You are on page 1of 20

An ISO 9001, ISO 14001 and OHSAS 18001

Certified Company

GAMMON
BULLETIN Volume : 9104 January - March 2013

G
A
M
M
O Inside

Tiroda Thermal Power Project

High Precision Fabrication Work


3

N
Paradigm Shift in Project Management 9

Prestigious CII Safety Award 13

News Flash from Projects 18

Company News 19
1 GAMMON BULLETIN
IMS POLICY Editorial
We are pleased to publish January-March 2013 issue of Gammon Bulletin.

Integrated Management
System Policy We take pleasure in presenting some of our recent significant achievements,
(Health, Safety, Environment & Quality Policy)
learnings, and events from across the country to our Gammon family, our
esteemed customers and other beloved stake holders.
Gammon is committed to create and deliver value
to all its stakeholders.

For us, compliance to applicable requirements is


only the beginning.
Gammon has just substantially completed major packages of civil works and
To ensure the well-being of all, we shall strive to
RCC Chimney for 3000 MW Tiroda Thermal Power Project. Being satisfied
achieve zero error.
with the performance of Gammon, M/s Adani Power Maharashtra Ltd. placed
To co-exist in harmony with nature, we shall help
sustain that balance. repeat orders for another two packages on Gammon. Concrete quantity of the
Our quest for excellence is addressed through
improvement and innovation.
order of 4,90,000 cum has already been poured for this project.
We take pride in being
'BUILDERS TO THE NATION'.
Another article titled ‘High Precision Fabrication work for Muthiara TPP at
Tuticorin’ highlights quality achievement of Gammon for this prestigious
Mumbai
2nd January, 2012
Abhijit Rajan
Chairman & Managing Director
project of M/s Coastal Energen Pvt. Ltd. High precision fabrication work of
nearly 25,000 t and painting and erection of the same has been successfully
GIL-ORGN-MGM-D-02A-02
completed in a record time with highest standards of quality and safety.

Theory of Constraints (TOC) and Critical Chain Management are buzz words
in today’s Project Management. Guest Article by K. Ramakrishna, Dr. Reddy’s
Corporate Sustainability Laboratory exhaustively covers this new concept in Project Management.
Policy Some of the learnings of their experiences are thought - provoking and eye
Gammon's commitment to Corporate Social
openers. Though construction companies are late in implementing the concept
Responsibility (CSR) means being accountable
for our actions to the broad range of stakeholders.
of Theory of Constraints and Critical Chain Management, it is never too late to
Gammon has long-established core values
introduce such new developments. This will need paradigm shift from hitherto
associated with health and safety, environment,
social and economic. prevailing practices of Project Management.
We recognize the importance of both financial
and non-financial performance in our efforts
to maintain long-term, sustainable performance for Gammon has been bestowed with the prestigious CII Award for exemplary
the Company.
HSE performance at its ISKON Temple Project in Kolkata. Gammon was winner
We put our policies into practice every day
as we manage our business to promote amidst the competition of several top class multi-national companies.
sustainable social, environmental and
economic benefits to all stakeholders wherever
Gammon operates.
In our quest to continue to improve the bulletin, we will be glad to receive
feedback and suggestions from our valued readers to make Gammon bulletin
Mumbai
Abhijit Rajan
2nd January, 2012
Chairman & Managing Director more and more interesting and informative for the readers.

Your feedback and suggestions may be sent to bulletin@gammonindia.com


GIL-ORGN-MGM-D-02D-01

SAFETY RECOGNITIONS

Jindal Civil Works, Bellary Malwa NDCT & Chimney Guwahati Water Supply Signature Bridge

For Private Circulation Only Cover Photo: Muthiara Thermal Power Plan Project, Tuticorin, Tamilnadu

GAMMON BULLETIN 2
Gammon’s Powerful Contribution in
Tiroda Thermal Power Project
Also included in the scope of Gammon challenging task due to acute shortage
is, construction of 275m tall Multi-Flue of space. With proper planning and
Pankaj Srivastava RCC Chimneys for Phase I, II and III. optimum utilization of space, we
Sr. Manager The civil works, included the foundation managed to accommodate our office,
for all the major complex structures like stores, quality lab, fabrication yard,
TG, Boiler Bunker and others, on which three batching plant, mechanical
1. Introduction the whole plant was to be built, and workshop, parking of 20 Transit Mixers
Promoted by Adani Power Maharashtra hence there was no room for delay or and other movable equipment like JCB,
Ltd (APML), a subsidiary of Adani Power errors. We ought to deliver a timely and Loaders, Hydra, Bar Bending & Cutting
Limited, the prestigious Tiroda Thermal quality product with required precision Yard, cement godown, stock and scrap
Power Project of 3300 MW consists of as entrusted upon us. yard etc.
three phases: Phase I–two units, Phase Shown below is the general layout
II–one unit and Phase III–two units plant and bird’s eye view of initial set
4. Execution
each of 660 MW. up developed by Gammon on fast- 4.1 RCC Chimney - This is one the largest
Amidst stiff competition, Gammon track basis: diameter Chimney in the country
was awarded prestigious packages for (59 m in diameter) wherein RCC raft
construction of Multi Flue RCC Chimney foundation involved concrete quantity
and Civil Works for Phase I and II of this of 13040 cum and reinforcement of
3 x 660 MW Power Project. 870 t. With meticulous macro and
Satisfied with the performance micro planning, the Chimney raft was
of Gammon, M/S Adani Power completed on fast-track basis - 20 days
Maharashtra Ltd placed repeat ahead of scheduled time.
orders for another two packages for
construction of Twin Flue Chimney,for
Phase III and Civil Works for Phase III
of 2 x 660 MW Tiroda Thermal Power
Plant. So far in this project, we have
lived up to the brand value of Gammon
and had delivered the goods to utmost
satisfaction of our esteemed customer.

2. Scope of Works Similarly for Twin Flue Chimney we


completed the foundation in scheduled
The scope of work includes construction time in spite of initial delay in handing
of Civil works, miscellaneous Structural 3. Site Mobilization over the work space.
Works and Architectural Works
involving Boiler, ESP, ESP Control Immediately on receipt of the first order The foundation diameter and shell
Building, Fans, ESP/VFD Room on 04th Nov 2008, Gammon swung into diameter of this Twin Flu chimney was
Foundations, PA & FD Foundations, action and started mobilizing various bigger than Multi Flue chimney to cater
Mill & Bunker Foundations, TG Raft resources including manpower, plant for better stability.
Foundations & Deck, MPH Building, and equipment etc. The excavation Since tall structures have its own
CCR Building, Main Power House work of Multi-Flue RCC Chimney was inherent safety hazards, it was
Floors, ARCW & Air Washer Building, commenced on 14th Nov 2008 i.e decided to go for additional safety
Cold Water System Civil Works, Water within 10 days of date of order. measures. Hence, the support of flue
Treatment Plant & PT Plant, Coal The overall plant is spreadover 1000 cans were modified at three places,
Handling Civil Works, Ash Handling acres of land. Various stretches covered were as the original design had it
Systems & AWRS Civil Works, Fuel Oil in our scope of works were distributed only at one place at 260 m. This has
System, Fire Detection & Protection, far apart from each other. Besides, led to redesigning of load girders at
Compressed Air System, Hydrogen because of constraint of space only a two other locations where additional
Generation Plant, Switch Yard 400 kV & small area to set up our site was made support was necessitated and
300 kV and miscellaneous Civil Works & available to us. To accommodate lay re-checking the overall design of
Finishing Works for phase I, II and III. down facilities, along with monsoon chimney was carried out. After
stock in the allocated area was a receiving the design, the Girders

3 GAMMON BULLETIN
were fabricated and erection was 2) Similarly when the segment of as to how concreting rate of TG raft
successfully completed by Jan 2011, Flue - 2 reached the top as fit-up and foundation and Bunker raft was
which was followed by flue can welding of erected segment with the continually improved:
erection. Considering the urgency of new one was in progress; sparks fell
client to light up the boiler, we took on the ground owing to which it was
up the challenging task of adopting not possible to carry out any single or
an innovative methodology of parallel activity inside the chimney for
simultaneous erection of two flues Flue - 3.
3) The above points were applicable
during the erection of Flue –3 as well.

