0 10.5 18 32.0 10.5 18

TX-1 & TX-2 73.4 24.1 40 94.7 31.1 40 96.1 31.6 40 104.6 34.4 40 106.1 34.9 40
Ghala
TX-3 & TX-4 50.0 16.4 40 51.5 16.9 40 53.0 17.4 40 54.6 18.0 40 56.3 18.5 40

TX-1 & TX-2 67.0 22.0 40 69.7 22.9 40 71.8 23.6 40 73.9 24.3 40 86.1 28.3 40
Ghala Heights
TX-3 & TX-4 55.0 18.1 40 67.2 22.1 40 68.9 22.7 40 80.7 26.5 40 82.5 27.1 40

Ghubrah TX-1 & TX-2 103.9 34.1 - 107.0 35.2 - 110.2 36.2 - 112.4 36.9 - 114.7 37.7 -

TX-1 & TX-2 - - - - - - 60.0 19.7 40 64.2 21.1 40.0 68.1 22.4 40
Mobella
Industrial
TX-3 & TX-4 - - - - - - 60.0 19.7 40 64.2 21.1 40.0 88.1 28.9 40

Jahloot 42.0 13.8 40 44.1 14.5 40.0 46.3 15.2 40 48.6 16.0 40.0 51.0 16.8 40

TX-1 & TX-2 - - - 30.0 9.9 40.0 31.5 10.4 40 33.1 10.9 40.0 49.7 16.3 40
Khoudh
TX-3 & TX-4 - - - 60.0 19.7 40.0 63.0 20.7 40 66.2 21.7 40.0 69.5 22.8 40

Mawalleh North 2x125 MVA 81.5 26.8 40 86.8 28.5 40 103.4 34.0 40 112.0 36.8 40 101.6 33.4 40

Page | 128
Five-Year Annual Transmission Capability Statement (2020-2024)

Table B. 1: (Continued) Load and Capacitor Data for Grid Station (2020-2024)
2020 2021 2022 2023 2024

G rid Stations P
P Load Q Load Caps Q Load Caps P Load Q Load Caps P Load Q Load Caps P Load Q Load Caps
Load
(MW) (MVAr) (MVAr) (MVAr) (MVAr) (MW) (MVAr) (MVAr) (MW) (MVAr) (MVAr) (MW) (MVAr) (MVAr)
(MW)

TX-1 & TX-2 98.1 32.2 40 92.0 30.2 40 95.7 31.4 40 99.5 32.7 40 103.5 34.0 40
Mawalleh South
TX-3 & TX-4 112.0 36.8 40 71.5 23.5 40 74.4 24.4 40 77.3 25.4 40 80.4 26.4 40

Misfah 67.3 22.1 - 70.7 23.2 - 74.2 24.4 - 77.9 25.6 - 81.8 26.9 -

Mobella 122.1 40.1 40 122.7 40.3 40 70.0 23.0 40 74.2 24.4 40 78.7 25.9 40

TX-1 & TX-2 79.2 26.0 40 87.1 28.6 40 90.2 29.6 40 91.8 30.2 40 93.4 30.7 40
MSQ
TX-3 & TX-4 76.4 25.1 40 84.5 27.8 40 87.9 28.9 40 89.6 29.5 40 91.4 30.1 40

Muttrah 71.2 23.4 - 71.2 23.4 - 71.2 23.4 - 71.2 23.4 - 71.2 23.4 -

Qurum 93.2 30.6 40 95.1 31.3 40 97.0 31.9 40 98.9 32.5 40 100.9 33.2 40

Quryiat 51.9 17.1 40 53.5 17.6 40 55.1 18.1 40 56.7 18.6 40 58.4 19.2 40

TX-1 & TX-2 54.1 17.8 - 58.4 19.2 - 61.9 20.4 - 65.7 21.6 - 69.6 22.9 -
Rusail Industrial
TX-3 & TX-4 88.3 29.0 - 95.4 31.4 - 101.1 33.2 - 107.2 35.2 - 113.6 37.4 -

TX-1 & TX-2 128.9 42.4 - 100.4 33.0 - 104.4 34.3 - 108.6 35.7 - 112.9 37.1 -
Seeb Main
TX-3 & TX-4 85.1 28.0 - 89.3 29.4 - 92.9 30.5 - 96.6 31.8 - 100.5 33.0 -

Wadi Adai 81.3 26.7 40 82.9 27.3 40 84.6 27.8 40 86.3 28.4 40 88.0 28.9 40

Tx-1 & Tx-2 69.1 22.7 40 69.1 22.7 40 69.1 22.7 40 69.1 22.7 40 69.1 22.7 40
Wadi Kabir
Tx-3 & Tx-4 59.6 19.6 40 59.6 19.6 40 59.6 19.6 40 59.6 19.6 40 59.6 19.6 40

Yitti 17.2 5.7 - 17.6 5.8 - 17.9 5.9 - 18.3 6.0 - 18.7 6.1 -

Total Muscat 33kV Load 2574.1 846.1 1018 2743.7 901.8 1098 2889.3 949.7 1178 3023.2 993.7 1178 3140.7 1032.3 1178

Muscat Airport 30.4 10.0 - 30.4 10.0 - 30.4 10.0 - 30.4 10.0 - 30.4 10.0 -

Muscat Steel 0.0 0.0 - 0.0 0.0 - 0.0 0.0 - 0.0 0.0 - 0.0 0.0 -

Modran Steel 0.0 0.0 - 0.0 0.0 - 0.0 0.0 - 0.0 0.0 - 0.0 0.0 -

R.O Ghoubrah 22.0 7.2 - 22.0 7.2 - 22.0 7.2 - 22.0 7.2 - 22.0 7.2 -

Total Muscat 2626.5 863.3 1018 2796.1 919.0 1098 2941.7 966.9 1178 3075.6 1010.9 1178 3193.1 1049.5 1178

Page | 129
Five-Year Annual Transmission Capability Statement (2020-2024)

Table B. 1: (Continued) Load and Capacitor Data for Grid Station (2020-2024)
2020 2021 2022 2023 2024

G rid Stations P
P Load Q Load Caps Q Load Caps P Load Q Load Caps P Load Q Load Caps P Load Q Load Caps
Load
(MW) (MVAr) (MVAr) (MVAr) (MVAr) (MW) (MVAr) (MVAr) (MW) (MVAr) (MVAr) (MW) (MVAr) (MVAr)
(MW)

MAZOON AREA

Adam 2X125MVA 52.5 17.3 48 55.1 18.1 48 57.9 19.0 48 60.8 20.0 48 62.6 20.6 48

Al Jawabi - - - - - - - - - - - - 80.0 26.3 40

Ayjah 72.7 23.9 20 74.9 24.6 20 89.3 29.4 20 91.6 30.1 20 94.0 30.9 20

Bahla 74.9 24.6 - 78.6 25.8 - 82.5 27.1 - 86.7 28.5 - 90.1 29.6 -

TX-1 & TX-2 56.2 18.5 40 59.0 19.4 40 62.0 20.4 40 65.1 21.4 40 67.0 22.0 40
Barka Main
Tx-3 28.6 9.4 - 12.4 4.1 - 0.0 0.0 - 0.0 0.0 - 0.0 0.0 -

Bedyah 49.8 16.4 40 51.8 17.0 40 53.9 17.7 40 56.0 18.4 40 58.3 19.1 40

Birkat Al Mouz 50.8 16.7 40 53.8 17.7 40 57.1 18.8 40 60.5 19.9 40 64.1 21.1 40

Blue City 124.3 40.8 48 128.0 42.1 48 140.8 46.3 48 144.8 47.6 48 148.9 48.9 48

Hay Asim 53.2 17.5 40 66.6 21.9 40 83.2 27.4 40 84.9 27.9 40 86.7 28.5 40

Ibra 79.9 26.3 40 83.0 27.3 40 86.2 28.3 40 89.5 29.4 40 92.1 30.3 40

Izki 2X125MVA 81.2 26.7 40 87.5 28.7 40 90.0 29.6 40 91.7 30.1 40 93.5 30.7 40

JBB Ali TX-1 & TX-2 120.0 39.4 48 146.8 48.3 48 151.8 49.9 48 157.0 51.6 48 82.4 27.1 48

JBB Hassan 73.2 24.1 40 83.1 27.3 40 86.2 28.3 40 89.4 29.4 40 92.7 30.5 40

Jebreen 64.0 21.0 40 66.5 21.9 40 69.2 22.7 40 71.9 23.6 40 74.1 24.4 40

TX-1 & TX-2 111.1 36.5 40 85.5 28.1 40 88.9 29.2 40 92.5 30.4 40 95.3 31.3 40
Khadhra
TX-3 & TX-4 34.3 11.3 40 65.7 21.6 40 68.3 22.5 40 71.1 23.4 40 73.2 24.1 40

TX-1 & TX-2 111.7 36.7 40 92.2 30.3 40 100.9 33.2 40 103.8 34.1 40 106.7 35.1 40
Madinat Barka
TX-3 & TX-4 25.0 8.2 40 50.0 16.4 40 52.0 17.1 40 54.1 17.8 40 55.7 18.3 40

Madinat Nizwa 63.2 20.8 40 65.8 21.6 40 68.4 22.5 40 71.1 23.4 40 73.3 24.1 40

MIS 45.3 14.9 - 47.2 15.5 - 48.6 16.0 - 50.0 16.4 - 51.5 16.9 -

Mudhaibi 2X125MVA 47.0 15.5 40 48.9 16.1 40 55.7 18.3 40 57.7 19.0 40 59.3 19.5 40

Page | 130
Five-Year Annual Transmission Capability Statement (2020-2024)

Table B. 1: (Continued) Load and Capacitor Data for Grid Station (2020-2024)
2020 2021 2022 2023 2024

G rid Stations P
P Load Q Load Caps Q Load Caps P Load Q Load Caps P Load Q Load Caps P Load Q Load Caps
Load
(MW) (MVAr) (MVAr) (MVAr) (MVAr) (MW) (MVAr) (MVAr) (MW) (MVAr) (MVAr) (MW) (MVAr) (MVAr)
(MW)

Mudhairib 56.5 18.6 40 64.7 21.3 40 67.1 22.1 40 69.5 22.9 40 71.4 23.5 40

TX-1 & TX-2 104.7 34.4 40 85.9 28.2 40 100.2 32.9 40 103.7 34.1 40 106.5 35.0 40
Muladah
TX-3 & TX-4 22.7 7.5 40 46.6 15.3 40 48.4 15.9 40 50.4 16.6 40 51.9 17.1 40

Nakhal 76.5 25.2 40 85.6 28.1 40 88.0 28.9 40 90.5 29.7 40 93.0 30.6 40

New Izki 20.6 6.8 40 21.4 7.0 40 22.3 7.3 40 23.2 7.6 40 23.9 7.8 40

Nizwa 85.1 28.0 40 96.6 31.8 40 109.3 35.9 40 112.0 36.8 40 114.8 37.7 40

Rustaq 3X125MVA 159.4 52.4 40 116.8 38.4 40 121.5 39.9 40 126.3 41.5 40 130.1 42.8 40

Samad 25.0 8.2 40 25.8 8.5 40 26.5 8.7 40 27.3 9.0 40 28.1 9.2 40

Sinaw 35.0 11.5 40 36.8 12.1 40 38.2 12.6 40 39.7 13.1 40 40.9 13.5 40

2X63MVA 52.4 17.2 40 54.0 17.7 40 55.1 18.1 40 56.2 18.5 40 57.3 18.8 40
Sumail
2X125MVA 108.9 35.8 40 59.6 19.6 40 62.0 20.4 40 63.9 21.0 40 65.8 21.6 40

Sumail Industrial Area - - - 53.6 17.6 40 55.2 18.1 40 56.9 18.7 40 58.6 19.3 40

Sur TX-1 & TX-2 94.0 30.9 48 96.8 31.8 48 99.6 32.7 48 102.4 33.7 48 105.4 34.6 48

Suwaiq 61.2 20.1 40 67.9 22.3 40 77.6 25.5 40 80.3 26.4 40 82.4 27.1 40

Wadi Bani Auwf 0.0 0.0 - 49.0 16.1 40 51.0 16.7 40 53.0 17.4 40 54.6 17.9 40

Total Mazoon 33kV Load 2321.0 762.9 1252 2463.5 809.7 1332 2614.8 859.4 1332 2705.4 889.2 1332 2786.0 915.7 1372

Total Mazoon 2321.0 762.9 1252 2463.5 809.7 1332 2614.8 859.4 1332 2705.4 889.2 1332 2786.0 915.7 1372

Page | 131
Five-Year Annual Transmission Capability Statement (2020-2024)

Table B. 1: (Continued) Load and Capacitor Data for Grid Station (2020-2024)
2020 2021 2022 2023 2024

G rid Stations P
P Load Q Load Caps Q Load Caps P Load Q Load Caps P Load Q Load Caps P Load Q Load Caps
Load
(MW) (MVAr) (MVAr) (MVAr) (MVAr) (MW) (MVAr) (MVAr) (MW) (MVAr) (MVAr) (MW) (MVAr) (MVAr)
(MW)

MAJAN AREA

Al Hayl 40.5 13.3 10 7.6 2.5 10 7.7 2.5 10 7.8 2.6 10 8.0 2.6 10

Bureimi 48.4 15.9 40 51.3 16.8 40 53.3 17.5 40 55.5 18.2 40 56.9 18.7 40

TX-1 & TX-2 40.2 13.2 40 41.0 13.5 40 42.0 13.8 40 43.1 14.2 40 44.6 14.7 40
Buriami Industrial
TX-3 & TX-4 50.4 16.6 - 59.6 19.6 40 61.2 20.1 40 62.9 20.7 40 66.4 21.8 40

Dank 38.1 12.5 10 42.6 14.0 10 47.7 15.7 10 51.3 16.9 10 52.2 17.1 10

Dil Abdusalam 73.3 24.1 40 78.3 25.7 40 80.6 26.5 40 82.3 27.1 40 87.2 28.7 40

Dreez 79.3 26.1 40 81.5 26.8 40 83.7 27.5 40 88.2 29.0 40 90.7 29.8 40

2X63MVA 38.9 12.8 10 40.1 13.2 10 41.3 13.6 10 40.6 13.3 10 41.9 13.8 10
Ibri
2X125MVA 78.2 25.7 40 80.2 26.4 40 82.2 27.0 40 84.3 27.7 40 86.8 28.5 40

Khaborah 88.0 28.9 40 91.2 30.0 40 95.4 31.4 40 99.7 32.8 40 104.3 34.3 40

TX-1 & TX-2 56.1 18.5 40 59.8 19.6 40 56.7 18.7 40 59.9 19.7 40 63.0 20.7 40
Liwa
TX-3 & TX-4 67.2 22.1 40 73.0 24.0 40 76.4 25.1 40 79.8 26.2 40 82.1 27.0 40

Madinat Shinas 64.5 21.2 40 73.7 24.2 40 78.9 25.9 40 82.9 27.3 40 86.6 28.5 40

Mahadah 24.1 7.9 10 17.2 5.7 10 17.4 5.7 10 17.8 5.9 10 18.0 5.9 10

Saham 86.2 28.3 40 87.4 28.7 40 90.0 29.6 40 90.2 29.6 40 95.1 31.3 40

Shinas TX-1 & TX-2 64.8 21.3 40 67.3 22.1 40 79.6 26.2 40 84.3 27.7 40 91.7 30.1 40

SIA 76.8 25.2 - 84.4 27.8 - 84.9 27.9 - 85.4 28.1 - 86.1 28.3 -

TX-1 & TX-2 55.7 18.3 40 58.6 19.3 40 68.2 22.4 40 90.0 29.6 40 94.4 31.0 40
Sohar
TX-3 & TX-4 108.7 35.7 40 112.9 37.1 40 112.8 37.1 40 97.5 32.1 40 100.7 33.1 40

TX-1 & TX-2 36.6 12.0 40 41.0 13.5 40 44.9 14.7 40 41.2 13.5 40 42.2 13.9 40
Sohar Free Zone
TX-3 & TX-4 49.1 16.1 - 50.4 16.6 40 51.4 16.9 40 52.6 17.3 40 54.3 17.8 40

Page | 132
Five-Year Annual Transmission Capability Statement (2020-2024)

Table B. 1: (Continued) Load and Capacitor Data for Grid Station (2020-2024)
2020 2021 2022 2023 2024

G rid Stations P
P Load Q Load Caps Q Load Caps P Load Q Load Caps P Load Q Load Caps P Load Q Load Caps
Load
(MW) (MVAr) (MVAr) (MVAr) (MVAr) (MW) (MVAr) (MVAr) (MW) (MVAr) (MVAr) (MW) (MVAr) (MVAr)
(MW)

TX-1 & TX-2 52.2 17.2 40 53.8 17.7 40 55.5 18.2 40 58.2 19.1 40 60.0 19.7 40
Uwaynat
TX-3 & TX-4 60.8 20.0 40 62.9 20.7 40 64.7 21.3 40 68.7 22.6 40 71.1 23.4 40

Wadi Sa'a 14.1 4.6 - 16.5 5.4 - 18.1 6.0 - 20.4 6.7 - 22.6 7.4 -

Yanqul 0.0 0.0 - 33.5 11.0 40 34.4 11.3 40.0 35.4 11.6 40.0 36.7 12.1 40

Total Majan 33kV Load 1392.1 457.6 680 1465.7 481.7 800 1529.0 502.6 800 1580.0 519.3 800 1643.9 540.3 800

Aromatics connected to 132kV (SIA) 0.0 0.0 - 0.0 0.0 - 0.0 0.0 - 0.0 0.0 - 0.0 0.0 -

Sohar Refinery 0.0 0.0 - 0.0 0.0 - 0.0 0.0 - 0.0 0.0 - 0.0 0.0 -

Sohar Steel (SSSRM) connected to 132kV


0.0 0.0 - 0.0 0.0 - 0.0 0.0 - 0.0 0.0 - 0.0 0.0 -
(SIA)

Jindal Shadeed connected to 220 (SIA) 60.0 19.7 - 60.0 19.7 - 100.0 32.9 - 100.0 32.9 - 100.0 32.9 -

VALE connected to 132kV (SIA) 85.0 27.9 - 85.0 27.9 - 85.0 27.9 - 85.0 27.9 - 85.0 27.9 -

Oman Alum. Rolling Co.LLC (ARMS)


4.2 1.4 - 4.2 1.4 - 4.2 1.4 - 4.2 1.4 - 4.2 1.4 -
connected to Liwa 132kV

OMP ET Connected ti SIA 132kV 0.0 0.0 - 4.0 1.3 - 4.0 1.3 - 4.0 1.3 - 4.0 1.3 -

Orpic (Liwa P lastic) 220kV SP S-2 25.0 8.2 - 25.0 8.2 - 25.0 8.2 - 25.0 8.2 - 25.0 8.2 -

Moon Iron & Steel Co connected to 220KV


15.0 4.9 - 15.0 4.9 - 15.0 4.9 - 15.0 4.9 - 15.0 4.9 -
SFZ

Sohar Aluminum 0.0 0.0 - 0.0 0.0 - 0.0 0.0 - 0.0 0.0 - 0.0 0.0 -

Al Tamam INDSIL 8.0 2.6 - 8.0 2.6 - 8.0 2.6 - 8.0 2.6 - 8.0 2.6 -

Total Majan 1589.3 522.4 680.0 1666.9 547.9 800.0 1770.2 581.8 800.0 1821.2 598.6 800.0 1885.1 619.6 800.0

Page | 133
Five-Year Annual Transmission Capability Statement (2020-2024)

Table B. 1: (Continued) Load and Capacitor Data for Grid Station (2020-2024)
2020 2021 2022 2023 2024

G rid Stations P
P Load Q Load Caps Q Load Caps P Load Q Load Caps P Load Q Load Caps P Load Q Load Caps
Load
(MW) (MVAr) (MVAr) (MVAr) (MVAr) (MW) (MVAr) (MVAr) (MW) (MVAr) (MVAr) (MW) (MVAr) (MVAr)
(MW)

DPC AREA

Al Qarm 34.4 11.3 - 33.2 10.9 - 36.0 11.8 - 27.7 9.1 - 28.5 9.4 -

Ashoor 68.7 22.6 - 55.8 18.3 - 56.7 18.7 - 56.7 18.6 - 57.7 19.0 -

Ittin 78.4 25.8 40 71.8 23.6 40 74.8 24.6 40 83.5 27.5 40 87.1 28.6 40

Mirbat 0.0 0.0 40 20.9 6.9 40 24.9 8.2 40 26.9 8.8 40 29.1 9.5 40

NP S 39.7 13.0 - 38.8 12.8 - 41.9 13.8 - 43.1 14.2 - 44.7 14.7 -

TX-1 & TX-2 65.0 21.4 40 80.6 26.5 40 88.5 29.1 40 101.9 33.5 40 105.5 34.7 40
S'aadah
TX-3 & TX-4 44.3 14.6 40 66.5 21.8 40 87.2 28.7 40 102.3 33.6 40 105.9 34.8 40

Raysut 101.7 33.4 40 111.5 36.7 40 109.0 35.8 40 108.3 35.6 40 108.5 35.7 40

Salalah-IP P 39.7 13.1 40 69.0 22.7 40 101.1 33.2 40 107.5 35.3 40 112.0 36.8 40

Shaha'aon 95.3 31.3 40 99.4 32.7 40 98.3 32.3 40 81.9 26.9 40 85.0 27.9 40

2x30 MVA 24.2 7.9 6 - - - - - - - - - - - -


Thumrait
2x63 MVA - - - 28.8 9.4 6 32.6 10.7 6 33.6 11.0 6 34.6 11.4 6

Total Dhof ar 33kV Load 591.2 194.3 286.0 676.3 222.3 286.0 751.1 246.9 286.0 773.4 254.2 286.0 798.5 262.5 286.0

Salalah Airport 7.0 2.3 - 8.0 2.6 - 8.0 2.6 - 8.0 2.6 - 8.0 2.6 -

Salalah Methanol Company 0.0 0.0 - 35.0 11.5 - 35.0 11.5 - 35.0 11.5 - 35.0 11.5 -

Total DPC 598.2 196.6 286.0 719.3 236.4 286.0 794.1 261.0 286.0 816.4 268.3 286.0 841.5 276.6 286.0

Page | 134
Five-Year Annual Transmission Capability Statement (2020-2024)

Table B. 1: (Continued) Load and Capacitor Data for Grid Station (2020-2024)
2020 2021 2022 2023 2024

G rid Stations P
P Load Q Load Caps Q Load Caps P Load Q Load Caps P Load Q Load Caps P Load Q Load Caps
Load
(MW) (MVAr) (MVAr) (MVAr) (MVAr) (MW) (MVAr) (MVAr) (MW) (MVAr) (MVAr) (MW) (MVAr) (MVAr)
(MW)

RAEC AREA

TX-1 & TX-2 0.0 0.0 - 0.0 0.0 - 0.0 0.0 - 60.8 20.0 40 61.8 20.3 40
Duqm
TX-3 & TX-4 0.0 0.0 - 0.0 0.0 - 0.0 0.0 - 53.4 17.5 40 54.3 17.9 40

Mahout 0.0 0.0 - 0.0 0.0 - 0.0 0.0 - 23.9 7.8 40 24.9 8.2 40

Saih Al Khairat 0.0 0.0 - 0.0 0.0 - 0.0 0.0 - 44.2 14.5 40 45.8 15.1 40

Total RAEC 33kV Load 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 182.2 59.9 160.0 186.8 61.4 160.0

Page | 135
Five-Year Annual Transmission Capability Statement (2020-2024)

Table B. 2: 2020 Branch Data Listing

From To Voltage No. Conductor Length R X B Rating Conductor Length Rating


R[Ω/km] X[Ω/km] B [MS/km]
Substation Substation (kV) Circuits Type (OHL) (Km) [Ω/km] [Ω/km] [MS/km] (MVA) Type (Cable) (Km) (MVA)

