Professional Documents
Culture Documents
net/publication/330910554
CITATION READS
1 1,562
3 authors, including:
Reda Abdulaal
King Abdulaziz University
20 PUBLICATIONS 442 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
Developing Fuzzy Multiple Criteria Decision Making Approach for Contractor Classification and Selection in Construction Industry at KSA View project
All content following this page was uploaded by Reda Abdulaal on 06 February 2019.
51
52 Ahmed M. Badeeb et al.
pipes, which are connected directly to the After the mixing time is completed, it will be
dissolver. The extenders will be added one by added through big pots into the dissolver.
one using the help of stacker and fixed crane Upon the completion of the mixing process, a
(fixed crane is available in each dissolver) sample of the paint will be taken in order to
where the stacker will be used to transfer the test the grinding stage on a paper panel. A 200
extenders which come in a bag of 1000 kg, Micron will be applied on the panel and then
and the crane will lift the bag and put it closer will be kept inside an oven for an average of
to the manhole. Once the addition of the 20 minutes. If the grinding test passed, then
extenders is completed, the operators will pre- another sample will be submitted to the lab in
weigh the next additives, which are placed in order to inspect the other specifications, such
cubic plastic tanks with a valve and a as the viscosity, PH-value, hiding power and
weighing scale. The additive will be mixed the application structure (Fig. 2).
with water before adding it to the dissolver.
Yes
No
No
Yes
The lab team will decide the net weight the label on each pail manually. According to
and gross weight according to the approved several process observations for the three stages
batch’s specific gravity and density. All the tasks of the manufacturing process, the filling process
described above carried out manually except the is the longest process in most of the products.
filling of paint into the pails. The arrangement of Figure 3 illustrates the filling process.
packing materials, empty pallets and moving the
4. The Proposed Methodology
pallets into the temporary storage area carried
out using stackers for transferring. Placing the The formed study team recommended
pails into the pallets is semi-auto task where an using some of lean manufacturing techniques
operator will use air lifter machine that sucks the to increase the company’s productivity. The
pail’s top and then placing it into the pallets, team starts with data collection followed by
where a worker operates the air lifter machine. data analysis and ends with implementing four
The number of the filling operators varies lean manufacturing techniques.
according to the production line capability and 4.1. Data Collection
the packing size to be filled (i.e. small, medium
and large packs). Labelling process is fully a Value Stream Mapping (VSM)
manual task where the filling operators will past technique is used to collect the data for the
56 Ahmed M. Badeeb et al.
No
Yes
Manufacturing process
Location: Water base factory
Problem: Productivity efficiency
Reduce the changeover time for the stackers. This step organizes the place and let
filling process workers perform their tasks much way easier
Reduce the human mistakes due to lack and faster than before. The huge impact of
of skills or knowledge defining a designated place for the stackers
Reduce the workload on operators and trolleys in the pre-weighing area occurred
as the travel distance by the pre-weighing
4.3. Lean Implementation operators reduced. Pre-weighing operators
Four lean manufacturing techniques become able to perform their task efficiently
selected as the most appropriate in order to and consistent.
achieve the company’s goals and to increase Each product in the production floor has
the productivity: its own filling size and correspondingly has its
Work place Organization, 5s own layout for filling. So, having one filling
Single minute exchange of dies, SMED line for different products a complex process
Work Standardization and leads to time-consuming for the preparation
Kanban of the layout especially when the area is
congested. Operators usually take long time for
5. Results and Discussions moving the filling line to the desired layout so
5.1 The Results Obtained Using Workplace they can start filling. The team has sort the area
Organization Technique (5S) and the filling line according to the size of
packing to be filled. After several meetings and
The impact of implementing 5S GEMBA (A Japanese word that literally means
technique in the raw material store and the "the real place", used in business process
pre-weighing area was significant. The team improvement contexts to refer to the place
has changed the location of several raw where value is added, such as a manufacturing
materials and defined a location for all the area or a workshop) on site they have decided a
tools and equipment’s. The unwanted or standard layout for each filling size of the
expired raw material was removed from the packing material. They came up with 3
place, which was making noise and delaying standard layouts for small, medium, and large
the movement of the workers in the area. packs. After finalizing the standard layouts, the
Unnecessary tools such as cleaning tools, layout for each size of packs marked using
unused weighing scales and defected trolleys yellow tape as illustrated in Fig. 7.
