PONDASI BANGUNAN
NOMOR: I-QAC-027/100.19
INSPECTION TEST & PLAN
PEKERJAAN PONDASI BANGUNAN
PT PGAS SOLUTION
LEMBAR PENGESAHAN
Disetujui di Jakarta
Pada Tanggal: Juni 2021
Disusun Oleh: Oleh
Specialist QA EPC Kepala Divisi Manajemen Proyek EPC
LEMBAR REVISI
A 10 Mei 2021 - - -
INSPECTION TEST & PLAN
PEKERJAAN PONDASI BANGUNAN
PT PGAS SOLUTION
DAFTAR ISI
1. TUJUAN
Memberikan panduan umum mengenai Inspection and Test Plan pada pekerjaan pondasi
bangunan yang berada di jaringan pipa gas bumi beserta fasilitas pendukungnya.
2. LINGKUP KERJA
Dokumen ini berisi persyaratan minimum pekerjaan pekerjaan tanah meliputi meliputi pekerjaan
piling work, bored pile, dan pekerjaan pondasi.
3. REFERENSI
3.1. ACI 301 Specifications for Structural Concrete for Building
3.2. ACI 304 Recommended Practice for Measuring, Mixing, Transporting and
Placing Concrete
3.3. ACI 308 Recommended Practice for Curing Concrete
3.4. ACI 311.5R Batch Plant Inspection and Field Testing or Ready Mixed Concrete
3.5. ACI 318 Building Code Requirements for Reinforced Concrete
3.6. ASTM A82 Wire, Plain Steel for Concrete Reinforcement
3.7. ASTM C33 Specification for Concrete Aggregates
3.8. ASTM C39 Test Method for Compressive Strength of Cylindrical Concrete
3.9. ASTM C40 Standard Practice for Soil Exploration and Sampling by Auger Borings
3.10. ASTM C94 Ready mixed Concrete
3.11. ASTM C150 Standard Test Method for Density of Unit Weight of Soil in Place by
Sand Cone Method
3.12. ASTM C260 Standard Test Method for Standard Penetration Test (SPT)
3.13. ASTM C136 Standard Test Method for Sieve Analysis of Fine and Coarse
Aggregates
3.14. ASTM C138 Standard Test Method for Unit Weight, Yield, Air Content (Gravimetric)
of Concrete
3.15. ASTM C143 Test Method for Slump of Portland Cement Concrete
3.16. ASTM C494 Specification for Chemical Admixtures for Concrete
3.17. SNI 2847:2019 Persyaratan Beton Struktural Untuk Bangunan Gedung dan
Penjelasan
3.18. SNI 2052:2017 Baja Tulangan Beton
3.19. SNI 7974:2013 Spesifikasi Air Pencampur Dalam Produksi Beton Semen Hidraulis
4. SINGKATAN
4.1. ACI American Concrete Institute
4.2. ASTM American Standard Testing and Material
4.3. SNI Standar Nasional Indonesia
INSPECTION TEST & PLAN
PEKERJAAN PONDASI BANGUNAN
PT PGAS SOLUTION
5. KETENTUAN UMUM
Istilah tingkat pemeriksaan yang digunakan dalam Rencana Inspeksi dan Pengujian untuk
semua pihak adalah seperti dibawah ini:
“ I ” Inspect : Pemeriksaan wajib terhadap pekerjaan yang telah diselesaikan seperti
yang ditunjukkan pasa symbol “I” pada Rencana Inspeksi dan
Pengujian. Kegiatan bisa berupa cek visiual, test, pengukuran
dimensional.
“P” Provide / : Tanggung jawab untuk menyiapkan pengujian / inspeksi atau
Perform menyiapkan dokumen (Prosedur, Instruksi Kerja, Laporan Inspeksi, dll.)
“M” Monitor : Kegiatan yang dilakukan berkelanjutan dan terjadwal, tanpa
pemberitahuan/undangan terlebih dahulu. Memantau kegiatan yang
dimaksudkan untuk proses verifikasi, bukan inspeksi / pengujian barang
/ material.
W ” Witness : Sebuah kegiatan yang membutuhkan kehadiran Inspektur atau
perwakilan yang ditunjuk pada proses kegiatan inspeksi / pengujian. Jika
Inspektur atau perwakilan tersebut tidak hadir pada saat kegiatan
inspeksi / pengujian, kegiatan dapat dilanjutkan tanpa Inspektur atau
perwakilan yang ditunjuk.
