You are on page 1of 52

ARCH MASONRY CALCULATION

The quantity of masonry work in arch is calculated by multiplying the mean length of arch by breadth of
wall and by the thickness of arch.
CASE:1 Segmental arch with span and angle given.
Arch of span S subtending an angle  at the centre
S= span, = angle at centre, r= radius, rm= mean radius,
Lm= mean length of arch, t= thickness of arch, B= breadth of wall.
𝜃 𝑆⁄ 𝑆 1
𝑆𝑖𝑛 = 2
, 𝑟 = × 𝜃
2 𝑟 2 𝑆𝑖𝑛
2

𝑡
𝑟𝑚 = 𝑟 +
2
𝑙𝑚 𝜃 𝜃
= 360 , 𝑙𝑚 = 2Π𝑟𝑚 ×
2Π𝑟𝑚 360

Quantity of arch masonry work Q = mean length of arch x breadth of wall x thickness of arch
= lm x b x t
1.An arch of 2.5m span subtends an angle of 80 at the centre, the thickness of arch is 30cm and the
breadth of wall is 40cm. Calculate the quantity of arch masonry.
Sol: Given
Span S = 2.5 m, Angle θ = 80o, Thickness t = 30 cm, Breadth B = 40 cm
𝑆 1
𝑟= ×
2 𝑆𝑖𝑛 𝜃
2
𝑡
𝑟𝑚 = 𝑟 +
2
𝜃
𝑙𝑚 = 2Π𝑟𝑚 ×
360
2.5 1 2.5 1 2.5 1
Radius𝑟 = × 80 = × 𝑆𝑖𝑛 40 = × 0.6428 = 1.945m
2 𝑆𝑖𝑛 2 2
2

𝑡 0.30
Mean radius (rm) = 𝑟 + = 1.945 + = 2.095 m
2 2
𝜃 22 80
Mean length of arch lm= 2Π𝑟𝑚 × =2∗ ∗ 2.095 × = 2.930 m
360 7 360

Quantity of arch masonry = lm * breadth of wall * thickness of arch = 2.93 * 0.40 * 0.30
= 0.352 cu.m
CASE: 2Segmental archof 60
Arch over doors and windows are usually segmental subtending an angle of 60 at the centre. 60 arch
forms an equilateral triangle on the span with radii.
S= span, = angle at centre = 60, r= radius, rm= mean radius,
Lm= mean length of arch, t= thickness of arch, B= breadth of wall.
𝑆 1 𝑆 1
𝑟= × 𝜃 =2× 60
2 𝑆𝑖𝑛 𝑆𝑖𝑛
2 2

r=S
𝑡 𝑡
𝑟𝑚 = 𝑟 + 2, 𝑟𝑚 = 𝑆 + 2
𝑙𝑚 𝜃 𝑙𝑚 60 𝑙𝑚 1
= 360 , = 360 , =6
2Π𝑟𝑚 2Π𝑟𝑚 2Π𝑟𝑚

1 1
𝑙𝑚 = × 2Π𝑟𝑚 = × Π𝑟𝑚
6 3
Quantity of arch masonry work Q = mean length of arch x breadth of wall x thickness of arch
= lm x b x t
Example 2: Calculate the quantity of brickwork in a 60 arch over a door of 1.2m width. The arch is
20cm thick and the thickness of the wall is 30 cm.
Sol: Given
Angle(𝜃) = 60o
Width of door (B) = 1.2 m = (r) radius of arch
Thickness of arch (t) = 20 cm
Thickness of wall (t w) = 30 cm
𝑡 0.20
Mean radius (𝑟𝑚 ) = 𝑟 + = 1.20 + = 1.30 m
2 2
1 1 22
Mean length (lm) = 3 × Π𝑟𝑚 = 3 × × 1.30 = 1.36 m
7

Quantity of brick work = mean length of arch (lm) x breadth of wall (B) x thickness of arch (t)
= 1.360 m x 0.30 x 0.20 = 0.082 cu.m
CASE: 3 Segmental arches with span and rise given.
l= length of arch of intrados, r= radius of arch i.e. of intrados, rm= mean radius,
Lm= mean length of arch, t= thickness of arch, B= breadth of wall, a=semi chord= ½ span =S/2, h= rise
of arch

From similar figures,


𝑙𝑚 𝑟𝑚 𝑟𝑚
= 𝑜𝑟 𝑙𝑚 = 𝑙 ×
𝑙 𝑟 𝑟
To find radius r,
𝑟 2 = 𝑎 2 + (𝑟 − ℎ ) 2
𝑆 2
𝑟 = ( ) + 𝑟 2 + ℎ2 − 2𝑟ℎ
2
2
𝑆2
+ ℎ2 = 2𝑟ℎ
4
𝑆 2 ℎ2
𝑟= +
8ℎ 2ℎ
𝑆2 ℎ
𝑟= +
8ℎ 2
𝑡
𝑟𝑚 = 𝑟 +
2
To findthe length of intrados, l
8𝑏−2𝑎
Mensuration formula 𝑙 = 3
𝑆
8𝑏 − 2 2
𝑙=
3
𝑏 = √𝑎2 + ℎ2
A and h being known, b can be determined, and hence l can be found.
𝑟𝑚
r, rm and l being calculated, lm can be found 𝑙𝑚 = 𝑙 × 𝑟

Quantity of arch masonry work Q = mean length of arch x breadth of wall x thickness of arch
= lm x b x t
Note: After finding radius r, the angle  subtended at the centre may also be determined as in case I and
them lm may be found.

Example 3: calculate the quantity of brickwork in a segmental arch of 2.2m span, 50cm rise and 30cm
thick. The breadth of the wall is 30cm.
Sol: Given
Span (S) = 2.2 m
Rise (h) = 50 cm = 0.50 m
Thickness (t) = 30 cm = 0.30 m
Breadth (b) = 0.30 m
Quantity of arch masonry = lm x b x t
𝑟𝑚
Where, mean length 𝑙𝑚 = 𝑙 × 𝑟
𝑆2 ℎ 2.22 0.50
𝑟 = 8ℎ + 2 = 8∗0.5 + = 1.46 m
2
𝑡 0.30
𝑟𝑚 = 𝑟 + = 1.46 + = 1.61 m
2 2

8𝑏 − 2𝑎
𝑙=
3
𝑆 2.20
𝑏 = √𝑎2 + ℎ2 , a = 2 = = 1.10 m
2

𝑏 = √1.102 + 0.502 = 1.21 m


8∗1.21−2∗1.10
𝑙= = 2.49 m
3
1.61
Mean length 𝑙𝑚 = 2.49 × 1.46 = 2.75 m

Quantity of arch masonry Q = lm x b x t = 2.75 x 0.30 x 0.30 = 0.247 cu.m


CASE: 4 Semi-circular arches
S= span, r=radius of arch, rm = mean radius, h=rise, lm= mean length of arch
Radius r= S/2
Rise h=S/2
Mean radius r m = (r+t/2)= (S/2+t/2)
𝜃
Mean length 𝑙𝑚 = 2Π𝑟𝑚 × 360

