Professional Documents
Culture Documents
participation in the project as high, medium, and low. On a five-point Likert scale, the
interval length is determined by taking the highest value minus the lowest value and dividing
it by the total number of intervals. Low level effectiveness varies from 1 to 2.33, medium
level effectiveness function goes from 2.34 to 3.67, and high level effectiveness function
ranges from 3.68 to 5 according to this formula. Results for four statements are shown in
n = 92
Variables Mean Std. Deviation
Community is not involved in sharing of benefits 3.48 1.002
of donor funded water project
Community was involved in financial transactions 2.52 0.078
of projects
The implementation team involved 2.31 0.99
community/group members in Project
identification/Conceptualization
Community was involved in Project 1.91 1.320
implementation through cost sharing
Average 2.56 0.8475
Source: Research survey (2020)
As shown in Table 4.2 above, the highest mean score is 3.48 which shows that the
sharing of benefits of donor funded water project. The lowest mean score is 1.91 which
community participation and influence on the CIMMYT projects design and implementation
in Mutoko District. This finding suggests that, generally, the community members have
limited participation and influence on the CIMMYT projects in the district. As Nyaguthii and
relevant strategies, tends to reduce sense of ownership among the community members for
attainment of desired outcomes. From the interviews conducted in this study, it emerged that
the community participation involves some limited knowledge and skills transfer. This
situation is expected to help the communities in the district with continuity or sustainability
capacity beyond the donor’s support, a concept also known as apprenticeship at CIMMYT.
The limited participation in the projects and the resultant adverse effects are emphasized in
Even through the projects have been completed, I would regard them as failure. For
instance, the boreholes installed in Wards 13 and 16 are continuously breaking down. This is
despite having maintenance team in place, but it appears they are not properly trained.”
(Respondent K). Another interview participant buttressed the above statement and reported
that:
The soil conservation project carried out in 2018 in which the community was
trained on how to conserve soil. As of today, instead of the community benefiting and
practising the methods taught, it’s now the opposite. Community members are now
planting in riverbeds, mountains, and sandy areas. Personally, would deem the
project as failure, because the community is not practicing what it was taught.”
The quotations above suggest three interrelated aspects. Firstly, the CIMMYT community
capacity development is either not effective or not relevant to the communities. Secondly,
there is a limited sense of ownership among the community members on the CIMMYT
projects which has resulted in compromised project outcomes. Thirdly, those who mastered
the concepts in the various trainings may have adequate resources to apply what they learned.
The findings indicate that most Mutoko Community participants were not involved in the
project’s identification by CIMMYT. As O’Halloran and Menoka, 2014 argue many studies
methodology and scholars strongly advocate the central role of stakeholder involvement in
delivering successful projects. Furthermore, the findings resonate with Chizimba (2018) who
stakeholder engagement. The difficulties were analyzed using descriptive statistics, such as
Descriptive Statistics
N Mean Std. Deviation
Limited feedback utilized 80 2.03 1.029
Limited of participatory 66 1.92 1.220
community
Improper dissemination 80 1.85 0.989
information
As shown in Table 4.3 above, the challenges were limited feedback utilization from the
0.989). The findings are corroborated by the interviews conducted where it emerged that the
key informants believed that limited participation by the community members in the projects
is one of the challenges being experienced. This notion was emphasized by one of the
…The community of Mutoko did not want to attend the project meetings called by
CIMMYT and project committees. They will always come up with excuses such as we
need to attend to other income generating activities (KI_03)
As can be seen in the quotation above, CIMMYT valued and practised stakeholder
engagement but the beneficiaries had limited appreciation of it. Thematic frequency analysis
of interview data shown in Table 4.4 below further corroborate the challenges that were
From the findings in Table 4.4 above it emerged that limited community participation and
poor information dissemination were the major challenges CIMMYT faced in the
Failure to attend was also attributed to lack of involvement in the early stages of the
projects…the project meetings always coincided with the winter period when they
were tilling the fields. (KI_09)
If we take a closer look at the passage above, we can see two important points. Community
participation was not designed to be comprehensive, in that community people were not
included from the beginning, but rather in phases throughout the project. Deuxièmement, the
meetings were often scheduled at a time that was not suitable for the community since it
ignored other obligations in the community The findings of the text search analysis, as shown
As Figure 4.4 above shows, the issues that emerged which limited stakeholder engagement in
the communities included cultural, conflicts and patriarchy. From these revelations, there are
development projects in Mutoko District. This finding is buttressed by the concept of ‘lack’
which came out from the interviews conducted as shown in Figure 4.5 below.
