The quantity of masonry work in arch is calculated by multiplying the mean length of arch by breadth of
wall and by the thickness of arch.
CASE:1 Segmental arch with span and angle given.
Arch of span S subtending an angle at the centre
S= span, = angle at centre, r= radius, rm= mean radius,
Lm= mean length of arch, t= thickness of arch, B= breadth of wall.
𝜃 𝑆⁄ 𝑆 1
𝑆𝑖𝑛 = 2
, 𝑟 = × 𝜃
2 𝑟 2 𝑆𝑖𝑛
2
𝑡
𝑟𝑚 = 𝑟 +
2
𝑙𝑚 𝜃 𝜃
= 360 , 𝑙𝑚 = 2Π𝑟𝑚 ×
2Π𝑟𝑚 360
Quantity of arch masonry work Q = mean length of arch x breadth of wall x thickness of arch
= lm x b x t
1.An arch of 2.5m span subtends an angle of 80 at the centre, the thickness of arch is 30cm and the
breadth of wall is 40cm. Calculate the quantity of arch masonry.
Sol: Given
Span S = 2.5 m, Angle θ = 80o, Thickness t = 30 cm, Breadth B = 40 cm
𝑆 1
𝑟= ×
2 𝑆𝑖𝑛 𝜃
2
𝑡
𝑟𝑚 = 𝑟 +
2
𝜃
𝑙𝑚 = 2Π𝑟𝑚 ×
360
2.5 1 2.5 1 2.5 1
Radius𝑟 = × 80 = × 𝑆𝑖𝑛 40 = × 0.6428 = 1.945m
2 𝑆𝑖𝑛 2 2
2
𝑡 0.30
Mean radius (rm) = 𝑟 + = 1.945 + = 2.095 m
2 2
𝜃 22 80
Mean length of arch lm= 2Π𝑟𝑚 × =2∗ ∗ 2.095 × = 2.930 m
360 7 360
Quantity of arch masonry = lm * breadth of wall * thickness of arch = 2.93 * 0.40 * 0.30
= 0.352 cu.m
CASE: 2Segmental archof 60
Arch over doors and windows are usually segmental subtending an angle of 60 at the centre. 60 arch
forms an equilateral triangle on the span with radii.
S= span, = angle at centre = 60, r= radius, rm= mean radius,
Lm= mean length of arch, t= thickness of arch, B= breadth of wall.
𝑆 1 𝑆 1
𝑟= × 𝜃 =2× 60
2 𝑆𝑖𝑛 𝑆𝑖𝑛
2 2
r=S
𝑡 𝑡
𝑟𝑚 = 𝑟 + 2, 𝑟𝑚 = 𝑆 + 2
𝑙𝑚 𝜃 𝑙𝑚 60 𝑙𝑚 1
= 360 , = 360 , =6
2Π𝑟𝑚 2Π𝑟𝑚 2Π𝑟𝑚
1 1
𝑙𝑚 = × 2Π𝑟𝑚 = × Π𝑟𝑚
6 3
Quantity of arch masonry work Q = mean length of arch x breadth of wall x thickness of arch
= lm x b x t
Example 2: Calculate the quantity of brickwork in a 60 arch over a door of 1.2m width. The arch is
20cm thick and the thickness of the wall is 30 cm.
Sol: Given
Angle(𝜃) = 60o
Width of door (B) = 1.2 m = (r) radius of arch
Thickness of arch (t) = 20 cm
Thickness of wall (t w) = 30 cm
𝑡 0.20
Mean radius (𝑟𝑚 ) = 𝑟 + = 1.20 + = 1.30 m
2 2
1 1 22
Mean length (lm) = 3 × Π𝑟𝑚 = 3 × × 1.30 = 1.36 m
7
Quantity of brick work = mean length of arch (lm) x breadth of wall (B) x thickness of arch (t)
= 1.360 m x 0.30 x 0.20 = 0.082 cu.m
CASE: 3 Segmental arches with span and rise given.
l= length of arch of intrados, r= radius of arch i.e. of intrados, rm= mean radius,
Lm= mean length of arch, t= thickness of arch, B= breadth of wall, a=semi chord= ½ span =S/2, h= rise
of arch
Quantity of arch masonry work Q = mean length of arch x breadth of wall x thickness of arch
= lm x b x t
Note: After finding radius r, the angle subtended at the centre may also be determined as in case I and
them lm may be found.