Here =180
180
𝑙𝑚 = 2Π𝑟𝑚 ×
360
22 𝑆 𝑡
𝑙𝑚 = Π𝑟𝑚 = × (2 + 2)
7

Quantity of arch masonry work Q = mean length of arch x breadth of wall x thickness of arch
= lm x b x t
Example 4: Calculate the quantity of brickwork in a semi-circular arch of 2.00m span, thickness of the
arch is 30cm and the breadth of the wall is 40cm.
Sol: Given
Span S = 2.00 m
Thickness (t) = 30 cm = 0.30 m
Breadth = 40 cm = 0.40 m
𝑆 2
Radius (r) = = 2 = 1.00 m
2
𝑡 𝑠 𝑡 0.30
Mean Radius (rm) = 𝑟 + 2= 2 + 2 = 1.00 + = 1.15m
2
22
Mean length 𝑙𝑚 = Π𝑟𝑚 = ∗ 1.15 = 3.61m
7

Quantity of arch work Q = lm x b x t = 3.61 x 0.40 x 0.30 = 0.433 cu.m


CASE: 5Flat arches
May be used over doors and windows for small spans, but a small camber should be given.
Flat arch usually subtends an angle of 60 at the centre and forms an
equilateral triangle.
Inclined thickness of arch at the springing point t 1 = t/sin 60
= t/0.866=1.15t
Mean length of arch lm = S+(t1/2)
Quantity of arch masonry work Q = mean length of arch x breadth
of wall x thickness of arch
= lm x b x t
For practical purposes t1 may be considered as equal to t and mean
length of arch may be taken as lm= S+(t/2).

Example 5: Calculate the quantity of arch work in flat arch over a door of 1.2m width. The thickness of
arch is 30cm and the breadth of wall is 30cm.
Sol: Given
Width of the door (s) = 1.2m
Thickness (t) = 30 cm = 0.30m
Breadth of the wall (bw) = 30 cm = 0.30m
Quantity of the arch masonry Q = lm x b x t
𝑡1
Mean length (lm) = 𝑆 + 2

S = 1.2 m
𝑡
𝑡1 = = 1.15𝑡 = 1.15 ∗ 0.30 = 0.345𝑚
𝑠𝑖𝑛60
𝑡1 0.345
Mean length (lm) = 𝑆 + = 1.2 + = 1.372m
2 2

Quantity of the arch work Q = lm x b x t = 1.372 x 0.30 x 0.30 = 1.23m


ESTIMATING OF SIMPLE STEPS
Steps are usually constructed when the construction of the building has progressed sufficiently and the
earthwork in foundation for step needs excavation afresh. The earthwork in excavation for step is
usually neglected.

Surface in steps 20mm plastered with 1:3 cement sand mortar finished neat cement rendering.

Length Breadth Height or


S.No. Items No. Quantity Units
m m Depth m
1 Earthwork in excavation 1 1.9 0.95 0.15 0.27075 cu m
2 concrete in foundation 1 1.9 0.95 0.1 0.1805 cu m
Brickwork-- 1st step 1 1.8 0.9 0.2 0.324 cu m
3 2nd step 1 1.8 0.6 0.15 0.162 cu m
3rd step 1 1.8 0.3 0.15 0.081 cu m
Total 0.567 cu m
Finishing 20mm cement plastered
4
Treads 3 1.8 0.3 - 1.62 sq.m
Risers 4 1.8 - 0.15 1.08 sq.m
2 0.9 - 0.15 0.27 sq.m
Ends 2 0.6 - 0.15 0.18 sq.m
2 0.3 - 0.15 0.09 sq.m
Total 3.24 sq.m
SINGLE ROOM – LONG WALL & SHORT WALL METHOD
 By using the plan which is representing the plan of super structure wall of a single room
building of 5m x 4m and sections represent the cross-sections of the walls with foundation.

Estimate the quantities of –


1. Earthwork for excavation in foundation
2. Concrete in foundation
3. Brick work in foundation and plinth
4. Brick work in super structure
QUANTITY ESTIMATION:
1 1
The length of long wall from centre to centre = 5.00 + 2 ∗ 0.30 + 2 ∗ 0.30 = 5.30𝑚
1 1
The length of short wall from centre to centre =4.00 + 2 ∗ 0.30 + 2 ∗ 0.30 = 4.30𝑚

Dimensions
Item Particulars of items of Height
No Quantity Explanatory Note
No work Length Breadth (or)
Depth

Earth work in excavation in foundation

10.04
Long Wall 2 6.20 m 0.90 m 0.90 m Length = 5.30 + 0.90 = 6.20 m
cu.m
1
5.51
Short Wall 2 3.40 m 0.90 m 0.90 m Breadth = 4.30 - 0.90 = 3.40 m
cu.m
Total 15.55 cu.m
Concrete in foundation
Long Wall 2 6.20 m 0.90 m 0.30 m 3.35 cu.m
2
Short Wall 2 3.40 m 0.90 m 0.30 m 1.83 cu.m

Total 5.18 cu.m

Brick work in foundation and plinth


3
Long Wall
Length = 5.30 + 0.60 = 5.90
1st footing 2 5.90 m 0.60 m 0.30 m 2.13 cu.m
m
Length = 5.30 + 0.50 = 5.80
2nd footing 2 5.80 m 0.50 m 0.30 m 1.74 cu.m
m
Length = 5.30 + 0.40 = 5.70
Plinth wall 2 5.70 m 0.40 m 0.60 m 2.74 m
m
Short Wall

1st footing 2 3.70 m 0.60 m 0.30 m 1.33 cu.m Length = 4.30 - 0.60 = 3.70 m

2nd footing 2 3.80 m 0.50 m 0.30 m 1.14 cu.m Length = 4.30 - 0.50 = 3.80 m

Plinth wall 2 3.90 m 0.40 m 0.60 m 1.87 cu.m Length = 4.30 - 0.40 = 3.90 m

Total 10.95 cu.m

Brick work in superstructure

Long Wall
Length = 5.30 + 0.30 = 5.60
4 1st footing 2 5.60 m 0.30 m 3.50 m 11.76 cu.m
m
2nd footing 2 4.00 m 0.30 m 3.50 m 8.40 cu.m Length = 4.30 - 0.30 = 4.00 m

Total 20.16 cu.m


DOUBLE ROOM – LONG WALL & SHORT WALL METHOD

 Estimate the quantities of the following items of a two roomed building from the given plan and
section
1. Earth work in excavation in foundation
2. Lime concrete in foundation
st
3. 1 class brick work in cement mortar 1:6 in foundation and plinth
4. 2.5 cm DPC
st
5. 1 class brick work in lime mortar in superstructure

0.30
The length of long wall from centre to centre = 4 + 6 + 0.30 + 2 ∗ = 10.60𝑚
2
0.30
The length of short wall from centre to centre =6 + 2 ∗ = 6.30𝑚
2

Quantity Estimation:
Dimensions
Item Particulars of items of Height
No Quantity Explanatory Note
No work Length Breadth (or)
Depth