“SW” Spot : Sebuah kegiatan yang dilakukan oleh Inspektur atau perwakilan secara
Witness acak pasa proses kegiatan produksi atau instalasi. Dalam hal ini
kegiatan dapat dilakukan tanpa kehadiran Inspektur atau perwakilannya.
“ R “ Review : Review dan evaluasi laporan, prosedur, kualifikasi dan memverifikasi
kesesuaian terhadap spesifikasi.
“A “ Approval : Persetujuan dokumentasi sebelum memulai tahap berikutnya,
persetujuan ini menyangkut dokumen dan laporan.
“ H “ Hold : Sebuah titik yang membutuhkan kehadiran Inspektur atau
perwakilannya pada proses kegiatan inspeksi / pengujian pekerjaan
hanya dapat dilanjutkan jika sudah ada persetujuan dari Inspektur atau
perwakilannya.
7. RISIKO POTENSIAL
Risiko Potensial pada pekerjaan pekerjaan pondasi adalah sebagai berikut:
Rencana Mitigasi:
Hindari perjalanan campuran beton yang terlalu tinggi dan
atau terlalu jauh serta membuat rancangan campuran yang
memadai, dengan atau tanpa bahan admixture.
2. Menghindari Risiko Potensial:
terjadinya cacat Terjadinya retak (shrinkage cracking) pada beton setelah
setelah dilakukan dilakukan pengecoran beton
pengecoran
Rencana Mitigasi:
Perlu menggunakan curing compound seperti Sodium silicate
based material & Wax based material untuk memperkecil
resiko shrinkage cracking.
3. Menghindari Risiko Potensial:
kegagalan saat Mesin pemancang (pile divers) roboh
melakukan
pemancangan Rencana Mitigasi:
Mesin pemancang (pile divers) harus ditumpu oleh dasar yang
kuat seperti balok kayu yang berat, bantalan beton atau
pondasi penguat lainnya. Mesin pemancang juga harus diberi
tali atau rantai penguat secukupnya.
4. Mencegah terjadinya Risiko Potensial:
kecelakaan kerja Pekerja tertimpa tiang pancang saat diangkat menggunakan
excavator
Rencana Mitigasi:
Pada saat pekerjaan pengangkatan tiang pancang harus
dilakukan oleh operator yang ahli. Pada saat pengangkatan,
lokasi di sekitar pekerjaan harus steril tidak boleh ada pekerja
di area tersebut.
8. LAMPIRAN
Lampiran – 1 Inspection and Test Plan Pondasi Bangunan
Lampiran – 2 Contoh Form Laporan Inspeksi
INSPECTION TEST & PLAN
PEKERJAAN PONDASI BANGUNAN
PT PGAS SOLUTION
Lampiran-1
Inspection and Test Plan Pekerjaan Pondasi bangunan
JOB No : REV
DOC. NO. :
Logo A
Pemberi Kerja INSPECTION AND TEST PLAN PONDASI BANGUNAN
DATE : BY CHD APVD
RESPONSIBILITY REMARKS
NO KEGIATAN INSPEKSI / ITEM UJI METODE INSPEKSI REF. DOCUMENT LEVEL OF ACCEPTANCE / REFERENCE VERIFIED DOCUMENT PEMBERI
PGAS PI MIGAS
KERJA
1 PEKERJAAN PEMANCANGAN
1.1. PERSIAPAN
1 Metode Konstruksi (peralatan konstruksi, kriteria pemancangan, peralatan, dll) Review App. Procedure & Eng. Spec. App. Procedure & Eng. Spec. Approved Procedure P,I R,A
3 Koordinat pengaturan pemancangan dengan survei Dimensional App. Drawing App. Drawing Inspection Report P,I SW,A
4 Urutan Piling Visual, Check App. Drawing, Data Sheet & Eng. Spec. App. Drawing, Data Sheet & Eng. Spec. Inspection Report P,I R
5 Metode Joint Review App. Procedure & Eng. Spec. App. Procedure & Eng. Spec. Inspection Report P,I R,A
6 Kualitas Bahan Tiang Pancang Visual, Dimensional App. Procedure & Eng. Spec. App. Procedure & Eng. Spec. Inspection Report P,I R,A
7 Jumlah & Ukuran Tiang Pancang Visual, Dimensional App. Procedure & Eng. Spec. App. Procedure & Eng. Spec. Inspection Report P,I R
8 Consumable Visual, Check App. Procedure & Eng. Spec. App. Procedure & Eng. Spec. Inspection Report P,I R
1.2. PEMANCANGAN
1 Lokasi dan kemiringan tiang pancang Visual, Check App. Drawing, Procedure & Eng. Spec. App. Drawing, Procedure & Eng. Spec. Inspection Report P,I SW,A