Example 3: calculate the quantity of brickwork in a segmental arch of 2.2m span, 50cm rise and 30cm
thick. The breadth of the wall is 30cm.
Sol: Given
Span (S) = 2.2 m
Rise (h) = 50 cm = 0.50 m
Thickness (t) = 30 cm = 0.30 m
Breadth (b) = 0.30 m
Quantity of arch masonry = lm x b x t
𝑟𝑚
Where, mean length 𝑙𝑚 = 𝑙 × 𝑟
𝑆2 ℎ 2.22 0.50
𝑟 = 8ℎ + 2 = 8∗0.5 + = 1.46 m
2
𝑡 0.30
𝑟𝑚 = 𝑟 + = 1.46 + = 1.61 m
2 2
8𝑏 − 2𝑎
𝑙=
3
𝑆 2.20
𝑏 = √𝑎2 + ℎ2 , a = 2 = = 1.10 m
2
Here =180
180
𝑙𝑚 = 2Π𝑟𝑚 ×
360
22 𝑆 𝑡
𝑙𝑚 = Π𝑟𝑚 = × (2 + 2)
7
Quantity of arch masonry work Q = mean length of arch x breadth of wall x thickness of arch
= lm x b x t
Example 4: Calculate the quantity of brickwork in a semi-circular arch of 2.00m span, thickness of the
arch is 30cm and the breadth of the wall is 40cm.
Sol: Given
Span S = 2.00 m
Thickness (t) = 30 cm = 0.30 m
Breadth = 40 cm = 0.40 m
𝑆 2
Radius (r) = = 2 = 1.00 m
2
𝑡 𝑠 𝑡 0.30
Mean Radius (rm) = 𝑟 + 2= 2 + 2 = 1.00 + = 1.15m
2
22
Mean length 𝑙𝑚 = Π𝑟𝑚 = ∗ 1.15 = 3.61m
7
Example 5: Calculate the quantity of arch work in flat arch over a door of 1.2m width. The thickness of
arch is 30cm and the breadth of wall is 30cm.
Sol: Given
Width of the door (s) = 1.2m
Thickness (t) = 30 cm = 0.30m
Breadth of the wall (bw) = 30 cm = 0.30m
Quantity of the arch masonry Q = lm x b x t
𝑡1
Mean length (lm) = 𝑆 + 2
S = 1.2 m
𝑡
𝑡1 = = 1.15𝑡 = 1.15 ∗ 0.30 = 0.345𝑚
𝑠𝑖𝑛60
𝑡1 0.345
Mean length (lm) = 𝑆 + = 1.2 + = 1.372m
2 2
Surface in steps 20mm plastered with 1:3 cement sand mortar finished neat cement rendering.
Dimensions
Item Particulars of items of Height
No Quantity Explanatory Note
No work Length Breadth (or)
Depth
10.04
Long Wall 2 6.20 m 0.90 m 0.90 m Length = 5.30 + 0.90 = 6.20 m
cu.m
1
5.51
Short Wall 2 3.40 m 0.90 m 0.90 m Breadth = 4.30 - 0.90 = 3.40 m
cu.m
Total 15.55 cu.m
Concrete in foundation
Long Wall 2 6.20 m 0.90 m 0.30 m 3.35 cu.m
2
Short Wall 2 3.40 m 0.90 m 0.30 m 1.83 cu.m
1st footing 2 3.70 m 0.60 m 0.30 m 1.33 cu.m Length = 4.30 - 0.60 = 3.70 m
2nd footing 2 3.80 m 0.50 m 0.30 m 1.14 cu.m Length = 4.30 - 0.50 = 3.80 m
Plinth wall 2 3.90 m 0.40 m 0.60 m 1.87 cu.m Length = 4.30 - 0.40 = 3.90 m
Long Wall
Length = 5.30 + 0.30 = 5.60
4 1st footing 2 5.60 m 0.30 m 3.50 m 11.76 cu.m
m
2nd footing 2 4.00 m 0.30 m 3.50 m 8.40 cu.m Length = 4.30 - 0.30 = 4.00 m
Estimate the quantities of the following items of a two roomed building from the given plan and
section
1. Earth work in excavation in foundation
2. Lime concrete in foundation
st
3. 1 class brick work in cement mortar 1:6 in foundation and plinth
4. 2.5 cm DPC
st
