Professional Documents
Culture Documents
Due date and time for submission of tender 12-03-2021 (11.00 hours)
Will be communicated to
Date and time of opening of BOQ/ price bid
qualified bidders
Table of Contents
Sl.No Particulars Page No
1. Pre Contract Integrity Pact 3
PART – 1 Technical Bid
2 Notice Inviting Tender 9
3. Form of tender 11
4. Draft Articles of agreement 13
5. Instructions to bidders 17
6. General instructions and special conditions of the contract 22
6.1. Mode of measurements 22
6.2. Mobilisation advance 22
6.3. Storage at site 22
6.4. Stay arrangement at site 22
6.5. Extension of time 22
6.6. Validity of tender 22
6.7. Item rate tender 22
6.8. Firmness of rates 22
6.9. Revision in tender 23
6.10. Liquidated damages 23
6.11. Compensation for delay 23
6.12. Variation items/ Extra items 23
6.13. Nature of work 23
6.14. Co-operation with other contractors 23
6.15. Contractor's Representative on Works 23
6.16. Dismissal of Workman 24
6.17. Inspection of work 24
6.18. Notices 24
6.19. Deletion of items 24
6.20. Technical Audit 24
6.21. Insurance 24
6.22. Termination of contract by the Employer 26
6.23. Termination of the contract by the contractor 27
6.24. Indemnity clause 27
6.25. Matters to be finally determined by the Employer 28
6.26. Corrections or overwriting 28
6.27. Mismatch in figures and words 28
6.28. Contract Labour (Regulation and Abolition Act, 1970) 28
6.29. Sub-standard work and material 29
6.30. Measurement books 29
6.31. Payment of bills 29
7. Safety code 30
8. Scope of Work 31
9. Technical Specifications 37
Annexure I (Proforma of undertaking for maintenance confirmation by the 47
tenderer)
Price Bid/ BOQ (Part-2)
11 Bill of Quantity 49
Between National Bank for Agriculture and Rural Development (NABARD) hereinafter
referred to as "The Principal" And ‘ ’ hereinafter referred to as "The
Bidder/Contractor"
Preamble
The Principal intends to award, under laid down organizational procedures, contract/s for
Design, Supply, Installation, Testing, Commissioning and Maintenance of IP
CCTV Surveillance System at NABARD’s Tamilnadu Regional Office & its
Quarters, Chennai. The Principal values full compliance with all relevant laws of the land,
rules, regulation, and economic use of resources and of fairness /transparency in its relations
with its Bidder(s) and/or Contractor(s).
In order to achieve these goals, the Principal will appoint Independent External Monitors
(IEMs) who will monitor the tender process and the execution of the contract for compliance
with the principles mentioned above.
Section 1 — Commitments of the Principal
(1) The Principal commits itself to take all measures necessary to prevent corruption and to
observe the following principles:-
a) No employee of the Principal, personally or through family members, will in connection
with the tender for, or the execution of a contract, demand, take a promise for or accept, for
self or third person, any material or immaterial benefit which the person is not legally entitled
to.
b) The Principal will, during the tender process treat all Bidder(s) with equity and reason.
The Principal will, in particular, before and during the tender process, provide to all Bidder(s)
the same information and will not provide to any Bidder(s) confidential / additional
information through which the Bidder(s) could obtain an advantage in relation to the tender
process or the contract execution.
c) The Principal will exclude from the process all known prejudiced persons.
(2) If the Principal obtains information on the conduct of any of its employees which is a
criminal offence under the IPC/PC Act, or if there be a substantive suspicion in this regard,
the Principal will inform the Chief Vigilance Officer and in addition can initiate disciplinary
actions.
Section 2 — Commitments of the Bidder(s)/Contractor(s)
(1) The Bidder(s) / Contractor(s) commit themselves to take all measures necessary to
prevent corruption. The Bidder(s) / Contractor(s) commit themselves to observe the
following principles during participation in the tender process and during the contract
execution:
a) The Bidder(s) / Contractor(s) will not, directly or through any other person or firm, offer,
promise or give to any of the Principal's employees involved in the tender process or the
execution of the contract or to any third person any material or other benefit which he/she is
not legally entitled to, in order to obtain in exchange any advantage of any kind whatsoever
during the tender process or during the execution of the contract.
b) The Bidder(s)/Contractor(s) will not enter with other Bidders into any undisclosed
agreement or understanding, whether formal or informal. This applies in particular to prices,
specifications, certifications, subsidiary contracts, submission or non-submission of bids or
any other actions to restrict competitiveness or to introduce cartelization in the bidding
process.
c) The Bidder(s)/Contractor(s) will not commit any offence under the relevant IPC/PC Act;
further the Bidder(s) / Contractor(s) will not use improperly, for purposes of competition or
personal gain, or pass on to others, any information or document provided by the Principal
as part of the business relationship, regarding plans, technical proposals and business details,
including information contained or transmitted electronically.
d) The Bidder(s)/Contractor(s) of foreign origin shall disclose the name and address of the
Agents/representatives in India, if any. Similarly the Bidder(s)/Contractors(s) of Indian
Nationality shall furnish the name and address of the foreign principals, if any.
e) The Bidder(s) /Contractor(s) will, when presenting their bid, disclose any and all payments
made, is committed to or intends to make to agents, brokers or any other intermediaries in
connection with the award of the contract.
f) Bidder(s) [Contractor(s) who have signed the Integrity Pact shall not approach the Courts
while representing the matter to IEMs and shall wait for their decision in the matter. The
Bidder(s)/Contractor(s) will not instigate third persons to commit offences outlined above or
be an accessory to such offences.
Section 3 — Disqualification from tender process and exclusion from future
contracts
If the Bidder(s) [Contractor(s), before award or during execution has committed a
transgression through a violation of Section 2, above or in any other form which put their
reliability or credibility in question, the Principal is entitled to disqualify the Bidder(s)
/Contractor(s) from the tender process.
Section 4 — Compensation for Damages
If the Principal has terminated the contract according to Section 3, or if the Principal is
entitled to terminate the contract according to Section 3, the Principal shall be entitled to
demand and recover from the Contractor liquidated damages of the Contract value or the
amount equivalent to Performance Bank Guarantee.
Section 5 — Previous transgression
(1) The Bidder declares that no previous transgressions occurred in the last three years with
any other Company in any country conforming to the anti-corruption approach or with any
Public Sector Enterprise in India that could justify his exclusion from the tender process.
(2) If the Bidder makes incorrect statement on this subject, he can be disqualified from the
tender process.
Section 6 — Equal treatment of all Bidders / Contractors/ Subcontractors
(1) In case of Sub-contracting, the Principal Contractor shall take the responsibility of the
adoption of Integrity Pact by the Sub-contractor.
(2) The Principal will enter into agreements with identical conditions as this one with all
Bidders and Contractors
(3) The Principal will disqualify from the tender process all bidders who do not sign the Pact
or violate its provisions.