were sent to scrap after the approval of area
owner. Paper handling was further improved In Fig. 8, the filled finish goods are
where a shelf of multiple racks were fixed on placed on pallets waiting to be transferred to
the wall, and marked for each work center. All the conveyor by stackers. For each filling line,
the shop orders for a certain W/C placed in its the area of placing the pallets has been
designated rack according to the sequence and marked. This step of making designated area
priority (need date). The waste was eliminated. for the filled pallets help the filling team to
The following paragraphs show the area better organize the filling floor and it gives
improved by applying 5S technique and its better reading for the supervisors. In addition,
impact on the production productivity. it worked like a Kanban for the pallets as the
stacker operator can see that the designated
Trolleys and stackers become easy to area for a specific filling line is full of pallets
accessible and to find (Fig. 6). Designated and thus he has to drive the stacker and move
place made to keep all the trolleys and the pallets to the conveyor. In fact, even safety
60 Ahmed M. Badeeb et al.
has been considered by marking the specific that needs to be collected and sent to the
area for the pallets, where there will be no designated area.
misplacement of pallets on the emergency Previous practice shows that types of
lines or green path allowing the operators to non-hazardous waste were collected in big
move smoothly to the fire assembly point cartons. After that, they placed on pallets in
when fire alarm starts. order to send to the non-hazardous huge waste
During preventive maintenance or any trash. Whenever the trash bin reaches to
breakdown, maintenance team or senior certain limit, the HSE (Healthy, Safety, and
operators have to bring their own tools and Environment) team will call the non-hazardous
equipment to fix the problem that is agent to visit the factory and remove all the
consuming time of movement. Several non-hazardous waste. The company has to pay
meetings held with the maintenance team and the agency per kilograms. HSE team has made
they have concluded that only specific tools several visits to different agency dealing with
are necessary to fix 80% of any breakdown of the non-hazardous waste and agreed with one
machine or to complete the preventive agency to take the non-hazardous waste with
maintenance job. Tools has been provided to no cost if segregated properly. The agency and
each machine whether its filling line or the company agreed to divide the waste into
dissolver or any other machinery that operated three main categories that are:
by workers. Tools have been kept in toolbox
Plastic waste (Nylons, paper cups, etc.)
nearby each machine and the keys kept with
the team leader (Fig. 9). Packing material
Figure 10 shows the different raw Jumbo and paper bags
materials in the raw material store and the pre-
The team has created new trash bins
weighing area. The area has fully reorganized
nearby workstations (Fig. 11), and ask the
and the raw materials have been placed in a
operators and cleaners to segregate the waste
way that reduces the movement of workers. In
once it generated immediately so no need to
addition, designated line made for each raw
accumulate all the waste and then segregated
material to ease the process of reading the area
on the site as expected to take long time.
and easily caught any shortages or near to
Figure 11 shows the types of waste bins crated
shortage of raw material.
by the team where the blue bins made for the
Future plan is to set re-order point for nylons bags and the green bins for the paper
each line to better read the area and control the bags.
stock of the raw material.