As evident in Figure 4.5 above, the concept of ‘lack’ was mentioned within the context vital
project implementation processes like lack of consultations, lack of early involvement in the
project conceptualization and design. In addition, it is also seen that limited attendance to
meetings was attributed to lack of community consultation by project leaders. The quotation
below from one of the key informants sheds more light on this finding.
Quotations from the KI`s presented below clearly
The CIMMYT project has been affected by cultural issues. The site that was chosen,
cultural issues were supposed to be fully addressed because the use of technology
solutions to power the water generation was met with resistance. The issue being
maintenance of the technology system in a rural setup like Mutoko District (KI_11)
community labour contribution needed to be paid in the form of food hampers. Food
for work concept. The community complained that the food hamper was small relative
to the job performed. (KI_05)
The quotation above clearly illustrates how the socio-cultural aspect adversely affect the
Recently, it has been observed that community involvement methods, particularly the
bottom-up strategy that involves extensive stakeholder engagement, are critical for project
diversified water use, a steady supply of components and operating and maintenance finance
As indicated in Table 4.5 above, 70% of respondents said that water was not available
throughout the year, whereas 30% said that water was available all year round. As a result of
these findings, the majority of respondents in the neighborhood noted a lack of water
Table 4.5 further shows the respondents view on the existence of the operational and
maintenance fund. The results indicate that 64% said no existence of such and 36% allude to
existence of the operation and maintenance fund. This shows that the majority alluded to the
non-existence of the fund which caters for operations and maintenance issues of the
CIMMYT projects. Fund availability enables resources access to cater for the project`s
operations after donor financial support withdrawal. Given the limited community
(beneficiaries’) engagement in the CIMMYT projects studied, it is quite probable that project
ownership and subsequently reduced propensity for project durability after the donor’s
According to Table 4.5, the researcher asked respondents about their water use owing to the
CIMMYT dam projects. The chart reveals that 54 percent of respondents mentioned several
applications of the water, whereas 46 percent did not name any uses for the water.
CIMMYT's built dam project water is used in a variety of ways, according to the majority of
respondents. By utilizing water for various purposes, the dam has benefitted the community.
The water may be used to irrigate the gardens and for other income-generating initiatives.
Table 4.5 above shows the results regarding the continued supply of spare parts after donor
withdrawal. Of the respondents 83% cited no supply of spare parts and 17% cited yes. Thus,
most respondents 83% cited no continued supply of spare parts after donor`s pull-out. This
shows that for the project to continue in existence, repairs should be attended promptly.
Sustainability is also shown by transfer of skills to the community members. In this study, the
results as shown in Table 4.5 revealed that 66% cited no qualified technical personnel to
attend to repairs and 34% cited availability of qualified personnel. Hence, most respondents,
66% cited the non- availability of qualified technical personnel to attend to repairs.
The above findings on the water Supply Structure functionality throughout the year were
The projects carried out by CIMMYT have been a success as they were completed on time.
The community benefited from the water and dam construction project carried out.
(Respondent H)
While the other respondent in line with the above results also indicated that
CIMMYT projects are a success. This is due to increased economic activity of market
gardening being practised by community members. Some people now have orchards, and
plant vegetables, potatoes and tomatoes all year. (Respondent, G)
carried out in Mutoko District, the researcher probed respondents. The aspects included
utilization of Monitoring and Evaluation feedback, the process and involvment. The results
21; 23%
None
48; 52%
Once
Twice
More than Twice
17; 18%
Figure 4.6 shows responses on how often Monitoring and Evaluation have been done on
CIMMYT projects in the Mutoko District. Of the respondents, 52% cited no Monitoring and
Evaluation activities have been done on the current projects while 23% recorded twice during
the project, 18% cited once and 7% recorded more than twice during the project lifetime.
Thus, most respondents, 52% cited little Monitoring and Evaluation was done on the
CIMMYT projects. This shows that Monitoring and Evaluation was considered as just a
project paper trailManagers and key stakeholders are provided with frequent feedback and
early indicators of progress (or lack thereof) towards attaining targeted objectives through
monitoring
1.4.2 Monitoring and Evaluation feedback was utilized
n = 92
50% 47%
45%
40%
Responses as Percentage
35% 33%
30%
25%
20%
15% 12%
10% 7%
5% 2%
0%
Strongly Disagree Neither Agree Strongly Agree
Disagree
Responses
As shown in Figure 4.7, the respondents view on utilization of Monitoring and Evaluation
feedback. Of the respondents, 47% disagreed that Monitoring and Evaluation feedback was
utilized by CIMMYT, 33% strongly disagreed as well while 12% agreed that Monitoring and
Evaluation feedback was utilized with 6% neither and 2% strongly agreeing. Therefore, most
respondents disagreed that Monitoring and Evaluation information obtained was utilised in
future projects. These findings do concur with those obtained in Figure 4.7 above in which
the majority 52% cited no periodic Monitoring and Evaluation was done on projects. These
35%
30%
25%
20%
15% 12%
10% 7%
5% 2%
0%
Strongly Disagree Neither Agree Strongly Agree
Disagree
Responses
Figure 4.8 shows the dissemination process regards the Monitoring and Evaluation activities.
