Professional Documents
Culture Documents
1
Greater Colombo Wastewater Management Project
Colombo sewerage system has a long history. Richerd Eustace Tickell wrote in
February 1923 in his paper on “Colombo Drainage Works” in the Minute of
Proceedings Vol.216, of the Institution of Civil Engineers, London that the planning
of the sewerage system in Colombo Municipal Council area was commenced in 1896
and the construction work was commenced in 1906. The sewerage system has been
funded by the then government through a loan to the Colombo Municipal Council.
The sewerage systems in Dehiwala, Mt Lavinia Municipal Council and Kolllonnnawa
Urban Council areas were built during 1983-1987 based on the Sewerage Master Plan
by Howard Humphrey done in 1972. Parallel to this the sewerage system in Colombo
Municipal Council area has partly been rehabilitated and expanded. The sewage from
Dehiwala Mt.Lavinia Municipal Council and Kolllonnawa Urban Council areas has
connected to Colombo system for sea disposal. Additionally 11 numbers of
institutions located outside Colombo Municipal limits discharge their sewage through
Colombo system.
Today the Colombo sewer system has experienced many failures requiring urgent
attention. There are several instances that public life was threatened and country’s
economy was affected due to sudden failures in the system. Several studies have been
carried out on the condition of the system and with the understanding of the criticality
of this service the Government has obtained a loan from the Asian Development Bank
to upgrade the most critical component of the system under the Greater Colombo
Wastewater management Project.
The project has originally planned to be completed within a period of 5 years and was
expected to be completed by 31st December 2014 with a loan closing date of 30th June
2015. The project completion date was extended till 30th June 2017 by taking into account
the time required for completion of agreed activities.
2
1. Project Cost
The project cost is estimated at USD 116.6 million, including taxes and duties
amounting to USD16.6 million. A summary of the cost estimates in $ million is given
in Table below.
3
Component 2: Strengthening Institutional and Operational Capacity
4
4. Project Implementing Area - Within Colombo Municipal Council Limits
5
5. Prevailing status of existing sewer lines and pumping stations
6
6. Status of Component 1 - Upgrading Sewerage Infrastructure
The component 1 of the project constitutes 80% of the project funds for
rehabilitation of main sewerage system, Rehabilitation of Gravity sewer,
Rehabilitation of Sea outfalls, Rehabilitation of Pumping Stations and supply of
non-fixed operational equipment and resettlement activities.
The project has procured 4 numbers Jetting and Vacuum Trucks, Spare parts and
accessories worth over Rs.223 Million to Colombo Municipal Council. These 04
jetting machines were given to District Engineer’s offices in the CMC and are
currently used for cleaning of accumulated grit, sand, hard deposits, encrustations
tree roots etc. from nearly 260Km of sewers and 7000 numbers of manholes.
7
maintenance of equipment was also conducted to the CMC staff by the particular
suppliers.
The Contractor for sea outfalls (including the removal of accumulated grit worth over
Rs. 2127 million) was awarded in March 2013. Work completed in May 2015.
At Weellawatta Outfall
Design and construction of sea based access chamber
Unblocking of diffuser ports and fixing of end plate
Repair land based damage of out fall pipe line
Cleaning and removal of accumulated grit and debris from outfall pipe line
8
Offshore junction chamber was casted at land
and brought to the sea for launching.
9
6.4 Rehabilitation of Gravity Sewers
The Contract was awarded in May 2014 and is in progress. The completion date of the
contract is 31st December 2016.
Major outcomes of the activity are enhanced carrying capacity of sewers, reduced
clogging/blockages in sewers, database of condition assessment sewers.
The defective sewer at Marine Drive is being replaced using micro tunneling
technology. Sewer rehabilitation works at Queen’s Road, Alfred Place, Deanstan
Place and Pedris Road are planned to commence as the next site under the contract.
10
Pipe jacking work at Marine Drive. The jacking machine is positioned on the guide rails in the
driving shaft. The alignment is monitored using laser technology. The jacking process is
powered using hydraulic forces.
11
Identification of damages in a sewer cannot be detected often until it surfaces through
sinkholes in roads or properties where the sewer pipe runs. The CCTV carried out has found
large number of defective sewers due to natural cracks due to the age of the system or misuse
of the systems.
The purpose of this Contract is to replace existing sewer pipes running under and
through the substandard houses/settlements in the area by constructing new sewers
along public roads to gain access for operation and maintenance.
12
Shoring work to support deep
excavation work for construction of
manhole at Wanathamulla sewer
upgrading site
The Contract was awarded in June 2015. The work will be completed in 3 ½ years
period.
13
6.6 Planning of new sewer systems for increasing sewerage coverage
The work includes the study of capacity analysis of existing sewers in the area.
Required capacity enhancements, re-routing to provide the coverage and also to
14
improve the access for operation and maintenance are taken into account when
planning and designing of the system improvement
The services of the Institutional Development Consultant (IDC) are provided in order
to support Colombo Municipal Council in implementing these institutional changes to
ensure sustainability of sewerage operation. Now Institutional Development
Consultancy is over and following activities have been performed.
Computer based Property Connection management system was developed and is in-
operation satisfactorily. Commencing from the origin of the sewer system in the city,
records of connections given are computerized to enhance efficiency and
effectiveness of service provision. In parallel public complains on sewer failures,
collapses handling system was established. Complains received are entered into the
system and attendance of complains is monitored on-line. Objective of developing
computer based systems is to enhance transparency and accountability of the
Colombo Municipal Council in service provision and also to have efficient and
effective database management system which is required for system improvement. .
15
A screen view of the Property connection
database. This ensures transparency,
accountability of the service provider.
The School Education Programme is carried out every year in the first term of the
year. Project staff together with the staff of the Drainage Division of Colombo
16
Municipal Council, with the blessings of the Ministry of Education, visits Schools and
explains the students and teachers on the aspects related to sanitation and sewerage
system. So far the programme has been carried out in 66 numbers of schools
and16705 numbers of students have attended the programme.
School education and Public Awareness Programme. School children actively participated at
programmes. Street Drama produced by the NGO attracted large crowds and participation of
the viewers on discussion was encouraged suing the Forum Theater concept.
17
A leader from a Community Based Organizations shares his views at a forum held to
discuss the mechanisms to strengthen the links established under the CPPE
Programme. The elected body; Council members attended the forum with the staff of
the council.
Consulting service is provided to the Project Management Unit for the design and
supervision of sewerage infrastructure works.
18
09- Investment Plan 2016
Allocation for
No. Main Activity / Sub Activity
2016 Rs. Mn.
3
Project Management and Implementation Support
3.1 Design, Supervision and Management Consultant 100
3.2 Training and Workshop 100
19