Earth work in excavation in foundation

11.70 25.74 Length = 10.60 + 1.10 =


Long Wall 2 1.10 m 1.00 m
m cu.m 11.70 m
1
17.16 Length = 6.30 - 1.10 = 5.20
Short Wall 3 5.20 m 1.10 m 1.00 m
cu.m m
Total 42.90 cu.m
Lime Concrete in foundation
11.70 7.72
Long Wall 2 1.10 m 0.30 m
m cu.m
2
5.15
Short Wall 3 5.20 m 1.10 m 0.30 m
cu.m
Total 12.87 cu.m

1st class Brick work in foundation and plinth

Long Wall
11.40 3.65 Length = 10.60 + 0.80 =
1st footing 2 0.80 m 0.20 m
m cu.m 11.40 m
11.30 1.58 Length = 10.60 + 0.70 =
2nd footing 2 0.70 m 0.10 m
m cu.m 11.30 m
11.20 1.34 Length = 10.60 + 0.60 =
3rd footing 2 0.60 m 0.10 m
m cu.m 11.20 m
3
11.10 1.11 Length = 10.60 + 0.50 =
4th footing 2 0.50 m 0.10 m
m cu.m 11.10 m
11.00 7.04 Length = 10.60 + 0.40 =
Plinth wall above footing 2 0.40 m 0.80 m
m cu.m 11.00 m
Short Wall
2.64 Length = 6.30 - 0.80 = 5.50
1st footing 3 5.50 m 0.80 m 0.20 m
cu.m m
2nd footing 3 5.60 m 0.70 m 0.10 m 1.18 Length = 6.30 - 0.70 = 5.60
cu.m m

1.03 Length = 6.30 - 0.60 = 5.70


3rd footing 3 5.70 m 0.60 m 0.10 m
cu.m m
0.87 Length = 6.30 - 0.50 = 5.80
4th footing 3 5.80 m 0.50 m 0.10 m
cu.m m
5.66 Length = 6.30 - 0.40 = 5.90
Plinth wall above footing 3 5.90 m 0.40 m 0.80 m
cu.m m
Total 26.10 cu.m

Damp Proof Course


11.00 8.80
Long Wall 2 0.40 m -
m sq.m
7.08
Short Wall 3 5.90 m 0.40 m -
4 sq.m
Total 15.88 sq.m
0.40 m 0.96
Deduct door sills 2 1.20 m -
Net sq.m
Total 14.92 sq.m

1st class Brick work in super structure


10.90 27.47 Length = 10.60 + 0.30 =
Long Wall 2 0.30 m 4.20 m
m cu.m 10.90 m
22.68 Length = 6.30 - 0.30 = 6.00
Short Wall 3 6.00 m 0.30 m 4.20 m
cu.m m
Total 50.15 cu.m

Deductions
5
1.51
Door Openings 2 1.20 m 0.30 m 2.10 m
cu.m
1.80
Window Openings 4 1.00 m 0.30 m 1.50 m
cu.m
0.60 Back of shelves 10 cm thick
Shelves 2 1.00 m 0.20 m 1.50 m
cu.m wall
0.14
Lintels over doors 2 1.50 m 0.30 m 0.15 m Bearing 15 cm
cu.m
0.23
Lintels over windows 4 1.30 m 0.30 m 0.15 m Bearing 15 cm
cu.m
0.12
Lintels over shelves 2 1.30 m 0.30 m 0.15 m Bearing 15 cm
cu.m
Total Deduction 4.40 cu.m

Net Total 45.75 cu.m


RESIDENTIAL BUILDING – LONG WALL & SHORT WALL METHOD
 Estimate the quantities of the following items of a residential building from the given drawing
1) Earthwork in excavation in foundation.
2) Lime concrete in foundation
3) First class brick in 1:6 cement sand mortar in foundation and plinth
4) 2.5 cm Damp proof course
5) First class brickwork in lime mortar in super structure
QUANTITY ESTIMATION:

Centre to centre length of wall:

Drawing and left hand side bed room combined:

C to C long walls = 6.00 + 4.00 + 0.30 + (2 * 0.15) = 10.60 m

C to C long walls = 5.00 + 2 * 0.15 = 5.30 m

Bed rooms right side (Both Combined):

C to C long walls = 5.00 + 4.00 + 0.30 + (2 * 0.15) = 9.60 m

C to C short walls = 4.50 + (2 * 0.15) = 4.80 m

Front Verandah:
0.30 0.20
Front wall C to C length =5.00 + 4.00 + 2 ∗ 0.30 + − = 9.65𝑚
2 2

0.30 0.20
Side wall C to C length = 2.00 + + = 2.25𝑚
2 2

Back verandah including bath room:

C to C long wall = 9.65 m (same as front vertical wall)


0.30 0.20
C to C length of side wall of bathroom =2.50 + + = 2.75𝑚
2 2

Dimensions
Item Particulars of items of Height
No Quantity Explanatory Note
No work Length Breadth (or)
Depth
Earth work in excavation in foundation - Drawing room and left bed room
11.50 20.70 Length = 10.60 + 0.90 =
Long Wall 2 0.90 m 1.00 m
m cu.m 11.50 m
11.88 Length = 5.30 - 0.90 =
Short Wall 3 4.40 m 0.90 m 1.00 m
cu.m 4.40 m
Earth work excavation in Bed room right side (Both Combined)
17.28 Length = 9.60 + 0.90/2 -
Long Wall 2 9.60 m 0.90 m 1.00 m
cu.m 0.90/2 = 9.60 m
1
Length = 4.80 - 0.90 =
Short Wall 2 3.90 m 0.90 m 1.00 m 7.02 cu.m
3.90 m
Earth work excavation in Front verendah
Length = 9.65 - 0.90/2 +
Front Long Wall 1 9.50 m 0.60 m 0.50 m 2.85 cu.m
0.60/2 = 9.50 m
Length = 2.25 - 0.90/2 -
Side Short Wall 1 1.50 m 0.60 m 0.50 m 0.45 cu.m
0.60/2 = 1.50 m
Earth work excavation in Back verendah including bathroom
Long Wall (rear wall Length = 9.65 - 0.90/2 +
1 9.50 m 0.60 m 0.50 m 2.85 cu.m
including bath) 0.60/2 = 9.50 m
Short wall (remaining Length = 2.75 - 0.90/2 -
2 2.00 m 0.60 m 0.50 m 1.20 cu.m
walls of bath) 0.60/2 = 2.00 m
Total 64.23 cu.m

Lime Concrete in foundation Drawing & left bedroom


11.50
Long Wall 2 0.90 m 0.30 m 6.21 cu.m
m Length value same as
earth work for excavation
Short Wall 3 4.40 m 0.90 m 0.30 m 3.56 cu.m

Lime Concrete in Bed room right side (Both Combined)

Long Wall 2 9.60 m 0.90 m 0.30 m 5.18 cu.m


Length value same as
earth work for excavation
Short Wall 2 3.90 m 0.90 m 0.30 m 2.11 cu.m