MIS
Sur P S Jahloot 400 2 Quad YEW 119.6 0.0211 0.2578 5.18 1774 − − − − − −
Ibri IP P New Izki 400 2 Quad YEW 264.4 0.0210914 0.2577821 5.18 1774 − − − − − −
Sohar IP P -3 Sohar Free Zone 400 2 − − − − − − 2500mm2 XLP E cable 10.2 0.01074 0.321 91.10619 2273
Sohar Free Zone
2500mm2 XLP E cable 3.524 0.01074 0.321 91.10619 2273
Sohar IP P -3 (P ortion 1) 400 2 Quad YEW 5.5 0.0210914 0.2577821 5.184822 1774
Sohar Free Zone
2500mm2 XLP E cable 0.9 0.01074 0.321 91.10619 2273
(P ortion 2)
Sohar Free Zone SIS 400 2 Quad YEW 33.3 0.0210914 0.2577821 5.18 1774 − − − − − −
Sur P S Qabel 400 2 Quad YEW 116.5 0.0210914 0.2577821 5.184822 1774 − − − − − −
Qabel New Izki 400 2 Quad YEW 106.2 0.0210914 0.2577821 5.184822 1774 − − − − − −
Sohar IP P -2 Sohar Free Zone 220 2 ARCURIA x 2 6.0 0.0258 0.321 3.82 673 2500mm2 XLP E cable 3.5 0.01074 0.321 91.11 625
Sohar Free Zone SIS 220 2 ARCURIA x 2 33.9 0.0258 0.321 3.82 673 2500mm2 XLP E cable 0.5 0.01074 0.321 91.11 625
SIA Sohar-1 P S 220 3 − − − − − − 2500mm2 XLP E cable 3.7 0.01074 0.321 91.11 625
Mahadha Al Oha (UAE) 220 2 ARCURIA x 2 51.4 0.0258 0.321 3.82 673 − − − − − −
Barka P ower station Filaj 220 2 ARCURIA x 2 10.0 0.0258 0.321 3.82 673 − − − − − −
Barka P ower station Filaj 220 2 ARCURIA x 2 9.2 0.0258 0.321 3.82 673 2500mm2 XLP E cable 0.8 0.01074 0.321 91.11 625
Filaj Mobella 220 2 ARCURIA x 2 9.8 0.0258 0.321 3.82 673 − − − − − −
Mobella Airport Heights 220 2 ARCURIA x 2 25.3 0.0258 0.321 3.82 673 − − − − − −
Airport Heights Misfah 220 2 ARCURIA x 2 15.5 0.0258 0.321 3.82 673 − − − − − −
Misfah MSQ 220 2 ARCURIA x 2 26.1 0.0258 0.321 3.82 673 − − − − − −
Misfah Jahloot 220 2 ARCURIA x 2 76.0 0.0258 0.321 3.82 673 − − − − − −
MIS SIS 220 2 ARCURIA x 2 107.2 0.0258 0.321 3.82 673 − − − − − −
SP S SIS 220 2 ARCURIA x 2 37.4 0.0258 0.321 3.82 673 2500mm2 XLP E cable 2.9 0.01074 0.312 91.11 625
Mahadha SIS 220 2 ARCURIA x 2 66.5 0.0258 0.321 3.82 673 − − − − − −
Blue City MIS 220 2 ARCURIA x 2 45.6 0.0258 0.321 3.82 673 2500mm2 XLP E cable 5.8 0.01074 0.321 91.11 475
Filaj Blue City 220 2 ARCURIA x 2 33.2 0.0258 0.321 3.82 673 2500mm2 XLP E cable 5.8 0.01074 0.312 91.11 475
Ibri Ibri IP P 220 2 ARCURIA x 2 32.1 0.0258 0.321 3.82 673 − − − − − −
Ibri IP P Mahadha 220 2 ARCURIA x 2 123.2 0.0258 0.321 3.82 673 − − − − − −

Page | 136
Five-Year Annual Transmission Capability Statement (2020-2024)

Table B. 2: (Continued) 2020 Branch Data Listing

From To Voltage No. Conductor Length R X B Rating Conductor Length Rating


R[Ω/km] X[Ω/km] B [MS/km]
Substation Substation (kV) Circuits Type (OHL) (Km) [Ω/km] [Ω/km] [MS/km] (MVA) Type (Cable) (Km) (MVA)

MIS
Barka IP P -3 Misfah 220 2 ARCURIA x 2 54.9 0.0258 0.321 3.82 673 2500mm2 XLP E cable 10.5 0.01074 0.321 91.11 625

Sur 3 P S Sur 2 GS 220 2 ARCURIA x 2 12.6 0.0258 0.321 3.82 673 − − − − − −


Jahloot Al Hamriyah 220 2 ARCURIA x 2 33.8 0.0258 0.321 3.82 673 − − − − − −
Sohar Free Zone Mahadha 220 2 Quad YEW 61.8 0.0210914 0.2577821 5.18 975 2500mm2 XLP E cable 0.25 0.01074 0.312 91.11 500
Mahadha Sohar Free Zone 220 2 − − − − − − 2500mm2 XLP E cable 0.26 0.01074 0.312 91.11 500
Sur 1 GS Sur 2 GS 132 1 − − − − − − 2500mm2 XLP E cable 0.10 0.01074 0.321 91.11 343
Sur 1 GS Sur 2 GS 132 1 − − − − − − 2500mm2 XLP E cable 0.186 0.01074 0.321 91.11 343
Al Kamil JBB Ali 132 2 YEW x 2 54.9 0.04283 0.2821 3.98 293 − − − − − −
Al Kamil JBB Hassan 132 2 YEW x 2 43.5 0.04283 0.2821 3.98 293 − − − − − −

Sur JBB Hassan 132 2 YEW x 2 60.9 0.04283 0.2821 3.98 293 − − − − − −
Barka Main Filaj 132 2 YEW x 2 6.2 0.04283 0.2821 3.98 293 − − − − − −
Mudhaibi Sinaw 132 2 YEW x 2 29.4 0.04283 0.2821 3.98 293 − − − − − −
Sinaw New Izki 132 2 YEW x 2 51.1 0.04283 0.2821 3.98 293 2500mm2 XLP E cable 0.62 0.01074 0.321 91.11 625
Manah Nizwa 132 2 YEW x 2 20.0 0.04283 0.2821 3.98 183 − − − − − −
Mawalleh Rusail Industrial 132 2 − − − − − − 2500mm2 XLP E cable 6.2 0.04282 0.08361 122.522 375
Mobella Barka Main 132 2 YEW x 2 11.5 0.04283 0.2821 3.98 293 − − − − − −

MSQ Wadi Adai 132 2 YEW x 2 8.4 0.04283 0.2821 3.98 293 − − − − − −
Mudhaibi Mudhairib 132 2 YEW x 2 60.0 0.04283 0.2821 3.98 293 − − − − − −
Muladah MIS 132 2 YEW x 2 11.5 0.04283 0.2821 3.98 293 − − − − − −
Nizwa Nahda (P DO) 132 1 ELM x1 67.4 0.1944 0.4207 2.71 89 − − − − − −
Nizwa Bahla 132 2 YEW x1 31.9 0.0857 0.3948 2.85 146 − − − − − −
Rusail Mobella 132 2 YEW x 2 13.1 0.04283 0.2821 3.98 293 − − − − − −
Rusail Sumail 132 2 YEW x 2 34.6 0.04283 0.2821 3.98 293 − − − − − −
Rustaq Muladah 132 2 YEW x 2 29.4 0.04283 0.2821 3.98 293 − − − − − −

SIS Uwaynat 132 2 YEW x 2 17.0 0.04283 0.2821 3.98 293 − − − − − −

Page | 137
Five-Year Annual Transmission Capability Statement (2020-2024)

Table B. 2: (Continued) 2020 Branch Data Listing

From To Voltage No. Conductor Length R X B Rating Conductor Length Rating


R[Ω/km] X[Ω/km] B [MS/km]
Substation Substation (kV) Circuits Type (OHL) (Km) [Ω/km] [Ω/km] [MS/km] (MVA) Type (Cable) (Km) (MVA)

MIS

Uwaynat Sohar 132 2 YEW x 2 19.0 0.04283 0.2821 3.98 293 − − − − − −

Sohar Wadi Jizzi 132 2 YEW x 2 28.3 0.04283 0.2821 3.98 293 − − − − − −

Sumail Izki 132 2 YEW x 2 60.9 0.04283 0.2821 3.98 293 − − − − − −

Wadi Adai Al Falaj 132 2 YEW x 2 2.7 0.04283 0.2821 3.98 293 − − − − − −

Wadi Jizzi Mahadha 132 2 ELM x 2 36.2 0.0972 0.3168 3.8 179 − − − − − −

Manah Adam 132 2 YEW x 2 49.0 0.04283 0.2821 3.98 293 − − − − − −

New Ghubrah Bousher 132 3 − − − − − − 2500mm2 XLP E cable 2 0.04 0.08 122.52 375

Bousher MSQ 132 1 YEW x 2 2.1 0.04283 0.2821 3.98 293 2500mm2 XLP E cable 2.7 0.04 0.08 122.52 375

New Ghubrah MSQ 132 3 YEW x 2 2.1 0.04283 0.2821 3.98 293 2500mm2 XLP E cable 4.3 0.04 0.08 122.52 375

Airport Heights Mawalleh North 132 2 − − − − − − 2500mm2 XLP E cable 8.6 0.04 0.08 122.52 375

Liwa Shinas 132 2 YEW x 2 19.5 0.04283 0.2821 3.98 293 − − − − − −

Shinas Madinat Shinas 132 2 YEW x 2 24.1 0.04283 0.2821 3.98 293 − − − − − −

Khaborah DAS 132 2 YEW x 2 33.4 0.04283 0.2821 3.98 293 − − − − − −

DAS Saham 132 2 YEW x 2 34.6 0.04283 0.2821 3.98 293 − − − − − −

Saham SIS 132 2 YEW x 2 23.3 0.04283 0.2821 3.98 293 − − − − − −

Mahadha Wadi Sa'a 132 2 YEW x 2 31.5 0.04283 0.2821 3.98 293 − − − − − −

Wadi Sa'a Dank 132 2 225 AAAC 58.4 0.04283 0.2821 3.98 89 − − − − − −

Jahloot Yitti 132 2 ARCURIA x 2 25.2 0.0258 0.321 3.82 404 − − − − − −

Rusail Misfah 132 2 YEW x 2 12.9 0.04283 0.2821 3.98 293 − − − − − −

Misfah Wadi Adai 132 2 YEW x 2 34.0 0.04283 0.2821 3.98 293 − − − − − −

Filaj Nakhal 132 2 YEW x 2 24.2 0.04283 0.2821 3.98 293 − − − − − −

Mahadha Bureimi 132 2 ELM x 2 36.7 0.0972 0.3168 3.8 89 − − − − − −

MSQ Qurum 132 2 YEW x 2 10.0 0.04283 0.2821 3.98 293 − − − − − −

Ibri Dank 132 2 YEW x 2 55.4 0.04283 0.2821 3.98 293 − − − − − −

Page | 138
Five-Year Annual Transmission Capability Statement (2020-2024)

Table B. 2: (Continued) 2020 Branch Data Listing

Conductor
From To Voltage No. Length R X B Rating Conductor Length Rating
Type R[Ω/km] X[Ω/km] B [MS/km]
Substation Substation (kV) Circuits (Km) [Ω/km] [Ω/km] [MS/km] (MVA) Type (Cable) (Km) (MVA)
(OHL)

MIS
Jahloot Quriyat 132 2 YEW x 2 48.7 0.04283 0.2821 3.98 293 − − − − − −

Nizwa Madinata Nizwa 132 2 YEW x2 12.4 0.04283 0.2821 3.98 293 − − − − − −
Wadi Kabir Al Hamriyah 132 2 YEW x1 1.9 0.0857 0.3948 2.85 146 1200mm2 1C CU XLP E cable 1.15 0.03 0.12 64.70 171
Al Hamriyah Muttrah 132 2 YEW x 2 2.7 0.04283 0.2821 3.98 293 2500mm2 XLP E cable 3.2 0.04 0.08 122.52 300

Sur Ayjah 132 2 YEW x2 35.1 0.04283 0.2821 3.98 293 − − − − − −


Al Hamryah Wadi Adai 132 2 YEW x1 3.7 0.0857 0.3948 2.85 146 − − − − − −
Qurum Al Hamryah 132 2 YEW x 2 7.6 0.04283 0.2821 3.98 293 − − − − − −
Rusail Rusail Industrial 132 4 − − − − − − 2500mm2 XLP E cable 0.192 0.04 0.08 122.52 375

Filaj Madinata Barka 132 2 YEW x2 11.5 0.04283 0.2821 3.98 293 − − − − − −
Madinata Barka Muladah 132 2 YEW x2 34.9 0.04283 0.2821 3.98 293 − − − − − −
Dank Al Hayl 132 2 YEW x 2 52.4 0.04283 0.2821 3.98 293 − − − − − −
Airport Heights Mawalleh South 132 2 − − − − − − 2500mm2 XLP E cable 9.1 0.04 0.08 122.52 375

Airport Heights Ghala 132 2 − − − − − − 2500mm2 XLP E cable 3.7 0.04 0.08 122.52 375
MIS Suwaiq 132 2 YEW x 2 7.0 0.04283 0.2821 3.98 293 − − − − − −
Suwaiq Al Khadhra 132 2 YEW x 2 18.8 0.04283 0.2821 3.98 293 − − − − − −
Al Khadhra Khaborah 132 2 YEW x 2 27.9 0.04283 0.2821 3.98 293 − − − − − −

Mahadha Bureimi Industrial 132 2 YEW x2 32.8 0.04283 0.2821 3.98 293 − − − − − −
Bureimi Industrial Bureimi 132 2 YEW x2 0.3 0.04283 0.2821 3.98 293 2500mm2 XLP E cable 5.6 0.04 0.08 122.52 375
Mawalleh South-B Seeb Main 132 2 − − − − − − 2500mm2 XLP E cable 7.8 0.04 0.08 122.52 375

Amerat Jahloot 132 2 YEW x2 23.3 0.04283 0.2821 3.98 293 − − − − − −


MSQ Amerat 132 2 YEW x2 25.0 0.04283 0.2821 3.98 293 − − − − − −
New Izki Izki 132 2 YEW x 2 17.1 0.04283 0.2821 3.98 293 2500mm2 XLP E cable 0.62 0.04 0.08 122.52 375
A'salam Seeb Main 132 2 − − − − − − 2500mm2 XLP E cable 7.1 0.04 0.08 122.52 375

Mobella A'salam 132 2 − − − − − − 2500mm2 XLP E cable 8.6 0.04 0.08 122.52 375
Ibri Dreez 132 2 YEW x 2 28.1 0.04283 0.2821 3.98 293 − − − − − −
Sohar Free Zone Liwa 132 2 YEW x 2 2.3 0.04283 0.2821 3.98 293 − − − − − −
Wadi Jizzi Sohar Free Zone 132 2 YEW x 2 27.2 0.04283 0.2821 3.98 293 − − − − − −

Page | 139
Five-Year Annual Transmission Capability Statement (2020-2024)

Table B. 2: (Continued) 2020 Branch Data Listing

From To Voltage No. Conductor Length R X B Rating Conductor Length Rating


R[Ω/km] X[Ω/km] B [MS/km]
Substation Substation (kV) Circuits Type (OHL) (Km) [Ω/km] [Ω/km] [MS/km] (MVA) Type (Cable) (Km) (MVA)

MIS
Muttrah Al Falaj 132 1 − − − − − − 2500mm2 XLP E cable 3 0.04282 0.08361 122.522 300
Muttrah Wadi Kabair 132 1 YEW x2 1.3 0.04283 0.2821 3.98 293 2500mm2 XLP E cable 2 0.04282 0.08361 122.522 375
Quriyat Daghmar 132 2 YEW x 2 3.7 0.04283 0.2821 3.98 293 − − − − − −
Nizwa Jebreen 132 2 YEW x 2 24.4 0.04283 0.2821 3.98 293 − − − − − −
Jebreen Ibri 132 2 YEW x 2 99.4 0.04283 0.2821 3.98 293 − − − − − −
Mudhairib Bedyah 132 2 YEW x 2 14.7 0.04283 0.2821 3.98 293 − − − − − −
Bedyah Al Kamil 132 2 YEW x 2 36.5 0.04283 0.2821 3.98 293 − − − − − −
Mudhaibi Samad 132 2 YEW x 2 36.4 0.04283 0.2821 3.98 293 − − − − − −
Ghala Ghala Heights 132 2 − − − − − − 2500mm2 XLP E cable 7 0.04 0.08 122.52 375
Ghala Heights Bousher 132 2 − − − − − − 2500mm2 XLP E cable 7 0.04 0.08 122.52 375
Nizwa Birkat Al Mouz 132 2 YEW x 2 15.6 0.04283 0.2821 3.98 293 − − − − − −
Birkat Al Mouz Izki 132 2 YEW x 2 16.7 0.04283 0.2821 3.98 293 − − − − − −
Mudhairib Qabel 132 2 YEW x 2 6.0 0.04283 0.2821 3.98 293 − − − − − −
Qabel Ibra 132 2 YEW x 2 22.0 0.04283 0.2821 3.98 293 − − − − − −
Mawalleh Rusail Industrial 132 2 240 ZTACIR 9.0 0.0261 0.075 0.0153 250 2500mm2 XLP E cable 6 0.04 0.08 122.52 375
Sohar Free Zone Shinas 132 2 Quad YEW 30.0 0.0210914 0.2577821 5.184822 585 − − − − − −
Rusail Sumail Industrial Area 132 2 YEW x 2 40.2 0.04283 0.2821 3.98 293 2500mm2 XLP E cable 1.6 0.04282 0.08361 122.522 375
Sumail Industrial
Sumail 132 2 YEW x 2 22.6 0.04283 0.2821 3.98 293 2500mm2 XLP E cable 1.6 0.04282 0.08361 122.522 375
Area
Dhof ar System
Thumrait Ittin 132 2 ELM x 2 61.2 0.0900 0.3000 3.00 183 − − − − − −
Ittin Al Qurum 132 2 YEW x 2 22.7 0.0388 0.289 1.43 359 − − − − − −
Ittin SFZ 132 2 YEW x 2 25.4 0.0388 0.289 1.429 359 − − − − − −
SFZ Shaha'aon 132 2 YEW x 2 18.8 0.0388 0.289 1.429 359 − − − − − −
Ashoor Al Qurum 132 2 YEW x 2 23.3 0.0388 0.289 1.429 359 2500mm2 XLP E cable 2.52 0.01075 0.141 91.1 279
SFZ NP S 132 2 YEW x 2 0.7 0.0388 0.289 1.43 359 2500mm2 XLP E cable 0.1 0.01075 0.141 91.1 279
Shaha'aon A'saada 132 2 YEW x 2 15.0 0.0388 0.289 1.429 330 2500mm2 XLP E cable 6.5 0.01075 0.141 91.1 300
A'saada Ashoor (P ortion-1) 132 2 YEW x 2 8.5 0.0388 0.289 1.429 330 2500mm2 XLP E cable 1.2 0.01075 0.141 91.10 279
A'saada Ashoor (P ortion-2) 132 2 YEW x 2 33.3 0.0388 0.289 1.429 330 2500mm2 XLP E cable 6.5 0.01075 0.141 91.10 300
Thumrait Wind Farm (P ortion-1) 132 1 ELM x 2 65.5 0.09 0.3 3.00 183 − − − − − −
Thumrait Wind Farm (P ortion-2) 132 1 YEW x 2 11.0 0.09 0.3 3.00 359 − − − − − −
Wind Farm
Harweel 132 1 ELM x 2 19.0 0.09 0.3 3.00 183 − − − − − −
(P ortion-1)
Wind Farm
Harweel 132 1 YEW x 2 11.0 0.09 0.3 3.00 359 − − − − − −
(P ortion-2)

Page | 140
Five-Year Annual Transmission Capability Statement (2020-2024)

Table B. 3: Progressive Change to Branch Circuit Data for 2020-2024


2021 Deletions

From To Voltage No. Conductor Length Rating Conductor Length Rating


R[Ω/km] X[Ω/km] B [MS/km] R[Ω/km] X[Ω/km] B [MS/km]
Substation Substation (kV) Circuits Type (OHL) (Km) (MVA) Type (Cable) (Km) (MVA)

MIS SIS 220 2 ARCURIA x 2 107.0 0.0258 0.321 3.82 673 − − − − − −

Mawalleh Rusail Industrial 132 2 240 ZTACIR 8.0 0.0261 0.075 0.0153 250 2500mm2 XLP E cable 6 0.04 0.08 122.52 375

Dank Al Hayl 132 2 YEW x 2 51.8 0.04283 0.2821 3.98 293 − − − − − −

Khaborah DAS 132 2 YEW x 2 33.0 0.04283 0.2821 3.98 293 − − − − − −

2021 Additions

From To Voltage No. Conductor Length Rating Conductor Length Rating


R[Ω/km] X[Ω/km] B [MS/km] R[Ω/km] X[Ω/km] B [MS/km]
Substation Substation (kV) Circuits Type (OHL) (Km) (MVA) Type (Cable) (Km) (MVA)

MIS

New Izki Misfah 400 2 Quad YEW 100.0 0.0211 0.2578 5.18 1775 − − − − − −

Ibri IP P Ibri Solar IP P 220 2 ARCURIA x 2 3.0 0.0258 0.321 3.82 673 − − − − − −

MIS KIS 220 2 ARCURIA x 2 46.0 0.0258 0.321 3.82 673 − − − − − −

KIS SIS 220 2 ARCURIA x 2 61.4 0.0258 0.321 3.82 673 − − − − − −

Dank Yanqul 132 2 YEW x 2 36.0 0.04283 0.2821 3.98 293 − − − − − −

Yanqul Al Hayl 132 2 YEW x 2 16.5 0.04283 0.2821 3.98 293 − − − − − −

Nakhal Wadi Bani Awf 132 2 YEW x 2 52.3 0.04283 0.2821 3.98 293 − − − − − −

Wadi Bani Awf Rustaq 132 2 YEW x 2 34.1 0.04283 0.2821 3.98 293 − − − − − −

DAS KIS 132 2 YEW x 2 24.4 0.04283 0.2821 3.98 293 − − − − − −

KIS Khaborah 132 2 YEW x 2 9.3 0.04283 0.2821 3.98 293 − − − − − −

Mawalleh Khoudh 132 2 240 ZTACIR 1.3 0.0261 0.075 0.0153 250 2500mm2 XLP E cable 0.7 0.04 0.08 122.52 375

Khoudh Rusail Industrial 132 2 240 ZTACIR 6.0 0.0261 0.075 0.0153 250 − − − − − −

Dhof ar System

Ashoor Mirbat 132 2 YEW x 2 32.0 0.0388 0.289 1.43 359 − − − − − −

Page | 141
Five-Year Annual Transmission Capability Statement (2020-2024)

Table B. 3: (Continued) Progressive Change to Branch Circuit Data for 2020-2024

2022 Deletions

Conductor
From To Voltage No. Length Rating Conductor Length Rating
Type R[Ω/km] X[Ω/km] B [MS/km] R[Ω/km] X[Ω/km] B [MS/km]
Substation Substation (kV) Circuits (Km) (MVA) Type (Cable) (Km) (MVA)
(OHL)

Ibri IP P New Izki 400 2 Quad YEW 264.4 0.0210914 0.2577821 5.18 1774 − − − − − −

Mobella Barka Main 132 2 YEW x 2 11.5 0.04283 0.2821 3.98 293 − − − − − −

2022 Additions

Conductor
From To Voltage No. Length Rating Conductor Length Rating
Type R[Ω/km] X[Ω/km] B [MS/km] R[Ω/km] X[Ω/km] B [MS/km]
Substation Substation (kV) Circuits (Km) (MVA) Type (Cable) (Km) (MVA)
(OHL)

New Izki Manah Solar IP P 400 2 Quad YEW 25.0 0.0210914 0.2577821 5.18 1774 − − − − − −

Manah Solar IP P Ibri IP P 400 2 Quad YEW 245.0 0.0210914 0.2577821 5.18 1774 − − − − − −

Mobella Mobella Industrial 132 2 YEW x 2 2.8 0.04283 0.2821 3.98 293 − − − − − −

Mobella Industrial Barka Main 132 2 YEW x 2 10.2 0.04283 0.2821 3.98 293 − − − − − −

Page | 142
Five-Year Annual Transmission Capability Statement (2020-2024)

Table B. 3: (Continued) Progressive Change to Branch Circuit Data for 2020-2024

2023 Deletions

From To Voltage No. Conductor Length Rating Conductor Length Rating


R[Ω/km] X[Ω/km] B [MS/km] R[Ω/km] X[Ω/km] B [MS/km]
Substation Substation (kV) Circuits Type (OHL) (Km) (MVA) Type (Cable) (Km) (MVA)

Manah Solar
Ibri IP P 400 2 Quad YEW 245.0 0.0210914 0.2577821 5.18 1774 − − − − − −
IP P

Rusail Misfah 132 2 YEW x 2 12.8 0.04283 0.2821 3.98 293 − − − − − −

Rusail
Rusail 132 4 − − − − − − 2500mm2 XLP E cable 0.192 0.04 0.08 122.52 375
Industrial
Sumail
Rusail 132 2 YEW x 2 40.6 0.04283 0.2821 3.98 293 2500mm2 XLP E cable 1.6 0.04 0.08 122.52 375
Industrial Area

2023 Additions

From To Voltage No. Conductor Length Rating Conductor Length Rating


R[Ω/km] X[Ω/km] B [MS/km] R[Ω/km] X[Ω/km] B [MS/km]
Substation Substation (kV) Circuits Type (OHL) (Km) (MVA) Type (Cable) (Km) (MVA)

MIS

Mahout Duqm 400 2 Quad YEW 152.0 0.0210914 0.2577821 5.184822 1774 − − − − − −

Duqm Suwaihat 400 2 Quad YEW 187.0 0.0210914 0.2577821 5.184822 1774 − − − − − −

Manah Solar IP P Nahadah 400 2 Quad YEW 80.5 0.0210914 0.2577821 5.18 1774 − − − − − −

Nahadah Ibri IP P 400 2 Quad YEW 166.5 0.0210914 0.2577821 5.18 1774 − − − − − −

Al Jefnen Misfah 400 2 Quad YEW 8.3 0.0210914 0.2577821 5.184822 1774 − − − − − −

Airport Heights Ghala 132 1 − − − − − − 2500mm2 XLP E cable 3.8 0.04 0.08 122.52 375
Rusail
Al Jefnen 132 4 − − − − − − 2500mm2 XLP E cable 6.4 0.04 0.08 122.52 375
Industrial
Sumail
Al Jefnen 132 2 YEW x 2 36.4 0.04283 0.2821 3.98 293 2500mm2 XLP E cable 1.6 0.04 0.08 122.52 375
Industrial
Dhof ar System

Saih Al
Thumrait 132 2 YEW x 2 88.0 0.04283 0.2821 3.98 293 − − − − − −
Khairat

Page | 143
Five-Year Annual Transmission Capability Statement (2020-2024)

Table B. 3: (Continued) Progressive Change to Branch Circuit Data for 2020-2024

2024 Additions

From To Voltage No. Conductor Length Rating Conductor Length Rating


R[Ω/km] X[Ω/km] B [MS/km] R[Ω/km] X[Ω/km] B [MS/km]
Substation Substation (kV) Circuits Type (OHL) (Km) (MVA) Type (Cable) (Km) (MVA)