Section 7 — Criminal charges against violating Bidders(s) / Contractor(s)/
Subcontractor(s)
If the Principal obtains knowledge of conduct of a Bidder, Contractor or Subcontractor, or of
an employee or a representative or an associate of a Bidder, Contractor or Subcontractor
which constitutes corruption, or if the Principal has substantive suspicion in this regard, the
Principal will inform the same to the Chief Vigilance Officer.
Section 8 — Independent External Monitor
(1) The Principal appoints competent and credible Independent External Monitor for this
Pact after approval by the Central Vigilance Commission. The task of the Monitor is to review
independently and objectively, whether and to what extent the parties comply with the
obligations under this agreement.
The Independent External Monitor appointed for NABARD is Shri Pramod Kumar
Sangewar, IRSS (Retd.), House no. 12-5-65/1, Flat no. 109, Sri Harsha Sethuram
Unique Vijayapuri Colony, Lalaguda South, Secundarabad 500017, Telangana.
(2) The Monitor is not subject to instructions by the representatives of the parties and
performs his/her functions neutrally and independently. The Monitor would have access to
all Contract documents, whenever required. It will be obligatory for him/ her to treat the
information and documents of the Bidders /Contractors as confidential. He / she reports to
the Chairman, NABARD.
(3) The Bidder(s)/Contractor(s) accepts that the Monitor has the right to access without
restriction to all Project documentation of the Principal including that provided by the
Contractor. The Contractor will also grant the Monitor, upon his/her request and
demonstration of a valid interest, unrestricted and unconditional access to their project
documentation. The same is applicable to Sub-contractors.
(4) The monitor is under contractual obligation to treat the information and documents of
the Bidder(s) /Contractor(s) / Sub-contractor(s) with confidentiality. The Monitor has also
signed declarations on 'Non-disclosure of Confidential Information and of 'Absence of
Conflict of Interest'. In case of any conflict of interest arising at a later date, the IEM shall
inform Chairman, NABARD and recuse himself/herself from that case.
(5) The Principal will provide to the Monitor sufficient information about all meetings among
the parties related to the Project, provided such meetings could have an impact on the
contractual relations between the Principal and the Contractor. The parties offer to the"
Monitor the option to participate in such meetings.
(6) As soon as the Monitor notices, or believes to notice, a violation of this agreement, he/she
will so inform the Management of the Principal and request the Management to discontinue
or take corrective action, or to take other relevant action. The monitor can in this regard
submit non- binding recommendations. Beyond this, the Monitor has no right to demand
from the parties that they act in a specific manner, refrain from action or tolerate action.
(7) The monitor will submit a written report to the Chairman, NABARD within 8 to 10 weeks
from the date of reference or intimation to him by the Principal and, should the occasion
arise, submit proposal for correcting problematic situations.
(8) If the Monitor has reported to the Chairman, NABARD, a substantiated suspicion of an
offence under the relevant IPC/PC Act, and the Chairman NABARD has not, within
reasonable time, taken visible action to proceed against such offence or reported it to the
Chief Vigilance Officer, the Monitor may also transmit this information directly to the Central
Vigilance Commissioner.
(9) The word 'Monitor' would include both singular and plural.
Section 9 — Pact Duration
This Pact begins when both parties have legally signed it. It expires for the Contractor 12
months after the last payment under the contract, and for all other Bidders 6 months after
the contract has been awarded. Any violation of the same would entail disqualification of the
bidders and exclusion from future business dealings.
If any claim is made/lodged during this time, the same shall be binding and continue to be
valid despite the lapse of this pact as specified above, unless it is discharge/determined by
the Chairman of NABARD.
Section 10 — Other provisions
(1) This agreement is subject of Indian Law, Place of performance and jurisdiction is the
Regional Office of the Principal, i.e. Chennai.
(2) Changes and supplements as well as termination notices need to be made in writing. Side
agreements have not been made.
(3) If the Contractor is a partnership or a consortium, this agreement must be signed by all
partners or consortium members.
(4) Should one or several provisions of this agreement turn out to be invalid, the remainder
of this agreement remains valid. In this case, the parties will strive to come to an agreement
to their original intentions.
(5) Issues like Warranty/Guarantee etc. shall be outside the purview of IEMs.
(6) In the event of any contradiction between the Integrity Pact and its Annexure, if any, the
Clause in the Integrity Pact will prevail.
(For & on behalf of the Principal) (For & on behalf of the Bidder/Contractor)
PLACE:
DATE:
Witness 1: Witness 2:
………………………………………………….… ………………..………………………………….
………………………………………………….… ………………..………………………………….
1.6. Envelope No.1 shall contain Integrity Pact (IP) as per format given, duly signed and
stamped by the bidder. Tenders submitted without IP will summarily be rejected and their
subsequent envelops will not be opened.
Yours faithfully,
Sd/-
(D Mitra)
Deputy General Manager
3. Form of tender
Dear Sir,
Tender for Design, Supply, Installation, Testing, Commissioning and
Maintenance of IP CCTV Surveillance System at NABARD’s Tamilnadu Regional
Office & its Quarters at Chennai
1) Having examined the conditions relating to the works specified in the tender
hereinafter set out, having visited and examined the site of the works specified in the said
tender and having acquired the requisite information relating thereto as affecting the tender,
I/We hereby offer to execute the works specified in the said tender within the time specified,
at the rates to be mentioned in the Price Bid which may be issued to us by NABARD in the
event that we qualify the technical bid and in accordance in all respects with the Technical
Specifications and instructions in writing referred to the Conditions of Tender, the Articles of
Agreement, Special Conditions, Price Bid to be later submitted if qualified and Conditions of
Contract and with such materials as are provided for, by and in all other respects in
accordance with such conditions so far as they may be applicable.
2) We also agree that our tender will remain valid for acceptance by the Bank for 90 days
from the date of opening of Part II of the tender and this period of validity can be extended
for such period as may be mutually agreed between the Bank and us in writing.
3) I/We hereby agree to abide by and fulfill the terms and provisions or the said
Conditions of Contract annexed hereto so far as they may be applicable.
4) We understand that you reserve the right to accept or reject any or all the tenders
either in full or in part without assigning any reason therefor.
5) We are enclosing a list of our clients with complete details as per the requirements and
proforma given in the Annexure.
Our Bankers are:
i)
ii)
I)
ii)
iii)
6) The Part 1 of the tender contains the tender conditions, all commercial terms and
conditions, technical specifications and the power of attorney for signing of proposal. Part II
contains Price bid in the Bank’s proforma.
Yours faithfully,
Signature of Tenderer
3. The Scope of work and all the terms and conditions as enumerated in this tender is
part and parcel of this agreement and binding on the parties. The vendor shall ensure that all
items of work specified in the scope of work is attended to. In case of difference between the
tender document and this agreement, the agreement will prevail.
4. This Agreement and documents mentioned herein shall form the basis of this contract.
5. NABARD reserves to itself the right of altering the nature/quantum of the work by
adding to or omitting any items having portions of the same carried out without prejudice to
this Contract.