The respondents 45% strongly disagreed that the process had an easier information
dissemination process to the community members in Mutoko District while 35% disagreed
with the process, 12% neither, 6% agreed and 2% strongly agreed that the process was very
clear. Thus, most respondents 45% strongly disagreed that the information dissemination
process was very clear with no challenges. These results could be an indication of project
problems being faced within CIMMYT. These challenges have been noted with many
international development agencies who fast-track the projects without properly following
due process.
1.4.4 Monitoring and Evaluation was fully participatory
n = 92
45% 42%
40%
35%
Responses as Percentage
30%
25%
25%
20%
15% 14%
10% 7% 7% 5%
5%
0%
Strongly Disagree Neither Agree Strongly Missing
Disagree Agree
Responses
To support the findings obtained above, as shown in Figure 4.9 respondents were probed on
the Monitoring and Evaluation as considered fully participatory or not. Of the respondents
43% strongly disagreed that the process was considered as fully participatory with 25%
agreeing as fully participatory. Thus, most respondents 43% strongly disagreed as fully
participatory. These findings concur with those obtained in Figure 4.6 and 4.7According to
participative M and E, local people have knowledge and experience and can objectively
to develop communities. The Zim-Asset is one of the policies critiqued by the study
participants. Zimbabwe recognizes and upholds the need to provide social protection to its
citizens as evidenced in Section 30 of its constitution which states that “… the state must take
(2013) also includes an inclusive Bill of Rights that underscores the supply of social
(Zim-Asset). In the Zim-Asset whitepaper, the need of social protection is emphasized. Zim-
strategic Asset's clusters focus on food security and nutrition, as well as social services and
chosen using a representation mechanism in which "male and female candidates are listed
alternately, with each list being led by a female candidate" (Constitution, 2013, Part 3, Article
120(1)). (2).
Tables 4.6 and 4.7 provide a summary of the criticism that was voiced.
Two key themes arose from the data analysis, notably the necessity for police awareness and
community, as shown in Table 4.6 above. Finally, the community development strategies
“Our community need trainings and workshops on knowing existing laws, knowing
their rights and the importance of having women in local leadership positions.”
(FGD03_R02)
In our area, we do not know of any existing quota systems, but we will appreciate if
there are any such policies. (FGD01_R02)
The findings were further supported by the Key Informants who mention that,
“…the biggest problem with donors is they want to impose what they did in other
countries to Zimbabwe. The environments are different, but they fail to consider
that ...” (KI_04)
“…the project steering committee was only interested in sitting allowances than
pursing the project objectives…. the meeting with other stakeholders were always in
conflict over simple issues. They failed to appreciate the main job was project
success…” (KI_13)
The findings from the study indicated that the critiqued community development policies,
plays a vital role in the development of the community via various ways. This was
emphasized by one of the Key Informant who was interviewed and indicated that,
“… these policies I think they are very important and vital within our community as
we are now able to develop and engage in many various projects…Furthermore we
are now able to live in peace and harmony as a developed community…” (KI04)
The findings from the above illustrations were in contradictory with the literature from the
study by Masanyiwa and Kinyashi (2018) posits that donor policies have been viewed as
important as they influence how contracts are formed, the length of funding, and what is
funded are all factors to consider. Stakeholders have an important role in promoting
to influence the direction and details, since this helps to foster a sense of belonging.
Appropriate time and resources for participatory analysis, as well as responding to demand-
driven approaches, are critical strategies to promote involvement (Stiglitz, 2016). As a result,
before starting a project, funders should use demand-driven methodologies and obtain input
from stakeholders.
For instance, Plan International Kenya projects involved in WASH projects have Water Point
Executive Committees. These committees have created some sort of ownership regards the
WASH projects. This has been one of the success points of the Plan International Kenya
projects. This approach avers well with Narayan (2016) who claimed that community
participation was critical to project effectiveness. Even if spare parts and maintenance
involvement (Harvey & Reed, 2016). However, this was in contradictory as it emerged from
the findings that there was lack of policy of awareness within the Mutoko community.
participants, response rates, data processing and presentation of the study findings in line
with the research goals are addressed in great length in this chapter of the book. The
following chapter covers the study summary, results, recommendations, and future research
ideas.