You are on page 1of 10

Tunnelling and Underground Space Technology 56 (2016) 12–21

Contents lists available at ScienceDirect

Tunnelling and Underground Space Technology


journal homepage: www.elsevier.com/locate/tust

Modelling of the EPB TBM shield tunnelling advance as a tool


for geological characterization
Laura Culí a,b,⇑, Estanislao Pujades a,c, Enric Vázquez-Suñé a, Anna Jurado a,c
a
GHS, Institute of Environmental Assessment & Water Research (IDAEA), CSIC, Jordi Girona 18-26, 08034 Barcelona, Spain
b
Universidad Nacional Autónoma de México, Instituto de Geología, Cd. Universitária, 04510 México DF, Mexico
c
University of Liege, Hydrogeological & Environmental Geology, Aquapole, ArGEnCo Dpt, Engineering Faculty, B52, 4000 Liege, Belgium

a r t i c l e i n f o a b s t r a c t

Article history: One of the main causes of problems during the construction of tunnels with tunnel boring machines
Received 21 January 2015 (TBMs) is a lack of characterization of the soil. Both geological and hydrogeological characterizations
Received in revised form 19 February 2016 are essential to avoid unexpected events. The advance of TBMs produces groundwater oscillations due
Accepted 23 February 2016
to hydraulic and mechanical effects. The magnitude of these oscillations depends on the characteristics
Available online 1 March 2016
of the soil and on the ‘‘parameters” of the TBM (e.g., earth pressures, penetration). Given that the impact
caused in the groundwater could be estimated numerically, this paper proposes to use hydrogeological
Keywords:
models based on the parameters of the TBM to validate or improve the previous geological characteriza-
TBM
EPB
tion. This procedure was tested by modelling the advance of a TBM-type earth pressure balance (EPB) at a
Advance parameters real site. This study arose during the construction of the tunnel for the high speed train in Barcelona. The
Tunnelling modelling previous geological characterization revealed a vertical fault whose exact position was unknown. The
Groundwater advance of the EPB was modelled to validate the previous characterization and to locate the fault. The
numerical model included a detailed geology and hydrogeology of the study site and the parameters
of the EPB. Note that the parameters of the EPB used in the model were more related to the groundwater
response. These were determined statistically from all of the measures taken by the machine. Given the
results obtained, hydrogeological modelling of EPBs was revealed to be a useful tool to validate previous
characterizations, both the geological and the hydrogeological, and to determine the position of some
geological structures, such as faults.
Ó 2016 Elsevier Ltd. All rights reserved.

1. Introduction Recently, some problems have occurred during tunnelling.


Some of them have been due to a lack in the soil characterization.
Tunnel boring machines (TBMs) are integral machines that drill, In 2005, a tunnel for the Barcelona Underground collapsed during
move away the excavated soil and place the lining. Basically there the construction of the station of ‘‘El Carmel”. During construction,
are two types of TBMs: (1) EPB TBM; shields (for soils) and (2) Hard the geology considered to execute the manoeuvre tail was extrap-
Rock TBM; moles (for rocks). Both have specific characteristics olated from the geology determined along the main tunnel (new
depending on the type of rocks or soils that is necessary to dig boreholes were not drilled) (Melis, 2005). As a result, an unantici-
and depending on the kind of support or coating required for each pated fault zone provoked the collapse of the tunnel (Jimenez and
type of terrain. Earth pressure balance (EPB) is a type of TBM for Senet, 2012). Sometimes, the rock mass rating, rock mass classifi-
the excavation of soils that uses a shield with earth pressure cation and support system proposed for fault zones are insufficient
(O’Carroll, 2005). The proper characterization during tunnelling is for explaining the deformation and failure mechanisms encoun-
essential to reach the objectives of the intended works. If the geol- tered during tunnelling. For example, the Tuzla tunnel (Turkey)
ogy of the site is not well considered, several kinds of problems was mainly excavated in faulted zones of shale and limestone
may occur and, obviously, the cost of the construction may using conventional and shielded TBM methods. The excavation of
increase. the tunnel was difficult because it was drilled into a fault-
collapsed karstic system and below the water table. Before excava-
tion, the quality of the rock was determined to be poor to fair.
⇑ Corresponding author at: GHS, Institute of Environmental Assessment & Water However, during the excavation, it was noticed that the quality
Research (IDAEA), CSIC, Jordi Girona 18-26, 08034 Barcelona, Spain. was poor to very poor. The faulted zones caused jamming of the
E-mail address: lauraculi@hotmail.com (L. Culí).

http://dx.doi.org/10.1016/j.tust.2016.02.017
0886-7798/Ó 2016 Elsevier Ltd. All rights reserved.
L. Culí et al. / Tunnelling and Underground Space Technology 56 (2016) 12–21 13