Rustaq Ibri IP P 400 2 Quad YEW 159.8 0.0210914 0.2577821 5.184822 1774 − − − − − −

Rustaq Al Jefnen 400 2 Quad YEW 85.2 0.0210914 0.2577821 5.184822 1774 − − − − − −

New Izki Nizwa 220 2 ARCURIA x 2 53.9 0.0258 0.321 3.82 673 2500mm2 XLP E cable 4.7 0.01074 0.321 91.11 625

Mahadha Bureimi 132 2 YEW x 2 32.9 0.04283 0.2821 3.98 293 2500mm2 XLP E cable 5.5 0.04282 0.08361 122.522 375

WTE IP P Madinat Barka 132 2 YEW x2 3.6 0.04283 0.2821 3.98 293 − − − − − −

JBB Ali Al Jawabi 132 2 YEW x 2 14 0.04283 0.2821 3.98 293 − − − − − −

Al Jawabi JBB Ali Wind 132 2 YEW x 2 9 0.04283 0.2821 3.98 293 − − − − − −

Duqm Duqm Wind 132 2 YEW x 2 49.7 0.04283 0.2821 3.98 293 − − − − − −

Page | 144
Five-Year Annual Transmission Capability Statement (2020-2024)

Table B. 4: Grid Station Transformers Data at 2020 Peak


Rating Voltage Vector Tap Tap Step Neutral Min Max Of f -Nominal Tap range Reactance (%
Substation Tx. No
(MVA) (kV) G roup Side (% ) Tap Tap Tap Upper (pu) Lower (pu) on rating)

MIS
1 500 400/220 YNa0d1 HV 1.25 11 21 1 12.50 -12.50 21.59
Ibri IP P
2 500 400/220 YNa0d1 HV 1.25 11 21 1 12.50 -12.50 21.58
3 500 400/220 YNa0d1 HV 1.25 11 21 1 12.50 -12.50 21.47
1 500 400/220 YNa0d1 HV 1.25 11 21 1 12.50 -12.50 22.35

Jahloot 2 500 400/220 YNa0d1 HV 1.25 11 21 1 12.50 -12.50 22.43


3 500 400/220 YNa0d1 HV 1.25 11 21 1 12.50 -12.50 22.22
4 500 400/220 YNa0d1 HV 1.25 11 21 1 12.50 -12.50 22.29
1 500 400/220 YNa0d1 HV 1.25 11 21 1 12.50 -12.50 21.41
Misfah
2 500 400/220 YNa0d1 HV 1.25 11 21 1 12.50 -12.50 21.44
3 500 400/220 YNa0d1 HV 1.25 11 21 1 12.50 -12.50 21.57

New Izki 1 500 400/220 YNa0d1 HV 1.25 11 21 1 12.50 -12.50 21.49


2 500 400/220 YNa0d1 HV 1.25 11 21 1 12.50 -12.50 21.49

Qabel 1 500 400/132 YNa0d1 HV 1.11 6 20 1 5.55 -15.54 23.28


2 500 400/132 YNa0d1 HV 1.11 6 20 1 5.55 -15.54 23.28
1 500 400/220 YNa0d1 HV 1.25 11 21 1 12.50 -12.50 22.70
SIS
2 500 400/220 YNa0d1 HV 1.25 11 21 1 12.50 -12.50 22.53
3 500 400/220 YNa0d1 HV 1.25 11 21 1 12.50 -12.50 22.50
1 500 400/220 YNa0d1 HV 1.11 6 20 1 5.55 -15.54 22.08
Sohar Free Zone
2 500 400/220 YNa0d1 HV 1.11 6 20 1 5.55 -15.54 22.08
3 500 400/220 YNa0d1 HV 1.11 6 20 1 5.55 -15.54 22.08
1 750 400/220 YNa0d1 HV 1.25 11 21 1 12.50 -12.50 21.80
2 750 400/220 YNa0d1 HV 1.25 11 21 1 12.50 -12.50 21.83
Sur IP P
3 750 400/220 YNa0d1 HV 1.25 11 21 1 12.50 -12.50 21.90
4 750 400/220 YNa0d1 HV 1.25 11 21 1 12.50 -12.50 21.96
5 750 400/220 YNa0d1 HV 1.25 11 21 1 12.50 -12.50 21.95

Airport Heights 1 500 220/132 YNa0d1 HV 1.11 6 20 1 5.55 -15.54 23.81


2 500 220/132 YNa0d1 HV 1.11 6 20 1 5.55 -15.54 23.90

Barka IP P 1 125 220/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.41


2 125 220/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.50

Blue City 1 160 220/33 YNd5 HV 1.10 5 19 1 4.42 -15.45 18.11


2 160 220/33 YNd5 HV 1.10 5 19 1 4.42 -15.45 18.57

Filaj 1 500 220/132 YNa0d1 LV 1.11 6 20 1 5.55 -15.54 23.25


2 500 220/132 YNa0d1 LV 1.11 6 20 1 5.55 -15.54 23.26

Page | 145
Five-Year Annual Transmission Capability Statement (2020-2024)

Table B. 4: (Continued) Grid Station Transformers Data at 2020 Peak


Rating Voltage Vector Tap Tap Step Neutral Min Max Of f -Nominal Tap range Reactance (%
Substation Tx. No
(MVA) (kV) G roup Side (% ) Tap Tap Tap Upper (pu) Lower (pu) on rating)

MIS

Al Hamriyah 1 500 220/132 YNa0d1 HV 1.11 6 20 1 5.55 -15.54 23.15

2 500 220/132 YNa0d1 HV 1.11 6 20 1 5.55 -15.54 22.74

Ibri 1 500 220/132 YNa0d1 HV 1.10 6 20 1 5.50 -15.40 23.28

2 500 220/132 YNa0d1 HV 1.10 6 20 1 5.50 -15.40 23.30

Jahloot 1 500 220/132 YNa0d1 HV 1.11 6 20 1 5.50 -15.54 22.02

2 500 220/132 YNa0d1 HV 1.11 6 20 1 5.50 -15.54 22.19

Mahadha 1 315 220/132 YNa0d1 HV 1.10 6 20 1 5.50 -15.40 13.96

2 315 220/132 YNa0d1 HV 1.10 6 20 1 5.50 -15.40 13.98

1 500 220/132 YNa0d1 HV 1.11 6 20 1 5.55 -15.54 21.35


MIS
2 500 220/132 YNa0d1 HV 1.11 6 20 1 5.55 -15.54 21.43

Mobella 1 500 220/132 YNa0d1 HV 1.11 5 19 1 4.44 -15.54 21.31

2 500 220/132 YNa0d1 HV 1.11 5 19 1 4.44 -15.54 21.13

MSQ 1 500 220/132 YNa0d1 LV 1.11 6 20 1 5.55 -15.54 23.30

2 500 220/132 YNa0d1 LV 1.11 6 20 1 5.55 -15.54 23.24

New Izki 1 500 220/132 YNa0d1 HV 1.11 7 21 1 6.66 -15.54 22.30

2 500 220/132 YNa0d1 HV 1.11 7 21 1 6.66 -15.54 22.29

1 500 220/132 YNa0d1 HV 1.10 6 20 1 5.50 -15.40 21.23


SIA
2 500 220/132 YNa0d1 HV 1.10 6 20 1 5.50 -15.40 21.24

3 500 220/132 YNa0d1 HV 1.10 6 20 1 5.50 -15.40 21.23

SIS 1 500 220/132 YNa0d1 HV 1.11 6 20 1 5.55 -15.54 21.37

2 500 220/132 YNa0d1 HV 1.11 6 20 1 5.55 -15.54 21.38

Sohar Free Zone 1 500 220/132 YNa0d1 HV 1.10 6 20 1 5.55 -15.54 21.23

2 500 220/132 YNa0d1 HV 1.10 6 20 1 5.55 -15.54 21.32

1 500 220/132 YNa0d1 HV 1.10 6 20 1 5.50 -15.40 22.10


Sur
2 500 220/132 YNa0d1 HV 1.10 6 20 1 5.50 -15.40 22.15

Page | 146
Five-Year Annual Transmission Capability Statement (2020-2024)

Table B. 4: (Continued) Grid Station Transformers Data at 2020 Peak


Rating Voltage Vector Tap Tap Step Neutral Min Max Of f -Nominal Tap range Reactance (%
Substation Tx. No
(MVA) (kV) G roup Side (% ) Tap Tap Tap Upper (pu) Lower (pu) on rating)

MIS

Adam 1 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.31

2 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.48

1 125 132/33 YNd5 HV 1.10 5 19 1 4.42 -15.46 18.31

Airport Heights 2 125 132/33 YNd5 HV 1.10 5 19 1 4.42 -15.46 18.37

3 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.41

4 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.43

Al Falaj 1 125 132/33 YNd5 HV 1.67 4 13 1 5.00 -15.00 19.56

2 125 132/33 YNd5 HV 1.67 4 13 1 5.00 -15.00 19.49

Al Hayl 1 40 132/33 YNd11 HV 1.25 5 17 1 5.00 -15.00 11.92

2 40 132/33 YNd11 HV 1.11 5 17 1 5.00 -15.00 11.69

1 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.73

Amerat 2 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.65

3 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.30

4 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.38

1 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.51

A'salam 2 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.61

3 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.61

4 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.61

Ayjah 1 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 18.39

1 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 18.39

Bahla 1 125 132/33 YNd5 HV 1.11 6 19 1 5.50 -14.30 18.02

2 125 132/33 YNd5 HV 1.11 6 19 1 5.50 -14.30 18.20

1 125 132/33 YNd5 HV 1.67 4 5 1 4.00 -15.00 17.00


Barka Main
2 125 132/33 YNd5 HV 1.67 4 5 1 4.00 -15.00 17.00

3 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.60

Bedyah 1 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.26

2 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.26

Birkat Al Mouz 1 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.26

2 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.26

Page | 147
Five-Year Annual Transmission Capability Statement (2020-2024)

Table B. 4: (Continued) Grid Station Transformers Data at 2020 Peak


Rating Voltage Vector Tap Tap Step Neutral Min Max Of f -Nominal Tap range Reactance (%
Substation Tx. No
(MVA) (kV) G roup Side (% ) Tap Tap Tap Upper (pu) Lower (pu) on rating)

MIS
1 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.26

Bousher 2 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.44


3 125 132/33 YNd5 HV 1.10 5 19 1 4.42 -15.46 18.56
4 125 132/33 YNd5 HV 1.10 5 19 1 4.42 -15.46 18.12

Bureimi 1 125 132/33 YNd5 HV 1.10 5 19 1 4.42 -15.46 18.87


2 125 132/33 YNd5 HV 1.10 5 19 1 4.42 -15.46 18.91
1 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 18.59

Bureimi Industrial 2 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 18.57


3 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.31
4 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.34
1 50 132/11 YNd1 HV 1.11 5 19 1 4.42 -15.47 32.21
Daghmar
2 50 132/11 YNd1 HV 1.11 5 19 1 4.42 -15.47 32.21
3 50 132/11 YNd1 HV 1.11 5 19 1 4.42 -15.47 32.21

Dank 1 63 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 14.56


2 63 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 14.56

Dil Abdusalam 1 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.49


2 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.49

Dreez 1 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.39


2 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.33
1 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.66

Ghala 2 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.75


3 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.70
4 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.42
1 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.40

Ghala Heights 2 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.38


3 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.37
4 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.36

Ghubrah 1 125 132/33 YNd5 HV 2.22 5 19 1 4.44 -15.54 17.37


2 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.31

Page | 148
Five-Year Annual Transmission Capability Statement (2020-2024)

Table B. 4: (Continued) Grid Station Transformers Data at 2020 Peak


Rating Voltage Vector Tap Tap Step Neutral Min Max Of f -Nominal Tap range Reactance (%
Substation Tx. No
(MVA) (kV) G roup Side (% ) Tap Tap Tap Upper (pu) Lower (pu) on rating)

MIS

Ibra 1 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 18.38

2 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.95

1 125 132/33 YNd5 HV 1.10 5 19 1 4.42 -15.46 18.44

Ibri 2 125 132/33 YNd5 HV 1.10 5 19 1 4.42 -15.46 18.38

1 63 132/33 YNd11 HV 1.21 5 17 1 5.00 -15.00 11.80

2 63 132/33 YNd11 HV 1.21 5 17 1 5.00 -15.00 11.97

Izki 1 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.68

2 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.31

Jahloot 1 125 132/33 YNd5 HV 1.10 7 21 2 5.50 -15.40 19.03

2 125 132/33 YNd5 HV 1.10 7 21 2 5.50 -15.40 19.27

JBB Ali 1 125 132/33 YNd5 HV 1.10 7 21 2 5.50 -15.40 17.84

2 125 132/33 YNd5 HV 1.10 7 21 2 5.50 -15.40 17.76

JBB Hassan 1 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 18.75

2 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 18.75

Jebreen 1 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.26

2 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.26

Khaburah 1 125 132/33 YNd5 HV 1.67 4 13 1 5.00 -15.00 18.21

2 125 132/33 YNd5 HV 1.67 4 13 1 5.00 -15.00 18.03

Khadhra 1 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.76

2 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.74

1 125 132/33 YNd5 HV 1.10 5 19 1 4.42 -15.46 19.24

Liwa 2 125 132/33 YNd5 HV 1.10 5 19 1 4.42 -15.46 18.24

3 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.58

4 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.42

Madinat Nizwa 1 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 18.59

2 125 132/33 YNd5 HV 1.11 6 20 1 4.44 -15.54 18.37

Madinat Shinas 1 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.34

2 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.37

Page | 149
Five-Year Annual Transmission Capability Statement (2020-2024)

Table B. 4: (Continued) Grid Station Transformers Data at 2020 Peak


Rating Voltage Vector Tap Tap Step Neutral Min Max Of f -Nominal Tap range Reactance (%
Substation Tx. No
(MVA) (kV) G roup Side (% ) Tap Tap Tap Upper (pu) Lower (pu) on rating)

MIS
1 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.69

Madinata Barka 2 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.88


3 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.41
4 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.46

Mahadha 1 30 132/33 YNd11 HV 1.67 7 13 1 10.00 -10.00 12.33


2 30 132/33 YNd11 HV 1.67 7 13 1 10.00 -10.00 12.49

Mawalleh North 1 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.60

2 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.60


1 125 132/33 YNd5 HV 1.25 5 17 1 5.00 -15.00 18.70

Mawalleh South 2 125 132/33 YNd5 HV 1.25 5 17 1 5.00 -15.00 18.70


3 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.24
4 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.24

MIS 1 125 132/33 YNd5 HV 1.10 5 19 1 4.42 -15.46 18.44


2 125 132/33 YNd5 HV 1.10 5 19 1 4.42 -15.46 18.64

Misfah 1 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.39


2 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.39

Mobella 1 125 132/33 YNd5 HV 1.10 5 19 1 4.42 -15.46 18.35


2 125 132/33 YNd5 HV 1.10 5 19 1 4.42 -15.46 18.35
1 125 132/33 YNd5 HV 1.67 4 13 1 4.42 -15.47 17.44

MSQ 2 125 132/33 YNd5 HV 1.67 4 13 1 4.42 -15.47 17.62


3 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.29
4 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.40 17.29

Mudhaibi 1 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.62


2 125 132/33 YNd5 HV 1.10 5 19 1 4.42 -15.46 15.32

Mudhairib 1 125 132/33 YNd5 HV 1.10 7 21 2 5.50 -15.40 17.81


2 125 132/33 YNd5 HV 1.10 7 21 2 5.50 -15.40 17.79
1 125 132/33 YNd5 HV 1.10 5 19 1 4.42 -15.46 18.43

Muladah 2 125 132/33 YNd5 HV 1.10 5 19 1 4.42 -15.46 18.44


3 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 18.32
4 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 18.33

Muttrah 1 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.50


2 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.32

Nakhal 1 125 132/33 YNd5 HV 1.10 5 19 1 4.42 -15.46 18.06


2 125 132/33 YNd5 HV 1.10 5 19 1 4.42 -15.46 18.07

Page | 150
Five-Year Annual Transmission Capability Statement (2020-2024)

Table B. 4: (Continued) Grid Station Transformers Data at 2020 Peak


Rating Voltage Vector Tap Tap Step Neutral Min Max Of f -Nominal Tap range Reactance (%
Substation Tx. No
(MVA) (kV) G roup Side (% ) Tap Tap Tap Upper (pu) Lower (pu) on rating)

MIS

New Izki 1 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.51

2 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.52

Nizwa 1 125 132/33 YNd5 HV 1.10 6 19 1 5.50 -14.30 18.64

2 125 132/33 YNd5 HV 1.10 6 19 1 5.50 -14.30 17.92

Quriyat 1 125 132/33 YNd5 HV 1.10 5 19 1 4.42 -15.46 18.44

2 125 132/33 YNd5 HV 1.10 5 19 1 4.42 -15.46 18.41

Qurum 1 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.28

2 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.51

1 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.99

Rusail Industrial 2 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.92

3 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.83

4 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.26

1 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.52


Rustaq
2 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.52

3 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.51

Saham 1 125 132/33 YNd5 HV 1.10 5 19 1 4.42 -15.46 18.31

2 125 132/33 YNd5 HV 1.10 5 19 1 4.42 -15.46 18.27

Samad 1 63 132/33 YNd5 HV 1.10 5 19 1 4.42 -15.46 15.21

2 63 132/33 YNd5 HV 1.10 5 19 1 4.42 -15.46 15.32

Samail Industrial Area 1 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.26

2 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.26

1 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.46

Seeb Main 2 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.42

3 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.30

4 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.25

Shinas 1 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.76

2 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.59

Page | 151
Five-Year Annual Transmission Capability Statement (2020-2024)

Table B. 4: (Continued) Grid Station Transformers Data at 2020 Peak


Rating Voltage Vector Tap Tap Step Neutral Min Max Of f -Nominal Tap range
Reactance (%
Substation Tx. No
on rating)
(MVA) (kV) G roup Side (% ) Tap Tap Tap Upper (pu) Lower (pu)

MIS

1 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.40


Sinaw
2 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.40

1 125 132/33 YNd5 HV 1.10 6 19 1 5.50 -14.30 17.78

2 125 132/33 YNd5 HV 1.10 6 19 1 5.50 -14.30 17.81


Sohar
3 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 18.42

4 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 18.35

1 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.58

2 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.55


Sohar Free Zone
3 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.44

4 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.43

1 125 132/33 YNd5 HV 1.10 5 19 1 4.42 -15.46 18.70


Sohar Industrial Area
2 125 132/33 YNd5 HV 1.10 5 19 1 4.42 -15.46 18.59

1 63 132/33 YNd5 HV 1.11 6 19 1 5.55 -15.54 14.87

2 63 132/33 YNd5 HV 1.11 6 19 1 5.55 -15.54 14.74


Sumail
3 125 132/33 YNd5 HV 1.13 5 19 1 4.44 -15.54 17.47

4 125 132/33 YNd5 HV 1.13 5 19 1 4.44 -15.54 17.45

1 125 132/33 YNd5 HV 1.10 7 21 2 5.50 -15.40 17.85


Sur
2 125 132/33 YNd5 HV 1.10 7 21 2 5.50 -15.40 17.72

Suwaiq 1 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.49

2 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.46

1 125 132/33 YNd5 HV 1.10 5 19 1 4.44 -15.54 17.48

Uwaynat 2 125 132/33 YNd5 HV 1.10 5 19 1 4.44 -15.54 17.54

3 125 132/33 YNd5 HV 1.10 5 19 1 4.44 -15.54 17.34

4 125 132/33 YNd5 HV 1.10 5 19 1 4.44 -15.54 17.36

Wadi Adai 1 125 132/33 YNd5 HV 1.11 6 19 1 5.55 -14.45 17.94

2 125 132/33 YNd5 HV 1.11 6 19 1 5.55 -14.45 17.88

Page | 152
Five-Year Annual Transmission Capability Statement (2020-2024)

Table B. 4: (Continued) Grid Station Transformers Data at 2020 Peak


Rating Voltage Vector Tap Tap Step Neutral Min Max Of f -Nominal Tap range Reactance (%
Substation Tx. No
(MVA) (kV) G roup Side (% ) Tap Tap Tap Upper (pu) Lower (pu) on rating)

MIS
1 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.31

Wadi Kabir 2 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.61


3 125 132/33 YNd5 HV 1.14 6 19 1 5.53 -14.47 18.40
4 125 132/33 YNd5 HV 1.11 6 19 1 5.55 -14.43 17.48

Wadi Sa'a 1 63 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 15.34


2 63 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 15.30

Yitti 1 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.45


2 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.45
Dhof ar System

Al Qarm 1 63 132/36 YNd5 HV 1.11 10 1 19 9.99 -9.99 15.37


2 63 132/36 YNd5 HV 1.11 10 1 19 9.99 -9.99 15.37

Ashoor 1 125 132/33 YNd5 HV 1.10 5 1 19 4.42 -15.46 18.27


2 125 132/33 YNd5 HV 1.10 5 1 19 4.42 -15.46 18.26

Ittin 1 125 132/33 YNd5 HV 1.11 10 1 19 9.99 -9.99 18.06


2 125 132/33 YNd5 HV 1.11 10 1 19 9.99 -9.99 18.16

NP S 1 63 132/33 YNd0 HV 1.11 10 1 19 9.99 -9.99 18.16


2 63 132/33 YNd0 HV 1.11 10 1 19 9.99 -9.99 18.16
1 125 132/33 YNd5 HV 1.10 5 1 19 4.42 -15.46 18.28
Raysut
2 125 132/33 YNd5 HV 1.10 5 1 19 4.42 -15.46 18.42
1 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.61
Salalah IP P
2 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.59

1 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.57

Sa'adah 2 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.53

3 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.66

4 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.60

Shaha'aon 1 125 132/33 YNd5 HV 1.11 5 1 19 4.44 -15.54 17.299

2 125 132/33 YNd5 HV 1.11 5 1 19 4.44 -15.54 17.284

Thumrait 1 30 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 12.5

2 30 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 12.5

Page | 153
Five-Year Annual Transmission Capability Statement (2020-2024)

Table B. 5: Grid Station Transformers Data from 2020 to 2024


2021Changes Deletions
Rating Voltage Vector Tap Tap Step Neutral Min Max Of f -Nominal Tap range
Reactance (%
Substation Tx. No
on rating)
(MVA) (kV) G roup Side (% ) Tap Tap Tap Upper (pu) Lower (pu)

Dhof ar System

1 63 132/36 YNd5 HV 1.11 10 1 19 9.99 -9.99 15.37


Thumrait

2 63 132/36 YNd5 HV 1.11 10 1 19 9.99 -9.99 15.37

2021 Changes Additions


Rating Voltage Vector Tap Tap Step Neutral Min Max Of f -Nominal Tap range Reactance
Substation Tx. No
(MVA) (kV) G roup Side (% ) Tap Tap Tap Upper (pu) Lower (pu) (% on rating)
MIS System

KIS 1 500 220/132 YNa0d1 HV 1.11 6 20 1 5.55 -15.54 23.28


2 500 220/132 YNa0d1 HV 1.11 6 20 1 5.55 -15.54 23.28
1 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.26

Khoudh 2 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.26


3 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.26
4 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.26

Wadi Bani Awf 1 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.26
2 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.26

Yanqul 1 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.26


2 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.26

Dhof ar System

Mirbat 1 63 132/36 YNd5 HV 1.11 10 1 19 9.99 -9.99 16.15


2 63 132/36 YNd5 HV 1.11 10 1 19 9.99 -9.99 16.15

Thumrait 1 30 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 12.5


2 30 132/33 YNd5 HV 1.11 6 1 20 5.55 -15.54 12.5

Page | 154
Five-Year Annual Transmission Capability Statement (2020-2024)

Table B. 5: (Continued) Grid Station Transformers Data from 2020 to 2024


2022 Changes Deletions
Rating Voltage Vector Tap Tap Step Neutral Min Max Of f -Nominal Tap range Reactance (%
Substation Tx. No
(MVA) (kV) G roup Side (% ) Tap Tap Tap Upper (pu) Lower (pu) on rating)

MIS

Barka Main Third Tx 3 125 132/33 YNd5 HV 1.11 5 19 1 4.44 -15.54 17.6

2022 Changes Additions


Rating Voltage Vector Tap Tap Step Neutral Min Max Of f -Nominal Tap range Reactance (%
Substation Tx. No
(MVA) (kV) G roup Side (% ) Tap Tap Tap Upper (pu) Lower (pu) on rating)

MIS
1 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.26

2 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.26


Modella Industrial
3 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.26
4 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.26

1 500 220/132 YNa0d1 HV 1.11 6 20 1 5.55 -15.54 23.28


Misfah
2 500 220/132 YNa0d1 HV 1.11 6 20 1 5.55 -15.54 23.28

2023 Changes Additions


Rating Voltage Vector Tap Tap Step Neutral Min Max Of f -Nominal Tap range Reactance
Substation Tx. No
(MVA) (kV) G roup Side (% ) Tap Tap Tap Upper (pu) Lower (pu) (% on rating)
MIS
Airport Heights 3 500 220/132 YNa0d1 HV 1.11 6 20 1 5.55 -15.54 23.28
1 500 400/132 YNa0d1 HV 1.11 6 20 1 5.55 -15.54 23.28
Duqm
2 500 400/132 YNa0d1 HV 1.11 6 20 1 5.55 -15.54 23.28
Nahadah 1 500 400/132 YNa0d1 HV 1.11 6 20 1 5.55 -15.54 23.28
2 500 400/132 YNa0d1 HV 1.11 6 20 1 5.55 -15.54 23.28
1 500 400/132 YNa0d1 HV 1.11 6 20 1 5.55 -15.54 23.28
New Rusail
2 500 400/132 YNa0d1 HV 1.11 6 20 1 5.55 -15.54 23.28
3 500 400/132 YNa0d1 HV 1.11 6 20 1 5.55 -15.54 23.28
Suwaihat 1 500 400/132 YNa0d1 HV 1.11 6 20 1 5.55 -15.54 23.28
2 500 400/132 YNa0d1 HV 1.11 6 20 1 5.55 -15.54 23.28
1 125 400/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.26
Mahout
2 125 400/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.26
1 125 400/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.26
2 125 400/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.26
Duqm 3 125 400/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.26
4 125 400/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.26
Dhofar System
Saih Al Khairat 1 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 18.3
2 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 18.3

Page | 155
Five-Year Annual Transmission Capability Statement (2020-2024)

Table B. 5: (Continued) Grid Station Transformers Data from 2020 to 2024


2024 Changes Additions
Rating Voltage Vector Tap Tap Step Neutral Min Max Of f -Nominal Tap range Reactance (%
Substation Tx. No
(MVA) (kV) G roup Side (% ) Tap Tap Tap Upper (pu) Lower (pu) on rating)

MIS

1 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.26


Al Jawabi
2 125 132/33 YNd5 HV 1.11 6 20 1 5.55 -15.54 17.26

New Izki 1 500 400/220 YNa0d1 HV 1.25 11 21 1 12.50 -12.50 21.49

1 500 400/132 YNa0d1 HV 1.11 6 20 1 5.55 -15.54 23.28

New Rustaq 2 500 400/132 YNa0d1 HV 1.11 6 20 1 5.55 -15.54 23.28

3 500 400/132 YNa0d1 HV 1.11 6 20 1 5.55 -15.54 23.28

1 500 220/132 YNa0d1 HV 1.11 6 20 1 5.55 -15.54 23.28


Nizwa
2 500 220/132 YNa0d1 HV 1.11 6 20 1 5.55 -15.54 23.28

Page | 156
Five-Year Annual Transmission Capability Statement (2020-2024)

Appendix C: Power System Studies


C.1 Summary of Load Flow Study results
The expected performance of the system at peak and minimum demand for each year from 2020 to 2024 are summarised
in a series of tables and presented pictorially.

