You are on page 1of 18

Project Plan for OGL 320 (Spring 2020 - A)

Jana Lee Cox Legend: Product PM Activity Optional Product Contingency

Planned Planned Actual Actual Comparison of


Due Planned Actual Start Planned time to Re-planned Re-planned Start Actual time Actual vs Planned
Product Date Delivery Delivery Tasks      Subtasks   Date End Date invest start date end date Date  End Date invested time invested
Read through Syllabus (Product Specifications) ### ### 15 min — — ### ### 15 min No difference
Read Client emails and announcements to learn client ### ### 30 min — — ### ### 30 min No difference
expectations
Familiarize with Community Forums to determine where
to go for information and questions ### ### 15 min — — ### ### 15 min No difference
Manage the Project:
Review Project Parameters, Study
### ### Read through ASU Online Course Policies, Welcome to
Contract, and Conduct First ### ### 1 hr — — ### ### 1 hr No difference
Weekly PM Status Meeting OGL 320, and Course Overview

Review Production Tools—Using Perusall, Video Quizzes,


and Peer Reviews—in order to understand how products ### ### 1 hr — — ### ### 30 min -30 min
are to be delivered

Set appropriate short-term goals ### ### 15 min — — ### ### 15 min No difference

Read the ASU Student Academic ### ### 1 hr 1/10/2020 1/10/2020 ### ### 45 min -15 min
Agreement to Adhere to the Policy
### ### ###
Academic Integrity Rules Enter and submit date of
### ### 10 min 1/10/2020 1/10/2020 ### ### 5 min -5 min
agreement

Determine Requirements Review Quality Criteria and Product Specifications to ### ### 10 min 1/10/2020 1/10/2020 ### ### 10 min No difference
determine spacing of notations
Course Structure Conversation
Contributions ### ### ### Take notes ### ### 3 hrs 1/10/2020 1/10/2020 ### ### 1 hr -2 hrs
(Perusall - 6 comments) Read text Annotate text, monitoring Perusall scores for quality ### ### 1 hr 1/10/2020 1/10/2020 ### ### 1 hr No difference
contributions. Revise as necessary

Determine Requirements Review Quality Criteria and Product Specifications to ### ### 10 min 1/13/2020 1/13/2020 ### ### 10 min No difference
Submissions that demonstrate determine spacing of notations
engagement with the concepts in
O'Connell (2011) Intro, Ch. 1 & ### ### ### Take notes ### ### 3 hrs 1/13/2020 1/13/2020 ### ### 3 hrs No difference
Ch. 2 Read text Annotate text, monitoring Perusall scores for quality
(Perusall - 7 comments) ### ### 1 hr 1/13/2020 1/13/2020 ### ### 2 hrs +1 hr
contributions. Revise as necessary

Register for appointment ### ### 5 min — — ### ### 5 min No difference

Attend optional one-on-one Read available information regarding Instructor phone


appointments ### ### 10 min — — ### ### 10 min No difference
meeting with Client (Instructor) to
### ###
review client expectations and Keep appointment. Talk with client. Establish trust. ### ### 30 min — — ### ### 40 min +10 min
Product Specifications
Take notes of expectations addressed during ### ### 15 min — — ### ### 15 min No difference
conversation.

Review Quality Criteria and Product Specifications to


Submissions that demonstrate Determine Requirements
determine spacing of notations
### ### 10 min 1/14/2020 1/14/2020 ### ### 10 min No difference
engagement with the concepts in
Wiefling (2007) Kickoff, Ch. 1 & ### ### ### Take notes ### ### 2 hrs 1/14/2020 1/14/2020 ### ### 2.5 hrs +30 min
Ch. 2 Read text Annotate text, monitoring Perusall scores for quality
(Perusall - 7 comments) ### ### 1 hr 1/14/2020 1/14/2020 ### ### 1.5 hrs +30 min
contributions. Revise as necessary
Answer Questions ### ### 10 min. 1/15/2020 1/15/2020 ### ### 10 min. No difference
Submissions that demonstrate
understanding of concepts in ### ### ### Watch Video
Respond to Prompts in video ### ### 15 min. 1/15/2020 1/15/2020 ### ### 15 min. No difference
Project Management Save prompts and responses in separate Word file as
Terminology Video Quiz reference for succeeding products
### ### 5 min 1/15/2020 1/15/2020 ### ### 5 min No difference

Answer Questions ### ### 10 min. 1/15/2020 1/15/2020 ### ### 10 min. No difference
Submissions that demonstrate
understanding of concepts in ### ### ### Watch Video
Respond to Prompts in video ### ### 15 min. 1/15/2020 1/15/2020 ### ### 15 min. No difference
Conversation with a PM - Part 1 Save prompts and responses in separate Word file as
Video Quiz reference for succeeding products
### ### 5 min 1/15/2020 1/15/2020 ### ### 5 min No difference

Answer Questions ### ### 10 min. 1/15/2020 1/15/2020 ### ### 10 min. No difference
Submissions that demonstrate
understanding of concepts in ### ### ### Watch Video
Respond to Prompts in video ### ### 15 min. 1/15/2020 1/15/2020 ### ### 20 min. +5 min
Baseline Assessment Video Quiz Save prompts and responses in separate Word file as
(Complete prior to Baseline Assessment) reference for succeeding products ### ### 5 min 1/15/2020 1/15/2020 ### ### 5 min No difference

Complete Baseline Assessment Video Quiz ### ### 30 min — — ### ### 30 min No difference
Complete product prerequisites Review Product Specifications ### ### 15 min — — ### ### 45 min +30 min
Review Quality Criteria ### ### 15 min — — ### ### 30 min +15 min

Respond to prompts in Product Specifications ### ### 3 hrs — — ### ### 2 hrs -1 hr