TBM cutter head and the deviation from the tunnel alignment layers (continuity of the layers), the existence of undetected layers
(Dalgiç, 2002). Another example of an accident due to lack of char- or even the presence of unknown structures, such as faults or
acterization of the soil occurred in Barcelona in 2010. An excava- faulted zones. However, it is not easy to model the impact of EPBs
tion below the Borràs Square collapsed during the construction. in aquifers because it is necessary (1) to determine what parame-
Alonso et al. (2010) suggested that the main reason for the accident ters of the EPBs are related to the groundwater behaviour and (2)
was poor characterization of the geology. Problems also arose dur- to implement these parameters in the numerical model. Generally,
ing the construction of the Dranaz Tunnel (northern Turkey). In studies focused on modelling the advance of EPBs do not consider
this construction, the difficult ground conditions, characterized the hydrogeological impacts. Moreover, they usually do not take
by alternating layers, folding and faulting, were not taken into into account the detailed geological complexity, as is reflected in
account well enough. As a result, 92 m3 of loose material flowed the examples explained below.
into the tunnel due to a collapse, which caused a delay of There are some works in the literature focused on studying the
2.5 months in the construction (Aydin et al., 2004). role of the foam injections applied for soil conditioning. Bezuijen
During tunnelling, groundwater can also cause important prob- (2002) proposes an analytical solution to approximate the excess
lems. Therefore, hydrogeological characterization also plays an of pore pressure at different distances from the tunnel face. They
important role during tunnel construction because unexpected conclude that, in soils with low values of hydraulic conductivity,
water inflows make construction difficult and could result in the (1) the penetration of the foam into the soil depends on the
collapse of the tunnel face, affecting surface structures. E.g., during groundwater flow and (2) the pressure in the working chamber
the drilling of a tunnel for the Barcelona Underground Line 9 into a is comparable to the pore pressure in the soil just in front the tun-
granitic rock massif, which had not been properly characterized, nel. Bezuijen et al. (2005) presented measurements performed in
large inflows occurred each time the TBM crossed fractured or dike the pressure chamber during the Botlek Rail tunnel construction
zones. These inflows produced several collapses, which made con- in Netherlands. Pressure distribution inside the chamber depends
struction difficult (Font-Capó et al., 2011, 2012, 2015). Other prob- on the properties of the mixture. Vertical pressure gradients are
lems also occurred during the construction of the Second Phase of controlled by the density and yield stress of the mixture, while
the Underground of Seoul (South Korea) because the groundwater horizontal pressure gradients, that can be considerable over the
was not properly considered. Although the tunnel was excavated tunnel face, are caused by the compression of grains in the
below the water table, dewatering operations were not undertaken mixture.
and five collapses occurred in the centre of the city because they Other studies are based on the correlation between EPB param-
found numerous weathered granites at the tunnel face (Shin eters, ground conditions and groundwater heads dynamics. Elkadi
et al., 2009). Other well-known incident was the collapse of the and Huisman (2002) built a 3D subsurface geotechnical model for
underground tunnel in Cologne in 2009 (Van Baars, 2011). the Second Heinenoord Tunnel, undertaken in the Netherlands. The
Tunnelling with a TBM under the water table affects the aquifer primary operational parameters used to model the TBM were the
because, during the advance of a TBM EPB, the head oscillates due total thrust, the cutting wheel thrust and the cutting wheel torque.
to hydraulic and/or mechanical effects (Pujades et al., 2015; These parameters were averaged at each ring over the selected
Monfort et al., 2008; Bezuijen et al., 2005). The oscillations are stretches. Afterwards, the parameters were correlated with the
mainly caused by the compressions and decompressions of the soil geotechnical data, considering the lithology observed in the tunnel
produced by the EPB while advancing (the soil is compressed each face during the advance of the TBM. The model, which was built
time the EPB pushes and is decompressed when the push ceases). using only the mechanical parameters of the TBM, did not consider
These compressions and decompressions modify the storage the impacts of groundwater. Gens et al. (2009) modelled the exca-
capacity of the soil (the porosity is modified), leading to groundwa- vation of a tunnel with an EPB. The aim of the numerical model,
ter oscillations. which was built using PLAXIS3D (3D finite elements code), was
Other less important causes are (1) the decompression pro- to study the relation between the loss of soil and the settlements.
duced by the loss of soil during the drilling of the tunnel and (2) The parameters considered were the pressure used for the stabi-
the grout injections performed once the EPB has constructed the lization of the excavation face, the pressure of bentonite between
tunnel (these injections are performed to mitigate tunnel conver- the shield and the soil, and the pressure of the injected grouting.
gence and the soil movements). The model showed that the vertical surface displacements are
The aquifer response to the drilling depends on the geology, the mainly related to the pressure for the stabilization of the excava-
hydrogeology, the soil parameters and the parameters required for tion face and the pressure of the grouting injections. This model,
the EPB to advance. Note that we named ‘‘parameters” of the EPB which was built using only the pressure parameters of the EPB,
(driving data) those variables measured by the machine, which did not consider the groundwater variations.
allow for managing its operation (e.g., thrust, torque, penetration, There are other works in the literature that are not focused on
earth pressure, overturn momentum, cutting wheel displacements, modelling the advance of TBMs, and whose goals, instead, are to
etc.). In fact, it is known that a relation exists between the proper- study the parameters measured in TBMs and the response of the
ties of the soil (geology and hydrogeology), the behaviour of the media. Emeriault and Kastner (2008) correlated the surface move-
EPB and the groundwater response. Thus, if the nature of the inter- ments and the TBM parameters. They compared several excavation
action between the soil, the EPB and the groundwater response is techniques, which had been used during the excavation of the Line
determined, the head evolution could be predicted (e.g., numeri- B of the Underground of Toulouse (France). They found that differ-
cally). This means that the geological characterization could be val- ences in soil response can be explained by the TBM parameters,
idated at the same time that the tunnel is constructed (e.g., from which the three most important were (1) the advance rate,
monitoring the head evolution and comparing the measures with (2) the hydraulic pressure used for the cutting wheel and (3) the
numerical estimations obtained while considering the initial char- vertical overturn momentum. This result was obtained for a partic-
acterization). This procedure would help to improve the soil char- ular site and in a homogeneous geological context. The analysis,
acterization and would reduce risks during construction. This which was made using only the pressure and the position param-
paper proposes to use hydrogeological modelling that includes eters of the TBM, did not consider the groundwater behaviour.
EPB advance parameters to predict the aquifer response and to Yamamoto et al. (2003) evaluated the geological condition of the
identify imprecisions in the previous geological characterization. soil around the tunnel face by analyzing geostatically the parame-
Imprecisions include inaccuracies in the geometry of geological ters of the TBM. They studied (1) the relation between the drill
14 L. Culí et al. / Tunnelling and Underground Space Technology 56 (2016) 12–21