2 Lime concrete in Front verendah


Length = 9.65 - 0.50/2 +
Front Long Wall 1 9.70 m 0.60 m 0.20 m 1.16 cu.m
0.60/2 = 9.70 m
Length = 2.25 - 0.50/2 -
Side Short Wall 1 1.70 m 0.60 m 0.20 m 0.20 cu.m
0.60/2 = 1.70 m
Lime concrete in Back verendah including bathroom
Long Wall (rear wall Length = 9.65 - 0.50/2 +
1 9.70 m 0.60 m 0.20 m 1.16 cu.m
including bath) 0.60/2 = 9.70 m
Short wall (remaining Length = 2.75 - 0.50/2 -
2 2.20 m 0.60 m 0.20 m 0.53 cu.m
walls of bath) 0.60/2 = 2.20 m
Total 20.11 cu.m

1st class Brick work in foundation and plinth in Drawing & left bedroom

Long Wall
11.20 Length = 10.60 + 0.60 =
1st footing 2 0.60 m 0.20 m 2.69 cu.m
m 11.20 m
11.10 Length = 11.20 - 2*0.05 =
2nd footing 2 0.50 m 0.20 m 2.22 cu.m
m 11.10 m
11.00 Length = 11.10 - 0.10 =
3 Plinth wall above footing 2 0.40 m 0.90 m 7.92 cu.m
m 11.00 m
Short Wall
Length = 5.30 - 0.60 =
1st footing 3 4.70 m 0.60 m 0.20 m 1.69 cu.m
4.70 m
Length = 4.70 + 2*0.05 =
2nd footing 3 4.80 m 0.50 m 0.20 m 1.44 cu.m
4.80 m
Length = 4.80 + 0.10 =
Plinth wall above footing 3 4.90 m 0.40 m 0.90 m 5.29 cu.m
4.90 m
1st class Brick work in Bed room right side (Both Combined)

Long Wall
Length = 9.60 - 0.60/2 +
1st footing 2 9.60 m 0.60 m 0.20 m 2.31 cu.m
0.60/2 = 9.60 m
Length = 9.60 - 0.50/2 +
2nd footing 2 9.60 m 0.50 m 0.20 m 1.92 cu.m
0.50/2 = 9.60 m
Length = 9.60 - 0.40/2 +
Plinth wall above footing 2 9.60 m 0.40 m 0.90 m 6.91 cu.m
0.40/2 = 9.60 m
Short Wall
Length = 4.80 - 0.60 =
1st footing 2 4.20 m 0.60 m 0.20 m 1.01 cu.m
4.20 m
Length = 4.80 + 2*0.05 =
2nd footing 2 4.30 m 0.50 m 0.20 m 0.86 cu.m
4.30 m
Length = 4.30 + 0.10 =
Plinth wall above footing 2 4.40 m 0.40 m 0.90 m 3.17 cu.m
4.40 m
1st class Brick work in Front verendah

Front Long Wall


Length = 9.65 - 0.40/2 +
Footing 1 9.65 m 0.40 m 0.20 m 0.77 cu.m
0.40/2 = 9.65 m
Length = 9.65 - 0.40/2 +
Plinth wall above footing 1 9.60 m 0.30 m 0.70 m 2.02 cu.m
0.30/2 = 9.60 m
Side Short Wall
Length = 2.25 - 0.40/2 -
Footing 1 1.85 m 0.40 m 0.20 m 0.15 cu.m
0.40/2 = 1.85 m
Length = 2.25 - 0.40/2 -
Plinth wall above footing 1 1.90 m 0.30 m 0.70 m 0.40 cu.m
0.30/2 = 1.90 m
1st class Brick work in Back verendah including bathroom

Long Wall

Footing 1 9.65 m 0.40 m 0.20 m 0.77 cu.m


Length value same as for
front verandah long wall
Plinth wall above footing 1 9.60 m 0.30 m 0.70 m 2.02 cu.m

Short wall (remaining walls of bath)


Length = 2.75 - 0.40/2 -
Footing 2 2.35 m 0.40 m 0.20 m 0.38 cu.m
0.40/2 = 2.35 m
Length = 2.75 - 0.40/2 -
Plinth wall above footing 2 2.40 m 0.30 m 0.70 m 1.01 cu.m
0.30/2 = 2.40 m
Total 44.95 cu.m

4 2.5 cm Damp Proof Course in Drawing & left bedroom


11.00
Long Wall 2 0.40 m - 8.80 sq.m
m
L Same as plinth wall
Short Wall 3 4.90 m 0.40 m - 5.88 sq.m

2.5 cm Damp Proof Course in Bed rooms inner side

Long Wall 2 9.60 m 0.40 m - 7.68 sq.m

Short Wall 2 4.40 m 0.40 m - 3.52 sq.m L Same as plinth wall

Verendah pillars 4 0.50 m 0.30 m - 0.60 sq.m

2.5 cm Damp Proof Course in Bathroom


Length = 2.20 + 2 * 0.15
Rear Wall 1 2.50 m 0.30 m - 0.75 sq.m
= 2.50 m
Side and Inner wall 2 2.40 m 0.30 m - 1.44 sq.m

Total 28.67 sq.m

Deductions

Door sills D1 6 1.20 m 0.40 m - 2.88 sq.m

Door sills D2 2 1.00 m 0.40 m - 0.80 sq.m

Door sills D3 1 0.75 m 0.30 m - 0.23 sq.m

Total Deduction 3.91 sq.m

Net Total 24.76 sq.m

1st class Brick work in super structure - Drawing & left bedroom
10.90 26.16 Length = 10.60 + 0.30 =
Long Wall 2 0.30 m 4.00 m
m cu.m 10.90 m
18.00 Length = 5.30 - 0.30 =
Short Wall 3 5.00 m 0.30 m 4.00 m
cu.m 5.00 m
1st class Brick work in super structure - Bed room right side (Both Combined)
23.04 Length = 9.60 - 0.30/2 +
5 Long Wall 2 9.60 m 0.30 m 4.00 m
cu.m 0.30/2 = 9.60 m
10.80 Length = 4.80 - 0.30 =
Short Wall 2 4.50 m 0.30 m 4.00 m
cu.m 4.50 m
1st class Brick work in super structure - Front verendah
Length = 9.65 - 0.30/2 +
Front wall as Solid 1 9.60 m 0.20 m 3.05 m 5.86 cu.m
0.20/2 = 9.60 m
Side wall as Solid 1 2.00 m 0.20 m 3.05 m 1.22 cu.m
1st class Brick work in super structure - Back verendah including bathroom
Length same as front
Back long wall as solid 1 9.60 m 0.20 m 3.05 m 5.86 cu.m
verendah
Side and Inner wall bath 2 2.50 m 0.20 m 3.05 m 3.05 cu.m