Segregating the waste according to the
Waste generation and treatment are new three categories described above, the
costing the company a lot of money. The waste handling become easier and the cost of
generated waste is divided into two categories handling the hazardous and non-hazardous
that are hazardous waste and non-hazardous waste decreased due to the changes in the
waste. Hazardous waste includes any waste disposing methodology where before the non-
that have contaminated by paint or any hazardous waste being collected by a supplier,
chemicals, while the non-hazardous waste is the company has to pay the supplier for taking
mostly the paper bags, plastics, the non-hazardous waste. However, the team
uncontaminated packing material, nylons, etc. members were able to find a contractor who
All stages of manufacturing generated waste has willingness to buy the waste if properly
An Application of Lean Manufacturing Techniques in Paint Manufacturing Company: A Case Study 61
segregated (i.e. cartons, plastic, nylons etc.). waste money company is paying. Table 1 and
So, the company has to stop paying the Fig. 12 illustrate the waste disposal progress.
contractor for removing the waste and the
Table 1. Monthly waste disposal in 2017.
opposite scenario occurred where the
Non Hazardous
contractor pay the company for the waste he Month Hazardous waste (KG)
waste(KG)
takes. In addition to the non-hazardous waste, January 6542 24090
the amount of the hazardous waste reduced February 5990 22368
March 6503 21951
due to the implementation and the close April 14151 21824
monitoring of the hazardous waste collected. May 7002 21782
The team has reinforced the differences June 3207 15549
between the hazardous waste and non- July 5988 23960
hazardous waste and the cost of treating each August 6221 21780
September 5240 21220
kind, the 5s teams stopped the wrong behavior October 5650 23100
of putting a non-hazardous waste into the November 6833 24772
hazardous waste area and causing the December 3122 3200
contractor to ask for more money, which is of
Fig. 6. Designated place for all trolleys and stackers in the pre-weighing area.
Fig. 11. Different types of trash bins (from left to right: Packing material, plastic waste, and jumbo and paper bags).
5.2. The Results Obtained Using Single sizes, which are 16.2 (large), 3.6 (medium) and
Minute Exchange of Dies (SMED) 0.9 (small) liters respectively. The first step to
apply SMED is to sort out the internal process
Filling of small Stock Keeping Units
and external processes.
(SKUs) consider as a big challenge for many
reasons. Lacking of fully automatic filling line, The internal process is a process or task
high mix of SKUs, number of workers required, that it can be performed only when the
ergonomics, etc. are top reasons that affect the machine is off, while external tasks can be
production plan adherence and the production of performed even when the machine or process
small SKUs efficiency. The plan to implement is running. The idea is to convert the internal
the SMED concept was decided to take place on process into external process. The main area of
a filling line that is designed to fill three packing improvement was to fabricate and design the
64 Ahmed M. Badeeb et al.
parts and adjustment in a way that more packing sizes when implementing SMED
efficient and with less cycle of time, the process over seven weeks.
maintenance team has suggested some points
5.3. The Results Obtained Using Work
of improvement as follows:
Standardization
Lid closer unit was standardized as some One of the reasons of low productivity is the
modification done to the holder in a way high number of defected output. So, Pareto
that only one holder can fit all types of analysis implemented in the charging process
lid closer. to understand the causes for rejecting the
Marking for the level of weight was batches by laboratory. Root cause analysis
defined to adjust easily from SKU to data for the full month gathered and analyzed
another (Drums to gallons or small packs for better understanding. The team stated
to drum). below points as the main factors that cause the
batch rejection during charging process:
The conveyor was adjusted in a way that it
can hold all the three sizes of packs with Operators skills/mistakes
only small adjustment of the safety guard. Wrong pre-weighing
Tables 2 and 3, describe the changeover Programmable logic controller (PLC) error
cycle time between all packing sizes before Wrong raw material label
and after the implementation of SMED. Others
Table 2. Changeover cycle time before implementing SMED. Operators’ skills/mistakes reflect any task
Before
performed by them but in a wrong manner or not
Time (Min.) as per the given instructions (e.g. mixing time,
Packing size Large Medium Small wrong addition, dissolver speed, etc.). Wrong
Large 0 20 30 pre-weighing means that the pre-weighing
Medium 30 0 15 operators give wrong raw material batch or there
Small 22 17 0 is deviation in the raw materials given (i.e.
Table 3. Changeover cycle time after implementing SMED. wrong weighing of row material or not accurate
weight). System's error is a reason that causes
After
the rejection of the batch through wrong addition
Time (Min.)