2 Pengelasan Visual, Check App. Procedure App. Procedure Inspection Report P,I SW,A
3 Periksa sambungan las. (WPS + Tukang Las) Visual, Check App. Procedure App. Procedure Inspection Report P,I R,A
4 Penetrasi dan Top Elevation Dimensional App. Procedure App. Procedure Inspection Report P,I R
5 Peninggian kepala tiang terputus Dimensional App. Drawing, Procedure & Eng. Spec. App. Drawing, Procedure & Eng. Spec. Inspection Report P,I R
6 Perawatan Pile Cap Visual, Check App. Drawing, Procedure & Eng. Spec. App. Drawing, Procedure & Eng. Spec. Inspection Report R
7 Survei pile off-set Dimensional App. Drawing, Procedure & Eng. Spec. App. Drawing, Procedure & Eng. Spec. Inspection Report P,I W,A
1.3. PENGUJIAN DAN PEMANTAUAN
1 Metode Tes Review App. Engineering Spec. App. Engineering Spec. Approved Procedure P,I R,A
2 Identifikasi titik akan diuji Visual App. Engineering Spec. App. Engineering Spec. Approved Procedure P,I R,A
3 Eksekusi Uji Test App. Engineering Spec. App. Engineering Spec. Inspection Report P,I R,A
1.4. INSPEKSI FINAL
1 Final Inspeksi Review App. Procedure & Eng. Spec. App. Procedure & Eng. Spec. Inspection Report P,I R,A
2 TIANG BOR
2.1. PERSIAPAN
1 Pembongkaran fasilitas yang ada Visual, Check App. Drawing, Procedure & Eng. Spec. App. Drawing, Procedure & Eng. Spec. Inspection Report P,I R
2 Investigasi fasilitas bawah tanah yang ada Visual, Check App. Drawing, Procedure & Eng. Spec. App. Drawing, Procedure & Eng. Spec. Inspection Report P,I R
3 Penentuan titik lokasi pengeboran Visual, Check App. Drawing, Procedure & Eng. Spec. App. Drawing, Procedure & Eng. Spec. Inspection Report P,I R
2.2. PEKERJAAN TIANG BOR
1 Pembongkaran fasilitas yang ada Visual, Check App. Drawing, Procedure & Eng. Spec. App. Drawing, Procedure & Eng. Spec. Inspection Report P,I R
2 Keamanan terkait pekerjaan pengeboran Visual, Check App. Drawing, Procedure & Eng. Spec. App. Drawing, Procedure & Eng. Spec. Inspection Report P,I R
3 Pengeringan Visual, Check App. Drawing, Procedure & Eng. Spec. App. Drawing, Procedure & Eng. Spec. Inspection Report P,I R
4 Pekerjaan Penulangan Beton Visual, Check App. Drawing, Procedure & Eng. Spec. App. Drawing, Procedure & Eng. Spec. Inspection Report P,I R
5 Pekerjaan Beton Visual, Check App. Drawing, Procedure & Eng. Spec. App. Drawing, Procedure & Eng. Spec. Inspection Report P,I R
RESPONSIBILITY REMARKS
NO KEGIATAN INSPEKSI / ITEM UJI METODE INSPEKSI REF. DOCUMENT LEVEL OF ACCEPTANCE / REFERENCE VERIFIED DOCUMENT PEMBERI
PGAS PI MIGAS
KERJA
3 Pemeriksaan Besi Penulangan Visual, Dimensional App. Drawing App. Drawing Inspection Report P,I R
4 Inspection of Form Work Visual, Dimensional App. Drawing App. Drawing Inspection Report P,I R
5 Ukur sisipan / Anchor Bolt Dimensional App. Drawing App. Drawing Inspection Report P,I R
6 Pouring Concrete (drop height, proper vibration, thickness) Visual, Dimensional App. Drawing App. Drawing Inspection Report P,I R
3.3 PENGUJIAN DAN PEMANTAUAN
1 Uji Slump untuk tekan Test App. Engineering Spec. App. Engineering Spec. Inspection Report P,I R,A
2 Ambil Sampel Uji Beton Visual App. Engineering Spec. App. Engineering Spec. Inspection Report P,I R,A
3 Ukur Kekuatan Tekan Test App. Engineering Spec. App. Engineering Spec. Inspection Report P,I R,A
4 Visually Inspection Surface Finish Visual App. Drawing App. Drawing Inspection Report P,I R,A
5 Pemeriksaan Akhir Fondasi Visual, Dimensional App. Drawing App. Drawing Inspection Report P,I R,A
INSPECTION TEST & PLAN
PEKERJAAN PONDASI BANGUNAN
PT PGAS SOLUTION
Lampiran-2
Contoh Form Laporan Inspeksi
Logo
Pemberi Kerja PROJECT TITLE
Contract No.