The study results are presented in the following tables:

Table C.1 – Grid transformer loadings at Peak Demand (2020-2024)

Table C.2 – Available capacity at Grid Stations for connection of new demand (2020-2024)

Table C.3 – Overhead line and cable circuit loadings at peak demand (2020-2024)

Table C.4– Transmission system voltage profile at peak demand (2020-2024)

Table C.5 – Transmission system voltage profile at minimum demand (2020-2024)

Table C.6 – Estimation of transmission losses and generation margin at peak demand (2020-2024).

C.2 Summary of Fault Level Study results


The expected maximu m busbar 3-phase and single-phase fault levels are presented in tabular form as follows:

Table C.7 – Maximum 3-Phase Short Circuit Fault Levels (2020-2024)

Table C.8 – Maximum Single-Phase Short Circuit Fault Levels (2020-2024).

C.3 Diagrams of the model for the Load Flow Study Results
The result of peak demand load flow studies for both MIS and Dhofar systems for the years 2020 to 2024 are presented
as Figures C.1 to C.10 respectively.

Page | 157
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C. 1: Transformers Loading (%) at Grid Stations (2020-2024)


Transformer loading (%)
Total Transformer S ubstation Firm
Location
Capacity (MVA) Capacity (MVA) 2020 2021 2022 2023 2024

MIS Area
400/220 kV Transformers
2 x 500 500 44.29 43.46 45.95 39.75
New Izki
3 x 500 1000 45.89
Ibri IPP 3 x 500 1000 30.38 26.39 20.04 20.42 15.26
M isfah 3 x 500 1000 0.29 37.41 55.23 46.16 28.89
SIS 3 x 500 1000 46.32 46.67 55.29 59.42 60.20
Sohar Free Zone 3 x 500 1000 39.71 43.12 45.53 51.10 54.73
Jahloot 4 x 500 1500 63.46 51.76 56.48 55.95 53.45
Sur 5 x 750 3000 32.99 33.54 41.22 42.08 43.07
400/132 kV Transformers
Duqm 2 x 500 500 12.44 6.53
Nahadah(PDO) 2 x 500 500 14.95 7.60
Qabel 2 x 500 500 24.62 15.62 41.94 40.36 31.65
Al Jefnen 3 x 500 1000 26.05 50.69
New Rustaq 3 x 500 1000 25.63
Suwaihat 2 x 500 500 13.79 8.01
400/33 kV Transformers
M ahout 2 x 125 125 10.02 10.48
220/132 kV Transformers
M ahadha 2 x 315 315 45.03 48.38 50.19 50.73 52.04
Airport Heights 2 x 500 500 41.38 48.22 61.32
Airport Heights 3 x 500 1000 47.92 42.89
Al Filaj 2 x 500 500 50.93 44.72 47.43 52.62 33.64
Al Hamriyah 2 x 500 500 52.77 52.02 49.17 43.68 43.59
Ibri 2 x 500 500 42.86 43.73 50.93 52.78 46.17
Jahloot 2 x 500 500 46.74 43.90 47.56 43.62 43.35
KIS 2 x 500 500 27.11 25.17 12.88 25.07
M IS 2 x 500 500 44.17 36.89 40.47 55.83 27.87
M SQ 2 x 500 500 45.80 59.24 53.91 42.06 43.36
M isfah 2 x 500 500 37.06 29.49 31.39
M obella 2 x 500 500 42.32 36.51 42.36 46.29 26.00
New Izki 2 x 500 500 42.09 41.83 41.21 35.22 37.12
Nizwa 2 x 500 500 29.55
SIS 2 x 500 500 49.04 42.82 47.09 47.12 48.60
Sohar Free Zone 2 x 500 500 45.40 49.37 51.07 53.53 56.88
Sur 2 x 500 500 25.29 26.11 41.41 42.84 41.80
SIA 3 x 500 1000 11.21 11.69 11.92 11.99 12.20

Page | 158
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.1: (continued) Transformers Loading (%) at Grid Stations (2020-2024)


Transformer loading (%)
Total Transformer S ubstation Firm
Location
Capacity (MVA) Capacity (MVA) 2020 2021 2022 2023 2024

MIS Area
132/33 kV Transformers
Tx (1&2) 2 x 125 125 53.81 52.20 36.07 39.32 41.58
A'salam
Tx (3&4) 2 x 125 125 20.43 38.14 41.55 46.16 40.87
Adam 2 x 125 125 23.28 23.55 25.37 26.07 26.63

Airport Tx (1&2) 2 x 125 125 34.88 37.20 38.43 39.92 42.65


Height Tx (3&4) 2 x 125 125 13.83 15.18 18.84 19.70 21.20
Al Falaj 2 x 125 125 34.45 36.66 36.78 36.79 36.46
Al Hayl 2 x 40 40 53.63 10.07 10.13 10.29 10.65
Al Jawabi 2 x 125 125 36.02
Tx (1&2) 2 x 125 125 41.99 42.13 45.60 49.61 46.67
Amerat
Tx (3&4) 2 x 125 125 22.20 27.39 30.21 33.39 43.34
Ayjah 2 x 125 125 30.60 31.57 38.13 38.80 39.41
Bahla 2 x 125 125 33.48 34.42 37.01 38.18 38.62
Tx (1&2) 2 x 125 125 23.70 24.94 35.18 28.14 28.57
Barka M ain
Tx (3) 1 x 125 Nill 24.20 10.43
Bedyah 2 x 125 125 21.01 21.70 23.11 23.97 24.53
Birkat Al M ouz 2 x 125 125 21.94 22.93 24.77 25.79 26.88
Tx (1&2) 2 x 125 125 33.27 43.16 45.29 46.95 48.49
Bousher
Tx (3&4) 2 x 125 125 55.54 45.81 48.12 49.93 47.03

Bureimi Tx (1&2) 2 x 125 125 16.79 17.24 17.61 17.97 18.96


Industrial Tx (3&4) 2 x 125 125 21.09 25.09 25.80 26.38 28.30
Bureimi 2 x 125 125 20.35 21.62 22.29 23.34 24.27
Dank 2 x 63 63 31.78 35.70 39.74 42.89 43.85
Dil Abdusalam (DAS) 2 x 125 125 32.31 33.57 34.08 35.20 37.21
Dreez 2 x 125 125 33.41 34.32 35.20 37.03 38.13
Tx (1&2) 2 x 125 125 26.00 26.50
Duqm
Tx (3&4) 2 x 125 125 22.82 23.26
Tx (1&2) 2 x 125 125 29.43 30.33 31.60 31.50 37.85
Ghala Heights
Tx (3&4) 2 x 125 125 23.09 29.23 30.31 34.45 36.23
Tx (1&2) 2 x 125 125 30.96 40.92 42.61 44.83 46.75
Ghala
Tx (3&4) 2 x 125 125 20.95 22.08 23.31 23.17 24.55

Page | 159
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.1: (continued) Transformers Loading (%) at Grid Stations (2020-2024)


Transformer loading (%)
Total Transformer S ubstation Firm
Location
Capacity (MVA) Capacity (MVA) 2020 2021 2022 2023 2024

MIS Area
132/33 kV Transformers
Ibra 2 x 125 125 33.98 34.83 36.94 38.33 38.82
63M VA 2 x 63 63 32.45 33.42 34.66 33.70 35.20
Ibri
125M VA 2 x 125 125 32.86 33.68 34.77 35.24 36.32
Izki 2 x 125 125 34.77 37.29 38.85 39.01 39.27
JBB Ali 2 x 125 125 52.61 64.42 71.44 73.94 36.80
JBB Hassan 2 x 125 125 30.99 35.08 37.85 39.08 39.83
Jahloot 2 x 125 125 17.71 18.62 19.49 20.55 21.51
Jebreen 2 x 125 125 27.84 28.45 30.24 30.79 31.33
Khaborah 2 x 125 125 39.53 39.44 40.95 43.47 45.22
Tx (1&2) 2 x 125 125 49.64 37.37 38.72 40.83 41.81
Khadra
Tx (3&4) 2 x 125 125 15.41 28.61 29.63 31.89 31.96
Tx (1&2) 2 x 125 125 12.53 13.34 14.10 20.91
Khoudh
Tx (3&4) 2 x 125 125 25.26 26.80 28.35 29.07
Tx (1&2) 2 x 125 125 23.69 25.18 23.73 25.18 26.63
Liwa
Tx (3&4) 2 x 125 125 28.15 30.86 32.16 33.37 34.63
M IS 2 x 125 125 19.72 20.34 20.91 22.17 22.21
Tx (1&2) 2 x 125 125 34.64 37.76 39.39 40.01 40.44
M SQ
Tx (3&4) 2 x 125 125 33.35 36.56 38.31 38.97 39.49
M adinat Tx (1&2) 2 x 125 125 48.48 39.29 43.49 46.08 46.91
Barka Tx (3&4) 2 x 125 125 10.74 21.14 22.18 23.71 24.18
M adinat Nizwa 2 x 125 125 27.87 28.40 30.18 30.77 31.02
M adinat Shinas 2 x 125 125 27.15 31.23 33.13 34.62 37.02
M ahadha 2 x 30 30 42.01 30.46 30.74 31.42 31.60
M awalleh North 2 x 125 125 34.42 37.34 44.31 48.01 44.66
M awalleh Tx (1&2) 2 x 125 125 41.21 38.86 41.16 43.09 43.46
South Tx (3&4) 2 x 125 125 47.08 30.00 31.77 33.23 33.75
M isfah 2 x 125 125 28.26 29.73 31.27 32.89 34.34
M obella Tx (1&2) 2 x 125 125 35.56 27.73 29.25
Industrial Tx (3&4) 2 x 125 125 24.47 27.73 38.03
M obella 2 x 125 125 52.70 52.77 29.64 32.30 34.23
M udhaibi 2 x 125 125 19.87 20.82 23.80 24.49 24.93
M udhairib 2 x 125 125 23.84 27.13 28.51 29.47 30.14
Tx (1&2) 2 x 125 125 46.46 37.46 43.95 46.91 46.76
M uladah
Tx (3&4) 2 x 125 125 9.97 20.13 20.94 22.48 22.45

Page | 160
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.1: (continued) Transformers Loading (%) at Grid Stations (2020-2024)


Transformer loading (%)
Total Transformer S ubstation Firm
Location
Capacity (MVA) Capacity (MVA) 2020 2021 2022 2023 2024

MIS Area
132/33 kV Transformers
M uttrah 2 x 125 125 31.09 30.70 30.81 30.82 30.52
Nakhal 2 x 125 125 32.78 36.16 38.09 40.27 40.28
New Ghubrah 2 x 125 125 45.91 46.82 48.65 49.48 50.10
New Izki 2 x 125 125 8.62 8.96 9.37 9.72 10.01
Nizwa 2 x 125 125 37.48 41.74 48.41 48.67 48.56
Quriyat 2 x 125 125 22.40 23.13 23.66 24.57 25.25
Qurum 2 x 125 125 40.91 41.27 42.34 43.16 43.63
Tx (1&2) 2 x 125 125 22.58 24.58 26.46 28.24 29.09
Rusail Industrial
Tx (3&4) 2 x 125 125 37.22 40.33 43.57 46.50 47.75
Rustaq Tx (1,2&3) 3 x 125 250 48.22 34.13 35.62 38.30 37.21
SIA 2 x 125 125 33.14 35.29 36.24 36.54 37.35
Saham 2 x 125 125 37.07 37.79 37.73 38.11 40.44
Samad 2 x 63 63 20.99 21.82 22.49 23.01 23.49
Tx (1&2) 2 x 125 125 55.68 42.88 44.50 47.66 47.55
Seeb M ain
Tx (3&4) 2 x 125 125 35.93 38.40 39.85 41.19 42.54
Shinas 2 x 125 125 27.10 28.39 33.55 35.32 38.90
Sinaw 2 x 125 125 14.74 15.58 16.22 16.70 17.18
Tx (1&2) 2 x 125 125 15.42 17.22 18.78 17.27 17.77
Sohar Free Zone
Tx (3&4) 2 x 125 125 20.52 21.22 21.54 22.12 22.94
Tx (1&2) 2 x 125 125 23.49 25.08 28.75 37.94 40.36
Sohar
Tx (3&4) 2 x 125 125 46.28 49.09 47.19 40.98 43.26
Sumail Industrial 2 x 125 125 0.29 22.70 23.83 24.48 24.65

63M VA 2 x 63 63 44.73 46.18 48.06 48.61 48.29


Sumail
125M VA 2 x 125 125 47.10 25.56 27.10 27.71 27.78
Sur 2 x 125 125 39.71 40.60 42.10 42.91 44.10
Suwaiq 2 x 125 125 26.79 29.39 33.58 35.87 35.81
Tx (1&2) 2 x 125 125 21.87 23.05 23.46 24.46 25.36
Uwaynat
Tx (3&4) 2 x 125 125 25.53 26.98 27.11 28.95 29.99
Wadi Adai 2 x 125 125 35.62 35.89 36.73 37.50 37.89
Wadi Bani Auwf 2 x 125 125 21.13 22.09 23.67 23.34

Page | 161
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.1: (continued) Transformers Loading (%) at Grid Stations (2020-2024)

Transformer loading (%)


Total Transformer S ubstation Firm
Location
Capacity (MVA) Capacity (MVA) 2020 2021 2022 2023 2024

MIS Area
132/33 kV Transformers
Tx (1&2) 2 x 125 125 30.16 29.78 29.89 29.90 29.61
Wadi Kabair
Tx (3&4) 2 x 125 125 25.99 25.67 25.75 25.77 25.52
Wadi Sa'a 2 x 63 63 11.76 13.69 15.11 17.01 18.85
Yanqul 2 x 125 125 14.07 14.50 14.78 15.55
Yitti 2 x 125 125 7.29 7.47 7.57 7.77 7.91
132/11 kV Transformers
Daghmar 3 x 50 100 23.22 23.25 23.08 23.30 23.23
Dhofar Area
132/33 kV Transformers
Ashoor 2 x 125 125 31.40 25.56 25.99 25.92 26.31

Ittin 2 x 125 125 36.01 32.76 34.41 38.24 39.74


Tx (1&2) 2 x 125 125 26.14 34.56 38.00 43.55 44.95
Sa'adah
Tx (3&4) 2 x 125 125 17.80 28.40 37.44 43.73 45.13

Raysut 2 x 125 125 43.47 47.90 46.44 45.78 45.58

Salalah- IPP 2 x 125 125 16.67 29.25 42.95 45.41 47.08

Saih Al Khairat 2 x 125 125 22.06 23.10

Shaha'aon 2x 125 125 43.82 45.43 45.22 37.52 38.78

Al Qarm 2 x 63 63 31.17 30.10 32.64 25.26 25.90

Mirbat 2 x 63 63 17.55 22.62 24.41 26.37

NPS 2 x 63 63 36.21 35.43 38.06 39.28 40.52

2 x 30 30 46.19
Thumrait
2 x 63 63 26.20 29.70 29.44 30.52

Page | 162
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.2: Available Capacity at Grid Stations (2020-2024) for Connection of New Demand
Available Capacity (MVA)
Total Transformer S ubstation Firm
Location
Capacity (MVA) Capacity (MVA) 2020 2021 2022 2023 2024

MIS Area
400/220 kV Transformers
2 x 500 500 57.12 65.41 40.60 102.51
New Izki
3 x 500 1000 311.66
Ibri IPP 3 x 500 1000 544.32 604.17 699.40 693.64 771.03
M isfah 3 x 500 1000 995.59 438.78 171.85 307.61 566.66
SIS 3 x 500 1000 305.16 300.02 170.80 108.69 97.05
Sohar Free Zone 3 x 500 1000 404.29 353.20 317.05 233.44 179.10
Jahloot 4 x 500 1500 230.78 464.79 370.60 381.06 431.09
Sur 5 x 750 3000 1762.76 1742.26 1454.63 1421.84 1384.69
400/132 kV Transformers
Duqm 2 x 500 500 375.62 434.66
Nahadah(PDO) 2 x 500 500 350.48 424.02
Qabel 2 x 500 500 253.81 343.79 80.60 96.39 183.52
Al Jefnen 3 x 500 1000 609.18 239.60
New Rustaq 3 x 500 1000 615.52
Suwaihat 2 x 500 500 362.10 419.85
400/33 kV Transformers
M ahout 2x125 125 99.95 98.79
220/132 kV Transformers
M ahadha 2 x 315 315 31.34 10.23 -1.13 -4.61 -12.83
Airport Height 2 x 500 500 86.20 17.77 -113.10
Airport Height 3 x 500 1000 281.13 356.58
Al Filaj 2 x 500 500 -9.32 52.78 26.20 -26.16 163.61
Al Hamriyah 2 x 500 500 -27.66 -20.22 8.40 63.23 64.08
Ibri 2 x 500 500 71.42 62.70 -9.30 -27.80 38.25
Jahloot 2 x 500 500 32.62 61.02 24.50 63.83 66.49
KIS 2 x 500 500 228.93 248.30 371.16 249.34
M IS 2 x 500 500 58.26 131.11 95.50 -58.35 221.28
M SQ 2 x 500 500 42.04 -92.44 -39.00 79.40 66.39
M isfah 2 x 500 500 129.50 205.08 186.07
M obella 2 x 500 500 76.80 134.92 77.00 37.14 240.02
New Izki 2 x 500 500 79.10 81.72 87.90 147.80 128.82
Nizwa 2 x 500 500 204.45
SIS 2 x 500 500 9.57 71.84 29.20 28.81 13.97
Sohar Free Zone 2 x 500 500 45.97 6.33 -10.70 -35.28 -68.77
Sur 2 x 500 500 247.06 238.91 86.00 71.63 82.00
SIA 3 x 500 1000 831.80 824.72 821.20 820.19 816.96

Page | 163
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.2: (continued) Available Capacity at Grid Stations (2020-2024) for Connection of New Demand
Available Capacity (MVA)
Total Transformer S ubstation Firm
Location
Capacity (MVA) Capacity (MVA) 2020 2021 2022 2023 2024

MIS Area
220/33 kV Transformers
Barka-3 PS 2 x 125 125 68.97 55.27 37.15 36.03 33.90
Blue City 2 x 160 160 25.82 24.11 8.16 0.30 -1.97
132/33 kV Transformers
Tx (1&2) 2 x 125 125 -9.54 -5.50 34.85 26.71 21.04
A'salam
Tx (3&4) 2 x 125 125 73.92 29.65 21.18 9.60 22.83
Adam 2 x 125 125 66.81 66.14 61.58 59.81 58.43
Tx (1&2) 2 x 125 125 37.80 32.00 28.95 25.21 18.37
Airport Height
Tx (3&4) 2 x 125 125 90.43 87.06 77.90 75.76 72.01
Al Falaj 2 x 125 125 97.44 95.67 95.58 95.57 95.83
Al Hayl 2 x 40 40 -94.07 14.84 14.68 14.27 13.38
Al Jawabi 2 x 125 125 34.96
Tx (1&2) 2 x 125 125 20.01 19.69 11.03 0.97 8.32
Amerat
Tx (3&4) 2 x 125 125 69.51 56.53 49.50 41.52 16.65
Ayjah 2 x 125 125 48.50 46.07 29.68 28.01 26.46
Bahla 2 x 125 125 41.30 38.96 32.50 29.54 28.46
Tx (1&2) 2 x 125 125 65.76 62.64 37.08 54.64 53.57
Barka M ain
Tx (3) 1 x 125 Nil -30.25 -13.03
Bedyah 2 x 125 125 72.49 70.74 67.23 65.09 63.68
Birkat Al M ouz 2 x 125 125 70.14 67.68 63.10 60.52 57.80
Tx (1&2) 2 x 125 125 41.82 17.10 11.80 7.61 3.78
Bousher
Tx (3&4) 2 x 125 125 -13.85 10.46 4.73 0.17 7.43

Bureimi Tx (1&2) 2 x 125 125 83.03 81.91 80.98 80.07 77.60


Industrial Tx (3&4) 2 x 125 125 72.27 62.26 60.50 59.06 54.26
Bureimi 2 x 125 125 74.13 70.94 69.28 66.64 64.31
Dank 2 x 63 63 22.95 18.01 12.93 8.96 7.75
Dil Abdusalam (DAS) 2 x 125 125 44.24 41.06 39.80 37.00 31.98
Dreez 2 x 125 125 41.49 39.20 37.00 32.44 29.68
Tx (1&2) 2 x 125 125 59.99 58.75
Duqm
Tx (3&4) 2 x 125 125 67.95 66.85
Tx (1&2) 2 x 125 125 51.42 49.18 46.00 46.25 30.38
Ghala Heights
Tx (3&4) 2 x 125 125 67.27 51.93 49.23 38.88 34.41
Tx (1&2) 2 x 125 125 47.60 22.71 18.50 12.92 8.13
Ghala
Tx (3&4) 2 x 125 125 72.62 69.80 66.73 67.08 63.62
Ibra 2 x 125 125 40.06 37.93 32.65 29.18 27.95

Page | 164
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.2: (continued) Available Capacity at Grid Stations (2020-2024) for Connection of New Demand
Available Capacity (MVA)
Total Transformer S ubstation Firm
Location
Capacity (MVA) Capacity (MVA) 2020 2021 2022 2023 2024

MIS Area
132/33 kV Transformers
63M VA 2 x 63 63 22.11 20.89 19.33 20.53 18.65
Ibri
Tx (1&2) 2 x 125 125 42.85 40.81 38.10 36.89 34.20
Izki 2 x 125 125 38.08 31.77 27.88 27.48 26.82
JBB Ali 2 x 125 125 -6.53 -36.05 -53.60 -59.85 33.00
JBB Hassan 2 x 125 125 47.52 37.30 30.38 27.29 25.43
Jahloot 2 x 125 125 80.72 78.46 76.28 73.62 71.23
Jebreen 2 x 125 125 55.40 53.87 49.40 48.03 46.67
Khaborah 2 x 125 125 26.18 26.40 22.65 16.32 11.94
Tx (1&2) 2 x 125 125 0.91 31.57 28.18 22.92 20.48
Khadra
Tx (3&4) 2 x 125 125 86.48 53.47 50.95 45.26 45.11
Tx (1&2) 2 x 125 125 93.66 91.65 89.74 72.72
Khoudh
Tx (3&4) 2 x 125 125 61.84 58.00 54.12 52.33
Tx (1&2) 2 x 125 125 65.78 62.06 65.68 62.05 58.43
Liwa
Tx (3&4) 2 x 125 125 54.63 47.86 44.60 41.59 38.42
M IS 2 x 125 125 75.69 74.16 72.75 69.58 69.48
Tx (1&2) 2 x 125 125 38.40 30.59 26.55 24.98 23.91
M SQ
Tx (3&4) 2 x 125 125 41.63 33.61 29.25 27.56 26.28
Tx (1&2) 2 x 125 125 3.80 26.78 16.33 9.81 7.73
M adinat Barka
Tx (3&4) 2 x 125 125 98.16 72.16 69.58 65.72 64.56
M adinat Nizwa 2 x 125 125 55.33 53.99 49.55 48.08 47.45
M adinat Shinas 2 x 125 125 57.13 46.93 42.18 38.46 32.44
M ahadha 2 x 30 30 4.80 11.72 11.56 11.15 11.04
M awalleh North 2 x 125 125 38.96 31.64 14.25 4.98 13.35
M awalleh Tx (1&2) 2 x 125 125 21.97 27.84 22.13 17.27 16.35
South Tx (3&4) 2 x 125 125 7.31 49.99 45.60 41.93 40.63
M isfah 2 x 125 125 54.36 50.67 46.85 42.77 39.16
M obella Tx (1&2) 2 x 125 125 62.03 55.68 51.87
Industrial Tx (3&4) 2 x 125 125 61.55 55.68 29.94
M obella 2 x 125 125 -6.75 -6.94 50.95 44.26 39.43
M udhaibi 2 x 125 125 75.31 72.96 65.50 63.77 62.68
M udhairib 2 x 125 125 65.40 57.17 53.73 51.31 49.66
Tx (1&2) 2 x 125 125 8.85 31.36 15.15 7.72 8.10
M uladah
Tx (3&4) 2 x 125 125 100.07 74.69 72.65 68.79 68.87
M uttrah 2 x 125 125 47.28 48.25 48.00 47.95 48.69
Nakhal 2 x 125 125 43.04 34.60 29.83 24.31 24.30