The erection work of Flue - 2 and


The highlights of achievements include,
Flue- 3 was carried out during
monsoon; hence we could not achieve • Successful completion of
the desired progress as welding works 4.9 Lakh cum concrete out of
got interrupted frequently. Along with total 5.1 Lakh CuMtr in a record
erection of two flues simultaneously, time. This volume of work
we had also taken a challenge of needed engaging over 5000
erecting the staircase and elevator workers and over 300,000 m of
which turned out to be practically scaffolding pipes including cup
difficult as the work has to be stopped lock during the peak time.
in either activity during parallel • By adopting new methodologies
working. As a result of the above our and proper management of
planned activities got delayed. resources, it was possible to limit
However clients agreed for extended the concrete wastage to one
period of construction considering the percent (including wastage in
positive efforts from Gammon and also concrete pumppipeline) and that
due the fact that the reasons for delays of reinforcement to less than two
were beyond our control. percent.

6. Quality Assurance
5.2 Civil Works
which was being done for the first Quality is one of the important
time in India. We took a decision of This part of the project was on item
rate basis. There was an initial delay parameter to be monitored for
manufacturing an additional jack with successful completion of such
High torque, once again the first of regarding the issuance of the drawing
due to which we were not able to start voluminous construction works. As
its kind in India. Initially, we faced the Gammon has entered in to the private
problem of grips cutting the strands the work.
power sector works with this project, it
which hampered the work during first With enthusiasm and team work, we was necessary to win the confidence of
four lifting, but was streamlined later. were able to complete and handover, client.
Boiler Area Foundations, Boiler Area
The first thing done was preparation of
5. Challenging Erection Job Mill/Bunker Building, ESP/VFD Control
a detailed QA and QC plan. We believe
Room, MPH Building, CCR Building, TG
5.1 Multi Flue Chimney R.C.C. Shell Raft & Deck for Unit1, 2 & 3, ARCW & Air that involving QA & QC at every stage as
with Platform Washer Building, Service Building, CW an integrated robust approach help in
Two Rail Tracks & Trolley were laid System Civil Works, Water Treatment achieving desired standards of Quality.
which were though enough for erection Plant, Ash Water Pump House, Ash We also provided in-built checks and
of Flue-1 and Flue-2, there was always Slurry Pump House, Fire Detection balances to ensure effective day to day
a waiting time for Flue Can either in & Protection Building, Compressor controls.
Flue-2 or Flue-3. This was due to the Building, Tower Foundations & This was followed by formation of
fact that it was coming in the same Equipment Foundation of Switch Yard quality circles to continually improve
single rail line of erection due to fixed of 400 kV & 132 kV etc., by Dec 2011. quality, various other steps like
orientation of Flue - 1, 2 and 3. use of Cuplock scaffolds (in lieu of
1) When we took the combination of conventional staging pipes), providing
By using special Tubular Scaffold for centralized yard for reinforcement
Flue - 2 & Flue - 3, at the time of lifting TG deck instead of conventional Truss
of segment of Flue –2, we could not and formwork, carrying out post pour
structure, we were able to improve our analysis, collecting feedback of pour
carry out any ground work for Flue - 3 concrete rate from TG-1 to TG-3.
considering the constraint of space and analysis from similar structure also
safety issues. The chart given below gives an idea helped a lot in quality control.

GAMMON BULLETIN 4
7. Feedback 8. Safety needs different qualities in both the
leader and the followers.
Brainstorming discussions and Safety is something which, we strongly
feedback on problems faced and believe, is everybody’s responsibility.
remedies thereof was an integral To keep the morale and sprit of the 10. Achievements
part of our daily routine. Based on team high, it was very important Gammon’s work has been appreciated
such brainstorming sessions several to preventany accidents, though at by various visiting dignitaries and
creative and innovative techniques Tiroda project the possibilities of minor Gammon was conferred with various
were adopted on regular basis. Weekly and major accident were quite high. awards in recognition of its enviable
internal audits by quality circle, and To minimize this risk, we introduced achievements, including three National
review of audit reports also helped effective induction programs on Safety, Awards (Safety, Design & Construction
us constantly in maintaining and Health and Personnel skills. of Chimney, 5S).
delivering good quality services to our Following are some of the initiatives
clients. that helped us a lot in clocking several
We also involved experts from CQRA million safe man-hours:
and others for training of our Engineers • At regular intervals the safety
and supervisors. Under their expert induction programs were
guidance, implementation of checklist organized
and standardized formats was done
• PPEs were distributed to workers
for compliance of quality standards
and its application was diligently
in various activities like shuttering,
enforced
reinforcement, providing foundation
bolts etc. • Third party safety training by
inviting safety experts was
organized
• Daily tool box talk, daily mock
drills and in – house training were
conducted on a regular basis
• Various awards like Monthly
Safety Award, Quality Awards
Good Housekeeping Awards, and
Best Engineer Award were given
to keep the morale high
• Video Message collection from 11. Conclusion
families of labors and broad-
The works, for which drawings and
casting the same at Site, Safety
fronts were made available, have
Awareness programmes, creening
already been successfully completed
of Safety Movies and Safety
by Gammon. There are some civil works
Exhibitions etc. were all
conducted at site on a regular yet to execute, which will be completed
basis by 2013. Personally there were lots of
learning for us in this project including
9. Stores Management new methodology and different ways
of self-improvement. We take this
Store Management was another opportunity to thank our young and
challenge in this project, as the work energetic team at site without whose
sites were spread away from stores
support this success would not have
and different type of electrical and
been achieved.
mechanical materials were to be
used. A new method of white board We also thank Mr. Vineet Jain, CEO-
display was used to monitor the daily Adani Power, and Mr. O. P. Bhardwaj,
consumption and stock levels. Project Director-Tiroda for their
It was not just the planning and invaluable support which had
methodology alone, but it was the contributed immensely to our success.
Awards and penalties for deserving
supervisors and engineers on weekly strong leadership and our commitment We also thankour Executive Director
and monthly basis was a routine and that aided us to achieve this feat. Mr. A. B. Desai and Corporate Office for
presentation of awards in presence of their utter faith in us and giving us the
It is one thing to frame certain
distinguished dignitaries encouraged guidelines, but to make others to move confidence to walk the new roads in
others to improve their performance. on those lines is something which construction field.