Total 93.99 cu.m

Deductions

Door Openings

Door Openings D1 6 1.20 m 0.30 m 2.10 m 4.54 cu.m

Door Openings D2 2 1.00 m 0.30 m 2.00 m 1.20 cu.m

Door Openings D3 1 0.75 m 0.20 m 1.80 m 0.27 cu.m

Window Openings

Window Openings W1 11 1.00 m 0.30 m 1.50 m 4.95 cu.m

Window Openings W2 1 2.00 m 0.30 m 1.50 m 0.90 cu.m

Window Openings W3 2 0.75 m 0.20 m 1.20 m 0.36 cu.m


Clerestory Window
18 0.75 m 0.30 m 0.60 m 2.43 cu.m
(C.W) opening
Back of shelves 10 cm
Shelves openings 5 1.00 m 0.20 m 1.50 m 1.50 cu.m
thick wall
Front verendah openings Length = 9.60 - 3 * 0.40 =
1 8.40 m 0.20 m 2.40 m 4.03 cu.m
in between pillars 8.40 m
Front verendah opening
1 2.00 m 0.20 m 2.40 m 0.96 cu.m
side
Length = 9.60 - 2.40 -
Back verendah opening 1 6.80 m 0.20 m 2.40 m 3.26 cu.m
0.40 = 6.80 m
Lintels

Overs Doors
0.405
Door D1 6 1.50 m 0.30 m 0.15 m Bearing 15 cm
cu.m
0.117
Door D2 2 1.30 m 0.30 m 0.15 m Bearing 15 cm
cu.m
0.029
Door D3 1 0.95 m 0.20 m 0.15 m Bearing 10 cm
cu.m
Over Windows
0.644
Window W1 11 1.30 m 0.30 m 0.15 m Bearing 15 cm
cu.m
0.103
Window W2 1 2.30 m 0.30 m 0.15 m Bearing 15 cm
cu.m
0.057
Window W3 3 0.95 m 0.20 m 0.15 m Bearing 10 cm
cu.m
0.770
Over C.W 18 0.95 m 0.30 m 0.15 m Bearing 10 cm
cu.m
0.293
Over Shelves 5 1.30 m 0.30 m 0.15 m Bearing 15 cm
cu.m
Verendah lintels
0.293 Length = 9.60 + 0.15 =
Front 1 9.75 m 0.20 m 0.15 m
cu.m 9.75 m
0.065 Length = 2.00 + 0.15 =
Side 1 2.15 m 0.20 m 0.15 m
cu.m 2.15 m
0.225 Length = 9.60 - 2.40 + 2 *
Back 1 7.50 m 0.20 m 0.15 m
cu.m 0.15 = 7.50 m
Total Deduction 27.401 cu.m

Net Total 66.59 cu.m


THREE ROOMED PLAN – LONG WALL & SHORT WALL METHOD
1. The plan and sectional elevation of a building are given. Estimate the quantities of the following
items of work of the building:
a) Earth work in excavation in foundation
b) Lime concrete in foundation
c) 1st class brick work lime mortar in foundation and plinth
d) Damp proof course
e) 1st class brick work in super structure including parapet
f) R.C.C work in roof slabs, lintels, sunshades
g) Steel reinforcement bars in R.C.C work at 1%.
Centre to Centre length of two adjoining rooms:
0.30 0.30
Long Walls = 4.5 + 0.20 + 4.2 + + = 9.20 𝑚
2 2
0.30 0.30
Short Walls = 3.60 + + = 3.90 𝑚
2 2

Square Room:
0.30 0.30
Long Walls = 3.60 + + = 3.90 𝑚
2 2
0.30 0.30
Short Walls = 3.60 + + = 3.90 𝑚
2 2

Front Verandah:
0.30 0.30
Long Walls = 3.60 + + = 3.90 𝑚
2 2

Short Walls = 1.80 + 0.20 = 2.00 𝑚


Back Verandah:
0.30 0.30
Long Walls = 3.60 + + = 3.90 𝑚
2 2

Short Walls = 2.50 + 0.20 = 2.70 𝑚


Quantity Estimation

Dimensions
Item Particulars of Height
No Quantity Explanatory Note
No items of work Length Breadth (or)
Depth

Earth work in excavation in foundation - Adjoining Room Combined

16.36
Long Walls 2 10.10 m 0.90 m 0.90 m Length = 9.20 + 0.90 = 10.10 m
cu.m
4.86
Short Walls 2 3.00 m 0.90 m 0.90 m Length = 3.90 - 0.90 = 3.00 m
cu.m
0.72
Inter 20 cm wall 1 3.00 m 0.60 m 0.40 m Length = 3.90 - 0.90 = 3.00 m
1 cu.m

Earth work in excavation in foundation - Square Room

Long Walls 1 4.80 m 0.90 m 0.90 m 3.88 cu.m Length = 3.90 + 0.90 = 4.80 m

Short Walls 2 3.00 m 0.90 m 0.90 m 4.86 cu.m Length = 3.90 - 0.90 = 3.00 m

Verendah Pillars 2 0.90 m 0.90 m 0.90 m 1.46 cu.m

Verendah dwarf
Long Walls
2 3.00 m 0.40 m 0.20 m 0.48 cu.m Length = 3.90 - 0.90 = 3.00 m
(Front & Back)
Short Walls
1 1.10 m 0.40 m 0.20 m 0.09 cu.m Length = 2.00 - 0.90 = 1.10 m
(Front Side)
Short Walls
1 1.80 m 0.40 m 0.20 m 0.15 cu.m Length = 2.70 - 0.90 = 1.80 m
(Back Side)
Steps 1 1.20 m 0.70 m 0.10 m 0.08 cu.m

Total 32.94 cu.m

Lime Concrete in foundation - Adjoining Room Combined

Length = 9.20 + 0.90 = 10.10


Long Walls 2 10.10 m 0.90 m 0.30 m 5.45 cu.m
m
Short Walls 2 3.00 m 0.90 m 0.30 m 1.62 cu.m Length = 3.90 - 0.90 = 3.00 m

Inter 20 cm wall 1 3.40 m 0.90 m 0.20 m 0.41 cu.m Length = 3.90 - 0.50 = 3.40 m

Lime Concrete in foundation - Square Room

Long Walls 1 4.80 m 0.90 m 0.30 m 1.30 cu.m Length = 3.90 + 0.90 = 4.80 m

Short Walls 2 3.00 m 0.90 m 0.30 m 1.62 cu.m Length = 3.90 - 0.90 = 3.00 m
2 Verendah Pillars 2 0.90 m 0.90 m 0.30 m 0.49 cu.m

Lime Concrete in foundation - Verandah dwarf


Long Walls
2 3.50 m 0.40 m 0.10 m 0.28 cu.m Length = 3.90 - 0.40 = 3.50 m
(Front & Back)
Short Walls
1 1.60 m 0.40 m 0.10 m 0.064 cu.m Length = 2.00 - 0.40 = 1.60 m
(Front Side)
Short Walls
1 2.30 m 0.40 m 0.10 m 0.092 cu.m Length = 2.70 - 0.40 = 2.30 m
(Back Side)
Steps 1 1.20 m 0.70 m 0.10 m 0.084 cu.m

Total 11.41 cu.m

1st class Brick work in foundation and plinth - Adjoining Room Combined (Long Walls)