Reread and edit script for clarity ### ### 1 hr — — ### ### 2hrs +1 hr
Communicate with client to reaffirm expectations ### ### 15 min — — ### ### 15 min No difference
regarding length of video
Create script for assessment video
Edit script for length ### ### 30 min — — ### ### 1 hr +30 min
Read script aloud and edit for ease and authenticity of
### ### 30 min — — ### ### 45 min +15 min
Baseline Assessment delivery
(Pre-requisite: Submissions that ### ### ### Edit script for ease of accessibility during production
demonstrate understanding of concepts in ### ### 30 min — — ### ### 15 min -15 min
(large type, one sentence per line)
Baseline Assessment Video Quiz)
Experiment with lighting and presentation ### ### 30 min — — ### ### 45 min +15 min
Perform basic trial run of presentation on video ### ### 15 min — — ### ### 20 min +5 min
Experiment to see how video responds to post- ### ### 15 min — — ### ### 10 min -5 min
Practice video production production software
View video and analyze results—make additional
### ### 15 min — — ### ### 20 min +5 min
adjustments as necessary
Perform additional trial runs as necessary ### ### 30 min — — ### ### 30 min No difference
Evaluate presentation ### ### 15 min — — ### ### 15 min No difference
Record final video Edit video using post-production software ### ### 15 min — — ### ### 10 min -5 min
Upload assignment to Canvas ### ### 15 min — — ### ### 15 min No difference

Manage the Project: Review requirements for coming week ### ### 10 min — — ### ### 15 min +5 min
### ###
Conduct Weekly PM Status Mtg Set appropriate short-term goals ### ### 10 min — — ### ### 15 min +5 min

Determine Requirements Review Quality Criteria and Product Specifications to ### ### 5 min 1/17/2020 1/17/2020 ### ### 10 min +5 min
Submissions that demonstrate determine spacing of notations
engagement with the concepts in ### ### ### Take notes ### ### 2 hrs 1/17/2020 1/17/2020 ### ### 2 hrs No difference
Wiefling (2007) Chapters 10 & 11
(Perusall - 7 comments) Read text
Submissions that demonstrate
engagement with the concepts in ### ### ###
Wiefling (2007) Chapters 10 & 11
(Perusall - 7 comments) Read text Annotate text, monitoring Perusall scores for quality ### ### 2 hrs 1/17/2020 1/17/2020 ### ### 2 hrs No difference
contributions. Revise as necessary

Review Quality Criteria and Product Specifications to


Determine Requirements ### ### 5 min 1/18/2020 1/18/2020 ### ### 10 min +5 min
Submissions that demonstrate determine spacing of notations
engagement with the concepts in ### ### ### Take notes ### ### 1 hr 1/18/2020 1/18/2020 ### ### 1 hr No difference
What is Quality Assurance?
(Perusall - 3 comments) Read text Annotate text, monitoring Perusall scores for quality
### ### 2 hrs 1/18/2020 1/18/2020 ### ### 1 hr -1 hr
contributions. Revise as necessary

Answer Questions ### ### 30 min 1/18/2020 1/18/2020 ### ### 15 min -15 min
Submissions that demonstrate
understanding of concepts in ### ### ### Watch Video
Respond to Prompts in video ### ### 15 min 1/18/2020 1/18/2020 ### ### 15 min No difference
Product Specifications and Save prompts and responses in separate Word file as
Quality Criteria Video Quiz reference for succeeding products
### ### 5 min 1/18/2020 1/18/2020 ### ### 5 min No difference

Answer Questions ### ### 15 min 1/18/2020 1/18/2020 ### ### 15 min No difference
Submissions that demonstrate
Respond to Prompts in video ### ### 15 min 1/18/2020 1/18/2020 ### ### 15 min No difference
understanding of concepts in ### ### ### Watch Video
Rubrics Video Quiz Save prompts and responses in separate Word file as
### ### 5 min 1/18/2020 1/18/2020 ### ### 5 min No difference
reference for succeeding products

Review Quality Criteria and Product Specifications to


Submissions that demonstrate Determine Requirements
determine spacing of notations
### ### 5 min 1/22/2020 1/22/2020 ### ### 10 min +5 min
engagement with the concepts in
De Reyck (2010) - Effective ### ### ### Take notes ### ### 2 hrs 1/22/2020 1/22/2020 ### ### 3 hrs +1 hr
Project Planning Read text Annotate text, monitoring Perusall scores for quality
(Perusall - 7 comments) ### ### 2 hrs 1/22/2020 1/22/2020 ### ### 2 hrs No difference
contributions. Revise as necessary

Answer Questions ### ### 15 min 1/22/2020 1/22/2020 ### ### 15 min No difference
Submissions that demonstrate
Respond to Prompts in video ### ### 15 min 1/22/2020 1/22/2020 ### ### 15 min No difference
understanding of concepts in ### ### ### Watch Video
Project Planning Video Quiz Save prompts and responses in separate Word file as
### ### 5 min 1/22/2020 1/22/2020 ### ### 5 min No difference
reference for succeeding products

Arrange to get off work early ### ### 5 min. — — ### ### 5 min. No difference
Review login instructions and prepare link day before ### ### 5 min. — — ### ### 5 min. No difference
Attend Jan 23rd Optional Open
session to familiarize with Project Write down possible questions ### ### 10 min — — ### ### 10 min No difference
### ###
Plan Specifications and review
client expectations Participate in meeting; Ask questions ### ### 1 hr — — ### ### 1.5 hr +30 min

Take notes and screenshots of important information ### ### 10 min — — ### ### 15 min +5 min

Review Product Specifications ### ### 1 hr 1/18/2020 1/18/2020 ### ### 2 hrs +1 hr
### ### Start Project plan
Follow Schedule for Assignment: Project Plan ### ### 3 hrs 1/18/2020 1/20/2020 ### ### 7 hrs. +4 hrs

Answer Questions ### ### 15 min 1/23/2020 1/23/2020 ### ### 15 min No difference
Submissions that demonstrate
understanding of concepts in ### ### ### Watch Video
Respond to Prompts in video ### ### 15 min 1/23/2020 1/23/2020 ### ### 15 min No difference
Planning for Contingencies Video Save prompts and responses in separate Word file as
Quiz reference for succeeding products ### ### 5 min 1/23/2020 1/23/2020 ### ### 5 min No difference

Manage the Project: Review requirements for coming week ### ### 15 min — — ### ### 15 min No difference
### ###
Conduct Weekly PM Status Mtg
### ### Manage the Project:
Conduct Weekly PM Status Mtg Set appropriate short-term goals ### ### 15 min — — ### ### 15 min No difference

Review requirements of
documentation so I can participate ### ### 15 min. — — ### ### 15 min. No difference
in open session with purpose
Documentation of Participation
in Jan 23rd Open session ### ### ### Attend Open session or view
recording ### ### 1 hr. — — ### ### 1.5 hr. +30 min
(Extra Credit - Optional)
Complete documentation ### ### 30 min — — ### ### 30 min No difference
Upload to Canvas or post on ### ### 5 min — — ### ### 5 min No difference
discussion board