Packing size Large Medium Small
of raw materials, which are added through PLC
Large 0 7 9 system i.e. automatic addition of bulk raw
Medium 6 0 4 materials through system and pipelines. Wrong
Small 5 4 0 raw material labels mean that the raw material
store have pasted wrong label for a specific raw
The overall time for performing the material. Others reflect any other reason that
changeover task from the large size to the causes the defect of the batch under process such
small packing before the improvement was 22 as dissolver breakdown during mixing process
minutes while it was reduced after the or any complex process. Out of 330 batches
improvement took place to reach only to 5 produced in a month there were 20 batches
minutes. However, the workers could not rejected by laboratory due to different reasons
sustain changeover time of 5 minutes, after (see Table 4). Pareto chart, given in Fig. 14,
seven weeks they have successfully sustained indicates that more than 70% of defected batches
at 9 minutes’ changeover. Figure 13, shows were because of the operator’s skills during the
the changeover cycle time between different charging process.
An Application of Lean Manufacturing Techniques in Paint Manufacturing Company: A Case Study 65
Table 4. Status of defected batches before applying work reduced to reach only six batches out of 322
standardization technique.
batches. (Table 5 and Fig. 15).
Before applying work standardization Table 5. Status of defected batches after applying work
Defects standardization technique.
Charging process (in batches) Defects (%)
Operator mistake 14 70% After applying work standardization
Wrong pre-weighing 2 10% Defects
Charging process (in batches) Defects (%)
PLC/System error 1 5%
Operator mistake 6 43%
Wrong label for RM 1 5%
Wrong pre-weighing 2 14%
Others 2 10%
PLC/System error 1 7%
20 100%
Wrong label for RM 2 14%
A month after the training session was Others 3 21%
finished, it showed that the number of defected 14 100%
batches caused due to operator’s skills/mistakes
Fig. 13. Cycle time for changeover between different packing sizes.
Fig. 14. current Pareto chart for the charging process defects.
66 Ahmed M. Badeeb et al.
Fig. 15. Pareto chart for the charging process defects after work standardization.
5.4 The Results Obtained using KANBAN the reasons behind the shortages and it was
Technique found that migration of raw material and
fluctuation of the lead-time from suppliers is the
In paint manufacturing, there are fast
most causes of the shortages of the raw material.
moving and slow moving liquid paint
In fact, the engineers have found that shortages
products. In the paint company under study,
of semi-finish product have a big contribution in
the liquid paint product, say product (A) is
the total shortages occurred during the year.
defined as fast moving product, which is
Further investigation concludes that the
contributed by 55% of the total production
shortages of the semi-finish raw material is not
annually. This type of products uses several
because of the unpredicted increase of the lead
raw materials for manufacturing. The raw
time, neither the delay from the custom nor from
materials used to manufacture the product (A)
the inspections but it was because of lack of
can be categorized as raw material that is
controlling of the stock of the semi-finish
coming from supplier directly and can be used
product. The raw material staff are busy with the
as it is or as raw material that is produced in
raw material follow up and has no clue with the
the factory as a semi-finish product to be used
semi-finish raw material. The production team is
for the manufacturing this product (A). The
not familiar of controlling of stock of raw
semi-finish product is stored in Intermediate
material and thus leading to shortages of such
Bulk Containers (IBCs), a big PVC tank
semi-finish raw material.
having a capacity of 1000 Liter.
A brain storming session conducted with
The production efficiency is monitored by
the production operators, supervisors, raw
the production engineers and coordinators.
material storekeeper and engineers to find best
However, the reports show that raw material
possible solution that can eliminate the sudden
shortages are a bottleneck in the production
shortages of the semi-finish raw material.