Page | 165
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.2: (continued) Available Capacity at Grid Stations (2020-2024) for Connection of New Demand
Available Capacity (MVA)
Total Transformer S ubstation Firm
Location
Capacity (MVA) Capacity (MVA) 2020 2021 2022 2023 2024

MIS Area
132/33 kV Transformers
New Ghubrah 2 x 125 125 10.22 7.95 3.40 1.31 -0.25
New Izki 2 x 125 125 103.45 102.60 101.58 100.69 99.99
Nizwa 2 x 125 125 31.30 20.66 4.00 3.32 3.61
Quriyat 2 x 125 125 68.99 67.17 65.85 63.56 61.87
Qurum 2 x 125 125 22.72 21.83 19.15 17.09 15.94

Rusail Tx (1&2) 2 x 125 125 68.55 63.55 58.85 54.41 52.28


Industrial Tx (3&4) 2 x 125 125 31.95 24.18 16.10 8.75 5.63
Rustaq Tx (1,2&3) 3x 125 250 69.18 122.01 116.43 106.39 110.46
SIA 2 x 125 125 42.16 36.78 34.40 33.66 31.63
Saham 2 x 125 125 32.33 30.52 30.68 29.72 23.91
Samad 2 x 63 63 36.55 35.51 34.66 34.01 33.41
Tx (1&2) 2 x 125 125 -14.20 17.79 13.80 5.84 6.12
Seeb M ain
Tx (3&4) 2 x 125 125 35.18 28.99 25.40 22.03 18.66
Shinas 2 x 125 125 57.25 54.02 41.13 36.70 27.74
Sinaw 2 x 125 125 88.14 86.05 84.45 83.24 82.06

Sohar Free Tx (1&2) 2 x 125 125 86.46 81.95 78.05 81.82 80.57
Zone Tx (3&4) 2 x 125 125 73.70 71.95 71.15 69.70 67.64
Tx (1&2) 2 x 125 125 66.27 62.31 53.13 30.15 24.09
Sohar
Tx (3&4) 2 x 125 125 2.27 5.65 22.55 16.84
Sumail Industrial 2 x 125 125 124.27 68.24 65.43 63.80 63.36

63M VA 2 x 63 63 6.64 4.81 2.46 1.75 2.16


Sumail
125M VA 2 x 125 125 7.25 61.09 57.25 55.73 55.55
Sur 2 x 125 125 25.73 23.50 19.75 17.72 14.74
Suwaiq 2 x 125 125 58.03 51.52 41.08 35.32 35.47
Tx (1&2) 2 x 125 125 70.32 67.37 66.35 63.84 61.61
Uwaynat
Tx (3&4) 2 x 125 125 61.17 57.56 57.23 52.61 50.01
Wadi Adai 2 x 125 125 35.96 35.28 33.18 31.26 30.27
Wadi Bani Auwf 2 x 125 125 72.18 69.80 65.82 66.66
Tx (1&2) 2 x 125 125 49.61 50.56 50.30 50.24 50.97
Wadi Kabair
Tx (3&4) 2 x 125 125 60.02 60.83 60.63 60.58 61.21
Wadi Sa'a 2 x 63 63 48.18 45.76 43.96 41.57 39.25
Yanqul 2 x 125 125 89.82 88.75 88.05 86.38
Yitti 2 x 125 125 106.77 106.34 106.08 105.59 105.22
132/11 kV Transformers
Daghmar 3 x 50 100 65.17 65.12 65.38 65.05 65.15

Page | 166
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.2: (continued) Available Capacity at Grid Stations (2020-2024) for Connection of New Demand
Available Capacity (MVA)
Total Transformer S ubstation Firm
Location
Capacity (MVA) Capacity (MVA) 2020 2021 2022 2023 2024

Dhofar Area
132/33 kV Transformers
Ashoor 2 x 125 125 46.51 61.09 60.01 60.19 59.23
Ittin 2 x 125 125 34.96 43.11 38.98 29.40 25.64
Tx (1&2) 2 x 125 125 59.66 38.59 29.99 16.13 12.63
Sa'adah
Tx (3&4) 2 x 125 125 80.51 53.99 31.41 15.67 12.17
Raysut 2 x 125 125 16.31 5.26 8.91 10.55 11.04
Salalah-IPP 2 x 125 125 83.32 51.87 17.64 11.48 7.30
Saih Al Khairat 2 x 125 125 69.86 67.26
Shaha'aon 2x 125 125 15.45 11.43 11.94 31.20 28.04
Al Qarm 2 x 63 63 23.73 25.07 21.87 31.17 30.37
M irbat 2 x 63 63 34.49 32.24 29.78
NPS 2 x 63 63 17.37 18.36 15.04 13.51 11.94
2 x 30 30 2.29
Thumrait
2 x 63 63 29.99 25.57 25.91 24.54

Page | 167
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.3: Overhead Line and Cable Circuit Loadings (%) at Peak Demand (2020-2024)
Circuit Circuit Loading at Max Demand (%)
Voltage No. of
Line Type Rating
(kV) Circuits 2020 2021 2022 2023 2024
(MVA)
MIS Area
Al Jefnen M isfah OHL 400 2 1774 11.02 4.02
Al Jefnen New Rustaq OHL 400 2 1774 17.42
Duqm M ahout OHL 400 2 1774 3.19 4.61
Duqm Suwaihat OHL 400 2 1774 5.67 5.79
Ibri M anah Solar OHL 400 2 1774 30.60
Ibri New Izki OHL 400 2 1774 17.31 21.00
Ibri IPP Nahadah(PDO) OHL 400 2 1774 33.22 15.54
Ibri New Rustaq OHL 400 2 1774 27.51
Jahloot Sur PS OHL 400 2 1774 35.78 29.18 31.84 31.54 30.13
M anah Solar New Izki OHL 400 2 1774 30.84 34.13 22.56
M anah Solar Nahadah(PDO) OHL 400 2 1774 29.77 14.48
M isfah New Izki OHL 400 2 1774 15.82 23.35 30.14 16.16
New Izki Qabel OHL 400 2 1774 7.44 7.27 8.01 8.48 11.11
Qabel Sur PS OHL 400 2 1774 2.72 9.89 14.36 15.73 18.47
SIS Sohar Free Zone OHL 400 2 1774 19.59 19.73 23.38 25.13 25.45
Sohar Free Zone Sohar-3 IPP3&4 OHL 400 2 1774 18.01 19.11 21.77 23.69 24.79
Sohar-1 IPP
Sohar Free Zone OHL 400 2 1774 13.67 14.22 15.86 17.44 18.09
1&2
Sohar Free Zone Sohar-3 IPP3&4 UGC 400 2 2273 14.00 14.87 16.95 18.44 19.30
Sohar Free Zone Sohar-3 IPP3&4 UGC 400 2 2273 14.27 15.10 17.13 18.69 19.53
Airport Heights M isfah OHL 220 2 673 4.99 20.25 22.55 36.76 15.46
Airport Heights M obella OHL 220 2 673 25.75 16.62 23.15 17.27 32.54
Al Filaj Barka PS 1&2 OHL 220 2 673 43.28 40.76 46.58 46.06 38.00
Al Filaj Barka PS 3&4 OHL 220 2 673 43.49 40.97 46.81 46.28 38.20
Al Filaj Barka PS 3&4 OHL 220 2 673 43.15 40.62 46.47 45.94 37.89
Al Filaj Blue City OHL 220 2 673 14.30 8.54 7.74 10.44 7.06
Al Filaj M obella OHL 220 2 673 56.78 43.10 54.13 50.49 51.63
Al Hamriyah Jahloot OHL 220 2 673 39.15 38.60 36.48 32.41 32.34
Barka-3 PS M isfah OHL 220 2 673 26.33 23.58 31.12 32.67 32.75
Blue City M IS OHL 220 2 673 24.76 14.37 15.05 18.68 16.47
Ibri IPP Ibri OHL 220 2 673 31.84 32.49 37.84 39.22 34.31

Ibri IPP Ibri Solar OHL 220 2 673 0.09 31.07 31.28 31.78

Ibri IPP M ahadha OHL 220 2 673 2.83 3.99 12.25 9.37 7.80

Page | 168
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.3: (continued) Overhead Line and Cable Circuit Loadings (%) at Peak Demand (2020-2024)
Circuit Circuit Loading at Max Demand (%)
Voltage No. of
Line Type Rating
(kV) Circuits
(MVA) 2020 2021 2022 2023 2024

MIS Area

Jahloot M isfah OHL 220 2 673 13.29 5.43 4.19 10.38 9.24

M IS SIS OHL 220 2 673 50.61

KIS M IS OHL 220 2 673 32.19 36.46 51.12 29.75

KIS SIS OHL 220 2 673 49.61 54.27 59.11 47.16

M SQ M isfah OHL 220 2 673 34.03 44.02 40.05 31.25 32.22

M ahadha SIS OHL 220 2 673 3.98 6.50 4.36 4.42 7.55

M ahadha Sohar Free Zone OHL 220 2 673 10.61 13.19 9.89 11.57 17.10

New Izki Nizwa OHL 220 2 673 21.50

SIS Sohar Free Zone OHL 220 2 673 16.80 16.03 28.32 29.36 25.19

SIS Sohar-1 PS OHL 220 2 673 23.42 22.12 8.20 6.74 5.12
Sohar Free Zone Sohar-2 PS OHL 220 2 673 23.37 25.32 31.61 31.50 33.35

Sur PS Sur OHL 220 2 673 18.77 19.37 30.72 31.78 31.01

Al Filaj Barka PS 3&4 UGC 220 2 625 46.75 44.03 50.32 49.75 41.06

Al Filaj Blue City UGC 220 2 475 23.73 17.31 16.34 20.10 15.35

Barka-3 PS M isfah UGC 220 2 625 27.38 24.80 32.54 34.24 34.48

Blue City M IS UGC 220 2 475 34.22 18.75 19.93 25.17 22.20

M ahadha Sohar Free Zone UGC 220 2 500 20.64 25.63 18.98 22.53 33.42

New Izki Nizwa UGC 220 2 625 22.21

Nizwa New Izki UGC 220 2 625 23.61

SIA Sohar-1 PS UGC 220 3 625 11.93 12.56 14.55 14.77 14.84

SIS Sohar Free Zone UGC 220 2 625 17.89 17.16 30.27 31.38 26.91

SIS Sohar-1 PS UGC 220 2 625 25.05 23.75 7.86 6.31 4.58

Sohar Free Zone Sohar-2 PS UGC 220 2 625 25.18 27.30 34.18 33.98 35.97

Sohar Free Zone Sohar-2 PS UGC 220 2 625 25.17 27.25 33.97 33.89 35.89

Adam M anah OHL 132 2 293 9.94 10.06 10.84 11.14 11.37

Al Falaj Wadi Adai OHL 132 2 293 2.92 3.00 10.05 10.49 9.67

Al Filaj Barka M ain OHL 132 2 293 20.01 27.79 30.12 27.34 46.13

Al Filaj M adinat Barka OHL 132 2 293 48.96 32.01 27.56 33.75 0.27

Al Filaj Nakhal OHL 132 2 293 13.92 15.85 23.64 26.96 10.20

Page | 169
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.3: (continued) Overhead Line and Cable Circuit Loadings (%) at Peak Demand (2020-2024)
Circuit Circuit Loading at Max Demand (%)
Voltage No. of
Line Type Rating
(kV) Circuits
(MVA) 2020 2021 2022 2023 2024

MIS Area

Al Hamriyah M uttrah OHL 132 2 293 22.83 22.73 18.25 18.04 18.32

Al Hamriyah Qurum OHL 132 2 293 17.08 16.59 28.20 21.68 18.63

Al Hamriyah Wadi Adai OHL 132 2 146 39.80 39.10 20.17 19.15 21.69

Al Hamriyah Wadi Kabair OHL 132 2 146 50.79 50.43 45.65 45.39 45.53

Al Hayl Dank OHL 132 2 293 7.33

Al Hayl Yanqul OHL 132 2 293 1.38 1.38 1.39 1.46

Al Jawabi JBB Ali OHL 132 2 293 12.21

Al Jawabi JBB Ali Wind Farm OHL 132 2 293 3.38

Al Jefnen M obella OHL 132 2 293

Al Jefnen Sumail Industrial OHL 132 2 293 17.66 21.59

Al Kamil Bedyah OHL 132 2 293 12.30 10.74 14.92 14.66 13.96

Al Kamil JBB Ali OHL 132 2 293 22.47 27.52 30.51 31.58 27.77

Al Kamil JBB Hassan OHL 132 2 293 2.31 4.41 17.50 18.60 16.28

Amerat Jahloot OHL 132 2 293 49.91 46.91 49.90 44.00 42.82

Amerat M SQ OHL 132 2 293 23.04 18.75 17.94 9.51 6.55

Ayjah Sur OHL 132 2 293 13.07 13.38 16.28 16.57 16.84

Bahla Nizwa OHL 132 2 146 28.60 29.40 31.61 32.62 32.99

Barka M ain M obella OHL 132 2 293 5.06 15.53

Barka M ain M obella Industrial OHL 132 2 293 16.66 15.99 34.25
Bedyah M udhairib OHL 132 2 293 4.86 4.80 23.44 23.55 22.88
Birkat Al M ouz Izki OHL 132 2 293 24.13 12.34 16.34 15.58 9.84

Birkat Al M ouz Nizwa OHL 132 2 293 16.88 6.24 14.44 8.90 5.47

Bousher M SQ OHL 132 1 293 42.59 50.25 70.23 38.39 37.35


Bureimi
M ahadha OHL 132 2 293 18.57 20.51 20.38 21.41 12.86
Industrial
Bureimi Bureimi Industrial OHL 132 2 293 3.09 3.04 3.14 3.27 6.01
M ahadha(Wooden
Bureimi OHL 132 1 89 33.72 37.20 36.98 38.85 23.76
Pole)
Daghmar Quriyat OHL 132 2 293 5.95 5.96 5.91 5.97 5.95

Dank Ibri OHL 132 2 293 5.47 6.32 6.70 7.95 10.43

Dank Wadi Sa'a OHL 132 2 89 32.89 44.69 31.49 31.02 54.36

Page | 170
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.3: (continued) Overhead Line and Cable Circuit Loadings (%) at Peak Demand (2020-2024)
Circuit Circuit Loading at Max Demand (%)
Voltage No. of
Line Type Rating
(kV) Circuits
(MVA) 2020 2021 2022 2023 2024

MIS Area

Dank Yanqul OHL 132 2 293 7.20 7.32 7.44 7.90

Dil Abdusalam Khaborah OHL 132 2 293 23.24

Dil Abdusalam KIS OHL 132 2 293 19.63 21.45 16.86 12.18

Dil Abdusalam Saham OHL 132 2 293 36.76 29.85 35.12 31.37 26.11

Dreez Ibri OHL 132 2 293 14.15 14.54 15.04 15.51 16.15
Duqm Wind
Duqm OHL 132 2 293 11.60
Farm
Ibra Qabel OHL 132 2 293 14.51 14.80 15.78 16.37 16.48

Ibri Jebreen OHL 132 2 293 31.37 33.85 43.90 42.17 33.99

Izki New Izki OHL 132 2 293 65.59 45.72 59.00 44.76 35.46

Izki Sumail OHL 132 2 293 33.14 20.23 35.86 14.78 10.55

JBB Hassan Sur OHL 132 2 293 11.92 13.68 33.16 34.83 32.60

Jahloot Quriyat OHL 132 2 293 15.43 15.75 15.93 16.38 16.65

Jahloot Yitti OHL 132 2 403 2.26 2.31 2.33 2.40 2.45

Jebreen Nizwa OHL 132 2 293 19.86 22.70 32.08 29.96 22.65

KIS Khaborah OHL 132 2 293 54.27 60.93 35.76 49.77

Khaborah Khadra OHL 132 2 293 6.58 38.04 43.96 17.44 30.90

Khadra Suwaiq OHL 132 2 293 21.20 14.93 18.42 13.62 8.03

Khoudh M awalleh South OHL 132 2 250 8.57 13.29 9.41 27.73

Khoudh Rusail Industrial OHL 132 2 250 27.33 7.39 30.59 52.31

Liwa Shinas OHL 132 2 293 11.60 12.81 14.04 15.07 16.59

Liwa Sohar Free Zone OHL 132 2 293 33.94 37.02 37.41 39.93 43.11

M IS M uladah OHL 132 2 293 30.77 50.60 56.94 52.87 18.55

M IS Suwaiq OHL 132 2 293 32.47 13.40 13.23 28.79 18.35


M SQ New Ghubrah OHL 132 3 293 32.64 38.12 52.40 29.81 29.09

M SQ Qurum OHL 132 2 293 1.91 1.48 10.28 3.58 0.23

Page | 171
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.3: (continued) Overhead Line and Cable Circuit Loadings (%) at Peak Demand (2020-2024)
Circuit Circuit Loading at Max Demand (%)
Voltage No. of
Line Type Rating
(kV) Circuits
(MVA) 2020 2021 2022 2023 2024

MIS Area

M SQ Wadi Adai OHL 132 2 293 3.93 2.07 31.36 17.68 21.09

M adinat Barka M uladah OHL 132 2 293 23.99 13.35 12.37 10.92 11.10
Waste to Energy
M adinat Barka OHL 132 2 293 19.95
Plant
M adinat Nizwa Nizwa OHL 132 2 293 11.90 12.13 12.89 13.14 13.19

M adinat Shinas Shinas OHL 132 2 293 11.55 13.34 13.78 14.71 15.81

M ahadha Wadi Al Jazzi OHL 132 2 178 13.88 13.82 19.82 18.17 9.35

M ahadha Wadi Sa'a OHL 132 2 293 12.33 16.27 12.23 12.72 20.02

M anah Nizwa OHL 132 2 293 20.22 37.68 36.75 34.69 17.99

M awalleh South-A Rusail Industrial OHL 132 2 250

M isfah Rusail OHL 132 2 293 11.86 12.70

M isfah Wadi Adai OHL 132 2 293 0.79 0.80 46.90 34.39 36.34

M obella M obella Industrial OHL 132 2 293 12.48 11.48 8.70

M obella Rusail OHL 132 2 293

M udhaibi M udhairib OHL 132 2 293 21.94 1.44 19.53 16.21 1.46

M udhaibi Samad OHL 132 2 293 4.52 4.70 4.84 4.95 5.03

M udhaibi Sinaw OHL 132 2 293 10.94 12.93 7.74 6.80 14.95

M udhairib Qabel OHL 132 2 293 27.82 11.82 52.19 49.05 34.98

M uladah Rustaq OHL 132 2 293 31.04 27.28 24.61 24.45

M uladah New Rustaq OHL 132 2 293 21.49

M uttrah Wadi Kabair OHL 132 1 293 4.11 3.87 1.54 2.06 0.91

Nakhal Wadi Bani Auwf OHL 132 2 293 7.75 8.71 10.78 12.41

New Izki Sinaw OHL 132 2 293 7.77 19.36 7.43 9.92 21.99

New Rustaq Rustaq OHL 132 2 293 11.99

Rustaq Wadi Bani Auwf OHL 132 2 293 8.49 4.99 4.28

New Rustaq Wadi Bani Auwf OHL 132 2 293 21.15

SIS Saham OHL 132 2 293 52.20 44.15 50.62 47.23 42.70

SIS Uwaynat OHL 132 2 293 27.55 29.57 26.35 29.55 37.88

Page | 172
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.3: (continued) Overhead Line and Cable Circuit Loadings (%) at Peak Demand (2020-2024)
Circuit Circuit Loading at Max Demand (%)
Voltage No. of
Line Type Rating
(kV) Circuits 2020 2021 2022 2023 2024
(MVA)

MIS Area

Shinas Sohar Free Zone OHL 132 2 585 5.65 6.21 6.67 7.14 7.82

Sohar Free Zone Wadi Al Jazzi OHL 132 2 293 13.95 15.22 14.74 15.44 17.33

Sohar Uwaynat OHL 132 2 293 8.18 8.71 6.52 7.71 15.06

Sohar Wadi Al Jazzi OHL 132 2 293 22.60 23.81 26.80 26.57 21.98

Sumail Industrial Rusail OHL 132 2 293 14.18 11.01 11.38

Sumail Industrial Sumail OHL 132 2 293 16.84 6.79 17.77 7.87 11.90

A'salam M obella UGC 132 2 375 41.84 42.95 39.27 42.96 27.45

A'salam Seeb M ain UGC 132 2 375 18.56 14.30 14.83 15.89 4.18

Airport Heights M awaleh South UGC 132 2 375 5.34 12.81 42.92 13.48 5.13

Airport Heights Ghala UGC 132 2 375 23.72 21.00 2.20

Airport Heights Ghala UGC 132 3 375 28.18 31.41

Airport Heights M awalleh North UGC 132 2 375 11.38 12.45 14.77 16.00 14.89

Al Falaj M uttrah UGC 132 1 300 24.08 24.72 11.13 10.19 12.86

Al Hamriyah M uttrah UGC 132 2 375 18.29 18.31 14.81 14.60 14.96

Al Hamriyah Wadi Kabair UGC 132 2 172 43.56 43.28 39.19 38.96 39.11

Al Jefnen Rusail Industrial UGC 132 2 375 18.19 40.36

Bousher Ghala Heights UGC 132 2 375 9.81 18.75 41.30 4.04 3.98

Bousher M SQ UGC 132 1 375 33.68 39.60 55.28 30.50 29.57

Bousher New Ghubrah UGC 132 3 375 14.16 18.20 29.01 11.37 10.49
Bureimi Industrial Bureimi UGC 132 2 375 3.32 3.39 3.45 3.64 5.49

Ghala Ghala Heights UGC 132 2 375 7.68 3.96 21.97 20.81 24.70

Izki New Izki UGC 132 2 375 51.08 35.57 45.91 34.75 27.52

Khoudh M awalleh South UGC 132 2 375 5.87 8.88 6.44 18.61

M SQ New Ghubrah UGC 132 3 375 26.07 30.26 41.51 24.01 23.28

M awalleh South Rusail Industrial UGC 132 2 375 39.39 17.11 3.75 19.05 34.25

M awalleh South Seeb M ain UGC 132 2 375 11.75 12.80 13.28 13.73 28.56

M uttrah Wadi Kabair UGC 132 1 300 4.38 3.84 2.47 2.99 1.44

M uttrah Wadi Kabair UGC 132 1 300 4.01 3.82 1.48 1.99 0.95

New Izki Sinaw UGC 132 2 375 5.23 14.89 4.84 6.92 16.91

Page | 173
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.3: (continued) Overhead Line and Cable Circuit Loadings (%) at Peak Demand (2020-2024)

Circuit Circuit Loading at Max Demand (%)


Voltage No. of
Line Type Rating
(kV) Circuits 2020 2021 2022 2023 2024
(MVA)
MIS Area
New Rusail Sumail Industrial UGC 132 2 375 11.94 9.23 9.67 13.92 17.05

Rusail Rusail Industrial UGC 132 2 375 28.95 27.87 14.41


Sumail Sumail UGC 132 2 375 12.73 4.88 13.67 6.10 9.18
Industrial
Sur-2 Sur-1 UGC 132 2 343 24.12 25.85 43.26 44.98 43.36
Dhofar Area
Al Qarm Ittin OHL 132 2 359 9.86 11.44 10.42 12.05 11.35

Ashoor Al-Qarm OHL 132 2 359 14.43 16.21 15.48 16.01 15.39

Ashoor M irbat OHL 132 2 359 3.74 4.47 4.78 5.16

Ashoor S'aadah (Portion-1) OHL 132 2 330 17.68 21.51 22.22 22.03 21.66

Ashoor S'aadah (Portion-2) OHL 132 2 330 17.53 21.64 22.32 22.20 21.83

Harwail Wind Farm(Portion-1) OHL 132 1 183 0.55 0.55 0.55 0.55 0.56

Harwail Wind Farm(Portion-2) OHL 132 1 359 0.36 0.36 0.36 0.36 0.36

Ittin Thumrait OHL 132 2 183 2.03 3.16 4.41 17.91 18.59

NPS Salalah Free Zone OHL 132 2 359 5.93 5.81 3.78 12.58 17.69
Salalah Free
Ittin OHL 132 2 359 7.04 2.86 5.63 10.46 12.04
Zone
Salalah Free
Shaha'aon OHL 132 2 359 13.22 15.40 19.09 20.27 22.01
Zone
Shaha'aon S'aadah OHL 132 2 330 1.83 0.91 4.71 8.88 10.30