5 GAMMON BULLETIN
High Precision Fabrication Work for Muthiara Thermal
Power Project at Tuticorin
• Five hydra cranes of 15 t capacity obtaining clearance firstly from GIL’s
for erection work internal quality team and secondly from
In addition to the above fleet of plant clients.
and equipment, two trailors of 13 m Only qualified welders as per ASME
and 7 m for transportation and erection section IX were used for all our structural
purpose were provided. works. About 500 welders were selected
V. S. Chacko after screening 700 plus welders. In order
Manager I 3. Fabrication to cover entire site requirements, ten
welding procedures were established.
The basic structural design was carried
1. Introduction SAW and SMAW machines were widely
out by TCE on behalf of clients. Based on
used to perform the procedures
Conceived by M/s Coastal Energen Pvt these basic designs, detailing and shop
(electrode grades vary from E 6013,
ltd, (a flagship Company of Coal & Oil drawings were prepared by Gammon
7018, 7018-1, S 708 L16 and S709 L16).
Group, Dubai), the prestigious 5200 MW and submitted to TCE for approval.
After completion of welding, ND tests
Muthiara Thermal Power Plant Project The grade of steel ranging from
were carried out. The volume of testing
started its first phase of 2x600 MW Unit IS 2062 Grade A, Grade B, Grade C and
involved was massive as shown below:
in Tuticorin, Tamilnadu in November IS 1239 & IS 1161 for pipe section was
2009. Amidst stiff competition, Gammon used. To ensure lamination free plate • DPT -13,700 Rmt
secured prestigious contracts for all the section, care was taken while making • MPT - 5800 Rmt
Civil work pertaining to Boiler, Turbine, Purchase Order of saw machines by • RT – 5300 Rmt
ESP and structural work of BTG including requesting UT passed sections. Most of
• UT – 2400 Rmt
Fabrication, design and construction of the materials are procured from Indian
275 m tall chimney. manufactures like SAIL and ESSAR
Though Gammon is well known in the through part of materials are imported
construction industry for its leadership from Ukraine and Korea. Plates were
and innovation in all types of projects, also tested and certified by our site
massive structural steel work of over established laboratory.
25,000 t (involving fabrication, painting
and erection) with high quality and
precision to be completed in a time-
bound schedule was a new challenge,
even for Gammon.
Fabrication Yard with Gantry Cranes
This article intends to provide an
overview of the challenges encountered Once the structure has passed required
during execution of work and a detailed quality tests, final inspection was carried
insight into the innovative approach out and all the welded joints were
adopted to successfully overcome these ground properly and forwarded to
challenges. SAW Machine for Built Up Column Welding painting yard.
The completed and approved structural
2. Mobilization of Resources membersare transported either by
As per the approved cutting plan,
Gammon mobilized four state-of-art materials are issued from store on a day- trolley over rail or by trailer to the
Gantry cranes of 35 t capacity on a rail to-day basis. Materials are issued only covered grit blasting unit.
track of 500 m length, apart from the after submitting approved cutting plan Blaster qualification is done with
following equipment in ample numbers: from Section in-charge for each plate various agencies according to Swedish
• 500 SMAW machines with respect to the size available in stock standard SIS-05 5900-1967 / ISO -8501-
to reduce the wastages and off cuts. The 1-1988 (surface preparation standard for
• Ten SAW machines
sizes of available off cuts for each plate painting steel surface).
• Eight GMAW machines thickness were updated every day in Prior to grit blast, identifications were
• 15 Hydra cranes with 15 t central store for proper usage at later marked on the surface of each structural
capacity in fabrication yard stage or redesigning the structures with member by punching. All welds were
• Two 250 t crawler crane respect to the available off cuts. be properly cleaned. Any burns spatters
• One 200 t crawler crane and one While edge preparation is done were removed. Grit size of 6 mm to
80 t wheel mounted crane based on the plate thickness/welding 1.6 mm is used for blasting purpose.
• One 75 t crawler crane requirement, welding is done after The coating provided included one

GAMMON BULLETIN 6
coat of High build organic Zinc silicate; when it came to the speed of welding
second coat of titanium dioxide/ process using SAW machines with
micaceous oxide epoxy, third coat with ‘W’ shape welding beds. To overcome
pigmented poly amide cured paint and
final coat of polyurethane pigment
finish with a total finish thickness of
250 microns.

4. Challenges
Such a massive high-precision
fabrication work obviously involved
several challenges, some of which are Double Track “W” Bed for SAW Machine
Erection of Roof Truss
briefly discussed below:
this limitation, two columns were
4.1 Wharfing/distortion of columns processed simultaneously using two
To ease transportation and erection, all SAW machines. The quality of weld and
the columns were fabricated in two or deposits were excellent and output was
three pieces. Due to high requirement far better than normal welding.
of weld deposit; the temperature was
increased in the heavy built up columns
4.5 Mass production Rolled section
which unfortunately resulted in the
beams & Bracings
wharfing of the column flanges. Since
any deformity in web or flange will
cause greater challenge during erection
at heights, they were corrected with the
help of a frame fitted with 500 t jack and
distraction was brought within stringent
permissible limit of 3 mm.
4.2 Chamber formation due to excess
heat Erection of Coal Bunker
To avoid the common problem of
chamber formation while cutting heavy
Jig for Mass Rolled Section Production
thickness plates, the other side was 6. Safety
heated and straightened before fit up To improve productivity in back to
and welding. back or box type welding in rolled The following initiatives were
4.3 Generation of off cuts in higher section members, screw fixed welding undertaken to ensure high safety
thickness plates jigs were preferred. This resulted in standards during execution:
When higher thickness plates are used high production and we were able to • All the fabrication and erection
as flange or web in columns, controlling produce perfect weld thick with a good process were carried out only after
the off cuts produced from 40 plus mm alignment. the approval of Hazard Identification
plates is a perennial issue. The problem Risk Analysis by the safety team
is accentuated by the fact that the 5. Erection • A 24 X 7 safety surveillance was
longitudinal joints were neither allowed To negate the challenges due to heavy ensured
nor viable in higher sized plates. weight structural columns and windy • Proper illumination was ensured
While preparing shop drawings for weather of coastal region, all major during night shift work
structures other than columns, our erection was taken up in the morning • A first aid room with the service of
structural engineers along with the session. We also ensured that sufficient
male nurse was made available at
design office explored the possibilities guyropes guide were provided, when
site in addition to a full time doctor
of redesigning the structures with off erecting an interconnecting bracing
provided by clients, on a 24 X 7 basis
cuts available based on daily updated to the adjacent structure. Butt welding
report of off cuts in stock. By doing so, of column flanges were completed the • All lifting tackles and equipment
it was possible to control the wastage same dayand it was made sure that fish were tested by external agency
and the quantity of off cuts was reduced plates provided in web was kept intact and SWL and color coding was
from 1700 t to 700 t. until the final welding was completed. provided accordingly
4.4 Welding of Built up columns using In addition all the Butt welding were • Mock up drills were conducted at
“W” shape bed Radiographic Tested and only tested regular interval. Training on usage
welders were allowed to perform the of PPE’s and fire extinguishers was
The variation in the column length
welding in the heights. arranged through external agencies
(from 30 m to 65 m) posed a challenge

7 GAMMON BULLETIN
• Tool box meetings helped a lot in 7. Conclusions inherent creativity and innovation-
improving safety performance and oriented mind set, it was possible to
Unlike executing civil works, high meet stringent quality standards by
were invariably carried out everyday
precision Fabrication works involve successfully overcoming all challenges
adopting different approaches which which are usually associated with such
• A short film on safety was demands meticulous initial planning. As massive fabrication and erection works.
premiered on every Sunday the work progresses, there is always a
evening in labour colony need to revisit the initial planning to suit The entire Gammon team is
the changing circumstances. in-debted to the team of Consultants
followed by a commercial film to
and Clients, as without their active
achieve dual objectives of Maintaining stringent standards during involvement, professional approach and
increasing the safety awareness fabrication and erection work is yet positive support it would not have been
and entertainment another challenge. With Gammon team’s possible to achieve this success.

BRICK AND MORTAR OF PLACEMENT Phamplets


BY HR! Circulated by
Where to place a new employee is new employees were left alone Patna Water
always a challenge. for eight hours. HR Head returned
after eight hours to analyze the
Supply Project
HR found a creative way out.
They accommodated all new situation. Team
employees in one closed room Based on the analysis of the
and provided 500 bricks to them. situation, HR framed seventeen
The doors were closed and the rules for placement as follows:-
Rule If…………. Placement
No.
1 If they are counting the bricks,            put them in  Accounts Department
2 If they are recounting the bricks which have put them in Audit Department
already been counted and tallied earlier,
3 If they are rearranging the bricks in some strange put them in Planning Department
order,
4 If they are debating and arguing on shape, size put them in Engineering
and strength of  brick, Department
5 If they have already left for the day, put them in Marketing Department
6 If they say they have tried different put them in Tendering Department
combinations, they are looking for more and yet
not a brick has been moved successfully,
7 If they are found cannibalizing bricks, put them in Plant Department
8 If they are trying to prove rejected bricks as put them in Purchase Department
good,
9 If they have broken the bricks into pieces, put them in IT Department
10 If they are unduly restricting height of stacks of put them in Safety Department
bricks,
11 If they have messed up the house-keeping of put them in Administration 
whole place with the bricks, Department
12 If they are found sleeping, put them in Security Department
13 If they are sitting idle doing nothing, put them in HR Department
14 If they are staring out of the window, put them in Strategic
Planning Department
15 If they are throwing the bricks at  others, put them in Operations
16 If they are not parting with the bricks but put them in Finance Department
keeping bricks close to their chest,
17 If they are not talking to each other and trying to put them in Top Management
topple each other, congratulate them and

