Professional Documents
Culture Documents
Design
Ahmed, T., Russell, P. A and Hamad, F
School of Science and Engineering, Teesside University, Southfield Road Middleborough TS1 3BA United Kingdom
T.Ahmed@tees.ac.uk
Abstract: Multiphase separators are intrinsic to the recovery of crude oil. This work compares
extant separator design models with a newly developed procedure to optimise existing models
by minimising economic cost. The new method avoids the use of ‘fudge factors’ or undefined
variables in the solution of the design. A comparison between results obtained from this model
and four extant models is presented. The newly developed model gave results similar to models
based on retention time theory without the need for undertaking a laboratory testing.
1
Optimisation of Three-Phase Separators: A Mathematical Model Design
The internal diameter (Di) is fitted by the GRG non- (𝐷𝑖 − ℎ𝑁𝑂𝐿 )
linear solver in excel subject to constraints. 𝑡𝑜𝑔 = (13)
𝑈𝑜𝑔
2.1.3 Calculated variable
𝑄𝑔 (𝐷𝑖 − ℎ𝑁𝑂𝐿 )
The main calculated variable in the cost equation is the 𝐿𝑔𝑟1 = (14)
𝑈𝑜𝑔 (VA − 𝐴𝑁𝑂𝐿 )
separator length. The separator length is the sum of the
lengths of the separator inlet, gravity settling section and The settling velocity (in this case, of oil droplets out of
the outlet sections. The gravity settling section length is gas phase) is determined by equating the gravity force to
calculated from the eq. 9 – 19. It is important to point out the drag force. This calculation is an iterative process
that the design of the separator inlet is not considered which start with an assumption for the initial value of the
here, however, it is believed that whatever the inlet device drag coefficient. The terminal velocity is calculated and
chosen, the length should not exceed 1m and is set as used to calculate the Reynolds number which in turn is
default. Vessel length can therefore be calculated from used to calculate the drag coefficient. This value is then
equation 8 below; used as the input into the terminal velocity equation and
the procedure is repeated until the difference between the
𝑉𝐿 = 𝐿𝑖 + 𝐿𝑔𝑟𝑣 + 𝐿𝑜 (8) calculated value equals the assumed value. Terminal
Length of the gravity settling section is obtained as the velocity, Reynolds number and drag coefficient are
maximum length required for a dispersed phase to settle calculated using eq. 15 – 17.
out of the continuous phase in the three – phase separator.
This length can be calculated by setting the phase 1.333 ∗ 𝑑𝑝 ∗ 𝑔 ∗ (𝜌𝑜 − 𝜌𝑔
𝑢 𝑇 = √[ ] (15)
retention time in the vessel equal to the bubble / droplet 𝐶𝐷 ∗ 𝜌𝑔
rising / settling time (see eq. 9). For this model, rising /
settling paths were assumed and used to calculate the 24 3
𝐶𝐷 = 0.34 + + (16)
lengths required for separation of the gas, oil and water. 𝑁𝑅𝑒 √𝑁𝑅𝑒
In a continuous gas phase, oil and water settle, water 𝜌 ∗ 𝑈 ∗ 𝑑𝑝
settle faster than oil so the oil droplet settling is 𝑁𝑅𝑒 = (17)
µ
controlling and is considered from the vessel top to the
Normal Operating Level.