6. The Vendor shall provide to NABARD a security deposit of Rs…………………. (Rupees
Only) (Interest Free).
7. In case of breach of any terms and conditions attached to this contract, the Security
Deposit of the Vendor will be liable to be forfeited by NABARD besides annulment of the
contract.
8. In case any of the documents furnished by the Vendor is found to be false at any stage,
it would be deemed to be a breach of terms of Contract making him/her liable for legal action
besides termination of contract.
9. The NABARD shall pay the vendor the said contract amount, or such other sum as
shall become payable, at the times and in the manner specified in the said Conditions.
10. This contract is an item rate contract for the complete work to be paid for according to
necessary installation carried out at site, at the rate contained in the Schedule of Rates or as
provided in the said conditions.
11. All payments by the NABARD under this contract will be made only at Chennai.
12. The Vendor shall afford every reasonable facility for carrying out all works of other
Contractors employed by the Employer and shall make good any damage done to walls, floors,
etc. after the completion of such works.
13. The Vendor shall indemnify and keep indemnified, defend and hold good NABARD,
its staff and agents against loss, damages or claims arising out of any violations of applicable
laws, regulations, guidelines during the contract period and for the breach committed by the
Vendor or their personnel on account of misconduct, omission and negligence by the Vendor
or his staff.
14. The Vendor shall ensure proper conduct of its personnel in NABARD’s premises, and
enforce prohibition of consumption of alcoholic drinks, paan, smoking, loitering without
work.
15. NABARD shall not be responsible for any damages, losses. Claims, financial or other
injury to any person/s engaged by Vendor in the course of their performing the
functions/works, or for payment towards any compensation.
16. Time shall be considered as the essence of this contract, and the Vendor hereby agrees
to commence the work/ job on the next day of receipt of the work order as provided for in the
said conditions and to complete the entire work within the time period prescribed below
reckoned from the date of receipt of such work order subject nevertheless to the provision for
extension of time.
17. NABARD reserves the right to withdraw/relax any of the terms and conditions
mentioned above so as to overcome the problem encountered by the contracting parties.
18. DISPUTE RESOLUTION
(a) In case of dispute regarding the quality of work and product / unsatisfactory
services etc., the final authority will rest with the Chief General Manager, NABARD,
RO, Chennai and the same will be binding on the Vendor.
(b) In the event of any claim, difference, dispute or controversy and questions
whatsoever arising between the parties under this agreement and subsequent
agreement shall in the first instance, be attempted to be resolved between the parties
themselves.
(c) If the dispute cannot be resolved through consultations between the Parties
with in 30 (thirty) days after 1(one) Party has served a written notice on the other Party
requesting the commencement of such discussions, any Party may thereafter in
writing, demand that the dispute be finally settled by an arbitration comprising of sole
arbitrator mutually appointed by the Parties in accordance with the Arbitration and
Conciliation Act, 1996 or any modifications thereof. The arbitrator shall be a person of
professional repute who is not directly or indirectly connected with any of the parties
to this Agreement and shall have prior experience as Arbitrator. The arbitration
proceedings shall be governed by the Arbitration and Conciliation Act, 1996. The seat
and venue of arbitration shall be Chennai. The language of arbitration shall be English.
(d) The award of the arbitrator/s so appointed shall be final and binding on the
parties.
(e) Work under the contract shall be continued by the Vendor during the
arbitration proceedings unless otherwise directed in writing by NABARD. No payment
due, or payable by NABARD, to the Vendor shall be withheld on account of the ongoing
arbitration proceedings, if any, unless it is the subject matter, or one of the subject
matters thereof
19. If the vendor becomes insolvent or found to have offered any bribe in connection with
the contract or the Vendor fails to observe or perform any condition of this contract then
notwithstanding any previous waiver of such default or action being taken under any other
clause hereof NABARD may terminate the contract and forfeit the said security deposit and
recover from the Vendor any loss suffered by NABARD on account of the contract being
terminated.
20. This agreement is being executed in duplicate, NABARD shall keep the original and
the Vendor shall keep the duplicate.
21. The Vendor shall bear the expenses for stamp duty on this agreement for both the
original and the duplicate copy.
22. That the several parts of this contract have been read by the Vendor and fully
understood by the Vendor.
IN WITNESS WHEREOF the NABARD and Vendor have set their respective hands to these
presents and two duplicates hereof the day and year first herein above written.
IN WITNESS WHEREOF the NABARD has set its hand to these presents through its duly
authorized official and the Vendor has caused its common seal to be affixed hereunto and the
said two duplicates hereof to be executed on its behalf, the day and year first herein above
written.
SIGNATURE CLAUSE:
SIGNED AND DELIVERED BY the National Bank for Agriculture and Rural Development by
the hand of………………………………………………………………..
Signature
Name & Designation
Signature
Name & Address
5. Instructions to bidders
6.1. Mode of measurements: Joint measurements will be taken and recorded in the
Measurement book/ register, in the unit of the price bid.
6.2. Mobilisation advance: No mobilization advance shall be paid to the Contractor.
6.3. Storage at site: Storage space may be allowed at site as per the availability. The
Contractor will have to make his own arrangement for security and locking arrangement of
the storage space. The Contractor may be required to vacate the storage space as per
Employer’s exigency without any extra cost.
6.4. Stay arrangement at site: Contractor’s workers will not be permitted to stay at site.
The contractor has to make his own arrangement of stay for his employees.
6.5. Extension of time: If the Contractors desire any extension of time for completion of
work on grounds of there having been unavoidable hindrances in execution or any other
ground, they shall apply in writing immediately after the occurrence of the hindrances. Such
application shall contain complete details of hindrances, which hindered the Contractors in
execution of the work. If in the opinion of Bank's Officials, works be delayed by force majeure
such as (a) war / hostilities, (b) riots or civil commotion, (c) earthquakes, fire tempest,
lightening or other natural / physical disasters, etc., (d) restrictions imposed by the
Government which prevent or delay the execution of the order or by any other reasons. If any
such extension of time is granted by the Bank, the extension of time will be given without
prejudice to Bank's right to recover liquidated damages or compensation under the relevant
contract clause and no extra claim will be paid by the Employer whatsoever on account of
delay or idle labour/machinery.
6.6. Validity of tender: Validity of the quoted rates shall be 3 months from the date of
opening of price bid.
6.7. Item rate tender: The tenderer shall note that unless otherwise stated the tender is
strictly on item rate basis and his attention is drawn to the fact that rate should be correct,
workable and self-supporting. The tenderer shall carry out all works necessary for completion
of work and for delivering the desired results. No claim shall be entertained on this account.
The successful tenderer is bound to carry out any or all items of work necessary for the
completion of the job even though such items are not included in the quantities and rates.
