If a large reduction in moment capacity occurs due
to spalling, then the plastic hinge length shall be: Lp = 0.3 fye db (7-6) The plastic hinge length, Lp (above ground), for pre- stressed concrete piles may also be computed from Table 31F-7-4 for permitted pile-to-deck connections as described in ASCE/COPRI 61 [7.5]. When the plastic hinge forms in-ground, the plastic hinge length may be determined using Equation (7-7) [7.5]: Lp = 2D (7-7) where: FIGURE 31F-7-3 STRESS-STRAIN CURVE FOR PRESTRESSED STEEL [7.4] D = pile diameter or least cross-sectional dimension 3107F.2.5 Concrete piles. TABLE 31F-7-4 PLASTIC HINGE LENGTH FOR 3107F.2.5.1 General. The capacity of concrete piles is PRESTRESSED CONCRETE PILES [7.5] based on permissible concrete and steel strains corre- CONNECTION TYPE Lp AT DECK (in.) sponding to the desired performance criteria. Pile Buildup 0.15fyedb ≤ Lp ≤ 0.30fyedb Different values may apply for plastic hinges form- Extended Strand 0.20fpyedst ing at in-ground and pile-top locations. These proce- Embedded Pile 0.5D dures are applicable to circular, octagonal, rectangular and square pile cross sections. Dowelled 0.25fyedb Hollow Dowelled 0.20fyedb 3107F.2.5.2 Stability. Stability considerations are important to pier-type structures. The moment-axial External Confinement 0.30fyedb load interaction shall consider effects of high slender- Isolated Interface 0.25fyedb ness ratios (kl/r). An additional bending moment due db = diameter of the prestressing strand or dowel, whichever is used to to axial load eccentricity shall be incorporated develop the connection (in.) unless: fye = design yield strength of prestressing strand or dowel, as appropriate (ksi) e/h ≤ 0.10 (7-4) D = pile diameter or least cross-sectional dimension where: dst = diameter of the prestressing strand (in.) fpye = design yield strength of prestressing strand (ksi) e = eccentricity of axial load 3107F.2.5.4 Plastic rotation. The plastic rotation is: h = width of pile in considered direction θp = Lpφp = Lp (φm - φy) (7-8) 3107F.2.5.3 Plastic hinge length. The plastic hinge length is required to convert the moment-curvature where: relationship into a moment-plastic rotation relation- Lp = plastic hinge length ship for the nonlinear pushover analysis. φp = plastic curvature The pile’s plastic hinge length, Lp (above ground) φm = maximum curvature for reinforced concrete piles, when the plastic hinge forms against a supporting member is: φy = yield curvature Lp = 0.08L + 0.15 fye db ≥ 0.3 fye db (7-5) The maximum curvature, φm shall be determined by the concrete or steel strain limit state at the prescribed where: performance level, whichever comes first. L = distance from the critical section of the plastic Alternatively, the maximum curvature, φm may be hinge to the point of contraflexure calculated as: db = diameter of the longitudinal reinforcement or ε cm dowel, whichever is used to develop the φ m = ------ - (7-9) cu connection where: fye = design yield strength of longitudinal reinforcement or dowel, whichever is used to εcm=maximum limiting compression strain for the develop the connection (ksi) prescribed performance level (Table 31F-7-5) cu = neutral-axis depth, at ultimate strength of section