5. 1 class brick work in lime mortar in superstructure
0.30
The length of long wall from centre to centre = 4 + 6 + 0.30 + 2 ∗ = 10.60𝑚
2
0.30
The length of short wall from centre to centre =6 + 2 ∗ = 6.30𝑚
2
Quantity Estimation:
Dimensions
Item Particulars of items of Height
No Quantity Explanatory Note
No work Length Breadth (or)
Depth
Long Wall
11.40 3.65 Length = 10.60 + 0.80 =
1st footing 2 0.80 m 0.20 m
m cu.m 11.40 m
11.30 1.58 Length = 10.60 + 0.70 =
2nd footing 2 0.70 m 0.10 m
m cu.m 11.30 m
11.20 1.34 Length = 10.60 + 0.60 =
3rd footing 2 0.60 m 0.10 m
m cu.m 11.20 m
3
11.10 1.11 Length = 10.60 + 0.50 =
4th footing 2 0.50 m 0.10 m
m cu.m 11.10 m
11.00 7.04 Length = 10.60 + 0.40 =
Plinth wall above footing 2 0.40 m 0.80 m
m cu.m 11.00 m
Short Wall
2.64 Length = 6.30 - 0.80 = 5.50
1st footing 3 5.50 m 0.80 m 0.20 m
cu.m m
2nd footing 3 5.60 m 0.70 m 0.10 m 1.18 Length = 6.30 - 0.70 = 5.60
cu.m m
Deductions
5
1.51
Door Openings 2 1.20 m 0.30 m 2.10 m
cu.m
1.80
Window Openings 4 1.00 m 0.30 m 1.50 m
cu.m
0.60 Back of shelves 10 cm thick
Shelves 2 1.00 m 0.20 m 1.50 m
cu.m wall
0.14
Lintels over doors 2 1.50 m 0.30 m 0.15 m Bearing 15 cm
cu.m
0.23
Lintels over windows 4 1.30 m 0.30 m 0.15 m Bearing 15 cm
cu.m
0.12
Lintels over shelves 2 1.30 m 0.30 m 0.15 m Bearing 15 cm
cu.m
Total Deduction 4.40 cu.m
Front Verandah:
0.30 0.20
Front wall C to C length =5.00 + 4.00 + 2 ∗ 0.30 + − = 9.65𝑚
2 2
0.30 0.20
Side wall C to C length = 2.00 + + = 2.25𝑚
2 2
Dimensions
Item Particulars of items of Height
No Quantity Explanatory Note
No work Length Breadth (or)
Depth
Earth work in excavation in foundation - Drawing room and left bed room
11.50 20.70 Length = 10.60 + 0.90 =
Long Wall 2 0.90 m 1.00 m
m cu.m 11.50 m
11.88 Length = 5.30 - 0.90 =
Short Wall 3 4.40 m 0.90 m 1.00 m
cu.m 4.40 m
Earth work excavation in Bed room right side (Both Combined)
17.28 Length = 9.60 + 0.90/2 -
Long Wall 2 9.60 m 0.90 m 1.00 m
cu.m 0.90/2 = 9.60 m
1
Length = 4.80 - 0.90 =
Short Wall 2 3.90 m 0.90 m 1.00 m 7.02 cu.m
3.90 m
Earth work excavation in Front verendah
Length = 9.65 - 0.90/2 +
Front Long Wall 1 9.50 m 0.60 m 0.50 m 2.85 cu.m
0.60/2 = 9.50 m
Length = 2.25 - 0.90/2 -
Side Short Wall 1 1.50 m 0.60 m 0.50 m 0.45 cu.m
0.60/2 = 1.50 m
Earth work excavation in Back verendah including bathroom
Long Wall (rear wall Length = 9.65 - 0.90/2 +
1 9.50 m 0.60 m 0.50 m 2.85 cu.m
including bath) 0.60/2 = 9.50 m
Short wall (remaining Length = 2.75 - 0.90/2 -
2 2.00 m 0.60 m 0.50 m 1.20 cu.m
walls of bath) 0.60/2 = 2.00 m
Total 64.23 cu.m
1st class Brick work in foundation and plinth in Drawing & left bedroom