6.8. Firmness of rates: The rates quoted in the tender/offer shall be for the complete item
including, design, supply, installation, testing, commissioning and maintenance at site. The
rate shall also include all charges for storing, watch and ward, reinstating and making good
the damaged work if any to its original finish, etc. The rates quoted shall be deemed to be for
finished work to be measured at site. The rates quoted in the tender shall include all charges
for packing, transport, loading, unloading and for delivery at site. The rates shall also be firm
during the period of contract including extended period if any and rates shall not be subject
to exchange variation, labour conditions, and fluctuations in railway freights, taxes or any
conditions whatsoever. Tenderers must include in their rates GST/Custom Duty, or any other
tax and prevailing duty or other levy as existing, levied by the Central Government or any
State Government or Local Authority, if applicable. No claim in respect of increase in tax,
GST or other tax, duty or levy during the duration of the contract shall be entertained by the
Employer. The same will remain firm during the contract period. While quoting their rates
the tenderer should include the following also if otherwise not stated herein before.
6.8.1. Samples and testing: Necessary cost of taking samples of materials supplied by
them, testing of the same at Govt.’s / approved laboratory including transportation, cost of
the samples, as and when required.
6.8.2. Test reports: Submission of test reports from National/ International test laboratory
for standards prescribed under BIS or any other accepted such procedure, of other materials
as may be specified by NABARD.
6.8.3. Sundry items: The quoted rate shall include the cost of all minor/sundry items to
make it functional.
6.9. Revision in tender: Any request for revision of original tender rates, specifications
or conditions by a tenderer received after opening of tenders shall not be entertained.
6.10. Liquidated damages: Time is the essence of the contract and Liquidated Damages"
shall be recovered from the contractor’s dues for delay in completion of the work on his part,
subject to force majeure clause (in para 6.5). The quantum of liquidated damages per week
shall be calculated at 0.25% of the accepted tender value subject to a maximum 5% of the
accepted tender amount.
6.11. Compensation for delay: The tenderer shall not be entitled to any compensation for
any loss suffered by him on account of delays in commencing or executing the work, whatever
the cause of delays may be including delays arising out of modifications to the work entrusted
to him or in any subcontract connected therewith or delays in awarding contracts for other
trades of the project or in commencement or completion of such works or in procuring
government controlled or other building materials or in obtaining water and power
connections for construction purpose or for any other reason whatsoever and the Employer
shall not be liable for any claim in respect thereof. The Employer does not accept liability for
any sum besides the tender amount, subject to such variations as are provided for herein.
6.12. Variation items/ Extra items: Rates of extra or substituted items shall wherever
possible be derived from the tender rates of related items or market rates whichever is less.
Whenever such rates are based on market rates of materials and labour, an element of profit
and overhead etc. @ 15% will be considered.
6.13. Nature of work: The tenderer must obtain for himself on his own responsibility and
at his own expenses all the information which may be necessary for the purpose of making
tender and for entering into a contract and inspect the site of the work, acquaint himself with
all local conditions, means of access to the work, nature of work and all matters pertaining
thereto.
6.14. Co-operation with other contractors: The successful tenderer must cooperate
with the other contractor appointed by the Employer so that the work shall proceed smoothly
with the least possible delay and to the satisfaction of the Bank’s Officials.
6.15. Contractor's Representative on Works: Contractor shall maintain at site
responsible, efficient, qualified and well experienced in charge during the contract period.
Any clarifications, explanation, instructions or notices given by the Employer to such in-
charge shall be deemed to be given to the contractor and shall be binding on the contractor.
6.16. Removal of Workman: Contractor shall, on the request of the Employer,
immediately remove from the work any person in the opinion of Employer be unsuitable or
incompetent.
6.17. Inspection of work: The contractor shall at the instructions of the Employer within
such time as notified, open up for inspection of any work and should the contractor refuse or
neglect to comply with such instructions, the Employer may employ other workman to open
the same. Such work if it is found not in accordance with approved specifications, or the
instructions, expenses of opening up and redoing if required shall be borne by and
recoverable from the Contractor from any money due or which may become due to the
contractor.
6.18. Notices: Notices of the Employer, to the contractor may be served personally or by
being left at or sent by registered post or be sent through e-mail to the last known place of the
business of the party to whom the same is given or in the case of the contractor by being left
on the works. Notices may be served at or sent by registered post or e-mail to the registered
office of the contractor. Any notice sent by registered post/ e-mail shall be deemed to be
served at the time when in the ordinary course of post, it would be delivered.
6.19. Deletion of items or Option Clause: The tender rates shall be fixed and applicable
for any increase or decrease in the tendered quantities. The Employer can increase or
decrease any quantities to any extent or even delete particular item as per requirements and
the contractor shall not be paid anything extra on this account. Nothing extra will be paid by
the Bank on account of omission / deletion of items or decrease in the quantity of items. The
Bank shall not entertain any claim whatsoever from the contractor on this account. The
payment shall be made as per joint measurement/pro rata basis.
6.20. Technical Audit: The work is liable to be technically audited by the Technical
Officers of Bank from Time to Time. Any defects, improvements or testing etc. pointed out by
the Technical Officer (TO) should be carried out by the contractor at his own cost and
deduction suggested by the TO will be borne by the contractor. The employer shall have a
right to cause a technical examination and audit of works and the final bills of the contractor
including all supporting vouchers, abstracts etc. to be made at the time of payment of the final
bills. If as a results of this examination or otherwise any sum found to have been overpaid in
respect of any work done by the contractor under the contract , the contractor shall be liable
to return an amount of overpayment and it will be lawful for the employer to recover the same
from any sum or sums due to him and in any other manner legally permissible and it is found
that the contractor was paid than what was due to him under the contract in respect of any
work executed by him under the contract, the amount of such underpayment shall be duly
paid by the employer. Any sum of money due and payable to the contractor (including
security deposit returnable to him) under this contract may be appropriated by NABARD and
set off against any claim of NABARD for the payment of sum of money arising out of or under
any other contract made by the contractor with NABARD.
6.21. Insurance: The Contractor, is required to keep the works duly insured in the joint
names of NABARD and the Contractor (NABARD’s name being first) until the completion
defect liability period of the works. The following insurance policies are required to be taken
by the contractor; From commencement to completion defect liability period of the works,
the Contractor shall take full responsibility for the care of the work and for taking precautions
to prevent loss or damage to the works and to minimize the loss or damage to the greatest
extent possible and shall be liable for any damage or loss that may happen to the works or
any part thereof from any cause whatsoever, inherent defects and failures due to poor
workmanship and causes such as fire, lightening, explosion, earthquake, storm, hurricane,
short circuits , floods, inundation, subsidence, landslides, rock slides, riots (excluding civil
war, rebellion, revolution and insurrection) and shall at his own cost repair and make good
the same so that at all times the work shall be in good order and condition and in conformity
in every respect with the requirements of the Contract.
Explanation: For the purpose of this condition, the expression "from the commencement to
completion defect liability period of the works " shall mean the time commencing from the
issue of the work order to the contractor and ending with successful completion defect
liability period.