Review Quality Criteria and Product Specifications to


Submissions that demonstrate Determine Requirements ### ### 5 min 1/26/2020 1/26/2020 ### ### 10 min +5 min
determine spacing of notations
engagement with the concepts in
Work Break Down Structure ### ### ### Take notes ### ### 2 hrs 1/26/2020 1/26/2020 ### ### 2 hrs No difference
(WBS) Read text Annotate text, monitoring Perusall scores for quality
(Perusall - 7 comments) ### ### 2 hrs 1/26/2020 1/26/2020 ### ### 2.5 hrs +30 min
contributions. Revise as necessary

Relate reading to personal experience ### ### 30 min. 1/25/2020 1/25/2020 ### ### 15 min -15 min
Read assignment
Formulate response to queries ### ### 2 hrs. 1/25/2020 1/25/2020 ### ### 1.75 hrs -15 min
Canvas Discussion: ### ### ###
Products, Tasks, and Subtasks Record responses in Word doc ### ### 10 min 1/25/2020 1/25/2020 ### ### 10 min No difference
Copy response to Canvas
### ### 10 min 1/25/2020 1/25/2020 ### ### 10 min No difference
discussion board

Review Product Specifications in detail ### ### 20 min 1/18/2020 1/18/2020 ### ### 45 min -25 min
Review Contract (Syllabus)
Review each Quality Criteria in detail ### ### 20 min 1/18/2020 1/18/2020 ### ### 45 min -25 min
Design spreadsheet using freeze frames to keep ### ### 15 min 1/18/2020 1/18/2020 ### ### 30 min +15 min
Create basic spreadsheet for headings always visible
Project Plan Determine column headings, referring to template in ### ### 15 min 1/18/2020 1/18/2020 ### ### 30 min +15 min
product specifications
Determine and record specifications for each individual
product ### ### 2 hrs 1/20/2020 1/20/2020 ### ### 2 hr No difference

List due dates ### ### 1 hr 1/20/2020 1/20/2020 ### ### 1 hr No difference
List each product expected by Develop and record tasks and subtasks for each product ### ### 3 hrs. 1/22/2020 1/23/2020 ### ### 5 hrs +2 hrs
client (from contract)
Project Plan ### ### ###
(Prerequisites: All previous products) Use due dates to develop Planned Start and End Dates ### ### 3 hrs. 1/23/2020 1/28/2020 ### ### 12 hrs +9 hrs

Record actual start dates on completed items ### ### 30 min 1/25/2020 1/29/2020 ### ### 4 hrs +3.5 hrs
Brainstorm possible risks and contingencies ### ### 1.5 hrs — — ### ### 1 hr -30 min
Develop Contingency plans Consider each individually and determine ways to ### ### 1.5 hrs — — ### ### 3 hrs +1.5 hrs
minimize impact
Check for accuracy and clarity ### ### 2 hrs — — ### ### 1.5 hrs -30 min
Add additional adjustments and items ### ### 30 min — — ### ### 2 hr +1.5 hrs
Review Project plan document
Adjust spreadsheet layout and design for professional
### ### 30 min 1/28/2020 1/29/2020 ### ### 2 hrs +1.5 hrs
appearance and ease of use
Upload Project Plan to Canvas Review Quality Criteria and upload final to Canvas ### ### 15 min 1/29/2020 1/29/2020 ### ### 10 min -5 min
Manage Planned Contingency: Pick up daughter at airport (see notes on tab 2, Risk ### ### 4 hrs — — ### ### 4 hrs No difference
Family Event Mgt.)

Look over entire plan 2/1/2020 2/1/2020 45 min 1/31/2020 1/31/2020 ### ### 20 min -25 min
Review plan for Peer #1
Complete Rubric evaluation 2/1/2020 2/1/2020 15 min 1/31/2020 1/31/2020 ### ### 40 min +25 min
Look over entire plan 2/1/2020 2/1/2020 45 min 1/31/2020 1/31/2020 ### ### 20 min -25 min
Review plan for Peer #2
Complete Rubric evaluation 2/1/2020 2/1/2020 15 min 1/31/2020 1/31/2020 ### ### 50 min +35 min
Peer Reviews of Colleagues' Look over entire plan 2/1/2020 2/1/2020 45 min 1/31/2020 1/31/2020 ### ### 20 min -25 min
Project Plans 2/1/2020 2/1/2020 ### Review plan for Peer #3
(Prerequisite: Project Plan) Complete Rubric evaluation 2/1/2020 2/1/2020 15 min 1/31/2020 1/31/2020 ### ### 20 min +5 min
Look over entire plan 2/1/2020 2/1/2020 45 min 1/31/2020 1/31/2020 ### ### 20 min -25 min
Review plan for Peer #4
Complete Rubric evaluation 2/1/2020 2/1/2020 15 min 1/31/2020 1/31/2020 ### ### 15 min No difference
Add actual start and end dates, and time invested,
Update project plan 2/1/2020 2/1/2020 5 min 1/31/2020 1/31/2020 ### ### 5 min No difference
adjust plan as necessary

Evaluate time available and current


(After evaluating time available and importance of 2/1/2020 2/1/2020 10 min 1/30/2020 1/30/2020 ### ### 10 min No difference
grade to see if I want to take on completing other products, decided to disregard)
MORE Peer Feedback on Initial Extra credit.
Project Plans 2/1/2020 2/1/2020 —
(Extra Credit - Opt.) Look over entire plan 2/1/2020 2/1/2020 45 min — — NA NA NA NA
Add'l Peer Review
Complete Rubric evaluation 2/1/2020 2/1/2020 15 min — — NA NA NA NA

Manage UNPLANNED Manage change of due date in work assignment: Presentation deadline advanced, so file upload due tonight.
Contingency response: Because critical work on upcoming products completed in advance, project is still on 2/3/2020 2/3/2020 6 hrs +6 hrs
Contingency: Work related
schedule.

Review requirements for coming week 2/1/2020 2/1/2020 15 min 2/4/2020 2/4/2020 2/4/2020 2/4/2020 10 min -5 min
Manage the Project: Set appropriate short-term goals 2/1/2020 2/1/2020 15 min 2/4/2020 2/4/2020 2/4/2020 2/4/2020 10 min -5 min
2/1/2020 2/4/2020 Conduct Weekly PM Status
Meeting / Update Project Plan Add in start and completion dates, time invested, and
2/1/2020 2/1/2020 30 min 2/4/2020 2/4/2020 2/4/2020 2/4/2020 10 min -20 min
make adjustments on upcoming event times.

