1 Hot Mix Plant Calibration APPOLO ANP 2000 160 TPH External 20-Sep-21 19-Dec-21
2 WMM Plant Calibration MAXMECH 200 TPH External 19-Sep-21 18-Dec-21
3 Batching Plant Calibration SCHWING STETTER CP-30 30 Cum/Hr External 4-May-21 3-Aug-21 PENDING