6.21.1. Contactor all risk policy: Without limiting the obligations and responsibilities
under this condition, the Contractor shall insure and keep insured the works from
commencement to completion, as aforesaid, for their full value provided under this Contract,
increased by 25% against the risk of loss or damage from any cause whatsoever including the
causes enumerated in the Clause (a) above. In the event of there being a variation in the
nature and extent of the work, the Contractor shall from time to time increase or decrease the
value of the insurance correspondingly. The entire premium shall be borne and paid by the
Contractor. The said insurance shall also provide for the removal of debris of the lost or
damaged works.
6.21.2. Workmen Compensation Policy: The Contractor shall at all times indemnify the
Employer against all losses, claims or damages or compensation under the provisions of the
payment of Wages Act 1936, Minimum Wages Act 1948, Employees Liability Act 1938,
Workmen's Compensation Act 1923, The Maternity Benefit Act 1961, Industrial Disputes Act
1947 and Contract Labour and Regulation and Abolition Act 1970, Employer State Insurance
Act 1948 or any modification thereof or any other law relating thereto and rules made there
under from time to time or as a consequence of any accident or injury to any workman or
other persons in or about the work whether in the Employment of the Employer, or
Contractor or not and also against all costs, charges and expenses of any suit, action or
proceedings whatsoever out of such accident or injury or combination of any such claims.
6.21.3. Third party liability policy for a total of Rs. 1.00 lakhs.
6.21.4. Before commencing the work, the Contractor shall without limiting his obligations
and responsibilities under this condition, insure against any loss of life or injury to any
personnel in the employment of Contractor/Sub-Contractor/Nominated Sub-Contractor. For
this purpose, insurance shall be taken by the Contractor/Sub-Contractor. Such insurance
shall be taken to include both employees/workmen covered by the Workmen's Compensation
Act 1923, as well those employees/workmen not covered by the said Act. Separate insurance
policies may be taken for employees/workmen covered by Workmen's Compensation Act
1923, and employees workmen not covered by the said Act. All the premiums shall be paid by
the Contractor.
6.21.5. The Contractor shall ensure that similar insurance policies are taken out by his sub-
contractors or nominated contractors, if any, and shall be responsible for any claim or loss
resulting from their failure to obtain adequate insurance protection in connection thereof.
While taking the insurance policies, contractor should indicate clearly to the insurance
companies that policies issued shall cover their sub-contractors and nominated sub-
contractors also.
6.21.6. No work shall be commenced by the Contractor unless and until he has obtained the
insurance or insurance required to be obtained by him under or by the foregoing clauses and
no work shall be carried out or continued by the Contractor unless and until each insurance
is current and valid at that time.
6.21.7. In the event of any claim for insurance becoming due on account of any eventuality
covered by the respective insurance policy/policies, the Contractor shall reinstate the
installation, replace the materials or equipment or pay compensating to the affected
personnel/Employees without waiting for settlement of the claim from insurance company.
6.22. Termination of contract by the Employer: If the contractor being an individual
or a firm, commit any “Act of Insolvency” or shall be adjudged an insolvent or being an
incorporated company shall have an order for compulsory winding up or applies for voluntary
winding up or subject to the supervision of the court and of the official assignee or the
liquidator, in such acts of insolvency or winding up shall be unable within seven days after
notice to him requiring him to do so, to show to the reasonable satisfaction of the employer
that they are able to carry out and fulfill the contract, and to give security, therefore, if so
required by the employer. OR
6.22.1. If the contractor (whether an individual Firm or Incorporated Company) shall suffer
execution to be issued, or shall suffer any payment under this contract to be attached by or
on behalf of any of the creditors of the contractor, or shall assign or sublet the contract
without the consent in writing of the employer first obtained. OR
6.22.2. Shall charge or encumber this contract or any payments due or which may become
due to the contractor there under. OR
6.22.3. If the contractor has abandoned the contract OR
6.22.4. Has failed to commence the works, or has without any lawful excuse under these
conditions suspended the progress of the works for seven days after receiving from the
employer written notice to proceed, OR
6.22.5. Has failed to proceed with the works with such due diligence and failed to make such
due progress as would enable the works to be completed within the time agreed upon, OR
6.22.6. Has failed to remove materials from the site or to pull down and replace work for
seven days after receiving from the employer written notice that the said materials of work
were condemned and rejected by the employer under these conditions OR
6.22.7. Has neglected or failed persistently to observe and perform all or any of the acts,
matters or things by this contract to be observed and performed by the contractor for seven
days after written notice shall have been given to the contractor requiring the contractor to
observe or perform the same, OR
or otherwise and also in respect of any award of compensation or damages consequent upon
such claim. The Contractor shall also indemnify and keep indemnified NABARD against all
claims which may be made against NABARD by any person/ member of the public or other
third party in respect of anything which may arise in respect of the works or in consequence
thereof. The Contractor shall also similarly indemnify the NABARD against all claims which
may be made upon NABARD whether under the Workmen Compensation Act or any other
statute in force during the currency of this contract or at Common Law in respect of any
employee of the Contractor or any Sub-Contractor.
6.25. Matters to be finally determined by the Employer: The employer’s decision,
opinion, direction, with respect to all or any of the matter such as scope of work, contractor
to provide everything necessary, materials and workmanship to conform the description,
assignment of subletting, defects after completion, delay & extension of time, opened up
works and the schedule of rates as contained in the Price Bid hereof and as to the exercise by
them the right to have any works opened up shall be final and conclusive and binding on the
contractor. Employer’s instructions if any, in this regard in case of any urgency, shall also be
complied immediately.
6.26. Corrections or overwriting: All erasures and alterations made while filling the
tender must be attested by initials of the tenderer. Overwriting of figures is not permitted.
Failure to comply with either of these conditions will render the tender void at the Bank’s
discretion.
6.27. Mismatch in figures and words: Rates and amounts should be quoted both in
figures and in words in columns specified. A Schedule of Probable Quantities in respect of
each work and Specifications accompany these General and Special Conditions. The Price Bid
should contain not only the rates but also the value of each item of work entered in a separate
column and all the amounts quoted against various items should be totalled in order to show
the aggregate value of the entire tender. If on check there are differences between the rates
given by the Contractor in words and figures or in the amount worked out by him, the
following procedure shall be followed;
6.27.1. When there is a difference between the rates in figures and in words, the rates which
correspond to the amounts worked out by the Contractor, shall be taken as correct.
6.27.2. When the amount of an item is not worked out by the Contractor or it does not
correspond with the rate written either in figures or in words, then the rate quoted by the
Contractors in words shall be taken as correct.
6.27.3. When the rates quoted by the Contractor in figures and in words tallies but the amount
is not worked out correctly, the rate quoted by the contractor shall be taken as correct and
not the amount.
6.28. Contract Labour (Regulation and Abolition Act, 1970): All registers and other
records required to be maintained under the Act and the rules shall be maintained up-to-date
and shall be kept at the office. Such registers shall be maintained legibly in English or Hindi.