Determine Requirements Review Quality Criteria and Product Specifications to 2/3/2020 2/3/2020 5 min 2/1/2020 2/1/2020 2/1/2020 2/1/2020 5 min No difference
Submissions that demonstrate determine spacing of notations
engagement with the concepts in Take notes 2/3/2020 2/3/2020 2 hrs 2/1/2020 2/1/2020 2/1/2020 2/1/2020 3 hrs +1 hr
Halvorson and Rock (2015) and 2/3/2020 2/3/2020 2/1/2020 Read text
with Annotate text, monitoring Perusall scores for quality 2/3/2020 2/3/2020 1 hr 2/1/2020 2/1/2020 2/1/2020 2/1/2020 2 hrs +1 hr
contributions. Revise as necessary
Desjardins (2018)
(Perusall - 7 comments) Add actual start and end dates, and time invested,
Update project plan 2/3/2020 2/3/2020 5 min 2/1/2020 2/1/2020 2/1/2020 2/1/2020 5 min No difference
adjust plan as necessary

Answer Questions 2/3/2020 2/3/2020 15 min 1/31/2020 1/31/2020 ### ### 10 min -5 min
Respond to Prompts in video 2/3/2020 2/3/2020 15 min 1/31/2020 1/31/2020 ### ### 10 min -5 min
Submissions that demonstrate Watch Video
understanding of concepts in 2/3/2020 2/3/2020 ### Save prompts and responses in separate Word file as 2/3/2020 2/3/2020 5 min 1/31/2020 1/31/2020 ### ### 5 min No difference
Biases Video Quiz reference for succeeding products

Update project plan Add actual start and end dates, and time invested, 2/3/2020 2/3/2020 5 min 1/31/2020 1/31/2020 ### ### 5 min No difference
adjust plan as necessary

Answer Questions 2/4/2020 2/4/2020 15 min 1/31/2020 1/31/2020 ### ### 15 min No difference
Respond to Prompts in video 2/4/2020 2/4/2020 15 min 1/31/2020 1/31/2020 ### ### N/A N/A
Submissions that demonstrate Watch Video
understanding of concepts in 2/4/2020 2/4/2020 ###
Habits Video Quiz
Submissions that demonstrate Watch Video
understanding of concepts in 2/4/2020 2/4/2020 ### Save prompts and responses in separate Word file as 2/4/2020 2/4/2020 5 min 1/31/2020 1/31/2020 ### ### 10 min +5 min
Habits Video Quiz reference for succeeding products
Add actual start and end dates, and time invested,
Update project plan 2/4/2020 2/4/2020 5 min 1/31/2020 1/31/2020 ### ### 10 min +5 min
adjust plan as necessary

Determine Requirements Review Quality Criteria and Product Specifications to 2/5/2020 2/5/2020 5 min 2/4/2020 2/4/2020 2/4/2020 2/4/2020 5 min No difference
determine spacing of notations
Submissions that demonstrate Take notes 2/5/2020 2/5/2020 2 hrs 2/4/2020 2/4/2020 2/4/2020 2/4/2020 2 hrs No difference
engagement with the concepts in 2/5/2020 2/5/2020 2/4/2020 Read text
Cottrell (2011) - Critical Thinking Annotate text, monitoring Perusall scores for quality 2/5/2020 2/5/2020 1 hr 2/4/2020 2/4/2020 2/4/2020 2/4/2020 3 hrs +2 hrs
(Perusall - 7 comments)
contributions. Revise as necessary

Update project plan Add actual start and end dates, and time invested, 2/5/2020 2/5/2020 5 min 2/4/2020 2/4/2020 2/4/2020 2/4/2020 5 min No difference
adjust plan as necessary

Answer Questions 2/5/2020 2/5/2020 15 min — — 2/5/2020 2/5/2020 10 min -5 min


Respond to Prompts in video 2/5/2020 2/5/2020 15 min — — NA NA NA NA
Submissions that demonstrate Watch Video
understanding of concepts in 2/5/2020 2/5/2020 2/5/2020 Save screenshots of key points as study aids to prepare 2/5/2020 2/5/2020 5 min — — 2/5/2020 2/5/2020 10 min +5 min
Critical Thinking Video Quiz for participation in Case Studies products

Update project plan Add actual start and end dates, and time invested, 2/5/2020 2/5/2020 5 min — — 2/5/2020 2/5/2020 5 min No difference
adjust plan as necessary

Review Quality Criteria and Product Specifications to


Determine Requirements 2/6/2020 2/6/2020 5 min 2/5/2020 2/5/2020 2/5/2020 2/5/2020 5 min No difference
determine spacing of notations
Submissions that demonstrate Take notes 2/6/2020 2/6/2020 2 hrs 2/5/2020 2/5/2020 2/5/2020 2/5/2020 1 hr -1 hr
engagement with the concepts in 2/6/2020 2/6/2020 2/5/2020 Read text
Wiefling (2007) Ch. 7 & 8 Annotate text, monitoring Perusall scores for quality
2/6/2020 2/6/2020 1 hr 2/5/2020 2/5/2020 2/5/2020 2/5/2020 3 hrs +2 hrs
(Perusall - 7 comments)
contributions. Revise as necessary
Add actual start and end dates, and time invested,
Update project plan 2/6/2020 2/6/2020 5 min 2/5/2020 2/5/2020 2/5/2020 2/5/2020 10 min +5 min
adjust plan as necessary

Determine Requirements Review Quality Criteria and Product Specifications to 2/8/2020 2/8/2020 5 min 2/7/2020 2/7/2020 2/7/2020 2/8/2020 5 min No difference
determine spacing of notations
Submissions that demonstrate
engagement with the concepts in Take notes 2/8/2020 2/8/2020 2 hrs 2/7/2020 2/7/2020 2/7/2020 2/8/2020 5 hrs +3 hrs
PMBOK 6th edition (2017) - PM 2/8/2020 2/8/2020 2/8/2020 Read text Annotate text, monitoring Perusall scores for quality
Overview and PM Processes 2/8/2020 2/8/2020 1 hr 2/7/2020 2/7/2020 2/7/2020 2/8/2020 3 hrs +2 hrs
contributions. Revise as necessary
(Perusall - 7 comments)
Update project plan Add actual start and end dates, and time invested, 2/8/2020 2/8/2020 5 min 2/7/2020 2/7/2020 2/8/2020 2/8/2020 10 min +5 min
adjust plan as necessary

Review requirements for coming week 2/8/2020 2/8/2020 15 min — — 2/8/2020 2/8/2020 5 min -10 min
Manage the Project: Set appropriate short-term goals 2/8/2020 2/8/2020 15 min — — 2/8/2020 2/8/2020 10 min -5 min
2/8/2020 2/8/2020 Conduct Weekly PM Status
Meeting / Update Project Plan Add in start and completion dates, time invested, and 2/8/2020 2/8/2020 30 min — — 2/8/2020 2/8/2020 30 min No difference
make adjustments on upcoming event times.