Thumrait Saih Al Khairat OHL 132 2 293 8.93 9.25

Thumrait Wind Farm (Portion-1) OHL 132 1 359 5.08 5.13 5.00 5.15 5.26

Thumrait Wind Farm (Portion-2) OHL 132 1 183 10.51 10.71 10.21 10.76 11.13

Ashoor Al-Qarm UGC 132 2 279 18.60 20.78 19.85 20.51 19.72

Ashoor S'aadah (Portion-1) UGC 132 2 279 20.97 25.65 26.47 26.30 25.86

Ashoor S'aadah (Portion-2) UGC 132 2 300 19.31 24.60 25.24 25.41 24.98

NPS Salalah Free Zone UGC 132 2 279 7.62 7.45 4.85 16.17 22.74

Shaha'aon S'aadah UGC 132 2 300 1.91 3.01 7.44 11.16 12.78

Page | 174
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.4: Transmission System Voltage Profile at Peak Demand (2020-2024)


Busbar Voltage at Maximum Demand (per unit)
Location
2020 2021 2022 2023 2024
MIS Area
400 kV Busbars
Al Jefnen 0.96 1.01
Duqm 1.01 1.01
Ibri IPP 1.04 1.03 1.05 1.05 1.04
Jahloot 0.98 0.99 0.97 0.97 0.98
M ahout 1.02 1.02
M anah Solar 0.99 0.99 1.02
M isfah 0.99 1.03 0.96 0.96 1.01
New Izki 1.04 1.03 0.99 0.99 1.02
New Rustaq 1.02
Nahadah(PDO) 1.01 1.04
Qabel 1.04 1.04 1.00 1.00 1.03
SIS 1.04 1.03 1.04 1.03 1.03
Sohar Free Zone 1.05 1.04 1.05 1.04 1.04
Sohar-3 IPP 1.05 1.04 1.05 1.05 1.04
Sur 1.04 1.05 1.030 1.03 1.04
Suwaihat(PDO) 1.01 1.02
220 kV Busbars
Airport Height 1.00 1.02 1.00 1.00 1.00
Al Filaj 1.02 1.04 1.02 1.01 1.01
Al Hamriyah 0.98 1.00 0.99 1.00 1.00
Al Oha (UAE) 1.04 1.04 1.06 1.05 1.05
Barka PS 1.03 1.05 1.03 1.02 1.02
Barka-3 PS 1.05 1.05 1.07 1.06 1.05
Blue City 1.00 1.02 1.01 0.99 1.00
Ibri 1.02 1.02 1.06 1.05 1.03
Ibri IPP 1.04 1.04 1.08 1.07 1.05
Ibri Solar 1.04 1.08 1.07 1.05
Jahloot 1.01 1.03 1.02 1.02 1.03
KIS 0.99 1.00 0.98 0.99
M IS 0.98 1.00 0.99 0.96 0.98
M SQ 0.98 0.99 0.99 0.99 0.98
M ahadha 1.04 1.04 1.06 1.05 1.05
M isfah 1.00 1.02 1.01 1.01 1.00
M obella 1.01 1.03 1.01 1.00 1.01
New Izki 1.03 1.03 1.03 1.04 1.05

Page | 175
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.4: (continued) Transmission System Voltage Profile at Peak Demand (2020-2024)
Busbar Voltage at Maximum Demand (per unit)
Location
2020 2021 2022 2023 2024
MIS Area
220 kV Busbars
Nizwa 1.02
SIA 1.05 1.05 1.06 1.05 1.05
SIS 1.04 1.04 1.05 1.04 1.04
Sohar Free Zone 1.05 1.05 1.06 1.05 1.05
Sohar-1 PS 1.05 1.05 1.06 1.05 1.05
Sohar-2 PS 1.05 1.05 1.07 1.06 1.05
Sur 1.01 1.04 1.01 1.02 1.03
Sur PS 1.02 1.04 1.02 1.03 1.04
132 kV Busbars
A'salam 1.01 1.02 1.02 0.99 1.00
Adam 0.97 1.01 0.98 1.01 1.01
Airport Height 1.03 1.01 1.02 1.02 0.99
Al Falaj 0.99 1.00 1.00 1.00 1.00
Al Filaj 1.02 1.03 1.02 1.00 1.02
Al Hamriyah 0.99 1.00 1.00 1.00 1.01
Al Hayl 1.02 1.02 1.03 1.04 1.02
Al Jawabi 0.96
Al Jefnen 1.01 1.04
Al Kamil 1.03 1.04 0.98 0.98 1.01
Amerat 0.99 1.00 1.00 0.99 1.00
Ayjah 1.02 1.03 1.01 1.02 1.03
Bahla 0.97 0.99 0.96 0.98 1.01
Barka M ain 1.02 1.03 1.02 1.00 1.01
Bedyah 1.02 1.04 1.00 1.00 1.03
Birkat Al M ouz 0.99 1.01 0.99 1.01 1.03
Bousher 0.98 0.99 0.99 0.99 1.00
Bureimi 1.03 1.02 1.06 1.04 1.01
Bureimi Industrial 1.03 1.03 1.06 1.04 1.01
Daghmar 1.00 1.00 1.01 1.00 1.00
Dank 1.03 1.03 1.04 1.05 1.02
Dil Abdusalam (DAS) 0.98 1.01 1.03 1.01 1.02
Dreez 1.03 1.03 1.03 1.05 1.04
Duqm 1.01 1.01
Duqm Wind Farm 1.01
Ghala 1.03 1.01 0.98 1.02 0.99
Ghala Heights 0.99 0.98 1.01 0.99
132kV Ghala Heights BB-1 0.98
132kV Ghala Heights BB-2 1.03
Ibra 1.02 1.04 1.01 1.01 1.04
Ibri 1.04 1.04 1.04 1.06 1.05

Page | 176
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.4: (continued) Transmission System Voltage Profile at Peak Demand (2020-2024)
Busbar Voltage at Maximum Demand (per unit)
Location
2020 2021 2022 2023 2024
MIS Area
132 kV Busbars
Izki 1.01 1.02 1.00 1.02 1.04
JBB Ali 1.00 1.00 0.94 0.94 0.97
JBB Ali Wind Farm 0.96
JBB Hassan 1.02 1.03 0.99 0.99 1.01
Jahloot 1.02 1.02 1.02 1.02 1.02
Jebreen 0.99 1.00 0.98 1.01 1.03
KIS 1.02 1.03 1.01 1.02
Khaborah 0.96 1.00 1.01 1.00 1.00
Khadra 0.99 1.00 0.99
Khadra-1 0.98 0.98
Khadra-2 0.96 0.96
Khoudh 1.03 1.01 1.00 1.04
Liwa 1.04 1.03 1.07 1.06 1.03
M IS 0.99 1.00 1.00 0.97 1.00
M SQ-1 0.99 1.00 0.99 0.99 1.00
M SQ-2 0.99 1.00 0.99 0.99 1.00
M adinat Barka 1.01 1.02 1.01 0.98 0.99
M adinat Nizwa 0.98 1.00 0.98 1.00 1.03
M adinat Shinas 1.03 1.02 1.06 1.04 1.01
M ahadha 1.04 1.04 1.07 1.06 1.02
M anah 0.98 1.02 1.00 1.02 1.03
M awalleh North 1.03 1.01 1.01 1.02 0.99
M awalleh South-1 1.04 1.03 1.01 1.00 1.04
M awalleh South-2 1.04 1.01 1.01 1.02 1.04
M isfah 1.04 1.02 1.03 1.02 1.03
M obella 1.02 1.02 1.02 1.00 1.00
M obella Industrial 1.02 0.99 1.00
M udhaibi 1.02 1.01 1.01 1.02 1.03
M udhairib 1.02 1.04 1.01 1.02 1.04
M uladah 1.00 1.00 0.97 1.00
M uladah-1 0.99
M uladah-2 0.98
M uttrah 0.99 1.00 1.00 1.00 1.01
Nakhal 1.01 1.03 1.01 0.98 1.01
New Ghubrah 0.98 0.99 0.99 0.99 1.00
New Izki 1.04 1.04 1.03 1.04 1.06
New Rustaq 1.01
Nahadah(PDO) 0.99 1.01 0.99 0.98 1.03
Nizwa 0.98 1.00 0.98 1.00 1.03

Page | 177
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.4: (continued) Transmission System Voltage Profile at Peak Demand (2020-2024)
Busbar Voltage at Maximum Demand (per unit)
Location
2020 2021 2022 2023 2024
MIS Area
132 kV Busbars
Qabel 1.03 1.05 1.02 1.02 1.05
Quriyat 1.00 1.00 1.01 1.00 1.00
Qurum 0.99 1.00 0.99 0.99 1.00
Rusail 1.05 1.03 1.01
Rusail Industrial 1.05 1.03 1.01 1.00 1.04
Rustaq 0.96 0.99 0.98 0.95 1.01
SIA 1.01 1.04 1.02 1.02 1.00
SIS 1.04 1.02 1.07 1.05 1.04
Saham 1.01 1.01 1.05 1.03 1.03
Samad 1.02 1.01 1.00 1.01 1.03
Seeb M ain 1.03
Seeb M ain-1 1.04 1.00 1.01 1.02
Seeb M ain-2 1.01 1.02 1.02 0.99
Shinas 1.04 1.03 1.07 1.05 1.02
Sinaw 1.02 1.02 1.01 1.02 1.04
Sohar 1.02 1.00 1.05 1.03 1.01
Sohar Free Zone 1.04 1.04 1.07 1.06 1.03
Sohar Refinery 1.01 1.04 1.02 1.02 1.00
Sumail 1.01 1.01 0.99 0.99 1.02
Sumail Industrial 1.02 1.01 0.99 1.00 1.03
Sur 1.03 1.04 1.03 1.04 1.05
Sur-2 1.03 1.04 1.03 1.04 1.05
Suwaiq 0.99 1.00 1.00 0.97 1.00
Suwaihat(PDO) 1.02 1.00
Uwaynat 1.03 1.01 1.06 1.04 1.02
Wadi Adai 0.99 1.00 1.00 1.00 1.00
Wadi Al Jazzi 1.04 1.02 1.07 1.05 1.02
Wadi Bani Auwf 0.99 0.99 0.96 1.00
Wadi Kabair 0.99 1.00 1.00 1.00 1.01
Wadi Sa'a 1.04 1.04 1.07 1.06 1.02
Waste to Energy Plant 1.00
Yanqul 1.02 1.03 1.04 1.02
Yitti 1.02 1.02 1.02 1.01 1.02
33 kV Busbars
Tx (1&2) 1.00 1.00 1.00 1.00 1.00
A'salam
Tx (3&4) 1.00 1.00 1.00 1.01 1.00
Adam 1.00 1.00 1.00 1.00 1.00

Page | 178
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.4: (continued) Transmission System Voltage Profile at Peak Demand (2020-2024)
Busbar Voltage at Maximum Demand (per unit)
Location
2020 2021 2022 2023 2024
MIS Area
33 kV Busbars
Tx (1&2) 1.00 1.00 1.00 1.00 1.00
Airport Height
Tx (3&4) 1.00 1.00 1.00 1.00 0.99
Al Falaj 1.00 1.01 1.00 1.00 1.00
Al Hayl 1.00 1.00 1.00 1.00 1.00
Al Jawabi 1.00
Tx (1&2) 1.00 1.00 1.00 0.99 1.00
Amerat
Tx (3&4) 1.00 1.00 1.00 0.99 1.00
Ayjah 1.00 1.00 1.00 1.00 1.01
Bahla 1.00 1.00 1.00 0.99 1.00
Tx 3 1.00 1.01
Barka M ain
Tx (1&2) 1.00 1.00 1.00 1.00 0.99
Barka-3 PS 1.00 1.01 1.00 1.00 1.00
Bedyah 1.00 1.00 1.00 1.00 1.00
Birkat Al M ouz 0.99 0.99 1.00 1.00 1.00
Blue City 1.00 1.01 1.00 1.00 1.00
Tx (1&2) 1.00 1.00 1.00 1.00 1.00
Bousher
Tx (3&4) 0.99 1.00 1.00 0.99 1.00
Bureimi 1.00 1.01 1.01 1.00 1.00
Tx (1&2) 1.01 1.00 1.00 1.01 1.00
Bureimi Industrial
Tx (3&4) 1.01 1.01 1.00 1.00 1.01
Dank 1.00 1.00 1.00 1.00 1.00
Dil Abdusalam(DAS) 0.99 1.00 1.00 1.00 1.00
Dreez 1.00 1.00 1.00 1.00 1.00
Tx (1&2) 1.00 1.00
Duqm
Tx (3&4) 0.99 1.00
Tx (1&2) 1.00 1.00 1.00 1.01 1.00
Ghala Heights
Tx (3&4) 1.00 1.00 1.00 1.00 1.00
Tx (1&2) 1.00 1.00 1.00 1.00 0.99
Ghala
Tx (3&4) 1.00 1.00 1.00 1.00 1.00
Ibra 1.00 1.00 1.00 1.00 1.00
125M VA 1.00 1.00 1.00 1.01 1.01
Ibri
63M VA 1.00 1.00 1.00 1.01 0.99

Page | 179
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.4: (continued) Transmission System Voltage Profile at Peak Demand (2020-2024)
Busbar Voltage at Maximum Demand (per unit)
Location
2020 2021 2022 2023 2024
MIS Area
33 kV Busbars
Izki 1.00 1.00 1.00 0.99 1.00
JBB Ali 1.00 0.99 1.00 0.99 1.00
JBB Hassan 1.00 1.00 1.00 1.00 1.00
Jahloot 1.01 1.00 1.00 1.00 1.00
Jebreen 0.99 1.00 1.00 1.00 1.00
Khaborah 1.01 0.99 1.00 1.00 1.01
Tx (1&2) 1.00 1.00 0.99 0.99 1.00
Khadra
Tx (3&4) 0.99 1.00 1.00 1.00 1.00
Tx (1&2) 1.01 1.00 1.01 1.00
Khoudh
Tx (3&4) 1.00 1.00 1.00 1.01
Tx (1&2) 1.00 1.00 1.01 1.00 1.00
Liwa
Tx (3&4) 1.01 1.00 1.00 1.01 1.00
M IS 1.00 0.99 1.00 1.00 1.00
Tx (1&2) 1.00 0.99 1.00 1.00 0.99
M SQ
Tx (3&4) 1.00 1.00 1.00 1.00 1.00
Tx (1&2) 1.00 0.99 1.00 0.99 0.99
M adinat Barka
Tx (3&4) 1.00 1.01 1.00 1.00 0.99
M adinat Nizwa 0.99 0.99 0.99 1.00 0.99
M adinat Shinas 1.00 1.00 1.00 1.01 1.00
M ahadha 1.01 0.99 0.99 0.99 1.01
M ahout 1.00 1.00
M awalleh North 1.00 1.00 1.00 1.00 1.00
Tx (1&2) 1.00 1.00 0.99 1.00 1.01
M awalleh South
Tx (3&4) 1.00 1.01 1.00 1.01 1.00
M isfah 1.00 1.01 1.00 1.00 1.01
M obella 1.00 1.00 1.00 1.00 1.01
Tx (1&2) 1.01 1.00 1.01
M obella Industrial
Tx (3&4) 1.00 1.00 1.00
M udhaibi 1.01 1.00 1.00 1.00 1.00
M udhairib 1.00 1.00 1.00 1.00 1.00
Tx (1&2) 1.00 1.00 1.00 1.00 0.99
M uladah
Tx (3&4) 1.00 1.00 0.99 1.00 0.99
M uttrah 1.00 1.00 1.00 1.00 1.00
Nakhal 1.01 1.00 1.00 1.00 1.00
New Ghubrah 1.00 1.00 1.00 0.99 1.00

Page | 180
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.4: (continued) Transmission System Voltage Profile at Peak Demand (2020-2024)
Busbar Voltage at Maximum Demand (per unit)
Location
2020 2021 2022 2023 2024
MIS Area
33 kV Busbars
New Izki 1.01 1.01 1.00 1.00 1.01
Nizwa 0.99 1.00 1.00 0.99 1.00
Quriyat 1.00 1.00 1.00 1.00 1.00
Qurum 1.01 1.01 1.00 1.00 1.00
Tx (1&2) 1.01 1.00 1.00 1.00 1.01
Rusail Industrial
Tx (3&4) 1.00 1.00 1.00 1.00 1.01
Rustaq-A 1.00 1.01 1.00 1.00 1.00
Rustaq-B 0.99 1.00 1.00 1.00 1.01
SIA 1.00 1.01 1.00 1.01 1.00
Saham 0.99 1.00 1.00 1.00 1.00
Samad 1.00 1.01 1.00 1.01 1.00
Tx (1&2) 1.00 1.00 1.00 1.00 1.00
Seeb M ain
Tx (3&4) 1.00 1.00 1.00 1.00 0.99
Shinas 1.01 1.00 1.00 1.00 1.00
Sinaw 1.00 1.00 1.00 1.00 1.00
Tx (1&2) 1.00 1.00 1.01 1.00 1.00
Sohar Free Zone
Tx (3&4) 1.01 1.00 1.00 1.00 1.00
Tx (1&2) 1.00 1.00 1.00 1.00 1.00
Sohar
Tx (3&4) 1.00 0.99 0.99 1.01 1.00
Sumail Industrial 1.00 1.00 1.00 0.99 1.00
125M VA 1.00 1.00 1.00 1.00 1.00
Sumail
63M VA 0.99 1.00 0.99 1.00 0.99
Sur 1.00 1.00 1.00 1.01 1.01
Suwaiq 0.99 1.00 1.00 0.99 1.00
Tx (1&2) 1.00 1.00 1.00 1.00 1.00
Uwaynat
Tx (3&4) 1.00 1.00 1.00 1.00 1.00
Wadi Adai 1.00 1.00 1.00 0.99 1.00
Wadi Bani Auwf 1.00 1.00 0.99 1.00
Tx (1&2) 1.00 1.00 1.00 1.00 1.00
Wadi Kabair
Tx (3&4) 0.99 0.99 1.00 1.00 1.00
Wadi Sa'a 1.00 1.01 1.00 1.00 1.00
Yanqul 1.00 1.00 1.01 1.01
Yitti 1.00 1.00 1.00 1.00 1.00
11 kV Busbars
Daghmar 1.00 0.99 1.00 0.99 1.00

Page | 181
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.4: (continued) Transmission System Voltage Profile at Peak Demand (2020-2024)
Busbar Voltage at Maximum Demand (per unit)
Location
2020 2021 2022 2023 2024
Dhofar Area
132 kV Busbars
Al Qarm 1.00 1.01 1.01 1.02 1.03
Ashoor 1.00 1.02 1.02 1.03 1.03
Ittin 1.00 1.01 1.01 1.02 1.02
M irbat 1.02 1.01 1.03 1.03
NPS 1.01 1.01 1.02 1.03 1.03
Raysut 1.01 1.01 1.02 1.03 1.03
Saih Al Khairat 0.99 0.99
Salalah IPP 1.01 1.01 1.02 1.03 1.03
Shaha'aon 1.01 1.00 1.01 1.02 1.02
S’aadah 1.01 1.00 1.00 1.01 1.02
Thumrait 1.00 1.01 1.01 1.00 1.01
Wind Farm 1.02 1.02 1.02 1.02 1.02
33 kV Busbars
Al Qarm 1.01 1.01 1.01 1.00 1.00
Ashoor 1.01 1.00 1.00 1.00 1.01
Ittin 1.00 1.01 1.00 1.00 1.01
M irbat 1.00 1.00 1.00 1.01
NPS 1.00 1.00 1.00 1.00 1.01
Raysut 1.00 0.99 1.00 1.00 1.00
Tx (1&2) 0.99 0.99 0.99 1.00 1.00
S’aadah
Tx (3&4) 1.00 1.00 0.99 1.00 1.00
Saih Al Khairat 1.01 1.00
Salalah IPP 1.00 1.00 1.00 1.00 1.00
Shaha'aon 1.00 1.01 1.00 1.00 1.01
Thumrait 1.00 1.00 1.00 1.01 1.00

Page | 182
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.5: Transmission System Voltage Profile at Minimum Demand (2020-2024)


Busbar Voltage at Minimum Demand (per unit)
Location
2020 2021 2022 2023 2024
MIS Area
400 kV Busbars
Al Jefnen 1.03
Duqm 1.00
Ibri IPP 1.01 1.01 1.00 1.00 1.01
Jahloot 1.00 1.02 1.01 1.01 1.02
Mahout 1.01
Manah Solar 1.01 1.02
Misfah 1.02 1.02 1.01 1.01 1.03
New Izki 1.00 1.02 1.01 1.01 1.02
Nahadah(PDO) 1.01 1.03
Qabel 1.01 1.02 1.01 1.01 1.03
SIS 1.00 1.02 1.02 1.02 1.01
Sohar Free Zone 1.00 1.03 1.02 1.03 1.01
Sohar-3 IPP 1.00 1.03 1.02 1.03 1.01
Sur PS 1.01 1.02 1.01 1.01 1.02
Suwaihat(PDO) 1.01
220 kV Busbars
Airport Height 1.01 1.02 1.02 1.01 1.02
Al Filaj 1.01 1.02 1.02 1.01 1.02
Al Hamriyah 1.02 1.02 1.01 1.01 1.02
Al Oha (UAE) 1.02 1.03 1.03 1.03 1.03
Barka PS 1.01 1.02 1.02 1.01 1.02
Barka-3 PS 1.02 1.03 1.03 1.03 1.03
Blue City 1.02 1.03 1.03 1.02 1.03
Ibri 1.01 1.02 1.02 1.01 1.02
Ibri IPP 1.01 1.02 1.02 1.02 1.03
Ibri Solar 1.02 1.02 1.02 1.03
Jahloot 1.01 1.02 1.01 1.01 1.02
KIS 1.02 1.03 1.02 1.02
MIS 1.02 1.02 1.03 1.02 1.02
MSQ 1.02 1.02 1.02 1.01 1.02
Mahadha 1.02 1.03 1.03 1.02 1.03
Misfah 1.02 1.02 1.02 1.01 1.02
Mobella 1.01 1.02 1.02 1.01 1.02
New Izki 1.01 1.01 1.02 1.01 1.03
SIA 1.00 1.00 1.00 1.01 1.00
SIS 1.02 1.03 1.03 1.03 1.03
Sohar Free Zone 1.02 1.03 1.03 1.02 1.02
Sohar-1 PS 1.00 1.01 1.01 1.01 1.00
Sohar-2 PS 1.02 1.03 1.03 1.02 1.02

Page | 183
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.5: (continued) Transmission System Voltage Profile at Minimum Demand (2020-2024)
Busbar Voltage at Minimum Demand (per unit)
Location
2020 2021 2022 2023 2024
MIS Area
220 kV Busbars
Sur 1.00 1.01 1.00 1.00 1.00
Sur PS 1.00 1.01 1.00 1.00 1.00
132 kV Busbars
A'salam 1.02 1.02 1.01 1.01 1.02
Adam 1.01 1.00 1.01 1.00 1.00
Airport Height 1.02 1.02 1.01 1.01 1.02
Al Falaj 1.01 1.02 1.01 1.01 1.02
Al Filaj 1.01 1.02 1.00 1.01 1.02
Al Hamriyah 1.01 1.02 1.01 1.01 1.02
Al Hayl 1.03 1.02 1.02 1.03 1.02
Al Jefnen 1.03
Al Kamil 1.02 1.01 1.01 1.01 1.01
Amerat 1.02 1.02 1.01 1.01 1.02
Ayjah 1.01 1.01 1.00 1.01 1.01
Bahla 1.01 1.00 1.01 1.00 1.00
Barka M ain 1.01 1.02 1.01 1.01 1.02
Bedyah 1.02 1.02 1.02 1.02 1.01
Birkat Al M ouz 1.01 1.01 1.01 1.01 1.01
Bousher 1.01 1.02 1.01 1.01 1.02
Bureimi 1.02 1.01 1.02 1.02 1.01
Bureimi Industrial 1.02 1.01 1.02 1.02 1.01
Daghmar 1.01 1.01 1.01 1.01 1.01
Dank 1.03 1.02 1.02 1.03 1.02
Dil Abdusalam (DAS) 1.00 1.01 1.02 1.01 1.02
Dreez 1.02 1.01 1.02 1.03 1.02
Duqm 1.01
Ghala 1.02 1.02 1.01 1.01 1.02
Ghala Heights 1.01 1.02 1.01 1.01 1.02
Ibra 1.02 1.02 1.02 1.02 1.01
Ibri 1.03 1.02 1.02 1.03 1.03
Izki 1.02 1.01 1.02 1.01 1.01
JBB Ali 1.01 1.00 1.00 1.00 1.01
JBB Hassan 1.01 1.01 1.01 1.01 1.01
Jahloot 1.02 1.02 1.02 1.02 1.02