In a continuous oil phase, the gas bubbles rise and the The length required for settling water droplets from the
water droplet settle. The gas bubble rise faster so the oil continuous phase and that of rising oil droplets from
water droplet settling is controlling and is considered water continuous phase are obtained using equations 18
from the Normal Operating Level to the Normal Interface and 19 respectively;
Level. 𝑄𝑜 (ℎ𝑁𝑂𝐿 − ℎ𝑁𝐼𝐿 )
In a continuous water phase, the gas bubble and the 𝐿𝑔𝑟2 = (18)
𝑈𝑤𝑜 (𝐴𝑁𝑂𝐿 − 𝐴𝑁𝐼𝐿 )
liquid droplet rise. The gas bubble rise faster and so the
oil droplet rising from the bottom of the vessel to the 𝑄𝑤 ℎ𝑁𝐼𝐿
𝐿𝑔𝑟3 = (19)
Normal Interface Level is controlling and therefore 𝑈𝑜𝑤 𝐴𝑁𝐼𝐿
considered. Length of the separator outlet section is calculated as;
Equations 9 to 14 below are examples developed based 𝐿𝑂 = 2(𝑑𝑛𝑜 + 𝑑𝑛𝑤 ) + 𝐿𝑤𝑒𝑖𝑟
on the separation of liquid droplet from the gas
continuous phase. The same procedure is used to The oil and water outlet nozzles can be calculated
determine the length required for gravity settling for the using Monnery and Svrcek, (1994) formula for
oil and water phases respectively. calculating nozzle sizes (see eq. 21);
𝑡𝑟 ≥ 𝑡𝑜𝑔 (9) 𝑑𝑛𝑝 = 0.146√𝑄 ∗ 𝜌0.5 (21)
2
Optimisation of Three-Phase Separators: A Mathematical Model Design
Once the objective function is calculated, the next step is the outlet nozzle, the extractor’s efficiency will be
to determine the constraints. reduced since most of the flow will be directed towards
the centre.
2.2 Constraints
The constraints set to the objective function are We can obtain the height of high high liquid level from
grouped into three; the area of High High Liquid Level. Powers (1990) and
Svrcek and Monnery (1993) are among the several works
2.2.1 Phase Outlet Constraint that reported on how to calculate dimensionless chord
The first group of constraints are set to ensure the height from dimensionless chord area and vice versa. In
various phases leave the separator through their this model, two user defined functions referred to as
designated outlets. Firstly, to avoid oil from escaping “HTOA” and “ATOH” were developed. These functions
through the gas outlet, there should be a minimum length are explained in the excel model development sections of
between the high high liquid level (hHHLL) and the inlet this paper.
of the mist extractor. Secondly, to avoid gas leaving the 𝐴𝐻𝐻𝐿𝐿
separator from the liquid outlets, there should be a 𝐻𝐻𝐻𝐿𝐿 = 𝐴𝑇𝑂𝐻 ( ) ∗ 𝐻𝑇 (22)
𝑉𝐴
distance between the weir height (hWH) and the low low To calculate hHHLL above we need to calculate
liquid level (hLLLL). Thirdly, to avoid water level from AHHLL. This can be calculated from the Norsok
reaching and overflowing the weir and leaving through Standard that states “In sizing the separators, the
the oil outlet, there should be a distance between the weir equivalent residence time between normal and alarm
height (hWH) and the high high interface level (hHHIL). level and between alarm and trip level should not be less
Finally, to avoid oil from leaving through the water than 30 seconds or 80mm for both high and low ranges”.
outlet, there should be a distance between the low low
interface level (LLIL) and the bottom of the vessel. (𝑄𝑜 + 𝑄𝑤 )∆𝑡𝑁𝑆 ≤ 𝑉𝐿 ∗ (𝐴𝑎 − 𝐴𝑏 ) (23)
1. Avoid liquid from leaving through the gas Therefore, we can calculate Area of HLL as;