Take notes ### ### 15 min 2/10/2020 2/10/2020 ### ### 25 min +10 min
Answer Questions ### ### 15 min 2/10/2020 2/10/2020 ### ### 15 min No difference
Submissions that demonstrate Watch Video Respond to Prompts in video ### ### 15 min 2/10/2020 2/10/2020 NA NA NA NA
understanding of concepts in PM ### ### ###
Processes in Case Study - 1 Video Save prompts and responses in separate Word file as
### ### 5 min 2/10/2020 2/10/2020 ### ### 20 min +15 min
Quiz reference for succeeding products
Add actual start and end dates, and time invested,
Update project plan adjust plan as necessary ### ### 5 min 2/10/2020 2/10/2020 ### ### 5 min No difference
Take notes ### ### 25 min 2/10/2020 2/10/2020 ### ### 20 min -5 min
Answer Questions ### ### 15 min 2/10/2020 2/10/2020 ### ### 10 min -5 min
Watch Video Respond to Prompts in video ### ### 15 min 2/10/2020 2/10/2020 NA NA NA NA
Submissions that demonstrate Save prompts and responses in separate Word file as
understanding of concepts in PM ### ### 5 min 2/10/2020 2/10/2020 ### ### 35 min +30 min
### ### ### reference for succeeding products
Processes in Case Study - 2 Video
Quiz Update project plan Add actual start and end dates, and time invested, ### ### 5 min 2/10/2020 2/10/2020 ### ### 5 min No difference
adjust plan as necessary
Responded to phone calls: one work-related, and the other from family member needing attention.
Manage UNPLANNED Contingency response: Still ahead of schedule, so this event impacted advance planning only, not overall project. ### ### 1.5 hr +1.5 hr
Contingency: Work/Family
Made necessary adjustments to project plan.

Take notes ### ### 20 min 2/10/2020 2/10/2020 ### ### 10 min -10 min
Answer Questions ### ### 15 min 2/10/2020 2/10/2020 ### ### 10 min -5 min
Submissions that demonstrate Watch Video Respond to Prompts in video ### ### 15 min 2/10/2020 2/10/2020 NA NA NA NA
understanding of concepts in PM ### ### ###
Processes in Case Study - 3 Video Save prompts and responses in separate Word file as
### ### 5 min 2/10/2020 2/10/2020 ### ### 10 min +5 min
Quiz reference for succeeding products
Add actual start and end dates, and time invested,
Update project plan ### ### 5 min 2/10/2020 2/10/2020 ### ### 5 min No difference
adjust plan as necessary

Manage Planned Contingency: Pick up daughter from airport - ### ### 2 hr 2/12/2020 2/12/2020 ### ### 2 hrs No difference
Family Event See notes on Tab 2, Risk Mgt.

Review Quality Criteria for original project plan 2/7/2020 ### 30 min 2/11/2020 2/11/2020 ### ### 30 min No difference
Review Quality Criteria for updated project plan 2/7/2020 ### 30 min 2/11/2020 2/11/2020 ### ### 30 min No difference
Review feedback from client and peers 2/7/2020 ### 30 min 2/11/2020 2/11/2020 ### ### 30 min No difference
### ### Update project plan
Document needed changes to project plan 2/7/2020 ### 30 min 2/11/2020 2/11/2020 ### ### 1 hr +30 min
Communicate with client for any needed clarification 2/7/2020 ### 15 min 2/11/2020 2/11/2020 ### ### 20 min +5 min
Review critical path feasibility--compare to calendar 2/7/2020 ### 15 min 2/11/2020 2/11/2020 ### ### 20 min +5 min

Review Quality Criteria and Product Specifications to


Determine Requirements ### ### 5 min 2/14/2020 2/14/2020 ### ### 5 min No difference
determine spacing of notations
Submissions that demonstrate Take notes ### ### 4 hrs 2/14/2020 2/14/2020 ### ### 3.5 hrs -30 min
engagement with the concepts in ### ### ### Read text
O'Connell (2011) Ch. 4, 5, & 6 Annotate text, monitoring Perusall scores for quality
### ### 2 hrs 2/14/2020 2/14/2020 ### ### 1.5 hrs -30 min
(Perusall - 7 comments)
contributions. Revise as necessary
Add actual start and end dates, and time invested,
Update project plan ### ### 5 min 2/14/2020 2/14/2020 ### ### 5 min No difference
adjust plan as necessary

Review requirements for coming week ### ### 15 min — — ### ### 10 min -5 min
Manage the Project: Set appropriate short-term goals ### ### 15 min — — ### ### 5 min -10 min
### ### Conduct Weekly PM Status
Meeting / Update Project Plan Add in start and completion dates, time invested, and ### ### 30 min — — ### ### 10 min -20 min
make adjustments on upcoming event times.