Long Wall
11.20 Length = 10.60 + 0.60 =
1st footing 2 0.60 m 0.20 m 2.69 cu.m
m 11.20 m
11.10 Length = 11.20 - 2*0.05 =
2nd footing 2 0.50 m 0.20 m 2.22 cu.m
m 11.10 m
11.00 Length = 11.10 - 0.10 =
3 Plinth wall above footing 2 0.40 m 0.90 m 7.92 cu.m
m 11.00 m
Short Wall
Length = 5.30 - 0.60 =
1st footing 3 4.70 m 0.60 m 0.20 m 1.69 cu.m
4.70 m
Length = 4.70 + 2*0.05 =
2nd footing 3 4.80 m 0.50 m 0.20 m 1.44 cu.m
4.80 m
Length = 4.80 + 0.10 =
Plinth wall above footing 3 4.90 m 0.40 m 0.90 m 5.29 cu.m
4.90 m
1st class Brick work in Bed room right side (Both Combined)
Long Wall
Length = 9.60 - 0.60/2 +
1st footing 2 9.60 m 0.60 m 0.20 m 2.31 cu.m
0.60/2 = 9.60 m
Length = 9.60 - 0.50/2 +
2nd footing 2 9.60 m 0.50 m 0.20 m 1.92 cu.m
0.50/2 = 9.60 m
Length = 9.60 - 0.40/2 +
Plinth wall above footing 2 9.60 m 0.40 m 0.90 m 6.91 cu.m
0.40/2 = 9.60 m
Short Wall
Length = 4.80 - 0.60 =
1st footing 2 4.20 m 0.60 m 0.20 m 1.01 cu.m
4.20 m
Length = 4.80 + 2*0.05 =
2nd footing 2 4.30 m 0.50 m 0.20 m 0.86 cu.m
4.30 m
Length = 4.30 + 0.10 =
Plinth wall above footing 2 4.40 m 0.40 m 0.90 m 3.17 cu.m
4.40 m
1st class Brick work in Front verendah
Long Wall
Deductions
1st class Brick work in super structure - Drawing & left bedroom
10.90 26.16 Length = 10.60 + 0.30 =
Long Wall 2 0.30 m 4.00 m
m cu.m 10.90 m
18.00 Length = 5.30 - 0.30 =
Short Wall 3 5.00 m 0.30 m 4.00 m
cu.m 5.00 m
1st class Brick work in super structure - Bed room right side (Both Combined)
23.04 Length = 9.60 - 0.30/2 +
5 Long Wall 2 9.60 m 0.30 m 4.00 m
cu.m 0.30/2 = 9.60 m
10.80 Length = 4.80 - 0.30 =
Short Wall 2 4.50 m 0.30 m 4.00 m
cu.m 4.50 m
1st class Brick work in super structure - Front verendah
Length = 9.65 - 0.30/2 +
Front wall as Solid 1 9.60 m 0.20 m 3.05 m 5.86 cu.m
0.20/2 = 9.60 m
Side wall as Solid 1 2.00 m 0.20 m 3.05 m 1.22 cu.m
1st class Brick work in super structure - Back verendah including bathroom
Length same as front
Back long wall as solid 1 9.60 m 0.20 m 3.05 m 5.86 cu.m
verendah
Side and Inner wall bath 2 2.50 m 0.20 m 3.05 m 3.05 cu.m
Deductions
Door Openings
Window Openings
Overs Doors
0.405
Door D1 6 1.50 m 0.30 m 0.15 m Bearing 15 cm
cu.m
0.117
Door D2 2 1.30 m 0.30 m 0.15 m Bearing 15 cm
cu.m
0.029
Door D3 1 0.95 m 0.20 m 0.15 m Bearing 10 cm
cu.m
Over Windows
0.644
Window W1 11 1.30 m 0.30 m 0.15 m Bearing 15 cm
cu.m
0.103
Window W2 1 2.30 m 0.30 m 0.15 m Bearing 15 cm
cu.m
0.057
Window W3 3 0.95 m 0.20 m 0.15 m Bearing 10 cm
cu.m
0.770
Over C.W 18 0.95 m 0.30 m 0.15 m Bearing 10 cm
cu.m
0.293
Over Shelves 5 1.30 m 0.30 m 0.15 m Bearing 15 cm
cu.m
Verendah lintels