All the registers, records and notices shall be produced on demand before the Inspector or
any other authority under the Act. Payment of wages to its workmen is the responsibility of
the contractor under the act.
6.29. Sub-standard work and material: If any work or material used at site is found to
be unsound, imperfect or inferior from what is specified in the contract, the Contractor shall
be advised to rectify or re-execute the work or remove the material as the case may be, within
a reasonable time depending upon the nature of work. If the Contractor fails to do so, the
work shall be got redone or rectified or the material replaced through any other agency at the
risk and cost of the Contractor.
6.30. Measurement books: The measurement Book (called MB hereinafter) is the basis
of all accounts of quantities of work done or of materials supplied. The payment for all works
done and for all materials supplied shall be made on the basis of detailed measurements
recorded in MBs.
6.31. Payment of bills: Payment will be made after the completion of all works subject to
the satisfaction of the Bank.
All payments will be made only by electronic fund transfer. The proforma for electronic
payment shall be submitted along with the tender as per annexure. The contractor shall be
entitled to receive payment on the basis of joint measurements taken on site, installation and
commissioning, approved and certified by the Bank Officials regarding compliance with
specifications and acceptability subject to deductions.
7. Safety code
7.1. During- the execution of works, every care shall be taken to ensure that the safety and
convenience of workmen staff, authority visitors to site and the public are duly catered to and
that all operations are carried out in such a manner as to cause least interference with the
traffic or ordinary pursuit of the people.
7.2. When a ladder is used, it shall be rigid construction made either of good quality wood or
steel. The steps shall have a minimum width of 450 mm. and a maximum rise of 300mm.
Suitable hand holds of good quality wood or steel shall be provided and the ladder shall be
given an inclination not steeper than ¼ to 1 (1/4 horizontal to 1 vertical).
7.3. Safe means of access shall be provided to all working places. Every ladder shall be
securely fixed. No portable single ladder shall be over 9 M. in length while the width between
said rails in sung ladder shall in no case be less than 190 mm. for ladder up to and including
3 M. in length. For longer ladders this width shall be increased at least 20 mm. for each
additional meter of length.
7.4. All personnel of the Contractor within the plant site shall be provided with safety helmets.
All welders shall wear welding goggles while doing welding work and all metal workers shall
be provided with safety gloves. Persons employed on metal cutting and grinding shall wear
safety glasses.
7.5. Adequate precaution shall be taken to prevent danger from electrical equipment. No
materials on any of the sites of work shall be so stacked or placed as to cause danger or
inconvenience to any person or the public.
7.6. The Contractor shall take all measure on the site of the work to protect the public from
accidents and shall be bound to bear the expenses of defense of every suit, action or other
proceedings at law that may be brought by any persons for injury sustained owing to neglect
of the above precautions and to pay any such persons or which may with the consent of the
Contractor, be paid to compensate any claim by any such person.
7.7. No electric cable or apparatus which is liable to be a source of danger over a cable or
apparatus used by the operator shall remain electrically charged.
7.8. All necessary personnel safety equipment as considered adequate by the Employer
should be kept available for the use of the persons employed on the site and the Contractor
should take adequate steps to ensure proper use of equipment by those concerned.
7.9. The Contractor shall not employ men/women below the age of 18 years.
7.10. All scaffolds, ladders and other safety devices mentioned or described herein shall be
maintained in safe condition and no scaffolding, ladder or equipment shall be altered or
removed while it is in use.
7.11. These safety provisions should be brought to the notice of all concerned by display on a
notice board at a prominent place at work spot. The person responsible for compliance of the
safety code shall be named thereon by the Contractor.
7.12. Notwithstanding all the above clauses there is nothing in these to exempt the
Contractor from the operations of any other Act or Rule in Force in the Republic of India.
8. Scope of Work
(ii) Repairs/ replacement of the defective units including re-loading working software etc. in
the event of any breakdown including replacement of spares/ components/ sub-system/
cards and any other component, part or whole, which may need replacement/ repairs. Prior
approval has to be taken for replacement of any spare parts and bills raised for the same will
be settled separately. No additional service charges will be paid for the said work.
(iii) Import of spares and stocking them shall be the responsibility of the tenderer. Non
availability of spares/ components will not be accepted as a reason for waiving of penalty
towards delay in rendering prompt service. For ensuring prompt service, at least some
important spares shall be retained in the custody of the Resident Engineer. After use of any
such spare unit/ cards etc., these shall be replenished at the earliest.
(iv) Providing required software upgrades free of charge, as and when released by the OEM.
Every year, renewal license of the anti-virus software of required users shall be procured by
the vendor at no additional cost to the Bank and installed in the servers/ workstations. This
will continue till the completion of AMC.
(v) The scope of maintenance in addition to periodic maintenance will also include attending
to any number of breakdown calls.
(vi) Other works:
1. Routine maintenance should be carried out in accordance with the Bank’s requirements.
2. All performance checks undertaken should be recorded in the system log book.
3. As a minimum, the following performance checks must be undertaken on each
maintenance visit.
• Remove dust and dirt from the camera enclosures (Inside & outside) exterior using
a soft brush or a lint cloth. A solvent which is harmless to the finishes of metal and
plastic may be applied to more stubborn stains.
• Examine the exterior of the enclosure for any signs of damage or loose cable glands
and rectify any faults found.
• Remove any dust or dirt from the interior of the camera &NVR using a soft brush or
a vacuum cleaner.
• Examine the printed circuit boards for signs of over-heating, dry joints and/or
damaged tracks.
• When any CCTV equipment is taken out for repair, such shifting should be done with
the prior permission of DPSP, NABARD, Tamilnadu RO as the case may be, and the
tenderer shall make all arrangements for removal of the equipment, its transportation
to the workshop and back to site and its reinstallation. Transit Insurance of such
equipment also has to be arranged by the Tenderer and all expenses for the above shall
be borne by the tenderer. The Tenderer shall hand over the systems in 100% working
condition after repair/maintenance/rectification. Thereafter, the Tenderer shall
reinstall the same machine after repair unless it is declared to be irreparable.
• During the period of the contract including AMC period, tenderer should attend to
all repairs/defects/replacement of major/minor spare parts free of cost. In case of
failure on the part of the supplier to attend all the defects within a reasonable period,
the Bank on its own will get the defects rectified through another agency at the risk
and cost of supplier and repairs rectified through another agency, in such
circumstances will not affect the liabilities of the supplier on the warranty for its
remaining period nor it will affect the supplier`s liabilities on the stipulated post-
warranty Annual Maintenance Contracts.