GAMMON BULLETIN 8
GUEST ARTICLE
Paradigm Shift in the way we
manage Projects
K Ramakrishna teams are flooded with work. But there 1. IDENTIFY the system’s constraint
Dr. Reddy’s was no formal priority list available for according to their importance on
Laboratory all the functions. Focus is shifted from the goal
resolving the issues of current project to 2. Decide how to EXPLOIT (make
Introduction starting a new activity in another project the most out of ) the constraint
as there are plenty of the projects to Make sure to use the constraint to
In this paper, I present a different work on. Bad multi tasking pushed the maximum extent possible
approach for managing projects the local priorities for each function 3. SUBORDINATE everything to the
in multi project environment. The and negatively influenced the overall above decision
implementation is done in one of the progress of the projects. All the other resources of the
top five pharmaceutical companies in system should be managed in
India for managing the new product In the rush to start working on the
project as early as possible, the such a way that they should
development process (NPD). Company supply all that is needed for the
has acknowledged Project Management preparations are often ignored and
there are instances of slowing down constraint of the system
as a significant competitive edge and 4. ELEVATE the system’s constraint
defined the organization structure for after the project is introduced into
development. Missing preparations Find / invest in additional capacity
managing projects much earlier than or alternatives
others. Tools and techniques are in prolonged the lead time of the projects
and effected the synchronization. 5. If at any time in a previous step
place for creating the project plans and a constraint has been broken
tracking the projects. Development Over years, Company has realized that
go back to Step 1 and “do not allow
process is mapped out, Phase gates the results are far less than the targets
INERTIA to become the constraint”
are defined and Project templates are set. Throughput is not consistent,
delivery is not reliable and the cycle Implementing these five steps will help
prepared with the micro level activities.
times were still high. There is huge any organization to be in a process of
Enterprise Project Management system
dissent in the overall system and the ongoing improvement, where change
is rolled out for tracking the status of
resources are stressed out due to crisis is not an exception but rather as norm.
the Projects. Ambitious targets were
mode of management. Where change is on-going, we must be
set for cycle time and throughput and
much more methodical in our approach
the teams started the journey very Project Managers are stressed with to the improvement process itself;
positively. frequent changes in prioritization of the otherwise it is just a matter of time until
Many new product ideas are pushed to projects. we give up and the organization will
development teams and the teams are This is the time, companyis introduced once again stagnate. The methodology
encouraged to start the work as soon as to CCPM [1] world, a new way to address to bring any change or improvement in
possible. Development teams started to the challenges we were facing. With a TOC way lies in answering in following
work on all the opportunities indicated the help of CCPM concepts, we could three questions,
by business as soon as possible in order analyse the root cause of the challenges
to not to miss out any opportunity. we faced and implemented appropriate 3 Questions
We believed that by starting the project solution to each of them.
1. What to change? (Pinpoint the
as early as possible, we can deliver CCPM is an application of TOC [2] core problems)
the project on time and we will have principles in Project Management. 2. What to change to? (Construct
sufficient time to handle the issues of simple, practical solutions)
the projects during the development. Theory of Constraints (TOC) 3. How to cause the change? (Induce
This belief has pushed many projects in the appropriate people to invent
Every system was built for a purpose
development pipeline. and implement such change)
and has a goal. A system’s constraint
When too many projects are executed is anything that limits a system from CCPM solution has been detailed using
simultaneously many resources found achieving a higher level of performance the reference of these three questions
themselves under pressure to work on versus its goal. Core problems in managing the
more than one activityat a time. Also,
To improve any system, the following projects (What to change?)
there was frequent need to prioritize
five steps of focusing are used.
the work between the projects as the
About the author
Mr. K. Ramakrishna has expertise in implementating the Project Management process and has been responsible for implementing the best practices in Project
Management across Dr Reddy’s. He managed roll-out of Project Management Tools namely Microsoft Enterprise Project Management (EPM), SAP Project Systems, SAP
Projects and Concerto. He leverages the experience of Software development in quickly rolling of the tools. He handholds Delivery Heads in setting up metrics, design the
organization structure and set up the governance mechanism. His experience helped Dr Reddy’s to smooth rollout CCPM initiative in Dr Reddy’s. He is a certified Project
Management Professional from PMI, USA.

9 GAMMON BULLETIN
Safety in Task estimates it in the end when it is too late and start Many people believe that multi-tasking
working in crisis mode. is an important skill which helps us to
It is very common to believe that the
Since most of the safety is hidden in do better and better. In multi Project
key to on-time delivery of a project
the task duration, nobody knows how it environment multi-tasking is counter-
is to complete each task on-time and
gets wasted. productive.
make people accountable for each
task by turning each task estimate Resource assigned with multiple tasks
into commitment. When people are Parkinson’s Law switches in between the projects
evaluated based on the on-time task The Parkinson’s Law states that “The frequently due to lack of formal priorities
completion, they tend to put some work expands to fill (and often exceed) and push by the Project Manager. As a
amount of safety in the task estimates the available time”. result, the work on each task stopped
so that they can cover up for the lost frequently and work on another task is
time due to uncertainty. started. It takes some time to prepare
for the new task and the resource again
What is the level of safety built-in in our
switches to another task before the
task estimates? The typical answers will
earlier task is complete. In a rush to show
vary from 50% to 100%. This is never
the progress and satisfy every one, each
explicitly mentioned any time. Also
project completion is prolonged much
safety increases with experience and
more than expected.
number of reviewers of the project plan.
Figure 1 shows typical variability in In projects, there are several Murphy’s Law
task execution and its impact on our dependencies in between tasks. A delay
estimates. in one task is passed, in full, to the next The Murphy’s Law states that “If anything
task. However, an advance made in one can go wrong, it will”. For instance, If you
Though the median time is around 50%, perceive that there are four possible
we generally quote around 90%. So, we task is usually wasted. Strangely, there is
little or no incentive to finish ahead of ways in which something can go wrong,
take care of this variability by padding and circumvent these, then a fifth way,
each task estimate with safety. time.
unprepared for, will promptly hit. So
Here we need to understand that If you finish a task earlier than planned,
task safety gets wasted when Murphy
estimate is an estimate. It is a range of you might be accused of sandbagging
strikes.
possibilities. Though every project is your estimates instead of being
rewarded for completing ahead of
different, two things are common in all Summary of why and how task
the projects – Uncertainty and Variation. schedule. Your future estimates are cut
safeties are wasted
The degree may vary from project to based upon history.
project, time to time, but uncertainty Even if you finish your task early, the next We try to protect the performance of
and variations are always there. task may not be ready for an early start each task. Most of this protection is
as the start is date driven. Further, you wasted. Despite so much of safety, the
are not liked by your colleagues who are project as a whole is exposed. Perhaps,
struggling to meet their due dates. putting Safety at task level may not be
a good idea.
Under the circumstances, people tend
to review their tasks again and again or The only thing that counts is the
keep polishing them or waste their time performance of the project as a whole.
rather than reporting early finish. We don’t have to win all the battles,
as long as we win the war! Similarly, it
Dependencies doesn’t matter how many tasks are not
Figure 1 completed on time…as long as the
In projects, we also have parallel project is delivered as per the due date.
While estimating we do account for dependencies and tasks integration
this and most of the time it is implicit. points. In the case of parallel steps, the We either need a crystal ball which will
Typically our worst experience drives biggest delay is passed on to the next take us ahead in time to see what is
the padding of task estimates. step. All other early finishes do not going to happen so that we know where
However, the safety embedded in the count at all. the safety will be needed. We need to
task is seldom used. Let’s understand find a better way to manage the safety.
why? Bad Multi Tasking
Solution to the Core Problem
Student Syndrome (What to change to?)

It is human nature to delay the start of CCPM provided the solution for
the task at hand, especially when there managing projects in TOC way.
is safety embedded in it. The solution lies in answering the
When the work is actually started and if following questions:
there is a problem, we become aware of – How to reduce bad multi tasking?