outlet (hMEI – hHHLL ≥ 0.10m) (𝑄𝑜 + 𝑄𝑤 )∆𝑡𝑁𝑜𝑟
𝐴𝐻𝐿𝐿 = + 𝐴𝑁𝑂𝐿 (27)
The difference between the height of mist extractor 𝑉𝐿
inlet and the height of the high high liquid level should 𝑉𝑠𝑢𝑟𝑔𝑒
be more than the safety factor which is 0.10m. Different 𝐴𝐻𝐿𝐿 = + 𝐴𝑁𝑂𝐿 (28)
𝑉𝐿
literature suggested different safety factors between the
mist extractor and the liquid level. Here, an average of To calculate the AHLL, the ANOL need to be
0.10m is used for this model. calculated. This can be calculated from the hNOL using
the dimensionless chord height formula as;
The Mist Extractor Inlet is obtained by subtracting the
vessel diameter by 0.3m. The mist extractor height is ℎ𝑁𝑂𝐿
𝐴𝑁𝑂𝐿 = 𝐻𝑇𝑂𝐴 ( )
usually set to be 0.15m (6inches). Another 0.15m is 𝐻𝑇 (29)
allowed from the top of the vessel to the mist extractor ∗ 𝐴𝑇
outlet. This height is set to obtain a uniform flow
distribution through the extractor. If placed too close to
3
Optimisation of Three-Phase Separators: A Mathematical Model Design
𝜋 ∗ 𝐷2 𝑄𝑤
𝐴𝑇 = (30) 𝑉𝐻𝑜𝑙𝑑𝑢𝑝 ( ) ≤ 𝑉𝑙 ∗ (𝐴𝑁𝐼𝐿 − 𝐴𝐿𝐼𝐿 ) (39)
4 𝑄𝑜
Di and hNOL are assumed which are then set by the 𝑄𝑤
excel solver. 𝑉𝑆𝑢𝑟𝑔𝑒 ( ) ≤ 𝑉𝑙 ∗ (𝐴𝐻𝐼𝐿 − 𝐴𝑁𝐼𝐿 ) (40)
𝑄𝑜
2. Avoid gas from leaving through the liquid outlets Rearranging eqn. 40 gives;
(hLLLL – hWH ≥ 0.10m) 𝑉𝑆𝑢𝑟𝑔𝑒 ∗ 𝑄𝑤
𝐴𝐻𝐼𝐿 =
The difference between the low low liquid level and 𝑉𝑙 ∗ 𝑄𝑜 (41)
the weir height is set to be greater than 0.10 m to avoid + 𝐴𝑁𝐼𝐿
the gas phase from leaving through any of the liquid ANIL can be calculated from the hNIL
outlets. Once the height of the low low liquid level is ℎ𝑁𝐼𝐿
calculated, the weir height can then be set as the low low 𝐴𝑁𝐼𝐿 = 𝐻𝑇𝑂𝐴 ( ) ∗ 𝐴𝑇 (42)
liquid level minus 0.10m. Low low liquid height can be 𝐻𝑇
calculated from the area of the low low liquid level which hNIL is assumed from the initial guesses.
can be calculated by rearranging equation 23.
4. Avoid Oil from leaving through the Water outlet
(𝑄𝑂 + 𝑄𝑊 )∆𝑡𝑁𝑆 (hLLIL ≥ 0.10m)
𝐴𝐿𝐿𝐿𝐿 = 𝐴𝐿𝐿𝐿 − ( ) (31)
Oil being lighter than water rise to the top of the water
𝑉𝐿
continuous phase. To avoid the oil from leaving through
(𝑄𝑂 + 𝑄𝑊 )∆𝑡𝑁𝑆 the water outlet, the height of the low low interface level
𝐴𝐿𝐿𝐿 = 𝐴𝑁𝑂𝐿 − ( ) (32)
𝑉𝐿 should be at least 0.10m. The height of the low low
interface level can be calculated as;
From eq. 25; 𝐴𝐿𝐿𝐼𝐿
𝑉𝐻𝑜𝑙𝑑𝑢𝑝 ℎ𝐿𝐿𝐼𝐿 = 𝐴𝑇𝑂𝐻 ( ) ∗ 𝐻𝑇 (43)
𝐴𝐿𝐿𝐿 = 𝐴𝑁𝑂𝐿 − (33) 𝐴𝑇
𝑉𝐿
ANOL is calculated from above 𝑄 ∗ ∆𝑡𝑁𝑆
𝐴𝐿𝐿𝐼𝐿 = 𝐴𝐿𝐼𝐿 − ( 𝑤 ) (44)
ℎ𝑊𝐻 = ℎ𝐿𝐿𝐿𝐿 − 0.1𝑚 (34) 𝑉𝑙
Water nozzle diameter (dnw) has been calculated using
3. Avoid Water from leaving through the Oil outlet equation 34
(hWH – hHHIL ≥ 0.10m) 𝑉𝐻𝑜𝑙𝑑𝑢𝑝 ∗ 𝑄𝑤
𝐴𝐿𝐼𝐿 = 𝐴𝑁𝐼𝐿 − (45)
In vessels with liquid outlets at the bottom of the 𝑄𝑜 ∗ 𝑉𝑙
vessel, weir is used to prevent the water phase from 𝑄 ∗ ∆𝑡𝑁𝑜𝑟
leaving the vessel through the oil outlet. To ensure this, 𝐴𝐿𝐼𝐿 = 𝐴𝑁𝐼𝐿 − ( 𝑤 ) (46)
the difference between the weir height and the high high 𝑉𝑙
interface level is set to be equal to or greater than 0.10m. ℎ𝑁𝐼𝐿
𝐴𝑁𝐼𝐿 = 𝐻𝑇𝑂𝐴 ( ) ∗ 𝐴𝑇 (47)
Failure to enforce this constraint in the separator might 𝑉𝐻
lead to the water flowing over the weir and escaping 2.2.2 Transportation Constraints
through the oil outlet at certain conditions. Therefore,
hHHIL is calculated from AHHIL using; The second group of constraints are new and are
default values. They were derived from the maximum
𝐴𝐻𝐻𝐼𝐿 dimensions allowed for road transport in the UK and US.