energy coefficient in front of the face, which was obtained from the head observations taken during the construction. The ground-
drill logging data and (2) the rock mass strength or excavating water behaviour was predicted and compared with the observa-
energy at the excavation site, which was derived from the data tions taken at the piezometers during the construction. This
of the TBM. Nevertheless, this analysis did not take into account procedure allowed us to improve the geology of the site and to
hydrogeological aspects. observe the relation between the geology, the EPB parameters
Finally, Monfort et al. (2008) analyzed the groundwater evolu- and the groundwater response.
tion during the advance of the EPB. Head evolution was observed The objective of this paper is twofold: (1) to determine what
at six piezometers during the construction of the Line 9 of the Bar- parameters of a EPB can be associated with the groundwater
celona Underground. They compared the groundwater behaviour response observed during tunnelling and (2) to suggest a method
with the parameters of the EPB. This study demonstrated (1) a high or procedure based on numerical modelling of EPB advance to ver-
correlation between groundwater oscillations and the phases of ify the characterization of the soil (stratigraphy, structure and soil
the installation of the tunnel rings and (2) a moderate correlation parameters) when a tunnel is constructed.
between the groundwater variations and the pressure used for
the stabilization of the excavation face. However, they have not 2. Methodology
modelled the groundwater response to the EPB advance.
This study arose during the construction of the tunnel for the Several steps were undertaken to reach the objectives of this
high speed train (HST) ‘‘Madrid-Barcelona-France frontier”. The study. These are summarized and explained below:
tunnel under Barcelona was drilled using a TBM type EPB
(Pujades et al., 2015) because this type of procedure is designed (1) Geological characterization: An accurate geological profile of
to reduce, as much as possible, the ground loss in front, above the study site was performed by considering the geological
and behind the TBM, which minimizes the surface settlements. regional context and the stratigraphic register of boreholes
The stretch of tunnel studied (and modelled) in this paper was located in the study section (Fig. 2).
located in the middle of the city (Fig. 1). It was 600 m long, the (2) Hydraulic characterization and detailed groundwater head:
average depth of the tunnel was 35 m and its radius was 12 m. Head evolution was measured at some piezometers located
The soil was characterized before and during tunnelling near the tunnel path.
advance using the information of several boreholes, and a fault (3) Analysis of the parameters of the EPB: All EPBs have an exca-
was detected in the path of the tunnel. However, given the distance vation control system, where all of the parameters of the
between boreholes, its location was unknown. Therefore, the machine are registered, to manage their advance. The main
advance of the EPB during the construction was modelled with a parameters were studied to determine which are more corre-
hydrogeological numerical model to locate the fault and to validate lated with groundwater behaviour. Furthermore, incidences
the previous characterization. The model was undertaken by con- that occurred during the construction of the tunnel, which
sidering the parameters of the machine. were recorded by the staff, were also considered to under-
The numerical model included a detailed geology of the study stand some unusual behaviour during the tunnelling process.
site, the hydrogeological parameters, some EPB parameters and (4) Numerical modelling.

Besós River
N

Study section
Padilla shaft

HST

Llobregat River

Barcelona

Spain

Fig. 1. Path of the tunnel of the high speed train (HST) in Barcelona. Lower image displays in detail the study section, where it is possible to observe the situation of Provença,
Mallorca and Valencia streets.
L. Culí et al. / Tunnelling and Underground Space Technology 56 (2016) 12–21 15

Fig. 2. Geological profile of the study section, which includes geophysical register, the path of the tunnel and the boreholes used to define the lithotypes. It is also possible to
observe the fault zone range, which affects the Pliocene lithotypes and the hydraulic conductivities of the main geological layers.

3. Application 3.1.2. Quaternary sublithotypes


Qa lithotype can be divided into three sublithotypes:
3.1. Geological characterization
– Qa1: Gravel with percentages of fine matrix lower than 10%.
As stated above, the study section is located inside the city of This is the dark pink sublithotype in Fig. 2.
Barcelona, which is situated in the NE of Spain. The city of Barce- – Qa2: Sands with variable propositions of silts, sandy silts with
lona is limited in the NE by the Besòs River, in the SE by the carbonate nodules and red brown clays with heterometric grav-
Mediterranean Sea, in the SW by the Llobregat River and in the els. This is the orange sublithotype in Fig. 2.
NW by the Collserola Range. The city is located above the ‘‘Barce- – Qacc: Calcrete layers. This is the white sublithotype in Fig. 2.
lona Coastal Plain”, which is a morphologic platform poorly
inclined towards the Mediterranean Sea and it is composed by
Pliocene and Miocene detrital and deltaic sediments (Vera, 2004). 3.1.3. Anthropic lithotypes (Ra)
The relief of Barcelona is conditioned by extensional Cenozoic Anthropic lithotype is composed of different materials. This
faults (Neogen age) (IGC, 2007). sublithotype is represented with diagonal black line pattern in
Fig. 2 displays the geological profile of the study site. The stratig- Fig. 2.
raphy, the underground structure and the percentage of sand of the The underground structure of the site is conditioned by the
main lithotypes can also be observed in this figure. Note that some existence of a fault, which was determined by the register
lithotypes were divided into sublithotypes based on their composi- observed at boreholes SL-15 and SL-16 and, to a lesser extent, by
tion (percentages of gravels/sands or fine sediments). Furthermore, the regional tectonic context. This fault was located between bore-
Natural Gamma Ray record of each borehole was also used for this holes SL-15 and SL-16, but its exact position was unknown before
purpose (Cripps and McCann, 2000). Due to the large amount of drilling of the tunnel commenced (Fig. 2).
information (numerous deep boreholes very close to each other
and Natural Gamma Ray record) and good correlation between geo- 3.2. Hydraulic characterization and groundwater head monitoring
logical profile developed and the materials drilled by the machine,
the distribution of soil layers was considered enough precise. The 3.2.1. Hydraulic characterization
main features of each sublithotype are summarized below: The Barcelona plain can be regarded as an aquifer with a high
vertical heterogeneity. Its effective transmissivity ranges from
3.1.1. Pliocene sublithotypes 100 to 200 m/d and it is exploited by several wells. Groundwater
PL lithotype can be divided into three sublithotypes: flows from the higher areas (Collserola Range) towards the sea.
The gradient is smooth and the piezometric surface is analogous
– PL1/PL2: Marls and fine sand with percentages of sand lower to the topographic slope. The city is intercepted by small pale-
than 10%. This is the dark green sublithotype in Fig. 2. ochannels that influence the piezometric surface.
– PL21: Marls and medium-fine sand with percentages of sand The HST tunnel is perpendicular to the flow direction in the
between 10% and 60%. This is the green sublithotype in Fig. 2. study area. The piezometric head was located at 15 m.a.s.l in the
– PL22: Medium and medium-fine sand with percentages of sand piezometers placed in Provença Street (upstream of the tunnel)
greater than 60%. This is the yellow sublithotype in Fig. 2. and at 8 m.a.s.l in the piezometers of Valencia Street (downstream)
16 L. Culí et al. / Tunnelling and Underground Space Technology 56 (2016) 12–21

KP 4+400 KP 4+200
SL-17 PA-110

01/07/10 21/07/10 SL-15 10/08/10 20/08/10


SO-30 Pz-8
10
Point of maximum closeness, between
SL-17 PA-110 Pz-8 EPB and piezometer

6 SL-15 SO-30 SL-15 Pz-8

Gaps of water pressure PA-110


sensors
2

-2

-6
01/07/10 11/07/10 21/07/10 31/07/10 10/08/10 20/08/1
Date

Fig. 3. Head variations measured at piezometers SO-30, SL-17, SL-15 and PA-110.