GAMMON BULLETIN 10
– How to prepare a project before it will lead to distorted picture. As a result, either the task will start late
release into execution? 2 If we ask the people estimations or it will lead to bad multi tasking as
– How to use the safety better against for task durations, then we will the same resource (Y) needs to work on
uncertainty? get wrong impression that there both the activities (T2 and T5).
– How to manage safety during is no safety in each task. TOC introduces critical chain to address
execution? Each task estimate is cut into half. After the issue of resource dependencies.
cutting the task duration, task estimates Critical chain is identified based on the
Reducing Bad Multi Tasking at are made aggressive but possible. longest path as well as the resource
Organization level dependencies as shown in Figure 5
Tasks with no variation in the duration
List of all the projects released for during execution should be mapped as
development is prepared and projects Fixed Lead time task (example: Curing
are prioritized. Around 25% of the of a slab). Task estimates are not cut for
Projects in the bottom of the list are these tasks.
frozen. List of open projects and frozen Review the tasks where there is no
projects are circulated formally by the possibility of completing within the Figure 5
Top Management. The work is formally duration after 50% cut (ex: done by Critical chain identified is T1 – T5 – T2 –
stopped on the frozen projects and external agencies and driven by SLA T3 – T4
resources from frozen projects are and contracts). Task estimates are cut
moved to work on the open projects. Now we understand that the Critical
by 25% for these tasks to make them Chain determines the length of the
This step has significantly reduced bad aggressive but possible.
multi tasking and increased the pace of project and it is the constraint.
Since it is essential to complete each If Critical Chain is the constraint, how do
execution on open projects.
project on-time, we need to have safety we exploit it? We need to make it sure
A frozen project will be released only at project level. But the safety required
after completing an existing project. A that the Critical Chain is always focused
for a project is not equivalent to sum of on. The tasks on Critical Chain should
new project will be released based on the safeties cut from each task.
completion of all the frozen projects. receive the highest level of priority.
Now the safety will not be wasted, gains However, this is not enough.
Priority is assigned to frozen projects as
will be transferred; delays and gains will In order to ensure that the variability
well new projects.
compensate each other. Thus we don’t of the tasks not to delay the Critical
need all the safety that was embedded
Ensuring Preparations Chain, we must protect it with safety by
in each task. building safety (time buffer) between
A team of project managers and Vast experience shows 50% of the the Critical Chain and the Project
function experts has identified the list of aggregated safety taken from each task delivery date. This buffer is created
preparations (Full Kit) required to ensure is good enough to protect the overall by cutting the task estimates into half
smooth execution. A team of experts are project. (Figure 6) and moving the safety to end
dedicated for doing the Full Kit before
of the Project (CCCB / Project Buffer as
projects arereleased to development. Important: This mechanism works shown in Figure 7).
The activities which should be titled only if the task estimates are not During the critical chain identification,
as preparations are officially defined measured as commitment. tasks are scheduled As Late as Possible
(Strategy, Licenses and Materials etc).
Example: A simple project with 6 tasks is instead of As early as Possible. This will
A Project is rarely released in execution mentioned in Figure 4 ensure to start the paths (chains) start
without complete full kit. as late as possible to avoid bad multi
There are two paths (chains) in this
tasking.
Safety at right place project.
Path 1: T1 – T2 – T3 – T4
It is not important to complete each task
on time, it is essential to complete each Path 2: T5 – T6
project on-time. Trying to complete Path 1 is the longest path in these
each task on time will lead to increase two paths and is popularly known as
in task safeties and there by significantly critical path. However, it does not take
prolongs the overall cycle time of resource dependencies into account.
project. Y is the resource need to work on T1, T2
To protect the completion date of entire and T5.
project, we should shift the safety
embedded in each task to the end of
the project. Figure 6
How do we identify how much safety is However we need to protect the chains
embedded in the task? (non critical paths) feeding into the
1 If we do some statistical analysis, critical chain. Hence buffers are placed
Figure 4

11 GAMMON BULLETIN
at the end of the feeding chains (T5 – the projects in Zones (Red, Yellow Figure 12
T6) as shown in Figure 8. and Green) Task Manager updates the remaining
– Provide the visibility of duration of in progress tasks every
penetrating tasks into buffers day and ask for help if the task is not
– Display the trend chart with progressing.
respect to Buffer Consumption
Task Manager should follow the concept
and Chain completion (daily/
of relay run i.e. task once made In
weekly/monthly)
Progress should be finished as early as
– Determine the Projected (Latest
possible.
Estimate) date of project
completion For each incoming task, the task manager
– List tasks in the order of priority ensures the necessary conditions to start
– List Tasks that are not progressing the task are in place: strategy, approvals,
Figure 7
/ need help designs, (uninterrupted) resources etc.
– List Tasks that are not started
though they are ready to start Project Manager
Project Manager review daily the list
of tasks penetrating the most into the
project buffer and ensure the recovery
Figure 8 actions required to ensure effective
progress of the project.
Key differences between traditional
planning and CCPM are shown below in
Figure 9.

Figure 10

Trend Chart Project manager verify the preparations


required for the upcoming tasks and
identify the bottlenecks in doing the
preparations / executing the tasks.
Figure 9
Roll out of a new Project Management Delivery Head
system based on CCPM methodology Delivery head reviews the recovery
(Concerto) has been rolled up. It help action’s progress for the Red projects or
in creating the Plans, track the status projects with deteriorating trend.
of buffers of each project, health of
Delivery head resolves the issues that
portfolio of projects. Figure 11
are escalated by Project Manager.
Execution Task Management Delivery heads takes actions to resolve
the portfolio level bottlenecks and
Once the Critical Chain is identified and Task List Screen in Concerto shows the prioritizes the projects based on the
buffers are inserted for each project, it tasks priority wise, tasks ready to start, buffer consumption.
is important to set up a mechanism to tasks need to be prepared.
track the buffer status of each project Delivery Head makes sure that the WIP
Daily update of the task is done in is maintained as defined and ensures
and health of each portfolio. less than Ten minutes. Task need to be the release control.
Buffer Management is a server task, updated every day (Remaining duration
scheduled to run every day to calculate How to cause the change? (Induce
for IP Tasks, comments and help
the impact of the task updates on the the appropriate people to invent and
needed).
crtical chain completion and buffer implement such change)
Role of the key stakeholders are defined
consumptions of each project. It stores The solution has been detailed out
and mentioned below:
the information of Buffer consumption using Strategy & Tactic Tree (S&T Tree).
and Chain completion of each project Task Manager It demonstrated a plan for successfully
every day. This enables concerto to Every day the task manager gets two implementing the strategy, what
– Determine the status of Critical lists of tasks: The list of tasks currently actions must be taken, by whom and
Chain & Buffers for all the projects being executed and the list of tasks that when. Resistance to change can block
– Determine the health of the are incoming, both sorted according to even the most perfectly laid strategies
portfolio status and categorizes their up-to-date priorities. and plans and hence building active