Page | 184
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.5: (continued) Transmission System Voltage Profile at Minimum Demand (2020-2024)
Busbar Voltage at Minimum Demand (per unit)
Location
2020 2021 2022 2023 2024
MIS Area
132 kV Busbars
Jebreen 1.01 1.01 1.01 1.01 1.01
KIS 1.02 1.02 1.02 1.02
Khaborah 1.00 1.01 1.01 1.01 1.02
Khadra 1.00 1.01 1.01 1.01 1.01
Khoudh 1.01 1.01 1.01 1.02
Liwa 1.00 1.01 1.01 1.01 1.00
M IS 1.01 1.01 1.01 1.01 1.02
M SQ-1 1.01 1.02 1.01 1.01 1.02
M SQ-2 1.01 1.02 1.01 1.01 1.02
M adinat Barka 1.01 1.01 1.00 1.01 1.02
M adinat Nizwa 1.01 1.00 1.01 1.01 1.00
M adinat Shinas 1.00 1.01 1.00 1.00 1.00
M ahadha 1.02 1.01 1.02 1.02 1.01
M anah 1.01 1.00 1.01 1.01 1.01
M awalleh North 1.02 1.02 1.01 1.01 1.02
M awalleh South-1 1.01 1.01 1.01 1.01 1.02
M awalleh South-2 1.01 1.01 1.01 1.01 1.02
M isfah 1.01 1.01 1.01 1.01 1.02
M obella 1.02 1.02 1.01 1.01 1.02
M obella Industrial 1.01 1.01 1.02
M udhaibi 1.02 1.02 1.02 1.02 1.01
M udhairib 1.02 1.02 1.02 1.02 1.01
M uladah 1.01 1.01 1.00 1.01 1.02
M uttrah 1.01 1.02 1.01 1.01 1.02
Nakhal 1.01 1.01 1.01 1.01 1.02
New Ghubrah 1.01 1.02 1.01 1.01 1.02
New Izki 1.02 1.02 1.03 1.02 1.02
Nahadah(PDO) 1.01 1.01 1.01 1.01 1.02
Nizwa 1.01 1.00 1.01 1.01 1.01
Qabel 1.03 1.02 1.03 1.03 1.01
Quriyat 1.01 1.01 1.01 1.01 1.01
Qurum 1.01 1.02 1.01 1.01 1.02
Rusail 1.01 1.01 1.01 1.01
Rusail Industrial 1.01 1.01 1.01 1.01 1.02
Rustaq 1.00 1.00 1.01 1.00 1.01
SIA 1.01 1.01 1.01 1.01 1.01

Page | 185
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.5: (continued) Transmission System Voltage Profile at Minimum Demand (2020-2024)
Busbar Voltage at Minimum Demand (per unit)
Location
2020 2021 2022 2023 2024
MIS Area
132 kV Busbars
SIS 1.01 1.01 1.01 1.02 1.02
Saham 1.00 1.01 1.01 1.02 1.02
Samad 1.02 1.02 1.02 1.02 1.01
Seeb M ain 1.02 1.01 1.01 1.01 1.02
Shinas 1.00 1.01 1.01 1.01 1.00
Sinaw 1.02 1.02 1.03 1.02 1.02
Sohar 1.00 1.01 1.01 1.01 1.01
Sohar Free Zone 1.01 1.01 1.01 1.01 1.01
Sohar Refinery 1.01 1.01 1.01 1.01 1.01
Sumail 1.01 1.01 1.01 1.01 1.02
Sumail Industrial 1.01 1.01 1.01 1.02
Sur 1.01 1.01 1.01 1.01 1.02
Sur-2 1.01 1.01 1.01 1.01 1.02
Suwaiq 1.01 1.01 1.01 1.01 1.02
Swaihat(PDO) 1.00
Uwaynat 1.00 1.01 1.01 1.01 1.01
Wadi Adai 1.01 1.02 1.01 1.01 1.02
Wadi Al Jazzi 1.01 1.01 1.01 1.01 1.01
Wadi Bani Auwf 1.02 1.00 1.01
Wadi Kabair 1.01 1.02 1.01 1.01 1.02
Wadi Sa'a 1.02 1.01 1.02 1.02 1.01
Yanqul 1.02 1.02 1.03 1.02
Yitti 1.02 1.02 1.02 1.02 1.02

33 kV Busbars

Tx (1&2) 1.00 1.00 1.00 1.00 1.00


A'salam
Tx (3&4) 1.00 1.01 1.00 1.01 1.00
Adam 1.00 1.00 1.00 1.00 1.00

Page | 186
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.5: (continued) Transmission System Voltage Profile at Minimum Demand (2020-2024)
Busbar Voltage at Minimum Demand (per unit)
Location
2020 2021 2022 2023 2024
MIS Area
33 kV Busbars
Tx (1&2) 1.00 1.00 1.00 1.00 1.00
Airport Height
Tx (3&4) 1.00 1.00 1.00 1.00 1.00
Al Falaj 1.00 1.01 1.00 1.00 1.00
Al Hayl 1.01 1.00 1.01 1.00 1.01
Tx (1&2) 1.00 1.01 1.00 1.00 1.00
Amerat
Tx (3&4) 1.00 1.00 1.01 1.00 1.00
Ayjah 1.00 1.00 1.00 1.00 1.01
Bahla 1.00 0.99 1.00 0.99 0.99
Tx (3) 1.01 1.00
Barka M ain
Tx (1&2) 0.99 0.99 1.00 1.00 1.00
Barka-3 PS 1.00 1.00 1.00 1.00 1.00
Bedyah 1.01 1.00 1.01 1.00 1.01
Birkat Al M ouz 1.00 1.00 1.00 1.00 1.00
Blue City 1.00 1.00 1.00 1.00 1.01
Tx (1&2) 1.00 1.00 1.00 1.00 1.00
Bousher
Tx (3&4) 1.00 1.00 1.00 1.00 1.00
Bureimi 1.00 1.00 1.00 1.00 1.00
Tx (1&2) 1.00 1.00 1.00 1.01 1.01
Bureimi Industrial
Tx (3&4) 1.00 1.01 1.00 1.01 1.00
Dank 1.00 1.00 1.00 1.00 1.00
Dil Abdusalam(DAS) 0.99 1.00 1.00 1.00 1.00
Dreez 1.01 1.00 1.00 1.00 1.00
Tx (1&2) 1.00
Duqm
Tx (3&4) 1.00
Tx (1&2) 1.00 1.00 1.00 1.00 1.00
Ghala Heights
Tx (3&4) 1.00 1.00 1.00 1.00 1.00
Tx (1&2) 1.00 1.00 1.00 1.00 1.00
Ghala
Tx (3&4) 1.00 1.00 1.00 1.00 1.01
Ibra 1.01 1.00 1.01 1.00 1.00
125M VA 1.00 1.00 1.01 1.01 1.00
Ibri
63M VA 1.00 1.00 1.00 1.00 1.00
Izki 1.00 1.00 1.00 1.01 1.01
JBB Ali 1.00 1.00 1.00 1.00 1.00
JBB Hassan 1.01 1.00 1.00 1.00 1.00

Page | 187
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.5: (continued) Transmission System Voltage Profile at Minimum Demand (2020-2024)
Busbar Voltage at Minimum Demand (per unit)
Location
2020 2021 2022 2023 2024
MIS Area
33 kV Busbars
Jahloot 1.00 1.00 1.00 1.00 1.01
Jebreen 1.00 1.00 1.00 1.00 1.00
Khaborah 0.99 1.00 1.00 1.00 1.01
Tx (1&2) 1.00 1.00 1.00 1.00 1.01
Khadra
Tx (3&4) 1.00 1.00 1.00 1.00 1.00
Tx (1&2) 1.00 1.00 1.00 1.01
Khoudh
Tx (3&4) 1.00 1.01 1.00 1.01
Tx (1&2) 0.99 1.00 1.00 1.00 1.00
Liwa
Tx (3&4) 1.00 1.00 0.99 0.99 1.00
M IS 1.00 1.00 1.00 1.00 1.00
Tx (1&2) 1.01 0.99 1.01 1.00 1.00
M SQ
Tx (3&4) 1.01 1.01 1.01 1.00 1.00
Tx (1&2) 0.99 0.99 0.99 1.00 1.00
M adinat Barka
Tx (3&4) 1.01 1.01 1.00 1.00 0.99
M adinat Nizwa 1.00 1.00 1.00 1.00 1.00
M adinat Shinas 1.01 1.00 1.00 1.01 1.00
M ahadha 1.00 0.99 1.00 1.00 1.01
M ahout 1.00
M awalleh North 1.00 1.00 1.00 1.00 1.00
Tx (1&2) 1.01 1.01 1.00 1.00 1.00
M awalleh South
Tx (3&4) 1.01 1.01 1.00 1.00 1.01
M isfah 1.01 1.01 1.00 1.01 1.00
M obella 1.00 1.00 1.00 1.01 1.01
Tx (1&2) 1.00 1.00 1.00
M obella Industrial
Tx (3&4) 1.00 1.00 1.00
M udhaibi 1.01 1.00 1.01 1.01 1.00
M udhairib 1.01 1.01 1.01 1.01 1.01
Tx (1&2) 1.01 1.00 1.00 1.00 1.00
M uladah
Tx (3&4) 1.00 1.00 1.00 1.00 1.00
M uttrah 1.01 1.01 1.01 1.00 1.00
Nakhal 1.01 1.00 1.01 1.00 1.00
New Ghubrah 1.01 1.00 1.00 1.00 1.00
New Izki 1.00 1.00 1.00 1.01 1.00
Nizwa 1.00 1.00 1.00 1.00 1.00
Quriyat 1.00 1.00 1.00 1.00 1.00
Qurum 1.00 1.01 1.00 1.00 1.00
Tx (1&2) 1.01 1.01 1.00 1.00 1.01
Rusail Industrial
Tx (3&4) 1.01 1.01 1.00 1.00 1.00

Page | 188
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.5: (continued) Transmission System Voltage Profile at Minimum Demand (2020-2024)
Busbar Voltage at Minimum Demand (per unit)
Location
2020 2021 2022 2023 2024
MIS Area
33 kV Busbars
Rustaq 1.01 1.00 1.00 1.01 1.00
SIA 1.01 1.00 1.01 1.01 1.01
Saham 1.00 1.00 1.00 1.00 1.00
Samad 1.01 1.00 1.01 1.01 1.01
Tx (1&2) 1.01 1.01 1.00 1.00 1.00
Seeb M ain
Tx (3&4) 1.00 1.00 1.00 1.00 1.00
Shinas 1.00 1.00 1.00 1.00 1.01
Sinaw 1.00 1.00 1.00 1.00 1.00
Tx (1&2) 1.00 1.00 1.00 1.00 1.00
Sohar Free Zone
Tx (3&4) 1.00 1.01 1.00 1.00 1.00
Tx (1&2) 1.00 1.00 1.00 1.00 1.00
Sohar
Tx (3&4) 1.00 1.00 1.00 1.00 1.00
Sumail Industrial 1.00 1.00 1.00 1.01
125M VA 1.00 1.00 1.00 1.00 1.00
Sumail
63M VA 1.00 1.00 1.00 1.00 1.00
Sur 1.00 1.00 1.00 1.00 1.00
Suwaiq 1.00 1.00 1.00 1.00 1.00
Tx (1&2) 1.00 1.00 1.01 1.00 1.01
Uwaynat
Tx (3&4) 1.00 1.00 1.00 1.00 1.00
Wadi Adai 1.01 1.00 1.00 1.00 1.00
Wadi Bani Auwf 1.00 1.00 1.00
Tx (1&2) 1.01 1.00 1.01 1.00 1.00
Wadi Kabair
Tx (3&4) 1.01 1.00 1.01 1.00 1.00
Wadi Sa'a 1.01 1.00 1.01 1.01 1.01
Yanqul 1.00 1.01 1.00 1.01
Yitti 1.00 1.01 1.01 1.01 1.00
11 kV Busbars
Daghmar 1.00 0.99 0.99 0.99 1.00
Dhofar Area
132 kV Busbars
Al Qarm 1.00 1.00 1.00 1.00 1.00
Ashoor 1.00 1.00 1.01 1.00 1.00
Ittin 1.00 1.00 1.00 1.00 1.00
M irbat 1.01 1.00 1.00
NPS 1.00 1.00 1.00 1.00 1.00

Page | 189
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.5: (continued) Transmission System Voltage Profile at Minimum Demand (2020-2024)
Busbar Voltage at Minimum Demand (per unit)
Location
2020 2021 2022 2023 2024
Dhofar Area
132 kV Busbars
Raysut 1.00 1.00 1.00 1.00 1.00
Saih Al Khairat 1.00 1.00
Salalah IPP 1.00 1.00 1.00 1.00 1.00
Shaha'aon 1.00 1.00 1.00 1.00 1.00
S’aadah 1.00 1.00 1.00 1.00 1.00
Thumrait 1.00 1.00 1.00 1.00 1.00
Wind Farm 1.01 1.01 1.02 1.01 1.01
33 kV Busbars
Al Qarm 1.00 1.01 1.00 1.00 1.00
Ashoor 1.00 1.00 1.00 1.00 1.00
Ittin 1.00 1.00 1.00 1.00 1.00
M irbat 1.01 1.00 1.00
NPS 1.00 1.00 1.00 1.00 1.01
Raysut 1.00 1.00 1.00 1.00 1.00
TX-1&2 1.00 0.99 1.00 1.00 1.00
S’aadah
TX-3&4 1.00 1.00 1.00 1.00 1.00
Saih Al Khairat 1.01 1.01
Salalah IPP 0.99 0.99 1.00 1.00 1.00
Shaha'aon 1.00 1.00 1.00 1.00 1.01
Thumrait 1.00 1.00 1.00 1.00 1.00

Page | 190
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.6: Estimation of Transmission Los ses and Generation Margin at Peak Demand (2020-2024)

2020 2021 2022 2023 2024


MW Mvar MW Mvar MW Mvar MW Mvar MW Mvar
Transmission Losses & Generation margin of MITS
Generation 6853 2506 7241 2438 7649 3599 8042 3860 8219 3153
External Infeed 0 0 0 0 0 0 0 0 0 0
Total Generation 6853 2506 7241 2438 7649 3599 8042 3860 8219 3153
Load (Grid+ Industrial+ Auxiliary
6724 2210 7114 2338 7478 2458 7871 2587 8069 2652
+Desalination)
Compensation Capacitor 0 0 0 0 0 0 0 0
Grid Losses 129.0 295.7 127.1 100.0 171.4 1140.8 171.4 1272.6 150.4 500.7
Grid Active Power Losses as a Percentage of
1.88 1.76 2.24 2.13 1.83
Total Generation (%)
Installed Capacity 9684 9682 8799 9300 10270
Generation 6853 7241 7649 8042 8219
Load Growth Rate (%) --- 5.80 5.12 5.26 2.52
Margin 2831 2441 1150 1257 2051
Margin (%) 29.2 25.2 13.1 13.52 19.97
Transmission Losses & Generation margin of Dhofar
Generation 646 207 768 301 843 348 915 372 943 380
External Infeed 0 0 0 0 0 0 0 0 0 0
Total Generation 646 207 768 301 843 348 915 372 937 308
Load (Grid+ Industrial+ Auxiliary
644 176 765 251 837 276 910 299 937 308
+Desalination)
Compensation Capacitor 0 0 0 0 0 0 0 0 0 0
Grid Losses 2.4 32.1 3.0 49.9 3.5 71.9 5.0 72.7 5.2 72.4
Grid Active Power Losses as a Percentage of
0.37 0.40 0.42 0.54 0.55
Total Generation (%)
Installed Capacity 1179 1179 1179 1179 1179
Generation 646 768 843 915 943
Load Growth Rate (%) --- 18.8 9.4 8.8 3.0
Margin 533 412 336 264 237
Margin (%) 45.2 34.9 28.5 22.4 20.1

Page | 191
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.7: Maximum 3-Phase Short Circuit Fault Levels


Voltage S witchgear Fault Rating Max Three-Phase S hort Circuit Ik" (kA)
S ubstations
(kV) (kA) 2020 2021 2022 2023 2024
MIS Area
400 kV Busbars
Al Jefnen 400 63 12.85 16.78
Duqm 400 63 0.97 0.97
Ibri IPP 400 63 20.79 21.50 21.31 21.35 24.01
Jahloot 400 63 11.01 11.07 11.07 11.10 11.26
M ahout 400 63 0.98 0.98
M anah Solar 400 63 14.18 14.50 15.02
M isfah 400 63 5.74 12.38 12.21 13.39 17.02
New Izki 400 63 12.27 15.57 14.95 15.38 16.30
New Rustaq 400 63 16.07
Nahadah (PDO) 400 63 13.54 13.58
Qabel 400 63 13.29 14.28 13.65 13.83 14.08
SIS 400 63 19.13 19.25 18.84 18.76 18.89
Sohar Free Zone 400 63 22.99 23.12 22.69 22.60 22.73
Sohar-3 IPP 400 63 23.34 23.46 23.05 22.97 23.09
Sur PS 400 63 17.26 17.33 16.89 17.00 17.22
Suwaihat(PDO) 400 63 1.07 1.07
220 kV Busbars
Airport Height 220 40 20.53 25.02 27.48 25.21 25.77
Al Filaj 220 40 28.65 31.47 32.45 30.84 30.91
Al Hamriyah 220 50 11.89 12.43 13.14 13.10 13.22
Al Oha (UAE) 220 50 25.21 25.25 25.14 25.12 25.14
Barka PS 220 40 30.21 32.69 33.52 32.01 31.41
Barka-3 PS 220 50 13.77 14.91 15.07 14.99 15.18
Blue City 220 40 16.46 17.29 17.46 17.00 18.15
Ibri 220 50 14.07 14.16 14.11 14.10 14.15
Ibri IPP 220 50 20.48 20.70 20.59 20.58 20.94
Ibri Solar 220 50 19.32 19.22 19.21 19.53
Jahloot 220 50 16.99 17.83 18.32 18.27 18.64
KIS 220 50 16.69 16.58 16.18 17.39
M IS 220 40 13.47 15.65 15.78 15.40 17.32
M SQ 220 40 14.23 16.67 17.12 16.91 17.36
M ahadha 220 40 30.41 30.64 30.06 29.94 30.06
M isfah 220 50 20.12 26.76 27.98 27.34 28.77
M obella 220 50 24.90 28.07 29.30 27.72 27.84
New Izki 220 50 12.00 12.43 12.54 12.45 14.58
Nizwa 220 50 9.27
SIA 220 40 27.79 27.91 21.65 21.57 21.70
SIS 220 40 37.88 38.58 36.00 35.55 36.29

Page | 192
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.7: (continued) Maximum 3-Phase Short Circuit Fault Levels

Voltage S witchgear Fault Rating Max Three-Phase S hort Circuit Ik" (kA)
S ubstations
(kV) (kA) 2020 2021 2022 2023 2024
MIS Area
220 kV Busbars
Sohar Free Zone 220 50 35.20 35.56 34.57 34.36 34.65
Sohar-1 PS 220 40 30.01 30.14 22.95 22.87 23.01
Sohar-2 PS 220 50 28.68 28.89 28.31 28.19 28.36
Sur 220 50 26.04 26.05 25.30 25.37 25.42
Sur PS 220 50 38.97 39.04 38.04 38.18 38.38
132 kV Busbars
A'salam 132 31.5 18.63 20.74 21.03 20.39 20.40
Adam 132 40 6.12 6.07 6.11 6.10 5.40
Airport Height 132 31.5 13.42 14.43 21.13 18.52 18.70
Al Falaj 132 31.5 16.93 17.96 21.42 21.29 21.28
Al Filaj 132 31.5 20.63 25.30 25.94 24.73 24.51
Al Hamriyah 132 40 17.61 18.70 22.11 21.98 21.51
Al Hayl 132 31.5 5.20 4.94 4.94 4.93 4.93
Al Jawabi 132 40 4.57
Al Jefnen 132 40 23.83 24.42
Al Kamil 132 31.5 16.05 15.66 10.25 10.25 9.82
Amerat 132 40 14.63 15.28 16.25 16.20 16.32
Ayjah 132 40 8.86 8.85 8.62 8.62 8.60
Bahla 132 31.5 6.88 6.80 6.86 6.84 6.89
Barka M ain 132 31.5 19.86 23.38 23.84 22.89 22.78
Bedyah 132 40 16.57 15.52 13.76 13.77 12.60
Birkat Al M ouz 132 40 15.11 14.51 14.99 14.84 13.93
Bousher 132 31.5 17.66 18.88 21.39 21.26 21.19
Bureimi 132 31.5 11.09 11.13 11.08 11.07 14.00
Bureimi Industrial 132 40 11.32 11.37 11.32 11.30 14.51
Daghmar 132 40 6.58 6.67 6.77 6.77 6.80
Dank 132 31.5 9.69 9.70 9.69 9.68 9.66
Dil Abdusalam (DAS) 132 40 6.91 16.53 16.45 14.78 16.90
Dreez 132 40 9.13 9.15 9.14 9.13 9.10
Duqm 132 40 2.63 2.63
Duqm Wind Farm 132 40 2.15
Ghala 132 40 13.08 14.04 18.50 18.09 18.27

Page | 193
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.7: (continued) Maximum 3-Phase Short Circuit Fault Levels


Voltage S witchgear Fault Rating Max Three-Phase S hort Circuit Ik" (kA)
S ubstations
(kV) (kA) 2020 2021 2022 2023 2024
MIS Area
132 kV Busbars
Ghala Heights-1 132 40 16.60
Ghala Heights-2 132 40 12.50
Ghala Heights 132 40 17.67 19.85 16.99 17.15
Ibra 132 40 11.69 11.25 11.12 11.13 10.51
Ibri 132 31.5 16.20 16.24 16.21 16.19 16.10
Izki 132 31.5 17.23 16.14 17.01 16.74 14.99
JBB Ali 132 31.5 6.43 6.37 5.24 5.24 5.13
JBB Ali Wind Farm 132 40 4.27
JBB Hassan 132 40 12.06 11.96 9.93 9.94 9.73
Jahloot 132 31.5 15.85 16.44 17.07 17.02 17.23
Jebreen 132 40 11.62 11.46 11.59 11.54 11.55
KIS 132 40 19.71 19.67 16.58 20.55
Khaborah 132 31.5 4.96 15.78 15.83 11.21 16.68
Khadra-1 132 40 7.73 7.32
Khadra-2 132 40 4.02 9.95
Khadra 132 40 15.03 15.22 16.58
Khoudh 132 40 21.08 20.32 22.39 22.75
Liwa 132 31.5 20.70 20.91 20.69 20.62 20.71
M IS 132 31.5 11.68 20.01 20.63 17.65 24.63
M SQ-1 132 31.5 18.65 20.02 22.87 22.72 22.64
M SQ-2 132 40 18.65 20.02 22.87 22.72 22.64
M adinat Barka 132 40 14.72 20.09 20.23 19.21 13.34
M adinat Nizwa 132 40 11.17 10.94 11.12 11.06 11.17
M adinat Shinas 132 40 9.42 9.47 9.42 9.41 9.43
M ahadha 132 31.5 22.66 22.83 22.62 22.56 22.61
M anah 132 31.5 12.42 12.21 12.38 12.32 9.76
M awalleh North 132 40 12.68 13.58 19.33 17.13 17.28
M awalleh South-1 132 31.5 20.48 21.05 20.52 22.36 22.72
M awalleh South-2 132 40 20.48 13.53 20.52 17.05 22.72
M isfah 132 31.5 14.82 14.79 20.00 19.84 20.21
M obella 132 31.5 20.30 22.84 23.19 22.41 22.43
M obella Industrial 132 40 22.96 22.15 22.13
M udhaibi 132 31.5 10.67 5.02 10.36 10.32 4.95
M udhairib 132 31.5 19.68 17.78 17.57 17.59 15.45
M uladah-1 132 31.5 7.86
M uladah-2 132 31.5 9.51
M uladah 132 31.5 18.05 19.00 17.03 24.43
M uttrah 132 31.5 17.02 18.05 21.40 21.28 21.09
Nakhal 132 31.5 11.18 12.83 14.42 13.95 16.11
New Ghubrah 132 40 17.75 18.98 21.52 21.39 21.32
New Izki 132 40 18.02 16.17 18.01 17.73 15.47

Page | 194
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.7: (continued) Maximum 3-Phase Short Circuit Fault Levels

Voltage S witchgear Fault Rating Max Three-Phase S hort Circuit Ik" (kA)
S ubstations
(kV) (kA) 2020 2021 2022 2023 2024
MIS Area
132 kV Busbars
New Rustaq 132 40 30.03
Nahadah (PDO) 132 31.5 2.28 2.28 2.28 15.00 15.01
Nizwa 132 31.5 14.61 14.22 14.53 14.42 14.60
Qabel 132 31.5 20.75 19.40 19.02 19.05 17.28
Quriyat 132 31.5 6.86 6.97 7.08 7.07 7.11
Qurum 132 31.5 16.65 17.67 20.29 20.18 16.84
Rusail 132 31.5 21.94 21.86 20.32
Rusail Industrial 132 31.5 21.91 21.84 20.33 23.25 23.64
Rustaq 132 31.5 6.44 9.95 12.09 11.41 29.14
SIA 132 31.5 20.70 20.74 18.47 18.44 18.49
SIS 132 31.5 21.55 25.09 24.60 24.05 24.79
Saham 132 31.5 11.64 17.03 16.85 16.13 17.06
Samad 132 40 6.42 3.83 6.31 6.30 3.79
Seeb M ain-1 132 31.5 18.91 12.83 18.95 15.95
Seeb M ain-2 132 31.5 17.43 19.25 19.50 18.96
Seeb M ain 132 31.5 20.81
Shinas 132 31.5 15.34 15.46 15.34 15.30 15.35
Sinaw 132 40 10.80 6.71 10.62 10.56 6.59
Sohar 132 31.5 16.17 16.96 16.78 16.64 16.82
Sohar Free Zone 132 40 22.42 22.67 22.41 22.33 22.43
Sohar Refinery 132 31.5 20.28 20.31 18.14 18.11 18.16
Sumail 132 31.5 11.75 11.55 11.36 11.46 11.13
Sumail Industrial 132 40 12.68 12.54 12.16 12.55 12.37
Sur 132 31.5 18.78 18.74 17.70 17.72 17.63
Sur-2 132 40 18.79 18.76 17.71 17.73 17.65
Suwaiq 132 40 10.26 17.76 18.18 14.59 20.90
Swaihat(PDO) 132 40 3.77 3.77
Uwaynat 132 40 17.22 18.71 18.46 18.22 18.53
Wadi Adai 132 31.5 17.35 18.45 22.36 22.22 22.41
Wadi Al Jazzi 132 31.5 20.37 20.82 20.59 20.49 20.62
Wadi Bani Auwf 132 40 6.84 10.47 10.07 15.71
Wadi Kabair 132 40 16.73 17.72 20.83 20.71 20.41
Wadi Sa'a 132 31.5 12.62 12.66 12.61 12.59 12.59
Waste to Energy Plant 132 40 12.92
Yanqul 132 40 5.94 5.93 5.93 5.92
Yitti 132 31.5 8.98 9.17 9.36 9.35 9.41

