Professional Documents
Culture Documents
COMMISSION ON AUDIT
National Government Sector
Cluster 6 – Health and Science
DEPARTMENT OF HEALTH - Regional Office 02
OFFICE OF THE AUDITOR
Carig Norte, Tuguegarao City
I. PREPARATORY REQUIREMENTS:
A. DOCUMENTS NEEDED: Present Absent Date Remarks
A.1. Project Procurement Management Plans(PPMP)
(Section 7.3.2. of Revised IRR)
A.2. Annual Procurment Plan (APP)
(Section 7.2. of Revised IRR)
A.3. Detailed Quantity and Cost Estimates
(Section 2.g. of Annex"A" of Revised IRR)
A.4. Program of Works for the Project
(Section 2.h. of Annex"A" of Revised IRR)
A.5 Approved Budget for Contract (ABC)
(Section 3.g. of Annex"A" of Revised IRR)
A.6. Complete Bidding Documents
PBD 4th Edition
(Section 6.2 of Revised IRR and GPPB Res.
No. 06-2010 dated Dec. 17, 2010
B. AUDIT ANALYSIS:
Yes No Date Remarks
B.1. Is the procurement project included in the Project
Procurement Management Plan (PPMP)?
B.2. Is the procurement project included in the Annual
Procurement Plan (APP)?
B.3. Does the APP match the budget per GAA,
corporate budget, appropriation ordinance,
as the case may be?
B.4. Is the Approved Budget for Contract (ABC) prepared
in prescribed form? Does it match with the detailed Quantity
and Cost Estimates and Program of Works?
B.5. For this procurement, was the Standard Philippine
Bidding Documents (4th edition) used containing the following?
Section I. Invitation to Bid (IB)
Section II. Instruction to Bidders (ITB)
Section III. Bid Data Sheet (BDS)
Section IV. General Conditions of Contract (GCC)
Section V. Special Conditions of Contract (SCC)
Section VI. Specifications
Section VII. Drawings
Section VIII. Bill of Quantities
Section IX. Bidding Forms
Section IX. Foreign-Assisted Projects
Page 1 of 7
II. BIDDING REQUIREMENTS:
1. Pre-Procurement Conference: (ABC above 5M)
prior to the date of 1st day of posting of Invitation
to Bid (IB) - (Section 20 of the Revised IRR)
B. AUDITORIAL ANALYSIS:
B.1. Was the Pre-procurement Conference conducted
within the required time?
B.2. Did the required participants attend the
Pre-procurement Conference?
B.3. Did the Pre-procurement Conference attain the
objectives of the conference?
a) Ensure that the procurement is in accordance with the
project and annual procurement plans;
b) Approval of the Bidding Documents including Invitation to Bid
b) Reiteratiom of “no contact rule” during the bid
evaluation process, and the applicable sanctions
and penalties
Page 3 of 7
5. Submission, Receipt, Opening and Preliminary
Examination of Bids : within the required time, max.
period from last day of advertisement up to the Submission
and Receipt of Bids: a) ABC 50 M and below - 50 cd
b) ABC above 50 M - 65 cd ( Section 25.4.b of the Revised IRR)
Page 4 of 7
A.3. Checklist on Financial documents (2nd Envelope) Present Absent Date Remarks
1. Financial Bid Form
2. Duly Signed Bid Prices in the Bill of Quantities
3. Duly Signed Detailed Estimates
Page 5 of 7
A. DOCUMENTS NEEDED: Present Absent Date Remarks
A.1. Invitation of three(3) obsevers in writing, at least
3 calendar days before procurement activity.
(Section 13 of the Revised IRR)
a. COA Representative
Date received :
b. Duly recognized private group
Date received :
c. Non-Government Organization (NGO)
Date received :
A.2. Submission of additional requirements within 3 cd from
receipt by the bidder of the notice from the BAC that the
bidder has the LCB as follows:
a) Latest income and business tax returns;
b) Certificate of PhilGEPS Registration; and
c) Other appropriate licenses and permits required by law
and stated in the Bidding Documents.
A.3. Post-qualification Evaluation Report by the TWG
A.4. Resolution of the BAC adopting and confirming the TWG Post
Qualification Evaluation Report and declaring the LCRB
A.4. Notice of Post-qualification to the LCRB
A.5. BAC Resolution Declaring LCRB and Recommending Approval
by the HOPE
Page 6 of 7
9. Contract Preparation and Signing : within ten (10) calendar days from
receipt by the winning bidder of the NOA. (Section 37 of Revised IRR)
6. PERT/CPM
Date :
Noted by:
Date :
Page 7 of 7