You are on page 1of 26

Chapter 2

Instruction for use IM & QM Cubicle


Cibitung, 2 – 5 March 2015
● Chapter 2 : Instruction for use IM & QM

General Description

Schneider Electric - Services Division – SM6 Cubicle Training – March 2015 2


IM – Switch cubicle
1. Bus bar compartment
2. LV compartment
3. Switch & earthing switch
4. Operating mechanism compartment
5. Cable compartment
A. Earth bar connection
B. Bus bar connection
C. Cable connection
D. Voltage indicator
E. Capacitive divider
F. Front panel
G. Inspection windows

Schneider Electric - Services Division – SM6 Cubicle Training – March 2015 3


QM – Fused switch combination cubicle
1. Bus bar compartment
2. LV compartment
3. Switch & earthing switch
4. Operating mechanism compartment
A. Earth bar connection
B. Bus bar connection
C. Voltage indicator
D. Tripping unit
E. Front panel
F. Cable connection
G. Inspection windows
H. Capacitive divider
I. Earthing switch

Schneider Electric - Services Division – SM6 Cubicle Training – March 2015 4


● Chapter 2 : Instruction IM & QM
Installation

Schneider Electric - Services Division – SM6 Cubicle Training – March 2015 5


MV cable connection for QM/IM cubicle

Open the earthing Fit the cable in same Close the earthing switch
switch using the order as for the IM
operating lever cubicle. Use a torque
wrench and a 16 mm
socket to tighten the
bolts. Tightening
torque : 50 Nm

Schneider Electric - Services Division – SM6 Cubicle Training – March 2015 6


● Chapter 2 : Instruction IM & QM
Operation Instruction

Schneider Electric - Services Division – SM6 Cubicle Training – March 2015 7


Operating instructions
IM and QM: operation and position indication

Schneider Electric - Services Division – SM6 Cubicle Training – March 2015 8


Continued ...

Schneider Electric - Services Division – SM6 Cubicle Training – March 2015 9


Continued ...

Schneider Electric - Services Division – SM6 Cubicle Training – March 2015 10


Continued ...

Schneider Electric - Services Division – SM6 Cubicle Training – March 2015 11


Continued ...

Schneider Electric - Services Division – SM6 Cubicle Training – March 2015 12


Fuse indications on QM cubicles

Schneider Electric - Services Division – SM6 Cubicle Training – March 2015 13


Discharging a CI2 operating mechanism

Cubicle de-energized: Cubicle energized:


Close the switch: button A Press the open button B.
Then open : button B Attention: this operation can
damage the operating mechanism
(CIT operating mechanism) perform only when stricly necessary.

Schneider Electric - Services Division – SM6 Cubicle Training – March 2015 14


Padlocking

Schneider Electric - Services Division – SM6 Cubicle Training – March 2015 15


Continued ...

Schneider Electric - Services Division – SM6 Cubicle Training – March 2015 16


Operating safety

Schneider Electric - Services Division – SM6 Cubicle Training – March 2015 17


● Chapter 2 : Instruction IM & QM
Start-up Instruction

Schneider Electric - Services Division – SM6 Cubicle Training – March 2015 18


Check before energizing
● Check that nothing has been left in the compartment, for all phases :
● Check that the fuse has been properly fitted
● Check that the field distributor covers have been properly closed on all
phases
● Check that the fault detector has been properly connected

Schneider Electric - Services Division – SM6 Cubicle Training – March 2015 19


Operating test before energizing

Operate the switch several Operate the earthing switch


times several times

Schneider Electric - Services Division – SM6 Cubicle Training – March 2015 20


Voltage indicator

As soon as the cables have been energized, the


voltage indicator lamp should go on

Schneider Electric - Services Division – SM6 Cubicle Training – March 2015 21


● Chapter 2 : Instruction IM & QM
Maintenance

Schneider Electric - Services Division – SM6 Cubicle Training – March 2015 22


Preventive maintenance
● Never lubricate the operating mechanism
● No particular maintenance is required under normal operating
conditions (temperature between –5 oC and 40 oC).
● For severe operating conditions (aggressive environment, dust,
temperature below –5 oC or above 40 oC, etc.), please consult
Schneider Electric

Schneider Electric - Services Division – SM6 Cubicle Training – March 2015 23


Corrective maintenance
● Replacing the fuses
● The cubicle must be de-energized
● The switch must be opened
● The earthing switch must be closed
● Open the front panel for access to the fuses
● Important :
● Standard IEC 282.1 & 23.2 states that all three of the MV fuses
should be changed whenever one of them blows.

Schneider Electric - Services Division – SM6 Cubicle Training – March 2015 24


Replacing a voltage indicator block

● Pull out the voltage indicator block. The cubicle can remain energize.

Schneider Electric - Services Division – SM6 Cubicle Training – March 2015 25


End Presentation

Schneider Electric - Services Division – SM6 Cubicle Training – March 2015 26