Table 1
Main features of piezometers in the study section. ⁄ KP kilometric point.
behaviours are those noticed after the pass of the EPB near
piezometer SL-15. It is possible to observe that the magnitude of
Piezometer Depth Screen Distance tunel axis PK cutterhead the head oscillations decreased. The probable reason was that the
(m) (m) (m) (m)
piezometer was silted by substances (bentonite, grout injections,
SL-18 40.2 0–40.2 12 4+537.5 etc.). These substances, which contribute significantly to the over-
SO-30 42 30–42 15 4+438.5
all efficiency of the tunnelling operation, were used to avoid the
SL-17 40 0–40 14.5 4+537.5
SL-15 40 0–40 13 4+171.0 collapse of the tunnel face during one stop of the EPB carried out
Pz-8 40 0 - 40 18 4+164.4 near this piezometer. In Fig. 3, it is also possible to observe that
PA-110 40.9 10–40 18 4+110.3 the piezometers located after the fault did not notice the EPB until
PA-133 51 25–38 6.5 3+925
it crossed the fault zone. This response of the aquifer allowed for
locating the fault.

(Fig. 1). The piezometric head in the street where the tunnel was 3.3. Analysis of EPB parameters
excavated (Mallorca Street) was at 13 m.a.s.l. (Jurado et al., 2012).
The regional hydraulic parameters of the main lithotypes 3.3.1. EPB parameters (driving data)
(described in the previous section) are as follows: The control systems of EPBs measure a wide variety of driving
data (498 parameters in total). From these, only those that can gen-
PL lithotype: The hydraulic conductivity (k) of the Pliocene fine erate hydraulic or mechanical effects in the aquifer were analyzed
materials ranges from 0.001 to 0.01 m/d. The k of the sand lay- (36 parameters in total) (online Appendix A). The parameters
ers ranges from 0.1 to 10 m/d (Pujades et al., 2014a, 2014b). related with energy (e.g., active energy, translation energy. . .), tem-
Qa lithotype: The k of the Quaternary clay layers ranges from perature (e.g., of oil. lubrication. . .), volume (e.g., grease, ben-
0.001 to 0.01 m/d and the k of the Quaternary sand and gravel tonite. . .), etc., were not considered.
layers ranges from 0.1 to 10 m/d (Pujades et al., 2014a, 2014b). Regarding the continuity of the register of the parameters, two
main groups of parameters can be differentiated: continuous and
Locally, the hydraulic parameters of the soil at the study site discontinuous. The continuous are those that are measured during
were obtained from pumping tests performed in the Padilla site the entire time, while the discontinuous cannot be measured dur-
(Fig. 2). These tests were performed to design the dewatering ing the stops of EPB cycle. Note that we name ‘‘EPB cycle” the event
system to excavate a maintenance shaft associated with the HST that consists of one stop and one start (advance) of the machine
tunnel (Pujades et al., 2014a). The k of the geological layers is and that finishes when the EPB stops again. Given that the duration
included in Fig. 2. of the stops and advances depends on several factors, the duration
of each EPB cycle is different.
3.2.2. Groundwater head monitoring The following parameters, which are listed depending on their
Fig. 3 displays the head evolution measured at SO-30, SL-17, continuity, were selected and evaluated to find those more related
SL-15, Pz-8 and PA-110. The situation and characteristics of these to the groundwater behaviour:
piezometers are shown respectively in Fig. 2 and Table 1. It is
possible to observe some unusual behaviour in Fig. 3, e.g., the gaps – Earth pressure and mass parameters (Continuous register): These
observed in the measurements taken at piezometer SL-17. During parameters are directly related to hydraulic effects (pressure)
the period of these gaps, no data were measured because the ‘‘wa- and volume or weight balance of the machine. They are
ter pressure sensors” were out of the water due to the large recorded on the shield and the cutter head during the entire
oscillations caused by the EPB in the aquifer. Other unusual time.
L. Culí et al. / Tunnelling and Underground Space Technology 56 (2016) 12–21 17

