Cleaning of the location of Space 3 Conveyor recovery E5 and or E4
Start: Tue 03/12/19ID: 10 Start: Tue 10/12/19ID: 11
Finish: Mon 09/12/1Dur: 1 wk Finish: Mon 06/01/2Dur: 4 wks
Res: Res:
Fabrication of Chute‐1, Chute diverter, C
Start: Tue 26/11/19ID: 15
Finish: Mon 09/03/2Dur: 15 wks
Res:
Modification Chute of TH3
Start: Tue 26/11/19ID: 16
Finish: Mon 09/03/2Dur: 15 wks
Res:
Fabrication for Conveyor TH3 to TH 3.1
Start: Tue 26/11/19ID: 17
Finish: Mon 09/03/2Dur: 15 wks
Res:
Fabrication Conveyor TH‐3.1 To TH 3.3
Start: Tue 26/11/19ID: 18
Finish: Mon 09/03/2Dur: 15 wks
Res:
Installation Installing TH3 Extended (TH3 to TH 3.1 )
Start: Tue 10/03/20ID: 19 Start: Tue 10/03/20ID: 20
Finish: Mon 18/05/Dur: 50 days Finish: Mon 18/05/2Dur: 10 wks
Comp: 0% Res:
Installing TH3 Extended (TH3 to H4
Start: Tue 10/03/20ID: 21
Finish: Mon 18/05/2Dur: 10 wks
Res:
foundation for conveyor
Start: Tue 07/01/20ID: 24
Finish: Mon 02/03/2Dur: 8 wks
Res:
ME Testing & Commisioning Demobilisation
Finish
Start: Tue 24/03/20ID: 25 Start: Tue 19/05/20ID: 26 Start: Tue 09/06/20ID: 27
Finish: Mon 18/05/2Dur: 8 wks Finish: Mon 08/06/2Dur: 3 wks Finish: Mon 15/06/2Dur: 1 wk Milestone Date: Tue 16/06/20
Res: Res: Res: ID: 28
Critical Critical Milestone Critical Summary Critical Inserted Critical Marked Critical External Project Summary Highlighted Noncritical
Project: Network Diagram
Date: Tue 19/11/19 Noncritical Milestone Summary Inserted Marked External Highlighted Critical