• Any problem arising in functioning of CCTV system, shall be rectified by the service
engineer within 24 hrs from time of lodgement of complaint. The time which will be
treated as the time of lodgement of the complaint will be the 1st Call on mobile or the
time of 1st email sent to the service centre in this regard. In case of failure in providing
service within the above time frame, Corporation has the discretion/reserves the right
to impose penalty as mentioned hereunder:
(B) Penalty for delay in service during defect liability (DLP) and AMC period:
During the DLP and the currency of the Annual Maintenance Service Contract, all care shall
be taken so that the downtime of the system is kept minimum and in any case, not more than
the allowed time for attending to repairs. Any defects in any of the cameras shall be repaired
within 24 hours from the time of reporting complaint in writing (complaints through SMS, e-
mails, fax etc. shall also be treated as complaints in writing). Any defects in any of the servers,
switches, routers etc., leading to complete breakdown of the system, shall be repaired within
12 working hours from the time of reporting complaint in writing. Any defects/ problems
associated with the software shall be attended to immediately, but not later than 4 hours from
the time of the problem being noticed/ reported. If the down time exceeds the above
mentioned period, penal recovery shall be made from the payments due to the contractor at
the following rates:
• 1-7 days excluding date of lodging of complaint: Rs. 100/= per day
• From 8th day to 30 days: Rs. 250/= per day
• More than 30 days: Rs. 350/= per day
• Non-functional server / software leading to system failure - @ Rs 2000/- per day or
part thereof beyond the authorised maintenance period
• Penalty of 0.5% of the cost of the equipment will be charged every quarter if, the
Preventive Maintenance is not done by tenderer. Penalty for Preventive Maintenance
not done will not be charged for the quarter in which the machine has been delivered/
installed.
The penalty amount will be recovered from the Security Deposit lying with the Bank.
Complaint(s) will be deemed to be resolved only on the availability of the Customer
Call Report(CCR) signed by both the service engineer and Bank’s authorized official,
confirming that the complaint is resolved. Date and time of resolution of the complaint
shall be indicated clearly.
Others Issues
a. The contractor must bear in mind that all the work shall be carried out strictly in
accordance with the specifications made by the Bank and also in compliance of the
requirement of the local public authorities and any other
Acts/Rules/Regulations and no deviation on any account will be permitted.
b. The contractor shall furnish a joint undertaking along with the OEMs of various
equipment’s/ systems as per the enclosed proforma (Annexure I) that they will maintain the
entire system satisfactorily for a committed period of 3 years from the date of expiry of the
defect liability period at the rate quoted by them in this contract towards all inclusive
maintenance service contract subject to the terms, conditions, scope indicated under scope
of service contract.
c. The Contractor shall carry out all the work strictly in accordance with drawing, details, and
instructions of the Bank’s engineer. If in the opinion of the Bank’s engineer, nominal changes
have to be made to suit the site condition and with the prior approval in writing of the Bank,
they desire the Contractor to carry out the same, the Contractor shall carry out the same
without any extra charge.
d. The tenderer must obtain for himself on his own responsibility and at his own expense, all
the information which may be necessary for the purpose of making a tender and for entering
into a contract and must examine the drawings, inspect the site of the work, and acquaint
himself with all local conditions, means of access to the work, nature of the work and all
matters pertaining thereto. The Bank’s decision in such cases shall be final and shall not be
open to arbitration.
e. A Schedule of Probable Quantities in respect of each work and Specifications accompany
these Special Conditions. The Schedule of Probable Quantities is liable to alteration by
omissions, deductions or additions at the discretion of the Bank.
f. The contractor shall not be entitled to any compensation for any loss suffered by him on
account of delays in commencing or executing the work, whatever the cause of delays may be,
including delays arising out of modifications to the work entrusted to him or in any sub-
contract connected therewith or delays in awarding contracts for other trades of the project
or in commencement or completion of such works. The Bank does not accept liability for any
sum besides the tender amount, subject to such variations as are provided for herein.
g. The successful tenderer is bound to carry out all items of work necessary for completion of
the job even though such items are not included in the quantities and rates. Schedule of
instruction in respect of such additional items and their quantities will be issued in writing
by the Bank.
h. The successful tenderer must co-operate with other contractors appointed by the Bank so
that the work shall proceed smoothly with the least possible delay. He should make his own
arrangement for storage and protection of all materials supplied by him.
i. The work has to be carried out in an occupied office building and, therefore, may have to be
carried out during restricted hours/ Saturdays/Sundays/Bank’s holidays.
Documentation:
The CCTV system contractor, upon completion of all the activities, shall offer the system to
the customer for acceptance. For this, the contractor shall provide the customer with the
following documentation:
Prior to final acceptance, the contractor shall provide complete operation and maintenance
instruction manuals to the Bank along with all the above mentioned documents. All aspects
of system operation and maintenance shall be detailed, including wiring diagrams of all
circuits, a written description of the system design, sequence of operation and drawing(s),
illustrating control logic and equipment used in the system. Checklists and procedures for
emergency situations, maintenance operations and procedures shall be included in the
manual. The Bank’s engineer and security officer then shall test and inspect the
functioning of various components (eg cameras and their functions, recording
features, etc.) and a joint report shall be prepared. In case of any observations from
Bank’s side, the same shall be conveyed to the contractor in writing and got attended to by
the contractor to the satisfaction of the inspecting officials.
The entire system then shall be taken over by the Bank and the defect liability period shall
start from the same day.
Bank reserves the right to inspect equipment's and OFC, Cat-6 cables, other equipment, etc.
Any inspected goods fail for confirm to specification after installation, Bank may reject them
and the Vendor shall have to replace the rejected goods. In case of inspection waiver the same
shall be obtained before the Sample approval should be obtained before installation for such
material.
TRAINING:
The contractor shall provide the Bank with details of the training required by personnel to
operate and maintain the CCTV system.
The Contractor and the customer shall jointly agree the number of staff to attend the training
courses.
For all the active components/ equipment, namely; CCTV cameras, server, network switch,
and Network attached storage device, the OEMs shall provide a certificate, indicating the end
of life and end of support in form of spares etc. The product selected should conform to the
tender specified life period. Further, all software provided for the above system, including
operating system, video management software, client software etc. should be upgraded, if
necessary, as and when a new upgrade is released by the developer/ OEM at no extra cost
during the tender specified life period of the above system. A certificate, confirming the
above, shall be submitted from the respective developers/ OEMs along with Part-I as per the
proforma specified in the tender.
The objective shall be to provide high degree of IP based Electronic surveillance to the entire
Premises. It is also essential to have recorded images of all cameras to be stored at least for
30 days to facilitate investigations of a reported case.
This section of the specification includes the Design, Engineering, supply, installation,
testing, commissioning and maintenance of IP CCTV system and imparting training to
concerned officials in connection with IP CCTV system including all components.
All equipment and materials used shall be standard components from the current line/range
of products that are regularly manufactured and used in the system.
9.2 Scope:
The proposed locations of cameras and their type is indicated in the attached layout/ drawing.
The control room which is proposed on Ground Floor at all 04 locations, shall have all the
equipment housed in an equipment rack.
The Contractor will install, test & commission the system as per the drawing. The viewing
angles and clarity, etc. shall be shown to the officials of NABARD to their satisfaction before
finalizing the location, zoom and angle, etc. The specifications of all components shall be
strictly followed as per given technical specifications or better.