– Mechanical and position parameters (Discontinuous register): parameters of its group and with the parameters of the other
These parameters are directly related to mechanical effects (tor- groups, the more representative parameters with high positive
que, cutter head displacements, overturn momentum, etc.). Pearson’s correlation coefficients, were selected to model the
They are recorded on shield and the cutter head. Given that advance of the EPB. Theses parameters (together with their units
these parameters are discontinuous, when the EPB is stopped, and groups) were the ‘‘earth pressure 1” and ‘‘the earth pressure
their value is zero. 5” (bar) from the ‘‘Earth Pressure group” and the ‘‘penetration”
(mm/rot) and the ‘‘advance velocity” (rpm) from the ‘‘Mechanical
3.3.2. Statistical analysis of EPB parameters Components group” (Table 2).
Statistical analyses of the parameters of the EPB were made by
using a Pearson matrix (XLSTAT, Excel module). The Pearson’s cor- 3.3.3. Incidences occurred during the EPB advance
relation coefficient is an index to measure the lineal relation The incidences that occurred during the construction of the tun-
between two random and quantitative variables. The study of this nel were taken into account to implement the parameters of the
coefficient allows for reducing the number of variables because, EPB in the numerical model. These events were considered as dis-
when the Pearson’s correlation coefficient between two compared tortions of the hydraulic or the mechanical phenomenon that
variables is high, it is possible to consider that their register is sim- altered the values of the parameters. Consequently, the values dur-
ilar. Therefore, only one of them can be used because this is repre- ing these events were neglected. The main incidents that occurred
sentative of both. In our study, if the Pearson’s correlation during the drilling through the study section were (1) increases of
coefficient between two parameters was higher than 0.7–0.8, only the pressure in the excavation chamber, which generated incre-
one parameter (of the compared) was selected. The Pearson’s cor- ments of the parameter ‘‘thrust” and decreased the parameter ‘‘ve-
relation coefficient between all of the parameters considered (36 in locity of advance”; (2) long stops of the EPB to extend the belt
total) can be observed in the online Appendix A. conveyor and the medium tension cable, which generated
Firstly, the different parameters of the EPB were grouped into decreases in all of the parameters; (3) reductions of the pressure
five main groups (earth pressure, position of cutter head displace- in the working chamber caused by the seal of the auscultation
ments, overturn momentum, mechanical components and param- piezometers, which produced decreases in the parameters of
eters without correlation), regarding the Pearson’s correlation ‘‘earth pressure”; and (4) short stops of the EPB provoked by the
coefficient between them and their nature. A more extended expla- obstruction of the grouting lines or the lining segment erector,
nation and the Pearson’s correlation coefficients between the which generated brief decreases in all of the parameters.
parameters of each group are included in the online Appendix B.
Secondly, four of these five main groups were also compared to 3.3.4. Groundwater head evolution and EPB parameters
each other statically. A more extended explanation and the Pear- Fig. 5a compares the evolution of the parameters ‘‘earth pres-
son’s correlation coefficients between the parameters of groups sure 5” (red line) and ‘‘penetration” (blue line), which were two
are included in the online Appendix C. of the parameters selected to model the advance of the EPB, with
Some additional considerations were taken into account in the the hydraulic head evolution measured at Pz-8 (green line). Both
selection of the more representative parameters (1) here were EPB parameters are averaged over each EPB cycle. Maximum (red
seven different parameters of the group named ‘‘earth pressure” dots) and minimum (blue dots) hydraulic head reached during
that had high Pearson’s correlation coefficients between them each EPB advance and stop, respectively, are plotted to show the
(Appendix B). Therefore, each of them could be used. However, influence of the EPB on groundwater head response. The magni-
the values of earth pressure from cells 1 and 5 were considered tude of the observed groundwater head response depends on the
because their distribution allowed for taking measures in function distance between the observation point and the EPB. Therefore,
of the fill of the chamber (Fig. 4); and (2) the direction followed by the values of the parameters were homogenized (weighted) by
the EPB was also considered to neglect some parameters of the considering the location of the EPB with respect the position of
group named ‘‘overturn momentum”. Given that the direction the piezometers (in the case of Fig. 5a, with respect Pz-8). The
was horizontal, the parameter of this group that indicated the value of the parameters was weighted with 1/r2 (where r is the dis-
overturn momentum in the vertical direction was neglected tance between the EPB and the projection of the piezometer over
(‘‘overturn momentum Hy (vertical)”). the path of the tunnel) (Fig. 5b). Both EPB parameters plotted in
Additionally, the main groups of parameters were also studied Fig. 5a influence the hydraulic head. However, this is more affected
by using SGeMS (Stanford Geostatistical Modelling Software, by ‘‘penetration” because ‘‘earth pressure 5” is more or less con-
2010) to obtain the probabilistic distribution of the adopted stant over the time. In general, when the EPB advances (‘‘penetra-
parameters. All of the parameters chosen had a Normal or tion” value increases) the hydraulic head tends to rise while when
Lognormal distribution. the EPB stops (‘‘penetration” value decreases) the hydraulic head
Following the methodology explained in this section, which drops.
consisted mainly of comparing each parameter with the In some cases (e.g. at 05/08/10 or at 08/08/10) the trend evolu-
tion of the groundwater head is different than the trend of the
parameters recorded by the EPB. This is because the heads mea-
surements respond to different kind of incidences during tun-
nelling. These unexpected hydraulic head behaviours observed

Table 2
Main EPB parameters selected using statistical tools.

Main parameters selected Parameter Units


Earth pressure cell 5 11 bar
Cutting whell displacements position group A 23 mm
Total overturn momentum 26 K Nm
Penetration 33 mm/rot
Cutting whell torque 34 M Nm
Fig. 4. Pressure cells of the EPB shield.
18 L. Culí et al. / Tunnelling and Underground Space Technology 56 (2016) 12–21

Maximum hydraulic head Hydraulic head Cell pressure 5 (bars) magnitude depends on the ‘‘penetration” recorded during the
Pz8 (m) EPB advance.
8 The instant flow was computed by multiplying the ‘‘penetra-
tion” (discontinuous parameter), which was averaged at each EPB
6 cycle, by a factor that depends on the percentage of sands of the
soil. Sand percentages are directly proportional to abrasiveness of
the soil (concentrations of minerals such as quarts and feldspar).
4
Three different factors were used in the model. The differences
between these factors, which were adjusted (calibrated) manually
2
by comparing the numerical heads with the observations, were
proportional to the variations of the percentage of sands. Factor
-1 1 = 50% of sands, factor <1 = <50% of sands and factor >1 = >50%
of sands. The factor introduced in the model was: 0.6 between
-3 rings 1 and 43 (from KP 4+280 to 4+206), 0.7 between rings 44
03/08/10 04/08/10 05/08/10 06/08/10 07/08/10 08/08/10 and 81 (from KP 4+206 to 4+150) and 1.6 between rings 82 and
Averaged hydraulic head Minimum Penetration 95 (from KP 4+150 to 4+128). Note that the relation between the
Date hydraulic head (mm/rot) deformation (produced at each push) and the variation of the head
(a) was linear in the study site (the soil is overconsolidated). This fact
is a consequence of groundwater evolution in the past (Vázquez-
r Suñé et al., 2005) and is reflected in the value of the specific storage
coefficient (Ss) (0.00001), which was obtained from the tests per-
formed at Padilla site (Fig. 2).
The continuous pressure in the chamber causes that the head
KP excavation front between cycles to be higher than those observed in natural condi-
tions and acts as a fixed head boundary. When the chamber pres-
Piezometer
sure drops, hydraulic head around the machine drops and when
(b) increases, hydraulic head in the aquifer rises. As a result, the cham-
ber pressure is equivalent and was modelled as fix head boundary
Fig. 5. (a) Evolution of ‘‘earth pressure 5”, ‘‘penetration” and head oscillations
whose value was calculated by averaging the values of ‘‘earth pres-
measured at Pz-8. Note that the units of the pressure and penetration, whose scales
are located in the right axis, are bars or mm/rot (10 3 m), respectively. Yellow sure 1” and ‘‘earth pressure 5” (continuous parameters). This mean
shaded areas represent unexpected hydraulic head behaviours. (b) Position of the value was normalized between 0 and 1 from its maximum value. It
machine with respect to piezometers, where r is the distance between the projected was assumed that soil conditioning (basically related with the
piezometer and cutter head. ⁄ KP kilometric point. (For interpretation of the influence of foam injections at the tunnel face (Bezuijen, 2002))
references to color in this figure legend, the reader is referred to the web version of
this article.)
was integrated in the recording of the pressure inside the chamber
introduced in the numerical model like a prescribed head.

