You are on page 1of 5

S Project Name

Colliers 1
International PRE-CHECK LIST
Project Code RISING MAIN
AC Project Management Consultancy INSTALLATION REPORT 7

Reference Drg No_____________________________________ Structure/Block/Tower No ___________________

Revision No R ____________ Drg Issue Date ___/____/____ Floor/Location/Other reference _______________

1 2 3 4 5 6 7 8

REFERENCE
TOLERANCE LIMIT CHECKED & APPROVED
S# VALUE REMARKS
CONT PMC CLIENT
Check Electrical Shaft size as per drawing.
1
Wet riser and sprinkler should not be in the
2 same shaft.

Electrical Shaft Clearance for no Water


seepage. Proper plastering / white wash /
3 tiling to avoid any seepage of Paint / Cement
on the busduct.

Installed supports are as per approved


drawing and the supports are not at jointing
4 section.

Check whether all electrical equipment like


transformer
5 /DG /Panels are positioned and as per
approved drawing.

Check the Detailed packing list with part


number(s) received, along with consignment
and verify, the same with approved drawing
whether all the bus duct sections are
received. And all busduct, and its accessories
6 are received as per approved drawing and
there is no
shortfall on accessories and hardware.

If any shortfall of accessories or hardware are


reported the same is inform to
7 manufacturer/supplier on the same day.

Busduct consignment to be stored in dry place


and covered with proper plastic. (Do not
remove the plastic wrapped on the load /
8 supply ends of the busduct till taken for
installation)

Check whether all required tools and tackles


mentioned in the installation manual are
9 available before starting the installation.

IR value check for every bus duct feeder


before Installation
10

Client's Competent Personnel should take


training on the method of installation of the
bus duct / Rising main / Lighting Trunking
11 from Godrej before start of installation.

Outdoor busduct is not weather resistant,


until completely and properly installed.
Should be treated exactly the same as indoor
12 busduct, until it is installed.

INSTRUCTION TO FILL:
Column # 3 = Any reference value to be recorded
Column # 4,5,6 = initials
dd/mm/yy
Column # 7 = Any Dicrepancy/ Issues Recorded

CHECKLIST #
______S/AC/1/7______

Our Knowledge is your property


S Project Name
Colliers 1
International
Project Code PRE-CHECK LIST
BUSDUCT INSTALLATION REPORT
AC Project Management Consultancy 7

Reference Drg No_____________________________________ Structure/Block/Tower No ___________________

Revision No R ____________ Drg Issue Date ___/____/____ Floor/Location/Other reference _______________

1 2 3 4 5 6 7 8

REFERENCE
TOLERANCE LIMIT CHECKED & APPROVED
S# VALUE REMARKS
CONT PMC CLIENT
Client's Competent Personnel should take
training on the method of installation of the
1 bus duct / Rising main / lighting Trunking from
Godrej before start of installation.

All the busduct lines are aligned in plumb in


case of riser & at zero level in case of
2 horizontal run of busduct.

Check whether all the joint bolts are sheared


@14-15 kg-m. and tightening of joint bolt is
100% responsibility of installation contractor /
3 Clients.

Take insulation resistance at 500V. Check the


IR before and after Shearing of joint Bolts. As
per IEC 60439-1, clause 8.3.4 insulation
4 resistance should be at least 1000 fi/V i.e. 0.5
M fi.
(To maintain stringent quality standards
Godrej recommends 1M fi)
Check whether all the spring Hangers top Nuts
are loosen and spring should be loaded in case
5 of Riser as per installation manual.

Check whether earthing run along with Bus


duct is physically connected to both the ends
6 of the busduct flanged & equipment.

Check whether all the bolts at Flanged end are


tightened.
7

Check tightening of all the bolts of flexible


links to equipment side like Panel
8 ,Transformer, DG

Check whether all the supports to the risers


and bus duct line are installed properly to
9 carry the required weight of Busduct

Check whether all the holding clips on the


horizontal supports are tighten
10

Check whether all the holding clips on Tap off


box are tighten
11

Relay Setting of all the MCCB / ACB.


12

Check for chance of water seepage on


Busduct / Rising Main from other utilities
13

Wet Riser & Sprinkler should not be in same


shaft.
14

Check whether the entire name plates on Tap


Off Box & panels indicating outgoing location
15 of supply.
Check whether caution / danger stickers
displayed on all the Tap Off Boxes and
16 Electrical Panels.

Check whether earthing wire is connected to


17 Tap Off Box door & bus duct housing.

Check Phase sequence of Rising Main (R, Y, B,


and N) in line with Tap off box incoming and
18 outgoing.

Check Whether Outdoor Installation Bus duct


is properly filled up with sealant/compound at
19 the joints in case of IP/65/68

Bus Duct / Rising Mains should not be


energized without checking of all above
20 instructions and installation Contractor /
Client to ensure all above points

INSTRUCTION TO FILL:
Column # 3 = Any reference value to be recorded
Column # 4,5,6 = initials
dd/mm/yy
Column # 7 = Any Dicrepancy/ Issues Recorded

CHECKLIST #
______S/AC/1/7______

Our Knowledge is your property


S Project Name
Colliers 1
International
Project Code MEGGER TEST REPORT
AC Project Management Consultancy 7

Reference Drg No_____________________________________ Structure/Block/Tower No ___________________

Revision No R ____________ Drg Issue Date ___/____/____ Floor/Location/Other reference _______________

Insulation Resistance Test (In Mega – Ohms)

Test Equipment Used:‐ Insulation Resistance Tester (Meggar)

Make:‐

Serial Number:‐
1 2 3 4 5 6 7 8
REFERENCE
TOLERANCE LIMIT CHECKED & APPROVED
S# VALUE REMARKS
CONT PMC CLIENT
R Phase ‐ Neutral

Y Phase ‐ Neutral
2

B Phase ‐ Neutral

R Phase ‐ Earth

Y Phase ‐ Earth

B Phase ‐ Earth
6

Neutral ‐ Earth
7

R Phase ‐ Y Phase
8

R Phase ‐ B Phase
9

B Phase ‐ Y Phase
10

INSTRUCTION TO FILL:
Column # 3 = Any reference value to be recorded
Column # 4,5,6 = initials
dd/mm/yy
Column # 7 = Any Dicrepancy/ Issues Recorded

CHECKLIST #
______S/AC/1/7______
Our Knowledge is your property

You might also like