GAMMON BULLETIN 12
consensus and collaboration, or buy-in
is crucial. Winning The Prestigious
After going through the workshops
using S&T Tree, Top Management has CII Award -The Gammon Way!
agreed to the solution and formed a - By Corporate Safety & Subhankar Sil
team to roll out the process. CEO of the
company has personally reviewed the We take immense pleasure in announcing light to show the Vedic Cultural values on
progress periodically. that the ISKCON Project, one of the completion of the temple construction
esteemed Projects of Gammon India Ltd. and on its inauguration.
A glimpse of S&T Tree methodology has is being bestowed with the prestigious In order to meet the quality criteria of
been given below award from CII for the eastern sector building the temple to age at least 500
on 30th of March 2013 most likely by years, Stainless Steel Reinforcement
the honourable Chief Minister of West has been used in Sub-Structure which
Bengal. The award was secured after consistsof 2300 nos. in Cast Situ Piles. Cast
a corporate safety presentation on in Situ Superstructure up to 50 m from GL
the safety management practices of (Ground level) had been completed so far
Gammon at ISKCON. The presentation and the erection of Stainless Steel Dome
was made by Mr. Prakash Tikare, VP structure over the Superstructure had
(HSE & Systems), Gammon HO, along commenced.
Each node in the S&T Tree is a proposed with the Project authorities (PM and
As the new Temple is being constructed
change that answer the following Safety in charge). Participation in the CII
adjacent to an existing Temple of ISKCON
HSE award was an ambitious decision
Mayapur, a renowned tourist spot of
- thanks to Mr. Prasanth Pilanku (CMS)
Necessary Why the change is needed?
West Bengal, extra efforts were in place
Assumption and Mr.Subhankar Sil (PM), who had faith
to ensure highest Safety standards.
Strategy What is the specific measurable objective and confidence in their team’s ability to
of the change?
deliver. We all know that Mr.Subhankar Earlier, an honest, vigil, dedicated and
Parallel Why do we claim the Strategy is possible
and his safety colleague Mr. Abdus Sattar smart work in ensuring 3.5 million safe
Assumption and what specific requirements, potential
negative branches or obstacles must be have gotsimialr recognition from NSC in man-hourspaid off as we secured NSC
considered when selecting the tactic for
their earlier project at Kadappa as well as award of “Prashansa Patra-2011” for
achieving the Strategy?
ISKCON Project. ISKCON Site. Hence, the inspired and
Tactic How to achieve the objective of the
change ex: what changes should be made motivated site team with strong support
The application requirement for CII was
to processes, policy or measurement? from corporate safetyteam took up the
not an easy one. It focused not only
Sufficiency This assumption is not always the part challenge in competing CII ER Safety
Assumption of S&T Tree. The sufficiency assumption on safety practices, but on overall HSE
tells us what we must pay attention to, award, along with top class multi-national
management. The implementation of
otherwise we would fail to achieve the manufacturing units like ITC, TISCO, Telco,
strategy and its related tactic IMS (Integrated Management System)
Tinplate, Tata Sponge Iron, Tata Power,
for over the last two years had directly
Tata Metaliks, Tata Cummins, Coca Cola,
or indirectly touched on all components
CCPM has been formally recognized Exide, Balco etc.
of HSE. The Corporate Safety and IMS
as the operating system of managing team are very confident that today,
product development projects. many of Gammon sites are in a position
A dedicated team is created to today, to present their case in all these
implement the solution and handholder areas with some degree of maturity.
all the stakeholders. We also considered reviewing our
various initiatives in safety and IMS
Results obtained implementations by independent
The cycle times are reduced by 30% experts in these fields to benchmark
ourselves with respect to the ‘Best in
and the Due Date Performance (DDP)
Class’ Multinational Organisations. This
is improved from 25% to 75% [3]. It Gammon India Limited is listed on the
recognition re-affirms that our safety
is easy to get the initial results with web-site of CII ER safety (http://www.
and IMS implementation is in fact in the
CCPM approach, the real challenge is to ciiersafety.com) as one of the SHE Award
right direction, and can be sustained
sustain the culture and results despite winner.
with continued support from the
change in portfolio, changes in key management at HO and at the sites. Following are some of the insights from
stakeholders. This company has been the presentation made to the jury on the
successful in implementing the CCPM ISKCON Temple project on completion
will be the largest Hindu Temple in the challenges faced by of the construction
culture and procedures and in the sector, and Gammon’s approach to Safety
world with a height of 108 m and a Floor
process of ongoing improvement. Management:
area measuring nearly to 60,000 Sqm.
References The temple have unique Architectural n Construction sector being the second
1. Dr Eli goldratt, “Critical Chain”, North River Press
features with a ‘Dome’ of 54 m Diameter, largest Labour intensive, unorganised
2. Dr Eli goldratt, “What is this thing called Theory of
Constraints”, North River Press Chatris, Arches for using sophisticated work sector with illiterate labours,
3. http://videos.realization.com/results/default.aspx technique with the help of laser and language barriers and cultural differences

13 GAMMON BULLETIN
incurs second highest number of fatalities of socially responsible practices such as women at sites, the commitment of our
in India, next only to Road Accidents. “no smoking-no alcohol-no drugs”, HIV- leadership and care given to the impact
Aids policy etc. on environment. All of the above were
nThe safety management structure is well
satisfactorily addressed in our response
(Courtesy NPCIL Safety Presentation to
established with dual reporting method, to the jury.
AERB)
continual contact and communication We take pride in sharing the above
nThe fatal accident rates incon-struction
between Corporate Office, Regions and summary to all those concerned and
works among advanced countries like
the Project Sites with a good monitoring interested to promote safety as an
system. integral part of our main job. We are
nSafety management practices confident that with support of everyone
were further strengthened through we will surely achieve new heights in
competency mapping and appropriate days to come.
matrices for structuring the safety
function.
nTool Box talks, 3Q meetings,
E learning etc.,played an important role
in improving safe work practices among
Gammon Sites.
nOne of the innovative methods used for

safety education and implementation at


all Projects, including ISKCON was the
exclusive use of the “Gammon intranet”.
The site allowed sharing of important
and innovative informations from other
Other achievements of Gammon India
Projects.It also hosts a 3 D animation film
Limited include:
on accident model of fall of material from
a high structure, exclusively developed n JSW Civil Works - 20 Million Safe
by HO safety team. Man hours - from JSW Steel limited
France and South Korea ranges from 0.17 n Malwa NDCT & Chimney - 7.5
to 0.35. Whereas, the figures pertaining Million Accident Free Man hours –
to Japan and USA are 0.18 and 0.19 from L & T
respectively and countries like Brazil and
n Munger Bridge - 6.2 Million Accident
Argentina has figures on the high side,
Free Man hours–from East central
0.43 and 0.49 respectively.
railway (Construction Department)
n It is heartening to note that Gammon’s n MBPT–Prashansa Patra Award from
figure stood at 0.29 comparable with National Safety Council Awards 2011
developed countries.
n ISKON - Prashansa Patra Award from
nUnfortunately, there are no figures
National Safety Council Awards 2011
readily available for Indian Construction
Industries to benchmark but figures Krishnapatnam - Prashansa Patra
n

estimated from the Insurance payment Award from National Safety Council
on fatal accidents and the Workmen’s n Legal compliance and tracking tool Awards 2011
compensation paid, point towards a high was another strong measure adopted n Lapanga - 1.5 Million Safe Man

value of 15.8. to ensure that all the statutory and legal hours & Chimney 1 & 2 RCC Shell
nGammon’s approach to Safety requirements were fully met. Project completion–from HINDALCO, Aditya
management on the “five pillar” model sites were encouraged to go beyond the Aluminium Project
for performance excellence had paved minimum requirements postulated by n Signature Bridge - 05 Million

the way for continual improvement in all the statues, to develop a strong safety Accident Free Man hours – from
the areas of ‘Safety Management’. We are culture. DTTDC
proud to claim that some of Gammon’s nThe presentation made was not limited
n JSW Civil Works, Malva NDCT and

Projects have achieved greater better to ISKCON butfeatured work from other Chimney, Guwahati Water Supply
maturity in its implementation. project sites as well, thus portraying the Project and Signature Bridge -
nThe foundation for a proactive functioning of HSE system in Gammon. received safety achievement
safety management and safe working The learned jury was highly impressed certificate from CMD Gammon India
practices were strongly laid by the top and was appreciative of Gammon’swork. Ltd. for achieving 20 Million Safe
management of Gammon in its “Vision, The first comment from the jury after Man hours, 7.5 Million, 6.25 Million
Mission and Policy statements”. It also the presentation summed it well and 5 Million safe man hours
promotes other social good habits -‘’Outstanding!! We have no questions”. respectively
and practices appropriately stressing However, they made some queries on
awareness measures on various faculties our practices pertaining to employing

GAMMON BULLETIN 14
WORKS IN PROGRESS

275 m Tall - Chimney at GMR - Raipur 275 m Tall - Chimney at Raigarh 155 m Tall - NDCT at JSPL, Raigarh

30,000 Cum / hr capacity - IDCT, Vallur Sea Water Intake, Kalpakkam

Building works, IGCAR - Kalpakkam Cooling Towers at JSPL, Raigarh

15 GAMMON BULLETIN
SERIOUSLY , LAUGHTER IS THE BEST MEDICINE
Humorous Side of Human Resource Management in Construction Companies - M. U. Shah