Page | 195
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.7: (continued) Maximum 3-Phase Short Circuit Fault Levels

Voltage S witchgear Fault Rating Max Three-Phase S hort Circuit Ik" (kA)
S ubstations
(kV) (kA) 2020 2021 2022 2023 2024
MIS Area
33 kV Busbars
Tx (1&2) 33 25 20.85 21.46 21.54 21.37 21.37
A'salam
Tx (3&4) 33 25 20.85 21.46 21.54 21.37 21.37
Adam 33 25 13.31 13.24 13.29 13.28 12.40
Tx (1&2) 33 25 18.38 18.82 20.97 20.26 20.32
Airport Height
Tx (3&4) 33 25 18.38 18.82 20.97 20.26 20.32
Al Falaj 33 25 18.97 19.28 20.15 20.13 20.12
Al Hayl 33 25 8.15 7.99 7.98 7.98 7.98
Al Jawabi 33 25 11.26
Tx (1&2) 33 25 18.48 18.73 19.08 19.06 19.10
Amerat
Tx (3&4) 33 25 18.48 18.73 19.08 19.06 19.10
Ayjah 33 25 15.76 15.76 15.56 15.57 15.55
Bahla 33 25 13.93 13.84 13.91 13.89 13.93
Tx (3) 33 25 12.28 12.57
Barka M ain
Tx (1&2) 33 25 21.70 22.63 22.73 22.51 22.48
Barka-3 PS 33 25 21.20 21.58 21.63 21.60 21.66
Bedyah 33 25 20.02 19.61 18.86 18.86 18.28
Birkat Al M ouz 33 25 19.18 18.93 19.13 19.07 18.67
Blue City 33 31.5 26.70 27.01 27.07 26.91 27.32
Tx (1&2) 33 25 20.67 21.07 21.79 21.75 21.74
Bousher
Tx (3&4) 33 25 19.83 20.20 20.86 20.82 20.81
Bureimi 33 25 17.20 17.22 17.19 17.18 18.67

Bureimi Tx (1&2) 33 25 17.15 17.18 17.15 17.14 18.69


Industrial Tx (3&4) 33 25 17.15 17.18 17.15 17.14 18.69
Dank 33 25 11.94 11.94 11.93 11.93 11.92
Dil Abdusalam(DAS) 33 25 14.01 19.85 19.82 19.17 19.98
Dreez 33 25 16.32 16.33 16.32 16.32 16.30
Tx (1&2) 33 25 7.74 7.74
Duqm
Tx (3&4) 33 25 7.74 7.74
Tx (1&2) 33 25 19.87 20.24 20.90 20.00 20.06
Ghala Heights
Tx (3&4) 33 25 18.09 20.24 20.90 20.00 20.06
Tx (1&2) 33 25 18.53 19.00 20.70 20.55 20.61
Ghala
Tx (3&4) 33 25 18.53 19.00 20.70 20.55 20.61
Ibra 33 25 17.45 17.20 17.12 17.13 16.75

Page | 196
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.7: (continued) Maximum 3-Phase Short Circuit Fault Levels


Voltage S witchgear Fault Rating Max Three-Phase S hort Circuit Ik" (kA)
S ubstations
(kV) (kA) 2020 2021 2022 2023 2024
MIS Area
33 kV Busbars
125M VA) 33 25 19.52 19.53 19.52 19.51 19.48
Ibri
63M VA 33 25 15.82 15.83 15.82 15.81 15.79
Izki 33 25 20.44 20.04 20.37 20.27 19.58
JBB Ali 33 25 13.58 13.51 12.13 12.13 11.97
JBB Hassan 33 25 17.46 17.40 16.20 16.21 16.07
Jahloot 33 25 18.84 19.04 19.25 19.24 19.30
Jebreen 33 25 18.05 17.94 18.02 17.99 18.00
Khaborah 33 25 11.66 19.49 19.51 17.32 19.82
Tx (1&2) 33 25 14.89 19.43 19.51 14.51 20.04
Khadra
Tx (3&4) 33 25 10.31 19.43 19.51 16.69 20.04
Tx (1&2) 33 25 21.82 21.61 22.16 22.25
Khoudh
Tx (3&4) 33 25 21.82 21.61 22.16 22.25
Tx (1&2) 33 25 20.86 20.92 20.86 20.84 20.87
Liwa
Tx (3&4) 33 25 20.86 20.92 20.86 20.84 20.87
M IS 33 25 17.49 20.69 20.85 20.00 21.73
Tx (1&2) 33 25 20.90 21.31 22.04 22.00 21.98
M SQ
Tx (3&4) 33 25 21.09 21.50 22.25 22.21 22.19
Tx (1&2) 33 25 19.22 21.06 21.10 20.81 18.60
M adinat Barka
Tx (3&4) 33 25 19.54 21.44 21.48 21.18 18.90
M adinat Nizwa 33 25 17.36 17.22 17.33 17.29 17.35
M adinat Shinas 33 25 16.19 16.22 16.19 16.18 16.19
M ahadha 33 25 8.65 8.66 8.65 8.65 8.65
M ahout 33 25 8.35 8.35
M awalleh North 33 25 18.42 18.87 21.06 20.34 20.39
Tx (1&2) 33 25 20.53 20.67 20.54 20.97 21.05
M awalleh South
Tx (3&4) 33 25 21.55 21.70 21.56 22.03 22.12
M isfah 33 25 19.58 19.57 21.40 21.36 21.47
M obella 33 25 20.76 21.36 21.44 21.27 21.27
M obella Tx (1&2) 33 31.5 22.29 22.10 22.09
Industrial Tx (3&4) 33 31.5 22.29 22.10 22.09
M udhaibi 33 25 17.30 11.89 17.09 17.07 11.80
M udhairib 33 25 21.02 20.43 20.36 20.37 19.58
Tx (1&2) 33 25 14.84 20.13 20.41 19.80 21.69
M uladah
Tx (3&4) 33 25 14.74 20.04 20.32 19.71 21.60
M uttrah 33 25 20.45 20.81 21.79 21.76 21.71
Nakhal 33 25 17.22 18.11 18.83 18.63 19.49

Page | 197
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.7: (continued) Maximum 3-Phase Short Circuit Fault Levels

Voltage S witchgear Fault Rating Max Three-Phase S hort Circuit Ik" (kA)
S ubstations
(kV) (kA) 2020 2021 2022 2023 2024
MIS Area
33 kV Busbars
New Ghubrah 33 25 20.73 21.14 21.86 21.82 21.80
New Izki 33 25 20.71 20.05 20.70 20.61 19.77
Nizwa 33 25 18.97 18.81 18.94 18.89 18.96
Quriyat 33 25 13.90 14.00 14.11 14.11 14.14
Qurum 33 25 20.31 20.68 21.49 21.46 20.39
Tx (1&2) 33 25 21.42 21.40 21.02 21.72 21.81
Rusail Industrial
Tx (3&4) 33 25 21.42 21.40 21.02 21.72 21.81
Tx (1&2) 33 25 13.64 16.77 22.77 22.15 23.17
Rustaq
Tx 3 33 25 9.29 10.65 22.77 22.15 12.91
SIA 33 25 20.86 20.87 20.25 20.24 20.26
Saham 33 25 17.48 19.81 19.75 19.50 19.82
Samad 33 25 9.51 7.61 9.45 9.44 7.57
Tx (1&2) 33 25 20.61 21.21 21.28 21.11 21.64
Seeb M ain
Tx (3&4) 33 25 21.21 18.72 21.22 20.16 21.76
Shinas 33 25 19.39 19.44 19.39 19.38 19.40
Sinaw 33 25 17.13 13.80 17.02 16.98 13.66
Tx (1&2) 33 25 22.17 22.23 22.16 22.14 22.17
Sohar Free Zone
Tx (3&4) 33 25 22.17 22.23 22.16 22.14 22.17
Tx (1&2) 33 25 19.87 20.16 20.09 20.04 20.11
Sohar
Tx (3&4) 33 25 19.48 19.76 19.70 19.65 19.72
Sumail Industrial 33 25 18.64 18.57 18.36 18.57 18.47
125M VA 33 25 17.97 17.86 17.74 17.80 17.60
Sumail
63M VA 33 25 12.24 12.19 12.14 12.16 12.07
Sur 33 25 20.74 20.73 20.40 20.41 20.38
Suwaiq 33 25 16.76 20.26 20.40 19.08 21.17
Tx (1&2) 33 25 20.42 20.92 20.84 20.76 20.86
Uwaynat
Tx (3&4) 33 25 20.56 21.06 20.98 20.90 21.00
Wadi Adai 33 25 20.19 20.55 21.60 21.57 21.61
Wadi Bani Auwf 33 25 14.20 17.31 17.03 20.07
Tx (1&2) 33 25 20.34 20.69 21.64 21.61 21.53
Wadi Kabair
Tx (3&4) 33 25 19.64 19.96 20.84 20.81 20.74
Wadi Sa'a 33 25 12.47 12.48 12.47 12.47 12.47
Yanqul 33 25 13.18 13.17 13.17 13.16
Yitti 33 25 16.12 16.27 16.42 16.41 16.46

Page | 198
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.7: (continued) Maximum 3-Phase Short Circuit Fault Levels

Voltage S witchgear Fault Rating Max Three-Phase S hort Circuit Ik" (kA)
S ubstations
(kV) (kA) 2020 2021 2022 2023 2024
Dhofar Area
132kV Busbars
Al Qarm 132 31.5 12.82 14.16 14.70 15.18 15.63
Ashoor 132 31.5 16.17 18.48 19.06 19.57 20.05
Ittin 132 31.5 12.98 14.37 15.17 15.90 16.62
M irbat 132 31.5 9.22 9.21 9.33 9.44
NPS 132 31.5 14.70 16.93 18.79 20.66 22.63
Saih Al Khairat 132 40 3.47 3.49
Raysut 132 31.5 14.98 17.31 19.17 21.02 23.03
Salalah IPP 132 40 14.98 17.31 19.17 21.02 23.03
Shaha'aon 132 31.5 12.23 13.61 14.50 15.32 16.14
S’aadah 132 40 11.46 12.60 13.19 13.71 14.22
Thumrait 132 31.5 6.68 6.93 7.05 7.17 7.27
Wind Farm 132 31.5 4.99 5.04 5.05 5.11 5.12
33kV Busbars
Al Qarm 33 25 10.49 10.74 10.83 10.90 10.97
Ashoor 33 25 16.39 17.04 17.18 17.30 17.41
Ittin 33 25 15.34 15.88 16.16 16.40 16.62
M irbat 33 25 11.05 9.28 9.32 9.35
NPS 33 25 9.60 9.85 10.02 10.17 10.30
Saih Al Khairat 33 25 7.83 7.86
Raysut 33 25 18.98 19.82 20.39 20.88 21.34
Salalah-IPP 33 25 17.76 20.40 21.00 21.52 22.00
Shaha'aon 33 25 17.71 16.04 16.39 16.69 16.97
TX-1&2 33 25 19.51 18.40 18.71 18.97 19.20
S'aadah
TX-3&4 33 25 15.43 18.35 18.65 18.91 19.15
Thumrait 33 25 5.83 8.52 8.58 9.43 9.48

Page | 199
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.8: Maximum 1-Phase Short Circuit Fault Levels

Voltage S witchgear Fault Rating Max S ingle-Phase Short Circuit Ik" (kA)
S ubstations
(kV) (kA) 2020 2021 2022 2023 2024
MIS Area
400 kV Busbars
Al Jefnen 400 63 13.94 17.91
Duqm 400 63 1.33 1.33
Ibri IPP 400 63 23.92 24.58 24.40 24.45 27.14
Jahloot 400 63 10.27 10.31 10.32 10.35 10.45
M ahout 400 63 1.33 1.33
M anah Solar 400 63 11.35 11.82 12.42
M isfah 400 63 5.81 11.00 11.34 14.45 17.96
New Izki 400 63 10.04 13.21 13.00 13.71 14.82
New Rustaq 400 63 14.61
Nahadah (PDO) 400 63 9.81 9.95
Qabel 400 63 11.64 12.40 12.14 12.31 12.47
SIS 400 63 18.56 18.67 18.37 18.32 18.40
Sohar Free Zone 400 63 27.21 27.34 26.91 26.83 26.95
Sohar-3 IPP 400 63 27.68 27.80 27.39 27.31 27.43
Sur PS 400 63 18.88 18.96 18.59 18.69 18.88
Suwaihat 400 63 1.33 1.33
220 kV Busbars
Airport Height 220 40 21.16 24.63 27.17 26.74 26.98
Al Filaj 220 40 31.54 33.85 34.73 33.65 32.92
Al Hamriyah 220 50 12.81 13.23 13.79 13.75 13.79
Al Oha(UAE) 220 50 22.66 22.68 22.62 22.61 22.64
Barka PS 220 40 34.90 37.16 37.92 36.73 35.35
Barka-3 PS 220 50 16.17 17.25 17.41 17.35 17.53
Blue City 220 40 15.97 16.56 16.66 16.42 17.09
Ibri 220 50 13.76 13.83 13.79 13.78 13.84
Ibri IPP 220 50 21.50 21.67 21.58 21.58 21.96
Ibri Solar 220 50 18.85 18.78 18.78 19.06
Jahloot 220 50 17.64 18.26 18.62 18.61 18.88
KIS 220 50 14.02 13.96 13.76 14.34
M IS 220 40 13.13 15.22 15.30 15.05 16.24
M SQ 220 40 15.05 17.05 17.56 17.30 17.52
M ahadha 220 40 24.49 24.59 24.32 24.27 24.74
M isfah 220 50 19.46 25.32 28.10 29.50 30.98
M obella 220 50 25.71 27.98 29.13 28.26 27.90
New Izki 220 50 12.17 13.03 13.14 13.20 15.89
Nizwa 220 50 9.94
SIA 220 40 33.17 33.27 24.75 24.68 24.79

Page | 200
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.8: (continued) Maximum 1-Phase Short Circuit Fault Levels

Voltage S witchgear Fault Rating Max S ingle-Phase Short Circuit Ik" (kA)
S ubstations
(kV) (kA) 2020 2021 2022 2023 2024
MIS Area
220 kV Busbars
SIS 220 40 35.29 35.86 34.13 33.87 34.33
Sohar Free Zone 220 50 38.50 38.80 37.95 37.79 38.04
Sohar-1 PS 220 40 35.43 35.55 25.96 25.89 26.01
Sohar-2 PS 220 50 30.55 30.71 30.24 30.15 30.29
Sur 220 50 23.51 23.52 23.09 23.13 23.16
Sur PS 220 50 46.45 46.52 45.54 45.68 45.89
132 kV Busbars
A'salam 132 31.5 23.67 25.94 26.65 26.04 25.35
Adam 132 40 7.24 7.19 7.23 7.21 6.52
Airport Height 132 31.5 18.09 19.37 28.27 24.93 24.86
Al Falaj 132 31.5 22.01 23.19 27.07 26.91 26.84
Al Filaj 132 31.5 24.80 29.17 29.77 28.76 27.00
Al Hamriyah 132 40 22.74 23.98 27.74 27.57 26.89
Al Hayl 132 31.5 5.56 5.81 5.80 5.80 5.80
Al Jawabi 132 40 5.93
Al Jefnen 132 40 30.60 31.85
Al Kamil 132 31.5 17.55 17.24 9.49 9.50 9.33
Amerat 132 40 17.35 17.97 18.85 18.79 18.90
Ayjah 132 40 9.84 9.83 9.63 9.63 9.62
Bahla 132 31.5 7.97 7.90 7.96 7.94 8.02
Barka M ain 132 31.5 23.45 26.65 26.80 26.05 25.52
Bedyah 132 40 17.43 16.58 14.99 15.00 14.02
Birkat Al M ouz 132 40 16.78 16.27 16.69 16.56 15.89
Bousher 132 31.5 23.50 25.27 28.70 27.25 26.94
Bureimi 132 31.5 13.89 13.93 13.87 13.86 17.01
Bureimi Industrial 132 40 14.22 14.27 14.21 14.19 17.68
Daghmar 132 40 7.77 7.86 7.96 7.95 7.98
Dank 132 31.5 10.16 10.49 10.48 10.47 10.46
Dil Abdusalam (DAS) 132 40 8.49 16.92 16.86 15.65 17.17
Dreez 132 40 10.29 10.30 10.29 10.28 10.27
Duqm 132 40 3.67 3.67
Duqm Wind Farm 132 40 2.31
Ghala 132 40 17.65 18.82 24.64 24.37 24.33
Ghala Heights-1 132 40 21.92
Ghala Heights-2 132 40 16.77
Ghala Heights 132 40 23.54 26.63 22.77 22.76
Ibra 132 40 12.53 12.19 12.09 12.10 11.59
Ibri 132 31.5 19.04 19.09 19.06 19.04 18.98

Page | 201
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.8: (continued) Maximum 1-Phase Short Circuit Fault Levels


Voltage S witchgear Fault Rating Max S ingle-Phase Short Circuit Ik" (kA)
S ubstations
(kV) (kA) 2020 2021 2022 2023 2024
MIS Area
132 kV Busbars
Izki 132 31.5 18.81 17.96 18.69 18.48 17.09
JBB Ali 132 31.5 7.53 7.48 6.34 6.34 6.62
JBB Ali Wind Farm 132 40 5.05
JBB Hassan 132 40 12.47 12.40 10.67 10.67 10.52
Jahloot 132 31.5 18.96 19.53 20.12 20.09 20.29
Jebreen 132 40 12.69 12.56 12.67 12.62 12.71
KIS 132 40 19.24 19.21 17.10 19.75
Khaborah 132 31.5 6.42 16.60 16.64 12.73 17.25
Khadra-1 132 40 9.02 8.39
Khadra-2 132 40 5.14 10.96
Khadra 132 40 17.39 17.55 18.72
Khoudh 132 40 26.09 26.07 27.75 28.54
Liwa 132 31.5 25.55 25.76 25.52 25.45 25.55
M IS 132 31.5 14.38 23.15 23.70 20.94 27.02
M SQ-1 132 31.5 24.90 26.74 30.37 29.44 28.95
M SQ-2 132 40 24.90 26.74 30.37 29.44 28.95
M adinat Barka 132 40 17.84 22.85 22.97 22.13 15.87
M adinat Nizwa 132 40 12.58 12.38 12.55 12.49 12.70
M adinat Shinas 132 40 10.53 10.56 10.52 10.51 10.53
M ahadha 132 31.5 23.53 23.65 23.50 23.45 24.18
M anah 132 31.5 14.13 13.94 14.09 14.04 9.38
M awalleh North 132 40 16.97 18.09 25.51 22.80 22.76
M awalleh South-1 132 31.5 26.56 27.35 27.75 28.95 30.04
M awalleh South-2 132 40 26.56 18.02 27.75 22.69 30.04
M isfah 132 31.5 15.84 15.82 22.37 22.54 22.92
M obella 132 31.5 25.53 28.20 29.14 28.40 27.74
M obella Industrial 132 40 27.71 26.99 26.72
M udhaibi 132 31.5 12.24 6.45 11.97 11.94 6.38
M udhairib 132 31.5 21.56 19.61 19.81 19.84 17.63
M uladah-1 132 31.5 9.92
M uladah-2 132 31.5 10.36
M uladah 132 31.5 21.36 22.22 20.40 26.90
M uttrah 132 31.5 22.18 23.37 27.14 26.98 26.72
Nakhal 132 31.5 11.99 13.30 15.05 14.71 16.18
New Ghubrah 132 40 23.61 25.38 28.83 27.41 27.10
New Izki 132 40 19.94 18.64 20.26 20.09 18.47
New Rustaq 132 40 31.88
Nahadah(PDO) 132 31.5 1.37 1.37 1.37 13.78 13.86
Nizwa 132 31.5 17.61 17.22 17.54 17.43 17.91
Qabel 132 31.5 22.25 21.16 21.00 21.07 19.47

Page | 202
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.8: (continued) Maximum 1-Phase Short Circuit Fault Levels

Voltage S witchgear Fault Rating Max S ingle-Phase Short Circuit Ik" (kA)
S ubstations
(kV) (kA) 2020 2021 2022 2023 2024
MIS Area
132 kV Busbars
Quriyat 132 31.5 8.31 8.42 8.52 8.52 8.55
Qurum 132 31.5 20.15 21.19 23.69 23.49 18.59
Rusail 132 31.5 28.47 28.52 27.27
Rusail Industrial 132 31.5 28.44 28.49 27.29 30.11 31.12
Rustaq 132 31.5 8.11 12.09 14.12 13.51 30.87
SIA 132 31.5 24.47 24.50 21.65 21.62 21.66
SIS 132 31.5 23.62 26.34 25.93 25.52 26.07
Saham 132 31.5 13.04 17.11 16.98 16.49 17.12
Samad 132 40 7.01 4.68 6.92 6.91 4.65
Seeb M ain-1 132 31.5 24.31 17.00 25.29 21.05
Seeb M ain-2 132 31.5 22.07 24.02 24.62 24.09
Seeb M ain 132 31.5 27.34
Shinas 132 31.5 17.41 17.51 17.40 17.37 17.41
Sinaw 132 40 11.99 8.24 11.85 11.79 8.13
Sohar 132 31.5 18.79 19.50 19.33 19.21 19.36
Sohar Free Zone 132 40 28.36 28.62 28.33 28.24 28.36
Sohar Refinery 132 31.5 23.92 23.95 21.22 21.20 21.24
Sumail 132 31.5 13.66 13.48 13.37 13.46 13.17
Sumail Industrial 132 40 13.85 13.74 13.53 13.85 13.72
Sur 132 31.5 21.05 21.02 20.12 20.13 20.06
Sur-2 132 40 21.06 21.03 20.13 20.15 20.08
Suwaiq 132 40 12.59 19.93 20.28 16.91 22.42
Suwaihat(PDO) 132 40 4.49 4.49
Uwaynat 132 40 20.33 21.69 21.45 21.24 21.52
Wadi Adai 132 31.5 22.30 23.54 27.98 27.77 27.96
Wadi Al Jazzi 132 31.5 17.19 17.40 17.29 17.24 17.33
Wadi Bani Auwf 132 40 8.15 11.69 11.37 15.73
Wadi Kabair 132 40 21.58 22.70 26.10 25.96 25.56
Wadi Sa'a 132 31.5 11.95 11.98 11.95 11.94 11.97
Waste to Energy Plant 132 40 14.66
Yanqul 132 40 7.42 7.42 7.41 7.41
Yitti 132 31.5 10.10 10.26 10.42 10.41 10.46

Page | 203
Five-Year Annual Transmission Capability Statement (2020-2024)

Table C.8: (continued) Maximum 1-Phase Short Circuit Fault Levels


Voltage Max S ingle-Phase Short Circuit Ik" (kA)
S ubstations S witchgear Fault Rating (kA)
(kV) 2020 2021 2022 2023 2024
Dhofar Area
132kV Busbars
Al Qarm 132 31.5 13.41 14.38 14.76 15.09 15.39
Ashoor 132 31.5 20.28 23.18 23.80 24.33 24.83
Ittin 132 31.5 14.47 15.61 16.26 16.87 17.43
M irbat 132 31.5 9.08 9.04 9.11 9.18
NPS 132 31.5 18.57 21.00 23.35 25.71 28.35
Saih Al Khairat 132 40 4.37 4.39
Raysut 132 31.5 19.36 22.02 24.36 26.67 29.47
Salalah-IPP 132 40 19.36 22.02 24.36 26.67 29.47
Shaha'aon 132 31.5 14.31 15.52 16.31 17.03 17.73
S’aadah 132 40 14.15 15.26 15.84 16.36 16.85
Thumrait 132 31.5 6.16 6.94 7.02 7.71 7.79
Wind Farm 132 31.5 4.94 4.98 4.99 5.26 5.28

Page | 204
Five-Year Annual Transmission Capability Statement (2020-2024)

Figure C. 1: MIS 2020 Max. Load Flow Condition


Page | 205
Five-Year Annual Transmission Capability Statement (2020-2024)

Figure C. 2: MIS 2021Max. Load Flow Condition


Page | 206
Five-Year Annual Transmission Capability Statement (2020-2024)

Figure C. 3: MIS 2022 Max. Load Flow Condition


Page | 207
Five-Year Annual Transmission Capability Statement (2020-2024)

Figure C. 4: MIS 2023 Max. Load Flow Condition

Page | 208
Five-Year Annual Transmission Capability Statement (2020-2024)

Figure C. 5: MIS 2024 Max. Load Flow Condition


Page | 209
Five-Year Annual Transmission Capability Statement (2020-2024)

Figure C. 6: Dhofar System 2020 Max. Load Flow Condition


Page | 210
Five-Year Annual Transmission Capability Statement (2020-2024)

Figure C. 7: Dhofar System 2021 Max. Load Flow Condition


Page | 211
Five-Year Annual Transmission Capability Statement (2020-2024)

Figure C. 8: Dhofar System 2022 Max. Load Flow Condition

Page | 212
Five-Year Annual Transmission Capability Statement (2020-2024)

Figure C. 9: Dhofar System 2023 Max. Load Flow Condition


Page | 213
Five-Year Annual Transmission Capability Statement (2020-2024)

Figure C. 10: Dhofar System 2024 Max. Load Flow Condition

Page | 214

You might also like