0.293 Length = 9.60 + 0.15 =
Front 1 9.75 m 0.20 m 0.15 m
cu.m 9.75 m
0.065 Length = 2.00 + 0.15 =
Side 1 2.15 m 0.20 m 0.15 m
cu.m 2.15 m
0.225 Length = 9.60 - 2.40 + 2 *
Back 1 7.50 m 0.20 m 0.15 m
cu.m 0.15 = 7.50 m
Total Deduction 27.401 cu.m
Square Room:
0.30 0.30
Long Walls = 3.60 + + = 3.90 𝑚
2 2
0.30 0.30
Short Walls = 3.60 + + = 3.90 𝑚
2 2
Front Verandah:
0.30 0.30
Long Walls = 3.60 + + = 3.90 𝑚
2 2
Dimensions
Item Particulars of Height
No Quantity Explanatory Note
No items of work Length Breadth (or)
Depth
16.36
Long Walls 2 10.10 m 0.90 m 0.90 m Length = 9.20 + 0.90 = 10.10 m
cu.m
4.86
Short Walls 2 3.00 m 0.90 m 0.90 m Length = 3.90 - 0.90 = 3.00 m
cu.m
0.72
Inter 20 cm wall 1 3.00 m 0.60 m 0.40 m Length = 3.90 - 0.90 = 3.00 m
1 cu.m
Long Walls 1 4.80 m 0.90 m 0.90 m 3.88 cu.m Length = 3.90 + 0.90 = 4.80 m
Short Walls 2 3.00 m 0.90 m 0.90 m 4.86 cu.m Length = 3.90 - 0.90 = 3.00 m
Verendah dwarf
Long Walls
2 3.00 m 0.40 m 0.20 m 0.48 cu.m Length = 3.90 - 0.90 = 3.00 m
(Front & Back)
Short Walls
1 1.10 m 0.40 m 0.20 m 0.09 cu.m Length = 2.00 - 0.90 = 1.10 m
(Front Side)
Short Walls
1 1.80 m 0.40 m 0.20 m 0.15 cu.m Length = 2.70 - 0.90 = 1.80 m
(Back Side)
Steps 1 1.20 m 0.70 m 0.10 m 0.08 cu.m
Inter 20 cm wall 1 3.40 m 0.90 m 0.20 m 0.41 cu.m Length = 3.90 - 0.50 = 3.40 m
Long Walls 1 4.80 m 0.90 m 0.30 m 1.30 cu.m Length = 3.90 + 0.90 = 4.80 m
Short Walls 2 3.00 m 0.90 m 0.30 m 1.62 cu.m Length = 3.90 - 0.90 = 3.00 m
2 Verendah Pillars 2 0.90 m 0.90 m 0.30 m 0.49 cu.m
1st class Brick work in foundation and plinth - Adjoining Room Combined (Long Walls)
1st footing 2 9.80 m 0.60 m 0.20 m 2.35 cu.m Length = 9.20 + 0.60 = 9.80 m
3
2nd footing 2 9.70 m 0.50 m 0.20 m 1.94 cu.m Length = 9.80 - 0.10 = 9.70 m
Plinth Wall 2 9.60 m 0.40 m 0.65 m 4.99 cu.m Length = 9.70 - 0.10 = 9.60 m
1st class Brick work in foundation and plinth - Adjoining Room Combined (Short Walls)
1st footing 2 3.30 m 0.60 m 0.20 m 0.79 cu.m Length = 3.90 - 0.60 = 3.30 m
2nd footing 2 3.40 m 0.50 m 0.20 m 0.68 cu.m Length = 3.30 + 0.10 = 3.40 m
Plinth Wall 2 3.50 m 0.40 m 0.65 m 1.82 cu.m Length = 3.40 + 0.10 = 3.50 m
Inter 20 cm wall 1 3.50 m 0.30 m 0.65 m 0.68 cu.m Length = 3.90 - 0.40 = 3.50 m
1st class Brick work in foundation and plinth - Square Room (Long Wall)
1st footing 1 4.50 m 0.60 m 0.20 m 0.54 cu.m Length = 3.90 + 0.60 = 4.50 m
2nd footing 1 4.40 m 0.50 m 0.20 m 0.44 cu.m Length = 4.50 - 0.10 = 4.40 m
Plinth Wall 1 4.30 m 0.40 m 0.65 m 1.12 cu.m Length = 4.40 - 0.10 = 4.30 m
1st class Brick work in foundation and plinth - Square Room (Short Wall)