1st footing 2 9.80 m 0.60 m 0.20 m 2.35 cu.m Length = 9.20 + 0.60 = 9.80 m
3
2nd footing 2 9.70 m 0.50 m 0.20 m 1.94 cu.m Length = 9.80 - 0.10 = 9.70 m

Plinth Wall 2 9.60 m 0.40 m 0.65 m 4.99 cu.m Length = 9.70 - 0.10 = 9.60 m
1st class Brick work in foundation and plinth - Adjoining Room Combined (Short Walls)

1st footing 2 3.30 m 0.60 m 0.20 m 0.79 cu.m Length = 3.90 - 0.60 = 3.30 m

2nd footing 2 3.40 m 0.50 m 0.20 m 0.68 cu.m Length = 3.30 + 0.10 = 3.40 m

Plinth Wall 2 3.50 m 0.40 m 0.65 m 1.82 cu.m Length = 3.40 + 0.10 = 3.50 m

Inter 20 cm wall 1 3.50 m 0.30 m 0.65 m 0.68 cu.m Length = 3.90 - 0.40 = 3.50 m

Total 13.25 cu.m

1st class Brick work in foundation and plinth - Square Room (Long Wall)

1st footing 1 4.50 m 0.60 m 0.20 m 0.54 cu.m Length = 3.90 + 0.60 = 4.50 m

2nd footing 1 4.40 m 0.50 m 0.20 m 0.44 cu.m Length = 4.50 - 0.10 = 4.40 m

Plinth Wall 1 4.30 m 0.40 m 0.65 m 1.12 cu.m Length = 4.40 - 0.10 = 4.30 m

1st class Brick work in foundation and plinth - Square Room (Short Wall)

1st footing 2 3.30 m 0.60 m 0.20 m 0.79 cu.m Length = 3.90 - 0.60 = 3.30 m

2nd footing 2 3.40 m 0.50 m 0.20 m 0.68 cu.m Length = 3.30 + 0.10 = 3.40 m

Plinth Wall 2 3.50 m 0.40 m 0.65 m 1.82 cu.m Length = 3.40 + 0.10 = 3.50 m

1st class Brick work in foundation and plinth - Verendah Pillars

1st footing 2 0.60 m 0.60 m 0.20 m 0.15 cu.m

2nd footing 2 0.50 m 0.50 m 0.20 m 0.10 cu.m

Plinth Wall 2 0.40 m 0.40 m 0.65 m 0.21 cu.m

1st class Brick work in foundation and plinth - Verendah Dwarf Walls
Long Walls
2 3.50 m 0.20 m 0.55 m 0.77 cu.m Length = 3.90 - 0.40 = 3.50 m
(Front & Back)
Short Walls
1 1.60 m 0.20 m 0.55 m 0.18 cu.m Length = 2.00 - 0.40 = 1.60 m
(Front Side)
Short Walls
1 2.30 m 0.20 m 0.55 m 0.25 cu.m Length = 2.70 - 0.40 = 2.30 m
(Back Side)
1st class Brick work in foundation and plinth - Steps

1st Step 1 1.20 m 0.60 m 0.15 m 0.11 cu.m

2nd Step 1 1.20 m 0.30 m 0.15 m 0.05 cu.m

Total 20.46 cu.m


2.5 cm Damp proof course - Adjoining Room Combined

Long Walls 2 9.60 m 0.40 m - 7.68 cu.m Length = 9.70 - 0.10 = 9.60 m

Short Walls 2 3.50 m 0.40 m - 2.80 cu.m Length = 3.40 + 0.10 = 3.50 m

Inter 20 cm wall 1 3.50 m 0.30 m - 1.05 cu.m Length = 3.90 - 0.40 = 3.50 m

2.5 cm Damp proof course - Square Room

Long Walls 1 4.30 m 0.40 m - 1.72 cu.m Length = 4.40 - 0.10 = 4.30 m

Short Walls 2 3.50 m 0.40 m - 2.80 cu.m Length = 3.40 + 0.10 = 3.50 m
4
Verendah Pillars 2 0.40 m 0.40 m - 0.32 cu.m

Total 16.37 cu.m

Deductions

Door sills D 4 1.00 m 0.40 m - 1.60 sq.m

Door sills D1 1 0.90 m 0.30 m - 0.27 sq.m

Total Deduction 1.87 sq.m

Net Total 14.50 sq.m

1st class Brick work in super structure - Adjoining Rooms

Long Walls 2 9.50 m 0.30 m 3.62 m 20.63 cu.m Height up to top of slab

Short Walls 2 3.60 m 0.30 m 3.62 m 7.82 cu.m Height up to top of slab

Inter 20 cm wall 1 3.60 m 0.30 m 3.50 m 2.52 cu.m Height up to bottom of slab

1st class Brick work in super structure - Square Room

Long Walls 1 4.20 m 0.30 m 3.62 m 4.56 cu.m Length = 3.90 + 0.30 = 4.20 m

Short Walls 2 3.60 m 0.30 m 3.62 m 7.82 cu.m Length = 3.90 - 0.30 = 3.60 m
5
Verendah Pillars 2 0.30 m 0.30 m 2.80 m 0.50 cu.m

1st class Brick work in super structure - Verendah 20 cm wall


Long Walls
2 3.60 m 0.20 m 0.30 m 0.43 cu.m
(Front & Back)
Short Walls
1 1.70 m 0.20 m 0.30 m 0.10 cu.m
(Front Side)
Short Walls
1 2.40 m 0.20 m 0.30 m 0.14 cu.m
(Back Side)
Parapet

Adjoining Rooms

Height of Parapet Wall = 0.39 + 0.08 + 0.03 = 0.50 m

Long Walls 1 9.50 m 0.20 m 0.50 m 0.95 cu.m Length = 9.20 + 0.30 = 9.50 m
Length = 3.60 + 0.30 + 0.10 =
Short Walls 2 4.00 m 0.20 m 0.50 m 0.80 cu.m
4.00 m
Front Verendah
1 2.40 m 0.20 m 0.50 m 0.24 cu.m Length = 1.80 + 0.60 = 2.40 m
Side
Back Verendah Length = 2.50 + 0.20 - 0.20 =
1 2.50 m 0.20 m 0.50 m 0.25 cu.m
Side 2.50 m
Square room -
1 4.20 m 0.20 m 0.50 m 0.42 cu.m Length = 3.60 + 0.60 = 4.20 m
Outer Wall
Wall B/W
Length = 3.60 + 0.20 + 0.10 =
Verendah & 2 3.90 m 0.20 m 0.50 m 0.78 cu.m
3.90 m
Room
Total 47.96 cu.m