ℎ𝐻𝐻𝐼𝐿 = 𝐴𝑇𝑂𝐻 ( )
𝐴𝑇 (35) Most of the work carried out on the sizing of three-phase
∗ 𝐻𝑇 separators does not consider the transportation of these
vessels from the manufacturing to the operation sites.
As mentioned earlier, Norsok guidelines are applicable
Hence, it is necessary to ensure all manufactured vessels
to interface levels. Hence eq. 36 can be represented for
are within the road transport limits. From the literature,
interface levels as;
the maximum length that can be transported by road is
𝑄𝑤 ∆𝑡𝑁𝑆 ≤ 𝑉𝑙 ∗ (𝐴𝑥 − 𝐴𝑦 ) (36) 18.75m and a diameter of 4.23m (Loh, Lyons and White,
Where; x = (HHIL, HIL, NIL, LIL) 2002; UK Government Revenue and Customs; US
y = (HIL, NIL, LIL, LLIL) Department of Transport)
Vl = (𝐿𝐼 + 𝐿𝑔𝑟 + 2𝑑𝑛𝑤 ). Therefore, the following constraints were developed;
AHHIL can be calculated by substituting x and y for The maximum separator diameter (VD) should not be
HHIL and HIL into eq. 36 which becomes; more than 4.23m
𝑄 ∗ ∆𝑡𝑁𝑆
𝐴𝐻𝐻𝐼𝐿 = 𝑤 + 𝐴𝐻𝐼𝐿 (37) VD = Di + 2tc (48)
𝑉𝑙
AHIL can be calculated using the maximum of eqns. 51 The maximum separator length (LT) should not be
and 54; more than 18.75m
𝑄 ∗ ∆𝑡𝑁𝑆 LT = VL + 2(HL + tc) (49)
𝐴𝐻𝐼𝐿 = 𝑤 + 𝐴𝑁𝐼𝐿 (38)
𝑉𝑙 HL = Di/4 (50)
AHIL can also be calculated using the Holdup and surge 2.2.3 Positive Decision Variables Constraints
volume. For interface levels, eqns. 25 and 26 can be
represented as; The third group of constraints are the decision
4
Optimisation of Three-Phase Separators: A Mathematical Model Design
5
Optimisation of Three-Phase Separators: A Mathematical Model Design
obtained from the retention time models within the as low ratios lead to plug flow causing poor separation.
expected range of 3. The results of Svrcek and Monnery The Ahmed et al (2016) results show similar trends for
(1994) are systematically low and show a slight decrease the retention time methods. The length of separators
in the ratio as flow is increased. The consequences of modelled using Abdel Aal and Aggour (2003) and Arnold
using the Svrcek and Monnery (1994) method are that the and Stewart (1998) increases linearly as the water
increase in diameter would produce a more expensive flowrate increases. Ahmed et al., (2016) model produces
separator because of the increase in material thickness separator length that also increase as the water flowrate
required to maintain the internal pressure. It may increases. Dokianos (2015) was found to produce
therefore be concluded that the use of optimisation of cost constant dimensions as in the previous group. All the
in the Ahmed et al., (2016) model leads to a design which diameters were found to be within 1.5 to 1.7 meters
is more in line with those predicted by retention theory excluding Svrcek and Monnery (1994). This same reason
without the need for experimentation. makes its length to be smaller than those of the other
models. Slenderness ratio was found to be within the
4.2 Comparison at Fixed Gas and Oil Flows
range of 1.5 to 5 with Svrcek and Monnery (1994) having
The next step was to fix the gas and oil flowrates at the lowest.