during some EPB cycles are represented using a yellow shaded area 3.4.2. Numerical model performance
in Fig. 5a. The length of the model was established to implement the fault
zone inside (Fig. 2). Some assumptions were made to introduce the
3.4. Numerical modelling geology in the model (1) the geological layers were considered as
horizontal, (2) they started and ended at the beginning or end of
3.4.1. Modelling of EPB excavation process by the seepage analysis the tunnel rings, and (3) the Quaternary sediments were
The advance of EPBs could be modelled using coupled hydro- implemented as a homogeneous layer (no layers were differenti-
mechanical models. These models require hydraulic and soil ated inside the Quaternary). The tunnel was also simplified
parameters, such as the Young’s modulus (E) or the Poison coeffi- because it was located at an average depth of 34 m. Note that
cient (c), were required to be included into the analysis. However, the numerical model did not consider the geological materials
due to the difficulties for quantifying the soil parameters in the located in the unsaturated zone (Fig. 6). The numerical model
present study, only hydrogeological numerical model was consid-
ered. Consequently, only hydrogeological parameters could be val- Piezometers Fault Tunnel rings
idated by the model. Despite of these difficulties, elastic soil
parameters, such as Young’s modulus (E) and the Poison coefficient
(c) were related to the storage coefficient considered in the hydro-
geological model. These relations could be established because the
soil of Barcelona is overconsolidated (Pujades et al., 2014a, 2014b)
and behaves elastically. Therefore, applying the Jacob equation
(1950) for elastic aquifers we can assume that the specific storage 30
coefficient is similar to the compressibility coefficient.
The main problem found to model the EPB consisted of simulat- 15
ing (1) the pushes that EPBs undertake over the soil to advance and
(2) the continuous pressure applied in the chamber of the EPB to
0
avoid the collapse of the excavation and inflows of water. The
(m)
EPB over the soil compress (deform) it reducing its porosity, and 0 50 100

therefore, increasing the hydraulic head around the construction.


Fig. 6. Elements implemented in the numerical model. Tunnel rings are in red,
Hydraulic head drops when the push ceases. Therefore, the modi- piezometers in purple, fault in green and geological layers in orange, dark green,
fications of the hydraulic head caused by the pushes over the soil green, and yellow. (For interpretation of the references to color in this figure legend,
were simulated implementing an instantaneous flow whose the reader is referred to the web version of this article.)
L. Culí et al. / Tunnelling and Underground Space Technology 56 (2016) 12–21 19

included 12 geological layers with percentages of sand greater than The boundary conditions adopted in the model consisted of pre-
60%, 10 geological layers with percentages of sand between 10% scribed heads and flows. Prescribed heads were considered at the
and 60%, one geological layer of Quaternary materials and, finally, lateral and lower boundaries and at the geological layers PL22
geological layers with percentages of sand lower than 10%. One (see Section 3.1) of the last layer (Ly9). These conditions were
fault (1.2 m of width), three piezometers and 95 tunnel rings were implemented because the distance between boundaries and the
implemented in the model. The fault was modelled as an area with EPB was enough to assume that the hydraulic effects caused by
a low value of equivalent permeability k (0.00001 m/d). the machine could be neglected. No flow boundary was considered
The numerical model comprised nine vertical layers. Note that, to the layer along the tunnel axis.
contrary to the normal the layers did not represent different This is a multi-layered model divided in 9 layers, where the
depths. The model considered vertical symmetry along the tunnel mesh was composed of 30,126 elements and 10,665 nodes. Near
axis. They were located in the horizontal direction and simulated the tunnel, the size of the elements was smaller (Fig. 7).
the soil at different distances from the tunnel. Horizontal distances The time period simulated is between July, 20th, 2010 (mod-
between layers and the tunnel were 4.5 m (Ly1), 8 m (Ly2), 13 m elling initial time, t = 0) and August, 10th 2010, (modelling final
(Ly4), 18 m (Ly5), 22 m (Ly6), 50 m (Ly7), 250 m (Ly8) and 500 m time t = 13.36 days) (Fig. 2). Model computing time steps are vari-
(Ly9) (Fig. 7). The tunnel rings were implemented only in Layer able depending on tunnelling advance steps. Time step ranges from
1, and the size of each one was 1.8  12 m. 0.03 min to 128 min. Moreover, time step considered were tested
to give enough precision using less computing time.

3.4.3. Modelled scenarios


The model was calibrated by comparing the evolution of mea-
sured groundwater heads versus computed heads, assuming differ-
ent hydrogeological conditions. Numerical models were performed
using the code TRANSIN-IV (Medina and Carrera, 2003; Medina
et al., 2000). Four different scenarios were modelled and their
results were compared with the field measurements. Firstly, sce-
narios S.1, S.2 and S.3 were built to evaluate the hydraulic conduc-
tivities used by comparing the magnitude of groundwater
oscillations. The hydraulic conductivity adopted in the most trans-
missive layers was the only difference between S.1, S.2 and S.3.
Hydraulic parameters obtained from the pumping test performed
at the Padilla site (Pujades et al., 2014a) were used for S.1. The
hydraulic conductivities of the more transmissive layers were
Fig. 7. Multilayer numerical model, which includes nine layers. The tunnel rings
increased one order of magnitude at S.2 and reduced (one order
were implemented only in Layer 1.
of magnitude) al S.3 with respect to S.1. The fault was located

40

S.1 S.2
30

20

10

40

S.3 S.4
30

20

10

30-Jul 1-Aug 3-Aug 5-Aug 7-Aug


0
28-Jul 30-Jul 1-Aug 3-Aug 5-Aug 7-Aug 28-Jul 30-Jul 1-Aug 3-Aug 5-Aug 7-Aug

Fig. 8. Numerical head variations (black dots) vs. computed heads variations (lines) obtained in the four different scenarios. Piezometric head is observed and computed in
Pz-8.
20 L. Culí et al. / Tunnelling and Underground Space Technology 56 (2016) 12–21

10 10
SL-15 Pz-8
8 8

6 6

4 4

2 2

0 0
28-Jul 30-Jul 1-Aug 3-Aug 5-Aug 7-Aug 9-Aug 28-Jul 30-Jul 1-Aug 3-Aug 5-Aug 7-Aug 9-Aug
10
PA-10
8

0
28-Jul 30-Jul 1-Aug 3-Aug 5-Aug 7-Aug 9-Aug
Date

Fig. 9. Measured head variations (black dots) vs. computed-head variations (lines) corresponding to S.1, in piezometers SL-15, Pz-8 and PA-110.