Watch for meeting time; Check availability ### ### 5 min. 2/17/2020 2/17/2020 ### ### 5 min No difference
Review login instructions and prepare link in advance ### ### 5 min. — — ### ### 5 min No difference
Attend February 17th Optional Write down possible questions ### ### 10 min 2/17/2020 2/17/2020 ### ### 10 min No difference
### ### Open session or watch video to
review Project Plan Specifications
Attend February 17th Optional
### ### Open session or watch video to
review Project Plan Specifications Participate in meeting if possible; Ask questions ### ### 1 hr — — ### ### 1 hr No difference

Take notes and screenshots of important information ### ### 10 min — — ### ### NA NA

Evaluate time available and current (After evaluating time available for project plan update
grade to see if I want to take on and experiencing major contingency, decided to ### ### 5 min 2/16/2020 2/16/2020 ### ### 5 min No difference
Extra credit. disregard)
Pre Peer Feedback on UPDATED Post updated Project Plan to
Project Plans ### ### NA ### ### 15 min NA NA NA NA NA NA
Canvas Discussion Board
(Extra Credit - Opt.)
Review Colleague's Project plan
with detailed feedback ### ### 2 hrs NA NA NA NA NA NA

Review feedback from Colleague ### ### 1 hr. NA NA NA NA NA NA

Review requirements of
documentation so I can participate ### ### 10 min — — ### ### 10 min No difference
with purpose
Documentation of Participation
in Feb 17th Open session Attend Open session or view
(Extra Credit - Opt.) ### ### ### ### 1 hr — — ### ### 1 hr No difference
recording
(Prerequisite: Attend Feb 17 Optional Open
Session) Complete documentation ### ### 1 hr — — ### ### 1.5 hr +30 min
Upload to Canvas or post on
discussion board ### ### 5 min — — ### ### 5 min No difference

Move "Contingency" and "Manage Product" headings to ### ### 1 hr 2/13/2020 2/13/2020 ### ### 1.5 hrs +30 min
Tasks column to reduce client confusion

Add task: Update Project Plan (to each Product) ### ### 1 hr 2/14/2020 2/14/2020 ### ### 1 hr No difference
Add brief description to each contingency; include
### ### 1 hr 2/14/2020 2/14/2020 ### ### 15 min -45 min
Contingency Response; update Tab 2, Risk Mgt
Update Project Plan according to
changes identified in PM "Update Indicate task relationships and dependencies ### ### 1 hr 2/17/2020 2/17/2020 ### ### 30 min -30 min
Project Plan" activity on 2/12/20
(Subtasks added on 2/12) Add Comparison column: planned vs actual time ### ### 2 hrs 2/14/2020 2/14/2020 ### ### 1 hr -1 hr
invested
Update Product Names to comply with client ### ### 2 hrs 2/14/2020 2/14/2020 ### ### 1.5 hrs -30 min
specifications (see announcement 2/13/20
Update event times —planned and replanned ### ### 1 hr 2/13/2020 2/15/2020 ### ### 30 min -30 min
Add and delete Tasks and Subtasks as needed ### ### 1 hr 2/14/2020 2/18/2020 ### ### 1 hr No difference

Review activities and notes ### ### 30 min. 2/17/2020 2/17/2020 ### ### 15 min -15 min

Review Quality Criteria for paper to determine what


### ### 15 min 2/17/2020 2/17/2020 ### ### 15 min No difference
information needs to be included
compile 3 paragraph paper about
PMs Active Planning activities Determine structure of paper to create general outline ### ### 15 min 2/17/2020 2/17/2020 ### ### 15 min No difference

Updated and Improved Project Write rough draft ### ### 2 hrs 2/17/2020 2/17/2020 ### ### 2 hrs No difference
Plan Review draft, making edits ### ### 3 hrs 2/17/2020 2/17/2020 ### ### 1 hr -2 hrs
(Prequisite: Feb 17th Open session /
Communication with Client [Instructor]) ### ### ### Make final edits to produce final draft ### ### 2 hrs 2/17/2020 2/17/2020 ### ### 2 hrs No difference
(Must complete before Peer Reviews of
Colleagues' Updated Project Plans,
following)
Updated and Improved Project
Plan
(Prequisite: Feb 17th Open session /
Communication with Client [Instructor]) ### ### ###
(Must complete before Peer Reviews of
Colleagues' Updated Project Plans,
following) Fractured bone in left arm / elbow during fall at work. Urgent Care and doctor appointments interfered with
planned tasks for project. Unable to use left arm to type or take notes (I'm left-handed)
Manage UNPLANNED Contingency response: Accessed some assignments on phone in UC waiting room. Project is still ahead of schedule, ### ### 5 hr +5 hr
Contingency: Injury
although lead time is narrowing. Can still type with right hand. May ask family member for help with typing. If
impact to product delivery appears unavoidable, will notify client.

Ensure all Products accounted for ### ### 30 min. 2/17/2020 2/17/2020 ### ### 10 min -20 min
Ensure that descriptions are sufficiently detailed ### ### 30 min. 2/17/2020 2/17/2020 ### ### 30 min No difference
Ensure Tasks and Subtasks sufficiently addressed ### ### 30 min. 2/17/2020 2/17/2020 ### ### 20 min -10 min
Ensure contingency plan is sufficiently detailed ### ### 30 min. 2/17/2020 2/17/2020 ### ### 20 min -10 min
Reanalyze first sector of rubric and compare to product. ### ### 30 min. 2/17/2020 2/17/2020 ### ### 15 min -15 min
Run Quality Analysis of project Adjust product as needed
Reanalyze second sector of rubric and compare to
### ### 30 min. 2/17/2020 2/17/2020 ### ### 10 min -20 min
product. Adjust product as needed
Reanalyze third sector of rubric and compare to ### ### 30 min. 2/17/2020 2/17/2020 ### ### 20 min -10 min
product. Adjust product as needed
Reanalyze fourth sector of rubric and compare to ### ### 30 min. 2/17/2020 2/17/2020 ### ### 20 min -10 min
product. Adjust product as needed

Make final adjustments to visual Consider organization format ### ### 1 hr 2/18/2020 2/18/2020 ### ### 30 min -30 min
presentation of excel file Consider fonts, spacing, borders, headings ### ### 30 min. 2/18/2020 2/18/2020 ### ### 15 min -15 min
Submit to Canvas ### ### 15 min 2/18/2020 2/18/2020 ### ### 15 min No difference
l
Look over entire plan ### ### 45 min 2/21/2020 2/21/2020 ### ### 30 min -15 min
Review plan for Peer #1
Complete Rubric evaluation. Include comments. ### ### 15 min 2/21/2020 2/21/2020 ### ### 15 min No difference
Look over entire plan ### ### 45 min 2/21/2020 2/21/2020 ### ### 15 min -30 min
Review plan for Peer #2
Complete Rubric evaluation. Include comments. ### ### 15 min 2/21/2020 2/21/2020 ### ### 15 min No difference
Peer Reviews of Colleagues' Look over entire plan ### ### 45 min 2/21/2020 2/21/2020 ### ### 15 min -30 min
Updated Project Plans ### ### Review plan for Peer #3
(Prerequisite: Updated Project Plan) Complete Rubric evaluation. Include comments. ### ### 15 min 2/21/2020 2/21/2020 ### ### 15 min No difference
Look over entire plan ### ### 45 min 2/21/2020 2/21/2020 ### ### 10 min -35 min
Review plan for Peer #4
Complete Rubric evaluation. Include comments. ### ### 15 min 2/21/2020 2/21/2020 ### ### 10 min -5 min
Add actual start and end dates, and time invested,
Update project plan adjust plan as necessary ### ### 10 min 2/21/2020 2/21/2020 ### ### 5 min -5 min

Review requirements for coming week ### ### 15 min — — NA NA NA NA


Manage the Project: Set appropriate short-term goals ### ### 15 min — — NA NA NA NA
### Conduct Weekly PM Status
Meeting / Update Project Plan Add in start and completion dates, time invested, and
### ### 30 min — — ### ### 5 min -25 min
make adjustments on upcoming event times.