department therefore, the team has investigated
Applying production Kanban will have the
An Application of Lean Manufacturing Techniques in Paint Manufacturing Company: A Case Study 67
potentials to better control the stock of the product. Once the container is fully consumed,
semi-finished raw material, the team the manufacturing operator will inform the
concluded. To do this, production engineers forklift operator to bring a new container from
calculated the number of Kanban that ensures the Kanban area. The forklift operator will go
no shortage would occur. The idea is to make to the Kanban area and will take one container
it visible and easily understand by the shop and place it in the manufacturing floor. This
floor operators. Two lean techniques were process will be repeated until there remains
used to help in this matter, Production Kanban only one container in the Kanban. Once the
and work standardization. forklift goes to bring the 5th container, he will
see a signal in the Kanban area (painted in red)
Here, production Kanban will be
that will indicate to the production planner to
handled. The team used the equation shown
place an order for the yellow oxide. Six days is
below to determine the number of Kanban
the time required to refill the Kanban area with
required to insure there will be no stoppage of
full 6 containers with a batch size of 3000
production due to yellow oxide shortage.
liters and it’s the average consumption rate for
the remaining container, i.e. the last container
that remains for use will be sufficient to run
the production for 6 days, which is the lead
Where demand during lead time = time to manufacture the yellow oxide and re
consumption per day multiply by lead time to fill the Kanban fully.
replenish an order. As mentioned earlier, one of the
Due to the high uncertainty for this item, bottlenecks in the pre-weighing process is
the safety stock decided to be 20% of the the number of the pre-weighed batches,
demand during the lead-time. One IBC which will affect the charging process if
(container) can take up to 500 Liter of yellow the next pre-weighed batch is not ready.
oxide. The daily average consumption of Product (A) which is 55% of total Jeddah
Yellow oxide is 370 Liters and the lead-time factory output is being produced in 5
to produce an order of yellow oxide is 6 different production lines which are
working days. The calculations show that dedicated for this product. Any delay in the
5.77≃6 containers/Kanban (500*6 = 3000 pre-weighing process will affect the
Liters batch) will be the ideal number of charging efficiency and thus can delay the
Kanban’s/Containers. manufacturing process and accordingly the
customer demand. The root cause behind
Since the production, process of yellow the delay of the pre-weighing process is
oxide is complex and it takes one full day of the sudden order of the next pre-weighed
production. Yellow oxide is produced on the batch from the charging operator where the
same dissolver that used to manufacture many shop order is still not yet submitted to the
different products that required by customers pre-weighing operator or because there is
(Finish goods products). The engineers decide an urgent order from a customer and the
to make a signal Kanban systems that can shop order is still not yet handled to the
store up to 6 containers (i.e. pallets). The pre-weighing store. There are three
Kanban area is consisting of 6 pallets. One standard batch sizes for five different
container will be placed in the manufacturing production lines. Table 6, illustrates each
floor, where it pre-weighted by the production line batch size.
manufacturing operators to produce another
68 Ahmed M. Badeeb et al.
Table 6. The different batch sizes according to the Manufacturing (LM) tools applied throughout
production line.
the manufacturing process made significant
difference. These four tools named: 5S,
SMED, work standardization and Kanban
achieved the study objectives. The study dealt
As described in the table above, there is with the three main processes in paint
only 3 different sizes of pre-weighing batches. manufacturing which are pre-weighing
Production lines 1 and 2 have the same batch process, charging process and filling process.
size and thus the pre-weighing materials are the The four LM techniques implemented in all
same for both tanks (i.e. the weight of the raw the three processes simultaneously.
material for both production lines is the same
and it can be used also for production line two
as the product is one and the size is the same).
The same concept is for production line four
and five. The team has decided to make a super
market Kanban for this product aligned for the
5 production lines. Racks has been installed and
divided into three columns, where each column
allocated to standard batch size, which are
4400, 6650 and 8022 liters. The idea is to let
the pre-weighing operators fill the Kanban with
no shop orders attached. This super market
Kanban will make sure that the pre-weighed
batches are always available to start the Fig. 16. Super market Kanban.