Implementing modern concepts of HR in “For marriage, Sir.” OVER WORKING


a Construction Company has always been “Because of criticality of my job, if I can’t One Project Manager’s wife was requesting
a big challenge. When an attempt is made take leave I depute someone else from my Project Manager to accompany her for a visit
to introduce such modern HR concepts in family for marriage.” to gynecologist but busy and overworked
Construction Company, though we may “But Sir, this is not possible.” Project Manager could not accompany her.
not be sure whether the introduction will Fed up, she went alone. When gynec gave
be successful or not; but, for sure, it leads to “What do you mean not possible?” the Boss her good news, overjoyed, the wife picked
creation, at times unknowingly, of roaring yelled, increasing his decibels. up phone and said to her husband, “Do you
hilarious situations. Presented below, “Sir, I need leave for my own marriage.” know what you have done? You made me
ofcourse with due respects to whole of HR “I had taken only three days leave for my pregnant!”
fraternity, few HR functions together with marriage.” Puzzled, the Project Manager asked, “Who is
corresponding humour associated with “Yes, Sir; for marriage I need only three days. speaking, please?”
these HR functions: Balance twelve days for my honeymoon.”
INTERVIEW “In my thirty five years glorious service, I PROMOTION
One Civil Engineer candidate, while filling up have never taken leave for such purpose!!” Becoming a Project Manager is the biggest
printed application form of a Construction “But, Sir ….” dream for any Civil Engineer. One Civil
Company, prior to interview, came across
The Boss ordered, “You take three days Engineer was nurturing this dream for
column: “Do you have any other source of
leave, finish your marriage nicely and report a long and was also sharing this dream
income?” Initially he thought of writing,
back to site so that we can achieve current with his wife. But, as usual, the promotion
“What business you have with my other
month’s targets. As regards honeymoon, was not forthcoming. However one fine
source of income?” But on second thought,
you can always have at site.” morning he received an email from HR
and more appropriately, wrote, “If I had
“Honeymoon at site?” site Engineer yelled confirming his promotion as a Project
other source of income, I would not have
trying in vain to control decibels. Manager. Overwhelmed with joy, he picked
applied for this Construction Company!”
up the phone and to give surprise to his
and when such answers appeared “Yes, Why not?” wife, he changed his voice and asked his
repeatedly, the Construction Company had
“Thank you, Sir. I don’t want even three days wife, “Would you like to become a wife of
to take a decision to delete this column
leave.” a Project Manager? “ But was shocked when
from the printed form.
“Why?” the Boss asked. his wife (who was frustrated by abnormal
Another Civil Engineer candidate, in reply to delay in promotion) replied, “May I know
an opening question by the interview panel, “Sir, I have decided not to marry. In fact
your name and address, please?”
“Can you give your family background?”; I would advise even my children not to
replied, “ After divorce of my parents, I was marry!!!”
staying with my father who brought me up. SEMINAR OUTING
My mother has obtained divorce after her SURGICAL OPERATIONS One HR guy who newly joined a
second marriage and now experimenting Construction Company gave a presentation
Extremely perturbed by frequent leave
live in relationships. My elder sister to the top Management that if we send
applications on the ground of surgical
separated within a year of her marriage and key employees like Project Managers for
operations, HR sent a Circular, “Operations
staying with us, though not yet divorced. an outing with their wives, it improves
are now completely banned. As long as you
My elder real brother is presently under organizational productivity. Impressed, the
are an employee with the organization, we
judicial custody. My younger half-brother top Management readily agreed though
need all your organs and in their original
has been rusticated from college.” they had their own apprehensions about
form. You should not consider removing
Interviewer remarked, “Whole family its success. HR implemented this idea and
anything or modifying anything. We hired
appears to be negative. Is there any positive organized a Seminar in a beautiful resort
you intact. While in service you need to
person in your family?” at a hill station for a week between 12th to
remain intact. To have something removed
19th March.
The Civil Engineer replied, “Yes, Sir; I am or modified constitutes a breach of
positive person in the family.” employment contract!” In the lounge of the Resort, one Project
Manager purchased some goods for himself
The interviewer happily remarked, “Good to
and came to cash counter. The shop owner,
hear that” and further asked, “What are your LEAVE TRAVEL ALLOWANCE looking at the accompanying lady, asked
positive attributes?”
There were lots of grievances about amount the Project Manager, “Anything for your
The Civil Engineer replied, “Sir, I am HIV of Leave Travel Allowance (LTA) being grossly wife, Sir?” The Project Manager asked, “Can
positive!!!” insufficient and many representations were I get a post-card?”
LEAVE made to HR for increasing the same but, For an immediate first-hand feedback
One Site Engineer phoned his Boss in H.O.; as usual, HR was adamant and refused to directly from wives, on 22nd March, HR
“Sir, I need fifteen days leave.” increase LTA. wrote to wife of each Project Manager as
“Leave? And that too fifteen days?” the Boss Frustrated, one Project Manager wrote to to how was the Seminar outing and mailed
yelled. HR: this letter to residence address.
“Yes, Sir” “Two years back I went on LTA to Simla and As many as 80 % of wives replied, “What
my wife became pregnant. Last year I went Seminar?!!!”
“This is the most critical period of your job.”
on LTA to Mount Abu and again my wife After the Seminar, one Project Manager
“Yes, Sir, But….” became pregnant. This year, Sir, I want to said to his close friend; “One letter from HR
“What for you need leave?” take my wife along with me!!!” changed my whole life. Earlier I was buying

GAMMON BULLETIN 16
imitation jewelry for my wife. After that FAMILY BONDING AND reaching home from Seminar venue,
letter I am buying diamond jewelry.” COMMUNICATION implemented this prescription. Shocked,
His innocent friend presumed that it must HR believed that family bonding his wife yelled and called their son, “Chhotu,
be a promotion letter or increment letter and communication with family is come here, call some doctor. Your dad has
from HR which improved his standard of very important and has a bearing on gone mad!!! ”
living and carried that impression for long organizational productivity and accordingly As a follow-up activity post the Seminar,
until he came across an interesting Cash invited an expert faculty to conduct a HR decided to conduct a survey asking all
Scroll book cum personal diary of Project Seminar. Project Managers, “Do you talk to your wife
Manager reading: The faculty asked each participant, “When when you make love?”
was the last time you said ‘I LOVE YOU’? “ As many as 80% replied, “Yah, I do talk, if
Period Date Value Purpose The faculty, though was a veteran in this mobile network is available!”
1st
Rs. 250 Dress for wife
field, as far as Construction Company Again this was the case of a poor framing
March is concerned, he was conducting such of question, which, like expert Seminar
6th Imitation jewelry for Seminar for the first time. The replies faculty, HR also realized subsequently.
Rs. 500
Pre- March wife received from the participants were
Seminar something which were not anticipated
10th
March
Rs. 5,750 Cosmetics for wife
by him nor something which can be No Entry !!!! - M. U. SHAH
11th Gent’s parlour discussed in a Seminar environment and
Rs. 12,500
March expenses for self hence immediately he admitted his mistake Recently when CMD show me in the back seat of
12 -19th Gift purchases during saying, “I am sorry. It is my mistake. I did not my car, he asked me, “You don’t drive car?”
Rs. 47,500
March seminar frame the question properly.” and reframed I replied,” No, Sir, I don’t”
Seminar
12 -19th the question: “When was the last time you He asked, “Why?”
Priceless Seminar experience
March said ‘I LOVE YOU’ to your wife?” I replied,“Earlier I was driving but because of one
incident, I left driving.”
24th Unqua- Receipt of letter from The replies ranged ‘from couple of years to
“Any accident?”
March ntifiable HR at residence. decade’ which surprised the faculty.
I said,” No, no, not accident, Sir” and I narrated
Orthopedic Doctor’s The faculty highlighted the need to express this incident.
bill for self (subject to
24th and reaffirm love every day or even several Once I was driving a car near a college in Kandivli.
Rs. 37,000 recovery, if any, from
Post- March
Group Mediclaim
times a day and being vocal about it I saw a brand new Audi car was behind my car.
Seminar
policy) rather than taking it for granted. He gave a This Audi car followed me for quite some time.
Diamond studded
prescription to reaffirm love on daily basis I saw from rear view mirror of my car that a
young gorgeous beautiful college girl, in her sweet
31st Rs. necklace with 24 carat or even more frequently and gave some
seventeen, was behind the wheel.
March 2, 22,500 gold for wife through useful tips.
She gave a beautiful smile to me which thrilled
Credit Card
One Project Manager, immediately on me though it was through mirror. I was pleasantly
surprised as for the first time in my life I
received a smile from a young girl and that too
from a girl from a rich family who can afford to
own and maintain Audi car.
When she kept on following me for 15-20
minutes, I got an impression that probably she is
interested in me.
But the very next moment a thought came to my
mind that how she could be interested in me? I
am almost three times her age but then they say
- love is blind and love do not see any age gap. She
might have fallen in love with me at first sight,
though I am neither handsome nor loveable.
She continued following me further and after
some time she brought her car near my car, gave
a beautiful smile to me and was about to tell
something to me but unfortunately, to my bad
luck, traffic signal became green.
This led me to confirm my belief that she wants
to propose to me.
I started thinking as to how I should respond to
her when she proposes to me which may happen at
the next signal and perhaps I would become the
first person to whom a girl proposed at a traffic
signal.
I started thinking as to what reason I should
give to my wife for divorce. But I decided to
concentrate first on rehearsal of my affirmative
reply to her when she proposes to me and about
the reason for divorce, I can always think later.
At the next signal again she brought her car near
my car, opened the power window of her car and
smiled at me. I was jumping with joy and made
myself ready to accept her, with open arms, the
moment she proposes to me.
Again she gave one more beautiful smile to me,
this time mischievously, and said, “Uncle, instead
car, why don’t you drive a hand cart ? !!!”

