You are on page 1of 6

SOFTWARE ENGINEERING

NAME:- SOPARIWALA MO.FAIZAN M

Enrollment No.:- 190410107133

Batch:- T.Y.C.E :- 2 – C

PRACTICAL NO.:- 3
Costing For Software Requirement Specification of
Vaccination Management Camp.

1)Function Point:-

FP = UFP * CAF

Organizations that use function point methods develop a criterion


for determining whether a particular entry is Low, Average or High.
Nonetheless, the determination of complexity is somewhat
subjective.

Where CAF is complexity adjustment factor and is equal to [0.65 +

0.01 x ΣFi]. The Fi (i=1 to 14) are the degree of influence and are

based on responses to questions.


1)Login:- For Unadjusted Function Point

Information Count Weighting Factor Count*WF


Domain
Low Average High
External Inputs (EIs) 3 3 4 6 18+8
2 3 4 6
External Outputs 2 4 5 7 14
(EOs)
External Inquiries 1 3 4 6 6
(EQs)
Internal Logical Files 1 7 10 15 15
(ILFs)
External Interface 0 5 7 10 0
Files (EIFs)
Count Total UFP = 61

2)Admin:- For Unadjusted Function Point

Information Count Weighting Factor Count*WF


Domain
Low Average High
External Inputs (EIs) 2 3 4 6 12

External Outputs 3 4 5 7 15+7


(EOs) 1 4 5 7
External Inquiries 0 3 4 6 0
(EQs)
Internal Logical Files 1 7 10 15 10
(ILFs)
External Interface 4 5 7 10 40
Files (EIFs)
Count Total UFP = 84

3)Vaccination & Schedule:- For Unadjusted Function Point

Information Count Weighting Factor Count*WF


Domain
Low Average High
External Inputs (EIs) 1 3 4 6 6+3+4
1 3 4 6
1 3 4 6
External Outputs 2 4 5 7 14
(EOs)
External Inquiries 1 3 4 6 4
(EQs)
Internal Logical Files 1 7 10 15 15
(ILFs)
External Interface 1 5 7 10 10
Files (EIFs)
Count Total UFP = 56

3)Payment & Reminder:- For Unadjusted Function Point

Information Count Weighting Factor Count*WF


Domain
Low Average High
External Inputs (EIs) 2 3 4 6 12+4
1 3 4 6
External Outputs 2 4 5 7 10
(EOs)
External Inquiries 1 3 4 6 4+4
(EQs) 1 3 4 6
Internal Logical Files 1 7 10 15 15
(ILFs)
External Interface 0 5 7 10 0
Files (EIFs)
Count Total UFP = 49

Average Of UFP Of Different Module of System:-

=(61+84+56+49)/4

=250/4

UFP =62.5

So sum of all Fi (i ← 1 to 14) = 5+3+2+0+5+4+2+0+2+4+4+0+5+4

∑Fi =40

Function Point(FP) = UFP*[0.65+(0.01*∑Fi)]

= 62.5*[0.65+(0.01*40)]

= 62.5*[0.65+0.4]

= 62.5*1.05

FP = 65

2) Constructive Cost Model (COCOMO):-

Our System is semi detached means Medium size project, Medium


size team, Average previous experience on similar project. For
example: Utility systems like compilers, database

systems, editors etc.


Basic COCOMO model takes the form:-

E= a(KLOC)^b

D= c(E)^d

where E is effort applied in Person-Months, and D is the

development time in months. The coefficients a, b, c and d are

given in table.

E=3(250)^1.12

=1455

D=2.5(1455)^0.35

=32

Average Staff Size:-


=E/D Persons

=1455/32

=45.46

= 45 Person