charging process. The shop order papers will be Pre-Weighing Process
with the charging operators instead of being
handed to the pre-weighing operators (Fig. 16). Since the pre-weighing process is the
Currently the number of pre-weighed batches first step in the real painting manufacturing
for is equal to 19 batches per shift and after the process and thus, any improvement in this
implementation of the super market Kanban the stage will directly improve the next processes
pre-weighing operator were able to pre-weigh that are charging and the filling process.
total of 30 batches where the waiting time has Supermarket Kanban and 5S techniques have
been reduced to reach only 2 minutes. significantly improved the pre-weighing
Production stoppage due to pre-weighing process. Organizing the workplace (5S)
process was reduced to reach only 3 times for a through creating dedicated (marked) areas for
full month and the process mapping for the pre- the weighing scales, trolleys, stackers, RM,
weighing stage further improved to be as etc. reduced the average pre-weighing time of
described in Fig. 17. a single batch by 36% (i.e., from 25 minutes to
16 minutes). The supermarket Kanban played
6. Discusstion a massive rule in increasing the productivity.
Applying lean principles and tools in The pre-weighing process daily output
manufacturing facilities is a quick win strategy increased by 57% and reached to 30 batches
especially if it is newly applied (i.e. first time instead of 19 batches daily. Below points
for application in a certain company). As a illustrate the improvement clearly:
conclusion, the suggested four Lean Pre-weighing Cycle time per batch: 16 min
An Application of Lean Manufacturing Techniques in Paint Manufacturing Company: A Case Study 69
The implementation occurred only in money as its more of administrative tools and
Dec.2017 to test the impact and it proves that solutions. Being able to control and minimize
the impact was significant. The overtime the waste using a technique like 5s, which not
associated for each month has been reduced as required big budget to implement, is a key
a result of implementing the LM techniques solution during recession. The benefit of
(Fig. 20). techniques like fishbone analysis, SMED, value
stream mapping, etc. not only in increasing the
7. Conclusion
productivity and identifying the area of
Understanding the manufacturing process weakness, in fact, theses techniques will enhance
deeply is a vital to track the bottlenecks and then the team work and will increase the engagement
the area of improvements. Lean manufacturing level of the people which itself will motivate
principles proofs its ability to increase the them and give them a space to innovate.
productivity without the need to spend much
An Application of Lean Manufacturing Techniques in Paint Manufacturing Company: A Case Study 71
Meeting the customer expectations applied will further enhance the productivity
during recession is important and will insure and identify more bottlenecks. Applying 7s,
more market share, where many rivals will which is the developed technique of 5s, will
suffer in meeting the customers' demands if enhance further the impact of the technique.
not responding quickly and effectively and Including the laboratory stage will further
lean manufacturing principles have all the increase the productivity and reduce the lead
abilities to do so. time. Future status of VSM will could better
point out the improved area. As human, the
8. Future Work
tendency to resist any new change is natural
This study has proven that applying the and therefore it should be tracked properly
Lean Manufacturing (LM) principles is a key prior implementing any new technique or
success factor in achieving high productivity procedure by introducing the change to the
rates and overcomes the productions people and letting them understand the change
bottlenecks. However, there are some before acting it.
recommendations and suggestions that if
Implementation on Industrial Organizations’ Proceedings of the 5th International & 26th All India
Performance. International Journal of Business and Manufacturing Technology, Design and Research
Management Invention, 2(3), 43-49 (2013). Conference (AIMTDR 2014), Guwahati, India, pp: 12-
14) (2014).
[9] Sajan M.P., Shalij P.R., Ramesh A. and Biju
Augustine P., Lean manufacturing practices in Indian [13] Lucherini, F. and Rapaccini, M., Exploring the Impact
manufacturing SMEs and their effect on sustainability of Lean Manufacturing on Flexibility in SMEs, Journal
performance, Journal of Manufacturing Technology of Industrial Engineering and Management, 10(5): 919-
Management, 28 (6) : 772-793 (2017). 945 (2017).
[10] Sabadka, D,. Molnar, V. and Fedorko, G., The use of [14] Dennis, P., Lean Production simplified: A Plain-
lean manufacturing techniques - SMED analysis - to language Guide to the World's Most Powerful
optimization of the production process, Advances in Production System, Productivity Press, 3rd Edition,
Science and Technology Research Journal, 11 (3): 187– pp:102-110 (2015).