Deductions

Door Openings

Door D 4 1.00 m 0.30 m 2.10 m 2.52 cu.m

Door D1 1 0.90 m 0.20 m 2.10 m 0.38 cu.m

Window Openings

Window W 5 0.90 m 0.30 m 1.50 m 2.02 cu.m

Window W1 1 1.80 m 0.30 m 1.50 m 0.81 cu.m

Over Shelves 4 0.90 m 0.20 m 1.80 m 1.30 cu.m

Lintels over doors, windows, shelves

Door D 4 1.30 m 0.30 m 0.10 m 0.156 cu.m

Door D1 1 1.20 m 0.20 m 0.10 m 0.024 cu.m

Window W 5 1.20 m 0.30 m 0.10 m 0.180 cu.m

Window W1 1 2.10 m 0.30 m 0.10 m 0.063 cu.m

Shelves 4 1.20 m 0.30 m 0.10 m 0.144 cu.m


Verendah lintels

Front & Back 2 4.10 m 0.20 m 0.30 m 0.492 cu.m

Side (Front) 1 2.00 m 0.20 m 0.30 m 0.120 cu.m

Side (Back) 1 2.70 m 0.20 m 0.30 m 0.162 cu.m

Total Deduction 7.60 cu.m

Net Total 40.36 cu.m

R.C.C Work 1 : 2 : 4
Two rooms
1 9.20 m 3.90 m 0.12 m 4.306 cu.m Bearing 15 cm
Combined
Square room 1 3.90 m 3.90 m 0.12 m 1.825 cu.m Bearing 15 cm

Verendah Front 1 4.05 m 2.15 m 0.10 m 0.871 cu.m Bearing 15 cm

Verendah Back 1 4.05 m 2.85 m 0.10 m 1.154 cu.m


VerendahChujja
2 4.55 m 0.50 m 0.06 m 0.273 cu.m
Front & Back
Side Front 1 2.15 m 0.50 m 0.06 m 0.065 cu.m

Side Back 1 2.85 m 0.50 m 0.06 m 0.085 cu.m

Sunshades Over Window

Window W 5 1.20 m 0.40 m 0.06 m 0.144 cu.m


6
Window W1 1 2.10 m 0.40 m 0.06 m 0.050 cu.m

Total 8.773 cu.m

Lintels over doors, windows, shelves

Door D 4 1.30 m 0.30 m 0.10 m 0.156 cu.m

Door D1 1 1.20 m 0.20 m 0.10 m 0.024 cu.m

Window W 5 1.20 m 0.30 m 0.10 m 0.180 cu.m

Window W1 1 2.10 m 0.30 m 0.10 m 0.063 cu.m

Shelves 4 1.20 m 0.30 m 0.10 m 0.144 cu.m

Verendah lintels

Front & Back 2 4.10 m 0.20 m 0.30 m 0.492 cu.m

Side (Front) 1 2.00 m 0.20 m 0.30 m 0.120 cu.m


Side (Back) 1 2.70 m 0.20 m 0.30 m 0.162 cu.m

Net Total 10.114 cu.m


Steel Reinforcement Bars
10.114 x 0.01 0.10114 cu.m
at 1%
7
Density of steel = 78.5

0.10114 x 78.5 7.92 q


SINGLE ROOMED PLAN – CENTRE LINE METHOD
 Estimate by using the centre line method the quantities of the following items of a single room
building.
1. Earth work in excavation in foundation
2. Concrete in foundation
3. Brick work in foundation and plinth
4. Brick work in super structure
QUANTITY ESTIMATION:
Dimensions
Item Particulars of items of Height
No Quantity Explanatory Note
No work Length Breadth (or)
Depth
Earth work in excavation 19.20 15.55
1 1 0.90 m 0.90 m
in foundation m cu.m Total centre length of all
19.20 5.18 walls = 19.20 m
2 Concrete in foundation 1 0.90 m 0.30 m
m cu.m
Brick work in foundation and plinth
19.20 3..46
1st footing 1 0.60 m 0.30 m
m cu.m
19.20 2.88
3 2nd footing 1 0.50 m 0.30 m
m cu.m
19.20 4.61
Plinth wall 1 0.40 m 0.60 m
m cu.m
Total 10.95 cu.m
Brick work in super 19.20 20.16
4 1 0.30 m 3.50 m
structure m cu.m
DOUBLE ROOMED PLAN – CENTRE LINE METHOD
 Estimate by using the center line method the quantities of the following items of a two roomed
building.
1. Earth work in excavation in foundation
2. Lime Concrete in foundation
st
3. 1 class Brick work in foundation and plinth
4. 2.5 cm D.P.C
st
5. 1 class Brick work in super structure

Total centre length of wall = 2 * C-C of long wall length + 3 * C-C of short wall length

= 2 * 10.60 + 3 * 6.30 = 40.10 m


QUANTITY ESTIMATION:
Dimensions
Item Particulars of items of Height
No Quantity Explanatory Note
No work Length Breadth (or)
Depth
Earth work in excavation 39.00 42.90 Length = 40.10 - (2* 1.10/2)
1 1 1.10 m 1.00 m
in foundation m cu.m = 39.00 m
Lime Concrete in 39.00 12.87 Length = 40.10 - (2* 1.10/2)
2 1 1.10 m 0.30 m
foundation m cu.m = 39.00 m
1st class Brick work in foundation and plinth
39.30 6.29 Length = 40.10 - (2* 0.80/2)
1st footing 1 0.80 m 0.20 m
m cu.m = 39.30 m
39.40 2.76 Length = 40.10 - (2* 0.70/2)
2nd footing 1 0.50 m 0.10 m
m cu.m = 39.40 m
39.50 2.37 Length = 40.10 - (2* 0.60/2)
3 3rd footing 1 0.40 m 0.10 m
m cu.m = 39.50 m
39.60 1.98 Length = 40.10 - (2* 0.50/2)
4th footing 1 0.50 m 0.10 m
m cu.m = 39.60 m
39.70 12.70 Length = 40.10 - (2* 0.40/2)
Plinth wall above footing 1 0.40 m 0.80 m
m cu.m = 39.70 m
Total 26.10 cu.m
Damp Proof Course 2.5 cm 39.70 15.88 Length = 40.10 - (2* 0.40/2)
4 1 0.40 m -
C-C m cu.m = 39.70 m
0.96
Deduction of door sill 2 1.20 m 0.40 m -
cu.m
Total 14.92 cu.m
1st class Brick work in 39.80 50.15 Length = 40.10 - (2 *
1 0.30 m 4.20 m
super structure m cu.m 0.30/2) = 39.80 m
Deductions
1.51
Door Openings 2 1.20 m 0.30 m 2.10 m
cu.m
1.80
Window Openings 4 1.00 m 0.30 m 1.50 m
cu.m
0.60 Back of shelves 10 cm thick
Shelves 2 1.00 m 0.20 m 1.50 m
5 cu.m wall
0.14
Lintels over doors 2 1.50 m 0.30 m 0.15 m Bearing 15 cm
cu.m
0.23
Lintels over windows 4 1.30 m 0.30 m 0.15 m Bearing 15 cm
cu.m
0.12
Lintels over shelves 2 1.30 m 0.30 m 0.15 m Bearing 15 cm
cu.m
Total Deduction 4.40 cu.m

Total 45.75 cu.m


THREE ROOMED PLAN – CENTRE LINE METHOD
 Estimate the quantities by using center line method of the following items of a residential
building from the given drawing
1) Earthwork in excavation in foundation.
2) Lime concrete in foundation
3) First class brick in 1:6 cement sand mortar in foundation and plinth
4) 2.5 cm Damp proof course
5) First class brickwork in lime mortar in super structure
QUANTITY ESTIMATION:

Total center length of all 30 cm walls = Total center length of walls of drawing and left side bed room +
Total center length of wall of bed rooms right side

Total center length of all 30 cm walls = (2 * 10.60 + 3* 5.30) + (2 * 9.60 + 2 * 4.80)

= 37.10 + 28.80 = 65.90 m

Number of junctions for 30 cm walls = 6 marked with ‘x’ in the plan

Total center length of 20 cm wall = (C.C of long front wall + C.C length of side wall) + (C.C length of
back verandah long wall including bath + 2 * C.C length of cross walls of bathroom)

Total center length of 20 cm wall = (9.65 + 2.25) + (9.65 + 2 * 2.75) = 11.90 + 15.15

Total center length of 20 cm wall = 27.05 m

Number of junctions of 20 cm wall = 5 junctions marked with ‘+’ with 30 cm walls

1 junction marked with ‘-’ is with similar 20 cm wall

Dimensions
Item Particulars of items of Height
No Quantity Explanatory Note
No work Length Breadth (or)
Depth

Earth work in
excavation in 63.20 56.88 Length = 65.90 - 6 * 0.90/2 = 63.20
1 0.90 m 1.00 m
foundation - (Wall with m cu.m m
main room six junctions)

Earth work in
1
excavation in
24.50 Length = 27.50 - 5 * 0.90/2 - 1 *
foundation - (Walls of 1 0.60 m 0.50 m 7.35 cu.m
m 0.60/2 = 24.50 m
verendahsincludig bath (
five and one junctions)

Total 64.23 cu.m

Lime Concrete in
63.20 17.06 Length = 65.90 - 6 * 0.90/2 = 63.20
2 foundation - (Wall with 1 0.90 m 0.30 m
m cu.m m
main room six junctions)
Lime Concrete in
foundation - (Walls of 25.50 3.06 Length = 27.50 - 5 * 0.50/2 - 1 *
1 0.60 m 0.20 m
verendahsincludig bath ( m cu.m 0.60/2 = 25.50 m
five and one junctions)

Total 20.12 cu.m

1st class Brick work in foundation and plinth - (Wall with main room six junctions)

64.10 7.69 Length = 65.90 - 6 * 0.60/2 = 64.10


1st footing 1 0.60 m 0.20 m
m cu.m m

64.40 6.44 Length = 65.90 - 6 * 0.50/2 = 64.40


2nd footing 1 0.50 m 0.20 m
m cu.m m

64.70 23.29 Length = 65.90 - 6 * 0.40/2 = 64.70


Plinth wall above footing 1 0.40 m 0.90 m
3 m cu.m m

1st class Brick work in foundation and plinth - (Walls of verendahs including bath ( five and one junctions)

25.85 2.07 Length = 27.50 - 5 * 0.40/2 - 1 *


footing 1 0.40 m 0.20 m
m cu.m 0.40/2 = 25.85 m

25.90 5.44 Length = 27.50 - 5 * 0.40/2 - 1 *


Plinth wall above footing 1 0.30 m 0.70 m
m cu.m 0.30/2 = 25.90 m

Total 44.93 cu.m

2.5 cm Damp proof course

64.70 25.88 Length = 65.90 - 6 * 0.40/2 = 64.70


Wall with main room 1 0.40 m -
m sq.m m

0.60
Verendah Pillars 4 0.50 m 0.30 m -
sq.m

Bathroom (total no of 3 2.19 Length = (2.20 + 2 * 0.15) + 2 *


4 1 7.30 m 0.30 m -
walls) sq.m (2.75 - 0.40/2 - 0.30/2) = 7.30 m

Deductions

2.88
Door sills D1 6 1.20 m 0.40 m -
sq.m

0.80
Door sills D2 2 1.00 m 0.40 m -
sq.m
0.23
Door sills D3 1 0.75 m 0.30 m -
sq.m

Total Deduction 3.91 sq.m

Net Total 24.76 sq.m

1st class Brick work in super structure

65.00 78.00 Length = 65.90 - 6 * 0.30/2 = 65.00


Wall with main room 1 0.30 m 4.00 m
m cu.m m

Walls of verendah and 26.20 15.98 Length = 27.50 - 5 * 0.30/2 - 1 *


1 0.20 m 3.05 m
bath m cu.m 0.20/2 = 26.20 m

Total 93.98 cu.m

Deductions

Door Openings

4.54
Door Openings D1 6 1.20 m 0.30 m 2.10 m
cu.m

1.20
Door Openings D2 2 1.00 m 0.30 m 2.00 m
cu.m
5
0.27
Door Openings D3 1 0.75 m 0.20 m 1.80 m
cu.m

Window Openings

4.95
Window Openings W1 11 1.00 m 0.30 m 1.50 m
cu.m

0.90
Window Openings W2 1 2.00 m 0.30 m 1.50 m
cu.m

0.36
Window Openings W3 2 0.75 m 0.20 m 1.20 m
cu.m

Clerestory Window 2.43


18 0.75 m 0.30 m 0.60 m
(C.W) opening cu.m

1.50
Shelves openings 5 1.00 m 0.20 m 1.50 m Back of shelves 10 cm thick wall
cu.m
Front verendah openings 4.03
1 8.40 m 0.20 m 2.40 m Length = 9.60 - 3 * 0.40 = 8.40 m
in between pillars cu.m

Front verendah opening 0.96


1 2.00 m 0.20 m 2.40 m
side cu.m

3.26
Back verendah opening 1 6.80 m 0.20 m 2.40 m Length = 9.60 - 2.40 - 0.40 = 6.80 m
cu.m

Lintels

Overs Doors

0.405
Door D1 6 1.50 m 0.30 m 0.15 m Bearing 15 cm
cu.m

0.117
Door D2 2 1.30 m 0.30 m 0.15 m Bearing 15 cm
cu.m

0.029
Door D3 1 0.95 m 0.20 m 0.15 m Bearing 10 cm
cu.m

Over Windows

0.644
Window W1 11 1.30 m 0.30 m 0.15 m Bearing 15 cm
cu.m

0.103
Window W2 1 2.30 m 0.30 m 0.15 m Bearing 15 cm
cu.m

0.057
Window W3 3 0.95 m 0.20 m 0.15 m Bearing 10 cm
cu.m

0.770
Over C.W 18 0.95 m 0.30 m 0.15 m Bearing 10 cm
cu.m

0.293
Over Shelves 5 1.30 m 0.30 m 0.15 m Bearing 15 cm
cu.m

Verendah lintels

0.293
Front 1 9.75 m 0.20 m 0.15 m Length = 9.60 + 0.15 = 9.75 m
cu.m

0.065
Side 1 2.15 m 0.20 m 0.15 m Length = 2.00 + 0.15 = 2.15 m
cu.m
0.225 Length = 9.60 - 2.40 + 2 * 0.15 =
Back 1 7.50 m 0.20 m 0.15 m
cu.m 7.50 m

Total Deduction 27.401 cu.m

Net Total 66.58 cu.m