17 GAMMON BULLETIN
NEWS FLASH FROM PROJECTS
They were highly impressed with
SATTVA GOLD SUMMIT : performance of PHPP site team in spite of INDIA SHOW IN TOKYO, JAPAN
difficult working conditions.

WOMEN’S DAY CELEBRATION

Women’s Day was celebrated with lots of


The site team led by Mr. Rajaram have fun and joy on 8th March, 2013 at Gam-
successfully completed the casting mon House & Belapur Office. “Gammon
of the helipad slab at 35th level Springs” had organized special competi-
(108 m above GL) at Sattva Gold Summit tions like Rangoli, Marble and Spoon race,
Project on 11th January, 2013. With the Sack race and Paper fancy dress which saw
completion of the helipad slab, the team a number of Gammonites participating Gammon has participated in an exhibition
has completed RCC works of The SATTVA enthusiastically. The winners were later at Tokyo, Japan. The objective of this
Gold summit project, which is the tallest falicitated with prizes. participation was to showcase our
building in south India as on date. strengths as India’s one of the oldest and
biggest construction company. The show
NATHANI HEIGHTS : was a grand success. We received an
overwhelming response from Japanese
The site team of Nathani Heights has construction and trading industry.
successfully commenced the RCC works of
We also had chance to have interaction
the Foundations, at our Project- Nathani
with Honorable Chief Minister of Madhya
Heights which is a 72 storied Prestigious
Pradesh, Mr. Shivraj Chauhan and Honorable
tallest Residential Tower as on date in
Minister of Industries, Madhya Pradesh
Mumbai.
Mr. Kailash Vijayvargiya.
JINDAL CIVIL WORKS :

SWEDISH
Delagation Visit to
GAMMON

Project- Jindal Civil Works, Bellary,


Karnataka, has recorded 20 Million Safe Man
Hours free of reportable accident as on 24th
November, 2012 and hence awarded for, by
the Chairman and Managing Director, JSW
Steel Limited.

VISIT TO PHPP at BHUTAN : One Day Integration Programme


Amal Bhattacharya – DGM & RCMS (Kolkata with Swedish Delagation lead by
Metro Project) and his family visited Puna Infrastructure Minister of Sweden
Sangchu Hydro Power Project, Bhutan.

GAMMON BULLETIN 18
COMPANY NEWS
Engineer
THANKS TO Abhishek Kumar Mishra GIL
ESTEEMED Diwanshu Gupta PARTICIPATION
CUSTOMERS Shailendra Kumar IN SEMINARS
Baluaha Ghat Koshi Bridge
Junior Engineer
Bihar Rajya Pul Nirman Nigam Ltd. Dr. N. V. Nayak
C. V. : Rs. 231 Crores Amrit Kumar Pait
16th January 2013
Delivered a lecture on“Innovative Use of Fine
WELCOME Officer and Ultrafine Pozzolanic Materials in High
Devyani Joshi Performance Concrete”at Kolkata, in seminar
To rganized by Ambuja Cements.
Tushar Dhanu
GAMMON FAMILY 23rd January 2013
AWARDS Delivered a lecture on “Benefits of Fine
Deputy General Manager and Ultrafine Pozzolanic Material in
High Performance Concrete – Indian
Birendra Narayan Singh
Innovations” at BIT collage Hall, Bangalore
ACCEI Award organized by BIT, RMCMA Quality Circle, &
Senior Manager “Association of Consulting Civil Engineers ACCE (I), Bangalore Centre, Bangalore.
Christuraj Joseph (India)” has conferred on Gammon
Prasad Neelkanth Dixit India Limited its Prestigious Award for Girish Bhat
“Excellence in Construction of Industrial Participated in Board Meeting of Chartered
structure” for “Construction of Natural Institute of Management Accountants (UK).
Manager Draught Cooling Towers at Aravali in
M.S Madhusoodanan Haryana and Simhadri in Andhra Pradesh. V.N. HEGGADE
Nikhil Ravindra Virkar 22nd March 2013
Samiran Biswas Attended IRC B-4 committee meeting at
Srisha Addoni MSRDC office, Bandra - Mumbai.
ASHISH GUPTA
Deputy Manager 16th Feburuary 2013
Rabi Ranjan Bhattacharya Participated and delievered a lecture on
Basavaraj Huggi Hydro-Power Development innovative
practices in construction and design
Bellary Polepalli Gangadhar aspects at Kolkata orgnized by WBSEDCL
Durairaj Kannappan JSW Safety Award
Satyendra Kumar Chaudhary Gammon India Limited was conferred with
Sumanta Kumar Roy
prestigious Safety Award by JSW Steels FAMILY
Limited, for achieving 20 Million Safe
Man Hours free of accident at Gammon RECOGNITIONS
Assistant Manager Project site - Jindal Civil Works, Bellary,
Amit Ashok Wakde Karnataka.
Desiree Nayak
Amrutha Devi Gokeda Granddaughter of Dr. N V Nayak has been
Arindum Bharti selected by Hindustan Times as one of the
Arvind Vishnu More top 50 Brightest Students amongst 57000
applicants from 280 schools in Mumbai.
Biswa Bikash Tripathy
Chandan Kumar Singh
Divya Thakkar, daughter of Mr. Bahvesh
Gita Srinivasan Iyer Thakkar (Deputy Manager, GIL) and
Jayesh Pandyaa Kiranmayi P. Rao, daughter of Mr. P. S. Rao
Kanda Kumaran.A (Manager, Plant) have entered Guiness Book
Safety Award –Godrej of World Records by participating in third
Navneet Jaykumar Bhalerao
We are very proud to communicate that international dance (Kuchipudi) convention
Rajan Jegan our Godrej Platinum (9104), Project SIte held at Hyderabad on 25th December 2012.
Senthil Kumar . Bangalore has won the First position with The convention created a record where
Shubhangi Shirpute 85.85% in the 4th edition of Godrej Safety over 5700 dancers ensemble to preform
Award amongst all the current Godrej Maha Brinda Natyam, organized by Silicon
Siddhartha Bhamidipati
projects across the country. Andhra.
Suresh Siva

19 GAMMON BULLETIN
BUILDERS TO THE NATION

Gammon’s Concrete Contribution in Reinforcing


Infrastructure in INDIA

Kosi Bridge NH-57

Agra Makhanpur Expressway NH-2

Mumbai- Nasik Expressway NH-3 Rajahmundry Expressway NH-16

< were incepted in 1919

We < have built largest number of bridges in commonwealth


TM

< developed one of the largest National/ State Highway network in India

< own 23 infrastructure projects on PPP model including 14 road projects


Designed & Printed by

< are in infrastructure encompassing

X Transportation: Roads, Railways, Ports

X Energy: Hydro, Thermal & Nuclear

X Environmental: Water & Waste Management

X Industrial Structures, Building & Utility Services

Head office: Gammon India Limited, Gammon House, Veer Savarkar Marg, Prabhadevi, Mumbai (INDIA) - 400 025
GAMMON BULLETIN 20
Contact: +91 22 6111 4000 / +91 22 67487200 Websites: www.gammonindia.com; www.gammoninfra.com

You might also like