You are on page 1of 1

ID Task Task Name Duration

Mode -1 1 2 3 4 5 6 7 8 9
1 Total Duration 150 days
2
3 Start 0 days 19/11
4 Mobilisation 1 wk
5 Preparation 1 wk
6 Demolition Work 1 wk
7 Cleaning and Recovery 25 days
8 Cleaning of the location of Space 2 1 wk
9 Recovery conveyor H4 and or H3 1 wk
10 Cleaning of the location of Space 3 1 wk
11 Conveyor recovery E5 and or E4 4 wks
12 Steel Structure 125 days
13 Fabrication 75 days
14 Fabrication of TH 3.1, TH 3.2, TH 3.2, 15 wks
15 Fabrication of Chute-1, Chute diverter, Chute-2 15 wks
16 Modification Chute of TH3 15 wks
17 Fabrication for Conveyor TH3 to TH 3.1 15 wks
18 Fabrication Conveyor TH-3.1 To TH 3.3 15 wks
19 Installation 50 days
20 Installing TH3 Extended (TH3 to TH 3.1 ) 10 wks
21 Installing TH3 Extended (TH3 to H4 10 wks
22 Foundation Work 40 days
23 Foundation for TH 3.1, TH 3.2, TH 3.3 8 wks
24 foundation for conveyor 8 wks
25 ME 8 wks
26 Testing & Commisioning 3 wks
27 Demobilisation 1 wk
28 Finish 0 days 16/06

You might also like