REINFORCING BAR INSTALLATION
Equipment No. : System No. :
Ref. Drawing : Sub System No. :
Area : Location :
1 Size/Length/Quality
5 Extra Length
9 Concrete Cover
13 Quality of Cleaning
Remarks :
Print Name
Signature
Date
Logo
Pemberi Kerja PROJECT TITLE
Contract No.
Construction site
Construction section
Requirements
Aggregate Type/Manufacturer/Quarry/Borrowpit
Cement manufacturing plant
aggregate % dm 3 / m3 kg / dm3 kg / m3 kg % kg kg
Cement
Water
Weight of Fresh Concrete
Concrete admixtures
Ultra fine concrete = kg/m 3 Cement = kg/m 3 Aggregate < 0.25 mm kg/m 3 Concrete additive = kg/m 3
Print Name
Signature
Date
Logo
Pemberi Kerja PROJECT TITLE
Contract No.
POURING CONCRETE
Equipment No. : System No. :
Ref. Drawing : Sub System No. :
Area : Location :
FORMWORK REBAR
Orientation Size
Location ( Coord. ) Spacing
size Clearance
Elevation Cleanliness
Clean & Oiled
Chamfer
Bracing
EMBEDMENTS MISCELLANEOUS
Remarks :
Print Name
Signature
Date
23 of 38
Logo
Pemberi Kerja PROJECT TITLE
Contract No.
Remarks :
Print Name
Signature
Date
Date :
Logo Form Number
Pemberi Kerja
PROJECT TITLE Page : of
Doc.No :
1. General
3. Test Result
Acceptable
Not Acceptable
Signature
Date
Date :
Logo
Pemberi Kerja
Form Number
PROJECT TITLE Page: of
Doc. No
Project no :
Subject : PILING SURVEY DATA
Project :
Location :
Ref. Drawing :
Print Name
Signature
Date
Date :
Logo
Pemberi Kerja Form Number
Page: of
PROJECT TITLE
Doc. No
Project no :
Subject : PILING SITE REPORT
Project : Location :
Total Nos : Ref. Drawing :
Cummulative :
NO PILE RIG NO. NO. OF SECTION TOTAL TOP OF PILE PENETRATION TO 10 BLOW FOR HAMMER REMARKS
REF. NO. 1 2 3 4 REV. ELEV. LENGTH AGL BGL GL SET TC SIZE FINAL TIP
WELDED
(M) (M) (M) (M) (M) ELEVATION
Print Name
Signature
Date
Date :
Logo
Pemberi Kerja
Form Number
PROJECT TITLE Page : of
Doc. No :
Project no :
Subject : WELDING & COATING RECORD FOR PILING
Project : Location :
Area : Ref. Drawing :
WPS No. : Weather :
JOINT WELDING
PILE REF. NO. TIME WELDER INSPECTION RESULT REMARKS
NO. ELECTRODE
Inspection Method :
V : Visual
Print Name
Signature
Date
Date ;
Logo
Pemberi Kerja
Form Number
PROJECT TITLE Page : of
Doc.No
Project No. :
Subject : PILE LOADING TEST RECORD
Project : Location :
Test Pile No. : Date of Testing :
Dated Installed : Test Load :
Size of Pile : Ground Level :
Working Load :
Length af Pile :
Description of Test :
Remarks
Signature
Date
Date :
Logo
Pemberi Kerja
Form Number
PROJECT TITLE Page : of
Doc.No
Project No.
Subject : BORE PILE
A. General
ACCEPTED
Description Remarks
Date Signature
B. Drilling
1. Size Dia. 19 h1
2. Lap Splacing min 40D
h2
3. Starter Bar h3
4. Hoop / Stirup Dia.10 @150
D. Concreting
1. Tremi Installation
2. Pouring Concrete fc 210/V
3. Removal of Casing
Acceptable
Not Acceptable
Print Name
Signature
Date