Determine Requirements Review Quality Criteria and Product Specifications to ### ### 5 min 2/24/2020 2/25/2020 ### ### 5 min No difference
determine spacing of notations
Submissions that demonstrate Take notes ### ### 3 hrs 2/24/2020 2/25/2020 ### ### 1 hr -2 hrs
engagement with the concepts in Read text
Why People Fail to Recognize ### ### Annotate text, monitoring Perusall scores for quality ### ### 2 hrs 2/24/2020 2/25/2020 ### ### 2 hrs No difference
contributions. Revise as necessary
their own Incompetence
(Perusall - 7 comments)
Update project plan Add actual start and end dates, and time invested, ### ### 10 min 2/24/2020 2/25/2020 ### ### 5 min No difference
adjust plan as necessary
Answer Questions ### ### 15 min 2/26/2020 2/26/2020 ### ### 15 min No difference
Respond to Prompts in video ### ### 15 min 2/26/2020 2/26/2020 ### ### 30 min +15 min
Watch Video
Submissions that demonstrate Save prompts and responses in separate Word file as
understanding of concepts in ### ### 5 min 2/26/2020 2/26/2020 ### ### 15 min +10 min
### ### reference for succeeding products
Conversation with a PM - Part 2
Video Quiz Re-watch video Respond to Prompts in video and answer questions ### ### 15 min 2/26/2020 2/26/2020 ### ### 15 min No difference

Add actual start and end dates, and time invested,


Update project plan ### ### 10 min 2/26/2020 2/26/2020 ### ### 10 min No difference
adjust plan as necessary

Review requirements for coming week ### ### 15 min — — NA NA NA NA

Manage the Project: Set appropriate short-term goals ### ### 15 min — — NA NA NA NA
Conduct Weekly PM Status Evaluate time available and current grade to see if I
### ### ### 10 min — — NA NA NA NA
Meeting / Update Project Plan want or need to do additional Extra credit
Not Needed - Finished early
Add in start and completion dates, time invested, and ### ### 30 min — — NA NA NA NA
make adjustments on upcoming event times.

Review Product specifications and ### ### 30 min 2/26/2020 2/26/2020 ### ### 30 min No difference
Quality Criteria
Copy assignment into Word doc ### ### 5 min 2/26/2020 2/26/2020 ### ### 5 min No difference
Canvas Discussion: Write culminating project review Review and answer prompts ### ### 2 hrs 2/26/2020 2/26/2020 ### ### 3 hrs +1 hr
Culminating Project Review ### ###
(Prerequisites: All previous required
Edit and revise ### ### 2 hrs 2/26/2020 2/26/2020 ### ### 2 hrs No difference
products)
Upload to Canvas Discussion Board ### ### 15 min 2/26/2020 2/26/2020 ### ### 15 min No difference

Add actual start and end dates, and time invested,


Update project plan adjust plan as necessary ### ### 10 min 2/26/2020 2/26/2020 ### ### 10 min No difference

Proposed Products for Extra Evaluate time available and current


Credit 3/1/2020 3/1/2020 grade to see if I want to take on 2/30/20 3/1/2020 15 min 2/28/2020 2/28/2020
(Extra Credit - Opt.) Extra credit.

Typos and Mistakes 3/3/2020 3/3/2020 Identify typos, submit on Canvas ### 3/3/2020 30 min — — ### ### 30 min No difference
(Extra Credit - Opt.)

Evaluate time available and current


Other Extra Credit Opportunities 3/4/2020 3/4/2020 grade to see if I want to take on 2/30/20 3/4/2020 30 min 2/28/2020 2/28/2020
(Extra Credit - Opt.) Extra credit.

Bonus Content - PM Happy Hour


Evaluate time available and current
Podcast on Biases Discussion 3/4/2020 3/4/2020 grade to see if I want to take on 2/30/20 3/4/2020 1 hr 2/28/2020 2/28/2020
Paper Extra credit.
(Extra Credit - Opt.)
Expected contingencies
General Contingency Principles

Family event: pick up Kalissa at airport


1/28/20

Family event: Pick up Amberlee at airport


2/13/20

Unexpected contingencies
Unexpected family phone calls or visits

Family emergencies

Computer crash

Power outage
Internet failure

Accident or Hospitalization

Family emergency in Spain


House fire or other major event

Required overtime at work or traffic delays

Illness

Risks
I might become overwhelmed and not
complete coursework
I might become too busy to complete
project

I might spend more time with family than


planned for in my project schedule.
I may not manage my time wisely, by over-
focusing on a less-important task, and
running short on time for more important
tasks.
Plan to minimize impact on project
With any contingency, certain principles and steps remain constant: 1) review priorities. Action plan will change
depending on what life priorities are impacted by the contingency (i.e. family, friends, work, school); 2)
Consider available options. Be creative. Ask what resources are available that can be utilized to achieve
objectives; 3) Ask for, and accept help from others; 4) Review plan to see if schedule can be adapted to the
circumstance. Oftentimes, step order can be rearranged to take advantage of available resources, if the
resources needed to complete the next step in line are unavailable; 5) Maintain good communication with the
client. Let client know of any circumstances that might impact the delivery of products.

Because I know this event will disrupt my schedule as my daughter has been away a long time, I will get ahead
in my school assignments and take the day off work so I can spend time with her. I will print out my project
plan and take it with me to the airport so I can work on it while I'm waiting for the plane to land. I will also
refuse to take on other projects until I've worked ahead and re-established my buffer zone for this project
(OGL 320).