5886m3/hr and 46.2m3/hr respectively and vary the water
flowrate from 6.6 to 33.12 m3/hr. to investigate the effect 4.3 Comparison at Fixed Oil and Water Flows
of water fraction on the separator size. These results are
Finally, it was decided to keep the oil and water flows
reported in Figure 5 and Figure 6. Again, the diameters
constant and vary the gas flow to check the effects of gas
predicted by Svrcek and Monnery (1994) method are
flows on the separator sizes. Results obtained in figure 7
systematically higher than the other methods. When
and 8 indicated that liquid capacity constraint the design
considering the slenderness ratio, the Svrcek and
in all the three models. Hence all the models produce
Monnery (1994) trend is again systematically low and
constant dimensions. Slenderness ratio was found to be
does not show a rise with increasing flow rate. The lower
between 2 to 5. With Dokianos (2015) at 4 and Svrcek
slenderness ratios of less than 2 across the range predicted
and Monnery (1994) at 2.
Svrcek and Monnery (1994) could be a cause for concern
AA – Abdel Aal and Aggour (2003); Arnold – Arnold and Stewart (2008); Svrcek – Svrcek and Monnery (1994)
Ahmed – Developed model; Williams – Dokianos (2015)
6
Optimisation of Three-Phase Separators: A Mathematical Model Design
10
AA (D) AA (L) Arnold (D)
Arnold (L) Svreck (D) Svreck (L)
Length and Diameter (m)
0
0 10 20 30 40
Water flowrate(m3/hr)
Figure 5: Diameter and Length against water flowrate
5.0
4.0
3.0
L/D
2.0
0.0
0 5 10 15 20 25 30 35
Water flowrate (m3/hr)
Figure 6: Slenderness ratio against Water flowrate
7
Optimisation of Three-Phase Separators: A Mathematical Model Design
10
AA (D)
Svreck (D)
4
Svreck (L)
Tariq (D)
2
0
0 2000 4000 6000 8000 10000
Gas Flowrate (m3/hr)
Figure 7: Diameter and Length against gas flowrate
5.0
4.0
3.0
L/D
2.0
0.0
0 2000 4000 6000 8000 10000
Gas Flowrate (m3/hr)
Figure 8: Slenderness ratio against Gas flowrate
8
Optimisation of Three-Phase Separators: A Mathematical Model Design
Arnold, K.E. & Koszola, P.J. 1990, "Droplet-Settling vs. Sayda, A.F. & Taylor, J.H. 2007, "Modeling and Control of
Retention-Time Theories for Sizing Oil/Water Separator", Three-Phase Gravilty Separators in Oil Production
vol. 5, no. 01, pp. 59-64. Facilities", 2007 American Control ConferenceIEEE, , pp.
4847.
Boiler, A. & Code, P.V. 1992, "Section VIII-Division
I", Pressure Vessels, Section UG-27, pp. 24. Seider, W.D., Seader, J., Lewin, D.R. & Widagdo, S. 2008,
"Product and Process Design Principles: Synthesis,
Dokianos, W.P., 2015, March. A simplified approach to sizing Analysis, and Design, Section 9.3".
2 and 3 phase separators for low GOR and low pressure
onshore production batteries. In SPE Production and Silla, H. 2003, Chemical process engineering: design and
Operations Symposium. Society of Petroleum Engineers. economics, CRC Press, United States of America.
Grødal, E.O. & Realff, M.J. 1999, "Optimal design of two-and Smith, H.V. 1987, "Oil and Gas Separators (1987 PEH
three-phase separators: A mathematical programming Chapter 12)" in Society of Petroleum Engineers.
formulation", SPE Annual Technical Conference and
ExhibitionSociety of Petroleum Engineers. Soffian, R.M. & Niven, T. 1993, "Emulsion Treatment
Program", SPE Asia Pacific Oil and Gas
Kaasa, O. 1995, SYNENERGI - Production Chemicals and ConferenceSociety of Petroleum Engineers.
Process Design, Society of Petroleum Engineers.
Svrcek, W. & Monnery, W. 1993, "Design Two-Phase
Loh, H., Lyons, J. & White, C. 2002, Process equipment cost Separators Within", Chemical Engineering Progress.
estimation.Final Report, National Energy Technology
Center, . Winston, W.L. 1994, "Operations research applications and
algorithms", Inc., Belmont, CA.