1st footing 2 3.30 m 0.60 m 0.20 m 0.79 cu.m Length = 3.90 - 0.60 = 3.30 m
2nd footing 2 3.40 m 0.50 m 0.20 m 0.68 cu.m Length = 3.30 + 0.10 = 3.40 m
Plinth Wall 2 3.50 m 0.40 m 0.65 m 1.82 cu.m Length = 3.40 + 0.10 = 3.50 m
1st class Brick work in foundation and plinth - Verendah Dwarf Walls
Long Walls
2 3.50 m 0.20 m 0.55 m 0.77 cu.m Length = 3.90 - 0.40 = 3.50 m
(Front & Back)
Short Walls
1 1.60 m 0.20 m 0.55 m 0.18 cu.m Length = 2.00 - 0.40 = 1.60 m
(Front Side)
Short Walls
1 2.30 m 0.20 m 0.55 m 0.25 cu.m Length = 2.70 - 0.40 = 2.30 m
(Back Side)
1st class Brick work in foundation and plinth - Steps
Long Walls 2 9.60 m 0.40 m - 7.68 cu.m Length = 9.70 - 0.10 = 9.60 m
Short Walls 2 3.50 m 0.40 m - 2.80 cu.m Length = 3.40 + 0.10 = 3.50 m
Inter 20 cm wall 1 3.50 m 0.30 m - 1.05 cu.m Length = 3.90 - 0.40 = 3.50 m
Long Walls 1 4.30 m 0.40 m - 1.72 cu.m Length = 4.40 - 0.10 = 4.30 m
Short Walls 2 3.50 m 0.40 m - 2.80 cu.m Length = 3.40 + 0.10 = 3.50 m
4
Verendah Pillars 2 0.40 m 0.40 m - 0.32 cu.m
Deductions
Long Walls 2 9.50 m 0.30 m 3.62 m 20.63 cu.m Height up to top of slab
Short Walls 2 3.60 m 0.30 m 3.62 m 7.82 cu.m Height up to top of slab
Inter 20 cm wall 1 3.60 m 0.30 m 3.50 m 2.52 cu.m Height up to bottom of slab
Long Walls 1 4.20 m 0.30 m 3.62 m 4.56 cu.m Length = 3.90 + 0.30 = 4.20 m
Short Walls 2 3.60 m 0.30 m 3.62 m 7.82 cu.m Length = 3.90 - 0.30 = 3.60 m
5
Verendah Pillars 2 0.30 m 0.30 m 2.80 m 0.50 cu.m
Adjoining Rooms
Long Walls 1 9.50 m 0.20 m 0.50 m 0.95 cu.m Length = 9.20 + 0.30 = 9.50 m
Length = 3.60 + 0.30 + 0.10 =
Short Walls 2 4.00 m 0.20 m 0.50 m 0.80 cu.m
4.00 m
Front Verendah
1 2.40 m 0.20 m 0.50 m 0.24 cu.m Length = 1.80 + 0.60 = 2.40 m
Side
Back Verendah Length = 2.50 + 0.20 - 0.20 =
1 2.50 m 0.20 m 0.50 m 0.25 cu.m
Side 2.50 m
Square room -
1 4.20 m 0.20 m 0.50 m 0.42 cu.m Length = 3.60 + 0.60 = 4.20 m
Outer Wall
Wall B/W
Length = 3.60 + 0.20 + 0.10 =
Verendah & 2 3.90 m 0.20 m 0.50 m 0.78 cu.m
3.90 m
Room
Total 47.96 cu.m
Deductions
Door Openings
Window Openings
R.C.C Work 1 : 2 : 4
Two rooms
1 9.20 m 3.90 m 0.12 m 4.306 cu.m Bearing 15 cm
Combined
Square room 1 3.90 m 3.90 m 0.12 m 1.825 cu.m Bearing 15 cm
Verendah lintels
Total centre length of wall = 2 * C-C of long wall length + 3 * C-C of short wall length
Total center length of all 30 cm walls = Total center length of walls of drawing and left side bed room +
Total center length of wall of bed rooms right side
Total center length of 20 cm wall = (C.C of long front wall + C.C length of side wall) + (C.C length of
back verandah long wall including bath + 2 * C.C length of cross walls of bathroom)