42 m away from Pz-8 in these three scenarios. Finally, the actual truncate cone (the smaller base of the truncated cone was assumed
position of the fault was evaluated by analyzing the time when to be in the site of the cutter head). Note that the angle considered
the piezometric head increases in Pz-8. The fourth scenario (S.4) between the side of the cone and the tunnel was 30° (Jiménez
was modelled considering the hydraulic conductivities obtained Salas, 1975). The maximum and minimum volumes of water
from the Padilla site but locating the fault 72 m away from Pz-8. inserted by the EPB were obtained from the mass balance of the
model (S.1). These volumes of water, which were 77.4 m3 (max)
3.4.4. Numerical model results and 17.1 m3 (min), were used to compute the height of the trun-
Fig. 8 compares the compute head of the four scenarios with the cated cone (distance affected). Following this methodology, the
field measurements. Magnitude of the measured groundwater maximum and minimum distances affected during the modelled
oscillations only agrees with those computed for S.1. Therefore, it period were 268 and 158 m, respectively. Both lengths are realistic
is possible to deduce that the hydraulic conductivities obtained according to the distance at which the piezometers noticed the EPB
from the pumping tests performed at Padilla site are reasonable approaching.
to simulate the groundwater response caused by the EPB advance.
Piezometric head for S.4 increases the groundwater response cause
by the EPB advance. Piezometric head for S.4 increases too early 4. Conclusions
and does not agree with the field measurements. However, time
when the computed piezometric head increases agrees with the Geological characterizations must be performed prior to tun-
field measurements when S.1 is considered. Therefore, it is nelling (particularly hydrogeological characterizations when the
deduced that the fault was located 42 m away from Pz-8. construction is performed below the water table). These character-
Fig. 9 shows the results of numerical model, which were izations will allow for designing the stages of the construction and
obtained considering the characteristics of S.1, and the measured avoiding unexpected events. However, although the characteriza-
head evolutions at piezometers SL-15, Pz-8 and PA-110. The ampli- tions may be performed carefully, they will probably contain inac-
tude of the variations is higher in the measured than in the com- curacies. During the construction of the HST tunnel in Barcelona,
puted heads. This occurs because the parameters of the EPB were the soil was characterized, and in the study site, a fault was
averaged by each EPB cycle to be implemented in the model. Note detected. Nevertheless, given the distance between the boreholes
that the amplitude of the oscillations increases when the EPB is used, this fault could not be located with precision. This fact was
located near one of the piezometers. Both head evolutions (numer- the motivation to build a hydrogeological numerical model of the
ical and measured) reflect the presence of the fault, which advance of the EPB to locate the fault.
hydraulically disconnects the two sides. Before the EPB crossed Furthermore, to model the advance of an EPB with a hydrogeo-
the fault, head oscillations were not observed in the piezometers. logical numerical model is not an easy issue. Given the large num-
However, when the machine passed the fault, the heads started ber of parameters registered by EPBs, a statistical study must be
to oscillate. conducted to determine those parameters associated with the
The model was compared by computing the maximum and groundwater response during tunnelling. Statistical tools are
minimum distances where the groundwater is affected by the therefore essential to obtain the parameters that allow for mod-
EPB during each push. These distances were determined by calcu- elling the advance of the EPB. The statistical study undertaken to
lating the volume of the aquifer affected. The calculation was model the advance of the EPB in Barcelona showed that the hydro-
undertaken assuming that (1) the Ss of the aquifer was 0.00001 geological impact caused by an EPB can be explained by consider-
(this value was obtained from the pumping tests) and (2) the vol- ing only four parameters (some of them continuous and others
ume of the soil affected by the pushes had the same shape as a discontinuous). The parameters implemented in the model were
L. Culí et al. / Tunnelling and Underground Space Technology 56 (2016) 12–21 21