Original Equipment Manufacturer Standard. All the original licensed copies of the
software(s) shall be kept in the custody of the Bank.
9.4 Approvals:
34 User/Host 20
35 Storage FTP ; SFTP ; Micro SD Card (support max. 256 GB); NAS
18 Day/Night Auto(ICR)/Color/B/W
19 BLC Yes
20 HLC Yes
21 WDR 120 dB
22 White Balance Auto/natural/street lamp/outdoor/manual/regional custom
23 Gain Control Auto/Manual
24 Noise Reduction 3DNR
25 Motion Detection OFF/ON (4 areas, rectangular)
26 Region of Yes (4 areas)
Interest(RoI)
27 Smart Yes
Illumination
28 Image Rotation 0°/90°/180°/270°
29 Mirror Yes
30 Privacy Masking 4 areas
31 Alarm Event Motion detection, video tampering, no SD card, SD card full, SD card
error, network discon-nected, IP conflict, illegal access, local alarm,
voltage detection
32 Network RJ-45 (10/100 Base-T)
33 Protocol HTTP; TCP; ARP; RTSP; RTP; UDP; RTCP; SMTP; FTP; DHCP; DNS;
DDNS; PPPoE; IPv4/v6; QoS; UPnP; NTP; RTMP; Multicast; HTTPS;
SFTP; 802.1x; ICMP; IGMP; ONVIF (Profile S/Profile G); CGI;
Milestone; Genetec
34 User/Host 20
35 Storage FTP ; SFTP ; Micro SD Card (support max. 256 GB); NAS
36 Mobile Phone IOS; Android
37 Power Supply 12V DC/PoE (802.3af)
38 Operating -40°C to +60°C (-40°F to +140°F)/less than ≤ 95% RH
Conditions
39 Protection IP67
40 Casing Metal
15 Day/Night Auto(ICR)/Color/B/W
16 BLC Yes
17 HLC Yes
18 WDR 120 dB
19 White Balance Auto/natural/street lamp/outdoor/manual/regional custom
20 Gain Control Auto/Manual
21 Noise Reduction 3D NR
22 Motion Detection Disable/Enable (4 areas, rectangle)
23 Region of Interest(RoI) Yes (4 areas)
24 Smart Illumination Yes
25 Image Rotation 0°/90°/180°/270°
26 Mirror Yes
27 Privacy Masking 4 areas
28 Audio Compression G.711a; G.711Mu; G.726
29 Network RJ-45 (10/100 Base-T)
30 Protocol IPv4; IPv6; HTTP; HTTPS; TCP; UDP; ARP; RTP ; RTSP; RTCP;
RTMP; SMTP; FTP; SFTP; DHCP; DNS; DDNS; QoS; UPnP;
NTP; Multicast; ICMP; IGMP; NFS; PPPoE; 802.1x; Bonjour,
ONVIF (Profile S/Profile G); CGI; P2P; Milestone; Genetec
31 User/Host 20
32 Storage FTP ; SFTP ; Micro SD Card (support max. 256 GB); NAS
18 Search Mode Time /Date, Alarm, MD and Exact Search (accurate to second)
Play, Pause, Stop, Rewind, Fast play, Slow Play, Next File,
Previous File, Next Camera, Previous Camera, Full Screen,
19 Playback Function Backup Selection, Digital Zoom
20 Backup Mode USB Device/Network/eSATA Device
21 Interface 2 RJ-45 port (10/100/1000Mbps)
HTTP, HTTPS, TCP/IP, IPv4/IPv6, UPnP, SNMP, RTSP, UDP,
SMTP, NTP, DHCP, DNS, IP Filter, PPPoE, DDNS, FTP, Alarm
22 Network Function Server, IP Search, ONVIF 2.4, SDK, CG
23 Max. User Access 128 users
24 Internal HDD 8 SATA III ports, up to 8TB Each, 1 eSATA port
25 HDD Management single, Raid 0/1/5/10 (Support global HDD hot-spare)
26 Interface Ports 4 USB ports(2 USB 2.0 , 2 USB 3.0), 1 RS485, 1 RS232
27 Power Supply Single, AC100V ~ 240V, 50 ~ 60 Hz
Pole Specification
S.No Features Specification
1 Lighting pole details Free standing 8 sided octagonal continuously Tapered structure.
2 Height of pole 5Mtr.
3 Size of pole Top 70mm X Bottom 130mm
4 Thickness 3mm
5 Base plate 220 x 220 x 10mm
6 Foundation Bolt :M16x600mm
7 Usage Camera
8 Wind loads for design As per IS-875
Metal protection Hot Dip galvanized confirming to BSEN ISO 1461 [65 micron
9 treatment thickness]
9U Rack Specification
S.No Features Specification
2 Height 9U (Usable)
3 Rail Adjustable 19”
2 Height 17 U (Usable)
3 Rail Adjustable 19”
2 Nos. or more working is exhaust mode (230 VAC)
4 FAN Unit
required
5 Front Door Fully perforated single lockable glass door
General:
All the vendors must attach the point by point compliance for below
specification in their technical bid.
9.6 Layout
Camera
S.No Location
Qty
1 NABARD Office 31
2 NABARD Staff Quarters Cenotaph Road 22
3 NABARD Staff Quarters South Boag Road 19
4 NABARD Staff Quarters Bazullah Road 27
Total 99
Proposed Installations plan of the said cameras is attached separately as annexure to this
page.
The preferred list of makes is given below. Agency wishes to supply other than the preferred
brands should check the eligibility condition of pre-qualification criteria for OEM brands.
SN Equipment Makes
Note: - Items which are not mentioned in above list but required at site, shall be supplied
with prior approval of purchaser. All the items should be high quality.
Annexure I
To,
The CGM,
Tamilnadu Regional Office,
NABARD,
Nungambakkam, Chennai
Dear Sir
We hereby undertake to maintain the CCTV Surveillance system in Bank’s Office Building &
it’s Quarters in Chennai installed by us through M/s ,our
authorised dealer/ system integrator satisfactorily, for a period of not less than 2 years after
expiry of the defect liability/warranty period of three years from the date of commissioning
and handing over the system to the Bank at the rates quoted in the tender.
Yours faithfully,
For______________________
For______________________
(OEM)
Signature with seal
Bill of Quantity
S.N
Product Description UOM Qty Rate Amount
o
Supply, Installation & Maintenance of 4 MP
1 Fixed Dome Camera with Wall Mount Clamp Nos 14
as per 9.5 of technical specifications
Supply, Installation & Maintenance of 4 MP
2 Fixed Bullet Camera with Wall Mount Clamp Nos 69
as per 9.5 of technical specifications
Supply, Installation & Maintenance of
Motorized 4 MP VFL Camera 60 Mtrs IR
3 Nos 16
Range with Wall Mount Clamp as per 9.5 of
technical specifications
Note: The Rate & Amount quoted above should be inclusive of GST,
Transportations and all other charges