Total center length of 20 cm wall = (9.65 + 2.25) + (9.65 + 2 * 2.75) = 11.90 + 15.15
Dimensions
Item Particulars of items of Height
No Quantity Explanatory Note
No work Length Breadth (or)
Depth
Earth work in
excavation in 63.20 56.88 Length = 65.90 - 6 * 0.90/2 = 63.20
1 0.90 m 1.00 m
foundation - (Wall with m cu.m m
main room six junctions)
Earth work in
1
excavation in
24.50 Length = 27.50 - 5 * 0.90/2 - 1 *
foundation - (Walls of 1 0.60 m 0.50 m 7.35 cu.m
m 0.60/2 = 24.50 m
verendahsincludig bath (
five and one junctions)
Lime Concrete in
63.20 17.06 Length = 65.90 - 6 * 0.90/2 = 63.20
2 foundation - (Wall with 1 0.90 m 0.30 m
m cu.m m
main room six junctions)
Lime Concrete in
foundation - (Walls of 25.50 3.06 Length = 27.50 - 5 * 0.50/2 - 1 *
1 0.60 m 0.20 m
verendahsincludig bath ( m cu.m 0.60/2 = 25.50 m
five and one junctions)
1st class Brick work in foundation and plinth - (Wall with main room six junctions)
1st class Brick work in foundation and plinth - (Walls of verendahs including bath ( five and one junctions)
0.60
Verendah Pillars 4 0.50 m 0.30 m -
sq.m
Deductions
2.88
Door sills D1 6 1.20 m 0.40 m -
sq.m
0.80
Door sills D2 2 1.00 m 0.40 m -
sq.m
0.23
Door sills D3 1 0.75 m 0.30 m -
sq.m
Deductions
Door Openings
4.54
Door Openings D1 6 1.20 m 0.30 m 2.10 m
cu.m
1.20
Door Openings D2 2 1.00 m 0.30 m 2.00 m
cu.m
5
0.27
Door Openings D3 1 0.75 m 0.20 m 1.80 m
cu.m
Window Openings
4.95
Window Openings W1 11 1.00 m 0.30 m 1.50 m
cu.m
0.90
Window Openings W2 1 2.00 m 0.30 m 1.50 m
cu.m
0.36
Window Openings W3 2 0.75 m 0.20 m 1.20 m
cu.m
1.50
Shelves openings 5 1.00 m 0.20 m 1.50 m Back of shelves 10 cm thick wall
cu.m
Front verendah openings 4.03
1 8.40 m 0.20 m 2.40 m Length = 9.60 - 3 * 0.40 = 8.40 m
in between pillars cu.m
3.26
Back verendah opening 1 6.80 m 0.20 m 2.40 m Length = 9.60 - 2.40 - 0.40 = 6.80 m
cu.m
Lintels
Overs Doors
0.405
Door D1 6 1.50 m 0.30 m 0.15 m Bearing 15 cm
cu.m
0.117
Door D2 2 1.30 m 0.30 m 0.15 m Bearing 15 cm
cu.m
0.029
Door D3 1 0.95 m 0.20 m 0.15 m Bearing 10 cm
cu.m
Over Windows
0.644
Window W1 11 1.30 m 0.30 m 0.15 m Bearing 15 cm
cu.m
0.103
Window W2 1 2.30 m 0.30 m 0.15 m Bearing 15 cm
cu.m
0.057
Window W3 3 0.95 m 0.20 m 0.15 m Bearing 10 cm
cu.m
0.770
Over C.W 18 0.95 m 0.30 m 0.15 m Bearing 10 cm
cu.m
0.293
Over Shelves 5 1.30 m 0.30 m 0.15 m Bearing 15 cm
cu.m
Verendah lintels
0.293
Front 1 9.75 m 0.20 m 0.15 m Length = 9.60 + 0.15 = 9.75 m
cu.m
0.065
Side 1 2.15 m 0.20 m 0.15 m Length = 2.00 + 0.15 = 2.15 m
cu.m
0.225 Length = 9.60 - 2.40 + 2 * 0.15 =
Back 1 7.50 m 0.20 m 0.15 m
cu.m 7.50 m