While this event will most likely not be as disruptive since this daughter has only been away for a month, it will
still require time away from my studies. I will continue to work ahead on my projects so I can take this time to
reconnect without getting behind schedule.

Plan to minimize impact on project


My goal is always to work ahead in class to account for any unexpected situations. I include family members in
my plans and goals, so they know what I am trying to do. I also schedule time to stay connected and take care
of any needs they may have. If, after all this, I still get an unexpected call, I will take the call, determine if needs
can be met at another time, and if so, ask to return the call then. If not, I will take care of whatever it is, then
return to my assignment as quickly as possible.

My family always comes first. In the event of a family emergency, I will take care of the immediate needs of
family members, make arrangements for other needs, then return to my studies as soon as I can.

To prevent data loss in case my computer stops working, I will save and backup my files to an external hard
drive at the end of each study session. If I need to work on or submit assignments I will borrow my daughter's
laptop until I can fix my computer.

I am in the process of acquiring a backup power supply formy computer in the event of a power failure.
If the internet is disrupted and I need to submit assignments, I may be able to submit them using the data on
my phone. Otherwise, I will borrow my neighbor's computer or go use the computers at the library.

To prepare for the possiblilty of an accident or need to be hospitalized, I will share the location of my school
files so family member can access and transfer them to my daughter's laptop so I can continue working during
recovery. If the event interferes with my ability to complete coursework, I will notify instructor.

If my daughter who is visiting in Spain had an emergency and needed me there, I would load my files on to her
laptop and work on my studies during the flight.
If the house burns down, or if some other major event disrupts my ability to complete the course, I will need to
find another way to access my files. My backup files should be able to survive, in which case I will ask to borrow
the computer of a family member or neighbor. If the event somehow prevents me from completing the course
in spite of my best efforts, I will discuss options with the school and my instructor.

If work requires extra hours, or if traffic delays interfere with my study schedule, I will either spend additional
free time in my studies or request an alternate day/time off work to compensate. As always, I will continue to
work ahead to minimize the impact.

I rarely get sick, anymore, but when I do, I'm usually able to continue working at the computer. If I was too sick
to do so, I might ask my daughter for help in typing as I dictate or to read my assignments aloud to me. If I was
unable to concentrate or think, I would notify my instructors to see what my options are, take the necessary
time off work, and continue with my studies as I could.

Plan to avoid Risks


My plan to avoid becoming overwhelmed is to monitor my stress levels; take nature breaks, breathe, put things
into perspective; adhere to my sleep schedule; avoid stress eating.
I sometimes take on more responsibilities than I reasonably have time to complete. Because I know this is a
problem, I will practice saying "No" when requested to take on work that would cut into my study schedule, or
that would increase my stress levels.

I will daily and weekly evaluate my schedule and commit to spending the necessary time to complete my
coursework.
To avoid this risk, I will review my project plan weekly and have a clear vision of what needs to be
accomplished. I will then take a few minutes each hour to evaluate where I am at, what I am working on, and
what needs to happen in the allotted time.
Evidence of Active Planning
 
Active Planning is a dynamic method of managing project plans so they respond
quickly to operational changes. It differs from Static Planning, which may look
impressive, but doesn’t adapt well when its fundamental parts vary. One way I
engage in active planning in my OGL320 course project is by referring to my plan on
a daily basis. A quick look at due dates on upcoming products helps to prioritize
daily activities. Reviewing Quality Criteria reveals needed updates, additions, or
deletions in existing tasks and subtasks. To facilitate these changes, I keep the
planning document open and accessible on my computer, and make adjustments as
needed. Some obvious evidence of this is the addition of a task to “Update Project
Plan” at the end of each product completion (going forward from the original
Project Plan submission), and the inclusion of a new section for the Updated Project
Plan with revisions I found necessary after reviewing feedback and quality criteria
from the first Project Plan submission.
Another way I engage in active planning is to ensure my document follows the
Active Planning Criteria, which specifies how tasks should be named, subdivided,
scheduled, and related to one another. For starters, my tasks are named as verb
phrases to show what specific actions are needed, and I’ve subdivided them into
meaningful subtasks that support the overall product development. I schedule tasks
in advance, relying on past experience to more accurately predict the amount of
time required for their completion. This was difficult, at first, because I often
underestimated, not realizing how ongoing minor contingencies, in the form of
distractions and interruptions, affect the schedule. To account for this, I now build
“contingency buffers” into my time estimates to lessen their impact. Evidence of this
can be seen by noting, in the “Comparison of Actual vs Planned time invested,” that
later tasks were completed in less time than originally anticipated. To document task
relationships, I’ve noted in the product names when there are dependencies and
prerequisites. This helps me see when I can work on two tasks simultaneously, or
when one task must be completed before the other.
Protecting the plan against contingencies is another important aspect of active
planning. Since most contingencies are unexpected, active planning must allow for
variances. I’ve addressed this concern by considering and documenting my options
for dealing with unexpected occurrences, which includes working ahead on the
project whenever possible and building a cushion into my time estimations. As
actual unexpected contingencies are usually different from those that I’ve planned
for, I’ve identified five principles that remain the same and can give direction for any
contingency in Tab 2 “Risk Management” of my project plan, along with planned
responses to some of the more likely events.
Active planning means creating a plan that can be maintained under any
circumstance. Being an active participant in updating tasks and subtasks creates a
project plan that is not only dynamic, but lives and breathes as a readily adaptable
blueprint of my project.
project plan that is not only dynamic, but lives and breathes as a readily adaptable
blueprint of my project.
ect plans so they respond
ning, which may look
parts vary. One way I
by referring to my plan on
ducts helps to prioritize
updates, additions, or
e changes, I keep the
r, and make adjustments as
a task to “Update Project
ard from the original
tion for the Updated Project
dback and quality criteria

my document follows the


d be named, subdivided,
asks are named as verb
ve subdivided them into
velopment. I schedule tasks
y predict the amount of
first, because I often
gencies, in the form of
ount for this, I now build
heir impact. Evidence of this
anned time invested,” that
ticipated. To document task
e are dependencies and
tasks simultaneously, or

mportant aspect of active


e planning must allow for
d documenting my options
working ahead on the
y time estimations. As
m those that I’ve planned
d can give direction for any
lan, along with planned

ntained under any


ks and subtasks creates a
hes as a readily adaptable
hes as a readily adaptable