195 (2017).
[15] Corona, E. and Pani, F. E., A review of lean-kanban
[11] Madhav, R., Marnewick, A., Nel, H. and Pretorius, approaches in the software development. WSEAS
J. H., Managing Changeover Waste in Manufacturing Transactions on Information Science and Applications,
Plants when Using Single Minute Exchange of Dies, 10(1): 1-13 (2013).
IEOM Society International, Morocco April (2016).
[16] Reddy, A. (2015). The Scrumban [r] evolution: Getting
[12] Bajpai, J. D., SMED (single-minute exchange of die) the Most Out of Agile, Scrum, and Lean Kanban.
methodology in garment manufacturing industry: Case Pearson Education, US, Indiana (2015).
study in reducing style change over time. In
An Application of Lean Manufacturing Techniques in Paint Manufacturing Company: A Case Study 73
تظبيق أساليب الترنيع الخالي من اليجر فى شخكة لترنيع الجىان :حالة دراسية
أحمد باديب ،و رضا عبد العال ،و عبد هللا بافيل
قدم الينجسة الرناعية ،كمية الينجسة ،جامعة الممك عبج العديد ،ججة ،المممكة العخبية الدعهدية
المدتخمص .نتيجة لالنكماش االقترادي الحاصل في المممكة العخبية الدعهدية ،بجأت شخكات الترنيع بالتفكيخ في تقميل التكمفة
التذغيمية وزيادة اإلنتاجية ،وذلك باستخجام نظخيات الترنيع الخالي من اليجر .وعميو ،فإن ىحه الهرقة تيجف إلى دراسة عممية
الترنيع في قظاع إنتاج الجىانات ،ومن ثم تحجيج المناطق التي تؤثخ بذكل سمبي عمى العممية الترنيعية ،وذلك باستخجام طخق
تحميميو تداعج عمى اكتذاف تمك المناطق .وبناء عمى تمك الجراسة ،تم اختيار بعض أساليب الترنيع الخالي من اليجر التي من
شأنيا تقميل اليجر في العممية الترنيعية وزيادة اإلنتاجية .تمت دراسة عممية ترنيع الجىانات بذكل تفريمي ساىم في تحجيج
مناطق اليجر ،وعميو فقج تم اختيار طخيقة "تنظيم منظقة العمل" و" تحدين وقت تغييخ إعجادات اآللة" حيث ساىمت الظخيقتان في
زيادة اإلنتاجية اليهمية ،وتم تقميل وقت التغييخ بندبة وصمت إلى .٪ 95إضافة إلى ذلك تم تظبيق طخيقة "تهحيج طخق التذغيل"
كإحجى أساليب الترنيع الخالى من اليجر ،وقج ساىم ذلك في تقميل ندبة الجفعات التذغيمية المخفهضة بندبة .٪ 95كما ساىمت
الظخق الحجيثة في التحكم ومخاقبة المخدون واإلنتاج في الحج من التهقف المفاجئ لمعممية الترنيعية بدبب نفاد المهاد الخام بذكل
كبيخ ،مما ساىم في زيادة إنتاجية المرنع ،وتحقيق أىجاف الهرقة العممية .إضافة إلى ذلك ،فقج تم تقميل تكمفة معالجة المخمفات
الرناعية الخظخة وغيخ الخظخة ،والناتجة من عمميات الترنيع ،بندبة بمغت ٪ 95و ٪ 59تهاليا ،وذلك عن طخيق تظبيق
أسمهب "تنظيم منظقة العمل".
كممات مفتاحية :ترنيع الظالء ،الترنيع الخالي من اليجر ،دقيقة واحجة لتبادل القهالب ،تقنية تنظيم مكان العمل ،تحدين وقت
تغييخ إعجادات اآللة.
74 Ahmed M. Badeeb et al.