the ‘‘penetration” (discontinuous parameter) and the average of Underground Space Use Analysis of the Past and Lessons for the Future. Taylor &
Francis Group, London, ISB 04 1537 452 9.
‘‘earth pressure 1 and 5” (continuous parameter). Model result
Dalgiç, S., 2002. Tunneling in fault zones, Tuzla tunnel, Turkey. Tunn. Undergr.
would be the same if the ‘‘penetration” was replaced by the ‘‘veloc- Space Technol. 18, 453–465.
ity of advance”. Cripps, A.C., McCann, D.M., 2000. The use of the natural gamma log in engineering
Different scenarios were simulated, and the previous character- geological investigations. Eng. Geol. 55, 3113–3324.
Elkadi, A.S., Huisman, M., 2002. 3D-GSIS geotechnical modelling of tunnel
ization was verified by comparing the numerical heads with the intersection in soft ground: the Second Heinenoord Tunnel, Netherlands.
observations. Given the position of the piezometers it was only Tunn. Undergr. Space Technol. 17, 363–369.
possible to locate the end of the fault from the groundwater Emeriault, F., Kastner, R., 2008. Tunneling with earth pressure balance tunnel boring
machines: observations and modelling. Jornada Técnica: Túneles con EPB.
response. However, results show that the piezometric head evolu- Simulación y Control de Tuneladora. Barcelona, Mayo 2008.
tion depends on the geology of the site, and therefore, other char- Font-Capó, J., Vázquez-Suñé, E., Carrera, J., Martí, D., Carbonell, R., Pérez-Estaum, A.,
acteristics of faults can be ascertained if more piezometers are 2011. Groundwater inflow prediction in urban tunnelling with a tunnel boring
machine (TBM). Eng. Geol. 121, 46–54.
available. For example, if there is one piezometers inside of wide Font-Capó, J., Vázquez-Suñé, E., Herms, I., Carrera, J., 2012. Groundwater
fault zone and other after, it would be possible characterize both, characterization of a heterogeneous granite rock massif for shallow tunneling.
the start and the end of the fault zone from the groundwater Geologica Acta 10 (4), 395–408.
Font-Capó, J., Pujades, E., Vázquez-Suñé, E., Carrera, J., Velasco, V., 2015. Assessment
response. In the same manner, data from a piezometer located of the barrier effect caused by underground constructions on porous aquifer
before an impervious fault could be useful to detect the position with low hydraulic gradient: a case study of the metro construction in
of the fault since it would act as a no-flow boundary conditioning Barcelona, Spain. Eng. Geol. 196, 238–250.
Gens, A., Persio, R., Di Mariano, A., Castellanza, R., Arroyo, R., 2009. Relación entre
the groundwater response in the piezometer depending on their
parámetros de una tuneladroa EPB y los movimientos del terreno. Terceras
distance. jornadas hispano portuguesas sobre técnica en las infrastructuras ferroviarias.
Given the results obtained, it is possible to suggest that numer- IGC, 2007. Mapa geològic de zones urbanes 1:5000. Barcelona, Carmel.
ical modelling is a useful tool to verify the characterization of the Jimenez, R., Senet, S., 2012. Teaching the importance of engineering geology using
case histories. In: McCabe, Patasidou, Phillips (Eds.), Shaking the Foundations of
soil (geological and hydrogeological) during the construction of a Geo-Engineering Education. Francis and Taylor Gropu, London, pp. 99–104.
tunnel with a TBM type EPB, even in real time. The advance of Jacob, C.E., 1950. Flow of groundwater. In: Rousep, H. (Ed.), Engineering Hydraulics.
the EPB should be modelled, and the numerical response should John Wiley, New York, pp. 321–386.
Jiménez Salas. Geotécnia y cimientos. Ed Rueda. Madrid, 1975. 500 p.
be compared with the observations. The procedure also allows Jurado, A., Mastroianni, N., Vázquez-Suñé, E., Carrera, J., Tubau, I., Pujades, E.,
for locating some geological structures, such as faults. Note that, Postigo, C., López de Alda, M., Barceló, D., 2012. Drugs of abuse in urban
to achieve the goals, a geological study, en exhaustive hydraulic groundwater. A case study: Barcelona. Sci. Total Environ. 424, 280–288.
Monfort, D., Font-Capó, J., Vázquez-Suñé, E., Gogu, R., Carrera, J., 2008.
characterization an monitoring of the groundwater prior to con- Comportamiento de un acuífero a nivel local al paso de una tuneladora (Caso
struction are required to build the numerical model. L9 de metro de Barcelona). Jornadas sobre el agua y las infraestructuras en el
medio subterráneo (Barcelona, 24–26 Noviembre 2008) AIH-GE, IGME, 2009.
Medina, A., Alcolea, A., Carrera, J., Castro, L.F., 2000. Modelos de flujo y transporte en
Acknowledgments la geosfera: Código TRANSIN IV (Flow and transport modelling in the
geosphere: the code TRANSIN IV). IV Jornadas de Investigación y Desarrollo
The authors would like to acknowledge ADIF (Administration), Tecnológico de Gestión de Residuos Radioactivos de ENDRESA. Technical
Publication 9/2000, pp. 195–200.
SACYR (Construction company) and INTECSA-INASA (Technical
Medina, A., Carrera, J., 2003. Computational different type of data. Geostatical
assistance) for their support throughout the hydrogeological mon- inversion of coupled problems:dealing with computational burden and
itoring of the civil works. The authors were appointed by ADIF as different types of data. Water Resour. Res. 32 (10), 3063–3076.
external advisors during the construction of the tunnel. Additional Melis, M., 2005. The collapse of a railway tunnel by face instability in soft or very
fractured rocks and soils (Second part). Revista de Obras Públicas 3458, 7–24.
funding was provided by Spanish Ministry of Science and Innova- O’Carroll, J., 2005. A Guide to Planning, Construction and Supervision Earth Pressure
tion (MEPONE project: BIA2010-20244); and the Generalitat de Balance TBM Tunnelling. Parson Brinckerhoff.
Catalunya (Grup Consolidat de Recerca: Grup d’Hidrologia Sub- Pujades, E., Vázquez-Suñé, E., Carrera, J., Jurado, A., De Simone, S., Ledesma, A.,
Ramos, G., Lloret, A., 2014a. Deep enclosures versus pumping to reduce
terrània, 2009-SGR-1057). settlements during shaft excavations. Eng. Geol. 169, 100–111.
Pujades, E., Vázquez-Suñé, E., Carrera, J., Jurado, A., 2014b. Dewatering of a deep
excavation undertaken in a layered soil. Eng. Geol. 178, 15–27.
Appendix A. Supplementary material
Pujades, E., Vázquez – Suñé, E., Culí, L., Carrera, J., Ledesma, A., Jurado, A., 2015.
Hydrogeological impact assessment by tunnelling in sites of high sensitivity.
Supplementary data associated with this article can be found, in Eng. Geol. 193, 421–434.
Shin, H.-S., Kwon, Y.-C., Jung, Y.-S., Kim, Y.-G., 2009. Methodology for quantitative
the online version, at http://dx.doi.org/10.1016/j.tust.2016.02.017.
hazard assessment for tunnel collapses based on case histories in Korea. Int. J.
Rock Mech. Min. Sci. 46, 1072–1087.
References Vázquez-Suñé, E., Sánchez-Vila, X., Carrera, J., 2005. Introductory review os specific
factors influencing urban groundwater, an emerging branch of hydrogeology,
Alonso, E., Pinyol, N., Puzrin, A., 2010. Geomechanica of Failures. Springer. with reference to Barcelona, Spain. Hydrogeol. J. 13, 522–533.
Aydin, A., Ozbek, A., Cobanoglu, I., 2004. Tunnelling in difficult ground: a case study Van Baars, S., 2011. Causes of major geotechnical disasters. In: Vogt, Schuppener,
from Dranaz tunnel, Sinop, Turkey. Eng. Geol. 74, 293–301. Straub, Braü (Eds.), ISGSR 2011. Bundesanstalt für Wasserbau, Germany.
Bezuijen, A., 2002. The Influence of Soil Permeability on the Properties of a Foam Vera, J.A., 2004. Geología de España. Sociedad Geológica de España y IGME. Ed.
Mixture in a TBM, Tunnelling. A Decade of Progress. GeoDelft 1995–2005. IGME. 884 p.
Taylor & Francis, 2006. http://dx.doi.org/10.1201/9781439834268.ch6. Yamamoto, T., Shirasagi, S., Yamamoto, S., Mito, Y., Aoki, K., 2003. Evaluation of the
Bezuijen, A., Joustra, J.F.W., Talmon, A.M., Grote, B., 2005. Pressure gradients at the geological condition ahead of the tunnel face by geostatical techniques using
tunnel face of an Earth Pressure Balance shield. In: Erdem, Solak (Eds.), TBM driving data. Tunn. Undergr. Space Technol. 18, 213–221.

You might also like