DATE: SEPTEMBER 16, 2021

TO: ENGR. RENE O. SO

THRU: JONATHAN GOMEZ

OPERATION SUPERVISOR

FROM: NELSON R. BALLON

RE: REQUEST OF MATERIALS AND COST OF LABOR

Sir,

We would like to request the purchase of the following materials intended for the repair of four
(4) hoppers. These hoppers are subjected for repair due to the massive corrosion and unsafe use on the
operation.

SCOPE OF WORK (FOR 15 WORKING DAYS):


I. Replacement of Damage Catwalk
II. Repair and Replacement of Screen Mesh
III. Repair of Damage Upper Sidings

MATERIALS AND TOOLS:


Plain Round Bar - 100 pcs. - ¾” x 20’ Standard
G.I. Pipe - 48 pcs. - 1 1/2” Sched 40 Standard
M.S. Plate – 4 pcs. – ¼” x 4’ x 8’ Standard
Welding Rod – 100 Kilos – 1/8” Ordinary
12 pairs Cotton Gloves
12 pairs Maong Gloves
2 pairs Welding Gloves
5 pcs Small Grinding Disc.
10 pcs. Small Cutting Disc
1 pc. Harris Cutting Holder
2 pcs. Cutting Tip No. 2
1 pc. Measuring Tape 7.5M
2 pcs. 300A Welding Holder
4 gal. Primer Paint Red Oxide
4 gal. QDE Paint Green
4 gal. Paint Thinner
4 gal. Rust Converter
4 pcs. Roller Brush – 4”
4 pcs. Paint Brush – 3”
4 pcs. Paint Brush – 2”
2 pcs. Overhead Welding Mask
3 pcs. Dark Glass
3 pcs. Clear Glass
4 pcs. Steel Brush
1 set Tip Cleaner
1 set Oxygen Gauge
1 set Acetylene Gauge

MANPOWER:
1. Arnold Pimentel – Foreman
2. Johnny Dela Cruz – Fabricator / Welder
3. Carl Anthony Gaerlan – Fabricator / Welder
4. Mario Esmilla – Fabricator / Cutter
5. Rolando Ducusin – Painter / Helper
6. Oskar Dyne Mon – Painter / Helper

COST OF LABOR:
(No. of manpower x rate x no. of days)
1 Foreman x P550 x 15 days = P 8,250.00
2 Fabricator/Welder x P500 x 15 days = P 15,000.00
1 Fabricator/Cutter x P500 x 15 days = P 7,500.00
2 Painter/Helper x P450 x 15 days = P 13,500.00
TOTAL: P 44,250.00

Hoping for your kind consideration. Thank you and More Power Sir!

Respectfully yours,

NELSON R. BALLON
Supervisor

NOTED BY:

JONATHAN T. GOMEZ
Operation Supervisor

APPROVED BY:

ENGR. RENE O. SO.


SAPC/Seaport Manager